I D 103.62: Ap 5/3x/97/ -* tv INFORMATION PAPER FOR APPLEGATE LAKE, A PART OF THE ROGUE RIVER BASIN PROJECT Prepared by PORTLAND DISTRICT, CORPS OF ENGINEERS Updated 15 October 1974 INTRODUCTION Rogue Basin Project was authorized by Congress in 1962: Lost Creek is under construction and will be available for flood control about December 1975; Elk Creek received construction funds in 1971, and is expected to be ready for flood control in 1978. Preconstruction planning on Applegate has been completed, funds for land acquisition were allocated in March 1974, and funds for continued land acquisition were appropriated by Congress for the present fiscal year (FY 1975) but allocation of those funds has not yet been made. The Rogue Basin Project was developed under comprehensive planning procedures for control, conservation, and the best use of the natural resources of the basin. Planning for the project has been a long, continued, cooperative, multiagency public endeavor. The following pages provide information for understanding the effort that has gone into the Rogue Basin Project, with particular attention to Applegate. BACKGROUND ON THE ROGUE BASIN PROJECT In 1935 (PL 74-183) and 1936 (1936 Flood Control Act), because of serious flood damages that had occurred and again in 1958 (1958 Flood Control Act), because of flooding again and other water related problems, Congress authorized and directed the Corps of Engineers to make studies of Rogue River and tributaries for flood control and allied purposes. A limited study was made prior to World War II, under the two early authorizations. After World War II the Bureau of Reclamation, under the 1902 Reclamation Act, began studies to investigate for possible irrigation development. The Corps made no studies while the Bureau's plan was under investigation. That development had planned a dam at a site on upper Rogue River about 9 miles downstream from present Lost Creek site. The Bureau's plan met with opposition from local and nationwide sportsmen's and conservationist groups, including Izaak Walton League of America and National Wildlife Federation and locally organized Preserve the Rogue Associattmrq:The dam was opposed because it was anticipated that about one-thp4"01f? the spring chinook run would be lost. As a consequence, no project wals authorized. 5OMMN OREGON SATE COLLEGE LIBRARY' WSHLAND, OREGON 97520 f I Two major and several lesser floods occurred after the completion of the Bureau's study. The first major flood was December 1955, and the second flood was in December 1964. As a follow-up to the 1955 floods, Congress: (1) sent an interim committee to look at flood damaged areas on the West Coast; (2) held a joint committee hearing in Medford to hear local views on flood damages, project potentials, the fishery resource, etc.; and (3) appropriated funds for resumption of studies by the Corps in FY 1957. Immediately following the 1955 flood, local people in Jackson and Josephine Counties (upper and lower valley areas, respectively) organized the Rogue Basin Flood Control and Water Resources Association (RBFC&WRA) to represent the people of the basin. The Association, supported by Jackson and Josephine Counties, represented almost all areas, groups, and organizations in the basin, including sportsmen's groups. The Corps held a public hearing in Grants Pass on 15 November 1956. The emphasis of testimony was on: Prevention of flood damages, with associated irrigation, power generation, and recreation benefits; however, it was emphasized that any flood control plan detrimental to the fishery resource would be unacceptable, both locally and by Federal and State fishery agencies. After our hearing, studies were made on all available alternatives to meet flood control and other water resource needs. Sites that would inundate significant anadromous spawning and rearing areas were not considered. About 36 upstream storage sites, as well as local flood protection works in damage areas were investigated. By 1958, studies showed that no more than three, or perhaps only one, storage project might be economically justifiable on the basis of benefits then available. The storage projects were Lost Creek on Rogue River and Elk Creek and Applegate. It was apparent to the Corps and the fishery agencies that any storage project having just flood control, irrigation, power generation, and recreation would be detrimental to the fishery and our laws did not allow any benefits for the fishery. On that basis, no alternative plan investigated up to 1958 would be both economically justified and assured of local and agency support; however, in August of 1958, Congress adopted new legislation which offered an opportunity to resolve the problem. The Revised Fish and Wildlife Coordination Act, adopted 12 August 1958, provided Federal recognition of fish and wildlife enhancement as a primary purpose for Federal water resource projects. It was decided to reopen project studies with fishery enhancement as one of the primary project purposes. A specific interagency team was formed to cooperate in the Rogue Basin study and to work with RBFC&WRA and any other interested parties. Team membership, under Corps' coordination, included Oregon State Water Resources Board, Fish Commission of Oregon, Oregon 2 S5U-1 RUR" 'TIAT COrCE.E Ol~hy ASHLN - OREGON 97520 State Game Commission, Bureau of Sport Fisheries and Wildlife, and other Federal and State agencies as appropriate. To properly evaluate fishery