Cutting Risk, Boosting Cash Flow and Developing Marginal Fields Terje Baustad Stavanger, Norway Increasingly, oil companies are seeking to minimize financial risk Guy Courtin SOEKOR E and P (Pty) Ltd. Cape Town, South Africa directly from a two-day well test to full-field development, operators Tim Davies Robert Kenison Jon Turnbull BP Exploration Operating Company Limited Aberdeen, Scotland Bob Gray Younes Jalali Jean-Claude Remondet Clamart, France Lars Hjelmsmark Cape Town, South Africa Tony Oldfield Christian Romano Ruben Saier Aberdeen, Scotland Geir Rannestad Statoil Stavanger, Norway For help in preparation of this article, thanks to Randy Hansen, Alistair Oag and Paul Wand, Anadrill, Aberdeen, Scotland; Dave Crowley and John Kozicz, Sedco Forex, Aberdeen, Scotland; Yves de Lavergne and Claude Massa, Schlumberger Wireline & Testing, Montrouge, France; Peter Montague, Dowell, Aberdeen, Scotland; Tom O’Rourke, GeoQuest, Aberdeen, Scotland; Graham Ritchie, Schlumberger Integrated Project Management, Aberdeen, Scotland; Gerald Smith and Bob Talbott, Schlumberger Wireline & Testing, Aberdeen, Scotland; and Kjell Ronaes, Schlumberger Wireline & Testing, Stavanger, Norway. BIGORANGE, Enerjet and MSR (Mud and Silt Remover) are marks of Schlumberger. 18 and accelerate return on investment. Lacking the confidence to go use extended well tests to deliver comprehensive, dynamic data and reduce economic uncertainty. When unwilling to wait for installation of conventional infrastructure, they are using low-cost, reusable production systems to speed up cash flow and cost-effectively bring marginal fields onstream. Many questions follow a hydrocarbon discovery. How much oil or gas is there; how much is recoverable; how fast can it be recovered; how much capital expenditure is required and what will be the return on investment? Answering these questions invokes a dilemma: Reservoir development may not proceed without assessment, but gaining adequate data for assessment requires some degree of development. Historically, well tests usually lasted less than a week, while time to first oil was measured in years. Development infrastructure built to specifications drawn up using welltest data often took dozens of months to build, install and commission. Yet when fields came onstream, production facilities sometimes proved inappropriate because reservoir performance and effluent characteristics differed vastly from what had been predicted. Today, smaller reservoirs and tighter economic conditions put operators under increasing pressure. Oil companies want to reduce exposure to financial risk by acquiring superior data, and need assets to quickly start paying their way. These requirements have changed the conventional order of field developments. Extended well tests (EWT) and early production systems (EPS) may be used to maximize data acquisition while minimizing development costs and generating cash flow. They allow commercial production and evaluation using dynamic data to be carried out simultaneously. A final development strategy may now be formulated using high-quality, dynamic production data from EWTs lasting up to 120 days. This reduces development risk and eliminates conservatism in facilities design (see “How Better Data Reduce Risk,” page 21). According to Jon Turnbull, Machar Team Leader, BP Exploration Operating Company Limited, “There can be a world of difference between developing a field on the back of a few days of well flow from a small number of wells, and observing production over a significant period of time.” Oilfield Review Then, even before any full-scale facilities are installed, an EPS may rapidly produce tens of millions of barrels of oil, cutting time to first oil to months or even weeks. In some cases, a marginal field may be developed for its entire life using low-cost facilities based on modular and reusable equipment. At their simplest, EWTs use standard, generally available well-test equipment upgraded for more rigorous safety and increased effluent treatment requirements. Well-testing technology has seen significant advances over the past 10 years, including high-technology drillstem test (DST) strings, environmentally clean burners to flare gas, and highly accurate, stable gauges. Perhaps one of the strongest incentives for these improvements has been the need to test high-pressure, hightemperature zones.1 For these critical wells, only equipment of the highest integrity may be used, and techniques like risk assessment and quality management have become increasingly necessary. If the well is not already completed, the first stage of an EWT must in effect complete the well. A packer is set to isolate the producing formation from wellbore fluid hydrostatic pressure. Downhole gauges measure pressure changes and a subsurface valve is used to shut in or flow the well. Rather than a production Christmas tree, EWTs frequently use DST well-control equipment. On surface, produced fluids are separated, treated and sampled, and stabilized oil is exported. Typically flowing for 30 to 120 days at rates of up to 30,000 BOPD [4770 m3/d]—high compared to the 5000 to 10,000 BOPD [800 to 1600 m3/d] achieved in a typical DST—some 10% of the contacted reservoir volume may be produced. Sale of produced oil will often cover EWT operating costs. 