7th Street Grade Separation Project Attachment 12 Basis of Design June 2015 MAPSS: 7th Street GSP DBM PORT OF OAKLAND 7TH STREET GRADE SEPARATION WEST PROJECT DESIGN BASIS MEMORANDUM (FINAL) MAPSS: 7th Street GSP DBM Vicinity Map The Port of Oakland MAPSS: 7th Street GSP DBM Table of Contents Contents 1. INTRODUCTION ...................................................................................................... 1 2. BACKGROUND ........................................................................................................ 2 3. 2.1 The Existing Roadway Networks ..............................................................3 PURPOSE AND NEED ............................................................................................. 4 4. Purpose ..................................................................................................................4 Need .......................................................................................................................4 DEFICIENCIES ......................................................................................................... 5 5. 4.1 Local Roadway and Intersection Operation Deficiencies ..........................5 4.2 Existing Railroad Conditions .....................................................................5 4.3 Traffic Accident Data and Safety Analysis ...............................................5 4.4 Secondary Deficiencies ..............................................................................6 TRAFFIC IMPACT ASSESSMENT ......................................................................... 6 6. 5.1 Preliminary Assessment and Findings .......................................................6 5.2 Summary of Grade Separation Analysis and Findings ..............................7 Intersection Turning Movements ........................................................................10 PROJECT SCOPE .................................................................................................... 10 7. 6.1 Site Constraints .......................................................................................10 6.2 Roadway Improvements .........................................................................13 6.4 Bridge and Other Structures....................................................................13 6.5 Bicycles and Pedestrians Improvements (Complete Street) ...................14 6.6 Traffic Signal and Lighting .....................................................................14 RIGHT-OF-WAY..................................................................................................... 14 8. 7.1 Right-of-Way Need:................................................................................14 Roadway .............................................................. Error! Bookmark not defined. 7.1 Railroad: ..................................................................................................15 UTILITIES ............................................................................................................... 15 9. PERMITS AND APPROVALS ............................................................................... 19 10. STAKEHOLDER ..................................................................................................... 20 11. DESIGN CODES, REGULATIONS, AND STANDARDS .................................... 21 10.1 Civil..........................................................................................................21 10.2 Architectural ............................................................................................24 10.3 Structures .................................................................................................24 10.4 Utilities.....................................................................................................24 10.5 Drainage ...................................................................................................24 10.6 Traffic Control and Lighting ....................................................................25 12. FUNDING ................................................................................................................ 25 13. SCHEDULE ............................................................................................................. 26 MAPSS: 7th Street GSP DBM 14. PROJECT PERSONNEL ......................................................................................... 26 ListofAttachments A. Port of Oakland MAPSS – Project Site Constraints B. Roadway Typical Cross Sections 1. INTRODUCTION Project Description: The Port of Oakland (Port) is the fifth busiest port in the US. It operates container terminals encompassing 779 acres in area. The Port and several railroad companies maintain and operate a network of roadways and railroads for movement of freight and goods within and outside the Port area. The Port has identified a number of infrastructure improvement projects to address current transportation constraints, support the need for existing and future tenants, and to promote and accommodate future growth. In November 2014, the Port developed a prioritized list of strategic projects to support the Port’s needs. The 7th Street Grade Separation Project (GSP) considered a top priority project. In addition, the Port identified improvement needs for Middle Harbor Road to improve circulation and provide access to new facility within the Port of Oakland. It is anticipated that feasibility study and project scoping for Middle Harbor Road will begin in mid 2015. 7th Street Grade Separation Project The 7th Street Grade Separation project has two components: the West Project and the East Project. The 7th Street Grade Separation West Project includes the construction of an elevated 7th Street/Maritime Street intersection and a tail track extension for the Burlington Northern–Santa Fe (BNSF) Oakland Intermodal Gateway (OIG), also known as the Joint Intermodal Terminal (JIT), that facilitates the expansion and reconfiguration of OIG. The proposed project will reconstruct the segment of 7th Street between Maritime Street and Navy Roadway. The portion of 7th Street west of Maritime Street will be realigned to form a T-intersection at its junction with Middle Harbor Road and West Maritime Street. Maritime Street north of 7th Street will become a cul-de-sac with limited access to the PG&E’s Davis and Cuthberston Substation and the Regional Technical Training facility. Navy Roadway will be demolished and traffic on Maritime Street will use the proposed 7th Street Tintersection to access West Maritime Street, and vice versa. The project also includes a rail spur that connection the OIG to Outer Harbor Intermodal Terminal (OHIT). Figure 1 below depicts the proposed 7th Street Grade Separation West Project elements. The project also includes utility infrastructure upgrades along 7th Street. The project cost was estimated at $176 million (in 2015 dollars) which includes costs for final design (PS&E), right-ofway and construction. The proposed 7th Street Grade Separation East Project is a planned longer-term future project that widens 7th Street at the UPRR Underpass. It also allows for the additional of rail spurs and tracks at the UPRR’s Oakland International Container Terminal (OICT) rail yard. However, it is outside the scope of the current project and is not included in this Basis of Design Memorandum. 1 Figure 1: Proposed 7th Street Grade Separation Project Elements 2. BACKGROUND The Port of Oakland (Port) is a major port and logistics support center in the San Francisco Bay Area, processing about 2.4 million TEU’s (twenty-foot equivalent unit) of container cargo in 2013 through eight active terminals. Landside shipping consists of about 77% trucks and 23% rail. In 2002, the City of Oakland prepared a project-level Environmental Impact Report (EIR) 1 to evaluate the environmental impacts of the Oakland Army Base (OAB) Redevelopment Plan. The City approved the Redevelopment Plan in 2002 and the Board of Port Commissioners adopted the EIR of the Oakland Army Base Redevelopment Plan in September 2002 as a responsible agency under California Environmental Quality Act (CEQA). The Redevelopment Plan designated approximately 360.5 acres of OAB property for transportation and logistics support purposes, including railroad and street infrastructure. The Port of Oakland has been working closely with the City of Oakland on the design concept to advance the development after the transfer of the Army Base property ownership. 1 Source: Environmental Impact Report for the Oakland Army Area Redevelopment Plan, City of Oakland/ Borchard & Associates, April 2002. 2 In 2004, the Port completed a Maritime Development Alternative Study (MDAS) to evaluate potential development plans. The study revealed that “The capacity of the Port is not currently constrainted by its maritime facilities. It is constrained by the capacity and performance of the road and rail intermodal connectors.” 