TWENTY SECOND ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE New Orleans, Louisiana APRIL 14TH & 15TH, 2011 "THE GOOD, THE BAD AND THE UGLY: THE PANAMA CANAL AND SURETY IN INTERNATIONAL CONSTRUCTION, THE RISKS INVOLVED." PRESENTED BY: PETER C. PAPPAS FORCON INTERNATIONAL CORP. 1216 Oakfield Drive Brandon, Florida 33511 (813) 684-7686 KATHERINE L. FREEMAN ZURICH SURETY “The Good, the Bad and the Ugly: The Panama Canal and Surety in International Construction, the Risks Involved.” 2011 Southern Surety Conference Peter C. Pappas, P.E. and Katherine L. Freeman, Esq., Zurich Surety I. INTRODUCTION In 2007, when the author’s proposal for the expansion of the Panama Canal came in second by a billion (that’s right, a billion) dollars, he was asked how he was going to go back to his management, after spending over $20 million on the bid, and explain this. He thought for a minute and replied, “How is the “winner” going to go back to his management and explain how he left a billion dollars on the table.” Performance and payment bonds aren’t common in foreign construction. The usual form is a bank guarantee, somewhere in the neighborhood of 10 percent of the contract price. However when bonding is required in foreign projects that are usually very large the penal sums of the bonds get interesting. In this paper we will take a recent foreign mega-project, the Panama Canal, and look at how the proposal went together and what the risks were that the bidders faced. We will then look in a generic way at the issues and challenges to the surety in these situations. II. A BRIEF HISTORY OF THE PANAMA CANAL The idea of a canal across Central America goes back to at least 1524 but the first real attempt was made by the French under the leadership of Ferdinand de Lesseps, who had designed and built the Suez Canal in the 1860’s. The Panama project kicked off in 1879 when a group of French investors voted to go ahead. De Lesseps was revered in France and no one thought that there could be any risk in something built by the great man. Ground breaking occurred in 1882. and the project was bankrupt by 1888. De Lesseps and his engineers made two significant mistakes in their planning . First, they had built the Suez Canal at sea level in a dry desert along relatively flat ground with good soil conditions but in Panama they were in mountainous jungle with very difficult soil conditions. They insisted on a sea level canal in Panama but the task proved to be impossible. Second, the French were not prepared for the malaria and yellow fever that ultimately killed more than 22,000 canal workers. The project was bankrupt by 1888 and de Lesseps and others were eventually found guilty of financial crimes related to the project. In 1899 Congress created a commission to look into building a canal and at first thought seriously about Nicaragua. Eventually the U.S. bought out the French assets for $40 million and settled on Panama. However the design chosen was for a system of locks that would raise the ships a total of 26 meters on both the Pacific and Atlantic sides, thus eliminating the problem of trying to dig down to below sea level. The U.S. also brought in the doctor who had been working in Cuba and who had understood the influence of mosquitoes on tropical diseases. He instituted a program that brought the disease problem under control. Teddy Roosevelt, pictured left operating one of the big shovels on the canal, was one of the main supporters of the Panama Canal, recognizing the economic benefits to the U.S. His actions also helped coin the phrase “gunboat diplomacy” when he stationed a U.S. warship off the coast of Panama to help convince Colombia to relinquish its claim on Panama. This allowed the new independent country to negotiate with the U.S. and grant it complete control over the Canal Zone. The U.S. began construction in 1903 and completed the canal in 1914. Thereafter the canal was operated as a non-profit facility and charged transit fees only adequate to cover the cost of operation. After the canal was returned to the Panamanians in 1999, they turned it into a profit making operation and it currently turns over it’s annual profit of around $800 million to the Panamanian government. Fees for a typical large, high value, commercial vessel are on the order of $100,000 to $200,000 for a single transit. After the expansion is completed, the largest vessels will pay close to $1 million for a single transit, still much less expensive than going around South America. As an example of the impact of the canal expansion, it will allow ships carrying up to 12,500 containers to transit compared to the current limit of 5,000 containers. This has also caused a flurry of port expansion projects in the eastern U.S. as ports gear up to be able to handle the much larger ships that will need berthing. III. THE TENDER FOR THE PANAMA CANAL EXPANSION Tendering for the canal expansion was a process that went on for over two years and kept three teams from some of the world’s largest contractors busy on a full time basis. The team led by the author was a consortium made up of Bechtel Corp. along with Taisei Corporation, Japans largest contractor, and Mitsubishi Corp., one of the world’s largest trading company. Each of the partners had joint and several liability. At peak this team had over 150 engineers and technicians working on the tender in England, Germany, Japan, China, and the U.S. The second consortium was made up of Sacyr of Spain, Impreglio of Italy, Jan de Nul of the Netherlands, and several other smaller companies. The third consortium was made up of ACS, Acciona, and FCC of Spain, Hoctief of Germany, and ICA of Mexico. These teams first had to go through a rigorous prequalification process that included detailed reviews of financial and technical capabilities. This ended in late 2007 with the teams selected. The canal expansion was a true design-build project. The Panama Canal Authority (ACP) had done some very preliminary design work to