MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Figure 3-6: Diesel Unloading Arm at Delimara Power Station Figure 3-7 is a satellite picture with a proposed lay-out superimposed. This lay-out shows one 60,000 m3 LNG storage tank at the reclaimed area next to the three diesel storage tanks right below the cooling water inlet structure. Above the cooling water intake structure is the 500 meter long berth. A new LNG loading arm and a vapour return arm have been placed in the middle of the existing berth. A LNG pipe corridor leads from the unloading arm to the LNG storage tank. The main LNG process area with (BOG blowers; De-Superheater vessel; HP Pumps and Submerged Combustion Vaporizers) is placed in the empty space between unloading arm and the existing cooling water inlet structure. LI 260442 Page 3-12 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 3 Figure 3-7: Layout of LNG Terminal with one 60,000 m LNG Storage Tanks The alternative layout option with two 30,000 m3 LNG storage tanks at the reclaimed area next to the diesel tanks is shown in the following figure. Due to difficult soil condition it may not be possible to build one large tank with a volume of 60,000 m3 and two smaller tanks have to be built instead. In case of LNG being a solution considered in line with the expansion plan, thorough assessment of geological conditions by sample drilling will have to be considered in this regard. LI 260442 Page 3-13 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Figure 3-8: Layout of LNG Terminal with two 30,000 m³ LNG Storage Tanks LI 260442 Page 3-14 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Nevertheless sample drilling which is a very extensive and costly measure and will not be executed before a more advanced stage of regarding the potential realization of such an LNG terminal. Modification on the existing Installations From a first visual inspection during a site visit the entire berth appears to be in good condition and does not require major modifications or refurbishments. Only the existing mooring hooks and mooring dolphins need to be checked if they are suitable for LNG vessels. It is anticipated that only minor upgrading is required. On the existing berth is an unloading arm for diesel fuel and a narrow pipe corridor to bring the diesel to the storage tanks. These installations do not necessarily need to be removed if Enemalta would like to retain a duel fuel capacity. Usage of diesel unloading equipment could be continued during periods were no LNG unloading operation is ongoing. Connection from LNG plant to the Marsa Power Station Site The existing gas turbine at the Marsa Power plant is currently running on diesel fuel. A fuel switch to natural gas is in principle possible; however natural gas has to be transported from the Delimara power station to Marsa. The Marsa power generation units will continue to run on diesel for the Base Demand Case Scenario. A fuel switch to natural gas is in principle possible; however natural gas has to be transported from the Delimara power station to Marsa. In order to avoid a costly 11.5 km long connection pipeline from Delimara to Marsa through populated areas the low quantity of gas required could be trucked from the pipeline landfall terminal station in Delimara using specialised LNG trucks to the Marsa power station. The turbines would have a daily consumption of about 180,000 m3 of natural gas which is the equivalent of 300 m3 LNG, This would require a min. storage tank for LNG of about 600 m3 to have a one day reserve. A LNG truck trailer has a cargo capacity of roughly 43 m3 which would require an average of 7 trips. Each roundtrip would take about 3 hours i.e. one hour driving the distance of 30 km (roundtrip) and one hour for loading and unloading. In total one complete cargo trip would take no longer than 3 hours. This means that in theory 7 trips could be done within one day. The picture below shows a typical LNG truck trailer. This particular trailer has a LNG cargo capacity of 43 m3. LI 260442 Page 3-15 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 3 Figure 3-9: Typical LNG Truck Trailer with a Capacity of 43 m A simple cost calculation in Table 3-3 shows the cost involved. Description Cost in Euro LNG Truck Filling Station at the terminal 400,000,-- LNG Trailer with capacity of 43 m³ 220,000,-- LNG Storage Tank at Marsa Power Station (600m³) 420,000,-- Vaporizer and HP LNG Pump, piping etc. at Marsa Power Station 180,000,-- Civil Works at Marsa Power Station 110,000,-- Total Estimate 1,350,000,-Table 3-3: Cost Calculation for LNG Supply at Marsa by Truck Trailer LI 260442 Page 3-16 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA However, it should be considered that the gas turbine at Marsa is not for base load power generation and is only utilized during peak demand; therefore it is questionable if an additional investment of 1.35 Mio EUR is justified for a fuel switch of a power generation unit that is used to cover peak demand only. 3.1.3 Potential Hazards Hazard identification for LNG terminal is conducted and the following hazards are identified: x x LNG Spills; x Thermal Radiation; x Ship Grounding and LNG Release; x Acts of Nature (storm, earthquake etc); x Vapour Dispersion; x Environmental Impacts; x Terrorism or sabotage; x External Fire; LNG Release due to Equipment or System Failure. LNG Spill is one of the hazards discussed for LNG. The primary hazard of the flammable LNG is the possibility of a fire. The two limiting conditions are an LNG release with and without immediate ignition. If the ignition is immediate or relatively soon after the start of the release, the fire size is determined by the LNG release rate which fuels the fire. If the ignition is delayed, an LNG vapour cloud will develop and disperse as it expands and/or moves downwind. For ignition to occur, the concentration of vapour in the atmosphere must be at less than 15% which is the Upper Flammable Limit (UFL). At concentrations above the UFL, there is not enough air to sustain combustion. As the cloud expands, eventually the concentration drops below 5% vapour in the atmosphere. This concentration of 5% is the Lower Flammable Limit (LFL). At concentrations below 5% vapour in the atmosphere there is not enough fuel to sustain combustion. If ignition occurs, the area with concentrations at or above the lower flammable limit (5%) will be at risk. The vapour cloud will burn back to the source of vapour. This source can be either the release itself or a pool of LNG accumulated prior to ignition. From these scenarios emerge two explicit requirements for the protection of the public beyond the boundaries of the facility. These are the two “exclusion zones” which are required for facility siting. Specifically, there are the “vapour dispersion exclusion zone” and the “thermal radiation exclusion zone”. LI 260442 Page 3-17 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Vapour Dispersion Hazards: When a release occurs, the LNG will vaporize as it comes into contact with the relatively warm surfaces and atmosphere. The initial hazard following a release comes from the LNG spreading over the surface and vaporizing as it absorbs heat. The vapour generated will mix with air which begins the vapour dispersion process. It is possible to calculate the theoretical distance the flammable concentration of a vapour cloud will travel and this distance is called the Lower Flammable Limit (LFL) vapour dispersion isopleths. LFL distance can be represented on a site plan as a ring of equal concentration. The isopleths for a LFL vapour cloud must not go beyond the LNG facility boundaries or property that cannot or will not have occupancies and thus result in a distinct hazard to the public. The hazard is not the vapour itself, but the possibility that it could be ignited. If ignited, the vapour cloud will not expand any further, but instead, will burn back to the vapour source. The LNG fire will continue to burn until the fuel is consumed or the fire extinguished. An LNG vapour cloud, mixed with air will not explode unless confined in an enclosure. The vapour dispersion calculations for the LNG facility shall be performed in order to define the vapour excursion from a design spill at each impoundment area. Thermal Radiation Hazards: If a fire occurs, there will be radiant heat from the flame which could cause personal injury, property damage and potentially secondary fires. The potential personal injury of the public is the primary concern. The severity of the injury depends on the intensity of the radiant heat, the exposure time and any protective factors such as clothing. The intensity or thermal flux level is measured in kilowatts per square meter (kW/m2). This unit is generally unfamiliar but if related to sunlight with a clear sky, direct sunlight radiant heat is about 1 to 1.5 kW/m2. The limiting radiant heat restriction on general public exposure is 5 kW/m2 or, say, 5 times as strong as sunlight. This is not instantly injurious but becomes quite uncomfortable fairly quickly. Ultimately these flux levels can cause injury. Recent “real live person” experiments have shown that 60 seconds at 5 kW/m2 is not injurious and does not cause continued discomfort after the radiant heat exposure is discontinued. The duration of exposure factor allows time for an exposed person to find protective shelter from the direct exposure and/or move away from the fire. In summary, the 5 kW/m2 exposure limit provides a high level of safety. The thermal radiation calculations for the LNG facility shall be performed for a full dike fire for the storage tanks or a fire over the full extent of each impoundment area. Environmental Impacts: Negative long-term environmental impact from an LNG release is virtually non-existent. LNG is colourless, odourless, and non-toxic and leaves no residue after LI 260442 Page 3-18 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA evaporation. LNG (liquid) has a specific gravity in the range of 0.45; therefore it will float on water. LNG and LNG vapour are not soluble in water which precludes water contamination. The specific gravity of LNG vapour is 0.55. LNG vapours become buoyant at temperatures above a value of -107 ºC. The buoyancy of the vapour enhances the dispersion in the atmosphere with no long-term hazardous effects. One of the attractive features of natural gas is that, unlike an oil spill, an LNG release does not require any environmental clean-up effort. Methane is considered to be a greenhouse gas but there are no vapours released in normal operations as all systems are vapour tight. Potential damage to environmental and socio-economic components is limited to short-term hazards to flora, fauna and humans in the immediate vicinity of the release. There are no LNG or vapour releases as a result of normal operations. Any short term releases would be the result of an accidental spill or component failure. The affected area would probably be in the cleared area around the tanks and process, but certainly within the facility boundaries. For example, any fish in the immediate vicinity (a few hundred meters) of an LNG ship release would unlikely be frozen or otherwise harmed as any freezing of the water would be at the surface of the water. The surface of the water will be at the melting temperature of the ice. The ice will soon melt and the environment will return to normal with no residual trace of the incident. Likewise, any animals or birds within the vapour dispersion or thermal radiation isopleths caused by a release could be immediately harmed or killed. An animal may not recognize a visible fog (vapour cloud) as a fire hazard and thus suffer if they are in the flammable cloud if it is ignited. If they were not within the vapour cloud if ignited, they could escape. If an LNG pool on water is ignited (“pool fire”), marine mammals will likely stay away. It should be noted that persons can and have run faster than a flame front. Immediately after an LNG release, the area would be suitable for animals and humans to use again. Local population (animals or people) and property should sustain no long-term effects from an LNG release. The LNG facility is designed to contain any incident on site or within the controlled property. An environmental emergency plan is required. Comprehensive safety and environmental procedures shall be prepared using the safety studies for code regulation compliance, analysis of emergency scenarios and the final facility design. Ship Grounding and LNG Spill: When evaluating the possibility of ship grounding at or near the terminal, two factors must be considered: the physical features of the navigable area adjacent to the waterfront and berth, and the speed and control of the LNG ship. The navigable waters surrounding the LNG facility shall be sufficiently deep that grounding would require a loss of ship’s propulsion or steerage that would cause the ship to leave the berth area. While grounding is always possible, as the ship approaches the facility it shall be under control of a licensed pilot. The manoeuvring for berthing and turning of the ship shall be assisted by tugs. The tugs shall LI 260442 Page 3-19 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA be able to control the movement of the ship and prevent grounding. The potential for damage in the event of grounding shall be further mitigated by the ship’s reduced speed as it approached the berth and its double hull. Terrorism or sabotage: The possible scenarios of terrorism attack or sabotage shall be studied in detail to define the necessary mitigation measures. However the chances of this type of threat are remote for several reasons, including: x x Terminal and shipping personnel are always screened before hiring. Ship crews tend to be very stable as the jobs are considered to be very attractive. There is very little turnover in terminal staffing. Terrorists are more interested in “high profile” targets with strong symbolic value, or targets that can cause mass casualties or severe economic damage. In general, LNG terminals are not attractive targets due to their “low political profile”, difficulty of attack, and high level of security. Acts of Nature: The possibility of a significant LNG release resulting from an act of nature, such as a severe storm, ice storm, or earthquake is remote because the design requirements shall take seismic, wind, and weather factors into account. The tanks shall be designed for the seismic rating of the region, and the tank profile shall take into account the wind loads (both typical and maximum) for the region. Equipment and structures shall be designed to withstand the harshest recorded environment for the region. A lightening strike shall not affect the system, unless it strikes a vent mast or other component that has a natural gas leak, creating a methane-rich environment. Significant leaks should be detected by mandated safety systems before they become a source of ignition. Such vent fires would be small and are easily extinguished. Should an act of nature cause a release, the result will be the same or less than other causes previously cited. An LNG release would be impounded and the resulting vapour dispersion or thermal radiation would be limited to the terminal site and not cause injury or damage to adjacent property. Acts of nature involving an LNG ship should be divided into two categories, predicted conditions, and unpredicted events. A predicted condition would be high winds, hurricane, ice storm, etc. Unpredicted acts would be those events that occur suddenly, such as earthquakes. The LNG ship will not dock and, if docked, will undock and depart should the weather exceed the design criteria. If extreme weather were predicted, the LNG ship’s officers would monitor the weather to avoid being caught in restricted waters during the storm. Unpredicted events of nature, such as earthquakes, present a different scenario. The worst case would be the LNG ship breaking its moorings during a cargo discharge. Breaking moorings LI 260442 Page 3-20 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA occurred once in the past when a sudden 100-mph wind, called a “Sumatra,” blew the LNG Aries off the dock while loading cargo in Bontang, Indonesia. In such a case, the unloading arms would exceed their operational range and the automatic disconnection (PERC) system would activate. A small amount of LNG would be released; probably not enough to even reach the water. If the LNG ship broke all its moorings and propulsion was not available, the ship could drift and either allied with the dock or with the ground. Allision at low speed would possibly be sufficient to penetrate the outer hull but not sufficient to breach the cargo tanks. (Allision is a relatively new term adopted by the marine regulators to indicate the impact of a moving ship with a fixed “obstacle” that is not moving.) Other damage to the