7 Contract Costing BASIC CONCEPTS AND FORMULAE Basic Concepts 1. Contract costing:- Contract or terminal costing, as it is termed, is one form of application of the principles of job costing. In fact a bigger job is referred to as a contract. Contract costing is usually adopted by building contractors engaged in the task of executing Civil Contracts. 2. Sub-Contract : Sub-contract costs are also debited to the Contract Account. 3. Extra work: The extra work amount payable by the contractee should be added to the contract price. If extra work is substantial, it is better to treat it as a separate contract. If it is not substantial, expenses incurred should be debited to the contract account as “Cost of Extra work”. 4. Cost of work certified: All building contractors received payments periodically known as “running payment” on the basis of the architect’s or surveyor’s certificates. But payments are not equal to the value of the work certified, a small percentage of the amount due is retained as security for any defective work which may be discovered later within the guarantee period. 5. Work uncertified: It represents the cost of the work which has been carried out by the contractor but has not been certified by the contractee’s architect. It is always shown at cost price. 6. Retention money: A contractor does not receive full payment of the work certified by the surveyor. Contractee retains some amount (say 10% to 20%) to be paid, after sometime, when it is ensured that there is no fault in the work carried out by contractor. 7. Work-in-progress: In Contract Accounts, the value of the work-in-progress consists of (i) the cost of work completed, both certified and uncertified; (ii) the cost of work not yet completed; and (iii) the amount of profit taken as credit. In the Balance Sheet, the work-in-progress is usually shown under two heads, viz., certified and uncertified. 8. Notional profit : It represents the difference between the value of work certified and cost of work certified. © The Institute of Chartered Accountants of India 7.2 9. Cost Accounting Estimated profit : It is the excess of the contract price over the estimated total cost of the contract. 10. Cost plus Contract : Under Cost plus Contract, the contract price is ascertained by adding a percentage of profit to the total cost of the work. Such type of contracts are entered into when it is not possible to estimate the Contract Cost with reasonable accuracy due to unstable condition of material, labour services, etc. 14. Operating Costing: It is a method of ascertaining costs of providing or operating a service. This method of costing is applied by those undertakings which provide services rather than production of commodities. 15. Multiple Costing: It refers to the method of costing followed by a business wherein a large variety of articles are produced, each differing from the other both in regard to material required and process of manufacture. In such cases, cost of each article is computed separately by using, generally, two or more methods of costing. Basic Formulas 1. When work on contract has not reasonably advanced, no profit is taken into account. In practice, no profit is calculated when work certified is less than 1/4th but less than ½ of the contract price. 2. When work certified is more than 1/4th but less than ½ of the contract price, following formula is used to determine the figures of profit to be credited to profit and loss account: 1/3 × Notional profit × 3. When work certified is more than ½ of the contract price, but it is still not in the final stage, following formula is used to determine the figure of profit to be credited to profit and loss account: 2/3 × Notional profit × 4. Cash recieved Work certified Cash received Work certified When the contract is almost complete, an estimate total profit is determined by deducting aggregate of cost to date and estimated additional expenditure from contract price. A portion of this estimated total profit is credited to profit and loss account. The figure to be credited to profit and loss account is ascertained by adopting any of the following formulae: 4.1 Estimated total profit × Work certified Contract price © The Institute of Chartered Accountants of India Contract Costing 4.2 Estimated total profit × Cash received Contract price 4.3 Estimated total profit × Cost of Work to date Estimated total cost 4.4 Estimated total profit × Cost of Work to date Cash received × Estimated total cos t Work certified 7.3 5. Profits on incomplete contracts: The overriding principle being that there can be no attributable profit until the outcome of a contract can reasonably be foreseen. Of the profit which in the light of all the circumstances can be foreseen with a reasonable degree of certainty to arise on completion of the contract there should be regarded as earned to date only that part which prudently reflects the amount of work performed to date. The method used for taking up such profits needs to be consistently applied.” 6. The computation of escalation claim is based on wording of escalation clause. Normally it is calculated on stipulated quantity of material and labour hours based on price and rate differential. 7. Work certified and consequent payment: Work certified and consequent payment m 7.1 The amount of work certified can be debited to contractee’s account. On receipt of money from contractee, his personal account will be credited and cash or bank account, as the cause may be will be debited. 7.2 At the time of balance sheet preparation, Contractee’s Account will be shown on the ‘Assets side’ as debtors. 7.3 Under the second method (it is more common than the first, students are advised to follow this method only) the amount of work certified is debited to work-in-progress account and credited to contract account. The work-inprogress should be shown on the assets side after deduction of cash received. Next year work-in-progress account will be debited to contract account. Question 1 Write note on cost-plus-contracts. Answer These contracts provide for the payment by the contractee of the actual cost of manufacture plus a stipulated profit, mutually decided between the two parties. The main features of these contracts are as follows: © The Institute of Chartered Accountants of India 7.4 Cost Accounting 1. The practice of cost-plus contracts is adopted in the case of those contracts where the probable cost of the contracts cannot be ascertained in advance with a reasonable accuracy. 