WARM-UP: Create a graph for the following information. Prerequisite (Edges) Task (Vertices) Time START 0 A 3 NONE B 7 A C 6 A D 1 B,C E 3 C F 3 D,E FINISH QUESTIONS: *What does it mean to finish the project? *How long should this project take to finish? HW 4.1 QUESTIONS: p172 #1-4, 7 (skip 5) 4.2 Critical Paths Of course, as the U.S. Government, how long would they want it to take to construct one of these? *EFFICIENCY!!! So, they came up with a technique called PERT (Program Evaluation and Review Technique) that allows them to find the earliest completion of the project. Finding this path of targeted tasks from the start and the finish is called the critical path. So, how do we go about finding a systematic way to identifying the critical path for this project? *We must find an earliest-start time (EST) for each task. This number represents the earliest an activity can begin. What do you think this is based on? *All of its prerequisite tasks are completed!!! To calculate the EST for each task: 1) Begin at the start. 2) Label each vertex with the smallest possible time that is needed before the task can begin. (You must wait till all pre-req. tasks are completed!!!) 3) Once all vertices are labeled, look for the critical path (HINT: It should be the LONGEST path from start to finish - the Highest start dates!) Doing example from before on board... Let's do an example off your HW - pg 177 #1 Find: 1) EST of each vertex 2) Critical Path 3) Min Project Time QUESTION: If you are looking to cut the minimum project time, what times should we look to decrease? QUESTION: If a task is not on the critical path, do we have to start that task as soon as the prerequisite task is finished? The latest a task can begin without delaying the project's minimum completion time is known as the latest-start time (LST) . Turn in by the end of the period: Find the EST, LST, and the critical path. Also answer the question below. QUESTION: What do you notice about the EST and LST of tasks on the critical path? HW: HW 4.2: p177 #1-5, 7-10 SMART Document Camera Ensure that a SMART Document Camera is connected and isn't in use in an other application.
© Copyright 2026 Paperzz