# 34 NEWSLETTER SEPTEMBER 2016 COWI MARINE NORTH AMERICA BAY BRIDGE PIER DEMOLITION BAY BRIDGE PIER DEMOLITION SVP MSG WINSTON HOSE TOWERS Caltrans is demolishing the old San Francisco-Oakland East Bay Bridge. A dry cofferdam around each of three caisson foundations to allow demolition down to the mudline 50 feet below water was one expensive option that would take years and cause noise that would stress fish, birds, and sea mammals. BLACK BALL FERRY LINE CONTENT SUBWAY STATION CONSTRUCTION AND GEOTECHNICAL ENGINEERING IN DOHA, QATAR HIGH-SPEED RAIL TRENCH AND TUNNEL IN DENMARK FEATURED ENGINEER COWI Marine North America provided engineering to facilitate an economical and clean way to eliminate the caissons. Caltrans and the general contractor proposed a different demolition method for the first caisson, E3. This option combined mechanical demolition above water with an implosion of the rest. If it worked, the demolition would last months rather than years and the effect on animals would be brief. COWI provided demolition sequence drawings, assessed the caisson's ability to support excavators, designed work platforms to support excavators and a drill rig, and provided a resident engineer to observe demolition. CONTINUED ON PAGE 5 2 # 34 NEWSLETTER SEPTEMBER 2016 3 SENIOR VICE PRESIDENT’S MESSAGE ABOUT COWI MARINE NORTH AMERICA (FORMERLY BEN C. GERWICK, INC. AND OCEAN AND COASTAL CONSULTANTS) COWI Marine North America’s structural, geotechnical, and coastal engineers and engineer-divers are experts in the design, construction engineering, inspection, maintenance, and repair of locks, dams, floodgates, flood walls, dry-docks, bulkheads, wharves, piers, cofferdams, bridge towers, pile-, drilled shaft-, and caisson-foundations, harbors, terminals, offshore platforms, offshore wind turbine foundations, immersed tubes, and cut-and-cover tunnels. Seismic retrofits and construction using float-in, concrete or steel elements are COWI specialties. LOCATIONS 35 Braintree Hill Office Park, Suite 100 Braintree, MA 02184 Tel: +1 508-830-1110 3780 Kilroy Airport Way, Suite 200 Long Beach, CA 90806 Tel: +1 562-598-9888 1036 Wall Street Mount Pleasant, SC 29464 Tel: +1 843-375-2013 400 Poydras Street, Suite 1160 New Orleans, LA 70130 Tel: +1 504-528-2004 276 Fifth Ave, Suite 1006 New York, NY 10001 Tel: +1 646-545-2125 1300 Clay Street, 7th Floor Oakland, CA 94612 Tel: +1 510-839-8972 1191 2nd Avenue, Suite 1110 Seattle, WA 98101 Tel: +1 206-216-3933 35 Corporate Drive Trumbull, CT 06611 Tel: +1 203-268-5007 101-788 Harbourside Drive North Vancouver, BC V7P 3R7 Tel: +1 604-986-1222 CONTACTS U.S. Army Corps and Offshore Marine Structures Dale Berner, PhD, PE FASCE [email protected] Inspection, Maintenance, Repair, and Diving Stephen Famularo [email protected] Wharves, Piers, Ports and Harbors Ted Trenkwalder, PE, SE [email protected] Water Resources, Waterways and Construction Engineering Michael O’Sullivan, PE, SE [email protected] Tunnels, Pipelines and Immersed Tubes Henrik Dahl, PE [email protected] Foundations and Geotechnical Winston Stewart, PE [email protected] Editor Michael Woods, PE, SE [email protected] www.cowi-na.com WINSTON STEWART, PE [email protected] Since the last edition of Gerwick News was published and distributed in 2014, many changes have occurred that bear reiterating. First, the two Marine legacy companies, Ben C. Gerwick, Inc. and Ocean & Coastal Consultants, Inc., merged at the beginning of 2015 to become COWI Marine North America, and a Business Unit of COWI North America, Inc. (hereinafter COWI). We added a Marine practice in North Vancouver, BC under the experienced leadership of Sara Fumagalli-Hui, P.Eng, and as at the date of this newsletter the staff numbers six (6). On January 1, 2016, the other two legacy companies, Buckland & Taylor and Jenny Engineering Corporation, also became business units of COWI, and were re-branded as COWI Bridge North America and COWI Tunnel North America. As the months went by in 2016, these business units have been referred to generally as BU Bridge (B), BU Tunnel (T) and BU Marine (M), to align with the rest of COWI BTM internationally. Each business unit is headed by a Senior Vice President and functions as individual P/L centers. Notwithstanding the changes that have occurred, I can say without hesitation to our clients that the quality of services that they have come to expect from the former legacy companies have not changed. If anything, these changes have significantly enhanced the capacity of COWI to deliver quality engineering services as prime consultant or as an equal partner in joint ventures on projects of varying sizes and complexities. The rest of my message will have a Marine focus, as it prefaces