Hinkley Point C Connection Project Reflections on the consent process for Nationally Significant Infrastructure Projects Joe Turner MRTPI Introduction National Grid: what we do Infrastructure planning and the Planning Act 2008 Our approach Hinkley Point C Connection project Alternatives for the decision maker Mendip Hills AONB and visual amenity Stakeholder engagement Securing mitigation Conclusions 2 National Grid: what we do… Electricity transmission Gas transmission Gas distribution Interconnectors 3 Planning Act 2008 – infrastructure planning Nationally Significant Infrastructure Projects (England & Wales) Infrastructure Planning Commission Independent decision-making body to consider & grant consents (BUT now abolished) National Policy Statements Six for energy – Designated by government in July 2011 Development Consent Order Concept of a single consent Mandatory pre-application consultation Previously not mandatory; now mandatory front-loaded process Concept of gaining ‘consensus’ and dealing with objectors before submission Primarily a written process Inquisitorial not adversarial hearings 4 NSIPs in the South West Project Developer Status Hinkley Point C Connection National Grid Decided (granted) Hinkley Point C Nuclear Power Station NNB Generation (EDF) Decided (granted) A30 Temple – Higher Carblake Improvement Cornwall Council Decided (granted) Bere Alston – Tavistock Rail Reinstatement Devon County Council Pre-application Portishead Branch Line – MetroWest Phase 1 North Somerset Council Pre-application Oldbury New Nuclear Power Station Horizon Nuclear Power Pre-application Avon Power Station Scottish Power Pre-application West Somerset Tidal Lagoon Longbay Seapower Pre-application Seabank 3 CCGT SSE Pre-application 5 National Grid’s approach PLANNING ACT 2008 / LOCALISM ACT 2011 NATIONAL POLICY STATEMENTS SQSS ELECTRICITY ACT obligations TRANSMISSION LICENCE obligations NEED CASE for new infrastructure established STRATEGIC OPTIONS identified / broad environmental appraisal ROUTE CORRIDOR studies / desktop environmental surveys and site visits DESIGN AND ROUTEING APPROACH DETAILED ROUTE ALIGNMENT developed / full Environmental Impact Assessment and surveys CONTINUING CONSULTATION and ENGAGEMENT (key stakeholders and public) 3 years APPLICATION FOR DEVELOPMENT CONSENT prepared 12-18 MONTH EXAMINATION / DECISION PERIOD BY PLANNING INSPECTORATE 6 Project overview The DCO provides powers for… • 400kV overhead line of approx. 48.5km; • 400kV underground cables of approx. 8.5km through Mendip Hills AONB; • three 400kV cable sealing end compounds; • New Sandford 400/132kV substation; • extension of existing Seabank 400kV substation; • removal of existing 132kV overhead lines and construction of replacement 132kV overhead lines and underground cables; and • extensions or other changes to existing 132kV substations at Churchill, Portishead, Avonmouth and Seabank. 7 The ‘T pylon’ Winner of Pylon Design Competition jointly arranged by RIBA, DECC and National Grid Designed by Bystrup Typically 30-35m tall – shorter than a typical lattice pylon (c. 50m) Training line constructed at National Grid training centre in 2015 Proposed for majority of Hinkley Point C Connection project 400kV overhead line sections Key dates in decision process Date Milestone 28 May 2014 Application submitted by National Grid 19 June 2014 Application accepted by Planning Inspectorate 12 July – 26 August 2014 Period for registration as interested party (‘relevant representations’) 28 November 2014 Notification of preliminary meeting (‘Rule 6’ letter) 19 January 2015 Preliminary meeting; examination opens 29 January 2015 Examination timetable published (‘Rule 8’ letter) 19 July 2015 Examination closes 19 October 2015 Examining Authority (ExA) issued report to Secretary of State (SoS) 19 January 2016 SoS issued decision letter agreeing with ExA recommendations 9 February 2016 DCO comes into legal force 2 March 2016 Judicial review deadline; deadline for applications for corrections to DCO 9 Undergrounding of existing WPD line (Option B only) Portishead substation Option B Option A Removal of existing WPD lines Undergrounding of existing WPD line Option A vs Option B Undergrounding and the AONB Substantial weight accorded to the AONB in accordance with EN-1 para. 5.9.9… 400kV underground cables South of Mendips SEC “The proposed development falls partly inside the nationally designated area of the Mendip Hills Area of Outstanding Natural Beauty (the AONB), for which the decision maker is to give substantial weight to the conservation of natural beauty and landscape” [ExA Report para. 5.9.4] ‘Serious concerns’ about treatment of AONB only addressed by submission of Design Approach during examination… The Panel is satisfied that the mitigation secured through the updated Design Approach document and embedded landscape planting … would sufficiently alleviate what were, initially, serious concerns about the potential adverse landscape and visual effects of the CSE compound in this location [ExA Report 5.9.37] Engaging stakeholders Stakeholder mapping Coordination of relationships (land, engineering, legal drafting, environmental) - Are we talking to the right people? - Every stakeholder needs an ‘owner’ Early preparation of SoCG (where possible?) Clear objectives Narrowing issues? Withdrawal of reps? Signed agreements? Need to help stakeholders engage - Make it easy for them Raising awareness of process 12 Securing mitigation Initial Design S42 Design Freeze Submission Design Freeze Consultation & engagement with Stakeholders EIA Develop mitigation Examination Response to LIR and reps Environmental Statement CEMP Draft DCO Requirements Discuss S106 commitments Update CEMP Develop requirements Finalise S106 13 Conclusions Delivering certainty for promoters Engaging communities and stakeholders Challenges of ‘frontloading’ – flexibility A ‘one stop shop’? A new way of making decisions Highly resource intensive 14
© Copyright 2024 Paperzz