PJM Generator Interconnection Queue #S62 LaSalle – Braidwood 345kV (500MW Energy and 100MW Capacity) System Impact Study Report DOCS#: 545674v5 December 2010 Revised November 16, 2012 © PJM Interconnection 2012. All rights reserved. Preface The intent of this System Impact Study is to determine a plan, with cost and construction time estimates, to connect the subject generation to the PJM network at a location specified by the Interconnection Customer. The Interconnection Customer may request the interconnection of generation as a capacity resource or as an energy-only resource. As a requirement for interconnection, the Interconnection Customer may be responsible for the cost of constructing: (1) Direct Connections, which are new facilities and/or facilities upgrades needed to connect the generator to the PJM network, and (2) Network Upgrades, which are facility additions, or upgrades to existing facilities, that are needed to maintain the reliability of the PJM system. The PJM Reliability Planning Process utilizes PJM planning criteria, NERC Planning Standards, NERC Regional Council planning criteria, and the individual Transmission Owner FERC filed planning criteria. In all cases, PJM applies the most conservative of all applicable planning criteria when identifying reliability problems and determining the need for system upgrades on the PJM system. The application of the NERC Planning Standards is adapted to the specific needs of the PJM system. In some instances an interconnection customer may not be responsible for 100% of the identified network upgrade cost because other transmission network uses, e.g. another generation interconnection or merchant transmission upgrade, may also contribute to the need for the same network reinforcement. All facilities required for interconnection of a generation interconnection project must be designed in compliance with the technical specifications (on PJM web site) for the appropriate Transmission Owner. After the System Impact Study Agreement is executed and prior to execution of the Interconnection Service Agreement, an Interconnection Customer may modify its project to reduce the electrical output (MW) (in the case of a Generation Interconnection Request) of the proposed project by up to the larger of 20 percent of the capability considered in the System Impact Study or 50 MW. The System Impact Study estimates do not include the feasibility, cost, or time required to obtain property rights and permits for construction of the required facilities. The project developer is responsible for the right of way, real estate, and construction permit issues. For properties currently owned by Transmission Owners, the costs may be included in the study. © PJM Interconnection 2012. All rights reserved. 2 General Invenergy Wind Development LLC has proposed a 500 MW Energy (100 MW Capacity) wind farm facility to be interconnected to the ComEd transmission system on the 345kV line 0104 between the LaSalle County to Braidwood nuclear stations. The developer has indicated windfarm will consist of 334 GE 1.5MW wind turbine-generators, to be divided on three 34kV collector busses, with a 34.5kV – 345kV transformer for each. The proposed in-service date for this project was the fourth quarter of 2012, and needs to be revised. Attachment Facilities The proposed interconnection of S62 into the existing 345kV line between LaSalle (STA 1) and Braidwood (STA 20) Substations via a new 345kV three-breaker substation is depicted in Figure #1. This proposed interconnection would consist of looping the existing 345kV line 0104 through the new 345kV Interconnection Substation, identified as Brookfield Township Wind Farm TSS 966, which is to be sited adjacent to Line 0104’s Right-of-Way. The existing Line 0104 will be renumbered as Line 96604 to Braidwood as indicated in Figure #1. As shown on Figure #1, the Interconnection Customer is proposing to construct and own a separate plant switchyard (Collector Substation) immediately adjacent to the interconnection substation, which will serve as the collection point for the wind farm generators and step-up the voltage from 34.5kV to 345kV. The 345 kV output will then be transmitted to the