KENAI PENINSULA BOROUGH Purchasing & Contracting 47140 E Poppy Lane ● Soldotna, Alaska 99669-7520 Phone: (907) 714-2260 ● Fax: (907) 714-2373 www.kpb.us/purchasing MIKE NAVARRE BOROUGH MAYOR ADDENDUM NO. 1 This addendum consists of 22 pages TO: All Bid Packet Holders FROM: Kenai Peninsula Borough – Purchasing & Contracting DATE: February 14, 2017 SUBJECT: Invitation to Bid – ITB17-016 Homer Medical Center Expansion DUE DATE: March 9, 2017, by no later than 2:00 PM Bidders must acknowledge receipt of this Addendum in the appropriate place on the Bid Form. Failure to do so may result in the disqualification or rejection of the bid. As specified in Section 9 of the Kenai Peninsula Borough’s invitation to bid, we have agreed to answer written questions received to date. Questions are now due February 20, 2017. We look forward to receiving your bid by no later than 2:00 PM on March 9, 2017. Note: Information in this addendum takes precedence over original information. provisions of the document remain unchanged. ITEM NO. REFERENCE 01-01 Change All other DESCRIPTION *** Last Day for Questions changed to February 20, 2017 by 5:00pm 01-02 Plan Holder Question Q: A: 01-03 Clarification Will this project need a Storm Water Pollution Prevention Plan? A formal SWPPP is not required for this project. The City of Homer requires a Conditional Use Permit, Zoning Permit and Storm Water Plan. All of which have been completed and paid for by Owner and approved by City. The successful Contractor will have to submit a Development Activity Plan to February 14, 2017 Owner / City outlining their staging area / office, construction dumpster location, construction fencing, and silt fencing, etc. For Bidding purposes Contractor shall include cost for installation and maintenance of 600LF of silt fence to be installed along the eastern and southern property lines. Contractor to also include cost for installation and maintenance of temporary construction fencing to protect the excavated expansion area. Fencing to remain in place until the building is weathered in. Development Activity Plan application is attached to this addenda. Contractor shall mark up the Site Plan from the Civil drawings as part of the DAP. 01-04 Clarification 01-05 Plan Holder Question Contractor will need to apply for City of Homer Water Service Permit. City Engineer is familiar with project, and has approved the Civil Drawings. Owner shall pay all fees directly to City of Homer for the permits as well as cover the cost for a new water meter if required. It is the understanding of the Owner the City does not make the tap; the Contractor will make tap under the City’s supervision. Q: A: 01-06 Clarification Page E100 is missing from the bid documents. Sheet E101 was accidentally printed twice. Please replace one of the sheets with the attached Sheet E100 which was missing. Please see the attached preliminary phasing plan for the project. Plan represents conversations with Clinic Staff on acceptable levels of disruption to their operations. Plan represents three phases. Contractor is required to develop their own phasing plan, which shall comply with Authorities Having Jurisdiction, as well as limiting disruption to the facilities ability to function during normal business hours. Page 2 of 3 February 14, 2017 01-07 Clarification Please see the attached Site and Soils Report for Contractor’s information. Contractor is responsible for providing and maintaining an excavation to allow work to proceed “in the dry”. This may require some form of dewatering system. Page 3 of 3 City of Homer Development Activity Plan Application The goal of the Development Activity Plan (DAP) is to ensure that construction activity is proactive in minimizing the effects of erosion, sediment transport, water runoff and pollutants. This is known as Best Management Practices (BMP’s) which must be maintained during the construction project and removed when vegetation is stabilized. Submit a detailed design early, in text and diagrams, along with photos of installed pre-construction measures. Some items below may not apply to your project. If so, indicate Not applicable, because ….. If you have any questions, Dotti Harness-Foster, Planning Dept. 435-3118. In Block lettering is city code. Italicized are suggestions. Applicant's Name: Applicant's Email: Mailing address: Phone numbers: Project Location: Legal: City Engineer Approval Date: Planning Approval Date What Triggers a DAP? Circle those that apply to your project. 