Seismic Retrofit of Piers Supported on Battered Piles Using Lead

Seismic Retrofit of Piers Supported on
Battered Piles Using
Lead-Rubber Bearings
Jeff Kilborn, MASCE, PE, SE
Robert Harn, MASCE, PE, SE
Yeliz Firat, PhD
Buildingonthe Past, Respectingthe Future
Presentation Overview
• Why Retrofit Batter Piles?
• Retrofit Case Study
– “Existing Pier” Response and Deficiencies
– Conventional Batter Pile Retrofit Scheme
– Lead Rubber Bearing (LRB) Retrofit Scheme
• Design Considerations
• Construction Process
• Advantages of LRB Retrofit Scheme
Buildingonthe Past, Respectingthe Future
Why Retrofit Batter Piles?
• Brittle Pile-to-Deck Connections
• Inadequate Geotechnical Capacities
• Inadequate Deck/Cap Reinforcement
Buildingonthe Past, Respectingthe Future
Case Study - “Existing Pier”
50’
(15.2m)
Deck
Pile cap
22’
6.7 m
A
Plumb piles
Batter piles
Section A-A
Under Strength
Brittle Connections
A
Partial Plan
Buildingonthe Past, Respectingthe Future
Seismic Response of Existing Pier
4500
Demand = 3900 kips
4000
CLE_5% Damping
CLE_10% Damping
3500
CLE_20% Damping
Base Shear (kips)
3000
Capacity Curve
2500
Ductility Limit
2000
1500
Capacity = 1300 kips
1000
500
0
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
Spectral Displacement (inches)
1.
2.
3.
Initial Batter Pile System Fails
Less Stiff Plumb Pile System remains
Plumb Piles are Overwhelmed
1 Kip = 4.45 kN
1 Inch = 2.54 cm
Buildingonthe Past, Respectingthe Future
Conventional Batter Pile Retrofit Scheme
24 new battered pipe piles
driven through the existing
deck
12 new pile
caps
A
A
Decouple longitudinal
battered piles typical
Section A-A
Partial Plan
Buildingonthe Past, Respectingthe Future
Batter Pile Retrofit Response
4500
CLE_5% Damping
CLE_10% Damping
CLE_20% Damping
Capacity Curve_Transverse
Capacity Curve_Longitudinal
Strengthen batter
system Transverse
4000
3500
Base Shear (kips)
3000
Ductility Limit
2500
∆ = 5.5”
2000
1500
1000
Plumb pile system
longitudinal
500
0
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
Spectral Displacement (in.)
Performance is Acceptable!
1 Kip = 4.45 kN
1 Inch = 2.54 cm
Buildingonthe Past, Respectingthe Future
7
Lead Rubber Bearing Elements
Lead Core
Rubber
Cover
Internal
Plate
Steel Shims
Between
Rubber
Layers
Flange
Plate
Buildingonthe Past, Respectingthe Future
8
LRB Retrofit Scheme
New LRBs mounted on new
subcaps supported on the
existing battered piles
A
Jacket/strengthen existing plumb
pile connection if required
Section A-A
A
Partial Plan
Buildingonthe Past, Respectingthe Future
LRB Retrofit Response
4500
CLE_5% Damping
CLE_10% Damping
CLE_20% Damping
Capacity Curve_ Example Pier
Capacity Curve_Pier w/ LRB
4000
3500
Base Shear (kips)
3000
2500
∆ = 4.3”
2000
Ductility Limit
1500
1000
500
0
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
Spectral Displacement (inches)
Better Performance Than Conventional Scheme!
1 Kip = 4.45 kN
1 Inch = 2.54 cm
Buildingonthe Past, Respectingthe Future
10
Design Considerations
Pier Deck
Pile Cap
e1
e2
LRB
e2
Pile
e1
Sub Cap
Elevation
Plan
Section
Buildingonthe Past, Respectingthe Future
11
Construction Process
Buildingonthe Past, Respectingthe Future
12
Pile Shell Removal
Buildingonthe Past, Respectingthe Future
Stage 1 Pilecap Construction
Buildingonthe Past, Respectingthe Future
Shoring & Pile Cutoff
Buildingonthe Past, Respectingthe Future
Anchoring Pile Reinforcement
Buildingonthe Past, Respectingthe Future
Example of LRB Installation
Buildingonthe Past, Respectingthe Future
Advantages of LRB Retrofit Scheme
• Avoid Pile Driving
• Work Occurs Under Deck
• Bearings Remain Undamaged
• Cost Competitive
• Reliable & Designable Stiffness, Strength, and Damping
• Global Torsion Can Be Designed Away
• Forces Reduced for All Elements
Buildingonthe Past, Respectingthe Future
THANK YOU !!
Acknowledgements
• Bob Harn
• Yeliz Firat
Buildingonthe Past, Respectingthe Future