Interconnection Substation. The Interconnection Customer is responsible for constructing all of the facilities on the Interconnection Customer side of the point of interconnection. It will be the Interconnection Customer’s responsibility to obtain any required right-of-way between the Interconnection Substation and existing ComEd right-of-way. Direct Connection Cost Estimate The scope of direct connection work includes installation of a new 345kV Substation TSS 966 Brookfield Township with three (3) 345kv circuit breakers and tie in the new Substation into the existing 345kV transmission line 0104 as shown in Figure 1. The total preliminary estimate for Direct Connection work performed by ComEd is given for two options in the following tables: a) For ComEd to Build the new Substation © PJM Interconnection 2012. All rights reserved. 3 Description Total Cost Three 345kV breaker Interconnection Substation Brookfield Township TSS 966 (assuming ComEd engineers, procures & builds the substation) (PJM Network Upgrade Number #N2109) $15,000,000 345kV transmission line tie-in (By ComEd) (PJM Network Upgrade Number #N2110) $ 2,000,000 Total $17,000,000 b) For Customer Exercising Option to Build (Customer to build new substation) Description Total Cost ComEd to review and approve substation engineering and to monitor construction (Customer to engineer, procures & builds the new 345kV substation) (PJM Network Upgrade Number #N2109) $ 2,000,000 345kV transmission line tie-in (by ComEd) (PJM Network Upgrade Number #N2110) $2,000,000 Total $4,000,000 Cost Estimate Notes: 1) These Estimates are Order-of-Magnitude estimates of the costs that ComEd would bill to the customer for this interconnection. These estimates are based on a one-line electrical diagram of the project and the information provided to PJM and ComEd by the Interconnection Customer. 2) These cost estimates do not include cost of acquiring right-of-way for the transmission line and purchasing any additional land, if needed, for the line terminations. The need and cost of acquiring property and associated legal costs will be investigated during Facilities Study for this project. 3) There were no site visits performed for these estimates. There may be costs related to specific site related issues that are not identified in these estimates. The site reviews will be performed during the Facilities Study or during detailed engineering. © PJM Interconnection 2012. All rights reserved. 4 4) These estimates are not a guarantee of the maximum amount payable by the Interconnection Customer and the actual costs of ComEd's work may differ significantly from these estimates. Per the PJM Tariff, Interconnection Customer will be responsible for paying all actual costs of ComEd's work. 5) The Interconnection Customer is responsible for all engineering, procurement, testing and construction of all equipment on the Interconnection Customer’s side of the Point of Interconnection (POI). Project Schedule Notes: The total timeframe to complete engineering, procurement and construction for the ComEd portion of this project is approximately 18 – 24 months after the Interconnection Service Agreement (ISA) and Construction Service Agreement (CSA) are executed. Scope of Non-Direct Connection Work There is relay and control work required at the remote ends of the lines due to the interconnection of the S62 wind facility and communication equipment to ensure system reliability. Non-Direct Connection Cost Estimate The total preliminary cost estimate for Non-Direct Connection work performed by ComEd is $1,000,000 (split between PJM Network Upgrade #N2111 for LaSalle and #N2112 for Braidwood) for remote end relay upgrades and communications. Cost Estimate Notes: 1) These Estimates are Order-of-Magnitude estimates of the costs that ComEd would bill to the customer for this interconnection. These estimates are based on a one-line electrical diagram of the project and the information provided to PJM and ComEd by the Interconnection Customer. 2) There were no site visits performed for these estimates. There may be costs related to specific site related issues that are not identified in these estimates. The site reviews will be performed during the Facilities Study or during detailed engineering. 