ministry of trade and industry

DRAFT
REPUBLIC OF GHANA
PROGRAM BASED BUDGET (PBB)
PILOT
FOR 2012-2014
MINISTRY OF TRADE AND INDUSTRY
TABLE OF CONTENTS
PART A: STRATEGIC OVERVIEW OF THE MINISTRY OF TRADE AND INDUSTRY
(MOTI) ................................................................................................................................................... 3
1.
GSGDA Policy Objectives........................................................................................................................... 3
2.
MDA Goal .................................................................................................................................................. 3
3.
MDA Core Functions ................................................................................................................................. 4
4.
MDA Strategic Policy Objectives ............................................................................................................... 5
5.
Policy Outcome Indicators and Targets .................................................................................................... 6
6.
MDA Summary – Expenditure Estimates by Budget Program, Economic Classification and Projects ..... 8
PART B: BUDGET PROGRAM SUMMARY ................................................................................ 10
PROGRAM 1: Management and Administration................................................................................................ 10
PROGRAM 2: Trade Development ...................................................................................................................... 28
PROGRAM 3: Business Development and Promotion ........................................................................................ 43
PROGRAM 4: Trade and Industry Promotion ..................................................................................................... 71
PROGRAM 5: Standardization and Conformity Assessment............................................................................... 82
PROGRAM 6: Industrial Development .............................................................................................................. 100
PART C: FINANCIAL INFORMATION ...................................................................................... 112
Annexure 1: Summary of Expenditure by Program, Economic Classification and Funding Source.................. 112
Annexure 2: Expenditure by Program and Sub Program .................................................................................. 113
Annexure 3: Expenditure by Program and Project ........................................................................................... 114
Annexure 4: Expenditure by Funding and Program .......................................................................................... 117
Annexure 5: Expenditure by Program/Sub-Program and Economic Classification .......................................... 118
Ministry of Trade and Industry
September 2012
Page 2
PART A: STRATEGIC OVERVIEW OF THE MINISTRY OF
TRADE AND INDUSTRY (MOTI)
1. GSGDA Policy Objectives
The GSGDA contains ten (10) Policy Objectives that are relevant to the
Ministry of Trade and Industry
These are as follows:










Improve private sector competitiveness domestically and globally
Attract private capital from both domestic and international sources
Pursue and expand market access
Make private sector work for Ghana, share the benefits of growth and transformation strategy
Ensure the health, safety and economic interest of consumers
Expand opportunities for job creation
Promote an enabling environment and effective regulatory framework for corporate
management
Improve efficiency and competitiveness of MSMEs
Ensure rapid industrialisation driven by strong linkages to agriculture and other natural
resource endowments
Develop and strengthen Ghana’s Creative economy in ways that would enable the nation to
actively engage in the world trade in Creative goods and services
2. MDA Goal
To establish Ghana as a major manufacturing, value added, financial and commercial hub in West
Africa
Ministry of Trade and Industry
September 2012
Page 3
3. MDA Core Functions
The core functions of the MOTI are to:











Formulate and harmonize policies that will ensure inter-sectoral collaboration in the
implementation of trade and industrial policies both at national and global levels.
Improve entrepreneurial skills, technological capability and accessibility to credit and
markets.
Develop programs and activities for institutional capacity building to meet the challenges of
the global market
Develop standards and quality systems to meet production requirements for local and
international markets
Facilitate the development and promotion of non-traditional export products.
Facilitate the development of the production base and expansion of cross-border trade
Collect, collate process, store and disseminate timely and accurate information for
stakeholders.
Facilitate the removal of institutional and legal bottlenecks
Facilitate private sector access to capital
Ensure that private sector development programs are complimentary and cover broad range of
needs.
Encourage and facilitate the provision of public service to the private sector.
Ministry of Trade and Industry
September 2012
Page 4
4. MDA Strategic Policy Objectives
The MDA has adopted the following strategic policy objectives to guide its
efforts to fulfill the national policy objectives:













Diversify and increase export base
Accelerate economic integration with other regional and/or sub-regional states
Ensure increased access of industries to reliable and adequate energy supply
Promote the application of science, technology and innovation in industry
Increase competiveness and enhanced integration into domestic and international markets
Ensure the creation of enabling environment to enhance industrial growth and provide the
momentum to achieve global competiveness
Improve Ghana’s position in global and regional markets
Enhance Government capacity for private sector policy formulation, implementation, and
monitoring and evaluation.
Ensure the health, safety and economic interest of consumers
Strengthen firms competency and capacity to operate effectively and efficiently
Develop and strengthen Ghana’s creative industry to actively participate in international
trade.
Accelerate development of strategic sectors
Enhance women’s access to economic resources.
Ministry of Trade and Industry
September 2012
Page 5
5. Policy Outcome Indicators and Targets
Baseline
Outcome Indicator
Description
Industrial Sector
Performance:
Manufacturing value
added share in GDP
Share of
manufacturing in
total export
Private Fixed
Investment (as %
gross domestic fixed
investment)
Unit of
Measurement
The indicators
measure the
contribution of
the
manufacturing
sector in total
production
Manufacturing
value added
share in GDP is
obtained by
dividing the
value added in
manufacturing
by the total
gross valueadded to GDP
at basic or
producers'
prices
expressed as a
percentage.
Share of
manufacturing
in total exports
is the
proportion of
manufacturing
in total exports
expressed as a
percentage
The ratio of
Gross Private
Domestic
Investment to
Gross
Domestic Fixed
Investment,
expressed in
percentage
Ministry of Trade and Industry
Latest status
Target
Year
Value
Year
Value
Year
Value
2009
7.9%
2011
6%
2014
20%
2009
32.4%
2011
33%
2014
40%
2009
25%
2011
88%
2014
45%
September 2012
Page 6
Domestic credit to the
Private Sector as ratio
of GDP
The value of
domestic credit
to the private
sector as a
share of GDP
Percentage change in
Non-Traditional
Exports, (Value in
Million US$)
The change in
value of nontraditional
exports (NTE)
expressed as
percentage of
the previous
year’s value
Total Merchandise
Export
The value of all
the goods and
services
including
Cocoa, Timber
and Gold
Ministry of Trade and Industry
2009
2009
2009
26.10%
$1,215
million
(9.5%)
US$5,839.70
million
2011
2011
2011
September 2012
15.2%
$ 2,423
million
(20.58%)
$13,000
million
2014
30%
2014
$5,000
million
2014
$25000
million
Page 7
6. MDA Summary – Expenditure Estimates by Budget Program, Economic
Classification and Projects
2010
Expenditure By Budget Program
Actual
2011
Budget
Est.
Outturn
BP1: Management and
Administration
BP2: Trade Development
BP3: Business Development and
Promotion
BP4: Trade and Industry Promotion
BP5: Standardisation and
Conformity Assessment
BP6: Industrial Development
Total Expenditure
2010
Expenditure by Economic
Classification
Actual
2011
Budget
Est.
Outturn
Current Expenditure
21 Compensation of Employees
22 Use of Goods and Services
25 Subsidies
26 Grants
27 Social Benefits
28 Other Expenses
Capital Expenditure
31 Non-Financial Assets
Total Expenditure
Expenditure by Program and
Projects
2010
Actual
BP1: Management and
Administration
BP2: Trade Development
BP3: Business Development and
Promotion
BP4: Trade and Industry
Promotion
Ministry of Trade and Industry
2011
Budget
Est.
Outturn
2012
2013
2014
Budget
Indicative
Indicative
GH₵
GH₵
GH₵
12,980,642
26,990,531
12,973,719
26,990,531
13,009,448
27,260,436
14,590,390
600,000
14,168,540
600,000
14,310,226
606,000
17,421,652
84,937,244
157,520,459
2012
17,421,102
84,937,244
157,091,136
2013
17,595,868
85,786,616
158,568,594
2014
Budget
Indicative
Indicative
GH₵
GH₵
GH₵
9,307,756
61,864,823
230,500
388,192
9,400,833
61,342,423
230,500
388,192
9,400,833
61,956,404
232,805
392,074
85,729,188
85,729,188
86,586,480
157,520,459
2012
157,091,136
2013
158,568,594
2014
Budget
Indicative
Indicative
GH₵
GH₵
GH₵
1,210,000
122,000
1,210,000
122,000
1,222,100
123,220
11,557,254
11,557,254
11,672,827
90,000
90,000
90,900
September 2012
Page 8
BP5: Standardization and
Conformity Assessment
BP6: Industrial Development
Total Expenditure
Ministry of Trade and Industry
11,748,690
61,001,244
85,729,188
September 2012
11,748,690
61,001,244
85,729,188
11,866,177
61,611,256
86,586,480
Page 9
PART B: BUDGET PROGRAM SUMMARY
PROGRAM 1: Management and Administration
1. Budget Program Objectives



To conduct the overall management, policy formulation and provide appropriate
administrative support services
To facilitate the recruitment, placement and training of employees
To ensure efficient records management system and free flow of information
2. Budget Program Description
The Management and Administration program provides efficient and effective administrative
and logistical support; procurement services; financial administration and skilled personnel for
the formulation and implementation of programs and projects of the Ministry.
The program collates data to undertake research and analysis for the formulation of policies and
to guide its implementation, monitoring and evaluation.
Ministry of Trade and Industry
September 2012
Page 10
3. Budget Program Summary : Expenditure by Sub-Program, Economic
Classification and Projects
Program 1: Management and Administration
2010
Expenditure By Budget SubProgram
Actual
2011
Budget
Est.
Outturn
BSP1: Finance and Administration
(Legal)
BSP2: Human Resource
Management
BSP3: Policy planning Monitoring
and Evaluation
BSP4: Statistics, Research and
Communication
Total Expenditure
Expenditure by Economic
Classification
2010
Actual
2011
Budget
Est.
Outturn
2012
2013
2014
Budget
Indicative
Indicative
GH₵
GH₵
GH₵
2,562,000
2,562,000
2,587,620
190,000
190,000
191,900
490,886
390,886
394,795
430,000
430,000
434,300
3,672,886
2012
Budget
3,572,886
2013
Indicative
3,608,615
2014
Indicative
GH₵
GH₵
GH₵
Current Expenditure
21 Compensation of Employees
22 Use of Goods and Services
25 Subsidies
26 Grants
27 Social Benefits
28 Other Expenses
Capital Expenditure
31 Non-Financial Assets
Total Expenditure
Expenditure by Projects
2010
Actual
2011
Budget
Est.
Outturn
9,307,756
2,462,886
-
9,400,833
2,362,886
-
9,400,833
2,386,515
-
1,210,000
12,980,642
2012
Budget
1,210,000
12,973,719
2013
Indicative
1,222,100
13,009,448
2014
Indicative
GH₵
GH₵
GH₵
Purchase Bus for Staff to improve
productivity
Manage the Ministry's properties
Renovate Office building and
Kumasi Guest House
Purchase of Vehicle for Financial
review
Rehabilitation of Office building
Total Expenditure
Ministry of Trade and Industry
September 2012
230,000
700,000
230,000
700,000
232,300
707,000
100,000
100,000
101,000
150,000
30,000
1,210,000
150,000
30,000
1,210,000
151,500
30,300
1,222,100
Page 11
Ministry of Trade and Industry
September 2012
Page 12
BUDGET SUB-PROGRAM SUMMARY
PROGRAM 1: Management and Administration
SUB-PROGRAM SP1.1: Finance and Administration
1. Budget Sub-Program Objective
To provide efficient and effective administrative, logistics and procurement services; financial
administration support for the programs of the Ministry
2. Budget Sub-Program Description
The key operations for this sub-program are to:












Manage and respond to all incoming mail and Cabinet decisions
Assist the Minister and Deputy Ministers in the implementation of all Cabinet directives and
policy decisions
Ensure timely routing of all correspondence to addresses
Collaborate with all other MDAs and MMDAs on administrative matters
Deliver services to all Divisions; Hold management team meetings;
Ensure that the physical plant, equipment and sundry related items are in good condition
(including vehicles)
Facilitate the timely sale of vehicles no longer required for use;
Provide services for the receipt, record, distribution and storage of written communications
coming and leaving the Ministry
Provide accounting services for expenditure allocated to the Ministry
Control and monitor the administration of the Ministry’s budget to ensure compliance with
the Financial Administration Act and Financial Administration Regulation, the Appropriation
Act and the Stores Rules
Safeguard government assets, review the financial and operational controls and conduct
board of survey activities
Establish proper Audit procedures and practices to ensure that Internal Audit provides a
service which is adequate and effective and which is suitably quality assured
Ministry of Trade and Industry
September 2012
Page 13
3. Budget Sub-Program Results Statement
The following output indicators are the means by which the Ministry measures the performance
of this sub-program. The table indicates the main outputs and an indicator for each. Where past
data has been collected this is presented. The projections are the Ministry’s estimate of future
performance.
Main Outputs
Preparation and
presentation of
financial reports
Procurement of
vehicles and
equipment
2009
Past
2010
2011
Budget
2012
Quarterly Financial
Reports submitted
by
15th day of
the next
month
15th day of
the next
month
15th days
of the next
month
15th day of
the next
month
Annual Financial
Reports Submitted
by
10th
February,
2010
22nd
March,
2011
2nd March,
2012
31st March
3
6
6
4
14
10
20
20
100
20
150
50
Output Indicator
Number of vehicles
procured
Number of
equipment
procured
Ministry of Trade and Industry
September 2012
Projections
2013
2014
15th day
of the
next
month
15th day
of the
next
month
31st March 31st March
Page 14
4. Budget Sub-Program Operations and Projects
The table lists the main Operations and Projects to be undertaken by the subprogram.
Operations
Projects (Investment)
Organize Policy Review meeting for MOTI and its
Agencies
Procure office equipment and supplies for the
Ministry
Prepare and present an audited accounts of the Ministry
to ARIC
Renovate office building and Kumasi Guest House
Pay utility bills (Pay electricity cost)
Purchase Bus for Staff to improve productivity
Prepare and present quarter audited accounts reports of
the Ministry
Prepare Budget execution report and communicate to
all spending units the information sought and the
format for their preparation
Conduct workshops and provide assistance to Agencies
on submission of budget estimates
Review financial information of each spending entity
Produce a consolidated quarterly report comparing
budget execution and revenue collection to the
estimates contained in the National Budget
Manage the Ministry's properties
Design and implement Communication Strategy
Develop and publish information and promotional
materials
Assess Counterpart funds for projects in the Ministry
by Dec., 2012.
Assess and Utilize Pooled Funds for Sekondi Industrial
Park
Facilitate the setting of clear target and dedicated
lending windows within government financed credit
facilities opened for women in industrial activities
Ministry of Trade and Industry
September 2012
Page 15
5. Budget Sub-Program Summary: Expenditure by Economic Classification
2010
Expenditure by Economic
Classification
Actual
2011
Budget
Est.
Outturn
Current Expenditure
21 Compensation of Employees
22 Use of Goods and Services
25 Subsidies
26 Grants
27 Social Benefits
28 Other Expenses
Capital Expenditure
31 Non-Financial Assets
Total Expenditure
Ministry of Trade and Industry
September 2012
2012
2013
2014
Budget
Indicative
Indicative
GH₵
GH₵
GH₵
1,352,000
-
1,352,000
-
1,365,520
-
1,210,000
2,562,000
1,210,000
2,562,000
1,222,100
2,587,620
Page 16
BUDGET SUB-PROGRAM SUMMARY
PROGRAM 1: Management and Administration
SUB-PROGRAM SP 1.2: Human Resource Management
1. Budget Sub-Program Objective
To ensure the effective and efficient operations of the Ministry through organizational
development and strategic manpower planning
2. Budget Sub-Program Description
The Human Resource Management sub-program focuses on the recruitment and retention,
performance management, training and development and welfare of staff.
The key operations are to:




Supervise the personnel functions
Process appointments, promotions and applications for transfers, leaves and the like
Match staff with budgeted post and salary scale
Liaise with the Public Service Commission, the department of Human Resources and other
Divisions on personnel matters
 Co-ordinate the Performance Appraisal process
 Coordinate training for employees in collaboration with the Department of Human Resources
and advice heads of divisions on available training courses
Ministry of Trade and Industry
September 2012
Page 17
3. Budget Sub-Program Results Statement
The following output indicators are the means by which the Ministry measures the performance
of this sub-program. The table indicates the main outputs and an indicator for each. Where past
data has been collected this is presented. The projections are the Ministry’s estimate of future
performance.
Main Outputs
Output
Indicator
Recruitment of
staff
Number of
Staff recruited
Staff training
and
development
Number of
staff trained
Ministry of Trade and Industry
Past
Budget
Projections
2009
2010
2011
2012
2013
2014
-
-
50
49
70
100
105
78
121
92
167
200
September 2012
Page 18
4. Budget Sub-Program Operations and Projects
The table lists the main Operations and Projects to be undertaken by the subprogram.
Operations
Projects (Investment)
Develop a new organogram for the Ministry of Trade
and Industry
No projects
Restructure MOTI
Train staff of MOTI
Develop incentive scheme for MOTI
Develop short and long range manpower requirement
of the Ministry
Train staff in project monitoring and evaluation
Upgrade IT and statistical skills of RIS staff
Train RIS, DT & T, PPME Divisions on how to
capture and analyze prices of specified commodities
Develop MIS training modules and run training
program
Ministry of Trade and Industry
September 2012
Page 19
5. Budget Sub-Program Summary: Expenditure by Economic Classification
2010
Expenditure by Economic
Classification
Actual
2011
Budget
Est.
Outturn
Current Expenditure
21 Compensation of Employees
22 Use of Goods and Services
25 Subsidies
26 Grants
27 Social Benefits
28 Other Expenses
Capital Expenditure
31 Non-Financial Assets
Total Expenditure
Ministry of Trade and Industry
September 2012
2012
2013
2014
Budget
Indicative
Indicative
GH₵
GH₵
GH₵
190,000
-
190,000
-
191,900
--
190,000
190,000
191,900
Page 20
BUDGET SUB-PROGRAM SUMMARY
PROGRAM 1: Management and Administration
SUB-PROGRAM SP 1.3: Policy, Planning, Budgeting, Monitoring and
Evaluation
1. Budget Sub-Program Objectives




Formulate, review and harmonize trade and industrial policies and programs to ensure intersectoral collaboration in implementation.
Ensure the development of well-coordinated and budgeted annual work programs for the
sector.
Develop effective monitoring and evaluation system to measure achievements of policy and
program objectives against set targets.
Track the implementation of policies, programs and projects in the sector
 Ensure the preparation of the sector budget
2. Budget Sub-Program Description
The sub-program develops, reviews, monitors and evaluates the implementation of all the sector
policies, strategies and programs to ascertain their impact on high level goals and outcomes that
the Government expects to achieve.
The key operations are to:






Review the Ministry’s programs for efficiency and effectiveness
Identify policies and legislations that impact negatively on the private sector and the business
environment, and develop policies to rectify them through amendments and improvements
Look at a range of performances of major exports to assess their impact on the growth in
foreign currency receipts
Assess and identify bottlenecks to increasing exports, their nature and what the Ministry can
do to remove or lessen their impact through policy or working with other institutions
Coordinate and harmonize all sector annual work programs and budgets
Progress in implementation is reported quarterly and annually and disseminated through
various means.
The operations are carried out by the Policy Planning, Sector Wide Budget, Private Sector
Development and Monitoring and Evaluation Units under the Policy Planning, Monitoring and
Evaluation Directorate.
Ministry of Trade and Industry
September 2012
Page 21
3. Budget Sub-Program Results Statement
The following output indicators are the means by which the Ministry measures the performance
of this sub-program. The table indicates the main outputs and an indicator for each. Where past
data has been collected this is presented. The projections are the Ministry’s estimate of future
performance.
Main Outputs
Develop and
coordinate
relevant trade
and industry
policies
Develop
comprehensive
programs for the
development of
the private
sector.
Trade and
Industry sector
annual work
programs
reviewed
Output Indicator
2009
Past
2010
2011
Budget
2012
Number of
policies
developed
1
1
3
4
6
6
Number of
policies approved
-
1
1
6
6
6
3
1
2
1
Number of
programs
developed
Composite work
programs
reviewed
-
1
Projections
2013
2014
1
1
2
3
3
3
Sector annual
work program
budgeted
Sector program
budget compiled
by:
1st
October
1st
October
1st
October
1st October
1st October
1st October
Establishment of
Monitoring and
Evaluation
documentation
Centre
M&E Centre
equipped and
made operational
by
-
-
-
-
31st
December
-
-
-
1
3
4
5
Monitoring and
Evaluation
Number of
monitoring visits
Ministry of Trade and Industry
September 2012
Page 22
4. Budget Sub-Program Operations and Projects
The table lists the main Operations and Projects to be undertaken by the subprogram.
Operations
Review existing trade and industry policies and revise
or develop relevant ones
Projects (Investment)
Procure equipment for M & E Unit
Undertake regular periodic monitoring exercises.
Undertake relevant policy, program and project
evaluations
Coordinate annual sector work program
Prepare medium term and annual sector budgets
Establish and equip M & E documentation Centre
Collect and collate quarter and annual progress and
prepare sector reports
Facilitate the setting of clear target and dedicated
lending windows within government financed credit
facilities opened for women and the vulnerable
engaged in industrial activities
Develop M&E capacity in the sector through training
Develop strategies equal opportunities in the industrial
labour market to both men and women including
physically challenged
Assist manufacturing firms to develop and implement
Workplace HIV/AIDS, TB and Malaria policies and
program
Organise Gender development program
Ministry of Trade and Industry
September 2012
Page 23
5. Budget Sub-Program Summary: Expenditure by Economic Classification
2010
Expenditure by Economic
Classification
Actual
2011
Budget
Est.
Outturn
Current Expenditure
21 Compensation of Employees
22 Use of Goods and Services
25 Subsidies
26 Grants
27 Social Benefits
28 Other Expenses
Capital Expenditure
31 Non-Financial Assets
Total Expenditure
Ministry of Trade and Industry
September 2012
2012
2013
2014
Budget
Indicative
Indicative
GH₵
GH₵
GH₵
490,886
-
390,886
-
394,795
-
490,886
390,886
394,795
Page 24
BUDGET SUB-PROGRAM SUMMARY
PROGRAM 1: Management and Administration
SUB-PROGRAM SP 1.4: Statistics, Research and Communication
1. Budget Sub-Program Objective
To provide credible International Trade, Domestic Trade and Industrial Data to support decision
making and policy formulation as well as maintain the ICT infrastructure of the Ministry
2. Budget Sub-Program Description
The sub-program serves the research, information and communication needs of the Ministry and
its stakeholders. It performs these tasks through the Research, Statistics and Information
Management Division and the Communications and Public Affairs Unit.
The operations carried out are to:










Regularly train staff in data methodologies and the use of ICT software
Modernise the information technology and communications infrastructure
Coordinate the ministry's media relations, marketing communications and service quality
Work with all other divisions within the Ministry to strategize their announcements from
policies to new initiatives
Work with Agencies and statutory boards on their various communications plans
Manage the Ministry website and the ministry's quality service functions, serving as a link
between the Ministry and the public
Coordinate all public awareness and educational activities of the Ministry
Prepare and circulate press releases and other information for the media
Manage the Ministry’s television program
Manage the publication and distribution of the Ministry’s newsletter for public knowledge
Ministry of Trade and Industry
September 2012
Page 25
3. Budget Sub-Program Results Statement
The following output indicators are the means by which the Ministry measures the performance
of this sub-program. The table indicates the main outputs and an indicator for each. Where past
data has been collected this is presented. The projections are the Ministry’s estimate of future
performance.
Main Outputs
Undertake
market surveys
to update Census
data
Undertake
market
intelligence on
selected
commodities
Output Indicator
Number of
market surveys
Number of
Intelligence
report(s)
2009
Past
2010
2011
Budget
2012
Projections
2013
2014
-
-
-
-
2
4
-
-
-
-
6
10
Preparation of
international
trade bulletins
Number of
bulletins prepared
4
4
4
4
4
4
Preparation of
domestic trade
bulletins
Number of
editions produced
annually
12
12
12
8
12
12
MoTI newsletter
published
Number of
editions
4
4
4
4
4
4
Ministry of Trade and Industry
September 2012
Page 26
4. Budget Sub-Program Operations and Projects
The table lists the main Operations and Projects to be undertaken by the subprogram.
Operations
Projects (Investment)
Provide international and domestic data to stakeholders
No projects
Prepare quarterly, half-yearly and annual reports on
prices of selected products on the domestic market
Facilitate the strengthening of GCNet’s connectivity to
Key MDAs, boarder points, freight forwarders and
other users
Ensure continuous connectivity to internet services
Ensure the smooth running of computer hardware,
software applications and network connectivity.
5. Budget Sub-Program Summary: Expenditure by Economic Classification
2010
Expenditure by Economic
Classification
Actual
2011
Budget
Est.
Outturn
2012
2013
2014
Budget
Indicative
Indicative
GH₵
GH₵
GH₵
Current Expenditure
21 Compensation of Employees
22 Use of Goods and Services
25 Subsidies
26 Grants
27 Social Benefits
28 Other Expenses
430,000
-
430,000
-
434,300
-
Capital Expenditure
31 Non-Financial Assets
Total Expenditure
430,000
430,000
434,300
Ministry of Trade and Industry
September 2012
Page 27
BUDGET PROGRAM SUMMARY
PROGRAM 2: Trade Development
1. Budget Program Objectives





Diversify and Increase export base
Increase competitiveness and enhance integration into domestic and international markets.
Improve Ghana’s position in global and regional markets
Accelerate economic integration with other regional and sub-regional states.
Ensure the health, safety and economic interest of consumers
2. Budget Program Description
The Trade Development program is responsible for



Creating competitive advantage on a more diversified range of products with higher levels of
value-addition
Ensuring International Trade competitive advantage in cost, price, quality, design and
logistics management, leading to timely sales and after sales service
Increasing export capacity and support direct investment flows via the implementation of
strategies directed at targeted markets.
Ministry of Trade and Industry
September 2012
Page 28
3. Budget Program Summary : Expenditure by Sub-Program, Economic
Classification and Projects
Program 2: Trade Development
2010
Expenditure By Budget SubProgram
Actual
2011
Budget
Est.
Outturn
BSP1: Domestic and International
Trade Development and Promotion
BSP2: Export Development and
Promotion
Total Expenditure
2010
Expenditure by Economic
Classification
Actual
2011
Budget
2012
2013
2014
Budget
Indicative
Indicative
GH₵
GH₵
GH₵
26,608,531
26,608,531
26,874,616
382,000
26,990,531
2012
382,000
26,990,531
2013
385,820
27,260,436
2014
Indicative
Indicative
Est.
Outturn
Budget
GH₵
Current Expenditure
21 Compensation of Employees
22 Use of Goods and Services
25 Subsidies
26 Grants
27 Social Benefits
28 Other Expenses
Capital Expenditure
31 Non-Financial Assets
Total Expenditure
Expenditure by Projects
2010
Actual
2011
Budget
Est.
Outturn
GH₵
26,858,131
10,400
26,858,131
10,400
27,126,712
10,504
122,000
26,990,531
2012
Budget
122,000
26,990,531
2013
Indicative
123,220
27,260,436
2014
Indicative
GH₵
GH₵
GH₵
Support implementation of Private
Sector Development strategy (PSDS
II)
Increase exports by 25% by Dec.,
2012.
Total Expenditure
Ministry of Trade and Industry
GH₵
September 2012
70,000
70,000
70,700
52,000
122,000
52,000
122,000
52,520
123,220
Page 29
BUDGET SUB-PROGRAM SUMMARY
PROGRAM 2: Trade Development
SUB-PROGRAM SP 2.1: Domestic and International Trade Development and
Promotion
1.
Budget Sub-Program Objectives





Promote and foster the exchange of goods and services.
Diversify and Increase export base
Accelerate economic integration with other regional and sub-regional states.
Increase competitiveness and enhance integration into domestic and international markets.
Improve Ghana’s position in global and regional markets
 Ensure the health, safety and economic interest of consumers
2.
Budget Sub-Program Description
The sub-program aims at ensuring that Ghanaian enterprises especially the Micro, Small and
Medium Enterprises (MSMEs) get the necessary support to be competitive and achieve their
full potential.
International Trade
The operations identified for the promotion of International Trade are:







Market access and trade facilitation
Institutional capacity development and coordination mechanisms
Expanding supply capacity and ensure information flow
International trade negotiations and agreements,
Import and export procedures and other measures affecting production
Transform the country into a more open, competitive and export-led economy with
expanded market access
In line with W.T.O measures, develop countervailing and anti-dumping duties, safeguards
and remedies and trade dispute settlement mechanism
Ministry of Trade and Industry
September 2012
Page 30
Diversification of Export Base and Value-Addition
 Facilitate diversification of export base and value-addition.
Trade Facilitation
The operations to improve trade domestically and across borders are:



Customs Services reform and modernization
Electronically exchange information and documents among relevant authorities and
stakeholders
Internet reference system for accessing statutory information and simulating transaction
costs, standardizing information requirements by simplifying procedures, encouraging use
of best practices as well as applying relevant information technology
Domestic Trade
The operations under Domestic Trade include:






Creation of an enabling environment for trade and investment to thrive
Integrating domestic trade with international trade given their interdependence
Improving business environment and elaborating the role of government and that of the
private sector in trade and investment promotion
Supporting domestic private businesses to improve upon their competitiveness
Encouraging public-private partnership in implementing various programs and activities
prescribed in the Public Partnership Policy
Distribution and Wholesale Trade
 Retail Trade and Informal Trade, ensuring consumer protection and fair trade
Ministry of Trade and Industry
September 2012
Page 31
3.
Budget Sub-Program Results Statement
The following output indicators are the means by which the Ministry measures the
performance of this sub-program. The table indicates the main outputs and an indicator for
each. Where past data has been collected this is presented. The projections are the Ministry’s
estimate of future performance
Past
Main Outputs
Negotiation of
Bilateral
International
Trade and
Investments
agreements and
treaties
Participation in
Multilateral and
Regional Trade
Negotiations and
implementation
of protocols
Streamline trade
and customs
procedures to
reduce cost and
risk of doing
business
Capacity
Building for
SMEs on bidding
government
contracts
Develop a
comprehensive
strategy for the
promotion of
made in Ghana
goods
Domestic trade
and investment
laws
enforcement
Budget
Projections
Output Indicator
2009
2010
2011
2012
2013
2014
Number of
Bilateral Trade
and Investment
agreements and
Treaties signed
-
-
3
3
3
3
Number of WTO
and ECOWAS
negotiations
participated in
-
-
8
8
10
10
Number of days
for forwarding
and clearing
goods at the port
reduced
-
-
-
2
3
3
Number of SMEs
trained
-
-
-
5
6
6
Number of
promotions and
awareness
programs
orgranised
-
-
-
3
6
8
Number of
investment laws
enforced
-
-
-
5
5
5
Ministry of Trade and Industry
September 2012
Page 32
Tariff dispute
resolution
Number of
complaints
resolved by
tariffs advisory
board
-
-
2
8
10
15
Domestic trade
data developed
and maintained
Number of trade
bulletins
produced
-
-
-
4
4
4
4.
Budget Sub-Program Operations and Projects
The table lists the main Operations and Projects to be undertaken by the
sub- program.
Operations
Projects (Investment)
Participate in WTO/EPA negotiations.
No Projects
Review of current tariff and exemption to identify
inconsistencies and recommend changes
Intensify the program for the promotion of Madein-Ghana goods.
Administer import permit efficiently
Establish Web-based Gallery website for locally
manufactured goods.
Ministry of Trade and Industry
September 2012
Page 33
5.
Budget Sub-Program Summary: Expenditure by Economic Classification
2010
Expenditure by Economic
Classification
Current Expenditure
21 Compensation of Employees
22 Use of Goods and Services
25 Subsidies
26 Grants
27 Social Benefits
28 Other Expenses
Capital Expenditure
31 Non-Financial Assets
Total Expenditure
Ministry of Trade and Industry
Actual
2011
Budget
Est.
Outturn
2012
2013
2014
Budget
Indicative
Indicative
GH₵
GH₵
GH₵
26,538,531
-
26,538,531
-
26,803,916
-
70,000
26,608,531
70,000
26,608,531
70,700
26,874,616
September 2012
Page 34
BUDGET SUB-PROGRAM SUMMARY
PROGRAM 2: Trade Development
SUB-PROGRAM SP 2.2: Export Development and Promotion
1.
Budget Sub-Program Objectives


2.
Diversify and increase export base of non-traditional products
Improve Ghana’s export position in global and regional markets for non-traditional
products
Budget Sub-Program Description
The Ghana Export Promotion Authority has a headquarters and five zonal offices in Kumasi,
Takoradi, Ho, Bolgatanga and Tamale.
The main operations undertaken within the sub-program are:

Ensure Market Access and Development: this done by organizing both inward and
outward market entry and penetration programs such as trade missions, trade fairs and
exhibitions, buyer-seller meetings and conferences and group marketing schemes.

Product Development and Supply base Expansion: This is done by organizing contract
production/supply schemes, establishing export production village schemes and offering
technical advisory services to facilitate product and market development as well as supply
chain management

Export Trade Information Dissemination and Communication Support: This is achieved
through the use of tools such as cyber café, trade library, e-mail broadcast to search, cull
and disseminate information to the exporter community in Ghana and beyond.

Export Human Resource Capacity Strengthening: It is achieved through the operation of
the Ghana Export School by organizing export management, product development, market
development and other specialized trade related courses and seminars. The GES
collaborates with trade related institutions to organize export-related training for them and
their clients.
Ministry of Trade and Industry
September 2012
Page 35

Coordinating of Export Development activities: This is undertaken through census
building with stakeholders by holding Consultative Exporters’ Fora.
The Organizational Units involved are:
Marketing and Promotion Division: Exhibition and Fares Department, Public Relations
Department Match – Making Department, Export Clearing House,
Research and Information Division: Library Department, Ghana Export Trade Information
Centre (GETIC), Information Technology Department, Traceability Department, Monitoring
and Evaluation Department
Product Development Division: Agriculture Department, Manufacturing Department,
Handicraft Department, Services Department
The program is funded by GOG, EDAIF and IGF (Exporter Registration Fees).
The customers of the program are exporters, financial institutions, academia, researchers,
MDA’s, District Assemblies and other private sectors.
Challenges/ Key Issues
 Late and sometimes failure of release of approved budget
 Limited medium and long-term export financing for the exporter community
 Inadequate funding for planned program and activities
 Weak supply base of non-traditional export products
 Presence of tariff and non-tariff barriers especially in the ECOWAS sub-region. Nonadherence to ETLS protocols by neighboring countries
 Lack of funds for monitoring and evaluation for programs and projects
Ministry of Trade and Industry
September 2012
Page 36
3.
Budget Sub-Program Results Statement
The following output indicators are the means by which the Ministry measures the
performance of this sub-program. The table indicates the main outputs and an indicator for
each. Where past data has been collected this is presented. The projections are the Ministry’s
estimate of future performance.
Main Outputs
Export Earnings
in the nontraditional
products.
Market Access
Programs
organized for
exporters
Output
Indicator
Value of
earnings in US$
Number of
Market access
programs
organized
Number of
Firms
participating
International
Trade
negotiations and
bilateral
meetings
(ECOWAS,
WTO, EPA,
Joint
Commissions
etc.)
National
Traceability
System (NTS)
established and
operational.
Directory of
Ghana Service
Providers
created
Number of
Trade and
investment
missions
organized
Number of
exporters using
the NTS.
Number of
Service
providers
registered to
export their
services.
Ministry of Trade and Industry
Past
2009
2010
Budget
2011
US$1.215 US$1.629 US$2.423
billion
billion
billion
Projections
2012
2013
2014
US$2.446
billion
US$3.308
billion
US$4.220
billion
3
8
7
11
11
11
36
92
150
180
185
190
2
3
4
4
3
-
-
-
30
150
160
15
14
10
11
19
35
4
September 2012
Page 37
Number of
exporters trained
251
1,107
1,006
1180
7
31
27
28
-
-
1
5
1190
1200
Exporters
trained in Export
Management
Number of
training
programs
organized
Strategic export
market research
conducted.
Number of
strategic export
market research
exercise
undertaken
Ministry of Trade and Industry
September 2012
30
2
35
4
Page 38
4.
Budget Sub-Program Operations and Projects
The table lists the main Operations and Projects to be undertaken by the
sub- program.
Operations
Projects (Investment)
Pay all administrative charges due by December 2012
Purchase of two (2) Toyota corolla cars for
Directors and two Toyota Pick-ups
Increase exports by 25% by Dec., 2012.
Purchase of 5 office desks and 5 executive chairs
Identify new market for promoting Ghanaian
products and services in Liberia in collaboration
with AGI, FAGE and the GNCCI.
Purchase of 5 Air conditioners and 2 heavy duty
photocopier machines
Participate in the National Policy Fair and Ghana
International Trade Fair 2012.
Renovation of office building and 12 Official staff
residences
Made-in-Ghana solo exhibitions are to be
organized in three selected ECOWAS countries
by December 2012. (Gambia, Sierra Leone and
La Cote d’Ivoire).
Purchase of 5 desktop computers and 2 laptops
Over 200 companies will be participated in four
International trade fairs in ECOWAS and other
African countries e.g. Abuja, Lagos, Lome and
Ouagadougou to maintain and improve the subregional market for Ghanaian products.
40 footer container to warehouse exhibits for trade
fairs
Contact Promotion Program in Saudi Arabia and
United Arab Emirates.
Construction of fence wall around Kumasi property
and completion of renovation work
Coordinate participation in two international
buyers fairs in Germany’s Ambiente and Fruit
Logistica
Participate in
 International Conferences (WTO, ECOWAS, EPA,
AGOA etc.)
 Permanent Joint Commission meetings (GhanaSouth Africa, Ghana-Benin, Ghana-Iran etc.)
 Trade & investment missions.
Such as WTO, ECOWAS, EPA, etc. Ghana-South
Africa, Ghana – Benin, Ghana – Iran, etc. AGOA,
Ministry of Trade and Industry
September 2012
Page 39
Form 4 sub-sector committees for the 4 identified
service sectors (BPO, Medical Tourism,
Education and Private Sector Consultancy)
Conduct Sector survey of professional service
providers leading to the creation of Directory of
Ghana service providers – at least 100 copies of
the directory to be produced.
Establish the National Traceability System for
Fresh horticultural products and fish products
Provision of training on benefits, basic
requirement and online registration on food and
drugs export to the USA.
Training of trainers and review of export school
manual.
Build capacities of farmers, bankers, customs
officials, port authorities, transporters etc. in
Export Marketing Skills
Establish district export committees to create
export awareness in 30 districts.
Workshop on Export Marketing Fundamentals
held in Eight (8) Regional Capitals
Two sensitization workshops to be conducted
and Companies assisted to complete registration
procedure for ETLS.
Provide training on ETLS for exporters
Cross-border and ECOWAS trade facilitation.
Improve the knowledge of GEPA Staff on
selected product/market situations, thus export
market research on Ghanaian products
Enhance capacity of 30 trainers by improving
their knowledge, skills and techniques of
delivery to exporters, producers and extension
officers
Train 20 GEPA Staff to enhance knowledge,
skills, and also acquire advance professional
Ministry of Trade and Industry
September 2012
Page 40
training.
Printing of reports i.e. newsletters, Export
guides, market & product profiles etc. for the
export community
Re-design corporate website to become a
proactive trade information system for the GEPA
and its clients
Provide critical trade notices/information to at
least 100 registered exporters by SMS by
December 2012
To develop an exporter registration database and
upgrade Exporter registration profiles.
Annual renewal of foreign and internet
subscriptions
Provide quarterly and annual export statistics to
the exporting community and the general public
Monitoring and Evaluation of all GEPA
programs and activities
To undertake desk and field research for access
to strategic markets in key African countries.
Ministry of Trade and Industry
September 2012
Page 41
5.
Budget Sub-Program Summary: Expenditure by Economic Classification
2010
Expenditure by Economic
Classification
Actual
2011
Budget
Est.
Outturn
Current Expenditure
21 Compensation of Employees
22 Use of Goods and Services
25 Subsidies
26 Grants
27 Social Benefits
28 Other Expenses
Capital Expenditure
31 Non-Financial Assets
Total Expenditure
Ministry of Trade and Industry
September 2012
2012
2013
2014
Budget
Indicative
Indicative
GH₵
GH₵
GH₵
319,600
10,400
319,600
10,400
322,796
10,504
52,000
382,000
52,000
382,000
52,520
385,820
Page 42
BUDGET PROGRAM SUMMARY
PROGRAM 3: Business Development and Promotion
1.
Budget Program Objectives