1. MacAndrew R, Parry N, Prieur J-M, Wiggelman J, Diggins E, Guicheney P, Cameron D and Stewart A: “Drilling and Testing Hot, High-Pressure Wells,” Oilfield Review 5, no. 2/3 (April/July 1993): 15-32. Winter 1996 19 Production Systems Modular Concept Full plant 20,000 to 70,000 BOPD Half plant 10,000 to 35,000 BOPD each Two-third plant 15,000 to 40,000 BOPD Production Systems Generic Package Black Oil Liquid Capacity: Oil: Water: Gas: Condensate Liquid Capacity: Oil: Water: Gas: Equipment: Options: Maximum 70,000 B/D Maximum 70,000 B/D 0 to 30,000 B/D 6 to 40 MMscf/D at 150 psi Minimum 20,000 B/D Minimum 120,000 B/D 0 to 15,000 B/D 50 to 150 MMscf/D at 600 psi Maximum 30 tons per skid First and second stage identical 72 in. by 20 in. 720 psi working pressure Third stage 96 in. by 25 in. 150 psi working pressure Pumping Series or parallel options Water treatment (cyclone or flotation) Gas compression (sized for specific project) Power generation ■Building blocks of Schlumberger Wireline & Testing standardized process plant. Twin, three-stage separator trains may be run in different configurations. Each train is capable of handling up to 35,000 BOPD [5565 m3/d], depending on effluent characteristics. Identical first and second stages are designed to handle flow surges of up to 20% above their capacity, while each of the two oversized third stages is able to process 80% of total plant capacity. For further flexibility when three-stage separation is not required, the standard plant may be reconfigured as three two-stage plants or two two-third plants. 20 Higher flow rates and longer production periods allow the reservoir pressure sink to be reached earlier and make boundaries more likely to be seen than with a short DST. To handle these higher rates, EWT process equipment must be more efficient than the production hardware used in standard tests to allow not only phase separation and measurement, but also the export of oil with commercial characteristics. In many cases, testing and early production projects require equipment that has more stringent specifications than typical well-testing process and control hardware. At the heart of such projects is the need for a flexible, economical way of evaluating reservoir potential. Schlumberger Wireline & Testing employs standardized modules and components to deliver this flexibility, allowing rapid mobilization of EWT and EPS equipment as well as fast-track development of marginal fields (left). Predesign and advance engineering accelerate delivery of equipment that traditionally has long lead times—sometimes more than a year. Additionally, to allow rapid response to emergencies or projects with short lead times, standard and reusable components are kept in stock. Standardization also reduces maintenance costs and improves reliability. After initial installation, capacity and process capability may be easily modified to fit changing reservoir requirements. Although components may be standardized, the way they fit together cannot be standard. For each well or reservoir, process engineers look at fluid composition and production criteria, and feed this information into a simulator to optimize setup and meet specific gas, water, power generation, loading and export requirements.2 After decommissioning, separators, heaters and pumps can be reconfigured to service another reservoir. To illustrate the scope of EWT, EPS and marginal field development techniques, this article looks at three case studies selected from more than 40 projects undertaken by Schlumberger Oilfield Services product lines since the 1970s. In each case, production systems technology has been deployed to deliver superior data, early oil, or both, thus reducing financial risk and delivering rapid cash flow to oil companies. Although these techniques are equally appropriate for onshore or offshore fields, the examples discussed here are all offshore projects, where higher risk promotes greater teamwork and cooperation overall. Oilfield Review How Better Data Reduce Risk 20 km N 12.5 miles Mungo Monan Cruden Bay At its most basic level, a conventional production test allows “back-of-the-envelope” calculations Aberdeen Marnock Lomond that attribute total production to expansion of the Mirren oil in place: NORTH SEA Skua Teeside production = compressibility × oil-in-place × pressure depletion. Medan Egret Heron Scoter Pierce This can be regarded only as an order-of-magni- Machar UK Cod simple production-equals-expansion assumption, Shearwater Elgin Erskine a value for the compressibility of the total system—acquired through extensive pressure-vol- Fields under development Franklin ETAP fields Other fields/discoveries tude estimate. To fine-tune this result using the ume-temperature (PVT) experiments and core 30/2a-J analysis—and accurate pressure depletion data Puffin High-pressure, hightemperature fields 30/1c 2a-T Blane are required. To be useful, a test must record a drop in reservoir pressure during production. The bigger the field, the greater the volume of production necessary to deliver a significant pressure drop and the longer the test. However, this production-equals-expansion ■BP Machar field North Sea location. model is not appropriate if the reservoir has an active aquifer, expanding gas cap, or other compli- Machar EWT/EPS, UK North Sea In some cases, it is hard to distinguish where an EWT operation ends and an EPS begins. A good example is the Machar field operated by BP Exploration Operating Company Limited in the UK North Sea (above).3 The Machar field is a carbonate reservoir overlying a salt diapir, where a salt dome has pushed up creating a steeply dipping, dual-porosity, fractured chalk formation with oil contained in the tight matrix, but produced from natural fractures (next page). Discovered in 1972, the field had uncertain commercial prospects until 1994, when a two-phase appraisal project was initiated. Phase one was designed to test deliverability of the reservoir. It involved an EWT that used two existing wells to prove that sufficient economic reserves could be produced by natural drive. BP awarded an integrated services contract for the Machar test and production system to Coflexip Stena Offshore, Sedco Forex, Schlumberger Wireline & Testing and Schlumberger Integrated Project Management—the TAP (Turnkey Additional Production) alliance of companies.4 2. For a review of reservoir simulation: Adamson G, Crick M, Gane B, Gurpinar O, Hardiman J and Ponting D: “Simulation Throughout the Life of a Reservoir,” Oilfield Review 8, no. 2 (Summer 1996): 16-27. 