3) These estimates are not a guarantee of the maximum amount payable by the Interconnection Customer and the actual costs of ComEd's work may differ significantly from these estimates. Per the PJM Tariff, Interconnection Customer will be responsible for paying all actual costs of ComEd's work. Project Schedule Notes: © PJM Interconnection 2012. All rights reserved. 5 The total timeframe to complete engineering, procurement, and construction for the ComEd portion of this project is approximately 18 – 24 months after the Interconnection Services Agreement (ISA) and Construction Services Agreement (CSA) are executed. Revenue Metering and SCADA Requirements For PJM: The Interconnection Customer will install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for IC’s generating Resource. See PJM Manuals M-01 and M-14D, and PJM Tariff Section 24.1 to 24.2. For ComEd: The Interconnection Customer will install equipment necessary to provide bi-directional Revenue Metering (KWH, KVARH) and real time data (KW, KVAR, circuit breaker status, and 345 kV voltage) for IC’s generating Resource. See ComEd Applicable Standards available on the PJM website (“TO Standards”) – “Exelon Energy Delivery Interconnection Guidelines (Generators Greater than 20 MW)”. Figure 1. Interconnection Single Line Diagram © PJM Interconnection 2012. All rights reserved. 6 Network Impacts The S62 project was studied as a 500 MW (100 MW Capacity) injection into the LaSalle County to Braidwood Blue 345 kV line 0104 in the ComEd area. Project S62 was evaluated for compliance with reliability criteria for summer peak conditions in 2012. Potential network impacts were as follows: Generator Deliverability (Single or N-1 contingencies for the Capacity portion only of the interconnection) No problems were identified. Multiple Facility Contingency (Double Circuit Tower Line contingencies were studied for the full energy output. The contingencies of Line with Failed Breaker and Bus Fault will be performed for the Impact Study.) Item Contribution MVA 1a 31.02 Overload % Rating Overloaded Contingency Element Element From To Type MVA LASCOPMP tower outage to of '345MAZON;B 98.93% 108.90% ALDR 264.5 L0101__B138 kV line S_+_345(36956 to L0102__R-S' 36968) Short Circuit (Summary of impacted circuit breakers) No problems were identified Contribution to Previously Identified Overloads (S62 contributes to the following contingency overloads, i.e. "Network Impacts", identified for earlier generation or transmission interconnection projects in the PJM Queue) No problems were identified. Steady-State Voltage Requirements (Summary of VAR requirements based upon the results of the steady-state voltage studies.) None. Stability and Reactive Power Requirement for Low Voltage Ride Through (Summary of VAR requirements based upon the results of the dynamic studies.) © PJM Interconnection 2012. All rights reserved. 7 The stability analysis of this project will be performed as part of the Facilities Study. The Low Voltage Ride Through (LVRT) study will also be performed during the Queue S62 Facilities Study. New System Reinforcements (Upgrades required to mitigate reliability criteria violations, i.e. Network Impacts, initially caused by the addition of this project generation) 1. Referring to item #1a, the overload of LaSalle to Mazon 138kV line 0108 is caused initially by the common tower outage of LaSalle to Plano 345kV blue line 0101 and LaSalle to Plano 345kV red line 0102. This overload can be relieved by increasing the thermal rating along approximately 10.25 miles of 138 kV line 0108. The estimated cost for this upgrade is $8,000,000. The estimated time to complete this upgrade is 18-24 months. Potential Issues Impacts to an Affected System (MISO) have not been determined at this time. Light Load Reliability Analysis (Summary of any reinforcements required to mitigate system reliability issues during light load periods. This light load study was evaluated for compliance with reliability criteria for Light Load conditions in 2014.) Generator Deliverability for Light Load None Multiple Facility Contingency for Light Load (Double Circuit Tower