BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION AT GANDHINAGAR Petition No. 1512 of 2015 In the matter of: Petition under Section 94 of the Electricity Act, 2003 and Regulation 45 read with Regulation 21 of GERC (Terms and Conditions of Intra-state Open Access) Regulations, 2011, Notification No. 3 of 2011 for Intra-State Open Access, against Short-Term Open Access transmission charges collected by SLDC for days for which the power is non-traded/under traded after receiving NOC from SLDC for respective months and for refund of Rs. 15,94,024.00 paid to SLDC against total of their demand dated 28.01.2015 and 16.04.2015. Petitioner : Steelcast Limited, Ruvapari Road, Bhavnagar – 364005 Represented by : Shri Vikram Shah V/s. Respondent No. 1 : State Load Dispatch Centre (SLDC) 132 KV Gotri Sub-station Compound, Near T B Hospital, Gotri Road, Vadodara – 390021. Represented By : Learned Advocate Shri M.G.Ramachandran with Shri H.D.Sharma Respondent No. 2 : Gujarat Energy Transmission Corporation Limited, Sardar Patel Vidyut Bhavan, Race Course Circle, Vadodara – 390007 Represented By : Learned Advocate Shri M.G.Ramachandran with Shri Amit Sachan and Ms. Venu Birappa Page 1 CORAM: Shri P.J.Thakkar, Member Shri K. M. Shringarpure, Member Date: 07/07/2016 ORDER 1) The present petition has been filed by the petitioner seeking following reliefs: i) To quash all the invoices raised against the short term open access consumers on maximum capacity as indicated in NOCs. ii) To direct SLDC to refund all payment collected under the Short Term Open access charges for reserved capacity for non-traded and undertraded days. iii) To direct SLDC and GETCO to take approval of the Commission prior to collection of charges from the open access consumers in similar cases. 2) The facts of the case as mentioned in the petition are as under: 2.1. The petitioner is a public limited company registered under the Companies Act, 1956 engaged in manufacturing of castings and related business. The petitioner is a consumer of the PGVCL having consumer No. 23064, Page 2 contract demand of 6000 KVA and receiving the electricity at 66 KV voltage. 2.2. A notice was issued by State Load Dispatch Centre on 19.04.2015 to the petitioner stating that as per the GERC (Terms and Conditions of IntraState Open Access) (First Amendment) Regulations, 2014 the transmission charges for Short Term Open Access shall be payable by the STOA consumer at the maximum capacity reserved for that consumer. 2.3. Accordingly, the SLDC started charging the transmission charges on the quantum of Short Term Open Access granted, even in cases where the NOC for collective transactions was issued by SLDC, but the power was neither traded nor scheduled. 2.4. As per CERC (Open Access in Inter-State Transmission) (amendments) Regulations, 2009, which is applicable to STOA, it is clearly stated in Chapter -3 that the Long Term customer and the Medium Term customer shall have priority over the Short Term Open Access customer for use of Inter-State transmission system. In other words, the STOA customer can have access to transmission line, if spare capacity is available with Inter- Page 3 State transmission system after catering to all Long Term and Medium Term customers. 2.5. The provision of transmission charges for the Short Term Open Access on the maximum capacity reserved, in GERC (Terms and Conditions of IntraState Open Access) (First Amendment) Regulations, 2014 under which the respondents have been claiming such transmission charges, was also there in the GERC (Terms and Conditions of Intra-state Open Access) Regulations, 2011. But no such invoices were issued under Clause 21 of the said Open Access Regulations, 2011 till April, 2014. As such this was a new practice adopted by SLDC for which SLDC should have taken the permission of GERC, before issuing such invoices to the STOA consumers. 2.6. As per Section 2 (74) of the Electricity Act, 2003, the definition of “transmit” means as conveyance of electricity by means of transmission lines and the expression “transmission” shall be construed accordingly. In other words, transmission charges are applicable if, and only if the energy is transmitted through the transmission lines. If energy is not conveyed through transmission lines, then transmission charges are not applicable and no invoice can be raised for transmission charges in such cases. Page 4 2.7. As per Central Electricity Regulatory Commission (Open Access in InterState Transmission) Regulations, 2008 and its subsequent amendments, the Long Term customer and Medium Term customer shall have priority over the Short Term Open Access customer for use of Inter-State transmission system and the Short Term customer shall be eligible for Short Term Open Access if surplus capacity is available on the Inter-State transmission system after use by the Long Term customer and Medium Term customer. So in line with the above, the transmission charges are decided based on the total power required to be transmitted by Long Term and Medium Term customers. Similar provision is made in the GERC (Terms and Conditions of Intra-State Open Access) Regulations, 2011. Thus, the transmission charges are fully recovered from Long and Medium term customers and STOA customers are paying the charges to STU for the spare capacity available in the transmission lines at a particular time when power is transmitted for him. In line with this theory, the STOA transmission charges in Gujarat were kept at one fourth of the charges for long term and medium term open access customers. Hence, the collection of charges from STOA customers for the reserved capacity is out of context. Page 5 2.8 In Gujarat State, the open access policy is governed by GERC (Terms and Conditions of Intra-state Open Access) Regulations, 2011. Regulation 21 (2) (i), of the said Regulations clearly indicates that the total transmission cost is to be shared by all long-term and medium-term open access customers. In other words it can be explained that the transmission charges are fully recovered from long term and medium term customers and the STOA customers are paying charges for the spare capacity, if any, available in transmission lines at a particular time when power is transmitted for them. 2.9. Further, the provisions of Regulation 21 (2) (ii) is misinterpreted by the respondents. In case if the actual scheduled energy is less than the NOC received by STOA consumer then the transmission charges can be collected up to a maximum capacity kept reserved for that particular date for STOA consumer. There is no question of reserving capacity for STOA consumers in Inter-State or Intra-State transmission network as scope itself says that STOA will be allowed only if spare capacity is available in the transmission network. Page 6 2.10 GERC (Terms and Conditions of Intra-state Open Access) Regulation, 2011 has provisions to deal with under utilisation or non-utilisation of open access capacity in intra-state transmission system. On examination of the provisions for under utilisation of open access capacity, it is evident that there is a provision for relinquishment of right to access only in relation to long-term open access consumers. There is no provision for relinquishment of right to access for Short Term Open Access consumers as they do not have right to access to the transmission system. As such compensation for stranded capacity for such non-utilisation/underutilisation is to be borne by the long term and medium term open access consumers for such relinquishment. 