prove the basic concept but otherwise the bidders were given performance criteria and were asked to provide their own preliminary design and a lump sum price to design and build two complete one-mile long sets of locks in a rain forest with one of the sets of locks crossing an active fault line. To understand why this would make a good contractor cry, and to appreciate the risks that go along, it’s necessary to understand how the canal works. There are two sets of locks in the canal, one on the northern end and one on the southern end. Because of the geography of the Isthmus, the canal actually runs from northwest to south east. Ships enter into the first chamber at sea level, the gates are closed and water enters the chamber to lift the ship by 8 meters. The gates open and the ship moves into the second chamber and the process is repeated. After rising in the third chamber, the ship passes through the Culebra Cut and into Lake Gatun which is fed by the Chagres River. The ship then travels to the end of the lake and enters the upper chamber of the opposite set of locks. All of the water used in the canal is provided by rainfall that flows from the Chagres River and other smaller rivers and this water is used in the locks to raise and lower the ships. The current locks, with three chambers each side measuring 110’ wide and 1,050’ long, use 26 million gallons of water for one ship transit. The three chambers in the new locks will be over 200’ wide and 1,500’ long and would use over 70 million gallons of water per ship transit. To avoid using this much water the concept design called for using water saving basins, which are common in Europe, but basins of this size had not been used before. In addition, there is an intricate system of culverts as large as 30’ across cast into the side walls and under the chamber floors that carry water from the lake level into and out of each chamber as the ship travels up or down the locks. The water moves entirely by gravity. There are no pumps in the system. Water always travels down from a higher chamber to a lower chamber even when a ship is travelling up the system. It was left to the bidders to do their own design of the water saving basins and the system of culverts formed inside the 30’ thick walls, then competitively bid a lump sum price to do final design and construction which in the end called for 4.5 million cubic yards of concrete, 600 million pounds of rebar, and 50 million cubic yards of excavation. At each end of each chamber there are two massive steel gates that slide sideways and open and to allow a ship to enter the chamber, then close to let the chamber fill with or empty depending on whether the ship is going up or down, and open to let it pass out into the next chamber or exit the locks. Again it was left to the bidders to figure how heavy and thick the gates had to be and how to design the carriages under the gates so that they can let a 3,000 ton gate travel over 200’ with more than 99% availability. Since there are two gates at each end of each chamber on both sets of locks, there are a total of 16 gates and no two pairs are identical. The canal is a very profitable business for the government of Panama, and the Panama Canal Authority turns over roughly $800 million per year to the government. Therefore the specs imposed a very exacting requirement for the transit time for each ship going through the canal so that at least 18 ships could transit each day. And to make sure the contractor kept this at the front of his mind the specs provided a set of acceptance testing to be done after the locks were finished. This included maximum transit time through the locks, travelling speed of the gates, and emptying and filling times for water in the chambers. At first, the penalty for failing this acceptance test was that the contractor had to return all the money they were paid to design and build the locks and demolish what they had built. Cooler heads prevailed and after much negotiation the canal authority agreed that the contractor, on failing the tests, only had to return a few hundred million dollars not counting LD’s. IV. BONDING THE PANAMA CANAL EXPANSION The Panama Canal Authority decided early in the game that it wanted performance and payment bonds on the project and not the typical 10% bank guarantee that is normally seen on foreign jobs. The original RFQ asked for 100% performance and payment bonds. Everyone knew that this project was worth several billion dollars and there was considerable concern among the Spanish, Italian, French and other European bidders who do not normally need bonding and who, in some cases, were far too weak to be able to obtain these bonds. This touched off considerable inside political maneuvering by the foreign competitors and over the course of the next several amendments to the RFQ (there were ultimately more than 20 amendments) the size of the penal sum of the performance bond was lowered to $400 million and the payment bond was lowered to $50 million. V. KEY RISKS FOR THE COMPETING CONSORTIA In the Bechtel/Taisei/Mitsubishi consortium, just as in the others, there was a focus on evaluating and mitigating risks. The risk register for this bid had several hundred risks identified and mitigation actions were identified for each as well as probabilities of occurrence. Before a proposal could be submitted senior management for all three companies had to be satisfied that all risks had been identified, analyzed, and mitigated. For the purposes of this discussion ten major risks that can affect a very large scale international project like this have been identified. We will consider how the contractor looks at those risks here and discuss the Surety’s perspective next. 1. Escalation risk. The contractor will be buying nearly two billion dollars of materials and over three hundred million dollars of heavy equipment over a five year period. Much of it could be contracted for early but first the contractor has to go through a one year design process to understand what materials and quantities are required. He knows that steel suppliers and cement suppliers and others will not guarantee their prices for more than a few months. Companies like Bechtel have large and sophisticated purchasing organizations that track and forecast material and commodity price moves but they know that prices for most commodities can double or halve in a year. How can a contractor set his lump sum price with these uncertainties? 