1 The study called for improvements of the inland transport links, including the two major Inland Point Intermodal (IPI) rail links: the Railport Oakland owned and operated by Union Pacific Railroad (UPRR), and the Oakland International Gateway (OIG) owned by the Port and operated by BNSF. The layout and operation of the Railport is outside of the Port’s control. With regard to the OIG, the former OAB property located between the UPPR mainline and the Port’s Outer Harbor Terminals was indentified in the MDAS as a potential location for an intermodal rail yard. The rail yard would increase the Port’s throughput potential and facilitate its expansion needs. However, the design of rail system will require reconfiguration of adjacent roadways because of the unique geometry of the Port. In addition, the Port has been experiencing significant traffic congestion along Maritime Street, 7th Street, and Middle Harbor Road due to substantial gate downtime required for train crossing at major intersections. For the past decade, the Port has been exploring alternatives to relieve truck and rail traffic congestion and to support both existing and proposed port activities, including the redevelopment of the OAB. A Planning level study indicates that a single train that is loaded at the Port is equivalent to 750 truck trips.2 Enhancing the rail access would potentially increase the capacity for rail movement and reduce the demand for truck transport and hence, help alleviate both rail and vehicle traffic congestion. In September 2007, a Port of Oakland Outer Harbor Intermodal Terminal (OHIT) Development Planning Study was performed to evaluate a range of rail and roadway conceptual design alternatives. It is determined that providing tail tracks which connect the OIG to the former OAB site, now being proposed to be OHIT, are critical to switching efficiency of the OHIT since this will allow simultaneous train movement 3. The construction of OHIT tail tracks and realigned access to OIG cross 7th Street in the vicinity of West Maritime Street will require a new grade separation. In 2008, a total of $242 million of Proposition 1B Trade Corridor Improvement Funds (TCIF) was allocated to the Port for the proposed OHIT and 7th Street Grade Separation projects. The TCIP funds require matching funds from private or other public sources. In July 2011, the City of Oakland Redevelopment Agency and the Port of Oakland executed a Cost Sharing Agreement for the development of infrastructure, OHIT rail yard, public utilities and public streets necessary for the OAB redevelopment. As part of the master planning and preliminary engineering process, an Initial Study (IS) was completed in 2012 as an addendum to the 2002 EIR to capture the change in land-use since the completion of the 2002 EIR. The Initial Study revealed that the OAB redevelopment plan is consistent with the City of Oakland’s General Plan Land Use designation for the site, and the Project would not result in any significant land use impacts not previously disclosed. This memorandum provides background for the project’s purpose and need, existing operational challenges, project constraints, project scoping, as well as the design criteria. 2.1 The Existing Roadway Networks The 7th Street Grade Separation Project is located in the Port of Oakland, California on 7th Street generally bounded by Maritime Street/Navy Roadway and Bay Street. The existing roadways within 1 Sources: Final Report Maritime Development Alterative Study, Port of Oakland, Parsons/JWD; Outer Harbor Intermodal Terminal, Parsons/JWD/TY Lin, September 2007 2 Source: Outer Harbor Intermodal Terminal, Parsons/JWD, September 2007 3 Source: Outer Harbor Intermodal Terminal, Parsons/JWD, September 2007 3 the Port facilities include 7th Street, West Maritime Street, and Middle Harbor Road. Maritime Street is south of 7th Street and West Maritime Street is north of 7th Street. 7th Street is one of the three main gateways to the Port of Oakland. Maritime Street (via West Grand Avenue from the north) and Middle Harbor Road/Adeline Street (from the south) are the two gateways. 7th Street 7th Street is a four-lane roadway with left turn pockets at most intersections. It provides access to the Port from the south. 7th Street provides a UPRR underpass between Bay Street and Maritime Street. Traffic signals are provided at its intersection with the I-880 ramps, Maritime Street, and Middle Harbor Road. The 7th Street interchange with the I-880 ramps forms the central gateway to the Port. 7th Street also provides access to the TraPac Terminal and Ben E. Nutter Terminal. Maritime Street Maritime Street provides the primary northern access to the Port and begins where it meets Wake Avenue under Interstate 80. The existing Maritime Street is a 4-lane roadway (2-lane in each direction) with a median left-turn lane between Burma Road and Navy Roadway, and between 7th Street and approximately 300 feet north of Middle Harbor Road intersection. Currently, there are no existing striped shoulders along Maritime Street. The median turn-lane north of 7th Street often supports the queue of eastbound left-turn truck traffic waiting to turn into the Ports America Terminal. The queues sometimes extend to 7th Street. Maritime Street also provides direct access to the Ports of America Outer Harbor Terminal and the OIG rail yard. Middle Harbor Road (Adeline Street) is currently striped as a 4-lane roadway (2-lane in each direction) with a two-way left-turn lane that provides southern access to the Port. Middle Harbor Road transitions to Adeline Street and connects to I-880 at the 5th Street intersection. Striped shoulders are provided in both directions. The BNSF rail tracks are running parallel to Middle Harbor Road on the north side of the street. Therefore, the center turn lane primarily serves the south side of Middle Harbor Road except at the intersections of Maritime Street/Middle Harbor Road and at the two entrances to Railport Oakland on Adeline Street at and east of the junction of Middle Harbor Road. 3. PURPOSE AND NEED Purpose Enhance the safe transport of freight by truck or rail in Alameda County, including projects that reduce conflicts between freight movement and other types of transportation. Reduce greenhouse gas production in the transport of goods. Mitigate environmental impacts of freight movement on residential neighborhoods. Enhance coordination between the Port of Oakland, the Oakland Airport and local jurisdictions for the purposes of improving the efficiency, safety, and environmental and noise impacts of freight operations while promoting a vibrant economy. Need 7th Street primary access from the Port of Oakland to I-880 and is a major Port gateway. The existing at-grade railroad crossing on Maritime Street south of 7th Street causes significant traffic backup throughout the Port area. As cargo shipment at the Port of Oakland increases, intra-port truck trips are expected to increase and will impact operations at individual roadway intersections. 4 The existing roadway network constraints the expansion of the OIG and the rail infrastructure serving the Port. 4. DEFICIENCIES 4.1 Local Roadway and Intersection Operation Deficiencies The Port currently experiences significant traffic congestion due to trains blocking both at-grade rail crossings that provide access to OIG. The two at-grade rail crossings intersect Maritime Street at 7th Street and at Middle Harbor Road. Maritime Street between 7th Street and Middle Harbor Road provides access to a number of uses, including the OIG, the Port’s maintenance yard, and warehouse facilities, including Unicold, GSC Logistics, and Pacific Coast Container. The blocked crossings cause significant congestion at the intersections of Maritime Street/7th Street and Navy Roadway/7th Street. 4.2 Existing Railroad Conditions The existing railroads includes two overpass structures over 7th Street within the Port of Oakland – one at the eastern end of the project (UPRR mainline) near the junction of 7th Street/ I-880; and the other one is located near the center of the project that is operated jointly by UPRR and OIG. The UPRR mainline underpass was constructed in the late 1990s while the joint UPRR/OIG Underpass was constructed between 1930s and 1950s. The joint UPRR/OIG railroad underpass provides two-lanes, two-way traffic (two lanes in each direction) that is separated by a pier wall in the median. The existing underpass has non-standard horizontal and vertical clearance. The narrow lane widths of the underpass do not accommodate sideby-side passage of trucks so this segment of 7th Street does not function as a two-lane street in each direction, except during extremely congested conditions where speeds are slow enough to accommodate side-by-side trucks. This creates congestion at the intersection of 7th Street/Maritime Street when the Ports America Terminal queue extends to 7th Street. The limited width of the deck of the underpass also constrains the installation of rail spurs and track needed to improve rail access to the various terminals and yards. The existing UPRR and OIG railroad tracks are running parallel to I-80 west of the freeway before they split westerly and southeasterly under the BART overheads structures. The speed limit for trains in this part of the Port is set at 10 miles per hour. Due to the tight turn radius below the BART structures, trains need to maintain a low speed through curves. The UPRR’s Railport Oakland intermodal yard is currently operating at capacity. Today, trains accessing the OIG must cross through UPRR’s yard. This requires all trains accessing the Port to slow significantly (no more than 5 miles per hour) and limits UPRR operations, causing significant delays to both BNSF and UPRR operations at the Port. This rail operational deficiency limits the good movements through the Port requiring additional cargos to be handled by trucks. The construction of the proposed OHIT Storage Yard and tail tracks would provide additional rail capacity to improve the rail operation efficiency, alleviate rail congestion at the OHIT, and reduce conflicts between rail and truck traffic at major intersections. 