Update on FCPS Construction/Renovation Projects November 2013 Breckinridge Elementary -- Renovation Architect: EOP Architects General Contractor: GC Contract Sum: $12,118,900 Total Project Cost: $14,793,927 Change Orders to Date (14): $116,375 Scheduled Contract Completion Date: July 2013 % of Contract Completed: Revised Completion Date per GC: Isaac Tatum Construction 89.37% January 2014 November 2013 Breckinridge Elementary -- Renovation Rendering of Final Façade November 2013 Breckinridge Elementary -- Renovation Work Completed to Date: Gym CMU work is complete and floor installation at 50% complete. Phase 3 steel set and decking started. Phase 3 concrete slabs poured. Asphalt turnaround complete. Playground mulched, equipment set, and turned over to the owner. Current Work Effort (November): Gym flooring will be complete and bleachers installed. Phase 3 Brick will be complete. Phase 3 roofing will be installed. Phase 3 doors and storefronts will be installed. Phase 3 soffits will begin along with painting. All sidewalks will be complete and fencing will be started. November 2013 Breckinridge Elementary -- Renovation Pavers & Sod Playground Plantings & Mulch Sidewalk @ Preschool Playground November 2013 Breckinridge Elementary -- Renovation Phase 3 -- Brick Gym Wood Flooring New Ramp @ Gym New Bleachers November 2013 Stonewall Elementary -- Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: GC Contract Sum: $12,577,700 Total Project Cost: $15,591,297 Change Orders to Date (15): Scheduled Contract Completion Date: % of Contract Completed: Revised Completion Date per GC: Burchfield & Thomas $218,875 December 2013 72% July 2014 November 2013 Stonewall Elementary -- Renovation Rendering of Final Façade November 2013 Stonewall Elementary -- Renovation Work Completed to Date: Work in Admin. Suite – revised occupancy for November 25 estimated. Cafeteria and Kitchen – masonry, roof & window work complete. Media Center masonry, slab, roof structure & interior soffit framing work complete. Area ‘B’ classroom wing masonry, slab roof structure & interior wall framing complete. MEP rough-in work on-going in Cafeteria + Kitchen areas & New Classroom Wing. Current Work Effort (November): Complete Admin Suite for occupancy. Complete MEP rough-in work in Cafeteria + Kitchen areas & New Classroom Wing. Begin Cafeteria interior finishes for January 2nd occupancy. Begin Kitchen interior finishes and kitchen equip. setup for Feb. 3rd occupancy. Complete Area ‘B’ classroom wing roofing work and set windows. November 2013 Stonewall Elementary -- Renovation Front Entry Canopy Café Looking Toward Entry Café Exterior Café Looking Toward Kitchen November 2013 Stonewall Elementary -- Renovation Kitchen Exterior Kitchen Interior Media Center Classroom Wing Corridor November 2013 James Lane Allen Elementary - Renovation Architect: Moody-Nolan Architects General Contractor: GC Contract Sum: $12,838,000 Total Project Cost: $15,717,304 Change Orders to Date (12): Scheduled Contract Completion Date: % of Contract Completed: Revised Completion Date per GC: Isaac Tatum Construction $171,416 December 2013 77.61% March 2014 November 2013 James Lane Allen Elementary-Renovation Rendering of Final Façade November 2013 James Lane Allen Elementary-Renovation Work Completed to Date: Finished installing the exterior walls in the kindergarten classroom area and Appomattox side of the administration area. Steel erector has set the roof steel. Completed all concrete footings. All windows installed in kindergarten classroom area. All concrete floor slabs have been installed. Current Work Effort (November): Complete the site work on the Appomattox side of the building, including the new bus loop driveway, sidewalks and rough grading. Complete installation of the CMU bearing walls around administration area and kitchen / cafeteria areas. Install the roof deck in the administration area and kitchen / cafeteria areas; begin new roof installation. Continue with overhead MEP rough-in work. November 2013 James Lane Allen Elementary-Renovation Main Entry Main Entry Admin. Area Kitchen Area November 2013 James Lane Allen Elementary-Renovation