Acknowledgement This research work would never have been undertaken without the initial suggestion and intellectual support of the former Vice-Chancellor of the University of the West Indies Professor; Rex Nettleford, who was every dear friend. I also wish to acknowledge the contributions of Professor Martin Cave from the University of Warwick and LSE and Michael Webb of Frontiers Economic, London both of whom commented on the initial papers and suggested ideas and improvements. I am also particularly indebted to Janet Mwaippo, my Tanzania Secretary, who had the tedious task of typing from the manuscript and also having to make endless corrections; to Sandra Griffiths who had the task of finally formatting the document and also to my wife Faye, who in addition to having to endure many lonely evenings, also had to undertake the burden of reading and editing the entire typescript. Her suggestions, especially from the point of her legal knowledge have helped to improve the presentation. Without the motivation and intellectual support of Vice-Chancellor Professor Rex Nettleford this work would not have been completed. Finally, to my supervisor Professor Edwin Jones, whose guidance and advice on a range of issues and comments on the draft chapters, contributed immensely to the final document. i Table of Contents Page ACKNOWLEDGEMENT i TABLE OF CONTENT S ii GLOSSARY vii LIST OF TABLES (with page Numbers) xvi LIST OF FIGURES (with page Numbers) xviii TEXT OF THESIS Chapter One Restructuring For Competition in Electricity Markets Introduction 1 The Economics of Electric Utility 2 Restructuring the Electricity Industry 8 The Impact of New Technologies on Scale Economics 9 Rise of Competition in Bulk Electricity Markets 12 Public Ownership VS Private Ownership 15 The Case for Private Ownership of Electricity 19 The Effects of Regulation 21 Vertical and Horizontal Restructuring 23 Electricity Industry Structural Models 26 The Wholesale Bulk Electricity Markets 31 Conclusion 34 End Notes 36 ii Chapter Two A Four Phase Development Model for Electricity Markets The Four Phase Development Model 44 Model One Stage: Franchised Monopoly Phase 47 Move Away From the Franchised Monopoly Phase 52 Model Two Stage: The Purchasing Agent Phase 55 Model Three: Bulk Electricity Market Phase 66 Bulk Electricity Market Design Options 73 Governance Structures of Power Pools and Exchange Markets 76 Model Four: Retail Competition or Consumer Choice Phase 78 Competitive Transformation of the Electric Utility Industry 86 Selection of Case Countries 93 End Notes 94 Chapter Three A Formula For Radical Reform: The British Electricity Experiment Introduction 99 1980s Political and Economic Thinking on Electricity Privatisation 103 The Pre-Privatisation Structure 108 Restructuring the England and Wales Electricity System 116 Privatisation Programme 122 Post-Privatisation Changes to the Industry Structure 125 The Scottish and Northern Ireland Electricity Reform 138 Bulk Electricity Market - The Pool 144 Critique and Changes to the Pool after 2000 152 End Notes 157 iii Chapter Four British Electric Utility Regulatory Reform The Case Against Rate of Return Regulation 161 British Approach to Utility Regulation 164 RPI- X Regulation 169 Rationale for Excluding Generation From Regulation 171 Transmission Price Regulation 172 Distribution Price Regulation 176 Regulating the Competitive Transformation of the Retail Market 179 Changes to UK Regulation 183 The Verdict 186 End Notes 192 Chapter Five Ownership, Deregulation and Privatisation of Electric Utility; The Jamaican Case The Early Years 196 Private Franchised Monopoly and the Failure of Public Utility Commission Style 199 Regulation State Ownership and Government Failure 202 Industry Structure and Deregulation of Generation 206 Problems with the Introduction of the Single Purchaser Model 209 The Case for Unbundling the Utility 211 Aborted Privatisation 218 Public Ownership with Internal Management Performance Contract 222 The Final Act of Privatisation 230 Summary and Conclusion 234 End Notes 240 iv Chapter Six Radical Restructuring and Privatisation of a Small Electric Utility Market: The Case of Bolivia Introduction 243 The Structure of the Industry Before Unbundling 248 The Restructuring Programme 251 The Divestiture Programme 253 Bolivia Bulk Wholesale Electricity Market 259 The Regulatory Framework 263 Regulation of Transmission 264 Regulation of Distribution Prices 266 Outcome 268 Lessons Learnt 273 End Notes 276 Chapter Seven Sub-Saharan Africa Electricity Reforms: Three Country Case Studies Macro-economic and Market Background 279 Rationale for Public Ownership of Electric Utility 284 Financial, Economic and Technical Performances 285 Institutional, Managerial and Regulatory Failures 287 The Role of Donor Agencies 289 The Challenge of attracting Foreign Direct Investment 290 Cote d’Ivorie Reforms 295 The Reforms in Ghana 300 The Tanzanian Power Sector Reforms 304 Regional Interconnection Opportunities 309 Conclusion and Policy Implications 310 End Notes 314 v Chapter Eight Analysis and Conclusion Global Trends In Electricity Sector Reforms 317 Structural Options 317 Purchasing Agent as a Reform Option 319 Bulk Electricity Market as a Reform Option 321 The Main Sub-options Under Bulk Electricity Markets 323 Retail Competition as a Reform Option 325 Main Lessons Learnt 327 The Rise of the Regulatory State 329 Conclusions 330 End Notes 333 BIBLIOGRAPHY 335 vi Glossary AGR Advanced gas cooled reactors ATC Available transmission capacity Averch – Johnson Effect Phenomenon under ROR regulation whereby regulated firms have incentive to over-invest in capital intensive solutions relative to other inputs as this increases the rate base and hence regulated returns; lead to “gold planning” over investment AES Allied Energy Systems Americas Inc. Affermage Contract An exclusive operating lease where the lessor takes responsibility for capital investment and the lessee operating costs and operating risks originated in francophone countries ABB Asea Brown Boveri ADB African Development Bank ANARE I’Autorite Nationale de Regulation du Secteur de I’Electricite BOOT Build Own Operate and Transfer BOT Build Operate and Transfer BPC Bulk power contract; contract for energy with power taken at any point in the system Base load The lowest load continuously supplied by electric power system over a period of time BNEL British Nuclear Fuels Plc By-pass Right of certain category of customers to purchase directly from producers (generators) or the market, requires equal access to the network BST Bulk supply contract BEA British Electricity Authority CCGT Combined cycle gas turbine vii CCGG Combined cycle gas generation CEGB Central Electricity Generating Board CfD Contracts for Difference CRI Centre for the Study of Regulated Industries Capacity payments Payments covering the fixed or capital cost of a generating plants capacity, cost is sunk costs. Competition for market Form of competition involving two or more firms competing for the right to supply a monopolistic market Competition in the market Product market competition, rivalry between two or more firms to meet customers demands CPI Consumer Price Index Constrained-on Generation set which despite their output being offered at a price in excess of SMP are called on by the transmission operator to operate as a result of limitations on the transmission system, demand forecasting errors or breakdown of other generation sets. Constrained-off Generation set which despite their output being offered at a price equal to or lower than SMP are instructed by the TO to operate as a result of limitations on the transmission system, demand forecasting errors or breakdown of generation sets. COBEE Compania Boliviana de Energia COM IBOL Corporacion Minera de Bolivia CESSA Compania Electrica Sucre S.A CRE Cooperativa Rural de Electricidad CNDC Commitee National de Despatcho de Cargo CDC Commonwealth Development Corporation CIE Compagnie Ivoirienne d’Electricite CIPREL Compagnic Ivoiriene d’Production de Electricite CRI Centre for the Study of Regulated Industries viii DGES Director General of Electricity Supply DGFT Director General of Fair Trading Dispatch Issue of instruction to release generated power into the electricity system Designated customer A customer who’s expected annual consumption will be less than 12,000 kWh, but excluded customers with unmetered supply or who are under the terms of a multisite contract or who have half-hourly metering or maximum demand metering DTI Department of Trade and Industry DGUR Director General of Utility Regulation ELECTROPAZ Electricidad de LaPaz S.A. EATS Economically adapted transformer system EECI Energie Electrique Cote d’Ivoire FNEE National Electricity Fund ENDE Empresa Nacional de Electricidad S.A ECG Electricity Corporation of Ghana ELFEC Empresa de Luz y Fuerza Elictrica de Cochabamba S.A. ELFEO Empresa de Luz y Fuerza Electrica de Oruro S.A EU European Union ESI Electricity Supply System ESMAP Energy Sector Management Assistance Programme EdF Electricite de France EWG Exempt wholesale generators ERB Electricity Regulatory Board E&W England and Wales FCC Federal Communication Commission ix FERC Federal Energy Regulatory Commission Gross pool Mandatory trading of all electricity through the centralised bulk electricity market GDP Gross Domestic Product HE Hydro Electric (Scottish) Hedge Contract Financial contract typically between generator (seller) and retail/distributor (buyer) which establishes a fixed price for a defined amount of electricity (seeks to hedge price risk in the spot market) IMF International Monetary Fund IPP Independent Power Producer ISD Independent Systems Operator ISER Institute of Social and Economic Research IEA Institute of Economic Affairs Installed capacity The highest capacity of output measured at the main alternator terminals which generating station or generating set is designed to be able to maintain indefinitely without causing damage to the plant IFC International Finance Corporation IDA International Development Agency IPTL Independent Power Tanzania Ltd. JPSCo Jamaica Public Service Company Ltd. JTC Jamaica Telephone Company Ltd. JLPCL Jamaica Light and Power Company Ltd. JPUC Jamaica Public Utilities Commission JPPC Jamaica Private Power Company Ltd. JEP Jamaica Energy Partners Ltd. LNC Leucadia National Corporation x LOLP Loss of load probability LRMC Long run marginal cost LDC Load Dispatch Centre VOLL Value of loss load MMC Monopolies and Mergers Commission MPP Merchant Power Plant MA&SO Market Administrator and System Operator Manweb Manweb Plc. Merit Order Dispatching of generator sets in an interconnected system ranked to establish economic order of preference usually based on the incremental cost of generation; from lowest cost to highest cost in ascending order NED Northern Electricity Department NP National Power Plc. NE Nuclear Electric Plc. NIE Northern Ireland Electricity Plc. NGG National Grid Group NGC National Grid Company NETA New Electricity Trading Arrangement NSHEB North of Scotland Hydro Board Open access Similar to common carriage, traditionally a common carrier was required to provide transport to all firms requesting it without discrimination OFGEM Office Gas and Electricity Markets OECD Organisation of Economic Cooperation and Development OFT Office of Fair Trading OCGT Open cycle gas turbine xi OUR Office of Utility Regulation PES Public Electricity Supplier PE Public enterprise PJM Pennsylvania – New Jersey – Maryland (used to refer to this regional power market). PPA Power purchase agreement PUC Public Utilities Commission PURC Public Utility Regulatory Commission PWR Pressurised water reactor PX Power Exchange PSP Pool selling price, price which forms the basis of payments for electricity by suppliers in the E&W Pool PPP Pool purchase price – price which forms the major part of the generator revenues under the pool trading system PURPA Public Utility Regulatory Policy Act Pool Electricity trading market for bulk power in England and Wales Peak Load That part of power demand which occurs for relatively short period. Plant designed for peak load may operate for only 30% of the time Pumped Storage Use of turbines to pump water to a reservoir at the top of a hill during periods where it can be released to generate power in peak periods, or called on to meet sudden shortfall PPT Private purchase tariff QF Qualifying facilities ROR Rate or return (system of controlling profits of regulated company) Revenue Cap System of controlling prices of regulated companies that focuses on the maximum revenues (rather than profits or xii price) the firm may recover from a regulated activity (variation of price cap) REC Regional electricity company Rate base The valuation of a firms capital and costs used to determine the allowable return under ROR regulation Reserve Additional generation capacity which is held in reserve to cater for the possibility of plant breakdowns and unexpected surges in demand Run of the River A hydro electric system using flows of stream as it occurs and having little or no reservoir capacity for storage of water Ramsey Pricing Theory of efficient pricing aimed at reducing the distortion impact; used as a principle for designing two or multi-part pricing in utilities. Regulatory Period Typically taken as 5 years, at the end of which the utility presents plans for investment and is subject to its price being reviewed. SADC Southern African Development Community SSAP Southern Africa Power Pool SSA Sub-Saharan Africa SIN Siestema Inter Connectedo National SEPSA Servicios Electricos Potosi S.A. SIRESE Sectoral Regulatory Authority SE Superintendent of Energy SB Single buyer SMP System marginal cost being the highest price of a generating set in the pool which clears the market SRMC Short run marginal cost SOE State own enterprise STS Second tier supplier, supplier licensed to sell to liberalised xiii customers in a franchised zone SSEB South of Scotland Electricity Board SWALEC South Wales Electricity Plc SWEB South Western Electricity Plc SEEBOARD SEEBOARD Plc. Spinning reserve The status of generating sets in which the turbines are spinning and able to generate more electricity in response to the system Spot market Market in which bulk electricity (commodity) is traded, establishing a price which equates supply and demand for each half hour or hour of day TANESCO Tanzania Electricity Supply Company Ltd. TDA Transportadora de Electricidad S.A. T&D Transmission and Distribution Company TAI Total average interruption TPA Third Party Access TCT Total cost of transmission TI Tariff income TO Transmission Operator “Take or Pay” A contractual obligation which requires a firm or party to take or pay for electricity or fuel or other contractual obligation, which requires the company to make payment in event that the firm does not take the electricity or fuel Uplift An amount of the PPP giving the PSP to cover additional cost due to forecasting errors, transmission and operational constraints and provision of ancillary services UWI University of the West Indies UEB Uganda Electricity Board VRA Volta River Authority xiv VOLL Value of loss load WEM Wholesale electricity market Wheeling Transportation of electricity across (high voltage) transmission (or lower voltage) generation lines WIEC West India Electric Company Ltd. YPFB Yacimientos Petroliferos Fiscales Bolivanos Yardstick competition Use of performance comparisons between different suppliers to provide competitive discipline often linked to specific incentive rules to reward above average performance and penalise below average performance. “X” A factor used to indicate level of productivity improvements that can be obtained, calculated as the Retail Price Index less the productivity factor “X” Abbreviation of Units kW Kilowatt (1000 watts) kV Kilovolts (1000 volts) kVA Kilovolt ampere (1000 volt-amperes) kg Kilogram km Kilometre MW Megawatt (1000 kilowatts) MWh Megawatt hour (1000 kWh) GW Gigawatt (1000 MWh) GWh Gigawatt hour (1000 MWh) kWh Kilowatt hour (1000 watt hours) xv List of Tables Table 1 Characteristics of the UK System in the 1980s Table 2 Electricity Privatisation Programme 1990 – 1996: Sales Proceeds Table 3 Output By Market Share – Percentages Table 4 Installed Capacity in England and Wales: 2000/01 Table 5 Percentage Share of New CCGT Capacity Commissioned: 1990 to 2000 Table 6 Fuel Use Changes in Percentage Share: 1990/91 and 2000/01 Table 7 Summary of Who Own Whom – 2000 (Intermediate holding companies have been omitted for clarity) Table 8 Changes in Electricity System’s Workforce Table 9 Profitability of ESI After Privatisation Table 10 Characteristics of Distribution Table 11 Pre and Post-Management Contract Results - Jamaica, JPSCo – Annual Revenues and Profitability Table 12 Jamaica – JPSCo, Number of Employees/Labour Productivity and Number of Customers Table 13 Energy Losses – Jamaica JPSCo Table 14 Pre- and Post-Performance Management Contract Results – Bulk Power and Industrial and Consumer Retail Prices Table 15 ENDE Generating Plant Capacity – 1994 Table 16 Bolivia, Installed Generation Capacity in 1994 Table 17 Generation Companies Capacity in the SIN – 1996 Table 18 Electricity Demand by Distribution Within the SIN:1996 Table 19 Post – Privatisation Distribution of Share Ownership xvi Table 20 Bolivia: - Revenues From Divestiture Table 21 Bolivia Average Real Retail Tariff – (in 1997 US¢/kWh) Table 22 Bolivia Profitability, Return on Equity – Percentage (After Taxation) Table 23 Bolivia Labour Productivity: GWh per Employee Table 24 Bolivia Number of Customers in the Interconnected System by the Distribution Companies Table 25 Bolivia Energy Losses: Percentages Table 26 Macro-Economic Characteristics of Case Countries Table 27 Electricity System’s Characteristic: Year 1993/94 Table 28 Economic Characteristics: Decades of the 1980s and 1990s Table 29 Regulatory Regime in Selected SSA Countries xvii List of Figures Figure 1 Figure 2 Figure 3 Figure 4 Figure 5 Figure 6 Figure 7 Figure 8 Figure 9 Figure 10 Figure 11 Figure 12 Figure 13 Figure 14 Figure 15 Figure 16 Sub-Additivity and Economics of Scale and Natural Monopoly Cost Curve Showing Plant Size – 1930-90 Franchised Monopoly Model Franchised Multiple Distribution Structure Franchised Monopoly (Phase 1 – Model One) Integrated Industry Structure Purchasing Agent Structure (US System after Liberalisation) T&D as Single Purchaser (Horizontally Unbundled Generation) Transco as Single Purchaser (Horizontally Unbundled Gencos and Discos with Large Consumer Bypass) Single Purchaser (Phase Two Model Two) Industry Structure (Electricity Flows) Single Purchaser (Phase Two Model Two) Industry Structure Financial Flows) Bulk Electricity Market Structure (UK System Immediately after Privatisation) Electricity Wholesale Market (Phase 3 Model Three) Industry Structure (Electricity Flows) Electricity Wholesale Market (Phase 3 Model Three) Industry Structure (Financial Flows) Bulk Electricity: Mandatory Power Pool Design Bulk Electricity: Balancing Trade Design Customer Choice Structure (Open xviii Figure 22 Network Structure) Retail Competition (Phase 4 Model Four) Industry Structure Electricity Flows Retail Competition (Phase 4 Model Four) Industry Structure Financial Flows Four Phase Electricity Restructuring Model Pre-Privatisation UK Industry Structure (1997) Annual Average Electricity Price (1999/2000 prices) Price Reductions Since Privatisation Figure 23 CNDC Organisational Structure Figure 24 SSA Restructuring Framework Figure 17 Figure 18 Figure 19 Figure 20 Figure 21 xix 1 Chapter 1 Restructuring For Competition in Electricity Markets Introduction Electricity has three important characteristics and these features have over the years had a major impact on the structure of the industry and its trading arrangements. First, electricity cannot readily be stored, with the result that the demand at any point in time must be matched by supply from generators, and failure to balance power inflows and outflows can within seconds result in serious deterioration of the systems operation. Second, it can only be transported through wires, which makes it a network industry. The nature of electricity is such that it is a formless product and in its transportation from generation to consumers it is not possible to trace its source of origin. Kirchof’s law states that; ‘power flows automatically and instantaneously along the path of least resistance and must conform to system- wide constraints of energy balance and frequency1‘. Arbitrage in power markets cannot be conducted as though electricity will flow along a path determined by contracts as in the case of other markets. Thirdly, electric utilities carry natural monopoly characteristics, with the result that until recently the industry was partially or totally excluded from market competition. These three features critically presented major challenges to reformers in the 1980s in their quest to move to a competitive and privatised industry structure. How these problems are resolved have had a major bearing on the transformation from a single utility monopoly industry structure, which dominated the scene for most of the post-war years to a market based structure. 2 Electricity production and supply consist of four district activities in the production and delivery value chain; generation at power stations, transmission through high voltage wires from generation plants to distribution wires, distribution through low voltage wires to customers’ premises, and supply, the buying and selling of electricity to customers or end users. The generation process involves production using various sources from hydro-electricity, internal combustion engine, steam turbines powered by fossil fuels, nuclear plants, wind driven turbines, photovoltaic technology and other forms of renewable energy. The transmission function is more than simply a transportation network. It is a complex coordinating system that integrates the various generators into an overall structure to provide reliable flow of electricity to dispersed distribution points or demand nodes and involves transformers, substations, as well as the transmission wires. Historically, the control function has been addressed within the context of a vertically integrated industry where all four functions come under one integrated management control structure. It has been estimated as a general rule that generation accounts for about 65% of total cost, transmission 10%, distribution 20% and supply 5%. These proportions vary in different systems depending on technology, size of country and density of connections. The important point of note is that generation accounts for the greater portion of system cost. The Economics of Electric Utility The industry is said to possess natural monopoly characteristics with significant benefits from economies of scale and scope. Investments in the electric production and the deliveryvalue chain, especially in transmission and distribution are specific and once costs are incurred they cannot be recovered if a decision is made to leave the market, given the fact of low residual value of specialised goods that cannot be used in any other productive activity. These irreversible costs act as strong barriers to entering and leaving the market. The large investments, long capital recovery period and irreversible costs further present a high level of risk to potential investors. In order to mitigate these risks, investors tend to seek long-term guarantees best obtained from integrated systems, in order to reduce the uncertainty of trading with third parties. Major changes in technology, however, have led to increased questioning of the extent to which scale economies continue to exist. However, a number of commentators’ for example, Gegax and Nowtony2 (1993) have argued that: 3 “In short a large body of evidence indicates that the electric utility industry has not exhausted economies of scale. Regulators cannot justify a policy to encourage entry into the electric utility industry solely on the basis that economies of scale in generation have been exhausted”. For these two economists, radical restructuring of electricity industry and the imposition of entry conditions are unwarranted in what remains an essentially natural monopoly and were not called for in the USA in the early 1990s. Joskow and Schmalensee (1983)3 stated that there is little doubt that the establishment of regional or national network can potentially be of great benefit to electricity consumers. To be included among the gains are the realisation of plant level scale economies, increased reliability of supply, efficient production from coordinating the operations of differing marginal costs of supply, lower total capacity requirements, resulting from aggregation of differing load characteristics, economies from coordination of maintenance schedules and economies from responding to emergencies. Electric industry has been considered over the years as a natural monopoly. For Baumol4: “a natural monopoly exists when a single firm can produce a desired level of output at a lower total cost than any output combination of more than one firm”. There is therefore, the condition of sub-additivity. Another important economic condition is that economic efficiency is achieved when prices equal incremental or marginal cost. However, where for a strong natural monopolist incremental cost is less than average cost, that firm is not viable. The monopolist will need at least to recover average cost. This, however, may not be the most economic outcome. Baumol5 Panzar, and Willig states that: (sub-additivity) “Surely, is what anyone has in mind, at least implicitly, when speaking of a monopoly being “natural” and that is what economists were undoubtedly groping for when they (as it turns out, mistakenly) identified natural monopoly with economies of scale”. Alternatively6 Gegax and Nowotny state that: 4 “an industry has been called a natural monopoly if a single firm producer can find price-output combination that precludes profitable entry by others”. For Gegax and Nowotny7: “The issue of economies of scale arises because such a cost condition is sufficient, but not a necessary condition of natural monopoly in a single product firm. A single product firm exhibits economies of scale if its long run average cost function is decreasing. While it is true that a production process, which exhibits economies of scale, is sub-additive at that output level, a production process may also be subadditive though it exhibits increasing average cost. It is a stronger condition to require decreasing average cost, than to require only that costs be sub-additive while allowing for increasing average cost. A firm that exhibits decreasing average cost is called a strong monopoly. A firm that exhibits increasing average costs, but whose costs are sub-additive is a weak monopoly”. A weak natural monopoly may not be able to prevent entry to the industry, however, regulators sometimes prefer a single firm producing that output, rather than several firms producing the same output and in so doing regulate entry, in which case prices must also be regulated. Electric transmission and distribution show major economies of scale (increasing returns and decreasing average costs), which has made it preferable, for production to be carried out in largescale integrated systems. Economies of scale in the generation sector depend on the relative size of demand with respect to the optimal scale of production for each of the respective production technologies. Generation is a weak monopoly. Beyond a certain level of demand, located on an upward curve of average costs, it is possible to reach a situation of decreasing returns and dis-economies of scale, even for the technology having the highest optimal scale of production. Even in the upward part of the average cost curve, where returns are declining and dis-economies of scale occur, or as shown in Fig. 1 at points 1, 2 and 3 there can be sub-additivity and as a result a natural monopoly without the benefit of economies of scale. In networks such as water pipeline, rail track, gas pipeline and power transmission and distribution it would be a waste of society’s resources to have several parallel networks of the same type 5 competing with each other. If they were to compete only one firm would survive. Network systems also display high sunk costs, requiring large and lumpy investments to enter and to maintain operation in the market8. In a multi-product firm it is economies of scope, which results in sub-additive conditions as stated by Baumol, Panzar and Willig (1982) 9. It is the indivisibilities and specialisation, which creates jointness and distinguishes the multi-product firm from the single product firm. Economies of scope exists in the multi-product firm if it is less costly for it to produce a given combination of outputs, than to produce the same level of each of the distinct output in separate unbundled firms. It is the economies of coordination that determine sub-additivity of the cost function in an electric system. COSTS D: DEMANDS A,B, & C: OPTIMAL SCALE S:SUBADDITIVITY LIMIT (ONE CO. PRODUCES AT LOWER COST) NATURAL MONOPOLY COMPETITION Source: Illustration developed from Baumol’s condition of sub-aditivity and economies of scale. Coordination economies arise from successfully matching diverse usage or demand patterns with a capital-intensive supply system. Network economies on the other hand arise from the joint production of multiple services on a network and the low production incremental cost of adding 6 more services. Whether an electric utility is vertically integrated or unbundled there is still the necessity for a continuous balancing function or for coordination and this coordination creates an external cost10 in the unbundled firm, while it is internalised11 in the integrated utility. Unforeseen demand surges or equipment failures, require central intervention by the grid operator, which may require some generating plants to be unexpectedly dispatched or turned off. The central grid operator requires a considerable amounts of information to be able to have substantial control over the whole system. Should there be an unbundled structure an externality effect to other firms is created, in that operators may not always bear the full consequences and costs of their decisions within the system. Decisions of one firm can drastically affect the systems viability and reliability and in so doing impose costs on others who are not party to the decision. The firm may, therefore, be opportunistic and engage in activities knowing that it is not singularly meeting the cost of its decision. Where several unbundled firms exist in the chain of production process, one firm must provide the balancing and system dispatch function. If the vertically integrated structure remains, then the utility is in a position to use its control of the transmission to discriminate in favour of its own generation sets. In the vertically integrated electric utility the single firm bears the full costs or derives the full benefits from its decision and hence the externalities are internalised. Internalisation is no longer possible when several independent firms operate at different stages of the production process. New institutional arrangements are needed to facilitate coordination in the unbundled production process. Reliance on voluntary cooperation to resolve transmission issues may be difficult in a competitive environment. The establishment of central coordination in order to overcome the externalities associated with the unbundled structure would seem to be in conflict with the goal of promoting competition through the encouragement of individualistic decision-making. The benefits of coordination have to be balanced against the benefits of competition and how this trade-off is addressed is one of the important features of recent electricity marketing arrangements. How to balance the natural monopoly in transmission with competition in the potentially competitive generation sector has been a central issue in designing power markets. Long-term bilateral contracts or power pools are now creating these arrangements. They, however, have Williamson’s (1979)12 transaction costs associated with them; 7 “Transaction costs are central to the study of economics; identification of the control dimensions characterising transactions, describes the main governance structure of transactions and indicates how and why transactions can be matched with institutions in a discriminating way”. The central focus of transaction costs is exchange of goods and differs from principal agency theory in that the former is concerned with contracts of labour and exchange of services. Transaction costs result from the several contracts that flow from more than one operator in the unbundled structure. In Tanzania, in the case of the proposed Songas Independent Power Project (IPP) there are over 30 contracts involved, while in Jamaica, IPP entry into the production process resulted in an even greater number of contracts. Firms often prefer to enter into longterm contracts, with very detailed conditions to reduce uncertainty, as well as to reduce the risk of rent seeking or opportunistic behaviour. The more firms in the system the greater the number of contracts and the higher the transaction costs are likely to be. Vertical integration also provides opportunities for cost savings in resource usage at the planning stage through the timing of needed investments, as well as in scheduling maintenance activities. At the same time, horizontal integration within the single firm may also create lower costs, and provide for increased load diversity, while lowering the amount of reserve capacity. All power systems need reserve capacity, both reserve margin and spinning reserve to accommodate unexpected increases in demand, equipment failures and regular maintenance. Joskow, (1997)13, has also argued that the separation of generation from transmission does “not fundamentally transform a sector with natural monopoly characteristics to one where these characteristics are completely absent. - - - - - a separate generation sector now makes sense in that generation of electricity is no longer a natural monopoly as a consequence of technological change is incorrect”. Generation has always been a weak natural monopoly and the tradition has always existed in many systems where there has been numerous un-integrated generating and transmission entities unaffiliated to the fully integrated utilities. Beesley and Littlechild (1997) 14 counter this argument by stating the view that: 8 “The unbundling of organisations might involve sacrificing economies of scale is dubious, for the state of the industries were determined largely by political or administrative, not market forces. In the absence of competition one cannot know in advance precisely what structure will prove efficient”. The factors that militate against unbundling are those that would lead to loss of the benefits of internalisation. Whether there is a net benefit from un-integrated operation depends to a large extent on whether the benefits from competition can more than offset the cost disadvantages of unbundling, loss of internalisation and increased transaction costs. In this respect system size, density of connection and a number of other factors must be taken into consideration. Restructuring the Electricity Industry The features outlined above have in the past led to an industry that has been characterized by large systems. Experience of the past has also been that utilities would build larger and larger power plants, often of sizes up to 4000 MW to benefit from scale economies in the generation sector. The preferred mode of operation was not only vertical integration but horizontal integration as well. This conventional industry structure more or less prevailed up until the 1980s. The first major structural change to the industry commenced in 1978 in the United States with the introduction of the Public Utility Regulatory Policy Act. (PURPA)15. This initiative was, however, to have a far reaching implication for the industry, and this implication has extended to the global arena. PURPA gave rise to a new player in the market, the independent power producer and in so doing unleashed for the first time major competitive forces within the industry. Experiences in the USA soon showed that IPPs could bring plants into operation often in very short time frame and on budget. A direct result of this development is that IPPs share of generating capacity in the USA increased from 3.6% in 1987 to 7.2% in 1995. Since 1990, IPPs have contributed over half of all new investments in the generating sector in the USA. In most instances these plants were of the sizes of 50-80 MW and could reliably be integrated into the system in modular form. Additionally, existing utilities were restricted by the law from owning more than 50% of the capital of the new producers. They in turn were restricted from making sales direct to purchasers other than the utilities. 9 In effect small independent power producers were given a protected market entry as wholesalers of bulk power supplies. Price determination was based on the utilities full-avoided cost or the incremental cost of adding new capacity. Although required purchase prices were to be at the incumbent utilities avoided cost, regulators calculated these prices in some states in ways that led to artificially high bulk electricity purchase prices. This further gave impetus to the growth and expansion of the IPPs16. Generally, they are permitted to sell at wholesale market-based rates and the Federal Energy Regulatory Commission (FERC) in return does not regulate these marketbased rates. PURPA therefore, facilitated the entry of the independent power producer with longterm power purchase agreements (PPAs) into the electricity market to supply new capacity on the basis of competitive bids and in so doing heralded large-scale entry competition into the market for the first time. IPPs, however, came to encounter restrictions on access to the incumbent utility’s transmission system. The introduction in 1992 of the Comprehensive National Energy Policy Act broke the incumbent utility’s monopoly of the electricity transportation system by imposing common carrier status on both transmission and distribution. IPPs and exempt wholesale generators (EWGs) on the basis of open access to the transmission and distribution system were for the first time able to supply bulk power to very large consumers or to the wholesale markets where they could sell at unregulated market rates. These developments expanded competition to another level that of wholesale competition among generating firms as distinct from competition for new capacity. The lower prices, which IPPs often charge later, resulted in divergences between the regulated prices of the incumbent utilities and the prices of the IPPs, with the result that IPPs were able in many cases to under bid the incumbent utility in proposed projects. The price of bulk power in the inter-utility wholesale market in the late 1980s in the USA was on average10% higher than the prices of the IPPs17. The Impact of New Technologies on Scale Economies It is not so much the institutional changes, however, but the impact of the new technologies (the new aero-derivative combined cycle generation often from cheaper natural gas) that has unleashed 10 the forces leading to the radical changes in the industry structure and its trading arrangements, as well as to increased competitive activities18. The advent of small, natural gas fuelled generators, coupled with falling prices of natural gas drastically reduced the capital cost of minimum efficient scale generating plants. These new combined cycle generating gas plants (CCGG), often have thermal efficiencies as high as 55% to 60% compared to the old coal or oil fired plants, with efficiencies of less than 40%. The fact that they are available in small systems made entry to the generation sector of the industry much easier19. These smaller systems are also easier to run and maintain than the larger scale plants. Additionally, they have reduced planning and construction lead-time and can be installed in a much shorter time frame. They are now produced in standardised units in competitive markets by several firms. It has, therefore, been easier for IPPs to obtain financing for new plants because of this shorter construction lead-time and lower financing costs. The development of combined cycle gas turbine (CCGT) plant has had a radical effect on the overall economies of generation. The fixed cost of installing a CCGT plant in the early 1990s in England and Wales was around US$600-650 per kilowatt, compared to US$750-800 for oil fired plant, US$900-1,200 for coal plant, and US$2,250 for a nuclear plant. Towards the end of the 1990s the capital cost of installation of the latest CCGT technology had fallen to US$373-450 per kilowatt. 11 Source: Hunt and Shuttleworth, Reproduced from ESMAP, World Bank ’Energy Service For the World’s Poor’, April 2000, p. 47 Fig. 2 above shows cost curves of optimal generation plant size, over the period 1930-1990. In the 1930s optimal thermal plant size was under 75MW. By 1970 optimal plant size had increased to 400 MW, increasing further to just less than 1000 MW by 1980. With the introduction of CCGT, optimal plant size has again fallen below 75 MW. New financial market innovations also allowed for the debt associated with IPP type (nonrecourse) financing, to be developed with the effect that the debt can be readily sold and hence the sunk cost hazard of investment experienced with large integrated plants are significantly minimised. The assignability of long term contracts also helps potential entrants to secure long term financing since a creditor can now step in and operate the system in the event that the buyer defaults. The market is therefore, made more contestable20. For Baumol: “a contestable market is one into which entry is absolutely free, and exit is absolutely costless. We use “freedom of entry” in Stigler’s sense, not to mean that 12 it is costless and easy, but that the entrant suffers no disadvantage in terms of production technique or perceived product quality, relative to the incumbent and that potential entrants find it appropriate to evaluate profitability of entry in terms of incumbent firms’ pre-entry prices”. With these developments, pressure has been building up in the USA since the latter part of the 1990s to extend competition from the bulk electricity market to the retail market. This would require generating companies or incumbent utilities to sell directly to final consumers in the franchised areas of the respective utilities, paying regulated rates for use of the utilities’ transmission and distribution lines. Rise of Competition in Bulk Electricity Markets There is no doubt that there has been a significant development in electric utility economics. Tenenbaum, Lock and Barker21 conclude that: “There is now broad (through not universal) acceptance that at least the generation function is potentially competitive. However, there is equally broad acceptance that the transmission function and at least the wires business in the distribution are in most circumstances a natural monopoly”. Joskow22 also supports the view that transmission and distribution sectors remain natural monopoly sectors. He however, maintains the position of integration and states that: “the available empirical evidence suggests that at the very least the distribution of electricity has important natural monopoly characteristics” He is also of the view that electricity supplies: “should continue to be distributed to retail customers by franchised monopoly companies, subject to price regulation” In Joskow’s view: “the optimal organisational form for an electric utility is incompatible with competition in distribution or transmission or with separate generation sector made up of competing firms” 13 He also voiced the view that: “vertical integration between generation, transmission and distribution and horizontal integration between interconnected generation plants represents the most efficient organisational arrangements for supplying electricity”. Joskow failed to separate the electricity retail business, which is a competitive segment of the industry from the distribution wires business, which continues to display the natural monopoly characteristics. In contrast Yarrow23, however, contends that: “While arguments for the existence of significant economies of coordination are generally sound, the attainment of such benefits does not necessarily require the creation or retention of a single company responsible for all electric generation and transmission activities-------------------------- for a number of reasons, however, scale economy arguments in favour of a single firm production are not entirely convincing even accepting the economies”. The old economy of scale argument today for a single firm production is more powerful when used to support a case for the conventional fossil or nuclear fuel based plants. The French Electricite de France (EdF) which is 85% nuclear based would seem to fall into this category. Economies of learning are much more significant for nuclear technologies. There is, therefore, a strong rationale for easing entry restrictions based on the premise that economies of scale have been exhausted from centralised production technology. Economies of scale are exhausted if the rate of increase in production cost rises fast or faster than output. A direct result of these developments has been growing liberalisation of electricity generation markets since the early 1990s. The England and Wales system; 52,400 MW, Argentine 15,000 MW and Chile 3,000 MW, which were the first set of markets to undergo restructuring were however, considered to be fairly large systems where scale economies may have been exhausted at the time of divestiture. There was still a debate in the early 1990s in the UK that 50,000 MW was the minimum efficient scale system for the operation of an electricity company. 14 Christensen and Greene24 focussing on firm level in 197624 concluded that economies of scale existed up to 4000 MW. Atkinson and Halverson25 in 1984 concluded that scale economies continue to exist at firm level up to 12000 MW. Well over 100 countries, however, have systems smaller than 1,000 MW. The question has, therefore, arisen as to how small a system should be before a competitive industry operation can be ruled out? This is the type of question several African countries with small systems must answer should they decide to take to liberalisation of their electricity markets. In the larger system it will be possible to provide for more radical restructuring and more intensive competition, as there is still the possibility of large size operating units, following from the unbundling process. In as late as 1990 consultants examining the Kenyan system, where the installed capacity was then 706 MW concluded that there was no scope for competition between a horizontally unbundled and separately owned generation sector. The consultants further concluded that even though there were no competitive possibilities in generation there were, however, benefits to be gained from vertical separation of generation into a single operating company. These conclusions were to influence the restructuring exercise in Kenya with the result that generation was unbundled into a separate company from transmission and distribution. Jamaica voiced pretty much the same conclusion in 1993 against disintegration and stated that separation of generation was not a feasible option and that the unbundling of the electricity industry was more a policy option for countries with large systems. In the opinion of Coopers and Lybrand; the Jamaican consultants at the time, horizontal separation of generation and vertical separation of transmission and distribution and further horizontal unbundling of distribution for the Jamaican system was not economically feasible for an operation of such small size. The World Bank in 199426 also argued that: “a minimum market size maybe necessary before unbundling becomes worthwhile, however, and in the very small markets of many low income countries, vertical separation of generation from transmission and distribution may not produce sufficient efficiency gains to offset the additional co-ordination costs”. The question still remain how small is small? Recent electricity industry restructuring has involved two distinct activities, changing ownership or privatisation and changing the industry’s structure by 15 unbundling vertically and horizontally. Privatisation should not be confused with vertical and horizontal restructuring. The effects are different, although they maybe reinforcing. Private ownership and operation, of itself, carries certain costs and benefits. Public Ownership Vs Private Ownership The historical approaches to dealing with electricity and other network utilities, especially over the last 50 years, have been state ownership. Electricity production in developing countries has been regarded as a public service and this has been fundamental to their development strategies. The placing of electricity to meet micro-economic and social development has been a basic policy strategy of most post-independence administrations. State ownership is said to provide the environment that would ensure the attainment of social, political and welfare maximising objectives. Electric utility, particularly when state owned, has been required to undertake costly tasks, such as uniform or below cost pricing to certain segments of consumers or is required to provide financial support through cross-subsidies to other sectors of the economy as in the case of support to coal mining and the nuclear industries in the UK. Such policies have resulted in substantial departure from efficient allocation of resources and the attainment of productive and allocative efficiencies. When prices are below the cost of production and such prices are guaranteed to all users and not just to those who need it most, the result is over consumption and unjustified waste. This concept was not only shared by developing country administrators, but by multi-lateral and bilateral organisations as well as most donor agencies. Infrastructure projects were seen as a means to alleviating social inequalities and promoting development. Experiences of state management of utilities, especially in developing countries have been well documented. Political intervention in day to day operations and lack of managerial accountability criteria for evaluating performance of public enterprises have resulted in a catalogue of disaster, with the sector characterised by very low levels of service availability, high levels of disinvestments, poor and inconsistent services, low productivity and excess and burdensome debt services costs to tax payers. Private ownership and government regulation also may not prove to be the answer. Intimately tied to the structural problems are regulatory deficiencies. In most 16 developing countries regulation as an economic concept, that is a set of legal and institutional provisions that seek to redress inefficient market operation in cases where there is market failure are relatively unknown. Moving from a fully state owned industry with modest restructuring, such as separation of generation from transmission and distribution and privatisation may provide the opportunity to obtain some of the benefits of private ownership. Strong theoretical arguments have been advanced over the years to support the transfer of ownership from the state to the private sector. These arguments have been based on the theories of property rights - De Alessi (1980)27, Alchain (1965)28, Demsetz (1966)29, Furubotn and Pejovich (1965)30 - principal and agency; Rees (1965)31; Jensen and Meckling (1976)32, Aharoni (1986)33, Bös (1991)34, Parker and Stephen (1996)35 transaction cost economics; Williamson (1979)36, North (1961)37 - public choice; Tulloch (1965)38, Niksanen (1971)39, Buchanan, et.al., (1978)40, Mitchell (1988)41. The principal and agency theory42 states that publicly held firms are not exposed to the discipline of product and financial market, they do not face the threat of takeovers, the competitive market for management and hard budgets and they are not exposed to bankruptcy. monitoring is at best very weak. Shareholder Private ownership is said to change the motivation of management towards profit making and leads to higher levels of efficiency, especially where a competitive environment is provided. A private firm will be less willing to provide uneconomic or subsidised services. Private firms have a general incentive to produce services in quality and the variety, which consumers prefer. In general, principals are assumed to be better risk bearers than agents, while agents are assumed to be specialised managers. Agency problems are more acute when the interests of agents and principal diverge, as is more likely with public enterprise. Beesley and Littlechild (1977)43 have argued, therefore, that ownership matters. The property rights theory44 states that the inability of the taxpayer to transfer individual rights, so as to capitalise on gains and losses, as is the case with the public firm reduces the individual’s incentives to minimise cost and maximise return. The setting up of opaqueness in the firm’s decision-making process makes it difficult for individual taxpayers to directly influence management decisions. For property rights the issue is one of incentives, in that under public ownership there are weak incentives for efficiency enhancing behaviour. 17 Public choice theory on the other hand places emphasis45 on the incentive structures facing the public officials. Cost efficiency of the firm takes second place to other political issues. Bureaucrats it is argued will maximise, their utility functions by trading privileges to special interest groups in return for various financial or social benefits. Politicians are vote maximisers often to the detriment of social welfare. They also trade special privileges in return for votes. The general conclusion of public choice is that political maximisation is often in conflict with cost efficiency and the tendency is for political maximisation to replace cost efficiency. An example of this practice has been years of cross-subsidy of the electricity industry in the UK to prop up the coal industry and certain manufacturing interests in order to secure the votes of the unionised workers in these industries. Public choice theory has had significant impact on public policy formulation, especially in the utilities since the 1970s. As early as 1970s, Friedmann (1974)46 highlighted the point that the demarcation line between public and private enterprise was in a flux, with many striking similarities. In the 1970s it was more the state that was invading the traditional private enterprise preserves. Since the 1970s, further breakdown of the demarcation barriers has come more from the private sector invading areas, which traditionally were public enterprise preserves. Friedmann, however, advanced the view that: “two further significant points which have often been forgotten in the debate. First there are three criteria as determinative of the question whether an enterprise is called public. They are: (a) who owns them? (b) Where do they get their financing? (c) How much control is exercised by government over them?” In the case of public enterprise, ownership is less important, in terms of economic performances. More crucial is the level of participation in management by the government. The higher the level of direct ministerial and political intervention in management, the more likely efficiency will be impaired. In the case of private enterprise, ownership may also be less important. Many enterprises remain legally private in terms of ownership, but in effect are dependent on state financing; through grants, subsidies, interest free loans, long-term advances on public contracts and this may compromise or defuse their commercial commitments. 18 There is also substantial empirical research evidence to support the position that private firms perform more efficiently than public firms and that the transfer of ownership from the state to private hands leads to improved efficiency. Atkinson and Halverson (1986) 47 Boordman and Vining (1989) 48, Bishop and Kay (1989) 49, and more latterly Shirley and Nellis (1991) 50, Goodman and Loveman (1999151 have presented empirical analysis to support the position that private ownership and privatisation itself brings superior performances. One of the most thorough empirical evidence has been the study carried out by the World Bank; Galal, Jones, Tandon and Vogelsang (1992).52. They analysed the post-privatisation performances of twelve companies in Britain, Chile, Malaysia and Mexico to determine whether the transfer to private ownership increased efficiency – and, if so, how the cost benefit of adjustment were allocated. Net welfare gains were identified in eleven of the twelve cases. Peltzman (1971)53 reaches the conclusion that price structures of public enterprises are less responsive than private enterprises to cost of serving specific consumer groups. For Peltzman: “The willingness of government enterprise management to trade profits for political support will lead managers to use the pricing system as a mechanism for redistributing wealth within the political constituency”. Megginson, Nash and Randenborgh (1994)54, in a more elaborate study of 149 companies listed as being privatised, compared post and pre-privatisation performances of 61 companies from 18 countries and 32 different industries and found that mean and median profitability, real sales, operating efficiency, output per employee and capital investment spending increased significantly after privatisation. The conclusion also showed that operating performances improved in both non-competitive and competitive environment, that improvement in profitability was not due merely to increases in prices and that privatisation itself – the involvement, of private investors in a firm’s ownership structure and control critically impacts on a firms operating and financial performances. The World Bank 1994 - World Development Report55 - further points out that the effectiveness of infrastructure provision derives not so much from general conditions of economic growth and development but from the institutional environment. In its review the Bank found a common pattern in developing countries consisting of operational inefficiencies; inadequate maintenance, excessive dependence on fiscal resources, lack of responsiveness to users’ needs, limited benefits to the poor and insufficient environmental responsibility. 19 The Case for Private Ownership of Electricity Privatisation exposes the companies to the pressures of financial market competition, even if product market competition is not possible. Floatation through stock exchanges help increase the total capitalisation of financial markets. There are also the benefits of the sale proceeds, and further recurring benefits from tax revenues which is more likely to flow from a privatised company. Beesley and Littlechild56 argue that: “Privatisation will generate benefits for consumers because privately owned companies have greater incentives to produce goods and services in the quantity and variety which consumers prefer -----------The discipline of the capital markets accentuates this process; access to additional resources for growth depends on previously demonstrated ability -------------. Resources tend to be used as consumers dictate, rather than according to the wishes of government, which must necessarily reflect short-term political pressures and problems. --------. Private companies will be less willing to provide uneconomic services”. While the conclusion, therefore, is that ownership of itself is not the major factor affecting differences in productive efficiency, (Pollitt, 1995) 57 it is how such ownership control is exercised. Public ownership provides the opportunity for influences other than cost efficiencies to dictate managerial decisions. Research undertaken by Price and Weyman-Jones, (1993)58 in the gas industry also showed significant increase in productivity following the privatisation of the gas industry in the UK in 1986. Empirical studies on public and private enterprise performances in respect of electric utilities are mixed. Kumbhakar and Hjolmarsson (1994)59 found that privately owned firms in electricity distribution were relatively more efficient than municipal utilities and that the efficiency of mixed (public – private) firms were closer to privately owned firms. 20 Hjalmarsson and Veiderpass (1992a) and (1992 b)60 found that when scale economies are accounted for in electricity retail distribution in Sweden, the differences between different types of ownership were very small, low efficiency was more associated with lack of competition in the industry. Dilorenzo and Robinson (1982)61 Fare, Grosskopf and Logan (1985)62, Neuberg (1977)63 found no significant differences; More (1970)64 found private firms to be more efficient. Hollas and Stansell (1987)65 concluded from their studies that privately owned firms tend to be more price efficient than municipally owned electricity firms. Vickers and Yarrow (1991)66 stated there are major problems with many of the empirical studies. There are problems of measuring key variables such as allocative efficiency and distributional effects, often firms of a similar nature do not exist which allow for like-with-like comparison between public and private, the elapsed time of several privatisations has been short and there are difficulties in distinguishing between the effect on efficiency from changes which result from ownership, as distinct from changes which result from competition or regulatory policies. Empirical studies also yield conflicting results on the relative efficiency of public and privately owned utilities, depending on the extent to which researchers have been able to control the effects of differences in input prices, technology and economies of scale. The general conclusion is that private firms are more efficient in competitive environments, Boardman and Vining (1989) 67. In the case of natural monopoly the results are mixed; some give the advantage to public ownership, and yet others find no significant differences. Two major factors seem to be at work, either that of regulatory policies on monopoly behaviour (public or private) or a competitive environment. The most significant points, however, to emerge from the evidence are that of the importance of competitive environment, regulatory policy and incentives for efficiency. In state owned electric utility, the superior public efficiency may be associated with natural monopoly condition. For Beesley68: “Competition is the most important mechanism for maximising consumer benefits and for limiting monopoly power. Its essence is in rivalry and freedom to enter 21 markets. What counts is the existence of competitive threats from potential as well as existing competitors”. An issue which leads to tension in the privatisation process is that the more monopolistic the structure of the industry at the time of divestiture, the more likely the prospects of monopoly profits and the earning of economic rent, the more attractive the company will be to prospective buyers, and the higher the likely divestiture income to the Treasury. The benefits of unbundled competitive structure, which tends to fetch lower divestiture prices, must therefore be balanced against the longer-term benefits to consumers and the general economy that is likely to flow from a more competitive industry. More and more governments are now recognising that direct intervention by the state to remedy market failure carries substantial negative costs. Problems arise from adapting to rapidly changing conditions, and resolving and reconciling different and at times conflicting objectives. It has also been shown that it is now possible to attain social and economic objectives, such as income redistribution through targeted subsidies while operating in competitive markets69. The Effects of Regulation There is also growing awareness of the major inefficiencies brought about by the regime of the regulated monopoly70. Regulatory reforms in the US of the 1970s and 1980s demonstrated that largely unregulated competitive industries yield more efficient performances in such traditionally regulated industries as air transport, railway, trucking, national gas distribution and long distance telephone. Regulation should not be retained when underlying market conditions have changed and is no longer relevant. There will, however, be strong pressures in some quarters to protect vested interest and also from those who seek to extort economic rent. Stigler (1971)71 in his analysis states that: “regulation imposes costs but does not yield benefits. Regulatory agencies are subject to capture, and maybe used by the industry to defend the status quo, preventing new entrant and maintaining high levels of profitability despite being inefficient”. 22 An example of this is the case of the State Regulatory Commissions in the USA in frustrating the introduction of more competition in the retail sector of the industry. The emergence of smart metering and micro-processor based systems that offer distributed control of selected circuits at customers’ premises which make it possible to unbundle electricity so that consumers can tailor the reliability of service by end use has been available for widespread use in the USA for many years. In fact according to Beesley and Littlechild72: ‘’The promotion of competition is not traditionally associated with regulation of utilities in the USA. The Regulatory Commissions have a long record of resisting entry and it has persuasively argued that the real purpose of regulation was to protect the incumbent from competition”. Different regulatory regimes have different effects on cost efficiency. Averch and Johnson (1962) 73 states that under rate of return regulation the form of regulation popularly adopted in the USA the firm has a strong incentive to over invest in capital, “gold plating” to increase the size of the rate base and obtain higher returns. Regulators also face the major problem of information asymmetry. The firm knows how to manipulate costs in order to maximise profits in the presence of the constraints imposed by the regulator. The regulator can only imperfectly observe costs and does so by incurring a regulatory resource cost, Byron and Myerson (1982) 74. Leibenstien (1996) 75 further states that the problem of information asymmetry makes it very difficult to regulate vertically and horizontally integrated monopolies, hence New Zealand’s approach of introducing strict information disclosure requirements in the sectors of the electricity industry which continue to display natural monopoly characteristics. The move to yardstick competition in electricity distribution also reduces the extent to which the regulator has to rely on information from the regulated. Yardstick competition, in electricity distribution is a special case of incentive regulation and involves the decoupling of the utility’s price structure from the firm’s reported costs. The objective is to reduce the asymmetric information problem. According to Wyman-Jones: “a set of empirically derived competitive efficiency measures are developed under yardstick regulation which seeks to compare firms within a given industry by first determining which firms are performing most efficiently, i.e., constitute the frontier 23 of the industry’s production function, and then constructing an index of how any given firm differs from those which make up the frontier firms”. This is the methodology being adopted for the distribution sector in the post-privatised Panama electricity system. Demsetz76 also states that: “Public utility regulation has been criticised because of its ineffectiveness or because of its undesirable effects on production. --The natural monopoly theory provides no logical basis for monopoly prices. The theory is illogical. Moreover for the general case of public utility industries, there seem no clear evidence that the cost of colluding is significantly lower than it is for which unregulated market competition seems to work’’. Developing country governments, therefore, need to weigh the policy options of direct ownership or that of private ownership and regulation of prices and entry conditions against the substantial welfare losses which from experiences have been attributable to state ownership, as well as to privately owned regulated firms, against the benefits of private ownership and competition and especially such benefits as the diversification of capital and the opportunity for wider investment flows which comes with private ownership. Vertical and Horizontal Restructuring Vertical unbundling involves the creation of two or more economic entities in different stages of the production chain, such as separation of the transmission from both generation and distribution. Unbundling serves to isolate relevant costs and revenues and reduces the opportunity for cross-subsidies and predatory pricing practices between the monopoly and competitive parts of the system. It also provides for yardstick competition and reduces the potential to use market power to the detriment of competitors. Vertical integration and vertical control (Yarrow 1994), 78 “can have anti-competitive effects that outweigh the benefits from reducing or eliminating the externalities. The anti-competitive effects tend to occur as a result of an extension of market power: a firm with market power at one stage of production maybe able to increase its profits by using that power to reduce competition at another stage of production. In general vertical integration and vertical control are unlikely to be problematic where there is significant horizontal 24 competition at different stages of the production and supply chain for then there is no great market power to extend in the first case). However, even where there is substantial market power at one stage of production stage “A” say, it remains difficult to justify any general presumption against vertical integration or control given the existence of potentially significant economic externalities when vertical integration and vertical control between generation and transmission is weakened, the case for weakening the vertical links must rest on the view that there is some substantial, offsetting benefits to be had from separation ----------Yet at first sight it can be difficult to see how such argument can be sustained. The core of market power in electricity supply systems lies in the natural monopoly activities of transmission and distribution. If, therefore, transmission is suspended from generation that market power will be left substantially in tack”. When a single firm controls the monopoly sector such as the transmission system and is also involved in the competitive sector such as generation it has the opportunity to stifle competition by charging either prohibitive or discriminatory prices or setting discriminatory technical standards of interconnection. Separation also reduces the requirements for regulatory oversight and regulatory costs. Whether vertical unbundling brings net benefits depends on the foregone economies of scale and scope, weighed against the benefits facilitated by competition. An option is accounting separation, requiring the vertically integrated firm to provide separate accounting for the separate vertical parts or operational separation, allowing for single ownership of the vertical parts but requiring a separate third party to operate the monopoly entity. Both accounting and operational unbundling requires heavy regulatory controls to minimise opportunistic behaviour. Vertical and horizontal restructuring has different effects from privatisation. Vertical separation of each stage into monopoly generation, monopoly transmission and monopoly distribution may serve to increase the effect of monopoly power while at the same time results in loss of economies of scale and coordination. An unregulated chain of monopolies will tend to sell at higher prices than an unregulated integrated monopoly, hence regulations is still crucial for the unbundled vertical monopolies. It is the combination of vertical and horizontal separation, which provides the opportunity to introduce competition. Yarrow (1986)79 argues that competition and managerial accountability are 25 more important than privatisation per se, in promoting economic efficiency and this position was later supported by Caves (1990)80. Horizontal unbundling is the creation of two or more economic entities from a single area of economic activity. Horizontal unbundling serves to dilute market power of the incumbent enterprise and eventually the barriers faced by new entrants to the market. It also reduces the burden of oversight by regulators. Where unbundling is carried out on a geographical basis, a location monopoly is created as with electricity distribution and water systems, however, the opportunity for yardstick competition between firms is created. The optimal number of entities will depend in part on economies of scale in the relevant activity and the density and the size of the market. Density of network connections has a profound effect on unit costs in distribution systems. Roberts81 explains the importance of density as follows: “A change in the quantity of electricity supplied by a firm will have different impact on cost depending on whether the output is supplied to existing customers or to an increased number of customers. Significant reduction in ray average cost result from increasing output to existing customers, while no substantial savings occur when servicing an increased number of customers”. Separation into several horizontal units also does not of itself lead to competition. A competitive framework, however, offers important advantages over monopoly. There is the need to introduce new institutions to facilitate competition. In the 1990s we have seen new market and trading innovations in the electricity market. A bulk electricity exchange market has emerged providing for rivalry and incentives to firms for cost reduction and to gain market share. Within the wholesale market where prices are determined by constant bidding, inefficient plant may remain idle at a given demand level. There is therefore, the incentive to reduce cost to increase market share. Maximising the benefits from generation will, however, require pricing policies, which accurately reflect transmission congestion and the cost of generation at different peak times. Efficiency gains from competition manifest at two levels, over the short run and over the long run. In the short run there will be increased utilisation of excess capacity from superior operation and maintenance of existing plants, from increased labour productivity, and in some cases, from better allocation of generation across plants with different costs. In the longer term competition facilitates better investment decisions regarding the amount, mix and speed of construction of new 26 plant. Allowing competition in the electricity utility industry does, however, brings tension in that the lowering of prices may lead to stranded costs82. The dynamics of international events and the resolution of economic problems in developing countries call for profound new policy approaches to the electricity and utility sector. The nation state economy, whereby governments largely control the forces of economic progress within its borders no longer applies in the new millennium. Globalisation has been exerting greater pressure for international competition and more and more governments are recognising that electric utility can no longer be allowed to operate with prices, which are substantially higher than those confronting their international competitors. Electricity Industry Structural Models Various writers have advanced different approaches to models of electricity industry restructuring. Invariably the models reflect the different approaches to the trading arrangements adopted the degree of physical restructuring undertaken or the level of competition accommodated. Joskow (1997) 83 identifies a two-structure model, consisting of a “portfolio manager model” and a “customer choice model”, essentially based on the trading arrangements. For Joskow under the former: “the local distribution utility retains its traditional obligation to supply customers in its de facto exclusive franchise areas with bundled retail service, at regulated prices, but relies on competitive procurement mechanism to buy electricity from the lowest cost suppliers in competitive wholesale markets rather than building new generating facilities”. It was intended to accommodate the entry and growth of IPPs, while allowing the incumbent utility to retain end users as captive customers. It does not require major physical restructuring of the industry. There is still a major oversight role retained for the regulator. In addition to regulating retail prices, the regulator may be required to supervise the incumbent utility’s competitive procurement of new generating capacity. In the customer choice approach or “retail wheeling” Joskow explains that: 27 “retail customers can access the wholesale market directly by purchasing unbundled distribution and transmission services from their local utility. Individual customers take on the obligation to arrange their own generating service supplies with independent competing electricity suppliers”. Under this model, generators can sell energy in a competitive spot market as well as through longterm bilateral contracts with intermediary traders or direct with retail consumers. The local distributor or incumbent utility is required to grant open access to the distribution system and in return charge prices determined by the regulator for “wire services” and for metering. An independent network operator may be required to operate the transmission system, which in turn is also required to provide open access to the transmission wires at regulated wire service price and be responsible for system control and dispatch. At a minimum, financial unbundling of the incumbent utilities transmission and distribution system is required, however, because there is likely to be self-dealing and conflicts of interest, vertical unbundling of transmission and distribution is preferable. In terms of transmission pricing, Joskow84 refers also to two models, a tradable physical rights model and a nodal pricing model. Under the tradable rights formula the available transmission capacity (ATC) is determined using power flow computer models based on a variety of system conditions and reliability. ATC is essentially the capacity a specific transmission interface has to accommodate generator schedules for 24 hours 365 days a year, with high probability. The rights to use the ATC over a “contract path” from a set of injection points to one or more injection points on the network are then traded to potential buyers. If the demand to use an interface rises beyond the capacity of ATC at the preferred schedules, the price for the fixed quantity of rights to use that interface will rise to balance supply with demand. The major problem encountered with this approach is that it is difficult to define a full set of contingent delivery and receipt of property rights from one point to the other given the nature of electricity. The property rights model, however, is said to afford maximum freedom of individual suppliers to structure transactions and minimises the role of the network operator, as the network operator is not required to participate in the bulk electricity trading transactions or in determining market prices for energy. The independent operator’s role is limited to maintaining the physical 28 integrity of the system, enforcing transmission rights rules, managing conflict, scheduling generation and actual capacity of the network and measuring and settling imbalances. In the nodal pricing model the network operator is required to run a set of day-ahead and hourahead auction markets for bulk electricity, along with ancillary services and uses the bids submitted to derive a “least cost” merit order generator dispatch schedule that matches demand and supply and which defines market clearing prices at each supply and demand node on the network, consistent with operating constraints. On the demand side customers articulate their willingness to pay for electricity, which includes willingness to contract or expand their use at different times as price varies. Node pricing is said to be superior to tradable rights in one respect, in that it solves the externality problem that arises when congestion of the transmission system becomes important and hence provides for efficient allocation of scarce transmission capacity. The nodal pricing approach calls for a more active and central role for the network operator in the energy market, when compared to the tradable rights approach. Resale of capacity rights on a non-discriminatory basis to enable competition in network facilities such as transmission system maybe theoretically possible, but in practice it has been found to be difficult to define, adjust and enforce such access or capacity rights in a manner that would facilitate competition in power systems. Power flows through a network according the path of least resistance, with the result that what capacity is used or unused at any moment in any part of the power system is a function of all the physical flows throughout the system and not a function of bargaining or individual transmission decisions. Rather than adopt tradable property rights as a basis for transmission pricing most systems have resorted to central dispatch that optimises the flows instantaneously matching supply with demand. The effect of this arrangement is that winning bidders will always have their supplies dispatched in a non-discriminatory basis and, therefore, eliminate the need to compensate holders of capacity rights for the effects of power flows, or available capacity. A related problem is who should be responsible for transmission investments to increase transmission capacity? In transmission supply the problem of “free rider” arises. There are two questions which must be addressed, who should identify the expansion opportunities and who 29 should pay? Broadly there have been two suggestions, either to rely primarily on all the private parties (or group of the parties) to propose and pay for upgrades and investments or alternatively require the network operator to identify the needed investments and share the costs amongst those who are required to use the expansion. The public policy direction often taken has been to delegate the responsibility to identify the expansion or upgrade capacity needs to the systems operator as well as the construction activity, with the requirement for the associated costs to be recovered from all network users. There is, however, the need to guard against over-investment or underinvestment in an unbundled transmission system. Tenenbaum, Lock and Barker (1992) 85 writing two years after the radical industry restructuring in England and Wales and the introduction of one of the first bulk electricity exchange markets, recognized a four model basic industry structure; classified as Models One, Two, Three and Four. Under Model One, the industry is characterised by the traditional horizontal and vertical industry structure, either privately owned and regulated by cost of service rate of return regulation or if publicly owned, normally with self-regulation and usually serving a well defined or exclusive franchise region or the nation as a whole. This structure does not provide for competition, nor are there sufficient incentives for efficiency enhancing behaviour. It is based on the concept that the electricity industry is a natural monopoly with economies of scale and scope. Under Model Two, the integrated and horizontal industry structure is usually retained; however, competitive procurement of new generation capacity is introduced. In essence the monopoly status of generation is removed and this sector of the industry is liberalised, allowing for incremental or entry competition through independent power producers. In the model two structure some of the traditional risks; construction risk, non-fuel operating risks and reliability risks remain with the IPP or are off loaded at a cost to some other party, with the purchasing company assuming the demand and fuel price risks. While the seller or IPP is exempted from regulation the purchase of new capacity requires independent supervision to ensure that purchases are made on a transparent and competitive basis. The transmission and distribution sectors in the model two-industry structure continue to require heavy-handed regulation. 30 Model two adopts contracts, which substitute for integration of generation and transmission within the single utility however contracts create transaction costs. Tenenbaum et. al.86 in their 1989 raise the matter as follows: “The issues, then, is one of vertical integration: is it more efficient for generation and transmission and distribution to be under one ownership? Economic theory gives no definitive answer nor has there been any empirical study that directly addresses this question for the electricity industry”. The general view, however, and especially since the UK experiences of the 1990s is that it is more efficient to unbundle the integrated utility so as to guard against market power. Model Three involves the development of a wholesale electricity market, whereby distributors and traders are allowed to buy bulk or high voltage electricity as a separately traded product from distant generators. It is very difficult, however, to regulate against discriminatory behaviour when the integrated utility runs the transmission system. In order to address this problem separate ownership of the system operation is required. One of the mechanisms considered in the USA is for the transmission system to be operated by an independent entity under contract. It still raises the question as to whether the system’s operator can be truly independent, while owned by the integrated utility or by regional distributors as the incentive to exercise market power remains. Therefore, there is a strong case for functional unbundling over operational unbundling. It eliminates the regulatory cost of enforcing behavioural rules. Under Model Four, functional separation of the industry into generation transmission, distribution and retail sectors is introduced along with the imposition of common carrier conditions on the distribution and transmission systems. Further separation of supply from distribution wire services allows for increased competition at the retail level. Hunt and Shuttleworth (1996) 87 also recognize a four-model industry structure, based on varying degrees of monopoly, competition and customer choice as afforded under each structure and state that: 31 “From the point of view of competition in product market there are really only four fundamentally different ways of structuring the industry although there are many possible variations of each”. The four industry structures are classified as monopoly, purchasing agency, wholesale competition and retail competition models. There are many similarities between the characteristics of each of the structural models presented by both groups of writers. The Wholesale Bulk Electricity Markets The development of bulk electricity wholesale markets has been one of the major new innovations that have been transforming the electricity industry. The wholesale market for bulk electricity is also central to the development of a competitive retail market as demonstrated in New Zealand in 1993. New Zealand tried to develop a competitive retail market before a functioning bulk wholesale market and the result proved to be failure. The critical design issue in developing a bulk electricity market resolves around the creation of an electricity industry in which the generating sector is at the same time effectively competitive and efficiently integrated with the monopoly transmission sector and the system co-ordination function, whilst providing deterrence against the exercise of market power. The strong vertical relationship between generation and transmission, despite physical unbundling makes it impossible for a decentralised market to manage physical electricity efficiently. There is, therefore, the need for a centralised market clearing process, analogous to those used in commodity and financial markets, to collect offers to buy and sell at various prices, determine market clearing prices for a specified period, give delivery instructions to sellers whose offers have been accepted and settle payments among traders. Ruff88 states that: “The only practical way to organise such markets in physical electricity is to integrate them with central dispatch, pooling and economy trading process - the process that utilities use now individually and in pools to manage their own trading”. A system operator is, therefore required, whose function is to collect cost and demand data, determines and offers least cost dispatches and issues dispatch instructions. The market 32 mechanism seeks to ensure that the vertical integration of generation and transmission, which is vital to ensure integrity of the system and electricity equilibrium in the sense of supply and demand balance, is maintained at every node in the network. Since random supply and demand shocks can happen very suddenly, faster than traders could conceivably respond to price signals, equilibrium requires central control. A fully decentralised market transactional system cannot meet the technological needs for continuous equilibrium. The most important requirement, therefore, for an efficient bulk electricity market, both in terms of achieving economically efficient outcomes and maintaining the security of the system, is that of ensuring effective energy balancing. How energy is balanced and who carries out the balancing is critical to operational and economic efficiencies of the system. Energy balancing is closely related to whether despatching is centrally coordinated and is associated with mandatory or compulsory requirements as well as to whether participants are able to selfdispatch and energy markets are voluntary. Two types of bulk electricity market designs have, therefore, emerged; centralised (gross) and often mandatory power pool, based on the experiences of England and Wales, and the balancing trade or (net) power pool based on the experiences of the Nordic countries which provides for bilateral contracting between participants in the market. The main difference between the two market designs is the importance assigned to the spot market and the dispatch process. The mandatory power pool attaches more importance to the spot market and requires all trades to be compulsory and carried out through the pool, whilst the bilateral trading and balancing market design allows unregulated parties to organise their own decisions. Two schools of thought have developed and there is very strong support for each of the two designs. Ruff 199289, Hogan 199290 , Hogan 199491 for example argue that the only practical way to internalise the real-time network externalities that otherwise make competition in electricity markets unacceptably inefficient and unrealisable is the power pool. The economic argument for a single mandatory pool is that it is considered to be efficient. A centralised dispatch process ensures that physical constraints permitting, the lowest cost available plant is always dispatched based on the principle of economic merit order. Without integration of the spot market with dispatch in 33 real-time these commentators argue it will not be possible to internalise the externalities in the operation of electricity grids and competition will be weakened. The proponents of the bilateral trading and balancing market concept do not accept this thesis and emphasise the danger of having a monopolist that controls dispatch and whose first priority is that of a systems reliability implementing market. For the bilateral traders the role of the systems operator is to implement the orders received from market participants and to preserve systems reliability. A multiplicity of entities are therefore, involved in scheduling output to follow load. In the view of the bilateral traders, an efficient market should reflect more than the good intentions and benefits of central dispatching and should be more like any other commodity market, reflecting demand side processes and should also offer consumers’ choices. Bilateral trading and balancing market provide for contractual freedom and commercially negotiated prices and this should ensure that prices track costs, as generators seek out purchases for their power, suppliers and consumers seek the most competitive terms from generators and traders enter markets, therefore, increasing market liquidity. For the proponents of net pool, consumers’ choice and freedom are the critical issues. Both sides, however, have come to accept the need for an independent systems operator, whose function is that of coordination of the transmission grid operation activities. The transmission wire business and the grid control process may also be structured into two distinct areas of operation to be handled by two separate entities. In one model the transmission operator is only required to provide transportation wire and related services and is neutral to the market (does not trade in bulk electricity). The functions of systems control, market operation and settlement payment arrangements are assigned to another entity. In the second approach the transmission operator is required to perform all the above listed functions. The former approach allows the transmission operator to concentrate on its core function, which is very important for system supply, and minimises the opportunity to exercise market power or the opportunity to be engaged in discriminatory behaviour. The method of price discovery in the spot market also can either be cost based, as is the case with Chile which has developed to be popular in a number of the newly reforming Latin American markets or price based as was the case with the initial England and Wales market. In cost based 34 pricing the properties of the firm’s cost function are used to set prices. Cost based pricing generally ignores social welfare considerations and even if they are market clearing, they may send incorrect signals about incremental costs of production and incorrect incentives to the firm. The cost base model, popularised in Latin America is derived from the generators actual or estimated costs and the dispatching procedures represent an extension of the pre-reform merit order procedures. The advantage of a cost based system, provided generators do not disguise their costs, is that it ensures efficient dispatch, makes it difficult for generators to exercise market power and is relatively easier to implement. European power markets, however, have not favoured cost based approaches and maintain that it provides weak incentives for efficiency. Instead, Europeans typically have opted for a price based spot market price discovery system of England and Wales origin. In the price-based system the systems marginal cost (SMC) determines the spot market price. The marginal cost of the bidder, which clears the market in a given period, sets the system-selling price for that period. Conclusions The different structural models and market designs, which Tenenbaum et al and Hirst and Shuttleworth described are characterised by different ownership arrangements, different levels of industry integration and a variety of different features in their trading arrangements. The defining features, which distinguish the respective structural options which have been advanced by the different writers, are that under Model One traders and consumers are denied choice. With Model Two, choice is afforded to the single purchaser and competition essentially is for incremental capacity. With Model Three, choice is extended to the distributors and other traders and competition is extended from competition for the market to product market competition for bulk supplies. Under Model Four choice, is further extended to retailers and all end users, with full competition throughout the electricity production and supply chain. What is apparent is that the electricity supply industry that has emerged in the 1990s has been developing through four distinct phases or four distinct structural models of operation. It remains 35 to define these phases more explicitly, determine whether the transformations of the individual markets follow any particular pattern, if there are variations in the transformation process and if so, what are these variations and what accounts for the differences? The two main conclusions that can be drawn from the preceding review are that in addition to major technological developments, utility economics has fundamentally changed since the 1990s, a change which is having major effects on society. For over one hundred years utility regulation, especially the United States brand has had as its central objective the prevention of new entrants to markets and the preservation of the monopoly status quo. Originating in Chile in the 1980s and expressly advanced in the United Kingdom in the 1990s, utility regulation no longer seeks to inhibit or prevent entry to the once traditionally recognised natural monopoly industries. A more forceful and dynamic objective of utility regulation is to facilitate competition in the segments of the industry where competition is possible and practical. The public policy implication of this development is far reaching, in that in one and the same industry, public policy will have to address market liberalisation, whilst at the same time addressing economic regulation. Secondly, economies of scale are less of a determining factor as to the industry structure. In terms of public policy governments now have the choice of several options as to the industry structure, which can be accommodated. This choice revolves around the degree of competition that is seen to be desirable or can be politically accommodated. 