4.3 Traffic Accident Data and Safety Analysis Collision data was collected for two roadway segments using the Statewide Integrated Traffic Records System (SWITRS) database as part of the Maritime Street and Middle Harbor Road Traffic Calming Memo. The two segments analyzed are: 1. Middle Harbor Road: 7th Street to Maritime Street 5 2. Maritime Street: 7th Street to Middle Harbor Road The most recent 5-year traffic accident data (from January 2008 to December 2012) was analyzed. There were 108 recorded crashes in the study area, with 49 occurring at intersections. The top 3 violations were improper turning (42.6%), unsafe speed (20.4%), and traffic signals and signs (5.6%). Two fatal crashes were recorded, both citing unsafe speed as the cause of collision. One occurred in the middle of the night, at 1:55 AM on August 17, 2012, and involved a vehicle hitting a fixed object approximately 300 feet east of the intersection of 7th Street and Maritime Street. The other occurred on a late Saturday afternoon, at 5:45 PM on January 30, 2010, when a speeding motorcycle collided with a pedestrian, approximately 1,800 feet west of the intersection of Middle Harbor Road and Maritime Street. Recently, the Port installed speed tables on Middle Harbor Road to deter reckless driving. Truck behavior related to these new devices was observed. The speed tables slightly reduce truck speeds, but in general, truck and auto traffic typically pass over the devices at speeds of 30 miles per hour. 4.4 Secondary Deficiencies The Port of Oakland has been having trouble with illegal street racing and the accompanying “sideshows” on Middle Harbor Road. These illegal gatherings have resulted in loitering on Port property and injuries to participants including two fatalities in the last couple of years. These illegal activities are also disrupting tenants some of whom operate on a 7 day, 24 hour basis. Typical disruptions include: Street racing and sideshows blocking access to tenant driveways Gunshots fired into the air Consumption of alcohol along the street Littering including broken glass on the roadways The Maritime Street and Middle Harbor Road Traffic Calming Memo (dated 2014) identified potential physical improvements and traffic calming measures to deter illegal and dangerous driving behavior on Middle Harbor Road and Maritime Street. 5. TRAFFIC IMPACT ASSESSMENT In order to assess the existing traffic conditions and to evaluate the performance of the proposed 7th Street Grade Separation Project, an At-Grade Rail Crossing Analysis Technical Memorandum (dated June 2014) was prepared for the project. The Rail Crossing Analysis studied the existing conditions and three Grade Separation concepts at the 7th Street crossing using VISSIM microsimulation model. The findings of the analysis were summarized in the subsections below. 5.1 Preliminary Assessment and Findings The At-Grade Rail Crossing Analysis focuses on the study of operational conditions for the three major intersections – Maritime Street/Middle Harbor Road, 7th Street/Middle Harbor Roads and 7th Street Maritime Street. Trains operate at 10 miles per hour through this part of the Port. Study indicated that a 10-minute railroad crossing gate downtime is required for the passage of a typical freight train (9,000 feet) entering OIG. An extensive length of traffic queue would form while vehicles are waiting at the crossing gate for train to clear the intersections. It often takes another 10 minutes for the traffic queue to dissipate during the peak hours, causing an overall 20-minute traffic delay for each train event. 6 Due to the current configuration of the intersection of 7th Street/Maritime Street, trucks often queue beyond the UPRR Underpass. Based on the output of the VISSIM model, the maximum length of queue is estimated at 1,701 feet, which is equivalent to the total length of twenty three STAA1 trucks, with 100.7 second per vehicle delays at the intersection of 7th Street/Maritime Street. The queues occur when trains block Maritime Street, as well as when the marine terminals along Maritime Street and 7th Street experience severe congestion at the terminal gates. The accumulative effect causes significant traffic delays in the Port. 5.2 Summary of Grade Separation Analysis and Findings Findings of the 2002 EIR The 2002 EIR concluded that redevelopment would cause the following potential significant impacts on transportation and traffic system in the vicinity of 7th Street and Maritime Street and that mitigation measures are required2: The Level of Service (LOS) to degrade to worse than LOS D at the intersections of 7th Street/Maritime Street (Impact 4.3.1); Result in traffic hazards to motor vehicles, bicycles, or pedestrians due to inadequate design features or incompatible uses (Impact 4.3-3); Fundamentally in conflict with adopted policies, plans, or programs supporting alternative transportation (Impact 4.3-5). The redevelopment would also result in the following significant cumulative transportation impacts: Increased congestion at intersections exceeding the cumulatively significant threshold at the intersection of 7th Street/Maritime Street (Impact 5.3-1). Findings of the 2012 IS Since the approval of the 2002 EIR, roadways in the vicinity of the project have been modified. 7th Street was extended and connected to Middle Harbor Road to provide access to Middle Harbor Shoreline Park. The former Middle Harbor Road was renamed Maritime Street. West Grand Avenue has been modified from three travel lanes to two travel lanes in each direction with the additional of a bicycle lane. A Class 1 bike path was installed on 7th Street east of Wood Street. The comparison of the existing intersection turning movement traffic counts collected in year 2002 and year 2012 indicated that the traffic volumes in 2002 were generally higher than the 2012 volumes. Table 1 below compares the LOS under year 2002 and year 2012 project conditions. 1 STAA – The Surface Transportation Assistance Act of 1982. The STAA vehicle is a truck tractor-semitrailer with the maximum length of 48-ft semitrailer. Although the tractor length and overall length is unlimited by law, the semitrailer length usually limits the overall length of the truck to 72-ft. 2 Source: Oakland Army Base Area Redevelopment Plan Environmental Impact Report, City of Oakland/Borchard & Associates, April 2002. 7 Table 1: Intersection Level of Service for the Year 2002 and 2012 Conditions. AM Peak Hour Intersection LOS PM Peak Hour Delay* LOS Delay* 2002 EIR Existing Conditions Plus Project Condition th 7 Street & Maritime Street F 126.8 E 78.5 D 36.4 B 19.8 2012 Existing Condition th 7 Street & Maritime Street C 25.0 2012 Existing Plus Project Condition th 7 Street & Maritime Street C 21.1 *Delay in seconds per vehicle Note: (1) Unacceptable level of service indicated in bold. As shown in Table 1, the 2012 Project would improve the PM peak hour traffic from existing LOS D to LOS B. The 2012 Project would not cause the LOS to degrade to worse than LOS E at the intersection of 7th Street & Maritime Street (Impact 4.3.1 and Impact 5.3-1). Therefore, the 2012 Project would not create a significant impact under Existing plus Project conditions and mitigation measures are not required. The 2012 IS also concluded that the OAB redevelopment project is consistent with the City’s General Plan In order to address 2002 EIR Impact 4.3-3, the following mitigation measures with regard to traffic hazards are recommended by the 2012 EIR: Mitigation Measure 3.16-5: The City shall provide a shoulder with a minimum width of 8 feet on the west side of the Maritime Street to accommodate queuing trucks and minimum intrusion onto the southbound travel lane. Mitigation Measure 3.16-6: The City shall provide a 9-foot wide area along the entire west side of Maritime Street in this area to accommodate sidewalk and utilities (exact dimensions of these elements will be determined by the City’s Transportation and Infrastructure Divisions during the PUD process). Mitigation Measure 3.16-7: The City shall provide an 18-foot wide area along the entire east side of Maritime Street in this area to accommodate Class I bicycle path and utilities (exact dimensions of these elements will be determined by the City’s Transportation and Infrastructure Divisions during the PUD process). The 2012 EIR concluded that emergency access routes to most of the site and adjacent properties appear to be reasonably well-served. In order to address 2002 EIR Impact 4.3-4 and Impact 5.3-4, the following mitigation measures with regard to emergency access are recommended: Mitigation Measure 3.16-15a: The Project Sponsor shall develop, in consultation and coordination with adjacent property owners (including EBMUD) an emergency response plan for the OAB project, which addresses ingress/egress. When comparing the number of daily traffic served under year 2002 and 2012 project conditions, the proposed 2012 IS project conditions would generate approximately 6,820 fewer daily trips than the 2002 EIR project conditions, including 1,410 fewer trips during the AM peak hour and 1,220 fewer 8 trips in the PM peak hour.1 In addition to the number of trips generated on the project site, travel outside of the project site would also be affected by the redevelopment project. Currently, BNSF maintains its major Northern California rail yard in Richmond