a case of Somanga 250MW CCGT Power Plant - ESI

Regional Large Scale Project Showcase:
From Development Plans to On-Stream Successes; a
case of Somanga 250MW CCGT Power Plant Tanzania
Presented By:
Decklan P. Mhaiki
Deputy Managing Director Investments
TANESCO
Contents
•
•
•
•
•
•
Introduction
Current Status
Available Energy Resources
ESI Reforms Road Map
Future Grid Map
Somanga CCGT 250MW Power Plant
–
–
–
–
–
–
Background
Location
Characteristics
Process
Timelines
Project Features
• Future PPP Projects
• Conclusions
Introduction - Tanzania
Population: 47.422Mil (2014 NBS est.)
Population Growth: 2.5%
Area : 945, 203 km2
GDP: 998.1USD (World Bank, 2014)
Electricity Demand Grown: 9% p.a (BRN, 2013)
Electricity Consumption: 131 kWh/Person (TANESCO, 2014)
Current Status - Generation
OIL,
223.4MW, 19.7%
HYDRO,
561.84MW, 45%
GAS,
441MW,
35.3%
Hydro
Gas
Oil
• Total Installed Capacity (Grid) – 1226.24MW
• Off-grid stations - 73.77MW (largely Oil)
Current Status - Generation
Installed Capacity By Fuel Type / Ownership
14.0%
5.7%
45%
15.1%
20.2%
HYDRO-TANESCO
GAS-TANESCO
LIQUID FUEL-TANESCO
LIQUID FUEL-IPPs/EEP
GAS-IPP
Current Status - System
The System:
50Hz, ±2.5%,
Max. Demand:
934.62MW (Dec. 2014)
Transmission:
400kV – Under construction
220kV (2732.4km)
132kV (1538.5km)
66kV (546km)
Distribution:
33kV (14,652km)
11kV (5507km)
Customers: 1,501,162 (June, 2015)
Available Energy Resources
S/NO
ENERGY RESOURCE
POTENTIAL
DEVELOPED TO
POWER
1
Gas
55Tcf
441MW
2
Hydro: Various sites
4.7GW
562MW
3
Geothermal: 58 sites
5,000MW
None
4
Coal
1.9 billion tons
None
5
Uranium Oxide
24,550 tons
None
6
Wind: 7 sites
Average wind speed 5 – 8m/s None
7
Biomass: wood fuel and
agricultural waste
500MW
8
Solar: Several sites
Average daily solar insolation About 4MW
4.6/kWh/m2
9
Tidal
Under study
35MW
None
Electricity Supply Industry Reforms Road Map 2014-2025
• Electricity Access rate: 38% (June, 2015)
• Connectivity level: 28.7% Av. (June, 2015)
8
Future Grid map by 2035
Somanga 250MW CCGT Power Plant
Background
• The project is earmarked in the
national 2012 Power System Master
Plan. It is planned to add 250MW in
the national grid.
• The proposed power plant
will utilize local natural gas
from the Mtwara – Dar es
Salaam main pipeline.
Background
• In the spirit of efficient
utilization of local energy
resources, the proposed
power plant will utilize a
Combined Cycle Gas Turbine
(CCGT) technology.
• The project was chosen to be a
pilot project to be implemented
under Public Private Partnership
(PPP)
arrangement.
All
preparatory works are financed
by the World Bank.
Location
• The Pre-feasibility study has indicated that the proposed plant has to
be relocated from Mkuranga area, Pwani District to Somanga, in
Kilwa District. The Kilwa site is near to the sea, gas infrastructure, Dar
– Mtwara road and proposed substation.
Characteristics
• Plant Cooling Water will be
sourced from the sea, with a
once-through cooling method.
• The generated power will be
evacuated through a 400kV
substation to the proposed
main 400kV Mtwara –
Kinyerezi Transmission line.
Intention
Characteristics
The project is planned to be
implemented under PPP arrangement
with an intention to:
• expedite project implementation;
• quality Improvement;
• access to new sources of private
capital; and
• allocate risks to the party (private
party) best able to manage the risk.
Process
For the competitive process, prior to start of EPC implementation
works will follow the following route .
Timelines
DURATION
(Months)
START
END
PFS
5
Oct. 2014
Feb. 2015
EOI (TA)
6
Feb. 2014
Jul. 2014
12
Aug. 2014
Aug. 2015
TRANSACTIONS
(+ Financial Close)
18
Sept. 2015
Feb. 2017
EPC
(Commissioning +COD )
30
Mar. 2017
Aug. 2019
ACTIVITY
RFP (TA)
Project Features
Project
Green field
Technology
CCGT
Capacity
300MW
Source of Cooling Water
Sea Water
Operation
Base load
Location
Kilwa District
(about 245km south of Dar)
Status
Under contracting of
Transaction Advisor
Implementation
PPP
Expected Commission date
August 2019
Future PPP Power Projects
Project
Size
Technology/Fuel
Location
Thermal Generation Projects
Ngaka Coal Project
400MW
Steam - Coal
Mbinga
Solar
50MW
Solar PV
(Shinyanga/Dodoma)
Kinyerezi IV
430MW
CCGT
Dar es Salaam
Hydro Generation Projects
Rumakali
520MW
Hydro
Njombe
Ruhudji
358MW
Hydro
Njombe
Conclusions
1. Tanzania has decided to develop IPP power projects using
competitive methods
2. This is the first project to be developed in the competitive
mode
3. Interested Investors are invited to participate in the
process
4. More projects under way for Hydro, Coal, Gas, Solar, etc
Thank You for Listening!