2.11 As per Minutes of Meeting dated 24.11.2011 held by the Commission, with regard to Open Access issues, it is minutised that the Open Access transactions through power exchanges are to be treated as collective transactions and to be dealt with according to the Inter-State Open Access Regulations of the CERC. 2.12 As per amendment made in Clause 10 in Regulation 16 and Clause 11 in Regulation 20 of CERC (Open Access in Intra-State Transmission) Regulations, 2009 for collective transactions except transmission charges Page 7 specified in the aforesaid Regulations no charges are payable by Short Term Open Access consumer. Therefore, the charges collected by SLDC are in violation of CERC Regulations, 2009. [3] Respondent State Load Dispatch Centre (SLDC), in reply to the petition, submitted that the transmission charges are being recovered strictly as per the provisions of GERC (Terms and Conditions of Intra-State Open Access) Regulations, 2011 as notified by the Commission. Regulation 21 (2) (ii) of the aforesaid Regulations provides that the transmission charges for the Short Term Open Access shall be payable on the basis of maximum capacity reserved for such customers. 3.1 The Commission vide its Notification No. 1 of 2014 dated 4.03.2014, issued GERC (Terms and Conditions of Intra-State Open Access) (First Amendment) Regulations, 2014 and amended the transmission charges payable by Short Term Open Access customer to make it equal to the charges payable by the Long and Medium Term Open Access customers. The same was made effective from 1.04.2014. However, there was no change in the basis of the charges i.e. maximum capacity reserved for customer. Both these Regulations provided that the transmission charges Page 8 for Short-Term Open Access shall be payable on the basis of maximum capacity reserved for such customers. 3.2 Subsequently, the Commission vide its Notification No.3 of 2014 dated 12.8.2014, issued GERC (Terms and Conditions of Intra-State Open Access) (Second Amendment) Regulations, 2014 in which for the first time it was specified that the transmission charges payable by Short Term Open Access customer shall be on actual scheduled energy basis. The notification was published in the official gazette on 14.8.2014, and from that date the respondents are charging the transmission charges on the basis of the energy actually scheduled for Short-Term transactions. As such the petition is misconceived and is liable to be dismissed. 3.3 The petitioner is seeking a declaration that the transmission charges for collective transactions should be on actual scheduled energy and not on maximum reserved capacity even for the period prior to 14.8.2014, namely for the period FY 2012-13 and FY 2013-14. However, SLDC has acted in accordance with the prevailing Regulations framed by the Commission namely, GERC (Terms and Conditions of Intra-State Open Access) Regulations, 2011 and GERC (Terms and Conditions of Intra-State Open Page 9 Access) (First Amendment) Regulations, 2014 which provide for transmission charges to be payable on the basis of maximum capacity reserved for the customers. The above action of the respondent, recovering transmission charges on the basis of maximum capacity reserved has already been upheld by the Commission vide Order dated 24.3.2015 in Petition No. 1440 of 2014 in case of Gujarat Granito Manufacturers Association V/s. SLDC and others. 3.4 The petitioner had sought the facility of Short Term Open Access on the State transmission system to procure electricity through Indian Energy Exchange as collective transaction. The consent or No Objection Certificate of the respondent, SLDC is required for such open access on the State’s Transmission system and the same has been recognized in the Central Electricity Regulatory Commission (Open Access in Inter-State Transmission) Regulations, 2008 also. 3.5 SLDC after considering the surplus capacity available after allotment to the Long and Medium Term Open Access customers, had granted the consent/NOC for 5.4 MW to the petitioner. Once granted, open access for such capacity is accounted for and kept reserved for the petitioner and deducted from the available surplus capacity while granting open access to Page 10 subsequent applicants. Thus, it is wrong on the part of petitioner to claim that there is no concept of reserved capacity. 3.6 The transmission charges applicable for the open access on the State network is to be determined as per GERC (Terms and Conditions of IntraState Open Access) Regulations, 2011 and the amendments thereto. The Central Electricity Regulatory Commission (Open Access in Inter-State Transmission) Regulations, 2008 which govern the Short-Term Open Access in Inter-State transmission system also provide that the transmission charges payable for use of state network is as fixed by the respective State Commission. Only in the absence of determination of the transmission charges by the State Electricity Regulatory Commission, the charges indicated in Regulation 16 (2) of CERC Open Access Regulations shall apply. The proviso to Regulation 16 (2) would not apply once the respective State Electricity Regulatory Commission has determined the transmission charges, as in the present case. GERC (Terms and Conditions of Intra-State Open Access) Regulations, 2011 was notified on 1.6.2011, which provided for transmission charges for Short-Term Open Access customers to be leviable on the basis of the maximum capacity reserved for such customers. Page 11 3.7 The said Regulations were amended vide GERC (Terms and Conditions of Intra-State Open Access) (First Amendment) Regulations, 2014 notified on 4.3.2014. The said Amendment substituted Regulation 21 (2) (ii) and equated the transmission charges for Short-Term Open Access to Long and Medium Term Open Access customers and also provided that the transmission charges for the Short-Term Open Access shall be payable on the basis of maximum capacity reserved for such customers. Thus, the proviso in the principal Regulations as well as the First Amendment made in principal Regulations by the Commission provide that the transmission charges for Short-Term Open Access shall be payable on the basis of maximum capacity reserved for the customers. 