Ontario Centers of Excellence DynaPlas Ltd: Green Plant Project by Mashal Kara A thesis submitted in partial fulfillment of the requirements for the degree of BACHELOR OF APPLIED SCIENCE Supervisors: W.L Cleghorn J.K. Mills Rick Packer Robert Kuhi Department of Mechanical and Industrial Engineering University of Toronto Executive Summary DynaPlas Ltd is an injection-molding manufacturer that caters to the automotive industry in North America. As the current economic crisis caused the big North American automotive manufacturers to reduce production, DynaPlas was forced to lay off 75% of their full time staff due to production losses in the past year and a half. As production decreases, the plant’s overhead costs begin to weigh more on the product pricing thus affecting DynaPlas’ ability to remain competitive. In the year 2007-2008, DynaPlas spent M$ 980 in electricity and natural gas. The purpose of this project was to reduce the energy consumed by the plant while maintaining or improving production quality and working conditions. We focused the scope of the project on the natural gas usage by and attempt to reduce the quantity of outside air we need to heat and introduced into the plant. Currently, the plant is exhausting a lot more air than it is forcing in to make sure all fumes are exhausted. The suggested system captures fumes from the source of the emissions allowing us to reduce the plant’s air changes per hour thus reducing the natural gas consumption. Implementing this system at DynaPlas will cost M$ 115 and will generate M$ 185 in energy savings every year thereafter. This project’s payback period of 0.62 heating seasons makes it highly feasible and we would recommend DynaPlas to go ahead with the work in early fall. Although this project was designed to be implemented at the DynaPlas injectionmolding facility, it can be repeated at any other manufacturing plant having a large volume of exhaust. 2 Acknowledgments: This project was accomplished with the support of DynaPlas Ltd and The Ontario Centers Of Excellence. Throughout the project, we appreciated the help of Rober Kuhi, Rick Packer, Ronnie Fong, Stephanie Ruthard and Johann Schimd without whom we would not have been successful. 3 Table of Contents Executive Summary ................................................................................................................. 2 Acknowledgments: .................................................................................................................. 3 Table of Contents ...................................................................................................................... 4 i. List of Figures: ........................................................................................................................ 5 ii. List of Tables.......................................................................................................................... 6 iii. Project Charter .................................................................................................................... 7 1. Motivation: ............................................................................................................................. 8 2. Energy Usage in the Plant............................................................................................... 10 2.1 Electrical usage: ........................................................................................................................ 10 2.2 Natural Gas Usage:.................................................................................................................... 12 3. Background information ................................................................................................ 14 3.1 Make Up Air Unit (MUA): ....................................................................................................... 14 3.2 General Room Exhaust Fan: .................................................................................................. 14 3.3 Unit Heater: ................................................................................................................................ 15 4. Current situation ............................................................................................................... 16 5. Proposed Solution: ........................................................................................................... 20 6. Cost/Benefit Analysis ...................................................................................................... 22 6.1 Baseline costs: ........................................................................................................................... 22 6.2 Benefits of Proposed Solution: ............................................................................................ 23 6.3 Installation Costs: ..................................................................................................................... 24 7. Problems encountered: .................................................................................................. 26 8. Conclusion: .......................................................................................................................... 