1. Land disturbing activity of 10,000 SF or greater; 2. The cumulative addition of 5,000 square feet or greater of impervious surface area from the pre-development conditions; 3. Grading, filling or excavating involving the movement of 1,000 cubic yards of material; 4. Grading activities that will result in a temporary or permanent slope having a steepness of 3:1 and having a total slope height, measured vertically from toe of slope to top of slope, exceeding 5 feet; 5. Grading activities that will result in the diversion of existing drainage courses, both natural or human-made, from their existing point of entry or exit from the grading site; 6. Any land clearing or grading on slopes steeper than 20%, or within 20 feet of wetlands, streams, or ponds; HCC 21.74 010(b). When a DAP is required, no person shall do or cause to be done any development activity on the site without first obtaining a DAP approved by the City. 21.74.020 These standards apply during construction and all other phases of development activity. a. Stabilization and sediment trapping. All exposed or disturbed soils with grades exceeding 10 percent and soils exposed to concentrated surface runoff flows, including soil stockpiles, shall be stabilized in a way that protects soil from the erosive forces of weather and flowing water. Applicable practices include, but are not limited to, the installation of silt fences, vegetative establishment, mulching, plastic covering, and the early application of gravel base on areas to be paved. No soils shall remain unstabilized for more than three days. At all times of the year, the contractor shall have sufficient materials, equipment and labor on site to stabilize and prevent erosion from all disturbed areas before initiating or continuing work. Suggestion: On your site plan or as-built survey, indicate where you intend to have soil stock piles, exposed or disturbed soils and the grades/slopes. Describe and illustrate when and where you are going to stabilize and project soils from erosion using of BMP’s such as: silt fencing, straw bales, mulching etc. b. Delineation of clearing and easement limits. Clearing limits, setbacks, buffers, and sensitive or critical areas such as steep slopes, wetlands and riparian corridors shall be clearly identified in the DAP, marked in the field, and inspected by the City prior to commencement of land clearing activities. Suggestion: Use your site plan to indicate clearing limits, setbacks, buffers, steep slopes, wetlands, drainages. Sign at the bottom of each page ________________________________ c. Protection of adjacent properties. Adjacent properties shall be protected from sediment deposition by appropriate use of vegetative buffer strips, sediment barriers or filters, dikes or mulching, or by a combination of these measures and other appropriate methods. Suggestion: Describe how you are going to protect adjacent properties from sediment deposit. d. Timing and stabilization of sediment trapping measures. Sediment ponds and traps, perimeter dikes, sediment barriers and other approved methods intended to trap sediment on-site shall be constructed as a first step. These methods shall be functional before additional land-disturbing activities take place. Earthen structures such as dams, dikes, and diversions shall not remain unstabilized for more than three days. Suggestion: Describe your time line and submit