FLOWCHART / GUIDELINES FOR HANDMOULDED BRICK PRODUCTION IN VSBK FIRING SYSTEM SOIL Remove Cut the soil Roots/Stones and build up a pile Check for lime and large granular stones STONE DUST / FINE SAND Sieve through Measure a fixed 3mm mesh volume of sand/stone dust Check for lime with acid BURNT COAL Sieve through Measure a fixed ASH 3mm mesh volume of burnt coal ash e.g. sponge iron Sieve through Measure a fixed waste, foundry 3mm mesh volume of internal fuel DRY MIXING Cut the pile and mix the INTERNAL FUEL waste, coal dust AGEING Add water - mix thoroughly materials at least twice and cover with plastic sheet in dry state before to prevent evaporation. adding water Store wet mix for minimum 1 day, preferably 3 days + Check CV of each batch of internal fuel delivered and record RICE HUSK Measure a fixed volume of rice husk WATER Ensure floor is EXCESS CLAY clean and level FROM MOULD Check plasticity and Sand to be sieved moisture content through 2mm mesh STOCK ROLL CLAY IN FILL MOULD APPLY PRESSURE CUT OFF EXCESS SHOVEL MOIST CLAY ON SAND AND MAKE WITH SOIL BY HAND AND SOIL WITH AND SMOOTH HAND CART HANDMOULDING A WEDGE UNDER PRESSURE STRIKE ON FLOOR BOW CUTTER SURFACE BY HAND FLOOR Use red burning Clean mould after sand every 50 bricks Mould dimensions to Experiment with be checked weekly different frog designs to reduce brick weight Sprinkle interior with clean, dry sieved sand SPRINKLE DRY SAND Dried bricks going to kiln Weigh and measure brick dimensions to be <5% MC (dry basis) Ensure that loading trolley / content and record. Compare bricks made by different moulders Ensure weekly maintenance of belts, wire rope, motor. daily before going to kiln. Check moisture Calculate % wastage and conveyer belt is not causes of waste. overloaded DRY TO STACK BRICKS DEMOULD LEATHER IN DRYING DRY GREEN BRICK LIFTING OF ONTO FLOOR HARD STATE STACKS TRANSPORT GREEN BRICKS Ensure floor is Keep distance Reject broken or Transport green bricks by clean and level as short as damaged bricks mechanized means possible and - Lift clean and level - Winch Wherever possible avoid Handle green bricks with handling the brick more than care to avoid damage. once. Preferably the trolley for Stack bricks at least 1 cm apart. transporting the bricks should Drying stacks should be be used from drying area to on a burnt brick layer. top of the kiln - Conveyer belt Any changes to the clay mix amount of internal fuel and its current CV to be notified to the firemaster. Always maintain a dense loading pattern at the centre after stabilization. Compare quantity of bricks loaded Spread coal uniformly at the periphery only. Check weigh Check fired brick for size, into kiln and quantity going into colour and ring to stockyard to calculate process establish if coal additions wastage and determine causes of need adjustments. wastage. scale accuracy Check CV of each delivery of coal Monitor fire position and Weigh and Determine loading, EXTERNAL FUEL flue gas temperature prior measure 10 transportation and (COAL) to unloading and loading. and record bricks daily unloading breakage and and record. determine causes VERTICAL LOADING OF LOADING OF SHAFT UNLOADING PLATFORM SHAFT BRICK KILN OF BATCH Keep the brick stack Ensure correct Rate of loading and unloading height at the same setting pattern is to be set to stabilize the level with shaft top to followed and coal position of the fire and as per ensure good ventilation. is added to the quality desired Ensure that the structure layer as instructed not overloaded Open dampers and lid when Maintain proper coal loading. After loading is complete size and quantity close lid and dampers STOCKYARD DESPATCH
© Copyright 2026 Paperzz