2. These contracts are preferred when the cost of material and labour is not steady and the contract completion may take number of years. 3. The different costs to be included in the execution of the contract are mutually agreed, so that no dispute may arise in future in this respect. Under such type of contracts, contractee is allowed to check or scrutinize the concerned books, documents and accounts. 4. Such a contract offers a fair price to the contractee and also a reasonable profit to the contractor. 5. The contract price here is ascertained by adding a fixed and mutually pre-decided component of profit to the total cost of the work. Question 2 Write notes on Escalation Clause Answer Escalation Clause: This clause is usually provided in the contracts as a safeguard against any likely changes in the price or utilization of material and labour. If during the period of execution of a contract, the prices of materials or labour rise beyond a certain limit, the contract price will be increased by an agreed amount. Inclusion of such a term in a contract deed is known as an 'escalation clause' An escalation clause usually relates to change in price of inputs, it may also be extended to increased consumption or utilization of quantities of materials, labour etc. In such a situation the contractor has to satisfy the contractee that the increased utilization is not due to his inefficiency. Question 3 Discuss briefly the principles to be followed while taking credit for profit on incomplete contracts Answer Principles to be followed while taking credit for profit on incomplete contracts: The portion of profit to be credited to, profit and loss account should depend on the stage of completion of the contract. This stage of completion of the contract should refer to the certified work only. For this purpose, uncertified work should not be considered as for as possible. For determining the credit for profit, all the incomplete contracts should be classified into the following four categories. (i) Contract less than 25% complete (ii) Contracts is upto 25% or more but less than 50% complete © The Institute of Chartered Accountants of India Contract Costing 7.5 (iii) Contracts is upto 50% or more but less than 90% complete (iv) Contracts nearing completion, say between 90% and 100% complete. The transfer of profit to the profit and loss account in each of the above cases is done as under: (i) Contract less than 25% complete: if the contract has just started or it is less than 25% complete, no profit should be taken into account. (ii) Contracts is upto 25% or more but less than 50% complete: In this case one third of the notional profit reduced in the ratio of cash received to work certified, may be transferred to the profit and loss account. The amount of profit to be transferred to the profit and loss account may be determined by using the following formula: Cash received 1 × Notional profit × Work certified 3 (iii) Contracts is upto 50% or more but less than 90% complete: In this case, two third of the notional profit, reduced by the portion of cash received to work certified may be transferred to the profit and loss account. In this case the formula to be used is as under: Cash received 2 × Notional profit × Work certified 3 (iv) Contracts nearing completion, say between 90% and 100% complete: When a contract is nearing completion or 90% or more work has been done on a contract. The amount of profit to be credited to profit and loss account may be determined by using any one of the following formula. (a) Estimated profit × Work certified Contract price (b) Estimated profit × Work certified Cash received × Contract price Work certified or Estimated profit × (c) Estimated Profit × (d) Estimated profit × (e) Notional profit × Work certified Contract price Cost of work to date Estimated total cos t Cost of work to date Cash received × Estimated total cost Work certified Work certified Contract price © The Institute of Chartered Accountants of India 7.6 Cost Accounting Question 4 Discuss the process of estimating profit/loss on incomplete contracts Answer Process of estimating profit / loss on incomplete contracts (i) If completion of contract is less than 25% no profit should be taken to profit and loss account. (ii) If completion of contract is upto 25% or more but less than 50% then 1/3 × Notional Profit × Cash received Work certified may be taken to profit and loss account. (iii) If completion of contract is 50% or more but less than 90% then 2/3 × Notional Profit × Cash received Work certified may be taken to profit and loss account (iv) If completion of contract is greater than or equal to 90% then one of the following formulas may be used for taking the profit to profit and loss account. 1. Estimated Profit × Work certified Contract price 2. Estimated Profit × Work certified Cash received × Contract price Work certified 3. Estimated Profit × Cost of the work to date Estimated total cos t 4. Estimated Profit × Cost of the work to date Cash received × Estimated total cos t Work certified 5. Notional Profit × Work certified Contract price Question 5 Brock Construction Ltd. commenced a contract on November 1, 2003. The total contract was for ` 39,37,500. It was decided to estimate the total profit on the contract and to take to the credit of P/L A/c that proportion of estimated profit on cash basis, which work completed bore © The Institute of Chartered Accountants of India Contract Costing 7.7 to the total contract. Actual expenditure for the period November 1, 2003 to October 31, 2004 and estimated expenditure for November 1, 2004 to March 31, 2005 are given below: November 1,2003 to October 31, 2004 (Actual) November 1,2004 to March 31 , 2005 (Estimated) (`) (`) 12,37,500 6,75,000 Material issued 5,62,500 4,50,000 Labour Paid 25,000 Prepaid 2,500 Outstanding 3,75,000 Plant purchased 3,50,000 2,00,000 Expenses Paid 25,000 50,000 Outstanding 3,00,000 75,000 Plant return to store (on March 31, 2004) (on March 31, 2005) (Historical cost) Full 20,00,000 Work certified 75,000 Work uncertified 17,50,000 Cash received 37,500 75,000 Material at site The plant is subject to annual depreciation @ 33% on written down value method. The contract is likely to be completed on March 31, 2005. Required Prepare the contract A/c. Determine the profit on the contract for the year November, 2003 to October, 2004 on prudent basis, which has to be credited to P/L A/C Answer Brock Construction Ltd. Contract A/c (November 1, 2003 to Oct. 31, 2004) Dr. Particulars To Materials issued To Labour paid Prepaid To Plant Purchased To Expenses paid 4,50,000 25,000 2,00,000 Amount (` ) 6,75,000 By Plant returned to store on 31/03/04 at cost Less: Dep (1/3) 4,25,000 By WIP 3,75,000 Certified Uncertified © The Institute of Chartered Accountants of India Dr. Amount (` ) 75,000 10,417 64,583 20,00,000 75,000 20,75,000 7.8 Cost Accounting To Outstanding To Notional profit c/d To P/L A/c 3,34,305 × (17,50,000 / 20,00,000) × (20,00,000 / 39,37,500) To Work-in-progress (Profit in reserve) 50,000 2,50,000 By Plant at site 31/10/04 at Cost Less: Dep (1/3) 6,89,583 By Materials at site 24,14,583 1,48,580 By Notional Profit b/d 3,00,000 1,00,000 2,00,000 75,000 24,14,583 6,89,583 5,41,003 6,89,583 6,89,583 Brock Construction Ltd. Contract A/c (November 1, 2003 to March 31, 2005) (For computing estimated profit) Dr. Cr. Particulars Amount Amount (` ) (` ) 19,12,500 By Material at site To Material issued 37,500 (6,75,000+12,37,500) To Labour (paid & 10,15,000 By Plant returned to 64,583 outstanding) stores on 31/3/04 1,72,222 (4,25,000+5,87,500+2,500) By Plant returned to To Plant purchased 3,75,000 stores on 31/3/05 3,00,000 Cost 1,00,000 Less: Dep. 27,778 Less: 5 month Dep. To Expenses 5,75,000 By Contractee A/c 39,37,500 (2,50,000 + 3,25,000) To Estimated profit 3,34,305 42,11,805 42,11,805 Question 6 Paramount Engineers are engaged in construction and erection of a bridge under a long-term contract. The cost incurred upto 31.03.2001 was as under: Fabrication Direct Material Direct Labour © The Institute of Chartered Accountants of India ` In Lakhs 280 100 Contract Costing 7.9 Overheads 60 440 Erection costs to date 110 550 The contract price is ` 11 crores and the cash received on account till 31.03.2001 was ` 6 crores. The technical estimate of the contract indicates the following degree of completion of work. Fabrication – Direct Material – 70%, Director Labour and Overheads 60% Erection – 40%. You are required to estimate the profit that could be taken to Profit and Loss Account against this partly completed contract as at 31.03.2001. Answer Estimation of Profit to be taken to Profit and Loss Account against partly completed contract as at 31.03.2001. Profit to be taken to P/L Account = Cash received 2 × Notional profit × Work certified 3 = 2 Rs` 600 lakhs × ` 92.48 lakhs × = `57.576 lakhs ` 642.48 lakhs 3 (Refer to working notes 1,2,3 & 4) Working Notes 1. Particulars Statement showing estimated profit to date and future profit on the completion of contract Cost to date Further Costs % Completion to date Amount 70 60 60 280.00 100.00 60.00 440.00 110.00 550.00 92.48 ______ Fabrication costs: Direct material Direct labour Overheads Total Fabrication cost (A) Erection cost: (B) Total estimated costs: (A+B) Profit (Refer to working note 2) 40 (`) (a) 642.48 © The Institute of Chartered Accountants of India % Amount completion (`) to be done (b) 30 40 40 Total Cost (`) (a) + (b) 120.00 66.67 40.00 226.67 60 165.00 391.67 65.85 ______ 400.00 166.67 100.00 666.67 275.00 491.67 158.33 ______ 457.52 1,100.00 7.10 2. Cost Accounting Profit to date (Notional Profit) and future profit are calculated as below: Profit to date (Notional Profit) = = Estimated profit on the whole contract × Cost to date Total Cost ` 158.33 × ` 550 ` 941.67 = ` 92.48 (lakhs) Future Profit 3. 4. = ` 158.33 – ` 92.48 = ` 65.85 Work certified: = Cost of the contract to date + Profit to date = ` 550 + ` 92.49 = ` 642.48 lakhs Degree of Completion of Contract to date: = Cost of the Contract to date ` 642.48lakhs × 100 = × 100 =58.40% Contract Price ` 1,100lakhs Question 7 A construction company undertook a contract at an estimated price of `108 lacs, which includes a budgeted profit of ` 18 lacs. The relevant data for the year ended 31.03.2002 are as under: (` '000) Materials issued to site 5,000 Direct wages paid 3,800 Plant hired 700 Site office costs 270 Materials returned from site 100 Direct expenses 500 Work certified 10,000 Progress payment received 7,200 A special plant was purchased specifically for this contract at ` 8,00,000 and after use on this contract till the end of 31.02.2002, it was valued at `5,00,000. This cost of materials at site at the end of the year was estimated at ` 18,00,000. Direct wages accrued as on 31.03.2002 was ` 1,10,000. Required Prepare the Contract Account for the year ended 31st March, 2002 and compute the profit to be taken to the Profit and Loss account. © The Institute of Chartered Accountants of India Contract Costing 7.11 Answer Contract Account for the year ended 31st March, 2002 Dr. Cr. ` ‘000 5,000 3,800 110 700 270 500 300 10,680 8,780 1,200 To Materials issued to site To Direct wages To Wages accrued To Plant hire To Site Office Costs To Direct expenses To Depreciation of special plant To Cost of contract To Profit & Loss A/c (Refer to working note 2) To Work-in-progress c/d (Profit in reserve) By Materials at site By Materials returned By Cost of contract By Work certified 20 10,000 ` ‘000 1,800 100 8,780 _____ 10,680 10,000 _____ 10,000 Working notes 1. Percentage of contract completion = = 2. Cost of work certified × 100 Value of the contract 100 lacs × 100 = 92.59% 108 lacs Since the percentage of Contract completion is more