2. Schedule risk. At the point of submitting the proposal the bidders for the canal had no detailed design and no fixed quantities, and in fact still had to schedule a year of design work before material could be bought and the first cubic yard of the 4,500,000 cubic yards of concrete could be placed. He then had to take an educated guess on how difficult the 50 million cubic yards of rock would be to excavate and how long it would take to crush this rock into sand and gravel that could be used in the concrete mix, since there was no rock or sand around. He then had to count on Caterpillar being able to deliver sixty 100 ton trucks on time, at a point when Cat’s delivery lead time on these mining trucks was 18 months, so he could haul the 50 million yards of rock. He had to hope the weather would behave and the rainy season wouldn’t be too severe so that his 60 trucks wouldn’t sink out of sight. He had to count on the sixteen gates that are 200 feet long and 100 feet high and 30 feet thick and that weigh 3000 tons each not sinking when they were completely assembled in China and set on a semi-submersible ship in the Yangtze River and sailed to Panama. If the contractor doesn’t get all this right, the LD’s are over $300,000 per day not counting the extended overhead for 7,000 people. It takes an outstanding management group and the world’s best technicians to get this right. How does the Surety get comfortable here? 3. Design risk. Over 200 designers from at least five different companies working in at least 6 different countries on three continents have to coordinate their work and produce several thousand drawings for a oneof-a-kind facility in less than a year. And this design has to be controlled so that it can be built for less that the lump sum price so estimators have to be part of the design team and run estimates constantly as the design develops. Controlling this process takes experienced design management that has done it before as well as state-of-the-art IT technology that can move megabites of data between countries seamlessly. 4. Quantity risk. The conceptual design provided by the canal authority was no more than outlines of what the locks could look like so there were no quantities available to the bidders. It was necessary during the bidding phase to complete enough design to understand basic quantities such as, how thick the walls are (over 30’ in some areas), or how much rebar is needed, or how deep the excavations have to go. The contractor then has to hope that his design team can produce a final design within the boundaries of the bid team design. In design-build work design creep is a real and serious risk that a contractor has to control or costs spiral out of control. Bechtel management uses the term AFGIS to remind their bid teams to consider the Allowance for Growth in Scope when deciding the final quantities to price. 5. Currency risk. When working in a foreign country U.S. contractors will normally insist on being paid in U.S. dollars but often the foreign customer will not accept this. The U.S. contractor also has to pay expenses in country in the local currency and often has to buy materials in third countries in several other currencies. No matter how sophisticated the contractor is in working in foreign situations, the recent history of fluctuations in the U.S. dollar compared to the Euro, the Pound, and several other currencies proves the point that sharp and unpredictable moves can take a big bite out of profits. 6. Political risk. If a contractor is planning to work in London or Japan there is little in the way of political risk. In other countries in Latin America, Africa, and Asia there are multiple political risks that can spell disaster for the contractor. It could be something straight forward like a sudden increase in local taxes or a coup with a new government that decides it has to review all of the “corrupt” contracts that the former government entered into. On the Panama Canal bid, the Bechtel/Taisei/Mitsubishi team made full use of the leverage that the U.S. and Japanese governments could apply in Panama. Numerous meetings were held with the U.S. and Japanese ambassadors to Panama and their staffs. They in turn, along with their counterparts in Washington and Tokyo, did what they cold to influence the Panamanian government. Wikileaks published at least six cables from the U.S. ambassador in Panama to the Departments of State, Commerce, Treasury, and Transportation as well as the CIA and other embassies. 7. Acceptance testing risk. The seriousness of this risk is specific to a project but it can be a very real risk when the customer is a foreign entity, including a foreign government. In countries with weak legal systems the customer can arbitrarily reject testing and use the rejection as an excuse for applying LD’s or delaying payments or forcing the contractor to accept price reductions. How can the Surety evaluate this? 8. Logistics and customs risk. Large foreign contracts by their nature mean that the contractor will have to ship large quantities of critical materials and equipment long distances on very tight schedules. And when the material arrives in country the contractor still has to clear it through customs, and customs may not always be cooperative and honest. The author has experience in situations where customs has held materials for months before finally clearing it after suitable payments were made. Can the Surety do anything to protect itself in this situation? We have so far