2010 OAWWA Annual Conference Maggie Rodgers, Water Quality Manager Tyrone Butler, Morgan Plant Manager Cleveland Water History of Morgan Existing Reservoir Issues Site Constraints Reservoir Design Construction Challenges Tracer Study(ies) Calculations 1856 - Distribution of water from Lake Erie 1911 - Disinfection 1916 - Garrett Morgan uses “safety hood” to rescue workers trapped by tunnel collapse during intake extension 1917 - Filtration Late 1910’s - 25 MG reservoir 20 MG cell 5 MG cell Late 1990’s facility plan identified replacement of the Morgan Reservoir as the #1 priority Significant cracks Silt No piles Root intrusions Poor baffling did not allow 20 MG cell to be removed from service while plant operating Significant site constraints Sludge World Filters Sed Basins El. 581 Flocs El. 667 MORGAN WATER WORKS PLANT SITE PLAN Step 1: Demolish Existing 5 MG Reservoir Cell Step 2: Construct New Pump Station Sludge World Raw Water Pump Station Filters Sed Basins El. 581 Flocs Step 6: Future West Reservoir Chemical Step 5: Demolish Existing 20 MG Reservoir Step 4: Construct New East Reservoir Step 3: Demolish Existing Pump Station El. 667 MORGAN WATER WORKS PLANT SITE PLAN Building Economic downturn – Do we really need two separate cells? Maximize size of “East” Reservoir Needs to be of sufficient volume that the plant can operate on half while the other half is down for maintenance/cleaning 15 MG - two 7.5 MG cells Drilled piers Resist lateral seismic loading better than driven Less duration, noise, and vibration 80’ deep to shale bedrock 364 piles R 18 foot spacing Obstacles Wooden piles from old pump station and boiler building foundations Concrete pads for old pumps Ohio EPA Policy for Determining Fluoride Compliance: “Public water systems that perform tracer studies using fluoride will not be in violation of ORC 6109.20 as long as DDAGW has received prior notification of the tracer study and the fluoride levels in the distribution system do not exceed the SMCL of 2.0 mg/L.” 327.33' 256' 42' 36.5' Valve Closed 180.33' North Cell (Out -of-service) To FHS Pumps To LS Pumps 144.67’ 108.33’ 15.5' F 144.67' 108.33' Filter Effluent Junction Chamber 3 F Clearwell Effluent Sampling Point South Cell (In Service) L:W = 45:1 Clearwell Influent Sampling Point Step dose, reverse tracer Ohio EPA protocol calls for F addition 10 pipe diameters before clearwell influent for proper dispersion Conduit not accessible at this location Used regular F feed point in the filter effluent Stabilize F through the reservoir (1.1 mg/L target) Take production to at least 75 MGD Lower water level in the clearwell to 10 feet (minimum anticipated operating level) Source water 30 minutes Clearwell influent 15 minutes until start 30 minutes during tracer Clearwell effluent 15 minutes until start 5 minutes during tracer Figure Tracer 2. Tracer Study Results - Graphical Method 1st Attempt Study Results – Graphical Method T10 9:53 1.4 1.3 Clearwell Effluent Clearwell Influent 1.2 Avg F Feed 1.1 Raw Avg F Raw 1 90% Retention 0.9 33.62 lbs 0.7 0.6 F Feed Stop 8:33 0.5 0.4 0.3 0.2 12.76 lbs 0.1 14.39 lbs Time 13:30 13:15 13:00 12:45 12:30 12:15 12:00 11:45 11:30 11:15 11:00 10:45 10:30 10:15 10:00 9:45 9:30 9:15 9:00 8:45 8:30 8:15 8:00 7:45 7:30 7:15 0 7:00 F (mg/L) 0.8 Why did it take so long for the influent fluoride to drop? Much discussion internally and with Ohio EPA Quantity in feed piping, after pump shut off responsible for discrepancy Mathematically subtracted this quantity Ohio EPA still said no Figure 2. Tracer Study Results - Graphical Method 1.2 1.1 Clearwell Effluent Clearwell Influent 1 Avg F Feed Source 0.9 Avg F Raw 90% Retention 0.8 0.6 0.4 0.3 T10=13:17 F Feed Stop 12:00 0.5 0.2 0.1 Time 15:15 15:00 14:45 14:30 14:15 14:00 13:45 13:30 13:15 13:00 12:45 12:30 12:15 12:00 11:45 11:30 11:15 11:00 10:45 10:30 10:15 0 10:00 F (mg/L) 0.7 2 hrs, 10 minutes for influent concentration F to equal effluent concentration Sampling continued until 3 hrs to make sure steady state was reached Effective Volume Factor = T10/T T = Theoretical Detention Time = 81.3 min T10 = Time when clearwell effluent F is lower than the influent F by 10% of the test range Test range = 1.083 – 0.130 = 0.953 mg/L T10 F = 0.90 x 0.953 + 0.130 = 0.988 mg/L Occurred at 77 minutes into the tracer Influent conduit detention time = 5 minutes Plug flow assumed since it is a pipe Clearwell T10 = 72 minutes Effective Volume Factor = T10/T = 72/81.3 = 0.89 Ohio EPA - Net advection of F must be within 10% of change in F storage within the clearwell Net Advection = (F out of clearwell) – (F fed to clearwell) Net advection = 45.679 – 10.059 = 35.620 lb Change in storage = (F in clearwell at t=0) – (F in clearwell at t=2:10) Change in storage = 40.363 - 4.524 = 35.839 lb % F accounted for = (Net Advection)/(Change in storage) x 100 % F accounted for = 35.620/35.839 = 99.4% Morgan plant staff MWH URS HMM
© Copyright 2026 Paperzz