Averting Disaster on the Grid Strategy to Mitigate Risks of Catastrophic Events By H arjeet Johal, K en Collison, Elliot Roseman, Dan Rogier 32 Public Utilities Fortnightly September 2016 © Can Stock Photo Inc. / pmfpires M aintaining the security of the electric grid today is far from business as usual. The grid is under increasing threats to its very viability from cyber-attacks, natural disasters, and physical assault. Moreover, the severity of each of these threats is on the rise. It is not possible to protect or harden the grid across the tens of thousands of miles of high-voltage lines and tens of thousands of substations. And while utilities maintain some operational spares to replace large power equipment that fails due to normal wear and tear, it is economically prohibitive for a utility to stockpile multiple million dollar pieces of equipment to prepare for the worst. This reality puts the grid and the reliable supply of power to customers at risk for extended periods. Many key pieces of equipment have long lead times and are difficult to replace. This could cripple the grid and severely extend the interruption of power supply. With the threats rising, utilities must develop plans on how they will mitigate the risks of such events. In fact, federal regulations now require this.1 Grid Assurance is a coalition of six major U.S. utilities2 dedicated to providing a costeffective solution to address the increasing threats to the security of power supplies. And to provide the right level of inventory in the right locations to expedite recovery following an event. Working together, Grid Assurance and its consultants created a first-of-a-kind framework to quantify the potential benefits of pooling equipment amongst utilities, and to develop best practices for inventory hosting. Regardless of size, there are clear economic benefits of pooling needs across multiple transmission owners for this vital service. Utilizing this framework, and pooling resources, will help reduce restoration times following a severe attack from months to weeks or days. Increasing Threat Landscape The 2013 coordinated rifle attack to sabotage the Metcalf substation in California is but one example of the new threats that face the nation’s grid. The energy industry is by far the most targeted Harjeet Johal is a senior manager with ICF International and an expert in energy economics and power system consulting. He has over ten years of experience in electrical engineering, energy planning, economic evaluation, and policy research. Ken Collison is a vice president at ICF. He is in his fifteenth year with the company. And an expert in power system planning, economic analysis, and reliability assessments. Ken also serves as an expert witness in electric transmission and distribution cases. Elliot Roseman is a vice president with ICF. And a senior policy and regulatory expert who specializes in electric transmission and energy infrastructure issues. He is in his fifteenth year with the company, and in the energy industry for a good deal longer. Dan Rogier is a veteran of thirty-six years in the utility industry, and is an executive of American Electric Power. He has served in a number of transmission engineering and operations roles, with additional leadership experience in distribution, generation, customer service and information technology. Mr. Rogier is currently serving as chief operating officer of Grid Assurance. The grid is under increasing threats to its very viability from cyber-attacks, natural disasters, and physical assault. for cyber-attacks. In 2014, the energy sector reported seventynine incidents, out of a total of two hundred forty-five (thirty-two percent of the total across all industries).3 Figure 1 further strengthens the argument. Physical attacks, cyber-attacks, combinations of the two, insider plots, and natural disasters are identified as top threats by NERC. These can have high likelihood of occurrence in the future, with potentially widespread consequences. The National Oceanic and Atmospheric Administration also clearly shows us the increase in damaging natural disasters. In 2016, there have been eight weather and climate disaster events with losses exceeding one billion each across the United States, as of July. The year 2012 was the second costliest year on record. It had more than seventy billion in damages, including the episodic derecho which cut power supplies to more than 4.2 million customers in just a few hours, traveling more than sixty miles per hour across the countryside. Hurricane Sandy was even worse.4 We all have insurance policies to protect against damage to our homes, vehicles and businesses. In the same way, the sharing of transformer inventories is an insurance policy for the grid and for the reliability of the electric power system. Naturally, there is a premium to pay for insurance. But it is a small fraction of the cost of incurring the catastrophic events against which it is protecting, events that are becoming increasingly common. September 2016 Public Utilities Fortnightly 33 Framing a Solution Squirrels Natural disasters Physical attack/theft Cyber attack Insider threat/ catastrophic human error Coordinated physical & cyber attack The increasing numbers, likelihood and severity of events like these demand enhanced resiliency measures. The goal is to ensure the continued reliable operation of our nation’s electric transmission grid. However, such events still occur infrequently and have few precedents. So it is challenging to develop a planning framework that accurately captures their risks to the power grid. In this section, we lay out the key elements Fig. 2 of such a framework. And we address the factors that affect the pooling benefits and ultimately the inventory requirement. The inputs for each utility may vary. But we found that the key to success is to How often do individual events deploy the following framework and analytic occur? process, including the six factors outlined below. See Figure 2. 1. Events: Not all events will be relevant to How diverse is each utility. For example, hurricanes are more equipment base? common in the Southeast, while tornadoes are more likely in the Midwest. 