ship caused by events of nature is not plausible due to the ship being designed to be seaworthy in all types of weather. External Fire: The possibility of an LNG release caused by external events, such as a forest fire or adjacent oil storage fire, is extremely remote because the facility is built from non-combustible materials, mostly steel and concrete. Further, the facility shall be designed to contain vapour dispersion and thermal radiation within the boundaries of the facility, as explained in detail above. The critical components of the import terminal for both operation and safety are not susceptible to even large fires at the distances provided by the exclusion zones and plant boundaries. These components are predominantly fire resistant. All components containing LNG are alloy steel externally insulated. The safety zones also work to isolate the facility and prevent an external fire from threatening the facility. Storage tanks would be protected by the impoundment dike, which would serve as a firebreak around the tank and process area. Furthermore, the facility shall be equipped with an extensive fire fighting system, which can be used to protect the facility from an external fire. An escalating LNG release as the result of a fire within the plant is unlikely for the same reason. Due to the flammable nature of LNG, terminal personnel are extremely safety conscious. While accidents have occurred, they do not typically result in fires large enough to initiate a subsequent release or emergency escalation. However, in the event of a fire initiating a release, vapour dispersion would not be an issue because an ignition source would be immediately present. A major release would be contained within the dike or sump and thermal radiation is predictable and part of the risk assessment process. A vapour release that ignited would burn until the fuel was consumed or the fire extinguished. In either case, the fire and thermal radiation would be contained within the facility boundaries, minimizing the danger to the surrounding area. The fire fighting systems should prevent the fire from spreading to storage tanks and process equipment not directly involved in the initial incident. All storage tanks and systems are sealed such that no fugitive vapours are present to be ignited. LI 260442 Page 3-21 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA LNG Release Due to Equipment or System Failure: The most credible type of release is the result of equipment or system leakage, such as a leaking valve seal or flange gasket. This type of release is typically small and non-threatening. The probability of such a failure is greatest at flanges or joints where components, pipes, and valves are connected and undergo temperature changes. These small leaks are visible and easily repaired by facility personnel. The next level of failure would be a leak associated with a piece of equipment. In this case, the equipment is typically replaced in service by a “spare” component and secured for repairs. The LNG facility shall be equipped with an extensive array of gas detection and flame detection equipment. Small leaks shall be detected either visually, by trained personnel working in the facility, or by the detection equipment. Small leaks and/or fires should be easily handled by facility personnel, with assistance from the local fire department if necessary. A system failure that generates a major release will have the same net effect as the other major incidents evaluated above. A release will be contained and directed to a sump, thus mitigating the extent of vapour dispersion. Should the vapour ignite, the thermal radiation will be mitigated by the release’s containment in the sump. The fire will continue until the fuel is consumed or the fire is extinguished. Damage will be confined to the terminal boundaries, including any controlled areas outside the property lines. The extensive Risk Assessment including HAZID, HAZOP, QRA and EIA shall be performed in order to analyse in detail and in specific the effects of these defined possible hazards and the related mitigation measures based on the following methodology: x x x Establishing the resulting LNG release from credible events; Calculation of the area extent of the hazards (pool fire and vapour cloud); Determining the potential exposures, primarily exposure of the public. Determining the surrounding distances to which these significant hazards extend, the zone of influence or “exclusion zone.” The purpose of the exclusion zone requirements is the protection of the public (population and property) surrounding the facility. Protection and safety of the facility itself is also covered, but the public safety requirements are so strict that the facility protection is a secondary benefit. Confirming that these zones of influence to not exceed the project codes and standards requirements. LI 260442 Page 3-22 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 3.2 Economic Description of the Proposed Scheme for Case (I) and (II) 3.2.1 Investment Costs of Major Components The below table provides the scheme’s investment cost in total and for each major component. In total, the projects investment cost amounts to 102.1 Mio Euro (10% contingencies and 12% contractors total profit, mark-up are included). The project duration regarding the recommended two LNG tanks scheme (total storage capacity of 60,000 m³) is estimated at three years. The disbursement schedule of the investment is shown in Table 3-5. Investment Costs in T EUR # Item 1 Direct Cost (Labor, Materials & Subcontracts) 2 Construction Equipment 851 3 Overhead and Indirects 2,174 4 Home Office Services (EPC Contractor) 2,941 5 Owner's Engineering Services 3,431 6 Specialty Contractors 47,219 45,458 Total: 102,101 Table 3-4: Investment Cost of LNG Scheme Case (I) and (II) Year n-3 n-2 n-1 n Disbursement in % 35% 35% 30% Start Year Table 3-5: Disbursement of the Investment Cost of LNG Scheme Case (I) and (II) As illustrated in Figure 3-10 the two major proportions of the investment cost are: (i) The Direct Cost which includes: o LI 260442 Site Preparation and Improvement; Page 3-23 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA o o o o o Process Equipment; Underground and Aboveground Pipelines; Underground and Aboveground Electric Equipment; Concrete, Instrumentation and Insulation; Over less cost intensive items. (ii) The Specialty Contractors Cost which includes: o o o o LNG Tank Costs; Jetty Upgrades Costs; Dredging Costs; Over less cost intensive items. 45% Direct Cost (Labor, Materials & Subcontracts) Construction Equipment 3% Overhead and Indirects 3% Home Office Services (EPC Contractor) 2% 1% Owner's Engineering Services Specialty Contractors 46% Figure 3-10: Investment Cost Break Down of the LNG Scheme for Case (I) and (II) LI 260442 Page 3-24 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Ownership and Operating Structure. Since the only customer of the LNG terminal appears to be Enemalta it would make sense that the Owner and Operator of the LNG Terminal would be a subsidiary of Enemalta. Regulatory Structure. There are a number of options available for the Buyer on how to structure the supply of LNG and on how to participate along the LNG value chain. The structure is mainly dependent on: x The sourcing structure (e.g. Point of sale, ex-ship, FOB); x The selected partner; x Desire of Buyer to move upstream; x Ability to invest and carry risk. The identified options can be summarised in three categories as follows: x Ex-ship LNG supply to a Re-gas terminal in Malta; x FOB LNG supply from a terminal in a gas producing country (e.g. Algeria); x Participation along the entire value chain. 3.2.2 Operational and Maintenance Costs LNG Price Estimation LNG imports into Europe are generally linked to crude oil prices (i.e. Brent) but prices are a bit more diverse in Europe as compared to Asia as LNG is competing with pipeline imports and to some extent also with indigenous supply in many countries. LNG supply contracts are not a public domain and the exact pricing formula for LNG is negotiated on a case by case basis. Traditionally LNG supply contracts were all long term i.e. over a period of 20 years and are usually indexed to a basket of competing fuels (i.e. crude oil; diesel etc). Recent changes in the LNG market have trended towards increased flexibility. Contracts have loosened terms on both price and volume, and can be negotiated for shorter periods of time. Additionally, flexibility in LNG shipping has led to an increase in short-term contacts. Traditionally the LNG price is expressed in USD/mBtu. The average LNG price in spring 2007 for LNG delivered to Spain was 6.3 USD/mBtu (Source: Argus Global LNG Services) which is equivalent to a natural gas price of some 167 EUR/1000m³ or 223.3 EUR/t. LI 260442 Page 3-25 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Regarding the development of the LNG price an indexation of the crude oil price forecast of the Energy Information Agency (EIA) was applied (for more details see chapter 6.2 within the Work Package I Report). Fixed O&M Costs For the LNG terminal the fixed operation expenditures have been estimated as stated in the following table. # Item 1 Technical Assistance 2 Inspection 3 Maintenance 4 Nitrogen 5 Management and Operation 960 6 Tugboat Operation Fees 160 7 Telecommunication 20 8 Permits & other Fees 30 9 Insurance Costs in T EUR/a 220 50 820 20 200 Total Annual Fixed OPEX: 2,480 Table 3-6: Estimate of Annual Fixed OPEX Variable O&M Costs Variable OPEX are the throughput dependent cost of operating the LNG terminal. The biggest expense is the cost for electricity. For the electricity consumption of the pumps and blowers a price of 0.05 Euro/kWh was assumed. Another cost item is related to the gas consumption of the regasification process. Assumption is that heat will be recovered during the operation of DPS. Assuming a typical plant availability of 91%, during the remaining time period gas itself will be utilised to regasify the LNG. A quantum of 0.14% of the sent-out is used as fuel gas using the price of 223.3 EUR/t. LI 260442 Page 3-26 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA # 1 Item Fuel Gas for LNG Vaporisation 2 Electricity for HP Pumpsand Blowers 3 Caustic Soda for Vaporisation Costs in T EUR/a 184 1,550 5 Total Annual Variable OPEX: 1,739 Table 3-7: Estimate of Annual Variable OPEX 3.2.3 Dynamic Unit Cost Assessment for Case (I) and (II) The approach applied for the economic analysis of fuel supply options was explained in section 3.1.3. The calculation of the DUC is provided in the following charts. Fuel supply figures are applied in accordance to the individual demand scenarios. Regarding the high gas demand scenario (Case I) the DUC of the proposed LNG supply scheme amount to 23.8 EUR per tonne of fuel. The DUC are marginally higher (3%) for the base gas demand scenario resulting in 24.4 EUR per tonne of fuel. Finally a comparison of the DUC for both gas supply options investigated in this study is provided. The lowest cost occurs for the LNG scheme regarding the high gas demand scenario. Its DUC are 9% lower compared with the DUC of the related pipeline scheme based on the same demand projection. Nearly the same result was evaluated for the base gas demand scenario. The DUC of the pipeline scheme are 10% lower compared with the DUC of the related LNG scheme based on the same demand projection. LNG Scheme high (Case I) LNG Scheme base (Case II) Pipe Scheme high (Case I) Pipe Scheme base (Case II) T EUR /a 116,320 116,320 139,090 139,090 T EUR /a 55,095 55,095 13,553 13,553 23.8 24.4 25.9 26.8 Item Unit PV Capital PV OPEX Dynamic Unit Cost EUR/t Table 3-8: Dynamic Unit Cost of LNG and Pipeline Schemes LI 260442 Page 3-27 LI 260442 T EUR /a T EUR /a t/a Fixed OPEX Variable OPEX Fuel Gas Supplied Fuel Gas Supplied DUC - Gas Supply EUR /t EUR /1000m³ t/a OPEX 4 Dynamic Unit Cost T EUR /a T EUR /a Capital 3 Present Value T EUR /a Year >> 102,101 6.5% 30 3 2011 Investment Cost Item 2 Cash Flow Total Investment in T EUR Discount Rate Lifetime in a Construction Period in a Start of Operation Case: 1 General Information n-3 23.8 17.7 7,216,329 55,095 116,320 0 0 0 35,735 n-2 0 0 0 35,735 n-1 0 0 0 30,630 490,709 1,739 2,480 0 1 517,539 1,739 2,480 0 5 0 10 546,681 1,739 2,480 Gas Demand Scenario High 580,292 1,739 2,480 0 15 613,903 1,739 2,480 0 20 648,647 1,739 2,480 0 25 685,357 1,739 2,480 0 30 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Table 3-9: Dynamic Unit Cost of the LNG Scheme - Case (I) Page 3-28 LI 260442 T EUR /a T EUR /a t/a Fixed OPEX Variable OPEX Fuel Gas Supplied Fuel Gas Supplied DUC - Gas Supply EUR /t EUR /1000m³ t/a OPEX 4 Dynamic Unit Cost T EUR /a T EUR /a Capital 3 Present Value T EUR /a Year >> 102,101 6.5% 30 3 2011 Investment Cost Item 2 Cash Flow Total Investment in T EUR Discount Rate Lifetime in a Construction Period in a Start of Operation Case: 1 General Information n-3 24.4 18.3 7,012,935 55,095 116,320 0 0 0 35,735 n-2 0 0 0 35,735 n-1 0 0 0 30,630 382,042 1,739 2,480 0 1 488,785 1,739 2,480 0 5 0 10 543,302 1,739 2,480 Gas Demand Scenario Base 576,300 1,739 2,480 0 15 609,370 1,739 2,480 0 20 643,857 1,739 2,480 0 25 680,296 1,739 2,480 0 30 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Table 3-10: Dynamic Unit Cost of the LNG Scheme - Case (II) Page 3-29 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 3.3 Technical Description of the Proposed Scheme for Case (III) As it can be seen in Figure 2-1 (Section 2.1.1) the projected gas demand figures for the Low Gas Demand Scenario is almost stagnant and actually declines slightly after the year 2020. Although it is a very small gas demand we have calculated the CAPEX and OPEX figures for this case. The main difference in the design of the LNG terminal for Low Gas Demand Scenario is the size of the LNG Storage tank. For this low gas demand we have taken the design sent-out of some 0.170 bcm/a and slightly higher volumes such as 0.200 bcm/a and 0.240 bcm/a to show the sensitivities of the low gas demand scenario. The vessel size was adopted for this low gas demand and vessels with a cargo volume of 5,000 m³; 10,000 m³ and 20,000m³ were selected. LNG vessels with a cargo volume of some LNG Storage Required 35,000 10,000 m³ Ship 30,629 25,513 24,672 24,041 25,000 25,000 m³ Ship 29,788 29,158 30,000 LNG Storage Required (m³) 20,000 m³ Ship 20,000 15,000 15,279 14,438 13,807 10,000 5,000 0 0.170 0.200 0.240 Natural Gas Send Out (bcm/a) Figure 3-11: Required LNG onshore Storage vs. LNG vessel size LI 260442 Page 3-30 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 20,000 m³ and below have a maximum length of 150 meters and a maximum draft of 7.6 meters. Therefore no dredging is required at the existing berth and the Delimara Power Station. General Data LNG Storage Vessel Size LNG Storage Vessel Size (Net) Number of days to provide reserve storage due to inclement weather/ship delays/plant operations/etc. Daily Send Out - Maximum (% over Nominal) Fuel Gas (% of Send Out) Low Gas Demand Scenario Gas Send Out Flow Rate Gas Send Out Flow Rate Gas Send Out Flow Rate Fuel Gas Flow Rate Gas Send Out (Gross) Reserve storage due to inclement weather/ship delays Sub-Total - Required Storage LNG Tank Heel Storage Required Ship Frequency Low Gas Demand Scenario Gas Send Out Flow Rate Gas Send Out Flow Rate Gas Send Out Flow Rate Fuel Gas Flow Rate Gas Send Out (Gross) Reserve storage due to inclement weather/ship delays Sub-Total - Required Storage LNG Tank Heel Storage Required Ship Frequency Low Gas Demand Scenario Gas Send Out Flow Rate Gas Send Out Flow Rate Gas Send Out Flow Rate Fuel Gas Flow Rate Gas Send Out (Gross) Reserve storage due to inclement weather/ship delays Sub-Total - Required Storage LNG Tank Heel Storage Required Ship Frequency 5.5% 5.5% 5.5% 10,000 9,700 25,000 m³ 24,250 m³ 20,000 19,400 4 10% 2.0% days 0.17 512,329 830 17 847 3,388 13,088 720 13,807 11.5 0.17 512,329 830 17 847 3,388 22,788 1,253 24,041 22.9 0.17 512,329 830 17 847 3,388 27,638 1,520 29,158 28.6 bcm/year m³/day (Gas) m³/day (LNG) m³/day (LNG) m³/day (LNG) m³ m³ m³ m³ days 0.2 602,740 976 20 996 3,985 13,685 753 14,438 9.7 0.2 602,740 976 20 996 3,985 23,385 1,286 24,672 19.5 0.2 602,740 976 20 996 3,985 28,235 1,553 29,788 24.3 bcm/year m³/day (Gas) m³/day (LNG) m³/day (LNG) m³/day (LNG) m³ m³ m³ m³ days 0.24 723,288 1,172 24 1,196 4,783 14,483 797 15,279 8.1 0.24 723,288 1,172 24 1,196 4,783 24,183 1,330 25,513 16.2 0.24 723,288 1,172 24 1,196 4,783 29,033 1,597 30,629 20.3 bcm/year m³/day (Gas) m³/day (LNG) m³/day (LNG) m³/day (LNG) m³ m³ m³ m³ days Table 3-11: Calculation for required LNG Storage Volume – Case (III) LI 260442 Page 3-31 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Looking at the graph in the figure above it is evident that the biggest factor in determining the onshore storage requirements is the size of the vessel that supplies the LNG. It appears that a LNG storage tank with 15,000 m³ is the optimum solution for the low gas demand scenario based on a LNG supply vessel with a cargo volume of 10,000 m³. However, in reality it will be difficult to secure a charter for a LNG vessel with 10,000 m³ cargo volume in the Mediterranean. It is more likely to secure a charter of a 25,000 m³ LNG vessel. It is therefore recommended to install a 30,000 m³ onshore storage tank for the low gas demand scenario. Please note that partial unloading of LNG i.e. unloading of 25,000 m³ from a 60,000 m³ LNG vessel is usually not allowed. LNG cargo vessels that are only partially filled are subject to the so called sloshing effect that make a vessel instable during bad weather and also lead to higher BOG rates during the journey. Table 3-11 shows the general assumptions for the LNG storage tank calculations. 