Line, Line with Failed Breaker and Bus Fault contingencies for the full energy output) 1. (205/218) The 05TWIN B - 18ARGNTA 345kV line (from bus 243234 to bus 256000 ckt 1) is overloaded to 106.93% of its rating 1409MVA for the Tower contingency 427 scenario. The S62 project contributes approximately 25.85MW to the thermal violation. Contribution to Previously Identified Overloads for Light Load (This project contributes to the following contingency overloads, i.e. "Network Impacts", identified for earlier generation or transmission interconnection projects in the PJM Queue) 2. (205/205) The 05OLIVE - 05DUMONT 345kV line (from bus 243229 to bus 243219 ckt 2) is overloaded to 152.83% of its rating 1272MVA for the © PJM Interconnection 2012. All rights reserved. 8 Single contingency 765-L11215__-S scenario. The S62 project contributes approximately 51.21MW to the thermal violation. 3. (217/217) The 17BABCOK - 17STLWEL 345kV line (from bus 255100 to bus 255113 ckt 1) is overloaded to 145.08% of its rating 1906MVA for the Single contingency 765-L11215__-S scenario. The S62 project contributes approximately 89.88MW to the thermal violation. 4. (217/217) The 17BUROAK - 17LESBRG 345kV line (from bus 255101 to bus 255106 ckt 1) is overloaded to 114.96% of its rating 1195MVA for the Single contingency 765-L11215__-S scenario. The S62 project contributes approximately 38.16MW to the thermal violation. 5. (217/217) The 17GARYAV - 17DUNACR 345kV line (from bus 255251 to bus 255103 ckt 1) is overloaded to 102.41% of its rating 1195MVA for the Single contingency 765-L11215__-S scenario. The S62 project contributes approximately 43.28MW to the thermal violation. 6. (217/222) The 17GRNACR - G ACR; T 345kV line (from bus 255104 to bus 270771 ckt 1) is overloaded to 144.73% of its rating 1091MVA for the Single contingency 765-L11215__-S scenario. The S62 project contributes approximately 51.04MW to the thermal violation. 7. (217/217) The 17MUNSTR - 17LKGORG 345kV line (from bus 255109 to bus 255107 ckt 1) is overloaded to 143.7% of its rating 1195MVA for the Single contingency 765-L11215__-S scenario. The S62 project contributes approximately 56.94MW to the thermal violation. 8. (217/217) The 17SCHAHF - 17BUROAK 345kV line (from bus 255110 to bus 255101 ckt 1) is overloaded to 135.76% of its rating 1195MVA for the Single contingency 765-L11215__-S scenario. The S62 project contributes approximately 45.3MW to the thermal violation. 9. (217/217) The 17SHEFLD - 17GARYAV 345kV line (from bus 255111 to bus 255251 ckt 1) is overloaded to 118.6% of its rating 1195MVA for the Single contingency 765-L11215__-S scenario. The S62 project contributes approximately 46.65MW to the thermal violation. 10. (217/222) The 17STJOHN - S JOH; T 345kV line (from bus 255112 to bus 270886 ckt 1) is overloaded to 152.83% of its rating 1091MVA for the Single contingency 765-L11215__-S scenario. The S62 project contributes approximately 58.58MW to the thermal violation. 11. (217/205) The 17STLWEL - 05DUMONT 345kV line (from bus 255113 to bus 243219 ckt 1) is overloaded to 172.24% of its rating 1598MVA for the Single contingency 765-L11215__-S scenario. The S62 project contributes approximately 91.91MW to the thermal violation. 12. (222/217) The BURNH; B - 17SHEFLD 345kV line (from bus 270674 to bus 255111 ckt 1) is overloaded to 174.87% of its rating 1069MVA for the Single contingency 765-L11215__-S scenario. The S62 project contributes approximately 52.16MW to the thermal violation. 13. (222/217) The BURNH;0R - 17MUNSTR 345kV line (from bus 270677 to bus 255109 ckt 1) is overloaded to 169.39% of its rating 1195MVA for the Single contingency 765-L11215__-S scenario. The S62 project contributes approximately 64.3MW to the thermal violation. © PJM Interconnection 2012. All rights reserved. 9 14. (222/222) The COLLI; - COLLI;2M 765/345kV transformer is overloaded to 147.36% of its rating 1379MVA for the Single contingency 765L11216__-S scenario. The S62 project contributes approximately 32.33MW to the thermal violation. 15. (222/222) The COLLI; - WILTO; 765kV line (from bus 270607 to bus 270644 ckt 1) is overloaded to 125.95% of its rating 4142MVA for the Single contingency Base Case scenario. The S62 project contributes approximately 120.14MW to the thermal violation. 