3.8 The Open Access Regulations were further amended vide GERC (Terms and Conditions of Intra-State Open Access) (Second Amendment) Regulations, 2014 notified on 14.8.2014, wherein Regulation 21 (2) (ii) was amended and transmission charges for Short-Term Open Access has been made leviable on actual scheduled energy. The second amendment has been made applicable effective from 14.8.2014. Hence, prior to 14.8.2014, GERC Open Access Regulations, 2011 and First Amendment thereto would apply to the petitioner. Page 12 3.9 After the Second Amendment to Open Access Regulations coming into effect, the transmission charges are recoverable based on actual scheduled energy and accordingly, SLDC has been recovering transmission charges from the petitioner and other customers as per the actual scheduled energy. However, prior to coming into effect of the above amendment, the transmission charges are to be paid based on the maximum reserved capacity. It is undisputed that the period in question i.e. 2012-13 and 201314 are prior to the notification of Second Amendment and therefore the provisions of the Second Amendment cannot be applied to such period. The above position has also has been upheld by the Commission vide Order dated 24.3.2015 in Petition No. 1440/2014. 3.10 Further, letters dated 14.3.2015 and 8.4.2015 issued by the respondent are consistent with the GERC Open Access Regulations, 2011 and amendments thereto. The petitioner has not disputed the calculation of the levy of transmission charges, but disputed the principle of determination of maximum reserved capacity for levy of charges as opposed to scheduled energy. The principle of determination of maximum reserved capacity has been applied only to the period prior to 14.8.2014 i.e. prior to coming into Page 13 force of the Second Amendment to the GERC Open Access Regulations, 2011. 3.11 As regards the issue of payment of transmission charges, it was to be settled by the power exchange and in the absence of such settlement, the payment is to be made by the STOA customer and accordingly the invoices were raised on the petitioner. Moreover, it is also clarified that once the capacity is reserved, the transmission charges are payable irrespective of whether the line has been used or not. The said principle is also recognised in the Open Access Regulations, which provide for transmission charges as per the reserved capacity. Therefore, SLDC is entitled to recover the transmission charges as determined by the Commission. 3.12 Moreover, the Open Access Regulations, 2011 prior to 14.08.2014 provided for transmission charges on maximum reserved capacity. Therefore even if the consumer did not use the transmission line, the consumer was required to pay the transmission charges for the capacity reserved for him. The regulations provide for recovery of transmission charges from the STOA customers at maximum reserved capacity (for the period prior to 14.08.2014) and therefore the recovery of transmission charges for the reserved capacity is valid and legal. Page 14 3.13 It is further submitted that the interpretation of the petitioner that scheduled capacity is reserved capacity is wrong and denied. The maximum reserved capacity is not determined on a day to day basis but it is the capacity reserved by the STOA customer for the period of open access, namely, the capacity for which NOC has been granted by SLDC. The capacity placed on bid by the petitioner and accepted by the power exchanges is not the reserved capacity under open access but the capacity sought to be purchased under open access. SLDC has granted NOC for the capacity of 5.4 MW for the petitioner for the period of 1.04.2012 to 31.03.2014 and this is the capacity that has been reserved by SLDC for the petitioner for the power transfer allowed to a short term customer, which is also clear from the definition of the reserved capacity. 3.14 It is submitted that there is no rationale for linking collection of transmission charges with existence of final power purchase agreements, particularly when the open access Regulations, 2011 clearly provide for recovery of transmission charges on reserved capacity. The petitioner has been granted a No Objection for certain capacity which is the reserved capacity and the open access Regulations provide for recovery of transmission charges on such capacity by SLDC. The NOC of the petitioner Page 15 has not been cancelled and therefore the recovery of transmission charges is legal and valid. 3.15 Based on the above submissions, the respondent SLDC submitted that there is no merit in the present petition and the same be dismissed with costs. [4] The matter was heard by the Commission on 7.11.2015, 21.11.2015, 8.12.2015, 19.12.2015 and finally on 22.01.2016. [5] Learned Advocate Shri Ramachandran, on behalf of the respondent, raised the preliminary objections that the present petition is not admissible and maintainable as the issue emerged for the decision of the Commission in the present petition is already covered in the order dated 24.03.2015 in case of Gujarat Granito Manufacture Association Vs. SLDC. 5.1 The petitioner has raised extraneous issues on determination of transmission charges for short term open access which are outside the scope of the present petition. 5.2 The principle of determination of transmission charges under STOA regulations cannot be challenged in the present proceedings. The open access customer is liable to pay transmission charges as determined in Page 16 accordance with GERC (Terms and Conditions of Intra-state Open Access) Regulations, 2011. 5.3 The petitioner sought open access on transmission facility to procure power through energy exchange. The consent/no objection was issued by the respondent for 5.4 MW capacity to the petitioner considering the surplus capacity available after allotment to the long term and medium term open access consumers. 