and a small yard facility near 34th and Wood Streets in Oakland. Under the current agreement with UPPR, BNSF uses the UP rail lines for rail movements between Richmond and Oakland, and from Oakland to marine terminals in the Port. Oversize and heavy loads need to be routed from Richmond to Wood Street yard through the UP mainline and then interchanged with the Oakland Terminal Railroad for the final movement to marine terminals. The OAB redevelopment proposes to expand the existing OIG intermodal capacity at the Port which would allow the BNSF to operate more effectively at the Port. Within the Port, intermodal cargo was handled in the Railport Oakland and OIG rail yards. From the Port and the Bay Area, most of UPPR’s and BNSF’s priority freight is shipped east to other points in the US through their Stockton Intermodal Facilities in California Central Valley. The OIG rail yard proposed by the OAB redevelopment project would serve at least 95% intermodal cargo, and would make available more capacity at the UPRR rail yard to serve domestic cargo that would otherwise need to be served in the Central Valley. It would improve the trip distribution and throughput at the Port. Near-term Traffic Improvement for 7th Street Grade Separation While the traffic studies for the 2002 and 2012 environmental documents include other background projects reflecting the OAB built-out conditions, a more localized analysis was completed in 2014 to evaluate the near-term operational benefits of the 7th Street Grade Separation Project over railroad operation2. The focus of the At-Grade Crossing Analysis examines the 7th Street intersection operation in relation to the Maritime Street railroad crossing south of 7th Street intersection. The At-Grade Crossing Analysis uses a VISSIM model to evaluate the effectiveness of grade separating traffic from railroad crossing. Table 2 summarizes the VISSIM results for the proposed 7th Street Grade Separation Project, western segment improvements. The study scenario assumes that existing 7th Street below the UPRR/OIG Underpasss continues to operate like a 2-lane roadway and that trains continue to use the OIG at-grade crossing at Maritime Street near 7th Street. In comparison to existing condition, the overall intersection delay would be reduced from 100.7 second per vehicle to 75.9 seconds per vehicle. 1 Source: 2012 Oakland Army Base Project Initial Study/Addendum, LSA Associates, Inc., May 2012 Source: Port of Oakland At-Grade Rail Crossing Analysis Technical Memorandum, Parsons Brinckerhoof, June 2014 2 9 Table 2: 7th Street/Maritime Intersection Operational Analysis Results Intersection Turning Movements Existing Condition 7th Street Grade Separation Project Condition (Western Segment Only) Average Delay** Average Delay** Overall 100.7 1701 75.9 1682 NBLT* 120.9 1469 139.9 1330 NBTH* 142.3 1469 126.2 1330 NBRT* 124.5 1469 118.6 1330 SBTH* 185.1 1603 87.9 57 EBRT* 126.2 394 101.7 1651 WBLT* 184.5 1362 144.6 1204 Notes: * Movements that conflict with the railroad crossing **Average Delay is measured in second per vehicle Results shown are the average results of five simulation runs. Reduction in southbound through movement queue length in is due to reduction in volume as a result of the reconfiguration. Max. Queue Length (ft) Max. Queue Length (ft) Source: Port of Oakland At-Grade Rail Crossing Analysis, Parsons Brinckerhoff, June 2014 6. PROJECT SCOPE The Port of Oakland has previously studied several alternatives for the 7th Street Grade Separation Project. Each alternative proposes to reconstruct 7th Street between the I-880/7th Street Interchange and a point west of the Bay Area Rapid Transit District (BART) facility to Middle Harbor Road and West Maritime Street. For all of the alternatives, the eastern half of the project is proposed to be a depressed section, with grade separations (underpasses) for the existing and proposed UPRR tracks. The western half of the project includes alternatives that will be elevated on bridge with an alternative alignment that ties 7th Street directly into Middle Harbor Road and West Maritime Street, connecting at a “T” intersection. Due to the unique geometry of the existing Port facilities, the design of the roadway alignments should be coordinated with the existing constraints, the Port’s master planning and planned improvements. 6.1 Site Constraints Below is a list of existing site constraints that need to be coordinated with design and construction. The proposed project site constraints are shown in Attachment A. BART The existing BART aerial structure runs east and west adjacent to 7th Street before it comes to grade and enters the Transbay Tube (Tunnel) that carries BART trains from Oakland to San Francisco under San Francisco Bay. The columns for this structure are on spread footings and must be protected during project construction activities. The Transbay Tube is located within the westerly area of the Port and access to the tunnel portal from the aerial structure should be maintained. .It will be 10 important to coordinate with BART and the facility will need to be monitored during construction to ensure that it is not affected. Distributing U.S. Customs Office The Distributing U.S. Customs office is designated for U.S. Customs and Border Protection (CBP) and is responsible for maintaining border safety while facilitating the movement of international commerce. Its additional roles include drug interdiction, food and drug examinations with FDA, protection from counterfeit merchandise entering the U.S; protection from unfair/illegal trade, stolen vehicle interdiction, prevention of illegal aliens from entering the U.S. and collection of customs duties and fees. Due to the critical nature of these activities the U.S. Customs office needs to be in operation at all time. The realignment of 7th Street will likely impact the existing U.S. Customs building located at the east corner of existing 7th Street and West Maritime Street intersection. It is anticipated that building relocation will be required prior to construction to avoid service interruption. Radiation Portal Monitors (RPM) The RPM system is located in the east side of West Maritime Street and is operated by Ports of America Seaport at Cargo Terminal Exit Gates 20-24. The system includes three RPMs (scanners), one booth and related equipment which provide early screening of cargo and containers at the port of entry. All containers, loaded or empty, are required to pass through the RPM system as they exit the marine terminal. The RPM is part of the U.S. Department of Homeland Security’s system to monitor the safety and security of the Port. The deployment of the RPM system involves infrastructure construction, equipment installation (including the radiation portal monitor assembly, radiation sensor panel, UPS system, electronic enclosure and IP Surveillance Systems), system testing and calibration. Therefore, disturbance to the existing RPM system must be minimized during construction. Alternately, the RMPs may be relocated as part of the re-configuration project. PG&E Substation The existing PG&E’s Davis and Cuthberston Substation, located at the northwest quadrant of the 7th Street and Maritime Street was built by U.S Department of Navy in the 1980s. The existing 115KV transmission line (POON line) that is feeding to the site was constructed by PG&E in 1992. The POON line runs for nearly three miles over Port property, from PG&E’s Substation C in Oakland to the Davis and Cuthberston Substations. In 2006, PG&E entered an amendment to the agreement among the Port of Oakland, U.S. Navy and East Bay Municipal District (EBMUD) to allow EBMUD to withdraw entirely from power usage, and, to reassign the Navy’s share of the POON line capacity to the City and County of San Francisco Treasure Island Redevelopment Authority (CCSF/TIDA), Schnitzer Steel Industries and PG&E’s retail customers. The second electrical line (12KV) in the Substation was co-owned by PG&E and the Port. The list below indicates the current users of the Substation1: 1 Outer Harbor Maritime Tenants Inner Harbor Maritime Tenants Dredging Operations Harbor Facility Complex, JIT and Maritime Support Center Oakland Army Base Site Schnitzer Steel Industries (Metals Recycling Yard and Port) Utility Technical Memorandum, 7th Street Grade Separation Project, URS, February 2008 11 PG&E’s Retail Customer Future users of the Substation include: OHIT Cold Ironing for Container Vessels Treasure Island (former Naval Station) North Gateway Development The Substation provides primary power supply for the Port and its tenants, as well as the adjacent facilities. The construction of the proposed project should not impact its operation. Site access to the Substation is provided through the driveway at Maritime Street near the 7th Street intersection. It is anticipated that the site access will remain after the Maritime Street is converted to a cul-de-sac near its junction with Navy Roadway/West Maritime Street. Railroad BNSF OIG Rail lines and Crossing It is anticipated that the existing BNSF OIG rail lines and crossing at Maritime Street will remain in full operation until the construction of the proposed OHIT tracks and facilities are completed. Impact to these existing BNSF OIG facilities during the 7th GSP construction shall be minimized. Due to the existing railroad alignment, railroad flagging will be required during construction. Once the proposed OHIT tracks under the 7th Street Overcrossing is in operation, BNSF would use the OHIT