3. An EPS is distinguished from an EWT in the UK because it requires a Field Development Plan and Production Consent from the UK Department of Trade and Industry. This requires operators to demonstrate long-term plans for the field and for maximizing production. On this basis, Machar was an EPS. However, the main objective was to gather significant dynamic data to help make the field developable. Newly developed jargon might call the Machar project an extended appraisal test (EAT) because the amount of oil produced exceeded that usually associated with an EWT—up to about 4 million barrels—and it involved more than one well. Nevertheless, the prime objective of either an EWT or EAT remains the same: to clarify reservoir uncertainties and confirm the field development model. 4. In the TAP alliance, Coflexip Stena Offshore charters the loading tanker and provides the flexible export riser; Sedco Forex provides the rig, drilling services and all well logistics; Schlumberger Wireline & Testing provides completion, production and testing services; and Schlumberger Integrated Project Management provides well engineering and well construction management services. Chafcouloff S, Michel G, Trice M, Clark G, Cosad C and Forbes K: “Integrated Services,” Oilfield Review 7, no. 2 (Summer 1995): 11-25. cated drive mechanisms. One way of taking these factors into consideration is to perform material balance calculations that integrate production history, pressure history and PVT properties from extended well tests and early production systems to give bulk estimates of oil in place. These calculations will not take into account such issues as segmentation of the reservoir into distinct flow units, stratification of each flow unit into various layers, or the impact of water injection on recovery. To address these factors, a preliminary reservoir model must be constructed that approximates the production history of the field. This working simulation of the reservoir may be constructed at an early stage only with the availability of continuous bottomhole pressure data from wells that is supplied by an EWT or EPS. After this, recoverable reserves may begin to be calculated and the full-scale development strategy—in terms of number and type of wells, and process facilities needed—can be formulated. In the past, a paucity of data led to over-conservative platform and facility designs capable of handling the most extreme, worse-case situations for a reservoir. By better understanding likely reservoir needs, facilities may be scaled down and development costs can be reduced. Winter 1996 21 1400 Well 10 1600 Well 10Z ■How Machar reservoir drapes over the salt diapir. The Machar structure, most of the well locations and the target for the new well—designated 23/16a-20—are shown with respect to previously drilled Well 3/16a-10, sidetrack 10Z, and the subsurface (top right). Not shown are natural fractures that made the location of wells so difficult. The steep dips of the diapir with respect to the salt dome (middle) are also shown along with a plan view of the reservoir (bottom). Target for Well 20 Top Sandstone: 1800 m TVDSS Top Ekofisk: 1830 m TVDSS Top Tor: 1850 m TVDSS Total vertical depth subsea (TVDSS), m 1800 2000 TD: 2250 m TVDSS Sandstone 2200 Well 2 2400 2600 Ekofisk Hole angle: 51° Azimuth: 287° 2800 Faults Fault Tor 500 m 3000 1640 ft Hod 3200 Salt dome Sandstone Ekofisk 500 m 1640 ft 3000 2800 2600 Tor Hod 2400 2200 2000 1800 1600 1400 1800 2400 2600 Chalk and sand Sand only No reservoir 2800 3000 TVDSS, m 1 km 0.625 miles 22 Oilfield Review Sedco 707 semisubmersible Dynamically positioned storage and shuttle tanker Flexible 6-in. export flowline 1 mile [1.6 km] Rigid production riser 23 ft [7 m] Jumper flowline ■Delivering data and early production from Machar. The Sedco 707 semisubmersible rig with full processing and water-injection facilities was located over the Machar wells. Oil was exported via a 1-mile [1.6-km] long flexible subsea pipeline to the dynamically positioned storage and shuttle tanker Stena Savonita, which, when full, transported oil to the terminal at Tetney, England. True to the objectives of integrated services, this contract included significant scope for sharing risk and reward between BP and the TAP companies (see “Machar Risk and Reward,” next page). A modular facility offering two-stage gasoil separation with pumping and metering to a quick-disconnect export line was designed, prefabricated and installed on the Sedco 707 semisubmersible rig. Oil was exported via a 1-mile [1.6-km] long flexible subsea pipeline to the dynamically positioned storage and shuttle tanker Stena Savonita, which transported oil to the Tetney terminal, England (above). Process equipment added some 220 tons [223,500 kg] to the rig deckload, so underdeck stiffening was required (right).5 The rig was moved onto location in March 1994. New production equipment was installed and commissioned while the rig was recompleting the two existing, but suspended wells—designated 23/26a-6Y and 23/26a-18Z—that would be used for phase one production. Installation took about two months, with 15% of project costs saved by not using a shipyard. Because of the size and flexibility of the 700-series semisubmersible, there was no problem locating new equipment on the deck. The only limiting factor during hookup was capacity of the living quarters. Electrical and instrumentation hookup was the most complicated part. In all, nearly 18 miles [30 km] of cable was needed to link the rig command-and-control system with the new equipment. Such was the speed of the design and installation of facilities that first oil flowed 5. Oldfield GA: “Early Production