than 90% therefore the profit to be taken to Profit and Loss Account can be computed by using the following formula. Profit to be taken to P & L A/c = Budged/Estimated Profit × = 1,800 × Question 8 Explain the following: (i) Notional profit in Contract costing (ii) Retention money in Contract costing © The Institute of Chartered Accountants of India Cash received Work certified × Work certified Contract price 7,200 10,000 7,200 × = 1,800 × = ` 1,200 10,800 10,000 10,800 7.12 Cost Accounting Answer (i) Notional profit in Contract costing: It represents the difference between the value of work certified and cost of work certified. Notional Profit = Value of work certified – (Cost of works to date – Cost of work not yet certified) (ii) Retention Money in Contract Costing: A contractor does not receive the full payment of the work certified by the surveyor. Contractee retains some amount to be paid after some time, when it is ensured that there is no default in the work done by the contractor. If any deficiency or defect is noticed, it is to be rectified by the contractor before the release of the retention money. Thus, the retention money provides a safeguard against the default risk in the contracts. Question 9 (a) Modern Construction Ltd. obtained a contract No. B-37 for ` 40 lakhs. The following balances and information relate to the contract for the year ended 31st March, 2008: 1.4.2007 31.3.2008 (`) (`) 9,40,000 30,00,000 • Work-in-progress: • Work certified • Work uncertified 11,200 32,000 • Materials at site 8,000 20,000 5,000 • Accrued wages Additional information relating to the year 2007-2008 are: 3,000 (`) • • • • • • • • • • Materials issued from store Materials directly purchased Wages paid Architect’s fees Plant hire charges Indirect expenses Share of general overheads for B-37 Materials returned to store Materials returned to supplier Fines and penalties paid © The Institute of Chartered Accountants of India 4,00,000 1,50,000 6,00,000 51,000 50,000 10,000 18,000 25,000 15,000 12,000 Contract Costing 7.13 The contractee pays 80% of work certified in cash. You are required to prepare: (i) Contract Account showing clearly the amount of profits transferred to Profit and Loss Account. (ii) Contractee’s Account. (iii) Balance Sheet Answer (a) Books of Modern Constructions Ltd. Contract No. B-37 Account for the year ended 31st March, 2008 (`) To (`) To To WIP b/d (9,40,000 + 11,200) Stock (materials) b/d Materials issued By 9,51,200 8,000 By 4,00,000 By To To Materials purchased Wages paid 1,50,000 By 6,00,000 To Wages Accrued c/d 3,000 To To To To To Architect’s fees Plant Hire charges Indirect expenses General overheads Notional profit c/d To Profit and Loss A/c 80 ⎞ ⎛2 ⎜ × 8,55,800 × ⎟ 100 ⎠ ⎝3 51,000 By 50,000 10,000 18,000 8,55,800 30,97,000 By 4,56,427 To WIP Reserve c/d Wages Accrued b/d 5,000 Materials returned to Store Materials returned to suppliers WIP c/d 30,00,000 Work Certified Uncertified work 32,000 Materials stock c/d 30,32,000 20,000 Notional Profit b/f ________ 30,97,000 8,55,800 3,99,373 8,55,800 Note: Fines and penalties are not shown in contract accounts. 25,000 15,000 _______ 8,55,800 Contractee’s Account (`) To Balance c/d 24,00,000 By ________ By 24,00,000 © The Institute of Chartered Accountants of India (`) Balance b/d (80% of 9,40,000) Bank 7,52,000 16,48,000 24,00,000 7.14 Cost Accounting Balance Sheet (Extract) as on 31.3.2008 (`) Profit and Loss A/c Less: Fines Outstanding wages 4,56,427 12,000 (`) Materials stock at site 4,44,427 Materials stock in store 3,000 WIP: Work Certified 30,00,000 Work Uncertified 32,000 30,32,000 Less: Advance 24,00,000 6,32,000 Less: WIP Reserve 3,99,373 20,000 25,000 2,32,627 Question 10 Compute a conservative estimate of profit on contract (which has been 90% complete) from the following particulars: (`) Total expenditure to date 22,50,000 Estimated further expenditure to complete the contract (including contingencies) 2,50,000 Contract Price 32,50,000 Work certified 27,50,000 Work uncertified 1,75,000 Cash received 21,25,000 Answer The contract is 90% complete, the method used for transfer of profit to Profit and Loss Account for the current year will be on the basis of estimated profit on completed contract basis. Credit to Proift and Loss Account = Estimated profit on completed contract × Work certified Cash received × Contract price Work certified Estimated profit on completed contract basis = Contract Price – (Total expenditure to date + Estimated further expenditure to completed contract) = 32,50,000 – (22,50,000 + 2,50,000) = ` 7,50,000. Credit to Proift and Loss Account = 7,50,000 × © The Institute of Chartered Accountants of India 27,50,000 21,25,000 × = ` 4,90,385 32,50,000 27,50,000 Contract Costing 7.15 Question 11 What is cost plus contract? State its advantages. Answer Cost plus contract: Under cost plus contract, the contract price is ascertained by adding a percentage of profit to the total cost of the work. Such types of contracts are entered into when it is not possible to estimate the contract cost with reasonable accuracy due to unstable condition of material, labour services etc. Following are the advantages of cost plus contract: (i) The contractor is assured of a fixed percentage of profit. There is no risk of incurring any loss on the contract. (ii) It is useful specially when the work to be done is not definitely fixed at the time of making the estimate. (iii) Contractee can ensure himself about the ‘cost of contract’ as he is empowered to examine the books and documents of the contractor to ascertain the veracity of the cost of contract. Question 12 Explain the importance of an Escalation Clause in contract cost. Answer During the execution of a contract, the prices of materials, or labour etc., may rise beyond a certain limit. In such a case the contract price will be increased by an agreed amount. Inclusion of such a clause in a contract deed is called an Escalation Clause. Question 13 A contract expected to be completed in year 4, exhibits the following information: Value of work certified Cost of work to date Cost of work not yet certified Cash received (` ) (` ) (` ) (` ) 1. 