facility for their primary rail operation. The existing BNSF OIG tracks at 7th Street/ Maritime Street intersection will remain as secondary tracks for backup use only. Kinder Morgan Jet Fuel Station Kinder Morgan Energy Partners L.O. operates its Jet Fuel Station adjacent to the UPRR/OIG tracks northeast of the 7th Street Underpass. Currently, there are two petroleum pipelines (10 inches and 12 inches) that connect to the high-pressure fuel tank with 20,000-barrel capacity. These pipelines carry a number of different petroleum products to supply the Oakland and San Francisco International Airport. The Fuel Station is currently outside the project construction limits. However, excavation by power equipment near the pipeline presents a potential threat. On-site monitoring during excavation operations is recommended to avoid this threat. UPRR/OIG Railroad Underpass The existing UPRR/OIG is located east of the 7th Street/Maritime Street intersection and is currently outside the project limits of GSP. The proposed 7th Street Grade Separation East Project is a planned longer-term future project that widens 7th Street at the UPRR Underpass. It also allows for the additional of rail spurs and tracks at the UPRR’s Oakland International Container Terminal (OICT) rail yard. The alignment of 7th Street for the elevated structure in the west needs to be compatible with the future planned Railroad Underpass widening in the east. Site Entrances and Exits There are a number of driveways, entrances and exits located within the vicinity of project, including the Ports of America Seaport’s Cargo Terminal Exit Gates 20-24, entrance/exit to Berths 30-32 and 60-63 cargo areas as well as the driveway to the PG&E Substation. Temporary relocation of site access may be required during construction. The construction of the 7th Street overpass may also affect the accesses to the parcels located east and west of Maritime Street, including the access to Ports of America, in which permanent relocation of accesses to these sites would be required. Close coordination with the site tenants shall be made to avoid impacting their operations. 12 6.2 Roadway Improvements The project proposes to realign and reconstruct West Maritime Street and the western portion of 7th Street to an elevated T-intersection and the construction of a new surface rail (tail tracks) underneath 7th Street. The proposed Maritime Street/7th Street Overpass would allow tail tracks to operate between the proposed intermodal rail terminal and the existing OIG without utilizing the existing atgrade crossing on 7th Street. As part of the realignment, the existing Navy Roadway will be demolished and the existing Maritime Street will be dead ended north of 7th Street. To obtain adequate vertical clearance over the tracks, 7th Street between West Maritime Street and Maritime Street will be set at a 5% grade. The portion of 7th Street to the east of the intersection of 7th Street/Maritime Street will remain at-grade following its current alignment. Two lanes of traffic would continue to be provided in each direction while median turn lanes, shoulders and bicycle and pedestrian path would be added. Maritime Street would continue to provide two lanes of traffic in each direction and a center dual-turn lane. A pedestrian and bicycle shared use path would be constructed on the east side of Maritime Street. The multi-use path would continue to the north side of 7th Street. Additionally, the path will continue southerly onto Middle Harbor Road to connect to the Middle Harbor Shoreline Park. Proposed roadway cross sections are included in Attachment B. Middle Harbor Road will be reconfigured and reconstructed to allow the installation of a raised median between Maritime Street and the entrance to Berths 60-63 and the Roundhouse/Sherex property. Several roadway mitigations measures recommended by the environmental documents would also be considered, including the following: Use of a minimum 8-feet wide shoulder on the west side of Maritime Street to accommodate queuing trucks; Provision of sidewalk; Construction of a Class I bicycle path along the entire east side of Maritime Street. To discourage illegal street racing and sideshows, the project will consider various traffic calming measures recommended by the Maritime Street and Middle Harbor Road Traffic Calming Memorandum.1 Recommended traffic calming measures include the use of speed tables and speed cushions to slow down vehicles, and implementation of lane dividers, such as rounded curbs to discourage sideshow activities. These devices will change the roadway characteristic by raising the height of the roadbed slightly - creating a physical barrier that is mountable by trucks while reducing the speed of passenger cars. Existing pavement will be reconstructed within the limits of roadway improvements. 6.4 Bridge and Other Structures An overhead structure spanning the railroad tracks at the west end of the project is planned along 7th Street. The bridge will begin slightly west of Maritime Street and will span the railroad tracks while maintaining a minimum clearance of 23 feet over the tracks. The bridge length and bridge type will be determined during the final design. The bridge length will be investigated in combination with retaining walls for the best overall solution. Feasible bridge types include precast, prestressed concrete girders with a cast-in-place deck (for speed of construction) or cast-in-place prestressed concrete box girders (for cost effectiveness, adaptability to curved alignments, and low depth-to-span 1 Maritime Street and Middle Harbor Road Traffic Calming Memorandum, Kittelson & Associates, Inc., May 2014. 13 ratio). Design of bridge over BNSF railway shall comply with the American Railway Engineering and Maintenance of Way Association (AREMA) and BNSF standards1. In California, BNSF current standard2 requires a minimum of 8’-6” horizontal clearance be maintained from centerline of tracks to highway bridge spanning over tracks. The bridge structure needs to be designed to carry fully-loaded trucks along its entire length in both directions. In the event of a major catastrophe in the Bay Area, the Port of Oakland will become a major hub for providing goods, services, and materials to the Bay Area and beyond. The structures for this main corridor and entryway into the Port should be designed to withstand AREMA impact loading and a major seismic event such that the facility will become operational within a short period of time. 6.5 Bicycles and Pedestrians Improvements (Complete Street) The City of Oakland Bicycle Master Plan (March 2007) designates 7th Street, Maritime Street, and Middle Harbor Road within the project limits as existing or future Class I bicycle facilities. On 7th Street, a 10-foot-wide pedestrian sidewalk will be provided on the north side. No sidewalk will be provided on the south side. On Maritime Street and Middle Harbor Road, a Class I bicycle facility with a separated bicycle path will be provided on the east side. The existing San Francisco Bay Bicycle Trail (Bay Trail) is not yet fully connected in the vicinity of the Port. The pedestrian/bicyclist shared-use path (Class I) proposed by these project will provides a safe and continuous route that is compatible with the existing pedestrian and bicyclists network upstream and downstream of the project. It will also satisfy an outstanding condition in a BCDC permit. This project element provides improved non-motorized access to Middle Harbor Shoreline Park and completes a missing gap in the San Francisco Bay Trail system. 6.6 Traffic Signal and Lighting Installation of traffic signal and signal modification will be coordinated with the findings of the Traffic Analysis. Street lighting will be installed along the proposed 7th Street elevated structure as well as intersections to be modified. To be consistent with the Port Area ITS Development Plan, all traffic signals and traffic control devices within the Port area and on all arterial streets serving the OAB shall include Intelligent Transportation System (ITS) elements, such as traffic signals interconnection, Pan/Tilt/Zoom (PTZ) monitoring cameras, transit/signal/emergency vehicle preemption devices, communication infrastructure equipment, and dynamic message signs capable of connecting to the Port office which may be connected to the Port’s and City’s Traffic Management Center in the future. 7. RIGHT-OF-WAY 7.1 Right-of-Way Need: The OAB redevelopment will take place in 360.5-acres of area owned by the Port of Oakland and City of Oakland. The project site contains truck parking, cargo container storage, maintenance facilities, rail yards, large warehouses, and vacant land. 7th Street and Maritime Street are located in City’s right-of-way dedicated for roadway use. The proposed 7th Street re-alignment would encroach on the existing Distributing U.S. Custom parcel and would impact the existing U.S. Custom building and facilities (wherein building and facilities relocations would be required). The proposed 1 Design Guidelines for Industrial Track Projects, BNSF Railway Company, December 2011 Clearance Requirements By State and Recommended BNSF Clearance, BNSF Standard Plan, Drawing No. 2509, Sheet No.2 2 14 realignment of Maritime Street to the west of existing location between the Ports of America Seaport Cargo Terminal Exit Gates 20-24 and the entrance to Berth 30-32 would encroach into the Port’s cargo container storage areas for Berths 30-32 and Berth 20-26. Permanent right-of-way easement and construction easement from Port of Oakland for public roadway would be required at those locations. It is anticipated that Navy Roadway will be demolished and the existing Maritime Street will be dead ended north of 7th Street. The existing right-of-way for Navy Road may be relinquished after the completion of the project. Right-of-way and easement requirements for all facilities (roadway, utilities, etc.) will be verified and incorporated into the final design. Existing right-of-way will be confirmed and propagated into the final design. 