discussed a large, high profile international project that included some of the largest contractors and engineers in the world and involved multiple significant risks to the contractor. However there are also smaller and less complex foreign jobs that require performance and payment bonds and many, if not all, of the same problems and risks apply. We will now look at some of the legal risks that the surety faces in the international market. VI. AN OVERVIEW OF INTERNATIONAL SURETY – LEGAL AND UNDERWRITING International contract surety includes a wide variety of project types and scopes. Some projects, such as the Panama Canal, are huge, incredibly sophisticated undertakings. Other projects that sureties may write may be technically similar to work bonded in the North American market. However, even on those apparently more “typical” projects, international work imposes another layer of risk analysis and complexity for the surety. The most important thing to remember is that international surety projects are not simply North American projects “transplanted” to another location. The contract scopes and structures may be different. The organization of the principal/ contractor and of the obligee may be much different and more complex than typically seen in North America. The distinction between “public” and “private” work may be much grayer, because many countries have governmental entities which support or guarantee private companies or which contract private projects. The bond forms may contain terms unique to the jurisdiction, or may not contain terms that we are accustomed to seeing. The surety’s rights and remedies may be dramatically different and more limited, and the role and rights of a project lender or financing organization may be equal to, if not superior to, the surety. Indemnity rights may be extremely limited and costly to pursue. Judgments may be difficult to enforce in another country. Therefore, international surety bonds require careful consideration of their unique features in order to properly evaluate and underwrite the risk. Contract development International contracts may have a wide scope of variation. Mammoth international contracts are likely to have extremely detailed and well-developed terms which are negotiated between the parties. At the other end of the spectrum, some international contracts may be much less defined than contracts we are usually accustomed to seeing. The relationships may be much looser, and some arrangements may be memorialized by a short letter and then “working it out” as the project goes along. Courts may look much more at the “intent of the parties” to fill in gaps, and may disregard or rewrite terms or concepts that are deemed unacceptable in the jurisdiction. The contract review and negotiation process may cross language, cultural and political barriers. For instance, some concepts, such as the contractor’s assignment of rights to the surety, may be virtually unknown and undeveloped in the local law. Others, such as “indemnity” or “penal sum” may be known by other names or those terms may mean something totally different in that country’s language and industry. The surety should become involved as early on as possible so that critical issues can be identified and addressed. International Surety Bonds a. Performance Bonds International projects may have something called a Performance Bond. A surety should not assume that an international “Performance” Bond is similar to what we envision as a Performance Bond here in North America. There are no standard “international” forms, and the customary forms may vary widely from country to country. Some larger projects may accept standard U.S. Bond forms, such as AIA forms or ConsensusDocs forms. However, most forms will be unique to the jurisdiction (and are unlikely to be in English, a further complication). International performance bonds tend to be shorter and more general. They often lack familiar terms, or may contain terms uncommon to the North American market. For instance, there may not be any notice requirement for default and termination until the owner makes a claim, after the project is complete. A formal termination may not be required to recover under the bond. The owner may have a wide variety of self-help available, and the surety may have very limited influence on the direction taken by the owner after a default occurs. Also in many cases, the surety has more limited remedies after default, particularly for on-demand Performance Bonds discussed below. The bond penal sum may be a percentage of the contract price, rather than 100%. The lower penal sum seems a favorable risk development, and in many cases it is. However, a percentage penal sum also makes it more likely that a surety would incur a full penal sum loss if a claim materializes. The smaller penal sum also might make the surety a “bit” player in the dispute, with very little leverage or control over the process. Further, the contractor still is bound to the owner for all damages awardable under its contract, and the contractor therefore could incur a significant financial loss if put into default. This loss could place the contractor’s other work in jeopardy and lead to surety losses on other bonded projects. b. On-Demand Bonds One common type of Performance Bond in the international market is an On-Demand Performance Bond. These bonds act as financial security, similar to an Irrevocable Letter of Credit. Typically, in markets where On-Demand Bonds are prevalent, sureties compete directly against banks for securing a construction project – sureties by issuing on-demand bonds and banks by issuing Irrevocable Letters of Credit (ILOCs). As a result, bond terms also tend to be very brief and may limit the surety’s obligation to payment of money. This payment may be a pre-established penalty rather than an amount related to the obligee’s actual damages arising from the default. On-Demand Bonds may be “unconditional,” meaning that the obligee’s claim is