36 End Notes 1. Electricity networks are not switched networks like telephone or railways, where a supplier makes a physical delivery of a particular product at point “A” and is then physically transported to a specific customer at point “B”. 2. Douglas Gegax and Kennnth Nowotny, “Competition and the Electric Utility Industry: An Evaluation”, Yale Journal of Regulation, Vol. 10, No. 1 (Winter 1993), p.71. 3. Paul L. Joskow and Richard Schmalensee, Markets for Power: An Analysis of Electric Utility Deregulation, Cambridge, MIT Press (1983), pp 59-77. 4. William J. Baumol, “On the Proper Cost Tests for Natural Monopoly in a Multi-Product Industry” American Economic Review, Vol. 67 (1977), p.809. 5. William J. Baumol, John C. Panzar and Robert D. Willig, Contestable Markets and the Theory of Industry Structure, San Diego, CA. Harcourt Brace Jovanovich (1982), p.170. 6. Gegax and Nowotny, op.cit. p. 67 7. Ibid., p.67. 8. Michael Klien, “Competition in Network Industries”, Washington, D.C., World Bank, Policy Research Working Paper, No. 159 (1996), p.4. 9. Baumol, Panzer and Willig, op.cit, p. 815 10. External cost or externalities refer to costs and benefits expected or which arises from third parties to a transaction. 11. Internalised cost or internalities refer to costs and benefits experienced from economic activities that are not accounted for in terms of trade. 12. Oliver E. Williamson, “The Transaction-cost Economics: The Governance of Contractual Relations”, Journal of Law and Economics, Vol.22 (1979), p.234. 13. Paul L. Jaskow, “Restructuring, Competition and Regulatory Reform in the US Electricity Sector”, Journal of Economic Perspectives, Vol. 11, No. 3 (Summer 1997), p. 122. 14. M.E. Beesley and S.C. Littlechild, “Privatisation, Principles, Problems and Priorities”, in Privatisation, Regulation and Deregulation, ed., M.E. Beesely, London, Routledge (1997), p.30. 15. Paul L. Joskow, “The Evolution of Independent Power Sector and Competitive Procurement of New Generating Capacity”, Research in Law and Economics, Vol. 13 (1991)), p.64. PURPA’s decision that US utilities were to be required to buy bulk electricity from renewable and co-generation sources led to the entry of new players; qualifying 37 facilitates and independent power producers to the industry for the first time. PURPA’s decision, however, was based more on the desire to reduce dependence on imported fuel oil and encourage renewable energy sources as part of a wider environmental policy initiative, rather than a policy initiative to restructure the industry. 16. IPPs were not restricted to fuel efficiency targets. Technically they are public utilities under the Federal Energy Act; however, their regulatory reporting requirements have been waived, giving them considerable flexibility. 17. Mathew White, “Power Struggles: Explaining Deregulatory Reforms in Electricity Markets”, Brookings Papers: Micro-economic Activities (1996), p.215. 18. The impact of CCGG technology on the electricity industry is almost as profound as the impact of the new telecommunication technologies; wireless, fibre optics and satellite transmission on the telecommunications industry. The single product telephone natural monopoly industry has been replaced by a competitive multi-product industry. The cost of entry and minimum scale operation has been significantly lowered. 19. J.D. Glen, Private Sector Electricity in Developing Countries – Supply and Demand, Washington D.C., IFC Working Paper No.15 (1992), p.8 20. William Baumol, “Contestable Markets: An Uprising in the Theory of Structure”, American Economic Review, Vol. 72, No. 1 (1982), p. 3. Industrial 21. Bernard Tenenbaum, Reinier Lock and James R. Barker, Electricity, Privatisation: Structural, Competitive and Regulatory Options, , Oxford, Butterworth Heinemann (1992), p.13. Transmission is typically distinguished from the “Wires business” of distribution on a somewhat arbitrary basis that of the voltage level of the transmission of power. The transmission wires tend to refer to the high voltage transportation lines, with the distribution wires being considered as the low voltage lines to the end users. 22. Paul L. Joskow, “Regulatory Failure, Regulatory Reform and Structural Change, in Electrical Power Industry”, Brookings Paper: Micro-Economic Activities (1989) , p.142. 23. John Vickers and George Yarrow, Privatisation: an Economic Analysis, Cambridge, Mass.MIT Press (1988), p.300. Vickers and Yarrow further state that even if the economics of replication and co-location are accepted there is little evidence to support minimum efficient scale of 50000 MW, the England & Wales system being 52400 MW in 1987. The continued success of smaller companies in countries such as the Nordic with more fragmented bulk electricity markets are evidence that the single firm argument was never entirely valid. 24. L.R. Christensen and William H. Greene, “Economies of Scale in US Electric Power Generation”, Journal of Political Economy, Vol. 84 (1976), p.655. 38 25. S.E. Atkinson and Robert Halvorsen, “Parametric Efficiency Tests: The Economies of Scale and Input Demand in US Electric Power Generation”, International Economics Review (1984), Vol. 25 p.647, 26. World Bank, World Bank Development Report 1994: Infrastructure Development, New York, Oxford University Press, (1994), p.116, For 27. Louis De A’lessi, “The Economics of Property Rights: A Review of the Evidence”, Research in Law and Economics, Vol. 2 (1980), pp.1-47. 28. Armen A., Alchain, “Some Economics of Property Rights”, 11 Politico, Vol. 30 (1965), pp.816-29. 29. Harold Demsetz, “Some Aspects of Property Rights, Journal of Law and Economics, Vol. 7 (1966), pp.61-70. 30. Eirik Furubotn and Svetozar Pejovich, “Property Rights and Economic Theory: A Survey of Recent Literature”, Journal of Economic Literature, Vol. 10, No.4 (1972), pp.11371162. 31. Ray Rees, “The Theory of Principal Agents”, Bulletin of Economic Research, Vol. 37, No. 1 (January 1985), Part 1 and Part 2, pp.1-26 and pp.75-95. 32. Michael C. Jensen and William H. Meckling, “The Theory of the Firm: Managerial Behaviour, Agency Costs and Ownership Structure”, Journal of Financial Economics, Vol. 3. No. 4 (1976), pp. 305-360. 33. V. Aharoni, The Evaluation and Management of State Owned Enterprises, Cambridge, Mass, Ballinger (1986). 34. Dieter Bös, Public Enterprise Economics: Theory and Application, New York, North-Holland (1986). 35. David Parker and Stephen Martin, Assessing the Impact of Privatisation on Company Efficiency, London, Centre for the Study of Regulated Industries (1996). 36. Williamson, op.cit., pp.233-262. 37. Douglas C. North, The Structure and Change in Economic History, New York, Norton (1981). 38. G. Tullock, The Politics of Bureaucracy, Washington, Public Affairs Press (1965). 39. William Niskanen, Bureaucracy and Representative Government, Chicago, Aldine Atherton (1971). 39 40. J.M. Buchanan, et.al., The Economics of Politics, London, Institute of Economic Affairs, Readings No. 18 (1978). 41. W.C. Mitchell, Government As It Is, London, Institute of Economic Affairs, Hobart Paper No. 109 (1998). 42. Principal and agency theory states that social and political life can be understood as a series of contracts in which one party, the principal enters into contract with another party the agent. The agent agrees to perform various functions for the principal; in exchange the principal agrees to reward the agent. In private firms managers are said to be the agent, acting on behalf of the shareholders, the principal. The shareholder or principal needs to provide incentives for the agent to maximise the welfare of the principal. The theory also assumes individuals are rational, self-interested and are utility maximisers. Incentives are said to be stronger in private firms, than in public firms, partly because of the problem of defining the principal. 43. Beesley and Littlechild, op.cit, pp.28-29. 44. Property rights deal with the allocation of contractual rights (cost and benefits) among participants in a transaction. There is greater incentive to the individual to maximise welfare under individual property rights than under common property rights. 45. Public choice claims that all human behaviour is dominated by self-interest, i.e. rational utility maximises, and accordingly politicians and bureaucrats will peruse their own interest at the expense of the common good of the wider public. Politicians and bureaucrats are sometimes accused of capturing the regulatory process against the interest of the powerful utility suppliers, against the interests of the wider consuming public. 46. Wolfgang Friedmann, Public and Private Enterprise in Mixed Economies. London, Stephens and Sons (1974), p.382. 47. Scot E. Atkinson and Robert Halvorson, “The Relative Efficiency of Public and Private Firms in a Regulated Environment: The Case of US Electric Utilities”, Journal of Public Economics, Vol. 1, No. 29 (1986) pp.281-294. 48. Anthony Boardman and Aidan Vining, “Ownership and Performance in Competitive Environments: A Comparison of Private, Mixed, and State Owned Enterprises”, Journal of Law and Economics, Vol. 32 (1989) pp.1-33 49. Mathew Bishop and John Kay, “Privatisation in the United Kingdom: Lessons from Experiences”, World Development Report 1989, Washington, D.C. (1989), pp.643-657 50. Mary Shirley and John Nellis, Public Enterprise Reform: The Lessons of Experience, Washington. D.C., World Bank (1991). p.6 51. John Goodman and Gary Loveman, “Does Privatisation Serve Public Interest,” Harvard Business Review, Boston, (November/December 1992), pp. 26-38. 40 52. Ahmed Galal, Leroy Jones, Pankaj Tandon and Ingo Vogelsong, Welfare Consequences of Selling Public Enterprises: An Emperical Analysis, Oxford University Press (1994). Pp 3-6 . 53. Sam Peltzman, “Pricing in Public and Private Enterprises: Electric Utilities in the United States”, Journal of Law and Economics, Vol. 14 (1971), p 112. 54. William Megginson, Robert Nash and Mathias Van Randenborgh”, The Financial and Operating Performance of Newly Privatised Firms: An International Emperial Analysis”, The Journal of Finance, Vol.49, No.2 (1994), p. 448 55. World Bank, 1994, op. cit., p. 27 56. Beesley and Littlechild, op. cit., p.28 57. Michael Pollitt, Ownership and Performance in Electric Utilities, Oxford University Press (1995), p. 185 58. G. Price and T.G. Weyman-Jones, Malmquist Indices of Productivity Changes in the UK Gas Industry Before and After Privatisation, Loughborough, Loughborough University Economics Research Paper, No. 93 (1993), p.12. 59. Subal C. Kumbhakar and Lennart Hjalmarsson, Relative Performance of Public and Private Ownership in Swedish Electricity Retail Distribution 1970-1990, Gothenburg, Sweden, Gothenburg University Working Paper (1994) p.12 60. Lennart Hjalmarsson and Ann Veirderpass, “Efficiency and Ownership in Swedish Electricity Retail Distribution”, Journal of Productivity Analysis, Vol. 3, (1992 a and 1992 b) p. 21 61. Thomas J. Dilorenzo and Ralph Robinson, “Managerial Objectives Subject to Political Market Constraints: Electric Utilities in the US”, Quarterly Review of Economics and Business, Vol.22, No. 2 (1982), 62. R. Fare, S. Gosskopf and J. Logan, “The Relative Performance of Publicly Owned and Privately Owned Electric Utilities”, Journal of Public Economics, Vol. 1, No. 26 (1985), pp 89-106. 63. Leland G. Neuberg “Two Issues in Municipal Ownership of Electric Power Distribution Systems”, Bell Journal of Economics, Vol. 8, No.1 (1977), pp. 303 – 323. 64. Thomas G. Moore, “The Effectiveness of Regulation of Electricity Utility Prices”, Southern Economic Journal, Vol. 36, No. 4 (1970), pp. 365-375. 41 65. Daniel R. Hollas and Stanley Stansell, “An Examination of the Effect of Ownership Form on Price Efficiency: Proprietary, Cooperative and Municipal Electric Utilities”, Southern Economic Journal, Vol. 54 , No. 1 (1987) p.349 66. John Vickers and George Yarrow, “The Economic Perspective of Privatisation”, Journal of Economic Perspectives, Vol. 5, No. 2 (1991), p.117 67. Boardman and Vining, op. cit., pp. 1-33 68. Beesley and Littlechild, op. cit., p. 28 69. UNCTAD, Competition and Public Utility, Geneva, UNCTAD (1997), p.8. 70. OECD, The Application of Competition Policy to the Electricity Sector, Paris, OECD (1997), p. 140 71. George Stigler, “The Theory of Economic Regulation”, Bell Journal of Economics and Management Science, Vol. 2 (1971) pp.3-12. The “Public Interest” or “Consumer Protection” hypothesis states that the goal of regulation is to pursue the general good of society see Richard Posner, “Theories of Economic Regulation”, Bell Journal of Economics and Management Sciences, Vol.5 (1974) pp.335-358. This view has been challenged by the “Capture School” which states that regulation is simple an arena in which special interests contend to trade power for their own narrow interests, see Sam Peltzman, “Towards a More General Theory of Regulation”, Journal of Law and Economics, Vol.19, No.2 (1976), pp.211-239. 72. Beesley and Littlechild, op. cit., p.72. 73. Harvey Averch and Leyland L. Johnson, “Behaviour of the Firm under Regulatory Constraint”, American Economic Review, Vol. 52 (1962), pp 1052 – 1069. 74. D, P. Baron and D. Besanko, “Regulation, Asymmetric Information and Auditing”, Rand Journal of Economics, Vol. 13 (1984), pp. 447-470. 75. Harvey Leibenstien, “Allocative Efficiency Vs X-Efficiency”, American Economic Review, Vol. 56 (1966), pp 392 – 415. 76. Thomas Wyman – Jones, “Problems of Yardstick Regulation in Electricity Distribution,” in The Regulatory Challenge, eds., Mathew Bishop, John Kay and Colin Mayer, Oxford University Press (1995)., pp 423-442. 77. Harold Demsetz, “Why Regulate Utilities”, Journal of Law and Economics, Vol. II (1968), pp 59. 42 78. George Yarrow, “Privatisation. Restructuring and Regulatory: Reform in Electricity Supply”, in Privatisation and Economic Performance, eds., Mathew Bishop, John Kay and Colin Mayer, Oxford University Press (1994). ,pp. 65 79. George Yarrow, “Privatisation in Theory and Practice”, Economic Policy, Vol. 2 (1986), pp 324-364. 80. Richard Caves, “Lessons From Privatisation in Britain: State Enterprise Behaviour, Public Choice and Corporate Governance”, Journal of Economic Behaviour and Organization, Vol.1. No. 13 (1990), pp. 145 – 169. 81. Mark Roberts, “Economies of Density and Size in the Production and Delivery of Electric Power”, Journal of Land Economics. Vol. 62 (1986), p. 362. See also Salvanes G. Kjell and Sigve Tjotta, Cost Differences in Electricity Distribution Industry, Bargen University of Oslo (1990). Returns to network density covers the economics of increasing production by increasing the amount of kWh produced when network is held fixed. 82. Gregory Sidak and Daniel Spulber, Deregulatory Takings and Regulatory Contract: Competitive Transformation of Network Industries in the US, Cambridge University Press (1997), p.29, Stranded costs are prior investments which turns out differently from expected or where regulators or the state have been party to utilities building excess capacity, sometimes with wrong technology. In unregulated markets the case of stranded cost does not arise, as it would simply be another business risk. It recovers outlays required by a regulator or state, which cannot be recouped under competitive condition. 83. Joskow, 1997, op. cit., p. 127. 84. Ibid., p. 130. 85. Tenenbaum, Lock and Barker, op. cit., p.9. 86. Ibid., p. 32. 87. Sally Hunt and Graham Shuttleworth, Competition and Choice in Electricity, New York, John Wiley and Sons (1996), p. 21. 88. Larry E. Ruff, “Stop Wheeling and Start Dealing: The Transmission Dilemma” in Electricity Transmission Pricing and Technology, eds., Michael Enhorn and Ralph Saggidi, Netherlands, Kluwer Publishers (1994), p.4. 89. Larry Ruff, Competitive Electricity Markets: Economic, Legal and Practical Implications, International Association of Energy Economics Workshop. Toures, France (1992), p.8. 90. William Hogan, “Contract Networks For Electricity Power Transmission”, Journal of Regulatory Economics, Vol. 4, No. 3 (1992), p. 215 43 91. William Hogan, “A Wholesale Pool Spot Market Must be Administered by the Independent System Operator: Avoiding the Separation Fallacy”, Electricity Journal (June 1994), pp.26-48. 44 Chapter 2 A Four Phase Development Model for Electricity Markets Four Phase Development Model In this section a model consisting of four phases of development, including the traditional franchise monopoly phase is presented. The basic argument of this thesis is that both technological and market pressures are forcing a movement away from the natural monopoly, vertically and horizontally integrated utility structure to new structures which allow for increased levels of competition and private ownership. The new structures tend to fall into three phases of development; the purchasing agent phase, the bulk wholesale electricity market phase and the retail competition or consumer choice phase. These phases will provide the template to evaluate developments in electricity markets, which have moved away or are moving away from the franchised monopoly phase. In the latter sections, the cases of selected countries that have or have been trying to move away from the franchise monopoly phase are presented. The aim is to evaluate the extent to which the developments in these countries are characterised by the features exhibited by the three new stages of development, which have been presented, and to identify the forces, which account for any variation along the development path. Is there evidence to support the view that emerging electricity markets are required to go through these three phases of development? The discussion will also focus on the factors, which constrain the development of the electricity market, especially smaller markets from moving from one phase to the next and clarify under what circumstance is it possible to make the change without going through all the three stages sequentially. Structural changes and development in the electricity industry can be seen as a form of institutional development, wherein an industry structure responds to competitive pressures. The indusry, 45 therefore, moves from one stage to the next over time to respond to competitive pressures, which emerge in the system. The Case Study Method as the Research Strategy Reliance has been placed on the case study method as the chief investigative technique. The case method (or multiple case studies as used in this investigation) is a distinctive form of empirical enquiry that is extensively used in the social sciences–sociology, political sciences and anthropology, as well as practice oriented fields such as urban planning, social work and public policy. It is a frequent mode of thesis and dissertation research in all these disciplines and fields, Robert Yin (1981b) .The case study as a research tool, should be distinguished from the case study as a teaching device popularised in the fields of business, law and medicine. It is a method of inquiry that investigates a contemporary phenomenon within the real life context, especially when the boundaries between the phenomenon and the context are not clearly evident. It allows the investigator to retain the holistic and meaningful characteristics of real life events such as institutional and organisational changes. It allows for exploratory, descriptive and explanatory evaluations. Unlike the survey method, the case method copes with technically distinct situations in which there are many variables of interest than a particularly set of data points and as a result relies on multiple sources of evidences which can combine the survey method as well. The survey method can deal with context and phenomena; however, its carries certain limitations. In survey design one constantly struggles to limit the number of variables to fall safely within a number of respondents that can be analysed and to allow for mathematical manipulation of the data. The case method is the preferred method when there is the need to understand complex social phenomena and when examining contemporary events. It allows for observation of the events being studied and interviews of persons involved in the events. Its unique advantage is that of its ability to deal with a variety of evidence. The case can be a mix of quantitative and qualitative evidence as is the situation with this study. The contrast between the qualitative and quantitative evidence does not distinguish the various research strategies. The selection of countries was not intended to reflect a random approach as in the survey method. The selection is based on the need to demonstrate certain observations. The multiple case methods also 46 allow the investigator to make comparison and to draw conclusion from more than one context. The UK was selected because it is made up of three distinct systems and each system presented different strategies of reforms. The England and Wales system was the first to introduce radical restructuring. Bolivia was selected because the argument in the early 1990s was that radical unbundling was not possible in small system the size of 665 MW. The thesis was that economies of scale is not exhausted in small systems and therefore moving through the competitive transformation process was more suited for countries with large systems and mature markets Jamaica on the other hand was selected because the policy makers rejected the thesis that small systems could be unbundled without serious cost penalties. The view then was that the benefits from competition would not be sufficient to compensate for the additional transaction costs and diseconomies. The three Sub-Saharan countries were selected because they have all carried out extensive reforms within the franchised monopoly phase without measurable success and as a result they have declared their intentions to introduce higher levels of competition and under go radical unbundling. It is therefore important to determine if there are lessons from the other case countries that could inform the policy choices of these African governments. In collecting the evidence visits were made to each country and quantitative and qualitative data collected from privatisation units, regulatory agencies and the relevant public utilities. Additionally, in the case of the African countries, it was possible to interview and collect data from public officials who attended a series of workshops on utilities reform, which was held for African public officials by Commonwealth Secretariat over the period 1999 to 2001. Evidence was therefore gathered from documents, interviews based on guided questionnaires rather than structured queries, as well as observations. The unit of analysis adopted for the investigation is that of the electrical industry supply system. The task then was to see to what extent the model explains the transformation through the four distinct phases from the empirical evidences. 47 Model One Stage - Franchised Monopoly Phase As the utilities under the pre-1980 environment were seen to be natural monopolies, there was the fear that such firms would abuse their monopoly power and extort rents or monopoly profits from the consumer who had no choice in the market. There was also the belief that every citizen has a right to certain basic services and electricity was regarded as one such essential service that it was unacceptable to provide supplies on the basis of profit and individual ability to pay: hence the public policy of universal services for the utility industries. Most governments concluded that in such a situation the state would be better disposed to protect consumer interests, resulting in wide spread state ownership of the vertically integrated monopoly utility, consisting of generation, transmission, distribution and retailing, all typically falling under one enterprise supported by self-regulation. Electricity supply systems pre -1990 presents two structural variations. Fig. 3 below presents the traditional vertically and horizontally integrated franchised industry publicly or privately owned, which dominated the system after the 1950s. . Fig. 3 Franchised Monopoly Model Traditional Vertically Integrated Electric Utility Generation Retail Customers Coordination Transmission Reliability Distribution Dispatch Source.See Note 2, p.102 Essentially, there have been two variations of franchised monopoly structure. In some markets, only one single vertically and horizontally integrated utility is permitted, whilst in other markets there has been a variation involving a “franchised multiple distribution system”. In this instance one franchised vertically integrated Generation and Transmission Company provides bulk power, as is the case of South Africa, New Zealand and England and Wales in pre-reform days. The vertically integrated generation and transmission company is accompanied by multiple franchised distribution enterprises, each operating in an exclusive zone and buys bulk power at bulk 48 tariff, fixed by an independent regulator or the state. In some markets like Bolivia and South Africa, the integrated generation and distribution company is also permitted to own franchised distribution businesses, either vertically integrated or as subsidiary companies. This franchised multiple distribution structure is shown in Fig. 4 below. The pattern of electricity and financial flows under phase one is shown in Fig. 5 below. America and a few other countries such as certain Caribbean Islands up to the 1960s presented a different ownership model, consisting of private ownership of the utility with independent regulation to curb the monopolistic and rent seeking tendencies of the franchised integrated utility. The defining feature at this stage of development is that of one single franchised monopoly company dominating the market in a given area. In return for the monopoly status, a universal service obligation is imposed, whereby the utility is required to provide energy to everyone in the service area at a regulated tariff. Where the monopoly is privately owned considerable problems of regulation are encountered. Fig. 4 Franchised Multiple Distribution Structure G&T Generation Transmission Reliability Dispatch Coordination Distribution Distribution Distribution Retail Customers Retail Customers Retail Customers 49 Fig 5 Franchised Monopoly ( Phase I-Model One ) Integrated Industry Structure G G G G G G G Transmission Distribution Financial Electricity Examples France EdF, Some USA Investor Owned Electricity Utility, • Jamaica Supply C C C C C C C Source, Note 2 Fig.4 and Fig. 5, p.102 Where countries or regions have interconnected systems, marginal trading sometimes prevailed, more as a back-up arrangement. Prices reflected the assumption of reciprocal trading and were not intended to cover full cost of operation. Essentially, the price for “wheeling across” a utility transmission system is based on variable cost with fixed cost borne by the selling utilities franchised or captive customers. Under the franchised monopoly model the technology is dominated by economies of size and scope with the result that large vertically integrated plants and horizontally structured systems provided for lower cost of production. At this stage of development, neither retailers nor final customers are allowed a choice as to source of supply. This integrated monopoly, (especially when operated by private investors) creates the need for costly regulatory structures to control monopoly power. Such regulations up to 1980 have essentially been based on cost of service rate of return, as has been practiced widely in the USA. The US regulators; the Public Utility Commissions, have established a tariff formula based on a test year, the period of time under examination. Rates are then set using the historic test year, adjusted for known and 50 measurable changes. The process yields an adjusted test year cost of service that is meant to be a predictor of a company’s revenue needs during the period rates will be effective2. RR = E + d + T = [r(Y– D)] Where RR = Revenue requirement, or total revenues. d = Annual depreciation expenses. T = Taxes E = Allowable expenses Y = Original book value of plant in services. D = Accumulated depreciation. Note: Y-D = a net rate base. r = Weighted average cost of capital. Rates = RR/Volume of Sales A less rigid formula has been used in many other countries; however, the principle reflects a cost of service rate of return formula3. Rates are also determined annually creating the need for annual reviews. The overall objective is to set economically efficient prices, which should to the greatest extent possible, reflect long run marginal cost of service, while enabling the utility a reasonable opportunity to recover its legitimate cost of providing such services, including a rate of return on investment. A problem faced by economic regulators is that historic cost incorporated by the utility to recover its rates may only bear passing resemblance to forward – looking long-run marginal costs; (LRMC). The reconciliation of the need to cover historic costs with the desire to set economically efficient prices and to meet other objectives of regulation, such as fair price and universal service, requires judgement and arbitrary decisions. Marginal cost of service is expected to be the cost incurred to provide an additional unit of consumption at a particular time and represents the cost to society to satisfy that incremental demand. The nature of a monopolist, however, is that he will seek to set price above marginal cost, which is in large measure an historic average cost. Setting prices strictly to equal marginal cost is therefore, a problematic exercise and may be too high or too low depending on the quality of cost information available (the information asymmetry problem) to the regulator. Rate of return 51 regulation has produced perverse affects. Averch-Johnson states that rate of return regulation leads to over capitalisation (gold plating) or the Averch-Johnson (1962) 4 effects. Under the franchised utility model, operation of the electricity system often carries with it several policy goals. These policy goals often reflect macro-economic and social development objectives, such as to deliver low cost services to particular classes of customers. The net effect is crosssubsidisation which encourages inefficient consumption by subsidised customers, discourages consumption by some users and distorts the pricing and rate structure, resulting in unfavourable economic consequences, such as weak credit worthiness and reduction in the utility’s ability to attract financing without cross-guarantees. France today presents the best example of a country, which has remained at the model one stage and has been reluctant to change, other than meet the minimum requirements of the European Union (EU) recent directive5. Electricitè de France (EdF) up to 2001 was a one hundred percent publicly owned (vertically and horizontally integrated) firm, with almost complete monopoly at all levels of the production and supply chain. France has only initiated limited reforms and has shown no willingness to privatise EdF, or even to sell a minority stake. There is still strong public support amongst French citizens for a publicly owned and nationally integrated firm, providing public service that is reliable and reasonably priced. EdF prices and quality of service compares favourably with prices in other EU countries and the firm does not rely on public subsidy. French historical commitment to a vertically and horizontally integrated system is partly due to technological consideration; over 80% of generated capacity comes from nuclear power plants with only 15% hydro-electric6. Nuclear and hydroelectric technologies continue to benefit from economies of scale and scope. There are also economies of coordination between nuclear and hydroelectric plants. Nuclear power systems also present special problems. The low valuation, high cost of decommissioning and increased risk associated with private operation, makes it difficult to sell state owned nuclear plants. This, however, is becoming less so with improved efficiencies and safer operation of the newer plants. Opportunities for privatisation have therefore improved. French policy of uniform pricing with built in cross-subsidies, adds another factor, which will make it difficult to introduce direct competition. 52 With a continued commitment to nuclear power, France will entertain only limited structural changes to EdF. This is likely to involve access provision to the transmission and distribution system and accounting ring fencing. The question, however, still remains as to how the French will reconcile independent regulation with the continued desire for parliamentary control over utility pricing. Again it can be seen that external pressure, is at play and it is this pressure in one form or another which brings about changes from the franchised monopoly stage. The American system although normally considered to be one of private investor owned utilities with independent regulation does display more than one type of institutional arrangement. Munasinghe and Sanghvi (1989)7 state that: “contrary to commonly held views, the electric utility industry in the US is not homogenously organised solely along the lines of private ownership and public regulation, whereas investor owned utilities are dominant factor in the market, about a fourth of the market is organised along the lines of public ownership”. In 1989 there were a total of 3,456 systems in the US with 783,000 MW of capacity. Private ownership represented 77% of generation capacity, serving 73 million of the 96 million connected customers. The other systems are municipally or state owned, totalling 2200 with only 9% of generation capacity as well as over 1000 co-operatives8. Typically all the municipal and co-operative systems were distribution enterprises, buying power mainly in a wholesale bulk power market or through long term power purchase contracts from the investor owned utilities. Move Away from the Franchised Monopoly Phase The development, which led to the move away from the franchised monopoly phase, was pointed out in Chapter One to have started in 19789. Between 1985 and 1994 Qualifying Facilities and Independent Power Producers’ (QF/IPP) generation accounted for an average of 39% of all new capacity in the US. QF/IPP accounted for 43000 MW or 6% of US capacity in 1994 with a further 66000 MW under development in 1994. QF/IPP has offered US utilities a clear alternative for acquiring new capacity10. 53 Despite these competitive market initiatives the 1992 Energy Policy Act of the USA limits FERC, from issuing orders requiring a state utility to transport (retail wheeling) electricity to retail customers. Again it is competitive pressure essentially the smaller and efficient CCGT plants that have been fuelling the liberalisation movement in the electricity market in the USA. The significantly reduced sunk cost associated with CCGT allows for several new entrants to the generation sector. The generation market through “all-source” competitive procurement has, therefore, become highly contestable in the USA. A second feature, which has given impetus to change from the franchised monopoly structure, has been the movement away from state ownership to private ownership. The popular experience of the state controlled power sector has been high cost of production and in most developing countries the experience has also been low levels of accessibility by householders. Under the traditional state owned franchised monopoly electric utility structure there are no economic incentives to reduce cost or to provide improved quality to the consumer. A change to private ownership on the other hand provides the incentive for efficiency and the opportunity to subject the industry to the discipline of product and financial markets. Privatisation also increases access to capital markets, thereby removing one of the major constraints that have plagued publicly owned systems in developing countries. The state owned franchised monopoly utility also presents certain problems from being in the public sector. Many countries in the 1970s and 1980s experienced considerable inflationary pressures. In order to control inflation, governments were forced to introduce (often mandated by the international lending agencies) monetary constraints on the utility with the result that the margin between revenue and cost, already unbalanced in the electricity sector from under pricing to favoured groups such as rural and household customers, over-manning, political patronage, theft of electricity, and high levels of un-collectables is further squeezed and prices fall further below properly accounted average economic costs, bringing on financial crisis in the electricity sector. The electric utilities particularly in developing countries invariably recovered less than 60% of power costs from revenues. Newbery (1999)11, states that: 54 “Performance (public electric utilities in developing countries) was frequently unimpressive, particularly in the high inflation period after the oil shocks of 1970s. Prices were normally below long run marginal cost often despite excess demand, so that investment could not be adequately financed out of profits as in many developed countries. The average real power tariffs declined to below 4USc/kWh (1986 constant $) for 60 World Bank countries in 1989, while the rate of return on revalued net fixed assets also declined to below 4% for a sample of 360 firms. Actual financial rates of returns for 57 World Bank countries was well below the 10% rate of return taken as the test discount rate by international agencies –-under pricing electricity resulted in heavy fiscal burden estimated at US$90 billion annually or about 7% of total government revenues in developing countries, larger than the annual power investment of US$80 billion”. Similarly, Newbery and Greene (1996)12 found that in the UK the rate of return earned by the Central Electricity Generating Board (CEGB) between 1948 and 1990 (the period between nationalisation and privatisation) was less than 3%, although the test rate of return for the period varied between 8-10%. Further the accounting and financial systems of these utilities also came to be influenced by the practices, which prevail in the public sector. Government budgeting in the public sector for example is based on annual rounds of allocation and a utility dependent on the central budget for new and replacement investment capital finds it difficult to undertake proper capital budgeting. Many state owned utilities and their respective governments under the franchised monopoly phase have sought to bring about improvements to the sector while maintaining state ownership by adopting several private sector management techniques and management tools. Cordukes (1990)13 noted that the reforms in African countries started with the introduction of an affermage arrangement in Cote d’Ivoire in 1990 and later in Senegal with a management performance contract. These reforms often involve, increased levels of commercialisation, where the legal status of the enterprise is changed from a government department to a statutory corporation or joint stock company. Increased autonomy is then provided to the management of the company, and commercial objectives replace public interest objectives. Management performance contracts are sometimes introduced with clear commercial objectives, reflected in a memorandum of understandings or framework agreements, providing for a more structured relationship between the enterprise and the state as to each party’s responsibilities. Government’s sometimes going further 55 and contract out management to an outside private sector firm, under some form of performance based management contract. In addition, welfare grounded economic concepts in the form of long-run marginal cost pricing, test rate of discounts in line with low risk industries and hard budgets are further introduced to the utilities. Rate rebalancing involving the elimination of cross-subsidies and concepts of peak and capacity pricing are also adopted to provide for more relevant pricing practices. Several British White Papers14 in 1961, 1967 and 1978, for example, sought to establish the basis of applying marginal cost pricing to public utilities. These measures often bring about some level of performance improvements; however, they have proven to be unsustainable. They ignore essential questions of incentives and motivation and the problem of public control, which still prevails over public finance. Hard budgets for example address the symptoms of the problems, without addressing incentives for cost reduction and prudent capital investment. A consequential effect is that the utility is starved of investment funds with further adverse effects on plant availability. With persistent shortage of investment capital, governments are forced to find other solutions to address the problems. In recent years the solution has been to invite private investors to finance new capacity. This puts pressure on the system to move to the next stage; the purchasing agency phase. Besant-Jones15 maintains that: “private financing of power investments in a competitive market is feasible in a sound business environment ------------ Power sector reform can yield huge productivity gains particularly through dynamic efficiency gain under competitive pressure.” Model Two Stage- The Purchasing Agent Phase Under the purchasing agent phase the existing vertically integrated generation, transmission and Distribution Company may continue to be owned by the existing state or private franchised incumbent, with most or all of the new generation capacity to be added by IPPs. The IPPs contract with the incumbent utility as a single purchaser in the form of power purchase agreements for new capacity. The incumbent utility then resells the bulk power acquired from the IPP, along with its own generated power to captive distributors. 56 The IPPs typically develop new generation on a project finance basis with highly leveraged financing, involving very little equity (often below 20%). Bank finance, therefore, provides most of the capital. As the Banks need to minimise their risks, various forms of guarantees have to be provided by the single purchaser often including sovereign guarantees of the state. Where countries have introduced the single purchaser phase without the required legislative framework, country and regulatory risks will be perceived to be very high and the cost of the project will be high, as well as the level of risk the state will be required to undertake. As long as the power sector remains strongly dependent on political decisions, private investment in the sector will be perceived as very risky, especially by foreign private investors. Although many IPP projects require sovereign guarantees to mitigate these risks, experiences in the last few years of default on PPAs have reduced the value of such sovereign guarantees. The purchasing agent era marks the second phase of institutional development in the electricity supply system; that of private generation for new capacity as independent power producers. Access to the transmission and distribution wire, (except where bypass for the large customers is permitted) is restricted, as generators must sell through the single purchasing agent. The purchasing agent continues to maintain monopoly power over the network facilities and over sales to the final consumer. The defining feature of the second phase of development is one firm dominates the market as a monopoly seller and monopsony buyer of bulk electricity. There are a number of variations of the single purchaser model. Under one arrangement the single purchaser acts as an active trader in the market, and is the sole purchaser and the sole seller, taking responsibility for receipts and payments and the associated risks. Under another arrangement, the single purchaser operates as a neutral agent, essentially as a facilitator and aggregator, with contractual commitments and payments flows taking place directly between the generators and distributors and other traders. A third variation is to allow for competition in the large end user market. These large end users and or distributors are then permitted to enter into bilateral contracts and purchase direct from generators and in so doing bypass the single purchaser or the franchised vertically integrated incumbent utility. Under these circumstances, open access to the transmission and distributions systems is required. Where other distributors are allowed to bypass the single purchaser and contact directly with generators, the arrangement is then described as the principal agent variation. 57 The transmission company may be separated out as the single purchaser, and organised as an active participant in the market or as a neutral participant. If the transmission company as an active single purchaser buys and sells in the market it is likely to be faced with liabilities far greater than its own wires business. Generators will, therefore, seek cross-guarantees from the state in respect of such payment risks. The advantages of the active single purchaser model is that it permits load aggregation and economies of scale in contracting, provides for a single bulk transfer price and the trading arrangements are simpler. The active single purchaser limits the development of further competition in the sector, especially opening of the market at the retail end. It also centralises payment risks in one firm. A distribution company that fails to collect from its customers or has high non-technical losses exposes the single purchaser to very high risks, without the single purchaser being able to do anything directly to reduce the losses. As the sole purchaser, there are also problems of independence and transparency and the sole purchaser may be vulnerable to political pressure and corruption. Where the single purchaser is neutral, he buys as a representative of the distribution companies (or end users where this is allowed). In effect he acts as a load aggregator and performs a go-between role (generators and distributors) in public tenders and contracting. Payment obligations and flows are directly between the generators and the distributors. The advantages are that this arrangement incorporates the knowledge of the distribution companies in the contracting process. As with the active single purchaser it also facilitates load aggregation and a single bulk electricity price. The trading rules remain simple; however, additional rules are required to define the limits of the rights and responsibilities of the single purchaser and the distributors. The problems of transparency although not eliminated is reduced. In the Panamanian principal/purchaser arrangement the distributors are allowed to buy up to 15% of their market needs directly from generators. The advantage of the principal/purchaser arrangement is that competitive pressures can be brought to bear upon the principal purchaser. Where by-pass of the distributive system of the integrated incumbent utility is granted to large end users then competitive pressures are also placed on the incumbent utility in respect of this liberalised market segment. Alternatively, the transmission and distribution segments may be unbundled from generation and incorporated as a single business to operate as the monopsony purchaser/principal 58 purchaser. The advantage of unbundling the integrated incumbent utility and separating transmission from generation and distribution is that it facilitates a higher degree of competition in later phases of the reform. The important feature at this phase is that new capacity is subject to competitive bidding; competition for market and additional capacity is acquired through long-term power purchase agreement. Additionally, retail customers continue to remain captive to the integrated utility or the franchised distributors, creating the need for significant levels of regulatory intervention. Fig. 6 below shows the industry structure for the vertically integrated single utility, as the single purchaser, whilst Fig. 7 shows the structure with the vertically integrated transmission and distribution company, as the single purchaser with a horizontally unbundled generating sector. Fig. 8 shows the structure where transmission is vertically unbundled from generation and distribution and with the transmission agency operating as the single purchaser. It is possible to establish only one generating company and one distribution company upon separation, however, if the intention is to increase competition, then generation and distribution should also be horizontally unbundled to reduce market power, monopoly of information and problems of self-dealing. Fig. 9 shows the electricity flows under the active single purchaser (vertically integrated utility), whilst Fig. 10 shows the financial flows. Fig 6 Purchasing Agent Model (a) US System after Liberalisation Wholesale Consumers Distribution Independent Private Investor Owned Wheeling Transmission Generation IPP IPP Qualifying Facilities IPP 59 Fig.7 T&D as Single Purchaser (Horizontally Unbundled Generation) Genco Genco Genco Transmission Distribution Captive Customer Captive Customer Captive Customer Captive Customer Source: Fig 6 and 7 see Note 2, p.102 Fig. 8 Transco as Single Purchaser (Horizontally Unbundled Gencos and Discos With Large Customer Bypass) Genco Genco Genco Transco Disco Captive Customer Disco Captive Customer Disco Free Customer 60 Fig. 9 Single Purchaser (Phase Two) Industry Structure (electricity flows) G G G G G Transmission G G Single Buyer Disco Disco Disco Supply Supply Supply C C Northern Ireland after 1990 reform C C C C C Source:Fig 8 and 9 see Note21 Page 102 Fig. 10 Single Purchaser (Phase 2-Model Two) Industry Structure (Financial Flows) G G G G G Transmission G G Single Disco Disco Disco Supply Supply Supply C Source: Note 2. p.102 C C C C C C 61 Maintaining the vertically integrated utility as the single purchaser presents considerable problems involving self-dealing and market power. Market power is the ability of the firm to earn economic profits in the long run without inducing entry and the ability to raise prices above competitively determined levels. Market share concentration and entry conditions are necessary but not sufficient conditions of market power, there must be high probability of abuse of such power in the industry16. The initial reforms should therefore, involve the vertical separation of transmission from generation and distribution. The single purchaser model requires clear policies with respect of risk allocation, and clear and enforceable contracts with a credit worthy purchaser. If enforceability and credit worthiness are in doubt alternative forms of credit guarantees will be needed, either in the form of sovereign guarantees with the state or cross-guarantees from other credit-worthy sources. Risk must be allocated between the incumbent utility and the IPP developers on the basis that the party that can most efficiently deal with risk or reduce it should bear such risk17. The single purchaser phase requires continued heavy handed regulation over quality of services and retail tariff. In addition, the regulator takes on a new role, that of creating the competitive conditions for the provision of new capacity to the system. Where bypass is allowed, regulatory intervention will also be needed to establish and ensure non-discriminatory access to the distribution and transmission lines. A continued requirement for the single purchaser phase is that of integrated resource planning to form the basis on which to evaluate future competitive bids and to provide a framework for potential investors. Bulk electricity prices offered by IPPs will generally reflect the cost of risk accepted by the IPP. The more stable and predicable the market conditions the lower the prices. The principal risks are currency payment and political, management and technology risks. IPPs receive payments in local currency, yet many of the costs; such as fuel and capital are in foreign currency. The financial strength of the single purchaser may be weak, especially where there are major problems with collectables, creating the risk of default on payments. Many countries are politically unstable, and experience frequent or sudden change of government, resulting in changes to the market rules. Developers or strategic investors of IPP companies normally only take a minority equity stake in the company and this increases the risk of management oversight. 62 Finally, the technology selected may not perform as originally expected. In general the greater the risks borne by IPPs the higher the bulk electricity prices therefore if governments need lower prices, then risk reduction through some form of sovereign guarantee from the state or cross-guarantee from an international financial institution will be needed. IPP plants are usually implemented on the basis of non-recourse financing18; the financing strength of the power purchase agreement is able to show that the cash flows from the contract can meet all debt payments, hence the long term nature of the contract; 10-15 years for CCGT plants and 25-30 years for hydro-plants. The length of the plant’s life determines the expected payback period for the investment, with shorter repayable period for CCGT plants. Power purchase agreements have increasingly become more complex overtime19, in an attempt to deal with all the many contingencies, such as providing for the IPP plants to be used more efficiently, to provide for more flexibility as with a two part pricing system or provide for buyout provisions or provisions which allow the purchaser to terminate the contract within a specific date or to allow the debt/equity to take over more of the risks. Gardner and Maine (2000)20 state that: “There are a growing number of examples where IPP merchant power plants are being constructed without long-term contracts. In these cases IPPs who have sufficient confidence in the economic, financial and operation of the electricity spot market or the strength of retail competition will finance plants based on expected cash flows from direct sales to retail customers to meet the debt repayment”. This development is relatively recent and is unlikely to be an option available to developing countries, because of their very poor risk ratings on international financial markets. A problem faced by several developing countries with a small electricity market, is that they have taken on board a number of IPPs in the mid-1990s in order to avoid radical structural changes to the electricity industry and the introduction of retail price rebalancing, which are essential elements of the reform process, for fear of adverse public reaction. The single purchaser for the PPAs is often the existing inefficient integrated state owned utility. Both the utility and the portfolio ministry, often do not possess the commercial skills and procurement experiences required in the 63 sophisticated negotiations involved in the development of the new contracts, with the net effect that the utilities, on the basis of political pressure are forced to sign high priced or poorly designed PPAs with elaborate payment guarantees that the Treasury can ill-afford21. An example of such a project is the first PPA agreement in Tanzania. This contract eventually ended up at international arbitration in order to resolve the dispute over the tariff, which should be paid by the utility to the developer. Countries that fail to restructure and introduce IPPs into the system to co-exist with the inefficient integrated utility not only create a number of problems22 but such countries may have forfeited the option of a well structured single purchaser enabling environment which would allow it to move to a more competitive bulk electricity market at a later stage. For efficient production under the single purchaser phase, the appropriate trading protocols, and legislative instruments will of necessity need to be developed and implemented, covering such matters as competitive bidding and evaluation process, regulatory oversight of the incumbent utility’s purchasing decisions, entrenchment of property rights and introduction of an independent regulatory agency. The single purchaser model trading arrangement normally involves contracts of “take and pay” nature. These are contracts for sale of energy availability and other generation services from an independent power producer and the obligation to pay remains even if the plant is not dispatched. In earlier stages of contract development the energy price was based on the average cost of the IPPs operation as it relates to a predetermined output or on the basis of the utility’s avoided cost. If the IPP achieved this level of output its cost would be covered and profits earned. The establishment of IPPs’ prices based on rolled in average cost (X/kWh), however, is an inefficient way to structure the contractual arrangement. Where bidding for new capacity by IPPs for example are through total embedded cost as in “take and pay” contracts, inefficient operations will be encouraged as once entry takes place the plant is effectively fixed and there is no further competitive pressure for the duration of the contract. A more efficient pricing mechanism was later developed which limited the energy price to the variable cost of the IPPs operation, combined with an availability charge where variable cost represents fuel and other variable operating charges. The introduction of two-part pricing system 64 with a variable element provides an opportunity for the energy (or variable) price to play a key element in economic dispatch and for competition to be improved23. With a system of economic dispatch, IPPs with the lower variable costs are dispatched in order of merit and in so doing an element of product market competition can be introduced. Two-part pricing also provides the opportunity to ensure that the price components reflect underlying cost of the technology being purchased. Hydro-plants display high fixed cost component and low variable component, whilst CCGT plants display higher variable cost component to fixed cost. Energy charges can be “one price” or different prices for different volumes. It may for example separate start-up cost from “on-load” costs. It can also be fixed by a formula, which takes into consideration the cost of fuel and the thermal efficiency of the plant. Fuel prices may then be indexed to an external factor. The availability payment in the two part pricing system is usually set to cover the capital and other fixed costs not covered by the energy charge. These costs are incurred whether the plant operates or not. Capacity charge is not normally subjected to escalation clauses. It is paid so as to have the plant available if called upon to dispatch and is important to meet mid-merit and peak demand. A target level of availability in terms of capacity is set for the year or for each hour in the year with a fixed annual payment to be paid if the target output is achieved. Adding incentives and penalties can include further sophistication. Other services may also be procured such as reserve, reactive power, and emergency generation or production above normal level. Often these are calculated as lump sum payments for willingness to perform each of the respective service. Under the purchasing agent arrangement the distribution companies buy bulk power at preset wholesale prices, established by a regulator. The regulator also sets the price to the final customer or retail price. The IPPs under the purchasing agent phase are insulated from technology and to a large extent market risks, hence there is less incentive for innovation. The purchasing agent takes most of the market risks. Newbery (1999)24 states that: 65 “the recent Asia financial crisis demonstrated the unsuitability of PPAs. East Asia attracted US$80 billion in the power sector between 1994-1998, over half the total by developing countries and substantially ahead of the only other major destination, Latin America with $53 billion. In 1996, 68% of incremental power sector investments in East Asia were financed by private capital and three quarters of the investment was in greenfield projects, mostly new generating plants. In contrast most of the investment in Latin America was for the purchase of divested publicly owned assets, with only onethird for financing new Greenfield capacity. Reforming countries in Latin America restructured and unbundled their ESI’s and created electricity markets. In contrast, East Asian countries invited private capital into generation through IPPs and negligible restructuring and reform”. The financial crisis of 1991 significantly impacted on the East Asian countries exchange rates and their GDP growth rates and in turn the demand for electricity. The collapse of some of the currencies resulted in a doubling in the domestic cost of electricity under the PPAs. The fall in demand also meant some of the electricity was not then needed, however, the utilities were under contract to meet the capacity payments. As the various East Asian governments were reluctant to pass on the increased cost in higher prices for fear of adverse public reaction, the financial crisis was transferred to the power sector. In Philippines the foreign debt of the state owned utility increased to more than 20% of the national debt25, creating strong pressure to default on payment or renegotiate the IPPs, and this further amplified the loss of confidence of foreign investors in the country. This form of private investment is equivalent to expensive foreign debt borrowed by government. When embarked on a large-scale basis by a developing country, it disguises the extent of the foreign debt exposure (the true cost is concealed in the PPAs). PPAs carry very high interest rates because of their higher risks and private source of financing, compared to the lower World Bank (and in the case of most African countries the much lower IDA interest rates) and softer payment terms, which has been the typical form of financing expansion for state utilities under the franchised monopoly phase. Introduction of IPPs, therefore, does not address the underlying problems of the electricity sector. 66 The extent to which private investment from IPPs with the implicit debt incorporated in the capacity payment and which is seen to offer a solution to the investment problems of developing countries is now subject to a lot of questioning and as argued by Newbery (1999)26 the single purchaser model serves to misallocate risks between the foreign investor and the domestic state owned utility and is a poor substitute to traditional forms of financing electricity investments from multi-national sources. It is also a poor substitute for competitive industry reforms. There is no doubt that the single purchaser model offers certain advantages. It allows for certain public policy objectives to be achieved, such as universal service obligation. It allows for continued central planning of the system, and for competitive entry of potential investments from the private sector to meet increased expansion needs, whilst it reduces funding requirement from the state and can be structured as a transitional phase to increased levels of competition. Its disadvantages are that investment is not market led, there is misallocation of risk between the IPP and the domestic utility as shown in the East Asian experiences in 1998 and this could lead to stranded costs, with the results that consumers or tax payers are required to meet the cost of inappropriate investment decisions. There is still supply monopoly, choice is still restricted as the distributors remain captive to the single purchaser and retail consumers remain captive to the distributors. Model Three Stage- Bulk Electricity Market Phase Over time, the purchasing agent phase arrangement comes under pressure, from distributors who seek to obtain direct access to the generators through open access to the transmission system. Open access to the transmission network creates the requirement for new trading arrangements for bulk electricity, and these become the defining features of the bulk electricity market phase. Distributors, however, continue to maintain monopoly of supply to final customers in their service areas, although a few large consumers may be allowed to bypass the distributors and buy in the wholesale market or contract directly with generators. Most final consumers, (particularly household consumers) however, continue to be denied choice in selecting the services needed. 67 The bulk electricity market structure imposes a requirement for transmission to be unbundled from both generation and distribution, and for separate ownership structures at each of the three vertical stages. Power purchase agreements are replaced by bulk power contracts (BPC) in which the contracts simply hedge price risk. BPC are different from PPA in that a PPA specifies the particular generating plant in question which is to supply the power, whereas a BPC specifies the node on the network where power will be delivered and allows the seller to choose any availably source of supply. This gives the seller more flexibility as he can sell the lowest cost source of power to meet a given demand. He could choose not to supply from his own plant and source supply from the spot market if the spot market is lower. It gives the supplier the option of “make or buy decisions”. Accounting and operational separation are, however, feasible options but must be supported by heavy-handed regulation. In accounting separation, separate accounts are required for the network activities, which are then ring fenced. In operational separation, whilst physical unbundling takes place, ownership remains unchanged, as is the case in the US where the transmission systems continue to be owned by the investor utilities, however, transmission is separately organised as an operator to provide the transmission services. PPAs can also be used under wholesale and retail competition phase. A wholesaler or aggregator is, however, needed to combine a number of PPAs with spot market purchases in order to assemble the volume of electricity required to service the wholesale or retail market. The trading arrangements under the bulk electricity market phase calls for an independent systems operator (ISO), to carry the responsibility of keeping the frequency and voltage of the transmission stable. The systems operation function can be combined with the functions involved in the transmission of wires services as one organisation. Alternatively a separate organisation, a load dispatch centre may be introduced to execute the systems control, and market administration functions. In order to ensure non-discriminatory behaviour international best practices now suggest that that the transmission operator should be made neutral to the system and not normally be allowed to trade in the bulk power market, in which case the transmission operator’s role is limited to that of providing wire services and the execution of dispatch based on instructions received at a price determined by the regulator. In the UK the dispatcher, transmission wire services and market 68 operator’s functions are all integrated into one firm, the National Grid Company. There is however, the concern of self-dealing with integration of the three functions. Hogan27 points out that: “the systems operator must be independent of the existing utilities and other sellers and buyers in the market”. This requires ownership separation between generators and transmission operators. Should the transmission company own generation, it is likely to favour dispatch of its own generation over competitive plants to the detriment of suppliers and customers. The privileged generators also will be under much less pressure to reduce cost and may not be the least-cost source of dispatch. In Victoria, Australia the market operator and the dispatcher’s functions are integrated28. The bulk electricity market model is shown in Figure 11. Fig. 12 shows the electricity flows and Fig. 13 shows the financial flows. The level of regulation in this phase is much less than under the two previous phases, in effect the nature of regulation changes with the emphasis being to ensure that market institutions, regulation and market structures are introduced which provide for the greatest level of competition and the greatest level of customer choice, including prices, service quality as well as provide for consumer protection. Economic regulation of the generation sector or for wholesale electricity is more to ensure that there are transparent non-discriminatory rules and to control market power and reintegration rather than that of price regulation. A market mechanism is developed to provide for price discovery. In the self-regulated exchange, ownership of generation by the transmission company, as was the case initially in Chile in the 1980s, makes the threat of entry less effective in holding down prices. 69 Fig. 11 Electricity Exchange Market Model UK System Immediately after Privatisation Reliability Coordination Power Pool Generation Company N A T I O N A L Generation Company D Captive Consumers D D Generation Company Captive Consumers D G R I D French System Generation Large Consumers free D Transmission Distribution Consumers Source Note 2 p.102 Fig.12 Electricity Wholesale Market (Phase 3-Model Three) Industry Structure (electricity flows) G G G G G C Disco Disco Disco Supply Supply Supply C C G Wholesale Market Transmission Large Customers G C C C England &Wales (Post 1990) Argentina (after1993) Bolivia (After1996) C 70 Source: Note 2,p.102 Fig.13 Electricity Wholesale Market (Phase 3- Mode Three) Industry Structure (financial flows) G G G G G G Wholesale Market Transmission Large Customers C G Disco Disco Disco Supply Supply Supply Supply C C C C C C Source: Note 2, Source p.102 The network characteristic also makes it difficult to provide transmission and distribution wire services on a competitive basis. Invariable there is one transmission system, however the transmission can be made neutral to the market. The distribution system at the same time can be horizontally unbundled into regional companies to provide for yardstick competition. The network element, the transmission segment and the distribution wires business remains a natural monopoly, and the only competitive opportunity available is that of by-pass competition involving the imposition of common carrier conditions on the transmission system. There is therefore, the need for the unbundling of the competitive generation segment. Preferably the generation business should be separated from the remaining core network element and privatised. Generators are then in a better position to compete for the bulk electricity market. 71 The regulator is also in a better position to focus more attention on the network areas and to ensure open access, competitive market conditions, and guard against the abuse of market power. Continued integration provides a better environment for the utility to abuse its market power, to impose its will on the market and to derive benefits from the control of valued resources; the network assets and information. Producers of generated electricity have a natural tendency to exercise market power or to engage in collusive or gaming behaviour. Firms will exercise market power to reduce transaction costs. The forces of vertical integration between generation and transmission remain strong, despite legal instruments, which mandate physical separation. The desire for vertical integration and or long-term contracts is therefore, a response to market risks and the need to reduce costs. The introduction of a competitive bulk electricity market overcomes two problems associated with both the franchised monopoly and single purchaser phases. It provides incentives for efficiency and a mechanism for adequate but not excessive investment finance. A competitive bulk electricity market forces firms to pursue initiatives which lead to cost reduction. It also ensures that expansion reflects long run marginal costs, whenever investment is needed. A series of fundamental and irreversible reforms to the industry structure and relationship must be undertaken to introduce a competitive bulk electricity market29. Phases One and Two structures are generally found to be inappropriate for such a market. The opportunity for free entry of private ownership and investments into the sector must be made mandatory and cost reflective tariffs must be introduced. While a bulk electricity market is superior to that of the single purchaser arrangement in terms of the superior price signals that it provides, it is often not the initial reform priorities in small developing markets of Sub-Saharan African and many developing countries, starting from a base of low accessibility (below 10%), pervasive under pricing, gross overstaffing, excessive cross-subsidisation, widespread political and corrupt interference in operations and high levels of commercial losses, involving theft of electricity or the high incidence of failure to make payments for electricity supplied. 72 Markets also cannot operate unless there is reliable excess capacity in the system, which is a feature absent in many developing countries’ electricity markets. New legislative frameworks, which support private capital and property rights, are needed as well as new independent regulatory institutions that have the confidence of private investors. Sub-Saharan Africa and many developing countries have very low regulatory endowment and the culture of independent regulation is absent and both act as major constraints to the introduction of power markets in these countries. In sequencing the reform, it is necessary first to separate out the network monopoly of distribution from the rest of the system and subject this sector to cost reflective tariffs. Second, the network monopoly of transmission should be separated from generation to create the conditions for regulated open access by third parties. Finally the horizontal unbundling of the generation sector should be undertaken to create large enough numbers of competing generating companies to avoid the problem of market power in the bulk electricity market. The importance of starting with distribution is that commercial sustainability and viability must first be demonstrated at this end of the market to provide the confidence of investment in transmission and generation. Some countries have expressed preference for the transmission system to be retained under public ownership. In such a situation, there will be the need to separate out the transmission wire service function from the systems and market operation functions. Foreign investors are not likely to be attracted to a system where the market is controlled by a state owned company. The case for initial ownership of the transmission company is that this aspect of the industry previously was never subject to any market arrangements, therefore, it is very difficult to value the business for sale. A case in point was in the UK where the National Grid Company was valued at £2.3 billion in 1990 (the implied value of 1996 prices was £2.7 billon). In 1996 when the private owners floated the shares on the stock market, the yield was £4.5 billion30. Performa accounts of the unbundled transmission company are no substitutive for a number of years of trading and valuation based on such revenue streams. Ownership of the transmission company in developing countries could also present expansion problems, especially where significant levels of investments are needed initially to reduce transmission constraints. Transmission is capital intensive and developing countries may still find it difficult to raise the initial capital for expansion, which is crucial to attract private investors to the sector. 73 In restructuring the generation sector the practice has developed of providing a set of vesting contracts (3-7 years and more likely 5-7 years in developing countries) to be held between the new privately owned generators and retail suppliers or between generators31. Vesting contracts provide revenue certainty and reduce financial exposure during the transitional period, which may arise from the veracity of spot markets or poorly designed markets. These contracts, also serve to limit discretion of inexperienced regulators in the initial and uncertain years of the reform. If the proportion of PPAs is significant, then these PPAs will need to be renegotiated to confirm to more sensible distribution of risks. These contractual changes will be purely financial in nature, and payment will not be contingent on dispatch of underlying plants. The difference between the capital value of the new contracts and the original debt is a measure of the size of the stranded costs. The stranded cost will need to be addressed: initially they will need to be taken over by the state or alternatively the state will need to provide cross-guarantees. The competitive bulk electricity market phase does not eliminate monopoly in the distribution and retail supply end of the industry. The monopoly retail market (or non-liberalised retail market) will need to be licensed with the obligation to supply all captive consumers in the respective franchise areas. Bulk Electricity Market Design Options The bulk electricity market can be organised as either a power exchange or pool, with associated markets for ancillary services. Sufficient numbers of generators will be needed or alternatively face sufficiently strong threat of potential entry from new entrants so that they are unable to exercise market power in the bulk electricity market. Suppliers and market participants should be free to buy in the bulk electricity market or sign contracts with generators and sell to eligible customers and be required to pay the cost of transporting electricity over the transmission system and for distribution line services. Two types of market arrangements; the centralised gross and often mandatory pool and the bilateral contracts and balancing spot market or net pool are illustrated below. Fig. 14 below depicts the 74 centralised power pool, whilst Fig. 15 depicts the net pool. Australia, New Zealand, England and Wales (pre-2000) and Spain adopted centralised markets, whilst Norway, Sweden, Finland and England and Wales (post of 2000) adopted the net pool. Wholesale power markets, as shown earlier are either cost based or price based as to the form of price discovery system. The price-based system has found widespread support in the power markets of Latin America. The design features of the transmission system also vary in respect of the institutional arrangements, ownership structure, extent of dis-aggregation of transmission charges and the structure of incentives provided to secure new investments and expansion of the system. In Panama, Guatemala, El Salvador, Peru and New Zealand the transmission entity is structured, in the form of a joint stock company, wholly owned by government. In Colombia, ownership is in the hands of a joint public-private company, whereas in Argentina (7 transmission companies) Chile, Bolivia and England and Wales, ownership is in the private sector. The method of divestiture of transmission companies also varies. In Argentina, Brazil, Bolivia, Chile and Peru divestiture is brought about by a long-term concession contract. Alternatively divestiture may take the form of sale of assets or sale of shares as in the case of England and Wales. A third approach is government ownership of the transmission assets, accompanied by an operating lease to a private specialist investor and operator of the transmission business. Balancing power market mechanisms can become extremely sophisticated, hence Besant-Jones and Tenenbaum (2000)32 have suggested a simple balancing arrangement as an alternative to the more sophisticated procedures. This procedure provides for large consumers and distributors to enter into bilateral contracts with a generator for most of their needs and then engage one of the generating companies or systems operators to meet the moment of moment fluctuation in demand. Balancing is then performed by a contracted agent and not by a balancing spot market. 75 Fig. 14 Bulk Electricity-Mandatory Power Pool Design Genco Genco Genco Pool Price Transmission tariff GROSS P OO L Disco Disco Disco Disco Large users Source: Note 2, p. 102 Fig 15 Fig 15 Bulk Electricity-Balancing Market DesignMarket Design Bulk ElectricityBalancing Genco Genco Genco Transmission Tariff; RESIDUAL POOL Balancing Price Disco Source: Note 2, p.102 Disco Disco Disco Large Users 76 An inherent problem of electricity markets as seen earlier is that the exercise of market power and the opportunity to exercise market power tends to be more pronounced during peak periods. If there are a small number of generators having discretionary power, the incentive for opportunistic behaviour to boost price will be strong. Firms will seek to maximise profits and constrain competitive behaviour, either from collusion or gaming the market. In constraining truly competitive conditions generators can increase prices and extort rents. If the firm behaves as a Cournot oligopolist33 that firm will bid into the market (especially during peak demand period) and will assume that the quantity bid by the other, will be the same as it was in the last similar period and as a consequence, the firm can assume that the remainder of the market demand curve is there to be exploited. The firm will, therefore, bid like a monopolist for that segment of the demand curve. If all firms behave the same way there will be an equilibrium price, higher than the price that will prevail under truly competitive bidding. Market design must, therefore, recognise this characteristic of an electricity supply system and should seek to minimise the exercise of market power. Holburn and Spiller (2000)34 state that: “Market power allegations have emerged as an anticipated major policy concern in many jurisdictions that have implemented competitive wholesale markets over the last decade”. In the design of power markets, a number of approaches have been adopted. Some auction rules have become very complicated, that they lead to gaming of the market, for example the situation in the UK where generation firms were able to withhold capacity from the market in order to drive up the spot market prices. Some Latin American markets such as Chile and Bolivia require bids to be based on audited marginal costs and the construction of elaborate system of rewarding fixed costs. This may be desirable in smaller markets or as transitional arrangements until the competitiveness in the market is more effectively established. Market power can also be reduced by encouraging or requiring plants to be contracted, for then the benefits of manipulating the wholesale price can only be obtained from the un-contracted segment of the market. Governance Structure of Power Pools and Exchange Markets Electricity pools, whether central mandatory or balancing trade net pools require a governance structure to ensure that self-regulation of the market is transparent and eliminates self-dealing, 77 conflicts of interest and abuse of market power. Four basic models have been developed; a multiclass stakeholder board, a non-stakeholder board, a single class board and not for profit enterprise, not affiliated with market participants35. The type of governance structure adopted, to some extent will be influenced by the ownership structure of the transmission system; publicly owned, as in New Zealand, privately owned as in Bolivia or jointly owned by a class of participants, as was the earlier case of the England and Wales pool, as well as to whether transmission is a neutral agent, providing only wire services and market operations and systems control is assigned to another entity. In the markets of England and Wales, Colombia and Panama the transmission company is an active agent, in the markets of Argentina, Bolivia, Chile, Guatemala the transmission is a neutral participant and a separate agency or Independent Systems Operator performs the system and market operations function. In a multi-class board, most or all of the market traders, including consumers are represented on the pool’s governing board. It fails to achieve independence if one class has veto powers. The nonstakeholder board members are prohibited from having conflicting interest with market participants. The non-stakeholder board is the dominant model in the USA. A non-stakeholder board, however, may become too detached, with no strong incentives for efficiency. In a single class board, one class controls decision-making where the pool is effectively a club of generators as is the case in Chile. The non-profit association or a single for profit organisation model not affiliated to market participants helps to ensure neutrality and minimises conflicts with respect to insider influence. In much the same way as no typical ownership structure has developed for the transmission system, no typical ownership and governance structure has developed for the management of the centralised pool or the balancing power exchange. Whatever the structure, the regulator needs to ensure that the pool is independent of special interest and should have the power to vet market rules to ensure transparency and guard against discriminatory rules and the exercise of market power. Design features in electricity markets are constantly evolving. Several factors influence choice of design features and these differ from market to market or from one country to another. There is, however, a trend towards market based solutions, both for bulk energy prices and for transmission services over administered arrangements. There is also a movement towards bilateral contracting and self-balancing markets as this option gives greater choice to participants and greater flexibility in 78 trading mechanisms and contractual forms. With advances in telecommunication and computer technology, several of the markets are also moving towards real time operation36. The theory that electricity generation is no longer a natural monopoly and therefore, can be subjected to full-competition without the need for regulation when the transmission function is unbundled from generation as required in the bulk electricity market phase does not remove the requirement for co-ordination which itself is inconsistent with competitive behaviour and each firm acting independently in the market. The regulatory requirement merely changes to providing the framework for a transparent market operation and to enable the market to cope with market power, which seems to recur even, when generators’ market share is as low as 10%. The principal advantages of a market for bulk power market are that it decentralises responsibility; expansion of new capacity is market led, it meets demand for more customer choice and competition and ensures efficiency enhancing behaviour, leading to productive and allocative efficiencies. In small markets it may not be possible to create sufficient generation companies to avoid market power and gaming of the market and this serves to frustrate competition. Additionally, governments also loose certain level of control over the industry, as it is not easy to accommodate social objectives. Often power markets present the problem of stranded cost and there is no easy solution to this problem. Balancing bulk electricity markets with bilateral contracting also provides for the economies of self-interest and the discipline of competition for further efficiencies. In theory no major disadvantage is associated with wholesale electricity markets. In reality the biggest problem is the level of knowledge required and the software and communication tools needed to implement the market arrangement. Model Four Stage - Retail Competition or Customer Choice Phase Model Four Phase or the customer choice model, forms the final phase that has emerged to-date. At this phase most final customers are allowed to choose their suppliers with the result that competition is provided at all three levels; new capacity, bulk electricity and at the retail level. Trading arrangements and access arrangements become more complex, in that access to the distribution network is required in addition to access to the transmission wires. In the customer 79 choice model a final separation is required, that of separation of the merchant function of supply from the distribution wire business. Figure 16 below illustrates the customer choice model or open network structure. In the bulk electricity market phase, the low voltage distribution wires are normally integrated with the supply function. Fig. 17 and 18 show the electricity and financial flows under the customer choice phase. During this phase of development, retailing becomes a separate function, distinct from the low voltage wires. Both generation and retail supply markets are then open to full competition. Generation must also be separated from transmission and distribution. Both the generation and retail segments can then operate in the competitive part of the market. Restrictions on cross ownership between generation and retail may not be necessary. The focus of regulation should then be on the natural monopoly segments of transmission and distribution. In the customer choice phase the pool operator does not take ownership of the power or take any market risk. The pool operator is really an auctioneer, as the trading is done between the generators and retailers or consumers. Extensive bilateral trading across the network is also facilitated. Although the volume of spot trade may be very small, the spot market is critical to the system. Fig. 16 Consumer Choice Structure (Open Network Structure) Genco 1 Disco 1 Consumer captive Consumer Free Genco 2 Generation Disco 2 Free Consumer Consumer captive Distribution Consumers 80 Source: Note 2, p.102 Under customer choice, phase metering of all customers becomes essential, as each customer must be metered half-hourly or hourly to show how much each individual customer takes from each retailer over the settlement period. In the absence of metering, profiling is sometimes adopted. Profiling involves the establishment or categorisation of the demand pattern of each consumer. The use of revenue grade meters can be seen by consumers to be relatively expensive when compared to the expected returns and can act as a barrier to the extension of competition at the retail stage. New Zealand initially adopted profiling to overcome the cost problem of retail metering. Consumer’s desire for choice and the general conclusion that in the bulk electricity market arrangement generators have failed to pass on costs savings to the retail consumers and this has fuelled pressures for the extension of competition to the retail market. Generators have failed to pass on the benefits of productive efficiency. Actual consumer choice in the power sector is often limited however despite this restriction pressures for more consumer freedom have been increasing in mature markets. In the United States for instance several states have been implementing reforms over the last three years to facilitate the wheeling of power over the incumbents utility company’s distribution lines to allow consumers to choose their power suppliers or more accurately to switch from one retailer to another retailer. Change of retailer does not imply a change of the physical network; the new supplier merely takes over the physical system from the displaced retailer. New Zealand has also recently introduced new regulations extending the benefits of retail competition to all consumers. The same forces, which have transformend the telecommunications sector, are now driving the transformation process in the electricity sector. In the case of electricity the pressure derives from large consumers seeking more cost competitive rates by negotiating bilateral contracts with independent power producers. Governments also often set special lower rates for low-income groups with the result that medium sized residential consumers find themselves subsidising both industrial and low-income consumers. These consumers then seek a fair framework and demand freedom to choose suppliers. The reduction in 81 optimal size of plants has in itself also encouraged large consumers to generate their own power, giving rise to a new type of power company; self-generators. These forces have combined to increase the desire of consumers to manage and understand their power purchases. This trend is expected to continue over the next ten years. Fig. 17 Retail Competition (Phase 4 – Model Four) Industry Structure (Electricity Flows) G G G G G Disco C Disco C G Wholesale Market Transmission Large Customers G Supply C C Supply 82 In the bulk electricity market phase discrimination continues against the domestic and household consumers. Medium sized domestic and household consumers are also called upon to subsidise low-income consumers. Beato and Fuente (1999)38 state that: “Consumers have become aware of the implications of cross-subsidy practices. Until recently despite the fact that electricity is a top consumption item, consumers have had little say on the purchase of electricity and no price information”. In the bulk electricity market phase discrimination continues against the domestic and household consumers. Medium sized domestic and household consumers are also called upon to subsidise low-income consumers. Beato and Fuente (1999)38 state that: “Consumers have become aware of the implications of cross-subsidy practices. Until recently despite the fact that electricity is a top consumption item, consumers have had little say on the purchase of electricity and no price information”. 83 FIG. 18 Retail Competition (Phase 4 – Model Four) Industry Structure (Financial Flows) G G G G Disco G Disco C G Wholesale Market Transmission Large Customers G C Supply C Supply C Source: Fig.17 and 18 see Note 2, p.102 In Europe variations in electricity cost is so wide, they cannot be accounted for purely from differences in fuel costs. Consumers are also questioning the huge stranded cost bill of the franchised monopoly37. In the bulk electricity market phase discrimination continues against the domestic and household consumers. Medium sized domestic and household consumers are also called upon to subsidise low-income consumers. Beato and Fuente (1999)38 state that: “Consumers have become aware of the implications of cross-subsidy practices. Until recently despite the fact that electricity is a top consumption item, consumers have had little say on the purchase of electricity and no price information”. If subsidy policy is to be adopted then a more transparent mechanism of cross-subsidy will need to be developed to pursue such public policy goals. The newer smaller CCGT plants, which are more mobile and can be connected into existing transmission systems, make it possible to use more substations to conduct the flow of high voltage energy from more generating plants to smaller groups of electricity users. Their easier integration 84 into the transmission network facilitates the sale of electricity between newer entrant generators and final consumers. Finally, the development of smart metering and the lowering of metering costs and communication systems also serve to facilitate the introduction of retail competition to the mass of household consumers, once considered captive to the franchised distributors. In retail markets metering by time of use is no longer a way of promoting competition. Metering becomes a commercial necessity. Each consumer needs to be metered according to settlement periods. Power prices typically change in very short time spans in competitive markets, therefore, it is necessary to know how much of each competing retailers’ supplies is used in each period in order to be able to bill the right customer and settle the right account balances. The development of smart metering has permitted the rapid expansion of retail competition to the full market. Household consumers annual consumption of electricity is however relatively small and the capital cost of acquiring smart meters may, be such that it takes a long payback period for the benefits of competition to offset the costs of acquiring meters. Distributors continue to be franchised in area markets, however, the services that they are allowed to provide is restricted to the network lines or transportation of low voltage electricity. The newly unbundled distributor, as part of the franchise rights given is required to provide open and nondiscriminatory access to facilitate the transportation of both retailers’ and consumers’ electricity. The consumer choice phase provides the final act in the separation of network services (which remain a natural monopoly) from energy services. It provides the opportunity to open both the up stream generating and the down-stream retailing segments of the market to competition. Retailers and consumers, in addition to buying from the power markets are free to also contract long term direct with generators. Hence, large supermarkets contract with generators and offer lower price retail electricity to their customers in order to strengthen supermarket patronage. In the design of retail markets, two vertical issues emerge; separation of generation from retail and separation of distribution services from retail services. The unbundling of the distribution lines business from retailing reduces the potential for self-dealing and conflicts of interest. Allowing distribution line operators to perform the retailing function also provides the opportunity for the 85 distribution businesses to cross-subsidise their retail business and to discriminate between classes of consumers. The opportunity to unbundle distribution is very high. Retailing is a merchant function and this function does not have to be provided by the owner of the distribution lines business. Distribution lines business is said to display economies of density rather than economies of scale. Large electricity distribution firms do not necessarily lead to a more efficient industry in terms of cost efficiency. Unit cost of distributing a given kilowatt hour to end users will differ, depending on structure of customers in terms of density of connection. Higher densities lead to lower costs. Other factors, which may affect costs, are topography, climate, load mix of energy and peak loading within a given area. Weak gains have been identified with increases in size, with size being considered as geographic area, network size; number of customers or of sales volume. Vertical integration of the retail and generating services in the competitive parts of the market is no longer a serious market failure issue and is therefore permissible. Because retailing, as an independent activity is a high risk and low return business, vertical integration is sometimes permitted between generating and retailing. Control of the retail market by generators, however, could affect market contestability and hamper effective competition. While welfare economics and competitive considerations call for ownership separation, in practice the level of separation permitted varies from market to market. Historical reasons may work against full separation. Consumers may resent the shift from their traditional supplier or fear increased costs. Vertical separation of retail and distribution lines business has been a very recent development, mostly taking place since 1998. Countries that have liberalised their retail markets are, Norway 1991; New Zealand, 1993-1994; England and Wales, 1990-1999; Finland, 1995-1997; Victoria- Australia, 1994-1998; Spain, scheduled for 1997 to 2007, and California 1998. In most of these countries a transition period is provided whereby sectors of the market are deregulated in phases with segmentation determined according to the size of customer demand. The defining feature of the consumer choice phase is the opportunity for all consumers; large and small to switch patronage and the opportunity for independent retailers to enter the market. 