Gwinnett County`s NRCS Watershed Dam Rehabilitation Program

Gwinnett County
NRCS Watershed
Dam Rehabilitation
Program
Jonathan Semerjian, PE
Dept. of Water Resources
Stormwater Management
Gregg Hudock, PE
Golder Associates
Sam Fleming, PE
Dewberry
Presentation Overview
•
•
•
•
•
•
•
•
Background
Program at a Glance
Program Drivers
Planning and Implementation
Challenges
Yellow River Dams
Other Keys to Program
Summary
2
Background
• Gwinnett County, GA
– Metro Atlanta
– 437 Square Miles
– Population 800,000+
• Piedmont Region
– Headwaters Watersheds
• 1/3 Gulf of Mexico
• 2/3 Atlantic Ocean
• 437 Square Miles
• Population
– 805,000
– 80% Unincorp. / 20% Cities (16)
3
Background
• Gwinnett County Government
– Dept. of Water Resources
• Stormwater Management
• Stormwater Utility Funded
– Unincorporated Gwinnett & Lilburn
• Implemented in 2006
• $34M Annual Revenues ($2.46/100 sf)
– Aging Stormwater Infrastructure
• ~1,300 Miles County-Maintained Pipe
– ~1,000 Miles Corrugated Steel
– ~500 Miles > 20 Years Old
• ~80,000 Drainage Structures
4
Background
• 14 NRCS Watershed Dams
– 357 Statewide
• GASDP Inventoried Dams – 139
– 30 Category I
• 16 County Owned/Operated
– 56 Category II
• 3 County Owned/Operated
– 3 Exempt High Hazard
– 45 Exempt
• 4 County Owned/Operated
– 1 Not a Dam
– 4 Not Classified
• 2 County Owned/Operated
5
Program at a Glance
•
Initiated NRCS Dam CIP in 1999
– Began Design 1 Dam/year 1999-2001
– Planning stage for remainder 2002-2004
– Construction 2003 - present
•
•
Status
– 9 dams upgrades completed
– 3 dams design completed and ready for
construction
– 2 dams met GASDP standards without
upgrade needs
Total Program $20 million
– $14.8 million County funded
– $5.2 million NRCS Grant funded
• 65 NRCS / 35 Local Match
6
Program Drivers
•
Public Safety and Regulatory
Compliance
– Signed O&M Agreement
• Responsible Operator
– RC&D & SWCD Co-Sponsors
• Generate Revenues
– State Regulation
• Safe Dams Act (1978)
• Original law exempted NRCS Dams
• Exemption ended in 2000
– Population Growth
• 72,000 (1970)
• 588,000 (2000)
• 805,000 (2010)
– Originally designed to protect agricultural
lands from flooding
– Increased Development in the Breach Zone
• Classification “High Hazard”.
– Inadequate Spillway Capacity and Stability
• Most designed prior to Act
• Stepped Design Criteria
7
Program Drivers
• Resource Protection
– Flood Protection
• Up to 98% reduction in 1% annual chance peak
– Recreation
• County Parks
– Fish and Wildlife Habitat
– Water Quality
– Public Infrastructure
• Smaller downstream bridges and culverts
• Roads & utilities
– Property Values
• Increased values around lakes
• Reduced floodplain downstream
8
Program Implementation
• CIP Implemented in 1999
–
–
–
–
Y15, Y14, N1 under design
6-year program outlook
Funded by General Property Tax
Y16 & Y17 under design by USACE thru
State
• Design Challenges
– Development encroachments
– Existing and Planned Development
– No room to widen earthen auxiliary
spillways
– Leverage dam length for overtopping
chute spillways
– RCC most cost effective
– Floodplain Management – No Rise
9
Program Implementation
• NRCS Grant funding availability
– Small Watershed Rehabilitation
Amendments of 2000
– 65/35 Cost share
– Federal Design Criteria plus
GASDP Standards
– Full PMP design (NRCS)
– GASDP design storm based on
size of dam
– ¼ to full PMP
– Refocus Design Strategies
– Enter into MOU with NRCS
– Try to secure Grant Funding
10
Program Implementation
•
No Business Dam No. 1 (N1)
– Located in a golf course
– Construction impacts to golf course
operations
– Necessary Spillway Width
– Construction Staging
– Loss of Revenue
– 35% Cost Share Fed Stds > 100% County
GASDP Stds
–
–
–
–
Grant req’d Spillway designed to full PMP
Greater impacts to adjacent properties
Greater costs to construct
Forwent grant pursuit and fund 100% local
– Widened earthen auxiliary spillway
11
Program Implementation
•
Planning Strategy
– Planning Studies on Remaining Dams
– Determine most cost effective solution
– 65/35 Cost Share (Fed and GASDP Stds) vs. 100%
Local (GASDP Stds)
–
Cost to meet GASDP only as little as 10% of cost to
meet Fed Std
– 5 dams RCC overtopping spillways
–
3 with NRCS Grant
–
1 Conv. Concrete Labyrinth Weir Chute Spillway over
the top of the dam (Y3 to be constructed)
– 6 dams combination modified earthen aux. spillways
and/or wave walls
– Better planned CIP
– Funding needs for timing of design and const.
– Commence Design for all Structures
– Y14 first to commence construction (2003)
12
Challenges
•
Design
– Converging Spillways
• Piedmont Region of GA
• Narrow, steep stream valleys
• Convergence beyond tested limits
– Test Studies Conducted
• Y15 USBR Hydraulics Laboratory
– County funded
• H3 USDA ARS HERU Laboratory
– NRCS funded
• Better to converge flow in control section
– Variety of Control Sections
• Arced Ogee, Straight Broad Crested,
Arced Broad Crested, Winged Broad
Crested, Sharp Crested Weirs
• Multi-stage spillways
– Floodplain Management (No Rise)
13
Challenges
•
Elected Officials and County Administration
–
Briefings, memos, briefings, memos, and more
briefings and memos
• “Spillways have never run around.”