the contents of this newsletter, which showcase selected and representative projects of BU Marine, both national and international. We have selected five (5) projects/articles that we hope will pique the interest of our readers and provide a glimpse into the talents and expertise of our engineering staff. Three (3) are from North America and one (1) each from Qatar and Denmark. # 34 NEWSLETTER SEPTEMBER 2016 The Bay Bridge Pier Demolition graces the front of the newsletter, perhaps because it is synonymous with the old East Bay Bridge that was a landmark in the state of California. We provided engineering services that resulted in an economical and efficient way to eliminate the caissons, which significantly reduced the demolition time and impact to the ecosystem of birds, fish and mammals. The article on Hose Towers provides a treatise on these marine structures, both in terms of their configurations and usefulness. They are essentially comprised of ordinary concentrically braced frames (OCBF) and are an integral part of liquid bulk terminals. COWI has significant experience in assisting terminal operators with designing these structures. The third article is on the Black Ball Ferry Line Belleville Terminal wharf in Victoria Harbour, British Columbia. Our staff provided final design and engineering support services during construction. By incorporating precast concrete pile caps, deck panels and edge beams we were able to design a rapid wharf replacement concept that facilitated construction activities without any disruption to normal ferry service. We provided geotechnical engineering services for the Doha Metro rail system in Qatar. The main geotechnical risks and challenges for this project included non-uniform and varying degrees of rock weathering and permeability and associated potential for dissolution cavities in the Limestone and reduced effectiveness for dewatering. Finally, BU Marine collaborated with colleagues in Denmark for the High Speed Rail Trench and Tunnel project for package 4 of the 36-mile Copenhagen to Ringsted Railway Line. Our staff performed designs for several components of the project that required out-of-the box thinking to address the unique challenges in attendance. Happy reading! Our services include underwater inspection, repair, and modification, coastal engineering, hydrographic surveys, dredging supervision, documentation for environmental regulation, construction administration, and asset management. We produce reliable, economical, innovative, and sensible-to-construct designs for challenging design-build and design-bid-build projects. We engineer large and small projects, globally and locally. Our company is a member of the COWI North America group, which includes COWI Bridge North America and COWI Tunnel North America. Engineers from each part of the group share offices and collaborate on bridges, tunnels, and marine structures. COWI Marine North America leads the global Seismic Center of Excellence for all of the COWI companies. The Engineering News-Record 2015 Global Sourcebook ranks COWI among the top international design firms for Marine and Port Facilities (4th largest), Bridges (2nd largest), and Transportation (15th largest). 4 # 34 NEWSLETTER SEPTEMBER 2016 5 # 34 NEWSLETTER SEPTEMBER 2016 HOSE TOWERS Hose tower structures are common in marine terminals that transfer liquid products to and from vessels. Because these structures serve a variety of vessel sizes and of liquid products, it is important to consider vessel size, tidal range, and location of manifolds on each vessel and on the hose tower. The primary purpose of hose towers is to hold an array of hoses connected to a manifold. The hoses are suspended from the front of the tower. A crane, mounted on top of the tower, handles the hoses and places them on the deck of a vessel where crews connect them to the vessel manifold. Hose towers are generally "ordinary concentrically braced frames" (OCBF), comprised of structural steel members. The main loads that the OCBF resists are the weight of the frame, equipment, and the oil or other fluid product. High lateral wind, seismic, or wave forces at some locations can add to the cost of the OCBF. Pipeline loads from thermal loads affecting pipelines are usually minimized by the use of low-friction pads; however, if pipelines are not equipped with low-friction pads and the pipelines are fixed to the tower, engineers must account for these lateral loads in the analysis. ENGINEERING FROM CONCEPTION TO CONSTRUCTION VESSEL INVENTORY In response to the deepening of navigation channels and raising of bridges to allow the use of larger vessels, marine terminal owners are upgrading their facilities to receive a greater