AN EXPERT WRITES... Delay analysis – a return to common sense? Recent developments in establishing causation in fact Introduction The Protocol There have been dozens of books, hundreds of articles and thousands of debates about how delay analysis should be carried out when looking at a construction project from a retrospective point of view to try to determine exactly what caused a delay to the completion date. A committee set up by the Society of Construction Law (SCL) produced, after much debate, the Delay and Disruption Protocol (the ‘Protocol’) which was published in October 2002. This was welcomed by many in the construction industr y as a valiant attempt, in its own words, to ‘provide useful guidance on some of the common issues that arise on construction contracts’. This erstwhile document tried to cover both live projects and also the forensic approach to be adopted in circumstances where a dispute had arisen and even where such a dispute had been referred to a formal procedure for resolution such as arbitration or litigation. It did of course come with a number of health warnings on the packet. For instance, it clearly stated that ‘it is not intended that the Protocol should be a contract document. Nor does it purport to take precedence over the express terms of a contract or be a statement of the law’. However, these warnings in the author’s view seem to have been often overlooked or ignored and the Protocol has been used in disputes to try to support an argument that a delaying event does not in fact have to delay overall completion of the project to entitle the contractor to an extension of time. Further explanation is required. The Protocol Guidance suggests at section 3 the way in which applications for extensions of time (‘EOT’) are to be assessed during the course of the project. This has, however, been extended by common usage by independent experts and consultants when addressing a retrospective critical path analysis of a delayed project in a dispute resolution process. In particular, clause 3.2.6 of the Protocol states that that the Updated Programme should be the primary tool used to guide the Contract Administrator (‘CA’) in determining the amount of the EOT. The EOT should be granted to the extent that the employer risk event is predicated to prevent the works being completed by the ‘then planned prevailing contract completion date’. The Protocol recommends that in deciding a contractor’s entitlement to an EOT, the adjudicator, judge or arbitrator should, so far as is practicable, put him/ herself in the position of the CA at the time when the employer risk event occurred. The above approach is often referred to as an entitlement to an EOT. The Protocol even suggests this entitlement approach should be applied in cases where there are concurrent delaying events, that is, where two or more delaying events arise at different times, but the effects of them are felt (in whole or in part) at the same time. This can be represented graphically as in Figure 1 below: 44 Bob Breeze Stapleton International, London and Darlington CONSTRUCTION LAW INTERNATIONAL Volume 7 Issue 2 June 2012 Figure 1 – The entitlement approach In the above example, the contract works are already running late and the contract completion date will not be met. The prevailing completion date when the employer risk event occurred was five days after the contract completion date. However, the Protocol states that it is the impact on the contract completion date which is to be analysed. In the above case, this would give rise to a three-day EOT; that being the period by which the employer risk event over-runs the contract completion date, despite the fact that the contractor was already going to be five days late and in fact no further delay occurred as a result of the employer risk event in question. Perhaps it is time for the SCL Protocol now to be updated to reflect current thinking? Recent authority This point was aired in the case of Adyard Abu Dhabi v SDS Marine Services [2011] EWHC 848 (Comm) where the Commercial Court had to determine whether SDS could rescind two shipbuilding contracts and reclaim the sums it had paid to Adyard. Adyard had commenced proceedings, arguing that SDS could not rescind as SDS had caused delays to the project. Adyard also argued the prevention principle but the Court found against Adyard in that respect. The Court also had to consider whether Adyard had proved that SDS had in fact caused the delay to the project in any event. Causation in law and fact Adyard’s case was that causation was established by showing that the duration of the employer’s risk event (a minor variation in this case to two sliding doors) went beyond the original contractual sea trial date (which was equivalent in this case to the delivery date), regardless of what other events may have been delaying the works and whether or not the variation did have any impact on the actual progress of the works. CONSTRUCTION LAW INTERNATIONAL Volume 7 Issue 2 June 2012 In his judgment, The Hon Mr Justice Hamblen stated: ‘If, for example, a two day variation was instructed the day before the sea trials date, and was a variation of a type which would need to be completed before sea trials, then, if there was an extension of time clause Adyard would be entitled to a one day extension of time, or, if there was no such clause, Adyard could rely on the prevention principle.’ Adyard submitted that this was the correct approach regardless of what other events may have been delaying the works and regardless of whether the variation would have any impact on the actual progress of the works. It argued that one looks only at the event/act in question and how it relates to the contractual completion date. So, if the project was already in six months irretrievable delay it would make no difference to the causation analysis. Adyard would still get its extension of time or be entitled to rely on the prevention principle. The Judge then went on to conclude that Adyard’s approach was wrong as a matter of both principle and authority. It was wrong in principle because in essence Adyard’s case was that there was no need to prove causation in fact. On its case there was no need to prove that the event or act caused any actual delay to the progress of the works and a notional or theoretical delay would suffice. It was also contrary to common sense. The Judge referred to the quote from the Protocol highlighted at the beginning of this article. In such circumstances the Protocol can, he said, be of little assistance in relation to the legal causation issues which arise in this case. The parties’ experts agreed that there was no actual delay, whether viewed prospectively or retrospectively, caused by any employer risk event and that the common-sense view of the events on-site should not be ignored. It followed that the actual delay had to be proved and Adyard’s causation claim failed. In a graphic form, the situation is as set out in Figure 2 below: 45 FEATURE AN EXPERT ARTICLE WRITES... Figure 2 – The causation approach In the subsequent case of Jerram Falkus Construction Limited v Fenice Investments Inc [2011] EWHC 1935 (TCC), completion of the works was delayed by several months and the employer, Fenice, claimed liquidated damages. Jerram disputed this entitlement. It argued that Fenice had prevented completion and that there was no mechanism in the contract for extending time in this event since the Joint Contracts Tribunal (JCT) clause 2.26 Relevant Event dealing with prevention events had been deleted from the contract. Time for completion was claimed to be at large and Fenice could not therefore levy liquidated damages. Coulson J examined the leading authorities in the area of prevention including the Adyard case. Here the court saw a distinction between a situation where the contractor would not have completed by the due date because of its own delay (where the prevention principle would apply in respect of a distinct non-concurrent period of employer-caused delay) and the situation described in the Adyard case which indicated that if there were two concurrent causes of delay, only one of which could be described as employer prevention and the other was the responsibility of the contractor, the prevention principle could not be relied on. Coulson J considered that the contractor must prove that the alleged act of prevention caused delay to the actual progress of work and stated: ‘The contractor must be able to demonstrate that the employer’s acts or omissions have prevented the contractor from achieving an earlier completion date and that, if that earlier completion date would not have been achieved anyway, because of concurrent delays caused by the contractor’s own default, the prevention principle will not apply.’ 46 Conclusion In summary, these cases send out a clear message that theoretical delay analysis techniques will not do in terms of proving causation in fact and in law. For any employer risk event to give rise to an EOT claim it must as a matter of fact cause actual delay or further delay to the then prevailing anticipated completion or delivery date and not the contract completion date. In the author’s view, this is a welcome return to a common-sense approach. Bob Breeze is Group Managing Director of Stapleton International and acted as the independent delay analysis expert for SDS Marine Services in the Adyard case. He can be contacted at bob.breeze@ stapletonint.com or tel: +44 1325 488048. CONSTRUCTION LAW INTERNATIONAL Volume 7 Issue 2 June 2012
© Copyright 2026 Paperzz