2. Frequency: How often do the individual What is planning events occur? The greater the likelihood of criteria for service reliability? occurrence of an event, the higher will be the inventory level required. 3. Diversity in equipment: Pooling benefits relate directly to the diversity in equipment base. If different areas have completely different voltage classes of equipment, the overall inventory requirement will increase. 4. Severity: The severity of the events determines the extent of damage. For example, the damage from category three storms would likely be limited to the coastal regions, while category five storms can have damaging effects many miles inland. 5. Operational Spares: Under some situations the operational spares can be used towards event restoration, which can help to lower the inventory requirement. 6. Desired Service Level: Planning criteria to provide insurance against catastrophic events. We proposed a very high service 34 Public Utilities Fortnightly September 2016 NERC Threat Landscape Fig. 1 Likelihood Substantial economic benefits are achieved by pooling the needs across multiple geographicdiverse utilities. Supply chain disruption or compromise Pandemics Geomagnetic disturbance Direct energy weapon CBR attack High-atitude EMP Nuclear Consequence Framework For Developing Optimal Inventory Levels EVENTS What are relevant events for each subscriber? FREQUENCY SEVERITY What is likely damage? Identify extent of damage Geographic impact areas from each relevant event Impact Assessment tool Company specific database is used to identify high voltage equipment at risk DIVERSITY SPARES Identify relevant events Physical attack, cyber attack, weather events, GMDs Can you count operational spares? Determine operational spares Percent of operational spares for event restoration SERVICE LEVEL Catastrophic Inventory Model tool Monte Carlo analysis to determine the inventory for a desired service level standard of 99.97 percent, or 5 Sigma. We used this approach on an illustrative example to assess the value of pooling the inventory needs across several utilities. This approach could in turn be applied to any combination of firms desiring to share in the protection from these catastrophic events. Simulated Physical Attack A carefully orchestrated physical attack on key substations can result in significant loss of large power transformers. It can cause widespread outages to customers and compromise the overall reliability of the transmission grid. Parameters for Selecting Target Substations Fig. 3 Transmission Lines Voltage Class kV Under 100 100–161 230–300 345 500 50 mil es We created a first-ofa-kind framework to quantify benefits of pooling equipment amongst utilities, and develop best practices. n Disruption of power in metropolitan areas will likely cause most havoc n Bigger substations are probably most critical n Likely that up to six substations can be attacked simultaneously City center 345/138 230/69 500/230 230/115 345/115 230/138 345/161 138/69 765/345 161/69 345/230 161/138 161/115 765/138 115/69 Number of transformers We used this construct to identify areas that could be likely targets, and screened for stations with large power transformers within a certain distance from the city center. Figure 3 conceptually shows the process used to identify such substations. A typical high-voltage substation can host several large power transformers. Our modeling assumed that a sophisticated attack would be successful in crippling all such transformers in the identified stations.5 In Equipment At Risk Across Multiple Metropolitan Areas Fig. 4 this illustrative example, Figure 4 counts a total of two hundred eighty-eight at-risk large 60 power transformers across multiple cities if Total relevant equivalent – 288 transformers they were simultaneously attacked. 50 Losing this number of units is clearly unrealistic. But one needs to understand the 40 full scope of the challenge to capture and plan for a severe situation which utilities could face. 30 In practice, just a few voltage classes have sufficient volumes to drive significant pooling 20 benefits. In this example, the 345/138 kiloVolt and the 230/69 kiloVolt classes account for 10 thirty-seven percent of the total equipment and appear in multiple metropolitan areas. As 0 such, the pooling benefits for transformers in these voltage classes will be higher than those in the classes with a much lower number of transformers. In its 2010 Critical Infrastructure Strategic Roadmap, NERC The equipment at risk is a key input to the Inventory Modelidentified such an attack as one of its three priority risk scenarios. ing Tool, a sophisticated Monte Carlo engine that is used to Such a scenario would disable difficult-to-replace equipment randomly simulate an attack on these cities in different years.6 such as large power transformers. The model optimizes the inventory requirements based on a Even without access to detailed information and sophisticated desired level of reliability. tools, public data exists that could be used to plan a grid attack. For example, a service level of one hundred percent implies For example, extra-high and high-voltage substations near major that the utilities would maintain adequate inventory to cover metropolitan areas could be presumed to serve a large number the worst case catastrophe, taking into account the lead time to replace equipment.7 Using our example model, there are of customers and critical loads. Similarly, attackers can target the grid serving major areas or fifty-five 345/138 kiloVolt transformers at-risk. The worst case popular tourist destinations to maximize international resonance. event would impact thirty of these units. September 2016 Public Utilities Fortnightly 35 36 Public Utilities Fortnightly September 2016 345/138 230/69 500/230 230/115 345/115 230/138 345/161 138/69 765/345 161/69 345/230 161/138 161/115 765/138 115/69 Number of transformers Number of transformers Power system planning does not require a Fig. 5 Example: Inventory Requirement for 345/138kV Transformers one hundred percent service level. Rather it By varying service level should cover all but highly unlikely events. 