System for the UK North Sea,” presented at the 9th International Floating Production Systems Conference, Genoa, Italy, May 25-27, 1994. ■Machar EWT/EPS. The Sedco 707 semisubmersible and Stena Savonita storage tanker at work in the Machar field. Winter 1996 23 Machar Risk and Reward According to Jon Turnbull, Machar Team Leader, For phase two—water injection—the risk and BP Exploration Operating Company Limited, BP reward structure was slightly modified to reflect has long wrestled with the difficulty of aligning the changed objectives. The efficiency and production goals of contractors with its own. The central prob- elements were combined into a single measure to lem is that the operator’s costs are the contractors’ reflect average daily production. However, to qual- revenue. Any cost-saving initiatives reduce the ify for reward payment, TAP had to achieve a mini- contractors’ revenue, while the operator pays the mum water-injection ratio. penalties in cost overruns if things go awry. One way of overcoming this is to develop a pay- The results of both phase one and two exceeded BP’s expectations and significant reward payments ment mechanism so that the contractor shares in were made to TAP. The mechanisms ensured that the rewards of a successful project, and similarly BP gains in cost savings were greater than the shares in the penalty of failure. The rationale for reward payments. A bigger question is whether the developing such a mechanism is to change the incentives changed the behavior of the people behavior of those who are actively involved in a involved in the project—compared to how they project or operation so that they are focused on a would have acted under a conventional contract. successful outcome. The Machar EPS was an ideal candidate for this Jon Turnbull is convinced that the incentive contract did change the way people acted, but not on its approach since it involved the cooperation of a own. “In order to be effective, the contract had to be number of major organizations in the Turnkey reinforced by appropriate behavior, awareness and Additional Production (TAP) alliance—Coflexip understanding,” said Turnbull. “In addition, it was Stena Offshore, Sedco Forex, Schlumberger Wire- vital that an element of the reward was paid to the line & Testing and Schlumberger Integrated Pro- individuals who made the project successful.” ject Management—in a single project with clear objectives and readily measurable deliverables. For phase one—natural depletion—a risk and reward mechanism was constructed, based on overall efficiency; health, safety and environment (HSE) performance; and total production. The efficiency element assumed a production efficiency of 77% based on expected weather downtime and shuttle tanker discharge time, during which production ceased. There was a downside cap limiting contractor exposure in the event of significant lost time. The HSE element was included to reinforce mutual objectives and ensure that significant reward payments would not be made in the unlikely event of unacceptable HSE performance. Finally, to align objectives to production volume, efficiency having been defined as timerather than production-related, a payment was made to reflect contractor sharing in the possible range of financial outcomes for the project—shar- from the two Machar wells at 30,000 BOPD in June 1994, within 19 weeks of project approval. During the subsequent 11 months of phase one, some 7.7 million bbl [1.2 million m3] of oil were produced, generating $130 million revenue for BP. To gain approval to operate the Sedco 707 as a production facility rather than a drilling rig, it was necessary to prepare a new design and operational Safety Case. As the first drilling contractor to submit a Safety Case in the UK after the Cullen Report on the North Sea Piper Alpha disaster, Sedco Forex was well positioned to do this. This particular Safety Case was drawn up by Sedco Forex in consultation with BP and the UK Health and Safety Executive.6 A further hurdle facing North Sea operators is the need to gain UK Government Department of Trade & Industry (DTI) approval for development strategies. In this case, the DTI put a cap on the extent of phase one production by limiting the permissible change in gas-oil ratio, the volume of oil that could be produced and the amount of gas that could be flared. Well 23/26a-6Y had been completed close to the gas cap, so an increase in the gas-oil ratio was expected during phase one. In fact, there was no large increase, which helped prove a higher reserve base than was previously thought, and also confirmed that the reservoir had a robust flow regime. Because of the success of phase one, BP decided to go ahead with phase two—testing the sustainability of production and whether additional reserves could be gained by water injection. The plan for phase two was developed while phase one was still under way, ensuring no interim demobilization. A month of engineering followed by four months of manufacturing and prefabrication preceded the upgrade. The process equipment was modified, converting it to a three-phase system 6. The Safety Case must show that management systems comply with the requirements of health and safety law; that there are arrangements for regular independent audits of the system; that hazards with potential to cause major accidents have been identified; and that risks of major accidents have been evaluated and all reasonable measures will be taken to reduce risks to personnel. For a full explanation of Safety Cases: Hansen H, Myers S, Redd E and Shannon R: “Pursuing the Case for Safety,” Oilfield Review 5, no. 4 (October 1993): 36-45. ing to a degree in the reservoir risk but not in the risk of a fluctuating oil price. 