photos of installed mitigation measures. e. Slope Stabilization. Cut and fill slopes shall be constructed in a manner that will minimize erosion. Roughened soil surfaces are preferred to smooth surfaces. Interceptors should be constructed at the top of long, steep slopes that have significant areas above that contribute runoff. Concentrated runoff should not be allowed to flow down the face of a cut or fill slope unless contained within an adequate channel or pipe slope drain. Wherever a slope face crosses a water seepage plane, adequate drainage or other protection should be provided. In addition, slopes should be stabilized in accordance with subsection (b) above. Suggestion: Describe and illustrate how you are going to stabilize slope from concentrated runoffs. If you have little to no slope, NA is an appropriate response. f. Controlling off-site erosion. Properties and waterways downstream from development sites shall be protected from erosion due to increases in the volume, velocity, and peak flow rate of stormwater runoff from the development site by the implementation of appropriate methods to minimize adverse downstream impacts. Suggestion: Describe and illustrate how you are going to protect neighboring property from your erosion. g. Stabilization of conveyance channels and outlets. All temporary and permanent on-site conveyance channels shall be designed, constructed and stabilized to prevent erosion from the expected flow velocity from a 2-year, 3-hour duration storm for the post-development condition. Stabilization adequate to prevent erosion of outlets, adjacent stream banks, slopes and downstream reaches shall be provided at the outlets of all conveyance systems. Suggestion: If your site doesn’t have conveyance channels or outlets, NA is acceptable. h. Storm drain inlet protection. All storm drain inlets made operable during construction shall be protected so that stormwater runoff shall not enter the conveyance system without first being filtered or otherwise treated to remove sediment. After proper written application, the requirement for inlet protection may be waived by the City on a site-specific basis when the conveyance system downstream of the inlet discharges to an appropriate on-site sediment control methods, including but not limited to sediment ponds or traps. The conveyance system will be adequately cleaned following site stabilization. Suggestion: If public storm drains are nearby, explain how your design will filter and remove sediment prior to entering the public storm drain. If no storm drains are nearby, NA is an acceptable response. Sign at the bottom of each page ________________________________ i. Underground utility construction. The construction of underground utility lines shall be limited, where feasible, to no more than 500 feet of open trench at any one time. Where consistent with safety and space considerations, excavated material shall be placed on the uphill side of the trench. Dewatering devices shall discharge to an appropriate sediment trap or pond, preceded by adequate energy dissipation, prior to runoff leaving the site. Suggestion: On your site plan or as-built survey illustrate where your underground utility lines are located and their length. Ensure that you will not have more than 500’ of trench ‘open’ at one time and that your excavated material will be placed on the uphill side of the trench so the any sediment will run into the trench. j. Constructed access routes. Wherever construction vehicle routes intersect paved roads, provisions must be made to minimize the transport of sediment (mud) and debris onto the paved road by use of approved methods. If sediment or debris is transported onto a road surface, the roads shall be cleaned thoroughly, as a minimum, at the end of each day. Sediment or debris shall be removed from roads by shoveling or sweeping and be transported to a controlled sediment disposal area. Street washing shall