7.1 Railroad: The OIG and UPRR serve freight along their right-of-way within the Port. The OIG is currently operated and maintained by Burlington Northern-Santa Fe (BNSF). The existing railroad tracks are located within the project site. Construction work will be performed adjacent to the railway. Construction staging should be planned in close coordination with the existing railroad operating facility to minimize potential impacts to operations. A railroad clearance letter may be required to certify that impacts to the railroad facility, if any, involved with the project have been addressed in the final design. Any traffic handling or detours beyond the proposed limits of construction should not impair the operation of the railroad facility. Potential update to the existing railroad agreements to include the new tail track connections to existing rail lines is anticipated. 8. UTILITIES Based on a review of available plans provided by various utility owners, an inventory of existing utilities located within the vicinity of the project is shown in Table 4. Table 4: Inventory of Existing Utilities Description Water System Utility Owner Size Location, Direction EBMUD 8” 7th Street, E-W 16” 7th Street, beginning at Maritime intersection, delineating to the west, E-W 8” Between underpass and Maritime Street, Tees off of 16” and delineates to the north, N-S 8” At 7th Street/Maritime Street intersection, Tees off of 16” and delineates to the south, N-S 4” At 7th Street/Maritime Street intersection, Tees off of 16” and delineates to the south, N-S 12” At 7th Street/Maritime Street intersection, Tees off of 8” and delineates to the south, N-S Port of Oakland City of Oakland 15 Description Utility Owner Size Location, Direction 10” On 7th Street: between Maritime Street and Navy Rd, Tees off of 8” and delineates to the south, NS 4” On 7th Street: between Maritime Street and Navy Rd, Tees off of 8” and delineates to the south, NS 2” On 7th Street: between Maritime Street and Navy Rd, Tees off of 8” and delineates to the south, NS 12” Navy Road, N-S 16” On Maritime St. beginning at Navy Rd., delineates to the north, N-S 6” & 8” Partially on Maritime St. beginning at Navy Rd., continues off of roadway, delineates to the north and west. 16” On Maritime Street, Tees off the 16” line coming from 7th Street Beginning from the entrance to the Outer Harbor Terminal and delineating south – N-S 12” On Maritime Street, with a cross off the 16” line coming from Maritime Street south of the entrance to the Outer Harbor Terminal and delineating south, E-W FH Service Gas PG&E Unknown Size Coming from east side of underpass, delineates E-W north of the 7th Street, enters 7th Street pavement west of the fuel tanks, delineates west entering Outer Harbor Terminal area. N-S 3” On Maritime Street, beginning at wye, start point unknown, delineates north on Maritime. N-S On Navy Road, beginning at Tee off of unknown size gas pipe on 7th Street, delineates north on Navy Road and then on Maritime Street N-S 4” Fuel Distribution 6” On Navy Road, beginning at Tee off of unknown gas pipe on 7th Street, delineates north on Navy Road and then on Maritime Street N-S 6” On Maritime Street, beginning at Tee off of unknown size gas pipe at 7th Street, delineates south, located off of the roadway pavement. N-S 8” Stated as abandoned. Loops east side of the fuel tank, crosses 7th Street towards south, angles to the west and enters 7th Street and delineates west entering Outer Harbor Terminal area. N-S 10” Begins at fuel tank, crosses 7th Street to the south, angles to the west, enters Maritime Street roadway pavement and delineates south on Maritime Street Kinder Morgan 16 Description Utility Owner EBMUD Sanitary Sewer System Size 12” Loops east side of the fuel tank, crosses 7th Street towards the south, angles to the west, enters Maritime Street roadway pavement and delineates south on Maritime Street 30” Coming from east side of underpass, enters 7th Street roadway pavement at Maritime intersection, delineates south entering Maritime Street, continues south o Maritime Street E-W & N-S 18“ On 7th Street beginning at Maritime Street from the 30” SS, delineating west towards Navy Road, the SS pipe changes to 30” at Navy Road. 30”/12”? On 7th ST, beginning at Navy Road intersection, from the 18” SS, delineates west on 7th Street, continues west to Outer Harbor Terminal. E-W 10” Beginning at SMH, located midpoint between underpass and Maritime Street, crosses 7th Street towards north. N-S 14” Beginning at SMH, located midpoint between underpass and Maritime Street, crosses 7th Street towards north. N-S 8” Tees off of the 18” SS at 7th Street, located in between Maritime Street and Navy Road, delineates to the south. 4” Tees off of the 18” SS at 7th Street, located in between Maritime Street and Navy Road, delineates to the south. 12” Starts off of the SMH (18” SS) at 7th Street, located in between Maritime Street and Navy Road, delineates to the NW. 54”/5’x5’ box culvert” Coming from east side of underpass, enters 7th Street roadway pavement at Maritime intersection, continues west on 7th Street E-W 36” / 48” On 7th Street, appears to be initiated from east side of underpass, delineates west., appears to change from 48” to 36”, continues west on 7th Street E-W 30” West of the underpass, SD pipe Tees off of the 5’x5’ box culvert, delineates towards north and crosses 7th Street north of the fuel tank. N-S Port of Oakland City of Oakland Port of Oakland Storm Drain System City of Oakland Location, Direction 15” West of the underpass, SD pipe Tees off of the 5’x5’ box culvert, delineates towards north and crosses 7th Street north of the fuel tank. N-S 30” At intersection of Maritime Street/7th Street, Tees off of 48” SD, delineates west on Maritime Street N-S 15” On 7th ST immediately east of Navy Rd., Tees off of 48” SD at 7th Street, crosses 7th Street to 17 Description Utility Owner Size Location, Direction the south. N-W 12” Starting on 7th Street Tees off of 36” SD, delineates north on Navy Road. N-S 18”/12” Starting on 7th Street Tees off of 36” SD, delineates north on Navy Road. N-S 12” Starting on 7th Street west of Navy Road, Tees off of 36” SD, delineates north. N-S 30”/24” On Maritime Street, Starting near the entrance to Outer Harbor Terminal, Tees off of 5’x5’ box culvert, continues south on Maritime Street N-S 8” On Navy Road. N-S 15” On Navy Road. N-S 24” Starting at Maritime/Navy Rd., delineates west. E-W 24” Starting at Maritime/Navy Rd., delineates west. E-W laterals to DI Electrical/Power System PG&E OH Lines On 7th Street, north side of the Street. – E-W OH Lines On 7th Street, south side of the Street starting east of the underpass and then crossing 7th ST> north of the fuel tank. E-W UG 12 KV On 7th Street south side of the street, appear to be located outside of the roadway prism, crosses Maritime Street, then appears to be located on the south side of the roadway within the roadway pavement. _E-W Multiple OH lines On 7th Street, north side of the street in between Maritime Street and Navy Road. E-W OH Lines On Maritime Street north side of the street, N-S UG 12KV On Maritime Street north side of the street, starting from the entrance to Outer Harbor Terminal and delineating towards south. Appear to be outside of the roadway pavement. N-S OH Line West of Navy Road. N-S OH Line Starting from the intersection of Maritime/Navy Road and delineating to the NW towards Outer Harbor Terminal OH Line Starting from the substation, delineating to the north, crossing Maritime ST a wye, then running along the east side of the street on Maritime Street Port of Oakland 18 Utility Conflict It is anticipated that utilities under the footprint of the proposed 7th Street and West Maritime Street overpass will be evaluated for potential conflicts with construction. Utility potholding will be conducted during final design to develop a good understanding of the underground conditions. To avoid service interruption, new utilities would be installed and be fully operational prior for removal of existing whenever possible. 