comprised merely of a demand letter. The surety’s only defense is the form of notice, and even that defense may not be allowed under certain bond forms. Some bond forms expressly require the surety to pay over the principal’s objection and despite the principal’s defenses to the claim. Other On-Demand Bonds are “conditional,” meaning that the obligee’s claim must be accompanied by certain documentation or proof of breach, a notice of default, or some other evidence beyond a bare demand. The surety may assert defenses to the claim, although the defenses are likely much more limited than with a typical Performance Bond. c. Payment Bonds Payment bonds are rooted in lien law developed from the common law tradition. Many countries with different legal systems do not have similar mechanic’s lien concepts, and so do not typically require Payment Bonds. However, as international projects grown in scope and size, North American surety law concepts regarding payment bonds have occasionally been adopted. Payment Bonds will probably become more common in the international market as contract surety becomes more global. d. Indemnity Ramifications One critical legal concept dealing with international surety is the potential impact on the surety’s indemnity rights if the contractor or its parent company are located outside North America. North American style indemnity agreements are very different from those used in other countries. Many indemnity concepts do not transfer well from one legal system to another. It can be challenging to develop and negotiate an appropriate indemnity agreement which provides the surety with the security it needs while also being enforceable and acceptable in the international jurisdiction. To the extent that any “typical” indemnity agreement exists, the type and complexity will vary widely. A wide range exists, from a one-page very basic “indemnity” to a much more sizeable “deed of indemnity” which may contain terms somewhat similar to a loan agreement. True “industry standards” for indemnity are rare. Further, even if an indemnity document is common to the particular jurisdiction for local projects performed by local companies, the document may not give a surety the tools and provisions it needs to protect itself in the more complex international contract surety arena. Here are some typical indemnity provisions which may create concerns for international customers or their sureties: Exoneration/ Place in Funds: Some countries have a well-established concept of exoneration or placing the surety in funds, but other countries may not. As a result, international companies struggle with the idea of being required to post funds with the surety before a “debt” is fully established. Generally, a surety lawyer can educate the customer on the reasons for exoneration and help the customer better understand the requirements of an indemnity agreement. Limitation on amount or time: Many countries may require that an indemnity agreement and/or parental guarantee have some sort of limitation in order to be enforceable in that jurisdiction. For instance, the indemnity agreement may have to state a specific dollar value at which the indemnity obligation is capped. Other countries do not require a cap, but require a specific time limitation be stated in the agreement. Pari-passu and Assignment: In Europe and many other countries, sureties are viewed as substitute bankers of sorts. In those countries, creditors may be required to share in any recovery “pari-passu.” This means creditors get an equal split of any recovery (similar to a very simplistic bankruptcy here in the US, with all creditors in a single class). Unfortunately, paripassu has significant ramifications on two of the surety’s most valuable assets: contract balances and assignment rights. First, a surety should understand what qualifies as “assets” in the applicable country. Many countries view contract balances as an “asset” of the principal which must be divided among creditors, because the applicable surety law does not generally envision true performance obligations. However, as projects grow larger and more complex, obligees may require a performance bond which requires some degree of completion obligation. Under a worst-case scenario, the surety could find itself obligated to bear the entire cost to complete the project, but having to share contract balances with other creditors on a share and share alike basis. Further, a number of countries view any assignment language in the GIA or a parental guarantee as a breach of this pari-passu equality of creditors. Rights or assets cannot be assigned to one creditor (the surety) to the detriment of the other creditors. Therefore, a surety’s assignment rights may be curtailed or voided entirely. A surety attorney should be very careful to understand the applicable law in the country where the contract occurs, and in the country or countries in which the surety may need to exercise its indemnity rights, as well as the implications on bond and contract language and indemnity rights. Enforcement: One significant challenge in any international project or indemnity action is enforcement of the surety’s rights and remedies. A surety writing a bond or taking indemnity in a particular jurisdiction should understand the legal system and differences in contract, bond and indemnity application and interpretation. Otherwise, a surety may find itself faced with unexpected obligations and huge obstacles to enforcing its rights, or even in enforcing and collecting under a judgment against the obligee or its indemnitors. There are a number of legal resources available on the internet, as discussed below. These resources can be very helpful in understanding the political, cultural and legal environment in which you are working. However, local counsel who is knowledgeable in surety law, assuming such can be found, is strongly recommended. Local counsel can guide a North American surety attorney through the process and to