0 50,000 50,000 0 2. 3,00,000 2,30,000 10,000 2,75,000 3. 8,00,000 6,60,000 20,000 7,50,000 End of Year The contract price is ` 10,00,000 and the estimated profit is 20%. You are required to calculate, how much profit should have been credited to the Profit and Loss A/c by the end of years 1, 2 and 3. © The Institute of Chartered Accountants of India 7.16 Cost Accounting Answer End of year Value of work certified (` ) Cost of work certified* (` ) Notional profit** (` ) Amount that should have been credited to Profit and Loss A/c by the end of year (` ) 1 0 0 0 0 2 3,00,000 2,20,000 80,000 2,75,000 1 × 80,000 × = 24,444 3 3,00,000 3 8,00,000 6,40,000 1,60,000 7,50,000 2 × 1,60,000 × = 1,00,000 3 8,00,000 Workings: End of Completion of Contract year Profit credited to P & L Account year 1 less than 25 per cent. No profit credited Year 2 25 per cent or more than 25 per cent but less than 50 per cent. Cumulative profit = 1 3 × notional profit × Cash received Value of work certified Cash received 2 50 per cent or more than Cumulative profit = × notional profit × 3 50 per cent but less than Value of work certified 90 per cent. * Cost of work certified = Cost of work to date – Cost of work not yet certified Year 3 ** Notional profit = Value of work certified – (Cost of work to date – Cost of work not yet certify Question 14 A contract is estimated to be 80% complete in its first year of construction as certified. The contractee pays 75% of value of work certified, as and when certified and makes the final payment on the completion of contract. Following information is available for the first year: (`) Cost of work-in-progress uncertified 8,000 Profit transferred to Profit & Loss A/c at the end of year I on incomplete contract 60,000 Cost of work to date Calculate the value of work- in-progress certified and amount of contract price. 88,000 © The Institute of Chartered Accountants of India Contract Costing 7.17 Answer As the contract is 80% complete, so 2/3rd of the notional profit on cash basis has been transferred to Profit & Loss A/c in the first year of contract. ∴ Amount transferred to Profit & Loss A/c = 2 × Notional Profit × % of cost received 3 or , 60,000 = 2 75 × Notional Profit × 3 100 or, Notional Profit = 60,000 × 3 × 100 = `1,20,000 2 × 75 Computation of Value of Work Certified Cost of work to date = ` 88,000 Add: Notional Profit = `1,20,000 `2,08,000 Less: Cost of Work Uncertified = 8,000 Value of Work Certified = `2,00,000 Since the Value of Work Certified is 80% of the Contract Price, therefore Value of Work Certified Contract Price = 80% = `2,00,000 = `2,50,000 80% Question 15 SB Constructions Limited has entered into a big contract at an agreed price of ` 1,50,00,000 subject to an escalation clause for material and labour as spent out on the contract and corresponding actuals are as follows: Material: A B C D Labour: L1 L2 Standard Quantity (Tonnes) Actual Quantity (Tonnes) 3,000 2,400 500 100 Hours 3,400 2,300 600 90 Hours 60,000 40,000 © The Institute of Chartered Accountants of India Rate per Tonne (`) 1,000 800 4,000 30,000 Hourly Rate (`) 15 30 56,000 38,000 Rate per Tonne (`) 1,100 700 3,900 31,500 Hourly Rate (`) 18 35 7.18 Cost Accounting You are required to: (i) Give your analysis of admissible escalation claim and determine the final contract price payable. (ii) Prepare the contract account, if the all expenses other than material and labour related to the contract are ` 13,45,000. Answer Statement showing additional claim due to escalation clause. (i) Std. Qty/Hours (a) Material A B C D Labour: L1 L2 Std. Rate Actual Rate (b) (c) 3000 1000 1100 2400 800 700 500 4000 3900 100 30000 31500 Material escalation claim 60,000 40,000 Variation in Rate (`) (d)= (c-b) Escalation claim (`) (e)= (a×d) +100 -100 -100 +1500 +3,00,000 -2,40,000 -50000 +1,50,000 1,60,000 15 18 30 35 Labour escalation claim +3 +1,80,000 +5 +2,00,000 3,80,000 Statement showing Final Contract Price (`) Agreed contract price Add: Agreed escalation claim: Material Cost Labour Cost Final Contract Price (ii) 1,50,00,000 (`) 1,60,000 3,80,000 5,40,000 1,55,40,000 Contract Account Dr. Cr. (`) To Material: A – 3,400 × `1,100 B – 2,300 × ` 700 C – 600 × ` 3,900 © The Institute of Chartered Accountants of India (`) By Contractee’s A/c 1,55,40,000 Contract Costing DTo 90 × `31,500 7.19 1,05,25,000 Labour: L1 – 56,000 × `18 L2 – 38,000 × `35 23,38,000 To Other expenses 13,45,000 To Profit and Loss A/c 13,32,000 1,55,40,000 1,55,40,000 Question 16 PQR Construction Ltd. commenced a contract on April 1, 2009. The total contract was for ` 27,12,500. It was decided to estimate the total profit and to take to the credit of P/L A/c the proportion of estimated profit on cash basis which work completed bear to the total contract. Actual expenditure in 2009-10 and estimated expenditure in 2010-11 are given below: 2009-10 2010-11 Actual( `) Estimated (`) Material issued 4,56,000 8,14,000 Labour 3,05,000 24,000 3,80,000 37,500 2,25,000 1,00,000 22,500 1,75,000 25,000 - Plant returned to stores (a historical stores) 75,000 1,50,000 (on Dec 31 2010) Material at site 30,000 75,000 12,75,000 Full 40,000 ---- 10,00,000 Full : Paid : Outstanding at end Plant purchased Expenses : Paid : Outstanding at the end : Prepaid at the end Work-in progress certified Work-in-progress uncertified Cash received The plant is subject to annual depreciation @ 20% of WDV cost. The contract is likely to be completed on December 31, 2010. Required: (i) Prepare the Contract A/c for the year 2009-10. (ii) Estimate the profit on the contract for the year 2009-10 on prudent basis which has to be credited to P/L A/c © The Institute of Chartered Accountants of India 7.20 Cost Accounting Answer PQR Construction Ltd. Contract A/c (April 1, 2009 to March 31, 2010) Dr. To Materials Issued To Labour Paid 3,05,000 Outstanding 24,000 To Plant Purchased To expenses Paid 1,00,000 (-) Prepaid 22,500 To Notional Profit c/d To Profit & Loss A/c (Refer to Working Note 5) To Work-in-Progress A/c (Profit-in-reserve) Dr. 