5.4 Once the open access is granted to the petitioner such capacity is reserved for him and the same is deducted from the available surplus capacity while granting open access to the subsequent applicants. Therefore, the claim of the petitioner that there is no access granted in case of STOA or there is no concept of reserved capacity is not legal and valid. The consent/NOC granted by SLDC is for a certain capacity which is a reserved capacity for open access customer. 5.5 The transmission charges applicable for open access on State Transmission network are determined and decided by this Commission as per the GERC (Terms and Conditions of Intra-state Open Access) Regulations, 2011. Regulation 21(2) (ii) of the principal Regulations as well as the first amendment thereto provide that the transmission charges for Short Term Open Access shall be payable on the basis of maximum capacity reserved Page 17 for the customers. The said Regulations were amended by the Commission on 14.08.2014. Regulation 21(2) (ii) was amended whereby the transmission charges are payable based on the actual scheduled energy and accordingly SLDC has been recovering the transmission charges from the open access customers as per the actual scheduled energy from the effective date of the aforesaid amendment, i.e. 14.08.2014. 5.6 Prior to 2nd Amendment in the principal Regulations, the transmission charges were payable by the short-term open access customers based on the maximum reserved capacity. 5.7 SLDC raised the invoices on the petitioner for the period FY 2012-13 and 2013-14, i.e. for the period prior to 14.08.2018 based on the provisions of Open Access Regulations prevailing at the relevant times. 5.8 The transmission charges were to be settled by the power exchanges. However, in the absence of such settlement the payment is to be made by the Short Term Open Access customers and accordingly the invoices have been raised by the respondent on the petitioner. SLDC is entitled to recover the transmission charges as per the provisions of the GERC (Terms and Conditions of Intra-state Open Access) Regulations, 2011. Page 18 5.9 The principal liability of transmission charges payment is of the open access customer irrespective of whether the line has been used or not by the open access customer once the capacity is reserved for the open access customer. Once the capacity is allocated to the open access consumer, he is liable to pay transmission charges in accordance with the prevailing Regulations. The open access consumer even if he does not use the transmission line, he is required to pay the transmission charges. 5.10 There is a violation of the CERC Open Access Regulations by the petitioner. The principal Regulations of CERC (Open Access in Inter-State transmission) Regulations, 2008, first amendment dated 20.05.2009 and 2nd Amendment dated 13.09.2013 recognised that the open access customer when availing the open access on Inter-State transmission network and also Intra-State transmission network has to pay the transmission charges for use of State transmission network as determined by the State Electricity Regulatory Commission in addition to the other transmission charges. The Commission has already determined the transmission charges in accordance with the GERC (Terms and Conditions of Intra-state Open Access) Regulations, 2011 from time to time. Therefore, the petitioner is liable to pay the transmission charges accordingly. Page 19 5.11 The maximum reserved capacity is not determined on day to day basis but it is the capacity reserved for the Short Term Open Access for the period of open access for which NOC has been granted by SLDC. The capacity placed on bid by the petitioner and accepted by the power exchange is not the reserved capacity under open access but the capacity sought to be purchased under open access. SLDC has granted NOC for the capacity of 5.4 MW to the petitioner for the period from 1.04.2012 to 31.03.2014 and this capacity has been reserved by SLDC for the petitioner. 5.12 The respondent denied that STOA customers were to be charged on the basis of actual energy scheduled because the GERC (Terms and Conditions of Intra-State Open Access) Regulations, 2011 provide that the transmission charges were payable on maximum reserved capacity. There is no relationship between the quantum of transmission charges per unit and the capacity reserved. Transmission charges are payable as provided under Open Access Regulations, 2011 which is applicable and binding to all concerned entities. SLDC is entitled to receive the transmission charges as per the provisions of Open Access Regulations, 2011. 5.13 The concept of surplus capacity at low priority is relevant at the time of allocation of short term open access. Once the consent or NOC is granted for STOA customer such capacity becomes reserved capacity as per the Page 20 Open Access Regulations, 2011 and it is blocked for such customer. Merely because the NOC does not use the term reserved capacity, it does not negate the clear provisions of the Open Access Regulations, 2011. NOC has been granted to the petitioner for drawl of certain capacity and the same has become his reserved capacity in terms of the Open Access Regulations, 2011. 5.14 There is no rationale for linking collection of transmission charges with existence of final power purchase agreements. It is not open to the petitioner to act in contravention of provisions of Open Access Regulations, 2011. No Objection of the petitioner has not been cancelled nor he has surrendered the unused capacity and therefore, the recovery of transmission charges is legal and valid as per the then prevailing Regulations. The price at which power is available in power exchange is not the issue. The petitioner is not entitled to challenge the principle laid down in the Open Access Regulations, 2011 in the present proceedings. The provision for relinquishment is only for long term or medium term open access and the same is not relevant in the present case. SLDC cannot be deprived of the legitimate transmission charges due to financial difficulties faced by the petitioner. In support of the above submission the Respondent relied upon the Order dated 24.03.2015 passed by the Page 21 Commission in Petition No. 1440 of 2014 in case of Gujarat Granito Manufacture Association Vs. SLDC and others. [6] Shri Vikram Shah on behalf of the petitioner, submitted that the order dated 24.03.2015 passed in petition No. 1440 of 2014 by the Commission is challenged by filing Appeal No. 247 of 2015 by Gujarat Granito Manufacture Association before the Hon’ble APTEL and the same is already admitted by the Hon’ble APTEL. 