86 Competitive Transformation of the Electric Utility Industry The market failure features of the electricity industry resulted in the exclusion of electricity from competitive markets for much of the post war years. For most countries state ownership or private ownership with public regulation provided the institutional mechanisms to resolve the conflict of interests between the private and public good. The policies of shifting to private ownership and liberalisation of markets, which have emerged globally since the mid-1990s, have been resulting in new entrants to electricity markets and increased competition. For most of the industries under state ownership, it was possible to sustain competition by mere abandonment of the statutory monopolies and subjecting the newly privatised or commercialised companies to the competition legislation. In the case of the electricity industry, it was not sufficient merely to discontinue exclusive franchise rights and allow for the private delivery of electricity services. Abandonment of exclusive franchise rights had to be supplemented with vertical and horizontal dis-integration in order to facilitate the introduction of competition. Providing for and sustaining competition in the utility industry such as electricity is a complex process, beyond the capacity of traditional competition laws. The introduction of competition in the electricity industry has essentially been technology driven with the competitive pressure being exerted mainly by combined cycle gas turbine technology and smart metering. In this context competition is defined as a state where sellers are powerless to set prices either from the number of players in the market or from, the threat of entry but must respond to market forces and not merely rivalry in markets. Competition seeks to ensure the most efficient allocation of resources to satisfy a given demand. Competition is not a simple a concept, which deals with ethical values. Sioshansi and Morgan (1999)39 state that: “among the discernable features of competitive markets is that they be truly competitive, self-regulating and resulting in efficient outcomes. In reality some policing and monitoring is always necessary to make sure the participants are not resorting to illegal means to manipulate prices or influence outcomes”. The different elements of the production and supply chain display different degree of market failure. It is therefore necessary to distinguish the types of competition applicable to the different elements and the linkages between the stages in the production and supply chain and the degree of dis- 87 integration needed to maximise production efficiency. It is possible to obtain important productive efficiency gains from competition in bulk electricity market, since the greater share of costs is at this end of the production chain. As is shown earlier, competition can be introduced in the electricity industry through competing production or competing networks, from common carrier arrangements and yardstick measures, by private supply and through wholesale competition, as well as through retail or border competition40. It is however very difficult to provide for competing transmission and distribution lines business because of the high fixed sunk cost and economies of scale which is associated with transmission and to a lesser degree with distributions lines. Although it is difficult to provide for competing transmission lines it is not impossible, as there are competing transmission lines in the Nordic countries. The simplest form of competition in the electricity market is that of competition to provide incremental capacity or competition, which comes with the single purchaser, phase and which involves the competitive procurement of new generation. Competition forces the bidders to providing the minimum cost for the incremental capacity. This form of competition, (Baumol competition) or competition for the market, is distinguished from product market competition or competition in the market which is facilitated by power pools and bulk electricity exchanges. Once the contract is awarded, under a single purchaser arrangement, further competition during the life of the contract is more or less ruled out. It is possible, however, to unbundled supply costs into capacity cost and energy cost, and provide product market competition for the energy cost component by subjection of the latter component to economic merit order dispatch, in that for any demand over a given time period the lowest energy cost operator is dispatched first. In thermal plants energy cost can be a significant element, providing opportunity for major efficiency gains. Competitive tendering also requires the incumbent to test his own production costs against the market and this helps the regulator to overcome some of the information asymmetry problems. It may not be possible to move to retail competition in many developing country markets for several years. Yardstick competition, however, provides a mechanism for the reduction of market 88 power. Yardstick competition can be promoted by three methods. First, the price a firm may charge can be based on the cost of a typical set of firms in the industry or a notional model firm. Secondly, benchmarking of companies against one another to estimate efficiency is possible. Benchmarking allows for the establishment of price caps, based on the cost structure of the model or typical set of firms. Adopting sophisticated statistical techniques, which also take into account differences in the companies operating environment, may also be used to set indicators. Thirdly, competition can be facilitated by information disclosure requirements, which mandate public presentation of the firm’s cost and performance data so that consumers are presented with market information to make comparison. Unbundling and information disclosure provide the opportunity for consumers to compare each locational monopolist’s costs. In Europe variations in electricity cost is so wide, they cannot be accounted for purely from differences in fuel costs. Consumers are also questioning the huge stranded cost bill of the franchised monopoly40. . The final form of competition is financial and capital market competition. Once the electricity enterprise is privatised, sets of owners and managers can compete to take over the assets and licences of the incumbent electric utility. Capital market pressure can play a significant role in enforcing efficiency, provided this is not frustrated by pre-emptive rights clauses or some arbitrary limit on share ownership. Beesley and Littlechild (1997) contend that capital market competition is a powerful efficiency driving feature41. The introduction of competition to the electricity industry requires a transitional period of managed competition or a competitive transformation period. Paradoxically, liberalisation of the network market often results in increased regulatory intervention to secure competitive outcomes. Sidak and Spulber (1997)42 state that: “Regulators are concerned with achieving competition “fairly”, yet markets are known for their efficiency properties, rather than the equity of their outcome”. It is therefore, important that regulators use an operational definition of fairness that does not attempt to specify outcomes. In the competitive transitional phase, regulators should ensure that incumbent burdens are dismantled or shared evenly across market participants as in the case of meeting universal service obligation. 89 It is important to identify non-commercial obligations and unbundled these from the commercial business. The incumbent and the new entrants may then be required to compete to supply the noncommercial services and the cost shared across all entrants. Secondly, regulators should not seek to pick winners in terms of technology, services or market institutions. Such a situation arises for example when the regulator specifies the type of technology, which should be used to meet customer demand. Regulators should refrain from market intervention that favours particular competitors and should dismantle regulation if a demonstrably competitive alternative exists. Liberalisation of electricity markets also creates the problem of a dichotomous regulatory environment during the market transformation phase, with the industry specific regulator being called upon to monitor the natural monopoly elements and the competition agency to monitor contestable elements. With the integrated electricity monopoly structure, there was no opportunity to engage in anti-competitive conduct. There was also no one to enter into agreements, which could be restrictive, or to behave in a manner that would lessen competition in the market for the relevant services. When the potentially contestable element is opened up to competition, the question of access to the network requires regulation to ensure the incumbent refrains from acting in a manner that would be disadvantageous to rivals in the competitive sector or to exercise market power. Ordinary competition rules are often insufficient to control market dominance in network industries with the result that increasingly since the mid 1980s the electricity industry regulators have also been given specific mandate to enforce competition rules. This new environment creates the potential for jurisdictional conflicts as the utility industry regulatory rules may conflict with the rules of the competition agency. Additionally, the rules of the competition agency may be so wide that it allows the competition regulator to challenge price fixing decisions of the utility regulator. There is also opportunity for conflicts of rules between the two regulators in respect of merger control matters. Unless the responsibilities between the two agencies are clearly defined and the boundaries delineated, it will then be left to the courts to interpret the language of the respective legislation and this could be long drawn out and expensive43. There is therefore the need also to provide for exemptions or establish legislative rules, which provide for primacy of one of the legislative instruments in a given situation. An alternative solution is to grant concurrent powers to both agencies. Concurrency, however, may create duplication without resolving the problem, as is the case where competition authority and the sectoral regulators take a 90 different position on a given matter. This problem has developed in the UK with the introduction of the 1998 Competition Act, which has provided for concurrency. With the introduction of competition and the application of competition law it may be argued that the electricity industry regulator is rendered unnecessary as the institutional instrument to remedying abuse of market power. The notion of electric utility industry regulation has traditionally been based on the premise that there is absence of competition. The question has therefore emerged as to whether general competition law should replace economic regulation. Prosser44 has, however, argued that it is not possible during the market transformation stage to do without industry specific regulatory rules and leave matters to the market and ordinary competition law, as even in the New Zealand situation where competition law is used, the threat of regulation and the right of the minister to fix prices remains. The opportunity to create competition in the electricity market is now substantial. The global situation is such that there is an uprising of competition, even in small electricity markets. Competition ensures that there is rivalry to meet consumers need, resulting in lower prices, better quality, wider variety of products, and more optimal investments. Resources are also used more productively. It is not so much perfect competition, which is important, but the threat of competition or the threat of regulation. 91 Fig. 19 Four-Phase Electricity Industry Restructuring Models Increased Private Ownership Distribution as a common carrier Open Access Transmission Common Carrier Open Access Increased Level of Unbundling Unbundling (vertically & Holizontally) Liberalisation Single Integrated utility (State or Private) Model 1 Monopoly (Partial Cost Pool) FRANCE Model 2 -Generation in Entry Competition -Power Purchase Agreements -Single Buyer JAMAICA IRELAND Model 3 -Wholesale Competition -Bulk Power Exchange -Spot Price -Futures Model 4 -Retail Competition -Large User Contract UK ARGENTINA VICTORIA, AUSTRALIA BOLIVIA Source: Note 2, p. 102 The process of competitive transformation in further illustrated by Fig. 19 above, which shows that as the industry moves from one phase to the next, there is increased competition, and increased levels of vertical and horizontal unbundling. 92 Increased levels of unbundling provides for a higher degree of private sector participation and ownership. While private ownership introduces incentives for higher levels of efficiencies and the discipline of hard budgets, it is competition facilitated by new technology, which delivers lower prices to consumers, and greater operating efficiencies. While ownership and a competitive environment are important for an efficient electricity market, ownership and a competitive environment per se are not enough. A competitive framework must be supported by rules to prohibit or restrict anti-competitive behaviour, and to guard against firms reintegrating to benefit from monopoly power. Competition addresses the three major causes of poor public enterprise performance. It removes shelter provided by monopoly, more importantly it minimises political interferences that distort the objective operation of the company and it resolves the property rights issue. Competition in those sectors of the industry, that no longer carries natural monopoly characteristics, also minimises regulatory oversight and regulatory costs and reduces the incidence of regulatory capture. The general picture which has emerged over the last 10 years has been one in which the industry structure adopted has followed a move away from the traditional Franchise Monopoly Phase. There have been three distinct structures: Purchasing Agent; Bulk Electricity Market and that of Retail Competition. There appears to be no requirement that an industry has to progressively move from one stage to the next. Some countries have opted for radical restructuring and have moved directly to the bulk electricity market. In other situations gradualist approaches have been preferred. The competitive transformation of the electricity industry and the stage that a country adopts at the point of reform are not only dependent on technological factors, competitive transformation depends also on political constraints and the extent to which efficient regulatory regimes can be structured and applied. In developing countries competitive transformation is restricted by crosssubsidisation, an unstable market environment and an inappropriate regulatory regime. Foreign investors will be reluctant to invest in markets, which are perceived to carry high risks and will demand long-term power purchase agreements in order to compensate for the high risks. In developed markets competitive transformation is restricted more by stranded cost. 93 Technological factors therefore, set the boundaries as to how far competition can be taken in any given country; however, it is political factors such as stranded cost, cross-subsidisation, an unstable market environment and the regulatory regime, which will determine the pace of market transformation in an individual country. Selection of Case Countries A number of countries that have reformed and privatised their electricity markets since 1990 will be illustrated as case countries to see to what extent these countries conform to the four phase model and development process outlined above. The cases are, the England and Wales and the rest of the UK reforms which commenced in 1989; the Jamaican reforms which commenced in 1990; the Bolivian reforms which were carried out after 1995, and Sub-Saharan Africa, inclusive of three selected countries, (Ghana, Cote d’Ivoire and Tanzania) that have since 1996 introduced policies to provide for significantly increased levels of competition in their electricity markets. The UK has been selected as it is in first case of radical reforms, involving the separation of generation from transmission and introduction of statutory requirement on the regulator to encourage competition in the sector. Jamaica’s relevance is that the policy makers came to the conclusion that radical restructuring involving horizontal and vertical disintegration was more a policy option for large electricity markets, and because of this view Jamaica proceeded to privatise the monopoly electric utility as a vertically and horizontally integrated company in 2001. Bolivia with a less developed economy and with an electricity market similar to the size of Jamaica (under 650 MW) rejected the market size constraint and introduced radical disintegration and full privatisation of the sector. The three African countries have all tried various degrees of reforms within the framework of state ownership and a franchise monopoly structure and have found that the improvements are not sustainable and have decided to radically reform their small electricity markets, (mostly under 1000 MW) into a disaggregated and competitive structures. There is, therefore, the question as to whether the Bolivian reforms offer a template or road map for these countries. 94 End Notes 1. Yin, R.K (1981b). The Case Study as a Serious Research Strategy, Knowledge: Creation. Diffusion, Utilization, vol.3, 97-114 2. Figures 3 to 19 present illustrations developed by the author to portray the various industry and market structures. Several writers have provided illustrations of these changing industry structures, however, the trend has been to focus on the traditional organisational relationships. A new dimension is that in the three new phases of development, illustrations are also provided of the electricity and financial flows. For organisation illustrations see Hunt and Shuttleworth, op.cit., Chapter 3-7, and Carole Hicks, Regulation of UK Electricity Industry, Centre for Study of Regulated Industries, London (1998). 3. Once the cost of service and the capital for the test year is determined a rate of return is established. The cost of service and the calculated returns then form the tariff for the next period. A criticism of this formula is that it is a cost plus approach, inflationary, and does not provide incentives for the utility to be efficient. It worked reasonably well in periods of low inflation. 4. In some countries the rate of return is fixed in the contract. Benchmark rates are sometimes established. The utility is allowed levels of profits, which falls within the benchmark as adopted in Jamaica. 5. Harvey Averch and Leyland L. Johnson, “Behaviour of The Firm under Regulatory Constraint”, American Economic Review, Vol. 52 (December 1962), pp.1052-1069. Averch and Johnson state that the rate of return formula as applied by US utility regulators leads to the employment of more capital (gold plating) than would be optimal. The rate of return constraint gives the firm an incentive to employ more capital than is normally needed. 6. The EU directive states that from 1999-2003 the share of the electricity market open to competition shall grow from 25% to 33% and by 2003 must apply to all end users above 9 GWh per year. The directive also calls for transparent and non-discriminatory access to EdF’s transmission system. 7. Nocolas Curien and Claude Henry, “Liberalisation and Regulation of Public Service in France”, in Regulatory Review 1998/99, ed., Peter Vass, Bath, England, Centre for the Study of Regulated Industries (1998), p.125. 8. Mohan Munasinghe and Arun Sanghvi, Recent Developments in US Power Sector and Their Relevance for the Developing Countries, Washington D.C., World Bank (1989), p.3. 9. Ibid; p.7. 10. John Wippen, Private Power Experience in the US, Washington, D.C., J. Makowski Associates, unpublished (1991), p.3. A total of 21500 MW (or 33%) of total additional power capacity, which came on stream between 1985-1990, were PURPA capacity. 95 11. Leboeuf, Lamb, Greene and MacRae, Competition, Structural Change and Regulatory Reform in the US Electricity Industry, London, Centre for the Study of Regulated Industries (1994), p.22. 12. David M. Newbery, Issues and Options for Restructuring the ESI, Washington, D.C., World Bank (June 1999), p.5. 13. David M. Newbery and Richard Greene, “Regulating, Public Ownership and Privatisation of English Electricity Industry,” in International Comparisons of Electricity Regulation, ed., Richard Gilbert and Edward P. Kahn, Cambridge University Press (1996), pp.25-81. 14. David A. Cordukes, A Review of Regulation of the Power Sectors in Developing Countries, Washington, D.C., World Bank. Working Paper Energy Series, 22 (1990), p.13. Cordukes found that the predominant organisational form in 22 developing countries in 1990 to be that of the publicly owned and controlled corporation. Many of these were nationalised after independence and were permitted to operate as monopolies. In most Sub-Saharan African countries the single public corporation operates the vertically integrated system. 15. British Treasury, The Financial and Economic Obligation of Nationalised Industries, London, HMSO, (1961), Nationalised Industries: A Review of Economic and Financial Objectives, London, HMSO, (1967); and Nationalised Industries, London, HMSO (1978). The 1961 White Paper broke with the Morrissonian model of nationalised industries being run on commercial lines only to break even one year after the other. The paper put forward an economic framework with financial targets with pricing policies to meet these targets. The 1967 Paper increased the economic controls, setting out detailed pricing and investment policies requiring prices to be set at long run marginal cost and investment policies, to be evaluated in terms of test rates and net present values. Prices were to be subjected to review by the Prices and Income Board. The 1978 Paper completed the shift to full commercialisation. Financial targets became the primary instrument of control. A rate of return was to be earned on capital. The National Economic Development Report Office reported in 1976, that the economic and financial regulatory framework that had been developed had failed, blatant political manipulation and intervention was still to be found and that the industries were being used to promote macroeconomic policies. The Morrissonian ideal of “arms length” public corporations managed independently proved unworkable and detailed direct regulation after the 1970s also failed. 16. John E. Besant-Jones, The England and Wales Electricity Model: Option for Developing Countries, Washington, D.C., World Bank Notes (1995), p.2, 17. Kenneth W. Costello and Kenneth Rose, “Some Fundamental Questions and Market Power: No Easy Answers for State Utility Regulators”, Electricity Journal, (July 1998), p.75. 18. Gardiner Maine and Montpelier Vermont, Best Practices Guide: Implementing Power Sector Reform, Washington, D.C., USAID/Institute of International Education, Regulatory Assistance Project Report (2000), p.12. 96 19. World Bank and USAID, Submission and Evaluation of Proposal for Private Power Generation Projects in Developing Countries, Washington, D.C., Occasional Paper No.2 (April 1994), p.22. IPP project involves the formation of a private company or joint venture, to plan and finance the business on a non-recourse basis, design contracts and operate the power plant. Lenders look to the projects cash flow for repayment of the principal and interest and returns on investment and to the assets as collateral in the event of default. The new company typically does not have any other assets or credit standing. The right to use project cash flows to meet debt service is normally structured in the PPA. 20. Several variations of IPPs have emerged. Initially IPPs were of the PURPA type where the investor owned utility was forced to buy power from IPPs at the utilities avoided cost. The IPP framework was then exported to South East Asia as Build-Own-Transfer (BOT) involving competitively bid tariff, followed by the “tolling IPP”, with a supply driven PPA in which the tolling agreement is with the fuel supplier. The supplier makes the decision when to sell gas, generate electricity or do nothing at all. This supplier pays a capacity fee to the plant and receives a power price netback from the plant. An example is Enron Sutten Bridge Plant in the UK. A fourth version is “hedged IPP”, here the plant sells into the grid and receives the spot price which varies half-hourly, (based on systems marginal price), however, the IPP enters into a financial agreement, contract of difference (CFD) as in the UK with the purchaser, whereby both agree to share the price risks. An alternative is to link the fuel price with the electricity spot market price as in the case of the AES Barry and Enfield plants in England. Hedged IPPs tend to be for short period, 4 to 5 years compared to “BOT IPPs” for 15 years. Additionally variations may involve still a further shifting of risks away from the purchaser to the equity or debt holders or both. “Merchant IPP” is at the end of this risk profile. In a pure Merchant IPP, there are no purchase contracts. Because of the associated risks project financing is difficult. This is so because of the highly leveraged nature of the transaction selling into a commodity market. 21. Gardiner and Maine, op.cit., p.13. 22. John E. Besant-Jones and Bernard Tenenbaum, California Power Crisis: Lessons For Developing Countries, Washington, D.C., ESMAP (2000), p. 14. 23. Elliot Roseman and Anil Molhatra, “Dynamics of Independent Power – IPPs Seed-to-Bottom Reform”, in Private Sector Special Edition, Washington, D.C., World Bank (1996), p.37. 24. World Bank/USAID, op. cit., p.79, provides an illustration on Virginia Power’s private power procurement contract with the use of bids involving capacity and energy charges as early as 1988. 25. Newbery, op.cit., p.12. 26. World Bank, Energy After the Financial Crisis, Washington, D.C. (1999), p.20. 27. Newbery, op.cit., p.13. 97 28. William W. Hogan, “A Wholesale Spot Market Must be Administered by an Independent System Operator, Avoiding the Separation Fallacy”, Electricity Journal, (June 1994) p.36. 29. Industry Commission, Energy Generation and Distribution, Vol. 11. Report, Canberra, Australia (May 1991), p.116. Australia contends that market operation and the dispatch functions go well together because of the benefit of sharing information. Australian policy makers also contend that the skills required for market operations are different from those required from transmission operations. 30. South Africa’s Eskom has advanced the idea of a bulk electricity market with horizontally disintegrated state owned enterprises. This is still inappropriate as in this arrangement the state owned firms would not be subject to financial market competition. The problems of public control and the opportunity for political interventions also are not resolved. New Zealand tried this approach and had to abandon it after five years as the experience was that competition was inhibited. 31. Newbery, op.cit., p.20. 32. Vesting contracts for example were provided in the Northern Ireland restructuring in 1992. see Brian Lunn, Northern Ireland Electricity Markets, unpublished (2000). 33. Besant-Jones and Tenenbaum, op.cit., p.12. 34. Daniel Spulber, Regulation and Markets, Cambridge, Mass. MIT Press (1989), p.371. 35. Guy L.F. Holburn and Pablo Spiller, Institutional or Structural: Sequencing Strategies for Reforming the Electricity Industry, Berkeley: University of California, Walter Hass School of Business (November 2000), p. 13. 36. James Barker, Bernard Tenenbaum and Fiona Woolf, Governance and Regulation of Power Pool and System Operation: An International Comparison, Washington, D.C., World Bank Technical Paper, No. 382 (1997). 37. Office of Gas and Electricity Market, The New Electricity Trading Arrangements, London, OFGEM (1999), P.43. 38. Paulina Beato and Carmen Fuente, Retail Competition in Electricity, Washington, D.C., Inter-American Development Bank (1999), p.3. 39. Ibid., p.4. 40. Fereidoon Sioshansi and Cheryl Morgan, “Where Function Follows Form: International Comparisons of Restructured Electricity Markets”, Electricity Journal (April 1999), p.26. 41. Border competition is also possible where retailers bordering supply zones are allowed to cross the border and supply to customers in the incumbents franchised supply zone. 98 42. Michael E. Beesley and Stephen, C. Littlechild, “Privatisation, Principles, Problems and Practices”, In Privatisation, Regulation and Deregulation, ed., M.E. Beesley, London, Institute of Economic Affairs, Routledge (1997), p.28. 43. J. Gregory Sidak and Daniel Spulber, “Deregulation and Managed Competition in Network Industries”, Yale Journal of Regulation, Vol. 15. No. 1 (Winter 1999), p .118. 44. OECD “Relationship Between Competition and Regulatory Authority”, Journal of Competition Law and Policy, Vol. 1, No. 6 (1999), p.196. 45. Tony Prosser, Law and the Regulators, Oxford: Clarendon Press, p.270. 99 Chapter 3 A Formula For Radical Reform: The British Industry Structure Introduction The restructuring, privatisation and regulation of the UK system, especially England and Wales (E&W) in the first half of the 1990s followed a radically new path. It was the first of the UK public utilities to involve significant major restructuring in order to promote competition in those sectors, which from an economic point of view were no longer characterised with natural monopoly features. British electricity reform has been instructive from the point of view of five major innovative approaches. Some of these approaches, although credited to the British were not novel concepts. Millan (2001)1 noted that although the English claimed that their competitive system was the first in the world, the Chilean model had been in effect for over a decade when the England and Wales system was established. The concept of promoting competition in a utility industry as against the tradition established by United States of maintaining the utility as an integrated monopoly was not a UK innovation. Britain merely built on the approach, and for the first time made the promotion of competition a statutory duty of the regulator. The second and most radical change introduced in the E&W system was that of vertical separation of generation from transmission and providing for ownership and operation of the transmission network to be carried out by an entity that is separate from the owners of the generators and distributors2. In the traditional US utilities, regulation for the most part, suppressed competition. With the new approach, the industry was to be vertically separated into the four elements of the 100 production and distribution chain; generation, transmission, distribution and supply. Supply competition, however, was to be phased over a period of 8 years. Generation and supply at the start of the reform combined to account for 70% of industry costs. Both these sectors were to be the subject of horizontal unbundling so as to accommodate competition. This reflected a clear departure from the US model of the vertically and horizontally integrated private investor owned electricity utility, which up to the 1990s was the dominant industry structure for privately owned electricity utilities. Third, the UK policymakers at the time of privatisation rejected the US rate of return, rate base, cost of service system of economic regulation and instead adopted the concept of incentive regulation or price base regulation for franchised services through caps on average revenue, based on the thinking of the Austrian School of Economists3. The underlying thesis of the Austrian School was that utility industries do not have to be operated as monopolies. Pure cases of long term natural monopoly were considered to be of the rarest occurrence. Utility monopolies persist only if they are buttressed by public authority. The new style UK regulation challenged the notion that utility industries have to be operated as monopolies, and explicitly sought to encourage new entry and competition, where competition was possible thereby seeking to minimise the disadvantages identified by Hayek and Friedman with regulated monopolies. The real challenge was to maximise the scope for competition. The new UK approach focused on price rather than profit, as had been the case with US style regulation up to 1990, hence the “RPI-X” formula. This new approach provided for the monopoly operated utility to raise prices for its services, by the economy-wide rate of inflation, adjusted for an efficiency factor. The formula incorporated the UK retail price index (RPI) and an incentive term called “X” factor, with the expectation that “X” would be a positive number and that the cost of the utility service would therefore fall in real terms to the consumer. This approach was expected to remove the need for technical judgment on the part of the regulator to provide strong incentives to the utility to reduce cost, as it was expected to share in the benefits of the efficiency improvements without the fear of profit “claw back”, inherent in the US system of annual rate hearings. As the reviews would be over a longer time period, a more predictable environment would be provided, when compared to annual rate reviews carried out in US systems. 101 Fourth, the UK electricity reform provides experiences of more than one approach to restructuring, in that there are three separate systems: E&W, Scottish and Northern Ireland and each system was subjected to different levels of unbundling and different degrees of competition were introduced. Unbundling raises an important question. Does the disintegrated or unbundled structure always minimise electricity supply costs or whether disintegration results in increased transaction costs and loss of economies of scope and scale, which eventually outweighs the competitive gains of disintegration? The different approaches pursued in the UK to some extent provide an empirical answer to this question. Fifth, a new price base market mechanism, an electricity wholesale power market replaced the informal load-scheduling mechanism based on merit ordering of power plants by marginal operating cost that the incumbent state owned utility previously used. The new system; essentially a power pool was the main innovative market mechanism introduced to facilitate competition in the generation sector. The wholesale power pool, which is virtually a spot market for bulk power, introduced the commodity exchange market concept to bulk electricity supply4. Generators are paid the pool purchase price for electricity supplied into the pool, whilst traders and large users pay a pool-selling price for electricity taken from it. The pool serves to provide for the close coordination needed between generation and transmission, which previously was facilitated by vertical integration. Coordination by contracts alone would have ended up approximating the integrated structure that had been rejected. Pools previously existed in the US; however, they operated at the margin, mainly facilitating exchange of surplus power between investor owned utilities. There was no empirical evidence then that the separation of transmission from generation being associated with effective competitive markets. Yarrow (19895 also questioned whether such separation would more likely create efficient and competitive solutions. Yarrow further argued that generation and transmission were naturally monopolistic or at least naturally duopolistic and that there were still strong vertical economies between the two segments, and it is these features, which historically had kept the electricity industry out of competitive markets. Primeaux (1989)6 had, however, in a 1960 study indicated that there was empirical evidence to the existence of competition in electric supply in a number of cities in the United States. Primeaux claimed that cost data collected from these cities with two or more competing electricity supply 102 companies , failed to support the widely held natural monopoly theory of electric utility. In fact cities with competing firms were found to present lower cost. Although Chile had sought to introduce a competitive market before the British, transmission was not operationally separated from the main generator at the time of creating the first electricity market. Littlechild (1999)7 further stated that apart from not knowing at the time of the existence of the Chilean experiment, it would not have helped politically, with the reputation of the Allende dictatorship administration. Although the UK reforms appear to have been extremely radical, in practice they were less so. The UK policy makers faced a series of conflicting objectives. On the one hand, there was the desire to create an economically optimal structure and not to repeat the monopolistic structures of the earlier telephone and gas industry privatisations. On the other hand, there was the need to balance this against a number of political objectives, such as to protect nuclear power and to offer financially attractive companies to the financial market. Additionally, there was also the overriding objective of the Conservative administration to secure a successful flotation within a tight time frame, influenced mainly by electoral consideration. There were two other objectives of the Conservative administration. First there was the desire to break the stranglehold on power of the trade unions, which historically were able to exert tremendous political power in industries like electricity and coal, which were not subject to competition. Second there was the desire to create a share-owning democracy that would markedly reverse socialism and state ownership. Despite the unbundling of generation, essentially a duopoly was created. Further, no restructuring of the distribution and supply market was undertaken as the incumbent twelve distributing Area Boards were retained with most of their monopoly privileges. Government’s competition policy initially concentrated on new entrants to the generation market and in the case of the supply market, on second tier suppliers. The natural monopoly transmission system, although vertically separated out from generation was partially re-integrated with the distribution sector, as the twelve incumbent distributors became joint equity owners of the new transmission company. The supply of electricity from the Scottish companies and French EdF to the generation market was permitted as a part of 103 the wider industry liberalisation policy and was expected to provide added competition for the bulk electricity market; however, the Scottish system was allowed to remain with its vertically integrated structure. 1980s Political and Economic Thinking on Electricity Privatisation In order to obtain a better understanding as to the final shape of the industry, which emerged, it is important to revisit the political and economic circumstances, which surrounded the industry in the period to 1990. This is important from the perspective of developing countries seeking to fashion their restructuring programmes based on the UK model. At the time of privatisation the system was plagued with over-capacity and economic motivation for reform was driven primarily by the desire to reduce cost. For most developing countries, with levels of electricity penetration of under 20% and especially in Sub-Saharan Africa where penetration levels are under 10%, the overriding driving force will of necessity have to be that of rapid expansion of penetration. The thinking as to what was then possible, significantly affected the policy options contemplated and it would be incorrect in hindsight to be extra critical based upon today’s knowledge or technological developments, which were perfected after the 1980s. At the time the privatisation debate came up in Parliament, Tony Blair, then Opposition Spokesman on energy was critical of Michael Heseltine, then Energy Minister, and not only pledged to reinstate electricity as a public service on a Labour administration return to power, he also claimed that privatisation would not only lead to increased prices but that, the case presented that privatisation would give consumers choice at the point of consumption had not been substantiated. Heseltine responded by stating that the only way to give consumer choice at the point of consumption was to run two cables in every home.8 How to provide competition in the small consumers’ market, without the uneconomic provision of multiple lines on each street and into each home was yet to be resolved. There was a strong view that unbundling and privatising of electricity could not be done and the exercise was one of political fantasy. Vertical unbundling of electricity and creation of competition in retail supply was not only a novel economic concept, in contrast to generation; there was 104 profound scepticism as to its practical outcome in retail supply. It was felt that only very large customers such as the British industrial firm, ICI would want to buy electricity direct from generators. Unbundling of the Central Electricity Generation Board (CEGB) was strongly resisted by the chairman and management of the company. Their argument was that a vertically and horizontally integrated generation and transmission company was needed to ensure adequate supply capacity and security of supply and that reform following the single buyer arrangement in which CEGB contracted with independent power producers for additional capacity at regulated charges would have been sufficient in terms of the changes that were needed. This, however, was not seen by the policy makers to meet the requirements for a competitive electricity market. A variation of the single buyer model was also advanced. This variation called for the regional distributing companies to be permitted to enter into long-term contracts with individual stations and to pay a capacity charge to cover fixed costs and an energy charge to cover the avoidable cost of generation. The suggestion was also rejected on the grounds that the creation of a market with these individual contracts with their two part tariffs would be far too complex. Although the electricity privatisation was pledged in the 1987 Conservative Election Manifesto, no details had been provided. The first blue print came in the February 1988 Government White Paper on Electricity Privatisation9 which intimated that the existing twelve distribution companies in E&W were to be incorporated as limited liability companies and sold intact and that the Central Electricity Generating Board, the generation and transmission enterprise, was to be disintegrated into three companies. The desire to protect nuclear electricity seemed to be the main rationale for such a duopoly structure in the generation market. In order to accommodate the nuclear power plants the privatisation programme provided for the creation of two generating companies (more or less the initial uncompetitive structure adopted in New Zealand and Chile); National Power and PowerGen. National Power was to own all the nuclear plants, in addition to approximately one half share of the fossil fuel plants. PowerGen was to absorb the remaining fossil fuel plants. A Power Pool was advanced as the main price setting mechanism for bulk electricity, supported by contracts of limited term outside the Pool. The Pool was to involve a “double sided” pool structure. Additionally, the 105 high voltage transmission and grid system was to be hived off and operated as an independent company. Government soon discovered that the financial market was sceptical of the proposed arrangements. The massive liabilities for spent fuel disposal and decommissioning, as well as the short remaining operating life of the Magnox nuclear plants presented unacceptable commercial risks, with the result that these had to be withdrawn from the privatisation programme in July 1989. The high rate of return required by private finance for the advanced gas-cooled reactors (AGR), also made these nuclear plants uncompetitive. Nuclear generation was a practical proposition so long as it was publicly subsidised. The policy was therefore, amended to provide for the privatisation of National Power without the nuclear plants. A new enterprise, Nuclear Electric, was to be created to own the nuclear plants and to continue operation as a state owned enterprise. With a political commitment to nuclear electricity, government found a face saving solution by imposing a 10% fuel levy on all electricity sales and this was to provide 40% to 50% of Nuclear Electric annual revenues in the initial years. The result of the commitment to nuclear was that these plants were mandated “must run plants”. The nuclear sector was to be excluded from bidding into the Power Pool. Fortunately, the European Commission imposed a requirement for the fuel levy to be phased out by 1998. British consumers, however, were required to shoulder the stranded costs of the nuclear assets during the early years following privatisation. In the autumn of 1989 the double sided pool structure which was to involve both generators and power purchasers bidding into the exchange also had to be abandoned in favour of a “single sided” pool structure involving bids only from generators. It was discovered late in 1989 that the complex computer software needed for a double sided pool could not be completed in time for vesting day, March 1990 when the Pool was to come into operation. This development led to removal of the requirement for purchasers placing bids into the Pool at the prices at which they were prepared to buy and made the price mechanism a market clearing system for generated electricity. The basic principle of a market-clearing price is that there are sufficient independent bidders in the Pool so that the chance of anyone firm influencing the price is negligible. The assumption in this particular instance was that Bertrand duopolies would deliver such competition. 106 Writing just prior to the publishing of the Government White Paper, Vickers and Yarrow (1988)10 identified four restructuring options as being available to the policy makers; continued vertical integration of the Central Electricity Generating Board )11, unbundling CEGB into a number of regionally integrated generation and transmission companies, vertical separation of transmission and generation and horizontal unbundling into several generators, vertical reintegration of distribution with generation and transmission and separation into a number of fully vertically integrated regional companies. Since the twelve Area Boards, the regional distributors were already vertically separated; reintegration was more or less ruled out. Vickers and Yarrow did not see privatisation of the distribution as sufficient condition for competition. The advantage of privatisation of the distribution companies is that they would be less likely to collude with the generators, and there would be more incentive to shop around for lower cost sources of bulk electricity supply. What was seen to be more important was the regulatory structure, which was to be put into place for the distribution companies following privatisation. Despite emphasising the importance of regulation to secure efficiency enhancing outcomes, the US style rate of return regulation was also advanced by Vickers and Yarrow as the method of price regulation for the distribution companies, as against the incentive price-cap regulation earlier introduced for telecommunications, on the grounds that the general public interest guidelines introduced in the periodic rate reviews would be a potential source of investor uncertainty, with the potential for under-investment in the distribution sector. Continuation of the vertically integrated CEGB, as well as creation of regional monopolies, either as vertically integrated transmission and generation firms or as fully vertically integrated generation, transmission and distribution companies all presented serious market power problems as well as problems of non-discriminatory access and barriers to entry that would have required heavy handed regulation. Vickers and Yarrow came down in favour of vertical separation of generation from transmission and several horizontally separated generators. The number of generation companies, however, was not seen to be critical as long as free entry was possible, as the market would provide its own correction. However, in the case of transmission Vickers and Yarrow concluded that:12: “We believe that, if a separate transmission firm is to be established, there is a strong case for independent ownership (possibly public) and control of the resulting entity. The independence of this firm from the generation and distribution companies 107 would assist the development of a more competitive market in bulk electricity and public ownership might be the best way of dealing with the considerable market power that the firm would possess -----Again we would warn against excessive reliance on structural remedies alone. Whatever structural option is chosen, it is likely to be the conduct of regulatory policy that will have the most significant effect on industrial performance. With the exclusion of the eight older Magnox nuclear plants Henney (1987)13 argued for four or five privatised generation firms. Statistical studies of US generation system also seem to have supported the case that ten viable generating companies could have been created from CEGB14. Veljanovski (1980)15 also called for horizontal unbundling into several competing generators and felt that the CEGB’s 38 fossil-fuel power stations (all the generation sets in excess of 100 MW) presented an opportunity to create eight unbundled companies, with average capacity of 6000 MW, which was seen to have been large enough to maintain scale economies in operation. The smaller Scottish system of 10000 MW capacity and 5600 MW peak demand, including 800 MW of exports to England and Wales in 1990, presented very different problems. The South of Scotland Electricity Board (SSEB) was 50% nuclear and North Scotland Hydro-Electric Board (NSHEB) was mostly hydroelectric. The different plant mix and the several routes with low densities in terms of end user connection called for a different solution. The substantial excess capacity also presented very little opportunity for new entrants; hence the case for radical restructuring of the Scottish system at the beginning of the 1990s was then seen to be weak. The considered options were to leave the integrated structure or to separate the industry into one generation and Transmission Company and several distribution companies. Either option, however, was seen to create the need for heavy-handed regulation. Northern Ireland, the much smaller system of less than 2000 MW capacity and 1500 MW peak demand and with a thin route distribution structure was seen to present limited options, much the same as in Scotland. When economies of scale consideration are taken into account major structural reforms of the Scottish and Northern Ireland systems, were ruled out by the policy makers and the analysts. 108 The Pre-privatisation Structure Public electricity supply in the UK goes back to 1881, when a private firm, Siemens began operation of a small hydroelectric generating plant in Godalming, Surrey. Between 1881 and the entry of state ownership in the 1940s the system was based around a structure of small scale, local, private or municipal undertakings, each operating in a particular area. Private firms were more common in the distribution sector. The Weir Committee Report16 of 1925 identified six hundred separate electricity supply undertakings, operating from four hundred generating plants. A 1919 Electricity Act served for the first time to introduce regulatory oversight through an Electricity Commission. State intervention came at the national level with the Electricity (Supply) Act of 1921, which mandated the establishment of a Central Electricity Board to construct and operate a national system of interconnected generation plants. As a result of this Act the state came to dominate the generation market; however, in the inter-war years the private sector continued to play an important operational role in the distribution sector. The Electricity Act of 1947 brought about full nationalisation of the electricity supply system. This Act mandated the establishment of the British Electricity Authority (BEA) in England and Wales and Southern Scotland to own and operate generation plants and to supply bulk electricity. BEA operated 12900 MW of capacity through 297 power stations in 1947. At the time of nationalisation there were 569 distribution undertakings, with two thirds connected to the national grid. These undertakings were later consolidated into 14 Area Boards and constituted as statutory bodies, responsible for distribution and supply in exclusive or franchise zones. Twelve of the boards covered franchise areas in England and Wales and two in Southern Scotland. In 1943, the North Scotland Hydro-Electric Board was established to promote both public electricity and economic development, followed by the establishment of the South of Scotland Electricity Board in 1955. The two Scottish Boards came to operate as vertically and horizontally integrated generation, transmission and distribution enterprises. In Northern Ireland a vertically integrated generation, transmission and distribution public enterprise; Northern Ireland Electricity (NIE) was established in 1972 and in 1975 a 300 MW interconnector linked the Northern Ireland system with the Republic of Ireland. 109 In England and Wales, the 1957 amendment of the Electricity Act further mandated clear separation of generation and bulk electricity supply functions from the distribution and retail supply activities. The Act provided for the creation of the Central Electricity Generating Board (CEGB) with its responsibilities restricted to power generation, national grid operation and construction. At the same time the Area Boards were restricted to distribution and retail supply. The amendment also provided for Electricity Council, with a supervisory role over the entire industry. The earlier British Electricity Authority operated as a highly centralised system, especially over industry policy and the finances of the Area Boards. Earlier, the 1954 Electricity Reorganisation (Scotland) Act had reduced the Area Boards to twelve and provided for the two Scottish Area Boards to be restructured into the two vertically integrated utilities. The system was supplemented by self-generators and by small imports from the state owned Electricite de France (EdF) and this system remained intact up to 1990. The CEGB they provided 95% of the power needs, with the small self-generators and EdF the rest. After 1957 the Area Boards were given the right to enter the generation market. However, few did so and only at the level of small-scale operation. By the late 1960s a number of problems, which worked against efficient operation of the system, began to be identified. The industry was not seen to be commercially driven and did not regard itself as having customers. Its monopoly power in product market translated into disproportionate bargaining power of the unions, allowing workers to extract wage rate increases greater than their annual increases in productivity. As the industry did not operate in a competitive market and did not face takeover threats, there was very little incentive to stimulate efficiency enhancing behaviour. The politicising of the industry’s decision-making resulted in uncertainty as to whether commercial objectives should take priority over political and public service objectives. Investment and pricing decisions came to be influenced excessively by short-term considerations. Added to this the government operated an industrial policy over the years which involved electricity providing massive cross-subsidies to prop up the coal and nuclear industries. Electricity was required to take all the supply of coal produced, regardless of the economics of other fuel sources. 110 A succession of Government White Papers in 1961, 1967 and 1978 on the nationalised industries, as commented on by Heald (1980)17 and which dealt with financial targets and the relationships of the enterprises with government did not bring any lasting solutions. The new price targets called for rates of return on averaged capital employed of 2.7% pre-tax (real) and 5% on new investment. In the 1980s, restrictive cash budgets were introduced with the requirements for the industry to reduce controllable unit costs per kWh by factors varying from 4.25% to 6.1%. Well intentioned statements which called for prices to be based on long run marginal cost and to adopt test rates of discount similar to those used for low risk private investment, however, were more often than not overridden by political considerations. More so, there were practical difficulties in the application of these economic concepts in the monopoly utility industries. These decision rules may have reduced the industry’s ability to extract monopoly profits, but reflected cost plus pricing principles and therefore, provided minimum incentives to CEGB to act efficiently, especially where it had monopoly of information. In the main these policies were abandoned by the Thatcher administration in the 1980s and electricity prices were increased as part of the government’s macro-economic policy objective to reduce government’s short-term borrowings. Electricity prices had shown a decline in real rates in the 1980s. In the domestic sector, real prices of electricity had declined steadily in the period up to publication of the 1988 White Paper.18. Prices in the immediate pre-privatisation years were rebalanced so as to make prices closer to relative costs of supply and generally increased as part of the process of making the companies more attractive for floatation. Prices of bulk electricity rose substantially relative to prices of other industrial fuels. This was partly because of the removal of some of the cross-subsidies to industry. Total capacity in 1987 was 63869 MW, with 79% supply coming from fossil fuel sources. Maximum demand was 52000 MW, with E&W accounting for 87.5%, Scotland 10% and Northern Ireland 2.5%. The total transmission and distribution lines in England and Wales amounted to 390,000 miles, connecting 24,754 customers. Over 2% of GNP was accounted for by the industry. The structure of industry costs in the pre-privatisation period typically consisted of fuel 42%, generation 29%, and transmission 6%, distribution 19% and retail supply 4%. Any significant economic efficiency gains had to come from the generation end of the market. 111 Table 1 below shows the other main characteristics of the industry in the UK in 1989. Fossil fuel accounted for 79% of fuel source, nuclear 10% and hydro 6%. Natural gas as a fuel source hardly existed. Additionally, there were 24.7 million customers, of which 22.4 million were small domestic household users. Figure 20 shows the pre-privatised England and Wales industry structure of a vertical integrated generation and transmission company and 12 regional distributors; Area Boards, as well as linkages through two interconnections respectively to Scotland and France. Table 1 Characteristics of the UK System In the 1980s Capacity by Fuel Source Capacity MW Fossil Fuel Nuclear Hydro & Pumped Storage Single Cycle Gas Turbine and Diesel Total Source: Consumer Category Number Thousands % 50263 6519 4085 79 10 6 Domestic Farm Industrial/commercial 22,383,000 863,000 2,103,000 3001 5 Other 5,000 63.869 100 Total 24,754.000 John Cheshire, “UK Electricity Supply Under Public Ownership”, (The British Electricity Experiment, Privatisation; The Record, The Issues, The Lesson, ed., John Surrey, London (1996) p.16. In the later part of the 1980s the Thatcher administration became concerned about a number of the inefficient features, which had emerged in the industry. CEGB had come to exercise too much power over generation station investment decisions as well as over distribution prices. As part of a policy of liberalisation an Energy Act was introduced in 1983 providing for the liberalisation of the energy market. The Act sought to reduce the barriers of entry faced by private operators and to break the monopoly of the CEGB on the generation market and in so doing provided for Area Boards to purchase bulk electricity from private generators at rates published as Private Purchase Tariff (PPT), calculated to yield only normal rates of return on capital employed and for the CEGB and the Area Boards to provide open access to the transmission and distribution lines. 112 Liberalisation, however, had little effect. The policy sought to create competition for new capacity, whilst preserving Fig. 20 Pre-Privatisation England and Wales Industry Structure (1987) CEGB Area Boards Domestic Consumers Area Boards Genco Transco Area Boards Scotland Industrial & Commercial Consumers Some Large Consumers EdF (France) Integrated Generation and Transmission Source: (12 Area Boards) Distribution and Supply Large and Small Consumers John Vickers and George Yarrow, “The British Electricity Experiment”, Economic Policy (April 1991), p.191 113 the centralised control. CEGB predictably responded to removal of its monopoly power by introduction of artificially high prices, which served to impede new entrants. The Private Purchase Tariff was not only based on the Area Boards’ avoidable costs but also on the bulk supply tariff (BST) of CEGB. The response of CEGB to the threat of competition from private providers was to restructure BST in a way that made it unprofitable for private providers of bulk electricity to enter the market. The raising of the non-avoidable cost component of BST, through the introduction of a new system charge and a non-marginal energy charge had the effect of increasing the fixed charges in BST from 1% of total revenue generated from Bulk Supply Tariff in 1983/84 to over 20% in 1987/89. The increase in the unavoidable cost component of BST effectively reduced the average price paid to private generators to well below the average cost paid by the Area Boards for CEGB bulk electricity. Competition failed to emerge, not so much that the principle was wrong but because government allowed the dominant player to set the terms of wholesale price and PPT. The policy sought to create competition for new capacity, whilst preserving the centralised controls. CEGB predictably responded to removal of its monopoly power by introducing artificial cost barriers to new competition. The Thatcher administration then concluded that the operation of the power supply system did not have to be determined by ownership. State ownership had resulted in too much interference in the day-to-day running of the industry and industry managers were denied the freedom and economic incentives to make commercial decisions. Government up to that time intervened in the appointment of all the board members, approved all major investment expenditures, approved borrowing requirements and controlled the retail prices of the Area Boards. Government’s restructuring policies, which were announced in the 1988 White Paper, were enacted in a new Electricity Act of 1989. This Act provided for vertical and horizontal unbundling of generation from transmission, and the liberalisation of the generation market in England and Wales. Liberalisation of generation meant that new independent power producers were free to enter the market to provide bulk power supplies. Government’s new policy called for the creation of a competitive electricity industry. These policy changes were expected to relieve government of the financial burden of the industry and in the process provide for wider public share ownership. 114 The newly established generating companies were to be privatised. The unbundled transmission line and grid system was to be restructured as the National Grid Company (NGC) to be jointly owned and controlled by the 12 regional distribution monopolies (RECs). The National Grid Company was to maintain a central role in planning and coordination and was to be responsible for the dispatch function. The merit order system of dispatching was to be maintained with the cheaper plants being the first to be dispatched to meet a given demand. Generating companies were to be prohibited from cross-ownership with the transmission company so as to avoid future control of the transmission system by companies owning power stations. The National Grid, however, was to be allowed to own the pumped storage stations. The policy changes meant that the generating companies were to face competition for new capacity as well as competition at existing demand for the first time, that of product market competition. The changes also provided for the twelve English and Welsh Area Boards to be incorporated as joint stock companies and privatised. NGC was to operate in future on the basis of contracts as against the command and control relationship, which prevailed under CEGB. Distribution companies were to be allowed to contract for electricity with the NGC or directly with existing or new generating companies for generating capacities. The statutory obligation to supply was to be removed from generating companies and placed on the distribution companies. New generating plants were to be introduced into the system through competitive tenders. The RECs were to be allowed to meet capacity needs from importation, purchase from existing generators or from contracting with new independent power producers. They were also to be given the right to own generating stations when this did not create local monopolies in their respective franchised areas and in this respect were allowed to generate up to 15% of their own power needs, subsequently increased to 25%. Integration of generation with distribution, however, creates a potential self-dealing conflict in the wholesale power market model as the distributing companies which have captive customers and have the opportunity to pass these higher costs will display very little interest in cost minimisation and will procure its self-generated power. Where there is competition in the retail market and the opportunity to pass on higher costs is reduced, this problem is more or less eliminated. Competition in the retail market allows customers to choose other retailers. 115 Adjacent distribution companies were also to be allowed to compete on the border (border competition) to supply large users. Large users were to be allowed to by-pass the distributor and contract directly with generators. Both the transmission system and the distribution lines were to be mandated as common carrier and in so doing provide free and open access to their systems. Tariffs were to be developed to reflect common carriage charges, which in turn were to reflect user costs. The transmission and distribution systems, being in large part natural monopolies were to be regulated by an electricity industry specific regulator; the Director General of Electricity Supply (DGES). This industry regulator was to replace the Electricity Council, which was to be abolished. The old rate of return-cost of service system for rate determination was to be abandoned and replaced by incentive or price cap regulation in the form of RPI-X in the transmission and distribution sectors. The industry was expected to operate efficiently so that consumers could benefit from improved performances. The monopoly aspect of distributing companies; the lines business was to be “ring fenced” from retail supply with separate accounts to be produced for each of the separate business activities. Distributors were to operate under specific licences called public electricity licences, (PES) and the DGES to be responsible for licence enforcement, price and service quality regulation, and regulation of open access to the transmission and distribution systems and to ensure protection of consumer interest. In Scotland, SSHEB and SSEB were to be replaced by two newly incorporated joint stock companies; Hydro-electric (HE) and Scottish Power (SP) respectively, however, the Scottish nuclear stations were to be horizontally unbundled into a new company; Scottish Nuclear (SN). The vertical and horizontal integration of the Scottish two utilities were to remain unchanged. In the case of Northern Ireland, the generating stations were to be vertically and horizontally unbundled and privatised as three separate companies through trade sale. Transmission, distribution and supply activities of the Northern Ireland, system were to be incorporated as a single joint stock company; Northern Ireland Electricity (NIE) and floated on the stock exchange. 116 Restructuring the England and Wales Electricity System Government had received considerable criticism in respect of the earlier monopolistic structure created for privatised telecommunications and gas companies and a genuine attempt was made to provide for more competition in post-privatised electricity. Gas was in fact privatised without restructuring, resulting in a change from a publicly owned franchised monopoly to a privately owned franchised monopoly. Despite the more fragmented structure, when compared to the earlier cases of telecommunications and gas, government’s policy towards electricity continued to follow organisational conservatism as manifested in the earlier utilities privatisation19. Robinson, (1989)20, stated that: “ the privatisation programme of the last few years demonstrated the inevitability of illiberal schemes for major industries. From the point of view of public choice theory, there will always be an irresistible combination of powerful forces in favour of retaining big monopoly where corporations are earmarked for transfer from the state to the private sector. Pressure groups; the management of the corporation, the unions, the city and political forces in the Treasury will successfully resist genuine competition and only token gesture will be made in the direction of effective competition. Moreover, the social benefits of increased competition is not only intangible their realisation tend to be long-term”. Vertical and horizontal separation of the different stages of electricity production raises a number of problems, such as market power, transactional costs and scale economy issues. Transaction cost occurs when electricity as a product is transferred across technologically separate interfaces or hierarchies. Transaction cost that, arises is the cost of operating the new electricity market systems and covers price discovery, search for information, negotiation and contracting costs and policing and enforcement costs. The more the number of separate interfaces the higher the quantum of the transaction costs. Economising in transaction costs is a motivating force for viable modes of contracting and an important feature in guiding restructuring and organisational design of the electricity sector. 117 Within the vertically and horizontally integrated firm, marketing and organisational costs are internalised and reduced, not eliminated, as the firm does not have to make a series of contracts with other agents of production interfaces. When there are transfers over several separately owned interfaces, a series of contracts replaces internal coordination and in the case of electricity the firms have to agree to obey the directives of a central control agent; the system operator, within certain limits. The competitive forces released by competition must therefore, result in savings and benefits to counter balance the increased transaction costs and losses from diseconomies. In the case of separation of transmission from generation, because of the strong vertical relationship and vertical economies and the unique characteristics of an electricity product, several problems will arise. In fact vertical disintegration is being imposed precisely over the two sector interfaces where vertical coordination is crucial. Complete deregulation of the bulk electricity market is unlikely to be realised in the near future; therefore, there will be the need for some measure of light-handed regulation. In terms of vertical and horizontal reforms in the distribution and retail supply sectors, there were no structural changes introduced, as the pre-existing twelve regional enterprises were privatised intact. Structural separation of distribution lines business from the more competitive retail supply business was ruled out in favour of the weaker accounting separation. Supply was separated vertically in the accounting sense; however, vertical ownership and control in the organisational sense was maintained. Allowing distribution companies, however, to perform retailing, reduces market competition, because distribution companies are in a position to subsidise their retail customers by imposing higher tariffs on the monopoly lines business, larger than cost justifies. Integration also allows the distribution company to discriminate between classes of consumers21. Accounting separation partially addresses the problem. Each REC, however, was given special public electricity supply licences, setting out its rights and obligations relating to supplies for designated customers within its designated area. These licences gave the REC monopoly rights to certain parts of the market. The only innovation in the retail supply sector was the introduction of second tier licences, which were given to the RECs and other suppliers and which allowed holders of such licences to sell to any customer in the competitive or 118 liberalised market, including the REC’s domestic market. Second tier licences were given not only to the RECs but also to the generating companies and a number of new suppliers. Competition in the retail market was to be phased, and was first to involve liberalisation of large consumer market (consumers with a maximum demand of 1 MW and over) in 1990, to be followed by medium sized consumer market (consumers with maximum demand of over 100 kilowatt hours) in 1994 and finally choice was to be given to the small domestic consumer market (consumers with peak demand of under 100 kW) in 1998. In order to participate in the liberalised market customers had to install a half-hour metering system with on-line communication facilities. The large customer market was required to have these meters from 1990, whilst the medium sized customer market was given an option up to 1998. Small customers desirous of participating in the liberalised market were also required to install half-hour metering or they could opt to stay with their REC, without the obligation to install half-hour metering. RECs were required to sell to captive customers at regulated prices in their designated areas and were prohibited from cross-subsidisation. As full competition progressed, the distinction between public electricity suppliers and second tier suppliers are expected to disappear. An important development in the small user market has been the widespread use of pre-payment meters. Economy of scale is not a serious factor with electricity distribution. Economies arise more from intensity of customer distribution, rather than number of customers and the total turnover in a given area. Several more distribution companies could have been accommodated when one considers that the average size of distribution companies in New Zealand was 50,000. Increased number of companies would have provided the opportunity for increased yardstick competition. The rigid time scale set for privatisation and the need to ensure the attractiveness of the proposed sales to private investors, however, dictated government’s privatisation of the distribution companies in their existing form. Creation of new distribution companies and vertical separation of distribution from supply and creation of new supply companies would have facilitated more competition; however, the establishment of new supply companies would have been time consuming. It was also concluded that floatation of these new companies with no track record on the stock market would have been far too risky. 119 An important vertical structural issue relates to the extent to which the RECs were permitted to generate power for own use. Options ranged from partial exclusion from the generation business to that of compulsory competitive tendering and or regulator’s audit of procurement of new capacity. The option selected for England and Wales was that of partial vertical integration and this arose from the fact that the RECs were allowed initially to source up to 15% of power needs from own generation. Many RECs in the so called “dash for gas” quickly came close to filling their quota 22. With joint ownership of the transmission company by the twelve RECs, other vertical issues were raised. This partial integration of transmission and distribution did not follow any logical reasoning, either from the position of history, or economics. There are no serious economies of scope to be gained from linking transmission with distribution and vertical integration is not necessary for technical reasons. In order to reduce the risk that the RECs would manipulate the policies of the National Grid Company (NGC) to serve their own interest, severe restrictions were placed on the extent to which the RECs could influence the policies of NGC. Again the desire to make the privatisation packages for the distribution companies attractive to investors seems to have motivated this arrangement. Further structural issues are raised in respect of the presence of the transmission operator in the generation market. NGC was allowed to own the two hydroelectric pumped storage generating plants located in Wales. Whilst the size was less than 2000 MW, they were strategic with regards to the efficient operation of the system. These plants not only played a key role in assuring system stability, they were able later to set pool prices in 1994 by 15% of the time. The UK model of restructuring the electricity supply industry has had a major influence on other reforming countries, however, no single preferred model has emerged internationally as to the best ownership and governance structure of the transmission operator as well as to the functions this entity should perform. There is a clear trend, however, in favour of more open access and neutrality and a move away from any vertical integrated relationship with generation or distribution. Separation of the monopoly transmission lines business and system operation functions from the companies selling electricity, either in bulk or in retail form is necessary to remove concerns relating to possible self-dealing and discriminatory behaviour. 120 Arguments have been advanced for the transmission company to remain publicly owned as is the situation in New Zealand. In Bolivia as we shall see later, ownership of transmission was transferred to a private operator in the form of a long term concession. The argument for initial public ownership of the transmission company is that it leaves government more options in terms of later reforms and the level of competition, which can be introduced into the system23. This, however, does not establish the need for government to operate the system. Management and operation can be contracted out to private providers who are specialist in delivering transmission services. Valuation and pricing of the transmission grid is extremely difficult, as traditionally this component of the electricity system has been shielded from exposure to external markets. The result is that at the time the 12 RECs were given joint ownership of NGC the company was valued at £1 billion. Within five years the NGC was sold at a value substantially higher than its original privatisation sales price. In the England and Wales reform the NGC was entrusted with the function of systems operation, with responsibility for dispatching of generators and maintenance of system stability, as well as overall physical maintenance and investment in the system. In this regard, it was permitted to purchase standby power from generators to maintain security of the grid. NGC also coordinates the daily operation of the market, drawing up the merit order schedule and calling plants on the grid as well as administering the pool settlement (financial outcomes) between generators and traders. Additionally, it coordinates transfer across transmission links involving the French and Scottish interconnectors. The conduct of these activities is governed by general agreements between the generating companies, the RECs and other traders and forms the pool’s market rules. Finally, NGC was given a specific mandate to facilitate competition in the electricity supply system. In addition to separating out transmission into the National Grid Company in April 1990, the generation assets of CEGB were restructured into three new companies. The fossil fired-plants (mainly coal fired) were divided into two companies; National Power and PowerGen with the nuclear assets going to Nuclear Electric. A limited amount of the hydro-plants went to National Power and PowerGen and the greater part of the pumped storage as indicated earlier going as First Hydro to NGC. Additionally, the liberalisation of the bulk electricity market also allowed for entry 121 of new plants, as well as facilitating competition from Scotland and France through the two interconnectors. The share of the thermal capacity at unbundling was National Power 65% and PowerGen 35%. The original privatisation plan, which called for a duopoly with all the nuclear plants going to National Power, would have given that company 67% and PowerGen 33%. The overall market share of generation capacity in 1990 was National Power, 51%, PowerGen 31%, Nuclear Electric 14% and First Hydro 4%. National Power was allocated 40 power stations with 29486 MW capacity, PowerGen 23 stations with 19802 MW capacities, Nuclear Electric 12, nuclear stations with 7963 MW and First Hydro was allocated 2000 MW pumped storage capacity. The installed capacity in the England and Wales market was just over 59000 MW with peak demand of 49000 MW. The net effect was an asymmetric duopoly structure, motivated by the desire to package the plants with the more attractive non-nuclear system. With the decision to separate out the nuclear capacity and retain nuclear in the public sector the option of resorting to a larger number of generating companies was rejected with the result of another missed opportunity in creating a more competitive structure. Again the rationale seems to be the politically motivated timetable to complete the privatisation before the 1991 election. The logistical difficulties related to the development of a more fragmented industry structure it was feared would have risked a delay in the sale. A disintegrated structure also would have been less attractive to investors. This duopoly structure gave considerable market power to the two thermal generating incumbents and this is over and above being incumbents with monopoly of information on generation. Although the price elasticity of demand for electricity is low, given the homogeneous nature of the product the price elasticity for the product for any generator is very high. Within a duopoly structure, therefore, there is a strong incentive to take advantage of the inelastic industry demand curve by suppressing competition either through collusion or gaming behaviour. Government relied on competitive transformation of the industry on a policy involving free entry to the generation market. The initial structure was considered to be of transient importance. The Schumpeterian (1976)24 gale of creative destruction in due course would compete away any monopoly profits of the incumbents and correct the imperfect initial industry structure. 122 Government, however, was to impose a number of restrictions on the competitive transformation process by imposing the fossil fuel levy or tax on electricity purchases. The bulk of this charge was, however, discontinued in 1996. Most of the cross-subsidy after 1996 went to the other renewable energy sources. It was also possible to eliminate the entire non-fossil fuel obligation in 1998, mainly as a result of efficiency and operating performance improvements, which were made by the nuclear stations. The levy declined from 10% at vesting to 0.9% in 1998. Market restriction was also created from mandating the RECs to buy specified amounts of non-fossil fuel every year until 1998. An interesting development from this energy policy has been the rise of wind power from virtually nothing in 1990 to 700 MW in 1999. In the inter-war years use of natural gas in power stations was defacto banned and was only allowed after the discovery of North Sea gas in the mid-1960s. Although constraint on fuel use was relaxed in 1990 for National Power and PowerGen, diversification move were hampered from government’s insistence that the two companies sign contracts with British Coal for the first three years of privatisation, up to March 1993. In this period, the requirement was for 70 million tonnes a year, reducing to 65 million. The contracts were further extended for four years from 1993 to 1998, however, subsequently the quantities were reduced to 40 million tonnes and then to 30 million. On critical examination, the radical restructuring thesis therefore, does not stand up to scrutiny. The development of a competitive optimal structure had to contend with more powerful political factors such as creating financially secure companies sufficiently attractive to the city financiers and potential shareholders and the need to protect the nuclear and the coal industry. Privatisation Programme The two non-nuclear power companies and the 12 regional distribution and supply companies were privatised by public floatation. All the shares of the RECs were sold in December 1990 for £5.1 billion. Included in the sale of the RECs was the sale of NGC. Only 60% of the generating companies’ shares were offered and sold in March 1991 and the shares fetched £5.7b. Scottish Power and Hydroelectric were sold in June 1991 for £ 2.8 billion and the Northern Ireland 123 Distribution and Transmission Company, NIE in June 1993 for £ 418 million. Table 2 below sets out the financial proceeds of the privatisation programme between 1990 and 1996 Table 2 Electricity Privatisation Programme 1990 – 1996: Sales Proceeds Companies Date RECs PowerGen National Power PowerGen National Power Scottish Power Hydro Electric NIE British Energy Total Dec. 90 Mar. 91 Mar. 91 100 60 60 CapitaliCost of sation Sale £ £ Billion Million 2.40 7.7 191 1.75 3.5 79 1.75 Mar. 95 Mar. 95 40 100 5.22 4.86 June 91 100 2.40 June 91 100 2.40 June 93 July 96 - 100 100 - 2.20 2.03 - Source: % Share Sold Share Price £ Equity proceeds £ Billion 5.1 Debt Repay £ Billion 2.8 2.17 0.8 - 57 3.6 - 2.9 98 2.8 0.6 0.362 1.4 - 31.5 32.0 488.5 0.418 1.4 15.48 (0.7M) 0.6 4.87 Carole Hicks, 1998, Regulation of UK Electricity Industry, London, Centre For The Study of Regulated Industries (1998), p. 11. The remaining 40% of the PowerGen and National Power were sold in March 1995 for £10.8 billion. Most of the shares in British Energy, the commercially viable part of the nuclear generating facilities was sold in 1996 for £1.4 billion. Trade sale of the Northern Ireland generating stations in 1992 also fetched £356 million. Overall sales proceeds amounted to £15.48 million. Ownership of the National Grid Company was subsequently removed from the RECs. The company’s shares were floated on the stock market in 1995 as National Grid Group (NGG). The pumped storage plant as First Hydro was also unbundled in 1995 and ownership transferred to Edison Mission Energy, an American owned company by trade sale. Almost all the new owners of the privatised companies were required to take over debt obligations from the previous state owned enterprises. Included in the balance sheet of the twelve RECs were 124 debts amounting to £2.8 billion, with repayment obligations imposed on the part of the new owners over a period of 18 years. In the case of the privatised fossil fuel companies, the debt obligation transferred was only £800 million, with requirement for repayment in three instalments; April 1991, March 1998, and March 2005. In the case of the Scottish companies new debt amounting to £600 million was created and was to be repaid in varying instalments by 2005. A total of £417 million of the Scottish Utilities debt were completely written-off, as well as the outstanding corporation tax losses arising out of unused capital allowances and amounting to £505 million. A total of £70 million in debt was taken over by the new owners of British Energy, whilst £600 million was retained in the balance sheet of the privatised company with instalment payment obligation up to 2016. A total of £700 million of inherited debt in British Energy was also converted to share capital with the remaining £445 million being written off. The treatment of the state owned utility enterprise debt has presented major problems for developing countries in their privatisation programme. It is clear from the policy adopted that the British Government sought to maximise cash flows. With a high proportion of households already connected to the system and having access to electricity, there was less pressure for new capital to expand the system as was the case later in Bolivia. In the British privatisation the sales proceeds went to the Treasury, whereas in Bolivia the sales proceeds, in most cases went to the company to expand the system. In the divestiture of utilities and essential services governments have sought to retain some measure of control following upon privatisation of the public enterprises. Many countries have opted to sell minority shareholding to a strategic investor with a management contract, giving the strategic investor management and operational control of the company. In the British case, in almost all instances, the entire shareholdings of the companies were sold to private portfolio investors. Britain had the option of a well-established stock market and therefore, stock market flotation was widely used to dispose of the utilities. In many developing countries stock markets do not exist and even where they do, their absorptive capacities are thin. Britain also introduced a new special share arrangement, which came to be known as the “Golden Share”, and which limited the voting rights of the private shareholders in special circumstances. The Golden Share more or less carried reserved rights conditions, requiring agreement of the Government in respect of clearly stated circumstances. 125 The Golden Share gave the UK Government the power to veto changes to the share structure where one person or entity sought to acquire 15% or more of the voting rights, or to vary the voting rights of any of the existing shares or to issue new shares with voting rights different from those of the ordinary shareholders of the company. Except for the NGG the Golden Shares in the privatised companies were all redeemable. Those in the distributing companies were redeemed in March of 1995, whilst those in the two generating companies were redeemed in 2000. In the case of NIE and the two Scottish companies these shares were redeemed in 1998 and in the case of British Energy they are eligible to be redeemed in 2006. The restriction on the size of the share ownership not only served to limit the scope for reintegration and restoration of monopoly operation it also served to restrict competition in the market for corporate control. It has become a practice in privatisation contracts to limit crossownership between generation and distribution companies, as well as between the generation and the distribution companies on the one side and the transmission company on the other. The 1996 Articles of Association of NGG initially prohibited any Pool member, electricity licence holder, or member of a distributing group from having an interest of 1% or more in the voting rights of NGG. Restrictions were also imposed prohibiting NGG from holding a generation or electricity supply licence and from any Pool member of an electricity licence holder from being a Director of NGG. Post-Privatisation Changes to the Industry Structure Given the imperfect market structure at privatisation, the regulator was left with no option but to intervene into the market to facilitate a more optimal structure. First, he mandated the discontinuance of the REC’s joint ownership of the NGC in 1996. The regulator regarded this relationship as potentially anti-competitive and inappropriate in that its independence could be compromised. There was, however, no evidence of exploitation. Second, the regulator regarded the vertical relationship of NGC with the pumped storage generation plants as carrying a conflict of interest as NGC was a competitor in the non-base load bulk electricity market and therefore, 126 requested unbundling of the pumped storage generating capacity in 1995. This led the system being incorporated as First Hydro and divestiture to Mission Energy in January 1996 for £680m. The Regulator also became concerned about the duopoly non-nuclear generating market and the market power of the two players to determine pool prices. A voluntary agreement was reached to sell 6000 MW of their coal fired plants to competitors by March 1996. In the autumn of 1995 PowerGen sold 2000 MW to Eastern Electric (now TXU Europe). A year earlier Eastern Electric was taken over by the Hanson Group. In April 1996 National Power sold 4000 MW of plant capacity also to the Hanson Group. The 6000 MW capacity involved 5 coal fired plants and were disposed of under 99-year leases. Further transfer of approximately 8000 MW of generation plants from PowerGen and National Power were also affected in 1999. PowerGen sold 4000 MW to Edison Mission Energy and National Power sold 4000 MW to AES. A further 2000 MW was sold to British Energy. PowerGen also sold 2000 MW of capacity to London Electricity/EdF in October 2000. Competition in the generation market emerged from several sources. The number of Pool members has increased from the original 22 in 1990/91 to 95 in 1999/00. This has reflected increased competition in both generation and supply. Of the 95 Pool members in 2000, 43 were sole generators, 13 were generators, which were also suppliers, and 39 were suppliers. The two incumbent duopolies have seen their market share as shown in Table 3 declined from 73.9% in 1990/91 to under 17.8% by November 2000. New entrants mainly combined cycle gas turbine independent generators have seen their market share rise from 17% to 56.7% in the same period. 127 Table 3 Output by Market Share-Percentages National Power PowerGen British Energy BNFL TXU Europe Interconnectors AES Others Total Total Output TWh Source: 1990/91 1994/95 1998/99 1999/00 45.5 28.4 17.4 7.0 1.7 100.0 268041 33.8 26.0 22.3 8.7 9.2 100.0 274037 21.0 17.7 17.1 8.0 7.7 7.5 21.0 100.0 295114 14.0 14.9 14.8 6.8 5.5 8.3 5.7 30.1 100.0 297550 Nov. 2000 11.0 6.8 15.2 4.1 5.4 6.2 8.3 43.0 100 na Electricity Association, Electricity Industry Review, No. 5, London, (January 2001), p.41 Three relatively large new players emerged, Edison Mission, Eastern/TXU and AES and they have come to account for more than 20% of output. Nuclear companies, BNFL and British Energy have marginally increased their combined market share from 17.4% to 19.3%. In terms of installed capacity the two incumbents’ share has declined to 22.8%, with the three large new players accounting for 27.2% of capacity in 2000/01. (See table 4). Market forces and regulatory intervention have significantly reduced market power and eliminated the duopolistic market structure imposed on the industry at privatisation. 