16. (222/222) The COLLI; - WILTO; 765kV line (from bus 270607 to bus 270644 ckt 1) is overloaded to 122.05% of its rating 4460MVA for the Single contingency 345-L2001__B-S scenario. The S62 project contributes approximately 131.28MW to the thermal violation. 17. (222/222) The COLLI;2M - COLLI; R 345kV line (from bus 275168 to bus 270697 ckt 1) is overloaded to 147.35% of its rating 1379MVA for the Single contingency 765-L11216__-S scenario. The S62 project contributes approximately 32.33MW to the thermal violation. 18. (222/217) The CRETE;BP - 17STJOHN 345kV line (from bus 274750 to bus 255112 ckt 1) is overloaded to 167.2% of its rating 1334MVA for the Single contingency 765-L11215__-S scenario. The S62 project contributes approximately 76.6MW to the thermal violation. 19. (222/222) The E FRA; B - CRETE;BP 345kV line (from bus 270728 to bus 274750 ckt 1) is overloaded to 167.54% of its rating 1334MVA for the Single contingency 765-L11215__-S scenario. The S62 project contributes approximately 76.6MW to the thermal violation. 20. (222/222) The E FRA; R - UPNOR;RP 345kV line (from bus 270729 to bus 274804 ckt 1) is overloaded to 165.57% of its rating 1091MVA for the Single contingency 765-L11215__-S scenario. The S62 project contributes approximately 60.83MW to the thermal violation. 21. (222/205) The G ACR; T - 05OLIVE 345kV line (from bus 270771 to bus 243229 ckt 1) is overloaded to 144.34% of its rating 1091MVA for the Single contingency 765-L11215__-S scenario. The S62 project contributes approximately 51.04MW to the thermal violation. 22. (222/205) The WILTO; - 05DUMONT 765kV line (from bus 270644 to bus 243206 ckt 1) is overloaded to 138.74% of its rating 4444MVA for the Single contingency NIPS9 scenario. The S62 project contributes approximately 170.19MW to the thermal violation. 23. (222/205) The WILTO; - 05DUMONT 765kV line (from bus 270644 to bus 243206 ckt 1) is overloaded to 141.81% of its rating 4047MVA for the Single contingency Base Case scenario. The S62 project contributes approximately 153.09MW to the thermal violation. 24. (205/205) The R60_S72_TAP - T130 POI 345kV line (from bus 99202 to bus 90986 ckt 1) is overloaded to 173.04% of its rating 878MVA for the Single contingency 361_B2 scenario. The S62 project contributes approximately 32.21MW to the thermal violation. 25. (222/217) The S JOH; T - 17GRNACR 345kV line (from bus 270886 to bus 255104 ckt 1) is overloaded to 152.78% of its rating 1091MVA for the © PJM Interconnection 2012. All rights reserved. 10 Single contingency 765-L11215__-S scenario. The S62 project contributes approximately 58.58MW to the thermal violation. 26. (205/205) The T130 POI - 05E LIMA 345kV line (from bus 90986 to bus 242935 ckt 1) is overloaded to 194.16% of its rating 878MVA for the Single contingency 361_B2 scenario. The S62 project contributes approximately 32.21MW to the thermal violation. 27. (222/205) The UPNOR;RP - 05OLIVE 345kV line (from bus 274804 to bus 243229 ckt 1) is overloaded to 164.68% of its rating 1091MVA for the Single contingency 765-L11215__-S scenario. The S62 project contributes approximately 60.83MW to the thermal violation. 28. (222/222) The WILTO; B - WILTO;4M 345kV line (from bus 270926 to bus 275233 ckt 1) is overloaded to 169.05% of its rating 1601MVA for the Line_FB contingency 112-65-BT2-3__ scenario. The S62 project contributes approximately 78.72MW to the thermal violation. 29. (222/222) The WILTO; B - WILTO;4M 345kV line (from bus 270926 to bus 275233 ckt 1) is overloaded to 123.61% of its rating 1379MVA for the Single contingency 765-L11216__-S scenario. The S62 project contributes approximately 49.52MW to the thermal violation. 30. (222/222) The WILTO; R - WILTO;3M 345kV line (from bus 270927 to bus 275232 ckt 1) is overloaded to 168.47% of its rating 1601MVA for the Line_FB contingency 112-65-BT5-6__ scenario. The S62 project contributes approximately 78.76MW to the thermal violation. 31. (222/222) The WILTO; R - WILTO;3M 345kV line (from bus 270927 to bus 275232 ckt 1) is overloaded to 123.49% of its rating 1379MVA for the Single contingency 765-L11216__-S scenario. The S62 project contributes approximately 49.62MW to the thermal violation. 