variety of traffic. TOWER WIDTH, OPERATIONS, AND SAFETY Towers can be as narrow as 24 or as wide as 50 feet, as short as 30 or as tall as 60 feet, depending on the layout and the number of product lines. Operations and safety need to be considered, specifically, the means of egress, fall protection, overhead clearances, walking clearances, and pipeline supports. Walking surface and overhead clearances are important for safe operations. Means of egress are also an important consideration. Stairs are preferred but ladders provide secondary egress. HOSE LENGTHS The lengths of hoses emerge from a layout study during conceptual design. To control costs during the upgrade of an existing hose tower, COWI reuses existing manifolds to the extent possible. Frequently, the location of the vessel manifold and the existing tower manifold do not align, such that longer hoses must bridge the gap between the two. Length depends on the distance between the tower and the connection points on different vessels. Hose lengths range from 40 to 70 feet. Hose diameter also varies, depending on the sizes of the pipelines connected. NUMBER OF STORIES Hose towers are of different heights and widths. Most of the hose towers that COWI Marine has designed or retrofitted have three levels-deck, intermediate, and top. All hoses connect to the manifold at the intermediate level. We select the elevation of this level so that the selected hose length permits the safe transfer of product between vessel and shore during the range of tides at the site. TOWER FOUNDATION Waterfront and offshore structures such as hose towers require deep foundations, typically vertical steel or concrete piles. If the hose tower is part of a pier or wharf that requires greater lateral stiffness, some of the piles will be installed with a batter angle. CORROSION PROTECTION The steel members of the tower are protected from corrosion by epoxy-coating or galvanization. Specifications will require steel members to be coated or galvanized during fabrication although minor touchup of the coating is performed on site. CONSTRUCTION Time is of the essence when dealing with construction at marine terminals; therefore, COWI usually details hose towers assembled from pre-fabricated sections. Towers may be constructed at an adjacent site, transported by barge, and then lifted and placed on the foundation using a barge-mounted crane. Derrick Crane Barge Demo Barge Access Gangway Excavator with Cutting Jaws Two Excavators with Breakers on Work Platform Support Barge with Baker Tanks (Dewatering) Dock Photo: Caltrans Figure 1 Site Overview with Marine Equipment and Caisson E3 Apron Slab Removed Figure 2 Demolition Completed to Nine Feet above Water for Several Cells (BAY BRIDGE DEMOLITION FROM COVER) Caisson E3, built in 1934, is the largest caisson; (see Figure 4.) Each of its cells was full of water. Its overall dimensions were 167 feet by 80 feet with a wall thickness of three feet. Two pedestals on the top deck had supported the steel bridge towers. Each pedestal was centered over four caisson cells having a top slab thickness of 17 feet. The top slab thickness of the center six cells was 39 inches. A perimeter apron slab with wing walls and a wall supporting fenders cantilevered 19½ feet from the top of E3. The contractor sealed openings in the caisson walls to contain cell water tainted with concrete dust. As the water level in the caisson increased following deposition of concrete debris in the cells, crews pumped the water into tanks for treatment elsewhere. Fish-, bird-, and sea mammalobservers were present during mechanical demolition. The contractor installed a bubble curtain to attenuate the implosion pressure spike; manifolded compressed air nozzles on the seabed created a curtain of low-density water 50 feet from the caisson. The authorities monitored water chemistry and turbidity and underwater acoustics on implosion day. ALEX MORA, PE [email protected] Caisson E3 Flexifloat Barge ENVIRONMENTAL MITIGATION The intermediate level is also the most congested part of the hose tower, because it is where the pipelines turn down, into the tower footprint, where the controls and valves are, and where the hoses connect. Engineers assist the marine terminal in selecting the reach of the crane, which is mounted on the top level. The top is also the level at which the hoses are suspended from an edge beam. Clearances around the edge beam allow the crane to reach the hoses easily in order to place them onto the vessel deck. STRUCTURAL FRAMING CONNECTIONS The structural member connections are generally bolted, for speed and ease of construction. Floors are decked with open steel grating. Support Barge (One not Shown) MECHANICAL DEMOLITION