128 Table 4 Installed Capacity in England and Wales in 2000/01 Company International Power /Innogy PowerGen British Energy TXU Europe Edison Mission AES BNFL London Electricity NRG Scottish Interconnectors French Interconnectors Other Producers Total Capacity Own Generation from Distributors Connected System Capacity MW 8336 8102 9330 6757 6349 4873 2869 2809 1059 1200 1988 12511 66183 % Share of Capacity 12.6 12.2 14.1 10.2 9.6 7.4 4.3 4.2 1.6 1.8 3.0 18.9 100.0 4400 - not Source: Electricity Association, Electricity Industry Review, No. 5, London, (January 2001), p.35. The increasing dependence on gas resulted in concerns by government about the security of the electricity supply system and this led to further government intervention in 1998 when a moratorium was imposed on construction of new gas-fired plants of significant sizes. Potential investors for larger gas-fired plants (small combined heat and power plants were excluded) had to obtain new consent permits. Government not only halted the “dash for gas” episode: a complete review of all fuel sources was initiated. Despite the progressive reduction in market shares of National Power and PowerGen, the Regulator, the Office of Gas and Electricity Markets (Ofgem) continued to be concerned about market power from the two companies and the limited price competition in the pool price setting. Although the market share of the CCGT/IPP operators had increased to 25% in 1999 they were able to set prices for only 3% of the time, compared to 86% of the time by National Power, PowerGen and Eastern. 129 The Regulator felt compelled to intervene once more into the generation market in October 1999 and published proposals to introduce a new set of licence requirements called Market Abuse Licence Conditions. These conditions provided that the licensee shall not engage in conduct, whether alone or in collusion which amounts to an abuse of a position of substantial market power in the determination of wholesale electricity prices under the relevant trading arrangements. Firms were therefore, prohibited from restrictive business practices such as collusive price bidding strategies, withholding capacity of supply and manipulation of market rules. The licences were to be issued to the seven major generators. Five of the generating companies consented to the conditions in April 2000 and the other two large players; British Energy and AES refused to sign the consent licences on the grounds that the Competition Act already provided the Regulator with adequate powers to deal with market abuse and as a result the dispute was referred to the Competition Commission. The Commission, however, handed down a decision in favour of the two operators and Ofgem had to remove the market abuse conditions from the licences of those generators that had earlier accepted the conditions. The need for special regulatory rules to control restrictive business and anti-competitive practices, despite the Fair Trade Practices Act, the Pool Rules and the Financial Services Regulation, highlights the particular characteristics of electricity, that of non-storability of the product, limited short term demand side responsiveness and the need to match demand with supply instantaneously. Whereas traditional criteria for market power by competition regulators have been a market share of over 25%, the UK electricity industry specific regulator was finding that market share of 10% resulted in market power sufficient to influence price setting in the Pool. The most important structural change, however which has emerged since 1990, is that of liberalisation of entry to the generation market. This has led to natural gas becoming the preferred fuel for new power plants in the UK. Between 1990/91 and 2000/01, 21735 MW of new CCGT generating capacity had been commissioned in England and Wales. Co-generation capacity also emerged as an important player and more than doubled by 1998/99, reaching 3,700 MW. There were four further co-generation schemes under construction in 2000, amounting to 500 MW of capacity. 130 Table 5 Percentage Share of New CCGT Capacity Commissioned 1990 – 2000 Generators PowerGen National Power IPPs Total Capacity MW 3040 3200 15495 21735 % 14.0 14.7 71.3 100.0 Source: Electricity Association, Electricity Industry Review, No. 5, London, (2001), p.34. There was 1875 MW of capacity under construction in 2000/01 The share of ownership of the new CCGT capacity is shown in Table 5 above. Over 71.3% of the new CCGT capacity came from players other than the two incumbents. CCGT plants accounted for the greater proportion of new capacity despite the bias in favour of coal through the coal contracts. The incumbents between them had installed only 6240 MW of CCGT capacity and this compares to the 15195 MW installed by the IPPs. There have been major changes overall in fuel source. By 2000/01 the percentage share of generation capacity in the Pool taken up by natural gas had increased from less than 1.0% to 30.4%, at the same time coal saw its share decline from 64.6% in 1990/91 to 32.7% in 2000/01. The short construction time of 2 to 3 years for CCGT, compared to coal at 6 to 8 years allows for greater flexibility in the decision on new stations. Their modular construction and their lower construction costs, which significantly reduce financial exposure, make CCGT plants ideal for fixed turnkey contracts provided by equipment suppliers. The new combined cycle gas plants also offer environmental advantages over fossil-fuel plants as they consume 27% less fuel, emit 58% less carbon dioxide, emit no sulphur dioxide, and 80% less nitrogen oxides for each unit of electricity produced and the capital cost is 50% less for each MW of capacity. 131 Table 6 Fuel Use Changes: Percentage Share 2000/01 Fuel Use Coal Nuclear Gas OCGT/Oil Other Total Major Power Producers Maximum Demand % Share of Market 1990/91 2000/01 64.6 32.7 23.6 14.3 0.7 30.4 9.4 10.5 1.7 12.1 100 100.00 73000 MW 66183 MW 53400 MW 56300 MW Source: Electricity Association, Electricity Industry Review, No. 5, London, (January 2001), p. 34. The IPPs had to buy most of the natural gas they need for operation from the British Gas monopoly and the terms were 15 year supply contracts at prices indexed to the general level of inflation. In turn the entire output of the IPPs was contracted to the RECs with 15 year “take and pay” contracts, and with full “pass through” of the gas purchase costs. The REC developed this vertical relationship with the IPPs because of their desire to diversify supply sources from the two incumbents and to avoid dependence on the duopoly market structure created at privatisation. Because of these “take and pay” contracts and the relatively high minimum bills the IPPs found a large element of their gas purchase cost fixed. Thus the marginal cost of gas to them is close to zero, creating a powerful incentive to ensure total dispatch into the Pool to secure base load operation. The use of a single system marginal price for bulk electricity sales was also found to unduly favour natural gas-fired and nuclear fuel base-load generators. This pricing mechanism allows base-load generators to offer zero prices in order to guarantee full dispatch because they know that they will receive the pool price regardless and this has worked to the disadvantage of the coal-fired generators. 132 The market structure has, therefore, led to channelling of competition into areas where it least affects the incumbents and has had less impact on wholesale prices. The incumbents, therefore, found themselves competing with each other for the critical part of the load curve; the mid-merit and peak load which operates with mid-merit (higher) variable cost. PowerGen and National Power have, however, been critical of a system which restricted them in the earlier part of the 1990s to compete only in one segment of the market (60%) and which excluded them from the base-load market25. They complained that the IPPs with “take and pay” contracts are operating in a risk free environment. Nuclear Power has a very large share of the wholesale market. Nuclear Power also operates as a “must run” generator, with the result that even if the two incumbents offer power at zero prices, Nuclear Power would still be dispatched. This condition arises from the inflexibility of nuclear plants. At the same time, the Scottish companies have the privilege of sending power into the England and Wales system with no reciprocal rights of access to the Scottish system by the incumbents. Scottish Power had also benefited from cross-subsidy through the non-fossil fuel levy. A further disadvantage to the two fossil-fuel incumbents resulted from the waiver of the fossil-fuel levy that the French system enjoyed through EdF. This meant that EdF obtained some £5 per megawatt hour above the maximum price permitted through the Pool price undertaking. EdF share of the market has varied from 4% to 6.0%. This subsidy was worth £95 million in 1991-92 to the French consumers. At privatisation government sought to maintain its protection of the coal mining industry, although, at much reduced levels, after 1993. These agreements were based on the ability of the RECs to “pass-through” the additional cost to the consumers. The introduction of increased competition at the small consumer market end of the system from 1998, effectively removed this ability of the RECs to pass-through this cost and the continuation of this cross-subsidy to the coal industry. In its argument for review of the Pool trading arrangement in 1997, the Government claimed that the Pool price mechanism distorted the choice of energy sourcing and that the use of a single system marginal price for all bulk electricity sales, unfairly favoured gas-fired and nuclear base-load 133 generators, which is a point the two incumbents with large coal plants had been making from 1993. Shuttleworth (1999)26 however, claimed: “that the government failed to show exactly how the pricing method hampered coal and why coal plants could not secure their output by adopting “take and pay” contracts as the gas-fired plants have done”. The incentive to build gas-fired plants is more a factor of their lower cost, whilst the incentive to run them depends on the form of contract. Reforming the pricing rules of the bulk electricity market is unlikely to change these factors or change the fuel sourcing relationship in favour of coal. In their continued support of the coal-fired plants, both Government and the Regulator strongly advocated divestment of coal plants by the two incumbents to curtail their market power. With the elimination of market power, the government argued that there would be a reduction in spot prices and this would eliminate the incentives for construction of gas-fired plants. If anything the moratorium on gas created a temporary scarcity for capacity and allowed the incumbents to attract higher prices for the disposal of coal plants after 1998. Government did not outline any clear ownership and merger policy at privatisation and only permitted the market for corporate control to operate after March 1995 when the golden share control mechanism was allowed to lapse and the removal of the restriction limiting a single voting entity from holding 15% of the voting rights in the distribution companies was lifted. The Golden Shares in National Power and PowerGen were only redeemed in October 2000. The lifting of the restriction in the autumn of 1995, not only ushered in a flurry of takeover bids some friendly; some contested; both the ownership and industry structure came in for considerable changes. Six of the initial takeovers took place without reference to the Monopolies and Mergers Commission (MMC), whilst Government referred the bids of the two incumbent generators to the MMC, with the result that these two bids were subsequently disallowed27. In the two-year period following 1995 alone, eleven of the regional distributing companies came to be owned by shareholding interests other than the investor groups at privatisation. Three of the 134 companies diversified into water supply and gas distribution and supply, making them multi-utilities, whilst eleven by 1999 had invested (and used up most of their 15% quota) in CCGT plants. Eight of the twelve firms were taken over by American interests and one by a Scottish company.. Government initially blocked the reintegration attempts of the two incumbent generators with retail supply, the reason being that competition had not sufficiently developed. Vertical reintegration in principle had, however, not been ruled out. Scottish Power had been allowed to merge with Manweb in 1995 and Eastern one of the large regional distributors was allowed to acquire generating capacity that the two incumbents were forced to sell. After 1997 PowerGen, one of the two incumbent generators was allowed to acquire East Midlands Electricity and National Power now Innogy Holdings, the second of the two incumbents was allowed also to acquire the supply business of Midlands Electricity on condition of further plant disposals. In 1999 British Energy, the nuclear generator also entered the takeover market and acquired the retail supply business of SWALEC, previously part of the Welsh water and electricity company; Hyder only to sell SWALEC six months later to Scottish and Southern Electric. EdF the French electricity utility also entered the market and acquired London Electricity and SWEB supply business, creating a new group that of LE Group. In 1998 Scottish Hydro also merged with Southern Electric. Edison Mission by 1999 had developed to be a major generator with interests in hydro, coal and gas plants. Because of these takeovers the Regulator’s pre-occupation with price control widened to cover the battle for corporate control and re-integration This increased forward vertical integration has also coincided with the liberalisation of the small consumer end of the retail supply market. Kennedy (1996)28 in his analysis of the relationship of industrial structures of the electricity industry in England and Wales concluded that ‘vertical mergers in the electricity would not necessarily be welfare reducing and might actually be welfare improving’. Vertical mergers he argued could be tolerated so long as there was competition in the generation end of the market. The ownership relationships of the various companies at the end of 2001 are shown in Table 7 below. 135 Table 7 Summary of who owns whom – 2000 (Intermediate holding companies have been omitted for clarity) Parent’s Owner Investor-owned (USA) % 100 Parent American Electric Power British Energy Brutish Nuclear Fuels Edison International Elctricit de France % 100 Subsidiary SEEBOARD Publicly quoted (UK) British Government (UK) 100 100 --100 --BNFL Magnox Generation Investor owned (USA) 100 100 100 GPU Inc*** 100 Edison Mission Energy LE Group (London Electricity and SWEB supply) GPU Power UK (formerly Midlands Electricity, distribution) French Government (France) 100 Investor owned (USA) may have third columns 3times and 5columns 4or5 times. Publicly quoted (UK) 100 Innogy Holdings 100 100 100 94.75 Publicly quoted (UK) 100 Privately owned (USA) incl. Berkshire Hathaway 100 Publicly quoted (UK) Parent’s Owner Investor owned (USA) 100 % 100 Publicly quoted (UK) 100 Publicly quoted (UK Investor owned (USA) 100 100 Investor owned (USA) 100 International Power MidAmerican Energy Holdings PowerGen UK Parent PP&L Resources with Southern Company 49%** Scottish and Southern Energy Scottish Power Southern Company** with PP&L Resources 51% Texas Utilities --- ** 100 100 100 United Utilities Viridian Group Xcel Energy --- 100 Northern Electric 100 % 51 East Midlands Electricity Subsidiary Western Power Distribution (formerly SWEB and SWALEC distribution) 100 Merger of Scottish HydroElectric and Southern Electric SWALEC (supply) Maweb Western Power Distribution (formerly SWEB and SWALEC distribution) 100 100 51 100 100 Public quoted (UK Public quoted (UK) Investor owned (USA) MEB (supply, now branded as power) Yorkshire Electricity 100 100 5.25 TXU Europe (formerly Energy Group and Eastern Electricity). In Turn owns: Norweb Energy (supply). Norweb (distribution) Northern Ireland Electricity Yorkshire Electricity In the USA, Southern Company has sold 19.7% of Mirant Corporation (formerly Southern Energy), which holds a 49% share of Western Power Distribution, in an initial public offering and intends to sell the remaining shares in April 2001. 136 *** In the USA, GPU Inc merged with First Energy. Source: Electricity Association There have also been major structural changes in the nuclear sector of the industry. Following the electricity industry restructuring in 1990 the five AGRs and the PWR of Size-well of 4750 MW were separated out from the seven older Magnox reactors of 3225 MW to form Nuclear Electric. Sizewell B PWR plant came on stream in 1994, adding 1188 MW of new capacity to the nuclear sector. Two years later the Magnox plants were incorporated as Magnox Electric and became a subsidiary of Nuclear Electric. In April 1996, the two Scottish and five English AGRs, along with the Size-well PWRs were restructured as two separate subsidiaries (Nuclear Electric and Scottish Nuclear) under British Energy. That same year the operations of the two national nuclear systems were further merged into one operational group within British Energy and privatised. Robinson, (1996)29, concluded that in horizontally integrating the English and Scottish nuclear plants into one company in anticipation of privatisation, there was another failure to seize the opportunity to enhance competition and rivalry in the generation sector. The nuclear plants could have been restructured into two companies of more equal size, as was the preferred position of the Regulator. Their geographical constraints could then have been discontinued and the plants privatised to become formidable competitors to the two incumbents in the Pool and contract markets. Government again allowed consideration such as attractiveness of the divestiture package to potential investors to override the requirements for a competitive market structure. British Energy with its seven AGRs and PWR plants was publicly quoted in 1996. In January of 1998 the small time-limited Magnox Company – Magnox Electric was transferred to British Nuclear Fuel Limited, (BNFL) to be retained in the state sector. BNFL has been operating two Magnox plants for weapons production for several years. The end result is that a duopoly market structure was created also for the nuclear generation market, consisting of one small state owned company and one larger privately controlled company. 137 British Energy’s nuclear plants have seen an overall increase in their productivity of 75% since the introduction of the reforms in 1990. With the introduction of private ownership in the nuclear sector the restrictions on diversification and geographical market sharing were later removed and the company has been allowed to integrate forward into the retail sector as well as to invest into coalfired operation. For the future Magnox Electric, because of its associated high operating and decommissioning costs will be precluded from competing in the market for bulk power. Inevitably, Magnox Electric will continue to operate in the state sector as price-taker and as “must run” plants, contributing nothing to competition until their eventual closure. Effectively they are stranded assets with the consumer and the general public having to meet the higher operating and decommissioning cost. Although British Energy has been in the private sector since 2002, given the inflexibility of nuclear plants they will continue to benefit from “must run” status and in so doing also continue to be a price-taker, with minimum direct contribution to competition in the Pool. With the loss of income, however, from the discontinuance of the fuel levy, British Energy now has a stronger incentive to compete in the contracts market and reduce its exposure to the Pool price through Contracts of Difference. In order to increase its competitive position it has already commenced diversification from nuclear, and in 2001 owned 1960 MW coal-fired plant capacity, which it acquired, from one of the incumbents. Contracts for base-load power as is provided by nuclear plants command relatively lower price when compared with power for mid-merit and peak-load plants. Further diversification into CCGT plants more likely from purchases from the REC owned IPPs, would improve its competitive position. With the end of the franchised small customer market in 1998 some RECs have decided not to remain in the generation market. Without a guaranteed consumer market, RECs find it more advantageous to reduce their long-term supply exposure and increase the proportion of power off-take from the power exchange. Integrating into the supply business has also served to strengthen the British Energy market position in the electricity supply industry. British Energy is, however, approaching 20% share of the bulk 138 electricity market: therefore, the Regulator will doubtless become concerned about its increasing size, especially as the Regulator’s preference has been for two competing private nuclear firms. The Scottish and Northern Ireland Electricity Reform In the case of Scotland and Northern Ireland, the reforms involved even more conservatism. In fact different structural approaches were introduced for the two smaller systems and at the time reflected classical industrial organisational issues of optimal vertical integration and disintegration. The question was which model of industrial structure, given issues of economies of scale and transaction costs, leads to lower cost to consumers and higher levels of efficiencies? Newbery (1995)30 concluded that: “The restructuring options are determined by the size of the electricity market and the fuel mix, hence it is more appropriate for small and especially isolated and geographically compact systems to consider retaining vertical integration to final consumers”. The policy in Scotland before the reform was to build large plants based on the rationale of economies of scale, hence very few large stations made up the system. Government’s position at privatisation was that the relatively small system; one eighth that of England and Wales, serving large areas of sparsely populated regions and with vertical integration being considered successful, there was a strong case to maintain the existing vertical structure and rely on competition between two privatised vertically integrated companies for the liberalised consumer market and indirect competition by comparison to ensure efficiency gains. A disintegrated and more competitive structure would have made it more difficult to maintain a cross-subsidy policy to rural areas. The Scottish people also provided strong political opposition to the UK type reforms. In the final structure adopted for Scotland in 1990 two vertically and horizontally integrated joint stock companies, Scottish Power (SP) and Hydro-Electricity (HE), now Southern Energy replaced SSEB and NSHER. The existing two nuclear gas-cooled plants, built by SSEB were initially transferred to a new state owned company, Scottish Nuclear as shown earlier. Scottish Nuclear first 139 became a subsidiary of UK Nuclear Electric in 1996, only to be merged as one operating unit in British Electric that same year and now forms part of privatised British Electric. SP and HE were given composite public electricity supply licences covering generation, transmission, distribution and retail supply for their designated region. However, vertical accounting separation of the four distinct businesses was mandated. The licences imposed a specific limit on what could be charged for generation. The licencing system also provided for the entry of second tier suppliers, allowing reciprocal competition in each others designated area for the liberalised large end user market (1MW and over) involving 500 end users and for other generators to contract with large end users making use of the two companies’ transmission and distribution systems. This was to be carried out on a non-discriminatory basis with the settlement balances between generators and purchasers settled on the basis of the E&W pool prices. Both companies were also allowed to hold second tier licences, giving them the rights to operate in E&W and more recently in the Northern Ireland markets. The transmission system of the two companies form an integrated system, and Scottish Power is in turn interconnected with E&W, originally by a 850 MW connector, but subsequently upgraded to 1600 MW. A 250 MW submarine cable connector was later developed, and linked the west coast of Scotland to Northern Ireland in 2000. In order to provide each company with a balanced mix of power plants a complex series of restructuring contracts, aimed at providing diversification of fuel source for each company was introduced. Under these contracts, HE was required to take a given output from SE’s coal firedplants, and in return SE was required to take a given output from HE’s hydro-plants. In addition to these restructuring power contracts, HE was required to enter into coal supply contracts to run to 2004 and SE hydro agreements, which run to 2039. Both companies were also required to enter into 15 year power supply contracts with Scottish Nuclear, under which all the nuclear capacity is supplied to HE and SE in the ratio of 25.1: 74.9 respectively, and these contracts are “must run” plants, with the effect that payment obligations accrue whether or not they are dispatched. Both non-nuclear companies had considerable excess capacity at privatisation and as a result entry to the Scottish generation market was initially prohibited. The entry of independent power producers was 140 not permitted until the latter part of 1990s; hence there have been only marginal changes to the structure since privatisation. At the time of privatisation, 1990/91, the market shares for electricity supplied were respectively, Scottish Nuclear 36%, Scottish Power 44%, and Hydro Electric 20%. Installed capacity has increased marginally from 1990 to 10,333 MW in 1999, with market shares respectively being, Scottish Nuclear/British Energy 22.3%, Scottish Power 34%, and Scottish and Southern Energy (former Hydro-Electric) 44.7%31. Coal as a fuel source had come to account for 35% capacity, nuclear 27% hydro 19%, gas and oil 18% and renewable 1.0% in 2000. Up until 1996/87 both HP and HE held 85% of the small domestic household and medium sized markets and 86% of the large industrial market (1 MW market). The medium sized 100 kW, market and over was also liberalised in 1995, a year after the UK market to bring 50% of supply into the liberalised market. Both companies also held the greater portion of the second tier market. In 1998/99, second tier suppliers, other than the two incumbents had only developed to account for 21% of the large industrial market, compared to 80% in the E&W market, where second tier supplies had come to account for 80% of the market32. Unlike in the UK, where the two incumbents experienced progressive decline in output in the first five years up to 1994/95, the Scottish generators experienced an increase of 28%. With opportunity for export to England and Wales, exports increased from 5% to 20% of output. Interestingly, the system size is more or less the same size as that of New Zealand. While New Zealand with similar outlying thin distribution areas disintegrated its structure and introduced both wholesale and retail competition, the Scottish market was retained as a franchised monopoly system. Maintenance of the vertically and horizontally integrated franchised utility, the weak interconnector system, control over access to their interconnector by the incumbents, the restrictive vesting contracts in both power supply and fuel supply, as well as the initial entry restrictions to the generation market have severely frustrated competition in the Scottish market, with the net effect that prices for domestic consumers which were lower in England and Wales in 1990, have developed to be significantly higher in Scotland by 2000. Similarly, the regulated wholesale bulk 141 electricity prices have also developed to be significantly higher in Scotland. The Scottish operations were also subjected to the same price cap tariff control formula of RPI-X With the gradual decline in the importance of the restructuring contracts, the expansion of the capacity of the interconnectors, the recent opportunity for IPP entry in the generation market, the European Commission’s liberalisation directives and the 1999/2000 liberalisation of the small domestic household market, Scotland can expect to progressively experience increased levels of competition in both the generation and retail supply market segments after 2000. Northern Ireland is the much smallest of the three markets in terms of size, being just over 2,000 MW in 2000 and more comparable to the size of electricity markets in the lesser developing countries. In 1990 Northern Irelands installed capacity was about 1600 MW. Although the market size was less than 20% of that of Scotland, the level of vertical and horizontal disintegration introduced was much higher. This indicates that size, therefore, was not the only influencing factor in the Scottish case. Northern Ireland opted for the model two phase of market development, that of the single buyer model. The rationale being that radical unbundling, as in the case of the UK was not a practical solution. There were concerns about the size of the market, the abuse of market power in a small market, excess capacity, lumpiness of investment in a small market with a few large generators, and lower density ( as was the case with Scotland ) on the distribution system. Restructuring and privatisation was initiated in 1992, two years after the commencement of the exercise in E&W. The single vertically and horizontally integrated publicly owned Northern Ireland Electricity (NIE) enterprise, which owned and operated four power stations, with total capacity of 2,300 MW, was vertically unbundled with generation separated from the transmission and distribution network sector. Generation was further unbundled into four power companies; Ballylumford which was sold to British Gas, and operates as Premier Power; Kilroot and Belfast West, both of which were acquired by Nigen, a joint venture project of AES Corporation of the USA and Tractrabel SA of Belgium and Coolkeeragh which was the subject of a management buyout, supported by a group of portfolio investors. 142 The network system was restructured as a vertically integrated transmission, distribution and retail supply company and floated on the stock market in 1993. NIE was restricted on privatisation to own no more than 5 MW of non-fossil fuel generating capacity. In 1998 NIE was taken over and became a subsidiary of Veridian Group. Market shares in 1999/2000 were respectively, Premier Power 52%; Nigen 33.7% and Coolkeeragh 14.3%, with a total capacity of 2,072 MW. Northern Ireland’s population in 1990 was is just under 1.7 million and compares to 5.1 million for Scotland and 50 million for England and Wales. NIE was required to establish a purchasing agency, Power Procurement Business (PPB), to act as the single buyer for all electricity produced and publicly supplied. All three generating companies were compelled to sell into NIE. Accounting separation was also mandated for the separate businesses, transmission, distribution, PPB and retail supply. This structure was seen as transitional to a more competitive system for bulk electricity, which was scheduled to come on stream by 1998, being the date for the earliest cancellation of the existing power purchase agreements. The PPAs were expected to run to the end of their remaining existing life, with the earlier ones due to expire between 1997 to 1999, and with the most recent PPA due to expire in 2024. The PPAs were all based on two part pricing, involving capacity or availability charges and energy charges, with the capacity element subject to “take and pay” conditions. Many of the PPAs, however, contracted on vesting, carried clauses which allowed the Regulator to cancel them before their expiry dates providing some flexibility for the introduction of the competitive bulk electricity market in 1998. NIE was given the only public electricity supply licence at vesting. Since then second tier suppliers have been allowed to sell in the liberalised or large end user market. NIE had initially been interconnected to the Republic of Ireland. The interconnector was destroyed in 1973, but was restored and reactivated in 1995. Additionally, a 65 Km 250 MW interconnector now links NIE with Scotland. The interconnectors which links NIE with the Electricity Supply Board of the Irish Republic has enabled the two countries to share spinning reserve and to trade when the marginal cost of either system is different from the other. There is also a half hour difference in the evening peak of the two systems. 143 A regulatory framework involving a single regulator was established for the electricity and gas industries and a Director General of Electricity and Gas and an Office of Electricity and Gas were established. The pricing structure consisting of availability payments and energy payments resulted in more than 50% coming from availability payments. Increased levels of investments, in effect increased efficiencies resulted in higher availability charges. The introduction of a viable competitive market for the relatively small Northern Ireland electricity market, however, has proven to be an illusive objective, with the result that the highly monopolistic structure, which prevailed over the period, had come to deliver over priced bulk power. The real price per kWh increased by 2% between 1990 and 1996, compared to a real price decline of 11.6% in the England and Wales market and this is despite important efficiency gains by the generators33. The reason for this state of affairs is that of lack of sufficient competition in the market and more than generous price increases by the Regulator. NIE’s electricity prices were 23% higher than the England and Wales prices in 1996 and by 1998 the difference had widened to 42% because of the lack of competition in the generation market and the protected long-term contracts market. In July 2000, 26% of the market in generation and supply was opened up to users with annual capacity of 2.5 GWh. Both Scotland and Northern Ireland have seen significant increase in natural gas as fuel source from conversion of oil stations. The electricity market Directive of the European Union, which is an authorisation procedure by which new entrant generators may enter the bulk electricity market, came into operation in 1999. Not only are eligible customers (2.5 GWh and over)) able to buy from suppliers and hence the generator of choice, suppliers are also able to buy from generators in the other markets of the EU. NIE has responded to the Directive by auctioning off some of its excess capacity to second tier suppliers and by 2001 some 334 MW contracted at privatisation were released as virtual independent power producers. Competition is also expected to improve from the upgrading of the Scottish/Northern Ireland interconnector to 1,400 MW by 2002. With the upgrading of these twointerconnectors, capacity will amount to 80% of the Northern Ireland peak demand, compared to fewer than 10% in the UK34. Interconnected capacity is, therefore, expected to have a major impact on competition in the two Irish markets. 144 The British reforms of the 1990s, merely transferred monopoly rights from the public to the privately operated NIE, with the net effect that prices in Northern Ireland have been driven to become one of the highest in Western Europe. With the EU market liberalisation Directive, Northern Ireland can now expect to see more intensive competition and prices driven down to levels converging to England and Wales, especially after 2003 when the existing set of IPPs under construction come on stream and the new England and Wales Trading Agreement comes into operation35. These developments are having the effect of radically changing a small system into a Scottish/Irish market; eight times the size of Northern Ireland. Bulk Electricity Market – The Pool Electricity system as explained earlier is characterized with strong vertical economies especially between generation and transmission. Under the vertically integrated franchised monopoly structure the traditional way of dealing with this relationship has been internalisation. With disintegration, which follows from unbundling, a solution had to be found to address the issue of coordination. The solution of the British has been a contractual approach to the externality problem, represented by compulsory pooling agreements. In this way, participants in the system seek to coordinate their behaviour contractually, rather than through the command and control model as under the franchised vertically integrated system. The contractual approach opens the system to horizontally independent generating companies, competing for bulk electricity supply. There is, however, a paradox. Competition in the market requires participating firms to behave independently, whereas the pool arrangement implies explicitly or implicitly, collusion through the various interutility or interface agreements. In one measure, inter-firm coordination is needed to counteract the internalities associated with the electricity system’s disequilibrium (but not inter-firm cooperation or collusion to counteract competitive profit maximising behaviour), hence Joskow and Schmalensee (1993)36 state that the power pool creates strong tensions between cooperation and competition. The Pool allows price competition and diminishes some of the problems of long term contracting; however, as with the situation with the single buyer model, it introduces poor risk profiles through the volatility of spot prices, which is inevitable. 145 The Pool, therefore, is the main area in the restructured electricity system where competition was expected to take place. As explained earlier, the original intention was to have a “two sided” market, with generators placing offers of minimum prices for supply and suppliers and large end users placing bids of maximum price for purchases. As pointed out earlier, also the double sided pool had to be abandoned six months before vesting day because of problems with the computer software; the result was that the traditional CEGB dispatching software had to be adopted and its limitation was that it could only accommodate a “one sided” Pool, with only generators placing bids into the market.37 The Pool required all generators exporting 50 MW on the system to hold a generators licence and to bid its output via what is in effect an open commodity market. Initially, the argument was that contracted power did not need to bid into the Pool to operate; it was feared, however, that such contracted power would work to force spot power off the system, especially where transmission capacity is tight. The pool was therefore, made compulsory for all licensed generators wishing to trade in the new electricity market. The Pool, which is an unincorporated association of members, decides how the market is operated and how the rules should change. No detailed direct regulatory powers were given to the regulator; the DGE, and what regulatory powers existed took the form of imposition of obligations on licensed generators wishing to participate in the wholesale electricity market and the instrument for this is the Pool and Settlement Agreement38. The Regulator’s role is limited essentially to that of being the final arbiter in cases of disputes and rule changes and his decision is binding. Governance is facilitated through a ten member Executive Committee; five representing generators and five representing suppliers. The National Grid Company, which owns the transmission system, has several roles. It is the systems operator (dispatcher of power), the market operator (calculates the prices) and the settlement payment administrator. Each generating unit is required to declare by 10.00 hours each day, its availability the next day, together with the price at which it is prepared to generate for each and every half hour time slot. The units are then called to generate, or dispatched by the systems operator, the National Grid Company in ascending order of price or economic merit order. At the same time, all suppliers are required to submit demand estimates at each transmission supply point (or node) from which they intend to 146 draw power, also for each and every half hour of the following day. NGC is in effect the agent of the Pool and carries a feature of centralisation of all transmission activities. In New Zealand the transmission lines business (transport of high voltage electricity) was separated and made neutral to the new system to reduce market power and a separate “not for profit” organisation was established to handle market operation and settlement administration. NGC then runs a computer plant-scheduling programme, which seeks to minimise systems generating costs over the next day in terms of the price bids. At this stage transmission constraints are ignored. The most expensive unit dispatched in each half hour, clears the market and in principle sets the system marginal price (SMP). The SMP covers the average starting up cost and its no-load price, plus its incremental price of running for the clearing plant. All generators including the clearing generator then receive the clearing price (a uniform price) and not their bid price. This price is calculated on the basis of a revised unconstrained schedule. The system is therefore, not the typical auction market of “pay as you bid”. Additionally, there is another feature of the pricing structure, designed to provide an incentive for having generating capacity available whether or not it is dispatched. The capacity element is given by LOLP x [(VOLL – max (SMP)] where LOLP is the loss of load probability, the risk that demand will exceed capacity and VOLL is the value of lost load, which is set administratively (and indexed to inflation) to reflect the cost of demand exceeding supply. VOLL is intended to be a measure of the economic cost of not supplying. LOLP is the probability that the amount of power bid will prove insufficient39. The combination of the SMP and the capacity charge gives the pool purchase price (PPP) and this is calculated a day ahead and published every day in the UK Financial Times (a daily newspaper). PPP = SMP + LOLP (VOLL – SMP). All companies buying from the Pool pay a pool-selling price (PSP) for their metered demand, which is adjusted to take account for average transmission losses in each half hour. This additional variable is known as “uplift” and incorporates charges for ancillary services, which are needed to ensure that the system remains, balanced and secure. The uplift was originally charged out to all consumers responsible for constraining on more expensive plants, rather than to the transmission operator. Subsequently following an enquiry the uplift was allocated between the consumers and the transmission company. 147 If a generator offers a price that is too high it may not be dispatched and if it is too low it may be dispatched at times when the spot price is below its real cost. Therefore, there is a price risk that in any single half hour time slot when the plant is running that the market price may be higher or lower than expected. The generator can never be sure what price will clear the market. There is also a quality risk in that variation in market conditions may affect the output of the generator. Changes in spot price in some time periods may require the generating plant to run for more or fewer hours than expected. There is also a fuel cost risk and this lies largely outside the control of the generator. Fuel price risk is the variation in the cost of source fuel and could have the effect of changing the number of hours the plant runs, the net revenue earned and its variable cost. The final risk is availability risks and like fuel price is outside the control of the generator. Even if the generator has a good idea of the pattern of demand and knows the fuel price, there is no guarantee that the generator will be available when it is required to be dispatched and in so doing miss the opportunity for production. An important feature of the spot market price is that it is exogenous to the generators’ cost, and this provides a strong incentive to increase productive efficiencies and reduce cost in the short run and in so doing maximise profits. Over the long run the sum total of such cost reduction allows the generator to bid lower prices and hence lower system marginal cost (SMC), which when passed through the market should translate into savings to consumers at lower prices, i.e. allocative efficiencies. The net effect of the almost real-time pricing has been price volatility, sometimes by as much as a ratio of 3:1 over the course of the day and still further volatility in peak periods. These “spikes” in prices have been a cause of concern and is not welcomed by either buyers or sellers. In order to minimise the effects of the volatility in the spot prices, participants in the market enter into short and long-term contracts, thereby making the resultant capacity and energy prices more predictable. These agreements are known as “Contracts of Differences (CfDs)” and typically involved a “strike” price (an agreed price per kWh) for a specified quantity over a specified period of time. If the spot price is below the strike price for any half hour the buyer (supplier) pays the generator the difference and conversely if the strike price is below the spot price the seller 148 (generator) pays the difference to the supplier. All contracts must go through the Pool, hence the CfDs are therefore financial instruments with the objective of hedging risks and does not affect the physical transfer of electricity. CfD’s are usually fixed time contracts and are expected to reflect expectations in the spot market price. In addition to the CfDs, a small market developed during the final years of the Pool’s operation for foreword trades. Littlechild (1998)40 claimed that with the introduction of the Pool, competition was facilitated in the bulk electricity market at several levels. First, the opportunity for product market competition was presented between the Bertrand duopolies at the mid-merit level (60% of the bulk electricity market). Second, the interconnectors (imported energy) were able to operate their connectors at full capacity, most of the time reflecting an increase in their output by about two thirds (market share increased from 3.5% to 7.5%). Third, the nuclear plants increased their output by 75%, from increased efficiencies and new capacity. Fourth, entry competition was intensified. New entrants’ fuel-efficient plants, often in joint venture partnership with the regional distributors, progressively came to account for the greater portion of sales. Three additional large players had emerged by 2000; Eastern TXU, AES and Edison Mission. By November 2000, AES had come to set Pool prices 32% of the time. At the same time PowerGen and International Power/Innogy’s influence on price setting had significantly declined and when combined they were only able to set prices 25% of the time. Fifth, the two incumbent coal fired generators, not only disposed of 18000 MW of their coal facilities but in addition 11000 MW of coal fired and 4200 MW of oil fired, being inefficient plants were closed and in part replaced by fuel efficient CCGT plants. By 2000 the original duopolistic market structure had been dismantled. Littlechild’s analysis further showed that the Herfindahl market concentration index, which is a measure of competitive activity, had increased twofold41. Although it was envisaged that most trade in the exchange would take place through the pool spot price, in practice over 90% of electricity sales came to be purchased under contract at fixed prices. As with financial and commodity contracts, trade in electricity contracts came to take a variety of forms, from bilateral negotiation between parties to trade in transparent markets with independent traders. Government determined the initial vesting contract structure. These contracts from the early 1990s covered most of the output supplied to the franchised or captive customers. In addition to the vesting power contracts there were “back to back” coal contracts between the two coal fired generators and British Coal. 149 These contracts were introduced to provide a certain degree of predictability in the transitional phase of the market development, and to cushion the effects on the coal industry. The vesting power contract prices were, however, above the pool price and the coal contract prices were also well above the international prices for coal. This not only facilitated the continued cross-subsidy to the coal industry, as these costs were passed on to the captive customers, there was a distributional transfer in favour of the shareholders of the two duopolies at the expense of the consumers. Voluntary contracts or CfDs supplemented these vesting contracts. As outlined earlier they were designed primarily to hedge price risks. Voluntary contracts typically varied from one week to one year, but could be for a particular time of day or for periods lasting several years. They were expected to shadow the spot market prices. The Government’s decision to restrict consent on the building of new gas fired power plants only served to restrict new CCGT entrants to the market. Government’s position is that distortion in pool prices has disadvantaged coal, although no conclusive evidence had been introduced to support this position. The restriction as stated earlier merely served to increase the disposal prices of the coal fired plants in 1999/2000. The UK electricity market has been criticised as being biased to favour base load plants and as a result most new plants, which came on stream after 1990 were built to run base load energy, as the structure of prices in the market made this market solution the most profitable. The new CCGT lower operating cost plants more or less created a situation in which the older and less fuel-efficient coal fired plants became mid-merit plants. However, as more and more coal fired plants are retired from the system and gas fired plant capacity is increased, its share of the market will increase to the point where gas fired plants will also have to operate in the mid-merit market segment. Both the CCGT plants and the nuclear plants came to monopolise the base load market. With the nuclear plants as “must run” plants, and the CCGT plants carrying 15 year take and pay contracts, their marginal cost was almost zero, with the effect that they were able to bid into the Pool at prices close to zero, knowing that they would be paid at the higher pool clearing prices. A number of 150 merchant-IPP plants have, however, started emerging with more equitable risk sharing provisions, the effect of this is that the scope for competition will be further enhanced. Additional anti-competitive features were either built into the system or emerged later and these features came to distort the market. A major problem has been that the Bertrand duopolies have been able to exert considerable market power and influence prices in the Pool, almost over the entire life of its operation. The average SMP and PSP steadily increased in real terms from 1990/91 to 1993/94. This reflected the market power of the duopolies and the artificiality of the pool price in the early years, which in turn reflected the influence of the vesting contracts. In the first year there was a 22% increase in SMP, partly from the higher uplift and capacity charges. Further increases in the level of capacity payments, as well as an increase in the ratio of peak to off-peak prices were also experienced. Littlechild (2000)42 commented that: “the two duopolists were able to increase average pool prices for several years from 2.5p/kWh (3.9 US cents) in 1990/91 to 3.15p/kWh (about 5.2 US cents) in 1993/94 (December 1999 prices). In the first year or two, this increase may have reflected an attempt by generators to redress an artificially low pool price. ------------However, the ability to secure repeated price increases demonstrated the significant market power of the major generators”. In 1993 the duopolies were able to set the pool price 90% of the time43. This led the Regulator to intervene by threatening to invoke a reference to the MMC. The result was a voluntary undertaking by the two incumbent generators not to bid a price into the Pool that would be fixed above a price cap. The price cap specified a time-weighted level of 2.4 p/kWh and a demand weighted price of 2.55 p/kWh (both in October 1993). The price cap agreement was also associated with a voluntary agreement as stated earlier, whereby the two incumbent generators also agreed to divest 15% of their coal-fired capacity. The price cap lasted for the period 1994/95 and 1995/96 and was imposed to give the market an opportunity to increase its level of competitiveness. The result was that between 1993/94 and 1995/96 there was a reduction in the average SMP. 151 Fig. 21 Source: Richard Green, “Markets For Electricity in Europe” Oxford Review of Economic Policy, Vol. 17, No.3 (Autumn 2001), p.333. The effects of the price cap, competitive pressures from new entrant CCGT plants and improvements implant efficiencies temporally resulted in a decrease in prices. In fact prices declined over the period between 1993/94 and 1996/97 from 3.15p/kWh to2.8p/kWk, (or 4.2 US cents) Despite the reduction in market share of the two incumbents to less than 50% in 1998, SMP in the Pool was still established 66.6% of the time by the two incumbent generators. Pool prices were still 10-20% above the prices of the latest natural gas fired entry plant. Figure 21 above shows the movement of the price components over the life of the pool, 1990/91 to 2000/01. Despite the reduction in fuel cost by over 50% and the substantial reduction in staffing levels and improvements in plant efficiencies, Pool prices were higher in 2000/01 than at vesting. 152 Critique and Changes to the Pool After 2000 In summary the following criticisms have been levelled against the Pool: First, the pattern of prices in the Pool did not show any significant decline in the initial five years and this is despite the limited growth in demand, excess supply, and 50% fall in coal prices. To the extent that prices were been higher than that which would have prevailed in a competitive market, an incentive was provided for excessive entry and this has favoured natural gas over coal as a fuel source. The gas industry, therefore, benefited at the expense of coal. Second, bids into the Pool have not been reflective of cost. Movements in bulk electricity prices have not fallen in line with reduction in costs. Wholesale spot prices have remained largely unchanged whereas fuel cost and capital cost of generation have each fallen by over 50%. The Pool has also been prone to price spikes. It is common practice of analysts to compare pool price over the decade and to imply that there has been no reduction in the effective price of bulk electricity. The effective price of bulk electricity is set by interplay of contracts and the average prices from the Pool. The contract prices at vesting were well above Pool prices in 1990/91. There has however been a reduction in the differential between contract and pool prices since 1990/91, with the net effect being an appreciable decline over the decade of prices in the Pool. Despite this decline these prices were still above the average price of new entrants to the market during the period under review 44. Third, the Pool trading arrangement facilitated the exercise of significant market power, with the net effect that there have been distributional transfers in favour of shareholders at the expense of consumers. Despite the fact that there is much less market concentration, pool prices were still exposed to manipulation. Pool prices have not been a good signal of marginal cost, because of the market power of the duopolies during most of the 1990s. In a normal competitive market, supply and demand interact to set prices. In the “one sided” pool arrangement a uniform market clearing prices is established, with the result that buyers have little or 153 no opportunity to exercise bargaining power to bring pressure on prices. In other words, the system provided limited or no demand side pressure on prices. Lack of demand side bidding stifles the development of the market and had the effect of a one sided market. The complexity of the price discovery process made it difficult for traders to understand how electricity prices are likely to behave and the fact that most trade came to be carried out through contracts, where prices are not public, leads to questioning of the transparency claim. The structure of bids were intended to reflect the underlying cost of the thermal plants; instead bids have tended to deviate from cost and more than anything have reflected commercial objectives. The complexity also encouraged gaming of the market to the advantage of the duopolies. Fourth, LOLP is of limited value as a short-term signal to encourage generation or demand participation to respond to rapidly changing conditions, as a change in availability of a plant has to last for 8 consecutive days before it had an effect on LOLP. The capacity payments have tended to provide a means for generators to manipulate price, rather than to act as a signal for new investment in capacity. The level of payments can be increased sharply by withholding capacity. Fifth, the price setting arrangement has inhibited the development of a derivatives market and reduced liquidity in the contracts market. This has resulted in very high margins on financial contracts at further cost to consumers. Sixth, the Pool governance structure has been considered to be too inflexible and consumer’s influence has been negligible. The Regulator had no power to initiate changes to pool rules, even when circumstances dictated such changes. The rules were designed to protect the minority interest against the majority. Potential changes were against the interest of some players; hence it was difficult to change the rules. Seventh, the compulsory nature and heavily centralised pool tends to reduce the freedom of participants’ commercial activities in the market. The arguments advanced by supporters of the Pool are that it has fulfilled its original objectives. In the first place there was always enough generation capacity to meet demand. There was never any shortage of capacity. Second, the market during its 10 year life of operation provided a stable 154 commercial environment and this has acted as an incentive for new investments and the introduction of new technologies. Third, with the new entrants there has been increased competition in the bulk electricity market. Fourth, increased competition and the application of new technologies have lead to reduced production cost. Fifth, there has been increased diversification of fuel sources. Sixth, the major reductions in staffing levels, which took place, resulted in increased efficiency and increased productivity. Most important, the Pool facilitated the introduction and development of competition in retail supply market with the ultimate outcome of significant reductions on preprivatisation prices, amounting to over 35% in real terms over the decade of the 1990s and this has benefited all consumers. Despite the view in some quarters, that changes could be made to the Pool to overcome its main shortcomings, such as reform of the governance structure to allow the option of trading outside the Pool, the Office and Gas and Electricity Markets in (1999)45 reported that:: “There is no simple way to modify the Pool to overcome its weaknesses, any worth while reforms would require the removal of compulsory membership, the introduction of firm offers, the incorporation of demand – side and implementation of “pay-as-bid” pricing. These are very substantial changes and would, for example, necessitate the introduction a balancing mechanism”. There were also new developments internationally in electricity market arrangements, which came into being after the introduction of the UK Pool. These developments OFGEM stated followed market based solutions for all elements of the electricity trading arrangement, and for market based solutions to ensure the security of supply, rather than administered arrangements and in so doing, provided greater choice and flexibility in trading mechanisms and contractual forms. The decision was, therefore, taken by the UK Government to replace the Pool with a bilateral contracts market, a balancing spot market, along with a series of futures markets and with less emphasis on central direction of the systems operator. The objective being to provide for more competitive pressure in the exchange, more choices, eliminate a uniform price set by one single marginal generating plant; encourage development of better risk management skills and provide more scope for competition in the retail supply market . 155 The programme of work to implement the new trading arrangements, (NETA) started in 2000, being a feature of the Utility Act of 2000. The new trading arrangement for bulk electricity which eventually came into being in 2000, provided for a series of markets involving forward markets, allowing bilateral trade ahead of time, at prices bilaterally negotiated between individual traders and brokers; a short-term power market which operates 31/2 hours before real time, and a balancing market. In the last 31/2 hours before real time operation, NGC the transmission operator runs a balancing mechanism to ensure stability of the system. Bids and offers are accepted, either to increase generation or reduce consumption. Each accepted trade is paid its own bid or offer, instead of the single uniform marginal cost price as practiced under the Pool. The balancing mechanism is also adopted to resolve transmission constraints. A system of tradable access rights has been proposed to deal with congestion on the line and would involve generators paying for rights in an exporting area, but could be paid for them in an importing area. In the bilateral contracts market, traders will be able to enter into commitments well in advance and in so doing give traders greater opportunity to hedge price risks. It is also possible to sign contracts in the short-term market or delay trading until the short-term market opens. Traders are required to notify a new agency Elexon, of their electricity contracts, which are compared between their metered demand and output. Where there are imbalances between these contracted positions and their metered positions, these then have to be “cashed out” at punitive prices. Companies needing to purchase power have to pay the system buy price (SBP), which is the average of the price that NGC paid to buy power in the Balancing Market. Companies needing to sell power do so at the system sell price (SSP), which is the average of the prices NGC receives for selling power in the balancing market46. The verdict was still out at the beginning of 2002 as to whether moving from uniform pricing to bilateral trading would have the effect of reducing the market power of generators to manipulate prices. NETA, however, has already led to a significant increase in trading; whether this is good or bad remains to be seen. What is clear, however, is that the unbundled structure and the associated competitive bulk electricity market has ushered in a fundamentally new industry for the electricity 156 supply system and this is now replicating itself globally in both developed mature markets and in weaker developing markets. Newbery (2000)47 states that in 1997 over 51 countries from 61 studied had been reforming their markets and with vertical separation in place or planned for 27 of the countries. The English model of structural reforms, involving vertical and horizontal unbundling and which is the second of the two first generation reform models, Chile being the other, has provided the template for reforms in both mature markets and developing countries. 157 End Notes 1. Jaime Millan, The Second Generation of Power Exchanges: Lessons from Latin America, Washington, D.C., Inter American Development Bank (2001), p.3. 2. John E. Besant-Jones, The England and Wales Electricity Model – Option or Warning For Developing Countries, Washington, D.C., World Bank (1996), p.1. 3. Steve Thomas, “The Privatisation of the Electricity Supply Industry”, in The British Electricity Experiment, Privatisation: The Record, the Issues, the Lessons, ed., John Survey, London, Earthscan Publishers (1996), p.48. Michael Beesley and Stephen Littlechild, the architects of UK style utility regulation inspired by the thinking of the Austrian school of economists developed the concept of incentive regulation, whereby monopoly utilities are allowed to raise prices by the general rate of inflation, adjusted for an efficiency factor. 4. Richard Green and David Newbery, “Competition in the British Electricity Spot Market”, Journal of Political Economy, Vol. 100, No.5 (1992), p.930. 5. George Yarrow, “Does Ownership Matter”, in Privatisation and Competition, A Market Prospectus, ed., Cento Veljanovski, London, Institute of Economic Affairs (1989), p.53. 6. Walter J. Primeaux, “Electricity Supply: And the End of Natural Monopoly, in Privatisation and Competition, a Market Prospectus , ed., Cento Veljanovski, London Institute of Economic Affairs (1989), p.13. 7. Stephen C. Littlechild, Privatisation, Competition and Regulation, London, Institute of Economic Affairs, Occasional Paper 100 (1999), p.23. 8. Graham Ward, Power to the People: a Decade of UK Electricity Privatisation, London, PriwaterhouseCoopers (1998), p.2. 9. Department of Trade and Industry, White Paper: Privatising Electricity: The Government Proposal For Privatisation of Electricity in England and Wales, London, HMSO (February 1998). 10. John Vickers and George Yarrow, Privatisation: Economic Analysis, London MIT Press, (1988). 11. CEGB was the state owned integrated generation and transmission company. 12. Vickers and Yarrow, op.cit. p.311. 13. Alex Henney, Private Power: Restructuring the Electricity Industry, London Centre For Policy Studies, Policy Studies, No. 83 (1987). 158 14. Thomas G. Weyman-Jones, “Regulating the Privatised Electric Utilities in the UK”, in The Political Economy of Privatisation, ed., Thomas Clarke and Christos Pitelis, London, Routledge (1993), p.100. 15. Cento Veljanovski, “Privatisation Monopoly Money or Competition”, in Privatisation and Competition: A Market Prospectus, ed., Cento Valjenovski, London, Institute of Economic Affairs (1989), p.34. 16. HMSO, The Report of the Committee to Review the National Problem of The Supply of Electricity, London, The Wier Committee, (1925). 17. David Heald, “The Economic and Financial Control of UK Nationalised Industries”, Economic Journal, Vol.90, No. 338 (1980) 18. George Yarrow, “Privatisation, Restructuring and Regulation: Reform in Electricity”, Privatisation and Economic Analysis, ed., Mathew Bishop, John Kay and Colin Mayer, Oxford University Press (1994), p.81, 19. Ibid, p.68. 20. Colin Robinson, “Privatising the Energy Industries”, in Privatisation and Competition, a Market Prospectus, ed., Cento Veljanovski, London, Institute of Economic Affairs (1989), p.114. 21. Pauline Beato and Carmen Fuente, Rail Competition in Electricity, Washington, Inter American Development Bank (1999), p.9. 22. Steve Thomas, “The Development of Competition”, in The British Electricity Experiment, Privatisation, the Record, the Issues, the Lessons, London, Earthscan (1997), p.50. 23. David Newbery, Guidelines for Private Sector Involvement in Electricity Supply Industry in Eastern Europe, Cambridge University, Department of Economics (1996), p.19. 24. Joseph Schumpeter, Capitalism, Socialism and Democracy (5th Edition) London, Allen and Unwin (1976). 25. Michael Reidy, “Privatisation, Regulation and Electricity Market”, in The British Utility Regulation: Principles, Experience and Reform, Oxford University Press, (1995), p.127. 26. Graham Shuttleworth, “The Electricity Industry 1997 – 1998”, in Regulatory Review 1998/99, Bath: England, Center For The Study of Regulated Industries, (1999), p.6. 27. Peter Boulding, Whither Regulation? Current Developments in Regulated Industries, London, Center for the Study of Regulated Industries (1997), p.16. 28. David Kennedy, Vertical Structure of The English Electricity Industry, London: Centre For the Study of Regulated Industries, Technical Report 6 (1996), p.14. 159 29. Colin Robinson, “Profit, Discovery and the Role of Entry: Case of the Electricity”, in Regulating Utilities: Time For a Change? ed., Michael Beesley, London, Institute of Economic Affairs (1996, p.135. 30. Newbery, op.cit. p.8. 31. Electricity Association, The UK Electricity System, London (1999). 32. Stephen Littlechild, “Generation and Supply of Electricity: The British Experience”, in Competition in Regulated Industries, ed., Dieter Helm and Tim Jenkinson, London, Center For the Study of Regulated Industries (1998), p.209. 33. Mathew Webb and Michael Bell, Reform Cases in Electricity: The UK Experience, Dar es Salaam, Tanzania, Tanzania Electric Utility Seminar (2000), p.9. 34. Douglas Mclldoon, “Liberated by Brussels: Cross-Border Electricity Market in Ireland”, in Regulatory Review, 2000/2001. ed., Peter Vass, Bath England, Center for the Study of Regulated Industry (2001), p.33. 35. The Coolkeeragh Plant for example in its search for higher efficiencies embarked on conversion of its oil fired plants into a 400 MW CCGT plant. The competitive pressures have provided strong incentives towards more efficient plants and the lowering of production costs. 36. Paul Joskow and Richard Schmalensee, The Markets for Power: An analysis of Electric Utility deregulation, Cambridge, Mass, MIT Press (1993). 37. David Newbery and Richard Green, “Regulation, Public Ownership and Privatisation of English Electricity Industry”, International Comparison of Electricity Regulation, ed., Richard Gilbert and Alfred Kahn, Cambridge University Press (1998), p.61. 38. George Yarrow, 1994, op.cit. 39. Steve Thomas, op.cit. p.80. 40. Littlechild (1998), op.cit, p.194. 41. Ibid. p.196. 42. Littlechild (2000), op.cit. p.16. 43. Green and Newbery (1998), op.cit. p.90. 44. Littlechild (2000), op.cit, p.16. The two incumbent generators; National Power and PowerGen, along with Eastern, accounted for the setting of prices by over 85% of the times in 1998. 45. Office of Gas and Electricity, The New Electricity Trading Arrangements, London (July 1999), p.30. 160 46. Richard Green, “Markets For Electricity in Europe”, Oxford Review of Economic Policy , Vol.17, No. 3 (2001), p.341. 47. David Newbery, Privatisation, Restructuring and Regulation in Network Industries, Cambridge, Mass, MIT (2000), p.200. 161 Chapter 4 British Electric Utility Regulatory Reform The Case against Rate of Return Regulation Regulatory reform was never a part of the Thatcher administration’s privatisation programme. The first set of industries, which were privatised steel, automobiles and oil were expected to face either domestic or international competition, hence it was felt that expansion of the role of the Office of Fair Trading (OFT) would have been sufficient to address market power issues arising from a changed industrial structure, OFT, however, declined to take on the responsibility. When the realisation dawned on the policy makers that the likely outcome of privatisation was that of an unregulated utility, several policy makers and academics tracked across the Atlantic to the US, the only country with a substantial history of independent regulation of privately owned utilities, seeking insights from US experiences. In fact up until the 1980s, American academics more or less exercised a monopoly on regulatory thought. Public Utilities Commission (Public Service Commission) the name given to the 49 state regulatory bodies had become synonymous with the more generic term of regulatory agency. The British also realised that if public utilities were to be successfully privately financed, regulation, which credibly satisfies the demands of both consumers and investors, was needed. If investors are fearful for the security of future returns, then it is unlikely that they would come up with the unprecedented levels of capital needed to finance and modernise the utilities. Earlier experiences in Britain as shown by Foreman-Peck and Millward (1994) 1 in the case of National Telephone 2 Company and Spiller and Sampson (1994) in the case of Jamaica Telephone Company in the 1960s, clearly demonstrated that privately owned utilities will refuse to provide the needed investments if adequate guarantees on returns are not provided, especially when nearing the end of the franchise period. For the American’s, the regulatory process was seen to be that of ensuring a balance between public interest and the interest of the investor. Public interest arose from the characteristics of natural 162 monopoly, information asymmetry and destructive competition. The regulator’s primary duty, therefore, was to protect the public interest, whilst providing the investor with a “fair” rate of return. US regulators had for over 100 years adopted cost of service, rate of return regulation (ROR) as the formula for establishing tariffs, with the institutional framework being that of a quasi-judicial commission, following procedures, which involved open public hearings3. Alan Walters, Mrs. Thatcher’s economic advisor was highly critical of the US approach to regulation, especially on the grounds that it was a form of taxation, with poor incentives for the utilities to operate efficiently and with a tendency to encourage capital-intensive solutions4. ROR regulation it was argued encouraged capital-intensive solutions when the rate of returns exceed the cost of capital (gold plating), the Averch and Johnson effect. It also results in allocative distortion when prices are set above average costs and not marginal costs. It is seen to be cost-plus pricing, as it seeks to recover total embedded cost, inflationary and does not provide incentives to the utility to reduce cost. The regulatory system in the US was developed to protect the interest of the investor against the interest of the public, Kolko (1965)5. Stigler (1971)6 argued that the system had been captured by the investor group. Munasinghe and Sanghvi (1989) 7 pointed out that the system came to protect the status quo and was a primary bottleneck to achieving significant efficiency gains in the US power industry. Distortion also tends to arise from the process whereby revenue requirements from new investments are front loaded, with the result that immediately following completion of a large base load electric plant and its incorporation into the rate base, tariffs rise sharply. Rates, therefore, tend to be high when capacity is substantially in excess of demand and visa versa, contrary to efficient pricing. The tribunal type open public hearing and the use of legal procedures, creating the need for each participant to engage lawyers to argue and support every decision, as if in a court of law served to create an adversarial process. The system had become too unresponsive to changes and unduly restrictive, where a departure from tradition is necessitated by technological changes or changes in the market, as has been the situations with the rapid developments in the telecommunication and electric utilities. Baldwin and C. McCrudden (1987)8 stated that: 163 “that although it is reasonable to expect trial type procedures to produce durable standards where issues do recur it is unrealistic to expect this when most cases are highly individual in character”. Decisions often were the result of compromises between conflicting interests on the Commission, which often lost sight of the broader public interest issues. Overall, the US style regulatory decisionmaking process is lengthy, and costly, rate decisions on average taking 12 months, is resource intensive; a highly skilled body of economists, financial experts and lawyers are required and the process is very expensive. Investment in US utilities is relatively risk free, because of the legally enforceable guarantees. The American regulatory system, however, offers an important advantage in that it provides for effective constraints against opportunistic behaviour on the part of the regulator or the state. It therefore, reduces regulatory risks and provides strong incentives for large sums of needed investment. It also provides for regulatory commitment; a guarantee that the investors immobile assets and sunk cost will not be expropriated (prices being set below marginal cost). Because of the long durability, non-transferability and asset specificity of much of electricity and other utility assets, the bargaining advantage for lower prices shifts to those whose interest it is to demand lower prices once the investment has been made. If the regulator or the government set prices at unremunerative levels the value of the investor’s assets is reduced and the investment is defacto expropriated. Regulatory commitment requires the respect for property rights and for prices to cover variable cost to ensure adequate production and that the return paid on capital is positive. This then calls for credible restraint against regulatory opportunism, which is all too familiar a problem in emerging and liberalising utilities markets. The regulator’s discretion must be constrained and the power of the government must be constrained from changing the regulatory framework through changes to the law, once the investments have been made. The problem of regulatory commitment is central to the design of new regulatory frameworks, and especially where there is an absence of a culture of independent regulation. The regulatory challenge for new and liberalising utility markets, therefore, centres on the creation of a credible framework, which satisfies the needs of the producer, the 164 consumer and the state. The state’s interest is to ensure adequate supply and security to meet economic and social development goals. In the case of America, the very strong regulatory contract derived from the constitution, which provides investors with various safeguards, for the protection of property rights; additionally, the well developed body of administrative law (the 1945 Administrative Act) prescribes the general rules of practice and procedures of agencies in relation to their conduct and the process by which decisions are made and challenged. Much of US regulation has been a response to investor owned utilities abusing their monopoly power at the expense of consumers. The remedy by the independent judiciary in the US has been to allow the utility to charge a price which just covers the cost of service and provides a “fair” rate of return upon the “value” of “employed assets” A series of land mark court decisions, or judicial precedents defines, “fair” rate of return, “value”, and “employed capital” and provides procedural fairness in the allocation of risks. British Approach to Utility Regulation Professor Stephen Littlechild, a Professor of Applied Economics at Aston University, England, the first electricity regulator, was commissioned in the early 1980s to develop the regulatory framework for the first privatised utility that of the telephone industry . He was the architect of the new British approach. Littlechild (1983)98 rejected the fundamental notion upon which US Utility regulation is based and challenged the approach that the utility industries have to be monopolies. Littlechild’s (2000)10 new regulatory structure departed radically from the US approach and in his view regulators should seek to: “promote competition where competition seems possible to do so, thereby seeking to maximise the disadvantages identified by Hayek and Friedman with regulated industries”. Littlechild sought to confine regulation to the non-competitive core of the utility industry, that of the network and to leave competition to restrain prices in the competitive sector thus providing 165 incentives and avoiding the complexity of the US system. Where competition did not exist public regulation would ensure that privatisation did not simply mean replacement of private monopolies. The long-term challenge posed by British approach to regulation from the point of view of public policy was how to convert much of the nationalised utilities into a private, competitive and unregulated industry. This is in sharp contrast to the US approach, where regulation has operated to suppress competition. Regulation in Littlechild’s (1999)11 view was to be temporary and was to remain until competition emerged. In the case of electricity, competition in supply was an entirely new concept, although Chile had already introduced a rudimentary form. Littlechild’s solution was to adopt the earlier precedent of telecommunications regulation, which provided for the right to free access to the network segments or the natural monopoly elements of the industry. In his view the primary role of the regulator, therefore, was to facilitate the competitive transformation process. The 1989 Electricity Act, for the first time established the statutory duty on the part of the regulator to facilitate competition. This is in contrast to the US where the duty of the regulator is to prevent entry to the industry and hence suppress competition. The traditional economic concern with monopolies has been that of allocative inefficiency, arising from the monopolist rent seeking behaviour of restricting output below competitive levels and charging high tariffs and in so doing reducing welfare benefits to society. The unconstrained monopolist also has an incentive to engage in price discrimination and charge users “up to their willingness to pay”; and increase the rents that can be captured12. The unconstrained monopolist, however, can charge well above their long run marginal costs of supply, thereby extracting a significant proportion of consumer surplus as economic rent that is profits beyond those, which would be required to induce the given level of output. Regulation of prices in its simplest form, therefore, is reduced to that of allocating rents between producers and consumers, how to ensure the producer receives a “fair” return on investment, whilst protecting consumers against “unfair” prices. It is not only consumers that have an interest in the allocation of rents, government itself, also has a strong interest. Government faces strong incentives to allocate rents in a way that maximises its utility. Powerful pressures come from populist outcry to intervene in pricing and investment decisions to achieve distributional and other social and political goals. 166 When government intervenes through cross-subsidies and divorces prices from long run costs, such as mandating uniform pricing or establishing universal service obligations, the allocation of resources are distorted. In a competitive market it is not possible to maintain cross-subsidy policies. Competition or the threat of competition from potential new entrants creates a powerful disciplinary pressure on incumbents in the market. It is the possibility to use the threat of potential competition, which led New Zealand to avoid the introduction of specific industry regulatory laws for the privatised utilities. In electricity, competition can be extended to the retail sector, allowing retail wheeling or the transport of low voltage electricity across the wires of the franchised utility operator. Competition not only eliminates concerns about monopoly pricing, its spurs productive efficiency – short term or static efficiency and long term or dynamic efficiency13. Firms operating under cost of service, rate of return regulation or as public enterprises have very few incentives to be efficient. Under pubic interest theory private ownership and ROR regulation and public ownership are essentially one and the same in their effects; they do not provide incentives for efficient behaviour The British policy makers in their decision to depart from the well tried and tested US system of regulation needed to ensure that the new system, not only provided incentives for allocative and productive efficiencies, but also provided for regulatory commitment (Williamson 200114.) In the development of an electricity regulatory framework the policy makers followed essentially the same structure and procedural arrangements adopted for the earlier privatised telecommunications, gas and water utilities. Each industry, including electricity was allocated its own regulatory agency, instead of the US multi-sector cross-sectoral approach. Instead of a collegiate body as the decisionmaking authority, a single individual, a Director General was appointed, supported by an Office. Although the Office is technically within the Government, the regulator is not a civil servant and does not take directions from the portfolio minister, except in clearly stated circumstances laid down in the law; hence the view that the regulatory system is independent15. Kay (1996)16 stated that: “ it is preferable to give discretion and autonomy to an informed individual capable of balancing conflicting duties and interest rather than for prescription of detailed rules through a Commission”. 167 Prosser (1997)17 argues that the expertise of these new regulators gave them their legitimacy”. Young (2001)18 states that : “to the regulated firms the regulator represents the government and consumers, to the government they are ostensibly an independent go between and to the consumers and the public they are referees responsible for establishing a fair deal from the utilities”. In Britain the regulators are recognised as experts with considerable discretion to bargain with participants. The procedures are very informal with no requirements for court style hearings and the emphasis is on co-operation rather than legal confrontation in open hearings. The role of the court is more or less limited in the regulatory process to instances of judicial review, whereas in the American situation the courts play an important role in the appeals process. Finally, instead of profit controls, the British adopted price regulation in order to provide incentives for the utilities to operate efficiently. The Acts under which the various utilities were privatised specify the duties and powers of the regulator and the roles of other parties; the sector Minister, OFT, the Monopolies and Mergers Commission (Now the Competition Commission) and the environmental agencies. These powers have over the last 15 years been tested and clarified in various rulings. The process has also been evolutionary and reflects a balance between a well-defined regulatory contract, setting out precisely the nature and scope of regulation, whilst at the same time allowing the system to adopt and grow as necessary. It has been a balance between the advantages of regulatory certainty and the associated risks of allowing the system to respond to a changed environment. The regulatory legal framework consists of the privatisation legislation, which sets out the powers of the regulator, reserving certain powers for the portfolio minister. It provides for individual licences to be granted to the operators in the regulated industries. The licence sets out in more detail the relationship between the regulator and the operator. The privatisation legislation imposes a set of primary duties on the regulator, requiring the regulator to ensure that supply meets reasonable demand, that suppliers should be able to finance the provision of the services they are called on to supply and to promote competition. Supplementing these primary duties are secondary ones, calling for the protection of the interest of consumers, promoting efficiency and economy, safety, research 168 and development, protecting the environment and to give consideration to the sick, elderly, disabled, and rural consumers. Various aspects of competition policy also apply, with both the Director General of the OFT and the Competition Commission (formerly the Monopolies and Mergers Commission) also having jurisdiction in certain circumstances, making the structure extremely complex. These duties reflect a combination of economic and social obligations often mutually incompatible. The regulatory duties are not ranked, leaving the regulator with substantial levels of discretion. Wider aims such as public interests, as with the US system, are not mentioned. The portfolio ministers generally issue the licences, which are more prescriptive in terms of the conditions of service and duties. In some instances the power to issue licences is delegated to the regulator. In the case of electricity, licences are required for the generating companies, the transmission operator, independent power producers, and in the case of the distribution sector, public electricity supply (first tier) and second tier licences are required. The public electricity supply (PES) licence creates an obligation on the part of the distribution companies to secure bulk power from the most economic source and it restricts own generation, so as to prevent re-integration. The transmission licence regulates the National Grid Company, the transmission owner and provides for non-discriminatory access to the grid, and for the operator to schedule power stations in order of the lowest bid, as well as to run a settlement system. Generators, NGC and the Pool Administrator are required to sign a pooling and settlement agreement containing the relevant contractual obligations under which bulk electricity is dispatched and paid. Except for generation, control is placed on the average level of prices. There is also prohibition against cross-subsidy, a requirement for non-discrimination and set of conditions which seeks to ensure security of supply. Licences are for 25 years with an option for extension for a further 10 years and can be modified in certain circumstances upon agreement between the regulator and the regulated firm, subject to veto by the portfolio minister or upon reference to the Competition Commission. The licences are also revocable after due notice or on grounds of serious misconduct or failure to perform. The structure of legislation and licences was introduced to address a relatively unique feature of the British parliamentary system. Its un-written constitution, guarantees the sovereignty of Parliament, which theoretically, allows Parliament to enact and repeal laws as it deems fit. The unwritten nature 169 of the British constitution based upon given and accepted conventions, perceptively, fails to provide the legislative certainty ordinarily guaranteed by written constitutions of other countries such as the USA. The Primary legislation on its own is therefore vulnerable to opportunism and provides weak regulatory commitment. The licenses are legally enforceable instruments and the courts will uphold property rights, hence the licence provides what can be described as the regulatory contract. This regulatory commitment is reinforced in the licence and complements the statutory requirement on the regulator to ensure that the utility can finance their licensed activities. Although the regulator is said to be independent, in point of fact this is not entirely true. Apart from sharing some of the regulatory powers with the portfolio minister, this minister often has the power to issue the licences. In most instances, the responsible minister (including establishing the initial price controls) issues the initial licences. The responsible minister also appoints the regulator and technically the regulator accounts through this minister. There are also powers of intervention in certain circumstances, such as in takeover and mergers cases, power to veto modification by agreement and power of reference to the Competition Commission. RPI – X Regulation The major departure of the electricity regulatory framework from the earlier three privatised utilities is that for the first time the provision was made for the statutory obligation on the part of the regulator to promote competition in respect of the generation and retail supply. The network sector (transmission and distribution lines business), the natural monopoly segments were to be regulated. At one and the same time the regulator was required to discharge the functions of industry specific regulator, whilst at the same time police competition in generation and supply. Prossor (1997)19 states that Littlechild, as electricity regulator saw his job as follows: “to provide competition where feasible and sensible to do so, bearing in mind that it was not possible at the time of privatisation to move by a single step from stateowned monopoly to privately owned fully competitive industry. My task in part is therefore to help complete the transition, not merely to monitor competition but to actively promote it”. For Rees and Vickers (1994)20 the most important aspect of the new regulatory framework was regulation through price control, introduced as RPI-X, and requiring the average price charged to 170 fall each year by a factor “X” percent in real terms. In its basic form RPI-X requires that the price index for a defined basket of the firms regulated products and services should increase by no more than the rate of inflation, minus ”X” percent per annum for a period of years. The price of the regulated basket must fall (or rise if X is plus) in real terms each year. In the case of electricity the formula was varied to provide for cost pass-through for input factors that were outside the control of the regulated firm. The formula then became RPI-X+Y with “Y” being the cost pass-through component. RPI-X is less vulnerable to cost plus inefficiency and over capitalisation. The company has the right to share efficiency gains during the regulatory period and this provides the incentive for productive efficiency21. It is also possible to pass on some of the expected efficiency improvements to consumers when determining the level of X at the review period, therefore providing for allocative efficiency. Prices not only tend to be lower than under rate of return regulation, it allows the company the flexibility to adjust to the most optimal price structure, within the basket to market conditions, whilst prices outside the basket are left to the forces of competition. It is seen to be a simple formula to operate; however, over the years it has become more complex. It is more transparent and better focused on parameters of greatest concern to consumers with price information exogenous to the regulated firm. The problem of information asymmetry is significantly reduced and the incidence of regulatory capture minimised. The regulatory burden and cost is significantly reduced, as the regulator’s role in the annual price changes is limited to checking that the price increase is in line with the formula. It also overcomes some of the regulatory commitment problem, to the extent that the regulatory law limits regulatory discretion between price reviews. RPX-X is also seen to be less interventionist with less need for the regulator to probe into the firm’s day to day affairs. In setting the annual value of X, the government was largely concerned with the marketability of the shares of the companies; however, in the periodic reviews the determination of the value of X becomes the decision of the regulator. More and more the regulators have been focusing attention on both the rate of profitability over the previous period and the rate of return on capital on the succeeding review period, exposing RPI-X to the criticism that it is rate of return regulation every five years. The same set of information needed to determine the value of capital and the cost of 171 capital in rate of return regulation are needed, with the result that the regulator is faced with the same information asymmetry problems as under rate of return regulation. Additionally, the formula lends itself to yardstick competition where the regulator sets a price based on the average cost of a group of potential producers or an ideal producer. Each of the regulated firms has the incentive to produce below the average unit cost of the group or the ideal firm to make additional profit. Rationale for Excluding Generation from Regulation Generation was excluded from economic regulation on the theory that the two thermal generators would compete fiercely as Bertrand oligopolists and in so doing secure efficient pricing. Additionally, with entry into generation by the new CCGT players made comparatively easy from the modest scale and cost of entry and especially through the 15-year power purchase contracts, the market was made contestable. Vertical separation of generation from transmission and horizontal unbundling of generation, however, raises the question as to whether unbundling is sufficient to exclude the necessity of regulating generation. This unbundling question is even more relevant when one considers that a number of economists, Henney (1987)22 and Helm (1988)23 had not only argued for several competing generators to reduce market power, but for the regulation of all the sectors. Vickers and Yarrow (1988)24 and Green and Newbery (1992)25 did not see the number of generators at start as critical, so long as entry was free. Vickers and Yarrow also felt that all the sectors should, however, have been regulated. Green and Newbery did not see the duopoly structure as a serious entry problem; however, they expressed concern over the duopolies ability to exercise considerable market power without collusion by offering a supply schedule that is considerably above variable cost and to exploit the constraints on the transmission network, depending on the degree of market power in the regional sub-markets, and this is in addition to being able to support these strategies by outright collusion. The scope for the exercise of market power was seriously underestimated, based on the misconception that Bertrand competition is sufficiently competitive in a highly concentrated market. 