24 Oilfield Review that increased production capacity to 35,000 BOPD [5565 m3/d]. Produced-water and seawater treatment equipment was installed, including a deaeration tower to reduce oxygen content in the injected water to below 20 parts per billion. Normal lead time for delivery of water injection pumps can be up to a year. Therefore, the rig mud pumps were adapted for treated seawater injection at 40,000 B/D [6360 m3/d ]. This was about half as expensive as using dedicated pumps. All this extra equipment was installed during the three-month production shutdown between phases one and two. At the same time, one of the two existing producers— Well 23/26a-18Z—was converted to water injection and a new production well—designated 23/26a-20Y—was drilled to the base of the oil column. This well was then stimulated by Dowell using an acid-fracturing treatment that yielded a record-breaking 460-fold increase in productivity index (see “Machar’s New Well: Drilling and Stimulation,” next page). A new DTI production license was granted. With water injection under way, water breakthrough in the reservoir was expected. However, when the test was concluded in June 1996, there had been no water breakthrough and the produced oil remained dry throughout. Ten months of early production yielded 6.8 million bbl [1.1 million m3] of oil, involved 9 million bbl [1.4 million m3] of injected water and demonstrated the viability of a waterflood in this field. In summary, the tests showed that under natural depletion some 60 million bbl [9.5 million m 3 ] of recoverable oil reserves remain. Adding a waterflood doubled producible reserves to 120 million bbl [19 million m3], narrowing the range of uncertainty surrounding development of the field. The EPS proved more reliable than anticipated. An uptime of 77% was originally factored into the risk and reward formula, including shutdown time when the Stena Savonita was shuttling oil to shore. In practice, greater than 80% uptime was achieved. There were also no lost-time incidents or discharges into the sea, and production targets were exceeded. The Machar field will now be developed as part of the 405 million bbl [64 million m3], seven-field Eastern Trough Area Project (ETAP) and will be tied into the Marnock field platform using subsea completions. Drilling of the four new wells that will drape Winter 1996 Moran Mungo Skua Marnock Egret Machar Heron Production Oil export Gas injection Gas export ■The Eastern Trough Area Project (ETAP). This 405 million-bbl development will link seven fields using platforms and subsea wells. the Machar salt diapir starts in 1997 with first oil expected from the full-field development in October 1998 (above). Underscoring the reusability of this design, Conoco UK is using the Sedco 707 for an EPS in the North Sea that is similar to the one in Machar field. Yme Field Production System, Norwegian North Sea A key element limiting the volume of oil that could be produced from Machar field was the amount of gas that could be flared. The Sedco 707 had originally been scheduled to stay on phase-two production until September 1996. However, having established viability of the field under waterdrive, BP was reluctant to continue operations with the EPS beyond June because further production would have meant additional flaring of associated gas. In the Norwegian sector of the North Sea, development of the marginal Yme field (roughly pronounced eeh-mah) using a production system on a jackup rig addressed the issue of gas production. Some produced gas is used to generate electricity. This power is then used to compress the remaining produced gas for gas lift and reinjection back to an underlying formation. The Yme field is located in 312 ft [95 m] of water some 90 miles [145 km] offshore about midway between Stavanger and the Ekofisk field. The field is operated by Statoil on behalf of itself and partners Saga and Deminex. This production project is in three phases. The first phase, Gamma West, is the main structure. The second phase, Beta East, 25 Machar’s New Well: Drilling and Stimulation The Machar discovery was proven using eight appraisal wells with five side- After underbalanced perforating using expendable 21⁄8-in. Enerjet strip guns at tracks, but drilling has always been difficult in the field. The fractured chalk two shots per foot, a well test was performed. The new well was then acid frac- reservoir is steeply sloping on the flanks of a salt dome and the angle of the ture stimulated using eight-stages of cross-linked gel pad followed by MSR (Mud beds makes drilling difficult. Field development problems are further exacer- and Silt Remover) treatment fluid—a mixture of hydrochloric acid with mud- and bated by the presence of the salt dome that distorts seismic data. In fact, silt-suspending chemicals. Perforation ball sealers were used after each stage to there were two sets of overlapping 3D seismic data for Machar field, each divert treatment fluids into the tightest part of the reservoir (below right). yielding different subsurface models. GeoQuest interpreters used log data, The job was carried out by the Dowell stimulation vessel BIGORANGE XVIII vertical seismic profiles and core information to develop sedimentological pumping through the subsea completion. Prior planning ensured that all elas- models that were used to constrain the 3D seismic data and improve the sub- tomeric seals were compatible with the acid, so there was no need to kill the surface structural model. well. Following the 5740-bbl [912-m3] fracture treatment, a second well test The two wells in production during phase one were Well 23/26a-6Y, com- showed a 460-fold increase in productivity index—a new world record. The objectives of a new well—designated 23/26a-20—were to have a high5500 Pressure, psi angle production well and to acquire a minimal set of logging data to aid in identification of productive fractures. Two nearby wellbores that had been abandoned during appraisal—Well 23/26a-10 and its sidetrack, 23/26a-10Z— provided geologic control over the top reservoir target location (below left). During drilling of Well 23/26a-20, real-time resistivity and gamma ray logging- Bottomhole pressure Bottomhole temperature 5000 120 100 80 4500 60 4000 40 3500 20 Temperature, °C pleted close to the gas cap, and Well 23/26a-18Z at the base of the reservoir. 