2.
To develop and transfer appropriate and marketable technologies to small and medium
scale enterprise in Ghana
To improve entrepreneurial skills and facilitate access to credit and markets for micro and
small scale enterprises
To promote the sustainable development of the Central Region
Budget Program Description
The program seeks to reduce post-harvest losses; drudgery, increase production, create jobs
and reduce poverty by carrying out research and development, design, prototyping and testing
of appropriate and marketable technologies for the agro-processing industry. The technology
developed is transferred through apprentice training, engineering skills development and
occupational and safety health environment of users of our equipment.
A thriving micro and small scale enterprise sector is considered worldwide as a key to the path
of successful and healthy economic development. NBSSI was therefore set up to promulgate
this agenda. The focus is to formulate, develop and implement national programs aimed at
encouraging rural self-employment and informal enterprises among the economically active
population to enable them contribute effectively to the growth and the diversification of
national economy.
The program is also responsible for promoting Central Regional Development across the
following areas Investment and Enterprise Promotion, Integrated Tourism Development,
Agriculture, Natural Resources and Rural Development, Communication and Information
Management.
Ministry of Trade and Industry
September 2012
Page 43
3.
Budget Program Summary : Expenditure by Sub-Program, Economic
Classification and Projects
Program 3: Business Development and Promotion
2010
Expenditure By Budget SubProgram
Actual
2011
Budget
Est.
Outturn
BSP1: Technology Transfer,
Research and Product Development
BSP2: Micro and Small Business
BSP3: Central Region Development
Total Expenditure
2010
Expenditure by Economic
Classification
Actual
2011
Budget
Expenditure by Projects
2010
Actual
2011
Budget
Est.
Outturn
2013
2014
Budget
Indicative
Indicative
GH₵
GH₵
GH₵
780,000
806,000
13,004,390
14,590,390
2012
Est.
Outturn
Current Expenditure
21 Compensation of Employees
22 Use of Goods and Services
25 Subsidies
26 Grants
27 Social Benefits
28 Other Expenses
Capital Expenditure
31 Non-Financial Assets
Total Expenditure
2012
369,150
806,000
12,993,390
14,168,540
2013
372,842
814,060
13,123,324
14,310,226
2014
Budget
Indicative
Indicative
GH₵
GH₵
GH₵
2,908,960
78,600
45,576
2,487,110
78,600
45,576
2,511,982
79,386
46,032
11,557,254
14,590,390
2012
Budget
11,557,254
14,168,540
2013
Indicative
11,672,827
14,310,226
2014
Indicative
GH₵
GH₵
GH₵
Purchase of one saloon and one pick
Up vehicle
Complete on-going foundry building
installed & commission equipment
by Dec. 2012
Purchase of (two) 2 Pick-Ups
Complete the construction and
reconstruction of Bridges, Culverts
and maintenance of Feeder roads by
June 2012
100,000
100,000
101,000
110,000
90,000
110,000
90,000
111,100
90,900
60,000
60,000
60,600
Complete the construction of
Ministry of Trade and Industry
September 2012
Page 44
Museum of Black History at Cape
Coast by June 2012
Complete the Construction of the
Emergency Centre and a Bunglow at
Agona Swedru Hospital by May
2012
Complete the Construction of the
Children's Library and Park at Kasoa
by June 2012
Complete the Construction of 57
Boreholes in the various MMDAs by
December 2012
Construct 50 Boreholes in the
various MMDAs by December 2012
Complete reconstruction of Swedru
Sports Stadium by May 2012
Complete the rehabilitation and
expansion of Duakwa Town Market
by July 2012
Complete construction of Rest Stop
at Esuehyia by July 2012
Complete the construction of Biriwa
Market by May 2012
Complete the construction of 2 ICT
Centres in 2 MMDAs by September
2012.
Construction of 4 ICT Centres in 4
MMDAs by December 2012.
Complete construction of pavement
at Mankessim Lorry Park and
Market Extension by August 2012
Complete the construction of 16
CHPS by October 2012
Complete the construction of 20
CHPS by October 2012
Complete and refurbish Swedru
Senior High School Assembly Hall
by May 2012
Construct Police Station and
accommodation at Duakwa by
August 2012
Construct a Police Station at Gomoa
Fetteh by December 2012
Complete and refurbish Breman
Asikuma Community Centre by
September 2012
Construct a market at Bisease by
August 2012
Convert old structures into
Community Nursing Schools at
Saltpond and Buadatta by October
2012
Ministry of Trade and Industry
September 2012
480,750
480,750
485,558
1,000
1,000
1,010
1,000
1,000
1,010
1,000
1,000
1,010
1,000
1,000
1,010
1,000
1,000
1,010
1,000
1,000
1,010
1,000
1,000
1,010
1,000
1,000
1,010
1,000
1,000
1,010
1,000
1,000
1,010
497,452
497,452
502,426
1,190,052
1,190,052
1,201,952
1,800,000
1,800,000
1,818,000
450,000
450,000
454,500
400,000
400,000
404,000
300,000
300,000
303,000
250,000
250,000
252,500
450,000
450,000
454,500
500,000
500,000
505,000
Page 45
Acquire site and construct PreSchool Teacher Training College at
Gomoa Abura in partnership with
GETfund and the Ministry
Establish a Community
Communication Centre at Gomoa
Dego by May 2012
Acquire site and construct a National
Park at Twifo Hemang by
Rehabilitate and Construct 1km
culverts and a bridge at
Rehabilitate existing salt works by
December 2012
Construct a 6-Unit classroom block
at Enyan Maim Senior High
Complete Nyakrom Senior High
School Assembly Hall by
Establish Eguafo Ancient Cave
Settlement Project by October
Construct Assin Fosu Police Station
and Accommodation by November
2012
Establish a Community Police
Training Centre at Abura Dunkwa by
December 2012
Procure one Generator as power
backup for CEDECOM
Construct 3 staff bungalows for
CEDECOM by December 2012
Revamp CEDECOM Computer
Learning Centre (CLC) to
Revamp CEDECOM's teak
plantations to generate sustainable
Rehabilitation of structures
constructed by CEDECOM at Brenu
Beach by May 2012
Procure two (2) coaches for tour
operations and tourism
Establish one Salt Bank in the
Region by July 2012
Total Expenditure
Ministry of Trade and Industry
500,000
500,000
505,000
100,000
100,000
101,000
500,000
500,000
505,000
220,000
220,000
222,200
500,000
500,000
505,000
300,000
300,000
303,000
250,000
250,000
252,500
85,000
85,000
85,850
400,000
400,000
404,000
500,000
500,000
505,000
50,000
50,000
50,500
540,000
540,000
545,400
104,000
104,000
105,040
20,000
20,000
20,200
200,000
200,000
202,000
100,000
100,000
101,000
500,000
500,000
505,000
11,557,254
11,557,254
11,672,827
September 2012
Page 46
BUDGET SUB-PROGRAM SUMMARY
PROGRAM 3: Business Development and Promotion
SUB-PROGRAM SP 3.1: Technology Transfer, Research and Product
Development
1.
Budget Sub-Program Objective
To increase industrial output, reduce drudgery and improve the competitiveness of domestic
and industrial products by developing and transferring appropriate and marketable technologies
through research, product development, and technology transfer
2.
Budget Sub-Program Description
The sub-program considers two main areas namely Research and Product Development and
Technology Transfer
Operations carried out under Research and Product Development involves:
 Conducting survey to identify drudgery and low productivity issues in the agri/agro
processing industry.
 Developing the idea from the survey into a product by the engineering design centre
 Prototyping and testing of the product by the Production and Quality Control outfit.
The main operation carried out under Technology Transfer involves:
 Provision of technical and income generating training for the youth, vulnerable groups,
men and women through apprenticeship training and short courses for practising engineers.
This hands-on and training platform is used to transfer technology which was developed by
the research and design unit.
The program covers all Regions, some Districts and Rural communities in Ghana.
The sub-program is funded by the Government of Ghana.
Our challenges include:
 Obsolete equipment
 Uncompleted administrative block and lecture rooms
 Uncompleted foundry project
 Rehabilitation of workshop buildings and design centre
Ministry of Trade and Industry
September 2012
Page 47
3.
Budget Sub-Program Results Statement
The following output indicators are the means by which the Ministry measures the
performance of this sub-program. The table indicates the main outputs and an indicator for
each. Where past data has been collected this is presented. The projections are the Ministry’s
estimate of future performance
Past
Main Outputs
Design and
prototyping of
agro-processing
equipment
Train Technical
apprentices in
metal machining,
welding and
fabrication and
foundry works
Vulnerable men
and women
trained in the use
of equipment we
have sold to
them.
Provide short
courses for
master craft
persons,
engineers,
architects and
technicians to
enhance their
skill.
Output Indicator
Budget
Projections
2009
2010
2011
2012
2013
2014
4
4
3
5
6
8
Number of
student graduated
200
282
438
150
250
300
Number of
vulnerable men
and women
trained.
580
319
439
500
600
650
Number of
trained personnel.
127
150
185
200
220
230
5
5
9
10
5
5
Number of
equipment
developed.
Organize fairs
and exhibitions
Number of fairs
for the promotion organized.
of our products
Ministry of Trade and Industry
September 2012
Page 48
4.
Budget Sub-Program Operations and Projects
The table lists the main Operations and Projects to be undertaken by the
sub- program.
Operations
Projects (Investment)
Administer GRATIS operations
Complete on-going foundry building by Dec. 2012
Train 100 staff in MIG-TIG welding and production
planning by Dec. 2012
Purchase of (two) 2 Pick-Ups
Design and develop a complete Shea butter processing
plant
Design and develop a complete oil palm processing
plant
Design and develop a complete cassava processing
plant
Design and develop a cocoa pod breaker
Establish product testing bay
Design and develop a complete groundnut processing
plant
Train trainers ( Staff development )-
Rehabilitate workshop equipment
Train technical apprentice
Establish apprentice training bay
Establish strength of material laboratory
Establish Practical (hands on) college of technology
Erecting of fence wall
Renovate workshop building
Train master craft persons, technician and engineers to
develop skills
Train vulnerable persons in occupational safety health
and environmental management during the use of our
equipment
Organize exhibitions and fairs to promote our
prototypes
Ministry of Trade and Industry
September 2012
Page 49
5.
Budget Sub-Program Summary: Expenditure by Economic Classification
2010
Expenditure by Economic
Classification
Actual
2011
Budget
Est.
Outturn
Current Expenditure
21 Compensation of Employees
22 Use of Goods and Services
25 Subsidies
26 Grants
27 Social Benefits
28 Other Expenses
Capital Expenditure
31 Non-Financial Assets
Total Expenditure
Ministry of Trade and Industry
September 2012
2012
2013
2014
Budget
Indicative
Indicative
GH₵
GH₵
GH₵
571,600
8,400
160,750
8,400
162,358
8,484
200,000
780,000
200,000
369,150
202,000
372,842
Page 50
BUDGET SUB-PROGRAM SUMMARY
PROGRAM 3: Business Development and Promotion
SUB-PROGRAM SP 3.2: Micro and Small Business Development
1.
Budget Sub-Program Objectives





2.
To improve entrepreneurial skills and facilitate access to credit and markets for small scale
enterprises
To provide MSEs access to substantial and high quality Business Development Services for
their development
To contribute to the creation of enabling environment for small scale enterprises
development
To contribute to the development of an enterprise culture in the country
To promote MSEs sector associations
Budget Sub-Program Description
The National Board for Small Scale Industries (NBSSI) was established to formulate, develop
and implement national program aimed at encouraging and accelerating the growth of micro
and small scale enterprises to enable them contribute effectively to growth and the
diversification of national economy.
NBSSI currently has ten Regional Offices in the Regional Capitals of the country and 124
District Business Advisory Centres (BACs). Other collaborating institutions are; Rural
Enterprise Project (REP), Ghana Regional Appropriate Technology Industrial Services
(GRATIS), Technology Consultancy Centre (TCC), Council for Science and Industrial
Research (CSIR) etc.
Ministry of Trade and Industry
September 2012
Page 51
The key operations include:








Creating enabling environment for the development of small scale enterprises
Promoting small scale enterprise association
Provision of employable skills to unemployed youth and school drop-out
Provision of training advisory and counseling services
Provision of information on small scale enterprise development to stakeholders
Facilitating MSMEs access to business development programs
Facilitating MSMEs access to institutional credits
Assisting MSMEs to participate in fairs
The NBSSI programs are substantially funded by Government of Ghana budget allocations and
IGF derived from its activities
The key challenges are:





Trade liberalization policy which has resulted in the lack of markets for local products
Promotional Agencies are not adequately equipped to address the needs of the MSE sector.
Negative attitude towards entrepreneurship and locally
Made products stifle growth of MSEs
Inadequate office equipment
Ministry of Trade and Industry
September 2012
Page 52
3.
Budget Sub-Program Results Statement
The following output indicators are the means by which the Ministry measures the
performance of this sub-program. The table indicates the main outputs and an indicator for
each. Where past data has been collected this is presented. The projections are the Ministry’s
estimate of future performance.
Main Outputs
Output Indicator
2011
2012
2013
2014
10,000
17,500
22,000
25,000
35,000
48,000
60
70
88
100
200
300
Number of
directory on
MSMEs printed
and distributed to
stakeholders
-
-
-
2
6
10
Number of
training material
developed
3
8
12
14
20
30
Number of MSEs
trained in
financial literacy
program
10,000
15,000
18,000
22,000
30,000
45,000
Number of
women provided
with BDS
1,500
4,200
7,500
10,000
15,000
25
36
50
75
Efficiency and
capacity of
officers improved
Number of
officers trained
Promotional
campaign
designed and
implemented
Projections
2010
Number of
enterprises with
access to business
development
services
Financial literacy
program for
MSEs in the
manufacturing
sector
Provision of
affordable
business
Development
services to
women
entrepreneurs
enhanced
Budget
2009
MSEs access to
Business
Development
Services
improved
Credible data on
MSMEs
compiled and
distributed to
stakeholders for
policy
formulation and
decision making
Standardized
training material
for MSMEs
developed
Past
Number of
promotional
activities
organised
Ministry of Trade and Industry
12
3,000
20
September 2012
Page 53
Capacity
building of
MSEs to take
advantage of
subcontracting
opportunities
supported
Number of MSEs
supported to take
advantage of
subcontracting
opportunities
5
15
25
40
70
100
Knowledge of
MSEs in record
keeping enhanced
Number of MSEs
provided with
training in record
keeping
10,000
30,000
50,000
75,000
90,000
110,000
MSEs supported
to formalized
businesses
Number of MSEs
business
supported
15,000
20,000
25,000
35,000
50,000
70,000
Financial and
operation control
systems
enhanced
Number of audit
reports issued
4
8
8
12
15
18
Accessibility to
formal credit for
MSEs enhanced
Numbers of
MSEs supported
with formal credit
2,000
3,000
4,500
8,000
12,000
20,000
Ministry of Trade and Industry
September 2012
Page 54
4.
Budget Sub-Program Operations and Projects
The table lists the main Operations and Projects to be undertaken by the
sub- program.
Operations
Projects (Investment)
Conduct visits to 124 Districts offices
Purchase of three saloon and one cross-country
vehicle
Design and implement client survey
Purchase of 150 computers and accessories
Monitor regional performance on credit delivery.
Rehabilitate head office building into a six-storey
office complex
Monitor gender activities
Procure office equipment and fittings
Conduct monitoring visits to 124 offices
Procure 20 Pick-up vehicles
Sanitary sites
Rehabilitate 10 regional bungalows
Rental of network and ICT equipment
Electricity charges
Telecommunications
Firefighting accessories
Maintenance and repairs - official vehicles
Fuel and lubricants - official vehicles
Running cost - official vehicles
Other travel and transportation
Toll charges and tickets
Office facilities, supplies and accessories
Other office materials and consumables
Textbooks and library books
Teaching and learning materials
Sports, recreational and cultural materials
Ministry of Trade and Industry
September 2012
Page 55
Contract cleaning service charges
Bank charges
Audit fees
Facilitate MSMEs access to Business Improvement
Programs
Develop affordable programs for women entrepreneurs
Develop and review reference materials for 124 BACs
Provide information on small enterprises development
to 50,000 stakeholders
Facilitate MSMEs access to institutional credit
Accessibility to credit of MSMEs increased annually
Assist MSMEs to participate in fairs
Train 120 officers in small enterprises development
Organise orientation seminar for 40 new officers
Equip 40 officers with managerial skills
Conduct financial and technical audit of 135 offices.
Workman compensation
Staff welfare expenses
Refund of medical expenses
Ministry of Trade and Industry
September 2012
Page 56
5.
Budget Sub-Program Summary: Expenditure by Economic Classification
2010
Expenditure by Economic
Classification
Actual
2011
Budget
Est.
Outturn
Current Expenditure
21 Compensation of Employees
22 Use of Goods and Services
25 Subsidies
26 Grants
27 Social Benefits
28 Other Expenses
Capital Expenditure
31 Non-Financial Assets
Total Expenditure
Ministry of Trade and Industry
September 2012
2012
2013
2014
Budget
Indicative
Indicative
GH₵
GH₵
GH₵
604,000
72,000
30,000
604,000
72,000
30,000
610,040
72,720
30,300
100,000
806,000
100,000
806,000
101,000
814,060
Page 57
BUDGET SUB-PROGRAM SUMMARY
PROGRAM 3: Business Development and Promotion
SUB-PROGRAM SP 3.3: Central Region Development
1.
Budget Sub-Program Objective
To promote the sustainable development of the Central Region through Investment Promotion,
Enterprise, Integrated Tourism, Agriculture, Natural Resource and Rural Development,
Communication and Information management.
2.
Budget Sub-Program Description
The Commission has four (4) key operational areas namely Investment Promotion and
Enterprise Development, Integrated Tourism Development, Agriculture, Natural Resource and
Rural Development, Communication and Information Management and Corporate Planning.
Investment Promotion and Enterprise Development
The Department is committed to acting as a catalyst to accelerate private sector development in
the region by developing viable Business Plans and conducting feasibility studies, forge
linkages among investors locally and abroad disseminating up to date information on
investment opportunities and incentive packages available to investors, and facilitating the
acquisition and documentation of land, and access to utility services.
Integrated Tourism Development
The Department is responsible for the development of culturally and environmentally
sustainable tourism products in the Central Region. It provides technical advice and training to
the hospitality industry as well as other industry practitioners.
Agriculture, Natural Resource and Rural Development
The Department is responsible for promoting agriculture and natural resource development to
enhance agricultural productivity, food security, environmental management and wealth
creation in the rural communities of the Central Region. It does this through facilitation of
farmers' capacity development in agroforestry, crop farming and non-traditional farming
businesses including, aquaculture and bee keeping.
Ministry of Trade and Industry
September 2012
Page 58
Communication and Information Management
The department is responsible for all information needs of CEDECOM's stakeholders from
both the public and private sectors. ICT is a major facilitator of economic and social
development and must be supported to enhance the management of both public and private
sector businesses. In line with this the department is also responsible for the provision of ICT
services and training for the people of the Central Region through the Commission's
Community Learning Centres at Cape Coast, BremanAsikuma and 2 other centres at Winneba
and Dunkwa-on-Offin which are yet to be completed.
Ministry of Trade and Industry
September 2012
Page 59
3.
Budget Sub-Program Results Statement
The following output indicators are the means by which the Ministry measures the
performance of this sub-program. The table indicates the main outputs and an indicator for
each. Where past data has been collected this is presented. The projections are the Ministry’s
estimate of future performance.
Main Outputs
Agriculture and
marine infrastructure
including fish
hatcheries developed
and promoted.
Salt Production
increased to support
the Petrochemical
Industry.
Output Indicator
Two cold stores
established
(% of work done)
Number of fish ponds
constructed
Number of Salt
miners supported to
rehabilitate pans
Feasibility study and
technical report on
Pineapple processing
plant prepared
Number of Pineapple
processing plant
established
Youth in the Central
Region sensitized,
trained and
supported in
vegetable and fruit
production, fish
farming and agroforestry practice
2011
Budget
2012
Projections
2013
2014
-
-
70%
100%
-
-
-
-
-
4
1
1
-
-
12
-
8
10
-
-
-
-
50
-
-
-
50%
-
100%
-
-
-
-
100%
-
-
-
-
-
-
-
1
350
-
-
300
500
500
Number of Acres of
land acquired for salt
production
One Piggery projects
established
Farmer-based groups
trained and
supported
2009
Past
2010
Youth in the Central
Region trained and
supported with farm
input
Ministry of Trade and Industry
September 2012
Page 60
Sensitization and
Publicisation of the
activities and
programs of the
CEDECOM
Number of newsletters
published
-
-
-
-
10
10
Number of news
bulletins published
annually
-
-
-
-
12
12
-
-
-
-
6
6
-
-
-
-
60
60
1
1
1
-
1
1
-
-
-
1
-
-
-
-
-
1
-
-
-
-
-
-
160
240
-
-
-
-
100%
-
-
-
-
-
-
100%
Number of coverage
by media on
activities/programs of
the Commission
Number of out-reach
programs conducted to
sensitize stakeholders
of the Commission
Number of Investment
Forums organised for
stakeholders
Bottlenecks to
Private Sector
development
reduced.
Number of ICT-based
socio-economic
database of the Central
Region for investment
promotion and
planning purposes
produced
Number of regional
one stop investment
and advisory centre
created
Number of acres of
land acquired for
creation of Industrial
Zones
Industrial Zones
created to foster
socio-economic
development of the
Central Region.
Report on Feasibility
study and Technical
details prepared on the
design of the Industrial
Zones
Access roads to the
Industrial Zones
constructed
Ministry of Trade and Industry
September 2012
Page 61
Industrial Zones
created to foster
socio-economic
development of the
Central Region.
Utility services
extended to the
Industrial Zones
Number of Investment
Promotion Fairs
organised
-
-
-
-
100%
-
-
1
-
-
-
6
200
-
-
20
80
80
Training of SMEs to
build their capacities
for business
enhancements.
Number of
entrepreneurs trained
to acquire skills in
Entrepreneurship and
Management skills
Group dynamics and
Leadership Skills
Training organised.
Number of Group
Development and
Leadership Skills
Training organised for
Trade Groups
-
-
-
-
6
6
Number of Business
Incubators established
-
-
-
-
1
-
Number of SMEs
visited on one-on-one
basis and coached in
business management
practices
-
-
-
-
50
50
Number of youth
induced to become
entrepreneurs
-
-
-
-
100
100
Information on SMEs
hosted on the
Commission's website
-
-
-
-
100%
-
-
-
-
-
3
3
Business incubator
established to create
an enabling
environment for
business.
SMEs provided with
advisory and
counseling services
Entrepreneurship
drive of youth from
tertiary and second
cycle institutions
increased by
interacting with
business leaders
through experiential
learning.
Information on
SMEs compiled into
a data warehouse for
easy networking.
Tourism products
developed and
marketed.
Number of new ecotourism products in
rural areas and less
visited districts
supported
Ministry of Trade and Industry
September 2012
Page 62
Tourism products
developed and
marketed.
Unemployed youth
and graduates
trained through
master craftsmen.
Study tours to
African countries.
Strategic
partnerships
developed to deliver
enhanced tourism
products
Tourism map on
Central Region
developed.
Tourism Marketing
Plan for the Central
Region developed
Procurement of tour
coach for tourism
promotion activities.
Brenu Beach master
plan reviewed and
Structures
rehabilitated.
Number of lesser
known festivals
supported in the
Central Region
-
-
1
1
-
-
-
2
2
Number of trade shows
attended to represent
the region.
-
Number of
unemployed youth and
graduate trained and
placed for experiential
learning with master
craftsmen at the
Abrafo handicraft
centre
50
-
-
-
-
-
Number of MOUs
signed with Strategic
Partners
-
-
-
-
1
-
Number of tourism
maps on Central
Region developed
-
-
-
-
200
-
-
-
-
-
1
-
-
-
-
-
-
1
-
-
-
-
100%
-
Number of countries
toured.
Number of tourism
Marketing Plans
developed
30-seater coach
procured
Review of Brenu
Beach Master plan
completed
Ministry of Trade and Industry
September 2012
-
-
3
3
40
40
-
3
Page 63
Rehabilitation of
structures at Brenu
Beach Completed
Abrafo Handicraft
Center fully
operationalised
Central Region
tourism promotion.
-
-
-
-
60%
100%
-
-
-
-
100%
-
100
-
-
100
-
-
-
-
37
100
-
-
-
-
5
100
-
-
-
-
16
20
25
-
-
-
40
100
-
-
-
-
30
100
-
-
-
-
23
100
-
-
-
-
30
100
-
-
-
-
47
100
-
-
Duakwa Markets
constructed
-
-
39
-
100
-
Number of Boreholes
constructed
-
-
57
20
-
-
Abrafo Handicraft
Center commissioned
and operational
Number of
practitioners in the
hospitality industry
trained in quality
service delivery and
product development
(% of work done)
One rest stop
constructed
One National Museum
of Black History to be
constructed
Infrastructure in the
Central Region
improved to attract
investors
domestically and
internationally
Number of
Community Health
and Preventive
Services (CHPS)
constructed
Pavements at
Mankessim market
extension and lorry
park constructed
Emergency centres and
a 3-bedroom doctors
flat constructed
Children’s Library
constructed
Construction and
reconstruction of
Culverts, Bridges and
maintenance of feeder
roads completed.
Swedru Sports
Stadium reconstructed
Ministry of Trade and Industry
September 2012
Page 64
Infrastructure in the
Central Region
improved to attract
investors
domestically and
internationally
Swerdru SHS
Assembly Hall
Refurbished and
completed
Duakwa Police Station
and accommodation
constructed.
Gomoa Fetteh Police
Station constructed
Breman Asikuma
Community Centre
completed
Bisease market
constructed
Conversion of old
structures into
Community Nursing
Schools at Saltpond
and Buadatta
completed
Acquisition of site for
the construction of
Pre-School Teacher
Training College at
Gomoa Abura in
partnership with
GETfund and Ministry
of Education
completed
Construction of an ICT
Centre at Gomoa Dego
Completed
Construction of Abura
Dunkwa Community
Police Training Centre
Infrastructure in the
Central Region
improved to attract
investors
domestically and
internationally
Number of ICT
Centres constructed in
selected MMDAs
Construction of 1km
culvert and bridge at
Anomabo completed
Ministry of Trade and Industry
-
-
-
100
-
-
-
-
-
100
-
-
-
-
-
-
100
-
-
-
-
100
-
-
-
-
-
-
100
-
-
-
-
100
-
-
-
-
-
100
-
-
-
-
-
100
-
-
-
-
-
100
-
-
-
-
2
4
10
5
-
-
-
100
-
-
September 2012
Page 65
Construction of a 9Unit classroom block
at Enyan Maim SHS
completed
Nyakrom Senior High
School Assembly Hall
completed.
Construction of market
at Nsuem Kyekyewire
completed
Construction of 1Km
culverts & roads at
Agona Nsabaa
township completed
Construction of Assin
Fosu
Expansion of CHPS
Compound at Otuam
completed
Construction of 1km
culverts at Agona
Nsaba completed
Agona Swedru
Mausoleum completed
Basic Furnishing and
landscaping of Swedru
Mausoleum
Continuation of
Gomoa Abura Preschool Training Centre
completed
Site acquisition and
construction of a
Police Station with
accommodation at
Anomabo
Construction of market
at Moree completed
Infrastructure in the
Central Region
improved to attract
investors
domestically and
internationally
Number of
Community Centres
constructed at Cape
Coast.
Number of
Community Centres
constructed at
Kommenda and
Eguafo
Ministry of Trade and Industry
-
-
-
-
100
-
-
-
-
100
-
-
-
-
-
-
100
-
-
-
-
-
100
-
-
-
-
100
-
-
-
-
-
100
-
-
-
-
-
-
100
-
-
-
-
100
-
-
-
-
-
-
100
-
-
-
-
-
100
-
-
-
-
-
100
-
-
-
-
-
100
-
-
-
-
-
2
-
-
-
-
-
2
-
September 2012
Page 66
Construction of
Market at Dunkwa-onOffin completed
Acquisition and
Construction of
National Park at Twifo
Hemang
Completion of major
Culvert on the main
road between AgonaSwedru and Agona
Nsaba
Construction of
Science Resource
Centre to cater for 5
communities at Sankor
Community
Ministry of Trade and Industry
-
-
-
-
100
-
-
-
-
-
100
-
-
-
-
-
100
-
-
-
-
-
100
-
September 2012
Page 67
4.
Budget Sub-Program Operations and Projects
The table lists the main Operations and Projects to be undertaken by the
sub- program.
Operations
Provide CEDECOM with logistics to undertake
administrative activities by December, 2012.
Projects (Investment)
Complete the construction and reconstruction of
Bridges, Culverts and maintenance of Feeder roads
by June 2012
Facilitate the enhancement of lesser known festivals in
the region by October 2012.
Complete the construction of Museum of Black
History at Cape Coast by June 2012
Carry out tourism mapping of the region by August
2012
Complete the Construction of the Emergency Centre
and a Bungalow at Agona Swedru Hospital by May
2012
Develop 3 new Ecotourism sites by October 2012
Compete the Construction of the Children's Library
and Park at Kasoa by June 2012
Provide training in product development by July 2012
Complete the Construction of 57 Boreholes in the
various MMDAs by December 2012
Develop tourism marketing plan for the region by May
2012
Construct 50 Boreholes in the various MMDAs by
December 2012
Produce ICT-based socio-economic database of the
Central Region for investment promotion and planning
purposes by March 2012.
Complete reconstruction of Swedru Sports Stadium
by May 2012
Create a regional one stop investment and advisory
centre by May 2012.
Complete the rehabilitation and expansion of
Duakwa Town Market by July 2012
Attract investment for job creation and poverty
reduction in the Central Region September 2012
Complete construction of Rest Stop at Esuehyia by
July 2012
Establish piggrey project at Assin Manso.
Complete the construction of Biriwa Market by May
2012
Research and build database on SMEs in the 17
MMDAs by April 2012
Complete the construction of 2 ICT Centres in 2
MMDAs by September 2012.
Establish one business incubator in the Central Region
by March 2012.
Construction of 4 ICT Centres in 4 MMDAs by
December 2012.
Strengthen the capacity of BDS institutions in the
Complete construction of pavement at Mankessim
Ministry of Trade and Industry
September 2012
Page 68
Region by May 2012
Lorry Park and Market Extension by August 2012
Organise 20 entrepreneurs and management training
programs for SMEs by April
Complete the construction of 16 CHPS by October
2012
Support 2 fishing communities and 2 fish farming
districts with industrial fish storage facilities and fish
ponds by May 2012
Complete the construction of 20 CHPS by October
2012
Train 300 youth in fish farming, vegetables cropping
and agro forestry in the Central Region by April 2012
Complete and refurbish Swedru Senior High School
Assembly Hall by May 2012
Develop strong linkages and partnership with SETIC,
China for bilateral seminars on local economic
development for the 17 MMDAs in the Region by June
2012
Construct Police Station and accommodation at
Duakwa by August 2012
Strengthen the capacity of CEDECOM personnel to
deliver services favourably June
Construct a Police Station at Gomoa Fetteh by
December 2012
Strengthen CEDECOM's linkages with the 17 MMDAs
in the region by March 2012
Complete and refurbish Breman Asikuma
Community Centre by September 2012
Resource the Communication and Information
Management of CEDECOM with logistics by May
2012.
Construct a market at Bisease by August 2012
Provide CEDECOM with logistics to undertake
administrative activities by December 2012.
Convert old structures into Community Nursing
Schools at Saltpond and Buadatta by October 2012
Acquire site and construct Pre-School Teacher
Training College at Gomoa Abura in partnership
with GETfund and Ministry of Education by
December 2012
Acquire site and construct a National Park at Twifo
Hemang by October 2012
Rehabilitate and Construct 1km culverts and a bridge
at Anomabo by October 2012
Rehabilitate existing salt works by December 2012
Construct a 6-Unit classroom block at Enyan Maim
Senior High School by November 2012
Ministry of Trade and Industry
September 2012
Page 69
5.
Budget Sub-Program Summary: Expenditure by Economic Classification
2010
Expenditure by Economic
Classification
Current Expenditure
21 Compensation of Employees
22 Use of Goods and Services
25 Subsidies
26 Grants
27 Social Benefits
28 Other Expenses
Capital Expenditure
31 Non-Financial Assets
Total Expenditure
Ministry of Trade and Industry
Actual
2011
Budget
2012
2013
2014
Budget
Indicative
Indicative
GH₵
GH₵
GH₵
1,733,360
6,600
7,176
1,722,360
6,600
7,176
1,739,584
6,666
7,248
11,257,254
13,004,390
11,257,254
12,993,390
11,369,827
13,123,324
Est.
Outturn
September 2012
Page 70
BUDGET PROGRAM SUMMARY
PROGRAM 4: Trade and Industry Promotion
1.
Budget Program Objectives



2.
Increase competitiveness and enhance integration into domestic and international markets
Ensure the creation of enabling environment to enhance industrial growth and provide the
momentum to achieve competitiveness
Accelerate economic integration with other regional and sub-regional markets
Budget Program Description
The program ensures that activities in the Trade and Industrial sector is actively promoted to
enhance policy research and development; trade, investment and business trends and
possibilities for developing new competitive areas; influence national development strategy as
they relate to trade, investment and business growth in the sector; defining the core processes
and activities of the office, submit yearly the resource needed to perform the relevant activities
and to define the desired outcomes and measures for monitoring, measuring and reporting on
trade, investment and business development growth required.
It also strengthens the technical and institutional capacity of the private sector to participate in
international trade; implement trade and industrial policy by organising outreach programs;
disseminate information on trade agreements and protocol their effect on trade and industry,
and organize programs to increase and diversify exports.
Ministry of Trade and Industry
September 2012
Page 71
3.
Budget Program Summary : Expenditure by Sub-Program, Economic
Classification and Projects
Program 4: Trade and Industry Promotion
2010
Expenditure By Budget SubProgram
Actual
2011
Budget
Est.
Outturn
2012
2013
2014
Budget
Indicative
Indicative
BSP1: Regional Services
BSP2: Foreign Trade Services
GH₵
110,000
490,000
GH₵
110,000
490,000
GH₵
111,100
494,900
Total Expenditure
600,000
600,000
606,000
2010
Expenditure by Economic
Classification
Actual
2011
Budget
Est.
Outturn
Current Expenditure
21 Compensation of Employees
22 Use of Goods and Services
25 Subsidies
26 Grants
27 Social Benefits
28 Other Expenses
Capital Expenditure
31 Non-Financial Assets
Total Expenditure
Expenditure by Projects
2010
Actual
2011
Budget
Est.
Outturn
2012
2013
2014
Budget
Indicative
Indicative
GH₵
GH₵
GH₵
510,000
-
510,000
-
515,100
-
90,000
600,000
2012
Budget
90,000
600,000
2013
Indicative
90,900
606,000
2014
Indicative
GH₵
GH₵
GH₵
Purchase vehicle for the Mission
Total Expenditure
Ministry of Trade and Industry
0
0
0
September 2012
90,000
90,000
90,000
90,000
90,900
90,900
Page 72
BUDGET SUB-PROGRAM SUMMARY
PROGRAM 4: Trade and Industry Promotion
SUB-PROGRAM SP 4.1: Regional Services
1.
Budget Sub-Program Objectives



2.
To identify resource potential of various regions as well as opportunities for enhancing
value addition through the development of micro, small and medium enterprise sector
To develop an up-to-date register and data on all industrial and commercial enterprises in
the regions as input for spatial distribution of industries
To ensure price stability for essential consumer goods through monitoring of price trends
Budget Sub-Program Description
The sub-program is responsible for the collection and maintenance of data and the provision of
information on resource potential, and activities of industries and commercial enterprises in the
regions.
The key operations are:








Explaining Government’s trade and industry policies to prospective investors and other
stakeholders and projecting these policies in the regions
Assessing the impact of Ministry’s policies and programs on the operations of businesses
in the regions and providing appropriate feedback
Studying other sector programs in the region and assessing their implications for trade and
industry and inform the sector Minister.
Maintaining up-to-date data on all industrial and commercial enterprises
Conducting monitoring visits to all industrial and commercial establishments in the region
and submitting monthly reports on the state of their operations
Representing the Ministry in the region at meetings that require the Ministry’s inputs and
contributions
Preparation and submission of quarterly and annual reports on all activities in the region.
Ensuring regional components of programs relating to the industrial and trade sectors as
well as Private Sector Development are effectively and efficiently implemented
Ministry of Trade and Industry
September 2012
Page 73
3.
Budget Sub-Program Results Statement
The following output indicators are the means by which the Ministry measures the
performance of this sub-program. The table indicates the main outputs and an indicator for
each. Where past data has been collected this is presented. The projections are the Ministry’s
estimate of future performance
Past
Main Outputs
Identification of
potential resources in
the region
Maintenance and
update of industrial
and commercial data
Price trend of selected
essential consumer
goods monitored in 3
District markets
Enforcement and
compliance of trade
and investment laws
intensified
Performance of
selected industries
monitored and
evaluated
Quality and credible
international and
domestic trade and
industrial data
available to
stakeholders
4 industrial crops
promoted, monitored
and evaluated
Undertake industrial
survey on
manufacturing
activities in selected
districts
Industrial/commercial
establishments
monitored
Budget
Projections
Output Indicator
2009
2010
2011
2012
2013
2014
Annual update of
resource register
-
-
-
1
1
1
Quarterly update
of data base
-
-
-
4
4
4
Monthly Trend
Reports
8
10
12
12
12
12
Status Report
-
-
-
4
4
4
Performance
Report
-
-
-
4
4
4
Publications on
trade and
industrial data
-
-
-
1
1
1
Monitoring
Reports
-
-
-
4
4
4
Survey Report
-
-
-
4
4
4
Number of Visits
-
-
-
3
3
3
Ministry of Trade and Industry
September 2012
Page 74
4.
Budget Sub-Program Operations and Projects
The table lists the main Operations and Projects to be undertaken by the
sub- program.
Operations
Projects (Investment)
Pursue rigorous and aggressive investment promotion
activities
No Projects
Creating the platform for local businesses to participate
in external fairs
Strengthen trade at the regional and district levels
Create awareness of the existence of trade potentials of
the regions and districts.
To sensitize the regional and district assemblies to
adopt the model market concept
Create awareness on the PPP concept
Develop programs to promote made in Ghana products.
Organise trade and industry fora to obtain views of the
private sector on government policies.
Organise breakfast meetings for private sector to
dialogue with the public sector on national issues
Ministry of Trade and Industry
September 2012
Page 75
5.
Budget Sub-Program Summary: Expenditure by Economic Classification
2010
Expenditure by Economic
Classification
Actual
2011
Budget
Est.
Outturn
Current Expenditure
21 Compensation of Employees
22 Use of Goods and Services
25 Subsidies
26 Grants
27 Social Benefits
28 Other Expenses
Capital Expenditure
31 Non-Financial Assets
Total Expenditure
Ministry of Trade and Industry
September 2012
2012
2013
2014
Budget
Indicative
Indicative
GH₵
GH₵
GH₵
110,000
-
110,000
-
111,100
-
110,000
110,000
111,100
Page 76
BUDGET SUB-PROGRAM SUMMARY
PROGRAM 4: Trade and Industry Promotion
SUB-PROGRAM SP 4.2: Foreign Trade Services
1.
Budget Sub-Program Objectives




2.
Ensure that Ghana and the entire citizenry obtain the best deals in market access, bilateral,
regional and multilateral trade and investment agreements
Provide critical and quality market intelligence information on trade and investment for the
country
Provide effective foreign market support for exporters, importers and investors
Project the country in the area of Commercial Diplomacy
Budget Sub-Program Description
The main area of operation is to co-ordinate economic relations with the International
Community in Bilateral and Multilateral domains. The Trade Missions also encourage foreign
investment, foreign assistance and stimulate trade and exports development.
The Missions major operations are to:







Promote Foreign investment through organization of fora, seminars, exhibitions etc.
Strengthen Bilateral and regional economic relations with other countries through
meetings, seminars, roundtable discussions.
Maintain economic relations with international organizations such as the World Trade
Organization (WTO), UNCTAD, International Trade Centre (ITC), European Union, the
Commonwealth etc
Promote exports and investment in targeted countries
Facilitate business on behalf of Ghanaian companies.
Provide a substantial footprint for Ghanaian business to access markets globally
Secure and expand Ghana's International market access, while improving our targeted
services for Ghanaian business. Through negotiations, business seminars and trade shows
Ministry of Trade and Industry
September 2012
Page 77





Promote International Trade and commerce through initiatives such as negotiation of
agreements to open and/or expand markets and
Facilitate of two-way trade and investment and encourages innovation through
international partnerships and science and technology (S&T);
Organise networking events with guests from local industry multipliers including
Chambers of Commerce, associations and business councils that are influential in the
business community.
Organise briefings and roundtables with the business community on local business
practices and opportunities.
Enhance and promote trade and investment relations
Ministry of Trade and Industry
September 2012
Page 78
3.
Budget Sub-Program Results Statement
The following output indicators are the means by which the Ministry measures the
performance of this sub-program. The table indicates the main outputs and an indicator for
each. Where past data has been collected this is presented. The projections are the Ministry’s
estimate of future performance.
Main Outputs
Participation in
Negotiation of
International
Trade,
Investments
agreements and
treaties
Participation in
Bilateral,
Regional and
Multilateral
Trade
Negotiations and
implementation
of protocols
Output Indicator
Past
Budget
Projections
2009
2010
2011
2012
2013
2014
4.9
20.58
27.30
31.15
35.24
38.50
-
-
-
3
4
4
15
15
15
15
15
15
Number of
meetings/
negotiation
attended
-
-
-
6
6
6
Promotion and
investment Reports
-
-
-
4
4
4
10
10
10
10
10
10
15
15
15
15
15
15
-
-
-
4
4
4
Percentage
increase in NTEs
Number of
meetings/
negotiation
attended
Number of
Reports
Promotion of
investment in the
industrial sector
from targeted
countries
Number of
promotional events
Number of events
and promotion
activities
Promotion and
Facilitation of
market access for
Ghanaian Exports Report on
promotional
activities
undertaken
Ministry of Trade and Industry
September 2012
Page 79
4.
Budget Sub-Program Operations and Projects
The table lists the main Operations and Projects to be undertaken by the
sub- program.
Operations
Projects (Investment)
Promote Ghana's interest abroad
Purchase vehicle for the Mission
Establish 3 Trade Offices (South Africa, China and
Brazil)
Purchase of 6 vehicle
Identify and promote investment opportunities to new
and existing investors
Purchase office equipment for new offices
Identify joint venture partners for Ghana businesses
Organise visits and meetings between potential
investors Ghana businesses
Facilitate investors in obtaining of approvals, permits,
grants, registration and other regulatory authorisation
licences
Provide an after-care service to investors
Providing economic and trade statistics and research to
sustain and enhance competitiveness
Organising inward and outward investment missions
Organising trade fairs, exhibitions and missions
Operating a resource centre with internet facilities,
periodicals, journals and other relevant information
materials for the business community
Make recommendations to the Government on changes
in the statutory and administrative framework affecting
the investment and export climate
Ministry of Trade and Industry
September 2012
Page 80
5.
Budget Sub-Program Summary: Expenditure by Economic Classification
2010
Expenditure by Economic
Classification
Actual
2011
Budget
Est.
Outturn
Current Expenditure
21 Compensation of Employees
22 Use of Goods and Services
25 Subsidies
26 Grants
27 Social Benefits
28 Other Expenses
Capital Expenditure
31 Non-Financial Assets
Total Expenditure
Ministry of Trade and Industry
September 2012
2012
2013
2014
Budget
Indicative
Indicative
GH₵
GH₵
GH₵
400,000
-
400,000
-
404,000
-
90,000
490,000
90,000
490,000
90,900
494,900
Page 81
BUDGET PROGRAM SUMMARY
PROGRAM 5: Standardization and Conformity Assessment
1.
Budget Program Objectives




2.
To develop standards and quality systems to meet production requirements for Local and
International Markets
To promote the application of Science, Technology and Innovation in all sectors of the
Economy
To ensure the health, safety and economic interest of consumers
To improve private sector competitiveness domestically and globally
Budget Program Description
The Ghana Standards Authority (GSA) is the statutory body responsible for the National
Quality Infrastructure including Standardization, Metrology and Conformity Assessment
(Testing, Inspection and Certification).
Metrology
It involves the inspection, verification and calibration of weights, measures, weighing and
measuring instruments and equipment.
Standards
It involves the development and dissemination of relevant National Standards and related
subjects in collaboration with stakeholders.
Conformity Assessment
It refers to activities of the Authority that are under taken to assess conformance of a product
or service to the requirements of applicable standard(s). It comprises of Inspection, Testing
and Certification operations.
Funding of the program is mainly through Government of Ghana (GOG) Budget and Internally
Generated Funds (IGF).
Ministry of Trade and Industry
September 2012
Page 82
Clients of this program are:
Regulatory Authorities, Ministries, Departments and Agencies (MDAs), Manufacturers,
Importers, Exporter, Security Agencies, Medical Institutions, Service Providers, Research
Organizations, Academia and Consumers.
The total staff strength is four hundred and eleven (411) as at the end of June 2012. This is
made up of two hundred and ninety three (293) permanent staff and one hundred and eighteen
(118) non-permanent Staff (Contract staff, National Youth Employment Personnel and
National Service Personnel).
The key issues/challenges for the program are as follows:
Inadequate staff - The Authority’s aim of promoting standardisation at the grassroots requires
additional staff to man the existing and newly created Regional Offices to ensure effectiveness
Poor appreciation of Standards- Most of our Stakeholders do not appreciate Standards and
as such do not comply with the requirements of applicable Standards
Lack of a National Quality Infrastructure Policy - The absence of a National Quality
infrastructure policy has led to confusion in the Nation’s quality management with an adverse
effect on the Authority’s operations. Duplication of mandates and functions is discouraging the
effective cooperation between the Authority as a Standards Body and some selected
Regulatory Agencies in Ghana.
Delay in the Review of Standards Decree, 1973 (NRCD 173) and Weights and Measures
Decree (NRC 326, 1975) - The delay in the review of the Standards Decree 1973, (NRCD
173) and the Weights and Measures Decree (NRC 326, 1975) is one of the challenges being
faced by the Authority. The review is to address the constraints adversely affecting the
Authority’s operations. A number of stakeholders’ fora were held to discuss the draft Decree
but it is yet to be presented to Parliament for consideration. It is expected that necessary action
on the review will be taken and the new Standards Bill passed.
Ministry of Trade and Industry
September 2012
Page 83
3.
Budget Program Summary : Expenditure by Sub-Program, Economic
Classification and Projects
Program 5: Standardization and Conformity Assessment
2010
Expenditure By Budget SubProgram
Actual
2011
Budget
Est.
Outturn
BSP1: Metrology
BSP2: Standards
BSP3: Conformity Assessment
Total Expenditure
2010
Expenditure by Economic
Classification
Actual
2011
Budget
Expenditure by Projects
2010
Actual
2011
Budget
Est.
Outturn
2014
Budget
Indicative
Indicative
GH₵
GH₵
GH₵
909,018
268,359
16,243,725
17,421,102
2013
918,108
271,043
16,406,718
17,595,869
2014
Budget
Indicative
Indicative
GH₵
GH₵
GH₵
5,188,846
151,900
332,216
5,188,296
151,900
332,216
5,240,735
153,419
335,538
11,748,690
17,421,652
2012
Budget
11,748,690
17,421,102
2013
Indicative
11,866,177
17,595,869
2014
Indicative
GH₵
GH₵
GH₵
Completion of second phase of
Administration block
Furnish the completed
Administration Block
Construct Standards Training School
Procure Office Equipment
Replace 5 disposed pick-ups
Replace 2 disposed saloon cars
Maintain 2 accredited Testing
Laboratories
Procure laboratory equipment
Ministry of Trade and Industry
2013
909,018
268,359
16,244,275
17,421,652
2012
Est.
Outturn
Current Expenditure
21 Compensation of Employees
22 Use of Goods and Services
25 Subsidies
26 Grants
27 Social Benefits
28 Other Expenses
Capital Expenditure
31 Non-Financial Assets
Total Expenditure
2012
September 2012
600,000
600,000
606,000
350,000
7,500,000
50,000
235,000
95,000
350,000
7,500,000
50,000
235,000
95,000
353,500
7,575,000
50,500
237,350
95,950
1,950
100,000
1,950
100,000
1,970
101,000
Page 84
Refurbish 3 Toxicology Laboratories
Refurbish 1 Cosmetics Laboratory
Accredit the Mycotoxin Laboratory
Accredit the Metallic Contaminant
Laboratory
Procure laboratory equipment
Accredit Volume Laboratory
Accredit Density Laboratory
Accredit Viscosity Laboratory
Accredit Dimensional Laboratory
Construct Aflao Office
Construct Takoradi Office Complex
Construct Kumasi Office Complex
Maintain the Accreditation of the
Pesticide Residue Laboratory
Maintain the Accreditation of the
Pesticide Residue Laboratory
Maintain Mass Accreted Laboratory
Maintain Pressure Accreted
Laboratory
Maintain Temperature Accreted
Laboratory
Total Expenditure
Ministry of Trade and Industry
142,500
47,500
28,400
142,500
47,500
28,400
143,925
47,975
28,684
21,840
100,000
21,700
21,700
21,700
21,700
550,000
900,000
900,000
21,840
100,000
21,700
21,700
21,700
21,700
550,000
900,000
900,000
22,058
101,000
21,917
21,917
21,917
21,917
555,500
909,000
909,000
980
980
990
12,580
12,580
12,580
12,580
12,706
12,706
12,580
12,580
12,706
980
980
990
11,748,690
11,748,690
11,866,177
September 2012
Page 85
BUDGET SUB-PROGRAM SUMMARY
PROGRAM 5: Standardization and Conformity Assessment
SUB-PROGRAM SP 5.1: Metrology
1.
Budget Sub-Program Objectives


2.
Promote the application of Science, Technology and Innovation in all sectors of the
Economy
Ensure the health, safety and economic interest of consumers
Budget Sub-Program Description
Metrology is the science of measurement and it involves the inspection, verification and
calibration of weights, measures, weighing and measuring instruments and equipment
Ministry of Trade and Industry
September 2012
Page 86
3.
Budget Sub-Program Results Statement
The following output indicators are the means by which the Ministry measures the
performance of this sub-program. The table indicates the main outputs and an indicator for
each. Where past data has been collected this is presented. The projections are the Ministry’s
estimate of future performance
Past
Main Outputs
Weighing and
Measuring
devices Verified
Weighing and
Measuring
instruments
calibrated
Weighing and
Measuring
devices
randomly
inspected
Standard
Weighing Scales
promoted
Budget
Projections
Output Indicator
2009
2010
2011
2012
2013
2014
Number of
devices verified
39,282
42,056
44,863
54,900
56,990
63,830
Number of
instruments
calibrated
5,884
5,769
7,014
8,550
8,748
9,800
Number of
devices
inspected.
1,612
2,663
1,279
3,600
3,968
4,445
Number of
promotional
activity
conducted
-
-
-
4
29
33
Ministry of Trade and Industry
September 2012
Page 87
4.
Budget Sub-Program Operations and Projects
The table lists the main Operations and Projects to be undertaken by the
sub- program.
Operations
Projects (Investment)
Weighing and Measuring devices verified
Refurbishment of Laboratories
Verify Cocoa weighing scales and test weights
Procurement of Laboratory equipment and reference
standards
Verify Motorized pumps and accessories
Procurement of Vehicles
Verify Trading scales
Calibration of primary standards
Verify Weighbridges
Weighing and Measuring devices calibrated
Receive and calibrate Weighing and measuring
instruments
Random inspection of weighing and measuring
devices/instruments conducted.
Select and inspect 3,600 trading devices throughout the
Country.
Standard Weighing Scales promoted
Promote the use of weighing scales
Calibration of Primary Standards
Select and inspect 3,600 trading devices throughout the
Country.
Standard Weighing Scales promoted
Ministry of Trade and Industry
September 2012
Page 88
5.
Budget Sub-Program Summary: Expenditure by Economic Classification
2010
Expenditure by Economic
Classification
Actual
2011
Budget
Est.
Outturn
Current Expenditure
21 Compensation of Employees
22 Use of Goods and Services
25 Subsidies
26 Grants
27 Social Benefits
28 Other Expenses
Capital Expenditure
31 Non-Financial Assets
Total Expenditure
Ministry of Trade and Industry
September 2012
2012
2013
2014
Budget
Indicative
Indicative
GH₵
GH₵
GH₵
682,638
10,500
2,940
682,638
10,500
2,940
689,464
10,605
2,969
212,940
909,018
212,940
909,018
215,069
918,108
Page 89
BUDGET SUB-PROGRAM SUMMARY
PROGRAM 5: Standardization and Conformity Assessment
SUB-PROGRAM SP 5.2: Standards
1.
Budget Sub-Program Objectives