60 We modeled a service level that is based on an industry accepted threshold of risk. This 50 allows for a loss of load expectation of one day 45% 40 in a ten-year period. This assumption equates to a service level 30 33% of 99.97 percent.8 While reducing the service 20 15% level from 100 percent to 99.97 percent may seem small, it substantially reduces the num10 ber of transformers required by thirty-three 0 percent, to twenty units. See Figure 5. Equipment Worst case event 99.97% 99% Further reduction in service level can at risk (100% service level) service level service level provide additional pooling benefits, but only marginally. At a service level to 99 percent, Desired Inventory Level at 99.97% Service Level Reliability Fig. 6 the required inventory reduces by three units By transmission class, multiple cities of the 345/138 kiloVolt at-risk transformers, 60 to seventeen units. We then repeated the Monte Carlo analysis 50 for all fifteen equipment classes across the Equipment at risk – 288 metropolitan areas. Figure 6 summarizes the Target inventory – 144 40 results for the optimal inventory level needed at the 99.97 percent service level. 30 The numbers show that substantial economic benefits are achieved by pooling the 20 needs across multiple geographic-diverse utilities, using an approach like Grid Assurance. 10 In this example, the required inventory is only fifty percent of the at-risk transformers. Or 0 one hundred forty-four transformers across all voltage classes. This level of reduction is not possible if individual utilities serving the multiple metropolitan areas develop their own inventory hosting program. Potential attackers will know that their plans to disrupt the reliable supply of power would be much less effective. Like a home Concluding Remarks security system, it could also cause those with bad intentions to look Our analysis outlines that the case for collaboration amongst elsewhere for targets where they would hope to have more impact. many utilities in this inventory service can be compelling. First, The most compelling impact of this collaboration will be to the protection and security offered to expedite the recovery from lower the costs to customers, which will be much smaller than if a catastrophic event is significant. Many studies have shown a utility were to consider developing a large inventory of critical how much customers rely upon a reliable source of electricity, equipment on its own. and how industrial, commercial and residential activity would By joining forces, utilities dramatically lower the number be crippled without it. of large power transformers required, as they share the cost of The economic losses can easily mount into hundreds of bil- building and maintaining this lower level inventory with others. lions from an extended outage. This inventory of long lead-time These compelling results provide utilities significant rationale equipment will provide the required additional capacity needed to assess their options to meet these new threats to our nation’s to meet the new threats that face the nation’s grid. grid. And to develop solutions that are the most cost-effective In addition, such a stockpile could have a deterrent effect. for their customers. PUF Expert $24 SEPTEMBER 2016 PUBLIC UTILITIES insight and analysis in FORTNIGHTLY “In the Public Interest” every issue Tom Flaherty, Bob Catell Charles Bayless, Ahmad Faruqui Roger Woodworth, Comm. Echols 25 contributing authors D.C. PSC Staff PUBLIC UTILITIES FORTNIGHTLY 1609 Cover-r1.indd 1 Subscribe today: fortnightly.com/subscribe “In the Public Interest” Your best source for unbiased and insightful coverage of the critical issues facing the energy industry. or sign up for a no obligation trial at fortnightly.com/free-trial or call 1-800-368-5001. Endnotes: 1. The North American Electric Reliability Corporation took the important step of focusing on the critical equipment in the standard on critical infrastructure protection for physical security (CIP-014-1) that became effective on January 26, 2015. The standard requires transmission owners to identify and protect equipment that could cause cascading outages and blackouts if damaged. Also, the bill H.R.2244 requires the Department of Energy, acting through the Office of Electricity Delivery and Energy Reliability, to submit to Congress a plan to establish a Strategic Transformer Reserve for the storage, in strategically located facilities, of spare large power transformers in sufficient numbers to temporarily replace critically damaged large power transformers. 2. American Electric Power, Great Plains Energy, Eversource, Edison Transmission, Duke Energy, and Berkshire Hathaway Energy. 3. U.S. Department of Homeland Security. ICS-CERT Monitor, September 2014 – February 2015. 4. These damage figures only account for the direct costs of repairing buildings, replacing infrastructure and fixing other facilities and possessions damaged in such events. In addition, there are the indirect costs to our economy of losing the contents of our refrigerators; losing retail sales at shopping malls and res- 9/2/16 9:29 AM 5. 6. 7. 8. taurants; losing industrial production; and losing job productivity that are many times the direct costs. We used industry-available data to identify the high-voltage transformers within a target substation. We did not include generation step-up transformers in our analysis. This example assumes that the likelihood of a physical attack on a metropolitan area is once in five years. Because of a lack of historical data on such events, once in five years is used as a best estimate. Sensitivities were evaluated to determine the best estimate to assess the impact on the inventory hosting requirements. This example assumes a large power transformer lead-time of eighteen months. The worst case event would therefore be a scenario where three metropolitan areas are attacked consecutively in three consecutive years but within a time span of eighteen months. One day in three hundred and sixty-five days per year, in ten years, is equivalent to a 99.97 percent reliability standard. In this illustrative example, using this reliability level with long-lead time equipment of eighteen months implies that a catastrophic event, which could result in inadequate inventory, is expected to occur once in every five thousand years on average. September 2016 Public Utilities Fortnightly 37
© Copyright 2026 Paperzz