Facility Location Proposal Year Proposal Originated Loaded Trains

Facility
Location
Proposal
Anacortes, WA
Shell Puget Sound Refinery proposes to
build a rail spur from the existing
adjacent BNSF mainline onto Shell PSR
property with equipment to pump oil
from rail cars into the refinery. The only
refinery in the Northwest that doesn't
receive oil by rail. Up to 61,200 barrels
of crude/day could be processed at
this facility.
2013
6.1
Domestic Shell
In the scoping
process to
determine what
factors to analyze
and what extent
WA. Dept. Ecology and they are considered Scoping period ends Nov. 5,
Skagit County
in the Draft EIS.
2015.
Vancouver, WA
Retrofit an existing terminal so it can
receive crude oil delivered by rail, store
it, and transfer it to marine vessels. Up
to 22,000 barrels/day could be
processed by this facility.
2014
2.2
Domestic NuStar Energy
City of Vancouver
Scoping period for
Draft EIS pending. Pending start of scoping period.
Vancouver Energy
Vancouver, WA
Develop and operate a new crude-by-rail
and marine loading facility. Up to
360,000 barrels/day of crude could be
processed at this facility.
2013
36
Tesoro Corp, Savage
Domestic Companies
EFSEC 5
Draft EIS in
progress, expected
in November, 2015. Pending release of Draft DEIS.
Westway Terminals
Terminal expansion to allow for the
receipt of crude oil unit trains, storage of
crude oil from trains, and shipment of
crude oil by vessel and/or barge from
Port of Grays Harbor Terminal. Up to
48,918 barrels/day could be processed
Grays Harbor, WA by this facility.
2014
4.9
Westway Terminal
Domestic Company
WA. Dept. Ecology and Draft EIS released
Hoquiam County
Aug., 2015.
Draft EIS comment period ends
Nov. 30th, 2015.
Imperium Terminals
Proposed expansion of existing bulk
liquid storage terminal to allow for: the
receipt, storage, and shipment of liquids
including crude oil. Bulk liquids would be
shipped by rail, trucks, ships, or barges
to and from the facility. Up to 73,500
barrels of crude/day could be
Grays Harbor, WA processed by this facility.
2014
7.4
Domestic Imperium Renewables
WA. Dept. Ecology and Draft EIS released
Hoquiam County
Aug., 2015.
Draft EIS comment period ends
Nov. 30th, 2015.
Grays Harbor Ral Terminal
Proposed bulk liquids rail logistics
facility. Bulk liquids, including crude oil,
would be delivered by rail, stored, and
transfered to marine vessels. Up to
45,000 barrels of crude/day could be
Grays Harbor, WA processed at this facility.
Shell Puget Sound Refinery
NuStar
Year Proposal Originated Loaded Trains/Week Destination Energy Company
2014
4.5
Total Loaded Trains/Week
1
United States Army Corp of Engineers
2
Washington State Department of Ecology
US Development, LLC
425.1-481.1
3
Environmental Impact Statement
4
Department of Environmental Quality
5
Energy Facility Site Evaluation Council
Permitting Authority Status
Public Comment Opportunity
Draft EIS in
WA. Dept. Ecology and progress, expected
Hoquiam Co.
early 2016.
Pending release of Draft EIS.