77,500 By Plant at Site 4,37,500 (Working Note No. 2) 15,25,000 1,59,263 By Notional Profit b/d 2,78,237 4,37,500 PQR Construction Ltd. Contract A/c (April 1, 2009 to December 31, 2010) (For Computing estimated profit) Amount 12,70,000 By Material at Site To Materials Issued (4,56,000+8,14,000) To Labour Cost (Paid & Outstanding) 3,05,000 + 24,000 + ∗3,56,000 + 37,500) To Plant purchased To expenses (77,500 + 1,97,500 + 25,000) To Estimated profit ∗ Amount 4,56,000 By Plant returned to Stores (Working Note 1) By Materials at Site 3,29,000 By W.I.P. 2,25,000 Certified 12,75,000 Uncertified 40,000 7,22,500 By Plant returned to Stores on 31.3.2010 By Plant returned to Stores on 31.12.2010 2,25,000 (Working Note 3) By Contractee A/c 3,00,000 4,32,000 29,49,500 Labour paid in 2010- 11:3,80,000 – 24,000 = 3,56,000 © The Institute of Chartered Accountants of India Cr. Amount 60,000 30,000 13,15,000 1,20,000 15,25,000 4,37,500 4,37,500 Cr. Amount 75,000 60,000 1,02,000 27,12,500 29,49,500 Contract Costing 7.21 Working Notes (`) 1. 2. 3. 4. 5. Value of the Plant returned to Stores on 31.03.2010 Historical Cost of the Plant returned Less: Depreciation @ 20% of WDV for one year Value of Plant at Site 31.3.2010 Historical Cost of Plant at Site Less: Depreciation @ 20% on WDV for one year Value of Plant returned to Stores on 31.12.2010 Value of Plant (WDV) on 31.3.2010 Less: Depreciation @ 20% of WDV for a period of 9 months Expenses Paid for the year 2009-10 Total expenses paid Less: Pre-paid at the end 75,000 15,000 60,000 1,50,000 30,000 1,20,000 1,20,000 18,000 1,02,000 1,00,000 22,500 77,500 Profit to be credited to Profit & Loss A/c on March 31,2010 for the Contract likely to be completed on December 31,2100 = Estimated Profit × = 4,32,000 × Work Cerfified Cash received x Total Contract Price Work Certified 12,75,000 10,00,000 = ` 1,59,263 × 27,12,500 12,75,000 Question 17 A contractor commenced a contract on 1-7-2011. The costing records concerning the said contract reveal the following information as on 31-3-2012. Material sent to site Labour paid Labour outstanding as on 31-3-2012 Salary to Engineer Cost of plant sent to site (1-7-2011) Salary to Supervisor (3/4 time devoted to contract) © The Institute of Chartered Accountants of India Amount (`) 7,74,300 10,79,000 1,02,500 20,500 per month 7,71,000 9,000 per month 7.22 Cost Accounting Administration & other expenses Prepaid Administration expenses Material in hand at site as on 31-3-2012 4,60,600 10,000 75,800 Plant used for the contract has an estimated life of 7 years with residual value at the end of life ` 50,000. Some of material costing ` 13,500 was found unsuitable and sold for ` 10,000. Contract price was ` 45,00,000. On 31-3-2012 two third of the contract was completed. The architect issued certificate covering 50% of the contract price and contractor has been paid ` 20,00,000 on account. Depreciation on plant is charged on straight line basis. Prepare Contract Account. Answer Contract Account (For the period 1.7.11 to 31.3.12) Particulars To Material Issued To Labour 10,79,000 Add: Outstanding 1,02,500 To Salary to engineer (20,500 x 9) 3 To Salary to Supervisor 9000 × × 9 4 To Administration & other expenses 4,60,600 Less: Prepaid 10,000 To Depreciation on Plant (Working Note 1) To Cost of Contract b/d To Notional Profit c/d To P&L A/c(W.N.3) To Reserve Amount Particulars (`) 7,74,300 By Material (Sold) By P&L A/c (Loss) 11,81,500 (13,500-10,000) 1,84,500 By Material in hand By Cost of Contract c/d 60,750 Amount (`) 10,000 3,500 75,800 26,39,600 4,50,600 77,250 27,28,900 26,39,600 By work-in Progress: -Work certified 50% of 45,00,000 2,70,300 -Work uncertified (W.N.-2) (26,39,600-19,79,700) 29,09,900 1,60,178 By Notional Profit b/d 1,10,122 2,70,300 © The Institute of Chartered Accountants of India 27,28,900 22,50,000 6,59,900 29,09,900 2,70,300 2,70,300 Contract Costing 7.23 Working Note 1. Calculation of depreciation on Plant Cost of the Plant 7,71,000 Less: Residual Value 50,000 7,21,000 Estimated life 7 Years Depreciation per annum 1,03,000 Depreciation for 9 months = 2. 1,03,000 12 × 9 = 77,250 Cost of work uncertified = Cost incurred to date minus 50% of the total cost of contract = `26,39,600(figure already shown in the contract A/c) - `19,79,700 = `6,59,900 3. Calculation of Profit to be transferred = 2 3 × 2,70,300 × 20,00,000 22,50,000 = 1,60,178 Question 18 From the following particulars compute a conservative estimate of profit by 4 methods on a contract which has 80 percent complete: (`) Total expenditure to date Estimate further expenditure to complete the contract Contract Price Work Certified Work not certified Cash received Answer Working Notes: (i) Calculation of Notional Profit = (Work certified + work not certified) – Total expenditure to date = ` (10,00,000+85,000) – ` 8,50,000 = ` 2,35,000 © The Institute of Chartered Accountants of India 8,50,000 1,70,000 15,30,000 10,00,000 85,000 8,16,000 7.24 (ii) Cost Accounting Calculation of Estimated Profit Contract Price – (Expenditure to date + Further expenditure to be incurred) = `15,30,000 – ` (8,50,000 + 1,70,000) = ` 5,10,000 Computation of Conservative Estimate of Profit by following methods: 1. Notional Profit x 2 Cash received x work certified 3 2 ` 8,16,000 = ` 2,35,000 x x = ` 1,27,840 3 ` 10,00,000 2. Estimated Profit x = ` 5,10,000 x 3. 8,50,000 8,16,000 × = ` 3,46,800 ( 8,50,000 + 1,70,000 ) 10,00,000 Estimated Profit x Notional Profit x = ` 2,35,000 x Cash received Contract Price 8,16,000 = ` 2,72,000 15,30,000 = ` 5,10,000 x 4. Cost of work done Cash received × Estimated total Cost work certified Work Certified Cash Received x Contract Price Work Certified 10,00,000 8,16,000 x = ` 1,25,333 15,30,000 10,00,000 5. Estimated Profit x Work Certified 10,00,000 = ` 5,10,000 x = ` 3,33,333 15,30,000 Contract Price 6. Estimated Profit x Cost of work done 8,50,000 = ` 5,10,000 x = ` 4,25,000 10,20,000 Estimated total Cost 7. Notional Profit x Work Certified Contract Price = ` 2,35,000 x 10,00,000 15,30,000 = ` 1,53,595 Most conservative Profit is ` 1,25,333, therefore profit to be transferred to Profit and Loss a/c is ` 1,25,333. © The Institute of Chartered Accountants of India Contract Costing 7.25 EXERCISE Questions for Practice 1. (i) Discuss the implications of cost-plus contracts from the view points of: (a) the manufacturer (b) the customer. (ii) 2. 