be allowed only after sediment is removed in this manner. Suggestion: How will you minimize transport of sediment onto paved roads? Ensure the City that you will remove any sediment or debris from the roads by shoveling or sweeping. If your site doesn’t have paved road, NA is an acceptable response. k. Removal of temporary erosion and sediment control methods. All temporary erosion and sediment control methods shall be removed within thirty days after final site stabilization is achieved or after the temporary methods are no longer needed. Trapped sediment shall be removed or stabilized on-site. Disturbed soil areas resulting from removal of temporary methods shall be permanently stabilized. The removal of temporary erosion and sediment control methods may not be required for those projects, such as single family developments, that will be followed by additional construction under a different permit. In these circumstances, the need for removing or retaining the measures will be evaluated on a site-specific basis. Suggestion: Describe your timeline for removal of temporary erosion and sediment control methods. Explain how you are going to permanently stabilize the trapped sediment. l. Dewatering construction sites. Dewatering devices shall discharge into an appropriate sediment trap or pond designed to accept such a discharge, preceded by adequate energy dissipation, prior to runoff leaving the site. Suggestion: If your site doesn’t require dewatering, NA is an acceptable response. m. Control of pollutants other than sediment on construction sites. All pollutants other than sediment that occur on-site during construction shall be handled and legally disposed of in a manner that does not cause contamination of ground or surface waters. Pollutants of concern include, but are not limited to, fuels, lubricants, solvents, concrete by-products and construction materials. Suggestion: All construction sites have potential pollutants. Describe how you are going to handle possible contamination. Explain what supplies you will have on site in the event of a pollutant spill. n. Maintenance. All temporary and permanent erosion and sediment control methods shall be maintained and repaired as needed to assure continued performance of their intended function. The owner shall be responsible for assuring that any such facilities damaged during floods, storms or other adverse weather conditions are immediately returned to normal operating condition. Sign at the bottom of each page ________________________________ Suggestion: If you are onsite daily, weekly, monthly describe your inspection and maintenance of the erosion and sediment control methods. o. Erosion control. Erosion Control Design Storm Event Facilities designed for the control of erosion and sedimentation shall be designed for the erosion and sedimentation control design storm event, defined as the 2-year, 3-hour duration storm. p. Changes in Site Topography: 1. The maximum surface gradient on any artificially created slope shall be two feet of horizontal run to one foot of vertical fall (2:1). This gradient may be increased to a steeper slope, if, in the judgment of the Director of Public Works, it has been demonstrated by the developer through engineering calculations performed by a qualified professional engineer that surface erosion at such a gradient can be controlled to that erosion rate equal to a properly stabilized 2:1 slope under the same conditions. Suggestion: Take measurements of the maximum grades. Does this apply to your site? 2. The developer shall, at all times, protect adjacent properties and public rights-of-way and easements from damage occurring during, or resulting from, grading operations. The developer shall restore public improvements damaged by the developer's operations. q. Correction of Defective Maintenance. If the developer or owner, or both, refuse or fail to adequately maintain and keep the erosion and sediment