2.
To develop standards and quality systems to meet production requirements for Local and
International Markets
To promote the application of Science, Technology and Innovation in all sectors of the
Economy
Budget Sub-Program Description
This sub-program covers standards development and dissemination: It involves the
development of relevant National Standards in collaboration with stakeholders and the
dissemination of Standards and related subjects.
Ministry of Trade and Industry
September 2012
Page 90
3.
Budget Sub-Program Results Statement
The following output indicators are the means by which the Ministry measures the
performance of this sub-program. The table indicates the main outputs and an indicator for
each. Where past data has been collected this is presented. The projections are the Ministry’s
estimate of future performance.
Main Outputs
Output
Indicator
Standards
Number of
developed/Reviewed/adopted Standards
Past
Budget
Projections
2009
2010
2011
2012
2013
2014
289
557
210
157
65
75
Standards promoted
/dissemination
Number of
Standards
promoted/
dissemination
21
-
37
30
45
50
Standards sold
Number of
Standards sold
589
770
1,587
1,000
1,000
1,120
Standards Harmonization
Number of
Harmonised
Standards
-
-
-
2
2
3
Ministry of Trade and Industry
September 2012
Page 91
4.
Budget Sub-Program Operations and Projects
The table lists the main Operations and Projects to be undertaken by the
sub- program.
Operations
Projects (Investment)
Standards Development,
Procurement of Office equipment
Prepare working draft documents
Procurement of vehicle
Organize Technical Committee meetings
Send Final draft document for Public comments
Receive public comments and finalized documents for
gazetting
Standards Promotion/dissemination
Identify relevant Standards
Develop promotional plans
Hold stakeholders meeting
Advertise/ Publish Standards
Standards sold
Sale of Standards
Standards Harmonization
Identify relevant standards with sub-regional
Standards setting bodies
Put in place a committee to harmonize the
Standards
Ministry of Trade and Industry
September 2012
Page 92
5.
Budget Sub-Program Summary: Expenditure by Economic Classification
2010
Expenditure by Economic
Classification
Actual
2011
Budget
Est.
Outturn
Current Expenditure
21 Compensation of Employees
22 Use of Goods and Services
25 Subsidies
26 Grants
27 Social Benefits
28 Other Expenses
Capital Expenditure
31 Non-Financial Assets
Total Expenditure
Ministry of Trade and Industry
September 2012
2012
2013
2014
Budget
Indicative
Indicative
GH₵
GH₵
GH₵
262,359
6,000
-
262,359
6,000
-
264,983
6,060
-
268,359
268,359
271,043
Page 93
BUDGET SUB-PROGRAM SUMMARY
PROGRAM 5: Standardization and Conformity Assessment
SUB-PROGRAM SP 5.3: Conformity Assessment
1.
Budget Sub-Program Objectives
 To ensure the health, safety and economic interest of consumers.
 To improve private sector competitiveness domestically and globally
2.
Budget Sub-Program Description
Conformity Assessment: It refers to activities and systems that are under taken to assess
conformance of a product, service or system to the requirements of applicable standard(s). It
comprises of Inspection, Testing and Certification operations.
Inspection: Is the provision of inspection services to the Manufacturing and Service industry,
and Regulatory bodies to ensure consumer protection. It involves inspection of imported High
Risks Goods Products, Factories and Exports Consignments as well as Market Surveillance and
issuance of Health Certificate to Fish Exporters.
Product Testing: It is the technical examination and analysis of goods/products according to
specified procedure or test method. It involves the measurement of dimensions, chemical
composition, microbiological examination and physical characteristics of materials or
structures for Quality Evaluation
Certification: It is the provision of third party assurance for Products and Systems to promote
the Manufacturing and Service Industries. It involves Product Certification, Management
Systems Certification, Export Certification and other industrial support activities.
Capacity building and Awareness creation/publicity: This involves the co-ordination of the
activities of the Scientific/Technical Divisions of the Authority in the areas of continuous
public education, training/ workshops/seminars/lectures, refurbishment of the Laboratories,
procurement of Chemicals, glassware, reagents and Equipment and storage.
Ministry of Trade and Industry
September 2012
Page 94
3.
Budget Sub-Program Results Statement
The following output indicators are the means by which the Ministry measures the
performance of this sub-program. The table indicates the main outputs and an indicator for
each. Where past data has been collected this is presented. The projections are the Ministry’s
estimate of future performance.
Main Outputs
Product samples
tested and analysed
Accredited Testing
Laboratories
maintained
Imported High Risk
Goods inspected
Health Certificates
issued to exporters
Output Indicator
Number of
Analyses
conducted
Number of
Accredited
Laboratories
maintained
Number of
inspections
conducted
Number of
Certificates
issued.
2009
Past
2010
2011
Budget
2012
Projections
2013
2014
14,019
16,341
19,020
23,114
24,338
27,260
2
2
2
3
4
5
64,527
69,222
84,970
95,040
114,050
127,736
1,644
1,260
1,235
1,800
1,200
1,340
Fishing Vessels,
establishments and
consignments
inspected
Number of
inspections
conducted
692
719
732
400
720
810
Factory Inspections
conducted
Number of
factories
inspected.
600
587
562
650
800
900
Market Surveillance
Number of
surveillance
conducted
61
79
70
103
124
140
Export
Consignments
Inspected
Number of
inspections
conducted.
1,91
1,92
318
700
414
470
Locally
Manufactured
Products certified
Number of
Certificates
Issued
602
498
539
543
1,090
1,220
Factory Audits
Number of
Factory Audits
conducted
39
-
78
50
100
110
1,337
1,357
1,589
1,572
1,600
1650
-
-
3
10
6
7
Export Certificates
issued
Systems Certified
Number of
Certificates
issued
Number of
certified
companies
Ministry of Trade and Industry
September 2012
Page 95
Training organised
for Industry
GSA Personnel
trained to build
capacity
Public awareness on
standardization and
GSB activities
promoted
International
Subscriptions and
other bills paid
Number of
Training
seminars/worksh
ops organized
11
10
18
35
27
30
Number of Staff
trained.
108
96
188
300
300
300
18
21
25
55
60
70
9
9
9
9
9
10
Number of
promotional
activities
organized
Number of
subscriptions and
bills paid.
Ministry of Trade and Industry
September 2012
Page 96
4.
Budget Sub-Program Operations and Projects
The table lists the main Operations and Projects to be undertaken by the
sub- program.
Operations
Imported High Risk Goods inspected
Projects (Investment)
Procurement of Vehicles
Inspection of Imported High Risk Goods
Procurement of Office equipment
Health Certificates issued to exporters
Issuance of Health Certificates to Fish exporters
Construct Destination Inspection Offices
Refurbishment of Laboratories
Fishing Vessels, Establishments and Consignments
inspected.
Procurement of Laboratory equipment
Inspect registered frozen vessel
Accreditation of refurbished laboratories
Inspect registered fish establishments
Procurement of chemicals and reagents
Inspect Fish Consignments meant for export
Establishment ISO 14001 Environmental
Factory Inspection
Management System Certification Scheme
Conduct Factory Inspection
Projectors
Market Surveillance conducted
Laptop Computers
Conduct market surveillance
Construction of Training School
Exports consignments inspected
Furnishing of Training School
Inspect Yam consignment meant for export
Construction of Regional Offices
Inspect other consignments meant for export
Testing
Furnishing of Regional offices
Refurbishment of Laboratories,
Product samples tested and analysed :
Refurbishment of Offices
Analysis of Food and Agricultural Samples
Procurement of Office equipment
Analysis of Drugs and Cosmetics samples
Procurement of Vehicles
Analysis of Material Science samples
Survey of level of awareness created
Analysis of Forensic samples
Analysis of Engineering samples
Analysis of Material Science Samples
Ministry of Trade and Industry
September 2012
Page 97
Microbiological Analysis
Accredited Testing Laboratories maintained
Maintenance of Accredited testing laboratories
Certification:
Locally manufactured products certified
Organize Certification Mark Committee meetings
Issue license to cover qualified products
Factory audit
Conduct Factory Audit of Certified Products
Export Certificates issued to exporters
Issue certificate to cover conforming product
Quality Management Systems of Companies certified
Conduct Systems Audit
Certify conforming companies.
Training for Industry organised
Identify training needs
Organise Quality Assurance training
workshops/seminars
Capacity building and Public Awareness creation:
GSA Personnel trained to build capacity
Identify training requirements
Train Staff locally in relevant areas
Train staff overseas in relevant areas
Public awareness on standardization and GSB activities
promoted
Design relevant promotional programmes
Publish brouches on the Authority’s activities and
standardization
Advertise programme in the print and electronic media
Organise sensitization workshops/seminars
International Subscriptions and other paid bill paid
Pay subscriptions
(ISO,ARSO,IEC,OIML,BPIM,AFRIMET,NEP)
Pay Insurance and Compensation
Pay utility bills
Ministry of Trade and Industry
September 2012
Page 98
5.
Budget Sub-Program Summary: Expenditure by Economic Classification
2010
Expenditure by Economic
Classification
Current Expenditure
21 Compensation of Employees
22 Use of Goods and Services
25 Subsidies
26 Grants
27 Social Benefits
28 Other Expenses
Capital Expenditure
31 Non-Financial Assets
Total Expenditure
Ministry of Trade and Industry
Actual
2011
Budget
2012
2013
2014
Budget
Indicative
Indicative
GH₵
GH₵
GH₵
4,243,849
135,400
329,276
4,243,299
135,400
329,276
4,286,288
136,754
332,569
11,535,750
16,244,275
11,535,750
16,243,725
11,651,108
16,406,718
Est.
Outturn
September 2012
Page 99
BUDGET PROGRAM SUMMARY
PROGRAM 6: Industrial Development
1.
Budget Program Objectives



2.
Ensure the application of science, technology and innovation in industry.
Strengthen firms competency and capacity to operate effectively and efficiently
Accelerate the development of strategic sectors
Budget Program Description
The program seeks to improve local production and distribution of goods, cost-competitive and
quality raw materials and other inputs: increase local content in the manufacturing sector;
promote sustainable industrial development, economic growth and transformation through
harmonized coordination within government and solid partnership with the private sector and
focus, inter-alia on the following:

Develop Resource-based Agro-Industries for value added products; and facilitate the
provision of logistics and other infrastructural facilities which provide a more favourable
atmosphere for industrial progress and agricultural production. The areas of focus are
commercial farming of oil palm, soya beans, cotton, tomatoes, Citrus, sorghum, cassava
and mango, mobilization of farmer-based organization and supply of inputs

Promote Science, Technology, and Innovation; Technical and Vocational education and
training to produce a workforce with skills and competences for jobs in industry. The
Ministry is collaborating with AGI, educational and training institutions in order to review
their curriculum and also carry out training programs for manufacturing industries

Promote sustainable production and consumption by influencing suppliers and customers
to produce and consume sustainably. Identify the waste in the area of production e.g. the
use of electricity, raw material and other resource in order to help them improve
production and competitiveness

Create support systems for sustainable Small, Medium and Large industries development.
Facilitate their access to credit, and efficient use of recourses and add value to products by
making use of their waste products especially citrus, oil palm, soya beans and the petrochemical and develop by products from them.
Ministry of Trade and Industry
September 2012
Page 100

Intensify the development of industries with focus in new areas of services, technological
enhancement; higher value added products and activities, innovative and creative human
capital and integrating Ghanaian industries and services into the regional and global
networks and supply chains. Sub-contracting in the mining sector by identifying
companies to produces parts locally to support the mining firms.

Support distressed but viable industries by identifying their needs in the following areas
and support them by providing them with the needed assistance
o Skills
o Technology
o Managerial
o Financial
o Access to market
Ghana’s manufacturing sector is characterised by low levels of entrepreneurial and
managerial skills. To enhance leadership and management skills and capacity in the
manufacturing sector, existing academic and training institutions earmarked to be
supported to significantly increase the delivery of entrepreneurship and management
training programs to SMEs in the manufacturing sector.
Entrepreneurial Skills Training Programs will be implemented for new entrants and
existing operators in the manufacturing sector to enhance personal traits that are essential
for starting and building industries. The training will cover the following areas: how to
build a successful business, such as self-motivation, innovative thinking, and risk-taking,
perseverance, planning and networking. Management Skills Training Programs will also
be organized for managers and supervisors of manufacturing firms in essential areas such
production management and supervision, people management, financial literacy and
product marketing.
Manufacturing companies also will be able to apply for support in the form of matching
funds from MSME Project to increase the number of staff participating in such training
programs.
The program will implement combine cost and risk reduction measures to increase
competition in the banking sector and its supply of loanable funds to the private sector.
This will be done in collaboration with Ministry of finance to review their criteria used to
give loans to the Manufacturing Sector. These measures are intended to address the
current high cost of borrowing, which tends to restrict the scope for growth of most SMEs
in the manufacturing sector by limiting their access to credit and raising the cost of doing
business.
Ministry of Trade and Industry
September 2012
Page 101
Access to land is largely determined by traditional practices, resulting in fragmented and
inefficient system of land administration. The Ministry through this program will
collaborate with Land Administration Project (LAP) to support the development of
effective land administration at national, regional and district levels to facilitate easy
access to and security of land. This will help ease the challenge of land acquisition for
investment purposes, including manufacturing.
In addition to expediting the implementation of the Land Administration Project (LAP),
improved access to land for industrial development will be achieved through the
establishment of Industrial Estates, enforcement of zoning regulations and development of
a Land Banks Website to publicize lands available for industrial and agricultural purposes.
The Ministry provides financial resources through the budget to acquire such lands and
develop them as industrial lands and allocate it to investors e.g. Tema Free Zone.
The program operation would be carried out by four divisions namely, Small, Medium and
Technology Division, Manufacturing Division, Value Chain and Logistics Division and
Standards and is funded through GOG and IGF
The beneficiaries of the program are: Industrialists, investors, and entrepreneurs in the
manufacturing sector; workers students and graduates of academic and educational
institutions; job seekers, civil society academia and R& D institutions, raw material
producers (famers, sub-contractors), consumers, utilities providers, transporters (land, sea
and air), exporters, marketers among others.
The number of manufacturing industries that are covered under the program is 3917. The
break-down is as follows: manufacturing firms with size ranging from 10- 99 workers and
above 100 workers are 3656 and 261 respectively.
The challenges that may impact on the program are:
 private sector buying into the program it would require sensitizing them;
 private sector incorporating science and technology in their programs;
 make farmers produce agro raw material at competitive price; availability of agrobased raw material through commercial production;
 Retooling of manufacturing firms by installing the state of the art plant/equipment and
technology.
Ministry of Trade and Industry
September 2012
Page 102
3.
Budget Program Results Statement
The following output indicators are the means by which the Ministry measures the performance of this
program. The table indicates the main outputs and indicator for each. Where past data has been
collected this is presented. The projections are the Ministry’s estimate of future performance.
Main
Outputs
Output
Indicator
Past
2009
SME
promotion and
development
project with
JICA improved
Primary
grading,
processing and
storage
promoted to
increase value
addition and
export earnings
Plant
production of
strategic
manufacturing
industries
increased
(fish products,
fruits and
vegetable, salt,
plastic product,
textiles
pharmaceutical
s, cosmetics,
steel,
aluminum and
non-metallic
mineral)
2010
Budget
Projections
2011
2012
2013
2014
120,000
mt of
palm oil
(crude)
120,00
0 mt of
palm
oil(cru
de)
Increase in
output of the
strategic subsector (palm
oil)
120,000mt
of palm
oil (crude)
120,000 mt
of palm
oil(crude)
120,000 mt
of palm oil
(crude)
120,000
mt of
palm oil
(crude)
increase in
export
earnings
from the
strategic subsectors (Oil
Palm)
9.2m USD
9.8m USD
20.3m
USD
20.3m
USD
9.2m
USD
9.8m
USD
110.45m
USD
(canned
tuna)
11.42m
USD
(canned
tuna)
220.7m
USD
(canned
tuna)
320m
USD
(canned
tuna)
20.62 m
USD
(fruits &
vegetable)
29.86m
USD (fruits
&
vegetable)
42.07 m
USD
(Fruits and
vegetable)
1.61m
USD
(salts)
3.65m USD
(salt)
50.5 m
USD (salt)
350.7m
USD
(canne
d tuna)
50 m
USD
(Fruits
and
vegeta
ble)
50.5 m
USD
(salt)
86.42m
USD
(plastics)
130.99 m
USD
(plastics)
300m
USD
(canned
tuna)
45 m
USD
(fruits
&
vegetabl
e)
1.61m
USD
(salts)
134m
USD
(plastics
)
20.62m
USD
(pharmace
utical)
22.77 m
USD
(textiles)
50.05m
USD
(textiles)
0.35m
USD
(pharmace
utical)
0.75m USD
(pharmaceu
ticals)
1.56m
USD
(pharmace
uticals)
increase in
export
earnings
from the
strategic subsector
Ministry of Trade and Industry
93.82m
USD
(plastics)
September 2012
52m
USD
(pharma
ceutical
)
1.80m
USD
(pharma
ceutical
)
48.86m
USD
(fruits &
vegetable
)
3.65m
USD
(salt)
140m
USD
(plastics)
145 m
USD
(plastic
s)
57 m
USD
(textiles)
60m
USD
(textile
s)
1.85m
USD
(pharmac
euticals)
2m
USD
(pharm
aceutic
als)
Page 103
Science ,
technology &
innovation
(ST& I) base
available to
Ghanaian
industrial firms
strengthened
Science and
technology
related element
integrated into
management
training
Application of
science,
technology and
innovation in
the
manufacturing
sector
promoted
Number of
manufacturin
g firms that
are provided
services by
research
institutions
and
universities
increases by
50%
annually
10
management
training
institutions
integrate
science and
technology
into
management
training
courses by
2015
200
manufacturin
g firms
report
increased use
of science,
technology
and
innovation
from
Ministry of Trade and Industry
23.25m
(cosmetics
)
21m USD
(cosmetics)
25.24m
USD
(cosmetics
)
11.31m
USD (iron
& steel)
7.88m USD
(iron &
steel)
11.48m
USD (iron
& steel)
16.9m
USD
(aluminu
m)
11.16m
USD
(aluminum)
22.96m
USD
(aluminum
)
23.25m
USD
(nonmetallic)
4.25m USD
(nonmetallic)
158.32m
USD
(nonmetallic)
-
-
-
-
10
15
-
-
-
-
2
2
-
-
-
-
50
70
September 2012
30m
(cosmet
ics)
11.00m
USD
(iron &
steel)
25m
USD
(alumin
um)
158m
USD
(nonmetallic
)
35m
USD
(cosmetic
s)
11.88m
USD
(iron &
steel)
26.00m
USD
(aluminu
m)
158m
USD
(nonmetallic)
40m
USD
(cosme
tics)
12m
USD
(iron &
steel)
30m
USD
(alumi
num)
158.32
m USD
(nonmetalli
c)
Page 104
Entrepreneuria
l and
management
skills to meet
needs of the
manufacturing
sector
improved
Technical
skills in
specialized
areas improved
Availability
and supply of
local
agricultural
raw material
and inputs
improved
Availability
and supply of
nonagricultural
raw material
improved
5 Large
Mining
companies
encouraged to
offer vendor
development
programs to
sub-contractors
Capacity
building of 10
manufacturing
industries
research
institutions
and
universities
by 2015
Percentage
increase in
entrepreneuri
al and
management
training
programs
and advisory
service
offered to
manufacturin
g firms
Industrial
associations
participated
in training
programs
Increase in
output of
vegetable
seed oil
production
Percentage
increase in
the volume
of
investment in
iron and
steel, clinker
Percentage
increases in
resources
(capital and
human
employed by
subcontracting
companies
Percentage
increase in
turnover of
subcontracting
companies
Ministry of Trade and Industry
-
-
-
-
20
20
-
-
-
-
2
2
-
1500mt of
soya
beans/grou
ndnuts
800mt of
soya
beans/
groundnuts
9,000mt
of soya
bean/gr
ound
nuts
10,000mt
of soya
bean/grou
nd nuts
15,000
mt
-
-
-
-
20
20
-
-
-
-
10
10
-
-
-
-
20
30
September 2012
Page 105
4.
Budget Program Operations and Projects.
The table lists the main Operation and Projects to be undertaken by the program
Operations
Projects (Investment)
Analyze basic building blocks of the National
Quality Infrastructure
Upgrading and retooling of laboratories and
workshops of CSRI-IIR and academia
Organize training of trainers and SMEs
enhancement in 3 regions
Construction of industrial estates
Assess Counterpart Fund for MSME by Dec. 2012
Establish Technology Innovation Centre for
capital goods with the state of the art
plant/equipment and technology to produce parts
and components for industrial machines to meet
global competitiveness
Implement MSME project by 2012
Provision of ICT Hardware and Software for
researchers, managers and Supervisors
Assess Counterpart Fund for REP III by Dec. 2012
2 Cross Country vehicle for monitoring
Implement REP III project by Dec. 2012
Implement TRAQUE to ensure quality standard for
industry by Dec. 2012
Recapitalize the Northern Star, Volta Star, Ayensu
Starch companies
Establish salt bank
Organize workshops in selected regions to improve
productivity of SMEs
Facilitate retooling of two industries
Collaborate with Global Alliance for improved
Nutrition (GAIN) to develop schemes to ensure
steady supply of Iodine for Iodization
Train SMEs in packaging in collaboration with
NBSSI/Ghana Institute of Packaging
Promote awareness of National Quality
infrastructure and TRF in Manufacturing and
service sector
Ministry of Trade and Industry
September 2012
Page 106
Assess and utilize Pooled Funds for Sekondi
Industrial Park
Establish a technical regulatory framework to
ensure domestic and imported products conform to
standards
Implement BAM by Dec. 2012
Establish and operate a Secretariat for Industrial
Sector Support Program
Encourage and attract investments in the agro
processing and manufacturing rather than
commercial operating investment
Organize 5 Sensitization workshops for salt
producers on the establishment of the importance of
salt bank
Implement one project under the District
Industrialization Program.
Review the existing salt iodization and
communication strategy with MOH
Train salt producers on best practices of salt
production for enhanced quality
Technology Audit to identify the potential relevant
research for the manufacturing sector
Analysis of the potential benefits to the
manufacturing sector of publicly funded science,
technology and innovation
Prepare joint cabinet memo for 1% of GDP for
science, technology and innovation to cover the
manufacturing sector
Assess infrastructural needs of other Craft Villages:
Ahwiaa, Bolga, Kpando (Fesi), Alloyi and Bompata
to determine the support needed
Procurement of a consulting firm to facilitate the
linkage between STI Institutions and Industry
Ministry of Trade and Industry
September 2012
Page 107
STI Institutions, Industry and consulting firm
implement the technology audit report
Monitor and evaluate the performance of the three
implementing institutions
Procure a consulting firm to conduct study to;
a.
Assess the current STI training capacity
and infrastructure in the public sector
b.
Identify capacity strengthen needs of
existing training institutions and examined the
justification for new institutions to meet the STI
skills requirement of industry
c.
Determine the required funding to
strengthen existing institutions and/or establish new
institutions to deliver STI training
Present the position paper to cabinet justifying and
requesting the strengthen STI Institution and/or the
establishment of new institutions
Establish knowledge transfer networks and for a
between Industry and STI Experts (researchers or
consultants);
a.
To raise the awareness of the key STI
issues facing Industry in their particular sector and
to facilitate the diffusion of solution to these issues
b.
To support the provision of increase market
intelligence on the sources of foreign technologies,
value for money and potential adaptability to local
conditions
Procure a consultant to implement the absorptive
capacity of firms
Procure a consultant to :
a.
Identify skill needs of owners and
managers of priority sub-sectors in the
manufacturing sector
Ministry of Trade and Industry
September 2012
Page 108
b.
Design training models and organize
training programs to address the identified training
needs
c.
Encourage managers in the sub-sector of
the manufacturing sector to provide the necessary
training for their own staff to meet their
entrepreneurial and managerial requirements
Monitor and evaluate performance of the trainees at
the firm level
Procure a consultant to:
a.
Identify the specialized areas in the priority
sub-sectors of the manufacturing sectors
b.
Identify skills gap in the specialized areas
c.
Identify the capacity strengthen needs of
the existing academic, technical and vocational
education and training institutes
d.
Strengthen the training institutions
e.
Identify training programs from bi-lateral
and multi-lateral organizations for the
manufacturing sectors
Roll-out the training programs both local and
foreign institutions
Identify crops for commercial cultivation to serve
as raw material base for agro-food manufacturing
industries
Liaise with Ministry of Food and Agriculture
(Department of Crop Services) farmers, R & D
Institutions, Agro-Industry Operators and financial
Organizations
Mobilize farmers and provide required support to
cultivate selected crops (improved varieties, agrochemicals, fertilizers
Identify non-agricultural raw materials and inputs
requirement of the priority sub-sector of the
manufacturing sector
Ministry of Trade and Industry
September 2012
Page 109
Develop data base on mineral deposit in
collaboration with relevant agencies
Liaise with GIPC and Minerals Commission to
attract investors in the exploration and mining of
mineral that are capital intensive
Facilitate the organization of Inter-Ministerial
Committee for Mining and processing iron ore
deposits into steel under PPP arrangement
Establish a platform to facilitate the exchange of
information on sub-contract opportunities and
capabilities in selected sectors
Procure a consultant to:

Identify and select specific industries for subcontracting opportunities
 Develop and implement modules for capacity
enhancement of industries to take advantage of
sub-contracting opportunities
 Develop special investment schemes to attract
investment that offer opportunities for subcontracting services
 Establish one-on-one business meetings
between large companies and sub-contractors
 Assist sub-contractors to prepare business plans
 Introduce STI in the operation of subcontractors to meet specifications of large
companies
Monitor and evaluate the production of
subcontractors
Special Financial Schemes are provided to assist
sub-contractors
Ministry of Trade and Industry
September 2012
Page 110
5.
Budget Program Summary : Expenditure by Program, Economic
Classification and Projects
Program 6: Industrial Development
2010
Expenditure by Economic
Classification
Actual
2011
Budget
Est.
Outturn
Current Expenditure
21 Compensation of Employees
22 Use of Goods and Services
25 Subsidies
26 Grants
27 Social Benefits
28 Other Expenses
Capital Expenditure
31 Non-Financial Assets
Total Expenditure
Expenditure by Projects
Establish and operate a Secretariat
for Industrial Sector Support
Program's (ISSP) by Dec., 2012.
Assess and Utilize Pooled Funds for
Sekondi Industrial Park
Recapitalise the Northern star, Volta
Star and the Ayensu Starch
Companies
Total Expenditure
Ministry of Trade and Industry
2010
Actual
2011
Budget
Est.
Outturn
2012
2013
2014
Budget
Indicative
Indicative
GH₵
GH₵
GH₵
23,936,000
-
23,936,000
-
24,175,360
-
61,001,244
84,937,244
2012
Budget
61,001,244
84,937,244
2013
Indicative
61,611,256
85,786,616
2014
Indicative
GH₵
GH₵
GH₵
7,220,000
7,220,000
7,292,200
53,751,244
53,751,244
54,288,756
30,000
61,001,244
30,000
61,001,244
30,300
61,611,256
September 2012
Page 111
PART C: FINANCIAL INFORMATION
Annexure 1: Summary of Expenditure by Program, Economic Classification and Funding Source
Ministry of Trade and Industry
September 2012
Page 112
Annexure 2: Expenditure by Program and Sub Program
Expenditure by Program and Sub Program
In GH¢
2010
Program / Sub Program
Actual
Ministry of Trade and Industry
2011
Budget
2012
Budget
Est. Outturn
2013
2014
forecast
forecast
0
0
0
157,520,459
157,091,136
158,568,595
0
0
0
9,307,756
9,400,833
9,400,833
0
0
0
9,307,756
9,400,833
9,400,833
0
0
0
3,672,886
3,572,886
3,608,615
1.1 Finance and Administration (Legal)
0
0
0
2,562,000
2,562,000
2,587,620
1.2 Human Resource Management
0
0
0
190,000
190,000
191,900
1.3 Policy planning Monitoring and Evalutaion
0
0
0
490,886
390,886
394,795
1.4 Statistics, Research and Communication
0
0
0
430,000
430,000
434,300
0
0
0
26,990,531
26,990,531
27,260,436
2.1 Domestic and International Trade Development and
Promotion
0
0
0
26,608,531
26,608,531
26,874,616
2.2 Export Development and Promotion
0
0
0
382,000
382,000
385,820
Business Development and Promotion
0
0
0
14,590,390
14,168,540
14,310,226
3.1 Technology Transfer, Research and Product Development
0
0
0
780,000
369,150
372,842
3.2 Micro and Small Business
0
0
0
806,000
806,000
814,060
3.3 Central Region Development
0
0
0
13,004,390
12,993,390
13,123,324
Trade and Industry Promotion
0
0
0
600,000
600,000
606,000
4.1 Regional Services
0
0
0
110,000
110,000
111,100
4.2 Foreign Trade Services
0
0
0
490,000
490,000
494,900
17,421,102
17,595,868
909,018
918,108
Management and Administration
Trade Development
Standardization and Conformity Assessment
5.1 Metrology
5.2 Standards
5.3 Conformity Assessment
Industrial Development
Grand Total
Ministry of Trade and Industry
0
0
0
0
0
0
0
0
0
0
0
0
17,421,652
909,018
268,359
16,244,275
0
0
0
0
0
0
0
September 2012
268,359
271,043
16,243,725
16,406,718
84,937,244
84,937,244
85,786,616
0
84,937,244
84,937,244
85,786,616
0
157,520,459
157,091,136
158,568,595
Page 113
Annexure 3: Expenditure by Program and Project
Expenditure by Program and Project
In GH¢
2010
Project / Program
Actual
2011
Budget
2012
Budget
Est. Outturn
2013
2014
forecast
forecast
Ministry of Trade and Industry
0
0
0
85,729,188
85,729,188
86,586,480
Management and Administration
0
0
0
1,210,000
1,210,000
1,222,100
Purchase Bus for Staff to improve prodcutivity
0
0
0
230,000
230,000
232,300
Manage the Ministry's properties
0
0
0
700,000
700,000
707,000
Renovate Office building and Kumasi Guest House
0
0
0
100,000
100,000
101,000
Review financial information of each spending entity
0
0
0
150,000
150,000
151,500
Produce a consolidated quarterly report comparing budget
execution and revenue collection to the estimates contained in
0
0
0
30,000
30,000
30,300
0
0
0
122,000
122,000
123,220
Support implementation of Private Sector Development strategy
(PSDS II)
0
0
0
70,000
70,000
70,700
Increase exports by 25% by Dec., 2012.
0
0
0
52,000
52,000
52,520
0
0
0
11,557,254
11,557,254
11,672,827
Purchase of one saloon and one pick Up vehicle
0
0
0
100,000
100,000
101,000
Complete on-going foundry buiding installed & commission
equipment by Dec. 2012
0
0
0
110,000
110,000
111,100
Purchase of (two) 2 Pick-Ups
0
0
0
90,000
90,000
90,900
Complete the construction and reconstruction of Bridges, Culverts
and maintenance of Feeder roads by June 2012
0
0
0
60,000
60,000
60,600
Complete the construction of Museum of Black History at Cape
Coast by June 2012
0
0
0
480,750
480,750
485,558
Complete the Construction of the Emergency Centre and a
Bunglow at Agona Swedru Hospital by May 2012
0
0
0
1,000
1,000
1,010
Compete the Construction of the Children's Library and Park at
Kasoa by June 2012
0
0
0
1,000
1,000
1,010
Complete the Construction of 57 Boreholes in the various MMDAs
by December 2012
0
0
0
1,000
1,000
1,010
Construct 50 Boreholes in the various MMDAs by December 2012
0
0
0
1,000
1,000
1,010
Complete reconstruction of Swedru Sports Stadium by May 2012
0
0
0
1,000
1,000
1,010
Complete the rehabilitation and expansion of Duakwa Town
Market by July 2012
0
0
0
1,000
1,000
1,010
Complete construction of Rest Stop at Esuehyia by July 2012
0
0
0
1,000
1,000
1,010
Complete the construction of Biriwa Market by May 2012
0
0
0
1,000
1,000
1,010
Complete the construction of 2 ICT Centres in 2 MMDAs by
September 2012.
0
0
0
1,000
1,000
1,010
Construction of 4 ICT Centres in 4 MMDAs by December 2012.
0
0
0
1,000
1,000
1,010
Complete construction of pavement at Mankessim Lorry Park and
Market Extension by August 2012
0
0
0
497,452
497,452
502,426
Complete the construction of 16 CHPS by October 2012
0
0
0
1,190,052
1,190,052
1,201,952
Trade Development
Business Development and Promotion
Ministry of Trade and Industry
September 2012
Page 114
Complete the construction of 20 CHPS by October 2012
0
0
0
1,800,000
1,800,000
1,818,000
Complete and refurbish Swedru Senior High School Assembly Hall
by May 2012
0
0
0
450,000
450,000
454,500
Construct Police Station and accommodation at Duakwa by
August 2012
0
0
0
400,000
400,000
404,000
Construct a Police Station at Gomoa Fetteh by December 2012
0
0
0
300,000
300,000
303,000
Complete and refurbish Breman Asikuma Community Centre by
September 2012
0
0
0
250,000
250,000
252,500
Expenditure by Program and Project
In GH¢
2010
Project / Program
Actual
2011
Budget
2012
Est. Outturn
Budget
2013
2014
forecast
forecast
Construct a market at Bisease by August 2012
0
0
0
450,000
450,000
454,500
Convert old structures into Community Nursing Schools at
Saltpond and Buadatta by October 2012
0
0
0
500,000
500,000
505,000
Acquire site and construct Pre-School Teacher Training College at
Gomoa Abura in partnership with GETfund and Ministry of
0
0
0
500,000
500,000
505,000
Establish a Community Communication Centre at Gomoa Dego
by May 2012
0
0
0
100,000
100,000
101,000
Acquire site and construct a National Park at Twifo Hemang by
October 2012
0
0
0
500,000
500,000
505,000
Rehabilitate and Construct 1km culverts and a bridge at
Anomabo by October 2012
0
0
0
220,000
220,000
222,200
Rehabilitate existing salt works by December 2012
0
0
0
500,000
500,000
505,000
Construct a 6-Unit classroom block at Enyan Maim Senior High
School by November 2012
0
0
0
300,000
300,000
303,000
Complete Nyakrom Senior High School Assembly Hall by
November 2012
0
0
0
250,000
250,000
252,500
Establish Eguafo Ancient Cave Settlement Project by October
2012
0
0
0
85,000
85,000
85,850
Construct Assin Fosu Police Station and Accommodation by
November 2012
0
0
0
400,000
400,000
404,000
Establish a Community Police Training Centre at Abura Dunkwa
by December 2012
0
0
0
500,000
500,000
505,000
Procure one Generator as power backup for CEDECOM
0
0
0
50,000
50,000
50,500
Construct 3 staff bungalows for CEDECOM by December 2012
0
0
0
540,000
540,000
545,400
Revamp CEDECOM Computer Learning Centre (CLC) to
generate sustainable income by June 2012
0
0
0
104,000
104,000
105,040
Revamp CEDECOM's teak plantations to generate sistainable
income by July 2012
0
0
0
20,000
20,000
20,200
Rehabilitation of structures constructed by CEDECOM at Brenu
Beach by May 2012
0
0
0
200,000
200,000
202,000
Procure two (2) coaches for tour operations and tourism
promotional activities in the Central Region by August 2012.
0
0
0
100,000
100,000
101,000
Establish one Salt Bank in the Region by July 2012
0
0
0
500,000
500,000
505,000
Trade and Industry Promotion
0
0
0
90,000
90,000
90,900
Purchase vehicle for the Mission
0
0
0
90,000
90,000
90,900
Standardization and Conformity Assessment
0
0
0
11,748,690
11,748,690
11,866,177
Completion of second phase of Administration block
0
0
0
600,000
600,000
606,000
Ministry of Trade and Industry
September 2012
Page 115
Furnish the completed Adminstration Block
0
0
0
350,000
350,000
353,500
Construct Standards Training School
0
0
0
7,500,000
7,500,000
7,575,000
Procure Office Equipment
0
0
0
50,000
50,000
50,500
Replace 5 disposed pick-ups
0
0
0
235,000
235,000
237,350
Replace 2 disposed saloon cars
0
0
0
95,000
95,000
95,950
Maintain 2 accredited Testing Laboratories
0
0
0
1,950
1,950
1,970
Procure laboratory equipment
0
0
0
100,000
100,000
101,000
Refurbish 3 Toxicology Laboratories
0
0
0
142,500
142,500
143,925
Refurbish 1 Cosmetics Laboratory
0
0
0
47,500
47,500
47,975
Accredite the Mycotoxin Laboratory
0
0
0
28,400
28,400
28,684
Expenditure by Program and Project
In GH¢
2010
Project / Program
Actual
2011
Budget
2012
Budget
Est. Outturn
2013
2014
forecast
forecast
Accredite the Metallic Contaminant Laboratory
0
0
0
21,840
21,840
22,058
Maintain the Accreditation of the Pesticide Residue Laboratory
0
0
0
980
980
990
Maintain the Accreditation of the Pesticide Residue Laboratory
0
0
0
12,580
12,580
12,706
Procure laboratory equipment
0
0
0
100,000
100,000
101,000
Accredite Volume Laboratory
0
0
0
21,700
21,700
21,917
Accredite Density Laboratory
0
0
0
21,700
21,700
21,917
Accredite Viscosity Laboratory
0
0
0
21,700
21,700
21,917
Accredite Dimensional Laboratory
0
0
0
21,700
21,700
21,917
Maintain Mass Accrdited Laboratory
0
0
0
12,580
12,580
12,706
Maintain Pressure Accrdited Laboratory
0
0
0
12,580
12,580
12,706
Maintain Temperature Accrdited Laboratory
0
0
0
980
980
990
Construct Aflao Office
0
0
0
550,000
550,000
555,500
Construct Takoradi Office Complex
0
0
0
900,000
900,000
909,000
Construct Kumasi Office Complex
0
0
0
900,000
900,000
909,000
0
0
0
61,001,244
61,001,244
61,611,256
Recapitalize the Northern Star, Volta Star, Ayensu Starch
companies.
0
0
0
30,000
30,000
30,300
Establish and operate a Secretariat for Industrial Sector Support
Programme's (ISSP) by Dec., 2012.
0
0
0
7,220,000
7,220,000
7,292,200
Assess and Utilize Pooled Funds for Sekondi Industrial Park
0
0
0
53,751,244
53,751,244
54,288,756
0
0
0
85,729,188
85,729,188
86,586,480
Industrial Development
Grand Total
Ministry of Trade and Industry
September 2012
Page 116
Annexure 4: Expenditure by Funding and Program
Expenditure by Program and Funding
In GH¢
2010
Economic Classification
Actual
Ministry of Trade and Industry
2011
Budget
2012
Budget
Est. Outturn
2013
2014
forecast
forecast
0
0
0
157,520,459
157,091,136
158,568,595
0
0
0
10,682,294
10,333,868
10,374,158
0
0
0
6,242,408
6,304,832
6,304,832
Management and Administration
0
0
0
931,886
931,886
941,205
Trade Development
0
0
0
742,000
742,000
749,420
Business Development and Promotion
0
0
0
1,636,000
1,225,150
1,237,402
Trade and Industry Promotion
0
0
0
600,000
600,000
606,000
Standardization and Conformity Assessment
0
0
0
250,000
250,000
252,500
Industrial Development
0
0
0
280,000
280,000
282,800
0
0
0
23,729,311
23,658,052
23,865,604
0
0
0
2,929,128
2,958,419
2,958,419
Management and Administration
0
0
0
2,430,000
2,330,000
2,353,300
Trade Development
0
0
0
618,531
618,531
624,716
Business Development and Promotion
0
0
0
50,000
50,000
50,500
Standardization and Conformity Assessment
0
0
0
17,171,652
17,171,102
17,343,368
Industrial Development
0
0
0
530,000
530,000
535,300
0
0
0
13,040,610
13,030,972
13,159,906
0
0
0
136,220
137,582
137,582
0
0
0
12,904,390
12,893,390
13,022,324
0
0
0
8,000,000
8,000,000
8,080,000
Trade Development
0
0
0
6,000,000
6,000,000
6,060,000
Industrial Development
0
0
0
2,000,000
2,000,000
2,020,000
0
0
0
311,000
311,000
314,110
0
0
0
311,000
311,000
314,110
0
0
0
70,987,244
70,987,244
71,697,116
0
0
0
70,987,244
70,987,244
71,697,116
0
0
0
8,875,000
8,875,000
8,963,750
0
0
0
8,875,000
8,875,000
8,963,750
0
0
0
2,265,000
2,265,000
2,287,650
0
0
0
2,265,000
2,265,000
2,287,650
0
0
0
19,630,000
19,630,000
19,826,300
0
0
0
19,630,000
19,630,000
19,826,300
0
0
0
157,520,459
157,091,136
158,568,595
Central GoG Sources
IGF-Retained Sources
SIP Sources
Business Development and Promotion
ITG Sources
SWIG Sources
Management and Administration
EU Sources
Industrial Development
WBTF Sources
Industrial Development
MDBS Sources
Industrial Development
Pooled Sources
Trade Development
Grand Total
Ministry of Trade and Industry
September 2012
Page 117
Annexure 5: Expenditure by Program/Sub-Program and Economic Classification
Expenditure by Program / Sub Program and Economic Classification
2010
Economic Classification
Ministry of Trade and Industry
21 Compensation of employees [GFS]