3.3.1 Basic Design The basic design for Case (III) is the same as for Case (I) and (II) 3.3.2 Location The location for Case (III) is the same as for Case (I) and (II). 3.3.3 Potential Hazards The hazards and risk for Case (III) is the same as for Case (I) and (II). LI 260442 Page 3-32 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 3.4 Economic Description of the Proposed Scheme for Case (III) 3.4.1 Investment Costs of Major Components The below table provides the scheme’s investment cost in total and for each major component. In total, the projects investment cost amounts to 75.7 Mio Euro (10% contingencies and 12% contractors total profit, mark-up are included). The project duration regarding is estimated at three years. The related disbursement schedule of the investment is shown in Table 3-13. Investment Costs in T EUR # Item 1 Direct Cost (Labor, Materials & Subcontracts) 2 Construction Equipment 876 3 Overhead and Indirects 2,237 4 Home Office Services (EPC Contractor) 2,730 5 Owner's Engineering Services 3,299 6 Specialty Contractors 22,944 Total: 75,705 43,619 Table 3-12: Investment Cost of LNG Scheme Case (III) Year n-3 n-2 n-1 n Disbursement in % 35% 35% 30% Start Year Table 3-13: Disbursement of the Investment Cost of LNG Scheme Case (III) As illustrated in Figure 3-12 the dominating investment cost proportion are the direct cost which includes: LI 260442 o Site Preparation and Improvement; o Process Equipment; Page 3-33 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA o o o o Underground and Aboveground Pipelines; Underground and Aboveground Electric Equipment; Concrete, Instrumentation and Insulation; Over less cost intensive items. Nearly a third of the total investment is caused by the specialty contractors cost which includes: o o o LNG Tank Costs; Jetty Upgrades Costs; Over less cost intensive items. Direct Cost (Labor, Materials & Subcontracts) 4% 30% 4% 3% Construction Equipment 1% Overhead and Indirects Home Office Services (EPC Contractor) Owner's Engineering Services Specialty Contractors 58% Figure 3-12: Investment Cost Break Down of the LNG Scheme for Case (III) LI 260442 Page 3-34 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 3.4.2 Operational and Maintenance Costs LNG Price Estimation: The price estimation and the approach regarding the price projection is described in the Section 3.2.1 of this report. Fixed O&M Costs; For the LNG terminal the fixed operation expenditures have been estimated as stated in the following table. # Item 1 Technical Assistance 2 Inspection 3 Maintenance 4 Nitrogen 5 Management and Operation 6 Tugboat Operation Fees 80 7 Telecommunication 20 8 Permits & other Fees 30 9 Insurance Costs in T EUR/a 200 40 690 20 960 150 Total Annual Fixed OPEX: 2,190 Table 3-14: Estimate of Annual Fixed OPEX Variable O&M Costs Variable OPEX are the throughput dependent cost of operating the LNG terminal. The biggest expense is the fuel cost for the regasification process the LNG. Assumption is that 1.5% of the sent-out is used as fuel gas using the price of 223.3 EUR/t. For the electricity consumption of the pumps and blowers a price of 0.05 Euro/kWh was assumed. LI 260442 Page 3-35 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA # 1 Item Fuel Gas for LNG Vaporisation 2 Electricity for HP Pumpsand Blowers 3 Caustic Soda for Vaporisation Total Annual Variable OPEX: Costs in T EUR/a 37 520 2 559 Table 3-15: Estimate of Annual Variable OPEX 3.4.3 Dynamic Unit Cost Assessment for Case (III) Similar to the results of the assessment of the low gas demand scenario pipeline scheme the DUC calculation brings out that the dynamic unit cost of the LNG scheme are extremely high. While the Case (III) gas demand figures are substantially lower compared to the base scenario, the CAPEX and OPEX of the scheme do not decrease in the same range. Finally the dynamic unit costs are nearly three times higher (78.3 EUR/t compared to 24.4 EUR/t). LI 260442 Page 3-36 LI 260442 T EUR /a T EUR /a t/a Fixed OPEX Variable OPEX Fuel Gas Supplied t/a Fuel Gas Supplied DUC - Gas Supply EUR /t EUR /1000m³ T EUR /a OPEX 4 Dynamic Unit Cost T EUR /a Capital 3 Present Value T EUR /a Year >> 75,705 6.5% 30 3 2011 Investment Cost Item 2 Cash Flow Total Investment in T EUR Discount Rate Lifetime in a Construction Period in a Start of Operation Case: 1 General Information 78.3 58.5 1,559,363 35,898 86,248 0 0 0 26,497 n-3 0.7414717 n-2 0 0 0 26,497 n-1 0 0 0 22,712 120,890 559 2,190 0 1 122,258 559 2,190 0 5 0 10 122,258 559 2,190 Gas Demand Scenario Low 116,145 559 2,190 0 15 116,145 559 2,190 0 20 116,145 559 2,190 0 25 116,145 559 2,190 0 30 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Table 3-16: Dynamic Unit Cost of the LNG Scheme - Case (III) Page 3-37 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 4 Techno-economic Specification of CNG Infrastructure Compressed Natural Gas (CNG) is not yet publicly traded in any sizeable from or shape, this is due to the lack of available infrastructure for CNG. Some countries have introduced miniature CNG pilot projects for CNG powered vehicles such as busses or trucks. However, CNG has still no sizeable market penetration that would allow the development of a commercial model for a large scale CNG supply to Malta. There are no CNG vessels that are currently operating to supply demand centres. Therefore CNG will not be considered in the further analysis. However, typical future applications for CNG would be the supply of small Islands or small remote areas that have no indigenous gas production or gas pipeline connection to supply gas. However instead a CNG supply scheme a LNG regasification vessel could be an alternative to the onshore LNG terminal or the sub sea gas pipeline from Sicily. 4.1 Technical Description of a LNG Regas Vessel The only feasibly alternative to a LNG import using a conventional LNG Import and regasification terminal is ship based re-gasification vessels developed by Exmar i.e. Energy Bridge. A regasification vessel is capable of three different modes of cargo transfer (i) off-shore transfer of gas via the STL Buoy; (ii) dock-side transfer via the high pressure gas manifold or (iii) LNG transfer dockside into tanks or across dock ship to ship . A typical re-gas vessel carries about 138 000 m3 LNG which converts to approximately 2.8 bcf Gas or ~80 Mio m3 natural gas Discharge pressure is up to 100 bars at a temperature of 4-5 deg. °C. Capacities of existing regas fleet: x Capacity in Off-shore Mode is 14,150,000 m3/d using sea-water (Unloading ~5.6 days); x Capacity in Dock-side Mode is 12,750,000 m3/d without sea-water (Unloading ~6.2 days); x The turn-down ratio for Regas vessels is quite high and can be as low as 2,830,000 m3/d. The requirements for the Base Gas Demand Scenario are: Average daily send-out is about 114,500 m3/h or 2,750,000 m3/d this means that the Regas vessel will take about 30 days to empty its cargo volume of 80;000,000 m3 natural gas. In total Malta would require 10 Regas shipments per year. LI 260442 Page 4-1 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA The maximum hourly sent-out is about 165,000 m3/h which is well within the range of the Regas vessel. The installation cost for the off-shore solution is about 32 Mio EUR not including the onshore interconnection pipeline. Please note that for continuous supply (i.e. base load terminal) a second STL Buoy has to be installed. The dock-side solution requires the use of a jetty. This technology is only about 2 years old and only about 15 LNG cargos have been delivered using Regas vessels. So far no technical problems have been encountered but it is premature to declare Regasification vessel a proven technology without risk! Below is a schematic drawing showing a typical Regas-vessel. High Pressure Pumps And Vaporisers Reinforced LNG Storage Tanks Oversized Boiler Traction Winch Buoy Compartment Energy Bridge™ Regasification Vessel Figure 4-1: Schematic Overview of a Regas-Vessel LI 260442 Page 4-2 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA It should be noted that there is no prevailing business Model to charter LNG Regas vessels. So far a “Fee for Service” approach has been used, but there is little to commercial history. The “Fee for Service” Schedule Rates are not published and most likely require extensive case by case negotiations. The LNG Regasification vessels were primarily developed (i) to have an alternative LNG delivery method in areas where conventional LNG Regas terminal can not be built due to environmental and general permitting concerns for a regasification terminal and (ii) where the gas demand is either very small (< 2 bcm/a) or only spot delivery of LNG is required. However, since Malta has the possibility to build a LNG terminal onshore it is not recommended to further pursue the Regas vessel as an alternative delivery method. LI 260442 Page 4-3 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 5 Dynamic Unit Cost Analysis for Gas Supply Alternatives In order to provide a transparent and methodologically sound indicator to compare the different gas supply options, the dynamic unit cost (DUC) calculation was carried out for each technically feasible option. The dynamic unit cost approach allows to consider the full supply costs taking into consideration its specific cost structure in terms of investment breakdown and expenditure schedule, and to condense this case-specific and therefore heterogeneous information into one homogeneous and meaningful cost information. This chapter provides the comparison of the DUC calculations presented in the previous sections. Under consideration of all gas demand scenario below Table 5-1 provides the total fuel LNG Scheme Base Gas Demand Pipeline Scheme Base Gas Demand EUR/t 180.0 202.6 Dynamic Unit Cost of Fuel Supply EUR/t 24.4 26.8 Total EUR/t 204.4 229.4 Item Unit LNG Scheme High Gas Demand Pipeline Scheme High Gas Demand Projected Market Fuel Price (2011) EUR/t 180.0 202.6 Dynamic Unit Cost of Fuel Supply EUR/t 23.8 25.9 Total EUR/t 203.7 228.5 Item Unit LNG Scheme Low Gas Demand Pipeline Scheme Low Gas Demand Projected Market Fuel Price (2011) EUR/t 180.0 202.6 Dynamic Unit Cost of Fuel Supply EUR/t 78.3 96.4 Total EUR/t 258.3 299.0 Item Unit Projected Market Fuel Price (2011) Table 5-1: Comparison of Fuel Supply Cost – Gas Supply Alternatives LI 260442 Page 5-4 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 270.0 Gas via LNG Conversion EUR/t 250.0 230.0 210.0 190.0 170.0 150.0 130.0 Year 110.0 2010 2015 2020 2025 2030 270.0 Natural Gas via Pipeline EUR/t 250.0 230.0 210.0 190.0 170.0 150.0 130.0 Year 110.0 2010 2015 2020 2025 2030 Figure 5-1: Comparison of Fuel Gas Prices of Supply Alternatives investigated LI 260442 Page 5-5 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA costs in EUR per tonne including the costs of the supply and the market price (for the first possible year of supply scheme’s operation). The approach for the price projection is described already in the Section 3.2.1 of this report. Exemplarily the results within the frame of the base gas demand are discussed here. The LNG scheme is the gas supply alternative which contributes the lowest fuel cost. The costs of some 204.4 EUR/t are 11% lower than the cost of the pipeline scheme. An overview of the costs’ development up to the year 2030 is provided in the above charts. The LNG alternative leads to 221.0 EUR/t in 2030 whereas the pipeline alternative reaches 248.2 EUR/t. In all comparative assessments, the LNG scheme is that one with the lowest costs. Therefore it is recommended as the least cost gas supply option and the related cost are used as input figures within the techno-economic assessment of the gas-based local power generation options. LI 260442 Page 5-6 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 6 Techno-economic Specification of Gas-Based Generation Options This chapter of the report is devoted to technical and economic aspects of gas-based generation options identified and considered as potential candidates for the expansion of the Maltese power generation system. Within the frame of the identification process LI’s experts considered two basic types of projects. These are: x x the construction of new generation units; and the refurbishment of existing units. The investigated supply options are summarised in the following Table 6-1. In the manner introduced for the existing power generation units (see Chapter 1 of this report) each supply option is labelled by an identification code which will be used in the following sections and later be applied within the computer-aided system simulation (Work Package III). Item Capacity Range Option 1 ~ 100 MW New Gas-fired combined cycle gas turbines in 2 GT and 1 ST configuration CCGT 2+1 Option 2 ~ 100 MW New Gas-fired combined cycle gas turbines in 1 GT and 1 ST configuration CCGT 1+1 Option 3 + 120 MW Repowering of an (existing) condensing steam turbine to combined cycle in 2 GT + 1 ST configuration 2+1 ST R Option 4 + 40 MW Repowering of (existing) gas turbines to combined cycle in 2 GT + 1 ST configuration 2+1 GT R Description Identification Table 6-1: General Data – New Gas-Based Generation Options LI 260442 Page 6-1 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 6.1 Technical Description of Gas-Based Generation Option 1 (CCGT 2+1) 6.1.1 Basic Design Due to their high efficiency combined cycle gas turbine (CCGT) stations are the dominant power generation technology in recent years in Europe (see also WP I Report). The plants can be operated on natural gas or oil (Gasoil, Light Crude Oil). The heat of the exhaust gas from the gas turbine is used to make steam to generate additional electricity via a steam turbine; this last step thus enhances the efficiency of electricity generation. For the first supply option a combined cycle power plant consisting of two gas turbines, two heat recovery steam generators (HRSG) and one condensing steam turbine was defined. At an international level three important manufacturers offer such power plants (i) General Electrics (GE) Power Systems; (ii) Alstom; and (iii) Siemens. In the following the major technical and operational characteristics of this supply option are presented. Maltese local conditions and provided fuel specifications have been considered. The performance data of this supply option as presented in the following is based on the gas turbine (GT) of type GE 6581B and dual pressure HRSG without duct burner firing. Plant Characteristics Unit Plant Type Set Size (nominal) Value CCGT 2+1 MW Partial Load 128.0 100% 85% 70% 50% 30% 20% Set Capacity (gross) MW 128.0 109.3 89.6 63.6 38.4 25.1 Set Capacity (net) MW 125.5 106.9 87.0 62.0 36.9 24.8 Auxiliary Power MW 2.5 2.4 2.6 1.6 1.4 0.3 % 1.9% 2.2% 2.9% 2.5% 3.8% 1.2% 2GT+1ST 2GT+1ST 2GT+1ST 1GT+1ST 1GT+1ST 1GT Partial Load 100% 85% 70% 50% 30% 20% kJ/kWh 7,441 7,647 7,963 7,528 8,478 13,974 Planned Outage d/a 20 Forced Outage %/a 3% Max Availability %/a 91.5% Self Consumption Turbines in Operation Net Heat Rate Table 6-2: Technical Data – Gas-Based Generation Option 1 LI 260442 Page 6-2 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Another possible gas turbine types of similar size are for example the Siemens SGT-800F. The gas turbines are designed with a dual fuel combustion system using LNG (gaseous) as primary fuel. The design capacity of the gas turbines amounts to 41.1 MW (Net) each. The design capacity of the steam turbine is 43.2 MW (Net). For the cooling system an open loop water cooling with a seawater inlet temperature of 20 °C and an allowable cooling water temperature rise of 8 K is assumed. The heat recovery steam generators (HRSG) are equipped with a bypass stack for simple cycle operation of the gas turbines in order to increase the operational flexibility of the plant. Most important for the steam cycle efficiency is the HRSG configuration and design. Both HRSG produce in total 35.4 kg/s high pressure steam with 67.7 bar and 529 °C and an intermediate pressure steam of 5.92 kg/s with 8.3 bar and 258 °C. Table 6-2 provides