28 Appendix A: Union gas calculator .................................................................................... 29 Appendix B: Quotes............................................................................................................... 30 B-1: PlymoVent Quote: ................................................................................................................... 30 B-2: Lincoln Electric Quote ........................................................................................................... 32 B-3: Tin Knockers Quote: .............................................................................................................. 33 Appendix C: Movable arm data sheet ............................................................................. 34 Appendix E: Updated Plant shutdown procedures .................................................... 41 Appendix F: Electrical usage .............................................................................................. 43 Appendix G: Natural gas usage.......................................................................................... 44 4 i. List of Figures: 1. Control chart KWh/kg of material melted…………………………………….......11 2. Control chart m^3 of natural gas/kg of material melted…………………...13 3. Roof map of HVAC equipment……………………………………………………………16 4. Location of all Unit heaters in the Plant……………………………………….....…16 5. Current exhaust strategy…………………………………………………………………..19 6. Point source exhaust system……………………………………………………………..20 7. Proposed Location of all Unit Heaters in the plant…………………………….21 5 ii. List of Tables 1. Equipment Volumetric Flow rate………………………………………………………17 2. Electrical benefits……………………………………………………………………………..24 3. Total implementation costs………………………………………………………………25 6 iii. Project Charter Project name: Green Plant Project Problem statement: In 2007-2008, DynaPlas spent M$ 980 in energy costs; as production is reducing, the overhead costs are weighing more on the plant’s ability to remain competitive. Project Goal: Reduce the overhead costs by reducing the amount of energy used at DynaPlas’ facility while maintaining or improving production quality and working conditions. Scope of the project: Electricity and natural gas usage. Project Leader: Mashal Kara Team: Mashal Kara, Rober Kuhi, Rick Packer, Jamie Waduck, Kevin Jenkins Customer Critical To Quality’s: Employee comfort and good production quality Defect: Energy consumption Cost of Poor Quality: $ 0.10 per kWh, $0.73 per m3 of natural gas 7 1. Motivation: DynaPlas is an injection molding company that caters to the automotive industry. Over the last few years as the big North American automotive companies have been reducing their production and sending more of their business to China, DynaPlas as most other manufacturing facilities were forced to make production adjustments that affect the way they run their plant. In the past they would run 24hrs a day and 7 days a week but due market changes they have been reduced to 5 days a week leaving the plant idle on weekends. In the last year and a half, they have laid off about 75% of their full time staff due to production losses. The reduced production causes DynaPlas’ overhead costs to carry more weight on the price of their products thus impacting the competitiveness of the company. A big part of the plant’s overhead is in their energy usage, which will be the main focus of this project. In the year 2007-2008 the plant used 7.4 million kWh of electricity and 330 thousand cubic meters of natural gas a year to run their equipment and maintain their buildings. This usage leads to total energy spending of $ 980,000. It has been noticed that energy is being wasted in many areas of the plant and it is in need of a study to determine which opportunities are the most feasible and attempt to implement a sustainable solution. 8 Reducing the plant’s energy consumption will reduce its overhead costs thus allowing DynaPlas to offer more competitive prices to their customers and gain more business. This project aims to reduce the plant’s environmental footprint allowing the company to better market its products as the World’s population becomes more conscious of the industry’s environmental impact. This will also make government grants and subsidies available to reduce the investment costs needed to complete the project. 9 2. Energy Usage in the Plant At DynaPlas, as in many other manufacturing plants, the main sources of energy are electricity and natural gas. In this section we will analyze where these two sources of energy are being used to determine where our opportunities lie. 2.1 Electrical usage: DynaPlas pays 10 cents for each KWh consumed. In the fiscal year 2007-2008, the plant used 7.5 million KWh thus spending M$ 750 in electricity. When scoping the plant we found that electricity was being used for the following purposes: Injection molding machines: The machines use electrical current to control the heat load used to melt plastic pellets before they are extruded into the molds. This process is highly sensitive and needs to be precisely controlled thus cannot be performed using any other energy source. HVAC equipment: There are many fans and blowers in the plant used to circulate and temper the plant’s ambient air. These equipments contain motors that are all electrically operated. Air Compressor: Compressed air is used to cool the molds and plastic parts after they are formed. The plant has an air compressor that cycles to maintain a specific pressure in the plant’s piping. Offices: Computers, printers, photocopying machines and other office equipment also consume electricity. 