32. (222/222) The WILTO;3M - WILTO; 345/765kV transformer is overloaded to 169.03% of its rating 1601MVA for the Line_FB contingency 112-65-BT5-6__ scenario. The S62 project contributes approximately 78.76MW to the thermal violation. 33. (222/222) The WILTO;3M - WILTO; 345/765kV transformer is overloaded to 123.48% of its rating 1379MVA for the Single contingency 765-L11216__-S scenario. The S62 project contributes approximately 49.62MW to the thermal violation. 34. (222/222) The WILTO;3M - WILTO; R 345kV line (from bus 275232 to bus 270927 ckt 1) is overloaded to 106.06% of its rating 1601MVA for the Line_FB contingency 112-65-BT4-5__ scenario. The S62 project contributes approximately 30.1MW to the thermal violation. 35. (222/222) The WILTO;4M - WILTO; 345/765kV transformer is overloaded to 169.05% of its rating 1601MVA for the Line_FB contingency 112-65-BT2-3__ scenario. The S62 project contributes approximately 78.72MW to the thermal violation. 36. (222/222) The WILTO;4M - WILTO; 345/765kV transformer is overloaded to 123.6% of its rating 1379MVA for the Single contingency 765-L11216__-S scenario. The S62 project contributes approximately 49.52MW to the thermal violation. © PJM Interconnection 2012. All rights reserved. 11 37. (222/222) The WILTO;4M - WILTO; B 345kV line (from bus 275233 to bus 270926 ckt 1) is overloaded to 105.65% of its rating 1601MVA for the Line_FB contingency 112-65-BT3-4__ scenario. The S62 project contributes approximately 30.11MW to the thermal violation. Steady-State Voltage Requirements (Results of the steady-state voltage studies should be inserted here) The S62 project contributes to multiple voltage problems in ComEd, AEP, and NIPSCO areas. New System Reinforcements (Upgrades required to mitigate reliability criteria violations, i.e. Network Impacts, initially caused by the addition of this project generation) None Contribution to Previously Identified System Reinforcements (Overloads initially caused by prior Queue positions with additional contribution to overloading by this project. This project may have a % allocation cost responsibility which will be calculated and reported for the Impact Study) (Summary form of Cost allocation for transmission lines and transformers will be inserted here if any) 1. Sorenson – East Lima 345kV. Cost $115M. Queue Project S57/58 S62 Impact, MW 63.6 32.21 Impact, % 66.38% 33.62% Cost, $M 76.3386 38.6614 2. Voltage/Thermal Upgrades. Cost $352M: Upgrades: n3436 n3437 n3448 Cost, $M Description Collins - Meadow Lake 765kV line Meadow Lake Station work for Collins-Meadow Lake line 250 MVAR Cap at Dumont 765kV sub Queue Project S57/58 S62 Impact, MW 1728.685 153.09 Impact, % 89.18% 7.90% 330 10 12 Cost ,$M 313.9060 27.7991 The following MISO MVP projects are also required for this project, but at this time no cost allocation is given to S62: ISO MVP project included in the study: Greentown – Meadow Lake 765kv line © PJM Interconnection 2012. All rights reserved. 12 TO CE AEP AEP Meadow Lake 765/345kV transformer Reynolds - Hiple 345 kV MISO has approved a 765kV line from Reynolds – Green Town, therefore, the final path of the Meadow Lake Green Town 765kV line MISO MVP project will be reviewed during the Facilities Study. Should the MISO MVP projects be withdrawn from MISO’s baseline, these projects would still have to be built by S57/S58 and subsequently queued projects. Potential Issues to Adjacent RTO’s Additional impacts may be defined in the Facilities Study. Delivery of Energy Portion of Interconnection Request PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting a Merchant Transmission Interconnection request. Table 1 below provides a summary of the congestion caused or contributed to by the S62 project on the ComEd transmission system: Item 2a 2a Overload % Contribution Overloaded MVA Element From To PLANO;R to ELECT;4R 59.71 97.02% 100.43% 345 kV line (36373 to 36311) PLANO;R to ELECT;4R 47.36 98.53% 101.53% 345 kV line (36373 to 36311) © PJM Interconnection 2012. All rights reserved. 13 Rating Type MVA Contingency Element ER 1739 operation outage of '345L16704_B-S' NR 1339 Base case
© Copyright 2026 Paperzz