the general technical parameters of the supply option (design conditions). A partial load range between 100% (full load) and 20% is selected regarding the provision of the operational characteristics, which can be summarized as follows: x x The plant’s self consumption (auxiliary power) drops from 2.5 MW to 0.3 MW in absolute terms. Related to the plants output the value increases from 1.9% (2 GT + 1 ST operation) to 3.8% (1 GT + 1 ST operation) and decreases then to some 1.2% (1 GT operation); The plant’s net heat rate increases from 7,441 kJ/kWh to nearly 14,000 kJ/kWh over the entire range of partial load. This is equal to a net efficiency decrease from 48.4% to 25.8% only. Assuming outage characteristics of an average of 20 days a year for the units’ maintenance and a 3% forced outage, the maximum availability of the plant is expected to amount 91.5% over a year. The net and gross heat rates of the gas based supply option 1 are shown in the following figure over the entire load range (calculated on fuel’s NCV). The results of GT Pro calculations are summarized within the heat and mass balance diagrams in the Figures 6-2 and 6-3. The calculations are based on the maximum load of the plant during summer and winter conditions. The comparison of the summer and winter parameters brings out the following results: x x The plant’s net capacity during summer amounts to only 88% (111.7 MW) compared to the net capacity during the winter period by some 127.1 MW. Our analysis of the existing system already brought out similar capacity levels in relation to the temperature fluctuations in Malta (see work package I); The plants’ net heat rate decreases from 7,560 kJ/kWh during summer to 7,414 kJ/kWh during winter. This is equal to a net efficiency increase from 47.6% (summer) to 48.6% (winter). LI 260442 Page 6-3 LI 260442 0 2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 0 20,000 40,000 80,000 Load (kW) 60,000 100,000 120,000 2+1 gross HR 2+1 net HR 1+1 gross HR 1+1 net HR 1+0 gross HR 1+0 net HR Heat Rates (kJ/kWh) of Supply Option 1 - 2+1 CCGT NG fired 140,000 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Figure 6-1: Gross and Net Heat Rates – Gas-Based Generation Option 1 Page 6-4 Heat Rate (kJ/kWh) 160 2.323 p 116 T 150.3 M LTE 2.323 p 125 T 2.609 M 152.9 M 160 IPB 3.08 M 20 T 190 237 9.159 p 9.159 p 171 T 176 T 152.9 M 23.9 M IPE2 LNG 8.771 m LHV= 117294 kWth 11.28 p 376 T HPE2 10.83 p 1132 T 267 73.79 p 230 T 125.7 M 237 1X GE 6581B HPE3 270 301 HPB1 HPS0 1.50 M 67.73 p 529 T 127.5 M 1.04 p 567 T 960.7 M 2 X GT 302 477 488 8.844 p 72.49 p 71.82 p 260 T 288 T 309 T 21.3 M 124.4 M 124.4 M IPS2 35742 kW 480.3 m 8.993 p 72.49 p 228 T 282 T 21.3 M 125.7 M IPS1 CCGT 2+1 configuration NG fired 100% load at summer conditions 488 21.3 M 488 Figure 6-2: Heat and Mass Balance – Gas-Based Generation Option 1 (Summer Conditions) 565 70.09 p 545 T 126 M HPS3 FW 2.384 m^3/kg 636.2 m^3/s 565 T 960.7 M 1.58 M 46 T 0.0385 M 0.1032 p 46 T 148.8 M 42645 kW 72.73 %N2 13.37 %O2 3.314 %CO2 9.705 %H2O 0.8758 %Ar Net Power 111711 kW LHV Heat Rate 7560 kJ/kWh p[bar], T[C], M[t/h], Steam Properties: IAPWS-IF97 316 08-20-2007 10:42:23 file=T:\26\0400\260442_malta\06_project_results\GTPro\Case 1 (2+1) neu\NG-fired\CCGT 2+1 NG fired 100% load summer conditions.gtm 1.136 m^3/kg 303.2 m^3/s 118 T 960.7 M 116 T 46 T 150.3 M 1p 36 T 471.6 m GT MASTER 17.0.1 LI - W. Eisenhart 1.01 p 36 T 70 %RH 471.6 m 70.09 p 545 T LI 260442 Final Report – Work Package IIA Energy Interconnection Europe - Malta Colours: Abbreviation: - high pressure steam red light blue - intermediate pressure steam p - pressure in bar MALTA RESOURCES AUTHORITY - gas, air and exhaust gas flow violet dark blue - feed water and water injection to gas turbine M - mass flow in kg / s T - temperature in °C 8.325 p 258 T Page 6-5 March 2008 163 2.323 p 125 T 1p 13 T 523 m 3.303 M 158.8 M 163 IPB 20 T 193 242 9.565 p 9.565 p 174 T 178 T 158.8 M 26.92 M IPE2 LNG 9.789 m LHV= 130906 kWth 12.44 p 358 T HPE2 11.94 p 1136 T 271 75.5 p 233 T 131.6 M 242 1X GE 6581B HPE3 274 303 HPB1 2 X GT HPS0 69.15 p 528 T 130.3 M 1.04 p 551 T 1065.5 M 305 471 482 9.198 p 74.08 p 73.36 p 261 T 290 T 309 T 23.61 M130.3 M 130.3 M IPS2 41563 kW 532.8 m 9.372 p 74.08 p 229 T 285 T 23.61 M 131.6 M IPS1 CCGT 2+1 configuration NG fired 100% load at winter conditions 482 482 Figure 6-3: Heat and Mass Balance – Gas-Based Generation Option 1 (Winter Conditions) 549 FW 2.299 m^3/kg 680.4 m^3/s 549 T 1065.5 M 34 T 0.0399 M 71.57 p 530 T 130.3 M HPS3 23.61 M 0.0544 p 34 T 153.9 M 46507 kW 75.3 %N2 13.95 %O2 3.378 %CO2 6.469 %H2O 0.9067 %Ar Net Power 127120 kW LHV Heat Rate 7414 kJ/kWh p[bar], T[C], M[t/h], Steam Properties: IAPWS-IF97 316 08-20-2007 10:43:22 file=T:\26\0400\260442_malta\06_project_results\GTPro\Case 1 (2+1) neu\NG-fired\CCGT 2+1 NG fired 100% load winter conditions.gtm 1.12 m^3/kg 331.6 m^3/s 2.323 p 114 T 155.5 M 117 T 1065.5 M LTE 114 T 34 T 155.5 M 1.01 p 13 T 45 %RH 523 m GT MASTER 17.0.1 LI - W. Eisenhart 71.57 p 530 T LI 260442 Final Report – Work Package IIA Energy Interconnection Europe - Malta Colours: Abbreviation: - high pressure steam red light blue - intermediate pressure steam p - pressure in bar MALTA RESOURCES AUTHORITY - gas, air and exhaust gas flow violet dark blue - feed water and water injection to gas turbine M - mass flow in kg / s T - temperature in °C 8.612 p 259 T Page 6-6 March 2008 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 6.1.2 Location Regarding the possible erection of new power generation units, in general it was set focus to the Delimara Power Station site. Potential sites for additional power generating facilities (such as CCGTs) are already reserved for the Delimara Power Station site. The geometric properties of supply option 1 would be comparable to those of the already existing combined cycle plant. This one and the potential sites for the new CCGT are illustrated in the modal and map provided in the following figure. LI 260442 Page 6-7 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Figure 6-4: Potential Location of Gas-Based Generation Option 1 6.1.3 Air Pollution Emissions In the following tables the environmental impact due to potential air pollution emissions is considered. Based on the unit’s capacity and thermodynamic parameters, like e.g. specific energy input and combustion temperatures as well as fuel air ratio lambda, the unit’s behaviour regarding all possible operation modes was simulated. As already known both from physical theory and operational experience, the partial load behaviour in terms of efficiency and fuel consumption cannot be compared with full load operation mode. According to CO2 and SO2 emissions, the specific values for considered generation technologies can be reviewed over several plant’s load characteristics. Moreover NOx conditions and influence parameters are shown as well as the specific emissions. Generally speaking, the NOx emissions are declining while the unit operates in partial load, because of being significantly addicted to the combustion temperature which is also declining due to thermo-dynamic simulations. Calculations were carried out to demonstrate that the supply option 1 complies with the EU environmental directives and with all the relevant aspects of the Maltese Legislation Act YY of 2001 (“Environmental Protection Act) as well as with the associated legal notices. With regard to the European Large Combustion Plant Directive (LCPD 2001/80/EC) EU Member States may choose, by 1 January 2008, to either comply with the Emission Limit Values (ELV) set down in the LCPD or to produce and implement a national emission reduction plan. National plans should reduce the total annual emissions of SO2, NOx and particulate matter to the levels that would have been achieved by applying the ELVs set out in the LCPD to existing plants in operation in the year 2000, on the basis of each plant’s operational performance averaged over LI 260442 Page 6-8 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA the last five years of operation up to and including 2000. Furthermore, national plans should specify the measures that will be implemented to ensure that this is achieved. Malta’s National Programme under the Emissions Ceilings Directive was prepared by the Malta Environmental and Planning Authority (MEPA) and published in December 2006. The programme describes clearly the current state and provides detailed targets regarding the future development of Nitrogen Oxides and Sulphur Dioxide emissions of the power generating sector in Malta. Impacts on the existing generation system were already described in the report of the work package I (in particular the limited operation hours of the Marsa Power Station). Regarding to the operation of new power plants the National Programme under the Emissions Ceilings Directive provides the following emission factors (EF): x x x x 2010: Unabated EF for NOx emissions of 500 t/PJ; Abated EF for NOx emissions of 155 t/PJ (assuming a removal efficiency of 69%); 2010: Unabated EF for SO2 emissions of 234 t/PJ; Abated EF for SO2 emissions of 57 t/PJ (assuming a removal efficiency of 80%); 2020: Unabated EF for NOx emissions of 500 t/PJ; Abated EF for NOx emissions of 155 t/PJ (assuming a removal efficiency of 69%); 2020: Unabated EF for SO2 emissions of 234 t/PJ; Abated EF for SO2 emissions of 57 t/PJ (assuming a removal efficiency of 80%). The above targets are related to the energy input before the conversion to the plant’s electricity output (sent-out). Transforming the values to the plant’s sent-out related emission limits the following ELV for new power generating facilities have to be considered: x x A maximum of 1.2 g/kWh regarding the emissions of NOx; A maximum of 2.2 g/kWh regarding the emissions of SO2. The Greenhouse Gas Emission Trading Scheme (EU Directive 2003/87/EC) was transposed in the L.N. 140/2005 of the Maltese Legislations and sets the limits on Greenhouse Gas Emissions (mainly CO2). Regarding the plant’s sent-out the EF amounts to: x A maximum of 630 g/kWh regarding the emissions of Greenhouse Gases. LI 260442 Page 6-9 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA General Information # Item 1 1 Plant Name Natural Gas Based Supply Option 1 2 Plant Type Combined Cycle Gas Turbine 3 Unit CCGT 2+1 NG fired 4 State Option 5 Unit_Ident 6 Comments No Comments Technical & Operational Data for Emissions (continued) Item Dim 1 7 Nominal Capacity MW 127.9 8 Max Capacity Sent-Out (Operation) MW 125.5 9 Min Capacity Sent-Out (Operation) MW 31.1 10 Heat Rate* Coeff A (2+1) - 3,010 11 Heat Rate* Coeff B (2+1) - -6,795 10000 5000 kJ / kWh # 0 - 11,238 10a Heat Rate* Coeff A (1+1) 15,328 11a Heat Rate* Coeff B (1+1) -16,885 12a Heat Rate* Coeff C (1+1) 12,144 13 Combustion Temp Coeff A - -742 14 Combustion Temp Coeff B - 1,579 15 Combustion Temp Coeff C - 485 16 Air Rate Lambda O Case1 20% 30% 40% 50% 60% 70% 80% 90% 100% 10700 [comb. temp.] 12 Heat Rate* Coeff C (2+1) 10% 8700 6700 4700 2700 700 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 1.0 - 1.09 Table 6-3: Specifications of D_CC1NGo (1/3) LI 260442 Page 6-10 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA NOx Emissions # Item 1 17 Thermal Nox Coeff. A 1E-21 Fuel Nox Coeff. A NA 18 Thermal Nox Coeff. B 7.72 Fuel Nox Coeff. B NA Fuel Nox Coeff. C NA 19 Fuel NOx Emissions over load (RAW) 20 Thermal NOx Emissions over load (RAW) mg/m³ mg/m³ 1,200 1,000 800 600 400 200 0 1,200 1,000 800 600 400 200 1 0 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 21 Specific NOx Emissions in g/kWh Absolute NOx Emissions in tons [g/kWh] 2.5 1.20 2.0 1.00 0.80 1.5 kg Nox RAW 300 255 211 200 0.60 1.0 0.40 0.5 0.20 0.0 0.00 10% 20% 30% 40% 50% 60% 70% 80% 100.0 158 150 80.0 60.0 107 100 50 140.0 120.0 250 63 76 40.0 64 42 7 22 20.0 0 0.0 13 26 38 51 64 77 90 102 115 128 90% Fuel Specifications 22 Initial Primary Fuel 23 Net Calorific Value Rich gas % of Carbon Natural Gas kJ/kg 48,156 24 Required Fuel at 100% load kg 19,795 25 Required Combustion Air m³ 9.89 Fuel Composition % of Nitrogen (Emission Relevant) 75.00% 0.00% % of Sulphur 0.00% % of Nox Reduc. 50.00% % of SO2 Reduc. 0.00% Potential Emission Reduction 26 Resulting Exhaust Gas m³ 10.34 Table 6-3: Specifications of D_CC1NGo (2/3) LI 260442 Page 6-11 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA CO2 and SOx Emissions # Item 1 27 Fuel needed at 100% load t 19.79 28 Density of Fuel 29 CO2 emission at 100% load 30 Specific CO2 Emissions in g/kWh kg / m³ 0.77 t 53.38 Absolute CO2 Emissions in t [t CO2] [g/kWh] 60 800 50 594 600 525 474 35.4 40 439 422 462 446 433 423 417 30 400 20 10 200 13.4 18.2 22.5 39.9 44.3 48.7 53.4 27.0 7.6 0 13 0 10% 31 20% 30% 40% 50% 60% 70% 80% 90% 26 38 51 100% Specific SOx Emissions in g/kWh 64 77 [MW] 90 102 115 128 Absolute SOx Emissions in tons n/a n/a Exhaust Gas development in m³ due to Gross Performance m³ Exhaust Gas 32 250,000 200,000 135,795 150,000 152,889 169,723 186,792 204,592 103,402 100,000 69,655 86,115 51,499 50,000 29,123 0 1 Table 6-3: Specifications of D_CC1NGo (3/3) LI 260442 Page 6-12 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA The air pollution emissions of the investigated supply option: x do not exceed the limit value for NOx emissions; x do not exceed the limit value for SO2 emissions. Natural gas does not cause such emissions at all; x are 54% below the current Green House Gas emissions (typical unit operation assumed) and do not exceed the limit value for CO2 emissions. Finally, Figure 6-5 provides a comparison of the calculated GHG emissions of the supply option and the today dominating technology in the Maltese power generation system. Specific Emissions g CO2/kWh . 1,000 900 800 921 871 700 600 500 400 420 300 200 100 Business as Usual (all STs) Business as Usual (DPS ST) Supply Option Figure 6-5: Comparison of Greenhouse Gas Emissions - Gas-Based Generation Option 1 LI 260442 Page 6-13 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 6.2 Economic Description of Gas-Based Generation Option 1 (CCGT 2+1) 6.2.1 Investment Costs of Major Components The payment plan for a power plant project such as for the investigated supply options is closely linked to the foreseen implementation schedule, in the way that there is normally a: x x down payment of 10 – 20% of the contract value, covered by a down payment security, after the award of contract to the Contractor; a final payment of about 5% at the end of the warranty period; and a series of intermediate payments linked to major events of work progress, the so-called “Milestones”, as there are: o Mobilisation and site preparation; LI 260442 o Civil works design; o Civil construction works, incl. administration building; o Architectural and civil finishing works; o Design, manufacturing and transport of mechanical, electrical and Instrumentation & Control (I&C) equipment; o Design, manufacturing and transport of the gas turbine generator(s); o Erection of the gas turbine with auxiliaries, incl. commissioning and testing; o Erection of heat recovery steam generator; o Erection and commissioning of steam turbine generator; o Erection and piping and components of water steam; o Erection of cooling water system, mechanical, electrical and I&C equipment; o Erection and commissioning of mechanical auxiliary equipment; o Erection of electrical equipment; o Erection of distributed control system (DCS) and other I&C equipment; o Commissioning of the combined cycle; o Reliability test run; o Taking over by Owner. Page 6-14 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Investment Costs in T EUR # Item 1 Gas Turbine Package incl. Generator 24,700 2 Steam Turbine Package incl. Generator 10,342 3 Heat Recovery Boiler 14,125 4 Cooling Facility/Cooling System 5 Balance of Plant 6,095 6 Electrical Equipment 7,189 7 I&C Equipment 1,354 8 Civil/Buildings incl. On-Site Transportation 8,905 9 Engineering 3,470 10 Plant Startup 750 644 11 Contractor's Soft Costs Total: 12,177 89,775 Table 6-4: Investment Costs of Gas-Based Generation Option 1 The above table provides the supply option’s investment cost in total and for each major component. In total, the projects investment cost amounts to 89.8 Mio Euro (10% contingencies included). The specific investment cost is 715 EUR/kW. Figure 6-6 illustrates the investment break down. The dominating cost proportions are (i) the gas turbine package; (ii) the heat recovery boiler; (iii) soft costs of the contractor and (iv) the steam turbine package. LI 260442 Page 6-15 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Year n-3 n-2 n-1 n Disbursement in % 50% 30% 20% Start Year Table 6-5: Disbursement Schedule of Gas-Based Generation Option 1 The investment’s disbursement was derived under consideration of the major project steps which were explained at the beginning of this section (see Table 6-5; n is equal to the first year of plants’ operation). 