draft or at least comment on the agreements pertinent to the contract, bond and indemnity, and assist in addressing these legal challenges. VII. LEGAL AND RISK MANAGEMENT CHALLENGES IN INTERNATIONAL SURETY As the Panama Canal project and the above discussion indicates, International Surety poses a number of unique legal and risk management challenges for the surety. First, a surety attorney has to understand and properly identify the risks that need to be addressed. In order to identify those risks, the attorney must understand the differences between North American contract and surety law and that in the foreign jurisdiction, and then develop a means to contain, control and resolve them. For instance, the surety attorney must identify when the surety’s obligations begin. This may not be clearly defined in the bond, or may not relate to a clear default by the principal. Many jurisdictions do not recognize the concept of “termination” and may look to the surety to cure any breach or default, or simply to pay money when it is demanded. Closely examine the bond language and the terms of breach in the particular contract. Negotiate appropriate default terms and tie those to the surety’s obligation if that can be achieved. Also, closely examine whether and to what degree the surety can assert the defenses of its principal. It is not unusual to see requirements in international bonds which require the surety to act over its principal’s objection. In many countries, this plays out (as a practical matter) as a payment with a reservation of rights. The surety pays or performs, and the principal then litigates against the obligee to recover the cost if the obligee’s claim was wrongful. A surety attorney also should confirm whether the surety has any ability to assert any independent surety defenses. In many countries, these defenses may be extremely limited or may not be recognized at all. A surety attorney should discuss the applicable indemnity issues with its indemnitors and confirm that its indemnitors understand the risks and their unconditional obligation to make the surety whole, regardless of any defenses which the surety or the principal might have. A surety attorney also should include appropriate place in funds language (with a very short trigger), right of settlement, waiver of principal and indemnitor defenses against the surety, and other similar provisions as the surety deems fit, in its indemnity agreements and parental guarantees. A surety attorney should also make sure its indemnitors understand that their liability to the surety is joint and several, if that is the surety’s intent, particularly if a guarantor is involved. Many guarantors will expect the surety first to seek recovery against the principal or the front-line indemnitors first before the surety can make demand against the guarantor. In these instances, it is critical to negotiate clear and very limited timeframes and conditions before the guarantor is required to make the surety whole. These contract and indemnity challenges may become even more complex if multiple jurisdictions and venues are involved. For instance, a contractor may be from the United States, its parent company and indemnitor may be in Europe or Asia, and the project may be in Latin America. Further, the assets may be in several other countries. This level of complexity is becoming more and more commonplace, and it is even more essential to investigate and understand how the various legal issues and concepts will “flow” through the multiple locations, and the path through which a surety would be required to pursue indemnity, enforcement and recovery. There may be some jurisdictions in which enforcement and recovery could be difficult, if not impossible. For instance, court systems may be completely unpredictable, unfriendly to North American companies, and disputes could drag out for years. Surety law may be virtually nonexistent and therefore after-the-fact enforcement and recovery unlikely. In these instances, a surety would need to determine whether it is still willing to write the particular risk, and should make alternate arrangements for its protection. This is where local counsel can be invaluable in giving accurate information regarding the difficulties in the particular country so that the risk can be properly underwritten. Indemnity options such as taking collateral up front, obtaining multiple indemnitors (including indemnitors in the US or another “friendly” venue) and strong and quick place in funds language could serve as options for difficult risks. On the other hand, a number of jurisdictions have very strong legal systems and well-developed surety law. While the legal concepts and court systems may be structured differently from the US, these jurisdictions may be appropriate and profitable locations for surety work. Also, arbitration is often a very viable option, even if the courts are not. Investigate the resources and determine what provisions would work for a particular situation. It is also recommended to have all documents state that they are to be written and interpreted in a stated language, such as the English language, and that any litigation, mediation or arbitration will be conducted in that language. Further, even the most basic bond and contract terms should be clearly defined. Some countries use different terms, or even conflicting terms, compared to North American surety law. An obligee in one jurisdiction may be known as the “principal” or the “beneficiary” in another. “Indemnity” may be known as “reimbursement” or a “guaranty.” Even more confusing, some standard North American terms may have a completely different meaning in another country. For instance, in the United States, “penal sum” or “bond penalty” is defined as the amount of the bond. However, in many countries, these terms refer to a true and fixed penalty assessed if the contractor breaches the contract. It is critical to define the terms, based on the applicable law and usage, so