Newsletter #9 FISH CREEK July 27, 2015 ESTES PARK, LARIMER COUNTY, COLORADO Public Infrastructure Project Schedule for Utility Work Utility repairs are wrapping up at the last few construction sites along Fish Creek Road. The contractor, KRS Swerdfeger, has had four crews working against difficult conditions to meet an aggressive schedule. Double the average precipitation in May and exceptionally high stream flow in Fish Creek through all of June caused several schedule setbacks. Substantial completion of utility work is currently scheduled for the middle of September, weather permitting, including utility installation and restoration of portions of the road that were removed to facilitate construction. A few weeks of clean-up and landscaping along the corridor will take place in late September and early October, but this work should be less obtrusive and impacts to traffic and other activities along Fish Creek Road are expected to be minimal. When will construction begin on Phase 2 – Road and Trail? The original Phase 2 construction schedule assumed that no additional right-of-way would be required to construct the roads and trails. After a careful public design process, it was determined that right-of-way acquisition is required in order to design the safest and most resilient road and trail system within the budget. There will be no full parcels acquired and no displacements of residences or businesses as a result of right-of-way acquisition; however, because of federal funding, there is a comprehensive federal process that must be followed. This process has mandated timeframes for specific tasks such as notice of intent of the proposed acquisition, the valuation process to determine the value of the proposed acquisition area, and the offer to purchase and negotiate on the parcel. This process has pushed groundbreaking on the road and trail from late 2015 into the spring of 2016. Have the environmental studies been completed? Yes, the NEPA document, which is a Programmatic Environmental Assessment (PEA), has been completed. The PEA provides an assessment of the expected environmental impacts associated with a project. The assessment concluded with a finding of “no significant impact” to environmental resources in the study area. Once FHWA signs off on the PEA, right of way acquisition will commence. This activity is anticipated to take up to____ months and will need to be complete before construction of Phase 2 Roads and Trails can commence. What elements are included in Phase 2 of the Fish Creek Public Infrastructure Project? The project is limited to addressing areas where flooding impacted existing infrastructure, including roads, trails, and utilities. The project also includes upgrades to protect against future floods. Project limits, in some instances, extend beyond the immediate damage sites. For example, installation of box culverts often results in additional improvements, such as raising the road profile and paving along local access roads so as to accommodate the culvert. Will the creek be restored as part of this infrastructure project? Yes and no. As dictated by funding sources, the Fish Creek Public Infrastructure Project is not a creek or habitat restoration project, but in certain locations resiliency improvements to the creek have been included because they provide additional protection to road and trail infrastructure. This occurs only in two locations. One Fish Creek Public Infrastructure Project location is south of Scott Avenue, where vegetated terraces are being installed. Vegetated terraces create floodplain capacity, aid in habitat restoration, and protect the wastewater utilities located in the area. Vegetated terraces will also be installed along the trail near the golf course. Improvements to over 1,000 feet of the creek helped reduce the need for retaining walls while increasing protection for both Fish Creek Road and the trail. And that is why the answer is both yes and no. The project will result in over 2,000 linear feet of work within the creek, but that still leaves miles of Fish Creek in need of additional restoration. How will additional creek restoration occur? Additional restoration efforts will be independent of the public infrastructure project. The Fish Creek Coalition of residents generated a watershed-level master plan for Fish Creek. The plan provides a long-term implementable vision for recovery and restoration; creates a strategy to reduce the impact of future flooding on the Estes Park community and its economy; develops strategies to restore the river’s ecological health and resiliency; and makes recommendations concerning habitat restoration, and river channelization, relocation, and/or realignment. The master plan does not include detailed design or implementable construction documents for specific May 8, 2015 recovery or restoration projects along the corridor. Therefore, a funding source for such work would need to be identified and each project would require property owner involvement and permission, as well as further study. The Fish Creek Coalition has recently merged with other Estes Valley watershed stakeholders to form the Estes Valley Watershed Coalition. If you’re interested in being involved in further work related to the Fish Creek watershed, get involved by calling...(we can ask Tina/Will for this contact information during review). As a reminder, materials from past public involvement meetings and construction impacts to residents, business owners, and visitors are posted and updated on the website every week: http://fishcreekcorridorrepair.com/ Stay Involved and Provide Input See the project website for additional information, www.fishcreekcorridorrepair.com, where you can leave comments and find contact information for project team members should you have additional questions.
© Copyright 2026 Paperzz