0 3000 Time while-drilling data were used to help locate the well on the seismic image. If borehole angle is wrong when drilling down a steep flank, wells can miss their targets by a long way. In this case, an unmapped fault skewed the inter- Sedco 707 semisubmersible pretation and Well 23/26a-20 had to be sidetracked twice before hitting the Surface tree target, even though control-wells 23/26a-10 and 10Z were only 130 ft [40 m] away. The first attempt hit a ridge into which reservoir fluids had percolated 2000 ft [600 m] higher than expected. The second attempt penetrated 492 ft BIGORANGE XVIII [150 m] too low and encountered too much water. The second sidetrack well was completed in the target fractured reservoir. In the end, total well depth was 9216 ft [2809 m] with a maximum 62.8° deviation. The diapir had thinned more than expected, so the well penetrated only about 492 ft of reservoir, instead of the planned 2165 ft [660 m]. However, a stimulation job that followed more than made up for this shortfall. Dual riser Well 6Y Well 10 Well 18Z Well 20Y Well 20 Well 10Z Emergency disconnect Lower-riser assembly Well 20Z ■Well 23/26a-20Y and its predecessors. The first drilling attempt—Well 23/26a-20 (black)—hit a ridge where reservoir fluids had percolated 600 m higher than expected. The second attempt—Well 23/26a-20Z (blue)—penetrated 150 m too low, encountering too much water. The third try—Well 23/26a-20Y (green)—was completed in the fractured reservoir target. 26 Crossover Subsea tree Stab base Wellhead Remotely operated vehicle ■Machar hookup and record-setting stimulation. The 5740-bbl acid fracture treatment of Well 23/26a-20 was performed by the Dowell BIGORANGE XVIII stimulation vessel in a single operation with very low treating pressures. The step-like bottomhole pressure development (top right) shows where diverter balls sealed perforations, pushing gelled acid fracture fluid to other, tighter parts of the formation. Because subsea equipment was designed to be compatible with the acid, there was no need to kill the well, which helped achieve the 460-fold increase in productivity and avoid subsequent formation damage. Oilfield Review is a nearby, smaller structure. Other prospects have been identified for an as yet unspecified third phase. Gamma West was the location of the field discovery—Well 9/2-1—which was then suspended. An eight-well template has now been installed on Gamma West. Following a dry hole, Well 9/2-3 was drilled and suspended at Beta East and a three-well template was installed (below). Maersk Giant, one of the world’s largest jackup rigs, is operated by Maersk Drilling. In January 1995, Maersk subcontracted Schlumberger Wireline & Testing to design, install and operate the Yme field EPS. The project scope was to equip the rig in accordance with Det Norske Veritas Production “N” Class and to satisfy Norwegian Petroleum Directorate regulations. Detailed engineering specifications were not issued with the contract. By November of the same Yme Field Layout Maersk Giant jackup Subsea well and structure Gamma West Beta East Maersk Giant jackup Storage tanker 945,000 bbl [150,000 m3] Shuttle tanker Flexible 8-in. flowline Anchor lines 1.5 miles 2.5 km ■Yme field development. The process plant is located on the Maersk Giant jackup rig positioned over the Gamma West reservoir. The Beta East reservoir is exploited using subsea wells tied back to the production facility by 7.5-mile [12-km] long flexible flowlines. Gas lift and chemical injection lines have been laid from the rig to the subsea template, although at present, both wells are flowing naturally. Produced oil is sent via a 1.5-mile [2.5-km] flowline to a 945,000-bbl [150,000-m3] permanent storage tanker with a submerged turret loading system. Shuttle tankers periodically connect to the permanent storage tanker to transport oil to shore. Winter 1996 27 ■The Yme 1400-ton [1.5-million kg] process plant before and after installation. The 50,000-B/D [8000-m3/d] capacity plant was placed on one of the Maersk Giant pipedecks. However, the rig is still able to continue drilling during production. A fire wall separating the living quarters and cantilever deck from the process area was constructed. 28 Oilfield Review 300,000 300,000 Operating capacity Gas lift 400,000 Design capacity A First stage gas Compressors 400,000 Injection B 400,000 Design capacity 400,000 Operating capacity 100,000 Fuel gas Booster All capacities sm3/d Second stage gas ■Handling Yme produced gas. There are two main gas compressors each with a capacity of 14.1 MMscf/D at 2500 psi [400,000 sm3/d at 17.2 MPa]. After compression to 4700 psi [32.4 MPa] using the combined low-pressure and high-pressure booster compressor, up to 400,000 m3/d may be reinjected, with another 10.6 MMscf/D [300,000 sm3/d] for gas lift and 3.5 MMscf/D [100,000 sm3/d] as fuel for power generation. year, the process equipment had been installed on the jackup at a shipyard in Rotterdam, The Netherlands (previous page). First oil was produced from Yme field to the tanker by February 1996. There are two main three-phase, two-stage separator trains, capable of a maximum fluid capacity of 50,000 B/D [8000 m3/d]. The system handles a maximum gas input of 28 MMscf/D [800,000 m 3/d] with three compressors—two main and one low-pressure/high-pressure booster—preparing gas for power generation, gas lift and reinjection. No gas is expected to be flared during normal