2% 8% 10% Gas Turbine Package incl. Generator and Air inlet cooling/heating if applicable Steam Turbine Package incl. Generator 4% 1% Heat Recovery Boiler 7% 14% 1% Cooling Facility/Cooling System Balance of Plant Electrical Equipment I&C Equipment 16% Civil/Buildings incl. On-Site Transportation Engineering 28% 12% Plant Startup Contractor's Soft Costs Figure 6-6: Investment Cost Break Down of Gas-Based Generation Option 1 LI 260442 Page 6-16 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 6.2.2 Operational and Maintenance Costs Gas Supply Costs Estimation As the result of the assessments in the chapters 1 to 5 the development of the costs of the supply of gas to the power plant is presented in the below Table. The year 2011 is selected as the first possible year of the plant’s operation. This assumption takes into account the project’s schedule given in the previous section. Item Fuel Supply Costs (via LNG conversion) Item Fuel Supply Costs (via LNG conversion) Unit 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 EUR/t 204.4 197.7 191.0 191.0 191.0 191.0 194.4 197.7 201.0 201.0 Unit 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 EUR/t 204.4 207.7 211.0 214.4 216.0 217.7 217.7 219.4 219.4 221.0 Table 6-6: Gas Supply Costs Fixed O&M Costs Fixed costs of operation and maintenance include expenses for staff salaries; insurance, fees and other cost which remain constant irrespective of the actual quantum of the plant’s electrical energy sent-out. The personnel costs are calculated by the estimated number of required staff (25 employees) and the average annual salary (30 T EUR/a). Based on experiences in similar assignments the proportion of the remaining fixed operation and maintenance costs is 2.5% of the capital costs. . # Item 1 Personnel Costs 2 Insurance, Fees and Others 2,244 Total Annual Fixed OPEX: 2,994 Costs in T EUR/a 750 Table 6-7: Estimate of Annual Fixed OPEX LI 260442 Page 6-17 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Variable O&M Costs Variable costs of operation and maintenance include the cost of fuel and costs for e.g. lubricating oil and chemicals which are consumed in proportion to the actual amount of the plant’s electrical energy sent-out. The dominating proportion of the variable OPEX is the cost of fuel, which depends on the fuel supply cost and the amount of fuel utilized. The latter item again depends on the plant’s efficiency and further on the plant’s operation mode (e.g. full load or partial load; number of turbines in operation). In the first section of this chapter the plant’s performance parameters are described in detail. The following economic analysis considers individual operation modes and the related specific fuel input. Based on our experience in similar assignment the value of the remaining variable OPEX is estimated at 1.6 EUR/MWh. 6.2.3 Dynamic Unit Cost Assessment for Option 1 The economic analysis involves the derivation of the dynamic unit cost (DUC) for the proposed local generation option. The (economic) dynamic unit cost is derived by dividing the present value of the project costs at economic prices, by the present value of the quantity of output (the plant’s net generation). In this case the DUC represents the specific power generation cost over the project’s life cycle. Costs in this context are in reference to the investment and the variable and fixed operation & maintenance costs. Duties, taxes, etc. are not taken into consideration for the derivation of the economic dynamic unit cost. A discount rate of 6.5% is applied. The period under consideration is equal to the estimated project’s economic lifetime. The following chart provides the calculation of the dynamic unit cost of the gas-based option 1. As far as the actual future operation of the plant is not known (this depends mainly on the most economic dispatch of the unit as one component of the entire power generation system; see Work Package III) we provide cost figures over the entire load range. Exemplarily the calculation in the chart is based on an 85% load assumption. Nevertheless, the results are shown for different operation modes from full load to partial load. The DUC trends are shown in Figure 6-7. Regarding the expected annual net generation the option’s maximum availability of 91.5% is considered in the 100% full load case. In the selected 85% load case the DUC of the gas-based local generation option 1 amounts to 46.1 EUR/MWh. Only slight fluctuations of the DUC are observed within the plant’s base load operation. In full load operation the DUC are 4% lower than the reference value. At 70% load level the DUC are 9% higher than the reference value. In intermediate and peak load operation the cost figures increase highly. At 50%-load an increase of 17% and at 20%-load an increase of 141% is registered in comparison to the reference value. The plant’s maximum annual net generation amounts to 1,006 GWh/a (at maximum availability and full load). LI 260442 Page 6-18 LI 260442 EUR/t T EUR/a t/a GWh/a Fuel Supply Costs (specific) Fuel Supply Costs (absolute) Fuel Input Net Generation DUC - Power Generation 4 Dynamic Unit Cost Capital OPEX Net Generation EUR/MWh Partial Load T EUR T EUR GWh T EUR/a Variable OPEX 3 Present Value T EUR/a Fixed OPEX Year >> 70% 89.6 87.0 2.6 2.9% 50% 63.6 62.0 1.6 2.5% 106 7 46.1 85% 44.4 125 5 0 0 0 0 0 0 26,933 n-2 70% 7,963 50.1 87 9 70% 0 0 0 0 0 0 17,955 n-1 50% 7,528 2GT+1ST 1GT+1ST 100% 103,891 457,810 12,173 0 0 0 0 0 0 44,888 n-3 85% 7,647 100% 7,441 20 3% 91.5% T EUR/a kJ/kWh d/a %/a %/a 2GT+1ST 2GT+1ST Investment Cost Item 2 Cash Flow Net Heat Rate Planned Outage Forced Outage Max Availability 85% 109.3 106.9 2.4 2.2% 30% 38.4 36.9 1.4 3.8% 20% 25.1 24.8 0.3 1.2% 53.9 62 8 50% 204 30,256 148,045 932 31,748 2,994 0 1 30% 8,478 1GT+1ST 71.8 37 7 30% 198 29,270 148,045 932 30,761 2,994 0 2 20% 13,974 1GT 3 110.9 25 1 20% 191 28,283 148,045 932 29,774 2,994 0 191 28,283 148,045 932 29,774 2,994 0 4 201 29,763 148,045 932 31,254 2,994 0 10 89,775 6.5% 30 3 221 32,723 148,045 932 34,215 2,994 0 20 238 35,296 148,045 932 36,787 2,994 0 30 Operation at 85% Load T EUR/a 2,994 EUR/MWh 1.6 -- Regas LNG kJ/kg 48,150 T EUR % a a Local Generation Option 1 (CCGT 2+1) 191 28,283 148,045 932 29,774 2,994 0 5 * other than Fuel Costs Fixed OPEX Variable OPEX* Fuel Type Net Calorific Value Total Investment Discount Rate Lifetime Construction Period MW MW MW % -- CCGT 2+1 128.0 100% 128.0 125.5 2.5 1.9% Plant Type Set Size (nominal) Partial Load Set Capacity (gross) Set Capacity (net) Auxiliary Power Self Consumption Turbines in Operation -MW 1.2 Economics p 1.1 Technical 1 General Information MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Table 6-8: Dynamic Unit Cost of the Gas-based Option 1 Page 6-19 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Dynamic Unit Cost EUR/MWh 140 120 100 80 60 40 20 0 20.0 40.0 60.0 80.0 100.0 120.0 Plant's Operation - Load (Net) in MW 140 1,400 120 1,200 100 1,000 80 800 60 600 40 400 20 200 0 10% Plant's Net Generation in GWh/a Dynamic Unit Cost EUR/MWh - 20% 30% 40% 50% 60% 70% 80% 90% 100% Plant's Operation as Percentage of Load Figure 6-7: Dynamic Unit Cost over Plant’s Load - Gas-Based Option 1 LI 260442 Page 6-20 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 6.3 Technical Description of Gas-Based Generation Option 2 (CCGT 1+1) 6.3.1 Basic Design This power plant is a combined cycle power plant consisting of one gas turbine, one HRSG and one condensing steam turbine as single shaft design. On an international level the following two important manufacturers can deliver such power plants: (i) General Electrics (GE) Power Systems; (ii) Siemens. The gas turbine is designed with a dual fuel combustion system using LNG (gaseous) as primary fuel and diesel as secondary fuel. Water injection for NOx reduction when burning diesel may be considered in order to meet the allowed NOx emission standard. Because of the single shaft configuration there is a steam turbine clutch installation assumed. A single cycle operation of the gas turbine is thereby possible and thus the operational flexibility of the plant is increased. The heat recovery steam generator (HRSG) is equipped with a bypass stack. The design capacity of the gas turbine amounts to 75.2 MW (Net). The design capacity of the steam turbine is 37.1 MW (Net). Plant Characteristics Unit Plant Type Set Size (nominal) Value CCGT 1+1 MW Partial Load 114.6 100% 85% 70% 50% 40% 25% Set Capacity (gross) MW 114.6 96.8 78.3 58.3 46.0 30.8 Set Capacity (net) MW 112.3 94.6 76.2 56.3 45.4 30.3 Auxiliary Power MW 2.4 2.2 2.1 1.9 0.6 0.5 % 2.1% 2.3% 2.7% 3.3% 1.3% 1.6% 1GT+1ST 1GT+1ST 1GT+1ST 1GT+1ST 1GT 1GT Partial Load 100% 85% 70% 50% 40% 25% kJ/kWh 6,930 7,141 7,471 8,122 12,564 15,101 Planned Outage d/a 18 Forced Outage %/a 3% Max Availability %/a 92.1% Self Consumption Turbines in Operation Net Heat Rate Table 6-9: Technical Data – Gas-Based Generation Option 2 LI 260442 Page 6-21 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Maltese local conditions and provided fuel specifications have been considered for the evaluation of the major operational parameters. The performance data of this supply option is based on the gas turbine (GT) of type GE 6111FA and dual pressure HRSG without duct burner firing. Another possible gas turbine type of similar size is for example the Siemens SGT-1000F but in this case an upgraded GT (with higher turbine inlet temperature and exhaust gas mass flow) or a HRSG with duct burner firing is needed. The HRSG produces in this case 29.7 kg/s high pressure steam with 67.5 bar and 585 °C and an intermediate pressure steam of 3.17 kg/s with 8.3 bar and 258 °C. The indoor located condensing steam turbine has a capacity of 37 MW. For the cooling system an open loop water cooling with a seawater inlet Temperature of 20 °C and a allowable cooling water temperature rise of 8 K is assumed. Table 6-9 provides the general technical parameters of the supply option (design conditions). A partial load range between 100% (full load) and 25% is selected regarding the provision of the operational characteristics, which can be summarized as follows: x x The plant’s self consumption (auxiliary power) drops from 2.4 MW to 0.5 MW in absolute terms. Related to the plants output the value increases from 2.1% to 3.3% (1 GT + 1 ST operation) and decreases thereafter to for example 1.3% (1 GT operation); The plant’s net heat rate increases from 6,930 kJ/kWh to more than 15,000 kJ/kWh over the entire range of partial load. This is equal to a net efficiency decrease from 51.9% to 23.8% only. Assuming outage characteristics of an average of 18 days a year for the units’ maintenance and a 3% forced outage, the maximum availability of the plant is expected to amount 92.1% over an entire year. The net and gross heat rates of the gas based supply option 2 are shown in the following figure over the entire load range (calculated on fuel’s NCV). The results of GT Pro calculations are summarized within the heat and mass balance diagrams in the Figures 6-9 and 6-10. The calculations are based on the maximum load of the plant during summer and winter conditions. The comparison of the summer and winter parameters brings out the following results: x x The plant’s net capacity during summer amounts to 86.1% (97.8 MW) compared to the net capacity during the winter period by some 113.6 MW. The plants’ net heat rate decreases from 7,113 kJ/kWh during summer to 6,903 kJ/kWh during winter. This is equal to a net efficiency increase from 50.6% (summer) to 52.2% (winter). LI 260442 Page 6-22 LI 260442 0 2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 0 20,000 40,000 Load (kW) 60,000 80,000 100,000 1+0 net HR 1+0 gross HR 1+1 net HR 1+1 gross HR Heat Rates (kJ/kWh) of Supply Option 2 - 1+1 CCGT NG fired 120,000 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Figure 6-8: Gross and Net Heat Rates – Gas-Based Generation Option 2 Page 6-23 Heat Rate (kJ/kWh) 157 2.323 p 115 T 119.6 M LTE 2.323 p 125 T 1p 36 T 666.8 m 2.225 M 121.8 M 157 IPB 3.12 M 31 T 189 227 9.077 p 9.077 p 171 T 176 T 121.8 M 13.63 M IPE2 LNG 14.45 m LHV= 193176 kWth 20 T 14.02 p 397 T HPE2 13.32 p 1318 T 263 73.45 p 229 T 104.9 M 227 1X GE 6111FA HPE3 265 301 HPB1 HPS0 1.73 M 67.49 p 585 T 107 M 1.04 p 629 T 681.2 M 302 506 520 8.783 p 72.22 p 71.71 p 260 T 288 T 309 T 11.41 M 103.9 M 103.9 M IPS2 62965 kW 681.2 m 8.952 p 72.22 p 228 T 282 T 11.41 M 104.9 M IPS1 CCGT 1+1 configuration NG fired 100% load at summer conditions 520 Figure 6-9: Heat and Mass Balance – Gas-Based Generation Option 2 (Summer Conditions) 520 627 FW 2.568 m^3/kg 485.9 m^3/s 627 T 681.2 M 1.38 M 46 T 0.0344 M 69.84 p 607 T 105.3 M HPS3 11.41 M 0.1032 p 46 T 118.4 M 37072 kW 72.39 %N2 12.3 %O2 3.837 %CO2 10.6 %H2O 0.8716 %Ar Net Power 97771 kW LHV Heat Rate 7113 kJ/kWh p[bar], T[C], M[t/h], Steam Properties: IAPWS-IF97 316 08-20-2007 11:27:33 file=T:\26\0400\260442_malta\06_project_results\GTPro\Case 2 (1+1) neu\CCGT 1+1 NG FIRED 100% load summer conditions.gtm 1.114 m^3/kg 210.8 m^3/s 109 T 681.2 M 115 T 46 T 119.6 M 1.01 p 36 T 70 %RH 666.8 m GT MASTER 17.0.1 LI - W. Eisenhart 69.84 p 607 T LI 260442 Final Report – Work Package IIA Energy Interconnection Europe - Malta MALTA RESOURCES AUTHORITY Colours: Abbreviation: - high pressure steam red light blue - intermediate pressure steam p - pressure in bar - gas, air and exhaust gas flow violet dark blue - feed water and water injection to gas turbine M - mass flow in kg / s T - temperature in °C 8.302 p 258 T Page 6-24 March 2008 160 2.323 p 114 T 124.1 M LTE 2.323 p 125 T 1p 13 T 746.8 m 2.619 M 126.7 M 160 IPB 0.001 M 31 T 193 232 9.536 p 9.536 p 174 T 178 T 126.7 M 15.75 M IPE2 LNG 16.29 m LHV= 217815 kWth 20 T 15.65 p 380 T HPE2 14.87 p 1328 T 267 75.38 p 233 T 110.8 M 232 1X GE 6111FA HPE3 269 304 HPB1 HPS0 69.1 p 584 T 109.7 M 1.04 p 606 T 763.1 M 305 499 511 9.173 p 74.01 p 73.47 p 260 T 290 T 309 T 13.12 M109.7 M 109.7 M IPS2 75611 kW 763.1 m 9.382 p 74.01 p 229 T 285 T 13.12 M110.8 M IPS1 CCGT 1+1 configuration NG fired 100% load at winter conditions 511 Figure 6-10: Heat and Mass Balance – Gas-Based Generation Option 2 (Winter Conditions) 511 604 FW 2.46 m^3/kg 521.5 m^3/s 604 T 763.1 M 34 T 0.036 M 71.52 p 586 T 109.7 M HPS3 13.12 M 0.0542 p 34 T 122.7 M 40367 kW 74.94 %N2 12.85 %O2 3.912 %CO2 7.395 %H2O 0.9023 %Ar Net Power 113597 kW LHV Heat Rate 6903 kJ/kWh p[bar], T[C], M[t/h], Steam Properties: IAPWS-IF97 316 08-20-2007 11:27:57 file=T:\26\0400\260442_malta\06_project_results\GTPro\Case 2 (1+1) neu\CCGT 1+1 NG FIRED 100% load winter conditions.gtm 1.098 m^3/kg 232.8 m^3/s 109 T 763.1 M 114 T 34 T 124.1 M 1.01 p 13 T 45 %RH 746.8 m GT MASTER 17.0.1 LI - W. Eisenhart 71.52 p 586 T LI 260442 Final Report – Work Package IIA Energy Interconnection Europe - Malta MALTA RESOURCES AUTHORITY Colours: Abbreviation: - high pressure steam red light blue - intermediate pressure steam p - pressure in bar - gas, air and exhaust gas flow violet dark blue - feed water and water injection to gas turbine M - mass flow in kg / s T - temperature in °C 8.601 p 258 T Page 6-25 March 2008 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 6.3.2 Location Regarding the potential location of supply option 2, the same site was selected as already depicted for supply option 1 in Figure 6-4. 6.3.3 Air Pollution Emissions The legal frame and the National targets are explained in detail in section 6.1.3. Calculations were carried out to demonstrate that the supply option 2 complies with the EU environmental directives and with all the relevant aspects of the Maltese Legislation. In the following tables the environmental impact due to potential air pollution emissions is presented. The air pollution emissions of the investigated supply option: x x x do not exceed the limit value for NOx emissions; do not exceed the limit value for SO2 emissions. Natural gas does not cause such emissions at all; are 56% below the current Green House Gas emissions (typical unit operation assumed) and do not exceed the limit value for CO2 emissions. Specific Emissions g CO2/kWh . 