ISSUE 10 – MARCH 2016 Welcome to Illumination, Winchester Cathedral’s projects newsletter. This issue will keep you up-to-date with the work that is well underway on all aspects of the project and reveal what is going on underneath our splendid temporary roof structure. Foliate boss before conservation (left), Tudor Rose after conservation (centre), and inscription found on the reverse of the large picture boss (right). PROJECT IN FULL SWING Our project is in full swing in many areas. Current activities include: Presbytery Windows: Holy Well Glass has been appointed to work on the glass conservation and the first pair of windows has been removed. In all, eight windows will be worked on off-site, in pairs, for conservation and restoration. The ninth window, the East Window, will be worked on in situ. The Cathedral stonemasons are restoring the stone tracery. Altogether, work to the windows will take three years to complete. The stone has been purchased from Caen, France Whilst working on the large picture bosses, the conservators made an exciting discovery. An inscription has been found on the reverse of one of the bosses commemorating Bishop Fox. Dated 1819, the inscription includes the names of the Bishop, Dean and Chapter, and the painter from the period of the major repair work to the bosses and roof, 1810–1819. South Transept: approval was granted in December 2015 by the Cathedral Fabric Commission for England (CFCE) for the new Roof bosses: conservation began on the roof lift providing access to the mezzanine and bosses in November 2015. Work has been triforium levels within the south transept. competed on the foliate bosses, removing It will be the first lift in a cathedral to travel the complete covering of 20th century cream through a 12th century groin vault. The paint to uncover the original deep colours and construction works package is currently gilding from the 1500s. Modern paint is also being removed from the picture bosses and the being agreed. original painted areas conserved. The rib vaults Mortuary Chests: the restoration of the mortuary chests was completed in October themselves are being cleaned and repainted. 2015, although work to examine the contents Once completed, the vibrancy of the bosses of the chests continues. will be striking. Cathedral Lighting: a lighting contractor, has won the contract to install new lighting in the East End of the Cathedral, encompassing the North Transept, the Presbytery and Presbytery Aisles, the Quire, Retroquire and Chapels. The project will provide beautiful lighting throughout these areas but most importantly it will remove the hazard of dangerous wiring and lights that generate heat. Works started in January 2016. This work has been funded by a grant from the First World War Centenary Cathedral Repairs Fund. IN FOCUS Work to the Pre The previous issue of Illumination described the enormous temporary roof that has been erected over the East End of the Cathedral. So what is it for – and just what is going on underneath? Quite simply, all the lead from the Presbytery roof needs to be taken off in order to be re-cast and then re-laid. This is necessary because the lead has reached the end of its ‘natural life’ and is failing to keep the Cathedral below water-tight. According to plaques found on the roof, the lead ranges in age from 1819 (the year Queen Victoria was born!) to 1897: it is fracturing or cracking in places and fittings have failed, leading to the sheets slipping out of alignment. ‘The lead is thicker than we would normally expect considering its age’, says Geoff Beetham of Norman and Underwood, one of the country’s leading roofing contractors, with extensive experience of cathedrals, churches and many other important buildings in the UK and abroad. ‘However additional quantities need adding to bring each element up to the required thickness for re-laying’. Around 50 tonnes of lead will be needed. ‘The lead will be re-cast on a casting table bedded with planed sand, using a process little changed since Roman times’, continues Geoff. ‘The process is carried out at our premises in Leicester, with a large extraction Top left: Old lead being removed Bottom left: New timbers and lead Centre: New lead joints being rolled Far right: Archive images supplied by Norman & Underwood Right top: Deathwatch beetle larvae Right centre: Original lead roof Right bottom: 1195 KG of lead packaged for collection esbytery Roof chimney and breathing apparatus. During the early 20th century, however, a horse and cart would have transported the casting table to site’. As a metal, lead suffers from thermal expansion and contraction: therefore the size of each sheet is restricted and joints must allow for movement. Hidden fixings are used to maintain waterproofing and clips allow the lead to move while also restricting lifting in high winds. ‘When lead is laid by experienced craftsmen to the standards set out by the Lead Sheet Association under the guidance of a good conservation architect, we would expect a lifespan well in excess of 100 years’, reports Geoff. His firm should know: Norman and Underwood have been repairing and restoring roofs since 1826. With 8 men having been working on the roof at any one time – and up to 14 when materials needed moving around – the work is now over three-quarters complete and due to be finished in April this year. The work has revealed deathwatch beetle, but readers should not be alarmed. The beetle larvae only eat damp wood: the whole object of the exercise is to eliminate leaks and thereby ensure that the roof timbers remain dry – and unappetising! CURATOR’S DIARY A ‘time capsule’ has been found by one of the conservators while working high on the scaffolding in the Presbytery vault last month. It consists of a folded piece of lead wrapped in coarse paper, inside which is a letter with a George III halfpenny dated 1807. There are numerous, rather confusing inscriptions on the lead which makes the sequence of events a puzzle, but it seems that it was first placed there by the Cathedral’s carpenter, Peter Stubington and his colleagues in October 1808. However as the letter inside is dated 1810, it must have been retrieved and the letter inserted at that date. It describes how the vault was renewed in 1810 using ‘Real English Oak’, and gives the names of the carpenters who worked on it with freemason symbols. A further inscription shows that it was rediscovered by two further workmen in 1819 who signed it with their names, James Jepp and Alexander McKenzie, and replaced it where it has remained undisturbed for nearly two hundred years. I hope to be able to put it on display for all to see very shortly. Jo Bartholomew, Curator and Librarian SUMMARY OF CAPITAL WORKS • Urgent repair work involving re-leading the Presbytery roof and conserving the fine 16th Century vault below with its 250-plus bosses • Conservation of the glass and renewal of the surrounding stonework of nine unique medieval glass windows in the Presbytery at Clerestory Level • The Learning Centre Project, including a new build extension in green oak using traditional building techniques, will greatly enhance the quality of our outreach to 20,000 children annually from Hampshire schools and beyond, as well as enabling all-age learning • New exhibitions at three levels in the Cathedral’s stunning South Transept will give visitors an exciting encounter with Winchester’s greatest treasures, including the world-famous Winchester Bible, which are currently not readily accessible and often overlooked • New wiring, lighting, sound and audio-visual systems in the Cathedral and Learning Centre. THE FRIENDS’ WINDOWS APPEAL Back in 2013, the Friends launched its five-year Windows Appeal, to raise £800,000 towards the cost of the conservation of the medieval stained glass in the Cathedral – an essential part of the Cathedral’s current development programme. In less than three years we have raised £772,000. This is an incredible achievement and we are so grateful to all the Friends for their amazing support. With £28,000 left to reach our target, the fundraising continues. As described on page 1, the work on the windows has begun, giving our search for the remaining funds a new urgency. The conservation of the windows will take longer than any other part of the Cathedral’s development programme. Despite this, we would like to secure our fundraising target as soon as possible, so that we can continue to help the Cathedral in other ways. If you would like more information on the Windows Appeal, the conservation work on the glass or how to donate, please contact Lesley Bestwick on [email protected]. Supported by the Heritage Lottery Fund Cathedral Office 9 The Close, Winchester, Hampshire SO23 9LS Tel: 01962 857 200 [email protected] www.winchester-cathedral.org.uk
© Copyright 2026 Paperzz