172 This misconception was fully borne out by subsequent experiences and the resultant inefficiencies thrown up from the less than optimal structure at start. Government at the time had the option of giving the regulator the power to impose a price ceiling in the competitive sectors in the hope that competition would hold prices below the ceiling or subject the matter to competition law as is the case in New Zealand or provide for reference to the competition regulator. The British chose the latter solution. There was concern that direct regulatory powers to secure desired outcome would serve to keep out competitive entry and threaten the competitive transformation process over the long term. Because of weak regulatory controls, however, the Regulator was forced to fight a running battle with the two incumbent duopolies. In 1994 when the regulator was faced with high and unpredictable pool prices and lack of transparency in the market, he was forced to intervene and impose an unofficial price cap, as well as to secure voluntary agreements for the disposal by the two duopolies of 15% of their generating capacity. This was made possible by the threat of reference to the Competition Commission. The regional distributors also responded to the duopolies’ market power by building their own CCGT generators. It was therefore more the credible threat of entry, which restrained prices. This however, came at the cost of high and volatile prices and the fact that important cost savings by generators were not passed on to the consumers until after 1995/96. There is therefore the question as to whether the absence of regulation was worth the inefficiencies and the extra cost of excess capacity and inefficient entry. We have seen earlier that by 2000 the duopoly structure had disappeared, with new entrants supplying more than 40% of the market. The absence of regulatory power to intervene more directly when it was apparent that the bulk electricity market was not competitive could be considered to be a policy error. Direct regulatory powers, however, should be limited to powers to impose structural remedies and not to impose price controls. Transmission Price Regulation In the restructuring and privatisation of network industries, access and access pricing have developed to be the most contentious regulatory issues. In the single buyer model, where the 173 integrated utility owns the network and at the same time competes in the delivery of services in the upstream and down stream markets, there is a clear case for very tight regulation. The main problem of the vertically separated transmission system is that the coordination and vertical economies might be lost from separation. It may be cheaper, for example to pay more to locate new generation capacity near high demand zones at the expense of building extra transmission lines. The question as to how to price transmission services and how to decentralise decisions in respect to generation location and investments in an unbundled transmission structure tends to be of the utmost importance. Liberalisation of the generation market is not by itself sufficient to maximise welfare. Competitive generators and retail suppliers must have free and non-discriminatory access to the transmission wires. A transmission operator particularly, one with centralised responsibility for all transmission services, possesses market power and the potential for opportunistic behaviour, for example, vertical bias in favour of some users. In the Chilean attempts to create a competitive market in the 1980s, the transmission system remained integrated with ENDASA, the largest generator and this presented serious entry problems. It was not until 1993 that the transmission assets in Chile were spun off into Transelec. In the case of the England and Wales market, because of the dense transmission system and excess generation capacity, which existed at restructuring, the problems of transmission bottlenecks and constraints were more or less ignored. In the cases of countries like Australia and Argentina, with distant networks or developing countries with weak and sparse networks and where the system is prone to bottlenecks, transmission pricing to ensure efficient outcome becomes critical. From a normative point of view transmission price should at least pay for the marginal cost created by users. Nodal pricing best reflects this principle, which allows for optimal dispatch throughout the system. Nodal pricing is a system of marginal cost pricing where differences in prices of each node reflect two sets of costs incurred; congestion cost and losses. However, these costs only account for about one third of transmission cost. The fixed cost must therefore be recovered by other mechanisms. If short run efficiency is the objective, then Ramsey two part pricing provides for optimal allocation of resources where the transmission operator has to balance its budget. Ramsey 174 two part pricing allows for the fixed costs, of the infrastructure to be allocated to all the users, otherwise large users will bypass the system and leave the smaller captive users with the burden of the fixed cost. Nodal pricing, however, allows for the exercise of market power when the system is ‘constrained-on’ and reduces market power when the system is ‘constrained-off’. Its attraction is that it defines the value of transmission links connecting adjacent nodes and apparently provides a solution to two problems, how to signal where consumers and generators should locate and how to decide when and where to build additional capacity. Instead of nodal pricing, a single integrated market as the benchmark with contracted rights to the transmission system was adopted for the English and Wales electricity market. The system provided for a single countrywide transmission price with provision for station specific adjustment. In a situation where transmission constraints prevented merit order dispatch at power stations they are compensated for by the difference between SMP less the station bid price. Power stations that bid above SMP and are required to run, are paid their bid price. The extra cost was recovered initially from all consumers and not just those constraining the system. Later connection and end use charges were regionally differentiated so that both suppliers and generators took transmission cost into account. Costs were distributed on the basis of the retailers’ peak demand and for generators on the basis of their capacity and output in the ratio of 75:25. The system adopted was seen to be simple to operate, eliminating the multiplicity of nodal prices. It however, had the disadvantage that it provided incentives to exploit any capacity constraint by the duopolies in manipulating bids offered. In setting the price control regime, a two part pricing mechanism was adopted consisting of new connection charges for individual users and as use-of-system service charges, with the latter covering system service charges and infrastructure charges, inclusive of zonal differentiation. The cost for new connection (as well as the cost for the French and Scottish connectors) is determined on the basis of rate of return, whilst the use of system charges, together with existing connected users, are the subject of the price cap regulation of RPI-X. 175 The price cap applies for the average charges and incorporates a correction factor to adjust for forecasting errors. The X factor provided at vesting was set at zero. In the first price review, which was carried out after three years, X factor, was tightened to minus 3% and lasted for the period 1993-1997. In the case of the second price review effective from April 1997-2001 the cap was further tightened through a one off reduction of 20%, followed by the X factor being relaxed to minus 1.5%, and accompanied by a one off reduction of 12%. Between 1989/90 and 1993/94 the numbers employed in the transmission system fell from 6442 to 5125 as shown in Table 8 below. Over the decade of the 1990’s manpower reduction have been estimated at 33.3%26. Operating cost, net of depreciation was reduced by an average of 40% over the first price review period. The rate of return earned by the NGC as shown in Table 9 in 1990/91 was 4.9%, this increased to 6.7% in 1994/95 and experienced a marginal decline to 5% in 1996/97. This compares with rates of return in the generation sector for the respective three periods of 4.0%, 9.5% and 11.0%. Generation experienced significant increases in profitability over the first seven years, whilst profitability in transmission, more or less stabilised after an initial increase. Table 8 Changes in the Electricity System Workforce Sector Total RECs Generators Transmission Total ESI 1989/90 82,478 40,822 6,442 129,742 Source: Electricity Association, Annual Report 1993/94 71,473 22,465 5,125 99,125 % Decrease per sector -13.5 -45.0 -30.5 -24.0 176 Table 9 Profitability of ESI after Privatisation Sector Generation Transmission Distribution Rate of Return, % 1990/91 4.0 4.9 6.5 1994/95 9.6 6.7 9.2 1996/97 11.0 5.0 8.0 Source: David Parker, “Public Utilities: Lessons from the UK”, International Institute of Administrative Sciences, Vol. 65, No. 1 (1999), p.124. Figures for distribution are on weighted averages. Distribution Price Regulation In the case of the distribution sector price controls in 1990 for eleven of the regional distributing companies (excluding London) took the form of the X factor being plus rather than minus and the controls were set at different figures for different companies, varying from zero to plus 2.5% in real terms for each year. X was set to provide for an increase in this sector to take account of underinvestment when the enterprises were under public ownership. It soon became apparent that government at vesting had seriously under-estimated the scope for cost reduction and the exercise of location market power. The effect of this initial liberal price control was that profits of the RECs progressively increased each year. Over 85% of RECs profits came from the distribution lines business, with the rest from retail supply. Pressure for an earlier review, than the review date of 1995 began to emerge from as early as 1992. The Regulator, however, resisted the pressure for a mid-term review and argued that unplanned intervention would be a breach of the regulatory commitment and would lead to a negative impact on incentives for future investments. The Regulator also resisted pressures to shorten the review period from five years to three years, the reason being that a shorter period would not provide sufficiently strong incentives for efficiencies in the distribution sector. The review which took place in 1994 was a long drawn out exercise and the price cap established by the Regulator which was set in August 1994 called for one off reductions, ranging from 11% to 17% and for an X factor of minus 2% to take effect from April 1995 to 2000, implying a reduction on a 177 typical domestic fuel bill of 8% to 17.5%. For the purpose of the reduction, the distribution companies were grouped into three categories. All the England and Wales RECs accepted the proposals; however, one of the Scottish firms, Hydroelectric called for a reference of the proposed changes to the MMC. The expectation also had been for a much harsher review, involving one off reductions of up to 30% and for an X factor of minus 4%27. The relatively lenient review resulted in share prices of RECs outperforming the stock market all summer of 1994. It was felt that as the companies carried very little debt, and that as no major investments were required in the near future, very little commercial risk was involved. An unexpected development in the market in December of 1994 changed the environment and led to questioning of the controls. The criticism was that they were not demanding. Trafalgar House, a non-electricity company made a hostile bid for Northern Electric. In its vigorous defence, Northern Electric offered £500 million in inducements to its shareholders to remain loyal, and promised cuts in costs, special payments of £5 per shareholder, increased gearing and subsequent increases in dividend payments in future years. The formal consultations for the review were due to end by 11 March 1995, however, much to the surprise of the City of London, the companies and even consumers, the Regulator announced that in view of the new information which came to light, he intended to consider further tightening of the controls. Share prices of the RECs immediately fell by 10-15%. In his final decision, the Regulator stated that the charges set for the first year 1995-96 would stand but for the further four years, new controls would be imposed. These consisted of the X factor being tightened to minus 3% and further one off cuts of 10% to 13%, effective from April 1997. The Regulator had also adopted the asset valuation method used by the MMC in the Scottish Hydro referral case 28 and this more or less made a successful referral by the RECs unlikely. The effect of this development was to demonstrate that RPI-X is not as trouble free as initially presented. Secondly the problem of information asymmetry which price cap regulation was claimed to have resolved remains problematical. Regulated firms have a monopoly on information and will only release information when is it seen to be in their interest. Third the fact that the Regulator was 178 able to change the price controls announced earlier and the informal nature of the procedures adopted shows that RPI-X regulation is relatively weak on regulatory commitment. Fourth in setting the X factor, the Regulator has had to resort to much the same sophisticated financial models of the business, calling for much of the same information as with rate of return regulation, such as the key parameters covering the cost of capital, rates of return and value of assets and for the regulated firm to earn no more than the normal rate of return. Fifth the Regulator himself admitted that there is a steep learning curve to be experienced with any new regulatory regime, which is in effect admittance that there were errors in the earlier judgement. One good outcome is that even when there is no product market competition to assist the Regulator, the market for corporate control helps to partially fill this gap. In 1999, the Regulator published new price controls for distribution, involving a one off reduction of 25% from April 2000 (of which an average of 8% was transferred to retail supply) followed by an X factor of minus 3% for the five-year review period. As at 2001 there were 12 licensed regional distributors in England and Wales, 2 in Scotland and one in Northern Ireland. Table 10 below shows the characteristics of the sector by number of customers, turnover and unit sales. There is wide variation in their sizes and customer densities. Table 10 Characteristics of Distribution - 2001 Company 1. East Midland Electric 2. London Electric 3. Manweb 4. Midland Electricity 5. Northern Electric 6. Norweb 7. SEEBOARD 8. Southern Electric 9. SWALEC 10. TXU Europe 11. Western Power Distribution Number of Customers 000’s 2415 2060 1432 2275 1536 2239 2122 2699 989 3261 1344 % Share of Customer s Turnover £M 355 370 240 362 236 346 283 417 199 249 442 Units Distributed GWh 17700 16500 12000 17200 10600 15500 NA 18900 9100 NA 8400 179 12. Yorkshire Electric England and Wales Total 13. Scottish Hydro 14. Scottish Electric Great Britain Total 15. Northern Ireland Electricity UK Grand Total 2061 24433 659 2059 27151 681 27832 100 319 3818 169 343 4330 NA 15300 4400 14000 4400 NA Source: Electricity Association, Electricity Review, No. 5, London (January 2001), p. 57. Since 1989/90 the distribution sector has benefited from investments of £12 billion. Over the same period and particularly during the first five years after vesting there has been continued shedding of labour. Improvements in productivity, however, have been smaller than in generation and transmission. The reduction in the workforce in the four years after 1989/90 was 13.5% as shown earlier in Table 9 above, compared to the industry’s average of 24.1%. Since 1996 there has also been widespread withdrawal of the regional distributors from the retail business, most of which has been divested to other generators, and to other utilities, giving rise to multi-utility operators. The multi-utility operators seek to capitalise on the economies of retailing gas and electricity or electricity and water. The RECs have also seen improvements in their profitability, with rates of return rising from 6.5% in 1990/91 to 9/2% in 1994/95. The tightening of the cap by the Regulator after 1995/96, however, has resulted in a marginal decline in profitability, which has stabilised at around 8.0%. With the improved profitability the RECs were able to pay off their debt obligation taken over at privatisation and in addition have been able to pay relatively high dividends and high executive salaries, leading to criticism and pressure for the Regulator to intervene. Regulating the Competitive Transformation of the Retail Market Although the retail business was declared potentially competitive in 1989 the policy framework for competitive transformation process called for regulation and liberalisation to be effected in the industry simultaneously. The retail business was segmented into three markets and competition was 180 to be phased, starting with the first segment, the large industrial consumers (demand in excess of 1 MW) in 1990, followed by the medium sized users (demand in excess of 100 kW and below 1 MW) in 1994. The small domestic and small business consumers’ segment (less than 100 kW) was to be liberalised in April 1998. The non-liberalised market was to be subject of the RPI-X price control and these controls were to remain in force up to liberalisation in 1998. The pricing formula was adjusted to RPI-X+Y revenue yield control, with the “Y” factor being input cost-pass through of five elements; energy, transmission, pool administration and distribution costs and the fossil-fuel levy and are the cost drivers for which the retail suppliers have no control over and account for 95% of total systems cost. The portion controlled by the supply cap, represents the value added, at 5% of system cost. The controls, which operated over the first review period to March 1994, regulated the maximum charge per unit of electricity supplied in both the franchised and non-franchise markets. The revenue applied to a constant term plus an allowance per customer served and an allowance per unit sold. The constant term varied between RECs, with the allowance per customer served, and per unit sold being uniform across RECs. The costs were distributed 75% for the number of customer served and 25% for the number of kilowatts sold. Additionally, there was a supplementary price control, which expired in March 1995. For the first price review period, X was set at zero. The first review in 1994 resulted in new controls. X was tightened to minus 2% and lasted until 1998. For the two-year period after April 1998, prices were subjected to a fixed maximum, and were designed to protect the small consumers during the transitional phase of liberalisation compared with the previous controls where the RECs were able to pass through the input costs. This new control applied to all “designated customers, users who consumed 12000 kWh per year or identified as domestic customers”, under the PES licence. Over the two-year period the average real reduction was estimated to be 9%. Further price controls were also proposed for the two year period to April 200229. These controls were to apply for all but the direct debit customers and took the form also of a cap on final prices in the first year, based on RPI-X and applied to two basic domestic tariff blocks. PES’s were encouraged to reduce prices if generation prices fell with the introduction of the New Electricity 181 Trading Arrangements (NETA). In the second year of the control, the maximum prices were expected to fall by 2.1% and 5.8% for the respective two tariff blocks. In 1990 the large consumer market segment amounted to 28% of the retail market and numbered 5000 customers, whilst the medium sized segment, which was to be liberalised in 1994 numbered 45,000 customers and accounted for 16% of the market, with the result that 44% of the market was offered choice by 1994. The remaining 54%, the small domestic customer market, estimated to be 23 million users in 1990 was scheduled to liberalised in April 1998, but was postponed to September 1998 due to the difficulties encountered with the application of the computer software and the sheer logistical problems presented by offering choice to 26 million new customers. The application of the liberalisation itself was phased. The first four RECs commenced in September 1998, the second group in December 1998, the third group in April 1999 and with the entire programme completed by June 1999. There are important economies of scale, which work in favour of the large, and medium sized consumers in exercising choice. Bonner (1996)30 shows that for a small domestic householder in 1994 with a typical annual bill of £400, the costs breakdown in percentage term was as follows; distribution 25%, retail supply 6% and transmission and generation as well as the levy 70%. This is in contrast to the large consumers, where the percentage breakdown was distribution 15%, supply 0.5% and generation transmission and the levy 84.5%. The marginal benefit to the large consumer is much greater than the small consumer, therefore, the marginal cost, becomes a critical factor in exercising choice. The transaction cost to the small consumer may be perceived to be greater than the marginal benefit from switching. By May 1999, 5% of small household consumers had exercised choice and at the end of 2000, 6 million or 25% had exercised choice31. In 1996, 37% of the large and medium sized consumers had exercised choice. The percentages increased to 80% for large consumers and 58% for medium sized consumers by the end of 200032. In terms of the second tier market, the PES themselves have accounted for 66% of the large consumer segment, 48% of medium sized consumers and 83% for the small consumer segment. In 182 2001 there were 27 million consumers, with the consumer base growing at 1% per annum and demand by 1.3%. Between 1989 and 1994, electricity prices on average real terms fell by 10%. The liberalised customers saw a real price reduction of 20%. Nominal prices increased from 7.74 pence/kWh in 1990 to reach 8.91 pence/kWh by 1992, declining to 7.74 pence/kWh, by 2000, reflecting a real decline of 36% over the 10-year period. For the large consumer group the real decline varied from 27% to 33%. The real reductions in prices are shown in Figure 22 for the various market segments. The reductions were less for the very large industrial group and this resulted from the elimination of the subsidies, which were available to the very large consumers prior to privatisation. Figure 22 183 Source: Stephen Littlechild, Privatisation, Competition and Regulation in the British Electricity Industry, with Implications for Developing Countries, World Bank/UNDP ESMDP Report, (2000), p.33. The retail market has been experiencing increased levels of consolidation since 1998 the result of several mergers, some leading to multi-utility providers. The multi-utility market has been growing as retailers seek economies of scale from realigning electricity and gas or water and electricity in there merchandising packages. Green and McDaniel (1998)33 predicted that the benefits of introducing competition in the small consumers’ market will result from three effects; further reductions in electricity costs, as retailers will no longer be able to pass on input costs to customers especially generation cost from their IPP associates, increased services and a fall in industry profit margins, where they exist above competitive levels. Changes to UK Regulation Despite the relative success of British style regulation, it was characterised by a number of deficiencies and these have attracted strong criticisms. The single decision maker is said to lead to personalisation of regulation and a disproportionate effect on regulatory outcomes. Further this system provided a weak institutional memory, as replacement of the single individual decision maker at a given time was likely to lead to discontinuity. There is the risk also that the single individual could be more readily subjected to undue political pressure. The process is less open, and in the case of electricity regulation there was very little involvement of consumers in the process. Overall the system lacked transparency in that there was no obligation on the part of the regulators to give reasons for tier decisions. The industry specific regulatory framework leads to a multiplicity of regulatory agencies, is relatively expensive and can lead to regulators adopting different approaches to common methodological issues. Several regulatory agencies give rise to regulatory arbitrage. 184 In many instances X is set quite arbitrarily, as no one knows how much efficiencies had developed in the publicly owned utilities prior to privatisation to be able to determine how much improved productivity is obtainable from X. In the UK, X was set very loosely, providing for the utilities to earn excessive profits in the initial years. There is no certainty that the starting tariff levels are the correct levels on which to base the subsequent reductions. In most instances, tariff rebalancing is needed as was the case in the UK in the years just prior to privatisation. In developing countries with extremely high levels of cross-subsidies and where rates do not reflect long-run marginal cost, tariff increases to the subsidised domestic householders may be needed initially rather than tariff reduction. This can be quite an unpopular political decision to take and implement. If price cap regulation is set in reference to actual cost incurred by the firm concerned, it is almost identical to ROR regulation. The increased need for information at price reviews particularly in relation to cost of capital, rates of return and value of assets results in the criticism that it is ROR every five years and gives rise to some of the same information asymmetry problems as in ROR regulation. Paradoxically, the more successful the regulated firm in reducing cost beyond what was anticipated by the Regulator the more customer dissatisfaction is engendered and criticism that regulation may have failed. Public pressures then build up for the Regulator or the state to claw back some of the benefits as was exemplified in the UK with the imposition of the windfall tax on the regulated utilities by the new Labour government in the later half of the 1990s. This could dilute some of the incentives which price cap regulation is said to provide to investors. Following from the various complaints, Government published in 1998 a set of consultation documents outlining proposals for future reforms34. An essential principle incorporated in the consultation documents was a movement away from regulation of services (as services were becoming competitive in several of the utilities), to regulation of the network. This reflects a further fundamental change in the British approach to regulation and is based on the underlying principle that competition is the best regulator. This principle was subsequently incorporated in the Competition Act of 1998 and the Utilities Act of 2000. The Utilities Act amends the 1986 Gas Act and the 1989 Electricity Act and provides for one regulatory regime for both industries, in effect recognising the growing convergence between both industries since privatisation. The Act also provides for the unbundling of distribution and retail 185 supply into separate legal entities, establishment of a New Electricity Trading Arrangement, for additional protection and involvement of consumers in regulatory affairs and for improved transparency, consistency and predictability of the regulatory process. A new corporate body; the Gas and Electricity Market Authority (GEMA) with a Board of at least three members replaced the two Director Generals of both Gas and Electricity. The Authority is supported with an Office of Gas and Electricity Regulation (Ofgem). It will be required to consult more widely, to provide a foreword programme with key objectives and to publish reasons for key decisions. Its pricing objective will be to protect the interest of consumers. Further changes empower the Authority with the mandate to grant licences, establish procedures for licence changes and effect licence modification without further primary legislation or ministerial approval. Instead of individual and unique licences for each operator, class licences with standard conditions are to be issued to ensure that all holders of a particular licence type are subject to the same conditions and to allow for collective modification. Government, however, issues the initial standard licence, with the Authority carrying powers of modification, subject only to veto powers by the Competition Commission. Provisions have also been made to impose mandatory penalties subject to a maximum limited to 10% of the firm’s turnover. The PES licence, which covered both distribution lines business and retail supply, is to be discontinued and separate licences to be issued for distribution and supply. Although distribution and supply will be separate legal entities, common ownership is not precluded. The concept of the PES ceased to apply as of April 2001 and the duty to supply is replaced by a duty to connect. Distribution licence will carry a duty to facilitate competition in generation and supply with non-discriminatory terms of access, as well as to provide non-discriminatory terms for services relating to metering, until full competition in metering develops. The licence for distribution will continue to be issued for a defined geographical area and will coincide with the existing PES boundaries and referred to as distribution services area (DSA). Retail licences, however, will not necessarily carry geographical restrictions and can be issued for all of Great Britain, for a particular region or for a class of customers. The distinction between first tier and second tier licences are to be removed, as well as tariff supply conditions and replaced by 186 commercial contracts between supplier and customers. The changes also downgrade the duty of the Regulator to promote competition and give more importance to protection of consumers, interests. Ofgem came into operation in 1999 and work on separation of licences (distribution lines business from retail supply) began in 1999. Work on the licence amendments commenced in 2000. The Competition Act on the other hand confers new powers on the utility regulators, giving them concurrent jurisdiction in respect of competition matters. A Competition Commission also replaced the Monopolies and Mergers Commission. This new Commission will also operate as the appeals body for the Office of Fair Trading and the individual industry regulatory agencies. A special panel of the Competition Commission has been established to hear appeals from the electricity industry. Under the new law, regulators will be required to institute procedures to determine when markets move from pre-competitive to fully competitive, to establish clear sets of procedures on the regulatory decision making process, as well as procedures on the regulatory methodologies to be adopted. Government, however, decided that despite the criticisms made against RPI-X price control, there was no justification for any substantial changes to the formula. The Verdict Over the 10 year period following privatisation, costs have fallen significantly in the generation sector in England and Wales; however, the fall in fuel costs in real terms in the first five years have been more dramatic than the fall in prices. The result is that the margin between fuel costs and bulk electricity prices widened. There were also significant improvements in efficiencies in transmission and distribution, but less dramatic than in generation. As bulk electricity prices did not fall nearly as fast as the decline in input costs, the privatised company’s experienced sharp increases in profitability, especially over the first five years. Combined profits of the industry rose from £2.0 billion in 1991/92 to £3.5 billion in 187 1995/96 and rates of return rose from 3% in 1990/91 to 11% in 1995/96. Share prices of the thermal generators tripled between floatation and 1995 and out performed the stock market by 100%35. Shareholders who bought the shares of the six electricity companies at vesting day earned annual average returns of 40% by 199636. Shareholders of the privatised companies gained immensely. The pressures from competition, following from vertical and horizontal unbundling provided increased incentives for efficiency improvements and cost reduction. Considerable improvements were obtained in labour productivity. Reduction of labour in the generation sector was over 45% and overall for the ESI 24% for the first five years after vesting. In the coal industry the indirect impact was dramatic. An industry, which employed over 250,000 in the mid-1980s, had declined to no more than 10,000 workers by the early 1990s. The improvements came with a cost to both labour and the nuclear industry. Plans to build more nuclear plants by 1996 were shelved, more or less permanently. The competitive pressures which were felt in the fuel industry and which led to the lowering of fuel prices came from replacing expensive and environmentally expensive coal and nuclear plants with cheaper and cleaner CCGT plants. The environmental benefits have resulted in a reduction in acid rain and CO2 emission. Consumers in the retail market, however, failed to see important benefits until after 1995/96. The idea of Bertrand competition to supply electricity at efficient prices to consumers failed to materialise. Market power of the incumbent fossil fuel duopolies was regularly abused, necessitating constant vigilance of the Regulator. The result was that the improvements in productive efficiencies and lower costs did not translate into reduced consumer prices or ; allocative efficiencies. Newbery and Pollitt (1997)37 constructed various counterfactuals about what might have happened without restructuring and with continued state monopoly operation and concluded that there was an overall net benefit in the first five years after vesting, which when converted to permanent savings; the unit cost to consumers amounted to a reduction of 3.2% to 7.5%, depending on the assumptions factored into the model. The distribution of the benefits, however, has been skewed towards the investors and stockholders who benefited from high profits and higher dividend payments. 188 Despite the sizable restructuring costs involved in the reforms and privatisation, the revenues from the sale of the companies, the increased tax flows and the fact that the Treasury no longer had to finance capital costs for the industry, also meant that government obtained appreciable benefits. Consumers, however, did not experience net benefits in the initial five years. Consumers began to see real benefits after 1996 and with full competition in retail supply after 1998. Green and McDaniel (1998)38 predicted three likely outcomes; further lowering of retail prices to consumers, reduced margins to the retailers, and improved quality of service. The British experience also shows that competition and restructuring of the electricity supply industry can take several forms. In Scotland, competition was expected to take place between the two vertically integrated franchised monopoly utilities. Pollitt (1998)39 concluded that whilst the reforms generated some beneficial effects in the nuclear industry in efficiency gains, there were very few discernable effects on efficiency improvements and productivity growth in the two integrated utilities. The Scottish companies were not only protected from product market competition, entry to the market was restricted until after 1998 and the market for corporate control was closed with the permanent incorporation of the “golden share”. Rather than lower real prices, consumers experienced increased real prices and consumer prices, which were lower than in E&W in 1990, were higher in 1999. In Northern Ireland where generation was vertically and horizontally unbundled and increased levels of competition accommodated in the generation sector, the reforms provided strong incentives to cut cost in the generation sector, especially from the conversion of expensive oil fired plants to CCGT plants. With a vertically integrated transmission and distribution utility operator and with competition in the large consumer market segment coming on stream after 1994, whilst that of the medium sized consumer (over 2.5 GWh consumption per annum) coming after 2000, very little of the efficiency gains have been passed to consumers. Pollitt (1997)40 showed that in the case of Northern Ireland, unit cost fell by 14% between 1991/92 and 1995/96, whilst retail prices increased faster than the rate of inflation. In 1996 the average level of prices in Northern Ireland was 23% above the average levels in E&W. The empirical evidence from the application of the three British models of restructuring is that the vertically operated privately owned and regulated utility is the least effective in bringing about 189 efficiency and welfare gains. Vertical integration as was applicable in Scotland muted the incentives for efficiency. Vertical and horizontal unbundling of generation as was applicable in Northern Ireland and the single buyer trading arrangement that formed the Northern Ireland structure provided for increased incentives for efficient investments in generation. Despite regulation of vertically integrated transmission and distribution in Northern Ireland, very little of the gains were passed on to consumers. The single buyer model is, however, superior to the fully integrated franchised monopoly operator. In the case of the E&W experiences with full disintegration, competition in the bulk electricity market, full competition in retail supply in 1999 and competition in the market for corporate control, significant gains were made in both productive and allocative efficiencies. Further gains from lower prices to consumers are also expected, now that competition has taken a strong hold in both generation and retail supply. Restructuring and exposing the privately owned utilities to competition, where competition is possible, and providing for incentive type regulation from price-caps, offer powerful incentives for improvements in economic efficiencies and welfare gains. The disintegrated privately operated ESI, operating under competitive conditions in generating and retail supply, and incentive regulation over the core network natural monopoly is superior to both privately owned with rate of return and cost of service regulation and publicly owned monopoly with self-regulation. Opening the industry to competition has resulted in new owners, new technologies, and new structures. In fact none of the original regional electricity companies has survived in its original form. Ownership in a few instances has changed three times. The British privatisation experiences seem also to have resolved the question as to the superiority of privately owned utilities versus publicly owned utilities. It was shown in Chapter 1, that since 1970, several studies carried out by various analysts, have examined the comparative financial performances, labour productivity and total factor productivity of publicly owned and privately owned utilities. Most of these studies found no strong evidence to support the thesis that privately owned utilities are superior to public utility enterprises in terms of economic efficiency. This general conclusion is not surprising, as most of the privately owned utilities prior to 1990 were integrated monopolies regulated by the rate of return methodology. Privately owned monopoly utilities with ROR regulation carry important similarities with publicly owned monopoly utilities. 190 Under both institutional arrangements the incentives for efficiency improvements and cost reduction are extremely weak. Restructuring exposes the privately owned electricity supply industry to competition and offers greater incentives for cost reduction and efficiency improvements than rate of return regulated privately owned or publicly owned utilities. Interest group theory of regulation points out that similar characteristics are to be found with privately owned rate of return regulated and publicly owned monopolies. Such firms will pursue economic rents and such rents will be distributed between the various interest groups in proportion to their bargaining power (Noll 1989) 41. The redistribution effects are x-inefficiencies and dead weight losses. In both privately owned and regulated monopolies, and publicly owned utilities, the consumer bears the risk of investment. Even with a bulk electricity market, with cost pass-through, the captive consumers bear the investment risks. A change to full retail competition, dramatically changes the risk balance, in that once consumers are free to change patronage, retailers will no longer be able to enter into long-term contracts knowing that they can pass the increased cost to consumers. Retail competition will result in more equitable distribution of risks between generators, retailers and consumers. These developments have led Littlechild (2000)42 to state that: “The principles of private ownership, competitive markets and independent regulation (England and Wales) have worked well. The British electricity industry is now more efficient and innovative……………… All groups of consumers have benefited significantly in terms of lower prices and better quality of service. The benefits of introducing competition already outweigh the costs and more benefits are to come”. In conclusion it would appear that the British experiences not only signalled the end of the vertically integrated state owned franchised monopoly as the dominant institutional form for the operation of utilities, it has also signalled the end of vertically integrated privately owned franchised monopoly utilities regulated by rate of return regulation. Whilst the circumstances for developing countries are different from those of a more mature market as that of England and Wales, the same principles of public polices would appear to be applicable. With appropriate adaptations especially for markets of less than 1000 MW, the policy of structural disintegration, competition where competition is 191 possible and independent regulation where market failure continues, appears to be the right public policy for developing countries. Privatisation and deregulation has also created a condition for the rise of the ‘regulatory state’ to replace the ‘development state’ of the past. Privatisation has not in fact led to a reduction of state intervention; there may be a decline in public ownership as is the case in Britain. However the state has transformed its role by replacing public ownership form of intervention with regulatory form of intervention. Regulation has become the new border between the state and the battleground for ideas as to how the economy is to be managed. 192 End Notes 1. J. Foreman-Peck and R. Millward, Public and Private Ownership of British Industry 1820 – 1990, Oxford; Clarendon Press (1994). pp.107 and 167. 2. Pablo Spiller and Cezley Sampson, Regulation, Institutions and Commitment; The Jamaican Telecommunications Sector, Washington, D.C., World Bank Policy Research Working Paper No. 1362 (1994) p.18. 3. The public utilities commission (or public service commission as they are known in some states) was first exported across the Atlantic, being derived from the Canal and Railway Regulatory Commissions of the mid 1850’s. 4. David M. Newbery, Privatisation, Restructuring and Regulation of Network Industries, Cambridge, Mass, MIT. (2000) p.50. 5. George Kolko, Railroads and Regulation, 1877 to 1916, Princeton University Press (1965). 6. George Stigler, “The Theory of Economic Regulation” Bell Journal of Economics and Management Science, Vol. 2, No.1 (1971). 7. Mohan Munasinge and Arun Sanghvi, Recent Developments in US Power Sector and Their Relevance to Developing Countries, Washington, World Bank, Working Paper Energy Series No. 12 (1989), p.14. 8. Robert Baldwin and C McCrudden, Regulation and Public Law, London (1987), p. 170. 9. S.C. Littlechild, Regulation of British Telecommunications Profitability, London, HMSO (1983). 10. S.C. Littlechild, Privatisation, Competition and Regulation in the British Electricity Industry With Implications for Developing Countries, Joint UNDP/World Bank ESMAP, Washington, D.C. (February 2000). p. 14 11. Ibid. p. 23. 12. In principle a profit maximising monopolist could engage in perfect discrimination and charge each user up to their willingness to pay, Ramsey pricing, with the result that there would be no loss to society. 13. A firm achieves technical efficiency when it minimises production cost of supplying any given output and achieves input price efficiency when it minimises inputs purchased for any given output; it purchases inputs optimally and produce at the optimal production level. Static efficiency relates to efficiency gains with existing technology, production process or 193 products; a movement on the production frontier. Dynamic efficiency relates to efficiency improvements over time and results from new technology, new products or new production process; a shifting of the production frontier outwards or a change to the slope of the production trajectory. Firms which are allocatively and technically efficient are said to be Xefficient, these firms, irrespective of their dominant positions in final markets act to keep cost as low as possible. It is possible for firms which face no competition to appear not to make excessive profits, yet to have inefficiently high cost and high prices, or X-inefficient, conversely firms which are X-efficient may make excessive profit yet have low cost and low prices. 14. Brian Williamson, “UK: Incentive Regulation, International Best Practices”, in Regulatory Review 2000/01, eds., Peter Vass, Bath, Centre for the Study of Regulated Industries (2001), p. 272. 15. Constitutional interpretation has the independent regulatory agencies in the UK as a separate institution from the respective sector ministry, see Lake Airways VS Department of Trade 1997, where the Court ruled against the right of the Minister to give guidance to the Civil Aviation Authority. The Court stated that guidance could supplement the CAA statutory objectives it could not replace them. In issuing pre-emptory instruction to the CAA, the Court also ruled that it constituted directions, rather than guidance. Custom and practice of UK unwritten constitution is that portfolio ministers do not interfere in the affairs of independent regulatory agencies. 16. John Kay, “The Future of UK Utility Regulation” in Regulating Utilities: Time For a Change? eds., M.E. Beesley, et.al. London, Institute of Economic Association (1996), p. 52. 17. Tony Prosser, Law and Regulators, Oxford, Clarendon Press (1997), p. 16. 18. Alison Young, “The Politics of Regulation: Privatised Utilities in Britain”, London, Pelgrave (2001), p. 26. Prossor, op. cit., p. 158 19. 20. Ray Rees and John Vickers, “RPI-X Price Cap Regulation”, in Regulatory Reform: Economic Analyses and British Experiences, eds., Mark Armstrong, Simon Cowan and John Vickers, Cambridge, MIT Press (1994), p. 166. 21. John Vickers and George Yarrow, “Regulation: Regulation of Privatised Firms in Britain” European Economic Review, Vol. 32, (1998), p. 468. 22. Alex Henney, “Private Power: Restructuring the Electricity Industry”, Policy Study, Centre For Policy Studies, No. 83 (1987). 23. Dieter Helm, “Regulating the Electricity Supply Industry”, Institute of Fiscal Studies, Fiscal Study No. 9 (August 1988). 24. Vickers and Yarrow, (1998), op. cit. 194 25. Richard Green and David Newbery “Competition in the British Electricity Spot Market”, Journal of Political Economy, Vol. 100, No. 5 (1992). 26. Littlechild, (2000), op. cit. 27. Times of London, 12 August 1994. 28. MMC concluded that the regulator had placed too high a value on the companies’ assets and that the companies should have absorbed the redundancy payments and not added on. 29. Ivan Adams, “Electricity Supply: The Second Tier Market”, in Energy – Transition or Maturity? Review of the Current Policy and Development, ed., Carole Hicks, London, Centre for the Study of Regulated Industries (1996), p. 61. 30. John Bonner, “Electricity Distribution, Review-Outcome and Response”, in Energy – Transition or Maturity? A Review of Current Policy and Development, eds., Carole Hicks, Centre for the Study of Regulated Industries, London (1996), 16. 31. Littlechild (2000), op., cit. 32. Ivan Adams, op.cit. p.61. 33. Richard Green and Tango McDaniel, “Competition in Electricity Supply: Will “1998” Be Worth It?” Fiscal Studies, Vol.19, (1998). 34. Department of Trade and Industry, A Fair Deal for Consumers: Modernising the Framework for Utility Regulation, London, HMSO, CM3898 (1998a); Department of Trade and Industry, Review of the Energy Sources for Power Generation: Consultation Document, London, HMSO, (1998b); Department of Trade and Industry, A Fair Deal for Consumers: Modernising the Framework for Utility Regulation: The Response to Consultation, London (1998c). 35. David Newbery and Richard Green, “ Regulating Public Ownership and Privatisation of English Electricity Industry”, in International Comparison of Electricity Regulation”, eds., Richard Gilbert and Alfred Kahn, Cambridge University Press, (1996), p. 100. 36. David Parker, Privatisation in Regulated Industries, Bath, Centre for the Study of Regulated Industries, Occasional Paper No. 4 (1997), p. 34. 37. David Newbery and Michael Pollitt, “The Restructuring and Privatisation of Britain’s CEGB – Was It Worth It? The Journal of Industrial Economics, Vol. 45, No. 3 (1997). 38. Green and McDaniel, op.cit., p.291. 39. Michael Pollitt, The Restructuring and Privatisation of Electricity Supply Industry in Northern Ireland- Will It Be Worth It? Cambridge University, Department of Economics, Mimo (February 1997), p.7. 195 40. Michael Pollitt, The Restructuring and Privatisation of Electricity Supply Industry in Scotland, Cambridge University, Department of Economics, Mimo (June 1998). 41. Roger Noll, “The Politics of Regulation” in Handbook of Industrial Organisation, ed., R. Schmalensee and R. Willig, Amsterdam, Elsevier Vol.2, (1989), Ch.22. 42. Littlechild (2000), op.cit. p.51. 196 Chapter 5 Ownership, Regulation, Liberalisation and Privatisation in the Electricity Utility; the Jamaican Case The Early Years Jamaica’s electric utility history, presents an interesting case to review institutional structures from the several regulatory regimes, industry structures and ownership structures, which have prevailed over the last fifty years. Electricity services were introduced in Jamaica in the 1892 by a private firm, Jamaica Electric Light and Power Company1. West India Electric Company (WIEC) came into operation and built one of the first hydroelectric plants in the world at the Bog Walk Gorge, St. Catherine. The company obtained a licence to supply light and power to Spanish Town and parts of St. Andrew. In 1907 WIEC leased the property and business of the Jamaica Light and Power Company Limited (JLPCL), successors to Jamaica Electric Light and Power Company. The Jamaica Public Services Company (JPSCo) came into being in 1923 when the Canadian based JPSCo purchased the assets of WIEC, including the tramway system and expanded power capacity by installing a coal burning power plant in Kingston2. While the financing for JPSCo came from Canada, the US firm, Stone and Webster Inc, provided management expertise3. Stone and Webster eventually came to own 20% of JPSCo. At the time of acquisition in 1925 the total connected customers amounted to 3958 and this increased to 16000 by 1960. Over the years, JPSCo acquired the several small power companies, which had been given separate licences, with the last to be acquired being the Savana-La-Mar firm in 1977. JPSCo found itself from the several acquisitions with over 26 licences for different areas, often with different standards. Most of these had to be renewed annually, and the uncertainty created by the annual renewals made it difficult for the company to obtain long term financing. As a condition of a World Bank loan in 1966, Government eventually provided JPSCo with a 25-year exclusive licence for the entire island (the All Island Licence). Between 1959 and 1963 the company carried out a frequency conversion programme, which facilitated the standardisation of supply, and uniform electricity rates Island wide. 197 In the 1960s JPSCo’s stocks were listed on the newly formed Kingston Stock Exchange as well as on the London Stock Exchange and this listing continued until 1974 when government acquired almost all of the outstanding shares then held by private investors. Following from a dispute with the overseas equity owners, Government earlier in 1971 had purchased the stocks of Stone and Webster amounting to 20% of the company’s equity. With compulsory acquisition of the rest of the company’s shares in 1974, the end of the first chapter that of 82 years of private ownership of the electricity industry, came to an end. The system of private ownership and independent regulation of utilities is often presented solely as an American experience. Jamaica also developed a system of private ownership of the utilities and independent regulation; however, the regulatory regime up to 1966 took a different form from the US system of Public Utility Commission. The regulatory structure prior to 1966 provided for the establishment of three-member ad hoc Rate Boards, appointed by the Colonial Governor of Jamaica4. The decisions of the Rate Boards could be appealed to the Courts and eventually to the Privy Council in London. Unlike the Jamaica Telephone Company, which operated under a 40-year licence granted in 1925, JPSCo had to seek annual renewal of its licences. Rate Boards were constituted or appointed for each review. They therefore lacked institutional memory, as there was no permanent member of staff. The Boards resorted to the use of ad hoc consultants, who were paid by the company, but selected by the Board to review the accounts of the company pursuant to an application for a rate increase. The Rate Boards suffered from serious structural information asymmetry vis-à-vis the utility companies. Additionally, the absence of a transparent and independent system of financing the Boards compromised their independence. The system of licence and contract with ultimate appeal to the courts, however, served the colonial period reasonable, well in an environment of low inflation. In between rate reviews the companies operated with little or no government interference and the eight percent real rate of return which was allowed, could also be considered adequate in an environment when the real interest rate was in single digits5. 198 The regulatory stability of the colonial days came to an end in 1955 when a socialist administration under the crown colony rule came to power and announced a policy of industrialisation based on the Puerto Rican model. Electricity was treated as an item of luxury up to 1955, despite the fact that there had been continued decline in prices since 1923. JPSCo was also able to maintain healthy profit returns over the years. Electricity rates had also been frozen by legislation in the early 1950s, the company being accused of trying to raise development capital from rate increases. As part of the industrialisation policy the socialist administration sought expansion of capacity by JPSCo to meet its development goals. JPSCo responded by declaring that their debenture holders and the company’s financial structure precluded expansion unless rates were increased. The annual renewal of the licences also provided for considerable uncertainty as the company was required to provide capital to develop the services even though there were no assurances that it would be given the permission to operate for more than one year or that the rate provided would allow it to raise new capital. The outcome was a protracted dispute where the commercial objectives of the transnational company came in sharp conflict with the development goals of the local administration. The dispute persisted for the life of the administration up to1962; however, new legislation; the Electricity Development Act 1958, was introduced and this led to the establishment of the Electricity Authority to generate electricity and interconnect with the utility’s system or to interconnect with other privately owned generating systems. The other Act governing the sector was the 1890 Electricity Lighting Act, establishing the Licencing regime for the supply of electricity. The 1890 Act permitted self-generation. Both the bauxite and sugar industries took advantage of this right to the extent that the installed capacity of the self-generators in 1960 was larger than the capacity of the utility company. Jamaica became independent in 1962 and the new Jamaica Labour Party (JLP) administration, which came to power, continued the dialogue with JPSCo for another three years up to 1965 in an effort to resolve the impasse. JPSCo eventually agreed to accept a new all-island exclusive franchise and for the company to be regulated by an American style public utilities commission. Although the agreement did not provide for any immediate rate increase, government agreed to guarantee a World Bank loan to the company to meet the cost of an agreed expansion programme. 199 The Jamaica Public Utility Commission Act (JPUC) of 1965 gave the portfolio minister the authority to licence any enterprise to generate and supply electricity for public use. At the same time under the Electricity Development Act of 1958 the same Minister had the authority to own, operate and develop electricity. It was through the Electricity Authority, that the government used as the vehicle to acquire the shares in the JPSCo between 1971 and 1974, and this gave the state 99% ownership of JPSCo. The Electricity Authority also owned the shares in the Rural Electrification Programme Company Ltd, which was established in the 1960s. An important element of the institutional structure of the Jamaican utility system has therefore, been that of a joint stock company with previous listing on stock exchanges, as distinct from the institutional form of a government department or statutory corporation. Jamaica differed from many of the other Commonwealth countries, such as New Zealand and Australia where the utilities have traditionally been developed and owned by government. The company had operated under a commercialised regime all its life; there was therefore, no need for corporatisation or commercialisation prior to privatisation, as was the case in New Zealand and several Sub-Saharan African countries. All that was needed to change ownership from public to private was sale of the shares to private interests. No new legislation was needed and therefore the Jamaican Government did not require from Parliament any mandate to divest the company. Private Franchised Monopoly and the Failure of Public Utility Commission Style Regulation In the period coming up to the nationalisation of the telephone and electric utilities, both enterprises had refused to increase investments to meet the national development objectives and this became a critical issue to the government of the newly independent country that was trying to force the pace of economic development6. With the introduction of the JPUC Act, the existing system of common law and licence was replaced for the first time with a legislative regulatory framework. JPUC employed a permanent secretariat and the Commission’s board members held their appointment on the basis of tenure. This facilitated the development of independence, institutional memory and addressed some of the problems of information asymmetry. The 25-year licence awarded by JPUC in 1976 incorporated provision for renewal and this provided a more stable investment environment for the company7. A new public 200 policy enshrined in the licences was that of increased local ownership. The Jamaican public was to hold a larger portion of the company’s shares, with limits placed on the holdings of any one individual. Minimum rates of return as practiced under the Rate Board system of rate determination was replaced by “fair rate of return” on the utilities rate base. Considerable regulatory independence was provided for in the new regulatory structure. JPUC was created as a statutory authority; however its decision was subject to judicial review by the Supreme Courts. It was given a very wide mandate. In respect of the electricity industry both the Act and the licence gave the Commission decision-making powers over the equity structure of the utility. Additionally, the Commission had to satisfy itself that the ownership structure was in the best interest of Jamaicans. The new licence also made provisions for the regulated utility to carry out programmes of development as prescribed in the licence and such further programmes as might be agreed with the regulator within the existing rate structure. Expansion programmes, therefore, had to be developed in consultation with the Commission. Service standards and utility rates were determined by the Commission and were to provide the company with a reasonable rate of return on equity after meeting all expenses, including depreciation and debt charges and earn a limited return on equity. The Commission also had regulatory powers over construction standards as they related to new facilities, as well as over the system of regulatory accounts to be maintained by the utilities. These were to be in the form prescribed by the Federal Power Commission of the USA. This provision was to address the problem where the company was able to increase its rate base by revaluation of its assets in 1951 and 1961 in order to increase its returns8. The Commission carried regulatory powers over disputes between the utility and its consumers and finally it was a statutory requirement to ensure that due regard was given to the needs of the country for expanded electric services. These were radical and fundamental new regulatory innovations, especially for a country embarking on self-government for the first time. Swaby (1981)9 stated that the new regulatory structure: “indicated that the government wished to attempt to exercise regulatory control over the privately owned utilities in a manner based on the North American precedents, combining the powers of the Federal Power Commission and the Securities and Exchange Commission in a manner subject to interpretation against a large body of law and practice built up in the USA”. 201 The Commission operated until 1975. During its life the major issue, faced was applications for rate increases. The JPUC Act required that ratemaking be handled through quasi-judicial public hearings, which were not a feature of the English and Commonwealth jurisprudence. The company was also required to provide development and financing plans as part of its submission for a rate increase. At the time of granting of the licence in June 1966, the Stone and Webster Company was the holder of the largest block of shares. The Board of JPSCo was also made up of mostly non-resident directors. JPSCo until then was a subsidiary of the company registered in Canada. Under the new licence, the company not only had to seek local registration, the majority of its Board of Directors also had to be Jamaican citizens as part of a public policy of localisation of management. The first application to the JPUC was made in 1969; however, the application was postponed after a preliminary hearing. The application was resubmitted in 1970 and the hearing lasted to the end of 1970 when the application for rate increase was rejected. A second rate application was made in 1972 and on this occasion, JPSCo was successful in obtaining a 25% rate increase, the first rate increase for several years. The duration of the proceedings, however, went beyond the anticipated six months stated in the law. With the sharp rise in oil prices in the early 1970s JPSCo was allowed changes to the fuel adjustment clause, and this change provided for amendment to the method of calculation .As a result the 60-day period for adjustment was reduced to a 30-day period. This was followed by a third rate increase application in 1974 when a 39% rise was approved. Between 1970 and 1975 the cost of electricity went up from 1.48 Jamaican cents per kWh to 6.70 cents per kWh for residential consumers. In 1975 industrial users paid 4.5 cents per kWh. The introduction of the JPUC brought into play the American style public hearing procedures. Learned Counsels represented both JPSCo and the Secretariat of the Commission. One of the immediate consequences was an adversarial relationship with sharp areas of conflicts between the utilities and JPUC. Conflicts developed with respect to the definition of the rate base, the accounting procedures adopted, the determination of cost of capital and the procurement practices of the two utility companies. 202 Whereas, the US utilities under a rate of return price fixing regime, were required to show their assets at original costs, ignoring all revaluation – JPSCo’s management carried out periodic revaluation at current replacement cost and this allowed the firm to inflate the value of its equity to support higher dividend payments10. The Secretariat levelled charges against JPSCo’s management of improper asset accounting, the use of transfer pricing, and the practice of waiting for demand to clearly establish itself11. The result of this quasi-judicial process was that Jamaica’s utility regulation came to be characterised by lengthy and costly rate hearings12. The World Bank in its review of the regime came to the conclusion that American style regulation was inappropriate for Jamaica and that the system had proved to be a failure. The Bank (1997)13 stated that: “Jamaica lacked the other institutions needed to make such a system workable. Whereas the US system has a variety of constraints on regulatory discretion (including well-developed rules of administrative process and constitutional protection of property rights, Jamaica had no checks and balances on Commission decision, the result was the price controls became progressively more punitive to the point that in 1975 Jamaica’s largest telecommunications operator was relieved to sell its assets to the government”. The shareholders of JPSCo were also more than willing to sell their shares to the state when government decided in 1974 to acquire the outstanding stocks remaining in private hands. This development more or less marked an act of regulatory expropriation. Regulation of the vertically integrated utility in Jamaica has therefore proven to be a difficult exercise. State Ownership and Government Failure Under the socialist ideology, several arguments were advanced in support of state ownership of utilities in Jamaica. Firstly, industries such as electric utilities, which are natural monopolies having opportunities for economies of scale should be operated by one vertically integrated firm. As these enterprises formed the “commanding heights” of the economy it was considered preferable by the government to have the state own and operate such firms, because of the inability of private firms to address the wider social and development objectives of society. The energy sector, telecommunications, water and airports were considered essential services and could not, it was claimed, be left to the “hidden hands” of the market. Secondly, the small size of Jamaica’s domestic 203 capital market and the reluctance of domestic investors to invest in low yield long gestation investment it was argued led inevitably to foreign direct control. Thirdly, the agenda of the transnationally owned utility and the objectives of the state often came into sharp conflict as the transnational objectives frequently lacked developmental vision. Jones (1974)14 states that: “Whenever the state involves itself in the economy, it immediately signals some motivation to engage in activities of production, accumulation and the creation or maintenance of conditions for these processes. The general motivation is always related to strategy, to structure and to some potential political conflict. As such the motivation has an ideological content ------socialist oriented regimes of the Commonwealth Caribbean (e.g. Jamaica and Guyana) rationalise the public enterprise strategy on the basis of their socio-political ideological outlook”. Brown (1981)15 also points out that one argument in favour of public ownership is that: “it reflects in large measure the greater responsibility for accelerating economic development which was assumed by the state as a consequence of political independence”. Although Jamaica in the 1960s had imported the 1940 British Labour administration policy of public ownership of economic activities, the policy was never pursued on ideological grounds until the 1970s. The replacement of private ownership with public ownership, especially of the monopoly utilities came to be seen as the most effective policy to secure the efficient operation of the industry, whilst at the same time serving the public interest. As with the UK experiences no formula was developed to resolve the inherent conflict of the two objectives. With state ownership of both utilities, the decision was taken in 1975 to transfer the powers of regulation from the JPUC to the portfolio minister, the reasoning being that there was no requirement for an independent government appointed agency to regulate the operations of a publicly owned company. Although the JPUC Act remained on the books up to the passing of the multi-sector regulatory Act in 1995, no Commissioners were appointed and hence the Commission became dormant. During the period 1975 to 1995 the powers of regulation remained under direct control of the utilities sector minister. At one and the same time, this Minister was responsible for 204 protecting investors’ interests, carrying out shareholder monitoring, whilst controlling monopoly power of the utility and protecting consumers’ interests. The only independent source of addressing consumers’ concerns against the bureaucracy of the state and the monopoly of utility was through the Office of the Utilities Ombudsman and his authority was limited to conciliation, as he had no powers over the utilities or the sector minister. With the change to public ownership a new all-inland licence was issued to the company in 1975. This new licence provided for the portfolio minister with responsibility for the utility to be the industry regulator. A number of other changes to the licence were also made. The provision regarding shares being made available to citizens of Jamaica was omitted. An 8% return on rate base, which was part of a 1974 amendment, was subsequently eliminated. In fact all the provisions relating to rate base and rate of return were removed and prices were no longer subjected to any limitations. Despite the removal of the 8% rule, determination of rates, however, came to be guided by the 8% return per annum on revalued plant rule, being a World Bank condition on its loans to JPSCo. The licence granted after 1975, therefore, moved away from the American rate base system of rate making through public hearings, and gave considerable flexibility and authority to the portfolio minister. Although the Ministry of Public Utilities established an Advisory and Monitoring Unit to review and advice on utility tariffs and investment, the basic issue of regulation during this period was that consumers became concerned that their interest was no longer taken into consideration, and this triggered regular protests. The Minister came to be seen to protect the interest of the investor at the expense of the consumers. Over the period the utilities were never allowed to operate as autonomous commercial firms and effectively became an arm of government itself, with high levels of ministerial intervention in pricing, investments, employment, wage determination and procurement. In much the same way as in the UK in the post-war years, the long-term commercial interest of the enterprises was subordinated for broader short-term political and macro-economic objectives. State ownership of the electric utility and ministerial regulation between 1974 and 1992, when the decision was taken to liberalise the new generation market, did not resolve the problem of 205 providing efficient utility services. The loss making, which resulted was not only due to subsidy pricing policies but also to poor management, poor maintenance of the system and dis-investment. The pricing policy of the Peoples National Party (PNP) administration which required the utility to meet only operating cost and contribute 30% of its capital needs, effectively reflected crosssubsidisation by tax payers. In 1994 the PNP administration had also introduced a direct subsidy to JPSCo to ease the burden of the rapid escalation in oil prices. Even with the subsidy, the 1974 price increases of 39% were followed by a 42% increase in 197616. In order to cope with the adverse financial impact from the rapid escalation in oil prices on JPSCo, as well as the negative impact from the decline in the exchange rate, electricity prices had been separated into a fuel clause element and a rate base element, with automatic monthly adjustments for the fuel clause being passed on to consumers in their monthly bills. With the automatic increases from the fuel clause consumers experienced sharp increases in electricity tariffs in Jamaican dollars. The industry’s monopoly in product market facilitated trade union opportunism in that the unions were able to secure wage increases, which could not be justified, by increases in productivity. For example, in 1976 wage increases awarded to JSPCo workers averaged 71%, whilst that of the urban transportation utility averaged 90%17. The size of the fiscal deficit and the foreign exchange burden at the time was such that they served to freeze major upgrading and expansion plans of the utilities. The JLP administration, which managed the economy for most of the 1980s, reversed the subsidy pricing policy under pressure from the multilateral lending agencies with a new policy, which required the utility, and other public enterprises to earn 8% real return. The 8% return came to form one of the World Bank loan conditions in the structural adjustment programme. With the sharp devaluation of the Jamaican dollar from J$1.78 to J$5.13 against the United States dollar in 1984, electricity prices experienced two further sharp increases, first by 40% in January 1984 and then 54% in May that same year18. While theoretical reasons have been advanced to support the case for privatisation more than anything else, however, it has been the large sums of capital needed to meet the expansion and upgrading of the utilities and infrastructure services, telecommunications, water, airports, and electricity, which forced the Jamaican bureaucracy to accept deregulation and privatisation, rather 206 than any belief in the inherent superiority of private capital and competitive markets. The decision to encourage the introduction of IPPs into the generation sector in the early 1990s was not based on a policy intended to provide for increased competition in the industry, but was based primarily on the need to secure capital for the development of the generation sector. State capitalism had provided major economic power to a group who in the past were disenfranchised from the “halls of power” and this group (chairmen and board members of the public enterprises) was not predisposed to see this power disappear without offering strong resistance. Some of the managers had come to reward themselves with compensation packages, which at times became an embarrassment to the administration in power as was the case reported at the National Investment Bank of Jamaica in 2001 and which led to the resignation of two senior public sector managers. Utility capacity studies in early 1990 indicated that US$257 million of capital expenditure was needed over the five year period up to 1997. This investment was needed to meet increased demand and replacement of obsolete plant, as well as to ensure that the utilities did not become bottlenecks in the system, constraining future economic growth. The total estimated new capacity projected for the 10-year period to 2000 was 1052 MW. In the first five years the projection was for 440 MW of which 230 MW or 50% was to meet requirements for replacements of old and obsolete plants. The overall capital projection was US$1 billion for the 10 years19. With serious restrictions imposed by the Treasury and with a very weak financial structure, the option of the utilities competing in the private commercial markets for capital was not a practical one. Industry Structure and Deregulation of Generation At the time deregulation was considered in 1990, the industry consisted of a single vertically integrated publicly owned utility, with 443 MW of installed capacity. Approximately, 68% was steam powered; 25% diesel/gas turbines and 5% (24 MW) hydro. Peak demand in 1990 was 325 MW, giving a reserve margin of 35%. 207 Private operators, mainly the mining and sugar companies generated electricity for their use and had an additional installed capacity of 265 MW20. Small exchanges of power took place between JPSCo and those private operators, which were connected to the national grid. Generation accounted for approximately 70 per cent of system costs. Fuel in turn accounted for 60 per cent of generation cost. Fuel was supplied to JPSCo under the San José Accord, a bilateral agreement with Mexico and Venezuela. This Accord provided Jamaica trading concessions on its fuel oil purchases and the agreement has been in place since the end of the 1970s. The transmission system consisted in 1990 of 170 circuit miles (272 km) of 138 Kv lines and 445 circuit miles (712 km) of 69 Kv lines, while the primary distribution system consisted of 7000 miles (11200 km) of distribution lines. The Rural Electrification Programme Company Limited (REP) provided subsidised distribution and connection to rural areas and formed part of a programme introduced in the late 1960s to increase the percentage share of homes then connected to the electricity system from 20 per cent to more socially accepted levels. There were 305000 connected customers in 1990, increasing from 116, 000 in 1970. For the year 1990, the level of access to electricity was estimated at 50%. In the 1970s the historical growth in demand was a modest 3.3%, followed by 2.2% to year 1985 and increasing to 6.1% by 199021. For successive governments, prices were held down for most of the period between 1965 and 1974, (a period of private ownership). JPSCo was therefore, forced to operate at a loss. Although intended as part of a policy to redistribute income to the poor, the main beneficiaries from this cross-subsidy policy were the middle classes, the main users of electricity. For the period 1974 to 1980 the period of public monopoly ownership, the financial performance of JPSCo was inconsistent, with profits in some years and losses in other years (majority years being loss). JPSCo, with its inadequate source of income had to rely on the government for almost all its capital needs during this period. With inadequate funds and under-maintenance in the system, efficiency fell sharply and was accompanied by load shedding, frequent intermittent power outages and irregular voltages. Systems losses varied between 17% and 22% and over 50% of this was non-technical loss. There were no increases in the tariff over the period 1985 to 1990 apart from the fuel clause adjustment, with the result that the financial performance of JPSCo up to 1990 continued to present 208 a poor state of affairs. A 37% increase in the basic tariff was granted in 1990 with the result that prices came to reflect long run marginal cost. The previous tariff setting system, which was based on declining block structure did not reflect marginal cost and was abandoned following a major tariff review in 1989. Electricity prices for residential householders in 1990, after the increases, amounted to just under US¢14/kWh with bulk electricity rates of US¢7.5/kWh. At the time of the first utility privatisation, that of telecommunications in 1985, no consideration was given to new entrants and the introduction of competitive forces in the industry. In fact, government went on to vertically integrate the two telecommunications operating companies; one in international telecommunications and the other serving the domestic market, as a single monopoly, in addition to providing the new owners with a 49-year exclusive license. This decision and the method of privatisation came in for considerable criticism from the public and the media in the period 1989-91, with the result that government was forced to give more attention to the industry structure when the state came to consider the electric utility deregulation and privatisation. Changes in Jamaica’s electricity sector commenced with deregulation in early 1992 with the World Bank energy sector deregulation and privatisation project. Entry into the generation sector was relaxed, allowing for the initial purchase of 130 MW of new generating capacity from independently owned private power producers. The bilateral funding agencies, World Bank, Inter-American Development Bank and International Finance Corporation provided over US$200 million in the form of credit to facilitate entry by the IPPs. The introduction of IPPs into the system followed a course of competitive bids and 20-year “take and pay” contracts, backed by Government of Jamaica guarantees. In effect at this point Jamaica had graduated from the single state owned franchised monopoly to the single purchaser phase. Three plants came on stream between 1993 and 1996: a twenty year contract for a US$103 million 72 MW medium speed diesel plant next door to the main JPSCo power station at Old Harbour, and developed by Jamaica Energy Partners Ltd., (JEP) a locally registered company of Wartsila Power Development Inc.; a twenty-year contract for US$144 million 60 MW low speed diesel plant at Rockfort, Kingston and owned by Jamaica Private Power Ltd., (JPPL) a joint venture of Mohawk Power Company, International Energy Finance Ltd and US Energy Corporation and a 3-year contract for a US$30 million 42 MW turbine plant at Bogue, St. James developed by Kenetech 209 Energy System. Inc22. Kenetech later sold 99% of its investments to another US based investor Quixx Corporation. All the contracts went to overseas syndicates; mostly American interests. The large auto-generators such as the sugar factories and the cement plant that produced supplies in excess of their own demand were also allowed for the first time to sell bulk electricity to JPSCo. Problems with the Introduction of the Single Purchaser Model Following the decision to encourage private financing of electric supply in order to relieve the government of the burden of financing the sector’s needs, a number of measures were taken to remove some of the barriers which were seen to inhibit the flow of private capital into the sector. The most critical of the problems were insufficient security to safeguard foreign direct investments, the limited size of the domestic market and the absence of a legislative framework for the evaluation of projects and the independent regulation of the sector. The introduction of the Office of Utilities Authority Act (OUR) in 1995 and the decision of the Government to provide sovereign guarantees were two of such measures. In developing the IPP transaction the government faced four key issues. First, there was a requirement to delegate authority to provide for a non-resident private commercial entity to make withdrawals from a World Bank loan to the letter of credit bank. Government eventually concluded that granting the authority was the only practical solution. Second, there was the requirement of guaranteeing JPSCo’s payment obligations to the IPP and the continuance of the guarantee after privatisation. Government found it easy to accept the guarantee requirement up to the time of privatisation of JPSCo. The period after privatisation presented a problem. Eventually it was agreed that a clause providing indemnification be included in any future sale agreement of JPSCo as a counter-guarantee of these obligations. Third, the requirement was raised for the project company to pay penalties to JSPCo for failure to supply at a rate equivalent to the economic cost of the loss of capacity. Such a clause made the cost of the likely penalty to be applied several times the value of the IPP. This requirement was eliminated as none of the bidders were prepared to undertake this obligation. 210 The fourth issue was the question of the price to be included in the PPA for the sale of bulk power from the IPPs to JSPCo. In the determination of bulk electricity tariff, comparisons have been made by the Jamaican bureaucrats between JPSCo’s cost of production for generation voltage and the charges required for bulk electricity from the IPPs. The JPPL’s plant at Rockfort charged US cents7.10/kWh, whilst the charge for JEP’s Old Harbour plant was US¢8.35/kWh, compared to JPSC’s, reported generation production cost of US¢7.3/kWh23. The government failed to take into account that JPSCo’s average unit cost, as stated are sunk cost with arbitrary method of cost allocation, reflecting historical accounting, with almost fully depreciated assets and with highly subsidised capital. It was, therefore, incorrect to adopt this method of accounting as the basis for cost comparison. Government also provided financial guarantees to JPSCo’s debts, most of which were obtained at non-commercial rates. In fact JPSCo financing, most of which came from multilateral sources, carried much lower rates than commercial market rates, at the time varying between 2% and 7%. Debt finance, which was used to finance the greater portion of IPP investments, varied at the time between 11% and 13% in the private financial market. Government financing through the multilateral agencies to JPSCo was provided at interest costed at 6% to 8%, a difference of approximately 5% from the IPP debt financing cost. Over the years JPSCo had declared virtually no dividend to the state; therefore, its equity cost (a subsidy) was zero, whereas the equity returns, taking Jamaica’s risk profile would have been of the order of 25%. When Jamaica went to the private bond market in the latter part of the 1990s it had to pay interest rates of 11% to 13%. It is the unit cost of production that JPSCo would have incurred for the same generation capacity at commercial market rates of interest that is relevant - the utilities avoided cost. In the USA the standard procedure then adopted for such evaluation has been that of long run average cost of new investment of capacity as would be constituted by the utility. The general principle applied by the US Federal Energy Regulatory Commissions in 1980 required that the price the utility was obligated to buy from a qualifying power production facility should reflect the utility’s avoided costs (the avoided cost principle) by purchasing from an independent supplier, compared to the best alternative available24. This determines the reservation price. In the USA the prospective utility tenders for a solicitation for a fixed amount of additional capacity and selects a winner through competitive bidding or negotiates with a pre-qualified pool of applicants. 211 It was also incorrect to make the comparison with the World Bank’s 8% return target rate. The fixed assets would more or less approximate to both the debt and equity employed by the IPP and because the cost of debt obtained by government for JPSCo is usually lower than the cost of equity, the return on net fixed assets will be significantly less than on equity returns. The purchase price of electricity from the IPPs reflected two-part pricing, consisting of a base element and an energy element with an indexation formula for the base element. The base element allows for “cost pass-through” as cost increases or cost savings which are beyond the direct control of the power supplier, such as fuel-oil is automatically passed to JPSCo. At the same time, the energy element ensures that additional cost resulting from poor performances of the IPPs is not passed to the buyer and in turn the seller takes the benefit of good performances. The net effect is that there is no specific rate of return guaranteed; the level of efficiency therefore ultimately determines the supplier’s rate of return over a given period. This, however, was projected to be between 20% and 25% on equity, which were typical for private power projects in the 1990s. Private power purchase through a long-term contract resulted in competition for new capacity and allowed the Jamaican system to take the first step to a more competitive industry structure. Government, however, could have allowed for common carrier status to the vertically integrated JPSCo transmission and distribution lines so that large-end users could procure electricity from any willing seller. This bypass policy would have provided increased levels of competition that JPSCo would have had to contend with in the market. Although the electricity network remains a natural monopoly, transportation of transmission and distribution voltages could have been opened to the market through non-discriminatory interconnection policies. The Case for Unbundling the Utility In 1991 Coopers and Lybrand of the UK was contracted to consider the most appropriate structure for privatisation of JPSCo and the most appropriate regulatory arrangements for the industry. The consultant’s recommendations, which were presented in 1993, called for unbundling of the industry into a fully competitive generation sector and a regulated transmission and distribution monopoly. Coopers and Lybrand (1993) 25 recommendations were stated as follows: 212 “Following from our considerations, analysis and discussion with JPSCo, we have concluded that a single operating company (Genco) should be formed which would own all JPSCo’s existing generating plant, together with the proposed gas turbine at Hunts Bay, with the remaining assets grouped as a Transmission and Distribution Company (T&D), responsible for transmission and distribution and supply on an all Island basis”. Coopers and Lybrand’s rationale for the vertical separation of generation without horizontal unbundling of generation was that liberalisation and entry into the generation market would have been sufficient to eliminate the future monopoly of a privatised Genco, as their projection was that 70% of the generation upon liberalisation would be supplied by IPPs and co-generators and this would be so even if the incumbent Genco was allowed to bid for incremental capacity. The creation of a single Genco it was argued would have created less disturbance to the status quo, would have resulted in less transaction cost, minimised the level of disruption to management, (a group which was fearful of the privatisation), would have provided for a more financially attractive package to take to the market and would have preserved economies of scale in the industry. These advantages, it was argued outweighed the disadvantage of market power from a single enterprise. The longer term advantages of a competitive structure and the overall benefit to consumers would appear not to be seen to have been important. What was more important was to offer an attractive package to the capital market and placate the management group. The consultants also came to the conclusion that there were no overriding reasons for the T&D Company to own any generating capacity. Additionally, a new multi-sector utilities regulatory agency, the Office of Utility Regulation, was to be established by statute, headed by a single Director General (DGUR), modelled on the UK system, and effectively rejecting the multi-member commission structure of the previous US style Public Utilities Commission. In order to ensure the independence of the DGUR, he was to be appointed by the Prime Minister, after consultation with the leader of the opposition, and the grounds for dismissal were to be strictly limited to misbehaviour or incompetence. As well as the legislation to establish the OUR, specific industry legislation was also prescribed for the electricity and other utility sectors to empower the DGUR to licence and fully regulate each sector and in so doing remove all requirements for ministerial 213 licencing and regulation and reduce the role of ministerial intervention to one of establishing broad industry policies. The relationship between the Genco and the T&D was to be on the basis of long-term power purchase contracts with the T&D acting as the single purchaser of all generated electricity from the new Genco and the independent IPPs, with dispatching on economic merit order basis. Additionally, the T&D was also to be responsible for retailing electricity to final consumers. The new legislation was to provide for competitive procurement and independent evaluation of new capacity. A transitional period, up to the point of privatisation was to be provided during which the Genco and the T&D Company would be established as separate and independent businesses, to facilitate shadow operation prior to privatisation. External separation and vesting was targeted for April 1994. In this new structure the role of the DGUR would be to approve least cost development plans by the T&D Company, approve the PPAs between the T&D and the generating companies, monitor the competitive bidding process, monitor tariff levels in the PPAs, establish tariff for retail electricity and monitor and enforce licence conditions. JPSCo, however, engaged its own consultant; Price Waterhouse Utility Economics and Financial Consultants Group (PW) of Washington, USA in the 1990s to comment on the most appropriate industry structure for its privatisation. Price Waterhouse conclusions were even more conservative than those of Coopers and Lybrand. In their conclusion PwC (1994) 26 stated: “based on our experience with other electric systems throughout the world, as well as the literature on this subject, the market for generation in Jamaica seems too thin to develop competition that would eliminate the need for regulation. Furthermore, numerous studies have shown that the minimum unit size for achieving economies of scale in electricity generation is approximately 400 MW. If a number of firms were to compete to generate electricity, the market share would be small and the resulting sizes will be well below the optimal size -------- Competitive generation is not an attractive alternative for Jamaica”. Price Waterhouse not only argued for sale of shares of the existing JPSCo to a broad based public, with a single strategic investor being offered 51% of JPSCo’s shares, they also argued for continued 214 government equity participation, the justification for the latter being that the Government’s equity ownership would ensure that the Government’s social objectives were met. Privatisation of the single integrated JPSCo, it was further argued would be politically and administratively easier as this simplified the sale transaction; planning synergies in the present integrated structure would be lost from unbundling, and the privatisation process would progress with much difficulty if the sale was for more than one unit. PW in its analysis, however, was clearly using electricity economics which were inappropriate and which was derived from conditions of the 1980s. They had clearly ignored the development of combined cycle gas turbine technology, which was well on the way to changing the economics of electricity generation markets. Reference to US experience was clearly irrelevant to Jamaica. With strong persuasion from the management and bureaucrats of the various ministries at a Policy Retreat on 26th January 1995, the policy makers rejected the Coopers & Lybrand’s recommendations and abandoned the strategy of restructuring before privatisation. The positions advanced by the bureaucrats were that the precedent set for electricity industry restructuring was derived from developed countries with large energy markets where economies of scale opportunities may have been exhausted and that competition offered efficiency gains that more than offset the benefits of the loss of internalisation and additional transaction cost. These gains were said not to be appropriate for small developing countries with small utility markets of less than 1000 MW. The arguments developed by Price Waterhouse, that of reduction in benefits from economies of scale, attractiveness of the integrated utility to credible foreign investors, ease of privatisation and increased risks from a vertically separated transmission and distribution company, were also presented at the retreat by the bureaucrats and especially by the JSPCo’s management to support the case for retention of the single vertically integrated company. The transition from public to private operation was also stated as requiring higher rates of return and it was not seen that the elimination of X-inefficiency from full private operation of generation would deliver higher rates of efficiency; therefore, the consumer it was argued would be required to pay higher prices for electricity. The higher electricity rates it was claimed would result in government having to face political problems with consumers. The proceeds, which the state would attract from the sale, it was further argued, would not be related to a fair value of the assets. Instead, the price would be based on the investor’s perception of the net cash flow from the acquisition of 215 the business. A faster sales process was also claimed to be possible with sale of the integrated company to a single strategic investor. Government would, therefore, have difficulty explaining the lower expected sales proceeds to the electorate. Further the bureaucrats argued that the small (T&D) Company would not be attractive to potential investors and that even if divestment of the unbundled generation system were to take place, the T&D company should not be precluded from future entry to the generation market as it could face future problems should the privately held companies fail to honour their contracts. Alternatively, it was argued that the privately held generating companies could collude to hold the T&D Company to ransom and endanger the security of the system. There is no empirical evidence to support these claims. In deciding on the appropriate privatisation policies, government was led into accepting the short-term consideration of maximisation of sales price over an industry structure that would have delivered competitive prices and ultimately superior services to the consumer over the long term. The Coopers & Lybrand consultants at the time were not by any means suggesting radical industry restructuring as was the earlier case of the UK. It merely sought to introduce a supportive environment for entry competition at the generation end and provide for open access to the transmission and distribution network, with the ultimate beneficiaries being the consumers of electricity. The arguments provided by the bureaucrats were not based on any rigorous economic analysis or empirical evidence and in the main were based on historical notions of electricity economics. It is a well-known position that bureaucrats and the managers of public enterprises who derive their power and prestige from state capitalism will resist efforts to unbundle industries and to expose them to competition. Given the opportunity, they will argue either for the enterprise to continue as a state monopoly or be transferred as a private monopoly. It was these same arguments that the utility managers had earlier offered and which led to the privatisation of the telecommunications industry as a single vertically integrated monopoly at undeniable future cost to the Jamaican consumer. The British utility managers had posted the same dire warnings about unbundling the England and Wales electricity system and the economic consequences of doing so during the UK electricity industry privatisation27. The only additional twist in Jamaica’s case was that the small market size of the 216 Jamaican economy was put forward to strengthen the claim against unbundling of the vertically integrated system. Competition is the best-known mechanism to maximise consumer benefits and limit monopoly power. The effects of the new technologies are not only evident in telecommunications; they are also equally applicable to the electricity utility. Bolivia, with a lower per capita income of under US$800 (1996), compared to Jamaica at US$2000 and with a small electricity market of the same size as Jamaica, 600 MW, demonstrated in 1995 that a small system can be restructured into several competing firms, without any significant increased costs from loss of scale economies or punitive levels of transaction costs (see page 292) Should the publicly integrated utility be allowed to enter the market for generation, there would be the need for an independent authority to consider and evaluate bids for new capacity. There was the suggestion that the repowering of the Old Harbour and the Hunts Bay plants should also take place under the framework of competitive bids with JPSCo bidding against the competition. JPSCo management at the time did not welcome this suggestion and opposed competitive tendering for the repowering work. If JPSCo were to be involved in generation, IPPs would always be suspicious of the integrated utility’s administration of the power purchase contract. There would be too much scope for opportunistic and discriminatory behaviour on the part of JPSCo. Integration also complicates regulation. If JPSCo were to bid for new generating capacity the question, as to how this would be financed would continue to arise. Most of the soft loan financing opportunities from the World Bank and the Inter-American Development Bank then was being sharply reduced. The policies of the two Banks at the time also called for generation activities to be financed from the private capital market and both agencies for the first time were in the process of structuring new approaches so that private companies could benefit directly from their financing windows. Once generation is separated from the T&D Company then the question of the system security arises. It is inevitable that the total size of the system to be operated and maintained by the IPPs will have to be such that it provides reserve margins for emergencies and peak demand, as well as providing for load balancing. The question of security of the system can be addressed in the power 217 purchase contracts. In fact there may be some advantage in having several operators at the generation end, so that in an instances of industrial dispute in one of the IPPs, Island wide disruption of electricity may be averted The argument that splitting up the vertically integrated electric utility might involve sacrificing economies of scale, and that separation would bring increased production and transaction costs which will offset the gains of competition, is at best of dubious merit, since the existing structure itself resulted from political and administrative arrangements. The policy makers failed to have taken their decision based on the options, which from a long-term perspective would have delivered the lowest possible prices, relieve the state of the responsibility for financing or guaranteeing the risks associated with investment in the generation sector and provide consumers with reliable electricity supply. The decision reflected a classic public choice theory case which points out that beneficiary interest groups in capturing the decision making process and being rational utility maximisers will ensure that their special interest prevails over the wider public interests. None of the lessons from the operation of the privately owned and integrated electric utility especially as a foreign owned entity in the period between 1960 and 1974 seemed to have been taken into consideration by the decision makers. The transfer pricing practices, the conflicts which developed between national objectives and the transnational’s objectives and the abuse of market power on the part of the foreign owned utility operator, seemed to have been buried with history. The decision also reflected the mistrust of the socialist disposed bureaucrats with competition and the hidden hands of the market. The bureaucrats continued to feel that they could succeed where the market has failed. Much of JPSCo’s life after 1950 as an integrated monopoly has been one of inefficient operation, prolonged periods of power outages and under-maintenance. JPSCo performances in terms of transmission and distribution line losses at levels varying between 17% to 20% for most of the 1970s and 1980s, compares very unfavourable, to figures of under 10 to 12% in developed countries28. These losses result from illegal connection, unmetered use, theft and inefficient transmission and distribution systems and can be eliminated by good management practices. In fact line losses increased from 13 per cent in the early 1970s to 20 percent in the late 1980s and declined to 17% by 1996. 