Use Existing Chilled Water Asset By Interconnecting a Customer’s Chiller System to a District Cooling System June 18, 2007 Applied Engineering Services An engineering solutions company. Introduction -North Building Built in 1961 • Converted to DC in 1991 -South Building Built in 1991 • Fully occupied in 1994 • Approximately 1 million square feet 2 West Street View 3 Washington Street View 4 View of Capital From Government Place 5 IGC – South Chilled Water • Two (2) 800-ton chillers using R-11 • Total connected AHU load 3,200 tons (peak of 2400 tons anticipated) -Chiller in lower level -Towers mounted on the roof • 1 million gallon chilled water storage tank installed -Chilled water storage tank also used for a backup for data center cooling 6 IGCS-Problems Encountered • Concrete chilled water storage tank needed an open system (tank at lowest point) • VE item in original design reduced pipe schedule from STD to SCH 10 • Chemical treatment contract was removed from MC’s bid • Only one chiller dedicated to chilled water tank charging at night due to labor dispute 7 IGCS-Problems Continued • Open system/thin wall pipe/no chemical treatment – pipe leaks abound • Control system breakdowns caused water hammer and vacuum conditions • Tower capacity reduction due to scaled fill – an acid cleaning was performed • Several 90°F plus days in a row caused the chilled water storage tank to deplete 8 IGCS Solutions Implemented • Open chilled water system removed from building • Data center mechanical backup cooling installed • District system added to the building as the “main” cooling system. Building Chillers used as a means to “load shed” during peak cooling periods • Install new cooling towers to match chiller load • Update mechanical room code requirements 9 IGCS Project 1 Install data center backup chiller capacity • Three 120 ton condenser less chillers installed in the generator room • A/C condensers mounted on the roof • Commissioned and checked with generator operation 10 Condenserless Chiller 11 IGCS Project 2 Chilled water interconnect with district chilled water system • New piping system installed (SCH 40) • New VSD chilled water circulating pumps installed • Connection to district system completed • New tower and water treatment system installed • Control system changes to initiate a “load shed” scenario 12 Interior Piping • Interior piping replaced • 1 ½ years total construction period 13 Mechanical Room Piping 14 New Ref Storage Tank 15 New Towers 16 Key to “Load Shed” Design • Building Balance Valve 17 Temp Control and Building Balance Valve Location 18 Lessons Learned: Commissioning • Remote condensers and refrigerant migration • Tuning a control valve • Time effort in commissioning key chiller plant • Tower water level control 19 Current Operations • 2005 summer data • 2,858 peak demand • Approximately 1000 tons load shed by site chillers • 112,900 THR used in July/August 20 Recent Issues Developed 2006 summer operating problems developed • Control system becomes unstable • Chiller Plant has shutdown when left unattended • 1990 vintage control system (parts an issue) 21 Conclusion • Indiana State Government gets a break on DC pricing by allowing use of existing equipment • CTE (district cooling company) connects another customer. No generating capacity need be added • 0.9 KW/ton chillers replaced with 0.6 KW/ton or better cooling capacity • Control system bugs need to be worked out 22 Closing • Questions? Comments? 23 7999 Knue Road Suite 300 Indianapolis, Indiana 46250 Phone: 317.585.8920 Fax: 317.585.8921 www.applied-e-s.com Thank You 24
© Copyright 2026 Paperzz