PROJECT CANADA CASE STUDY 2 PROJECT CANADA - CASE STUDY Introduction Early September 2015 XYZ Inc. (Company name has been changed for privacy) invited 4 or 5 project forwarders to participate in a Tender for the delivery of the project cargo items, from terminal Shanghai China to delivered quayside Port Belledune QC Canada. The marshalling yard located there was to receive the dismantled components and to reassemble them with other components shipped and delivered separately. Once assembled the consignee was responsible for arranging the delivery of the complete built up unit to Port Cartier project site. The delivery was to be done using a barge contracted separately from the ocean part charter handled by Icecorp. XYZ Inc advised all Bidders that the final award would be based on the price of the part charter proposed and transit time/routing due to time constraints involved for final assembly and door project site delivery. A specific discharge date to Port Belledune was requested as being NO LATER than November 12, 2015 or a closer date. The original Packing List for the cargo items was not fully finalized as the fabricators in China were still producing the finished articles and final weights and dimensions were not fully determined at the time of tender submission. Overview CARGO DETAILS: 1. 1 unit gantry 103,103 18.00 x 12.00 x 4.01 866.16 2. 1 unit slew bed 68,970 13.40 x 9.80 x 4.90 643.47 3. 1 unit C Frame 76,448 15.50 x 7.79 x9.55 1,153.12 4. 1 unit 24 wheel beam 33,300 13.22 x1.70 x 2.50 56.19 5. 1 unit 10 wheel beam 10,500 8.36 x2.09 x 2.35 12.80* 6. 1 unit 10 wheel beam 10,500 8.36 x2.09 x 2.35 12.80 3 PROJECT CANADA - CASE STUDY * #5 is optional, may or may not be shipped as break-bulk cargo with remaining 5x pieces. This was only 10.50 MTs and 12.80 cbm did not affect the part charter option rates wise whether included or excluded TOTAL 6x PIECES WEIGHT 302,821 kg/ 2,744.54 Cubic meters and subject to change TENDER INFORMATION: The Tender issued to all bidders required: • Coordination with two fabricators near Shanghai to arrange for the cargo to be delivered alongside vessel under hook Shanghai port (unnamed terminal). *All charges prepaid • Receive the cargo from barge, loaded to the nominated charter vessel, fully positioned on deck, blocked and braced. • Delivery by part charter to ocean terminal Port of Belledune before November 12 2015. • Arrange unloading from vessel discharged to road trailers positioned alongside the vessel for the Canadian fabricator to take possession and arrange delivery to their nominated marshalling area nearby. HOW THE BID WAS WON: ICECORP was aware that to win the bid it was necessary to source numerous ocean carrier options with vessels small enough to ensure reasonable pricing but with sufficient on board ship’s gear to handle the heavy lift cargo items involved. • Source vessel owners who had other cargo commitments to ensure a reasonable part charter pricing was achieved for this cargo (an element of luck and timing plays a large part in this regard). • Select a vessel who had experience in discharging this type of cargo in Canadian ports in the region and would be able to price accordingly • Select a vessel with reasonably fast transit times so the delivery deadline can be met 4 PROJECT CANADA - CASE STUDY To ensure a big selection of ocean carriers were approached for pricing and offer, ICECORP decided to work closely with their agency PPG office overseas as ICECORP is the solely appointed PPG Member for Canada. ICECORP found two suitable options but the price differential was quite high between the two. In the end the carrier nominated was Thorco Shipping, with offices in Singapore and Houston TX and the final rate was negotiated. Tentative rates were agreed and conditions of Bill of Lading discussed, subject to changes being agreed should ICECORP win the Tender and firm booking was to be considered. The rates received from six charter operators ranged from US$ 850,000 to US$ 1,300,000 for the cargo in question and the Tender was submitted on time. Towards mid/late September 2015, ICECORP was advised that our Bid was successful and XYZ Inc had awarded them the business. Once confirmed in writing ICECORP proceeded to make firmer arrangements with all parties involved to confirm loading date of the cargo in Shanghai port. Wording of the Part Charter agreement and initial Booking Note was carefully constructed and prepared by ICECORP ensured all legal Issues were covered and clearly defined. At this stage the final cargo piece count, weight and dimensions were still under review, waiting to be loaded on the barge. 