218 Jamaica’s electricity tariff and line losses compare very unfavourably with that of Bolivia in 1996. The average retail tariff in 1996 was US¢4.50/kWh in Trinidad and Tobago, an oil producing country29 and under US¢7.0 kWh in Bolivia. Line losses in Bolivia were also under 12%. Failure to effect separation is, therefore, another Jamaican case of “missed opportunity” of introducing an appropriate industry structure in the Island’s utilities before privatisation. Aborted Privatisation In 1995 government, eventually through the direction of the National Investment Bank of Jamaica (NIBJ) and a specifically created Enterprise Team, initiated privatisation of the vertically integrated JPSCo. An internal NIBJ memorandum stated that the objectives of privatization were as follows: a) Sell at least 51 per cent of the company’s ordinary shares; b) Relieve the budget from the financial burden of upgrading and financing expansion of services; c) Give the enterprise a higher capability to attract domestic and foreign direct investment; d) Optimise returns from the sale; e) Secure the lowest possible price for electricity to consumers, consistent with available commercial financing and the establishment of the systems reliability at its economically efficient level. As some of these objectives are conflicting, it was inevitable that the final decision-making would be fraught with difficulties. Advertisements for pre-qualification were issued nationally and internationally week July 23-29, 1995. Fourteen submissions were received. Subsequent to the receipt of these proposals the Divestiture Enterprise Team which was established by government pre-qualified five applicants. On 6th November 1995, all five applicants were supplied with copies of the “Request for Proposal” with a deadline for 5th January 1996 for their responses. Applicants were advised that the selection of the successful bid was to be based on attractiveness of the offer price for the shares, the attractiveness of the development plan, the level of commitment to Jamaica and commitment to establishing linkages with local industries, the technical and managerial competence of the bidder to operate electric utility, and the level of technology transfer and local staff development anticipated. At the close on 5th January 1996 two proposals were received from 219 Houston Industries Energy and Southern Electric International both of the USA. Some of the prequalification conditions acted as a disincentive to attracting investors. During the negotiating process, which followed, government had sought to obtain a counterguarantee relating to the JPSCo’s loans, already guaranteed by the state in relation to the Independent Power Producers projects. Both bidders failed to provide the appropriate counterguarantees. In subsequent negotiations, both bidders stated that a counter-guarantee by their principals carried a price, which would either have to be passed through the rate to consumers, or deducted from the offer price. This requirement was seen by government to be a “deal breaker” as future IPP investors would also be seeking government guarantees. Without this guarantee the government would continue to bear much of the risks in investments, which it held no equity interest. The problem, however, is that the highly leveraged financing regime of the IPPs makes these guarantees essential. Both proposals failed to provide the parent cross-guarantee to the government’s counter-guarantees, which were provided to the existing IPP operators. Without a parent cross-guarantee or the government counter-guarantee it would have been difficult to ensure competitive procurement of new capacity. Both bidders’ offer price for the shares was also lower than the government’s reserve price. While the sale of a fully integrated company may seem comparatively more attractive in terms of privatisation income to government, there is always complication in determining the value of the business. Investors are not interested in the current sunk cost of JPSCo. It will be the net present value of the future cash flows over a given period, which will determine sale price. Other methods have been used, including using the net asset value and the operating cash flow, together with an assessment of the market, as well as asset value, the profits earned and the stock market share value. In the case of utilities, there are three critical elements to be addressed: the expected price, future demand and the scale of future investment. Market valuation is difficult to achieve in developing countries like Jamaica where capital markets are thin.30 Investors are interested in the potential income-earning capacity of an ongoing business and not in the asset values on its own or either in historical cost valuation or physical valuation. Valuation becomes more important when there is only one bidder. In a competitive bid situation, the bid price is the market price. 220 The price of the shares based on discounted value rests on a whole range of assumptions, most critical of which are the rate of growth of future demand and future tariff obtainable from the utility regulatory agency. The bidders would have pursued a worst-case scenario, contemplating higher risks in the analysis than the assessment by the government bureaucrats, particularly where there is a questionable track record of the regulatory system. These problems have always raised controversy in the privatisation valuation process in developing countries. Investors in utilities in developing countries prefer to lock in a specific rate of return into the bidding contract in order to reduce exposure to risk of regulatory expropriation31. Of the three options available for tariff regulation; rate of return regulation, price cap and negotiated contract, price-cap regulation is being used more and more as the preferred option. Coopers and Lybrand also recommended price cap regulation, as this is seen to be less costly and less time-consuming to operationalize and has the added advantage in providing incentives for more efficiency when compared to rate or return regulation. A major advantage of price regulation from the point of view of the regulatory process is that the JPSCo price would no longer be related to its internal cost of production. There would, therefore be less opportunity of JPSCo as a vertical integrated utility to influence its prices. Although the recommendation for a new regulatory structure was advanced as early as 1991, up to 1995 government had failed to establish an independent regulatory regime for the utilities to replace the Public Utilities Commission. It even appeared at one stage that the emergence of a transparent independent regulator was doubtful and in absence of regulation by contract, investors would inevitably perceive a high risk in a situation where the new regulatory regime carried no track record. In such an environment investors will evaluate income flows under the worst-case scenario and this in turn is likely to give a lower offer price than the government’s reserve price. A regulatory regime, which provides for a high level of ministerial and political intervention, will also raise concerns about regulatory expropriation. Where the regulatory capacity is inadequate or subject to political interference, a negotiated concession (regulation by contract) may be used, which is likely to be more attractive to the foreign investor, than relying on legislation and discretionary decision of a new regulator. 221 In the end government opted for a multi-sector industry regulator, to regulate the utilities and transport sectors. The structure also provided for a single regulatory decision maker, a Director General. Jamaica and the Caribbean in their adoption of multi-sector agencies have been pioneers from a developing country perspective. Unlike the UK, where each industry carried its own regulator, Jamaica has opted for a single regulatory agency to regulate the utilities and transport industries. Jamaica chose the multi-sector structure as it was seen to be less costly to operate, provides for more consistency in the regulatory decisions, and ensures that a certain distance is developed between the regulatory agency and individual sector ministries. Five or six industry regulators in a small country with a small market would have resulted in a doubling of regulatory costs on the consumers and would have presented serious funding and staffing problems, most likely leading to an unsustainable regulatory regime. Up-to 2000, government had failed to introduce the electricity industry specific regulatory legislation, which was needed to provide the detailed regulatory framework for the industry32. The uncertainties as to the regulatory regime would have influenced the price proposals of the bidders. The price proposals of both bidders failed to reflect appreciable improvements (lower tariff) on the existing JPSCo rates to consumers. This was to be expected in the short term, as JPSCo costs of capital as shown earlier are heavily subsidised. One would, however, expect that Xefficiency would follow from private management and superior technology which, in the long run, should allow the privatised utility to obtain higher levels of output from existing resources and hence lower long-run average cost. Government was faced with the decision to accept one of the bids or to reject both offers. There was never any enthusiasm on the part of utility managers and the ministry bureaucrats to transfer JPSCo to the private sector. State capitalism is still preferred by many from this group, because it offers them greater economic power and personal benefits than would accrue to them under private ownership and control. The short timetable which was set for the privatisation also appeared to have been inadequate to resolve the complex issues thrown up in the negotiations. Public Ownership with Internal Management Performance Contract 222 Government eventually announced in Parliament on 22nd October 1995 that it had decided not to pursue privatisation of JPSCo at that time. The reasons given were that the offer price was too low; the bidders proposed retail prices were too high, that the bidders were not willing to relieve the government of its IPP counter-guarantee commitments and unacceptable dividend policy. The privatisation was, therefore, aborted. JPSCo was to continue to operate as a vertically integrated utility, except that the relationship with government was to be put on more “arms-length” basis. Government also announced that it would seek to re-list JPSCo shares on the stock market. If this were to have taken place there would have had to be at least a 20 per cent floatation of the state’s equity on the Kingston Stock Market. JPSCo historical financial performance, combined with continued state control, certainly would not have provided the appropriate incentives for a successful floatation of 20% of the company’s equity. The Prime Minister, in making the statement, did not elaborate on the new procedures for a more commercial and “arms length” relationship. Interestingly, in 1960 when the railway was made a statutory body, a commercial and “arms length” relationship was also mandated by the administration of the day. This did not, however, prevent political and bureaucratic intervention. In subsequent years, political intervention in railway management eventually led to the collapse of the Jamaica Railway Corporation, and in the early 1980s it ceased to operate. The application of private sector operating principles with the chief executive officer having an “arms length” relationship through an internal management performance contract with the sector minister, which became the main instrument for governance up to then, full privatisation has been the model introduced in New Zealand for many social and economic services and is the approach Jamaica adopted immediately after the decision was taken not to go the route of immediate privatisation. Jamaica’s situation, however, differs from New Zealand’s; therefore the same results could not have been expected in Jamaica. Historically, New Zealand operated many of its utilities as departmental enterprises, i.e. they were not separated from the central civil service. Jamaica moved to the joint stock company form as the institutional structure for several of the utilities from as early as the 1960s. This institutional structure provides the opportunity for the greatest managerial autonomy for the management of state enterprise. Government in theory could also have exposed JPSCo to the threat of takeover and possible liquidation as it did with the Jamaica Omnibus Service 223 Company Limited in the latter part of the 1980s33 so as to put more pressure on management for efficiency enhancing behaviour. Internal management performance contract sets out a procedure for establishing clearly specified objectives for the chief executive officer and the public corporation on the one hand and the objectives of sector minister and the ministry on the other hand. The management performance agreement provided for an average tariff mechanism to hold tariff constant in US dollar terms for three years to 31 March 2000, explicit financial and non-financial targets, regulated operating and performance standards and for JPSCo to operate in a manner to enable it to finance its expansion overtime and pay annual dividends to its shareholders mainly government. Unless these are legislated with checks and balances there will be violation of these agreements if left solely to ministerial discretion. As JPSCo continued to fall under the Public Accounts Act detailed intervention in management by the Ministry of Finance, was still likely and there was no suggestion at the time to exempt JPSCo from this Act. An internal performance contract was eventually signed in 1997; however, the contracting party was not the sector ministry but the privatisation agency, the National Investment Bank of Jamaica. This arrangement had a significant advantage over the traditional structure in that it provided for a neutral and more credible agent to monitor the agreement. Kerf and Smith (1996)34, however, stated that: “in response to growing appreciation of the problems of the traditional public enterprise model, many governments in Africa and elsewhere have attempted to improve the performance of state-owned enterprises through performance contracts with public managers or corporation. These reforms have attempted to give greater emphasis to commercial principles and provide a degree of insulation from shortterm political influences -----------. In the vast majority of cases, however, performance agreements have had a poor record of sustaining reforms. In Ghana and Senegal for example, government reneged on their commitments to, inter alia, increase tariffs and promptly pay bills of government and other state owned enterprise. Problems stem from the conflicting objectives, which the government is tempted to pursue under these arrangements. There is a growing realisation that combining within government the roles of owner, regulator and operator is a poor institutional structure for attempting to operate on commercial principles. In most cases, 224 governments will find it difficult to implement the range of internal and external disciplines on which the effectiveness of corporate entity depends”. Experiences of the UK in respect of commercialisation, “arms length” relationships and performance related operation in the 1960s also proved to be a failure. There are two major problems with performance contracts. Firstly, the workers are major players in the efficiency matrix and they are not bound by the agreements as shown by Kerf and Smith. Secondly, it is difficult to enforce the obligations, especially those commitments made by government because the framework agreement or memorandum of understanding is not usually a legally binding document. The UK and other countries’ attempt to develop an institutional framework, which allowed for progressive improvements in efficiency by state capitalism more than anything else, resulted in a failure to provide strong incentives to the industry and their boards. At another level, it has been a failure to recognise the fundamental principal and agent problem in public enterprises. It is unlikely therefore, that Jamaica would have found the formula to resolve these problems any more than the UK over the long run or for that matter find a solution that would reduce the temptation to use utilities to serve political and macro-economic ends. Jamaica incorrectly concluded that a competitive industry structure is inappropriate as the efficiencyenhancing route for their traditional natural monopolies and went ahead and invited private capital including foreign investors into the vertically and horizontally integrated electric utility. Foreign investors are unlikely to be attracted as minority partners without a management contract; government was forced to reconsider the policy of public floatation of 20% of JPSCo’s equity through the Kingston Stock Market. In pursuing this strategy government made the same mistake as it did in privatising the telecommunications utility as a vertically and horizontally integrated company. This once again will be a missed opportunity35 as once private capital comes on board; government will not be able to take up any future opportunity for unbundling which will surely present itself, either from technological or commercial developments, without transgressing on property rights. In which case government will either have to pay compensation or face expensive litigation without any guarantee that its position will prevail in the end36. 225 Most of the improvements to the reliability of supply over the five-year period up to 1998/99 seem to have emerged as a result of the new capacity brought on by the IPPs. In this period, JPSCo’s power purchases from private generators, IPPs and auto-generators increased from less than 1.0% to over 30%. If this trend continues with the introduction of additional IPPs and power purchase agreements for the 160 MW of additional capacity needed over the medium term, nearly 50% of capacity will in future come from private sources and Jamaica will have locked itself into an industry structure of that of a single purchaser model which offers the least efficiency enhancing opportunities and the least opportunity to move to a competitive electricity market. The cost of capital from IPP investment will in itself also lead to higher cost of electricity when compared to the lower cost of capital JPSCo obtains from the softer multilateral financial market. IPP type capital investment carries very little risk to the investor and Jamaican taxpayers carry this risk through guarantees, which the government has had to provide and will have to continue to provide to attract such investments. Table 11 shows that sales growth in GWh has averaged about 6.5% per annum, over the period 1994/95 to 1998/99. For the four year period up to 1997/98 JPSCo showed after tax losses. The year 1998/99, however, showed a profit of US$12.1m, with a return on equity of 13.6% and return on assets of 10%. The most significant point, however, has been the dramatic increase in bulk power purchases after 1994/95, increasing from 4% to 30% in 1997/98 and declining to 23% in 1998/99. Without the introduction of the IPPs, Jamaica’s state owned electric utility would not have been able to meet the increased demand and mostly likely its financial position would have shown an unhealthier picture during this period. 226 Table 11 Pre and Post-Management Performance Contract Results Jamaica, JPSCo Annual Revenues and Profitability Pre-Post Performance Contract After Tax Profit (US$) Tax Paid (US$) Dividend Paid (US$ Return on Equity Return on Asset Sales Turnover (US$) Sales GWh Proportion of Bulk Electricity Supplies from IPPs (%) Percentage increase (GWh) Post-Performance Contract 1997/98 1998/99 1994/95 1995/96 1996/97 -7,013 -1,602 -45,537 -56,823 12,122 5.1 4.6 4.7 4.7 4.6 -1.6% 0.9% 228,797,146 -0.2% 0.9% 241,648,452 -19.0% -7.1% 287,531,307 -33.1% -9.4% 292,814,893 13.6% 10.1% 311,260,230 1,890 2,037 2,147 2,334 2,476 4% 20% 24% 30% 23% 7.4 5.4 8.7 6.1 Source: Jamaica Public Service Company Table 12 shows that the number of employees in the generation sector fell from 390 to 310 over the period, a decline of 20%. At the same time the number of employees in distribution and sales remained relatively stable over the pre and post-performance management contract periods. The decline in the number of employees in generation commenced during the pre-management performance contract period, therefore, the improvement could not be attributable to the effect of the internal management performance contract. Total employees declined from 2113 in 1994/95 to 2039 in 1996/97. The numbers of employees for each of the two post-management performance contract years were higher than the year preceding the introduction of the contract. Productivity (kWh generated per employee) commenced its decline also in the pre-performance management contract period and continued up to the first year of the changes. However, in the second year, the productivity level was higher than the level achieved in 1994/95. Customers per employee at the same time showed progressive improvements over the five-year period, rising from 176 to 216. 227 Table 12 Jamaica – JPSCo Number of Employees/Labour Productivity and Number of Customers Pre-Performance Contract 1994/95 1995/96 1996/97 Post-Performance Contract 1997/98 1998/99 Features Number of Employees in Generation and Transmission Number of Employees in Distribution and Sales of JPS Employees in Central Administration of JPS Total number of Employees KWh Generated per Employee Number of Customers Customers per Employee Proportion of Household Connected Access (%) Amount of Bulk Electricity bought from IPPs (GWh) Total Number of Household Connected 390 357 324 321 310 1,254 1.281 1,268 1,298 1,251 469 477 447 475 514 2,113 1,064,28 9 371,755 176 53% 2,085 941,263 2,039 951,077 2,094 940.537 2,075 1,102,598 390,367 187 55% 404,984 199 57% 430,364 206 60% 448,783 216 62% 693 851 645 488 85 330,162 346,823 360,067 381,817 398,387 Source: Jamaica Public Service Company As shown in Table 13, technical and non-technical losses from transmission and distribution showed marginal improvements in the two post-performance management contract years, however, at 16.9% in 1998/99, it was still above the 13% level recorded in the 1970s. Technical line losses were relatively stable, varying from 10.5% to 11%, while non-technical losses varied from 6.4% to 6.7%. Access to electricity also showed progressive increases over the five-year period, increasing from 53% to 62%. Access to electricity is very high compared to developing country standards and while it is much higher than most African countries and comparable to South Africa it is substantially below the level of Mauritius, another small island economy. Jamaica with a population of 2.6 million has 465,000 connected customers in 2000 and this is marginally more than the 450,000 connected in Tanzania with a population of 31 million and is significantly more than the 140,000 connected customers in Uganda with population of 18 million. 228 Table 13 Energy Losses – Jamaica - JPSCo Pre-Performance Contract Losses (%) 94/95 95/96 96/87 1.8 9.1 10.9 10.9 6.7 97/98 1.8 8.8 10.6 106 6.5 98/99 1.8 8.7 10.5 10.5 6.4 17.3 16.0 17.6 17.1 16.9 Transmission Loss (%) Distribution Loss (%) TOTAL (%) Technical Losses (%) Non-Technical Loss (%) TOTAL (%) Post-Performance Contract Note 1 – Breakdown of energy losses prior to 1996/97 is not available. Source: Jamaica Public Service Company JPSCo’s retail sales price was US10.5 ¢/kWh for industrial users in 1994/95 and 13.6 cents for household consumers as shown in Table 14. Retail prices for both household and industrial consumers declined in 1995/96, respectively reflecting a decline of 11% and 12%. In 1996/97 prices reflected marginal increases. Thereafter prices remained relatively stable for the two management contract years. When one accounts for inflation, consumers seem to have benefited from the relatively stable prices over the five-year period. JPSCo’s bulk purchase prices from the IPPs was US 9.2¢/kWh in 1995/96, rising to 11 cents in 1996/97 before falling to 9 cents in the two post-management contract years. These changes, however, seem to have reflected the cost escalators in the power purchase agreements. JPSCo’s overall retail prices are very high when taken at the international level. JPSCo and the IPPs, however, produce almost all their generated power from imported fuel oil and do not have access to natural gas and significant levels of hydro-sources, which have been important benefits to the Bolivian and Trinidad and Tobago systems. It would appear that once a decision is taken to privatise, significant forces come in to play leading to appreciable improvements in performance. Once the pressures to privatise are relaxed, the forces for improved performances also seem to weaken. 229 Table 14 JAMAICA - JPSCo Pre and Post Performance Management Contract Results Bulk Power and Industrial and Consumer Retail Prices Electricity US Cents per KWh JPSCO Retail Prices Average Bulk Power Price JPS buys from IPPs US Cent Per KWh Pre-Performance Contract 1995/96 1996/97 Indu House Indus House strial hold trial hold 9.2 12.1 8.0 10.6 11.0 13.6 Pre-Performance Contract 1997/98 1998/99 Indus House Indus House trial hold trial hold 10.2 9.0 13.7 10.4 13.1 9.0 Source: Jamaica Public Service Company Between 1999 and early 2001, the performance of the electricity supply system in Jamaica fell off sharply with recurrence of regular outages, irregular voltages and load shedding. Some of the problems were due to lower levels of equipment availability from the IPPs and problems with the aged plants due for replacement Government also was unable to provide the foreign currency to meet the cost of the high maintenance bills, fund the cost of imported fuel and meet the investment needs so that adequate reserve margins could be provided at all time in the system. JPSCo also failed to provide the indicative investment plans to the Office of Utility Regulation to form the basis of competitive procurement of new capacity. The need for additional capacity to come on stream in the period 1998 to 2002 (over and above the capacity of the three IPPs which came on stream between 1994 and 1996) was forecasted in the 1990 World Bank ESMAP Report. That report emphasised the fact that 50% of the additional capacity would have been needed to replace the older units which were expensive to operate and prone to sudden failure. Apart from two co-generators, which provided additional capacity of 23 MW during 1998, no new capacity was expected to come on stream before 2003. The result was that reserve margins fell to 21%. With prolonged outages at one of the large power plants at Hunts Bay and major plant failure of one of the IPP Company, the reserve margin 230 was insufficient to avoid the recurrence of major island wide power outages in the later part of 2000 and throughout 2001. JPSCo’s Annual Report showed that the company’s financial performance declined further in 1999/2000. Operating and maintenance cost increased by 36%, mainly from a 90% increase in oil prices and 28% increase in the price of IPP purchased power, whilst operating revenues increased by only 28%. Operating revenues increased mainly from 48% increase in fuel component of the tariff. The non-fuel component remained unchanged from 19991. Demand on the system in 2000 was 521 MW, increasing at 6.5% per annum. Installed capacity was 656 MW of which 25% was provided by four private companies, JEP providing 74.2 MW; JPPC providing 61.3 MW; Jamalcoa providing 11.1 MW and Jamaica Boilers, another 12.1 MW to make a total of 158.6 MW. The country’s financial situation, especially the country’s balance of payment also continued to deteriorate with the result that the budget for the financial year 2000/01 had to be financed by privatisation proceeds amounting to J$7.2 billion. JPSCo was the last major enterprise that could make a substantial privatisation income contribution. The Final Act of Privatisation With over US$300 million of additional investment for the 160 MW which was needed by 2003 and the investments for technical improvements in plant efficiency, the Prime Minister was left with no option but to offer the company for sale (despite vigorous opposition by the Minister of Mining an Energy) for a second time to a strategic investor and to abandon the previous policy of floatation of 20% of the company’s shares on the local stock exchange. The recommendation to privatise came from a recommendation made by Planning Institute of Jamaica one of the agencies falling under the control of Ministry of Finance. In selling JPSCo the opportunity was provided to reduce the public debt by US$ 120 million. Because of the pressure to obtain additional resources Government again dismissed the restructuring and unbundling option, despite the interest shown by some of the potential investors 231 in acquiring only the generation facilities on the grounds that the sale of the vertically integrated JPSCo was the best option to ensure even development of the power sector and adequate and reliable power supply of electricity at all times. This decision again reflected a distrust of the market and a failure to take the consumers interest fully into account. Instead of competitive international tender (this was ruled out because of the time constraints) the Government settled for what was in effect a negotiated sale. Invitations for Expression of Interest were sent to four selected companies including the two previously short-listed for the first privatisation exercise. Houston Energy one of the original bidders declared that they were no longer interested in the Caribbean. Two of the others receiving the Expression of Interest, Duke Power and Enron Corporation expressed interest only in the generation facilities and this is one of the new realities of the global electricity industry, specialisation of investment. Government was, therefore, left to negotiate with one company, Southern Energy Inc of Atlanta Georgia. On the 21 September 2000 the Prime Minister announced that Government had signed a Memorandum of Understanding for the sale of majority interest in the restructured JPSCo. The final state sale agreement in March 2001 provided for the following: • Southern Electric’s Subsidiary, Mirant JPSCo (Barbados) SRL to acquire 80% of JPSCo’s shares for US$201 million and assume US$120 of debt, with the government to provide counter guarantee for this debt for a further 12 months after closing. • Southern to commit itself to US$500 million investments in additional generating capacity over a period of 10 years after closing. • Government’s 19.9% remaining equity interest to be entitled to annual dividends. (The public already held 0.01% for JPSCo’s shares). • Mirant, to make available up to 5% of its voting stocks to employees and to commence action to list the company on the local stock exchange immediately after the end of the first three years. • Government of Jamaica to assume responsibility for J$9.9 billion of JPSCo’s debt of which J$4.7 is directly on the Government books and the balance of J$5.2 on JPSCo’s books but guaranteed by Government at average interest rate of 6.6%. 232 • The company to be relieved from GCT tax (value added tax) and import duties on capital expenditure for the first 10 years. • Government’s 20% shareholding to give entitlement to three Board members and the remaining six Board members to come from the strategic investor. • In the first three years neither party to be allowed to transfer any portion of its equity and for the Government to be allowed to assume operation of the company if the buyer ceases to operate all or any substantial portion of the electricity system and to have rights of first refusal in respect of Mirant shares: of the 242 properties owned by JPSCo, only 106 to form apart of the deal. There was to be no redundancy in the short-term. • A new 20 year exclusive all island electricity licence was awarded in March 2001 by Government, essentially under the terms of the then existing licence, except that the terms do not provide for any guaranteed rate of return. In respect of the right to additional generation capacity, exclusivity was provided for up to 3 years after closing, thereafter (1 April 2004) new generation capacity is to be acquired on the basis of competitive tendering. The new owners are permitted to continue with the vertically integrated structure with exclusive rights to the transmission, distribution and all of the retail market. • The company under the licence conditions, gave an undertaking not to abuse its position of market power and for tariff to be fixed by the OUR. The two part pricing structure was to remain, with the non-fuel component subject to review every five years and the fuel component to be recalculated each month based on an indexation formula. JPSCo, under oversight of the electricity regulator is to be responsible for the management of the tendering process for all new generation capacity, despite the fact that the company is expected to be one of the bidders. In proceeding to sell JPSCo as a vertically integrated company, Government choose the single buyer trading arrangement and replaced a public monopoly with a private monopoly as all consumers were denied choice of supply. The opportunity to graduate to a wholesale electricity market phase at a later date was precluded under the 20-year exclusive franchise granted to the foreign operator for the transmission and distribution market segments and failure to liberalise the large consumer market segment. At least Government should have insisted upon operational unbundling of the generation business. Additionally the transmission business should have included a condition mandating accounting ring fencing from generation and distribution, with 233 a separate transmission licence from the distribution and retail supply licence. The granting of a three-year exclusivity for new generation capacity also served to delay the introduction of competition for new capacity. The decisions in fact were made in the interest of short-term gains; providing revenues to the Treasury against the longer-term interest of a competitive market delivering more efficient services to consumers. Had the Government provided for liberalisation of the large consumer market after a transitional period of say five years (possibly users with demand exceeding 1 MW) and for equal and non- discriminatory access to the network natural monopoly segment of the industry the longer term consumers’ interest would have been better served. In this way, an element of competition could have been introduced at the retail end of the market during the life of the current franchise. Government’s failure to consider the consumers’ interest went further by removing the actions and behaviour of JPSCo from the jurisdiction of Fair Trading Competition Commission. There is no guarantee that the level of investments stated will be made. It has been found from international experiences that it is extremely difficult to enforce capital programmes in the postprivatisation periods. The commitment not to abuse market power should have been accompanied by specific anticompetitive rules to determine abuse, with penalties specified for such abusive conduct. The British experience has shown that one of the critical problems in a post-privatisation period has been that of abuse of market power. Government could easily have provided for bypass of the transmission and distribution network operator, so that large industrial and commercial consumers could go direct to the generators and buy bulk electricity. The responsibilities for developing the least cost plan, as well as the forecasting of future demand should have been returned to the ministry with portfolio responsibility for energy. Additionally, management of the procurement process should have been assigned to a neutral agency, such as the National Investment Bank of Jamaica where such expertise lie and not to JPSCo or the OUR. The role of the Office of Utility Regulation should have been limited to the establishment and regulation of the procurement proceedures. The OUR’s role should have been restricted more to the traditional regulatory responsibility that of addressing the problem of market power and not in the selection of entrants to the market. 234 There is a conflict of interest on the part of JPSCo’s involvement in managing the procurement process. Competitive tendering can contribute to a reduction in the cost of generation, when compared to bilateral negotiations between the incumbent single buyer and a selected company and also offers the attraction of rapid entry without the need for drastic restructuring of the industry. What Jamaica has done is to graft the procurement process onto the vertically integrated and unreformed electricity supply industry. The disadvantage of this arrangement is considerable. JPSCo has a strong incentive and opportunity to select bids from its own generation facilities or bias the competition to favour its own interests. It has been well known that incumbent monopoly utility operators are loath to face the test of competition, which may reveal the high cost of current operations, and are well placed to disfavour attempts at entry by loading unreasonable conditions on entrants. Even if JPSCo genuinely opens up to competition in the bulk electricity market and if corruption can be prevented from biasing the outcome the new entrant will be selling to a monopsonist and will need strong assurances against ex post opportunism. Jamaica experienced these problems with Cable and Wireless during the liberalisation of the telephone market in the 1990s. It is unlikely JPSCo will behave any different from Cable and Wireless in accommodating the opening of the market for bulk power. In adopting these arrangements the Government has placed considerable regulatory responsibilities on the embryonic regulatory agency and missed an oppertunity of using competition to reduce the regulatory burden. Summary and Conclusion In the period up to 1963, the industry structure consisted of several small privately owned systems, each company operating in a prescribed franchise area and with relatively little government regulation. Between 1923 and 1966, JPSCo, the company based originally in Kingston the capital city, acquired all the other privately operated electricity systems other than the self-generators. In 1966 JPSCo came to acquire a licence for the entire island and at that point operated as a vertically and horizontally franchised monopoly for the entire country. Private ownership came to an end in 1974 when the government nationalised the company with the Government taking ownership of 99% of the company’s stock. The Jamaican experience shows 235 that even under the Phase One or franchised monopoly stage of development, institutional changes continued to take place. Ownership of the integrated monopoly electricity utility over the period of the early 19970s changed from private monopoly to public monopoly. Direct interventionist ministerial management gave way to a more autonomous relationship in the form of internal performance management contract in the 1995. The regulatory regime first changed from rate boards to a public utility commission in 1965, followed by a further change to ministerial regulation in 1975. Ministerial regulation lasted up to 2001 despite the introduction of the Office of Utility Regulation in 1995. The role of the Office during this period was purely advisory. The single integrated franchised monopoly phase came to an end shortly after 1993, following government’s decision to liberalise the generation market and to allow independent power producers into the generation market segment. With the entry of the first IPPs into the market after 1994, the vertically integrated JPSCo came to operate as the sole purchasing agent for bulk electricity. Jamaica then entered the second phase of development that of the purchasing agent phase. The regulatory regime experienced its fourth period of change. New legislation was introduced in 1995 establishing a multi-sector regulator, headed by a single Director General outside the hierarchical structure of the sector ministry. In 1998, the regulatory portfolio was transferred from the utilities sector minister; the Minister of Public Utilities and Transport to the Minister of Industry and Technology. The result of this change was that both competition regulation and utility industry regulation came under one ministerial portfolio. The three utilities, covering water, electricity and telecommunications were assigned to separate portfolio ministers. In order to give the new regulator powers over electricity and the other utility industries, the OUR Act was further amended in early 2000. Amongst a number of changes made to the Act were legal recognition of the new reporting relationship, which was administratively established in 1998, and extension of the regulatory remit of the OUR to cover the utility service providers which were in existence prior to the Act, such as electricity and water. JPSCo continued to operate as a vertically integrated state owned enterprise with monopoly over the transmission and distribution market. Although the generation market has seen new entrants, and although the new capacity which will be needed to come on stream over the next six years will most likely be IPPs, JPSCo as a vertically integrated privately owned firm ( after 2001) will continue 236 to maintain monopsony power over the bulk electricity purchases and monopoly over distribution and retail supply. In 1996 the Jamaican Government discontinued its official credit relationship with the IMF after 20 years of stabilisation and structural agreements. With the departure of the IMF, the external pressure to privatise was removed and as a result government has been slow in completing the rest of the privatisation and public enterprise reform programme and seems to have drifted back to favour the strategic development role of public enterprises. Government has had to inject huge amounts of public funds to prop up Air Jamaica, a public/private sector joint venture, with the justification of maintaining a national airline. The national budget, therefore, continued to face pressure from the competing demands of education, security and health on the one side and the financial demands of continued state involvement in utilities and transport operations on the other side. The decision to eventually privatise JPSCo in 2001 was forced on the government from financial circumstances, despite the fact that a policy of privatisation had been announced from the early 1990s. In privatising JPSCo as a vertically and horizontally integrated enterprise, Jamaica has exchanged a public monopoly for a private monopoly, accompanied by public regulation at a time when many developing countries have been looking at the introduction of increased competition in the wholesale bulk electricity and retail sectors of the market. The decision not to privatise JPSCo in the form of a disintegrated set of businesses is another case of missed opportunity to secure a competitive industry structure following upon privatisation and will prove to be a costly decision to the detriment of the Jamaica consumers. It will be more difficult also to regulate the vertically integrated private utility and extremely difficult to unbundle in future. In adopting what is essentially a purchasing agent model, where the vertically integrated incumbent electric utility operates as the a sole purchaser of bulk power and as a supply monopolist over the transmission, distribution and supply system, Jamaica seems to have opted for the least efficient of the new industry structures that have been developing in the electricity industry since the late 1980s. Whilst in the early 1990s, it was questionable whether a small electricity market under 1000 MW could be effectively unbundled to allow for an increased competitive structure this was certainly not 237 the case in 2001. Small markets such as Bolivia, El Salvador and Panama have since 1995 successfully unbundled their systems and in so doing have provided for a more competitive framework, without experiencing any serious cost penalties in the initial years. In contrast to Jamaica, the very small Uganda system in 2000 decided to place the emphasis on competition in electricity supply to promote efficiencies. Uganda Electricity Board (UEB) Owens Fall generating facilities have been vertically unbundled and offered for concessioning through two separate power purchase agreements. The new Bujangali hydro-plant (under construction) is being carried out also under separate IPP/PPA arrangements. Transmission has been separated out as the single buyer, initially to remain under public ownership. New transmission capacity, however, is to be developed, owned and operated by the private sector. UEB’s distribution business has been vertically unbundled into a single distribution company and is to be divested through long-term concession. The reform plans also call for the liberalisation of the large end user market and for transmission and distribution to be mandated to provide non-discriminatory and third party access to the network system. The total installed capacity of UEB at restructuring was 180 MW, just over 25% of the system size of JPSCo. The number of connected customers was 148,000, about 25% that of Jamaica and with 70% of these customers located in Kampala and Entebbe area. The bulk of the electricity over 72% is consumed by 12% of the population. Less than 5% of Uganda’s population of 18 million was connected to UEB system. Technical and non-technical losses of UEB exceeded 30% of the electricity billed, collections were received from less than 50% of customers and over 50% of accounts payable remained due for more than one year38. In its tariff rebalancing exercise, which has preceded the privatisation, the Ugandan Government increased domestic tariff by 50%.39 Because of the very small system size, Uganda has settled on the single buyer phase with third party access; however, unlike Jamaica, the vertically integrated UEB has been vertically unbundled into three companies; generating, transmission and distribution with the generation and distribution companies to be divested through long-term concession. Six firms have expressed interest in buying the generating company whilst three firms have expressed interest in the distribution companies. This demonstrates that international interests also exist for small facilities. 238 Secondly, even if the option is for the integrated utility to operate as the single purchaser, the legislative framework for competitive procurement of incremental capacity should have been laid out from 1995. Although a multi-sector regulatory agency was established in 1995, government took a long time to specify clearly the role of the regulator in regulating the incumbent utility industry providers of water, telecommunications and electricity. This created a lot of uncertainty and would have impacted negatively on the first attempt to privatise JPSCo. Potential bidders more likely would have perceived high regulatory risks in such an environment and hence the reason for the additional sovereign guarantees sought when the government went out for tenders in the first instance. Third, the process was too drawn out. This has been a major problem in privatisation in developing countries. The process of resolving the interest of the contending forces leads to delays and compromises and very often the optimal solution is rejected at higher cost to the country and consumers. What was needed for the privatisation exercise was a clearly defined time frame, certainly with duration of less than ten years. Bolivia for example, established a time frame of 5 years for the privatisation of the main utilities. Fourth, internal management performance contracts can be appropriate as a transitional internal privatisation option to improve the commercial aspects of the enterprise in the period up to privatisation; it has not proven from experience to be a solution to bring about sustainable longterm improvements. Management performance contracts still leave the problem of investment financing unresolved. This was certainly the case in Jamaica in 1999 and this is what led to the forced privatisation transaction. Fifth, the managers of the enterprise and the public bureaucrats who stand to benefit from the publicly owned utility will oppose privatisation and competitive market operations. At one point the bureaucrats argued that while there may be a general case for private ownership and competition in the utilities, this did not mean that such a framework was appropriate for Jamaica. In effect the Jamaican situation was being advanced as a special case, which need not conform to the new developments. The fall off in performance of the system after 1999 showed that it is questionable whether there is any special case to the new imperatives of the 1990s. 239 Sixth, developing countries like Tanzania and Ghana that are in the process of abandoning state ownership for private operators (especially foreign) and independent regulation would be well advised to learn from Jamaica’s experiences of private ownership and regulation of the vertically integrated monopoly utility in the period prior to 1975. A private monopoly is not an effective solution to a public monopoly. Private operation also brings with it new tensions and conflicts. The traditional American approach of a Public Utility Commission with quasi-judicial public hearings and incorporating rate of return rate base tariff formula has also been shown to be inappropriate for developing countries where the culture of independent regulation is absent and regulatory institutional endowment is low. Finally, developing countries also need to develop better capabilities in the selection of external consultants to advice on the restructuring and privatisation process. The Jamaican situation shows that external consultants will invariably opt for recommendations based on the experiences of their own country, rather than on a systematic assessment of international experiences and what is needed for the local environment. This was clearly the case of the Price Waterhouse consultancy in 1995. 240 End Notes 1. Jamaica Public Service Co. Ltd., A History of Electric Power in Jamaica, Kingston (undated), p.1. 2. E.C. William, Jamaica Public Service Ltd: A History of Its Origins and Development, 1923-1978, JPSCo (unpublished 1993), p.16. 3. Raphael A. Swaby, “The Rationale For State Ownership of Public Utilities in Jamaica”, Social and Economic Studies, UWI, Special Issue, Public Sector in the Commonwealth Caribbean, Vol. 30, No. 1 (March 1981), p.82. 4. The telephone utility, which was, incorporated in the 1980s as a private company and which remained in private hands until 1973 was also regulated by the rate board system. 5. Pablo Spiller and Cezley Sampson, Regulation, Institutions and Commitment: The Jamaican Telecommunications Sector, World Bank, Policy Research Working Paper No.1362 (1994), and p.18. 6. The Jamaica Telephone Company’s 40-year licence was also due to come to an end in the period immediately preceding independence in 1962. An interesting development prior to the expiration of the licence is the “end game” in which the firm and the government embarked on opportunistic actions to improve their bargaining position in the period immediately prior to renewal or granting of a new licence. The period of uncertainty was heightened further as the method of valuation of the company’s assets was not clearly specified in the licences. The company’s resorted to revaluation of their assets in order to increase the asset base on which the rate of return was calculated. In the case of JPSCo the company increased asset valuation by J$4 million, see Swaby, op.cit. p.85. 7. Jamaica Telephone Company received its licence in 1965; however, this was amended in 1966 to accommodate the JPUC Act. 8. JPSCo was now required to use book values at original cost and the values were to be at 1953, with additions at cost and with the applicable depreciation rate. 9. Swaby op.cit. p.86. 10. L.A. Swaby, “Some Problems of Public Utility Regulation by Statutory Boards: the Jamaican Omnibus Case ”, Social and Economic Studies , UWI, Vol.23, No. 2 (1974), p.252. 11. Swaby, op.cit. P.88. Plants were shown not to be taken at the original 1953, (book value) and assets which were obsolete or written off were still carried in the accounts. JPSCo was paying Stone and Webster 20% of the cost of the capital project in respect of the Old Harbour power plant as consulting fees. The Commission’s calculation of the rate base was significantly less than that claimed by JPSCo. The rate of return on rate base was 8.4% against the 7.4% submitted in the application and the rate of return on equity was 13.5%. JPSCo had claimed that they needed 13 to 16% returns on equity. 241 12. G.E. Mills, “Public Policy and Private Enterprise in Commonwealth Caribbean”, Social and Economic Studies, UWI, Vol.10, No. 2 (1974), p.231, also 1990, in G.E.Mills ed. A Reader in Public Policy and Administration , ISER, Mona ,Jamaica , pp. 145-70 13. World Bank, Development Report – 1997: The State in a Changing World, Oxford University Press (1997), p.70. 14. Edwin Jones, “Role of the State in Public Enterprise” Social and Economic Studies, UWI, Special Issue, Public Sector Issues in Commonwealth Caribbean, Vol.30, No. 1 (March 1981), p.17. 15. Adlith Brown, “Issues in Public Enterprise” Social and Economic Studies, UWI, Special Issue, Public Sector Issues in Commonwealth Caribbean, UWI, Vol. 30, No. 1 (March 1981), p.2. 16. Adlith Brown and Helen McBain, “The Public Sector in Jamaica”, Social and Economic Study, UWI, Studies in Caribbean Public Enterprise (1993), Vol 1 , p.101. 17. Ibid. p.95. 18. Cezley Sampson, Strategic Marketing Cases: Jamaica Public Service Company, Kingston, University of the West Indies, Mona Institute of Business (1986), p.20. 19. Earle Richards, Overview of Private Sector Role in Jamaica Energy/Power Sector, Jamaica Public Service Company Abstract, (unpublished 1991), p.3. 20. World Bank, Jamaica Energy Sector, Strategy and Investment Planning Study, Washington, D.C., ESMAP, Vol. 1, Main Report (August 1992), p.55. 21. Ibid, p.52. 22. Basil Sutherland, Financing Jamaica’s Rockfort Independent Power Project: A Review of Experience for Future Projects, Washington, D.C., World Bank (1998), p.23. 23. National Investment Bank of Jamaica, Privatisation of JPSCo: Issues Affecting the Privatisation of JPSCo (unpublished, February 1995), Appendix 1, p.3. 24. Paul Joskow, “The Evolution of Independent Power Sector and Competitive Procurement of New Generating Capacity”, Research in Law and Economics (1991), p.70. 25. Coopers and Lybrand, Jamaica Power Sector Regulatory Framework and Privatisation, Phase Two Report, Kingston, Jamaica (1993), Section 205. 26. Price Waterhouse Utility Economics and Financial Consultancy Group, Options for Privatisation and Regulation of JPSCo, Washington (1994), p.17. 242 27. Colin Robinson, “Profit Discovery, Rate of Entry: The Case of Electricity” in Regulating Utilities: Time for a Change, eds., M.E. Beesley, London Institute of Economic Affairs, Reading, No.44 (1996), p.112. 28. W. Glen, Private Sector in Electricity in Developing Countries, Supply and Demand, Washington, DC., International Finance Corporation, Working Paper, No. 15, (1991), p.15. 29. Jamaica Public Service, Annual Report, 1995-96, Kingston (1996), p.39. 30. UNCTAD, Design, Implementation and Results of Privatisation Programmes: Review of National Experiences, New York, United Nations (1994), p.21. 31. Cable and Wireless purchase of the telecommunications utility is 1985 is a case in point where the tariff formula is structured around the rate of return and was set at 17.5% to 22% on revalued assets, after tax. 32. The Telecommunications industry regulatory legislation was introduced in 2000, finally setting out the powers of the OUR to regulate the telecommunications sector 33. Jamaica Omnibus Services Company Ltd., the Kingston urban passenger service provider was wound up and private providers took over the provision of public passenger services in Kingston. 34. Michael Kerf and Warrick Smith, Privatising Africa’s Infrastructure: Promise and Challenge, Washington, D.C., World Bank Technical Paper, No. 337 (1996), p.5. 35. Pablo Spiller and Cezley Sampson, “Telecommunications Regulation in Jamaica”, in Regulations, Institutions and Commitments: Comparative Studies in Telecommunications, eds., Brian Levy and Pablo Spiller, Cambridge University Press (1996), p.37. 36. Government of Jamaica has had to pursue protracted and expensive negotiations with Cable and Wireless Jamaica Ltd., to terminate the 49-year exclusivity, which apparently was provided in the 1985 telecommunications licences. This matter was resolved in 2000 when a more liberalised cellular market regime was agreed upon and additional cellular operators were allowed to enter the telecommunications market. 37. JPSCo, Annual Report 1999-2000 (April 2000), p.5. 38. Uganda Government, Power Sector Restructuring and Privatisation: New Strategic and Implementation Plan, Uganda (June 1999), p.2. 39. Uganda increased power tariff by 70% to US 10.8 c/kWh in 2001 as part of preparation for privatisation. The rates, however, was reduced to 8.5 US 8. 5 c/kWh following from protest from Parliamentarians. The rate were rebalanced and increased to eliminate cross-subsidies and government subsidies. Uganda is almost 100% hydro-based. 243 Chapter 6 Radical Restructuring and Privatisation of Small Electric Utility Market: The Case of Bolivia Introduction: Bolivia restructuring of electricity presents a number of interesting developments. Up to 1995, the World Bank commentators were still expressing reservations as to the efficacy of vertical and horizontal unbundling of small electricity systems in order to create competition. Writing in the Banks Occasional Paper series Bacon1 came to the conclusion that: “even when it is possible to introduce limited competition in generation and achieve some benefits, the cost of vertical separation may be so high as to offset the gains from competition”. Up until 995 unbundling and dis-integration of electricity markets had been confined to systems of over 3000 MW, with Chile being the smallest market to have unbundled its system. Besant-Jones2, another Bank commentator further stated that: establishing of competition in markets such as through a price based pool and the functioning of autonomous regulatory agencies as with the England and Wales model has only limited long-term relevance for many developing countries, because of several reasons” . Most importantly, they were seen to be too small, being less than 1000 MW. In addition, to the small size, the operation of a competitive pool based on spot market pricing was not only seen to be beyond the capabilities for all but the most advanced developing countries, there was concern that liberalisation of the generation market would present too high a risk for the attraction of significant levels of foreign direct investments. One year after these pronouncements, Bolivia with two vertically integrated small systems, of total installed capacity of 616 MW, unbundled into 12 operating entities and dispelled the myth that significant levels of competition was not obtainable in small systems. These views continued to reflect the economies of scale thesis, which had prevailed during the post war years. These views 244 also came to have had a determining influence when the Jamaican policy makers decided not to unbundle the Jamaican electricity system (700 MW) in 1995. In 1990, Bolivia a land locked country was one of Latin American’s poorest countries, with a small under developed economy; population of 7.5 million people, and land area of 1,098,581 square kilometres (424164 square miles), about the combined size of France and Spain. Approximately 58% of the population lives in the rural areas, compared to 9% in Argentina. Native Americans and people of mixed ancestry make up 78% of the population, compared to less than 10% in Argentina. Average household consists of 4.36 persons. The largest city La Paz has a population of 1.2 million, compared to Buenos Aires with 15.0 million. Total GDP in 1994 was US$6.2 billion. Per capita income was estimated of US$ 920 or 12% of that of Argentina. This level of development is much closer to that of Sub-Saharan Africa. Between 1987 and 1994 GDP growth rates averaged 4% and this was preceded by a seven-year period where GDP fell by an annual average of 2.5%. Hyper-inflation measured by the CPI Index reached 28,000% in 1984.3 Bolivia’s economic situation in 1995 was that of a crisis of unprecedented proportions, brought about by years of socialist economic policies. In 1984 Bolivia defaulted on its foreign debt obligation. The restructuring started in 1985 with the Paz Estenssoro administration which came into power introducing one of the most austere economic shock packages ever implemented in Latin America, which marked a dramatic shift from stateism to that of a free market economy. The reform programme combined comprehensive structural reforms with tight monetary and fiscal policies. The austere economic stabilisation programme quickly brought inflation under control and by 1990 it was down to 18%, reaching the single digit of 9% by 1995. In 1998 the inflation rate had fallen to 4.0%. Foreign commercial debt, which was US$680 million, had virtually been eliminated.4 Bolivia presents one of the first truly textbook restructuring programmes to have been introduced in the Americas in recent years. The fundamental objective of the reforms, which had started in 1985, was to change the economic system from a state capitalist economy to a private market economy. The basic principles of the new policies were that market forces were required to determine prices and there was to be a single 245 real and flexible foreign exchange rate. Most importantly, the government concluded that the domestic capital market was not only underdeveloped, but also was insufficient, and at best could only support a small proportion of its citizens with a reasonable standard of living. Bolivia’s privatisation policies which formed an integral part of the market reforms were therefore motivated by the desire to attract foreign capital, to expand the level of access to basic utility services and to develop the country’s rich natural resources, especially that of natural gas. As a landlocked country it saw the opportunity of exporting electricity and natural gas to its neighbours, especially Argentina and Brazil, and in so doing, significantly extending its domestic market. Fundamental to the reform was the entrenchment of property rights in new legislation. A major restructuring of the public sector and state enterprises was also introduced in 1993, involving the transfer to the private sector the function as a producer in order for the Government to concentrate on policy formulation, social development and regulation. The principal laws, which helped to transform the state enterprises, were the Privatisation, Capitalisation, Regulatory and Investment Acts. The latter promoted the protection of foreign and domestic investments. The 1994 Law for sectoral regulation (SIRESE) provided the regulatory framework for the major utilities, while the electricity, telecommunications, and hydrocarbon laws dealt with the industry specific structure in each instance. Instead of seeing privatisation as a means of obtaining additional income for the Treasury as in the case of Argentina and Jamaica, for the Bolivians, it was a means of attracting new investments to expand accessibility of electricity to the citizens. A critical component of the institutional reform of the state companies in 1994 was the establishment of a Ministry of Capitalisation and a privatisation office. Although the IMF, the World Bank and the Inter-American Development Bank exerted a lot of influence towards these reforms in the early years of the 1990s, by 1994 they were also promoted with conviction by the new administration. Bolivia’s divestiture of state owned utilities and infrastructure firms took three different forms; capitalisation, outright privatisation though trade sale of shares and concession contracts. Long distance telecommunications was the first divestiture transaction to come under the capitalisation programme followed by electricity generation, hydrocarbons, airline and the railways. 246 Airports, water and sewerage were disposed of by the concession route, while electricity transmission and distribution were fully privatised though the route of trade sale of shares. Divestiture over the post-1993 period also included enterprises in the manufacturing, mining and tourism sectors, and the programme was accompanied by major reforms of both the tax system and the pension system. Outright privatisation of 49 business units over the period 1993-1997 brought in an income of US$97.5 million, while the capitalisation programme resulted in new equity inflows of US$1.67 billion by 1998 and covered investments in the hydrocarbons, telecommunication, electricity and transport sectors.5 The capitalisation process, involved the state entering into partnership with foreign private investors, the contribution of the state being the value of the enterprise to be privatised and that of the investor being the capital to be introduced. The formula took the form of sale of new shares to private investors; equal to 50% of the stock in each enterprise6. This was accompanied by handing over full management control to the strategic investors with an obligation to use the capital as investment for the privatised company. Instead of the sales proceeds going to the Treasury, the funds were ploughed back into the company to improve efficiency and quality of service and to expand production. Government was relieved of the burden of financing expansion of these capitalintensive industries and at the same time the enterprise on divestiture had access to immediate cash, without having to take on increased debt portfolio. The remaining 50% of the shares held by the state were subsequently transferred to privately managed pension funds. The pension fund managers are required to administer the resources of the fund for the benefit of the population at large 7. The capitalisation process can be summarised as follows: (a) Raising new shares up to 50% of the enterprise stocks were made the subject of public tender, usually to a strategic investor. The strategic investor is required to enter into a capitalisation and share subscription agreement between the Generator, the Government and other investors. (b) All the privatisation transaction agreements which the investor is required to sign on taking ownership are agreed to between the pre-qualified bidders and the government before final tendering with the result that the final evaluation of the bids are based on only one variable; the proposed purchase price of the shares. 247 (c) The valuation of the assets of the enterprises was carried out on the basis of book value. There is no need for any other valuation, since the bid price is the market price of the assets. If the market value of the bidders turns out to be higher than the book value this makes it easier for the government to sell the divestiture programme as a financial success. (d) A new company, (or mixed corporation) is then established in which the state and the workers own all the shares. This is followed by a fresh issue of shares by the new company to the new investors. (e) An offer for international public tender is issued, and this involves bidding for the block of new shares. The bidder offering the highest sum for the 50% block of shares becomes the new owner operator. The shareholding is then transferred to the new investor, along with a contract of administration (management contract). The administration contract is an agreement between the strategic investor the other shareholders and the government, granting management control to the strategic investor, subject to certain controls in the share subscription agreement. (f) The shares corresponding to the state’s interest were initially deposited with a Bahamasbased Citi-trust, which acted as a trustee and temporary custodian. The shares were later transferred to the National Pension Fund. (g) The strategic partner then delivers the cash value of the shares purchased to the company and the money is deposited overseas under strict conditions and only released to meet the capital expansion programme. A new company was established in respect of the privatisation of each generation business and in exchange for buying one share in the new company at a nominal value of US$20, the workers were offered the option to acquire an additional block of shares at the original purchase price.8 Upon capitalisation by the new investor, the workers benefited from real capital gains on their investment. Bolivia also ensured that both the new legislation and the regulatory framework were in place (like Argentina) before the implementation of the privatisation process. In the case of electricity sector, four pieces of legislation central to the divestiture of the electricity industry were introduced and they were as follows: the 1994 Capitalisation Law, the 1994 Regulatory Framework Law (SERESE) the 1995 Electricity Law and the 1995 Electricity Regulation. 248 In the development of the electricity framework law, Bolivia made sure that it benefited from the experiences of other countries that had introduced major restructuring and privatisation of their electricity industries. In particular extensive studies were made of the restructuring and regulatory regimes in England and Wales, Chile and Argentina. The guiding principles of the Electricity Laws are neutrality of the regulatory process, transparency of actions, flexibility of the system, incentives for efficiency, improvements to product quality and continuity. The Structure of the Industry before Unbundling Prior to privatisation of generation in 1995, the electricity sector comprised of Empresa Nacional de Electricidad S.A. (ENDE), principally a state owned generation and transmission company selling bulk electricity, although it had some end consumers. In addition to the public electric utility company there was one privately owned vertically integrated company; Compania Boliviana de Energia Electrica – (COBEE) as well as a number of private distributors and generators (the latter were mainly mining companies) supplemented by a number of isolated entities supplying electricity to rural and isolated areas, unconnected to the main network. These isolated entities used mainly diesel fuel and were either owned by municipalities or cooperatives. COBEE, the private company generated 34% of Bolivia’s power in 1992. It held 95% of the shares in a distribution company; Empresa de Luz Fuerza Electrica de Oruro S.A. (ELFEO), with private shareholders owning the other 5%, in addition to its vertically integrated La Paz distribution division. COBEE distributed electricity to 228,000 customers in 1994. It was formed in 1925 and had its stocks originally quoted on the New York Stock Exchange.9 The company operated 13 power stations, all powered by run of the river hydro-plants on the Zongo and Migullas rivers, with 142.2 MW capacity, representing 21% of the Siestema Interconnectodo Nationol (SIN) capacity and generating 774.6 GWh of electricity or 30% of the SIN’s product . Nine of the plants operated in the La Paz division, having a maximum capacity of 112.5 MW and four with a maximum capacity of 19 MW, serve its Oruro division. Plans were also in place to increase capacity by 61 MW in the Zongo Valley.10 249 The company also operated transmission lines, linking its plants and distribution facilities. COBEE’s forty-year licence with La Paz Municipality expired in September 1990, however, a new national licence was proclaimed by Presidential decree in 1994. COBEE also purchased substantial quantities of electricity from ENDE for its distribution subsidiary and in return sold bulk power to ENDE in the off peak periods. From the early 1990s until 1994 Leucodia National Corporation (LNC) was the principal shareholder. In 1994 LNC sold its shareholding to Liberty Power and Congentrix Bolivia Inc; a wholly owned subsidiary of Congentrix Energy of the USA. In addition to ENDE’s and COBEE’s distribution interest, there were three other distribution companies operating mainly outside the La Paz area to make a total of five distribution companies. ENDE the state owned company was formed in 1962 to rationalise the chaotic situation, which existed prior to the 1970s. ENDE commenced operation with the 27MW Corani plant. At that time the electricity sector was in the hands of a number of small municipalities. The formation of ENDE involved the centralisation of publicly held assets as against nationalisation or the take over of private assets, which was the experience in other Latin American countries at that time. It was formed as a limited liability company and not as a statutory corporation, with its shares being held by the government and two state companies. Government directly held 84.6%, the state mining company, Corporacion Minera de Bolivia – COMIBOL held 3.9% and the state oil company; Yacimientos Petroliferos Fiscales Bolivianos (YPFB) held 11.5%. All the shares were transferred directly to government prior to the formation of the new generation companies. ENDE also owned 2359 km of transmission and sub-transmission lines of 230 KV and 25 kV. Although the company was not vertically integrated with distribution facilities, it held significant equity interest in Empresa de Luz y Fuerza Electrica de Cochabamba S.A (ELFEC), Cooperativa Electrica de Sucre S.A (CESSA) and Servicios Electricos Potosi S.A (SEPSA). Its total revenues in 1994 amounted to US$ 72.2m from sales of 1768 GWh of electricity.11 Its mandate was to provide electricity to all the areas, which were not then served by the private companies. ENDE, unlike many Latin American public enterprises was able to escape political interference in its management, as the World Bank, which had funded its formation, had imposed a 250 condition that the Bank had to approve the appointment of the Managing Director for the first fifteen years. It was also able to develop a cadre of professional and efficient managers. The company carried out substantial investments in its operations in its early years. Financing for most of its pre-divestiture expansion came from the World Bank and the Inter-American Development Bank and during this period it had developed a very good credit record. In 1994 the company’s generation plant capacity was 461.2 MW, and this formed 75.0% of the interconnected system, as shown in Table 15 and 16. Of the 1687 GWh of electricity generated in 1994, ENDE accounted for 59% compared to COBEE’s 31%. Table 15 ENDE Generating Plant Capacity – 1994 Company Corani (Hydro) Guaracachi (Thermal) Valle Hermoso (Thermal) Total Capacity (kW) 126.0 186.5 148.5 461.2 Production (GWh) Projected (MW) 485 765 438 70 110 63 1687 243 Source: Ministry of Capitalisation and Investment, Generation Briefing Memorandum, Bolivia (1995) p.9 The Government in 1970 significantly reduced ENDE’s debt with the injection of US$107m of capital.12 The capital was introduced in order to strengthen the company’s balance sheet, following its financial weakening from the hyper–inflation years. Its average tariff in 1990 was US3.6¢/kWh. Bolivia’s 1994 per capita consumption of electricity of 320 kWh compared unfavourably with the regional average of 1100 kWh and the level of access was 64%.13 Its consumption level ranked among the three lowest in Latin America and the Caribbean. Return on assets in respect of ENDE’s investments in the 1990s was very low, being 5%. This low rate of return resulted from the very large past investments on hydro-plants. 251 Table 16 Bolivia, Installed Generation Capacity in 1994 Company/Plant ENDE Corani Guaracachi Valle Hermoso Total ENDE COBEE Hydro Others Total Capacity MW Percent 126.0 186.5 148.7 461.2 20.5 30.3 24.2 75.0 142.2 11.5 23.1 1.9 614.9 100.0 Source: Ministry of Capitalisation and Investment, Generation Briefing Memorandum, Bolivia (1995) p.12. Up to the time of privatisation the industry structure, which had emerged, was that of a duopoly between of two vertically integrated systems, each firmly entrenched in its respective geographical area. There was virtually no competition between the two companies. Overall, the regulatory process, which had developed, proved to be ineffective and was directed more by political considerations rather than economic factors. Prices were invariably fixed on the basis of political consideration. An outcome of this regulatory process was the lack of competition and efficiency at the distribution stage. The process provided no incentives to encourage private investments The Restructuring Programme Most advisors opposed the implementation of radical vertical and horizontal unbundling within the Bolivian electricity systems because of its size and the fact that it was considered to be one of the most efficient systems in the region. One advisor however recommended restructuring into three vertically integrated companies each to operate as a monopolist in each of the three main population centres. Others proposed the continuation of the two integrated utilities within the framework of a single purchaser regime, with competition to come from new IPP entrants to the market.14 ENDE would remain a vertically integrated state owned utility and under this model would act as the single purchaser of bulk power from the IPPs. Despite these views, the policy makers concluded that the 252 existence of efficient companies within the industry, provided opportunity to proceed with the reform. Efficient companies it was argued would make the industry more attractive to private investors not only to buy the companies but also to expand the system. It was also the strong view that competition and private investment would further enhance the efficiency of the companies. The overriding factor, which influenced the government to ignore the external advisors and adopt a radical restructuring approach, was the need for capital to fund the large future electricity investments and at the same time meet the investment requirements of health, education and national security.15 Radical restructuring, involving vertical and horizontal unbundling of the two systems were eventually selected as the option to follow. ENDE’s generation system was unbundled in 1995 into three companies; Corani S.A., Valle Hermoso S.A., and Guaracahi S.A. Its transmission system was also separated out into new business units, with 168 employees and restructured into a single interconnected system. Transportadora de Electricidad S.A. (TDE) was incorporated in 1997 with responsiblity for maintaining and operating the interconnected transmission system. TDE was then linked to the COBEE generating plants in the Zongo and Miguilla basins, the Corani hydro-plant in the Corani basin, as well as to the two thermal generating plants of Valle Hermoso and Guaracachi. The main thermal plants were located near the main natural gas production fields in the Eastern region. The interconnected system spanned approximately 700 km, running north to south and 600 kV running west to east, inclusive of four substations. Of the total network of 1818 km, 722 consisted of 230 kV lines, 897 kV formed 115 kV lines and 199 kV formed 69 kV lines. A further 1117 mm of 155 kV lines was nearing completion in 1997 and was to be transferred to the new system on commissioning. In addition to the 19 substations there was a fairly modern load dispatch centre. The transmission system made up less than 6% of the overall retail price of electricity, however, it is capital intensive and accounted for 20% of the assets of the overall system. In addition to the integrated system there were a number of isolated systems, which accounted for less than 20% of installed capacity and for less than 14% of electricity production in 1996.16 In accordance with the 1994 Electricity Law, COBEE was required to divest its interest in distribution; Electricidad de La Paz S.A. (ELECTROPAZ) and ELFEO. Of the three major 253 distribution companies, which were not controlled by ENDE and COBEE, two were organised as cooperatives, and they were Cooperativa Rural de Electricidad (CRE) in Santo Cruz, and CESSA in the Surce region. Additionally, there was the publicly owned SEPSA in the Potosi area. COBEE held 67% of the stocks in ELFEO, whilst the municipalities held 28% and the remaining 5% going to 200 small private shareholders. Following from the restructuring six independent distribution companies emerged and these were designated as public service companies.17 The Divestiture Programme ENDE’s generating facilities were divested through the capitalisation formula, with the distinguishing feature being that the sales proceeds remained in the company to finance future investments. A new set of shares was issued to strategic investors for the three horizontally unbundled generating businesses. The Government’s share of the new company was distributed to the Bolivian people via the special pension fund to realise 100% private ownership. In leaving the proceeds in the company, Government was able to solve the shortage of cash for working capital and investments. In the new structure the strategic investor owns 50%, whilst the Pension Fund holds 50%. In June 1994, 32 firms were pre-qualified from the various inquiries for the three ENDE generating companies. Subsequently, ten of these firms submitted their proposals and six was selected (see Table 17 below) to submit financial offers for the 50% equity interest in each of the three companies. 254 Table 17 Generation Companies in the SIN in 1996 Name Corani Cap acity MW 126 19 Guaracachi 217 32 Valle Hermoso 180 27 COBEE 144 21 Others Total SIN CT 674 7 10 0 Isolated system 82 Other Generators 104 Total Est 860 Source: % Electrici ty GWh Generat ed 536 19 1008 33 423 15 Hydro/Thermal 865 30 Hydro 17 2849 1 10 0 Operator Dominion Energy Energy Initiatives Constellation Energy/Odgen Power NRG / Vattenfall COMIBOL Type Hydro (Run of River) Thermal (Gas Turbine) Thermal (Gas Turbine) % 192 (30 Hydro 162 Thermal) (94 H) (169 T) 246 3287 Ministry of Capitalisation and Investment, Information Memorandum, Bolivia (1995) p.40. The six firms were Energy Industries Inc., Dominican Energy Inc., Energy Trade and Finance Corporation, AES Americas Inc., Constellation Energy and Enron Energy. Eventually the companies were divested to three of the groups. Empresa Electrica Corani (Corani), essentially a hydroelectric company of 126 MW, commenced operation with US$335.0 million worth of expansion projects. This project was expected to double capacity from 450 GWh to 900 GWh and involves three new water capture schemes. All four pre-qualified bidders placed a bid for this system and the winning bidder was Dominion Energy; a Virginia power company from the USA. The bid price was US$58.8 million. 255 Empresa Electrica Guaracachi (Guaracachi) Company consisted of a 162 MW gas fired plant at Santo Cruz, a 35 MW plant at Sucre and a 14 MW plant at Potosi. Four offers were received for this company and the winning bidder was Energy Industries, a company controlled by EPU International of the Jersey Central Power and Light group. Within a year Guaracachi embarked on a $30 million project expansion, representing the greater portion of the US$47 million brought in by the strategic investor. Empresa Electrica Valle Hermoso (Valle Hermoso) consisted of the Cochabamba thermal plants amounting to 87 MW. The winning bidder was a Consortium of the Baltimore based Constellation Energy and the Baltimore Gas and Electric Company of Maryland, both of the USA. The owners also inherited a project which was 20% completed; consisting of two 54 MW, gas turbine plants in the Chapare region, and estimated to cost US$54 million on completion. Constellation Energy paid US$33.0 million for its 50% share of the equity. In the case of COBEE, NRC Energy of Northern States Power Group of Minnesota and Vattenfall, the Swedish state owned company acquired 95% of its equity in 1996 for US$ 185 million. The new owners also embarked on major expansion, involving a 64 MW hydroelectric plant at a cost of US$105 million in the Zongo Valley. In December 1996 the installed capacity of the generation system reached 860 MW Installed hydroplants represented 32% of capacity and 46% of production output. A number of the auto- generators also formed part of the SIN. The two largest plants were held by an oil and gas company and a mining company and amounted to 30 MW combined capacity.18 The transmission company’s divestiture followed the more traditional form, that of a trade sale; the prospective investors were required to bid for at least 51% of the equity of the company. The successful bidder was to be given an indefinite licence as distinct from a concession19 to provide electricity transmission services in the integrated system and was required to maintain a minimum shareholding of 26% for a predetermined number of years, with responsibility for future transmission investments. 256 For each extension, a separate licence was required and the regulator was given the right to call a tender if agreement could not be reached between the participants in the SIN and TDE. The strategic investor paid US$39.9 million for 99% equity interest in TDE, in addition to taking over a further US$12.9 million of ENDE’s old debt. The transmission operator was restricted from owning equity in either generation or distribution and distribution and generation operators were restricted from holding equity interest in TDE. In the first 12 months of operation (in 1996) actual revenues amounted to US$10.5 million from electricity sales of 2817 GWh. The six large distributors accounted for 94% of volume and this representing 80% of transmission revenues. On the establishment of the three new generation companies; the employees (491) were encouraged to buy shares in the new company up to the value of their severance entitlement. Workers were required to make a down payment of 5% cash, with the balance payable over a period of 13 months from closing of sale with the strategic investors. Over 90% of the workers subscribed for their full allotment. The actual divestiture involved little or no retrenchment. In fact in the case of Guaracachi 12 new workers were taken on, in addition to the 72 transferred from ENDE. The distribution divestitures in contrast took the form of a concession. Approximately 95% of ENDE’s 67% equity interest in the Cochabamba distribution company, ELFEC was sold in 1996 to a Chilean utility company, ENEL at a price of US$50 million. ENEL also took over US$22.5 million of debt. ELFEC’s four hundred and eleven employees in 1994 were reduced to 313 by 1996, mostly through natural separation. The employees took up the remaining 5% of the equity. The company provided electricity to 70% of households in the Cochabamba area. Its gross revenue or the first full year following divestiture was US$30 million.20 COBEE the private operator also divested its equity interest in its La Paz distribution company; ELECTROPAZ, along with 95% equity interest in ELFEO to Iberdrola; a Spanish electricity utility operator. Table 18 shows the structure of distribution following restructuring and divestiture. 257 Table 18 Electricity Demand by Distribution within the SIN – 1996 Distributor ELECTROPAZ CRE ELFEC ELFEO CESSA SEPSA Non Regulated Others Total Source: Principal Owner Iberdrola Co-op EMEL Iberdrola Coop/state State Private Electricity Demand GWh 866 842 444 159 93 68 208 33 2713 % 32 32 16 6 3 3 8 1 100 Customers No. 245,000 153,000 156,000 34,000 29,000 24,000 (small) 5000 646,000 % 34 31 17 6 3 3 5 1 100 Ministry of Capitalisation and Investment, Information Memorandum, Bolivia (1997) p.46. There were 646,000 customers, with ELECTROPAZ and CRE, the two largest each respectively accounting for 34% and 32% of customer base. CESSA and SEPSA respectively had 29,000 and 24,000 customers, each with less than 6% of customer base. Up to 1999 the shares held by the state in SESPA and CESSA had not been divested. Within the isolated system there were two additional distribution companies with combined customer base of fewer than 35,000. Table 19 shows the distribution of equity interest following privatisation, whilst Table 20 shows the divestiture revenues. The strategic investors for the three generating companies were required to take over debts amounting to US$141.1 million and the issue of new equity brought in US$139.7, whilst the sale of shares of ENDE’s transmission and distribution interest realised US$90.0 million. Strategic investors also acquired 96% of COBEE’s interest in ELFEO and the entire 100% stock of ELECTROPAZ. 258 Table 19 Bolivia Post-Privatisation Distribution of Share Ownership Electricity Companies Generation Companies • Corani • Valle Hermoso • Guaracachi Transmission Company (TDE) Distribution Companies • ELFEC • ELFEO • CESSA1 • SEPSA1 • CRE2 • ELECTROPAZ 1. 2 Strategic Investor % Employ ee % 50 50 50 96 Pension Fund % 2.0 0.7 0.5 96 96 100 47.0 49.3 49.5 Oth er % Tota l % 1 100 100 100 100 4 4 100 100 100 The Privatisation was in process up to 1999– CESSA 60% private 40% state, SEPSA 100% state, Cooperative own by the users. Source: Compiled from information supplied by SIRESE Since restructuring, a number of new generating projects have also come on stream or are scheduled for commissioning by the year 2002. The most important of these is the ambitious Electrobol project, with a proposed investment of US$600 million. The plant is expected to export most of its power to the southwest state of Mayo in Brazil. 