9. PERMITS AND APPROVALS The 2012 IS indentified the potential discretionary regulatory requirements and permits for project approval and construction. Below is a summary of potential permits, consultation, agreements as well as the responsible agencies for project consultation and permits approval: Table 5: List of Potential Regulatory Requirements and Permits Agency Local City of Oakland Port of Oakland Alameda County Transportation Commission (ACTC) Federal U.S. Army Corps of Engineers (ACOE) Federal Railroad Administration Federal Aviation Administration Environmental Protection Agency (EPA) National Maritime Fisheries Service (NMFS) Federal Highway Administration (FHWA) United States Department of Transportation (U.S. DOT) United States Fish and Wildlife Service (FWS) Western Area Power Administration (WAPA) State and Regional Permits, Approvals, Consultation Regulatory Trigger Development Agreement (DA) Planned Unit Development (PUD) Subdivision Map Conditional Use Permit (CUP) Demolition Permits Encroachment Permits Excavation Permits Grading Permits P-Job Permit Other Various Building-Related Permits Possible clarifying General Plan amendment and rezoning Lease Disposition and Development and Franchise Agreement (LDDA) Possible City and Port land exchanges Development Permit for any improvements in the Port Area, as defined in the City Charter Possible City and Port land exchanges Funding and oversight Section 404 Permit (Clean Water Act) for grading and excavation in certain areas of the site Section 404 (Clean Water Act) and Section 10 of the Rivers and Harbors Act of 1899 for berth maintenance dredging at proposed bulk terminal Wetland delineation and possible permits Inspection Notice of Proposed Construction or Alterations (required for cranes or structures that my affect navigable airspace) Oversight Consultation for ACOE permits Funding and oversight Funding and oversight Consultation for ACOE permits Consultation and agreements 19 California Department of Fish and Game (CDFG) SF Bay Conservation and Development Commission (BCDC) State Department of Transportation (Caltrans) California Public Utilities Commission Regional Water Quality Control Board – San Francisco (RWQCB) State Lands Commission (SLC) California Department of Toxic Substances Control (DTSC) Bay Area Air Quality Management District (BAAQMD) East Bay Municipal Utilities District (EBMUD) Pacific Gas and Electric (PGE) American Telegraph and Telephone (AT&T) California Transportation Commission (CTC) California Air Resources Board (ARB) Metropolitan Transportation Commission (MTC) Bay Area Rapid Transit (BART) Bay Area Toll Authority (BATA) Other City and County of San Francisco Union Pacific, BNSF & OTR (private) Review under CEQA pertaining to potential effects to state protected species Consultation on possible state regulatory permits Permit for any activity within BCDC jurisdictional area (normally 100 feet inland from mean high water level or edge of wharf), including dredging Review of Seaport Plan and potential amendments Review BCDC Bay Plan and proposed improvements Review under CEQA pertaining to potential effects to State transportation facilities and obtaining grant funds for infrastructure Rail at-grade crossings Stormwater Pollution Prevention Plan (SWPPP) Municipal Separate Stormwater Program Phase II (MS4) (administered by the RWQCB and EPA) National Pollution Discharge Elimination System Permit (Waste Discharge Requirements – WDR’s) Discharge of treated ground water (if required) Effects to surface water quality from discharge of site run-off General Permit for construction on site of 5 acres or more Authorizations for discharges of fill and dredged material under Clean Water Act Section 401 and the Porter-Cologne Water Quality Control Act Wetland delineation and possible permits Compliance with 2006 Tidelands Trust Exchange Agreement restrictions Possible approval of City-Port Tidelands Trust land exchange Comply and/or modify Remedial Action Plan (RAP) and accompanying Risk Management Plan (RMP), Consent Agreement, FOSET, oversee post-compliance remediation program Demolition permits, stationary source permits Confirmation of 2002 Water Supply Assessment per CEQA Guidelines Consultation/coordination regarding water infrastructure planning Consultation regarding connections to main lines, electric service Agreements, design and approval Oversight and funding Consultation Oversight and funding Permit to enter Construction Permit Consultation and oversight Possible consultation regarding impacts to power lines (from Davis Substation to Treasure Island) Consultations/coordination and possible agreements for relocating and connections to rail lines and new crossings Source: 2012 Oakland Army Base Project IS, LSA Associates, Inc., May 2012. 10. STAKEHOLDER The Port of Oakland has been working in partnership with City of Oakland and others to advance this project. The project will cause temporary and permanent impact to the existing the Port facilities. Traffic circulation and access to parcels near the proposed 7th Street overpass would also be modified. As part of the planning process the Port has been educating their tenants of the potential for interruptions during construction. Formal public outreach is anticipated during subsequent stages to further inform the Port’s tenants, businesses and local communities of the project. The project is in 20 the early planning phase (there was no formal stakeholders’ meetings performed up to the present time). It is anticipated that opportunities for project stakeholders’ involvement will be provided as the project progresses. Key stakeholders for this project include the following organizations: Port of Oakland UPRR BNSF BARTD Oakland Public Works Agency Kinder Morgan Caltrans Alameda County Transportation Commission (ACTC) Federal Highway Administration (FHWA) Utility companies (PG&E [Pacific Gas and Electric Company], EBMUD [East Bay Municipal Utility District], AT&T) City of Oakland Economic Development Agency (formerly OBRA) Environmental Agencies (RWQCB, DTSC) Port tenants and terminal operators Metropolitan Transportation Commission (MTC) West Oakland Community Group 11. DESIGN CODES, REGULATIONS, AND STANDARDS The following subsections documents the design standards and criteria that will be used to develop detailed engineering design for various disciplines. The criteria listed below are guiding principles to achieve consistent work products. One should check for any updates to these standards and criteria as the project progresses. 10.1 Civil The Civil design of the project will consist of geometric design, grading, utilities, pavement design, and signing and striping for local streets and access roads within the Port’s facilities. Civil design shall conform to the standards established by the City of Oakland, and supplemented by the Caltrans’ Highway Design Manual (HDM) and American Association of State Highway and Transportation Officials’ (AASHTO) A Policy on Geometric Design of Highways and Streets (Green Book) based on the following functional classification of streets and design speed: Table 6: Street Functional Classifications and Design Speed Design Functional Classifications Maritime Street Urban Arterial Street 21 Design Speed Posted Speed Limit 35 mph 30 mph 7th Street Urban Arterial Street 35 mph 30 mph Middle Harbor Road Urban Arterial Street 35 mph 30 mph Minimum design speeds conform to Index 101.1 and 101.2 of HDM per functional classifications of the facility listed above. Where the local facility connects to or crosses over or under the railroad corridor, the design standard shall conform to the railroad agency’s standard. If the local agency’s standards exceed the railroad standards, local agency standards shall apply. Geometric Design Geometric design shall conform to the standards provided in the Caltrans Highway Design Manual. The tables below summarize the geometric design criteria: Horizontal Roadway Alignments: Minimum Radius of Horizontal Curve Radius: (Design Speed = 35 mph) 400’ Roadway Profiles: Minimum Stopping Sight Distance: Minimum Length of Crest Vertical Curve (VC): 250 feet (Design Speed = 35 mph) Per HDM Figure 201.4 Minimum length of Sag Vertical Curve (VC): Maximum Superelevation Rate: Per HDM Figure 201.5 4% (urban street less than 35 mph) 6% (urban street between 35-45 mph) 5% Maximum Longitudinal Slope: Roadway cross sections: Traveled Lane: Left- or Right-Turn Lane: Sidewalk: Pedestrian and Bicycle Multi-use Path: 12’ Conform to STAA truck turning template 6’ 10’ Note: Pedestrian and bicycle shared use path shall be separated from traveled lane by a physical barrier. Cross Slopes: Bridge Deck: Approach Roadway: Sidewalk: Multi-use Path: Side Slope: 2% 2% to 4% 2% Max 2% Max and Varies 2:1 Max Horizontal and Vertical Clearances: Horizontal Clearances to Railroad Tracks: (From Center of Track to Face of Bridge Abutment or Pier) Vertical Clearance over Tracks: (From Top of Rail to Bottom of Bridge Structure) Vertical Clearance over Local Streets: Traveled Way 22 18’ 23’-0” 15’ Shoulders Minimum Clearance to Roadside Fixed Objects 14’-6” 4’ (without curb) 1’-6” (with curb) Design Vehicles: Design Vehicle Turning Template: STAA - Standard Truck per HDM Figure 404.5 Driveway: Driveway design shall conform to Standard Details for Public Works Construction, City of Oakland Public Work Bureau of Engineering and Construction Engineering Design Division. Roadway Intersection and Lane Configurations: Design of roadway and intersection shall be based on the intersection lane configurations recommended by the Traffic Analysis prepared for the project. Roadway should be designed to accommodate the design year peak hour traffic volumes to operate at a predetermined LOS. Intersection curb ramp design shall conform to the Standards Details for Street Improvements, City of Oakland Public Work Bureau of Engineering and Construction Engineering Design Division. Roadside Signs and Pavement Delineation The California Manual on Uniform Traffic Control Devices (CA MUTCD) established uniform standards and specifications for traffic control devices in California and shall be used as guideline for design of roadside signs and traffic striping and markings. The CA MUTCD supplemented by the pavement markers, traffic striping and pavement markings details shown in the Caltrans Standard Plans provide the guiding principles for signing