that the documents can be correctly drafted and interpreted. Also, execution of documents will likely follow different procedures than in North America. For instance, notaries may or may not exist in the country. Documents may need to be apostilled or otherwise certified by a governmental agency, in order to verify the signatures. The country may have a corporation code under which the document can be sealed rather than signed, or requiring only specific authorized and registered persons to sign the document in order for it to be enforceable. A surety attorney should confirm the legal requirements for execution, and may need to consider having a local attorney review the executed documents, particularly any indemnity agreements or guarantees, and provide a legal opinion that the documents were properly executed. In addition to contract and indemnity issues, a surety will need to examine co-surety and/or reinsurance requirements. Many large projects will require co-sureties, and that relationship will have implications on the contract and indemnity issues. In addition, many North American sureties are not licensed to write bonds directly in a number of foreign countries. Therefore, the North American company will need a “fronting” surety who will issue the bonds on their behalf, with the North American company serving as a “reinsurer” to the fronting surety. Usually this fronting surety will require its own indemnity agreement with the principal and indemnitors (sometimes putting the fronting surety in a superior position to the reinsuring surety). The fronting surety can often guide the reinsuring surety on licensure issues and compliance with local laws, but generally independent counsel is recommended. The surety should understand the interaction between foreign insurance law and financial regulations in the country. As stated above, in many countries, sureties and lenders are relatively direct competitors in offering security for construction projects. The particular country may treat a bond much more like an Irrevocable Letter of Credit, and therefore treat a surety much more like a lender. It may be important to understand the country’s applicable financial regulations and to confirm that those regulations do not conflict with a surety’s internal policies or domestic regulatory requirements. Also, many countries have strict privacy laws which may complicate or conflict with a company’s normal document handling and retention standards. Again, a surety attorney should consider these issues in any risk management evaluation. It is important to know where to start your international legal research. The internet is a good starting point, and there are a number of free resources for international legal research. The following sites are good places for basic information: For legal, cultural and political research: Globalex, NYU’s Foreign Law Research tool http://www.nyulawglobal.org/globalex/Foreign_Law_Research1.htm World Legal Information Institute - http://www.worldlii.org/ Juriglobe, University of Ottowa Foreign Law database - http://www.juriglobe.ca/eng/index.php Washburn University School of Law, by country and/or region http://www.washlaw.edu/forint/alpha/n/northamerica.html Federal Judicial Center, Primer on the Civil Law System http://www.fjc.gov/public/pdf.nsf/lookup/CivilLaw.pdf/$file/CivilLaw.pdf Library of Congress, Guide to International Law Online http://www.loc.gov/law/help/guide/international.php Library of Congress, Global Legal Information Network - http://www.glin.gov/search.action The World Bank Group, Doing Business Law Library - http://www.doingbusiness.org/law-library InterNet Bankruptcy Library, International Bankruptcy and Insolvency Laws http://bankrupt.com/lbr/internationalbankruptcyrules.html Society of Construction Law, mostly UK but may have broader applicability http://www.scl.org.uk/papers The Economist - http://www.economist.com/countries For law firms working in various countries: Consulegis - http://www.consulegis.com/ Lexmundi - http://www.lexmundi.com/lexmundi/default.asp International Bar Association - http://www.ibanet.org/Default.aspx The Legal 500 - http://www.legal500.com/ Lastly, a surety should understand the implications of cultural, language and political issues on legal analysis. Cultural and political factors can enhance an already strong relationship, or conversely can derail the project completely. Language barriers and conflicting usage or definitions of seemingly identical terms can create miscommunications which could disrupt even the most strongly worded contracts. All of these issues can be managed and mitigated with proper research and planning during the underwriting process. VIII. CLAIMS CHALLENGES IN INTERNATIONAL SURETY Claims challenges also should be anticipated and investigated during the underwriting process. A surety attorney should understand whether a claims handler must be licensed in the jurisdiction, and what requirements might be applicable. A number of countries and territories require that claims handlers be located in-country and have specific licensure requirements. This is an expense and condition that should be anticipated up front. Further, the investigation process may be affected. Bonds with simple terms and few defenses available may only require review of the notice and limited documentation. On the other hand, bonds related to large, complex projects with multiple parties may require a team of specialists and investigators. Again, these needs should be anticipated up front, so that a surety is prepared to respond promptly if a claim arises. Notice of a claim: The bond terms and/or local law and practice will dictate notice requirements. Frequently the requirements are incredibly brief. Usually, notice will be served on an in-country agent or underwriter. The bond should indicate an address for notice, if possible. The surety then should put in place a process for the notice to be received and transmitted to the claims handler in a