problems and needs, it was necessary to detail and document the extent and specific nature of the water temperature problem. For that purpose, the fishery agencies and local interests installed a system of about 25 recording thermographs, in Rogue River and tributaries from Laurelhurst Bridge (river mile 165) to Marial (river mile 52). Also, with local assistance, the fishery agencies investigated the location of spawning areas, potential spawning gravels, and related fishery problems. As the cooperative study progressed, local meetings arranged by or through RBFC&WRA were held by the interagency team to present progress reports on their findings. About 22 meetings were held, usually in consecutive sessions from the upper Rogue (Shady Cove area) to Grants Pass or Gold Beach starting in November 1956 up to the final public hearing in September 1961. Also, radio and television question-and-answer sessions were held prior to the public hearing. On the basis of study findings and the record of the public hearing of 15 September 1961, the Corps prepared a report recommending authorization of a Rogue Basin Project including Lost Creek, Elk Creek, and Applegate Dams. Recommendation was for the primary project purposes of flood control, irrigation, power generation, fish and wildlife enhancement, recreation, water supply, and water quality control. With the active support of the Izaak Walton League of America (IWLA) and of the National Wildlife Federation (NWLF) as well as of RBFC&WRA and the Oregon delegation, the Congress, in the 1962 Flood Control Act, authorized the Rogue Basin Project. With continued support from IWLA, NWLF, and RBFC&WRA, the Congress appropriated detailed planning funds for the project and start-of-construction funds (1967) for Lost Creek and (1971) for Elk Creek, and land acquisition funds (1973) for Applegate. Detailed planning and design have been accomplished and construction is well underway in continuing coordination and cooperation between and among the interagency team and local people as represented by RBFC&WRA and the Jackson County Chapter, IWLA. In addition to the 22 meetings during the preauthorization period noted above, the Corps participated in more than 50 local meetings (dealing with the Rogue Basin Project) since that period. Examples of recent meetings particularly concerned with Applegate are: (1) League of Women Voters in Medford in April 1973; (2) an informational meeting held by Senator Bob Packwood of Oregon in Medford in August 1973; and (3) Corps' meeting with Applegate landowners at Upper Applegate Grange in August 1974. Changes resulting from detailed planning and design have been only minor detail; the basic concepts and functions, developed as outlined have been adhered to in all respects. 0 Docs-U.S. D 13.62:Ap 5/3x/974 Information ate Lake a 3 5138 (00000312 APPLEGATE BASIN Applegate Basin begins in the Siskiyou Range in northern California at an elevation of about 7,400 feet, and flows north and west 58 miles to its confluence with Rogue River. The total Applegate drainage basin is 768 square miles. The climate of the drainage area is dominated by maritime influences which contribute to mild, wet winters and warm, dry summers. Normal annual precipitation above the damsite is 45 inches, ranging from about 30 inches at the damsite to nea~rly 60 inches in the headwaters. Temperatures are generally such that a large portion of the winter precipitation at high levels occurs as snow, with rain predominating at low elevations. Normally about 75 percent of the annual precipitation occurs during the November to March period. By contrast, less than 2 percent of the annual precipitation occurs during the July-August period. The streamflow regimen is similar to the precipitation pattern. Low flows prevail from July through September, the period of low precipitation. Streams respond rapidly to the many storms that occur from November to April. Runoff in May and June is moderate and results from melting snow at the higher elevations. Average annual runoff at the damsite is about 317,000 acre-feet. Discharges have ranged from a minimum of 13 c.f.s. to a peak of 29,000 c.f.s. at the damsite. Floods on Applegate River are flashy in character and may occur at any time between November and March. They are primarily the result of heavy rains augmented with snowmelt runoff. After the ground becomes saturated, runoff from heavy rains occurs almost immediately and surface losses are small. Water-shortage problems exist in the Applegate River Basin. Stored water is in great-demand for conservation uses. Irrigation water rights filed for natural flows total 356 c.f.s., which is considerably greater than the summer flow of the river. The natural, low summer flows are depleted by the diversion for irrigation and other purposes. This leads to increased warming of the stream which is harmful to fish. The temperature of the water in the Applegate River is satisfactory for the rearing of fish except during the low-flow months. During the winter, the water temperature is generally below 40° F. In July and August, the maximum daily water temperature at times exceed 800 F. When water temperatures above 70° F. are experienced, fish life is seriously affected. Applegate River and its tributaries support a fish population including fall chinook salmon, coho salmon, steelhead, resident rainbow and cutthroat trout. To support the sport fishery, legal sized trout are planted in the stream each year. There