• “Do we really need to spend this much money?”
• “What happens if we don’t do anything?”
• “Why did we save those O&M Agreements?”
• “Can we get out of this?”
• “If we fix this once, will we have to go back
again?”
–
Communication was the key
• Explain options, benefits, consequences
• Brief and to the point
•
Funding
–
Initially funded by General Fund
–
Stormwater Utility Funding starting in 2006
–
BOC final authority on budget
–
Securing Grant Funds
14
Challenges
•
Public Acceptance
– Multiple Public Meetings
• Discussed alternatives and get input on
selected alternative
– Aesthetics
• Exposed RCC not acceptable
• No exposed concrete preferred
– Graffiti
• Vegetative cover on RCC chute steps
after Y14
– Fish
• Drain lakes during construction
• Restock after construction
– Often Contentious
• Threatened lawsuits (Y15 and Y16)
• Assignment of easement offered (Y15)
• Had to find a champion
15
Challenges
•
Land Rights
–
Flowage Easement
• Referenced to an elevation (Top of Dam)
– Some amended to lower elevation
• Flood Flowage, Ingress/Egress, and O&M
• Interpreted to allow Construction Upgrades
•
–
Temp Const/Perm Drainage Esmts where const
activities went beyond Flowage Esmt
–
Cost to Cure
Construction
–
Contractor Pre-qualification
–
On-site RCC pug mills and staging areas
–
Construction Traffic
–
Water source for RCC
–
Minimizing Change Orders
• RCC Mtls, Unsuitables, Stone, etc…
–
Complaints by local residents
–
Grant administration
16
Yellow River Dam No. 14 (Y14)
•
•
•
•
•
•
•
•
•
In a developed subdivision
– Proposed development in land
between exist. aux. spillway and dam
Grant funded (65/35 Cost Share)
Maintained reservoir levels 3-feet below
normal pool during construction (Fish)
Interceptor sewer along right abutment
GA Power Easement primary access
•
Allowable construction activity coordination
Stage RCC Pug Mill, material stockpiles, etc… in
existing earthen aux. spillway
•
Maintain 50% width clearance
Provided off-duty patrol for traffic control
Converging spillway with arced ogee weir
Construction 2003-2004 (Golder, Thalle)
17
Yellow River Dam No. 14 (Y14)
18
Yellow River Dam No. 15 (Y15)
•
•
•
•
•
•
•
•
In a developed subdivision
Active, uncooperative, and litigious HOA
– Threatened lawsuits
– Assignment of easement offered
Half Dam length available for overtopping
spillway control section
Collins Hill Rd d/s and adjacent to dam
Grant funded (65/35 Cost share)
Model test at BOR
Converging spillway with winged broad
crested weir, vegetative cover
Construction 2007-2008 (Golder, ASI)
• Construction bundled with Y16
• Pug mill adjacent to site
19
Yellow River Dam No. 15 (Y15)
20
Yellow River Dam No. 16 (Y16)
•
•
•
•
•
•
•
•
In a developed subdivision
– HOA coordination
Took over design from GASWCC
Interceptor sewer thru exist. earthen aux.
spillway
20-foot wide dedicated access btwn houses
– Const. access thru lake bed
D/S private lake normal pool elev higher than P/S
outlet pipe and toe drains
100% local funded
Converging spillway with sharp crested weir and
vegetative cover
Construction 2007-2008 (Schnabel, ASI)
•
Construction bundled with Y15
•
Pug mill off-site (4-miles away)
•
Fish kill during pre-const lake draining
21
Yellow River Dam No. 16 (Y16)
22
Yellow River Dam No. 17 (Y17)
•
•
•
•
•
•
•
•
In County Park
Park used for HS overflow parking
Designed by USACE thru GASWCC
Grant funded (65/35 Cost Share)
Construction procured and
administer by Gwinnett
Significant unsuitables at toe of
dam from original construction
Converging spillway with broad
crested weir and vegetative cover
Construction 2004-2005 (USACE,
Golder, ASI)
23
Yellow River Dam No. 17 (Y17)
24
Other Keys to Program
•
Operation and Maintenance
–
Mowed twice per year and removed debris as
needed
–
Annual Inspections
• Now quarterly
–
•
•
No major deficiencies to address other than spillway
capacity
Instrumentation
–
Remote monitoring being installed to monitor
reservoir levels
–
Plan to install on all NRCS Dams
Emergency Action Plans
–
Developed for all 14 NRCS Dams
–
Sunny Day and Storm in Progress (PMP) Failure
Events
–
Imminent, Potential, and Non-failure Classifications
–
Property Owner listing for notifications
• Reverse 911
–
Expanding to private dams
25
Summary
• Understand Needs/Drivers
– Benefits, Consequences, and Options
• Communication
– Elected Officials
– Management/Administration
– Public
• Planning
– Identify Funding Sources
– Concept Planning before Implementation
– EAPs
• Operation and Maintenance
– Keep O&M and Inspections Up to Date
• Qualified Consultants and Contractors
26
Questions
Jonathan Semerjian, P.E.
Section Manager
Gwinnett Co. Dept. of Water Resources
684 Winder Hwy.
Lawrenceville, GA 30045
678.376.6934
[email protected]
Gregg Hudock, P.E.
Golder Associates
770.496.1893
[email protected]
Sam Fleming, P.E.
Dewberry
678.537.8627
[email protected]
27