Proposed Millennium Expansion - Delaware Riverkeeper Network

ProposedMillenniumExpansion–TwoNewCompressorsandMorePipe
TheMillenniumPipelineCompany(Millennium)hasannounceditsproposedEasternSystemUpgrade
Project—whichincludes:
Ø anew22,400horsepowercompressorstationintheTownofHighland,NY
Ø additionofanew22,400horsepowercompressorunitattheexistingHancockCompressorStationin
DelawareCounty,NY
Ø installationof7.3milesofnew36-inchpipelineparalleltoMillennium’sexisting24-inchlinebetween
theHuguenotandWesttownmeterstationsinOrangeCounty,NY
TheprocesswassetintomotiononJanuary19,2016whenMillenniumfiledaRequestforPre-FilingReview
withtheFederalEnergyRegulatoryCommission(FERC).Theproject’sPre-filingdocketnumberisPF16-3.
Millenniumhasalreadytakenstepstoadvancetheirnewconstruction—includingpurchasingnecessaryland,
conductinginitialstakeholderconsultations,andpre-filingtheirproposalwithFERC.Thecompanyhaslaidout
theirintendedtimelinegoingforward(seebelow),whichincludesthesubmissionoftheirofficialapplication
toFERCinJuly2016andconstructionbeginninginSeptember2017.
TheproposednewcompressorstationwouldbelocatedinEldred,
ahamletoftheTownofHighlandinSullivanCounty,NYequidistant
fromtheexistingHancock(DelawareCounty)andMinisink
CompressorStations(OrangeCounty).Millenniumhasalready
purchased80acresoftheEldredPreserve,alongstateRoute55,
forthispurpose.Thecompanyhasindicatedthattheyintendto
buildthecompressorstationonthesouthwestcornerofthe
property.ThismapisadaptedfromMillennium’sRequestforPreFilingReview,andshowsthelocationoftheproposedcompressor
stationandpotentialaccessroad.
AboutMillennium:TheMillenniumPipelineCompanyisatthe
heartoftheproposedcompressorstation.Millennium,also
responsiblefortheHancockandMinisinkCompressorStations,
doesnothaveagoodtrackrecordinSullivanandneighboring
counties.IntheTownofHancock,Millenniumacquiredthe
propertythatwaseventuallyusedfortheircompressorstation
ProposedCompressorStation
aftertheirpipelineexpansionactivitiesdamagedthefoundation
andsepticsystemofthepreviousowner’shouse.InMinisink,negativehealthimpactsfromcompressor
DELAWARE RIVERKEEPER NETWORK
925 Canal Street, Suite 3701
Bristol, PA 19007
Office: (215) 369-1188
fax: (215)369-1181
[email protected]
www.delawareriverkeeper.org emissionshavealreadyforcedanearbyfamilytoabandontheirhome.Additionally,theTownofCochecton
accusedthepipelinecompanyofleavingbehind$1millionindamagestocountyroadsaftertheir2008
pipelineexpansionproject—whichMillenniumdenied.
Process&Involvement:Weencouragecommunitymemberstosignupforupdatesonanyofficial
communicationbetweenthecompanyandFERCbyusingtheproject’sPre-Filingdocketnumber:PF16-3.
TimelineforActivities:
December23,2015:Millenniumpurchased80acresoftheEldredPreservefor$447,812
January8,2016:MillenniumPipelineCompanyrepresentativesmetwithHighlandTownSupervisorJeff
HaasregardingtheirintendedEasternSystemUpgradeProject
January11,2016:MillenniumwrotealettertotheBoardofHighland,reportingonJanuary8meeting
withSupervisorHaas
January19,2016:Millenniumsubmittedtheirrequestforpre-filingreviewtoFERC
February5,2016:MillenniumplanstofileinitialdraftsofResourceReport1andalternatives
March2016:TentativedateforMillenniumopenhousewithofficialsandcommunitymembers
April27,2016:MillenniumplanstofileDraftsofResourceReports1through12
July29,2016:MillenniumplanstosubmittheirSection7(c)ApplicationwithFERC
July31,2017:MillenniumwillrequestthatFERCissueanorderapprovingtheirupgradeproject
Fall2017:Millenniumhopestobeginconstruction
September1,2018:Millenniumplanstocompleteprojectandplaceprojectfacilitiesintoservice
ForongoinginformationandtogetinvolvedinchallengingtheMillenniumEasternSystemUpgradeProject
sendanemailtokeeper@delawareriverkeeper.orgorcall2153691188andasktobeaddedtocommunity
listchallengingthisdamagingproposal.
Sources:
‘EasternSystemUpgrade’RequestforPre-FilingReview.MillenniumPipelineCompany,LLC.SubmittedtoFERCJanuary19,2016.
http://elibrary.ferc.gov/idmws/common/OpenNat.asp?fileID=14123526
LetterfromMicheleC.HooktotheHighlandTownBoard.MillenniumPipelineCompany,LLC.January11,2016.Responsiveto
January20,2016FOILrequestoftheTownofHighland.
“Frackingbanwon’tstopplanforcompressorstation,”AndrewBeam,TimesHerald-Recorder.January22,2016.
http://www.recordonline.com/article/20160122/NEWS/160129765
“PipelinecompanyseekscompressorstationinEldred,”AndrewBeam,TimesHerald-Recorder.January12,2016.
http://www.recordonline.com/article/20160112/NEWS/160119785
“Millenniumplanscompressorstationincounty,”DanHust,January11,2016.SullivanCountyDemocrat.
“Millenniumbuys80acresfromEldredPreserve,”FritzMayer.January7,2016.RiverReporter.
Page2of2
Updated:January26,2016