control facilities functional at all times, and the owner of the property is given seven days notice to perform the work necessary to make the facility functional and fails to do so, the City may use public funds to complete maintenance of the facilities at the cost of the developer and the property owner, who shall be jointly and severally liable for such costs. r. Progress of Work. All work required or approved under this section shall proceed continuously to completion in an expeditious manner unless otherwise authorized by the Director of Public Works, with the intent that work may be halted, for example, due to weather conditions or the need to coordinate other construction on the project site. _______________________________ _____________________________ Signature of Property Owner Print Name ______ Date _______________________________ _____________________________ Signature of Project Manager Print Name ______ Date _______________________________ _____________________________ Signature of Excavator Print Name ______ Date Sign at the bottom of each page ________________________________ Sheet E100 POLE 42.10 EM RECESSED RECESSED WALL EX WALL/CEILING 2X2 RECESSED LED, ENCLOSED LENS, PROVIDE 0-10V DIMMING COLUMBIA LIGHTING: LTRE 22-40 HL G - RFA-ED U - G1 2X4 RECESSED LED. HIGH EFFICIENCY ACRYLIC CENTER LENS STEEL HOUSING. EXTRA HIGH LUMEN OUTPUT. COLUMBIA LIGHTING: LCAT 24 - 40 XL G - U SAME AS C/80, EXCEPT FIXTURE IS 2X2 VERY HIGH LUMEN OUTPUT. COLUMBIA LIGHITNG: LCAT 22 - 40- VL G - EU LED EMERGENCY LIGHT, THERMOPLASTIC HOUSING, INTEGRAL LED BASED LAMP. PROVIDE SELF-DIAGNOSTICS OPTION. DUAL LITE: EV 4 I LED EXIT SIGN. DUAL LITE: EVE U G W I NIC NOT IN CONTRACT CKT CIRCUIT - NUMBER AS NOTED (TYP.) UON UNLESS OTHERWISE NOTED A/100 LIGHTING FIXTURE DESIGNATION - SEE SCHEDULE ETR EXISTING TO REMAIN AC WP ABOVE COUNTER T CKT-XX WEATHERPROOF E EMERGENCY LIGHT, CIRCUIT, PANEL C CONDUIT, CONCEALED. SIZE AS NOTED (TYP.) CONDUIT, UNDERGROUND OR UNDERFLOOR CONDUIT, EXPOSED FLEX CONDUIT, FLEXIBLE MULTI-OUTLET ASSEMBLY-RECEPTACLES AS INDICATED M HOMERUN TO PANEL/CIRCUITS AS NOTED #X NEUTRAL, HOT, GROUND # 12 UON/SPECIFIED PNL PANELBOARD - SEE SCHEDULES 1 REFER TO INDICATED NOTE RECPT TELECOM OUTLET DUAL PORT TELECOM OUTLET IN FLOOR BOX F/60 6100 110 SURFACE LED LENSED STRIPLIGHT, STEEL CHANNEL, ACRYLIC FORMED DIFFUSER. COLUMBIA LIGHTING: LCL 4 - 40 HL- EU-U 2X4 RECESSED LED TROFFER. COLUMBIA LIGHTING: LJT24-40LWG-FSA12-EU TELECOM OUTLET IN FLOOR BOX DUPLEX RECEPTACLE - NEMA 5-20R QUADRUPLEX RECEPTACLE - NEMA 5-20R 7" ~ L-80X26# PIPE PILE G/40 FINISHED GRADE OR ASPHALT RECESSED DUPLEX RECEPTACLE - NEMA 5-20R GFCI TYPE 49.40 SURFACE CEILING 24" LED UNDERCABINET LIGHT, INTEGRAL DRIVER IN EACH UNIT. THIN PROFILE. PROVIDE HARD WIRE CONNECTOR. CON-TECH LIGHTING: LPU 24 40K-P-LPAHW72-P 2X4 RECESSED LED TROFFER. COLUMBIA LIGHTING: LJT24-40HLG-FSA12-EU 1381 73.1 RECESSED 6" OPEN SQUARE LED DOWNLIGHT. NON-CORROSIVE STEEL PLATFORM. PRE-WIRED J-BOX PRESCOLITE LIGHTING: LF6SQLED6G440K L/50 36.40 100 CABLE MOUNT 9'-0" AFF 2X2 LED, ENCLOSED LENS. FIXED OUTPUT. PROVIDE CABLE MOUNT ACCESSORIES PART NUMBER; CM48Y2SC3F-KIT COLUMBIA LIGHTING: LTRE 22-40 HL CM - RFA-E U - G1 LED PROCEDURE LIGHT, CEILING MOUNTTOUCHLESS ON/OFF CONTROL WITH DIMMING. SIX 5,500K LED. GREEN SERIES 900 PROCEDURE LIGHT. WELCH ALLYN: 44900-C CEILING DUPLEX RECEPTACLE IN FLOOR BOX RECEPTACLE - NEMA CONFIGURATION AS NOTED K/20 M/120 SIMPLEX RECEPTACLE TV SYSTEM OUTLET WALL MOUNTED AT STANDARD DEVICE HEIGHT UON J-BOX 1 E100 POLE BASE DETAIL-ELEVATION VIEW NTS W/120 2993 9235 72.1 82 RECESSED 25' POLE ADD ALT#1 X/30 2662 95 WALL 14' AFG POLE BASE NOTES 1. ALL PILING SHALL BE STEEL, 7 INCH L-80X26#. 2. ALL STRUCTURAL STEEL SHALL BE ASTM A36. Y/120 9235 82 25' POLE 3. ANCHOR BOLTS SHALL BE STEEL ASTM A 307. 1111 60.7 5. ELECTRICAL CONTRACTOR SHALL VERIFY ALL UTILITY LOCATIONS & OBTAIN CLEARANCE FROM THE OWNER PRIOR TO BEGINNING PILE DRIVING OPERATION. 