timely fashion. Notice will likely be given in the country’s language, which means it must be translated. If supporting documents are desired, the surety should be prepared to ask for them quickly, as timeframes for response to claims are usually very short. Performance Bond issues: As stated above, many international bonds do not envision formal completion by a surety. The performance requirement may be payment of a set sum, or reimbursement of the obligee’s damages. Often investigation time is very limited, and defenses are even more limited. A surety attorney should understand what procedures are required to respond to a performance claim, and confirm the legal requirements and ramifications, so that the surety can respond appropriately. If formal completion is an option under the bond, this completion will likely raise a number of additional issues compared to a North American project. Local consultants, or at least knowledgeable consultants with international experience, will probably be required. Most of the documentation will not be in English and will require translation. There are likely to be a number of entities involved, including governmental entities, even on private projects. Therefore, a surety may find itself dealing with a wide group of people, all having some input into what will be required from the surety. You may also find that negotiation becomes a much more critical process, and that give and take is expected in order to resolve any dispute. Finding the proper balance between social and business expectations and legal obligations may be a delicate and challenging task. Even physically making the payment can be challenging. Information must be collected, verified and transmitted prior to payment. In the case of a United States surety, Federal law, such as The Patriot Act, may impose regulatory requirements and oversight of any payments made. If the payment is to be made internationally, wire transfers may be used, particularly if the country’s banking system is unstable or limited. Also, determining the proper currency for payment may be an issue, and may affect the timing and method of payment. Payment Bond issues: Payment Bonds are not as common in the international market as Performance Bonds. However, when a Payment Bond is issued, it may create unexpected challenges. Notice and language barriers may be significant. Documentation may be difficult to understand or non-existent. Many countries may not have common procedures for periodic payments and releases. In fact, in certain countries, payment of subcontractors and suppliers is typically made in cash. Therefore, merely determining the contract amount and current contract balance may be an effort. Physically making any required payment may be another effort, as discussed above. However, these issues can usually be resolved with proper research and local assistance. Exoneration and Indemnity issues: A surety should consider exoneration and indemnity issues as part of the underwriting process. However, even the best plans may prove difficult to execute if a dispute arises. Receiving adequate collateral up front places the surety in a much stronger position, and should be carefully considered, particularly for international customers. Strong indemnity agreements, appropriately drafted for the applicable jurisdictions, timely and detailed periodic financial reporting, and close oversight of the account and the project are critical. If a dispute with your indemnitors arises, local counsel will likely be required to guide you through the resolution process. That process may include litigation or arbitration. A surety attorney should understand the laws applicable in the jurisdiction for litigation, arbitration and for enforcement of judgments. These may include legal sources not commonly considered in the domestic market, such as international treaties: Arbitration Treaties: The United Nations Convention on the Recognition and Enforcement of Foreign Arbitral Awards (the “New York Convention”), 1958. http://www.uncitral.org/uncitral/en/uncitral_texts/arbitration/NYConvention.html The Inter-American Convention on International Commercial Arbitration, 1975. http://www.adr.org/sp.asp?id=31620 Enforcement of Judgments: Hague Convention #16: Convention of 1 February 1971 on the Recognition and Enforcement of Foreign Judgments in Civil and Commercial Matters, entered into force 20-VIII-1979 (only five countries have actually ratified this treaty as of late 2010 – the US is not one of the ratifying countries. However, the principles embodied in this Hague treaty are a good starting point for seeking to enforce a US judgment in any foreign country). http://www.hcch.net/index_en.php?act=conventions.text&cid=78 Related Treaties: Hague Convention #12: Convention of 5 October 1961 Abolishing the Requirement of Legalisation for Foreign Public Documents, entered into force 1965; (a very large number of countries have ratified this treaty, including the United States). http://www.hcch.net/index_en.php?act=conventions.text&cid=41 Hague Convention #37: Convention of 30 June 2005 on Choice of Court Agreements, not yet entered into force. The US, Mexico and the European Union have ratified this Convention, and so it would serve as guidance for any venue provisions in International contracts, at least with respect to these countries, even though the Convention itself is not yet effective. http://www.hcch.net/index_en.php?act=conventions.text&cid=98 As the construction market becomes more global, international surety provides exciting and challenging opportunities for North American sureties. The applicable laws and the cultural, political and financial issues will often direct, or at least strongly influence, a surety’s course of action, and the eventual outcome of a claim. Sureties can use all these issues as tools to evaluate the risks and challenges and lay the foundation for a successful and profitable venture into this global market.
© Copyright 2026 Paperzz