17/03/2015 Pricing and payment under construction and supply agreements David Nancarrow DLA Piper Australia 17 March 2015 Introduction "A penny saved is a penny earned" - Benjamin Franklin In-House Counsel Day 2015 2 1 17/03/2015 Pricing vs Payment Pricing – how the total amount payable is determined Payment – how the amount payable is paid In-House Counsel Day 2015 3 Structures for pricing Number of possible ways to structure pricing: Lump sum or fixed price Guaranteed Maximum Price (GMP) Provisional sum (or provisional sum items) Cost reimbursable (cost plus) Schedule of rates Most appropriate structure will depend on the particular circumstances and nature of the work Contracts can include a combination of pricing methods Pricing structure is not the same as the contract structure Lump sum = pricing structure EPC, Turnkey, etc. = contract structure In-House Counsel Day 2015 4 2 17/03/2015 Lump sum / fixed price Contractor provides fixed sum for the completion of the whole of the works Rarely is it absolute – usually subject to adjustment Suitable when extent of work is known and work can be can be accurately priced Not appropriate if the scope of work is not known or well defined at the commencement of the contract Can be easy to administer Lump sum/fixed price method impacts on relationship between principal and contractor In-House Counsel Day 2015 5 Lump sum / fixed price - variations Contract will invariably allow the fixed price to be increased in certain circumstances: usually when the scope of work has been varied by the principal; or for cost increases which the contractor could neither reasonably foresee or control, such as latent conditions, industrial action and change in law. Should be clear processes set out in the contract for claiming and determining a variation In-House Counsel Day 2015 6 3 17/03/2015 Provisional sums Provisional sums are used when the principal has not yet decided whether to include certain items as part of the scope or the items are to be included but the quantity or type is not yet known Process for converting the provisional sum into a confirmed part of the scope must be clearly set out in the contract Key issues to consider and document include: clear description of scope reasonable estimate (the provisional sum) process for pricing Contractor entitlement to profit In-House Counsel Day 2015 7 Cost reimbursable Cost-reimbursable or cost-plus structure compensates the contractor for the costs of the work completed with added amounts for profits and overheads Principal carries the risk of project costs increasing Requires detailed records and verification of costs to be reimbursed (often referred to as "open-book") Can be an appropriate method when quantities are unknown or if the works involve new or complex methods or technology Allows for greater potential for transparency in relation to costs and profit In-House Counsel Day 2015 $700.00 $600.00 $500.00 $400.00 Cost $300.00 Costs + Profit $200.00 $100.00 $0.00 Time 8 4 17/03/2015 Schedule of rates Amount to be paid is based on an agreed price per unit of construction Unit of construction may be based on: time (e.g. hourly rate) quantity of material (e.g. tonnes of soil removed) quantity of construction completed (e.g. kilometres of pipe laid) The contract specifies units used and their value in a schedule usually called "schedule of rates" Risk allocation: principal bears risk of quantity necessary for job contractor bears risk for fluctuation in unit prices In-House Counsel Day 2015 9 Currency fluctuations Currency of pricing and payment is critical for cross border projects where: key items sourced for construction are priced in a currency different to the payment price where parties are headquartered in different jurisdictions and principally operate in different currencies Risk of currency fluctuations can be hedged against Fluctuations in exchange rates can also work in favour of a risk-bearing party Allocation of currency fluctuation risk should be expressly dealt with in the contract In-House Counsel Day 2015 10 5 17/03/2015 Rise and fall The direct costs of performing the construction contract are likely to rise and fall during the course of construction Not all risk cannot be controlled by the principal or the contractor Contracts may provide mechanisms for adjusting contract price to reflect changes in costs Cost adjustment may be applied to labour or materials If there is no adjustment mechanism for the rise and fall of long-term costs, contractors may when tendering: overestimate the costs (inflating the project costs) or underestimate the costs (risking the financial viability of the project) In-House Counsel Day 2015 11 Options for payment Options for payment: advance payments progress payments milestones value of work completed on-site off-site fixed Cash flow is critical In-House Counsel Day 2015 12 6 17/03/2015 Structures for payment – progress payments Value of work completed progress payments are the most common structure for payment in major projects Contractor remunerated for work completed during a given period Progress payment process: contractor submits a description of work completed during the previous time period, along with details of the value of the work completed work is certified and valued contractor is then paid the certified value of that work minus any retention, advance payment deduction or any other sum owing from the contractor to the principal In-House Counsel Day 2015 13 Progress payment as interim payment Progress payments are not final determinations of the value of the works Progress payments are an interim assessment of the value of the works In-House Counsel Day 2015 14 7 17/03/2015 Materials not yet incorporated Contract must clearly state when the contractor is entitled to be paid for materials which is ordered and partially complete but not yet incorporated into the works Must state: the materials and equipment that will be paid for; the amounts payable; timing and requirements for payment. Other issues to be dealt with are: when does title pass/who bears the risk/who must insure the materials; and the impact of the Personal Property Securities Act 2009 (Cth) (PPSA) In-House Counsel Day 2015 15 Subcontractors and employees Timing: responsibility of contractor to ensure that the timing of payment provisions under a main contract align with the timing of payments to subcontractors under any subcontracts Information requested from the subcontractor for payment should align with the information required under the main contract "Pay if paid" and "pay when paid" arrangements are prohibited by law throughout Australia A contractor cannot make the payment of its subcontractor contingent on the contractor being paid by another person (such as the principal) a provision of a construction contract that purports to do this has no effect In-House Counsel Day 2015 16 8 17/03/2015 Security of payment Each state has enacted legislation In WA it is Construction Contracts Act 2004 (WA) Key provisions include: act applies to defined work carried out in WA prohibition on pay if/when paid clauses maximum 50 days from claim to payment implied provisions if contract is silent on payment progress dispute adjudication process In-House Counsel Day 2015 17 Set off Right of set off common in construction contracts Set off rights allow the principal to set off any amounts owing from the contractor to the principal from any amounts the principal is otherwise obliged to pay the contractor under the contract For example: if contractor owes principal liquidated damages for late completion; and Liquidated Damages Progress Payments principal also owes progress payments to the contractor; then principal can deduct the amount of the liquidated damages owed from the progress payments the principal owes to the contractor. In-House Counsel Day 2015 18 9 17/03/2015 Remedies for non-payment Interest Suspension Termination Security of payment adjudication Dispute resolution In-House Counsel Day 2015 19 Conclusion Consider and agree methods that are best for project Ensure contract drafting is detailed and clear Train contract administrators Comply with the contract In-House Counsel Day 2015 20 10 17/03/2015 Questions In-House Counsel Day 2015 21 Key Contacts David Nancarrow Partner T: +61 8 6467 6028 [email protected] In-House Counsel Day 2015 22 11
© Copyright 2026 Paperzz