6. PILING SHALL BE DRIVEN TO A MINIMUM DEPTH OF 15' BELOW THE FINISHED GRADE INTO STRUCTURAL SOIL. MOTOR CONTROLLER MOTOR DISCONNECT COMBINATION STARTER/DISCONNECT VFD CONTROLLER LITEFRAME: LC6LED8 120-6LCLED940K8 POLE MOUNT AREA LED, THERMAL MANAGEMENT RUGGED CAST ALUMINUM HOUSING. INTEGRAL WEATHERTIGHT LED DRIVER COMPARTMENT. FULL CUTOFF CREE LED: OSQ A NM 3ME A 40K UL BK LED OUTDOOR WALL PACK, PERIMETER ILLUMINATION. ALUMINUM HOUSING, RATED FOR -40 DEGREES OPERATING TEMPERATURE, WITH BATTERY PACKUP RATED DOWN TO -20 DEGREES. PROVIDE INTEGRAL BATTERY OPTION FOR EMERGENCY. FULL CUTOFF HUBBELL OUTDOOR LIGHTING: LNC2 12L 1 4K 3 2 BBU POLE MOUNT AREA LED, THERMAL MANAGEMENT RUGGED CAST ALUMINUM HOUSING. INTEGRAL WEATHERTIGHT LED DRIVER COMPARTMENT. PROVIDE BACKLIGHT SHIELD OPTION. FULL CUTOFF CREE LED: OSQ A NM 3ME A 40K UL BK 6" SQUARE RECESSED DOWNLIGHT. NON-CORROSIVE STEEL PLATFORM. UL LISTED FOR WET LOCATION. PROVIDE EMERGENCY BATTERY PACK OPTION. UL LISTED FOR WET LOCATION, AND CSA CERTIFIED. PRESCOLITE LIGHTING: LF6SQLED6440K SWITCH - SINGLE POLE SWITCH - TWO POLE 2 SWITCH - THREE WAY 3 SWITCH - FOUR WAY 4 SWITCH - DIMMING TYPE D SWITCH - OCCUPANCY SENSOR SWITCH - THERMAL OVERLOAD O SWITCH - THREE WAY DIMMER 3D CALL-IN SWITCH SWITCH - WITH TIMER X FS SPRINKLER FLOW SWITCH TS SPRINKLER TAMPER SWITCH PHOTOELECTRIC TYPE SMOKE DETECTOR IONIZATION TYPE SMOKE DETECTOR HEAT DETECTOR- F INDICATES FIXED TEMP ONLY C INDICATES ABOVE CEILING RESIDENTIAL TYPE SMOKE DETECTOR T TS FS TS P F°135 I HC R DUCT MOUNTED SMOKE DETECTOR FIRE ALARM HORN/STROBE H 8. SPLICES IN PILING PIPE SHALL BE MADE USING A QUALIFIED WELDING PROCEDURE IN ACCORDANCE WITH ASTM B31.1 USING P3 PROCEDURE. (7018 ROOT 7018 INTER & CAP) 9. CONCRETE SHALL ATTAIN A 28 DAY COMPRESSIVE STRENGTH OF 2500 PSI. 4, 1 1/8" HOLES FOR 4-1" A307 BOLTS MATCH POLE BASE BOLT CIRCLE FIRE ALARM MANUAL STATION FACP FIRE ALARM CONTROL PANEL F FACP FANN FIRE ALARM REMOTE ANNUNCIATOR FANN TEMPERATURE SENSOR T COMPUTER OUTLET C TTB/C TELEPHONE TERMINAL BOARD/CABINET PC PHOTOCELL PROJECT NO. BC BELOW COUNTER DRAWN BY: SNS NURSE CALL - PATIENT STATION REVIEWED BY: EWC NURSE CALL - CEILING LIGHT CONSTRUCTION DOCUMENTS NURSE CALL - EMERGENCY PULL CORD SHEET TITLE EXIT SIGN LIGHTING FIXTURES - VARIOUS TYPES AS NOTED OCCUPANCY SENSOR - CEILING MOUNT OC SMOKE DETECTOR SD DLM ADD ALT#1 ELECTRICAL LEGENDS AND SCHEDULE SHEET NO. E100 POLE BASE DETAIL NTS 8-16-2016 DATE ABOVE COUNTER DOCUMENT CAMERA E100 1516.00 PC AC DIGITAL LIGHT MANAGEMENT CONTROLLER (DLM) 2 Copyright Livingston Slone, Inc. all rights reserved. All parts of this drawing and the design it represents are instruments of service, and without the expressed, written consent of Livingston Slone, Inc., remain its exclusive property and shall not be used, reproduced, or stored in any form. The "Livingston Slone, Inc." name and logo are trademarks of Livingston Slone, Inc. TTB BATTERY-POWERED EMERGENCY LIGHT 7"~ L-80X26# PIPE PILE EN ED P R O F E S S I O NA L EMERGENCY SHUT OFF PUSHBUTTON SWITCH 7"~ STL. PIPE PILE EDWARD W. CARLSON 08/16/2016 EE-9354 T G ER FIRE ALARM STROBE RADIUS TO MATCH POLE BASE PLATE 7. PILING SHALL BE DRIVEN TO A VERTICAL TOLERANCE OF 1/4 INCH PER 10'-0" OF VERTICAL AND TO A HORIZONTAL TOLERANCE OF 1 INCH. 10. WELDED SIRE FABRIC SHALL CONFORM TO ASTM A185. RECESSED J IS Z/20 E R EG 4. ALL WELDING SHALL BE PERFORMED IN ACCORDANCE WITH AMERICAN WELDING SOCIETY. (AWS) D1.1-86 6" LED DOWNLIGHT. 0-10V DIMMING OPTION. ONE-PIECE NON-CORROSIVE STEEL HOUSING. HIGH PURITY ALUMINUM REFLECTOR. ROUGH-IN FOR FUTURE SOUND FIELD EQUALIZATION SYSTEM AT +66" AFF. PROVIDE 1" CONDUIT FROM JUNCTION BOX TO ACCESSIBLE CEILING SPACE. PROVIDE BLANK 1-GANG COVER PLATE. JUNCTION BOX MOTOR - SIZE AS INDICATED SW N/50 TV ARCHITECTURE 5490 62.5 Consulting Engineers, Inc. 500 MBA H/10 CONDUIT SLOTS 15'-0" 107 DUPLEX RECEPTACLE - NEMA 5-20R SPLIT WIRED J/50 24" MIN 4151 HOMER, ALASKA 4255 80.20 RECESSED COLUMBIA LIGHTING: LTRX 24 40 AX G RFA-EAX U- G1 TRANSFORMER 3900 ARCTIC BOULEVARD SUITE 301 ANCHORAGE ALASKA 99503 6X6 BY 10X10 WWM REINFORCEMENT 8503 100 2x4 HIGH EFFICIENCY RECESSED ENCLOSED LED EXAM FIXTURE. GRID LAY-IN CEILING TYPE. PROVIDE LENS GASKETING OPTION. XFMR INTERIOR DESIGN 24" DIAMETER CONCRETE BUMPER WITH 8" HOLE FOR PILING. 