3. 4. What is the relevance of escalation clause provided in the contracts? Answer: Refer to ‘Chapter No. 6 i.e. Method of Costing I’ of Study Material. Discuss briefly the principles to be followed while taking credit for profit on incomplete contracts. Answer: Refer to ‘Chapter No. 6 i.e. Method of Costing I’ of Study Material. What are the main features of 'Cost-Plus-Contracts' Answers: Refer to ‘Chapter No. 6 i.e. Method of Costing I’ of Study Material. The following particulars are obtained from the books of Vinak Construction Ltd. as on March 1983: ` 4,90,000 ` 2,00,000 Plant and Equipment at cost Vehicles at cost Details of contract which remain uncompleted as on 31.03.1983:– Contract Nos. V.20 (` Lacs) Estimated final sales value Estimated final cost Wages Materials Overheads (excluding depreciation) Total costs to date Value certified by architects Progress payments received V.24 (` Lacs) 7.00 6.40 2.40 1.00 1.44 4.84 7.20 5.00 V.25 (` Lacs) 5.60 7.70 2.00 1.10 1.46 4.56 4.20 3.20 16.00 12.00 1.20 0.44 0.58 2.22 2.40 2.00 Depreciation of Plant and Equipment and Vehicle should be charged at 20% to the three contracts in proportion to work certified. You are required to prepare statements to show contractwise and total: (i) Profit/loss to be taken to the P&L A/c for the year ended 31st March 1983; (ii) Work-in-progress as would appear in the Balance Sheet as at 31st March 1983. Answer: (i) Profit (loss) to be taken to Profit & Loss account (ii) Work in progress 5. V.20 1 V.24 1.40 1.56 0.38 Deluxe Limited undertook a contract for `5,00,000 on July, 1986. On were closed, the following details about the contract were gathered: © The Institute of Chartered Accountants of India 1st 30th V.25 0.06 Total 0.46 0.40 2.34 June, 1987 when the accounts 7.26 Cost Accounting (`) 1,00,000 Materials Purchased Wages Paid 45,000 General Expenses Plant Purchased Materials on Hand 30.06.87 Wages Accrued 30.06.87 Work Certified Cash Received Work Uncertified Depreciation of Plant 10,000 50,000 25,000 5,000 2,00,000 1,50,000 15,000 5,000 The above contract contained an escalator clause which read as follows: "In the event of prices of materials and rates of wages increase by more than 5% the contract price would be increased accordingly by 25% of the rise in the cost of materials and wages beyond 5% in each case." It was found that since the date of signing the agreement the prices of materials and wage rates increased by 25%. The value of the work certified does not take into account the effect of the above clause. Prepare the contract account. Workings should form part of the answer. Answer: Profit to be transferred ` 20,000 6. Rex Limited commenced a contract on 01.07.1988. The total contract price was ` 5,00,000 but Rex Limited accepted the same for ` 4,50,000. It was decided to estimate the total profit and to take to the credit of profit and loss account that proportion of estimated profit on cash basis which the work completed bore to the total contract. Actual Expenditure till 31.12.1988 and estimated expenditure in 1989 are given below:– Expenses Materials Labour Plant Purchased (original cost) Misc. Expenses Plant Returned to Stores on 31.12.88 at original cost Actuals Till 31.12.88 (`) 75,000 55,000 40,000 20,000 10,000 Estimate For 1989 (`) 1,30,000 60,000 — 35,500 35,500 As on 30.09.89 Materials at Site Work Certified Work Uncertified Cash Received 5,000 2,00,000 7,500 1,80,000 Nil Full Nil Full The Plant is subject to annual depreciation @ 20% of original cost. The contract is likely to be completed on 30.09.1989. You are required to prepare the contract account for the year ended 31.12.88. Workings should be clearly given. It is the policy of the company to charge depreciation on time basis. Answer: Profit to be transferred to P/L A/c ` 26,400 © The Institute of Chartered Accountants of India Contract Costing 7.27 Profit in reserve ` 32,100 Plant returned to stores ` 27,750 7. A contractor, who prepares his account on 31st December each year, commenced a contract on 1st April 1990. The costing records concerning the said contract reveal the following information on 31st December, 1990; (`) Materials charged to site Labour engaged Foremen's salary 2,58,100 5,60,500 79,300 Plants costing ` 2,60,000 had been on site for 146 days. Their working life is estimated at 7 years and their final scrap value at ` 15,000. A supervisor, who is paid ` 4,000 p.m. has devoted approximately threefourths of his time to this contract. The administrative and other expenses amount to ` 1,40,000. Materials in hand at site on 31st December, 1990 cost ` 25,400. Some of the material costing ` 4,500 was found unsuitable and was sold for ` 4,000 and a part of the plant costing ` 5,500 (on 31.12.90) unsuited to the contract was sold at a profit of ` 1,000. The contract price was ` 22,00,000 but it was accepted by the contractor for ` 20,00,000. On 31st December, 1990, two thirds of the contract was completed. Architect's certificate had been issued covering 50% of the contract price and ` 7,50,000 had so far been paid on account. Prepare contract account and state how much profit or loss should be included in the financial accounts to 31st December, 1990. Workings should be clearly given. Depreciation is charged on time basis. Also prepare the Contractee's account and show how these accounts should appear in the Balance Sheet as on 31st December, 1990. Answer: Notional Profit ` 2,13,250 Profit & Loss A/c ` 1,06,625 Profit Reserve ` 1,06,625 8. One of the building contracts currently engaged in by a construction company commenced 15 months ago and remain unfinished . The following information relating to the work on the contract has been prepared for the year just ended: `' 000 Contract Price Value of work certified at the end of year