6.1 The petitioner has raised the issue under Regulation 45 of GERC (Terms and Conditions of Intra-State Open Access) Regulations, 2011 viz. Power to Remove Difficulties. Therefore, the issue cannot be termed as extraneous. As per the present Regulations the NOC to STOA customers can be cancelled. There is nothing like constraint in the power network and NOC granted to all applicants. So there is nothing like reserved capacity when the NOC is granted to STOA applicants. The transmission charges should be collected for the energy approved for transmission as per Clause 16 (2) of CERC Open Access Regulations, 2008. As per the said Regulation the transmission charges should be collected on approved energy transmission. When no energy is received under STOA, no charges are payable by the STOA customer. The amendment made in Regulation 20(6) of the CERC principal Regulations provides that no charges other than Page 22 those specified in the said Regulations shall be payable by any person who is granted STOA under this Regulation. 6.2 The invoices issued by SLDC are arbitrary. SLDC had not originally demanded any transmission charges on the basis of so called reserved capacity but sudden recovery is demanded with back effect which is not legal as the goods produced in related time with power cost consideration as per prevailing billing is a non-reversible process and payment at such stage will add to the difficulties faced by the steel manufacturing units who are just surviving the closure of units. The petitioner has not procured the power under STOA for due to lay-off given to the employees in the petitioner’s unit. Also the bills issued by the respondent are without any detailed calculations. 6.3 The transmission charges are to be settled by IEX. The power exchange is asked to pay the transmission charges for non-traded or under traded quantity of power by SLDC but the same is denied by IEX vide letter dated 3.04.2014 and 9.04.2014 stating that the collective transactions are InterState in nature and the State network used in conjunction with the InterState network. Therefore, the SLDC can recover the transmission charges for power actually traded by the STOA consumer. Page 23 6.4 As per the definition of transmission, if no conveyance of electricity is made then the transmission charges cannot be recovered. As per CERC Regulations the STOA customer can use the network only if surplus capacity is available on the Inter-State transmission system. The IntraState transmission system is used in conjunction with the Inter-State transmission system by the STOA customers for transactions on power exchanges. Therefore, when the Inter-State line is not available in that case the Short-term open access customer has not to pay the transmission charges. 6.5 As per Regulation 21(2) (i) of the GERC (Terms and Conditions of Intrastate Open Access) Regulations, 2011 the total transmission cost is to be divided amongst all long term and medium term open access customers as the STOA consumers are not creating extra burden for the STU. The recovery of transmission charges from STOA customers who have availed power under collective transactions for the under or non-utilized capacity approved under NOC is against the CERC Regulations. The collective transactions are governed by the CERC Regulations. Therefore, the transmission charges are recoverable as per the CERC Regulations. The term reserved capacity which can be cancelled by SLDC at any time, if there is congestion in the system as happened in past can be considered as Page 24 reserved or not is to be decided by the Commission and the same is applicable to the STOA consumers who are availing power from the energy exchange under collective transactions is to be decided. 6.6 Based on the above, he submitted that the Commission may grant the prayers of the petitioner. [7] Considering the submissions made by the parties the following issues emerged for the decisions of the Commission: (i) Whether the invoices raised by the respondent SLDC for FY 2012-13 and 2013-14, are legal and valid. (ii) Is the petitioner entitled for refund of all the payments collected under STOA charges for the reserved capacity for non-traded and short traded days by SLDC. (iii) Is any directions to SLDC and GETCO necessary for recovery of charges from open access customers and whether such recovery requires prior approval from the Commission. [8] We have carefully considered the submissions made by the parties. We note that the petitioner had obtained STOA during FY 2012-13 and 201314 for procurement of power through energy exchange. It is also Page 25 undisputed between the parties that the petitioner had paid the transmission charges at relevant time for the STOA granted by SLDC. 8.1 The issue emerged in the present petition is with regard to the claim raised by the respondent, SLDC vide invoice No. SLDC/12- 13/STOA/190/dated 16.04.2015 for the period 1.04.2012 to 31.03.2013 for an amount of Rs. 71,099/- and invoice vide invoice No. SLDC/1314/STOA/554/dated 28.01.2015 for the period from 1.04.2014 to 31.03.2015 for an amount of Rs. 15,22,925/-. The aforesaid invoices raised by the respondent on the ground that the STOA charges recovered by them were only for the days on which the petitioner had carried out the transaction and not for entire period for which SLDC, Gujarat has issued NOC. It is also stated that as per the GERC (Terms and Conditions of Intrastate Open Access) Regulations, 2011 the petitioner is liable to pay the transmission charges on the basis of maximum reserved capacity. Therefore, the petitioner is required to pay the transmission charges for the period which was not paid by it. 8.2 The petitioner raised the following issue: (i) the transmission charges are applicable and permissible to be collected only if the energy is transmitted through the transmission lines. Page 26 (ii) As per CERC (Grant of Connectivity, Long-term Access and Mediumterm Open Access in Inter-State Transmission and related matters) (first amendment) Regulations, 2009 the STOA charges are decided based on total power required to be transmitted by LTOA and MTOA and hence no charges are to be collected from STOA customers for non use of lines. (iii) As per Regulation 21(2)(i), of the GERC (Terms and Conditions of Intra-state Open Access) Regulations, 2011, the total transmission cost to be shared by LTOA and MTOA. The STOA customer is required to pay the charges for the spare capacity available in the transmission lines at a particular time when power is transmitted for him. (iv) As per the Minutes of Meeting dated 24.11.2011 issued by the Commission, the collective transactions are to be dealt with in accordance with the CERC Intra-State Open Access Regulations. As per CERC Regulations no transmission