3640 RECESSED MODEL ER D/50 3/8" 103 DESCRIPTION PLANNING C/80 BASE COVER PROVIDE SLOPE FOR WATER RUNOFF 8283 MOUNTING (907) 274-2622 / FAX (907) 274-0914 [email protected] B/50 LUMEN/WATT INE GALV. FASTENERS, PER ASTM A307 1.5" PLATE TO MATCH POLE BASE WITH 7 1/16" HOLE FOR PIPE FILE TOTAL LUMEN SYMBOL ENGINEERING A/100 SYMBOL SOUTH PENINSULA HOSPITAL HOMER MEDICAL CLINIC EXPANSION CALLOUT EXPLANATION KENAI PENINSULA BOROUGH ABBR. #10 BONDING JUMPERS 36" LEGEND LUMINAIRE SCHEDULE HAND HOLE THIS IS A STANDARD LEGEND, ALL SYMBOLS SHOWN ON LEGEND ARE NOT NECESSARILY ON THE DRAWING(S). Phasing Plan FIRE ALARM PANEL AND FIRE DEPARTMENT CONNECTION SAMPLE PHASING DIAGRAMS (INFORMATION ONLY) XRAY MAINTAINING CLINIC OPERATIONS DURING CONSTRUCTION IS A HIGH PRIORITY. ACHIEVING THIS WILL REQUIRE CAREFUL CONSTRUCTION PHASING AND COORDINATION BETWEEN THE CONTRACTOR AND KPB MEDICAL AND MAINTENANCE STAFF. PRIMARY CONSTRUCTION FOCUS TEMPORARY PUBLIC EGRESS PATH INCLUDING COVERED STAIRS. MUST EXTEND TO PUBLIC WAY. EXISTING ROOMS WITH NATURAL VENTILATION. VENTILATION MUST BE MAINTAINED WHILE ROOMS ARE IN OPERATION. SEE MECHANICAL SPECIFICATIONS * FOR CLARITY, ONLY EXISTING WALLS ARE SHOWN IN THIS DIAGRAM THESE DIAGRAMS DO NOT REPRESENT ALL REQUIREMENTS OR POSSIBILITIES FOR PHASING. CONSTRUCTION WILL NOT BE LIMITED TO THE AREAS SHOWN IN THESE DIAGRAMS. EXAMPLE OF PHASED CONSTRUCTION, PHASE I (EXTENT AND NUMBER OF PHASES TO BE DETERMINED BY CONTRACTOR IN COORDINATION WITH KPB) PRIMARY CONSTRUCTION FOCUS TEMPORARY EXTERIOR CONTRACTOR ENTRANCE IN THIS AREA TO AVOID CROSSING PUBLIC PATHS EGRESS PATH MUST EXTEND TO PUBLIC WAY. SPRINKLER SYSTEM AND FIRE ALARM SYSTEM MUST BE COMPLETE BEFORE OPENING THIS AREA TO THE PUBLIC NOT AVAILABLE TO STAFF OR PUBLIC DURING THIS PHASE DUE TO INSUFFICIENT EGRESS. INTERIOR WORK MAY BE EXTENDED OR SHIFTED FROM PHASE 1 TO PHASE 2 IN THIS AREA. * FOR COORDINATION PURPOSES, BOTH NEW AND EXISTING WALLS ARE SHOWN IN THIS VIEW EXAMPLE OF PHASED CONSTRUCTION, PHASE 2 (EXTENT AND NUMBER OF PHASES TO BE DETERMINED BY CONTRACTOR IN COORDINATION WITH KPB) PHASE 3 CONTRACTOR ENTRY PRIMARY CONSTRUCTION FOCUS * FOR CLARITY, ONLY FINISHED LAYOUT IS SHOWN IN THIS VIEW. EXAMPLE OF PHASED CONSTRUCTION, PHASE 3 (EXTENT AND NUMBER OF PHASES TO BE DETERMINED BY CONTRACTOR IN COORDINATION WITH KPB) THESE DIAGRAMS ARE NOT FOR CONSTRUCTION. THEY ARE SAMPLES FOR THE CONTRACTOR'S INFORMATION ONLY. CONTRACTORS ARE ENCOURAGED TO PROVIDE DIAGRAMS AS PART OF THE DISRUPTION PLAN OUTLINE REQUIRED AT BIDDING. THE DIAGRAMS ON THIS PAGE ARE PROVIDED ONLY AS A GRAPHIC EXAMPLE. SOUTH PENINSULA HOSPITAL HOMER MEDICAL CLINIC EXPANSION SITE & SOILS INVESTIGATION MAY 5, 2016 WINCE-CORTHELL-BRYSON BOX 1041 KENAI, ALASKA 99611 TELEPHONE: 283-4672 FAX: 283-4676 WINCE CORTHELL BRYSON Consulting Engineers Box 1041 Kenai, Alaska 99611 Phone 907-283-4672 Fax 907-283-4676 Email: [email protected] May 5, 2016 Livingston Sloane, Inc. 3900 Arctic Boulevard, Suite 301 Anchorage, Alaska 99503 Attention: Ryan Johnson Subject: Homer Medical Clinic Site & Soils Investigation T6S, R13W, Section 18, S.M., Alaska, Fairview Subdivision No 11 Lot 2-A Block 5 In conjunction with the building expansion at the Homer Medical Center, we have performed a site and soils investigation on the subject property. Following is a narrative of our procedures, findings, conclusions and recommendations for your review and use. SITE TOPOGRAPHY The proposed site for the expansion of the Homer Medical Center is in the southeast corner of a lot 1.8 acres in size, bordered on the west by Bartlett Street, on the south by E Fairview