Choosing the Right Set of FIDIC Conditions of Contract for your Project Special Advisor, M.Sc., Michael Mortimer-Hawkins. Project Director, B.Sc., EE, Svend Poulsen, Atkins Danmark A/S, Denmark. Introduction FIDIC, the International Federation of Consulting Engineers (the acronym stands for the French version of the name), represents, globally, the consulting engineering industry. As such, the Federation promotes the business interest of firms supplying technology-based intellectual services for the built and natural environment. This paper gives an introduction to the first set of Conditions of Contract written and issued by FIDIC. The history At the mid of the 1950’s FIDIC decided to issue a standard form of Contract for international construction projects. This was the first Red Book. At the time it was felt that such a document would be suitable for all international work. Soon it became apparent that this was not the case and it was found that the Red Book was not suitable for Electrical and Mechanical projects. The Red Book did not deal with for instance plant life, design responsibility, guarantees etc. which just proved that it was impossible to include for everything in just one set of standard conditions of Contract. In 1963 FIDIC issued the first Yellow Book written especially for E & M projects. From the issue of the Yellow Book and until the end of the 80’s there was a choice of FIDIC Conditions of Contract: • The Red Book if the project mainly involved construction, and • The Yellow Book if the project involved mainly Electrical and Mechanical work. The two books reflected the differences in the disciplines or type of work. The Red Book was primarily covering civil works such as roads, dams, tunnels, bridges etc. The Red Book is based on the Works being designed by the Employer’s Consulting Engineer supported by detailed specification and drawings. The Yellow Book was tailored for electrical and mechanical work such as power stations, production facilities, plant etc., usually designed by the Contractor or the Supplier. The works would have a limited expected life depending on the nature of the facility and the normal life of an electrical and mechanical facility. Page 1 (9) © FIDIC The contracts also differed in that for a construction project the Engineer (on behalf of the Employer) produced a detailed Specification showing exactly what the Contractor was required to do and how to do it, with a detailed Bill of Quantities and the Contractor being paid for the work he did based on measurement of actual quantities, and the Contractor’s job was in effect, to do what he was told. Whereas with an E & M project, the Employer’s specification was often in the form of a Performance Specification which gave the Contractor the basic performance requirements which the Employer was looking for in the way of output and production and maybe layout etc. and it was the Contractor who made the design and constructed the facility to meet those performance requirements. Payment was usually based on unit item prices, such as 1 turbine or 1 generator, rather than detailed re-measurement. As a result the type and allocation of risk between the Parties differed between the Red and Yellow Books. The 1999 versions and the suite of Conditions of Contract Since then, the range of FIDIC contracts has increased considerably, mainly to meet the increasing demands of the market and the industry for more sophisticated contractual arrangements and procurement strategies. In 1999 FIDIC issued a totally revised set of Conditions of Contract, and we now have: Conditions of Contract for Construction (the Red Book), Conditions of Contract for Plant, Design-Build (the Yellow Book), Conditions of Contract for EPC/Turnkey (the Silver Book). Not surprisingly, these documents are now referred to as The FIDIC Rainbow Suite. The family has grown and now also includes: Conditions of Contract for Design-Build and Operate (Gold Book), Conditions of Short Form of Contract (Green Book), and Conditions of Contract for Dredging Work (Blue Book). Also, with the 1999-editions, the difference between the books is now not so much the discipline of the work to be done, whether it is a road or a power station, but more a question of design responsibility. The key question is “who is doing the design?” This is the key factor in determining who carries the major financial and commercial risks during the execution of the project. It is more a question of risk – and risks cost money. Page 2 (9) © FIDIC Choosing the right Form of Contract When the Employer chooses the form or book he intends to use for a given project, it is very important that he chooses the right book – the right set of conditions of Contract. The consequences of using the wrong book will be very serious and lead to all the things which the parties to a Contract are trying to avoid – divided responsibilities, confusion, disputes, delays, cost overruns etc. It is unfortunately the case that the contracts with problems often are the ones where the Employer has chosen to use the wrong form of Contract. Choosing the right form of contract involves a number of factors. Employers are generally looking for certainty of price and minimum risk. They see words like “Contractor’s Risk” and “fixed price”, and irrespective of any other considerations – that is what they want and that is the book they choose. They may also prefer an “Employer’s Representative” to an “Engineer” believing it puts them one step ahead when it comes to claims and disputes. And of course, any reference to “Employer’s Risks” is to be avoided at all costs. So changes are introduced into the Conditions of Contract by the Employer where all “Employer’s Risks” mysteriously become Contractor’s Risks, and where disciplines and time bars etc. against the Employer fade away in some strange re-wording of the offending clauses. All these changes move the set of conditions away from the intention