259 Table 20 Bolivia Revenues from Divestiture ENDE Transmission - TDE Distribution ELFEC Generation: • Corani • Guaracachi • Valle Hermoso Total Strategic Investor Capitalisation Income Equity US$ Cash Taken Paid Debts Taken Over Bid No (US$ M) . Method of Sale 99 95 39,991,196 50,300,000 12,000,000 22,533,559 1 4 Privatisation Privatisation 50 50 50 58,796,000 47,131,000 33,921,100 57,425,466 35,759,501 13,393,509 5 6 3 Capitalisation Capitalisation Capitalisation - 230,139,926 141,102,035 - Source: Compiled from information supplied by SIRESE Bolivia Bulk Wholesale Electricity Market The Bolivian electricity market reflects many of the characteristics of the Chilean model, except it has added some of the rigorous set of processes adopted by Argentina. The bulk electricity exchange market, like Chile is that of a cost based “gross pool”, whereby plants are dispatched in merit order, based on the system’s marginal cost, which essentially covers the cost of fuel and non-fuel variable cost. In addition to the energy node prices, which are calculated by the Load Dispatch Committee on a semi-annual basis (no later than 24 April and 25 October) for each node in the SIN, generators are able to commit firm capacity to the market and obtain a capacity payment, adopted from the Argentine and England and Wales experiences. The price discovery mechanism follows the nodal pricing principle. Node prices21 are made up of three components; base peak capacity prices, energy prices, capacity and energy loss factors and transmission payments. The node prices for the capacity and energy are indexed on a monthly basis 260 to reflect changes in various domestic and international components, including the Consumer Price Index (CPI). The market is a “gross pool” because all trades of electricity must occur through the spot market, however, parties may establish contracts but these are financial contracts to hedge risks associated with future prices. The operation started with optimum economic dispatching based on seasonally audited generation costs and water availability information. Recently the system has allowed for a seasonal bidding procedure. In effect the model is a seasonal electricity exchange market, rather than a daily pool. The process of dispatching is carried out by selecting plants in economic merit order, that are bid up to the point at which demand is satisfied. At this point the market clears. In general the pool dispatches first the run of the river hydropower, then the cheap CCGT plant, then the hydro- storage plants and finally the expensive gas turbines. The Pool controls operations and records the prices and energy trades between generators, as well as payments by users to the owners of the network. Although schedules are made yearly, monthly, weekly and daily, final dispatch occurs within real time and the whole tariff regime is based upon the system actual hourly spot prices. In order to minimise price fluctuations, distributors are required to buy 80% of their anticipated demand through three-year contracts, with 20% of transactions to be made on the spot market. However, the system in the main has up to 2000 delivered spot prices that were above node prices. At the same time distributors prefer to sign contracts at node prices, since that is what is allowed in the cost pass through to end use retail customers, whilst generators prefer to sell at spot prices as this offers higher revenues than contract revenues. The net effect is that 100% of Bolivia’s transactions are being made on spot prices, with the four generators competing for sales. This situation may change as more excess capacity builds up into the system and generators come to appreciate the benefit long-term contracts. In order to ensure transparency a national load dispatch committee; Committee National de Despacho de Cargo (CNDC) was established in 1995, with responsibility for the rules of the market involving both contract and spot prices and the rules relating to rights and duties of the agents operating in the market. In addition to planning and operating the load dispatch functions it also 261 calculates the payments to be made by all the agents operating in the market. The Committee is made up of one representative from each of the following groups; generation, transmission, distribution and large users, with the electricity regulator appointing one member who acts as the Chairman. The operating unit of CNDC is a non-profit association of all the agents of the market, which instructs the generating companies as to the timing and volume of dispatch of their respective plants. The load dispatch centre is owned by TDE, which is paid a fee by CNDC for owning and maintaining the centre. This relationship is governed by an agreement. Fig. 23 shows the organisational structure of CNDC. The separation of ownership of the load dispatch centre from control of the centre is critical to transparency. Within the market, distributors are allowed to contract directly with any generator for bulk supply, alternatively they may source supply for bulk power from the spot market. Large end users (those with annual consumption of 1000 kilowatt hours) are also allowed to buy direct from the spot market or to effect direct contracts with generators. In order to facilitate trade by large end-users, open access conditions are imposed on the distribution and transmission systems. The liberalisation of the large end user market, however, was suspended for five years to 2001 (except for those large end users who traditionally held contracts with generators, being mainly the mining companies). These large end users accounted for less than 10% of volume in 1995. In operation of the market CNDC effects a valuation of energy delivered and capacity confirmed by generator in the spot market. The price of energy is the SRMC of the system and in the absence of any constraint, this is the marginal cost of the most expensive plant in operation in that particular hour and which clears the market. CNDC also determines the firm capacity for each generating unit, which constitutes an estimate of the capacity of each plant that would be required at peak demand in a dry year. 262 Fig. 23 CNDC Organisational Structure Gencos Electricity Regulator Chairman Discos Liberalised End Users TDE Transco CNDC Board (Supervisory) Operating Unit (Management) Dispatch Instructions Load Dispatch Information Centre Feed Back (Operations) Source: Ministry of Capitalisation and Investment Information Memorandum, Bolivia, (1997) p. 16. The firm capacity is remunerated on the basis of unit cost calculated as an annuity of investment and fixed cost operating, and maintenance costs of standard plants suitable to provide peak capacity. The unit cost is increased by a reserve margin, necessary to maintain an adequate availability of peak capacity in the system. Firm capacity confirmed is remunerated irrespective of dispatch. CNDC calculates the energy and monetary balances resulting from operation, taking into account the output of generators, the demand of distributors and liberalised end users and the transactions covered by term contracts. As a result of these balances, CNDC informs each of the trading agents of their financial obligations or receipts with results from operation of the market over a specified period. CNDC acts as the coordinator for the pool into which all dispatched generators deliver all their output at the SRMC and for which all distributors withdraw their energy requirements to satisfy their contractual obligations. 263 The Regulatory Framework Bolivia like Argentina introduced the industry’s regulatory framework before restructuring and privatisation. The Sectoral Regulatory Law (SIRESE) was introduced in 1994 and provided the basic framework for the regulation of the activities of telecommunications, electricity, hydrocarbons, transport and water. The first superintendent was appointed towards the end of 1995.22 SIRESE is an innovative model that draws from the advantages of main regulatory trends. The structure established is neither a multi-sector agency, as is found in Jamaica nor a unisectoral body as is the situation in Argentina, but a hybrid of the two models.23 The structure provides for independence and autonomy, continuity and regulatory commitment and benefits from both the specialisation of a unisectoral model and sharing of cost and specialised human resources from the multi-sectoral model. At one level there is a General Superintendent, which does not directly exercise routine regulatory functions and does not have a hierarchic authority, but provides a set of rules aimed at supporting and strengthening SIRESE as a whole. Its main functions are to act as a second level appeals body and to supervise the regulatory functions of the sector superintendences, issuing opinions on the efficiency and effectiveness of their performances. The General Superintendent also coordinates operations to ensure consistency within the system. The SIRESE law provides for the promotion of competition in the utilities and transport industries where competition is possible as a fundamental objective and for regulation to correct market failures where applicable. At the other level are the sectoral superintendences (of which electricity is one of five such sectors) which have full autonomy to exercise the regulatory functions in their respective sectors. At the same time the five superintendencies operate within a common framework. The functions of the sectoral superintendents are to enforce the sectoral law and the industry specific rules. They carry regulatory powers over licencing, tariffs, technical safety and operating standards, anti-trust matters, and consumer protection matters, in addition to ensuring compliance. In the case of electricity, the superintendent was first appointed in 1996. Superintendents have been appointed for hydrocarbon, utility water, telecommunications and transport. 264 The General Superintendent and the five superintendents are all appointed by the President of the Republic from a list of three candidates (for each position) and must be confirmed by two thirds of the Senate. They exercise their functions for a period of five years and cannot be dismissed, except in the event of non-compliance of their duties. Candidates must have a university degree and ten years professional experience. SIRESE is funded from a levy, imposed on the industry and this further serves to facilitate its independence. The sectoral ministries are also prohibited from any direct involvement in the dayto-day regulatory decision-making process. The executive arm of government is restricted to the establishment of the policies and regulatory rules. SIRESE has no rule making powers; the result is that very detailed sector legislations are provided. The decisions of the General Superintendent, on appeal can further be challenged in the court; however, the court has no power to change the regulators substantive decisions and is limited to ultra-vires decisions. The electricity law also provides the regulatory framework for the operations of the electricity exchange market and empowers the superintendent with regulatory powers over the natural monopoly transmission and distribution sectors. The real challenge of the regulatory process is to promote competition in a market with so few players. As more and more independent generators enter the market, the competitive environment should, however, improve. Regulation of Transmission In addition to requiring a licence from the regulator, transmission as a natural monopoly is regulated by SIRESE in terms of technical, safety and reliability standards and prices. The transmission operator is restricted from holding equity interest in both generation and distribution and is neutral to the system in that it does not trade in energy or take any interest in the supply of energy. The regulator also ensures that the transmission operator provides open and non-discriminatory access to agents in the use of the system. 265 Transmission losses in 1995 and 1996 were 2.5% and 2.6% respectively. In 1995 the system experienced interruptions, with a total average interruption being (TAI) 43.3 minutes and of this 52% was attributable to transmission faults. TAI is the expected value of the total interruption for the average consumer for a specified period of time expressed in minutes. Failure to meet standards of reliability and safety attracts penalties. Transmission pricing also follows a two-part structure, based on capacity charge and energy charge. Transmission prices are determined on the basis of a formula; TCT = T0LL + T1 where TCT equals total cost of transmission and T1 equals tariff income. The Electricity Law specifies that maximum transmission revenues will be equivalent to total transmission costs. These costs comprise recovery of investment costs and operating, maintenance and administration costs for an Economically Adopted Transmission System (EATS). The annualised investment cost is based on an annuity methodology and is calculated on the basis of an asset life of 30 years and the discount rate specified in the Law. The recovery of operating, maintenance and administration costs cannot exceed 2% of the value of the EATS. The transmission company or owner of the Trunk Interconnected System is required to appoint an independent consultant, every four years and this appointment is subject to being approved by the SE. The consultant’s brief is to review the EATS, its replacement value and the level of operating, maintenance and administration costs. The findings of the report are the basis for the transmission tariffs, including their indexation, for the following four-year period. On a six monthly basis the SE approves the transmission payment to be made by each agent in the SIN as well as the relevant indexation formula and the conditions for use of the transmission facilities. Transmission revenue is made up of two components; a tariff income and transmission toll charge. The tariff income is the difference between (i) the total value of energy and maximum capacity withdrawn from the transmission system and (ii) the total value of the energy and maximum capacity injected into the system with values determined at the respective SRMC. This is estimated by the CNDC in respect of the following 12 months. The transmission toll in aggregate is the difference between the total revenue of the transmission system and the tariff income outlined above. It is 266 calculated on the basis of the projected tariff income and the use of the transmission system made by each participant in the SIN and is expressed as a fixed charge per kW of maximum capacity demand (in the case of consumers) or firm capacity connected (in the case of generators) at each node. The transmission toll is attributed either to generators or consumers in accordance with the Area of Influence Criteria. The Area of Influence of a generator is the line of the SIN in which transmission of energy is increased when energy supplied by such generator displaces that of the marginal plant located at the reference node. Similarly, the Area of Influence of a Consumer reflects those lines where transmission increases as a consequence of the increase of supply in the reference node to satisfy an increase in demand in the consumer’s node. Expansion of the transmission system can only be undertaken upon the approval of the CNDC and the Superintendent Energy. Returns to the TDE on new expansion have to be agreed between the other agents (but not all) in the SIN. Regulation of Distribution Prices The maximum electricity price that distributors can charge their regulated consumers is subject to price regulation. The base tariffs are calculated taking into account the following: • The cost of operating, maintenance and administration costs, interest charges, electricity purchases, taxes and other charges levied on distribution concessionaires; depreciation and return on equity. The maximum price at which electricity purchases can be passed through to regulated consumers is the relevant node price. The SE has the right to disallow any cost which it believes to be excessive or that do not reflect the appropriate level of operating efficiency or are unrelated to the distribution of electricity; • The distributor’s forecasts of electricity sales to its consumers; • The distributor’s projected revenue in respect of the sale and transportation of electricity, the use and maintenance of elements of services and any other revenues it may obtain. The tariff structure described above reflects the technical characteristics of the supply and consumption of electricity of each distribution company. The base tariffs are indexed and adjusted 267 monthly. The indexation formula comprises two components: The first component reflects variations in the distributor’s costs and is calculated as variations in price indices, less any efficiency factor to be established by the SE. The second component reflects variations in the distributors’ purchase costs of electricity and any variations in taxes or levies. The SE approves the maximum price of electricity for supply to the regulated consumers of each distribution company for periods of four years. The tariffs and the indexation formulae are also subject to major price reviews every four years. However, the SE may revise the base tariffs in the event that there is a significant variation between actual electricity sales and the forecast electricity sales used in establishing the base tariffs. The rate of return on equity used in establishing the base tariff is the arithmetic average over the last three years of the equity rate of return of the companies listed on the New York Stock Exchange and forming part of the Dow Jones Index of Public Utilities. In 2000 the rate was set at 10% real. The SE regulates the financial costs to be recognised as part of the operating costs of the distributor. The prices invoiced to the distributors and large users, however, are prices determined by the Load Dispatch Committee and is based on six month forecasted prices. Distributors and un-regulated customers are also allowed to enter into electricity supply contracts. Such contracts serve the purpose of providing an assured revenue stream to the generator, while hedging price risks of distributors. Electricity supply contracts are also allowed between two generators. Generators are therefore, able to buy and sell electricity between each other to enable them to discharge their contractual obligations in the manner that is most profitable. The original method adopted more or less involved a cost plus approach to pricing, resulting in spurious items being included in the asset base, which was passed on to the end user in the tariff. A major change subsequently, was introduced to the cost plus approach with the incorporation of price cap or RPI-X methodology. A second change has been to incorporate the rate of return to be on equity rather than assets. These changes provided the introduction of more incentives to distributors to increase efficiencies and reduce costs as they are allowed to keep their efficiency 268 savings within the four-year interval to the next review. After every four years a new tariff structure is approved. Outcome Between 1996 and 2001 over US$500 million of new capital has flowed into the electricity system for expansion. Since the restructuring, a number of new privately funded projects have come on stream without the benefit of any government guarantees. The accessibility of rural households to electricity has gone up from 14% to 19% over the period, whilst overall accessibility has gone up from 64% to 70%. A social security system has been provided for all Bolivians. In real terms all the distribution companies have shown increased prices since the privatisation of the companies in 1997 as shown in Table 21 Table 21 Bolivia -Average Real Retail Tariff (in 1997 US¢/kWh) Company Electopaz CRE ELFEC CESSA SEPSA ELFE0 Pre-divestiture 1994 1995 6.20 6.19 6.64 6.67 7.14 7.15 6.29 6.24 7.45 7.03 6.56 6.50 1996 5.99 6.69 6.84 6.44 6.92 6.24 Post divestiture 1997 1998 6.39 6.57 7.01 7.32 7.05 7.57 6.98 9.01 6.92 8.24 6.31 7.68 Source: Gonzelo Chavez Alvarez, The Electricity Sector in Bolivia, Second Draft; 2001 In 1998 nominal tariff varied between US¢6.79/kWh and US¢7.33 kWh compared to US¢6.01/kWh and US¢ 6.95/kWh in 1996. In 1995, the average price of bulk electricity from COBEE was US$36.7/MWh and for ENDEE the bulk price was US$ 37/MW. In 1998 the bulk prices had increased marginally to US$ 39.5/MWh, an average increase of 7% over the 3 year period. Prices in the bulk electricity market have shown much smaller increases than in the retail market. 269 When compared to the pre-privatisation period the divested new companies, both in generation and distribution have displayed significant increases in profitability after 1996 as shown in Table 22. The taxes paid by the companies before 1995 were negligible. The taxes paid by the industry increased to over US$ 12 million by 1997. The transmission company, TDE also increased its profit from US$ 2.9 million in 1997 to US$ 3.8 million in 1997. Table 22 Bolivia -Profitability Return on Equity Percentages (After Taxation) Company ENDE COBEE CORANI Valle Hermoso Guracachi Distribution Electropaz CRE ELFEC CESSA SEPSA ELFEO 1994 0.75 - 1995 0.63 - 1996 18.6 11.9 4.5 1997 11.1 12.2 3.6 1998 7.2 7.2 4.8 - - 6.3 3.6 5.6 - - 12.4 5.4 8.9 6.4 -36.6 -0.3 11.1 6.0 10.1 4.6 6.8 12.4 10.9 6.8 9.1 8.4 6.5 16.9 Source: Gonzelo Chavez Alvarez, The Electricity Sector in Bolivia, Second Draft; 2001 The profitability (before tax) of the overall industry in 1994 was US$ 5.1 million. In 1997 the industry profits had increased to US$ 48 million. The general picture has been one of increased profitability and increased revenues to the Treasury. There is also the added benefit in that government is no longer required to fund capital expansion costs in the industry. All the companies have increased their productivity since 1996 when compared to the pre-privatised year, as shown in Table 23. Companies have either shed labour or increased output from the same number of workers employed, or both. In 1994, there were 2500 workers in the electricity supply industry. The trend has been for a decline in the overall employment levels. 270 Table 23 Bolivia – Labour Productivity, GWh per Employee Company ENDE COBEE CORANI Valle Hermoso Guracachi Distribution Electropaz CRE ELFEC CESSA SEPSA ELFEO 1994 3.14 - 1995 3.12 - 1996 3.0 8.4 7.3 14.4 1997 3.0 10.6 11.5 11.7 1998 3.1 3.1 9.1 13.9 2.07 1.55 1.27 0.74 0.67 0.92 2.85 1.77 1.43 0.83 0.71 2.09 3.11 1.86 2.13 NA 0.87 2.68 Source: Gonzela Chavez Alvarez, The Electricity Sector in Bolivia, Second Draft; 2001 Table 24 shows that during the period 1994 to 1999 the number of customers served increased by an annual average of 8%, slightly higher than the average growth in the first five years of the 1990s Table 24 Bolivia -Number of Customers by Distribution Companies Company Electropaz ELFEC CRE ELFEO SEPSA CESSA Total 1996 238 169 164 36 26 31 665 1997 230 177 177 37 27 33 703 1998 263 197 192 39 29 36 757 1999 279 208 207 41 31 38 804 Source: Gonzela Chavez Alvarez, The Electricity Sector in Bolivia, Second Draft; 2001 Alvarez (2001)24 estimated that between 1996 and 1999 the total amount of capital investment executed in the generation and transmission sectors was US$ 245 million and in the distribution sector, US$ 156 million to give a total executed investment of US$ 401 million. Installed capacity 271 went up from 670 MW in 1996 to 730 MW in 1999, whereas maximum demand increased from 544 MW to 622 MW over the same period, giving a reserve margin of 17%, a decline from 24% over the previous period. Energy losses for the transmission system as seen in Table 25 above fell from 5.34% in 1994 to 2.67% in 1997, an improvement of 50%. Energy losses for the six distribution companies varied from 8.9% for ELFEC to 12.3% for ELECTROPAZ. ELECTROPAZ, ELFEO, and SEPSA all showed reduced energy losses between the pre and post-privatisation periods, whilst ELFEC and CRE showed marginal increases. It is still too early to fully evaluate the results of the liberalisation and privatisation; however, certain trends began to emerge after 1996. In the national economy, private investment overtook public investment. In 1998 private investments had reached 74.4%, with foreign direct investments amounting to 63.3% of total investments.25 More than half, 66.5% of the foreign investment comes from the new corporatized companies and a significant proportion of this investment went into electricity and natural gas sectors. The indications are that in the Bolivian example there were gains from privatisation in terms of higher levels of investments, improved product quality, improved benefits to the employees, improved technical efficiencies and improved fiscal benefits to the Treasury. Whether these gains from privatisation compensated for the negative distributional impact of higher retail prices and reduction in employment is another question. In the case of prices, the regulator’s role is to ensure that the efficiency gains from privatisation are fully realised and contributes to improvements in income distribution. 272 Table 25 Bolivia -Energy Losses: Percentage Companies PreRestructuring/Divestiture 1993 1994 1995 Distribution1 Electopaz CRE ELFEC ELFEO CESSA SESPA Transmission2 Company (TDE) 1 2 13.69 7.51 8.12 12.82 8.98 14.18 4.72 12.50 6.67 8.60 11.45 8.77 14.85 5.34 11.92 8.64 9.33 11.44 9.83 11.23 4.78 PostRestructuring/Divest 1996 1997 1998 8.68 10.5 7.71 8.68 8.82 7.71 12.10 10.80 9.64 9.51 9.88 10.4 3.7 2.67 12.3 9.8 8.9 10.3 9.9 9.4 N/A For each distribution company pre and post-divestiture losses Transmission post-divestiture Source: Compiled from information supplied by SIRESE There are a few important distinctions between the Jamaican electricity market and that of Bolivia. In the former, one vertically state owned firm had operated since 1972, whereas in the latter, despite the size of the market being under 600 MW a duopoly existed between the integrated state utility company and an integrated privately held electric utility. Jamaica has been dependent on imported fuel for over 95% of energy source, whereas Bolivia has access to domestic hydropower and natural gas. Bolivia had over six distribution companies in operation at the time of privatisation, compared to the single integrated distribution company in Jamaica. Bolivia had a fairly efficient electric utility system up to the time of privatisation with a tariff to consumers, less than 50% of tariff to consumers in Jamaica. Both countries had prior experience in the regulation of the electric utility markets. Jamaica divested a system with similar installed capacity and similar levels of accessibility as a vertically and horizontally integrated monopoly, whilst Bolivia took the route of radical unbundling and the introduction of competition in bulk wholesale electricity market. Bolivia went to Phase Three level of development. Jamaica, however, through the single purchaser model was prepared to 273 settle for competition for new capacity, or Phase Two level of development, without third party access. The World Bank ESMAP 2000 Report26 stated that: “The competitive model chosen by Bolivia is a hybrid of a “wholesale” and “limited” retail models, generation, transmission and distribution are unbundled but distribution covers both low voltage grid and final sales of supply. The market was closed to new entrants up until the end of 1999. ESMAP27 went on to state that: “Bolivia has chosen a “hybrid” system: it wants to enhance competition but at the same time stabilise prices through a “regulated” contracts system. A pool oriented system might be more robust” and a better solution. Hydro-plants are volatile by nature and trying to hide this will mean that the “natural” risks are hidden”. Bolivia in providing for competition at the bulk electricity market stage and limited competition at the retail market in the form of bypass which allowed large users to go direct to generators ensured that competitive pressures were introduced to the wholesale and retail markets Lessons Learnt The most important lesson from the Bolivian experience has been to demonstrate that the minimum scale of generation plants has fallen significantly; this means that several small hydroelectric and natural gas plants can operate in a relatively open and competitive bulk electricity market. The capacities of each of the post–privatised companies were less than 230 MW. The Bolivian restructuring and privatisation of a small electricity market has provided a number of other lessons, both from the point of view of public utility economics and public policy. The thesis which states that it is only in large and advanced electricity market that it is possible to carry out radical dis-integration and introduce high degrees of product market competition is no longer valid. Bolivia by introducing a well designed power market incorporating a cost based system of price discovery has demonstrated that it is possible to radically unbundle small electricity markets, below 1000 MW and introduce a high degree of competition and that the dis-benefits from increased 274 transaction costs, and loss of economies of scale are more than compensated for by the benefits of competition. It is, therefore, possible to introduce commodity exchange markets for bulk electricity and move directly from Phase One to Phase Three level of development without going through Phase Two, the Single Purchaser Phase. Power markets are not only practical in small electricity markets; with carefully constructed market design; such markets can work fairly efficiently without the serious negative effects which may arise from the exercise of market power by the small number of generators. Holburn and Spiller28 also came to the conclusion that: “in addition to the organization of transmission, governments have several options to reform the generation sectors, chief among these is decision to create a competitive wholesale generation market, where sellers bid against each other to supply electricity on a continuous basis with prices determined by market-making mechanism. Although the introduction of wholesale markets have in general been perceived as a desirable policy goal, questions have been raised about the feasibility of implementing radical reforms in smaller countries where, it is agreed only a small number of generation companies can be supported leading to an oligopolistic situation”. By entrenching the independence of the regulatory agency in the legislation the Bolivian experience shows that it is possible to develop independent and credible utility regulatory structures and regime in the poorer developing country environment. The importance of independence of market operation and regulation from the political institutions is clearly reflected in the institutional design of SIRESEE. The executive arm of government is not represented on the Load Dispatch Committee, the operator of the power market, as is the case in Argentina and Chile. The legislature mandated a clear separation for the regulatory decision making process from the executive arm of government. Not only are there transparent procedures established for the appointment of regulators, they cannot be dismissed by the executive branch unless a court finds that they are not carrying out their duties according to law. Appointments require confirmation by the legislature and this decision it is not left to the discretion of a minister, which is a feature common to most developing country regulatory regimes. In both Kenya and Tanzania the regulators were dismissed summarily without any due process of law. 275 Holburn and Spiller29 further state that: “designing regulatory institutions that are flexible enough to make balanced policy decisions in response to unanticipated events, but that they are also rigid enough to insulate policy from political pressures is a difficult task” The Bolivian privatisation experience shows that it is not only the industrial structure, which is important, also of fundamental importance is the regulatory governance structure. Bolivia provides an example where a credible regulatory governance structure has been created with the capacity to handle inappropriate political pressures and opportunistic behaviour. Finally, there is also a widely held perception that within the distribution sector, scale economies are such that horizontal fragmentation leads to increased distribution costs and encourages inefficient investment decisions. Economies of scale in distribution are driven by economies of densities, implying that the minimum scale distribution company can be very small and that the degree of fragmentation can be large. This is supported by the experiences of Norway with over 24030 and New Zealand with over forty.31 Again the Bolivian experience supports the thesis that economies of scale is not the significant factor in restructuring the distribution sector but economies of densities, hence the variation in sizes of the distribution companies from a 25000 to 240000 customers base, without any serious cost penalties to the smaller firms. 276 End Notes 1. Robert Bacon, “Restructuring the Power Sector: The Case of Small Systems” in Private Sector Infrastructure, Washington, D.C., World Bank, Special Edition (1996), p.86 2. John E. Besant-Jones, “The England and Wales Electricity Model: Option for Developing Countries” in Private Sector Infrastructure, Washington, D.C., World Bank (1996), p.47. 3. Salomon Brothers, Information Memorandum – Capitalisation of YPFB, Bolivia, Ministry of Capitalisation and Investment (1997), p.22. 4. Ministry of Capitalistion and Investment, Capitalisation Slides, The Bolivian Economy (1998) 5. Ministry of Capitalisation and Investment, Capitalisation Slides, The Bolivian Privatisation (1998) 6. Richard Bauer and Sally Bowen, From State Capitalism to Capitalisation: The Bolivian Formula, Chile, McGraw Hill (1997), p.25. 7. Capitalisation contemplates cooperation between the Bolivian citizens and strategic partners who bring fresh capital into the state owned industries. An important component of the reform was the creation of a new private pension system to replace the near bankrupt state pension, allowing Bolivian citizens shareholdings in the privatised industries. 8. In order to comply with Bolivian commercial law for each capitalisation a notional company, Sociedad Anonima Mista (SAM) was set up once the privatisation procedure and the prequalification of potential bidders was underway. This was necessary so that the SAM could issue shares. The law requires that there must be private shareholders alongside the state and the solution was to convince the workers to purchase shares prior to privatisation. In exchange for one share at US$20 (nominal) the workers were offered an option on later purchases at the same fixed price. 9. Ministry of Capitalisation and Investment (1997), Generation Briefing Memorandum, Bolivia (1995), p.34 10. Ibid, p.35 11. Ibid, p.36 12. ESMAP, Bolivia Power Generation and Transmission, Washington, D.C., World Bank (January 1993), p.20 13. Ministry of Capitalisation and Investment, Generation Briefing Memorandum, op. cit., p.35 277 14. ESMAP, Introducing Competition in the Electricity Supply Industry in Developing Countries: Lessons from Bolivia, Washington D.C., Joint UNDP/World Bank Study (August 2000), p.7 15. The Government no longer had the option of financing the utilities through multilateral sources, as both the World Bank and the Inter-American Development Bank stated that they were no longer willing to finance the investment cost of the utilities. 16. Ministry of Capitalisation and Investment, Transmission Information Memorandum, Bolivia (1997) p.42 17. Public service companies have a legal obligation to provide utility services within their franchise areas. 18. Ministry of Capitalisation and Investment, Capitalisation Slides, The Privatisation Results (1998) 19. According to Bolivian law, a concession is defined as a public service, which imposes a legal obligation on the concessionaire to provide public service on request. Concessions, therefore, apply only to the distribution, operators. The transmission and generation operators were given licences. 20. Ministry of Capitalisation and Investments, Transmission Information Memorandum, op.cit p.44 21. They are equal to the marginal costs of meeting peak power (kW) and energy (kWh) demand at each point or node in delivery to the distribution network. Marginal costs are estimated for a generator/transmission power system economically adapted to the demand. 22. Jose Antonio Criales and Warrick Smith, Bolivia Regulatory Reforms: Defining the State’s Role, Seminar on Bolivia’s Capitalisation Programme, Washington, D.C., World Bank (1997), p.2. 23. SIRESE, Sectoral Regulation System, Bolivia (1997), p.9 24. Gonzola Chavez Alvarez, The Electricity Sector in Bolivia, Second Draft, (unpublished 2001) 25. SIRESE, Sectoral Regulation in Bolivia (1998), p.9 26. ESMAP, 2000, op.cit., p.10 27. Ibid, p.18 278 28. Guy L.F. Holburn and Pablo Spiller, Institutional or Structural: Sequencing Strategies for Reforming the Electricity Industry, Berkeley, University of California, Hass Business School (November 2000), p.8. 29. Ibid., p.11 30. L. Hjalmarsson and A. Veiderpass, “Efficiency and Ownership in Swedish Electricity Retail Distribution”, Journal of Productivity Analysis (1997 a), Vol. 3, p.21 31. New Zealand Institute of Economic Research, Electricity Lines Business Performance, Ministry of Commerce , Wellington (200), p.15 279 Chapter 7 Sub-Saharan Africa Electricity Reforms: Three Country Case Studies Macro-economic and Market Background In order to understand the problems and process of electricity reform efforts in Sub-Saharan Africa (SSA), it is necessary to consider the reform agenda within the framework of development policies, which prevailed in the region after the post-war years. The problems of Sub-Saharan Africa’s electricity systems are not unique to the developing world; it is the extremity of the problems, and their levels of convergence, which give special urgency to the Africa situation. The three SSA countries selected along with South Africa have indicated their intentions to introduce radical reforms involving unbundling and introduction of competition. These countries have not only declared their intentions; they are well advanced in the implementation process. South Africa is excluded because it is a very large and fairly well developed system and typically does not display the characteristics of SSA systems. Cote d’ Ivoire was the first SSA country to introduce the single purchaser /IPP model. Ghana is the first to declare its intention to move to a power market and Tanzania, having decided first to privatise on the basis of selling the vertically integrated utility, as was adopted by Jamaica, has now decided to vertically and horizontally unbundle its small 600 MW system. Africa’s total primary consumption of energy amounts to less than 3% of world consumption, yet Africa is blessed with 15% of world hydropower potential1. Countries such as Angola, Mozambique, Zimbabwe, Zambia, Kenya, Namibia, South Africa and Tanzania are resource rich in terms of sources for power generation; hydro, coal, and geothermal or natural gas2. Despite this rich resource base, access to electricity in SSA countries is amongst the lowest in the world. In rural areas access to electricity is less than 2%3. The net effect is that the vast majority of people are denied access to electricity. Energy use per capita in 1995 averaged 238 Kg; compared to per capita of 5518 Kg in high-income countries. 280 Most of the countries in varying degrees share the same demographic and economic characteristics as shown in Table 26 for the selected case countries. For 26 SSA countries average per capita income in 1994 was US$305, amongst the lowest in the world. The rapid rate of growth in population and the combination of low per capita income means that very high levels of sustained GDP growth rates are needed to impact significantly on living standards. In fact there has been a reversal of living standard in several SSA countries. GDP growth rates for the 26 SSA countries in the decade 1970-1980 grew at 5.5%, and stagnated until 1995, before plummeting to extremely low levels for the period up to 1995 as shown on Table 26. Growth rates at an annual average of the order of 6% are needed to significantly raise the level of aggregate demand. In several countries, over 60% of the population lives in rural areas; this feature imposes serious cost penalties in expanding access. Most countries possess two are three large urban centres and outside of these centres, population is often thinly scattered and this makes it uneconomic to extend transmission and distribution lines. In fact in rural areas access to electricity is often less than 1%. Almost all the countries experienced huge budget deficits and crippling external debt burden. The high levels of fiscal imbalance and high levels of external debt, severely constrain the level of domestic capital available to maintain and expand the sector. Most of the countries have seen dramatic declines in their exchange rates and this not only raises the cost of imported capital goods needed for industry, the cost of debt when factored into an electricity tariff puts the service beyond the reach of all but a small elite group. Governments have been reluctant to pass on cost increases to domestic users, which result from a decline in exchange rate and from increased fuel prices. . 281 Table 26 Macro-Economic Characteristics of Case Countries Characterises Tanzania Area (km2) Size Population (Million) 1994 Population Growth Rate 198394 (%) Population Density, 1994 (person p/(km2) Rural Population, 1993 (% of Total) GDP 1994 (billion US$) GDP Per Capita 1994 (US$) GDP Per Capita Growth Rate 1989-94 (%) Average Inflation, 1994 (CPI p.a.) External Debt (% of GNP), 1992/93 Cote d’Ivoire Ghana Bolivia 945,000 28.1 3.1 322,463 13.7 3.6 239,000 16.9 3.2 2,150,000 7.2 2.2 30 43 71 3.0 77 58 65 41 1.6 60 0.1 10.5 665 -4.0 6.1 380 0.9 4.7 585 1.9 24.5 32 24.5 7.9 303.8 228.0 65.5 74.3 Source: Luis Gutierrez, “How do Sub-Saharan African Utilities compare”, in Power Sector Reform and Efficiency Improvement in Sub-Saharan Africa, Joint UNDP/World Bank, Washington. D.C. (June 1996) pp 61-63. For many of the SSA countries production costs are very high combined with very high tariffs. The tariffs shown in Table 27 are typical of SSA countries other than those bordering on to South Africa Peak demand for most of the markets is under 1000 MW with installed capacity around or under 1500 MW in 2000 as shown in Table 28. Most of the system sizes are much smaller than those found in Asia and Latin America and except for Ghana are about the size of Bolivia. The fact that capacity may have doubled over the last two decades, the base that they have had to develop from is very small. The systems are overwhelmingly hydro-based. An important advantage of hydro is that fuel cost is effectively free and operations and maintenance costs are much lower than for thermal plants. Capital cost is, however, much higher and the construction period much longer; consequently the payback period is much longer, often over 25 years. 282 Table 27 Electricity Systems Characteristics (Year 1993/1994) Characterises Installed capacity (MW) Reserve margin (%) Peak load (MW) Hydro (% of Total) Thermal (% of Total) T&D losses,( % of net generated) Customers per employee Residential, (as % of Total) MWh generation per employee % of population with Access Energy consumption per annum (kg. oil equivalent) Number of customers Demand growth rate (%) Sales revenue (US$ Million) Avg. tariff market excluding rates (US¢/kWh) Rate of return (%) Employees (1994) Tanzania Cote d’Ivoire Ghana Bolivia 516 71.7 301 84.0 16.0 18.0 34 240 6.0 34.0 918 142.3 382 57.6 42.4 16.3 160 41.6 957 21.0 109 1,187 0.25 1,190 99.3 0.7 17.8 126 34.0 1,918 20.0 96 646 28.0 504 52.1 37.9 11.4 314.0 35.0 1,283 56.4 309 255,070 7.6 116 8.0 481,912 3.8 641 30.1 400,000 1.5 132 3.2 549,700 6.0 225 8.4 -5.7 7457 NA 3182 6.0 3182 5.2 - Source: Louis Gutierrez, “How do Sub-Saharan African Utilities Compare” in Power Sector Reform and Efficiency Improvements in Sub-Saharan Africa, Joint UNDB/World Bank, Washington, D.C., (June 1991) pp.61-63. Only around three countries currently produce more than their domestic needs. Intra-country trade in electricity with these countries offers good potential to reduce production cost in high cost producing countries. Except for a few major hydro-plants and some coal plants in South Africa, plant sizes are relatively very small; on average below 75 MW. In many instances power is generated at a few relatively remote sites, effectively giving rise to long transmission lines and higher transmission losses and transportation costs. Between 1971 and 1989 electricity production increased at an annual average rate of 6.3% in Africa as a whole, compared to 3.3% in OECD countries, a rate, which exceeds GDP growth rates over the same period. Despite this growth, use of electricity has remained essentially an urban experience and outside of the reach of the greater proportion of the population, and especially those in the rural areas where the level of household access to electricity has been less than 2% 283 Table 28 Economic Characteristics: Decade of the 1980s and 1990s Characteristics Tanzania GDP 1998 (US$ billion) Inflation 1980-90 (%) Inflation 1990-98 (%) Real GDP Growth 1980-90 (%) Real GDP Growth 1990-98 (%) FDI 1998 Flows (US$ Million) External Debt (US$ billion) GDP Per Capita (US$) Per Capita (kWh) Access (%) Installed Capacity (MW) Peak Demand (MW) 2000 Source: 7.2 30.7 23.7 2.9 2.8 190 7.8 210 52 7 863* 450 Cote Ghana Africa d’Ivoire 11.0 7.2 5.8 47.4 15.9 7.8 28.6 25.8 -0.4 2.1 2.8 3.4 4.3 2.5 174 255 17.7 6.3 690 390 174 318 25 25 1300 1512 NA 1070 - African Development Bank, African Development Report 1999; Infrastructure Development in Africa, Oxford University Press (1999) pp 199-218. The challenge for the future is formidable, and raises the question as to whether SSA countries’ state owned monopoly electric utilities could rise to this challenge. Schramm states that4: “electricity demand in developing countries is likely to grow at more than 6% per annum over the next few decades, compared to little over 1% in the developed world. This will require huge investments for which capital will not be available if the power sector in the countries continue to perform badly as they do now - - - - - - - - - - - - steps can be taken now to reduce both capital needs and environmental impacts by more than one half if operational performance of the power sector in these countries could be improved and brought up to standards prevailing in the developed world.” Hadjimichael, Nowak, Sharer and Tahari5 of the IMF came to the conclusion that: the adjustment experience of Sub-Saharan Africa has demonstrated that to achieve gains in real per capita GDP, expansion in private savings and investment are still too low in relation to GDP to finance a satisfactory and sustainable expansion in output (of which electricity, is key, my inclusion) - - - - - - - Accordingly, public policies need to be aimed at creating an environment conducive to private sector development”. 284 The Rationale for Public Ownership of Electric Utility in Africa The rationale for public ownership of the electric and other utility enterprises by the SSA countries came about from programmatic and ideological considerations. There was the faith that the state could succeed where markets appeared to fail.6 The public ownership model has failed because political considerations have been allowed to supersede economic consideration. Ownership of the electric utility was deemed to be central to national sovereignty. The utilities were therefore, constituted with national responsibilities with the central objective being that of economic development. This is in contrast to the United States where the central objective is that of commercial profits. In many of the African countries, the privately owned electric companies were nationalised as part of taking control of the commanding heights of the economy. There was also the belief that the supply technology, being a natural monopoly required an interventionist government approach. Although electricity supply is a private good and not a public good it however, exhibits strong public interest characteristics7. The official international financial agencies, the IMF, World Bank, regional development banks and the main bilateral funding agencies equally accepted the strategic role assigned to the electric and other utilities in the process of economic development in the years up to 1980. In fact many of the state owned power projects were initiated and financed by these agencies. Of the Bank’s total US$16.5 billion of funding to developing countries for completed projects,; the 26 SSA countries received 7%8. Electric utilities therefore, came to be operated either as departments of power ministries or as statutory corporations with limited autonomy. The pre-dominant institutional arrangement for the electric utility has been that of the statutory or publicly owned organization, operated as a vertically and horizontally integrated monopoly. Kenya provided the exception, with a structure that historically has been one of joint public/private ownership. Cote d’Ivoire, while publicly owned, provided for private operation through a concession type contract since 1991. In South Africa and Namibia, ownership is distributed between the central government and the municipalities with the municipalities mainly owning distribution companies. In Zambia the private sector has been allowed to own and operate the transmission and distribution network. 285 Following the global economic crisis of 1995, there has been questioning of the traditional development model. For most of the people in the rural areas of Sub-Saharan Africa, this policy has failed to provide one of the most basic services and the prospect of receiving supply in the near future has become more distant and unlikely each year. Even for the small urban minority with access to electricity, the experiences of indifferent and poor services and sustained and frequent power outages made them impatient with the power utility performance. The World Bank experiences have been that the overall improvements in institutional development of the utilities have been modest, economic rates of return inadequate, typically below 10% and with a few exceptions improvements in operating efficiencies have been marginal. Generally, the subsidised tariff, which was designed for low income and rural consumers mostly, found its way to existing middle and high-income earners. An analysis of the electric power utilities must therefore, reflect this historical setting. This traditional policy approach, however, did deliver a certain amount of growth. Between 1970 and 1985 the installed capacity of SSA countries increased by 270% and many of the projects implemented came to symbolise success of the emerging nations, such as the Owns Fall Hydroscheme in Uganda. The overwhelming picture, however, which emerged regarding state owned power utility markets at the beginning of the 1990s, was that of low productive efficiency and poor allocative efficiency. This poor state of affairs reflects itself in the areas of technical, economic, and financial performance and managerial, institutional and regulatory deficiencies. Financial, Economic and Technical Performances One of the more serious problems experienced in SSA countries in the period up to the early 1990s was that of inadequate and poor revenue collection. The effect of weak revenue collection is that the enterprises have been unable to meet either the economic objective of economic efficiency, recovery of long run marginal costs or financial objectives, cost recovery with average revenue being equal to average cost. 286 Over the period 1979 to 1988 developing countries average tariffs fell by 32%9 in real terms, partly because of the high rates of inflation experienced and partly because of the reluctance of governments to charge tariffs, which sought to recover long run marginal cost (LRMC). In eleven of the SSA countries average tariff remained below US¢5/kWh in 1993. In general in SSA countries, except for Kenya and more recently Cote d’Ivoire10, the proportion of cost recovered from tariff revenues has been under 50% of costs. The net effect is that rates of return on assets have generally been low or negative. Very common in SSA countries has been the practice of providing subsidy or cross-subsidies from industrial users to all consumers, instead of using lifeline tariffs, and this typically benefits middle and high-income households, as they are the ones, that tend to be connected, and the ones to use more power11. The target group for the subsidy, the poor, do not benefit from the subsidy. Poor revenue collection results from inadequate accounting and billing practices, poor meter reading and poorly maintained and inaccurate meters (or the absence of meters), poor record keeping and non-payment of bills. Illegal connection, fraudulent billing and theft of electricity have been found to be widespread. In addition to commercial losses, technical losses often exceed 15% compared to developed countries where technical losses are under 7%. Many governments have been unwilling to pass on higher costs to consumers as well as to apply penalties to delinquent customers. In the small systems in SSA countries and especially those with hydro as the dominant fuel source, the reserve margins required have typically been established at very high levels, owing to variation in weather patterns and poor maintenance standards. The high levels of installed capacity which have had to be maintained, result in over-investment for the given load requirement. Although installed capacity is generally higher than peak demand, equipment downtime is often in excess of 30%, leading to inadequate capacities at times and failure to meet existing demand of customers. Weak transmission and distribution lines which typically characterise many of the systems. This leads to poor product quality; wide variation in voltage levels and sharp drops in voltages. Such variation and sharp drops in voltages resulted in damages to customers’ equipment, both household and 287 industrial. Industrial, commercial and private users have had to install backup power systems and standby generators. The general picture of most state owned companies is that they are loss makers, having to rely on public funds for both working and investment capital. Very few systems have been able to provide self-financing of their investment needs. In general they have had to depend on IDA /World Bank financing for most of their capital investment. Productivity levels are typically very low. The World Bank’s median for customers per employee in 1994 was 104, whilst for developed countries the median was over 20012. Institutional, Managerial and Regulatory Failures Almost all SSA countries have been characterised by institutional and managerial weakness and regulatory failures. Girod and Percebois13 state that: Except for a few countries, the organisation of most of Africa’s power..………..has taken a common form since the beginning of the 1970s involving establishment of national enterprises, in a situation of monopoly (de facto or by law) in charge of ensuring a public electricity services, vertical integration of the three segments of production, transport and distribution within one enterprise with supervision and the function of regulating ensured by the public ministries (tariff definitions, choice of investments, financing modalities, and appointment of managers). The establishment of power utilities as vertically and horizontally integrated state owned monopolies has meant that their operations have not been exposed to competition. There is a lack of autonomy of management, in that management does not have control over day-to-day operations or over decisions on prices, wages, employment, investments, technologies and budgets. Many power utilities are over-staffed because SSA governments use them to create public sector jobs. Employment practices are very rarely carried out on a competitive basis, with the result that the firm ends up with inappropriate skills’ levels. There is very little orientation of the enterprises to recognise and meet consumers’ needs. Users are unable to express their preferences or dissatisfaction through choice and market signals cannot be relied on to provide information about 288 demand. Regulation is enforced through self-regulation or highly intrusive ministerial regulatory practices. Regulatory reform, involving the creation of independent regulatory regimes, transparent processes and professional staff, and regulation to support the market rather than to replace the market, remains one of the major challenges. A sample survey of thirteen SSA countries by the researcher in 1998 showed that economic regulation is typically effected through the parent ministries. Table 29 shows that only Ghana and South Africa from the sample of thirteen countries had introduced independent regulatory agencies by 1998. Table 29 Regulatory Regime in Selected SSA Countries Countries South Africa Mauritius Botswana Gambia Mozambique Ghana Kenya Uganda Cote d’Ivoire Tanzania Namibia Malawi Lesotho Decisions Over Tariff & Licences Regulator Ministry Ministry Ministry Ministry Regulator Ministry Ministry Ministry Ministry Ministry Ministry Ministry Source: Compiled from Sample Survey by Researcher, 1998 Kerf and Smith14 have found from their survey that: “in response to the growing problems being experienced with the traditional public enterprise model, many Governments in Africa and elsewhere have been attempting to 289 improve performance of state-owned enterprise. These reforms attempt to give greater emphasis to commercial principles and provide a greater degree of insulation from short term political influences ---countries around the world are retreating from the public enterprise model in all sectors.” The overriding factors influencing the reform agenda in SSA countries, however, have been the need to reduce the fiscal deficit and the pressures of the IMF and the World Bank through their stabilisation and structural loan policies. SSA African countries have very rarely been receptive to the introduction of the market economy and a reduction of the role of the state in productive activities. The Role of the Donor Agencies It is unlikely that there would have been reforms without the instigation for changes by the donor agencies and especially the World Bank and IMF. Since the mid-1990s the World Bank, the regional development banks and many of the donor agencies have stated that the power and other utility sectors can support financing from the private financial markets, and that their concessionary financing will be directed more towards education, health and very basic infrastructure. A shift in policy direction took place in 1993 when the Bank reduced its emphasis on project loans and redirected its programmes towards commercialisation of the enterprises, provision of independent and transparent regulation and increased participation of the private sector in the delivery of electricity supplies. The principal mechanism for support by the IMF and World Bank has been through the various stabilisation and structural adjustment programmes. The IMF and World Bank credits have specifically been supporting reforms, including providing technical assistance, institutional capacity development and advice in building consensus. Since the early 1990s the two agencies have introduced effectiveness conditions tied to their programmes. These conditions lay down specified outcomes or performance benchmarks which must be achieved in order for the individual government to benefit from specified tranche releases, as balance of payment support. The donor agencies, however, can be faulted for a number of failures as in the case of Kenya and Ghana where the governments were initially coerced into accepting reforms that they did not 290 understand or that they did not fully accept.15 The time frame established for programme implementation, often failed to take into consideration the complications of the power sector or its institutional capacity constraints as well as the political sensitivity surrounding ownership, as is the case with Tanzania. The Challenge of Attracting Foreign Direct Investment There can be little doubt that the biggest challenge faced by SSA countries in their quest to expand access of electricity and improve product quality is that of attracting private capital and especially foreign direct investment. Kerf and Smith16 observed that: “During the last decade” of the 1990s, investment both foreign and domestic, fell to dramatically low levels and Africa’s share of FDI flowing to developing countries also fell from 16% in 1970s to 3.5% in 1990s. With investments typically large and immobile, prices tending to be political and revenues usually denominated in local currency, investors demand substantial evidence of government commitment to regulatory and other undertakings. The challenge of attracting large flows of foreign private capital is often greater than many SSA governments have come to realise. First, political instability in the region fosters suspicion as to the credibility of many governments to long-term commitments. Second, the low per capita income, often below US$ 500 and a background of high levels of non-payment, raise concern as to whether consumers can pay market related tariffs, based on financing from the private international financial market. Third, prices are not only politically sensitive they are denominated in domestic currencies and as such revenues are exposed to unstable currencies. Fourth, domestic capital markets are thin with low capital absorptive capacities and very little opportunity in mobilising significant levels of local capital for joint venture partners. Historical rates of return of less than 5% on revalued assets are also unattractive. Fifth, African governments will not only have to be less politically sensitive to private ownership of the power and other utilities, they will need to provide credible evidence that independent regulatory structures will be developed and allowed to operate free from political interferences. Gutierrez17 observed that from a survey of 21 African countries, 291 “the investment needs for the period 1995 – 2005 is US$ 18 billion, based on a conservative demand forecast of 3.5% per annum”. It is clear that the funding required will be substantial and beyond the capacity of most governments. They will need to introduce what must be seen as radically new policies, involving cost recovery, new industry structures, hands off approaches to management and operation, higher levels of private ownership and the insulation of pricing decisions from political considerations. Both the international financial agencies and individual governments will need to take responsibility for and write off most of the debt obligations which were created from inappropriate investment decisions of the past, as it is unlikely that at privatisation the private sector would be willing to take over these liabilities. The first phase of the reform efforts, which commenced in the 1980s, sought to address the problems of poor financial and operational performances and some of the institutional and managerial weaknesses. The second phase, which commenced after 1994, provided for some relaxation of entry restrictions into the electricity generation market and the introduction of IPPs. In many respects, the single purchaser phase came about because the donor agencies, especially the World Bank came to the conclusion it was not sufficient to effect changes within the existing institutional framework and industrial structure. Fundamental changes to the traditional state owned franchise monopoly model was needed as the earlier changes to management techniques and rules had proven to be insufficient to secure sustainable improvements. It is with this realisation that the conditions of the Bank shifted from measures designed to provide for better technologies and commercialisation of the state owned enterprises to focus on liberalisation of markets, private participation and the introduction of independent regulatory structures. In the first phase of reform several governments introduced internal management performance contracts. Many of these, however, were superseded by external management contracts. External contracts are typically introduced at the stage of crisis. The experiences of these performance contracts, however, have not been encouraging. 292 The World Bank18 eventually concluded that: “In the vast majority of cases, however, performance agreements have had a poor record of sustaining reforms. In Ghana and Senegal, for example, governments reneged on their commitments to inter alia, increase tariff and promptly pay bills of government and other state owned enterprises -------Problems stems from conflicting objectives which governments are tempted to pursue under these types of arrangements. There is a growing realisation that combining government role of owner, regulator and operator is a poor institutional structure for attempting to operate on commercial principles”. In principle internal performance contracts are not legally enforceable. The realisation was that deeper reforms were needed requiring the termination of the monopoly or franchise rights of the state-owned enterprise in areas where competition is obtainable, as is the case with the generation sector and the introduction of private operators in the form of independent power producers. SSA countries responded to the reform agenda in the second phase by expanding the rate entry of independent power producers into the generation market, and concessioning out public enterprise operations. These approaches have been popular as they preserve much of the status quo, do not require the state to give up ownership of existing operations and resolve some of the problems of finance for new capacity. Partial liberalisation and partial privatisation of some services, however, do not allow for sustainable performance improvements. Profound transformation, involving vertical and horizontal unbundling of generation, transmission and distribution, the introduction of competition for bulk electricity, and increased levels of private ownership are needed. Figure 24 presents the reform framework in SSA countries. 293 Figure 24 SSA Restructuring Framework State-owned Vertically Integrated Franchised Monopoly Single Purchaser or Entry Competition in Generation Introduction of Independent Power Producers (IPPs) through 15 – 25 years Power Purchase Agreement Government Department Statutory Corporation Commercialisation Management Contracts Liberalisation of market for entry by cogenerators Joint Stock Company Concession Bypass for large consumers or liberalisation of large consumer market Joint Public/ Private company Fully Private Company Industry structure, either continued vertically integrated state monopoly as single purchaser or vertical unbundling of transmission and distribution with the T&D company as the single purchaser or alternatively separation of transmission as single purchaser Source: Adapted from Ikhupuleng Dube, “Introduction to the Zimbabwean Power Sector” in Reforming the Power Sector in Africa, eds, M.R. Bhagavan, London, Zed Books (1998), p. 244. Several governments have also sought to separate regulatory responsibilities from the operating company and the portfolio ministry so as to enhance transparency and independence in monitoring the competitive procurement of new capacity and in determining tariff. In the franchised monopoly era, governments through liberalisation have allowed limited entry of foreign investments to the utility industry; however, without a new legislative framework, uncertainties develop as to the rules of entry and the process of awarding concessions and licences to private operators. It is, therefore, important that along with liberalisation, rules are established setting out the scope of private participation and the process that will be adopted. Rules need to be established and enforced as to 294 the regulatory process. An important concern of private investors is the level of discretion to be allowed the new cadre of regulators, especially in the formative years of the regulatory process. The new regulatory framework requires pricing and other economic decisions to be divorced from political consideration. The requirement that a regulatory decision making process be divorced from the political and administrative bureaucracy and devolved to an independent agency is not only new to SSA countries, it is a radical step to make and presents a major challenge to the African administrative environment. As an initial step in the process of regulatory reform many governments have taken the first step, that of establishing the regulatory agency outside the traditional structure of the civil service and the ministry hierarchy. However, the regulatory reforms so far introduced do not go far enough, as in most instances the newly established agency operates only in an advisory capacity, rather than as a decision maker. A concurrent requirement of establishing competitive power markets is the need for an independent regulator and transparent processes, not only to safeguard independent and nondiscriminatory operation of the market, but also to ensure independent regulation of the monopoly transmission and distribution network. Up until 1995 reforms, which provided for private ownership of the power sector, governments and the wider public generally resisted structural unbundling and the introduction of competition. The solutions, which then emerged often, reflected a compromise between internal and competing forces, resulting in what was seen as politically acceptable. At the forefront of the opposition to private ownership and vertical unbundling have been public sector managers, unions and workers, sector ministry bureaucrats and particular parliamentarians. Because the process has had to be negotiated, reflecting political realities the reforms have been slow, often with uncertainties as to their outcomes. South Africa for example announced that it would introduce private ownership and vertical unbundling from as early as 1988; up to 2001; Eskom the state owned electric utility remains a vertically integrated generation, transmission and distribution company. The pace of the reform has been much slower than in other regions such as East Asia and Latin America, often with missed opportunities. Under pressure from the loan 295 conditions embodied in the structural agreements, governments often proceed to implement the reforms under hurried conditions, resulting in less than optimal outcomes. Even though many SSA governments have come to accept the rationale for change to more radical solutions, many have failed whole-heartedly to embrace the process of change. For many there is still suspicion as to the long term viability of an economic system based on competition and the guiding hand of the market, as well as to the capacity of the private sector to work for the national goal, over the limited focus of profitability and shareholder value for the few. Pressure to maintain historical privileges and uncertainty as to the outcomes have led to guarded adoption of the new market based approach. African governments often state that the priority needs of domestic electricity system is to increase accessibility from the current very low levels as against cost reduction, which has been the motivating force in mature electricity markets. More and more governments, however, have come to accept the failure of the state owned development model. The recent reform efforts have also coincided with technological developments and new market concepts, providing governments with more options in respect of reform approaches. Cote d’Ivoire Reforms Cote d’Ivoire a francophone country is located in West Africa and borders Ghana, Liberia, Mali and Burkina Faso. The population in 1998 was 15 million with per capita GDP of US$690. Inflation rate averaged 3.4% during the period 1990 and 1998, with real GDP growth rate of 3.4%. Real GDP growth rate in the period, 1980-90 showed –0.4. %. The country had a relatively stable political climate until 2000. The installed capacity of the system in 2000 was 1300 MW with 55% hydro and 45% thermal. The total number of connected customers was 525,000, giving 25% of population with access to electricity. Over the period 1952 to 1990, the franchised monopoly model prevailed, with one vertically and horizontally integrated generation, transmission, and distribution company; Energie Electrigue Cote d’Ivoire (EECI). EECI carried responsibility for all investments and rural electrification and also engaged in the export of power to its neighbours. In 1994 the ownership structure was 92.3% state, 4.7% CFD, 1.3% EdF and 1.3% small private shareholders. EdF 296 originally held 15%, however, this decreased progressively by agreement. The company is structured on a limited liability basis. By 1990, the company’s operations and finances had reached crisis level. Accumulated debt amounted to US$350 million, with the company fast running out of cash19. The problems faced were poorly designed hydro-plants, poor maintenance, low equipment availability, poor levels of revenue collection and transmission and distribution losses in excess of 20%, regular and frequent power outages, poor quality supply and a catalogue of management errors. The Government of Cote d’Ivoire was one of the first countries in Africa to initiate reform of its power sector. The reforms have been carried out in two phases. The initial reforms in 1991 involved the granting of an “Affermage Contract”, essentially an exclusive operating lease to a consortium of two French companies, the Bouygues Group20 and EdF to take over operation and management of the power system. A new limited liability company; Compagnie Ivoirienne d’Electricite (CIE) was formed with ownership structured as follows: State with 20%, SAUR and EdF 51%21, local private interest 24% and employees 5%. As part of the reforms the system was unbundled horizontally, with the state retaining ownership of the assets and responsibility for major capital investments and CIE accepting operational responsibilities, including investments for working capital. EECI was established as an asset holding company (as the Ministry of Finance continued to fund its capital investments), overseeing the concession contract, planning future investments and supervising major equipment overhaul and expansion projects on behalf of the state. CIE responsibilities included metering and invoicing customers in its own name, daily operation and routine maintenance of the facilities and in return it paid pays a fee to the state and EECI for the exclusive concession rights. Regulation of CIE was effectively by contract between CIE and EECI, rates were however, determined by the Government. The contract provided for a rate fixing mechanism, which allowed a rate of return of 20% and also included an indexation formula. The formula took into account cost as follows: CIE operating cost 35% to 40%, fuel cost 45% to 50% and investment 5% to 10%. The operation of the system also provided penalties for non-performance. This approach to the 297 reforms enabled government to continue to retain ownership, whilst the operations and management were subject to competitive tender, private operation and commercial management. The Government also removed the exclusivity for power generation in 1990 and allowed independent power producers entry to the sector. The first IPP licences were awarded in December 1992, one of the first in Sub-Sahara Africa, and programmed for commissioning between 1996 and 1998. The Power Purchase Agreement was on the basis of a “Take and Pay Contract” and all power had to be sold to CIE, being the single purchaser. The PPA was eventually signed between the Government and a new consortium22; Compagnie Ivoireinne d’ Production de Electricite, (CIPREL) jointly owned by SAUR and EdF (in the ratio of 65:35). The first set of power plants of 99 MW came on stream in 1995, followed by a further 66 MW in 1996 and the final 110 MW in 1997, providing for a total of 275 MW of new capacity. A second IPP licence was awarded in 1997, with commissioning phased over 1999 – 2000 and required the licensee, CINERGY to build a set of thermal power plants on the basis of a Build Own Operate and Transfer agreement (BOOT). The BOOT contract was to be for 23 years. The joint venture partners are Swiss based Asea Brown Boveri, (ABB), Industrial Promotion Services, an affiliate of the Aga Khan Fund and EdF. The project also benefited from US$30 million of IDA credit. As part of the institutional reforms, the Ivorian Government in 1994 created a National Electricity Fund (FNEE), under the oversight of the Ministries of Energy and Finance with responsibility for financing capital investments, servicing of debt and supervising regular payment by CIE of its fees to government. EECI roles were therefore, reduced to being that of engineering consultancy, and with continued responsibility also for planning and the execution of capital projects23. Between 1990 and 1995 the number of customers went up from 440,000 to 480,000. Average outages dropped from 50 hours per customer per year to 13 hours. Billing anomalies fell from 15% to 3%, and collection rate increased from 50% to 98.5%24. In the first year of operation, CIE earned a profit of US$2.5 million. Over the same period transmission and distribution losses fell, installed capacity increased to 1004 MW. Between 1993 and 1998 system loss fell from 20% to 17%.25 298 Access increased from 18% to 25% and workers were receiving much higher wages. Natural gas replaced fuel oil, allowing for foreign exchange savings. Exports to Ghana, Togo, Benin and Burkina Faso were now possible. Although the reforms did bring about several improvements a number of problems surfaced. Apart from the arrangements being too complex, there was lack of clarity regarding responsibility for major maintenance and investments in the distribution system and in tariff setting. Problems also developed with respect to the regulatory framework, as this activity involved some six different state organisations, each with a different role in the power sector, hence there were problems of coordination, duplication of effort, with no one state organisation having any real power over the concessionaire. When performance targets were not met each side blamed the other. Non-payment of bills by public users continued as a problem, however, on a reduced scale. The second period of reform was instituted in 1998 after a review of the operations of the industry was carried out. The decision was taken that the sector was to be opened up to further competition after the expiration of the lease contract in 2005; generation plants were to be unbundled and privatised. Distribution was also to be vertically and horizontally unbundled to provide for multiple distribution companies. In the period up to 2005 the single purchaser model was to continue to operate. Government also declared its intention to discontinue regulation by contract. In the period between 1998 and 2000 the institutional structure was simplified into three public bodies and EECI and FNEE were liquidated. One of the new bodies; I’Autorite Nationale de Regulation du Secteur de I’Electricite (ANARE) operates as the industry regulator and carries the responsibilities for economic regulation, issuance and renewal of licences, enforcement of licence conditions, and regulation of service standards. In respect of setting tariff and granting of licences, however, ANARE powers, are limited to an advisory role. The Board of ANARE is made up essentially from government officials. As part of the new structure the role of the Ministry of Energy is restricted to that of formulating and implementing general policies for the industry, carrying out indicative planning and ensuring that investments are technically sound. The executive, however, is still responsible for determination of rates, subject to the terms of the contract. 299 There has been criticism of the new reform measures. ANARE has been created by decree and not by statute and does not operate as an independent agency. Government still retains powers over rate fixing. ANARE also does not have an independent source of finance and must depend on the Treasury for annual subvention. No mechanism has been established for participation by consumers in the regulatory decision making process. Tariff continues to be set on cost-plus rate of return basis with no incentive for efficient operation by the private operators. The single purchaser system while an important improvement, only allows entry competition and does not provide for competition in bulk electricity supply or competition in the large end user market; hence, there is no pressure on bulk tariff and bulk suppliers to reduce cost. In 2001 Government announced that it intended to introduce a power market after 2005, however the transitional arrangements necessary to move from a single purchaser phase were not been stated. Although the Ivorian experiences have been regularly cited as a model to the rest of Africa, Girod and Percebois26 state that: “Many operators consider that a separate infrastructure firm, set up through an operations contracting arrangement represents no more than an empty shell, which cannot really invest because its fees are insufficient; further it may be preferable to opt for the pure concession formula, however, this is more difficult to accept given nationalist sentiment but economically more efficient”. The Ivorian reforms essentially reflect the reform agenda adopted in France. France has been reluctant to separate transmission from generation and allow the market to determine tariff. The French have been the principal foreign investors in the former French colonies of Africa . 300 The Reforms in Ghana At independence in 1957 Ghana had one of the highest per capita income levels in Sub-Saharan Africa, however, by 1993 Ghana’s economy had virtually collapsed. Average real GDP growth during the period 1980 to 1990 was 2.3%, increasing to 4.3% during the period 1990 to 1998. GDP in 1998 was US$7.1 billion. Inflation levels in the two periods respectively were 47% and 28.4%: Per Capita income in 1997 was US$370. Ghana has carried out one of the most thorough adjustment programmes in SSA27. As a result the average annual increase in real GDP increased from 2.3% in the period 1980-1990 to 4.3% in the period 1991 - 1998. Ghana discontinued the socialist and controlled economic model of development in the early 1990s and aggressively embarked on a market-based approach with strong support from the IMF and World Bank. As regards the state owned enterprises the reform agenda first focused on commercialisation and the exposure of the enterprises, to hard budgets. The divestiture, however, did not get off the ground until 1994 when foreign investor participation in the Ghana Stock Exchange was allowed for the first time. The installed capacity of electricity in 2000 was 1652 MW, increasing from 1032 MW in 1998. The system consists of 1072 MW hydro-plants, made up of the 912 MW Akosombi station and the 160 MW Kpong station28, in addition to 550 MW of thermal capacity. Peak supply, however, is about 870 MW, while peak consumption is 1070 MW, giving a shortfall of 200 MW, made up mainly from imports from Cote d’Ivoire. Imports in 1998 amounted to 18% of demand. Access to electricity also increased from 20% in 1994 to 25% in 1998. Per capita consumption of electricity is 255 kWh. Large industrial users consume 40% of output in Ghana, presenting a different consumption pattern when compared to the other two case study countries. The Volta River Authority (VRA), founded in 1961 operated as a vertically and horizontally integrated state owned utility up to the early 1990s, providing the only source for generated power. VRA owned 94% of national generation capacity with the remainder belonging to two large mining and aluminium owner operators. VRA sold bulk power to two state owned distribution utilities; the Electricity Corporation of Ghana (ECG) founded in 1967, and operating as a transmission and distribution monopoly in the South of the country and Northern Electricity Department (NED), a 301 subsidiary of VRA operating with similar monopoly rights to the North of the country. VRA also sold directly to large users and at that time exported to Togo and Benin. In 1989 as part of the government’s reform effort VRA’s operation was placed under a management performance contract. In 1994 ECG entered into an external management performance contract with a joint venture interest, involving SAUR and EdF for the handling of the firm’s customer service activities. Reforms introduced in the early 1990s, terminated VRAs monopoly on generated power and VRA has since been required to compete with private power producers. Generators are also allowed to trade amongst themselves, sell to intermediaries, to major consumers or sell directly to the two distributing operations. With the liberalisation of the generation market, a number of IPPs were awarded power purchase agreements in the latter part of the 1990s. The first set of PPAs went to the Tokoradi Power Complex. The complex has been designed for installed capacity of 660 MW of two CCGT plants each of 330MW. The investment is owned 50% by VRA and 50% by CMS Energy of Michigan USA. A number of other PPAs were also awarded; however, construction of some of these facilities was never initiated. Government was also developing a 125 MW power barge, which was to be installed at Efasu in the western region, and the intention was to privatise this facility by a long-term operating lease. In 1998 Ghana went through a major power crisis due to the low reservoir levels in the two existing hydro-facilities, Akasombo and Kpong. As a short-term measure two power purchase contracts, with duration of 18-24 months were signed; one with a UK firm Aggreko Plc., and the other to Cummins Power Generation Plc, each for 30 MW additional capacities. Both came on stream after 2000. Despite earlier liberalisation of generation, Ghana has not been able to meet its power needs. The previous administration announced further reforms calling for a move away from what is a single purchaser model to introduce vertical and horizontal restructuring of the industry, as well as to provide for the introduction of product market competition in bulk power supplies. Under the new reform measures, VRA’s transmission system is to be unbundled and incorporated, as a fully state owned National Grid Company (NGC). NGC is to be given a licence to operate as 302 an electricity transmission operator. In this capacity NGC will only be required to provide transmission wire services and will not participate in the trading of bulk power. The distribution assets of ECG and VRA are to be horizontally unbundled into five regional distribution companies. Government is expected to sell 51% of the equity in each of the five companies to strategic private investors and to retain 49%. A wholesale power market is to be established providing for a bilateral contracts market and a balancing spot market. The contracts market will provide for agreements for physical capacity between generators on one side and large users, distribution companies and intermediary traders on the other side. The market for large end users (over 5 MW) is to be liberalised, enabling these users to enter the power market or contract directly with generators for their supplies. An independent entity, a Market Administrator and Systems Operator (MA and SO) is to be established to carry out the market administration and systems operations functions, operate the price discovery system, determine dispatch instructions, and manage the settlement arrangements. The MA & SO is to carry a three-member governance board, made up of one representative from the regulator, one from the Energy Commission and an industry representative. Essentially, Ghana has opted for a non-stakeholder board to supervise the power market operation; however, the board required to supervise the electricity market is to include two public officials out of a membership of three. This could be seen to involve too much public involvement in the liberalised market operation. Government also introduced a Public Utility Act in 1997, providing for the establishment of a multisector utilities regulatory agency based on the state regulatory system in the USA to regulate the energy and water sectors. Telecommunication has a separate industry regulator. The new agency, Ghana Public Utilities Regulatory Commission (PURC) was established in 1998 as an independent authority. Theoretically it is supposed to be free from ministerial control and direction. Administratively, PURC comes under the umbrella of the Office of the President, with the Chairman accountable directly to the Office of the President. PURC consists of a board of nine, with stakeholder representatives from labour, industry and commerce and domestic consumers, as well as four professionals selected as independent experts and appointed by the President. It is to be funded and eventually self-financed from a levy, imposed on the industry. Its statutory legal powers 303 are to grant licences, regulate tariff and standards, promote competition, provide for protection of consumers’ interest and advise the Government on industry policies. The Board of the Commission is supported by a professional secretariat with a full-time Director. An additional institution established under the Public Utilities Act is that of an Energy Commission to act as an advisory body to the Ministry of Mines and Energy and to co-ordinate energy policies. The changes with respect to the new industry structure and market arrangements are to be implemented over a transitional period of five years, 2000 to 2005. A new administration however came into power in 2001 and has delayed the implementation, while carrying out a review of the existing policies29. Ghana also intends to play a leading role in the development of the proposed West African Power Pool. Ghana is one of the first SSA countries to declare its intention to establish a power market for bulk supplies; however, the Government involvement as joint venture partner in the generation and distribution companies is likely to circumscribe the competitiveness of the market. It is very difficult to see how a competitive market structure will be able to develop when Government owns the major generation company and that state company is also a 50% shareholder in the main thermal company. Additionally, transmission is to be fully owned by government and the five proposed distribution companies are to be 49% owned by the state. The combination of rate of return regulation, based on the US system, continued major state ownership at all phases of the ESI and expansion of private power by long term power purchase agreements will not provide the necessary competitive pressures for improved efficiencies and lowering of cost. All indications are that these reforms are not well thought out and that effective competition is unlikely to develop. The major problem is that Government is still reluctant to devolve itself of ownership of the industry despite its stated public policy of the private sector being the engine of growth, reflecting continued mistrust of private ownership and the market in the essential utilities. Ghana estimates that the capital requirement for the system over the 5 year period will exceed US$1 billion dollars. It is unlikely that the state will be able to finance its share of investments to be able to hold on to 49% of equity in the respective companies selling of shares on the domestic stock market or experience a reduction in its equity holding is a likely consequence . 304 The Tanzanian Power Sector Reforms The Tanzania electricity sector displays one of the most extreme case of poor performance of a state owned electric utility. The period 1960 to 1980 saw serious decline in economic performance with the result that by the mid-1980s, the Tanzanian economy was at a state of collapse. GDP in 1998 was US$7.8 billion and although the Tanzanian population of 32 million is slightly larger than Kenya, its economy is only about 75% the size of that of Kenya. Up until the 1990s, Tanzania followed an extreme socialist model with the state owning most assets and responsible for all development. Over 400 state enterprises came into existence. Over the two periods, 1980-1990 and 1990-1998 real GDP growth was 2.9% and 2.8% respectively. Tanzania is one of the poorest countries in the World, with per capita income in 1997 of US$210. The country’s external debt reached US$7.8 billion in 1998 and the country had come to exist mainly from donor support and food aid. In 1990, the socialist policies were reversed and Tanzania with strong support from the World Bank, the IMF and a group of donor agencies led by the Scandinavian countries, set about major reform of the economy. The reform is attempting to reduce the state’s role in production and in regulating economic activities and is placing more emphasis on macro-economic stability and fiscal prudence. The market based approach; with the private sector assigned the principal role to drive the production process, formed the foundation of the policy shift. The macro-economic fundamentals between 1995 and 2000 have been positive. Real GDP growth has averaged just over 4% per annum, inflation fell from 21% in 1996 to 5.9% in 200030 and the exchange rate has more or less stabilised. The state owned enterprises have been a major drag on the fiscal budget31 ; a result reforming this sector via privatisation and introduction of competition became a central platform of the reforms. The installed capacity of the Tanzania interconnected electricity system amounted to 712 MW in 2000. An additional 28 MW formed the isolated system. The system is dominated by hydro, with installed capacity of 555 MW, the balance of 167MW being thermal. Additional capacity of 100 MW of thermal power was due to be operationalised in early 2002. Peak demand in 2000 was 440 MW, 305 in principle giving a substantial reserve margin of around 80%32. The hydrological situation, however, is such that variation in the hydro-generation can result in 40% lowering of available capacity over the average level. There have been three periods of drought, resulting in major load shedding since the 1990s, the most recent being in2000, when 16 hour daily power cuts became common. Power outages continue as a regular experience despite the addition of 75 MW of thermal capacity in 1995 and 180 MW hydro-capacities in 2000. Less than 7% of the population has access to electricity and in the rural areas access is less than 1%. The Tanzania Electricity Supply Company (TANESCO) has been the sole vertically and horizontally integrated electricity supplier on the mainland and supplies bulk electricity to Zanzibar. There are two small private producers and both supply bulk power, amounting to a combined capacity of 5 MW to the grid. Tanzania also imports power each year via cross-border connections with Uganda and Zambia, amounting to 8 MW and 5 MW respectively. Electricity production in Tanzania started in 1908 when the Germans established a plant to supply the railway workshop. In 1920, the British administration established an electricity department under the direction of the General Manager of Tanganyika Railway to provide supplies to the public. By 1931 two private companies emerged and were each given separate licences; one of 60 years and the other of 80 years. Government in 1964, however, nationalised the private operators and merged the existing electricity interests into a new entity, TANESCO as a limited liability company with the Government as the sole shareholder. TANESCO operates under a 55 year licence awarded in 1957. TANESCO has been run at the subordination of the Government with relatively little autonomy. The system of pricing has over the years reflected excessive subsidisation. In terms of tariff policy the company is allowed to increase prices by 5% each year. Increases above 5% and up to 10% require the approval of the sector ministry and over 10% that of the Cabinet. TANESCO’s tariff has over the years failed to recover cost. In the early 1990s the tariff fell from US¢11.31/kWh to ¢4.32/kWh, before increasing to ¢9.38/kWh in 199433, mainly because government failed to pass on increased cost resulting from devaluation and inflation. Residential consumers which account for 60% of total sales in 2000 were supplied at rates which were 40% to 50% below long run marginal cost, and Zanzibar its largest customer amounting to 5% of sales, paid 306 rates which were less the 50% of LRMC. Industrial customers were required to cross-subsidise residential customers and in doing so pay more than 40% above LRMC34. Government and the World Bank responded to the weak technical and financial performance of TANESCO initially by seeking to improve the system’s technical and administrative capabilities. A series of World Bank projects, funded under IDA’s concessionary credits sought to modernise the plants, increase capacity and improve the management and technical operating capabilities. A performance management contract was introduced in 1996 and an attempt was made to raise prices to LRMC. Government responded with further reform measures in 1996, discontinued TANESCO’s monopoly for generated power and under hurried and non-competitive conditions, (sole source negotiation) awarded a power purchase agreement to a Malaysian consortium, Independent Power Tanzania Ltd (IPTL). Construction of the IPTL 100 MW facility was completed in 1998, but up to October 2001 the plant had not been commissioned due to a dispute, which developed over the bulk tariff. The matter went to arbitration and the arbitrators ruling in December 2000 disallowed US$38 million of capital charges, which was to be recovered as capacity charges. Investment was originally estimated at US$90 million, but on completion the IPP declared costs of US$150 million. The contract called for a slow speed diesel; however, a medium speed diesel was installed. Typical cost of medium speed diesel was of the order of US$850/kW to US$900/kW, compared to the project cost at US$1700/kW. TANESCO and Government are required to bear all IPTL’s significant risks associated with this project, including cost overruns, taxation and inflation. The open ended sovereign guarantees provided mean that Government will have to meet the stranded costs incorporated in the high capacity charges. The introduction of IPTL into the system will result in a 20% average increase in tariff, which at over US¢10/kWh is already one of the highest in Africa. Government also entered into a second agreement in 1997 to convert 112.5 MW of TANESCO’s diesel turbine capacity to natural gas as part of a gas to electricity project, involving extraction of natural gas from Songo Songo Island and transporting via a 25 km marine and a 217km land pipeline to the Dar es Salaam Ubungo Plant. The project is expected to cost US$285 million. Equity is equivalent to US$72 million. The lead partner is AES Americas Inc., and the consortium of 307 financiers includes the World Bank, European Investment Bank, and the Commonwealth Development Corporation. Government’s very small equity position (less than 5%) is to be held through TANESCO and one other state agency. The contract is structured as a Build Own and Operate (BOO) instrument , and the duration of the PPA is 20 years. With the IPTL court case this project also ran into problems and has since been renegotiated to include the existing partners with the new date for commissioning being 2003, the gas development cost, however, is included in the capacity charge and the result is a relatively high unit charge. TANESCO, however, remains the sole supplier to end users, as the IPPs are required to sell all bulk electricity to the vertically integrated utility. Although there are 400,000 connected household users, over 50% are based in Dar es Salaam the main urban centre. The rural areas rely on wood and charcoal to meet their energy needs. The company has continued to experience inefficient operation and poor financial performances, despite charging an average tariff of US¢10/kWh. Its system losses have been estimated at 25% to 35%, with over 50% coming from illegal connection, incorrect billing and corrupt sales practices. The company has been recovering revenues from less than 60% of power produced and receivables amount to over 6 months revenues at times. Government and public enterprises account for over 75% of receivables, and Zanzibar its largest customer with 5% of sales, has failed to pay its bills which are being invoiced at under US¢3/kWh.35 The company’s debt equity ratio in 2000 was 90% and this crippling debt burden means that government has had to meet most of the company’s long-term debt servicing obligations to the donor agencies. The company is over-manned and needs to shed 30% of its work force. Its productivity levels are very poor, less than 57 customers per employee in the year 2000. Generation outages reached 1130 hours in 1995 and have fluctuated widely over subsequent years. TANESCO’s annual revenues in 1997 amounted to US$174 million, and for the first time for several years the company posted a profit of US$5.6 million. The losses, however, continued after 1999. The company’s poor financial performance has become a major concern of both the Government and the World Bank.36 308 These developments led to a decision by Government in 1998, to privatise 51% of the vertically integrated company. The researcher as lead advisor on public enterprise reform to the Government was able, however, to influence the authorities to revisit this decision, and a new policy was announced in October 1999 calling for vertical and horizontal unbundling, the introduction of a bulk electricity market and increased levels of competition in the electricity supply system. The Government faces difficulty in implementing this new policy, since it has already committed 212 MW of capacity of a system with 440 MW peak demand to 20 year PPAs and a portion of the capacity charges reflect stranded cost. The question arises as to how much competition will be possible in such a situation. The new policy direction, in addition to vertical separation calls for horizontal unbundling of generation, into three companies, two hydro and one thermal, two regional distribution companies, separation of social electricity from commercial electricity and the establishment of an independent multi-sector regulatory agency. There is to be one single transmission operator, preferably with its assets owned by Government and leased to an investor for private operation. In order to facilitate increased competition in the electricity supply system, third party access is being considered for the transmission and distribution sectors, with bypass for large end users. The new policy calls for private investors to play the leading role in providing future investments and in the operation of the industry. There is still, however, pressures from special interest groups for Government to maintain major equity ownership in the generation and distribution companies targeted for sale. A multi-sector regulatory Act was passed in April 2001 and an Energy and Water Utility Regulatory Authority is to be established in 2002. Separate industry legislation is also scheduled for introduction in 2003. Over the period 1998-2000 TANESCO’s operating and financial performance has, however, deteriorated to an alarming level. Government has, therefore decided as an interim measure to award a two-year management performance contract to a private management firm from March 2002. At the end of the two-year period the unbundled generating and distribution businesses are to be privatised. 