Avenue, on the north by W Danview Avenue and on the east by residential lots. The site is moderately sloping to the south, leveled out by previous construction, mostly developed with parking in the north half of the lot and the existing building south central. The area for the planned expansion to the south and east of the building is landscaped with sod. CLIMATE The area’s proximity to the Gulf of Alaska, Cook Inlet and the Kenai Mountain Range causes climatic conditions classified as a transitional zone but influenced by many maritime factors. While the area generally experiences less cloudiness and precipitation than maritime zones, it has a higher amount of precipitation and somewhat warmer winters than other transitional areas of Alaska. Ground frost tends to thaw as much as a month prior to transitional areas as little as 80 miles to the north of Homer. The University of Alaska Environmental Atlas lists the following climatic averages for the area: Mean Annual Precipitation Mean Annual Snowfall Mean Annual Temperature Low/High Mean Temperatures in January Low/High Mean Temperatures in July Philip W. Bryson PE Mark E. Blanning PE 36 inches 70 inches 37 degrees F 16/28 degrees F 44/62 degrees F Alan N. Corthell PE E. Casey Madden PE GEOLOGY According to the “United States Department of Agriculture, Soils Survey of the Homer – Ninilchik Area”, the site soils are categorized as moderately sloping beluga silt loam. The beluga series consists of poorly drained soils that are moderately deep and deep to firm underlying material. The beluga soils are mottled and stratified and commonly underlain by colluvium. Well boring logs from nearby lots confirm that the depth of silt loam material is greater than 70 feet. SUBSURFACE CONDITIONS On April 25, 2016, a small track mounted hydraulic excavator was used to dig three test holes to depths up to 9 feet below existing ground surface. Generally speaking, soils consisted of 0.3 feet of sod and 3.0 feet of sandy silt with cobbles over native silt. The native silt ran to the bottom of each test hole. The firmness of the silt increased with depth and as the water content lowered. The test holes showed water content increasing to the west side of the lot. A penetrometer was used to quantify the soil bearing value of the material at variable depths in the excavations. The soil bearing values range from 0.75 tons per square foot to 3.0 tons per square foot. Copies of the test boring logs are attached to this report. EXISTING FOUNDATION A test hole excavated at the south perimeter of the existing building revealed the foundation for the existing building consisted of a footer with a 40 inch CMU wall. The footer rests on approximately 4’ of non frost susceptible (NFS) poorly graded sand (sp). The foundation drain is installed approximately 1 foot below the bottom of the footer leaving 3 feet of saturated sand below. See attached sketch. UTILITIES The property is well served with water, sewer, telephone, gas and electric utilities adjacent to and crossing the site, as shown on the attached site plan. Collection of subsurface water below the existing foundation is achieved with a shallow system that drains to daylight at the south edge of the lot. Storm runoff is relieved into sizable ditches along the streets to the west and south of the lot. The existing roof drains are connected to the foundation drainage system. CONCLUSIONS Based on our investigation, we conclude that the soils strata though the site are uniform in consistency but variable with water content in density. All native and imported fill materials outside the existing building foundation are frost susceptible materials. Constructing a foundation in the native silt material will require draining it of subsurface waters to an adequate depth and importing NFS gravel material to support structures. Philip W. Bryson PE Mark E. Blanning PE Alan N. Corthell PE E. Casey Madden PE
© Copyright 2026 Paperzz