Gwinnett County NRCS Watershed Dam Rehabilitation Program Jonathan Semerjian, PE Dept. of Water Resources Stormwater Management Gregg Hudock, PE Golder Associates Sam Fleming, PE Dewberry Presentation Overview • • • • • • • • Background Program at a Glance Program Drivers Planning and Implementation Challenges Yellow River Dams Other Keys to Program Summary 2 Background • Gwinnett County, GA – Metro Atlanta – 437 Square Miles – Population 800,000+ • Piedmont Region – Headwaters Watersheds • 1/3 Gulf of Mexico • 2/3 Atlantic Ocean • 437 Square Miles • Population – 805,000 – 80% Unincorp. / 20% Cities (16) 3 Background • Gwinnett County Government – Dept. of Water Resources • Stormwater Management • Stormwater Utility Funded – Unincorporated Gwinnett & Lilburn • Implemented in 2006 • $34M Annual Revenues ($2.46/100 sf) – Aging Stormwater Infrastructure • ~1,300 Miles County-Maintained Pipe – ~1,000 Miles Corrugated Steel – ~500 Miles > 20 Years Old • ~80,000 Drainage Structures 4 Background • 14 NRCS Watershed Dams – 357 Statewide • GASDP Inventoried Dams – 139 – 30 Category I • 16 County Owned/Operated – 56 Category II • 3 County Owned/Operated – 3 Exempt High Hazard – 45 Exempt • 4 County Owned/Operated – 1 Not a Dam – 4 Not Classified • 2 County Owned/Operated 5 Program at a Glance • Initiated NRCS Dam CIP in 1999 – Began Design 1 Dam/year 1999-2001 – Planning stage for remainder 2002-2004 – Construction 2003 - present • • Status – 9 dams upgrades completed – 3 dams design completed and ready for construction – 2 dams met GASDP standards without upgrade needs Total Program $20 million – $14.8 million County funded – $5.2 million NRCS Grant funded • 65 NRCS / 35 Local Match 6 Program Drivers • Public Safety and Regulatory Compliance – Signed O&M Agreement • Responsible Operator – RC&D & SWCD Co-Sponsors • Generate Revenues – State Regulation • Safe Dams Act (1978) • Original law exempted NRCS Dams • Exemption ended in 2000 – Population Growth • 72,000 (1970) • 588,000 (2000) • 805,000 (2010) – Originally designed to protect agricultural lands from flooding – Increased Development in the Breach Zone • Classification “High Hazard”. – Inadequate Spillway Capacity and Stability • Most designed prior to Act • Stepped Design Criteria 7 Program Drivers • Resource Protection – Flood Protection • Up to 98% reduction in 1% annual chance peak – Recreation • County Parks – Fish and Wildlife Habitat – Water Quality – Public Infrastructure • Smaller downstream bridges and culverts • Roads & utilities – Property Values • Increased values around lakes • Reduced floodplain downstream 8 Program Implementation • CIP Implemented in 1999 – – – – Y15, Y14, N1 under design 6-year program outlook Funded by General Property Tax Y16 & Y17 under design by USACE thru State • Design Challenges – Development encroachments – Existing and Planned Development – No room to widen earthen auxiliary spillways – Leverage dam length for overtopping chute spillways – RCC most cost effective – Floodplain Management – No Rise 9 Program Implementation • NRCS Grant funding availability – Small Watershed Rehabilitation Amendments of 2000 – 65/35 Cost share – Federal Design Criteria plus GASDP Standards – Full PMP design (NRCS) – GASDP design storm based on size of dam – ¼ to full PMP – Refocus Design Strategies – Enter into MOU with NRCS – Try to secure Grant Funding 10 Program Implementation • No Business Dam No. 1 (N1) – Located in a golf course – Construction impacts to golf course operations – Necessary Spillway Width – Construction Staging – Loss of Revenue – 35% Cost Share Fed Stds > 100% County GASDP Stds – – – – Grant req’d Spillway designed to full PMP Greater impacts to adjacent properties Greater costs to construct Forwent grant pursuit and fund 100% local – Widened earthen auxiliary spillway 11 Program Implementation • Planning Strategy – Planning Studies on Remaining Dams – Determine most cost effective solution – 65/35 Cost Share (Fed and GASDP Stds) vs. 100% Local (GASDP Stds) – Cost to meet GASDP only as little as 10% of cost to meet Fed Std – 5 dams RCC overtopping spillways – 3 with NRCS Grant – 1 Conv. Concrete Labyrinth Weir Chute Spillway over the top of the dam (Y3 to be constructed) – 6 dams combination modified earthen aux. spillways and/or wave walls – Better planned CIP – Funding needs for timing of design and const. – Commence Design for all Structures – Y14 first to commence construction (2003) 12 Challenges • Design – Converging Spillways • Piedmont Region of GA • Narrow, steep stream valleys • Convergence beyond tested limits – Test Studies Conducted • Y15 USBR Hydraulics Laboratory – County funded • H3 USDA ARS HERU Laboratory – NRCS funded • Better to converge flow in control section – Variety of Control Sections • Arced Ogee, Straight Broad Crested, Arced Broad Crested, Winged Broad Crested, Sharp Crested Weirs • Multi-stage spillways – Floodplain Management (No Rise) 13 Challenges • Elected Officials and County