MARGUERITE AQUATICS COMPLEX

Marguerite Aquatics Complex Renovation
Monthly Report
MARGUERITE
AQUATICS COMPLEX
MONTHLY REPORT
February/March 2017
Page 1 of 7
Marguerite Aquatics Complex Renovation
Monthly Report
PROJECT SUMMARY

Construct One Corp was able to finally drill the 12 caissons for the dive tower. The caissons
are 18” in Diameter and are 30 feet deep in the ground. A 48” concrete pile cap was
poured over the 12 caissons on Saturday 3- 4-17

Construct One Corp discovered that the piping underneath the pool shells in the 50
meter pool are undersized and inconsistent with the anticipated mechanical design. The
City revised the approved Health Department Plans, resubmitted them and they have
been re-approved by the Health Department. This piping change will require the concrete
pool shell to be cut and the actual piping upsized to meet the code. City is waiting for a
revised estimate for this increase effort from Construct One Corp.

The Contractor stood the first 23 feet of the Dive Tower wood forms. The forming shown
in the images is the back wall and the 2 side walls. The forming details shown are placed
on the inside of the form and then once approved will be enclosed and concrete will be
placed inside the forms.

California Commercial Pools is continuing to place the extensive conduits and plumbing
runs to the 50 meter pool and the Activity pool in preparation for the new utility runs to
each of the 3 pools.

The City is in the process of getting the delayed submittals through the City Building
Department for the Shade Structures, Bleachers and the Musco activity lighting prior to
the contractor installation.

The City/Contractor isolated the water source between the Aquatics Facility and the
Tennis Pavilion. Previously the centers were serviced from the same water meter.

The project to date has experienced the following calendar day delays:
Rain Days
Hazardous Mitigation Days
Total Days for Delay
30 days
30 days
60 days
Page 2 of 7
Marguerite Aquatics Complex Renovation
Monthly Report
BUDGET UPDATE
Total Estimated Construction Budget
(Budget Amendment #1 1-10-17)
Energy Efficiency Additions
$10,218,051
Total Budget
$10,433,221.40
$215,170.40
Expenses
Aquatics Design Group
Change Order #2
Griffin Structures (PM)
Change Order #1
Petra Geotechnical
GMU (Soils)
RJM Design Group
LSA Associates
Permits and Plan Check
SMWD
OC Health
Plan Check and Insp.
State Water Resource Permit
Miscellaneous
Advertising
Printing
Tuff Shed Design
Tuff Shed Buildings
Misc. Expenses
Total
$629,000.00
$144,650.00
$75,175.00
$299,900.00
$9,146.00
$55,560.00
$29,876.00
$1,778.00
$100.00
$1,932.00
$28,000.00
$575.00
$81.00
$8,087.53
$6,750.00
$158,391.00
$570.33
$1,449,667.33
Construct One (GC)
(Original Contract)
Cont. Amend. #1
$8,568,731.00
$215,170.40
Total Construct One
$8,783,901.40
Page 3 of 7
$10,433,221.40
($1,449,667.33)
($8,783,901.40)
Marguerite Aquatics Complex Renovation
Monthly Report
Hazardous Mitigation
Castlerock Environmental Inc.
(Original)
Cont. Amend#1
Cont. Amend#2
Cont. Amend#3
$47,740.00
$19,386.00
$14,934.00
$12,727.00
Total Castlerock Enviro.
$94,787.00
H2 Environmental Consulting Services Inc.
(Original)
Cont. Amend#1
$4,900.00
$2,500.00
Total H2 Environmental
Consulting Service
$7,400.00
Total Remaining Budget
($94,787.00)
($7,400.00)
$97,465.67
KEY DATES
A schedule has been prepared and attached to the report. The schedule was prepared by Griffin
Structures as the Project Managers for the team. The Design Team met and all agreed to the dates.
-
50% Construction Documents due
Prequalification’s Questionnaire Due
Prequalification Questionnaire Legal Review
Issuance of Prequalification Questionnaire
Prequalification Submission Deadline
Submission of Construction Documents for Plan Check
Anticipated Agency review completion
Anticipated Council Meeting for Approval to Bid
Bid Opening conducted 9-9-2016
Council Meeting to Award Contract 10-12-2016
Anticipated Construction Start
Notice to proceed set for mid-November
Anticipated demolition of the dive tower
Removal of the Transite Pipe around the Pool Decks
Removal of the Transite pipe below deck on 50 M
Drilled the 12 Caissons
Poured the 48” Concrete pile cap on the 12 caissons
Installed the first section of the Dive Tower forms
Page 4 of 7
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Early November
Completed
Completed
Completed
February 15th
February 12th-23rd
March 4th 2017
March 8th, 2017
Marguerite Aquatics Complex Renovation
Monthly Report
PHOTOS AND RENDERINGS
Drilling of the Caissons
Drilling of the Caissons
Placing rebar in the pile cap
Placing rebar in the pile cap
Page 5 of 7
Marguerite Aquatics Complex Renovation
Monthly Report
48” Concrete pile cap poured waiting
For the Dive Tower Forms
Conduit Runs under the pool deck
Dive Tower Forms first 23’
Interior of First level of Dive
Tower forms
Page 6 of 7
Marguerite Aquatics Complex Renovation
Monthly Report
Interior of the First level of the
Dive Tower forms
Page 7 of 7