Costs - EarthCare Landscaping

B A EarthCare Landscaping
21730 Stevens Creek Blvd, #201B
Cupertino, CA 95014
2015
Pricing Sheet
We hope this worksheet gives our customers a rough idea of local costs.
A site visit is the only way to deliver a more accurate bid for your project.
Please see www.earthcareland.com/who-we-are/bid-fee-policy.
ROUGH OVERALL SFT COSTS
Demo’n, Soil Prep, Planting, Irrigation Only
Soft & Hardscape, Typical
More Complex Hardscape
$8 to $10/sft
$13 to $18.5/sft
$27 to $39/sft & beyond
DEMOLITION & ROUGH GRADE
$45/hr + hauling
DRAINAGE
$435 downspout to a drywell
ELECTRICAL
Lay Elec.Conduit
Outlet
$15/linear ft
$450 each
CARPENTRY
Decks
Arbors
Fencing
Gates
Screens/Trellis
Repairs/Misc
PATIOS/PATHS
Gold or Grey Fines
Gravel
Flagstone in Sand, fines joints
Flagstone in Sand, groundcover
Flagstone in Concrete
Flagstone Over Existing Concrete
Concrete
Concrete Steps/Landings
Pavers
Pavers Over Existing Concrete
TurfBlock/Stone
Pervious Pavers
Bricks in Sand
Bricks in Concrete
Bricks Over Existing Concrete
$30 to $35/sft + benches, steps
$30 to $40/sft
$51/linear ft for 6' tall
$275 each
$20/sft + gates
$10/sft inc. excavation & borders
$8/sft inc. excavation & borders
$21/sft Ariz & $22/sft full range Conn inc. excavation
$19/sft Ariz & $20/sft f.r. Conn + planting & irrigation
$37/sft Ariz & $38/sft f.r. Conn inc. excavation
$23/sft Ariz & $24/sft f.r. Conn + crack isolation
$16/sft plain; $17/sft color; $18.5/sft aggregate;
$22/sft stamped; $18/sft pervious w/color inc. exca.
$500 for 3'x3' raised landing; $155 for each 3' wide step
$21/sft inc. excavation
$14.5/sft in sand, generally no demo or excavation needed
$19/sft inc. excavation + irrigation & planting
$27/sft inc. excavation
$21/sft inc. excavation
$39/sft inc. excavation
$15.5/sft in sand & $24/sft in mortar, no demo or exca
2015 Pricing Sheet
Page 1 of 3
Office 408-871-2792
Fax 408-706-5601
B A EarthCare Landscaping
21730 Stevens Creek Blvd, #201B
Cupertino, CA 95014
PATIOS/PATHS (continued)
Recycled Concrete/Urbanite
Staining & Other Concrete Resurfacing
Asphalt
Playground Poured in Place
$20/sft inc. excavation
$4 to $15/sft
$10/sft inc. excavation
$25/sft inc. excavation & borders
WALLS
Wood
Sonoma Fieldstone
Stacked Recycled Concrete
Stacked Flag/ Ledgerstone
Stacked Block
Concrete Block
Brick
Poured Earth
Poured Concrete
Stucco Fence
Columns
Caps
Veneer
Built-in-BBQs
$43/sft rdwd & $41/sft PT inc. grading & drainage
$52/sft inc. grading & drainage
$30/sft
$90/sft Ariz & $100/sft Conn inc. grading
$50/sft inc.grading & drainage
$78/sft inc. grading, drainage & stucco + cap
$52/sft single & $86/sft double + grading
$80/sft 9" wide
$74/sft 8" wide + color
$61/sft 9" wide
4'Tx22"W: $1550 stucco or $2300 flag veneer + cap
$50/sft random Ariz; $40/sft pre-cut Ariz; $47/sft El Dorado
$45/vertical sft Ariz. Flagstone;
$10,000 to $20,000
RAISED VEGETABLE BEDS
$
DRY CREEKS
$10/sft inc. excavation
FOUNTAINS
$300 to $400/sft
BORDERS
$6/linear ft 1x4polywog; $7/linear ft 2x4 rdwd; $8/linear ft Trex
LAWNS & MEADOWS
Synthetic
$2.5 to $3.5/sft
$18/sft inc. excavation
SOIL PREPARATION
Soil Prep by Yard
$1.5 to $2.5/sft
$115/yard using onsite soil
BOULDERS
$90 small; $180 med; $290 large Sonoma
STEPPING STONES
$16/linear ft Ariz & $18.5/linear ft Conn single spaced, no lawn
PLANTS
Plants
Trees
Vines
Planting Only
Pots
Root Barrier
conditional 4 month warranty on plants & 1 year for trees
$20/ 1 gal; $55/ 5 gal; $180/ 15 gal shrub
105/ 5 gal; $200/ 15 gal; $425/ 24" box; $1500/ 36" box
$55/ 1 gal; $85/ 5 gal
no warranty: $8/ 1 gal; $16/ 5 gal; $85/ 15 gal tree
$100 each + cost of pot, plants & irrigation
$23/ linear ft for 24" deep + root pruning
2015 Pricing Sheet
Page 2 of 3
Office 408-871-2792
Fax 408-706-5601
B A EarthCare Landscaping
21730 Stevens Creek Blvd, #201B
Cupertino, CA 95014
IRRIGATION
Backflow Devices
Hose Bibbs
Timers
Drip
Inline Drip
Sprinklers
Shut-off Valves
Irrigation Boxes
Misc. Irrigation
LIGHTING
Traditional
LED
MULCH
Tan Bark
Wood Chips
Shredded
Shredded on Hills
Playground Fiber
Mulch Broken Down
MISC
Wrought Iron Fences
Wrought Iron Gates
Chain Link Fence
Timber Steps
Hourly Rates
$240 each
$420 each inc. some mainline
$350/ 6 station; $440/ 9 sta12;
$500/ 12 sta. + outdoors
$6.5/emitter inc. drip valve
$1.3/ sft inc. drip valve + raised beds
$1.5/sft lawn; $2.5/sft 6" pop-ups;
$3.5/sft 12" pop-ups
$25 each
$175 each
$400 trans.; $135 path & up lts; $190 down; $230 wall
$350 trans.; $215 path; $215 up; $230 down; $250 wall
$1.2/sft inc. newspaper
$..95/sft inc. newspaper
$..95/sft inc. newspaper
$1.80/sft inc. newspaper & jute
$4/sft inc. fabric & 5" of fiber
$25/sft
$100/sft
$7.5/sft
$48/linear ft redwood + if walls needed
$45/hr laborer; $60/hr mason; $70/hr carpenter
2015 Pricing Sheet
Page 3 of 3