operations (above). There is one 37,750-B/D [6000-m3/d] high-speed pump for water injection. Winter 1996 Two 6-MW gas turbines supply electrical power to the gas compressors, water injection pump, electrical submersible pumps (ESPs) and process utilities, while offering up to 1 MW of power to the rig. By using gas to generate the required 12 MW of electricity, up to 88 tons [90,000 kg] of diesel are saved every day. With the process equipment installed, the rig was moved onto location in November 1995. Final installation and offshore commissioning work followed and the original discovery well was recompleted and brought onstream at the end of February 1996. Since then, two additional producing wells have been drilled on Gamma West and one of them has been brought onto production. Both wells use ESPs to aid production. In addition, a dual, gas and water injection well has been drilled. Water is currently being injected at some 37,750 B/D. Ultimately, there will be up to seven producing wells and one dual-completion gas/water injector on the Maersk Giant template. On Beta East, the original exploration well and another new well—drilled and completed by semisubmersible rig Deep Sea Bergen—have been brought onstream using subsea completions and dual flowlines to the Maersk Giant. The original plan anticipated at least three years of production, although current predictions estimate that the wells will be on line for at least six years. Norwegian mythology relates that after being killed by his sons, the body of the god Yme became the earth, the sky and the rest of our world. In choosing this name, Statoil clearly sees the Yme field development as a precursor of future EPS projects and marginal field developments offshore Norway. 29 Johannesburg REPUBLIC Alexander OF Bay SOUTH AFRICA ATLANTIC OCEAN Mossel Cape Bay Town Port Elizabeth Durban INDIAN OCEAN CALM buoy Storage and shuttle tanker Orca semisubmersible 400 km 250 miles 32 km George 20 miles Mossel Bay Stilbaai Flexible 6-in. flowline N Wellhead E-S Flexible 6-in. flowline E-AR E-AA E-BD E-BT E-AD E-AJ E-CB ■South Africa’s first oil development. A floating production system (FPS) will be used to exploit the E-BT field. ■How E-BT will be developed. Sedco I—renamed Orca—was converted to a floating production facility. Oil will be exported via the catenary anchor leg mooring (CALM) buoy facilities to a storage and shuttle tanker. Dynamic risers and flexible 6-in. flow lines from subsea wellheads to the rig and from the rig to the CALM buoy will be installed. This allows the semisubmersible rig to be located over the production wells, permitting relatively easy intervention if needed. E-BT Marginal Field Development, Offshore South Africa The progression from Machar field EPS to the production system on Yme—gas flaring to gas utilization—is clear. The next step is for production system providers to also take responsibility for the subsea part of developments as well as crude-oil storage and export. In this third example, an alliance led by Schlumberger product lines has responsibility for delivering oil from the mudline to the refinery. The E-BT project will be South Africa’s first oil development and first floating production system. SOEKOR E and P (Pty) Ltd. is the field operator along with partner Energy Africa Bredasdorp (Pty) Ltd. An alliance of Schlumberger Oilfield Service product lines—Schlumberger Wireline & Testing and Sedco Forex—plus Fred Olsen Tankers, has entered into an agreement with SOEKOR and Energy Africa to upgrade and operate the semisubmersible Sedco I (renamed Orca) as a floating production facility for the E-BT field. Phase one of the project is to deliver first oil in early 1997. The second phase is to operate the field for an estimated period of four years (above left). 30 This is a turnkey offshore development. The scope of work includes procuring and upgrading the semisubmersible rig, providing subsea trees and carrying out well installation work, providing and installing the catenary anchor leg mooring (CALM) buoy facilities, commissioning all the equipment, providing the export tanker and transport to the refinery, and managing and operating the project for the entire production period. Schlumberger Oilfield Services will provide project planning and management; Sedco Forex will provide rig upgrade and rig management services; Schlumberger Wireline & Testing will be responsible for the process plant and production operations. Fred Olsen Tankers will provide the CALM buoy for exporting oil, a customized tanker for storage and transport to the refinery, and tanker management. The project alliance is working with the field and reservoir management team of operator SOEKOR. The alliance will be turnkey equipment supplier, except for completion tubulars and components, which will be supplied by SOEKOR. The rig and associated process and buoy equipment belong to SOEKOR and Energy Africa. During 1996, Orca was upgraded at a shipyard in Simons Town, South Africa. Following an audit and fatigue analysis, a program of life enhancement and structural strengthening was carried out. Rig accommodations have been modernized, the mooring system was upgraded to withstand marine conditions offshore South Africa, and the drilling equipment was enhanced to provide full workover capability. Oil storage capacity has also been installed inside the rig’s three columns—nine tanks and a total capacity of 30,000 bbl. Oilfield Review Intelligent Production Systems Intelligent production systems (IPS) are based on A typical system for production optimization is an effective way of diagnosing process irregu- the premise that liquid yield of a hydrocarbon sepa- consists of a dedicated PC-workstation installed larities and abnormalities. In short, the IPS simu- ration process can be improved if process-operat- either at the