1,000 900 800 921 871 700 600 500 400 401 300 200 100 Business as Usual (all STs) Business as Usual (DPS ST) Supply Option Figure 6-11: Comparison of Greenhouse Gas Emissions - Gas-Based Generation Option 2 LI 260442 Page 6-26 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA General Information # Item 2 1 Plant Name Natural Gas Based Supply Option 2 2 Plant Type Combined Cycle Gas Turbine 3 Unit CCGT 1+1 NG fired 4 State Option 5 Unit_Ident 6 Comments No Comments Technical & Operational Data for Emissions (continued) # Item Dim 2 7 Nominal Capacity MW 114.6 8 Max Capacity Sent-Out (Operation) MW 112.3 9 Min Capacity Sent-Out (Operation) MW 30.8 10 Heat Rate* Coeff A (1+1) - 5,619 11 Heat Rate* Coeff B (1+1) - -10,966 12 Heat Rate* Coeff C (1+1) - 12,336 10000 20000 5000 10000 kJ / kWh 15000 5000 0 46,433 11a Heat Rate* Coeff B (1+0) -50,173 12a Heat Rate* Coeff C (1+0) 25,219 13 Combustion Temp Coeff A - -742 14 Combustion Temp Coeff B - 1,579 15 Combustion Temp Coeff C - 485 16 Air Rate Lambda O Case1 20% 30% 40% 50% 60% 70% 80% 90% 100% 1400 1300 [comb. temp.] 10a Heat Rate* Coeff A (1+0) 10% 1200 1100 1000 900 800 700 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 1.0 - 1.09 Table 6-10: Specifications of D_CC2NGo (1/3) LI 260442 Page 6-27 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA NOx Emissions # Item 2 17 Thermal Nox Coeff. A 1E-21 Fuel Nox Coeff. A NA 18 Thermal Nox Coeff. B 7.72 Fuel Nox Coeff. B NA Fuel Nox Coeff. C NA 19 Fuel NOx Emissions over load (RAW) 20 Thermal NOx Emissions over load (RAW) mg/m³ mg/m³ mg/m³ 1,200 1,200 1,200 1,000 1,000 1,000 800 800 800 600 600 400 400 600 400 200 2000 200 0 0.1 21 Specific NOx Emissions in g/kWh [g/kWh] 1.20 kg Nox RAW 2.0 1.00 250 300 0.80 250 200 1.5 0.20 200 150 150 100 100 50 50 0.00 0 0.60 1.0 0.40 0.5 0.0 20% 30% 40% 50% 60% 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 Absolute NOx Emissions in tons 2.5 10% 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 0 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 70% 80% 90% 214 255 175 211 131 158 90 65 13 7 11 13 63 36 22 42 23 26 34 38 46 51 75 76 57 64 54 64 80 90 92 102 120.0 100.0 100.0 80.0 80.0 60.0 60.0 40.0 40.0 20.0 20.0 89 107 69 77 120.0 140.0 103 115 115 128 0.0 Fuel Specifications 22 Initial Primary Fuel Rich gas 23 Net Calorific Value kJ/kg 48,156 24 Required Fuel at 100% load kg 16,633 25 Required Combustion Air m³ 9.89 % of Carbon Natural Gas Fuel Composition % of Nitrogen (Emission Relevant) 75.00% 0.00% % of Sulphur 0.00% % of Nox Reduc. 50.00% % of SO2 Reduc. 0.00% Potential Emission Reduction 26 Resulting Exhaust Gas m³ 10.34 Table 6-10: Specifications of D_CC2NGo (2/3) LI 260442 Page 6-28 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA CO2 and SOx Emissions # Item 2 27 Fuel needed at 100% load t 16.63 28 Density of Fuel 29 CO2 emission at 100% load 30 Specific CO2 Emissions in g/kWh kg / m³ 0.77 t 44.85 Absolute CO2 Emissions in t [t CO2] [g/kWh] 50 1,400 800 1157 1,200 594 600 1,000 40 954 525 800 400 600 474 803 439 704 422 462 462 436 446 415 433 423 401 393 32.3 27.6 30 417 26.5 30.0 33.3 36.8 21.9 20 13.3 391 400 200 200 10 0 00 11 10% 20% 20% 30% 30% 40% 40% 50% 50% 60% 60% 10% 31 44.9 40.5 70% 70% 80% 80% 90% 90% 23 34 46 100% Specific SOx Emissions in g/kWh 57 69 [MW] 80 92 103 115 Absolute SOx Emissions in tons n/a n/a Exhaust Gas development in m³ due to Gross Performance m³ Exhaust Gas 32 200,000 250,000 200,000 150,000 123,762 105,860 150,000 100,000 100,000 50,832 50,000 50,000 29,123 101,558 103,402 83,834 51,499 69,655 114,808 135,795 127,639 152,889 140,880 169,723 155,361 186,792 171,912 204,592 86,115 0 0.1 10% 0.2 20% 0.3 30% 0.4 40% 0.5 50% 0.6 60% 0.7 70% 0.8 80% 0.9 90% 1 100% Table 6-10: Specifications of D_CC2NGo (3/3) LI 260442 Page 6-29 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 6.4 Economic Description of Gas-Based Generation Option 2 (CCGT 1+1) 6.4.1 Investment Costs of Major Components The projects implementation plan (already described in section 6.2.1) leads to the investment cost’s disbursement schedule shown in Table 6-12. The total duration of the project’s implementation is estimated at three years. A lifetime of 25 years is assumed for the supply option 2. The investment cost in total and for each individual major component is provided in Table 6-11. In total, the projects investment cost amounts to 74.6 Mio Euro (10% contingencies included). Investment Costs in T EUR # Item 1 Gas Turbine incl. Generator 2 Steam Turbine Package incl. Generator 9,698 3 Heat Recovery Boiler 9,954 4 Cooling Facility/Cooling System 5 Balance of Plant 5,163 6 Electrical Equipment 5,737 7 I&C Equipment 8 Civil/Buildings incl. On-Site Transportation 7,812 9 Engineering 3,292 10 Plant Startup 11 Contractor's Soft Costs 20,853 672 853 603 Total: 9,894 74,550 Table 6-11: Investment Costs of Gas-Based Generation Option 2 LI 260442 Page 6-30 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Year n-3 n-2 n-1 n Disbursement in % 50% 30% 20% Start Year Table 6-12: Disbursement Schedule of Gas-Based Generation Option 2 The specific investment cost amounts to 664 EUR/kW, approximately 7% less compared to the gas-based generation option 1. Figure 6-12 illustrates the investment break down. The dominating cost proportions are (i) the gas turbine package; (ii) the heat recovery boiler; (iii) soft costs of the contractor and (iv) the steam turbine package. Gas Turbine incl. Generator 1% 8% 10% 4% Steam Turbine Package incl. Generator 1% Heat Recovery Boiler 7% 13% 1% Cooling Facility/Cooling System Balance of Plant Electrical Equipment 13% I&C Equipment Civil/Buildings incl. On-Site Transportation Engineering 13% 28% Plant Startup Contractor's Soft Costs Figure 6-12: Investment Cost Break Down of Gas-Based Generation Option 2 LI 260442 Page 6-31 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 6.4.2 Operational and Maintenance Costs Gas Supply Costs Estimation The development of the costs of the supply of gas to the power plant is presented in the below Table. The year 2011 is selected as the first possible year of the plant’s operation. This assumption takes into account the project’s schedule given in the previous section. Item Fuel Supply Costs (via LNG conversion) Item Fuel Supply Costs (via LNG conversion) Unit 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 EUR/t 204.4 197.7 191.0 191.0 191.0 191.0 194.4 197.7 201.0 201.0 Unit 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 EUR/t 204.4 207.7 211.0 214.4 216.0 217.7 217.7 219.4 219.4 221.0 Table 6-13: Gas Supply Costs Fixed O&M Costs Fixed costs of operation and maintenance include expenses for staff salaries; insurance, fees and other cost which remain constant irrespective of the actual quantum of the plant’s electrical energy sent-out. The personnel costs are calculated by the estimated number of required staff (25 employees) and the average annual salary (30 T EUR/a). Based on experiences in similar assignments the proportion of the remaining fixed operation and maintenance costs is 2.5% of the capital costs. In total the annual fixed OPEX amount to 2.6 Mio EUR/a. . # Item 1 Personnel Costs 2 Insurance, Fees and Others 1,864 Total Annual Fixed OPEX: 2,614 Costs in T EUR/a 750 Table 6-14: Estimate of Annual Fixed OPEX LI 260442 Page 6-32 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Variable O&M Costs Variable costs of operation and maintenance include the cost of fuel and costs for e.g. lubricating oil and chemicals which are consumed in proportion to the actual amount of the plant’s electrical energy sent-out. The dominating proportion of the variable OPEX is the cost of fuel, which depends on the fuel supply cost and the amount of fuel utilized. The latter item again depends on the plant’s efficiency and further on the plant’s operation mode (e.g. full load or partial load; number of turbines in operation). In the first section of this chapter the plant’s performance parameters are described in detail. The following economic analysis considers individual operation modes and the related specific fuel input. Based on our experience in similar assignment the value of the remaining variable OPEX is estimated at 2.0 EUR/MWh. 6.4.3 Dynamic Unit Cost Assessment for Option 2 The following chart provides the calculation of the dynamic unit cost of the gas-based local generation option 2. As far as the actual future operation of the plant is not known (this depends mainly on the most economic dispatch of the unit as one component of the entire power generation system; see Work Package III) we provide cost figures over the entire load range. Exemplarily the calculation in the chart is based on an 85% load assumption. Nevertheless, the results are shown for different operation modes from full load to partial load. Furthermore, the DUC trends are illustrated in Figure 6-13. Regarding the expected annual net generation the option’s maximum availability of 92.1% is taken into consideration in the 100% full load case. In the selected 85% load case the DUC of the gas-based local generation option 2 amounts to 43.7 EUR/MWh. Only slight fluctuations of the DUC are observed within the plant’s base load operation. In full load operation the DUC are 4% lower than the reference value. At 70% load level the DUC are 9% higher than the reference value. In intermediate and peak load operation (1 GT + 1 ST mode, and 1 GT mode respectively) the cost figures increase rapidly. At 50%-load an increase of 28% and at 25%-load an increase of 161% is registered in comparison to the reference value. The plant’s maximum net generation amounts to 906 GWh/a (at maximum availability and full load). LI 260442 Page 6-33 LI 260442 50% 58.3 56.3 1.9 3.3% 40% 46.0 45.4 0.6 1.3% 25% 30.8 30.3 0.5 1.6% EUR/t T EUR/a t/a GWh/a Fuel Supply Costs (specific) Fuel Supply Costs (absolute) Fuel Input Net Generation DUC - Power Generation 4 Dynamic Unit Cost Capital OPEX Net Generation EUR/MWh Partial Load T EUR T EUR GWh T EUR/a Variable OPEX 3 Present Value T EUR/a Fixed OPEX Year >> T EUR/a kJ/kWh d/a %/a %/a 95 4 43.7 85% 41.9 112 3 0 0 0 0 0 0 22,365 n-2 70% 7,471 47.5 78 6 70% 0 0 0 0 0 0 14,910 n-1 50% 8,122 1GT+1ST 1GT+1ST 100% 86,272 389,482 10,891 0 0 0 0 0 0 37,275 n-3 85% 7,141 100% 6,930 18 3% 92.1% Investment Cost Item 2 Cash Flow Net Heat Rate Planned Outage Forced Outage Max Availability 1GT+1ST 1GT+1ST 55.8 56 1 50% 204 25,279 123,693 834 26,947 2,614 0 1 40% 12,564 1GT 79.1 44 9 40% 198 24,455 123,693 834 26,123 2,614 0 2 25% 15,101 1GT 3 113.7 28 1 25% 191 23,630 123,693 834 25,298 2,614 0 191 23,630 123,693 834 25,298 2,614 0 4 191 23,630 123,693 834 25,298 2,614 0 5 * other than Fuel Costs 10 201 24,867 123,693 834 26,535 2,614 0 2,614 2.0 Regas LNG 48,150 74,550 6.5% 30 3 221 27,341 123,693 834 29,009 2,614 0 20 238 29,490 123,693 834 31,158 2,614 0 30 Operation at 85% Load kJ/kg -- T EUR/a EUR/MWh 70% 78.3 76.2 2.1 2.7% Fixed OPEX Variable OPEX* Fuel Type Net Calorific Value 85% 96.8 94.6 2.2 2.3% T EUR % a a MW MW MW % -- CCGT 1+1 114.6 100% 114.6 112.3 2.4 2.1% Total Investment Discount Rate Lifetime Construction Period -MW Local Generation Option 2 Plant Type Set Size (nominal) Partial Load Set Capacity (gross) Set Capacity (net) Auxiliary Power Self Consumption Turbines in Operation p 1.2 Economics General Information 1.1 Technical 1 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Table 6-15: Dynamic Unit Cost of the Gas-Based Option 2 Page 6-34 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Dynamic Unit Cost EUR/MWh 140 120 100 80 60 40 20 0 20.0 40.0 60.0 80.0 100.0 120.0 Plant's Operation - Load (Net) in MW 140 1,400 120 1,200 100 1,000 80 800 60 600 40 400 20 200 0 10% Plant's Net Generation in GWh/a Dynamic Unit Cost EUR/MWh - 20% 30% 40% 50% 60% 70% 80% 90% 100% Plant's Operation as Percentage of Load Figure 6-13: Dynamic Unit Cost over Plant’s Load –Gas-Based Option 2 LI 260442 Page 6-35 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 6.5 Technical Description of Gas-Based Generation Option 3 (2+1 ST R) 6.5.1 Basic Design For this supply option one of the existing conventional thermal power units of DPS, with the auxiliary boiler, the steam turbine and the generator, has been modelled in order to recalculate the design performance of the plant. The model was developed so that the gross output and heat rate was consistent with data obtained from the station at the conditions described in the plant documentation. The present technical parameters of the Delimara 60 MW steam turbines are provided already in Table 1-8 (Specifications of D_ST1e) and respectively in Table 1.10 (Specifications of D_ST2e). Then the auxiliary boiler in the model was replaced by two gas turbines with two heat recovery steam generators. All steam turbine ports (formerly for feedwater heater) were closed and a new combined cycle power plant is received. This power plant is a combined cycle power plant consisting of two gas turbines, two HRSG and one (existing) condensing steam turbine. The performance data is based on the GT type of Alstom’s ALS GT8C2 and double pressure HRSG without duct burner firing. On international level three important suppliers offer such power plant equipment: x x x General Electrics (GE) Power Systems, Alstom Siemens. The gas turbines are designed with a dual fuel combustion system using LNG (gaseous) as primary fuel and diesel as secondary fuel. Water injection for NOx reduction when burning diesel may be considered in order to meet the allowed NOx emission standard. Because of the single shaft configuration there is a steam turbine clutch installation assumed. A single cycle operation of the gas turbine is thereby possible and thus the operational flexibility of the plant is increased. The heat recovery steam generator (HRSG) is equipped with a bypass stack. The design capacity of the two gas turbines amounts to 55.3 MW (Net) each. As the result of the plant’s addition by two gas turbines the design capacity of the steam turbine is 49.1 MW (Net). The heat recovery steam generators (HRSG) are equipped with a bypass stack for simple cycle operation of the gas turbines in order to increase the operational flexibility of the plant. Both HRSG produce in total 41.2 kg/s high pressure steam with 87.1 bar and 493 °C and an intermediate pressure steam of 10.3 kg / s with 9.8 bar and 259 °C. For the cooling system an open loop water cooling with a seawater inlet temperature of 20 °C and an allowable cooling water temperature rise of 8 K is assumed. LI 260442 Page 6-36 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Plant Characteristics Unit Plant Type Set Size (nominal) Value CCGT 2+1 MW Partial Load 162.9 100% 85% 70% 50% 30% 20% Set Capacity (gross) MW 162.9 139.1 111.5 81.3 47.7 33.8 Set Capacity (net) MW 159.6 136.0 108.7 79.2 45.9 33.4 Auxiliary Power MW 3.2 3.1 2.9 2.1 1.8 0.4 % 2.0% 2.2% 2.6% 2.5% 3.8% 1.2% 2GT+1ST 2GT+1ST 2GT+1ST 1GT+1ST 1GT+1ST 1GT Partial Load 100% 85% 70% 50% 30% 20% kJ/kWh 7,377 7,537 7,897 7,436 8,422 12,874 Planned Outage d/a 30 Forced Outage %/a 3% Max Availability %/a 88.8% Self Consumption Turbines in Operation Net Heat Rate Table 6-16: Technical Data – Gas-Based Generation Option 3 Maltese local conditions and provided fuel specifications have been considered for the evaluation of the major operational parameters which are provided in Table 6-16. A partial load range between 100% (full load) and 20% is selected regarding the provision of the operational characteristics, which can be summarized as follows: x x The plant’s self consumption (auxiliary power) drops from 3.2 MW to 0.4 MW in absolute terms. Related to the plants output the value increases from 2.0% to 2.6% (2 GT + 1 ST operation); from 2.5% to 3.8% (1 GT + 1 ST operation) and decreases thereafter to only 1.2% (1 GT operation); The plant’s net heat rate increases from 7,377 kJ/kWh to 12,874 kJ/kWh over the range of partial load investigated. This is equal to a net efficiency decrease from 48.8% to 28.0%. Regarding the planned outage duration, the current figure (30 days a year) was applied. It is assumed that maintenance works for the both GTs will carried out within this time frame. The addition of a typical forced outage rate for the type of technology (3%) leads to a maximum availability of the plant of some 88.8%. LI 260442 Page 6-37 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA The net and gross heat rates of the gas based supply option 3 are shown in the following figure over the entire load range (calculated on fuel’s NCV). The results of GT Pro calculations are summarized within the heat and mass balance diagrams in the Figures 6-15 and 6-16. The calculations are based on the maximum load of the plant during summer and winter conditions. The comparison of the summer and winter parameters brings out the following results: x x The plant’s net capacity during summer amounts to nearly 20 MW less (141.6 MW) compared to the net capacity during the winter period which is 161.2 MW. The plants’ net heat rate decreases from 7,522 kJ/kWh during summer to 7,357 kJ/kWh during winter. This is equal to a net efficiency increase from 47.9% (summer) to 48.9% (winter). LI 260442 Page 6-38 LI 260442 0 2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 0 20,000 40,000 60,000 100,000 120,000 140,000 160,000 180,000 Energy Interconnection Europe - Malta Load (kW) 80,000 2+1 gross HR 2+1 net HR 1+1 gross HR 1+1 net HR 1+0 gross HR 1+0 net HR Heat Rates (kJ/kWh) of Supply Option 3 - 2+1 ST R NG fired MALTA RESOURCES AUTHORITY March 2008 Final Report – Work Package IIA Figure 6-14:Gross and Net Heat Rates – Gas-Based Generation Option 3 Page 6-39 Heat Rate (kJ/kWh) 165 2.323 p 116 T 187.4 M LTE 2.323 p 125 T 1p 36 T 632.2 m 3.215 M 190.6 M 165 IPB 2.06 M 20 T 197 256 10.77 p 10.77 p 178 T 183 T 190.6 M 40.41 M IPE2 LNG 11.06 m LHV= 