of having a balanced set of contract conditions which is one of the fundamental issues of the FIDIC Conditions of Contract. And yet Employers will still call it ‘a FIDIC Contract’. It is not only important to use the right set of Conditions of Contract, but it is also equally important – especially for the Contractor – to make sure that the Contract is what it is made out to be e.g. that it is in fact a Red Book contract and not a somewhat distorted form of the Red Book. Some key FIDIC issues Principles of the FIDIC Conditions of Contract The FIDIC suite of Conditions of Contract (CoC) is based on 20 clauses in the different CoC and the same structure can be found throughout the different set of conditions. Generally, FIDIC Conditions of Contract (CoC) include three parties Employer, Engineer, Contractor. Also, as you will note, all defined terms are written with capital letters throughout the conditions of contract. The purpose of this is to make the interpretation of key words, and terms, exact. Page 3 (9) © FIDIC Reasonable risk sharing FIDIC also firmly believes that the way to handle project risk is one of fair risk sharing; FIDIC finds this approach will lead to better and more successful projects. By allocating the risk to the Party that is best placed to control it and deal with it, will result in more efficient and effective risk handling. The role of the Engineer The Engineer acts as an agent of the Employer. This is often criticised by contractors that find it difficult to see that the Engineer can indeed act fairly when deciding matters under the Contract, while being paid by the Employer. Some Employers even omit the Engineer when using FIDIC CoC and replace the Engineer by a person within their own organisation or the Employer may even redefine the role of the Engineer to a more project management role. To make the FIDIC CoC work properly it is paramount that the Engineer has a technical insight. The basis for the FIDIC CoC is that the Engineer has a very important role in administering the Contract and in making fair decisions. His authority is described in the Contract and he cannot amend the contract. For this to work, the Engineer shall act impartially when carrying out certain actions, which include making determinations in accordance with sub-clause 3.5. The philosophy is that fair decisions by the Engineer keep the focus on the execution of the Works. Should any party not be satisfied with the Engineer’s determination, that party can raise the Engineer’s determination to a Dispute Adjudication Board (DAB); a body that is jointly appointed by the Parties for prearbitral decision. The intention of having the DAB is to allow for disputes being handled in a real-time fashion and to avoid disputes, if practicable, from being settled through costly arbitration. Design obligations of the Contractor In the FIDIC Contracts, the Contractor has design obligations under the Plant and Design-Build CoC (The Yellow Book), the EPC Turnkey CoC (The Silver Book) and the Design, Build and Operate CoC (The Gold Book). The Contractor obligation is to carry out the design in a way that ensures that the Works are fit for the purposes for which the Works are intended (see for instance P&DB scl. 4.1). This does not only put a major responsibility on the Contractor, but also gives the Employer an obligation to describe the purpose of the Works in a very unambiguous and exact fashion. This is accomplished in the Employer’s Specifications or Employer’s Requirements depending on which form of Contract is used. Page 4 (9) © FIDIC Finding the suitable Form of Contract The principles of Risk sharing The principles of risk sharing and Employer’s involvement and influencing the project during design and construction decide some of the fundamentals in choosing the right form of contract. “There is no such thing as a free lunch” – the same counts for the transfer of risk without it having influence on other factors. The price the Employer pays to let the Contractor handle the risk is losing influence under the design and construction phase. The traditional set up with the Employer transferring his ideas and thoughts into drawings and specifications lets the Employer be in control of every solution to his indentified needs and ideas. This also includes the ownership of the major part of the risks. The Employer has the ability to control these risks and can raise a budget to mitigate risks occurring. In the other end of the spectre is the situation where the Employer looks for a high level of certainty and will pay for the Contractor to take all risk. This is the argument for using the EPC/Turnkey set up. The price is that the Employer cannot interfere with the design or make changes without taking over some risk and also the costs related to the “disturbance” of the Contractor’s work. Small projects If the project is of relatively small value, say under US$ 500,000, has a short construction time (less than 6 months) or involves well know products/work the Short Form of Contract (Green Book) would be sufficient for such projects. It doesn’t matter whether the design is provided by the Employer (or his Engineer) or by the Contractor and it doesn’t matter whether the project involves construction, electrical, mechanical, or other engineering work. Large complex projects The Employer could have an interest in conducting the design himself or hire a team of consultants to do the necessary design. Employers with complex projects and a need for maximum influence before the works are contracted and the right to vary during construction should decide for the “traditional” form of contract i.e. the Conditions of Contract for Construction for Building and Engineering Works Designed by the Employer (Red Book). The Conditions of Contract for Construction is typically used for projects, such as infrastructure, buildings, hydropower, roads and bridges etc, with the Engineer administering the