10 Lighting: All plant and office lighting. The assumption was made that most of the electrical load was from running the injection molding machines thus assuming that electrical usage in the plant was correlated with production. In order to prove the above assumption, we used the amount of kg of material melted in a month as a metric to represent production and divided it by the total KWh consumed in a month. If the assumption above were true our ratio would yield a constant. The data was then entered in MiniTab to obtain the following control chart: Figure 1: Control chart KWh/kg of material melted From Figure 1, we can see that this process in under control thus the assumption made earlier is valid: Electrical usage is strictly correlated with production. 11 2.2 Natural Gas Usage: DynaPlas pays 73 cents per cubic meter of natural gas. In the fiscal year 20072008 the plant used 330 thousand cubic meter of natural gas thus spending M$275. The plant was also scoped to determine where natural gas was being used. We learned that natural gas was not used in any production equipment and its sole usage in the plant was for space heating and employee comfort. We then made the assumption that the amount of natural gas used depended on the outside temperature. To prove the above assumption we used a metric called a Degree Day. A Degree Day is a measure of heating or cooling by measuring the difference in temperature from the heating set point (usually 18 degrees C). We then divided the total cubic meters of natural gas used in a month by the total Degree Days in that time period. If the assumption made above is true, the ratio would yield a constant. The data was then entered into MiniTab to obtain the following control chart: 12 Figure 2: Control chart m^3 of natural gas/kg of material melted Observing Figure 2 we can see that this system is under control thus the assumption made earlier has been verified: Natural gas usage depends on the outside temperature. Knowing where each energy source is being used and the factors that control their demand we were able to narrow the scope of our project. We decided to focus on reducing the plant’s natural gas usage in the winter since it did not affect production and is a main contributor to the overhead costs. 13 3. Background information DynaPlas owns and uses different HVAC equipment such as Make Up Air (MUA) units, General Room exhaust fans and Unit Heaters. In this section we will be giving a brief background on each of these units. 3.1 Make Up Air Unit (MUA): The primary reason for using Make Up Air units is to prevent negative pressure from building up inside the building. They take air from outside, pass it through a burner in the winter and deliver ambient temperature air into the plant. Since there is no heat exchanger MUA units introduce CO2 into the building thus should not be operating without adequate exhaust for the safety of the plant employees. 3.2 General Room Exhaust Fan: General Room Exhaust fans take air from the plant and deliver it into the atmosphere. They are positioned on the roof, which makes them very cost effective at removing heat from the building in the summer. When an injectionmolding machine jams up, it burns plastic and generates some fumes. These fumes can be harmful to the plant’s employees. In the winter, the creation of fumes is the only reason why these exhaust fans are running. 14 3.3 Unit Heater: Unit Heaters are used to increase the plant’s ambient temperature. They recycle air from within the plant, heat it by passing it through a heat exchanger and redeliver it into the plant. The use of a heat exchanger ensures no products of combustion enter the plant and makes the unit more efficient by not introducing cold outdoor air. 15 4. Current situation The plant currently owns three (3) MUA units, seven (7) general room exhaust fans and six (6) unit heaters, see figures 3 and 4 for their locations in the plant. Figure 3: Roof map of HVAC equipment Figure 4: Location of all Unit heaters in the Plant All the injection-molding machines are located on the left side of the building; the right side is used for storage and has no air exchange with the environment. 