147890 kWth 16.21 p 430 T HPE2 15.48 p 1171 T 256 279 95.26 p 229 T 147.7 M 1X ALS GT8C2 HPE3 282 318 10.58 p 93.28 p 229 T 299 T 37.18 M 147.7 M IPS1 320 1.04 p 531 T 1286.5 M 2 X GT HPB1 2.06 M 87.1 p 493 T 148.3 M 462 10.4 p 93.28 p 261 T 306 T 37.18 M 146.3 M IPS2 47392 kW 643.3 m CCGT 2+1 configuration (refurbishment steam power plant), NG fired 100% load at summer conditions 462 529 FW 2.279 m^3/kg 814.3 m^3/s 529 T 1286.5 M 47 T 0.05 M 90.14 p 510 T 146.3 M HPS3 37.18 M 0.1042 p 47 T 185.4 M 49897 kW 72.86 %N2 13.76 %O2 3.124 %CO2 9.381 %H2O 0.8773 %Ar Net Power 141552 kW LHV Heat Rate 7522 kJ/kWh Figure 6-15: Heat and Mass Balance – Gas-Based Generation Option 3 (Summer Conditions) p[bar], T[C], M[t/h], Steam Properties: IAPWS-IF97 316 08-21-2007 13:50:28 file=T:\26\0400\260442_malta\06_project_results\GTPro\Case 3 (2+1) refurbishment 60MW ST\CCGT 2+1 REFURBISHMENT ST NG FIRED 100% load at summer con 1.159 m^3/kg 414.1 m^3/s 126 T 1286.5 M 116 T 47 T 187.4 M 1.01 p 36 T 70 %RH 632.2 m GT MASTER 17.0.1 LI - W. Eisenhart 90.14 p 510 T LI 260442 Final Report – Work Package IIA Energy Interconnection Europe - Malta MALTA RESOURCES AUTHORITY Colours: Abbreviation: - high pressure steam red light blue - intermediate pressure steam p - pressure in bar - gas, air and exhaust gas flow violet dark blue - feed water and water injection to gas turbine M - mass flow in kg / s T - temperature in °C 9.8 p 259 T Page 6-40 March 2008 168 2.323 p 125 T 4.075 M 195.1 M 168 IPB 20 T 200 260 11.1 p 11.1 p 181 T 184 T 195.1 M 45.02 M IPE2 LNG 12.32 m LHV= 164714 kWth 17.75 p 411 T HPE2 16.95 p 1178 T 260 282 95.24 p 233 T 149.6 M 1X ALS GT8C2 HPE3 285 319 10.88 p 93.2 p 229 T 301 T 40.97 M149.6 M IPS1 HPB1 321 2 X GT 1.04 p 514 T 1414.4 M 87 p 492 T 148.2 M 453 10.67 p 93.2 p 260 T 306 T 40.97 M148.2 M IPS2 55470 kW 707.2 m CCGT 2+1 configuration (refurbishment steam power plant), NG fired 100% load at winter conditions 453 512 FW 2.196 m^3/kg 862.8 m^3/s 512 T 1414.4 M 34 T 0.0511 M 90.05 p 495 T 148.2 M HPS3 40.97 M 0.0543 p 34 T 189.1 M 53513 kW 75.42 %N2 14.3 %O2 3.205 %CO2 6.17 %H2O 0.9081 %Ar Net Power 161209 kW LHV Heat Rate 7357 kJ/kWh Figure 6-16: Heat and Mass Balance – Gas-Based Generation Option 3 (Winter Conditions) p[bar], T[C], M[t/h], Steam Properties: IAPWS-IF97 316 08-21-2007 13:51:14 file=T:\26\0400\260442_malta\06_project_results\GTPro\Case 3 (2+1) refurbishment 60MW ST\CCGT 2+1 REFURBISHMENT ST NG FIRED 100% load at winter condi 1.144 m^3/kg 449.3 m^3/s LTE 2.323 p 114 T 191.1 M 125 T 1414.4 M 114 T 34 T 191.1 M 1p 13 T 694.9 m GT MASTER 17.0.1 LI - W. Eisenhart 1.01 p 13 T 45 %RH 694.9 m 90.05 p 495 T LI 260442 Final Report – Work Package IIA Energy Interconnection Europe - Malta MALTA RESOURCES AUTHORITY Colours: Abbreviation: - high pressure steam red light blue - intermediate pressure steam p - pressure in bar - gas, air and exhaust gas flow violet dark blue - feed water and water injection to gas turbine M - mass flow in kg / s T - temperature in °C 9.979 p 258 T Page 6-41 March 2008 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 6.5.2 Location Figure 6-17 shows the location of the existing steam turbines and boilers at the Delimara Power Station site, which is also the location of the proposed refurbishment measure. LI 260442 Page 6-42 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Figure 6-17: Potential Location of Gas-Based Generation Option 3 In the following more details of the unit’s geometry are provided. The first two drawings depict the gas turbine package (Figure 6-19). The total length of the package is calculated at approx. 22 meters. The width of one package is calculated at approx. 5 meters. Figure 6-20 shows the geometry of the heat recovery steam generator. The total length amounts to some 27 meters. The width of one HRSG amounts to 7 meters. Summarizing the dimension of the plant’s components the below figure provides a suggestion regarding the arrangement of the required two HRSGs and two GTs. As the result a square of 27 x 27 meters is calculated and considered as realizable. HRSG GT GT approx. 27 m HRSG approx. 27 m Figure 6-18: Suggestion regarding the Formation of HRSGs and GTs LI 260442 Page 6-43 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 1 2 FOR QUALITATIVE INDICATION ONLY 3 4 5 6 7 8 A A E B B C C A D D B C D E E Thermoflow, Inc. Company: Lahmeyer International GmbH User: LI - W. Eisenhart SHAPE, DIMENSIONS & SCALE ARE APPROXIMATE GAS TURBINE PACKAGE ELEVATION A B C D E F G H I J Date: 11.12.07 F GE 6561B 133 F Drawing No: 11.4 m 3.4 m 6.5 m 1 4.4 m 11.6 m 2 - - 3 - - - 4 C:\TFLOW17\MYFILES\GTMAS.GTM 5 6 7 8 PEACE/GT MASTER 17.0.2 1 2 FOR QUALITATIVE INDICATION ONLY 3 4 5 6 7 8 A A B B A C C D C B D D E E Thermoflow, Inc. Company: Lahmeyer International GmbH User: LI - W. Eisenhart SHAPE, DIMENSIONS & SCALE ARE APPROXIMATE GAS TURBINE PACKAGE PLAN A B C D E F G H I J Date: 11.12.07 F GE 6561B 133 F Drawing No: 3.4 m 21.9 m 1 2.5 m 2.6 m 2 - 3 - 4 - 5 C:\TFLOW17\MYFILES\GTMAS.GTM 6 7 8 Figure 6-19: Dimensions of one GT Package LI 260442 Page 6-44 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 1 2 FOR QUALITATIVE INDICATION ONLY 3 4 5 6 7 8 A A B B C C F G D D H E E A C D E Thermoflow, Inc. Company: Lahmeyer International GmbH User: LI - W. Eisenhart HEAT RECOVERY STEAM GENERATOR ELEVATION A B C D E F G H I J Date: 11.12.07 F F Drawing No: 5m - 7.1 m 1 10.9 m 2.1 m 2 22.2 m 12.1 m 3 2.7 m - 4 - C:\TFLOW17\MYFILES\GTMAS.GTM 5 6 7 8 PEACE/GT MASTER 17.0.2 1 2 FOR QUALITATIVE INDICATION ONLY 3 4 5 6 7 8 A A B B G F C C A C D E D D E E Thermoflow, Inc. Company: Lahmeyer International GmbH User: LI - W. Eisenhart HEAT RECOVERY STEAM GENERATOR PLAN A B C D E F G H I J Date: 11.12.07 F F Drawing No: 5m 1 7.1 m 10.9 m 2 2.1 m 3.7 m 3 3.1 m 4 - 5 C:\TFLOW17\MYFILES\GTMAS.GTM 6 7 8 PEACE/GT MASTER 17.0.2 Figure 6-20: Dimensions of one HRSG LI 260442 Page 6-45 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 6.5.3 Air Pollution Emissions The legal frame and the National targets for local generation options are explained in detail in section 6.1.3. In the following tables the environmental impact due to potential air pollution emissions is presented. The air pollution emissions of the investigated supply option: x x x do not exceed the limit value for NOx emissions; do not exceed the limit value for SO2 emissions. Natural gas does not cause such emissions at all; are 56% below the current Green House Gas emissions (typical unit operation assumed) and do not exceed the limit value for CO2 emissions. Specific Emissions g CO2/kWh . 1,000 900 800 921 871 700 600 500 400 420 300 200 100 Business as Usual (all STs) Business as Usual (DPS ST) Supply Option Figure 6-21: Comparison of Greenhouse Gas Emissions - Gas-Based Generation Option 3 LI 260442 Page 6-46 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA General Information # Item 3 1 Plant Name Natural Gas Based Supply Option 3 (Refurbishment) 2 Plant Type Combined Cycle Gas Turbine 3 Unit CCGT 2+1 NG fired 4 State Option 5 Unit_Ident 6 Comments No Comments Technical & Operational Data for Emissions (continued) # Item Dim 3 7 Nominal Capacity MW 162.9 8 Max Capacity Sent-Out (Operation) MW 159.6 9 Min Capacity Sent-Out (Operation) MW 38.6 10 Heat Rate* Coeff A (2+1) - 3,764 11 Heat Rate* Coeff B (2+1) - -7,944 12 Heat Rate* Coeff C (2+1) - 11,566 5000 kJ / kWh 10000 0 18,027 11a Heat Rate* Coeff B (1+1) -18,884 12a Heat Rate* Coeff C (1+1) 12,381 13 Combustion Temp Coeff A - -742 14 Combustion Temp Coeff B - 1,579 15 Combustion Temp Coeff C - 485 16 Air Rate Lambda O Case1 20% 30% 40% 50% 60% 70% 80% 90% 100% 1400 1300 [comb. temp.] 10a Heat Rate* Coeff A (1+1) 10% 1200 1100 1000 900 800 700 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 1.0 - 1.09 Table 6-17: Specifications of D_CC3NGo (1/3) LI 260442 Page 6-47 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA NOx Emissions # Item 3 17 Thermal Nox Coeff. A 1E-21 Fuel Nox Coeff. A NA 18 Thermal Nox Coeff. B 7.72 Fuel Nox Coeff. B NA Fuel Nox Coeff. C NA 19 Fuel NOx Emissions over load (RAW) 20 Thermal NOx Emissions over load (RAW) mg/m³ mg/m³ mg/m³ 1,200 1,200 1,200 1,000 1,000 1,000 800 800 800 600 600 600 400 400 200 2000 400 200 0 0 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 0 21 Specific NOx Emissions in g/kWh [g/kWh] 1.20 kg Nox RAW 2.0 1.00 350 300 0.80 1.5 0.60 1.0 0.40 0.5 0.0 20% 30% 40% 50% 60% 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Absolute NOx Emissions in tons 2.5 10% 0 70% 80% 0.20 50 0.00 0 90% 322 255 300 250 250 200 200 150 150 100 100 199 158 80.0 100.0 60.0 134 107 9 7 16 13 28 22 33 26 53 42 49 38 78 63 65 51 96 76 81 64 80 64 98 77 114 90 130 102 200.0 140.0 120.0 150.0 100.0 265 211 147 115 163 128 40.0 50.0 20.0 0.0 Fuel Specifications 22 Initial Primary Fuel Rich gas 23 Net Calorific Value kJ/kg 48,156 24 Required Fuel at 100% load kg 24,985 25 Required Combustion Air m³ 9.89 % of Carbon Natural Gas Fuel Composition % of Nitrogen (Emission Relevant) 75.00% 0.00% % of Sulphur 0.00% % of Nox Reduc. 50.00% % of SO2 Reduc. 0.00% Potential Emission Reduction 26 Resulting Exhaust Gas m³ 10.34 Table 6-15: Specifications of D_CC3NGo (2/3) LI 260442 Page 6-48 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA CO2 and SOx Emissions # Item 3 27 Fuel needed at 100% load t 24.99 28 Density of Fuel 29 CO2 emission at 100% load 30 Specific CO2 Emissions in g/kWh kg / m³ 0.77 t 67.38 Absolute CO2 Emissions in t [t CO2] [g/kWh] 80 70 60 50 40 30 20 10 0 800 598 594 600 525 522 474 467 439 432 422 417 462 457 446 440 433 427 423 418 417 414 400 200 0 17.0 20% 30% 40% 50% 60% 70% 80% 90% 22.8 28.1 50.1 61.3 67.4 34.0 9.7 16 10% 31 44.6 55.6 33 49 65 100% 81 98 114 130 147 163 [MW] Specific SOx Emissions in g/kWh Absolute SOx Emissions in tons n/a n/a Exhaust Gas development in m³ due to Gross Performance m³ Exhaust Gas 32 300,000 250,000 250,000 200,000 200,000 150,000 150,000 100,000 100,000 50,000 50,000 171,072 135,795 65,209 51,499 87,460 69,655 107,851 86,115 192,117 152,889 213,135 169,723 234,914 186,792 258,244 204,592 130,165 103,402 37,316 29,123 0 10% 0 20% 0 30% 0 40% 0 50% 0 60% 0 70% 0 80% 0 90% 0 100% 0 Table 6-15: Specifications of D_CC3NGo (3/3) LI 260442 Page 6-49 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 6.6 Economic Description of Gas-Based Generation Option 3 (2+1 ST R) 6.6.1 Investment Costs of Major Components Under consideration of the project’s implementation plan (already described in section 6.2.1) and taking into account the already existing components, an implementation duration of two years is estimated. The investment cost’s disbursement schedule is shown in Table 6-19. The lifetime of the supply option 3 is related to the remaining lifetime of the existing steam turbine which is estimated at 15 years (see Table 1-8 Specifications of D_ST1e). The investment cost in total and for each individual major component is provided in Table 6-18. In total, the projects investment cost amounts to 88.1 Mio Euro (10% contingencies included). Investment Costs in T EUR # Item 1 Gas Turbine Package incl. Generator 32,792 2 Heat Recovery Boiler 17,027 3 Balance of Plant 6,576 4 Electrical Equipment 7,289 5 I&C Equipment 1,430 6 Civil/Buildings incl. On-Site Transportation 8,332 7 Engineering 2,933 8 Plant Startup 9 Contractor's Soft Costs 10,926 Total: 88,063 758 Table 6-18: Investment Costs of Gas-Based Generation Option 3 LI 260442 Page 6-50 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Year n-2 n-1 n Disbursement in % 60% 40% Start Year Table 6-19: Disbursement Schedule of Gas-Based Generation Option 3 The specific investment cost amounts to 552 EUR/kW, approximately 23% less compared to the gas-based generation option 1, respectively 17% less compared to the gas-based generation option 2. Figure 6-22 illustrates the investment break down. The dominating cost proportions are (i) the gas turbine package; (ii) the heat recovery boiler; (iii) soft costs of the contractor and (iv) the civil works. 8% 2% Gas Turbine Package incl. Generator and Air inlet cooling/heating if applicable 9% 3% Heat Recovery Boiler 1% 7% Balance of Plant 12% Electrical Equipment I&C Equipment 19% Civil/Buildings incl. On-Site Transportation Engineering Plant Startup 37% Contractor's Soft Costs Figure 6-22: Investment Cost Break Down of Gas-Based Generation Option 3 LI 260442 Page 6-51 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 6.6.2 Operational and Maintenance Costs Gas Supply Costs Estimation As the result of the assessments in the chapters 1 to 5 the development of the costs of the supply of gas to the power plant is presented in the below Table. The year 2011 is selected as the first possible year of the plant’s operation. This assumption takes into account the project’s schedule given in the previous section. Item Fuel Supply Costs (via LNG conversion) Item Fuel Supply Costs (via LNG conversion) Unit 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 EUR/t 204.4 197.7 191.0 191.0 191.0 191.0 194.4 197.7 201.0 201.0 Unit 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 EUR/t 204.4 207.7 211.0 214.4 216.0 217.7 217.7 219.4 219.4 221.0 Table 6-20: Gas Supply Costs Fixed O&M Costs Fixed costs of operation and maintenance include expenses for staff salaries; insurance, fees and other cost which remain constant irrespective of the actual quantum of the plant’s electrical energy sent-out. The personnel costs are calculated by the estimated number of additionally required staff (10 employees) and the average annual salary (30 T EUR/a). Based on experiences in similar assignments the proportion of the remaining fixed operation and maintenance costs is 2.5% of the capital costs. . # Item 1 Personnel Costs 2 Insurance, Fees and Others 2,202 Total Annual Fixed OPEX: 2,502 Costs in T EUR/a 300 Table 6-21: Estimate of Annual Fixed OPEX LI 260442 Page 6-52 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Variable O&M Costs Variable costs of operation and maintenance include the cost of fuel and costs for e.g. lubricating oil and chemicals which are consumed in proportion to the actual amount of the plant’s electrical energy sent-out. The dominating proportion of the variable OPEX is the cost of fuel, which depends on the fuel supply cost and the amount of fuel utilized. The latter item again depends on the plant’s efficiency and further on the plant’s operation mode (e.g. full load or partial load; number of turbines in operation). In the first section of this chapter the plant’s performance parameters are described in detail. The following economic analysis considers individual operation modes and the related specific fuel input. Based on our experience in similar assignment the value of the remaining variable OPEX is estimated at 4.0 EUR/MWh. 6.6.3 Dynamic Unit Cost Assessment for Option 3 The following chart provides the calculation of the dynamic unit cost of the gas-based local generation option 3. As far as the actual future operation of the plant is not known (this depends mainly on the most economic dispatch of the unit as one component of the entire power generation system; see Work Package III) we provide cost figures over the entire load range. Exemplarily the calculation in the chart is based on an 85% load assumption. Nevertheless, the results are shown for different operation modes from full load to partial load. Furthermore, the DUC trends are illustrated in Figure 6-23. Regarding the expected annual net generation the option’s maximum availability of 88.8% is taken into consideration in the 100% full load case. In the selected 85% load case the DUC of the gas-based local generation option 3 amounts to 52.2 EUR/MWh. Fluctuations of the DUC are observed within the plant’s base load operation. In full load operation the DUC are 2% lower than the reference value. At 70% load level the DUC are 11% higher than the reference value. In intermediate and peak load operation (1 GT + 1 ST mode, and 1 GT mode respectively) the cost figures increase rapidly. At 50%-load an increase by 24% and at 20%-load an increase by 150% is registered in comparison to the reference value. The plant’s maximum annual net generation amounts to 794 GWh/a (at maximum availability and full load). This quantum considers exclusively the additionality of the repowering measure. LI 260442 Page 6-53 LI 260442 50% 81.3 79.2 2.1 2.5% 30% 47.7 45.9 1.8 3.8% 20% 33.8 33.4 0.4 1.2% EUR/t T EUR/a t/a GWh/a Fuel Supply Costs (specific) Fuel Supply Costs (absolute) Fuel Input Net Generation (minus exisitng) DUC - Power Generation 4 Dynamic Unit Cost Capital OPEX Net Generation (minus exisitng) EUR/MWh Partial Load T EUR T EUR GWh T EUR/a Variable OPEX 3 Present Value T EUR/a Fixed OPEX Year >> T EUR/a kJ/kWh d/a %/a %/a 135 7 52.2 85% 51.4 159 6 0 0 0 0 0 0 52,838 n-2 70% 7,897 58.2 111 8 70% 0 0 0 0 0 0 35,225 n-1 50% 7,436 2GT+1ST 1GT+1ST 100% 97,445 274,065 7,116 0 0 0 0 0 0 0 n-3 85% 7,537 100% 7,377 30 3% 