and striping design. Sign installation shall conform to Standard Details for Traffic, City of Oakland Public Work Bureau of Engineering and Construction Engineering Design Division. Pavement Design The modified access of the 7th Street GSP will be the Port’s main entry into the marine container terminals. An estimated 40 percent of the Port’s vehicular traffic will pass through this corridor. Constructing this gateway into the Port as a low-maintenance facility will minimize or eliminate facility downtime and minimize traffic impacts. For Annual Average Daily Traffic (AADT) less than 150,000 vehicle per day and Annual Average Daily Truck Traffic less than 15,000 vehicle per day, Caltrans Highway Design Manual recommends the minimum pavement design life for new construction or reconstruction projects be 20 or 40 years. The selection of design life and pavement types (ridge, flexible and composite) is dependent on the characteristics of the roadway, the objective of the project, soil characteristics and the projected traffic volume and loading. Pavement construction and maintenance program shall be determined through a Life-Cycle Cost Analysis (LCCA) when the truck traffic information for pavement engineering (such as projected volume, axle classification, axle configurations, axle loadings) becomes available. Groundwater is encountered at approximately 3 to 4 feet below existing ground surface. Due to the presence of BART structures and foundations, and undesirable ground water and subsurface soil conditions, the subject pavement LCCA shall take into consideration for a pavement sections that minimize existing structure impacts while providing the required pavement stability. 23 10.2 Architectural The architectural design of the proposed 7th Street Overpass, including bridges, retaining walls and abutment walls will be an iterative process. It will be developed through on-going discussion with the project’s stakeholders. The aesthetic design of the proposed 7th Street Overpass will be visually compatible with its surrounding. 10.3 Structures The following general design criteria for the bridges are proposed. Design Codes: Overheads shall be designed in accordance with American Association of State Highway and Transportation Officials – Load and Resistance Factor Design (AASHTO LRFD), Bridge Design Specifications, 2012 6th Edition with California Amendments. The Caltrans Seismic Design Criteria Version 1.7 shall be used and will supersede provisions for seismic design, analysis and detailing of bridges contained in the AASHTO LRFD Bridge Design Specifications. Underpasses shall be designed in accordance with the American Railway Engineering and Maintenance-of-Way Association (AREMA) Manual for Railway Engineering. The UPRR Engineering Standards, Guidelines for Design and Construction of Grade Separation Underpass Structures and the BNSF Guidelines for Design and Construction of Grade Separation Structures shall also be followed. Dead Load: Assumed unfactored unit weight of concrete including reinforcement shall be 150 pounds per cubic foot. For the underpasses, the dead load shall include 30 inches of ballast with tie weight and 200 pounds per foot for track weight. For the overheads, the dead load shall include 35 psf for future wearing surface. Live Loading: For the overheads, HL-93 design vehicular live loading and California P-15 long deck trucks shall be used. For the underpasses, Cooper E-80 with impact shall be used. Seismic Loading: For the overheads, an appropriate Caltrans Seismic Design Criteria Acceleration Response Spectra (ARS) curve (for a specific soil profile, earthquake magnitude and peak rock acceleration) shall be used, augmented with pertinent provisions of Bridge Design Specifications and Caltrans Memos-toDesigners. For the underpasses, the AREMA three-level earthquake shall be used. 10.4 Utilities Utility protection, relocation and installation shall be in conformance with the latest technical specifications and practices of the City of Oakland and the respective utility owners. Section 8 – Utilities of this Memorandum describes the existing utilities located within the vicinity of the project area. 10.5 Drainage The City of Oakland’s Storm Drainage Guidelines provide the procedures and practices for hydrology and hydraulic design of drainage facilities. The guidelines were developed based on the Hydrology and Hydraulics Manual published by the Alameda County Flood Control and Water Conversation District and shall be used for the design of the drainage facilities for the project. The Drainage Standard Details established by the City of Oakland Public Work Bureau of Engineering and 24 Construction Engineering Design Division provide the standard drainage inlet, manhole and structures that can be applied for the project. Base on the Federal Emergency Management Agency’s (FEMA) Flood Insurance Rate Map (FIRM), the project site is located in Zone X – areas determined to be outside of 0.2% annual chance (or 500 year) floodplain and Zone D – areas in which flood hazards are undermined, but possible. For drainage areas outside of the FEMA 100-year flood plan, the City of Oakland Storm Drainage Design Guidelines (July 2006) specifies that the design storm frequencies shall be 10-year for secondary facilities1 and 25-year for primary facilities2. The design tailwater elevation for secondary and primary facilities shall be the water surface elevation of the receiving waterway. For additional drainage added to the railroad right-of-way, a hydrology study using the 50-year and 100-year water surface elevations for both the existing and proposed conditions is required for railroad owned or maintained track. 10.6 Traffic Control and Lighting The proposed 10% design work will not include new traffic signal design and traffic signal modification in the vicinity of the project. Any proposed traffic signal design will comply with the latest version of the California Manual on Uniform Traffic Control Devices (California MUTCD), the Caltrans Standard Plans, and the City of Oakland design standards. The traffic signal design will accommodate truck, passenger car, bicycle and pedestrian movements. Any signal timing and phasing changes will be coordinated with the Port of Oakland and the City of Oakland. Below is list of locations that will need traffic signal design. Other locations may be included as needed in the design process. 7th Street and Maritime Street (traffic signal modification) 7th Street and Maritime Street Grade Separation (new traffic signal) Roadway lighting will be designed to Street Light Standard Details per City of Oakland Public Work Bureau of Engineering and Construction Engineering Design Division, Caltrans Standard Plans and will conform to Illuminating Engineering Society (IES) standards. 12. FUNDING The projects will be funded in the following manner: Table 7: Project Costs Project 7th Street Grade Separation Total Project Costs (in Million)* 176 1 Secondary facilities are drainage-facilities or waterways with tributaries areas less than 50 acres. This include majority of the City’s drainage conduits. (Source: City of Oakland Storm Drainage Design Guidelines, July 2006) 2 Primary facilities are waterways and drainage facilities with tributary areas between 50 acres and 25 square miles. These facilities mostly consist of creeks and larger improved waterways and drainage facilities. Many of these facilities are owned and maintained by the Alameda County Flood Control District. (Source: City of Oakland Storm Drainage Design Guidelines, July 2006) 25 * Cost is escalated to 2019 dollars 13. SCHEDULE Table 2: Project Schedule for Major Milestones Scheduled Delivery Date Project Milestones Preliminary Engineering/Environmental Final Design (PS&E) Right-of-Way Construction 01/15 – 09/15 10/15 –09/16 10/15 – 09/16 10/16 –09/19 14. PROJECT PERSONNEL Alameda County Transportation Commission Chwen Siripocanont, PE, TE, Program Manager PTOE Port of Oakland Imee Osantowski, PE Thanh Vuong, PE Principal Maritime Engineer Port Supervising Engineer Consultant Team Francis Lo, PE BayPac Consulting, Project Oversight Thomas A. Ward, PE/SE, D.PE Parsons Brinckerhoff, Project Manager Brady Nadell, PE Parsons Brinckerhoff, Deputy Project Manager 26 (408) 796-3171 (510) 627-1479 (510) 627-1266 (510) 517-3680 (510) 285-3372 (510) 541-7767 ATTACHMENT A Port of Oakland MAPSS – Project Site Constraints A PORT OF OAKLAND MAPSSPROJECT SITE CONSTRAINTS M AR IT IM ES TR EE T PORTS AMERICA OUTER HARBOR CONTAINER TERMINAL ES 9 SF D AN LIN BN NA VY RO AD W AY UP R L AI 2 1 10 6 3 4 7TH ST 7 REET 880 8 5 JOINT INTERNATIONAL RAIL TERMINAL JIT OAD MIDDLE HAR B OR R N SITE CONSTRAINTS LEGEND 1 Existing BNSF OIG Rail lines 6 Future Lift Station Area of High Sensitivity (Do Not Disturb) 2 BART Portal and Tunnel 7 Kinder Morgan Jet Fuel Station Area of Medium Sensitivity (Try Hard Not to Disturb) 3 Disturbing U.S. Custom 8 Existing UPRR/OIG Railroad Underpass Area of Medium to Low Sensitivity (Prefer Not to Disturb) 4 PG&E Substation (Davis and Cuthberston) 9 Radiation Portal Monitor (RPM) Area of Low Sensitivity (O.K. to Disturb) 5 Existing BNSF OIG Rail Crossing 10 BART Aerial Structure DRAFT 03-05-2015 ATTACHMENT B Roadway Typical Cross Sections B 7th St TYPICAL CROSS SECTIONS SCALE: NTS X-4 7th St 7th St TYPICAL CROSS SECTIONS SCALE: NTS X-3 MARITIME ST NB ON RAMP MARITIME EXISTING TYPICAL CROSS SECTIONS SCALE: NTS X-1 MARITIME EXISTING MARITIME ST TYPICAL CROSS SECTIONS SCALE: NTS X-2
© Copyright 2026 Paperzz