16 In the past production had been consistently running 24/7 thus the heat generated by the injection molding machines, the MUA units and employees present was sufficient to keep the building temperature at reasonable levels without the use of the Unit Heaters in the winter. Because of the busy production schedule, maintenance for the unit heaters was neglected therefore most of them stopped working and some have also been removed. The purpose of the seven (7) general room exhaust fans is to remove heat from the building in the summer and to remove some fumes generated by the injection molding machines during production. Currently, all exhaust fans remain on during production and idle shifts. To balance all the exhausted air in the plant, all three (3) MUA units also run continuously. Table 1 shows the volumetric flow rate of each fan: Table 1: Equipment Volumetric Flow rate Exhaust fans 1 2 3 4 5 6 EF1 MUA 1 2 3 CFM hp 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 17,000.00 77,000.00 4 4 4 4 4 4 7 CFM (15,000.00) (15,000.00) (17,000.00) (47,000.00) hp 15 15 17 17 The 30,000 CFM imbalance created by the excess exhaust forms a partial vacuum in the plant. The natural forces attempt to balance inside and outside air pressure by pulling in replacement air from doors, windows and holes in the building construction. This leads to uncomfortable drafts, stagnant air pockets, cold offices, and reduces the efficiency of the plant’s ventilation equipment. Given the current settings, the plant undergoes 8 air changes per hour. In the winter all the air brought into the plant needs to be tempered thus reducing the number of air exchanges would reduce the natural gas usage. The reason for these many air exchanges is to remove the fumes generated by the injection molding machines. Figure 5 represents the current exhaust strategy: 18 Figure 5: Current exhaust strategy Currently, the exhaust fans are twenty (20) feet above the source of the fumes. This process of exhaust is highly inefficient and requires a lot of exhaust capacity. 19 5. Proposed Solution: To reduce the amount of air exhausted we decided to replace our current exhaust system with a point source system. This will allow us to capture the fumes at the source of emission thus reducing the required flow rate. Figure 6 below is a schematic representation of the proposed system. Figure 6: Point source exhaust system The arms will need to be flexible to accommodate machine attendants when a mold needs to be changed (See Appendix C). We would like to have this system implemented on forty-one (41) machines along three lines. Each line will have a circular trunk duct go across the plant and finish at the roof to exhaust the fumes out to the atmosphere. The arms will be branching off from the main truck duct as it goes over each machine. 20 We have also selected three (3) fans so that the volumetric flow rate at each unit will be around 250 cfm (See Appendix D). The size of the ducts was determined from the convention of having a flow velocity of 3000-4000 feet per minute. This system would reduce our required exhaust flow rate to less than 15,000 cfm, allowing us to permanently shutdown two (2) out of the three (3) MUA units. In the winter, during production we would have one (1) MUA unit and our new exhaust system running, this will balance the air exchanges in the building and not create any negative air pressure buildup. On idle shifts, all ventilation equipment will be turned off and the plant’s unit heaters should sustain the building heat. To make sure the plant temperature remains reasonable on the weekends, we would need to repair all damaged unit heaters and install three (3) additional ones as shown in figure 8. Figure 7: Proposed Location of all Unit Heaters in the plant We have updated the plant shutdown and startup procedures to make sure the settings remain consistent regardless of the operator (See appendix E). 21 6. Cost/Benefit Analysis This project suggests different settings on production (weekdays) and idle (weekends) shifts. We will first calculate the estimated costs of our current baseline and compare it with the data collected from DynaPlas’ energy bills to validate our calculations. We will use the same methodology to calculate the expected savings on weekdays and weekends. Then we will discuss the cost associated with this project and analyze its feasibility. The Natural gas costs were estimated using a calculator produced by Union Gas (See Appendix A) based on the following equation: 6.1 Baseline costs: For out baseline we inputted the following data: Flow rate: 47,000 cfm Supply air temperature: 75 F Average outside temperature: 35 F Number of hours in heating season: 5300 hrs Number of hours of operation per week: 168 hrs/week (24/7) Incremental natural gas rate: 0.73 $/m3 The calculator outputted the Cost of operation: $225,167 22 The actual total cost of natural gas as reflected on DynaPlas’ bills amounts to M$ 275, which including office heating. It can thus be assumed that the calculator provides an accurate estimate and that M$ 50 a year is spent to heat the offices. 