Engineering

Use Existing Chilled Water
Asset By Interconnecting a
Customer’s Chiller System
to a District Cooling
System
June 18, 2007
Applied
Engineering
Services
An engineering solutions company.
Introduction
-North Building Built in 1961
• Converted to DC in 1991
-South Building Built in 1991
• Fully occupied in 1994
• Approximately 1 million square feet
2
West Street View
3
Washington Street View
4
View of Capital From
Government Place
5
IGC – South Chilled Water
• Two (2) 800-ton chillers using R-11
• Total connected AHU load 3,200 tons
(peak of 2400 tons anticipated)
-Chiller in lower level
-Towers mounted on the roof
• 1 million gallon chilled water storage
tank installed
-Chilled water storage tank also used
for a backup for data center cooling
6
IGCS-Problems Encountered
• Concrete chilled water storage tank
needed an open system (tank at lowest
point)
• VE item in original design reduced
pipe schedule from STD to SCH 10
• Chemical treatment contract was
removed from MC’s bid
• Only one chiller dedicated to chilled
water tank charging at night due to
labor dispute
7
IGCS-Problems Continued
• Open system/thin wall pipe/no
chemical treatment – pipe leaks abound
• Control system breakdowns caused
water hammer and vacuum conditions
• Tower capacity reduction due to scaled
fill – an acid cleaning was performed
• Several 90°F plus days in a row caused
the chilled water storage tank to
deplete
8
IGCS Solutions Implemented
• Open chilled water system removed
from building
• Data center mechanical backup cooling
installed
• District system added to the building as
the “main” cooling system. Building
Chillers used as a means to “load shed”
during peak cooling periods
• Install new cooling towers to match
chiller load
• Update mechanical room code
requirements
9
IGCS Project 1
Install data center backup chiller capacity
• Three 120 ton condenser less chillers
installed in the generator room
• A/C condensers mounted on the roof
• Commissioned and checked with
generator operation
10
Condenserless Chiller
11
IGCS Project 2
Chilled water interconnect with district chilled water system
• New piping system installed (SCH 40)
• New VSD chilled water circulating
pumps installed
• Connection to district system completed
• New tower and water treatment system
installed
• Control system changes to initiate a
“load shed” scenario
12
Interior Piping
• Interior piping replaced
• 1 ½ years total construction
period
13
Mechanical Room Piping
14
New Ref Storage Tank
15
New Towers
16
Key to “Load Shed” Design
• Building Balance Valve
17
Temp Control and Building
Balance Valve Location
18
Lessons Learned:
Commissioning
• Remote condensers and
refrigerant migration
• Tuning a control valve
• Time effort in commissioning key
chiller plant
• Tower water level control
19
Current Operations
• 2005 summer data
• 2,858 peak demand
• Approximately 1000 tons load
shed by site chillers
• 112,900 THR used in July/August
20
Recent Issues Developed
2006 summer operating problems developed
• Control system becomes unstable
• Chiller Plant has shutdown when
left unattended
• 1990 vintage control system (parts
an issue)
21
Conclusion
• Indiana State Government gets a
break on DC pricing by allowing
use of existing equipment
• CTE (district cooling company)
connects another customer. No
generating capacity need be added
• 0.9 KW/ton chillers replaced with
0.6 KW/ton or better cooling
capacity
• Control system bugs need to be
worked out
22
Closing
• Questions? Comments?
23
7999 Knue Road
Suite 300
Indianapolis, Indiana 46250
Phone: 317.585.8920
Fax: 317.585.8921
www.applied-e-s.com
Thank
You
24