Admin. Area Side Work New Mechanical Room Exterior of Area C November 2013 Meadowthorpe Elementary -- Renovation Architect: Pearson & Peters Architects General Contractor: GC Contract Sum: $11,252,000 Total Project Cost: $13,958,509 Change Orders to Date (7): Scheduled Contract Completion Date: % of Contract Completed: Revised Completion Date per GC: Isaac Tatum Construction ($8,191) December 2013 66% June 2014 November 2013 Meadowthorpe Elementary -- Renovation Rendering of Final Façade November 2013 Meadowthorpe Elementary -- Renovation Work Completed to Date: Terrazzo flooring installed at balance of Phase 1 area. Kitchen equipment installation complete. Rubber flooring installed in Cafeteria. Wood flooring and stripping installation complete in Gym. Furniture delivered for new media center New bus loop drive near completion. Current Work Effort (November): Phase 1 move in to begin November 22nd and be complete including offices by December 2nd. FCPS will clear out balance of existing school for start of Phase 2-balance of school renovation. New driveway will be complete and open for use by school. November 2013 Meadowthorpe Elementary -- Renovation New Bus Loop Drive New Café New Entry at Café Renovated Gym November 2013 Meadowthorpe Elementary -- Renovation New Nature Studies New Media Center New Music Room New Walk/Ramp @ Bus Loop November 2013 Tates Creek Elementary -- Renovation Architect: GBBN Architects General Contractor: D.W. Wilburn, Inc. GC Contract Sum: $13,844,000 Total Project Cost: $17,163,856 Change Orders to Date (6): Scheduled Contract Completion Date: % of Contract Completed: Revised Completion Date per GC: $278,295 December 2013 82% May 2014 November 2013 Tates Creek Elementary -- Renovation Rendering of Final Façade November 2013 Tates Creek Elementary -- Renovation Work Completed to Date: Office bearing walls have been completed. Mezzanine structural steel has been set and concrete slab placed. Terrazzo flooring has been completed in the northwest classroom wing. Bus loop sub grade is complete and retention pond is 90% complete. Current Work Effort (November): Complete framing of all partition walls. Complete all roofing installation. Complete floor tile and ceramic tile in the kitchen. Place asphalt on new bus drive. November 2013 Tates Creek Elementary -- Renovation New Kitchen New Main Entry Completed Restrooms North Admin. Addition November 2013 Tates Creek Elementary -- Renovation Storm Water Drainage Curbs & Gutters @ South Drive Sidewalk & Curbs @ South Drive South Entrance November 2013 Deep Springs Elementary -- Renovation Architect: EOP Architects General Contractor: GC Contract Sum: $12,152,800 Total Project Cost: $15,082,114 Change Orders to Date (5): Scheduled Contract Completion Date: % of Contract Completed: Revised Completion Date per GC: Griggs Enterprises $162,962 December 2014 26.59% February 2015 November 2013 Deep Springs Elementary -- Renovation Rendering of Final Façade November 2013 Deep Springs Elementary -- Renovation Work Completed to Date: Phase 1 bar joist and deck installation is complete. Roofing has begun at the Decagon. Brick has started at the Decagon area. Duct and sprinkler has been installed in the gym. Sod has been installed around the retaining wall. Footings and foundations have been installed at the Area A addition. Current Work Effort (November): Metal stud work will continue in the Decagon. CMU will be completed in the Phase 1 Area. Brick in the Decagon area will be complete. Install windows and storefronts in the Decagon. Start painting in the Decagon and Gym. Complete roofing at the Decagon and Gym areas. November 2013 Deep Springs Elementary -- Renovation Footings at Area A Addition Decagon – Brick New Rear Entry Corridor Decagon – Metal Stud Framing November 2013 Deep Springs Elementary -- Renovation Openings for Storefront Windows Gym Remediation Joists, Deck & Light Tubes Windows in Decagon November 2013 Garden Springs Elementary -- Renovation Architect: Sherman Carter Barnhart Architects General Contractor: GC Contract Sum: $11,765,500 Total Project Cost: $14,758,998 Change Orders to Date (0): Scheduled Contract Completion Date: % of Contract Completed: Revised Completion Date per GC: D.W. Wilburn $0 December 2014 39% No Change November 2013 Garden Springs Elementary--Renovation Rendering of Final Façade November 2013 Garden Springs Elementary -- Renovation Work Completed to Date: Completed stone & brick veneer at north wing. Completed tile in north addition restrooms. Completed steel erection and metal decking at Administration Area. Started stone & brick veneer at Administration Area Started Window installation. Started painting in west and north additions. Continued metal stud framing at Administration Area. Current Work Effort (November): Start terrazzo flooring in Phase 1 areas. Start installation of roof top units at Phase 1 areas. Start metal wall panels. Continue painting at Phase 1 areas. Complete window installation at Phase 1 areas. November 2013 Garden Springs Elementary -- Renovation New Admin & Lobby North Addition Steel Framing – Admin Area West Addition November 2013 Garden Springs Elementary -- Renovation New Windows & Walls @ Existing Classroom New Tile New Classroom New Music Room November 2013 Glendover Elementary -- Renovation Architect: Pearson & Peters Architects General Contractor: GC Contract Sum: $12,163,000 Total Project Cost: $15,100,225 Change Orders to Date (2) Scheduled Contract Completion Date: % of Contract Completed: Revised Completion Date per GC: Woodford Builders $27,702 December 2014 29% No Change November 2013 Glendover Elementary -- Renovation Rendering of Final Façade November 2013 Glendover Elementary -- Renovation Work Completed to Date: Interior and exterior CMU partition walls nearly complete. Under slab sanitary complete and interior slabs poured back at all trenches. Roof joists, metal deck and CMU walls complete at classroom addition. Electrical, Plumbing, Sprinkler and HVAC rough-in at approximately 68% complete. Aluminum Window Frames installed. Permeable Pavers installed over compacted gravel base at new vehicular drive. Current Work Effort (November): Complete installation of permeable paver system at drive back to site access point. Continue mechanical, plumbing, electrical, fire alarm and sprinkler rough-ins. Install glazing at all exterior window frames. Complete installation of exterior wall rigid insulation and begin brick veneer. Install new electrical switch gear. November 2013 Glendover Elementary -- Renovation Permeable Paver Drive New Electrical Transformer Slab Permeable Paver Drive New Classroom Addition November 2013 Glendover Elementary -- Renovation West Classroom Wing West Classroom Wing Above-ceiling Rough-ins Rough-in at Restrooms November 2013 Jessie Clark Middle -- Renovation Architect: Tate Hill Jacobs Architects General Contractor: GC Contract Sum: $18,041,500 Total Project Cost: $22,377,666 Change Orders to Date (3): Scheduled Contract Completion Date: % of Contract Completed: Revised Completion Date per GC: Alliance Corporation $8,249 July 2015 10.14% No Change November 2013 Jessie Clark Middle -- Renovation Rendering of Final Façade November 2013 Jessie Clark Middle -- Renovation Work Completed to Date: Installed shoring in Gym and demo’d stage floor. Installed footings and slab in Future Entry Corridor and began CMU block installation for firewall. Installed, grouted and insulated approx. 80% of CMU for exterior wall along front of New Addition. Installed Daiken VRV units boxes in Phase 1 classroom renovation area. Completed underground sanitary and acid pipe installation in Phase 1 classroom renovation area Current Work Effort (November): Begin installation of curbs at new entry road and parking lot. Begin demolition of existing steel beam and CMU block at Gym Stage area. Begin roof work on existing Gym Complete interior footings and install concrete slabs in 1st floor New Addition. Begin brick installation on New Addition. November 2013 Jessie Clark Middle -- Renovation Foundation at Future Entrance Firewall Installation Storm Sewer Installation Restroom Plumbing Wall November 2013 Jessie Clark Middle -- Renovation Enlarging Stage Opening Construction 101 Construction 101 in Job Trailer Utility Installation November 2013
© Copyright 2026 Paperzz