309 Tanzania will not be able to attract merchant plant type investors. At the other extreme long term PPAs for the entire production will need to be avoided. The solution would, therefore, seem to be to allow distribution companies to acquire part of their power needs through direct contract from the generating companies; including the assignment of the TANESCO’s PPAs, and for a balancing or spot market to operate to facilitate the integration of transmission with generation. The expectation is that a contracts market will operate in the initial years gradually leading to bilateral contracting and a balancing spot market. In order to introduce competition in bulk the electricity market, considerable changes will be required to the institutional structure, technical system, especially in the load dispatch centre and telecommunication system. New water rights legislation will be required and the future role of the Government, especially in allowing for independent operation of the market and the regulatory regime, will need to be assured. The financial structure of the industry also presents a major problem in respect of the very high capacity payments of the two PPAs, which are in effect expensive foreign debt financing, and when rolled into the cost structure leads to unacceptably high average tariff. These challenges, which Tanzania faces, have yet to be successfully overcome in any SSA country. Regional Interconnection Opportunities The Southern African Power Pool (SAPP) provides the first formalised market for cross-border electricity trading. Regional electricity trading provides an opportunity to reduce power systems cost. The opportunity to reduce costs arises from the mis-match between countries which have economic hydro-resources and South Africa’s excess fossil-fuel capacity and the countries with the greatest load or the opportunity to replace high cost thermal production as is currently the case with Botswana, Namibia and Zimbabwe. Constraint to trade arises from physical, political and market factors. Currently interconnection is at the level of the sub-regions; East Africa, Central Africa, West Africa and Southern Africa. A number of studies such as the Tanzanian/Zambian Transmission and the SAPP Interconnection studies are underway exploring the feasibility for wider interconnection in the SAPP system. Most 310 trade at present is carried out at the border and transmission prices tend to reflect marginal cost of the exporting country, covering transmission losses and contribution to fixed cost, rather than LRMC. Overall prices are low. The existing structure of SAPP is that of a loose pool and builds incrementally on the existing structure of electricity trade in the region, based on long term contracts. SAPP protocol which came into being in 1995 and which involves 12 countries provides a framework for such contracts and seeks to complement them with an additional framework for spot trading. The larger SAPP market provides the best opportunity over the short term for a power market to develop to meet the lower cost electricity needs of the high cost producers like Tanzania and Ghana. Countries like Botswana, Namibia and Swaziland that are interconnected into the SAPP Pool and have emphasised developments in transmission and distribution benefit from costs of under US¢/3.5 kWh. A factor, which will aid the process is the increased willingness of SSAP member states to discontinue a policy of self-sufficiency in generation and to depend on their bulk power needs from cheaper neighbouring states. SAPP member states also need to cooperate and develop common legal and regulatory framework. In fact a regional regulator for the network sector of each country would be strong incentive to foreign investors. IPP faced with the opportunity for multiple purchasers would have greater confidence in its ability to sell to several large industries with strong balance sheets and therefore, minimise requirements for sovereign guarantees to be given by the respective governments. Conclusion and Policy Implications The experiences of the three case countries and the rest of the SSA are that to date they have conformed to the first two phases of the development model that of the state owned franchised monopoly and single purchaser phase. The three case countries and the most of the rest of SSA countries have moved away from a single franchised state monopoly in generation by liberalising the generation market and allowing entry of new IPP plants into the generation sector. 311 In the post-independence period the power sector formed a central policy tool of the state development model. The state owned franchise monopoly came to be entrenched as the industry structure in all the countries. Many of the problems of the sector have, therefore, been a part of the wider problem of management of the economy. The initial response of governments has been to seek solutions, which involved continued state ownership and maintenance of the vertically integrated utility. Policies, which are pursued to improve the performance of the sector in isolation of macro-economic policies, however, have not been sustainable. State operated power utilities, even where they have been exposed to commercial principles and hard budget constraints have often failed to provide for sustainable improvements in performance, as is clearly demonstrated in Tanzania. In order to avoid financial collapse of the system, the Government has had to bring in a private external management contractor in anticipation of restructuring and privatisation. While independent power production through a power purchase agreement provides the opportunity for the mobilisation of private capital and private sector participation as is seen in Cote d Ivories and also evidenced in Kenya, it does not provide the full answer. Weak local capital markets, lack of potentially strong domestic partners, imperfect legislation, especially in areas of water rights, property rights and regulatory frameworks, as well as weak court systems and antiprivate sector sentiments, still persist. IPP/PPA arrangements should be seen as a short to medium term solution; hence, it is important not to set too long a term for such contracts. Governments in their reform programme should separate transmission from generation and the opportunity should be taken to link prices to the market or else the opportunity for product market and retail competition will be put off indefinitely. IPP/PPA with take and pay commitments may come to impose serious problems in terms of future external debt obligations, should economic recession set in and demand is not realised and the take and pay foreign obligation has to be met, as experienced by the East Asian countries in the period after the financial shocks of 1998. The question therefore, arises can the systems of SSA countries, given their characteristics of being highly hydro-based with small markets graduate to a competitive power market or Phase Three level of development? An important development working in the favour of these countries is the emergence of new technology, which has reduced the minimum scale plant size, especially for 312 thermal systems. Most SSA generation plants are below 75 MW; however, today’s technology provides for minimum scale plant size of as low as 30 to 40 MW. Lending institutions in the region such as the ADB, however, as late as 1999, have expressed scepticism as to how far the structural options and competition can be taken by SSA countries in reforming their system. The ADB36 in 1999 states that: “In comparison with the telecommunication sector the electric power sector does not present scope for segmentation of services --------. Dictated by such characteristics the only segment that has opened up for private participation thus far in Africa is the generation segment of the industry. And even then, there is still debate about whether the preponderance of small scale power generation by private users is more efficient than large scale production”. The view that public ownership or the franchised state owned electric utility monopoly is strategic politically and economically to economic development has proven from the experiences of SSA countries to be flawed. Centralised control by Government not only fail to bring about efficient results, it severely limits the amount of investment capital available to the sector.37 Despite the disastrous experiences of state ownership and operation all three case study countries are still not convinced that the state should withdraw from the sector in place of full private ownership and operation. There has been reluctance on the part of many political leaders to leave such a key sector of the economy to the hidden hands of the market. Additionally, there is also the fear that the market will not respond to the needs of the rural economy and the poor. Can the Bolivian experiences provide a road map for the reform of the three case countries? Bolivia shares most of the macro-economic and systems characteristics of SSA countries; except that when Bolivia entered the reform phase it had a more efficiently operated electrical supply system. Since Bolivia, other small markets such as Panama and El Salvador have introduced radical power market reforms. In fact El Salvador envisions going beyond the structural option of a bulk electricity market and embrace retail competition or Phase Four level of development. The track records of these smaller third generation reformers are not yet well established and the 313 existing information is inadequate for us to arrive at any definitive conclusions. However, changes in the industry technology, economic theory and the growing body of examples, clearly suggest that radical reform is an appropriate structural reform option to pursue for small electricity systems. In terms of future policies governments must be prepared to limit their role in the industry to policy matters, to allow competition in the sector of the market where competition is obtainable and provide legislative framework, which allows for independent and transparent regulation. At the heart of the problem is the willingness of governments to remove themselves from interfering in the price setting decision-making process and to allow the private sector to take responsibility for investment and ownership of the industry. SSA countries will not be able to fund the capital needs, variously estimated at US$ 20 billion that will be needed over the next 10 years for the electricity sector from public finance. Without independent regulatory regimes, free from political intervention in economic regulation, these countries will not attract the high levels of private capital that will be needed. Governments of the region will need to provide the legislative framework and the market rules and not be directly involved as an active participant in market operation. A regional power market as shown earlier through SAPP offers an alternative option to pursue a competitive bulk electricity market structure. Again in terms of policy implication, individual governments will need to discontinue policies, which call for self-sufficiency of power generation. The SAPP region had a capacity of over 68000 MW and peak demand of just over 35000 MW in 2000; there is therefore, excess capacity to accommodate regional trading. Prices have, however, continued to be established below long-run marginal cost of operation. A fully working regional power market would lead to prices which reflect LRMC and although this would be of the order of US ¢4/kWh to ¢5/kWh, this is significantly lower than the cost of production of bulk power in high producing countries where costs have been estimated to be as high as US ¢8/kWh. Irrespective of the restructuring option chosen, the evidence clearly shows that the period since the mid-1990s has marked the end of an era for the sole vertically integrated franchised state owned or franchised multiple distribution electric utility in Sub-Saharan countries. The future directions will be 314 one of increased levels of competition and increased levels of private ownership and operation of electric utilities. End Notes 1. World Bank, World Development Report 1999 Knowledge For Development, Washington, D.C. (1999) 2. Sub-Saharan Africa has 8% of the hydropower potential and 6.2% of the world’s natural gas potential. 3. Kevin Morgan, Electricity Supply Industry Restructuring and Regulatory Development in South Africa, Sub-Saharan Power Conference, Midrand, South Africa (February 1999), p.3. 4. Gunter Schramm, “Issues and Problems in Power Sector of Developing Countries”, Energy Policy (July 1993), p.735. 5. M.T. Hadjimichael, M. Nowak, R.S. Sharer and A. Tahari, Adjustment for Growth: The African Experience, Washington. D.C., IMF Occasional Paper Series (October 1996), p.1. 6. G.E. Mills, Public Enterprise in Commonwealth Caribbean with Particular Reference to Jamaica and Trinidad, Kingston, Jamaica, UWI. (1995), P.5. 7. “Private goods” can be defined as those that are rival (consumption by one reduces consumption available to other users) and excludable (users can be prevented from consuming its output). In contrast, “public goods” are neither rival nor excludable. 8. World Bank, Lending for Electric Power in Sub-Saharan Africa, Washington, D.C., (1995), p.13. 9. See Schramm (1993), average tariff from a sample of sixty developing countries fell from US¢3.78 kWh in 1988, a reduction of 32% in real terms. Average tariff in 1988 was 4.46 ¢/kWh compared to average US¢8.07/kWh in-developed countries. 10. After the first set of reforms was introduced in Cote d’Ivoire in 1991. 11. Alan Townsend, “Energy Access; Energy Demand and Information Deficit”, in Energy Services for the World Poor, Washington. D.C., World Bank (2000), p.11. 12. Luis Gutierrez, “How do Sub-Saharan Africa Utilities Compare”, in Power Sector Reform and Efficiency: Improvements in Sub-Saharan Africa, Washington, D.C., Joint UNDP/World Bank ESMAP (1996), p.53. 13. Jacques Girod and Jacques Percebois, “Reforms in the Sub-Saharan African Power Industries”, Energy Policy, Vol. 26, No. 1. (1998), p.28. 315 14. Michel Kerf and Warrick Smith, Privatising Africa’s Infrastructure: Promise and Challenge, Washington. D.C., World Bank Technical Paper Series, No. 337 (1996), p.5. 15. Oliver White and Anita Bhatia, Privatisation in Africa, Washington. D.C., World Bank (1998), p.123. 16. Kerf and Smith, op.cit. p.21. 17. Gutierrez, op. cit., p.57 18. Kerf and Smith, op.cit. p.5. 19. Ibid, p.16. 20. The Bouygues Group through its subsidiary SAUR International was already involved in water distribution in Abidjan. The contract was for 15 years, lasting from 25 October 1990 to 2005. 21. SAUR owned 33% and EdF 18%. SAUR and EdF formed a holding company: Societe, Internationale de Services Publics: with ratio of stake holding 65:36. EdF also hold 35% of Saur. 22. The original PPA was with a consortium, Compagnie des Energies Nouvelles de la Cote d’Ivoire, however, it was suspended in 1994 and replaced by the CIPREL project using newly discovered oil and natural gas. 23. Jacques Girod and Jacques Percebois, “The Electric Power Sector in SSA: Current Institutional Reforms,” in Power Sector Reform and Eficiency: Improvements in Sub-Saharan Africa, Washington, D.C., Joint UNDP/World Bank ESMAP (1996), p.99. 24. Infrastructure Development in Africa, Oxford University Press (1999), p.147. 25. Allexon Chiwaya, “Malawi Power Sector”, in Reforming the Power Sector in Africa, ed., M.R. Bhagavan, London, Zed Books (1998), p.46. 26 Girod and Percebois, op.cit. p.100. 27. Ajay Chhibber and Nemat Shafik, “The Inflationary Consequences of Devaluation with Parallel Markets: The Case of Ghana”, in Economic Reform in SubSaharan Africa, eds., Ajay Chhibber and Stanley Fisher, Washington, D.C., IMF (1991), p. 39. 28. Although the installed capacity of the two hydro-plants is 1072 MW, the firm capacity is more like 670 MW due to variation in the water levels in the reservoir resulting from variation in rainfall pattern. 29. Ministry of Energy “Energy for Poverty Alleviation and Economic Growth: Policy Framework, Procurements and Projects”, Ghana, (2002). 30. Economist Intelligence Unit, Tanzania Country Report, London (August 2000), p.6. 316 31. World Bank, Adjustment in Africa; Reform, Results and the Road Ahead, Oxford University Press (1994), p. 101. 32. Stig H. Moberg, The Tanzania Power Sector, Swedish International Development Agency, Tanzania, (2001) p.12. 33. M.R. Bhagavan, Reforming the Power Sector in Africa. London, Zed Books (1998), p.92. 34. Stig H. Moberg, op.cit. p.16. 35. Deloitte & Touche, Financial Review of Performance in Tanzania, Internal Tenesco Report (2001), p. 32. 36. ADB, Op.cit. p.144 37. World Bank Aid Memorie Tanzania Project Development No. 6, World Bank, Washington D.C. (2001) ,p 8 317 Chapter 8 Analysis and Conclusion Global Trends in Electricity Sector Reforms Since 1990 there has been a global trend towards liberalisation and disintegration of the electricity supply industry. Pollitt (1997)1 states that the electricity industry has been undergoing liberalisation in 51 out of 62 countries he studied, with privatisation in 30, and vertical separation in place or planned in 27 countries. Izaguirre (1998)2 on the basis of World Bank’s data states that 70 countries have involved the private sector in their electricity supply industry between 1990-1999, with total investments of US$110 billion. This transformation is being fuelled by technological developments, which have eliminated aspects of the economies of scale characteristic, which traditionally persisted in certain sectors of the industry. The developments have radically changed electric utility economics for the foreseeable future. Both the empirical argument and the theoretical evidence presented in the case countries, strongly support the thesis that the industry is experiencing a process of competitive transformation, during which the electricity industry is moving away from the vertically integrated franchise monopoly structure, public or privately owned and which has persisted for most of the post- war years, towards one which offers consumers more choice in sourcing their energy needs. In this process of change three distinct phases have been identified, that of the purchasing agent, the bulk electricity market and retail competition. The Structural Options Some countries have tried to introduce reforms within the framework of the vertically franchised state owned monopoly structure. Invariably this has taken the route of internal privatisation or the introduction of private sector methods of operation, whilst retaining public ownership. The SSA countries, Jamaica and the UK reflected this experience. Whilst initial improvements are realisable they are not sustainable. The introduction of new methods and procedures of operation have been 318 insufficient to significantly improve economic performances that are sustainable. This was clearly brought out in the Jamaican experiences between 1998 and 2000. The structural reforms introduced in Scotland provide an example where the vertically integrated monopoly structure was retained and two privately owned and vertically integrated monopolies were created, accompanied by pubic regulation. The expectation was that yardstick competition would have been sufficient to provide incentives to the private monopolist to perform efficiently. The reforms also permitted trading amongst the two monopolists (across an interconnector), third party access was allowed and the large consumer market segment liberalised. There were, however, serious entry barriers to the competitive sector, no new independent power producers entered the generation sector between1990 to 1998. Up to 1996 the second tier retail market had grown to amount to less than 6% of the overall retail market and most of this development came from the two incumbents trading as second tier suppliers in each other’s market. It proved extremely difficult for the regulator to prevent each of the vertically integrated monopolists from exploiting sensitive information of third parties to further their own interest. The opportunity for competition for corporate control of the two incumbents was also frustrated by the golden share conditions incorporated in the two companies’ articles of association. The Scottish reforms sought to recognise horizontal and vertical economies and to accommodate non- economic goals. The net effect has been that the Scottish electricity tariff, which was the lowest in the UK in 1990, developed to be the highest by 2000. Littlechild (1996)3, the electricity regulator at that time expressed scepticism as to whether such a structure was conducive to competition and remarked that the Scottish structure was anomalous to changes taking place at the global level. Scotland has since had to conform to the European electricity competition directives and as a result several changes are under consideration, including integration into the E&W market, interconnector trading and the establishment of an independent systems operator so as to provide for a more transparent and competitive environment. 319 Purchasing Agent as a Reform Option The reforms in Jamaica, Northern Ireland, Cote d’Ivoire, Ghana and Tanzania reflect the policy choice of countries that have opted for the purchasing agent phase of development. At this stage, the critical changes have been liberalisation of the generation sector and introduction of competition for new capacity, with competing generators given the right to sell to a single or principal buyer. In the pure purchasing agent model, third party access is not permitted; hence all consumers remain captive buyers. Modifications are sometimes introduced, providing for bypass for very large industrial consumers to contract directly with generators. At this phase of development, the critical structural issue is whether generation is separated from transmission. Separation has the advantage that it reduces the problem of self-dealing and internal conflicts of interest. Where third party access and bypass are allowed for large industrial consumers, additional competitive pressure is introduced on the incumbent to improve its performance. The structural relationship of transmission and distribution is not critical at this stage. Northern Ireland and Kenya in their restructuring kept transmission and distribution integrated. However, if retail competition is the long term objective, transmission should be unbundled from distribution so as to reduce the problem of market power. Sub-Saharan Africa, East Asia and the European Union reforms have adopted the purchasing agent model. The motivation is that it relieves the national budget of the responsibility for capital to expand the industry and involves less structural upheaval. To a large extent, the status quo can be maintained as the state can continue to retain ownership of the incumbent integrated utility. Many SSA countries are still fearful of the uncertainties of free market and private ownership and often face intensive pressure from a coalition of interest groups (labour, management and the churches) to retain state control. The EU has also adopted the principal agent model except that bypass of the network has been mandated to allow up to 33% of end users (eligible consumers)4 choice in sourcing their supply. The French have significantly influenced the European Union’s policies. France has been reluctant to disintegrate its electricity utility and provide for private operation. The Principal agency model as a form of restructuring is considered a likely option where economies of scale is still strong and 320 opportunity for competition is weak or non-existent and where the monopoly structure is still considered the most efficient arrangement. This is said to apply to the French dominated nuclear system.5 Economies of scale are still obtainable with large nuclear plants. Uganda has also opted for a purchasing agent model because the hydroelectric Owens Falls power complex dominates the relatively small system of less than 200 MW. France like Scotland has had to introduce reforms recently to meet the European Union electricity competition directives. In 2000 France introduced legislation designed to restructure the ESI. The changes call for accounting, operational and management separation of transmission from EdF’s generation business into a new division, questionnaire du reseau public de transport (GRD) as well as and accounting and operational separation of distribution from transmission. The separated distribution business and 170 non-nationalised distributers were designated as qestionnaire des reseaux de distribution (GRDS). The Act also provides for the establishment of an independent industry specific regulator, Commission de regulation de I'electricite. (CRE)6 The regulator is empowered to regulate third party access, interconnection and the system operator. In the principal agency phase the regulatory responsibility resolves itself around preventing the natural monopoly network sector from leveraging its market power for its own interest and ensuring competitive procurement of new capacity. If generation, transmission and distribution are vertically integrated, regulation is required to guard against self-dealing and conflicts of interest. In the case of France, CRE’s power is limited to references to the Conseil de la Concurence. The purchasing agent structure is superior to that of the vertically integrated franchise monopoly model in that it reduces the regulatory burden. A certain amount of capital market pressure is introduced into the industry and the opportunity for inter-utility competition is enhanced where generation is vertically and horizontally unbundled. The structure also provides incentives for more efficient levels of investment in capacity and this was demonstrated by the experiences of the Northern Ireland system where inefficient oil plants were replaced with cheaper natural gas plants. Its major problem is that the structure does not readily accommodate retail competition should the decision be taken at a later date to provide for choice for all consumers. If third party access is 321 permitted for the large industrial users, then the small household domestic consumers are left to shoulder any stranded cost, which may have resulted from the poorly designed power purchase agreements. For those countries that have introduced a disproportionate amount of power purchase agreements with elaborate sovereign guarantees incorporated in the PPA’s, there is the risk that the national budget may have to shoulder the foreign capacity charge obligation should there be economic recession and the forecasted demand fail to materialise. Bulk Electricity Markets as a Reform Option In the third phase of market transformation, that of the bulk electricity market, competition amongst horizontally unbundled generators is introduced, as was the case in England and Wales in 1990 and Bolivia in 1996. In both cases the reforms did not have to progress through the purchasing agent phase. Instead radical unbundling was introduced, with the structure being transformed from the franchised monopoly stage to the bulk electricity market model. The bulk electricity market arrangement adopts most of the principles of commodity markets, however, electricity inter-changeability is not as simple as other commodities, such as gold or oil as it cannot be stored for later use. One shipment of electricity at one point in time is not a perfect substitute for another shipment at a different point in time. This makes it difficult for arbitrage in electricity as is possible with other commodities. There are strong vertical economies between generation and transmission, despite physical unbundling, and the need for system balance sets up a contradiction between the requirement for central coordination and the individual action needed for competition. Market power cannot therefore be entirely eliminated. Bulk electricity markets entails bilateral contracting between generators and multiple local distributors, supported by a centralised pool, as was the case of E&W market (during the first 10 years) and the Bolivian market or a balancing spot market which provides for settlement balancing between contracted amounts and physical flows, as is the current E&W and Scandinavian markets. The local distributors, in addition to paying for energy and related services are also required to pay a wheeling charge for use of the network. The important structural decision revolves around the separation of transmission from generation and the creation of horizontally unbundled independent generation companies. If transmission is 322 integrated with generation as was the case in Chile up to 1993 or if transmission is jointly owned by the generators as is the case in USA where in some states the investor owned utilities have separated out transmission into a jointly owned not-for- profit company or if transmission is jointly owned by the distributors as was the case in E&W up to 1996, the problem of leveraging market power and self- dealing arises, requiring stringent regulatory oversight. There is also the need to separate generation from the distribution lines business and to avoid distribution companies owning significant levels of generating capacity as this provides strong incentives for the distributors to favour their generating arm although this may not be the least cost plant when dispatching. There is a lessening of the regulatory burden at this phase of transformation in that the need to set bulk energy tariff is eliminated; however, the regulator should be given the powers to approve the rules for the market and any future changes to such rules as well as to monitor the operation of the market to guard against abuse of market power. The main regulatory effort can then be structured to concentrate on the natural monopoly network so as to prevent this sector from charging monopoly prices. Where there are only a few players in the generation market as is often the case in small emerging markets, the opportunity to exercise market power is significantly increased. Because of the duopoly structure, which was created in the E&W market in1990, the problem of market power persisted for most of the ten-year life of the Pool. The bulk electricity market phase introduces product market competition, provides incentives for productive efficiencies and for distributors to rationalise their businesses into more efficiently organised enterprises. Market and technology risks are restructured and are more equitably distributed and the electricity industry becomes less vulnerable to the errors of central planning. Power markets also create distributional problems in favour of shareholders and investors. Without competition at the retail level there is no guarantee there will be allocative efficiencies. Regulators have only marginal power to correct this problem since the regulator controls less than 30% of system cost. On the negative side, transaction costs are significantly increased from the several market agreements and technology risks. The cost of capital becomes much higher as the industry now has to secure its finances from the commercial financial market. The introduction of a bulk electricity 323 market also raises the problem as to how to deal with the stranded capacity charges. In Tanzania it was estimated that the tariff would need to be increased by 20% (or US¢2 /kWh) to accommodate the stranded cost of the two IPPs. This raises the question as to whether the users should meet the burden of the stranded costs or whether this should be borne by the general taxpayers. In the UK a levy of 10% was introduced during the first 6 years to meet this cost whereas in the US the regulators have tended to pass it on through the retail tariff. Distributional problems are also raised if one segment of the end user market is liberalised and the household captive users are required to underwrite all the stranded costs. It is possible to move from a franchised monopoly stage to a bulk electricity market, however, in most developing countries electricity markets are not sufficiently mature to accommodate such a radical change and they need to go through a transitional period of a 5 to 7 years before transforming to a commodity market, as was the case in Panama and as was contemplated for Northern Ireland. The Main Sub-options under Bulk Electricity Markets The objectives of electricity markets like all other commodity markets are to provide for transparent transactions, to facilitate price formulation, provide maximum incentive for efficient production and provide incentives needed for additional capacity. Despite these common objectives, international experiences have been that of wide variation in the design of electricity markets. The questions as to whether markets should be compulsorily organised or whether price discovery should be pricebased or cost-based have still to be resolved. The transmission system also can be designed to take on several different roles. The introduction of a two-sided balancing spot market with balancing contracts in the England and Wales market in 20017, for example, intensified the controversy as to whether a single-sided, one price mandatory auction market is less effective in providing for competition than a voluntary twosided discriminatory price auction market. Both single-sided and discriminatory price auction markets are commonly used in financial and other commodity markets. 324 In England and Wales, operation of the single-sided pool and the particular characteristics of the market resulted in widespread exercise of market power, particularly close to real time when the system was constrained. This problem persisted even after a significant reduction in market concentration and when there was no single generator with market share of more than 20%. The expectation therefore has been that the two-sided auction market would significantly reduce the scope for the exercise of market power. For Trebilcock and Gal (1999)8 a two-sided market provides better discipline over market power than a one-sided auction market. In sharp contrast, Harbord and McCoy (2002)9 state that “neither theory or empirical evidence tells us that discriminatory price auctions perform better than uniform price auctions” .In Harbord and McCoy’s view, the new England and Wales market is severely flawed in that the design increases, rather than reduces the opportunity for market power. When the trading arrangements were put into experimental test in 1999, one clever trader, writing specious quantities and prices in the balancing market fictionally made millions of pounds in a matter of days to the embarrassment of the designers. Norway was the first country to adopt the bilateral contracting, and voluntary spot market; however, the system unlike in the UK and Chile did not have a history of centralised system operation. Several small municipally owned hydro-plants provide over 60% of generation in Norway, and bilateral contracting was found to be more appropriate for this structure. In the case of cost-based versus price-based mechanisms for price discovery, Millan (2001)10 points out that Latin America has by and large opted for cost-based and this is in sharp contrast to the Europeans, where the priced- based mechanism has been preferred. The characteristic of hydropower systems in many Latin American countries and a history of cost-based dispatching by merit order of hydro plants, seem to have influenced the Latin American policymakers towards a costbased power market. The supporting arguments for the use of a cost- based price discovery mechanism, especially in small electricity systems are that it ensures efficient dispatch and if generators are honest about their cost it reduces the opportunity to exercise market power (which is critical in concentrated small 325 systems). It is less sophisticated, easier and less costly to implement and it can evolve to a price based system as the market matures. In the early phase of small concentrated markets, there are usually insufficient bidders to secure effective competition. Policy makers also encounter a range of options as to the role of the transmission operator as well as the ownership of the transmission system. In the England and Wales market all the functions are centralised under the privately owned National Grid Company. In New Zealand, the transmission owner (a state owned company) is neutral to the system and does not trade in bulk electricity. Systems and market operations are competitively tendered to the private operators. There are strong arguments for government to initially own the transmission system following restructuring as it is very difficult to value transmission assets for sale. The view however, is that management and operation should be franchised to private operators as this gives more confidence to private investors to enter the market. When the transmission operator is neutral to the system, market power and conflicts of interest are also reduced. These differences in organising power markets have led Sioshansi and Morgan (1999)11 to conclude that “the choice of market structure comes down to an ideological preference or a compromise for either economic efficiency or customer choice”. There are however, good reasons for the diversity of designs. No two countries start from the same point or have the same physical features. Market size, fuel mix and ownership structure vary from market to market. In developed markets, restructuring is often motivated by the desire to introduce competition and to make markets more efficient, more service orientated and for services to be delivered at lower prices. In most developing countries with weak infrastructure, low accessibility to electricity and chronic financial shortages, the need to reform is driven by the desire to attract foreign direct investment. Retail Competition as a Reform Option The final phase of transformation is that of retail competition. The England and Wales, New Zealand and Nordic markets have since 2000 come closest to this structure. At the final phase, 326 choice is allowed to all end users to source electricity supplies from competing generators. Product market competition is extended from bulk supplies to retail supply or low voltage energy. Most important of the reform measures is that of liberalisation and access to distribution lines by both industrial and small domestic household consumers, as was introduced in England and Wales during the period 1999 to 2000. Competition is also encouraged through entry of retailers and other intermediary traders. Retailers and other intermediaries’ contract with generators supported by a bulk electricity spot market, with payments made for wheeling across the transmission as well as the distribution wires. Separation of the merchant retail function from the distribution lines business, creation of local distribution companies and encouragement of multiple retailers, form the most important structural decisions to be contemplated. Both the retailing of energy and the related services can be made to operate under competitive markets. The requirement to unbundle the network natural monopoly distribution lines from the competitive merchant retail section is central to reducing the opportunity for abuse of market power, self-dealing and conflict of interest. Minor changes are also required to regulation to meet the regulatory requirements under the retail competition phase. The regulator is no longer required to fix prices for low voltage electricity; the price fixing function is restricted to the network natural monopoly transmission and distribution line business. The regulator also takes on the increased role of guarding the consumer from anticompetitive practices. Where there is vertical integration of the distribution line business with the retail supply there will be the need for greater regulatory effort. New Zealand has mandated vertical separation of distribution lines from retail supply and distribution companies had to decide which of the two businesses they intended to eventually operate in. This has been supported by strict information disclosure rules on the line business operators. In the UK, although vertical separation into independent legal entities was mandated between the two sectors, cross ownership was not excluded. In some markets only vertical accounting separation is prescribed. Retail supply is often seen to be a low margin business and it is sometimes argued that with stand-alone operation the business may not be attractive to investors, hence the decision to impose only accounting separation. 327 Increased transaction costs are associated with retail competition. For the small household domestic user, the transaction and trading costs of each component of the final product may outweigh the benefits of choice. There is also the problem of identification of responsibility by the consumer for poor services when the distributor and retailer are separate. In most if not all cases, the introduction of retail competition has been phased. In the England and Wales case it took nine years, 1990 to 1999. Phasing has been found to be necessary because of the complexity of introducing millions of users to competition.12 It is also not possible to achieve effective retail competition without a bulk electricity market. New Zealand tried to liberalise the retail market in 1992, however, there was no incentive by end users to change source of supply. Argentina, Chile, Norway, Spain and Victoria, Australia have all been transitioning to the retail competition phase. Main Lessons Learnt As the industry moves from one phase to the next, increased levels of competitive pressure are exerted in the market, higher levels of disintegration are experienced and private participation and ownership expand at the expense of public ownership. Whilst privatisation is a necessary condition for the realisation of economic efficiency, the empirical evidence, as demonstrated in the England and Wales and Scottish reforms is that privatisation alone is not a sufficient condition. The greater the extent of private ownership the greater opportunity there is for competition. A completely unbundled industry would be one in which the four stages of the production and supply chain are under different ownership and there is no cross-ownership between each sector. This may not be completely possible. Markets, however, which fail to adopt structural separation and substitute accounting ring fencing or management separation, provide more opportunities for the exercise of market power and an increase in the regulatory burden. Although in the Scottish reforms independent regulation was introduced, the evidence also is that regulation is not a substitute for competition and is inevitably inefficient and should be confined to the natural monopoly network sectors. Regulatory institutions provide the opportunity for bargaining by interest groups and the misallocation of resources. Policymakers therefore should seek to minimise the opportunity for inefficient bargaining over rents by reducing the number and power 328 of interested parties who participate in the regulatory process. If the agency for example is not independent of the portfolio ministry the more likely its decision will be subjected to bargaining by politicians and represented interest groups. Several studies in the past have shown that there is very little evidence to support the position that privately owned monopoly utilities are superior in terms of economic efficiency to publicly owned utilities. Privately owned utilities however, in the past have not been exposed to competition, being then the subject of public regulation. The result is that there is no incentive for both publicly owned and privately owned and regulated electric utilities to find least cost solutions and reduce cost. Under both institutional arrangements, interest groups seek to relocate returns in socially undesirable ways. The gains to be redistributed are monopoly rents and such gains will be distributed in proportion to the strength of the bargaining power of the groups. The England and Wales and the Scottish reforms clearly demonstrate that for superior economic performance, private ownership of the industry has to be accompanied by competition. The changes in the electricity utility have merely expanded what started in the telecommunications utility in the mid 1980s and is helping to shift the boundaries between the state and markets, as well as the boundaries between public and private ownership and between political control, exercised through public regulation or public ownership and market forces. The central idea is that market forces are superior to hierarchical bureaucratic control as a way of managing economic institutions. In the USA where traditionally most of the network monopolies were private investor owned utilities, the changes have been one of liberalisation of markets and decentralisation of the industry structure. Decentralisation and liberalisation, unlike privatisation, which is about ownership is more about subjecting the utilities to market forces and competition and providing more powerful incentives for economic efficiencies. Liberalisation of network utilities, however, also redistributes rents and raises regulatory concerns in managing the interface between the regulated network and the competitive sectors. Liberalisation has not entirely resolved the problem of market power. In fact new market power issues have emerged from the ability of the network sector to leverage its monopoly power into the competitive parts, as well as in the potentially competitive generation and retail supply sectors. The result is that 329 ordinary competition law as adopted by New Zealand is not only insufficient but also very expensive in dealing with market power issues. The development of the electricity industry was through private ownership and free markets. It is during the period between 1930 and 1990, the conventional wisdom and the accepted view of utility economics was that electricity and other network utility should be organised as vertically integrated franchised monopolies. This structure, while it did deliver expansion and increased levels of service to society by 1990 serious concerns emerged as to the efficient operation of the industry in both developed and developing economies. The Rise of the Regulatory State The market as an agent in creating economic growth is a relatively new thinking in most developing countries as well as Western Europe. Under liberalisation and privatisation the expectation was that regulation would be temporary and that there would be contraction in the size of the state. In abandoning public ownership however Britain found it necessary to follow the Americans and introduce independent regulation of prices and to expand the scope of the competition agency. Experiences have been that market concepts when applied on their own were not sufficient to generate economic growth. Market concepts must also be accompanied by institutional changes. Feigenbaum, Henig and Hammit13 state that those changes are: “intended to establish the legal and regulatory framework within which market transactions can be protected and enforced” Privatisation and liberalisation have therefore led to an increase in regulation Veljanoveski14 states that: “it would be unrealistic to assume that the state will confine itself to a minimalist level of intervention designed solely to protect consumers and enforce competition, sectoral interest will result in the regulatory role expanding well beyond what is needed to ensure efficient production.” 330 Giandomenico Majone15 noted that statutory regulation by independent agencies outside the hierarchical control or oversight by central administration and referred to as American style regulation has in fact accelerated with privatisation. In fact Majone16 further states that: “Privatisation and liberalisation seem to have created the conditions for the rise of the regulatory state to replace the dirigiste state of the past. The reliance is now on regulation rather than public ownership, planning and control. Regulation has become the new border between the state and the economy and the battle ground for ideas as to how the economy should be run” The regulatory state is said to have replaced the welfare and development state. The regulatory state attempts to increase the allocative efficiency of markets by correcting various market failures; natural monopoly, information asymmetry and externalities or failure of the market to deliver public goods. Mascarenhas17 has argued that: ‘the cure to the crisis of capitalist economies is not a question of replacing the state with the market. The role of the state as a political agent will continue to be significant, whilst its role as an economic agent will continue to decline. The remedy lies in altering the balance in the relationship between the state and the market and not as is claimed by neo-liberals rolling back the state’ It is not the existence of the state that privatisation and the expansion of markets have brought into question but the function of the state. In Britain the regulatory industry is said to be one of the fastest growing industries. From virtually no regulatory agencies in Sub-Saharan Africa in 1990, by 2001 there were well over 36 such agencies. Conclusions The changes and developments which have been taking place, have since the 1990s been providing governments with a range of policy options as to industry structure, market mechanism, and regulatory frameworks. Governments are now in a better position in adopting public policies to take into consideration economic and institutional constraints and resource endowment in the design of 331 their electricity supply industry. The flexibility is not only at the level of the industry structure but also over a range of sub-options. Where governments from a fear of the operation of free enterprise adopt vertical and horizontal separation but retain high levels of common ownership across sectors, as contemplated in South Africa and Ghana, then there will be severe hindrance to the competitive process. It will be difficult to provide for competition in an unbundled government owned utility structure, although this may be possible where several municipally owned utilities could compete on a national market as in Norway. The global tendency therefore has been for structural reforms and the introduction of increased levels of competition in the ESI to be accompanied by privatisation. Optimal structure in the generation market is important but not critical to the competitive transformation process so long as the opportunity for free entry exists as shown in the case of the England and Wales market. The experience in the E&W market did not support the assumption that Bertrand competition is a sufficient condition to drive down cost. It is much more difficult to sustain competition in the electricity industry and especially in small electricity markets. The greater the number of players, given market size constraints, the less opportunity there will be for market power and conversely the smaller the number of players the greater the opportunity presented for the exercise of market power as firms will seek to constrain competition either from collusion or gaming the market. It is also much easier to introduce the right structure before privatisation rather than to use regulation to create competition after privatisation. Jamaica will find it a major challenge to create competition in its electricity supply industry following the conclusion of the initial three-year exclusivity period for new generation capacity. The creation of an efficient industry is not just a question of private ownership. Private ownership with public regulation is hardly superior to public ownership and self-regulation as the UK experience demonstrates. In both these two institutional arrangements the incentives for efficiencies are very weak and the opportunity to capture the system for the benefit of special interests is very high. It is the introduction of competition in the competitive parts of the industry, which brings about productive and allocative efficiencies. 332 The policy approach of private ownership and competitive markets for the sectors where competition is possible and independent incentives based regulation for the natural monopoly network sector, offers far greater benefits to consumers, when compared to integrated publicly owned or integrated privately owned utilities with public regulation. The important consideration in addressing a competitive electricity market is that of reducing market power. Structural reforms alone are not enough. There must be free entry to the competitive sections of the market and transparent and independent regulation to constrain the monopoly network segments. The regulatory effort has been moving away from regulating services to regulating the network. Structural changes however bring an important benefit it reduces the regulatory burden and regulatory costs. Technology has made it possible to disintegrate the industry and for a policy of competitive entry and increased competitive market operation. The effects of the technological developments and the application of new trading arrangements including the application of the principles of commodity market have put an end to the vertically integrated franchised monopoly as the dominant institutional and structural arrangement in the industry; the end of the franchised monopoly era and have fuelled an uprising of competition in the utility electricity industry. Amongst the reluctant reformers are France and Scotland, leaving Jamaica in an anomalous position to the global trends. The reforms in the small markets such as Bolivia in 1995 have silenced the view that restructuring, involving unbundling and the introduction of competition should be reserved only for countries with large and mature markets. The same basic economic principles, which apply to these markets, also apply to the developing markets. Each country, however, should consider its particular requirements and circumstances and introduce the appropriate measures within the overall framework of an unbundled and privately operated electricity supply industry. End Notes 333 1. M.G. Pollitt, The Restructuring and Privatisation of Electricity Supply Industry in Northern Ireland – will it be worth it? Memo, Cambridge University Press (1997) , p. 6. 2. K. Izaguirre, “Private Participation in the Electricity Sector – Recent Trends; Private Sector (December 1998), p. 5. 3. S. Littlechild, “Privatisation, Competition and Regulation in Scottish Electricity Industry”, Scottish Journal of Political Economy, Vol.43, No.1 (1996), p.14 4. Eligible consumers have been classified as those with annual consumption of 16 GWh. In 2003 this is will be reduced to 9 GWh. EdF lost 45 industrial customers with operations covering 60 sites during the period following liberalisation in 1998 and up to 2000. Most of these customers switched to Spanish or German suppliers. This accounted for only 3% of EdF’s market share 5. Over 75% of the French ESI system is nuclear powered and as late as 2001 two plants, each of 1450 MW was brought into operation. EdF, the state owned incumbent which traditionally has been vertically integrated accounts for 90% of generated power and 95% of the distribution market, with the remaining 5% distributed by some 170 small independent distributors, mostly municipally owned. 6. M. Marquis, Introducing Free Markets and Competition to the Electricity in Europe. England, Wisdom House (2001) p.144 7. In a voluntary two-sided auction market, bidders pay or receive what they bid or offer for each unit, bought or sold, whereas in a single-sided mandatory auction market a single bid, that of the marginally accepted bid clears the market and all dispatched generators receive the marginal price (systems marginal price) irrespective of their bid. 8. Michael J. Trebilcock and Michael S. Gal, “Market Power in Electricity Industry Restructuring”, World Competition, Vol. 22, No.1 (1999), p. 159 9. David Harbord and Chris McCoy, “Miss-Designing the UK Electricity Market”, European Competition Law Review, Vol. 21 (2000), p. 359 10. Jaime Millan, The Second Generation of Power Exchange: Lessons for Latin America, Washington, D.C., IADB (2000), p. 4, also in Second–Generation Reforms in Infrastructure Services, , eds, Federico Basanes and R. Willig, IADB (2002), p. 268 11. Fereidoon P. Sioshansi and Cheryl Morgan, Where Function Follows Form: International Comparison of Restructured Electricity Markets, Electricity Journal (April 1999) p.23 12. The technology of smart metering and the sophisticated telecommunication system had not been developed in 1990. New Zealand tried to introduce retail competition in the early 1990s and had to resort to profiling which was not a success. 334 13. Feigenbaum, J. Henig and C. Hammit, Shrinking the State: the Political Underpinnings of Privatisation, Cambridge University Press (1998 ), p.168 14. Cento Veljanoski and Mark Bentley, Selling the State: Privatisation in Britain, Widenfield and Nicholson, London (1987), p. 206. 15. Giandomenico Majone, ‘Rise of the Regulatory State in Europe’ in Reader in Regulation, ed., R Baldwin, C. Scott and C. Hood, Oxford University Press (1998) p.193 16. Giandomenico Majone, Regulating Europe, London and New York, Routledge (1996) p.49 17. R. Mascarenhas, Government in the Economy in Australia and New Zealand: the Politics of Economic Making, Austin and Windfield (1996) p.160 335 Bibliography Adams, I. 1996, “Electricity Supply: The Second Tier Market,” in C. Hicks, ed., Energy–Transition or Maturing? A Review of Current Policy and Development. London: Centre for the Study of Regulated Industries, pp. 59-70 ADB. 1999, African Development Report: Infrastructure Development in Africa, Oxford University Press. Aharoni, V. 1986, The Evaluation and Management of State Owned Enterprises, Cambridge, Mass: Ballinger. Alchain, A.A. 1965, “Some Economics of Property Rights”, II Politico, Vol. 30, pp. 816 – 29. Alvarez, G.C. Unpublished 2001, The Electricity Sector in Bolivia, Bolivia (Second Draft). Armstrong, M., S. Cowan and J. Vickers. 1994, Regulatory Reform - Economic Analysis and British Experience. Cambridge Mass.: MIT Press. Atkinson, S.E., and R. Halvorsen. 1984, “Parametric Efficiency Tests: The Economics of Scale and Input Demand in US Electric Power Generation”, International Economic Review, Vol 25, pp. 647-62. ___________1986, “The Relative Efficiency of Public and Private Firms in a Regulated Environment: The Case of US Electric Utility”, Journal of Public Economics, Vol. II, No. 29, pp.281-94. Averch, H., and L.L. Johnson. 1962, “Behaviour of the Firm Under Regulatory Constraint”, American Economic Review, Vol. 52, pp.1052-69. Bacon, R. 1996, “Restructuring the Power Sector: The Case of Small Systems”, in Private Sector Infrastructure, Washington, D.C., World Bank, Special Edition. Baldwin, R. 1995, Regulation in Question, the Growing Agenda, London School of Economics and Political Science. __________and McCrudden. 1981, Regulation and Public Law, London: Weidenfield and Nicolson. Baldwin, R., C. Scot and C. Hood. 1998, Reader in Regulation, Oxford University Press Barker, J., B. Tenenbaum and F. Woolf. 1997, Governance and Regulation of Power Pools and Systems Operation: An International Comparison. Washington, D.C., World Bank, Technical Paper No. 382. Baron, D.P., and D. Besanko. 1984, “Regulation, Asymmetric Information and Auditing”, Rand Journal of Economics, Vol.15, pp. 447-70. 336 Bauer, R., and S. Bowen. 1997, From State Capitalism to Capitalisation: The Bolivia Formula, Chile: MćGraw Hill. Baumol, W.J. 1977, “On the Proper Cost Tests for Natural Monopoly in a Multi-Product Industry”, American Economic Review, Vol. 67, No. 1, 1971, pp. 809-822. __________J.C. Panzar and R.D. Willig. 1982, Contestable Markets and the Theory of Industry Structure”, San Diego, CA: Harcourt, Brace, Jovanovich . Baumol, W. J. 1982, “Contestable Markets: An Uprising in the Theory of Industrial Structure”, American Economic Review, Vol. 72, No. 1, pp. 1-15. __________and R. Willig. 1981, “Fixed Costs, Sunk Costs, Entry Barriers and Sustainability of Monopoly”, Quarterly Journal of Economics, Vol. 96, No.3, pp.405-32. Beato, P., and C. Fuente. 1999, Retail Competition in Electricity, Washington, D.C., IADB, also 2002, in F, Basanes and R. Willig, eds., Second -Generation Reforms in Infrastructure Services , IADB,Washington, D. C. pp 283-320. Beesley, M.E., and S.C. Littlechild. 1997, “Privatisation: Principles, Problems and Priorities”, in M.E. Beesley, ed., Privatisation, Regulation and Deregulation, London: Institute of Economics Affairs pp.26-41. __________1989, “The Regulation of Privatised Monopolies in the United Kingdom”, Rand Journal of Economics, Vol.20, No. 3, pp.454-72. Besant-Jones, J.E. 1993, Reforming the Polices for Electricity Power in Developing Countries, Washington, D.C., World Bank, Industry and Energy Department. __________1995, The England and Wales Electricity Model: Option For Developing Countries, Washington, D.C., World Bank. __________and B. Tenenbaum. 2000, California Power Crisis: Lessons For Developing Countries, Washington, D.C., World Bank. Bhagavan, M.R. 1999, Reforming the Power Sector in Africa, London: Zed Books. Besques, F., and Willig. 2002, Second-Generation Reforms in Infrastructure Services, IADB, Washington DC. Binz, R, and M. Frankena. 1988, Addressing Market Power: The Next Step in Electricity Restructuring, Washington, D. C., Competition Policy Institute. Bishop, M., and J. Kay. 1989, “Privatisation in United Kingdom: Lessons From Experience”, World Development Report 1989, Washington, D.C., World Bank, pp.643-57. 337 Boardman, A., and A. Vining. 1989, “Ownership and Performance in Competitive Environment: A Comparison of Private, Mixed and State Owned Enterprises”, Journal of Law and Economics, Vol. 32, pp.1-33. Bonner, J. 1996, “Electricity Distribution Review – Outcome and Response”, in C. Hicks, ed., Energy-Transition or Maturity? A Review of Current Policy and Development, London: Centre for the Study of Regulated Industries, PP .15-38. Bös, D. 1986, Public Enterprise Economics: Theory and Application, North Holland Boulding, P. 1997, Whither Regulation? Current Developments in Regulated Industries, London: CRI.Breyer, S. 1982, Regulations and Its Reform, Cambridge, MA: Harvard University Press. Breyer, S. 1982, Regulation and Its Reform, Cambridge, MA: Harvard University Press. British Treasury. 1961, The Financial and Economic Obligation of Nationalised Industries, London: HMSO. Brown, A., and H. Mcbain. 1983, “The Public Sector in Jamaica”, SES, UWI, Studies in Caribbean, Public Enterprise in Commonwealth Caribbean, Vol 1 pp.85-122. __________1993, “Issues in Public Enterprise”, SES, UWI, Special Issue, Public Sector Issues in Commonwealth Caribbean, Vol. 30. No.1, pp.1-16. _________1967, Nationalised Industries: Review of Economic and Financial Objectives, London: HMSO. _______1978, Nationalised Industries, London: HMSO. Buchanan, J.M. et.al. 1978. The Economics of Politics, London: Institute of Economic Affairs Readings No.18. Burns, P. 1995, “Yardstick Competition in UK”, in P. Vass, eds., The Regulatory Review 1995, England: Centre for the Study of Regulated Industries .. Caves, R. 1990, “Lessons from Privatisation in Britain: State Enterprise Behaviour, Public Choice and Corporate Governance”, Journal of Economic Behaviour and Organisation, Vol.1, N.13, pp.145-69. __________and R, Bradburd. 1988, “The Empirical Determinants of Vertical Integration”, Journal of Economic Behaviour and Organisation. April Chhibber, A., and N. Shafix. 1991, “The Inflationary Consequences of Deregulation with Parallel Markets: The case of Ghana”, in A. Chhibber and S. Fisher, eds., Economic Reform in Sub-Saharan Africa, Washington, D.C., IMF., pp. 39-65. 338 Chiwaya A. 1998, “Malawi Power Sector”, in M.R. Bhagavan, ed., Reforming the Power Sector in Africa, London: Zed Books. Christensen, L.R., and W.H. Greene. 1976, “Economies of Scale in US Electric Power Generation”, Journal of Political Economy. Vol. 84. No. 4, pp. 655-676. Coopers and Lybrand. 1993, Jamaica Power Sector Regulatory Framework and Privatisation, Kingston, Jamaica, Phase Two Report. Cordukes, D.A. 1990, A Review of the Power Sector in Developing Countries, Washington, D.C., World Bank, Working Paper Energy Series 22. Criales, J. A, and W. Smith.1997, “Bolivia Regulatory Reform: Defining the States Role , Paper presented at Seminar on Bolivia’s Capitalisation Programme”, Washington, D. C. World Bank Costello, K.W., and K. Rose. 1998, “Some Fundamental Questions of Market Power: No Easy Answers for State Utility Regulators”, Electricity Journal, June pp.71-79. Curien, N., and C. Henry. 1998, “Liberalisation and Regulation of Public Service in France”, in P. Vass, eds., Regulatory Review 1998-99, London: Centre for the Study of Regulated Industries, pp. 113-31.. De Alessi, L. 1980, “The Economics of Property Rights: A Review of the Evidence”, Research in Law and Economics, Vol.2, pp.1-47. Demsetz, H. 1966, “Some Aspects of Property Rights”, Journal of Law and Economics, Vol. 7, pp.61-70. __________1968, “Why Regulate Utilities?” Journal of Law and Economics, Vol. II, pp.55-66. Department of Energy. 1988, Privatising Electricity: Government Proposal For Privatisation of Electricity Supply Industry in England and Wales, London: HMSO. Department of Trade and Industry. 1998a, A Fair Deal For Consumers: Modernising the Framework for Utility Regulation, Cmnd 3898,London: HMSO. __________1998b, Review of Energy Sources for Power Generation: Consultation Document, London: HMSO. __________1998c, A Fair Deal for Consumers: Modernising the Framework for Utility regulators: The Response to Consultation, London: HMSO. Dilorenzo, T.J., and R. Robinson. 1985, “Managerial Objectives Subject to Political Market Constraints: Electric Utilities in the US”, Quarterly Review of Economics and Business, Vol. 22, No.2, pp.113 -125 Economists Intelligence Unit. 2000, Tanzania Country Report, London 339 Electricity Association, 1999, The UK Electricity System, London. __________2001, Electricity Industry Review, London. ESMAP, 1993, Bolivia Power Generation and Transmission, Washington, D.C., World Bank. __________2002, Introducing Competition in Electricity Supply Industry in Developing Countries: Lessons From Bolivia, Washington, D.C., Joint UNDP/World Bank Study Estache, A., and M. Rodriquez-Pardinas. 1998, Light and Lighting at the End of the Public Tunnel: The Reform of Electricity in the Southern Cone, Washington, D.C., World Bank. Fare, R., S. Grosskopf and J. Logan. 1985, “The Relative Performance of Publicly Owned and Privately Owned Electric Utilities”, Journal of Public Economics, Vol. 1, No. 26, pp. .89106. Feigenbaum, J. H., and C. Hammit. 1986, Shrinking the State: The Political Underpinnings of Privatisation, Cambridge: Mass. MIT Press. Foreman-Peck, J., and R. Millward. 1994, Public and Private Ownership of British Industry 1820-1990, Oxford: Clarendon Press. Friedmann, W. 1974, Public and Private Enterprise in Mixed Economies, London: Stephen and Sons. Furubotn, E., and S. Pejovich. 1972, “Property Rights and Economic Theory: A Survey of Recent Literature”, Journal of Economic Literature, Vol.10, No. 4, pp.1137-62. Galal, A., L. Jones, P. Tandon and I. Volgelsang. 1994, Welfare Consequences of Selling Public Enterprises: An Empirical Analysis, New York: Oxford University Press. Gegax, D., and K. Nowotny. 1993, “Competition and the Electric Utility Industry: An Evaluation”, Yale Journal of Regulation, Vol. 10, No. 1, pp.63-87. Girod, J. and J. Percebois. 1998, “Reforms in Sub-Saharan Africa Power Industries”, Energy Policy, Vol. 26, No.1, pp.21-32. _________1996, “The Electric Power Sector in SSA: Current Institutional Reforms”, in Power Sector Reform and Efficiency: Improvements in Sub-Sahara African, Washington, D.C., Joint UNDP/World Bank ESMAP, pp. 75-100. Glen, J.D. 1991, Private Sector Electricity in Developing Countries – Supply and Demand, Washington, D.C., IFC Working Paper No. 15. Goodman, J., and G. Loveman. 1992, “Does Privatisation Serve Public Interest”, Boston: Harvard Business Review, November/December. 340 Green, R.J., and D.M. Newbery. 1992, “Competition in the British Electricity Spot Market,” Journal of Political Economy, Vol. 100, No.5, pp.929-53. __________1998, “The Electricity Industry In England and Wales”, in D. Helm and T. Jenkinson, eds., Competition in Regulated Industries, Oxford: Oxford University Press. __________2001, “Markets for Electricity in Europe” Oxford Review of Economic Policy, Vol.17, No. 3, pp.329-45. __________and T. McDaniel. 1998, “Competition in Electricity Supply: Will ‘1998’ be Worth It?”, Fiscal Studies, Vol. 19. No. 3, pp. 273-93. Grosh, B. 1991, The Public Enterprise in Kenya: What Works, What Doesn’t and Why? London: Lynne Reiner. Gutierrez, L. 1996, “How do Sub-Saharan Africa Utilities Compare”, in Power Sector Reform and Efficiency: Improvements in Sub-Saharan Africa, Washington, D.C., Joint UNDP/World Bank, ESMAP, pp. 23-74.. Hachette, D., and R. Ludgers. 1993, Privatisation in Chile: An Economic Appraisal, California: International Centre for Economic Growth, ICS Press. Hadjimichael, M.T., M. Nowak, R.S. Sharer and A. Tahari. 1996, Adjustment for Growth: The African Experience, Washington, D.C., IMF Occasional Paper Series, October.’ Harbord, D., and C. McCoy. 2000, ‘‘Mis-Desigining the UK Electricity Market” European Competition Law Review ,Vol . 21, pp. 259-61 Heald, D.R. 1980, “The Economic and Financial Control of UK Nationalised Industries”, Economic Journal, Vol. 90, No. 338, pp.243-265. Helm, D.R. 1995 British Utility Regulation: Principles, Experiences and Reform, Oxford University Press. __________ 2003, Energy, The State and the Market: British Energy Policy Since 1979, Oxford University Press _________and T. Jenkinson. 1998, Competition in Regulated Industries, Oxford: University Press. 1988, ‘‘Regulating the Electricity Supply Industry”, London:Institute of Fiscal Studies, Fiscal Studies, No. 9, August. Henney, A. 1987, Private Power: Restructuring the Electricity Industry, London: Centre for Policy Studies, No. 83. 341 Hicks, C. 1998., Regulation of UK Electricity Industry, London:Centre for the Study of Regulated Industries... Hjalmarsson, L., and A. Veirderpass. 1992a, “Efficiency and Ownership in Swedish Electricity Retail Distribution”, Journal of Productivity Analysis, Vol.3, pp.7-23. _________1992b, “Productivity in Swedish Electricity Retail Distribution”, Scandinavian Journal of Economics, Vol.94, pp.193-205. HMSO. 1925, The Report of the Committee to Review the National Problem of Supply of Electricity, London, The Weir Committee. Hogan, W. 1992 “Contract Networks For Electricity Power Transmission”, Journal of Regulatory Economics, Vol.4, No.3, pp.211-242. __________1994, “A Wholesale Pool Spot Market Must be Administered by in Independent System Operator: Avoiding the Separation Fallacy”, Electricity Journal, June, pp.36-48. Holburn, G.L.F., and P. Spiller. 2000, Institutional or Structural: Sequencing Strategies for Reform in the Electricity Industry, Berkeley: University of California, Walter Hass School of Business, November. Hollas, D.R., and S. Stansell. 1987, “An Examination of the Effect of Ownership Form on Price Efficiency: Proprietary, Cooperative and Municipal Electric Utilities”, Southern Economic Journal, Vol.54, No.1, pp.336-50. Holmstrom, B. 1983, “Moral Hazard and Observability”, Bell Journal of Economics, Vol.10, pp.74-91. Hunt, S., and G. Shuttleworth. 1996, Competition and Choice in Electricity, New York: John Wiley and Sons. Izaquirre, K. 1998, ‘’Private Participation in Electricity Sector- Recent Trends” Private Sector , Washington, D. C World Bank Jensen, M.C., and W.H. Meckling. 1976, “The Theory of the Firm: Managerial Behaviour, Agency Costs and Ownership Structure”, Journal of Financial Economics, Vol.3, No.4, pp.30560. Jones, E. 1981, “Role of the State in Public Enterprise”, Social and Economic Studies, UWI, Special Issue, Public Sector Issues in Commonwealth Caribbean, Vol. 30, PP.17-42. Joskow, P.L., and R. Schmalensee. 1983, Markets For Power: An Analysis of Electric Utility Deregulation, Cambridge: MIT Press. Joskow, P.L.,1997, “Restructuring, Competition and Regulatory Reform in the US Electricity Sector”, Journal of Economic Perspectives, Vol.11, No.3.pp.119-138. 342 _________1991, “The Evolution of Independent Power Sector and Competitive Procurement of New Generation Capacity”, Research in Law and Economics, Vol. 13, pp.63-100. __________1989, “Regulatory Failure, Regulatory Reform and Structural Change in Electrical Power Industry”, Brookings Paper: Micro-economics Activities , pp.125-199. JPSCo. Undated, A History of Electric Power in Jamaica, Kingston, Jamaica. __________1996, Annual Report 1995-96, Kingston, Jamaica. __________2000, Annual Report 1999-2000, Kingston, Jamaica. Kahn, A.E. 1998, The Economics of Regulation, Principles and Institution, New York: Wiley, Vol. 1 and 2. Kay, J. 1996, “The Future of UK Utility Regulation”, in M.E, Beesley, et.al. eds., Regulation Utilitises: A Time for Change?, London: Institute of Economic Affairs , Readings No.44, pp. 145-170. Kelly, J. 2001, Evidence on Scale Economics in Electric Utility, Distribution and What it Implies: Is Bigger Better?, Washington, D.C., American Public Power Association. Kennedy, D. 1996, Vertical Structure of the English Electricity Industry, London: Centre for the Study of Regulated Industries, Technical Paper No. 6. Kerf, M., and W. Smith. 1996, Privatising Africa’s Infrastructure: Promise and Challenge, Washington, D.C., World Bank Technical Paper No. 337. Kjell, G., and S. Tjotta. 1990, Cost Differences in Electricity Distribution: Economies of Scale and Economies of Density in Norwegian Electricity Distribution Industry, Bergen: University of Oslo. Project No. 16 Klien, M. 1996, Competition in Network Industries, Washington, D.C., World Bank, Policy Research Working Paper No. 159. Kolko, G. 1965, Railroads and Regulation 1877-1916, Princeton: Princeton University Press. Kreps, D., and J. Scheinkman. 1983, “Quantity Precommitment and Bertrand Competition Yield Cournot Outcomes”, Bell Journal of Economics. Kumbhakar, S.C., and L. Hjalmarsson. 1994, Relative Performance of Public and Private Ownership in Swedish Electricity Retail Distribution 1970-1990, Gothenburg, Sweden: Gothenburg University Working Paper. Lalor, P., and H. Garcia. 1996, Reshaping Power Markets: Lessons From Chile and Argentina, Washington, D.C., World Bank, Private Infrastructure. 343 Leboeuf, Lamb, Greene and MacRae. 1994, Competition, Structural Change and Regulatory Reform in US Electricity Industry, London: Centre for the Study of Regulated Industries . Leibenstien, H. 1966, “Allocative Efficiency Vs X-Efficiency”, American Economic Review, Vol. 56, pp.392-415. Littlechild, S.C. 2000, Privatisation, Competition and Regulation, London: IEA Occasional Paper No.110. _________1988, “Generation and Supply of Electricity: British Experience”, in D. Helm and T. Jenkinson, eds., Competition in Regulated Industries, Oxford: Oxford University Press., pp. 193-212. _________1983, Regulation of British Telecommunications Profitability, London: HMSO _________2000, Privatisation, Competition and Regulation of British Electricity Industry With Implications for Developing Countries, Washington, D.C., Joint UNDP/World Bank ESMAP. _________2001, “Electricity Regulation” in P. Vass, eds., Regulatory Review 2000-01, Bath: England: Centre for the Study of Regulated Industries. pp. 25-62 _________ 1996, ‘’ Privatisation, Competition and Regulation in the Scottish Electricity Industry”, Scottish Journal of Political Economy, Vol.43, No. 1, pp.1-15 Maine, G., and M. Vermont, 2000, Best Practice Guide: Implementing Power Sector Reform, Washington, D.C., USAID. Majone, G. 1996, The Rise of the Regulatory State in Europe, London: Routledge Marquis, M. 2001, Introducing Free Markets and Competition to The Electricity Sector in Europe, England, Wisdom House. Mascarenhas, R. 1996, Government in the Economyof Australia and New Zealand: the Polictics of Economic Making, Austin and Windfield Mclldoon, D. 2001, “Liberated by Brussels: Cross-Boarder Electricity Market in Ireland”, in P. Vass, eds., Regulatory Review 2000-01, Bath, England: Centre for the Study of Regulated Industries pp 327-41. Megginson, W., R. Nash and M. Van Randenborgh. 1994, The Financial and Operating Performance of Newly Privatised Firms: An International Empirical Analysis”, The Journal of Finance, Vol.49, No.2, pp.403-52. Millan, J. 2001, The Second Generation Power Exchanges: Lessons for Latin America, Washington, D.C., IADB. Also – 2002 in F. Basanes and R Willig eds., Second-Generation Reforms in Infrastructure Services , IADB, Washington, D.C. pp. 266-282. 344 Mills, G. E. 1974, “Public Policy and Private Enterprise in Commonwealth Caribbean”, Social and Economic Studies , UWI, Vol. 10, No. 2., pp. 226-251 , also ,1990 , in G. E. Mills , ed. A Reader in Public Policy and Administration, ISER., Mona, Jamaica, pp. 145-170. __________1995, Public Enterprise in Commonwealth Caribbean with Particular Reference to Jamaica and Trinidad, UWI, Department of Government Ministry of Capitalisation and Investment.1995, Generation Briefing Memorandum, Bolivia. Ministry of Capitalisation and Investment. 1997, Transmission Information Memorandum, Bolivia . Mitchell, W.C. 1988, Government As It Is, London: Institute of Economic Affairs, Hobart Papers No. 109. Moberg, S. H. 2001, The Tanzania Power Sector, Tanzania: Swedish International Development Agency Moen, J. 1994, Electricity Utility Regulation, Structure and Competition: Experiences From Norwegian Electricity Supply Industry, Oslo: Norwegian Water Resource and Energy Administration. More, T.G. 1970, “The Effectiveness of Regulation of Electric Utility Prices”, Southern Economic Journal, Vol. 36, No.4, pp. 365-75. Morgan, K. 1999, Electricity Supply Industry, Restructuring and Regulatory Development in South Africa, Paper presented at Sub-Sahara Power Conference, Midrand, South Africa. Munasinghe, M., and A. Sanghvi. 1989, Recent Developments in US Power Sector and Their Relevance for Developing Countries, Washington, D.C., World Bank Working Paper Energy Series, No. 12. National Investment Bank of Jamaica. 1995, Privatisation of JPSCo: Issues Affecting the Privatisation of JPSCo., Kingston: NIBJ. Neuberg, L.G. 1977, “Two Issues in Municipal Ownership of Electric Power Distribution Systems”, Bell Journal of Economics, Vol.8, No.1 pp. 303 – 23. Newbery, D. M. 1999, Issues and Options for Restructuring the ESI, Washington, D.C., World Bank. __________and R. Green, 1996, “Regulation, Public Ownership and Privatisation of English Electricity Industry,” in R. Gilbert and E. P. Kahn, eds; International Comparisons of Electricity Regulation. New York: Cambridge University Press, pp. 25-81. _________1996, Guidelines for Private Sector Involvement in Electricity Supply Industry of Eastern Europe, Cambridge: Cambridge University Department of Economics. 345 __________2000, Privatisation, Restructuring and Regulation of Network Industries, Cambridge: Mass. MIT Press __________and M. G. Pollitt. 1997, The Restructuring and Privatisation of Britain’s CEGB – Was it Worth It? Journal of Industrial Economies, Vol. 40, No. 3, pp. 269 – 303. Niskanen, W. 1971, Bureaucracy and Representative Government, Chicago: Aldine Atherton. Noll, R. 1989, “The Politics of Regulation”, in R. Schmalensse and R.D. Willig, eds., Handbook of Industrial Organisation, Amsterdam: Elsevier, Vol.2. North, D.C. 1981, The Structure and Change in Economic History. New York: Norton. OECD. 1999, “Relationship Between Competition and Regulatory Authority, Journal of Competition Law and Policy, Vol. No. 6. __________1997, The Application of Competition Policy to the Electricity Sector, Paris OFGEM. 1999, The New Electricity Trading Arrangements. London: Office of Gas and Electricity Markets Ogus, A. 1994, Regulation: Legal Form and Economic Theory, Oxford: Clavendan Press. Parker, D., and S. Martin. 1996, Assessing the Impact of Privatisation on Company Efficiency, London: Centre for the Study of Regulated Industries. __________1999, “Regulating Public Utilities”, International Review of Administrative Sciences, Vol. 65, pp. 117 – 131. __________1997, Privatisation in Regulated Industries. London: Centre for the Study of Regulated Industries , Occasional Paper No. 4. Peltzman, S. 1971, “Pricing in Public and Private Enterprises: Electric Utilities in the United States, Journal of Law and Economies, Vol. 14, pp. 109-147, pp 109 – 47. __________1976, “Towards a More General Theory of Regulation” Journal of Law and Economics, Vol. 19, pp. 211 – 40 Pescatrice, D. R. and J. M. Trapani 111., 1980, “The Performance and Objectives of Public and Private Utilities Operating in the United States”, Journal of Public Economics, Vol. 13, pp. 259 – 76 Phillips, A. 1969, The Economics of Regulation, New York: Richard D. Erwin. Pollitt, M.G. 1995, Ownership and Performance in Electric Utilities, Oxford University Press. 346 __________1997, The Restructuring and Privatisation of Electricity Supply Industry in Northern Ireland – Will it be Worth It? Cambridge University, -Department of Economics, Mimeo, February. __________1977,’The Restructuring and Privatisation of CEGB- Was It Worth it? ‘Journal of Industrial Economics, Vol XLV No. 3, pp. 269- 301 __________1998, The Restructuring and Privatisation of Electric Supply in Industry in Scotland, Cambridge University, Department of Economic, Mimeo, June. Posner, R. A. 1974, “Theories of Economic Regulation”, Bell Journal of Economics and Management Sciences, Vol. 5 pp 335-58. Price Waterhouse Utility Economics and Financial Consultancy Group. 1994, Options for Privatisation and Regulation of JPSCo., Washington, DC. Price, C. and T. G. Weyman – Jones. 1993, Malmquist Indices of Productivity Change in UK Gas Industry, Before and After Privatisation, Loughborough: Loughborough University Economics Research Working Paper No. 93. 1989, “Electricity Supply and the End of Natural Monopoly”, in C. Primeaux, W. J. 1989, “Electricity Supply: An End to Natural Monopoly”, in C. Veljanovski, ed.; Privatisation and Competition: A Market Prospectus , Affairs London: Institute of Economic Affairs ,Hobart No 28 pp 129-134 __________1986, Direct Electric Utility Competition: The Natural Monopoly, Pregger. Prosser, T. 1997, Law and Regulators, Oxford: Clarendon Press. Ramsey, F. P. 1927, “A Contribution to the Theory of Taxation,” Economic Journal, Vol. 37, pp 47 – 61. Reidy, M. 1995, “Privatisation, Regulation and Electricity Market,” in D. Helm, eds., The British Utility Regulation: Principles, Experience and Reform, Oxford University Press.,pp. 123-30. Rees, R. and J. Vickers, 1994, “RPI – X Price Cap Regulation,” in M. A. Armstrong, S. Cowan and J. Vickers, eds., Regulatory Reform, Economic Analysis and British Experience, Cambridge: MIT Press, pp.167-93.. __________1985, The Theory of Principal Agents”, Bulletin of Economic Research. Vol. 37, No. 1, Parts 1 and Parts 2, pp. 1-26 and 75 -95 Richards, E. Unpublished 1991, Overview of Private Sector Role in Jamaica Energy/Power Sector, Kingston: JPSCo. 347 Roberts, M. 1986, “Economics of Density and Size in the Production and Delivery of Electric Power”, Journal of Land Economics, Vol. 62, No. 4, pp. 378-87. Robinson, C. 1989, “Privatising the Energy Industries”, in C. Veljanovski, eds; Privatisation and Competition: A Market Perspective, London: Institute of Economic Affairs .pp. 113-28. __________1996. “Profit, Discovery and the Role of Entry: the Case of Electricity,” in M E Beesley, ed., Regulating Utilities: Time for a Change? London: Institute of Economic Affairs, Readings 44 , pp 119-36. Roseman, E., and A. Molhatra. 1991, Dynamics of Independent Power, – IPPs Seed – To Boltom Reform. Washington, D.C., World Bank, Private Sector Special Edition, pp. 37 – 40. Ruff, L. E. 1994, “Stop Wheeling and Start Dealing: The Transmission Dilemma,” in M. Enhorn and R. Saggidi, eds., Electricity Transmission Pricing and Technology, Netherlands: Kluwer Publishers. pp. 1-23. __________1992, Competitive Electricity Markets: Legal and Practical Implications. Presented at the International Association of Energy Economics Workshop, Toures, France. Sampson, C. 1986, “Strategic Marketing Cases: Jamaica Public Service Company. UWI, Mona Institute of Business Schramm, G. 1993, “Issues and the Problems in Power Sector of Developing Countries”. Energy Policy, Vol. pp. 736-47 Schumpeter, J. 1976, Capitalism, Socialism and Democracy, London: Allen and Unwin. 5th Edition Shirley, M., and J. Nellis. 1991, Public Enterprise Reform: The Lessons of Experience, Washington, D.C., World Bank. Shleifer, A. 1985, A Theory of Yardstick Competition, Rand Journal of Economics, Vol. 16, pp. 319-27. Shuttleworth, G. 1999, “The Electricity Industry 1997 – 1998,” in P. Vass, ed., Regulatory Review 1998/99, Bath, England: Centre for the Study Regulatory Industries pp.19-34 Sidak, G., and D. Spulber, 1997, Deregulatory Takings and Regulatory Contract, Competitive Transformation of Network Industries in the US, Cambridge University Press __________1999, “Deregulation and Managed Competition in Network Industries,” Yale Journal of Regulation, Vol.15, No.1, pp. 117-47 348 Sioshansi , F. P., and C. Morgan, 1999, “Where Function Follows Form. “International Comparison of Restructuring Electricity Markets”, Electricity Journal, April, pp. 20-30 SIRESE. 1997, Sectoral Regulatory System, Bolivia __________1998, Sectoral Regulation in Bolivia, Bolivia. Smith , 1996. The Independence Debate, Washington, D.C., World Bank View Point Note 127 Solomon Brothers, 1997. Information Memorandum – Capitalisation of YPFB, Bolivia, Ministry of Capitalisation and Investment Spiller, P., and C. Sampson. 1994, Regulation, Institutions and Commitment; The Jamaican Telecommunications Sector. Washington, D.C., World Bank, Policy Research Working Paper No. 1362 Spulber, D. 1989, Regulation and Markets, Cambridge: Mass. MIT Press. Stelzer, I.M. 1991, “Regulatory Methods: A Case for Hands Across the Atlantic”, in C. Veljanovski, et..al., eds., Regulation and the Market, London; Institute of Economic Affairs pp .88102 __________1996, “Lessons for UK Regulation from Recent US Experience”, in M.E Beesley, et.al., ed., Regulating Utilities: Time for a Change?, London: Institute of Economic Affairs pp. 189-202. Stigler, G. J., 1971, “The Theory of Economic Regulation.” Bell Journal of Economics and Management Sciences, Vol.2, No.1 pp. 3-21 _________and C. Friedland, 1962, “What Can Regulators Regulate? The Case of Electric Utilities in the USA,” Journal of Law & Economics, Vol. 5, pp. 1-16. Sutherland, B. 1998, Financing Jamaica’s Rockfort Independent Power Project: A Review of Experience for Future Projects. Washington D.C., World Bank. Swaby, R.A. 1981, “The Rationale for State Ownership of Public Utilities in Jamaica” Social and Economic Studies. UWI, Special Issue, Public Sector in the Commonwealth Caribbean, Vol. 30, No 1, pp.75-104. __________1974, “Some Problems of Public Utility Regulation by Statutory Boards in Jamaica: The Jamaica Omnibus Case”, Social and Economic Stidies. UWI, Vol. 23, No.2. pp 250-271 Swan, D. 1988, The Retreat of the State: Deregulation and Privatisation in the UK and USA, Michigan: Michigan University Press Tenenbaum, B. , R. Lock and J.R. Barker. 1992, Electricity Privatisation: Structural, Competitive and Regulatory Options; Energy Policy, Oxford: Butterworth Heinemann. 349 Thomas, S. 1996, “Privatisation of the Electricity Supply Industry” in J. Surrey, eds., The British Electricity Experiment, Privatisation: The Record, The Issues, The Lessons. London, Earthscan.pp. 67-94 Townsend, A. 2000, Energy Access: Energy Demand and Information Deficit in Energy Services for the Word’s Poor, Washington, D.C., World Bank. Trebilcock, M. J., and Michael Gal.1999 “ Market for Power in English Electricity Industry Restructureing , World Competiton,Vol 22, No 1 pp 119-169 Tullock, G. 1965, The Politics of Bureaucracy, Washington: Public Affairs Press. Ugandan Government. 1999, Power Sector Restructuring and Privatisation: Strategic and Implementation Plan, Uganda UNCTAD, 1997. Competition and Public Utility. Geneva __________1994, Design, Implementation and Results of Privatisation Programme: Review of National Experiences, New York: United Nations. Veljanovski, C. 1989. “Privatisation: Monopoly Money or Competition” in C. Veljanovski, ed., Privatization and Competition: A Market Perspective, London: Institute of Economic Affairs. Hobart No. 28 , pp. 26-53 __________1997, “Selling the State: Privatisation in Britain,” London: Wiedenfield and Nicolson. __________1996, “Regulations and Markets: An Assessment of the Growth of Regulation in the U.K”, London: Institute of Economic Affairs . Vickers, J., and G. Yarrow. 1988, Privatisation: An Economic Analysis. Cambridge: Mass.MIT Press. ____ ___1991 _”The Economic Perspective of Privatisation”, Journal of Economic Perspectives,Vol.5, No.2, pp.111-32. __________1991, “The British Electricity Experiment”, Economic Policy Vol. 12, pp. 187-232. __________1998 Regulation of Privatised Firms in Britain” European Economic Review, Vol. 32, pp. 465-72 Ward G., 1998, Power to the People: A Decade of UK Privatisation, London: Price Waterhouse. Wade, R. 1990, Governing the Market: Economic Theory and the Role of Government in East Asian Industrialisation, Princeton University Press. 350 Webb, M., and M. Bell. 2000, Reform Cases in Electricity: The UK Experience, Presented at Electric Utility Seminar, Tanzania. White, O., and A. Bhatia. 1998, Privatisation in Africa, Washington, D.C., World Bank White, M. 1996 “Power Struggles: Explaining Deregulatory Reforms in Electricity Markets,” Brookings Papers: Macro-economic Activities, pp. 201-250 William, E.C. Unpublished 1993, Jamaica Public Service Company Ltd.: A History of Its Origins and Development 1923-1978, Kingston, Jamaica JPSCo Williamson, B. 2001, “UK: Incentive Regulation: International Best Practices? ” in P. Vass, ed., Regulatory Review 2000/01. Bath, England: Centre for the Study of Regulated Industries, pp. 271-92. Williamson, O.E. 1979, “Transaction-cost Economics: The Governance of Contractual Relations”, Journal of Law and Economics. Vol. 22, pp. 233 - 262. World Bank. 1992, Jamaica Energy Sector, Strategy and Investment Planning Study, Washington, D.C., ESMAP, Main Report. __________1993, The World Banks Role in the Electric Power Sector, Washington, D.C. __________1994, World Bank Development Report: Infrastructure for Development, New York: Oxford University Press. __________and USAID. 1994, Submission and Evaluation of Proposal for Private Power Generation Projects in Developing Countries, Washington, D.C., Occasional Paper No.3. __________1994, Adjustment in Africa, Reform, Results and the Road Ahead, Washington, D.C, World Bank. __________1995, Lending for Electric Power in Sub-Saharan Africa, Washington, D.C, World Bank __________1999, Energy after the Financial Crisis, Washington, D.C __________1997, Development – 1997: The State in a Changing World, Oxford University Press. __________1999, World, Development Report 1999: Knowledge for Development, Washington, D.C. __________2000 Introducing Competition Into the Electricity Supply Industry in Developing Countriess: Lessons From Bolivia, Joint UNDP/World Bank Study, No 233/00 351 Wyman-Jones, T. 1995, “Problems of Yardstick Regulation in Electricity Distribution,” in M. Bishop, J. Kay and C. Mayer, eds., Regulatory Challenge, Oxford University Press, pp.42342. __________1993, “Regulating the Privatised Utilities in the UK” in T. Clarke and C. Pitelis, eds., The Political Economy of Privatisation, London: Routledge, pp. 93-107. Yarrow, G. 1994, “Privatisation, Restructuring and Regulatory Reform in Electricity Supply”, in M. Bishop, J. Kay and C. Mayer eds., Privatisation and Economic Performance, Oxford University Press.pp 63-87 __________1986, “Privatisation in Theory and Practice” Economic Policy, Vol.2, pp. 324 – 377 __________1989, “Does Ownership Matter?” in C. Veljanovski, ed., Privatisation and Competition: A Market Prospectus, London: Institute of Economic Affairs Hobart No 28 , pp 52-69. Young, A. 2001, The Politics of Regulation: Privatised Utilities in Britain. London: Pelgrave.
© Copyright 2026 Paperzz