88.8% Investment Cost Item 2 Cash Flow Net Heat Rate Planned Outage Forced Outage Max Availability 2GT+1ST 2GT+1ST 64.9 79 8 50% 204 24,212 118,467 757 27,239 2,502 0 1 30% 8,422 1GT+1ST 90.0 47 9 30% 198 23,422 118,467 757 26,449 2,502 0 2 20% 12,874 1GT 3 131.1 31 9 20% 191 22,632 118,467 757 25,660 2,502 0 191 22,632 118,467 757 25,660 2,502 0 4 191 22,632 118,467 757 25,660 2,502 0 5 * other than Fuel Costs 201 23,817 118,467 757 26,844 2,502 0 10 2,502 4.0 Regas LNG 48,150 88,063 6.5% 15 2 208 24,606 118,467 757 27,634 2,502 0 12 216 25,593 118,467 757 28,621 2,502 0 15 Operation at 85% Load kJ/kg -- T EUR/a EUR/MWh 70% 111.5 108.7 2.9 2.6% Fixed OPEX Variable OPEX* Fuel Type Net Calorific Value 85% 139.1 136.0 3.1 2.2% T EUR % a a MW MW MW % -- CCGT 2+1 162.9 100% 162.9 159.6 3.2 2.0% Total Investment Discount Rate Lifetime Construction Period -MW Local Generation Option 3 (CCGT 2+1 ST R) Plant Type Set Size (nominal) Partial Load Set Capacity (gross) Set Capacity (net) Auxiliary Power Self Consumption Turbines in Operation p 1.2 Economics General Information 1.1 Technical 1 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Table 6-22: Dynamic Unit Cost of the Gas-Based Option 3 Page 6-54 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Dynamic Unit Cost EUR/MWh 140 120 100 80 60 40 20 0 20.0 40.0 60.0 80.0 100.0 120.0 140.0 160.0 Plant's Operation - Load (Net) in MW 140 1,400 120 1,200 100 1,000 80 800 60 600 40 400 20 200 0 10% Plant's Net Generation in GWh/a Dynamic Unit Cost EUR/MWh - 20% 30% 40% 50% 60% 70% 80% 90% 100% Plant's Operation as Percentage of Load Figure 6-23: Dynamic Unit Cost over Plant’s Load – Gas-Based Option 3 LI 260442 Page 6-55 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 6.7 Technical Description of Gas-Based Generation Option 4 (2+1 GT R) 6.7.1 Basic Design This supply option one deals with the re-powering of the two existing GTs at the Delimara Power Station site. The specifications of these turbines are provided in Table 1.12 (Specifications of D_GT1e) and respectively Table 1.13 (Specifications of D_GT2e). Except the consideration of two already existing (former) open cycle gas turbines, the general layout of the combined cycle plant is comparable to that one described in detail in the chapter “Technical Description of the Gas-Based Generation Option 1 (CCGT 2+1)”. The gas turbines are designed with a dual fuel combustion system using LNG (gaseous) as primary fuel. As the result of the refurbishment, the design capacity of the gas turbines amounts to 38 MW (Net) each. The design capacity of the steam turbine is 38.5 MW (Net). For the cooling system an open loop water cooling with a seawater inlet temperature of 20 °C and an allowable cooling water temperature rise of 8 K is assumed. Plant Characteristics Unit Plant Type Set Size (nominal) Value CCGT 2+1 MW Partial Load 117.8 100% 85% 75% 50% 30% 20% Set Capacity (gross) MW 117.8 99.6 87.4 58.6 36.4 23.5 Set Capacity (net) MW 115.3 97.2 85.1 56.9 34.9 23.2 Auxiliary Power MW 2.5 2.4 2.3 1.7 1.5 0.3 % 2.1% 2.4% 2.6% 2.8% 4.1% 1.2% 2GT+1ST 2GT+1ST 2GT+1ST 1GT+1ST 1GT+1ST 1GT Partial Load 100% 85% 75% 50% 30% 20% kJ/kWh 7,513 7,599 7,847 7,606 8,551 12,911 Planned Outage d/a 20 Forced Outage %/a 3% Max Availability %/a 91.5% Self Consumption Turbines in Operation Net Heat Rate Table 6-23: Technical Data – Gas-Based Generation Option 4 LI 260442 Page 6-56 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA The heat recovery steam generators (HRSG) are equipped with a bypass stack for simple cycle operation of the gas turbines in order to increase the operational flexibility of the plant. Most important for the steam cycle efficiency is the HRSG configuration and design. Both HRSG produce in total 32.6 kg / s high pressure steam with 67.95 bar and 518 °C and an intermediate pressure steam of 5.82 kg / s with 8.3 bar and 259 °C. Table 6-23 provides the general technical parameters of the supply option 4 (design conditions). A partial load range between 100% (full load) and 20% is selected regarding the provision of the operational characteristics, which can be summarized as follows: x x The plant’s self consumption (auxiliary power) drops from 2.5 MW to 0.3 MW in absolute terms. Related to the plants output the value increases from 2.1% (2 GT + 1 ST operation) to 4.1% (1 GT + 1 ST operation) and decreases then to some 1.2% (1 GT operation); The plant’s net heat rate increases from 7,513 kJ/kWh to nearly 13,000 kJ/kWh over the entire range of partial load. This is equal to a net efficiency decrease from 47.9% to 27.9%. Assuming outage characteristics of an average of 20 days a year for the units’ maintenance and a 3% forced outage, the maximum availability of the plant is expected to amount 91.5% over a year. The net and gross heat rates of the gas based supply option 4 are shown in the following figure over the entire load range (calculated on fuel’s NCV). The results of GT Pro calculations are summarized within the heat and mass balance diagrams in the Figures 6-25 and 6-26. The calculations are based on the maximum load of the plant during summer and winter conditions. The comparison of the summer and winter parameters brings out the following results: x x The plant’s net capacity during summer amounts to only 87% (102.0 MW) compared to the net capacity during the winter period by some 116.8 MW. Our analysis of the existing system already brought out similar capacity levels in relation to the temperature fluctuations in Malta (see work package I); The plants’ net heat rate decreases from 7,650 kJ/kWh during summer to 7,484 kJ/kWh during winter. This is equal to a net efficiency increase from 47.1% (summer) to 48.1% (winter). As mentioned at the beginning of this section, the configuration of this gas-based generation option number 4 is very similar to the configuration of the new CCGT evaluated as gas-based generation option number 1. The comparison of the net efficiencies between both alternatives provides only a slight derating of the efficiency by 0.5 %-points. LI 260442 Page 6-57 LI 260442 0 2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 0 20,000 40,000 80,000 Load (kW) 60,000 100,000 120,000 2+1 gross HR 2+1 net HR 1+1 gross HR 1+1 net HR 1+0 gross HR 1+0 net HR Heat Rates (kJ/kWh) of Supply Option 4 - 2+1 GT R NG fired 140,000 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Figure 6-24: Gross and Net Heat Rates – Gas-Based Generation Option 4 Page 6-58 Heat Rate (kJ/kWh) 161 2.323 p 116 T 139.7 M LTE 2.323 p 125 T 2.467 M 142.1 M 161 IPB 2.97 M 20 T 190 239 9.149 p 9.149 p 171 T 176 T 142.1 M 23.42 M IPE2 LNG 8.102 m LHV= 108352 kWth 10.76 p 368 T HPE2 10.33 p 1099 T 268 74.04 p 230 T 115.5 M 239 1X GE 6541B HPE3 271 301 8.981 p 72.73 p 228 T 282 T 20.96 M 115.5 M IPS1 HPB1 HPS0 1.51 M 67.95 p 518 T 117.3 M 1.04 p 558 T 907.8 M 2 X GT 302 473 484 8.843 p 72.73 p 72.05 p 261 T 288 T 309 T 20.96 M 114.4 M 114.4 M IPS2 32757 kW 453.9 m CCGT 2+1 configuration (refurbishment of single-cycle plant), NG fired 100% load at summer conditions 484 484 556 FW 2.358 m^3/kg 594.5 m^3/s 556 T 907.8 M 1.46 M 46 T 0.0372 M 70.32 p 535 T 115.8 M HPS3 20.96 M 0.1035 p 46 T 138.2 M 38875 kW 72.78 %N2 13.52 %O2 3.241 %CO2 9.581 %H2O 0.8764 %Ar Net Power 101978 kW LHV Heat Rate 7650 kJ/kWh Figure 6-25: Heat and Mass Balance – Gas-Based Generation Option 4 (Summer Conditions) p[bar], T[C], M[t/h], Steam Properties: IAPWS-IF97 316 08-29-2007 12:38:06 file=T:\26\0400\260442_malta\06_project_results\GTPro\Case 4 (2+1) refurbishment 2x37MW GT\NG fired\CCGT 2+1 REFURBISHMENT NG FIRED 100% load at summ 1.139 m^3/kg 287.3 m^3/s 119 T 907.8 M 116 T 46 T 139.7 M 1p 36 T 445.8 m GT MASTER 17.0.1 LI - W. Eisenhart 1.01 p 36 T 70 %RH 445.8 m 70.32 p 535 T LI 260442 Final Report – Work Package IIA Energy Interconnection Europe - Malta Colours: Abbreviation: - high pressure steam red light blue - intermediate pressure steam p - pressure in bar MALTA RESOURCES AUTHORITY - gas, air and exhaust gas flow violet dark blue - feed water and water injection to gas turbine M - mass flow in kg / s T - temperature in °C 8.331 p 259 T Page 6-59 March 2008 164 2.323 p 114 T 144.3 M LTE 2.323 p 125 T 1p 13 T 496.4 m 3.06 M 147.3 M 164 IPB 20 T 193 243 9.553 p 9.553 p 174 T 178 T 147.3 M 26.5 M IPE2 LNG 9.077 m LHV= 121387 kWth 11.93 p 354 T HPE2 11.45 p 1105 T 272 75.4 p 233 T 120.6 M 243 1X GE 6541B HPE3 275 303 9.355 p 73.98 p 229 T 285 T 23.43 M 120.6 M IPS1 HPB1 2 X GT HPS0 69.06 p 517 T 119.4 M 1.04 p 540 T 1010.9 M 305 466 476 9.192 p 73.98 p 73.26 p 261 T 290 T 309 T 23.43 M 119.4 M 119.4 M IPS2 38504 kW 505.4 m CCGT 2+1 configuration (refurbishment of single-cycle power plant), NG fired 100% load at winter conditions 476 476 538 FW 2.268 m^3/kg 636.8 m^3/s 538 T 1010.9 M 34 T 0.0384 M 71.48 p 519 T 119.4 M HPS3 23.43 M 0.0543 p 34 T 142.7 M 42275 kW 75.35 %N2 14.1 %O2 3.303 %CO2 6.34 %H2O 0.9073 %Ar Net Power 116781 kW LHV Heat Rate 7484 kJ/kWh Figure 6-26: Heat and Mass Balance – Gas-Based Generation Option 4 (Winter Conditions) p[bar], T[C], M[t/h], Steam Properties: IAPWS-IF97 316 08-29-2007 12:38:53 file=T:\26\0400\260442_malta\06_project_results\GTPro\Case 4 (2+1) refurbishment 2x37MW GT\NG fired\CCGT 2+1 REFURBISHMENT NG FIRED 100% load at winte 1.124 m^3/kg 315.7 m^3/s 118 T 1010.9 M 114 T 34 T 144.3 M 1.01 p 13 T 45 %RH 496.4 m GT MASTER 17.0.1 LI - W. Eisenhart 71.48 p 519 T LI 260442 Final Report – Work Package IIA Energy Interconnection Europe - Malta Colours: Abbreviation: - high pressure steam red light blue - intermediate pressure steam p - pressure in bar MALTA RESOURCES AUTHORITY - gas, air and exhaust gas flow violet dark blue - feed water and water injection to gas turbine M - mass flow in kg / s T - temperature in °C 8.604 p 259 T Page 6-60 March 2008 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 6.7.2 Location Figure 6-27 shows the location of the existing gas turbines at the Delimara Power Station site, which is also the location of the proposed re-powering measure. Figure 6-27: Potential Location of Gas-Based Generation Option 4 LI 260442 Page 6-62 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 6.7.3 Air Pollution Emissions The legal frame and the National targets are explained in detail in section 6.1.3. Calculations were carried out to demonstrate that the supply option 4 complies with the EU environmental directives and with all the relevant aspects of the Maltese Legislation. In the following tables the environmental impact due to potential air pollution emissions is presented. The air pollution emissions of the investigated supply option: x x x do not exceed the limit value for NOx emissions; do not exceed the limit value for SO2 emissions. Natural gas does not cause such emissions at all; are 53% below the current Green House Gas emissions (typical unit operation assumed) and do not exceed the limit value for CO2 emissions. Specific Emissions g CO2/kWh . 1,000 900 800 921 871 700 600 500 400 430 300 200 100 Business as Usual (all STs) Business as Usual (DPS ST) Supply Option Figure 6-28: Comparison of Greenhouse Gas Emissions - Gas-Based Generation Option 4 LI 260442 Page 6-63 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA General Information # Item 4 1 Plant Name Natural Gas Based Supply Option 4 (Refurbishment) 2 Plant Type Combined Cycle Gas Turbine 3 Unit CCGT 2+1 NG fired 4 State Option 5 Unit_Ident 6 Comments No Comments Technical & Operational Data for Emissions (continued) # Item Dim 4 7 Nominal Capacity MW 117.8 8 Max Capacity Sent-Out (Operation) MW 115.3 9 Min Capacity Sent-Out (Operation) MW 34.9 10 Heat Rate* Coeff A (2+1) - 6,725 11 Heat Rate* Coeff B (2+1) - -12,970 12 Heat Rate* Coeff C (2+1) - 13,748 5000 kJ / kWh 10000 0 28,344 11a Heat Rate* Coeff B (1+1) -27,591 12a Heat Rate* Coeff C (1+1) 14,312 13 Combustion Temp Coeff A - -742 14 Combustion Temp Coeff B - 1,579 15 Combustion Temp Coeff C - 485 16 Air Rate Lambda O Case1 20% 30% 40% 50% 60% 70% 80% 90% 100% 1400 1300 [comb. temp.] 10a Heat Rate* Coeff A (1+1) 10% 1200 1100 1000 900 800 700 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 1.0 - 1.09 Table 6-24: Specifications of D_CC4NGo (1/3) LI 260442 Page 6-64 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA NOx Emissions # Item 4 17 Thermal Nox Coeff. A 1E-21 Fuel Nox Coeff. A NA 18 Thermal Nox Coeff. B 7.72 Fuel Nox Coeff. B NA Fuel Nox Coeff. C NA 19 Fuel NOx Emissions over load (RAW) 20 Thermal NOx Emissions over load (RAW) mg/m³ mg/m³ mg/m³ 1,200 1,200 1,200 1,000 1,000 1,000 800 800 800 600 600 600 400 400 200 2000 400 200 0 0 0 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 0 21 Specific NOx Emissions in g/kWh [g/kWh] 1.20 1.00 0.90 1.00 0.80 0.70 0.80 0.60 0.60 0.50 0.40 0.40 0.30 2.0 1.5 1.0 0.20 0.20 0.10 0.00 0.5 0.0 20% 30% 40% 50% 60% 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Absolute NOx Emissions in tons 2.5 10% 0 0 70% 80% 90% kg Nox RAW 237 250 300 255 193 211 250 200 200 150 150 100 100 50 50 0 80.0 99 107 8 7 12 13 22 22 24 26 40 42 35 38 47 51 71 76 59 64 60.0 60 64 71 77 120.0 100.0 145 158 57 63 140.0 40.0 20.0 82 90 94 102 106 115 118 128 0.0 Fuel Specifications 22 Initial Primary Fuel Rich gas 23 Net Calorific Value kJ/kg 48,156 24 Required Fuel at 100% load kg 18,354 25 Required Combustion Air m³ 9.89 % of Carbon Natural Gas Fuel Composition % of Nitrogen (Emission Relevant) 75.00% 0.00% % of Sulphur 0.00% % of Nox Reduc. 50.00% % of SO2 Reduc. 0.00% Potential Emission Reduction 26 Resulting Exhaust Gas m³ 10.34 Table 6-20: Specifications of D_CC4NGo (2/3) LI 260442 Page 6-65 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA CO2 and SOx Emissions # Item 4 27 Fuel needed at 100% load t 18.35 28 Density of Fuel 29 CO2 emission at 100% load 30 Specific CO2 Emissions in g/kWh kg / m³ 0.77 t 49.50 Absolute CO2 Emissions in t [t CO2] [g/kWh] 60 800 663 594 600 49.5 50 556 525 481 474 437 439 426 422 470 462 40 446 430 433 421 423 420 417 33.2 30 400 20 200 10 17.0 20.6 44.7 25.1 7.8 0 0 12 10% 31 13.1 36.8 40.5 20% 30% 40% 50% 60% 70% 80% 90% 24 35 47 100% 59 71 82 94 106 118 [MW] Specific SOx Emissions in g/kWh Absolute SOx Emissions in tons n/a n/a Exhaust Gas development in m³ due to Gross Performance m³ Exhaust Gas 32 189,703 200,000 250,000 171,171 200,000 150,000 150,000 100,000 100,000 50,000 50,000 29,927 29,123 50,201 51,499 65,123 69,655 78,992 86,115 96,109 103,402 127,232 135,795 140,955 152,889 155,261 169,723 186,792 80% 0 90% 0 204,592 0 10% 0 20% 0 30% 0 40% 0 50% 0 60% 0 70% 0 100% 0 Table 6-20: Specifications of D_CC4NGo (3/3) LI 260442 Page 6-66 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA 6.8 Economic Description of Gas-Based Generation Option 4 (2+1 GT R) 6.8.1 Investment Costs of Major Components Under consideration of the project’s implementation plan (already described in section 6.2.1) and taking into account the already existing components, an implementation duration of two years is estimated. The investment cost’s disbursement schedule is shown in Table 6-26. The lifetime of the supply option 4 is related to the remaining lifetime of the existing gas turbines which is estimated at approximately 15 years (see Table 1.12 Specifications of D_GT1e respectively Table 1.13 Specifications of D_GT2e). The investment cost in total and for each individual major component is provided in Table 6-25. In total, the projects investment cost amounts to 54.4 Mio Euro (10% contingencies included). Investment Costs in T EUR # Item 1 Steam Turbine Package incl. Generator 2 Heat Recovery Boiler 3 Cooling Facility/Cooling System 4 Balance of Plant 5,893 5 Electrical Equipment 4,932 6 I&C Equipment 1,332 7 Civil/Buildings incl. On-Site Transportation 6,533 8 Engineering 2,510 9 Plant Startup 10 Contractor's Soft Costs 9,805 13,317 729 615 Total: 8,752 54,441 Table 6-25: Investment Costs of Gas-Based Generation Option 4 LI 260442 Page 6-67 MALTA RESOURCES AUTHORITY Energy Interconnection Europe - Malta March 2008 Final Report – Work Package IIA Year n-2 n-1 n Disbursement in % 60% 40% Start Year Table 6-26: Disbursement Schedule of Gas-Based Generation Option 4 The specific investment cost amounts to 472 EUR/kW, approximately 34% less compared to the Gas-Based Generation option 1, 29% less compared to the gas-based generation option 2, and respectively 14% less than the specific investment cost of supply option 3. Figure 6-29 illustrates the investment break down. The dominating cost proportions are (i) the heat recovery boiler; (ii) the steam turbine package; (iii) soft costs of the contractor and (iv) the civil works. 12% 5% Steam Turbine Package incl. Generator 1% 2% Heat Recovery Boiler Cooling Facility/Cooling System 9% 16% Balance of Plant Electrical Equipment 11% I&C Equipment Civil/Buildings incl. On-Site Transportation 1% 18% Engineering Plant Startup 24% Contractor's Soft Costs Figure 6-29: Investment Cost Break Down of Gas-Based Generation Option 4 LI 260442 Page 6-68
© Copyright 2026 Paperzz