charges are payable other than what is specified by the CERC. 8.3 As the issues raised by the petitioner, are interwoven, we decide the same together. The petitioner has raised the issue that the transmission charges are payable only when the transmission of energy takes place in the Page 27 transmission system. He referred the definition of “transmit” given in subsection 74 of Section 2 of the Electricity Act, 2003 which reads as under: "transmit" means conveyance of electricity by means of transmission lines and the expression "transmission" shall be construed accordingly; 8.4 As per the aforesaid definition transmit/transmission is a conveyance of electricity by means of transmission lines. The said definition is silent on transmission charges. The Electricity Act, 2003 is also silent on the definition of transmission charges. The transmission charges are recovered by the transmission licensee as per the GERC (Terms and Conditions of Intra-state Open Access) Regulations, 2011 and amendments thereto. The concept of transmission charges is incorporated in the Regulations to enable the transmission licensee to recover the cost of services provided by it through the intra-state transmission infrastructure created by it. The transmission network created by the transmission licensee/STU/CTU is used by the beneficiaries for the Long Term, Medium Term or Short Term periods. Therefore, the Commission has notified the GERC (Terms and Conditions of Intra-state Open Access) Regulations, 2011 which mandated the transmission licensee to allow non discriminatory open access to the open access customer for the Long Term period, Medium Term period or Short Term period. The transmission licensee incurs the cost for creation Page 28 of the transmission network for evacuation of power from one place to another place (point of injection to point of drawl). The licensee is eligible to recover the cost incurred by it from the beneficiaries who utilise its network, which is approved by the Commission in the ARR/tariff petition filed by the transmission licensee. Moreover, the beneficiaries of such transmission network reserve the capacity in the network for different periods, i.e. long–term, medium term or short term. Once the capacity is reserved by the beneficiaries it is the duty cast upon the licensee to keep it reserved for such beneficiaries. Therefore, if the beneficiaries reserve the transmission network and do not utilise it and do not pay the charges due to non-utilisation, it leads to a situation that the transmission licensee though eligible for recovery of the charges against the cost incurred by it for the creation of the transmission network is deprived of the recovery of such cost or the transmission charges are to be recovered from the consumers who utilise the transmission network at the rate higher than what is approved by the Commission to make up for the shortfall due to non-payment of transmission charges by such the open access customers, as the transmission licensee is revenue neutral to the extent of ARR approved by the Commission. The content of petitioner that the Page 29 transmission charges are payable only if the network is utilised by the beneficiaries is thus illegal and not valid. 8.5 We further note that the transmission charges are recoverable from the long term, medium term or short term open access customer by the transmission licensee/STU for utilisation for Intra-State transmission network as per the Regulations of the Commission. The relevant provisions of the principal Open Access Regulations notified by the Commission on 1.06.2011 read as under: “21.Transmission Charges Open Access customer using transmission system shall pay the charges as stated hereunder: (1) For use of inter-State transmission system : As specified by the Central Commission from time to time. (2) For use of intra-State transmission system : (i)By Long-Term and Medium-Term Open Access Customers: The Total Transmission Cost (TTC) as determined by the Commission in the Annual Transmission Tariff Order of the STU shall be shared by all long-term and medium-term open access customers on monthly basis (including existing Distribution Licensees) in the ratio of their allotted capacities, in accordance with the following formula: Monthly Transmission Tariff (MTT) = TTC/(ACs x 12) (in Rs./MW/month); Page 30 Where; TTC = Total Transmission Cost determined by the Commission for the transmission system for the concerned year (in Rs), and ACs = sum of capacities allocated to all long-term and medium-term open access customers in MW. Provided that Monthly Transmission Tariff shall also be shared by a Generating Company if power from such Generating Company is sold to a consumer outside the State of Gujarat, to the extent of capacity contracted outside the State: Provided further that the transmission tariff payable by any long-term or medium-term open access customer utilizing the transmission system for part of a month shall be determined as under: Transmission Tariff = TTC/(ACs x 8760) (in Rs./MWh); Where; TTC = Total Transmission Cost determined by the Commission for the transmission system for the relevant year (in Rs), and ACs = sum of capacities allocated to all long-term and medium-term open access customers in MW. Provided that where a dedicated transmission system used for open access has been constructed for exclusive use of an open access customer, the transmission charges for such dedicated system shall be worked out by transmission licensees for their respective systems and got approved by the Commission and shall be borne entirely by such Page 31 open access customer till such time the surplus capacity is allotted and used by other persons or purposes. (ii)By Short-Term Open Access Customers: Transmission Charges payable by a Short-Term Open Access customer shall be at a rate one-fourth of the transmission charges applicable to the Long-Term / Medium-Term customer, as described above. Transmission charge payable by Short-term open access customers = 1 4 × Rate of transmission charge payable by long-term / medium-term open access customers Provided that the Transmission charges payable by Short–term open access customers for use of the system for part of a day shall be as follows: (a) Upto 6 hours in a day in one block = (b) More than 6 hours and upto 12 hours in a day in one block = (c) More than 12 hours upto 24 hours in one block = 1 ( × 4 short-term open access rate) ( 𝟏 𝟐 × short-term open access rate) short-term open access rate Provided that transmission charges for short-term open access shall be payable on the basis of maximum capacity reserved for such customer.” Page 32 8.6 Thus, the transmission charges are payable by the long term and medium term open access consumers, as per Regulation 21(2)(i), on the capacity reserved for long term and medium term open access customer as per the formula given in the aforesaid Regulations. 