operator’s offices or the production lator is a tool to aid in the proper management of ing parameters are fine-tuned as wellstream com- facility. In either case, a communication link via process facilities. position and reservoir conditions vary, or ambient modem is required to transmit data between the conditions change. These improvements may typi- facility and the office. cally be in increments of a few percent—100 BOPD per 10,000 BOPD. The PC will host the IPS process simulator and An added dimension is upstream and downstream optimization, which is particularly relevant when injection programs and artificial lift systems the proprietary interface, which permits retrieval are implemented, or when choke manifolds oper- of essential process parameters from a data base ate under subcritical conditions.1 In the latter several zones, each saturated with different types at the production facility—including upstream and case, variation of separator pressures can have an of crude oil. There may also be an areal variation downstream choke pressures, separator pressures impact on reservoir deliverability and well pro- of crude gravity and sharp fluctuations in seasonal and temperatures, and gas and oil flow rates. ducibility. Hence, it is imperative that the process temperature that affect surface operations. The net These data are then filtered, validated and simulator be linked to a working upstream model effect is that the separation process will be ineffi- directed to a simulator that computes the current to optimize the production system. cient unless operating parameters are adjusted to optimal conditions of separation. For example, the wellstream may originate from meet changing demands. Besides pinpointing optimal separation conditions, the simulator also raises flags if measured and computed values disagree significantly. This A fully modular production system with a capacity of 25,000 BOPD [3975 m3/d] was installed. This system, offering water injection, two-stage separation, gas flaring and produced water processing, is similar to the one used on the Sedco 707 for the Machar EPS. The rig, process plant and loading buoy equipment were built or upgraded for ten years of production (previous page, right). Average output from the two production wells will be 20,000 BOPD [3180 m3/d]. This can be choked back to 5000 BOPD if bad weather delays offshore loading or transport to refinery. In this case, the production at the reduced rate is diverted into the 30,000-bbl capacity buffer storage in the rig columns. Before production starts, the rig mud pumps will be used to start water injection into one well at up to 30,000 B/D and 3000 psi [20.7 MPa]. The cementing unit offers additional water injection capacity. Gas for lift purposes will be injected via the control umbilicals, which will also convey instrumentation data. By early 1997, Orca will be on location completing the wells, and the dedicated storage and transport tanker will arrive in South Africa following shipyard work to install the necessary modifications to accommodate the CALM system. The CALM loading buoy itself was upgraded in Singapore. A diving-support vessel will install the flowlines and dynamic risers, and position the CALM loading buoy. Winter 1996 The E-BT project is not envisaged as an “early” production system, but is intended to stay in service for the full production life of the field. This represents a significant reduction in platform investment, and eventually will reduce concerns about how to deal with permanent marine structures once their useful life has ended. Smarter Production, Not Just More Data and Early Oil When designing a production system, whether as an EPS or to last for the life of the reservoir, it is important to use well-test data to optimize processing hardware. Then, data gathered during the productive life of the reservoir may be used to fine-tune EPS operating parameters and maximize production. For example, as produced fluids or flowing conditions change, the hydrocarbon separation process can be altered slightly to improve liquid yield. This may be achieved using intelligent production systems, a powerful production management tool that optimizes reservoir depletion by linking permanent monitoring and reservoir modeling to an online topside simulation. Operating conditions can now be fine-tuned to yield maximum liquid hydrocarbons (see “Intelligent Production Systems,” above). There is no doubt that operators are increasingly inclined to consider imagina- 1. The general definition of critical flow for oil wells is that pressure upstream of the choke is greater than twice the downstream pressure. Thus fluid velocity is greater than the sonic velocity of the choke. tive ways of extracting data and early oil from their assets. The Schlumberger Wireline & Testing production systems group has been active since 1974—a track-record that may be traced back to the days of Flopetrol Schlumberger—and has notched up cumulative production of an estimated 350 million bbl [55 million m3] of oil. The ten plants currently in operation deliver an average of 190,000 BOPD [30,200 m3/d]. However, new projects now under way will dramatically increase this tally. Early production systems are akin to fullscale development projects. They require the same planning, regulatory approval and safety analyses. At the same time, these solutions rely on a wide range of human and institutional interfaces. Many of these interfaces are already well-known to the well-testing community. Other interfaces, for example those concerning offshore storage facilities and shuttle tankers, may be relatively new. However, it is clear that the service industry tradition of rapidly deploying equipment and services using multifunctional teams is helping operators profit despite ever-tightening margins. —CF 31
© Copyright 2026 Paperzz