5 PROJECT CANADA - CASE STUDY CRITICAL SUCCESS FACTORS: Key elements and communications required for set up of firm booking and loading included: • Final cargo piece count, weights and dimensions and compiling a final Packing List for vessel owner to determine vessel load plan and lashings on board • Establishing barge size and dimensions, what protection existed on the barge port and starboard sides whilst unloading occurred alongside the charter vessel to avoid damages/claims etc. • If the barge is self-propelled or being towed by a tug (it was self-propelled) • Identifying loading plan/cargo pattern on board the barge. The fabricators provided ICECORP with a barge loan plan for charter vessel to review for their loading to vessel purposes and approved the positioning of each cargo item on the barge itself. Two cranes operating in tandem together were required and turning circle once placed on board had to be calculated to allow for cranes to operate unhindered. And to place specific cargo pieces in preselected places on charter vessel deck. • To meet our delivery deadline date it was negotiated with the shipping line to have this project cargo loaded in Shanghai last and to be discharged in Port Belledune first. Where the cargo was placed on deck during the loading proceed was extremely important to ensure quick access for offloading at destination. • Until Thorco Shipping was able to arrange loading of the steel in Japan and confirm anticipated date of arrival in Shanghai port we had to ensure daily communications existed with both fabricators. This was done to determine the last date of loading the cargo to their nominated barge, thus allowing two days transit time for arrival Shanghai terminal and ensure that the barge arrived at loading terminal around the same day that the vessel was available to receive the cargo. A delay in loading of the vessel incurs vessel demurrage charges in excess of US$ 15,000 per day or pro rata. 6 PROJECT CANADA - CASE STUDY CONCLUSION: Final vessel name was determined as being the Thorco Empire and technical details of this vessel were conveyed to ICECORP/XYZ Inc. XYZ Inc provided ICECORP with confidential CAD Drawings of the relevant cargo items which the charter vessel owner used to determine best lifting and positioning methods ex barge onto their vessel. The C Frame was able to be loaded upside down provided none of the frame lugs were touching the vessel deck, thus providing the vessel operators more space to work with on deck. Third Party Liability Insurance for charter vessel coverage was provided by The Japan P&L (Protection & Liability) Club, in case the barge/stevedores damaged the vessel during the barge offloading process. XYZ Inc Canada requested permission for a Marine Surveyor appointed by them to board the vessel and inspect both the cargo as offloaded from the barge, their on deck positioning and final blocking and bracing done for the vessel voyage. XYZ Inc paid for the Surveyor and detailed report/photos were compiled for XYZ. It was extremely important that the Marine Surveyor did not delay or disrupt the loading process and cargo positioning on deck. (No delays were experience) 7 PROJECT CANADA - CASE STUDY The vessel from barge loading date was agreed as being October 3 or 4, 2015 allowing the Thorco Empire 1.5 day’s transit from loading the steel in Nagoya Japan, departing Nagoya 1st October and to arrival Shanghai port. ICECORP organized all the export documentation and authorities with the Port of Shanghai/China Customs before the loaded vessel was authorized to commence export sailing to destination. Loading of this project cargo was anticipated to take one day allowing for minor delays, weather etc. Departure date from Shanghai was set to be October 4, 2015. Based on a vessel calculated speed of 13.5 knots and allowing for a 5% loss of timing, bad weather and storms en route the transit time to Belledune was calculated as being 36 to 37 days without any guarantee implied or given. Thus arrival at Belledune was estimated to be November 9 or 10, 2015 within the time frame requested by XYZ Inc (12 November.) Two days transit through the Panama Canal was added to allow for heavy vessel activity, bad weather. Regular daily vessel monitoring and tracking by GPS Satellite was maintained and position status updated for XYZ Inc, as they were nervous about the final arrival date to Belledune. Updated position maps were emailed to XYZ Inc as and when received/updated. Vessel anticipated arrival date at Belledune was 14 -15 November 2015 weather/circumstances permitting. Before the actual voyage commencement, advance vessel and cargo reporting had to be made to the Canadian Authorities via the vessel owner's Canadian representative based in Montreal, Quebec. The MV Thorco Empire arrived at Port Belledune on November 24, 2015 around 20.00 hours and the discharge time frame was expected to be between 13 and 16 hours. The XYZ Inc cargo was the first to be discharged. Arcelor Mittal's regular Canadian customs broker ensured the cargo was fully customs cleared and most importantly the cargo itself was customs released before the vessel was in Port Belledune and made ready for discharge. XYZ Inc requested permission for their Canadian appointed Marine Surveyor to board the vessel in Belledune prior to delashing and offloading of the cargo to ensure everything was found to be in good condition and order. One Source. One Solution
© Copyright 2025 Paperzz