211 Wages and Salaries
2011
Actual
Budget
In GH¢
2012
Budget
Est. Outturn
2013
2014
forecast
forecast
0
0
0
157,520,459
157,091,136
158,568,595
0
0
0
9,307,756
9,400,833
9,400,833
0
0
0
9,307,756
9,400,833
9,400,833
0
0
0
9,307,756
9,400,833
9,400,833
0
0
0
8,527,905
8,613,184
8,613,184
21110
Established Position
0
0
0
5,754,691
5,812,238
5,812,238
21111
Non Established Position
0
0
0
1,343,711
1,357,148
1,357,148
21112
Other Allowances
0
0
0
1,429,503
1,443,798
1,443,798
0
0
0
779,850
787,649
787,649
0
0
0
779,850
787,649
787,649
Management and Administration
0
0
0
3,672,886
3,572,886
3,608,615
1.1 Finance and Administration (Legal)
0
0
0
2,562,000
2,562,000
2,587,620
0
0
0
1,352,000
1,352,000
1,365,520
0
0
0
1,352,000
1,352,000
1,365,520
212 Social Contributions
21210
National Insurance Contributions
22 Use of goods and services
221 Use of goods and services
22101
Materials - Office Supplies
0
0
0
444,000
444,000
448,440
22102
Utilities
0
0
0
80,000
80,000
80,800
22103
General Cleaning
0
0
0
41,000
41,000
41,410
22105
Travel - Transport
0
0
0
350,000
350,000
353,500
22107
Training - Seminars - Conferences
0
0
0
437,000
437,000
441,370
31 Non Financial Assets
0
0
0
1,210,000
1,210,000
1,222,100
311 Fixed Assets
0
0
0
410,000
410,000
414,100
31112
Non residential buildings
0
0
0
30,000
30,000
30,300
31121
Transport - equipment
0
0
0
380,000
380,000
383,800
0
0
0
800,000
800,000
808,000
0
0
0
800,000
800,000
808,000
0
0
0
190,000
190,000
191,900
0
0
0
190,000
190,000
191,900
0
0
0
190,000
190,000
191,900
130,000
130,000
131,300
312 Inventories
31222
Work - progress
1.2 Human Resource Management
22 Use of goods and services
221 Use of goods and services
22101
Materials - Office Supplies
0
0
0
22107
Training - Seminars - Conferences
0
0
0
60,000
60,000
60,600
0
0
0
490,886
390,886
394,795
0
0
0
490,886
390,886
394,795
0
0
0
490,886
390,886
394,795
1.3 Policy planning Monitoring and Evalutaion
22 Use of goods and services
221 Use of goods and services
22101
Materials - Office Supplies
0
0
0
260,000
160,000
161,600
22105
Travel - Transport
0
0
0
60,000
60,000
60,600
22107
Training - Seminars - Conferences
0
0
0
170,886
170,886
172,595
Ministry of Trade and Industry
September 2012
Page 118
1.4 Statistics, Research and Communication
22 Use of goods and services
221 Use of goods and services
0
0
0
430,000
430,000
434,300
0
0
0
430,000
430,000
434,300
0
0
0
430,000
430,000
434,300
22101
Materials - Office Supplies
0
0
0
350,000
350,000
353,500
22107
Training - Seminars - Conferences
0
0
0
80,000
80,000
80,800
0
0
0
26,990,531
26,990,531
27,260,436
Trade Development
ACTIVATE SOFTWARE Printed on Thursday, September 20, 2012
Ministry of Trade and Industry
Page 1
Expenditure by Program / Sub Program and Economic Classification
2010
Economic Classification
2.1 Domestic and International Trade
2011
Actual
Budget
In GH¢
2012
Budget
Est. Outturn
2013
2014
forecast
forecast
0
0
0
26,608,531
26,608,531
26,874,616
0
0
0
26,538,531
26,538,531
26,803,916
Development and Promotion
22 Use of goods and services
221 Use of goods and services
0
0
0
26,538,531
26,538,531
26,803,916
22101
Materials - Office Supplies
0
0
0
60,000
60,000
60,600
22105
Travel - Transport
0
0
0
538,531
538,531
543,916
22107
Training - Seminars - Conferences
0
0
0
25,940,000
25,940,000
26,199,400
31 Non Financial Assets
0
0
0
70,000
70,000
70,700
312 Inventories
0
0
0
70,000
70,000
70,700
0
0
0
70,000
70,000
70,700
0
0
0
382,000
382,000
385,820
0
0
0
319,600
319,600
322,796
0
0
0
319,600
319,600
322,796
31222
Work - progress
2.2 Export Development and Promotion
22 Use of goods and services
221 Use of goods and services
22101
Materials - Office Supplies
0
0
0
204,390
204,390
206,434
22102
Utilities
0
0
0
52,400
52,400
52,924
22105
Travel - Transport
0
0
0
35,200
35,200
35,552
22106
Repairs - Maintenance
0
0
0
8,930
8,930
9,019
22108
Consulting Services
0
0
0
18,280
18,280
18,463
22111
Other Charges - Fees
0
0
0
400
400
404
0
0
0
10,400
10,400
10,504
0
0
0
10,400
10,400
10,504
28 Other expense
282 Miscellaneous other expense
28210
0
0
0
10,400
10,400
10,504
31 Non Financial Assets
General Expenses
0
0
0
52,000
52,000
52,520
311 Fixed Assets
0
0
0
52,000
52,000
52,520
31122
0
0
0
52,000
52,000
52,520
Business Development and Promotion
0
0
0
14,590,390
14,168,540
14,310,226
3.1 Technology Transfer, Research and
0
0
0
780,000
369,150
372,842
0
0
0
571,600
160,750
162,358
0
0
0
571,600
160,750
162,358
Other machinery - equipment
Product Development
22 Use of goods and services
221 Use of goods and services
22101
Materials - Office Supplies
0
0
0
39,600
3,300
3,333
22102
Utilities
0
0
0
60,000
6,650
6,717
22105
Travel - Transport
0
0
0
131,600
29,300
29,593
Ministry of Trade and Industry
September 2012
Page 119
22106
Repairs - Maintenance
0
0
0
98,800
10,700
10,807
22107
Training - Seminars - Conferences
0
0
0
220,000
92,500
93,425
22111
Other Charges - Fees
0
0
0
21,600
18,300
18,483
0
0
0
8,400
8,400
8,484
0
0
0
8,400
8,400
8,484
0
0
0
8,400
8,400
8,484
31 Non Financial Assets
0
0
0
200,000
200,000
202,000
311 Fixed Assets
0
0
0
200,000
200,000
202,000
31121
Transport - equipment
0
0
0
90,000
90,000
90,900
31122
Other machinery - equipment
0
0
0
110,000
110,000
111,100
0
0
0
806,000
806,000
814,060
28 Other expense
282 Miscellaneous other expense
28210
General Expenses
3.2 Micro and Small Business
ACTIVATE SOFTWARE Printed on Thursday, September 20, 2012
Ministry of Trade and Industry
Page 2
Expenditure by Program / Sub Program and Economic Classification
2010
Economic Classification
22 Use of goods and services
221 Use of goods and services
Actual
2011
Budget
2012
Est. Outturn
Budget
In GH¢
2013
2014
forecast
forecast
0
0
0
604,000
604,000
610,040
0
0
0
604,000
604,000
610,040
22101
Materials - Office Supplies
0
0
0
45,000
45,000
45,450
22102
Utilities
0
0
0
57,000
57,000
57,570
22103
General Cleaning
0
0
0
5,000
5,000
5,050
22104
Rentals
0
0
0
18,000
18,000
18,180
22105
Travel - Transport
0
0
0
200,900
200,900
202,909
22106
Repairs - Maintenance
0
0
0
31,000
31,000
31,310
22107
Training - Seminars - Conferences
0
0
0
229,000
229,000
231,290
22108
Consulting Services
0
0
0
10,000
10,000
10,100
22111
Other Charges - Fees
0
0
0
8,100
8,100
8,181
0
0
0
72,000
72,000
72,720
0
0
0
72,000
72,000
72,720
0
0
0
72,000
72,000
72,720
0
0
0
30,000
30,000
30,300
0
0
0
30,000
30,000
30,300
0
0
0
30,000
30,000
30,300
31 Non Financial Assets
0
0
0
100,000
100,000
101,000
311 Fixed Assets
0
0
0
100,000
100,000
101,000
31121
0
0
0
100,000
100,000
101,000
0
0
0
13,004,390
12,993,390
13,123,324
0
0
0
1,733,360
1,722,360
1,739,584
0
0
0
1,733,360
1,722,360
1,739,584
27 Social benefits [GFS]
273 Employer social benefits
27311
Employer Social Benefits - Cash
28 Other expense
282 Miscellaneous other expense
28210
General Expenses
Transport - equipment
3.3 Central Region Development
22 Use of goods and services
221 Use of goods and services
22101
Materials - Office Supplies
0
0
0
26,280
26,280
26,543
22102
Utilities
0
0
0
87,580
87,580
88,456
22103
General Cleaning
0
0
0
12,000
12,000
12,120
22104
Rentals
0
0
0
14,400
14,400
14,544
Ministry of Trade and Industry
September 2012
Page 120
22105
Travel - Transport
0
0
0
150,900
150,900
152,409
22106
Repairs - Maintenance
0
0
0
13,800
13,800
13,938
22107
Training - Seminars - Conferences
0
0
0
568,000
568,000
573,680
22108
Consulting Services
0
0
0
243,000
243,000
245,430
22109
Special Services
0
0
0
600,000
600,000
606,000
22111
Other Charges - Fees
0
0
0
17,400
6,400
6,464
0
0
0
6,600
6,600
6,666
0
0
0
6,600
6,600
6,666
0
0
0
6,600
6,600
6,666
0
0
0
7,176
7,176
7,248
0
0
0
7,176
7,176
7,248
0
0
0
7,176
7,176
27 Social benefits [GFS]
273 Employer social benefits
27311
Employer Social Benefits - Cash
28 Other expense
282 Miscellaneous other expense
28210
General Expenses
ACTIVATE SOFTWARE Printed on Thursday, September 20, 2012
Ministry of Trade and Industry
Expenditure by Program / Sub Program and Economic Classification
2010
Economic Classification
2011
Actual
Budget
2012
Budget
Est. Outturn
7,248
Page 3
In GH¢
2013
2014
forecast
forecast
31 Non Financial Assets
0
0
0
11,257,254
11,257,254
11,369,827
311 Fixed Assets
0
0
0
8,801,000
8,801,000
8,889,010
31111
Dwellings
0
0
0
540,000
540,000
545,400
31112
Non residential buildings
0
0
0
6,836,000
6,836,000
6,904,360
31113
Other structures
0
0
0
670,000
670,000
676,700
31121
Transport - equipment
0
0
0
100,000
100,000
101,000
31122
Other machinery - equipment
0
0
0
655,000
655,000
661,550
0
0
0
2,456,254
2,456,254
2,480,817
0
0
0
2,456,254
2,456,254
2,480,817
Trade and Industry Promotion
0
0
0
600,000
600,000
606,000
4.1 Regional Services
0
0
0
110,000
110,000
111,100
0
0
0
110,000
110,000
111,100
0
0
0
110,000
110,000
111,100
0
0
0
110,000
110,000
111,100
0
0
0
490,000
490,000
494,900
0
0
0
400,000
400,000
404,000
0
0
0
400,000
400,000
404,000
0
0
0
400,000
400,000
404,000
31 Non Financial Assets
0
0
0
90,000
90,000
90,900
311 Fixed Assets
0
0
0
90,000
90,000
90,900
31121
312 Inventories
31222
Work - progress
22 Use of goods and services
221 Use of goods and services
22107
Training - Seminars - Conferences
4.2 Foreign Trade Services
22 Use of goods and services
221 Use of goods and services
22107
Training - Seminars - Conferences
0
0
0
90,000
90,000
90,900
Standardization and Conformity Assessment
Transport - equipment
0
0
0
17,421,652
17,421,102
17,595,868
5.1 Metrology
0
0
0
909,018
909,018
918,108
0
0
0
682,638
682,638
689,464
0
0
0
682,638
682,638
689,464
22 Use of goods and services
221 Use of goods and services
22102
Utilities
0
0
0
1,200
1,200
1,212
22103
General Cleaning
0
0
0
25,000
25,000
25,250
Ministry of Trade and Industry
September 2012
Page 121
22104
Rentals
0
0
0
28,800
28,800
29,088
22105
Travel - Transport
0
0
0
424,888
424,888
429,137
22107
Training - Seminars - Conferences
0
0
0
100,265
100,265
101,268
22108
Consulting Services
0
0
0
102,485
102,485
103,509
0
0
0
10,500
10,500
10,605
0
0
0
10,500
10,500
10,605
0
0
0
10,500
10,500
10,605
0
0
0
2,940
2,940
2,969
0
0
0
2,940
2,940
2,969
0
0
0
2,940
2,940
2,969
31 Non Financial Assets
0
0
0
212,940
212,940
215,069
311 Fixed Assets
0
0
0
210,000
210,000
212,100
31122
0
0
0
210,000
210,000
212,100
0
0
0
2,940
2,940
2,969
0
0
0
2,940
2,940
2,969
0
0
0
268,359
268,359
271,043
27 Social benefits [GFS]
273 Employer social benefits
27311
Employer Social Benefits - Cash
28 Other expense
282 Miscellaneous other expense
28210
General Expenses
Other machinery - equipment
312 Inventories
31222
Work - progress
5.2 Standards
ACTIVATE SOFTWARE Printed on Thursday, September 20, 2012
Ministry of Trade and Industry
Page 4
Expenditure by Program / Sub Program and Economic Classification
2010
Economic Classification
22 Use of goods and services
221 Use of goods and services
Actual
2011
Budget
2012
Est. Outturn
Budget
In GH¢
2013
2014
forecast
forecast
0
0
0
262,359
262,359
264,983
0
0
0
262,359
262,359
264,983
22101
Materials - Office Supplies
0
0
0
113,649
113,649
114,785
22102
Utilities
0
0
0
18,665
18,665
18,852
22103
General Cleaning
0
0
0
25,000
25,000
25,250
22104
Rentals
0
0
0
16,800
16,800
16,968
22106
Repairs - Maintenance
0
0
0
1,000
1,000
1,010
22107
Training - Seminars - Conferences
0
0
0
15,000
15,000
15,150
22108
Consulting Services
0
0
0
72,246
72,246
72,968
0
0
0
6,000
6,000
6,060
0
0
0
6,000
6,000
6,060
0
0
0
6,000
6,000
6,060
0
0
0
16,244,275
16,243,725
16,406,718
0
0
0
4,243,849
4,243,299
4,286,288
27 Social benefits [GFS]
273 Employer social benefits
27311
Employer Social Benefits - Cash
5.3 Conformity Assessment
22 Use of goods and services
221 Use of goods and services
0
0
0
4,243,849
4,243,299
4,286,288
22101
Materials - Office Supplies
0
0
0
666,019
666,019
672,680
22102
Utilities
0
0
0
338,032
338,032
341,412
22103
General Cleaning
0
0
0
668,000
668,000
674,680
22104
Rentals
0
0
0
293,100
293,100
296,031
22105
Travel - Transport
0
0
0
652,892
652,342
659,421
22106
Repairs - Maintenance
0
0
0
240,800
240,800
243,208
22107
Training - Seminars - Conferences
0
0
0
477,094
477,094
481,865
22108
Consulting Services
0
0
0
907,912
907,912
916,991
0
0
0
135,400
135,400
136,754
27 Social benefits [GFS]
Ministry of Trade and Industry
September 2012
Page 122
273 Employer social benefits
27311
Employer Social Benefits - Cash
28 Other expense
282 Miscellaneous other expense
28210
General Expenses
0
0
0
135,400
135,400
136,754
0
0
0
135,400
135,400
136,754
0
0
0
329,276
329,276
332,569
0
0
0
329,276
329,276
332,569
0
0
0
329,276
329,276
332,569
31 Non Financial Assets
0
0
0
11,535,750
11,535,750
11,651,108
311 Fixed Assets
0
0
0
11,510,000
11,510,000
11,625,100
31112
Non residential buildings
0
0
0
10,990,000
10,990,000
11,099,900
31121
Transport - equipment
0
0
0
330,000
330,000
333,300
31122
Other machinery - equipment
0
0
0
190,000
190,000
191,900
0
0
0
25,750
25,750
26,008
0
0
0
25,750
25,750
26,008
0
0
0
84,937,244
84,937,244
85,786,616
0
0
0
84,937,244
84,937,244
85,786,616
0
0
0
23,936,000
23,936,000
24,175,360
0
0
0
23,936,000
23,936,000
24,175,360
312 Inventories
31222
Work - progress
Industrial Development
22 Use of goods and services
221 Use of goods and services
22101
Materials - Office Supplies
0
0
0
2,040,000
2,040,000
2,060,400
22105
Travel - Transport
0
0
0
60,000
60,000
60,600
22107
Training - Seminars - Conferences
0
0
0
21,786,000
21,786,000
22,003,860
22108
Consulting Services
0
0
0
50,000
50,000
50,500
ACTIVATE SOFTWARE Printed on Thursday, September 20, 2012
Ministry of Trade and Industry
Page 5
Expenditure by Program / Sub Program and Economic Classification
2010
Economic Classification
Actual
2011
Budget
2014
forecast
forecast
0
0
0
61,001,244
61,001,244
61,611,256
311 Fixed Assets
0
0
0
60,891,244
60,891,244
61,500,156
31111
0
0
0
60,891,244
60,891,244
61,500,156
0
0
0
110,000
110,000
111,100
0
0
0
110,000
110,000
111,100
0
0
0
157,520,459
312 Inventories
31222
Work - progress
Grand Total
Ministry of Trade and Industry
September 2012
Est. Outturn
2013
31 Non Financial Assets
Dwellings
Budget
2012
In GH¢
157,091,136
158,568,595
Page 123