BENCHMARKING OF KEY AREAS OF DAHANU POWER STATION IN MAHARASHTRA PERIOD OF VISIT : 17.02.05 TO 19.02.05 I. BRIEF DESCRIPTION OF THE PLANT • Dahanu Power Station (DTPS) of Reliance : Installed capacity 500 MW (2 x 250 MW), 135 Km away from Mumbai city in Thane district. • Commissioned : Unit 1 - July 1995, Unit 2 - January 1996 • Project started in 1989, cost is Rs 1240 crore • The transmission project cost is Rs 235 crore • Total land area Plant area Ash Disposal area Colony area II. : : : : 821.58 hectare 351.58 hectare 370 hectare (3 ash ponds at present, 4th one being constructed) 100 hectare SCOPE OF BUSINESS • DTPS provides power to North Mumbai • Maximum System requirement is approx 1300 MW • The shortfall in supply of demand is met by import of power from Tata Power III. • GENERATION COST BREAKUP Generation cost breakup for 2003-04 is as follows : Fuel Cost Staff Cost O&M Cost Insurance Interest Depreciation IV. : : : : : : 71.61% 3.23% 5.81% 0.65% 0.65% 18.06% OPERATION A. HEAT RATE • MERC approved Heat Rate for 2004-05 is 2319 Kcal/Kwh • Heat Rate for 2004-05 (till Jan ‘05) is 2260 Kcal /Kwh • GCV of as-fired coal is found out (coal sampling is done at the time of bunkering). Coal consumption is found out from feeder totaliser readings. Heat rate is thus calculated. 1 Boiler efficiency is found out from loss method on a daily basis. Cycle efficiency is then found out. Heat rate is calculated like this also for cross checking. B. COMBUSTIBLES IN ASH • • Combustibles in Fly Ash is 0.6 to 0.8% (design value is 1%) • Combustibles in Bottom Ash is 3 to 4% (design value is 5%) C. OTHER PARAMETERS • Other parameter trends is as follows : PLF (%) PAF (%) Loading Factor (%) Auxiliary (%) Heat Rate (Kcal/Kwh) Oil Rate (ml/Kwh) Coal Rate (Kg/Kwh) DM Make Up (%) No of outages Trippings per 1000 hr running 1998-99 (Actual) 1999-00 (Actual) 2000-01 (Actual) 2001-02 (Actual) 2002-03 (Actual) 2003-04 (Actual) 76.55 92.24 88.68 98.42 82.68 92.33 87.83 93.02 90.53 91.03 100.34 97.94 2004-05 (Actual) (till Jan05) 100.99 96.58 82.99 90.10 89.55 94.42 99.45 102.45 104.57 103.00 7.44 7.04 7.20 7.82 7.43 7.34 7.54 7.34 2337 2313 2313 2320 2312 2319 2260 2319 0.50 0.48 0.27 0.17 0.31 0.12 0.127 0.2 1998-99 (Actual) 1999-00 (Actual) 2000-01 (Actual) 2001-02 (Actual) 2002-03 (Actual) 2003-04 (Actual) 2004-05 (Actual) (till Jan05) - 0.565 0.538 0.534 0.545 0.526 - 1.25 0.9 0.69 0.74 0.67 0.39 0.37 - 9 26 10 17 6 6 - 0.2892 1.2982 0.2455 0.627 0.117 - 2004-05 (MERC approved) 98.77 95.89 • MERC has not allowed backing down of DTPS units when demand is more than generation capacity. The balance requirement of power over and above generation capacity can only be bought from TPC • DTPS operates each unit at around 262 MW, which is higher than the rated capacity of 250 MW. The unit is being operated within the parameters specified by the equipment manufacturers and no technical limits are being violated. • Both the units have once-through condenser cooling system 2 V. FUEL AND FUEL HANDLING PLANT • Raw coal is procured from Dipka/Gebra collieries (Gr F) of SECL. DTPS receives washed coal from SBCWL (ST-BSES Coal Washeries Ltd) Coal Washery project at Jamnipalli, Korba, MP. This Washery project is a joint venture between BSES Ltd (now Reliance Energy Ltd) & Spectrum Technologies, USA. Cost of washing is approx Rs 100 /Te and yield is 80%. • Imported coal is procured from Indonesia (Kideco & Adaro collieries) and China only in the months of October to April because of rough sea condition in the other months • Coal comes from Indonesia by ship, which anchors in the high sea. It is then brought to the jetty (16 km away) alongside DTPS by barges (500 – 1000 Te capacity). Dumpers then bring the coal to the plant stock yard (3 km away). The handling charge from ship to stock yard is approx Rs 250 /Te. • Washed coal and imported coal is blended in the ratio of 80 : 20 • Design coal characteristic of DTPS is as follows (Source : BHEL Data Sheet on Dahanu) : Proximate Analysis Inherent Moisture (%) Volatile Matter (%) Ash (%) Fixed Carbon (%) HHV (kcal/kg) HGI • Design Coal 10 19 40 31 3700 55 Best Coal 10 22 34 34 4160 58 Worst Coal 20 17 40 23 3000 50 Imported coal characteristic is as follows : Proximate Analysis Total Moisture (%) 25 Inherent Moisture (%) 12 Ash (%) 2.5 Sulphur (%) 0.15 GCV (kcal/kg) 5700 • Calorific value of fuels for 2003-04 and 2004-05 is as follows : 2003-04 Wtd Avg Coal Calorific Value (Kcal /Kg) Wtd Avg Secondary Oil Calorific Value (Kcal /L) Actual MERC approved 2004-05 MERC approved 4306 4306 4500 9739 9739 10619 3 • In 2004-05, as approved by MERC, landed cost of washed coal is Rs 2184 /Te and that for imported coal is Rs 2360 /Te • The trends in actual coal price as submitted in the petition to MERC is as follows : Fuel Raw Coal Washed Coal Imported Coal Coal Basket* * Coal Unit 1998-99 1999-00 2000-01 Rs /MT 1558 1596 1496 Rs /Gcal 428 447 402 Rs /MT 1933 1927 Rs /Gcal 619 458 Rs /MT 2519 2561 2801 Rs /Gcal 426 484 441 Rs /MT 1815 1884 2003 Rs /Gcal 427 489 450 basket includes washed coal and imported coal 2001-02 2002-03 2003-04 1926 464 2661 499 2038 470 1645 467 1985 481 2056 387 1968 457 1638 1915 1691 1864 433 2004-05 (MERC approved) 2219 433 NB : MERC has approved the actual values in 2003-04 • The fuel cost of generation as approved by MERC for 2003-04 and 2004-05 is Rs 1.01 /Kwh • Unloading of rakes is carried out in 2 Rotary Wagon Tipplers (Elecon make) with Beetel chargers. There are also 2 shunting locomotives. Free time for unloading is 10 hours and demurrage paid is almost nil. • The wagon tipplers have Avery make electronic weighbridges. • The Fuel Handling Plant operation and maintenance is done by contract personnel in 3 shifts • There are 4 coal stock yards each of capacity 1 lakh tonnes. Proposal for another stockyard of 1 lakh Te capacity has already been placed with the higher management. • There are 2 stacker /reclaimers in the stock yard. Washed coal and imported coal is stacked separately. 3 dozers are also used for reclaiming coal through reclaim hoppers. • As on 19.02.05, the total coal stock was 354473 Te (washed coal - 181513 Te and imported coal – 172959 Te) VI. • MAINTENANCE General schedule of Turbine overhauling is as follows : HP and IP turbine LP turbine Generator – every 6 years - every 2 years - after 20000 running hours 4 • Overhaul details of various units of DTPS are as follows : Unit 1 Unit 2 2004-05 2003-04 2002-03 2001-02 2000-01 - 18 - 35 7 HP+IP+LP+Gen+Blr Blr - 11 LP+Gen+Blr 15 - LP+Gen+Blr 31 HP+IP+LP+Gen+Blr Blr • The turbine overhaul is carried out wholly by M/s BHEL, who hires all the contract personnel needed for the job (cost incurred recently is approx Rs 90 lakh for LP + Generator overhauling job) • DTPS personnel are engaged in overall supervision of the turbine overhauling while the boiler overhauling is being done by themselves (cost approx Rs 11-12 lakh for labour part). • The total overhaul cost is approx Rs 4 to 5 crores (labour + material) • DTPS has spares available for boiler and turbine overhauling till 2005-06 • Total inventory holding is about Rs 17 crores • The R&M Expenses as approved by MERC for 2004-05 is Rs 63.81 crores while expenditure done in 2003-04 and approved by MERC was Rs 78.26 crores. • All the maintenance departments work in general shifts. A skeletal gang consisting of 6 Engineers from Mechanical (4), Electical (1) and C&I (1) along with a handful of non-executives are there on duty beyond 17.30 hrs till 08.30 hrs next morning. VII. DIFFERENT O&M PRACTICE • After a forced shutdown (e.g. tube leakage of boiler), the boiler is vented to atmosphere and the drum metal temperature comes down to maximum 110 deg C within 5 hours. This is achieved by keeping the HP & LP bypass of the turbine open while forced cooling by draught fans is also being carried out. Maximum difference that occurs between top and bottom drum metal temperature is 70 deg C. • After about 12 hours of shutdown, when turbine inner casing temperature is about 370 deg C, the barring gear is stopped, lubricating oil pumps are stopped, jacking oil pump continues to run and blanking of oil pipelines to the generator bearings is carried out (process takes about 15 min). The generator is now decoupled from the turbine. During the decoupling process, hand barring is being done regularly. By this process the Generator overhauling job can start from the second day itself, thereby saving time. 5 • During overhauling of the boiler, tube thickness gauging is carried out by DTPS Engineers by hand only. If slight erosion is observed, then the necessary part is replaced. In the burner corners, the first 5 tubes are always changed. VIII. ENVIRONMENT • DTPS has an ESP of collection efficiency 99.9%. The ESP has 4 passes, 6 fields per pass and 2 hoppers per field • On line SOx, NOx and TPM monitoring is installed • 4 ambient air quality monitoring stations are positioned within a radius of 25 km to monitor pollution parameters • A mobile pollution testing van is also there • The SOx emission limit set by MERC is 80.4 TPD. IX. ADMINISTRATION • Headed by a Vice President who is the Plant Manager • There are approx 200 executives and 300 non-executives working in the plant. About 500 contract personnel support them 6
© Copyright 2026 Paperzz