Cost of work not yet certified at the end of year Costs incurred: Opening balances: Case of work completed Materials on site (physical stock) During the year: Materials delivered to site Wages 580 © The Institute of Chartered Accountants of India 2,500 2,200 40 300 10 610 7.28 Cost Accounting Hire of plant 110 Other expenses Closing balance Materials on site (physical stock) 90 20 As soon as materials are delivered to the site, they are charged to the contract account. A record is also kept of materials as they are actually used on the contract. Periodically a stock check is maintained and any discrepancy between book stock and physical stock is transferred to a general contract material discrepancy account. This is absorbed back to each contract, currently at the rate of 0.5 of materials booked. The stock check at the year end revealed a stock shortage of ` 5,000. In addition to the direct charges listed above, general overheads are charged to contract at 5% of the value of work certified. General overheads of ` 15,000 had been absorbed into the cost of work completed at the beginning of the year. It has been estimated that further costs to complete the contract will be ` 2,20,000. this estimate includes the cost of materials on site at the end of the year finished and also a provision for rectification. Required: (a) Explain briefly the distinguishing features of contract costing. (b) Determine the profitability of the above contract and recommend how much profit to nearest `'000) should be taken for the year just ended. (Provide a detailed schedule of costs) (c) State how your recommendation in (b) would be affected if the contract price ` 40,00,000 (rather than rs. 25,00,000) and if no estimate has been made of costs to completion. (If required, suitable assumption should be made by the candidate). 9. Answer: (a) Refer to Chapter No. 6 Method of Costing (b) Estimated Profit ` 5,07,000 Profit to be taken to Costing P/L A/c ` 4,51,034 (c) Notional Profit ` 4,67,000 A construction company under-taking a number of contracts, furnished the following data relating to its uncompleted contracts as on 31st March, 1996. (` In Lacs) Contract Numbers 723 726 729 731 Total Contract Price 23.20 14.40 10.08 28.80 Estimated Costs on completion of Contract 20.50 11.52 12.60 21.60 Direct Materials 5.22 1.80 1.98 0.80 Direct wages 2.32 4.32 3.90 2.16 Overheads (Excluding Depreciation) 1.06 2.60 2.62 1.05 Profit Reserve as on 01.04.95 1.50 — — — Plant issued at Cost 5.00 3.50 2.75 3.00 Expenses for the year ended 31.03.96 © The Institute of Chartered Accountants of India Contract Costing 7.29 Material at Site on 01.04.95 0.75 — — — Materials at Site on 31.03.96 0.45 0.20 0.08 0.05 Work Certified till 31.3.95 4.65 — — — 12.76 13.26 7.56 4.32 Work Uncertified as on 31.03.96 0.84 0.24 0.14 0.18 Progress payment received during the year 9.57 9.00 5.75 3.60 Work Certified during the year 1995-96 Depreciation @ 20% per annum is to be charged on plant issued. While the Contract No. 723 was carried over from last year, the remaining contracts were started in the 1st week of April, 1995, required. (i) Determine the profit/loss in respect of each contract for the year ended 31st March, 1996. (ii) State the profit/loss to be carried to Profit & Loss A/c for the year ended 31st March, 1996 Answer: (i) 723 726 729 731 Profit (loss) ` In Lacs. 5.20 4.28 (1.27) (0.06) (ii) Profit to be taken to 2.60 1.80 - - Profit & Loss Account (` In Lacs) 10. A company undertook a contract for construction of a large building complex. The construction work commenced on 1st April 1993 and the following data are available for the year ended 31st March 1994. Contract Price Work certified Progress Payments Received Materials Issued to Site Planning & Estimating costs Direct Wages Paid Materials Returned From Site Plant Hire Charges Wage Related Costs Site Office Costs Head Office Expenses Apportioned Direct Expenses Incurred Work Not Certified ` '000 35,000 20,000 15,000 7,500 1,000 4,000 250 1,750 500 678 375 902 149 The contractors own a plant which originally cost `20 lacs has been continuously in use in this contract throughout the year. The residual value of the plant after 5 years of life is expected to be ` 5 lacs. Straight line method of depreciation is in use. As on 31st March, 1994 the direct wages due and payable amounted to ` 2,70,000 and the materials at site were estimated at ` 2,00,000. © The Institute of Chartered Accountants of India 7.30 Cost Accounting Required: (i) Prepare the contract account for the year ended 31st March, 1994. (ii) Show the calculation of profit to be taken to the profit and loss account of the year. (iii) Show the relevant balance sheet entries Answer: Notional Profit ` 3,324000 Profit and Loss A/c ` 1,662000 Work-in-progress in Balance Sheet ` 3,487000 11. Compute a conservative estimate of profit on a contract (which has been 80% complete) from the following particulars. Illustrate four methods of computing the profit: Total expenditure to date Estimated further expenditure to complete the contract (including contingencies) Contract Price Work Certified Work not certified Cash Received Answer: Estimated profit Notional Profit 12. (`) 1,70,000 34,000 3,06,000 2,00,000 17,000 1,63,200 ` 1,02,000 ` 47,000 Explain escalation Clause. Answer: Refer to ‘Chapter No. 6 Method of Costing (I)’ of Study Material 13. An expenditure of ` 4,85,000 has been incurred on a contract till 31st March, 2006 and value of the work certified is ` 5,50,000. The cost of work performed but not yet certified is ` 15,000. The profit of ` 30,000 had been taken to the credit of Profit & Loss Account till 31st March, 2005. The estimated future expenses are ` 1,00,000. The estimated total expenses is to include a provision of 2-1/2 per cent for contingencies. The contract price is ` 7,00,000 and the payment received till date is ` 5,00,000. Calculate the profit to be taken to the credit of Profit and Loss Account for the year ended on 31st March, 2006. Answer: ` 48,571. © The Institute of Chartered Accountants of India
© Copyright 2026 Paperzz