Three hydraulic excavators equipped with breaker units, cutting jaws or catcher baskets removed portions of E3 between elevations nine and 37 feet. The marine equipment shown in Figure 1 supported excavator operations. Demolition began with two excavators on the top deck chipping at the top deck slab. Crews broke openings through the deck in order to send all mechanical demolition debris to the bottom, inside the caisson cells. Then they removed the concrete pedestals to the top of the deck slab. Figure 5 shows pedestal demolition underway. COWI Marine's first contribution was the design of two 20-foot by 40-foot work platforms to support two 50-ton excavators. The platforms, supported by three parallel caisson walls, consisted of W18x97 beams with gusset plate connections; (see Figure 6). The contractor secured mats of 12x12 timbers to the top flanges. The platforms supported the excavators as they removed walls and top slabs. It was not possible for the apron slab and the walls supporting it to allow equipment on the apron slab because it was too weak and had a one vertical to four horizontal (25%) slope. The apron slab and its walls were removed with one excavator on a work platform at the caisson top level. Two excavators operated side-by-side from a barge, which was positioned such that the reinforced concrete debris landed on it. Crews made strategic cuts, using the excavators, and lifted large sections of the apron support wing walls and perimeter wall with a barge-mounted derrick. Excavators working from a barge and on the work platforms, as shown in Figure 2, demolished the remaining caisson walls, down to nine feet above the reference water elevation. Once again, crews made strategic cuts; then they used an excavator to topple large wall sections into the caisson cells. THE IMPLOSION The contractor reused the steel beams from the two original work platforms with timber mats to construct a drill rig platform, which COWI designed to cover the top surface of the remaining caisson cells. COWI engineered grout pads to create firm, level support points for the beams. Workers operated a 20-ton drill rig to install explosives from this deck. Crews drilled holes for 22,000 pounds of explosive charges 80 feet down, into the caisson walls, at three-foot spacing. The deck was left in place during the implosion in order to contain the blast. 6 # 34 NEWSLETTER SEPTEMBER 2016 7 BLACK BALL FERRY LINE BELLEVILLE TERMINAL WHARF REPLACEMENT Figure 3 Sonar Image of Caisson Before and After Implosion Figure 4 Caisson Layout and Demolition Limits Figure 5 Pedestal Demolition Underway Twenty minutes prior to the implosion, police halted traffic on the new Bay Bridge to avoid startling drivers. The marine division of the California Highway Patrol kept boaters 1,500 feet away. BART shut down the sub-sea BART rapid transit tube. News helicopters filmed. Bird, fish, and sea mammal spotters were vigilant. At 7:17 am on Saturday, November 14, 2015, the blasting subcontractor detonated charges embedded in the caisson. The implosion sent twenty million pounds of debris into the bottom of caisson cells below the mudline. See Figure 3 for “before” and “after” sonar images. Portions of the bubble curtain are apparent. Scientists predicted that as many as 1,500 fish would die; however, they concluded that the implosion had a low impact on both fish and birds. Figure 6 Work Platform Spanning Caisson Cell SUMMARY This demolition of E3 was a success; therefore, the contractor will demolish the other two caissons in the same manner. The cost at E3 was approximately $20 million. COWI helped the contractor to provide a demolition technique that is economical, fast, and environmentally sound. OWNER: California Department of Transportation GENERAL CONTRACTOR: Kiewit-Manson JV MECHANICAL DEMOLITION: Silverado IMPLOSION: Contract Drill & Blasting MICHAEL GEBMAN, PhD, PE [email protected] COWI Marine North America provided final design and construction support services for the replacement of the Black Ball Ferry Line Belleville Terminal wharf in Victoria Harbor, British Columbia. Black Ball Transport operates the MV Coho Ferry, an automobile ferry that runs daily between Victoria and Port Angeles, Washington. The ferry has carried 23 million passengers and 8 million vehicles since 1959. The existing wharf - owned by the BC Ministry of Transportation and Infrastructure - was nearing the end of its life and needed to be replaced without affecting ferry operations. # 34 NEWSLETTER SEPTEMBER 2016 8 # 34 NEWSLETTER SEPTEMBER 2016 9 # 34 NEWSLETTER SEPTEMBER 2016 SUBWAY STATION CONSTRUCTION AND GEOTECHNICAL ENGINEERING IN DOHA, QATAR Originally, Black Ball Transport retained COWI Marine as a