8.7 Moreover, the Regulation 21(2) (ii) of the aforesaid Regulations provides that the STOA customer shall pay the transmission charges @ 1/4th of the rate of transmission charges payable by long term or medium term open access customers. The proviso to the said Regulation provides that the transmission charges are payable for part of a day at the rate specified in the table contained in the said Regulation. The 2nd provisio to the said Regulation provides that the transmission charges are payable by the SOTA customers on the basis of maximum capacity reserved for such customers. 8.8 The petitioners have referred Regulation 16 of CERC (Open Access in InterState Transmission) Regulations, 2008, which reads as under: Transmission Charges 16. (1) In case of bilateral transactions, for use of the inter-State transmission system, the transmission charges at the rate specified Page 33 hereunder shall be payable by the applicant for the energy approved for transmission at the point(s) of injection: Type of Transaction Transmission charges (Total (Rs./MWh) (a) Bilateral, intra-regional 30 (b) Bilateral, between adjacent regions 60 (c) Bilateral, wheeling through one or more intervening regions 90 (2) In case of the collective transaction, for use of the inter-State transmission system, transmission charges at the rate of Rs.30/MWh for energy approved for transmission for each point of injection and for each point of drawal shall be payable. (3) The intra-State entities shall additionally pay transmission charges for use of the State network as determined by the respective State Commission: Provided that in case the State Commission has not determined the transmission charges, the same shall not be a ground for denial of open access and charges for use of respective State network shall be payable for the energy approved at the rate of Rs.30/MWh: Provided further that transmission charges for use of the State network shall be intimated to the Regional Load Despatch Centre concerned for display on its web site: Page 34 Provided also that transmission charges shall not be revised with retrospective effect. Regulation 16 (2) provides that in case of the collective transaction, for use of Inter-State transmission systems, transmission charges are payable at the rate of Rs. 30/MWh for energy approved for transmission for each point of injection and each point of drawl. Regulation 16 (3) provides that in case of Intra-State, the open access customer shall pay additional transmission charges for use of State network as determined by the respective State Commission. The first proviso of the said Regulation provides that in case the SERC has not determined the transmission charges, the same shall not be a ground for denial of Open Access and charges for use of respective State Network shall be payable for the energy approved at the rate of Rs. 80/MWh. Thus, the aforesaid Regulation recognizes that when the Intra-State Transmission network is utilized, the Open Access customers shall pay the transmission charges either at the Rate of Rs. 80/MWh if no charges are determined by SERC concerned else it shall pay as per the transmission charges determined by the respective State Commission. Page 35 8.9 We further note that, the petitioner relied upon Clause 16 of CERC (Open Access in Inter-State transmission) (first amendment), Regulation 2009 and the CERC (Open Access in Inter-State transmission) (Second amendment), Regulation 2013 and submitted that in case of collective transactions only CERC Regulations are applicable and no other charges are payable by the STOA customers. It is necessary to refer the said Regulation which reads as under: 16. (1) In case of bilateral transactions, the transmission charges at the rate specified hereunder shall be payable by the short-term customer for the energy approved for transmission at the point or points of injection: Type of Transaction Transmission charges(Total)(Rs./MWh) (a) Bilateral, intra-regional 80 (b) Bilateral, between adjacent regions 160 (c) Bilateral, wheeling through one or more intervening regions 240 (2) In case of the collective transactions, transmission charges at the rate of Rs. 100/MWh for energy approved for transmission separately for each point of injection and for each point of drawal, shall be payable. Page 36 (3) The intra-State entities shall pay the transmission charges for use of the State network as fixed by the respective State Commission in addition to the charges specified under clauses (1) and (2): Provided that in case the State Commission has not determined the transmission charges, the charges for use of respective State network shall be payable at the rate of Rs.80/MWh for the electricity transmitted: Provided further that non-fixation of the transmission charges by the State Commission for use of the State network shall not be a ground for refusal of open access: Provided also that the transmission charges payable for use of the State network shall be conveyed to the Regional Load Despatch Centre concerned who shall display these rates on its web site: Provided also that the transmission charges payable for use of the State network shall not be revised retrospectively.” 8.10 The aforesaid Regulation states that no charges are leviable/recoverable from the open access consumers other than what is specified in the said Regulation of the CERC. Prior to deciding this issue, we clarify that whenever any provisions of the Act/Rules or Regulations framed there Page 37 under is decided to be applied, it is necessary to refer other relevant provisions on the same subject matter also if any provided in the said Act/Rules or Regulations, and then decide the issue with combined reading of such provisions. Regulation 16 of the CERC Regulations as referred above, provides that the transmission charges for utilization of Inter-State network is as per CERC Regulations and for utlisation of Intra-State network, the same is as per the Regulations notified by the SERCs or as per the aforesaid CERC Regulations if the SERC has not determined the transmission charges. Therefore, the contention of the petitioner that no charges are leviable other than the CERC Regulations is not legal and valid as the CERC Regulations itself recognize the recovery of transmission charges by SLDC for utlisation of Intra-State network as determined by the State Electricity Regulatory Commission. Therefore, the aforesaid contentions of the petitioner is not acceptable and the same is rejected. 