6.2 Benefits of Proposed Solution: The following data was entered in the calculator as the improvement made to the case above: Flow rate: 15,000 cfm Supply air temperature: 75 F Average outside temperature: 35 F Number of hours in heating season: 5300 hrs Number of hours of operation per week: 168 hrs/week (24/7) Incremental natural gas rate: 0.73 $/m3 The calculator returned the following output: Average annual cost saving: $ 173,837 Implementing these changes will reduce the plant’s natural gas bill by M$ 174 a year. As a result of this project, we have been able to reduce the plant’s electrical load in the winter by 38 hp. The electrical savings need to be calculated based on the 25 week heating season this project will be affecting. Table 2 summarizes the calculations made: 23 Table 2: Electrical benefits hr/week # of weeks HP kW/HP Load Factor Before 168 25 78 0.746 0.75 After 120 25 40 0.746 0.75 kW kWh 43.641 183,292.20 22.38 67,140.00 This project will reduce the plant’s load by 116,000 kWh per year saving an additional M$ 11.6 The total energy savings for this project will be M$ 185.6 per year. 6.3 Installation Costs: After finalizing the design, we contacted a list of suppliers to purchase and install the equipment. PlymoVent and Lincoln Electric provided the following quote (See Appendix B-1 and B-2): Material (41 hanging arms, 41 extension columns, 3 fans): $45,965 $90,920 Installation and ducting: $55,882 - $56,000 We also acquired quotes for the additional Unit Heaters from the Tin Knockers (See Appendix B-3) at $4,500 each. Other internal costs will be associated with the electrical installation to finalize the job and the completion of a Certificate of Air Emissions. Being an energy saving initiative, this project would qualify for many government grants and incentives 24 available to reduce the investment costs. Table 3 illustrates all the costs associated with this project. Table 3: Total implementation costs Material Ducting Unit Heater $45,965.00 $55,882.00 $13,500.00 $115,347.00 Given the costs and benefits described above, this project will yield a payback time of 0.62 heating seasons or less than 16 weeks. It is financially worth completing this project given high benefits and low payback period. It would be recommended to begin the installation in early fall, before the heating season begins to minimize the payback time. In addition to financial benefits, this project will have solved the negative air pressure problem within the plant. The building being balanced will have not have any drafts from windows, doors and holes in the building structure. As a result, employees will be more comfortable and the exhaust system will be able to better capture fugitive fumes from the injection molding machines. 25 7. Problems encountered: In this section, we will talk about some of the obstacles we encountered and what we did to over come them. Given the nature of the project, many employees will be affected by the changes made. When scoping the plant, it was very difficult to obtain real information because each employee had a different understanding of the process. Information was initially gathered from many different employees then verified physically by following pipes, conduit and looking at technical drawings. Given the large scope of the project, there were many factors to consider thus lengthening the task of gathering information. As the project progressed, we became familiar with each employee’s area of expertise and knew what information they could each produce accurately. Many times, instructions were sent to machine attendants or mechanics through their supervisors and miscommunications occurred or feedback was not conveyed back to the project leaders. To bridge these lapses and build trust with all the employees affected, we spent a lot of time communicating the goals and progress of the project with all employees. This also helped us get the employees buy-in on the project and they communicated directly with us when issues arouse. 26 Six (6) months into the project, one of our industry supervisors, Robert Kuhi was laid off as the business was going through some difficult economic times. Robert was our main contact person at the plant and his removal made completing the project more difficult. In the early stages of the project, Robert had introduced us to all the plant’s key employees and explained to us what their area of expertise was. Knowing where to get the information needed, we were able to continue the project without losing a significant amount of time. As we gathered quotes for the installation of the system, suppliers were not consistent in how they quoted the job making the comparisons more difficult. We were obliged to thoroughly review each quote to make sure they were identical. 27 8. Conclusion: Implementing this project will significantly reduce DynaPlas’ energy consumption and save M$ 185.6 every year there after. This cost reduction will allow the company to be more competitive as it reduces its overhead thus increasing market share. This initiative will also create a new marketing strategy by becoming a greener plant. These increases in sales will allow DynaPlas to re-hire some of the employees laid off earlier this year and help the company survive through the current economic crisis. This project, although specific to DynaPlas can be repeated in other manufacturing facilities that exhaust large amounts of air due to their process. 28 Appendix A: Union gas calculator 29 Appendix B: Quotes B-1: PlymoVent Quote: 30 31 B-2: Lincoln Electric Quote 32 B-3: Tin Knockers Quote: 33 Appendix C: Movable arm data sheet 34 35 Appendix D: Exhaust fan data sheets 36 37 38 39 40 Appendix E: Updated Plant shutdown procedures 41 42 Appendix F: Electrical usage 43 Appendix G: Natural gas usage 44
© Copyright 2026 Paperzz