sub-consultant to provide expertise on the seismic analysis and pile design only. However, as the project progressed and the design schedule became critical, the client asked COWI to assume full responsibility as the Engineer of Record for the entire wharf, including fender and mooring systems. Relying on precast concrete pile caps, deck panels, and edge beams, COWI Marine designed a rapid wharf replacement concept that enabled construction without any ferry service interruptions. COWI engineered the connections to accommodate potential misalignment of piles driven to support the completed structure. A key technical challenge was the wharf's location on a seismically-unstable slope subject to liquefaction and movement during an earthquake. COWI designed the replacement wharf using stateof-the-art displacement-based methods. The design featured composite concrete-filled steel pipe piles socketed into bedrock. COWI engineered the piles to resist lateral spreading resulting from slope movements in addition to supporting operational loads. The Black Ball Ferry Wharf replacement began as a traditional design-bid-build project but evolved smoothly to resemble a design-build contract. In order to construct the ferry-loading ramp during an eight-week winter shut-down window when ferry service is suspended each year, construction had to begin before the design was completed. To facilitate the tight schedule, COWI Marine prepared an early-release design package for procurement of pipe pile steel from a mill in China. In addition, COWI divided the precast component designs into numerous packages in order to initiate fabrication of concrete elements early and keep the precast manufacturer in production. Altogether, 27 design packages were required to meet the contractor’s desired construction sequence and fabrication schedules. As a result, ferry service resumed on schedule at the end of February. In less than ten years, the population of the Doha metropolitan area doubled to a million. The government has taken swift action to mitigate the severe congestion that accompanies such rapid growth by providing a subway and elevated rail system. When completed, the Doha Metro system will consist of four lines, named the Red, Green, Gold and Blue lines, 186 miles of track and 98 stations. It will cost $36 billion. Phase I of the project, which includes the construction of all four lines, will last until the end of 2019. PLAXIS 2D and WALLAP by Geosolve. The excavation support systems that we investigated included mesh-reinforced, shotcreted slopes with rock bolts, anchored soldier piles with timber lagging, and anchored diaphragm walls. Of the four stations where we performed engineering, West Bay Station absorbed most of COWI Marine North America's time. The excavation for this challenging station was 580 feet long and 91 feet wide, reaching a maximum depth of 110 feet. For the Red Line North Underground, the first of four underground segments of the whole system that serves the most densely populated parts of Doha, COWI engineered seven miles of twin-bored tunnels and seven underground stations. The tunnels have an internal diameter of 20 feet and will be built at an average depth of 65 feet below ground. We performed analysis of the temporary support of the station. We designed the diaphragm walls with a combination of ground anchors and struts supporting the station excavation, specified the required design details and notes, and laid out the associated drawings. We were also on hand to respond to client and owner queries and modify the design to accommodate conditions encountered in the field. COWI Denmark interpreted the subsurface conditions and specified the dewatering wells that construction crews installed along the wall to control groundwater levels and reduce water pressures on the wall. COWI Marine North America assisted COWI Denmark with four of the seven subway stations. We also performed engineering to connect the stations to the bored tunnels. Our work included construction engineering of temporary measures for deep excavations, which needed to be coordinated with permanent parts of the stations. Ground conditions included fill, surficial deposits, limestone, and shale. Geotechnical risks include randomly varying degrees of rock weathering and permeability with the potential for dissolution cavities in the limestone and reduced effectiveness of dewatering. The water table is generally high despite the arid climate, because of the proximity to the Persian Gulf. PAUL GUENTHER, PE, SE [email protected] COWI Marine North America's scope included the soil-structure interaction analyses for excavation support systems of the underground stations and for cut-and-cover