8.11 The petitioner contended that the no capacity is reserved for STOA customers. In STOA the schedule is determined from time to time based on the demand and supply. The STOA customer is committed to scheduled capacity which in effect is the reserved capacity and not NOC quantum. The STOA customer is required to be charged on the basis of energy scheduled. As the issue is raised with regard to the reserved capacity by the petitioner, Page 38 it is necessary to refer the definition of reserved capacity defined in the GERC (Terms and Conditions of Intra-state Open Access) Regulations, 2011, which reads as under: “Reserved Capacity” means the power transfer in MW between the specified point(s) of injection and point(s) of drawal allowed to a short-term customer on the transmission/distribution system depending on availability of transmission/distribution capacity and the expression "reservation of capacity" shall be construed accordingly; 8.12 As per the aforesaid definition the power transfer in MW between the specified point of injection and point of drawl to a STOA customer depending upon the availability of capacity in transmission/distribution network is the reserved capacity. Therefore, the reserved capacity is specifically recognized as the availability of capacity to STOA customer in the existing transmission /distribution network. Therefore, any contention against it pleaded by the petitioner is not acceptable and the same is rejected. We further clarify that the schedule of energy given by the open access customer is with consideration of the capacity reserved for him. There may be mismatch between the actual schedule and actual drawl, which is dealt through commercial mechanism in energy accounting prepared by SLDC. The scheduling of energy is also required to be done by the LTOA and MTOA customers. Scheduling has no linkage with the Page 39 transmission charges payable by the open access customers and once the capacity is reserved for such customers they have to pay for it irrespective of its usage. On this count also the plea of the petitioner that no capacity is reserved for STOA customer is not acceptable and the same is rejected. 8.13 The petitioner contended that when the rate quoted by him was not commercially viable or bid submitted in the exchange did not get clear in that case there was under utilisation or non utilisation of Intra-State transmission system booked by the STOA customer. Moreover, the petitioner himself did not avail the STOA for some days due to lay off declared by the petitioner or due to non working day/weekly off of the petitioner’s company resultantly there was no utilisation or under utilisation of the transmission network by the petitioner. When there is no or under utlisation of network, the claim of the respondent SLDC for transmission charges is illegal and arbitrary. In this regard, we clarify that once the STOA is allowed to the open access customer as per the GERC (Terms and Conditions of Intra-State Open Access) Regulations, 2011 it is necessary for the licensee to keep the capacity reserved for such customer irrespective of whether the network is utilised by such customer or not. In case of non-utilisation of network or under-utilisation of network the open access customer is liable to pay the transmission charges for the reserved Page 40 capacity as per the Regulations notified by the Commission. We, further note the contention of the petitioner that he has underutilized or not utilized the capacity reserved for him when lay off was granted or there were non working/weekly off days of their organization. We, note that there is no evidence on record to substantiate that the petitioner surrendered the reserved capacity on those particular days or time during the period of STOA granted to him by the respondent. Had the petitioner surrendered his reserved capacity during those days, the respondent could have allocated such unused reserved capacity to another STOA customer to optimize the utilisation of the licensee’s network. However, the evidence on record does not support the allocation of surrendered capacity to another STOA customer. In the absence of surrender of the unused capacity by the petitioner, the respondent was unable to spare such capacity to other beneficiaries, and hence the claim of the petitioner that he is not liable for the transmission charges on such unused capacity is not legal and valid. Once the STOA demanded by the open access customer is granted by the licensee and SLDC by issuing NOC, such capacity is reserved for him. Therefore, short utilization or non-utilisation of the reserved capacity by the STOA customer does not exempt him from the payment of transmission Page 41 charges and he is liable to pay the transmission charges for the reserved capacity as claimed by the respondent. 8.14 We note that the claim of the respondent for FY 2012-13 of Rs. 71,099 and FY 2013-14 of Rs. 15,22,225/- as per the invoices raised by him is for recovery of transmission charges for the capacity reserved for the petitioner under STOA. The petitioner failed to prove that the respondent did not allow him the STOA during the aforesaid period for particular days or months in the FY 2012-13 and 2013-14 when there was non-utiliastion or under utilisation of the allocated capacity and therefore, the claim of the respondent for the STOA charges is legal and valid. In the absence of above we note that there is no merit in the submission of the petitioner for nonpayment of transmission charges claimed by SLDC. On this ground also the contention of the petitioner that he is not liable to pay the STOA charges claimed by the respondent through invoices raised on him is not acceptable and the same is rejected. [9] Based on the above observations, we decide that the issues raised by the petitioner to declare the claim of STOA charges by the respondent SLDC through the invoices for FY 2012-13 and FY 2013-14 as illegal and direct the respondent SLDC to refund the amount collected under STOA charges Page 42 for reserved capacity for non-traded and short traded days are not acceptable and the same are rejected. [10] In view of above observation, we decide that the present petition is devoid of merit and the same is dismissed. [11] With this order the present petition stands disposed off. [12] We order accordingly. Sd/- Sd/- [P.J.THAKKAR] [K.M.SHRINGARPURE] MEMBER MEMBER Place: Gandhinagar. Date: 07/07/2016. Page 43
© Copyright 2025 Paperzz