Administration – Briefings, memos, briefings, memos, and more briefings and memos • “Spillways have never run around.” • “Do we really need to spend this much money?” • “What happens if we don’t do anything?” • “Why did we save those O&M Agreements?” • “Can we get out of this?” • “If we fix this once, will we have to go back again?” – Communication was the key • Explain options, benefits, consequences • Brief and to the point • Funding – Initially funded by General Fund – Stormwater Utility Funding starting in 2006 – BOC final authority on budget – Securing Grant Funds 14 Challenges • Public Acceptance – Multiple Public Meetings • Discussed alternatives and get input on selected alternative – Aesthetics • Exposed RCC not acceptable • No exposed concrete preferred – Graffiti • Vegetative cover on RCC chute steps after Y14 – Fish • Drain lakes during construction • Restock after construction – Often Contentious • Threatened lawsuits (Y15 and Y16) • Assignment of easement offered (Y15) • Had to find a champion 15 Challenges • Land Rights – Flowage Easement • Referenced to an elevation (Top of Dam) – Some amended to lower elevation • Flood Flowage, Ingress/Egress, and O&M • Interpreted to allow Construction Upgrades • – Temp Const/Perm Drainage Esmts where const activities went beyond Flowage Esmt – Cost to Cure Construction – Contractor Pre-qualification – On-site RCC pug mills and staging areas – Construction Traffic – Water source for RCC – Minimizing Change Orders • RCC Mtls, Unsuitables, Stone, etc… – Complaints by local residents – Grant administration 16 Yellow River Dam No. 14 (Y14) • • • • • • • • • In a developed subdivision – Proposed development in land between exist. aux. spillway and dam Grant funded (65/35 Cost Share) Maintained reservoir levels 3-feet below normal pool during construction (Fish) Interceptor sewer along right abutment GA Power Easement primary access • Allowable construction activity coordination Stage RCC Pug Mill, material stockpiles, etc… in existing earthen aux. spillway • Maintain 50% width clearance Provided off-duty patrol for traffic control Converging spillway with arced ogee weir Construction 2003-2004 (Golder, Thalle) 17 Yellow River Dam No. 14 (Y14) 18 Yellow River Dam No. 15 (Y15) • • • • • • • • In a developed subdivision Active, uncooperative, and litigious HOA – Threatened lawsuits – Assignment of easement offered Half Dam length available for overtopping spillway control section Collins Hill Rd d/s and adjacent to dam Grant funded (65/35 Cost share) Model test at BOR Converging spillway with winged broad crested weir, vegetative cover Construction 2007-2008 (Golder, ASI) • Construction bundled with Y16 • Pug mill adjacent to site 19 Yellow River Dam No. 15 (Y15) 20 Yellow River Dam No. 16 (Y16) • • • • • • • • In a developed subdivision – HOA coordination Took over design from GASWCC Interceptor sewer thru exist. earthen aux. spillway 20-foot wide dedicated access btwn houses – Const. access thru lake bed D/S private lake normal pool elev higher than P/S outlet pipe and toe drains 100% local funded Converging spillway with sharp crested weir and vegetative cover Construction 2007-2008 (Schnabel, ASI) • Construction bundled with Y15 • Pug mill off-site (4-miles away) • Fish kill during pre-const lake draining 21 Yellow River Dam No. 16 (Y16) 22 Yellow River Dam No. 17 (Y17) • • • • • • • • In County Park Park used for HS overflow parking Designed by USACE thru GASWCC Grant funded (65/35 Cost Share) Construction procured and administer by Gwinnett Significant unsuitables at toe of dam from original construction Converging spillway with broad crested weir and vegetative cover Construction 2004-2005 (USACE, Golder, ASI) 23 Yellow River Dam No. 17 (Y17) 24 Other Keys to Program • Operation and Maintenance – Mowed twice per year and removed debris as needed – Annual Inspections • Now quarterly – • • No major deficiencies to address other than spillway capacity Instrumentation – Remote monitoring being installed to monitor reservoir levels – Plan to install on all NRCS Dams Emergency Action Plans – Developed for all 14 NRCS Dams – Sunny Day and Storm in Progress (PMP) Failure Events – Imminent, Potential, and Non-failure Classifications – Property Owner listing for notifications • Reverse 911 – Expanding to private dams 25 Summary • Understand Needs/Drivers – Benefits, Consequences, and Options • Communication – Elected Officials – Management/Administration – Public • Planning – Identify Funding Sources – Concept Planning before Implementation – EAPs • Operation and Maintenance – Keep O&M and Inspections Up to Date • Qualified Consultants and Contractors 26 Questions Jonathan Semerjian, P.E. Section Manager Gwinnett Co. Dept. of Water Resources 684 Winder Hwy. Lawrenceville, GA 30045 678.376.6934 [email protected] Gregg Hudock, P.E. Golder Associates 770.496.1893 [email protected] Sam Fleming, P.E. Dewberry 678.537.8627 [email protected] 27
© Copyright 2026 Paperzz