portions, primarily using software programs As of April 2016, all tunneling for the $2 billion Red Line North Underground contract is complete. Bottom-up construction of each of the seven stations continues and has nearly reached the surface. PARTIES INVOLVED IN THE RED LINE NORTH UNDERGROUND CONTRACT OWNER: Qatar Railways Company (Qatar Rail) DESIGN-BUILD CONTRACTOR: The ISG consortium of Salini Impregilo (Italy), SK Engineering and Construction (South Korea), and Galfar Engineering and Contracting (Qatar) DESIGN OF CIVIL WORKS: A COWI-led joint venture under contract to ISG MARNEL DAWAY, PE [email protected] TP4 Railway Trench Construction Precast Concrete Plank Tunnel Roof HIGH-SPEED RAIL TRENCH AND TUNNEL IN DENMARK The TP4 (tunnel bid package 4) subsection of the 36-mile Copenhagen to Ringsted Railway Line Project includes dual tracks to replace a congested, existing railway and increase capacity. Replacing the line with Denmark's first high-speed railway will provide more departures, fewer delays, and shorter travel times with trains traveling 155 mph. The total cost of the line is $1.6 billion and it will open in 2018. COWI Marine North America provided structural and geotechnical engineering for 1,680 feet of 39-foot-wide railway trench and a 16,600 square foot-rain water drainage collection basin in the town of Hvidovre as well as the analysis of a cut-and-cover tunnel roof in Valby. The part of the line within our scope consisted of two sloping (1.6% maximum grade), opencut trenches leading to a bridge in the middle, where the line crosses over Harrestrup Brook. The 600-foot east trench and 400 feet of the west trench have steel AZ sheet pile walls. 680 feet at the west end of the west trench have 46 ½-inch diameter secant pile walls because, at that location, the top-of-rail elevation passes below the water table. The maximum retaining wall height is 29 feet during construction and 27 feet permanently. Many of the sheet pile and all of the secant pile retaining walls are anchored with one row of anchored rods grouted into the soil. COWI Marine performed the geotechnical analysis of the trenches using WALLAP (software for the geotechnical design of retaining walls). Where the rails of the east trench are at an elevation below the water table and at the west end of the west trench, COWI designed concrete floors to withstand hydrostatic uplift pressures. To save the cost of extra excavation and concrete thickness, COWI detailed a partial fixity connection between the floor slab and the walls. There were two types of connections, one for sheet piles and the other for secant piles. At four locations, where the sheet pile walled trenches cross existing utility pipes (up to 8.2 feet in diameter), COWI provided gaps in the sheet pile walls. Walers above the openings transfer lateral earth pressures into anchor rods and adjacent full-length sheet piles. Where the trench is shallow, COWI called for walers but doubled the spacing of anchor rods. Because of limited space within the trench, COWI located all walers on the retained soil side of the wall. Where there are walers, COWI's detail transfers loads from the wall to the waler to the anchor rod and back into the soil. Otherwise, anchors are connected directly to every other pile. Where the 22-foot wide Vigerslev Park pedestrian and bicycle bridge crosses the east trench, COWI engineers designed the sheet pile walls of the trench as bridge abutments. COWI designed a 16,600 square foot rain water drainage collection basin to collect runoff from the trench. Constructed of anchored sheet piles, the basin runs alongside the railway trench and shares a wall with the trench. The basin measures 184 feet parallel to the train tracks and has an average width of 88 feet. COWI engineered the reinforced concrete floor of the basin to resist hydrostatic uplift pressures with vertical anchors spaced at 9.8 feet each way. Anchored Sheet Pile Wall with Rebar Installation for RR Slab The 2,780-foot long cut-and-cover Kulbane tunnel in Valby allows trains to pass beneath streets and intersections. COWI Marine examined the tunnel roof design to determine the precast concrete plank and joint controlling forces. We analyzed the tunnel with SAP2000 structural models as an aid to detailing and then we detailed the reinforcement within and between the roof planks to resist wheel and lane loads from the automobile traffic above. MICHAEL GEBMAN, PhD, PE [email protected] COWI Marine North America saved money and time on the TP4 trenches, rain water basin, and cut-and-cover tunnel roof by applying knowledge of construction methods, cofferdams, retaining walls, and U.S. and Eurocode requirements. CLIENT: COWI Tunnel Denmark. GENERAL CONTRACTOR: Aarsleff A/S MICHAEL WOODS, PE, SE [email protected] 12 # 34 NEWSLETTER SEPTEMBER 2016 ALEX MORA, PE [email protected] FEATURED ENGINEER Alex I. Mora, PE is a Senior Marine Engineer based in Trumbull, Connecticut. Alex started his engineering career working on the analysis, design and rehabilitation of pre- and post-tensioned concrete structures shortly after receiving his Master's Degree in Civil Engineering/ Structures from the City College of New York. Subsequently Alex analyzed and designed telecommunication towers, condominium buildings, steel and concrete buildings (including the Stamford Courthouse), institutional buildings (e.g. Greenwich Academy, Burr Street Elementary, and the UCONN campus dormitory), as well as pre-cast concrete parking garages (for example, the Stamford train station garage). Alex has had a strong interest in waterfront structures since college. His first opportunity to be involved with one arrived during the construction of a Stamford, CT condominium building that required shoreline stabilization. During this work he learned about COWI Marine North America and since 2003 he has worked on marine terminals along the Atlantic seaboard from Massachusetts to New Jersey. Alex works closely with clients to meet their operational and time-sensitive requirements by assisting them with insurance claims and the prompt reconstruction of damaged structures, coordinating the structural, mechanical, electrical, and plumbing professions, from the conceptual stage to the operational stage, and rehabilitating their terminals. Examples of his work include anchored and cantilevered steel sheet pile bulkheads, multiple or single pile-supported mooring and breasting dolphins, concrete- and steel-framed manifold platforms, steel-framed hose towers, pipeline support framing, timber piers, concrete piers and wharves on steel piles, steel-framed containment and disposal facilities, and cellular sheet pile dolphins. Alex is a professional engineer licensed in Connecticut, New York, New Jersey, and California. AWARDS 2015 Caltrans Partnering in Motion Award for Demolition of Pier E3 of the San FranciscoOakland Bay Bridge 2016 ACEC California Engineering Excellence Honor Award, for the Crescent City Harbor Inner Boat Basin Reconstruction Project 2015 ACEC New York Engineering Excellence Platinum Award for Rebuild by Design Living Breakwaters PRESENTATIONS Dale Berner, PhD, PE, FASCE and Mike O’Sullivan, PE, SE, LEED AP; Deep Foundations Institute 40th Annual Conference on Deep Foundations; October 15, 2015; Army Corps Mega Project Benefits from Innovative Foundations Stephen Famularo; ASCE COPRI Coastal Structures & Solutions to Coastal Disasters Joint Conference; September 11, 2015; Rapid Identification and Assessment of New York City’s Waterfront Dennis Lambert, PE; PIANC Dredging 2015; October 20, 2015; P3 for the Nation’s Inland Marine Transportation System – Focus on Dredging Daniel Kennedy, PE and Jean Toilliez*, PhD, PE, M.ASCE; ASCE 2016 Ports Conference; June 15, 2016; Risk-Based Approach for More Resilient and Sustainable Structures Dennis Lambert, PE, M.ASCE ; ASCE 2016 Ports Conference; June 15, 2016; Moderator of the Port Planning and Operations session Dennis Lambert, PE, M.ASCE, Norma Jean Mattei*, PhD, PE, F.ASCE, F.SEI, and Derek Gardels*, PE, M.ASCE; ASCE 2016 Ports Conference; June 14, 2016; P3 Solutions for the Nation’s Inland Marine Transportation System Joseph Marrone, PE, Brent Cooper, PE, and Christopher Streb*, PE, LEED AP; ASCE 2016 Ports Conference; June 15, 2016; Improving the Sustainability of Steel Sheet Pile Bulkheads Michael O’Sullivan, PE, SE, LEED AP and Gabriel Verdugo, PE; ASCE 2016 Ports Conference; June 15, 2016; Lake Borgne Surge Barrier Tour Paul Guenther, PE, SE, William Elkey*, PE, SE, and Eric Herzstein*, PE, SE; ASCE 2016 Ports Conference; June 15, 2016; The Elliott Bay Sea Wall Replacement Project: Protecting and Enhancing Seattle’s Waterfront Samuel Christie, PE, GE and Yu Zhang, PhD, PE; ASCE 2016 Ports Conference; June 13, 2016; Seismic Design of the New Elliott Bay Sea Wall Using Conditional Mean Spectrum Stephen Famularo, PE, D.PE, M.ASCE, Brian Crane*, and Jim Hall*, GISP; ASCE 2016 Ports Conference; June 14, 2016; Managing New York City’s Aging Waterfront Infrastructure Ted Trenkwalder, PE, SE, M.ASCE, Michael O’Sullivan, PE, SE, LEED AP, and Dale Berner, PhD, PE, M.ASCE; ASCE 2016 Ports Conference; June 13, 2016; Designing, Permitting, and Constructing Resilient Structures Ted Trenkwalder, PE, SE, M.ASCE, Andy Espinoza, PhD, PE, and Sandy Yee, PE, SE, LEED AP: ASCE 2016 Ports Conference; June 15, 2016; Marine Oil Terminal Trestle Repair and Replacement Project *Not a COWI engineer
© Copyright 2026 Paperzz