Contract, and certifying payPage 5 (9) © FIDIC ment, and with payment according to bills of quantities or lump sums for work done, and with variations being controlled and ordered by the Engineer. Should the Employer decide to contract the works based on a performance specification or a set of Employer’s Requirements to let the Contractor take care of the detailed design another type of FIDIC Conditions of Contract should be used. Performance specifications prepared by the Employer can be used for traditional electrical and mechanical projects including the supply of plant and equipment where the majority of the design will be done by the Contractor. Also other engineering and construction projects where the Contractor is responsible for carrying out most of the design work based on an outline or performance specification prepared by the Employer requires another type of contract. In these types of projects the Engineer will administer the project and certify payment is usually based on milestones or lump sum basis. In these cases the Conditions of Contract for Plant and Design-Build for Electrical and Mechanical Plant and for Building and Engineering Works Designed by the Contractor (Yellow Book) should be used. Where the Employer is looking or higher degree of certainty that the agreed contract price and time will not be exceeded and the Employer wishes to use his own (Employer’s) Representative rather than an Engineer and does not wish to be involved in the day-to-day administration of the project, then the Employer should choose the Conditions of Contract for EPC Turnkey Projects (the Silver Book). For major infrastructure projects (e.g. road, rail link, bridge, water or sewage treatment plant, transmission line, even dam or hydropower plant or similar) where the Employer provides the finance there is often a requirement for a high level of certainty to cost and time. The straight forward choice is to use a contract form suited for Turnkey or EPC projects. FIDIC has the Conditions of Contract for EPC/Turnkey projects (the Silver Book) for use in these situations. If it is a Building Project where the Employer wishes to have his building(s) constructed on a Fixed-Price Turnkey Basis generally complete with all furniture, fittings and equipment, then again, the Employer should consider the Conditions of Contract for EPC Turnkey Projects (i.e. the Silver Book) but, depending on the nature of the project, certain modification may be necessary. Using the EPC/Turnkey contract form it is important, that the Contractor has sufficient time to inspect and assess the risks he will be expected to carry under the Silver Book. The Contractor will for instance need to examine the ground conditions as he is to carry the risk of unforeseen conditions etc. If the time does not allow for thorough inPage 6 (9) © FIDIC vestigations by the bidders (Contractors) and also if the Employer is not capable of precisely issue a set of Employer’s Requirements he should not choose the Silver Book. It would then be more suitable to use the Yellow Book as mentioned above. Projects involving the operational phase With a Design Build project where the Employer wishes the Contractor to provide a long term operation service of the plant or facility and where the Contractor is responsible for the design and construction of a facility based on an outline or performance specification prepared by the Employer and then operates the facility for a long term (typically more than 20 years) including the maintenance and replacement of parts and assets as necessary, before handing it over to the Employer for him to continue operating the facility himself, then, if it is a new facility (a Green Field scenario), the Employer should be looking at the Design, Build and Operate form of Contract (the Gold Book) If the work involves the refurbishment or renovation of an existing facility this is called a Brown Field scenario. FIDIC is currently preparing a new set of conditions especially for this type of projects. The FIDIC Suite of Contracts covers the majority of projects FIDIC provides a wide range of Books to choose from, and as mentioned, it is essential that the Employer selects the right form. Each form has been written to minimise the risk of disruption and dispute for the particular type of work and/or project, and if the wrong form is chosen, not only will these benefits be lost, but the likelihood is that the project will cost more for both parties. Upcoming Conditions of Contract After the successful issuing of the FIDIC Conditions of Contact for Design-Build and Operate (DBO) it has been decided to also produce a set of conditions of contract that will be suitable for major plants or infrastructure where the owner wants to hire a contractor for the continued operation and upcoming refurbishment of the facilities. This is what is classified as a brown field scenario that comprises Operation, Design and Build (ODB). FIDIC expects to issue this form in 2013. In cooperation with the International Tunnel Association (ITA) FIDIC is working to produce a form of contract suitable for tunnel works. In general FIDIC is very aware of market requirements for new types of contracts. Often the existing suite can cater for the requirements in the industry but if a special field of business calls for a new contract form this is considered. For instance the growing market in sustainable energy that for instance includes wind farms and not the least off-shore wind farms could trigger a combination of the Dredging and Page 7 (9) © FIDIC Reclamation Conditions of Contract combined with the set of condition for Plant and Design-Build. Page 8 (9) © FIDIC Contact Details FIDIC World Trade Center 2 Geneva Airport PO Box 311 CH-1215 Geneva 15 Switzerland Tel: +41 22 799 49 00 Fax: +41 22 799 49 01 [email protected] www.fidic.org Managing Director Enrico Vink General Manager Francois Baillon Page 9 (9) © FIDIC
© Copyright 2026 Paperzz