is no spring chinook run. 4 There is a run of fall chinook salmon that use the lower Applegate River. Low flows prevent migration and good spawning utilization in some years. Floodflows frequently cause losses to fall chinook embryos in the gravel. PROJECT FUNCTIONS Flood Control. - Applegate Lake will be operated to regulate the river downstream from the damsite to keep it within its banks to the maximum extent possible. Whenever a flood appears likely and it is expected to exceed bankfull stage, the project discharge will be reduced. It will not always be possible to obtain a high degree of regulation in the lower reaches, as only about half of the drainage area above the town of Applegate is upstream of the dam. Therefore, Applegate project will be capable of reducing most flood peak discharges at Applegate by about 50 to 60 percent. Project releases during a flood may be reduced to a minimum of 50 c.f.s. to insure maximum effectiveness of the project to control downstream flooding. As an example, the maximum discharge, in c.f.s., from Applegate Dam (with 65,000 acre-feet storage) for the following floods would be: (Drainage Area 223 Sq. Mi.) Natural Regulated 1955 20,300 4,600 1964 1974 29,000 27,900 11,000 10,000 Maximum flow in the river, in c.f.s., at the town of Applegate would be: (Drainage Area 483 Sq. Mi.) Natural Regulated 1955 1964 35,700 45,700 16,500 1974 51,500 27,400 23,000 The flood (stage reduction) would be reduced from 4 feet to 6 feet at Applegate for floods of record (1890, 1955, 1964, and 1974). A major environmental gain from flood control will be a decrease in erosion and sedimentation of streambanks and bottom lands and will also reduce losses of fish eggs in stream gravels. 5 Fish and Wildlife. Fishery enhancement. - A major function to be served by Applegate Lake will be flow augmentation during the low-water season, for fishery enhancement. Cooler river temperatures and increased flows will yield a substantial fishery benefit. Special temperature studies indicate the feasibility of such a project function. Desirable minimum releases and downstream water requirements that are proposed for the project for fishery enhancement are shown in the following tabulation. Minimum Releases Month January February March April May June July August September October November December Minimum natural flows at Copper, c.f.s. 34 86 192 230 117 61 30 13 13 19 29 42 Release at dam, c.f.s. Flows, Little Applegate to Williams Creek, c.f.s. Flows from Williams Creek to mouth, c.f.s. 100 100 170 170 170 200 230 200 200/130 130 100 100 200 200 265 265 265 265 230 200 200/240 240 240 200 300 300 340 340 360 360 120 120 120 360 360 300 Water shortages for fishery enhancement averaged 12 percent for the 37 years studied. The specific years in which shortages occurred were 1929, 1930, 1931, 1934, 1936, 1939, 1944, 1949, 1955, and 1959. Fishery benefits were adjusted to reflect the shortages experienced. Fishery flow protection. - Flows released for fishery enhancement will remain in the river from Applegate Dam to the Pacific Ocean. These releases will be protected from diversion for other uses. Protection will be provided under the Federal Act which authorized the projects and by programs adopted by Oregon State Water Resources Board. The Fish Commission of Oregon and Oregon Wildlife Commission have jointly filed water rights for storage of water and for water to be released from conservation storage in the reservoir. Natural flow water rights will have no claim to that water. All water rights are policed by the State Water Master, working for the State Engineer. Those water rights will assure an adequate flow for fishery enhancement. 6 Temperature of water released from storage. - The proposed increase in flows in Applegate River downstream from Applegate Dam will result in benefits to anadromous and resident fish provided adequate temperature control is achieved in the 25-mile reach affected. Studies indicate that such temperature control is possible; although with the limited storage available, optimum water temperatures might not occur in all years. Fish production will be limited by the least flow or highest temperature regimen attained. The following tabulation shows desirable temperature regimen of water that would be released from Applegate storage. Month Temperatures (degrees F.) April May June 55 55 55 July 50 August September October 55 50 55 The above temperatures are the goals. In some short water years, they may not be attained. Nevertheless, in many years the lowwater flows during August and September at Applegate will be more than five times the past observed flows. The improved flow and temperature are the basis for the prediction by the fishery experts that a spring chinook run will be reestablished in the Applegate. Recreation. - The recreation potential of the lake and adjacent land area will be developed and managed for public use by the U.S. Forest Service. Development of 37 recreation sites, totaling 185 acres, will comprise the major recreational development of the area. Other land has potential for limited use, such as hiking and scenic viewing. Presently scheduled for development during the first 10 years of project life are 250 camping units, 200 picnic units, three boat launching areas, four swimming areas, vista points, trails, and various other facilities. A viewpoint will be developed near the damsite for public viewing of construction activities. Future development at new sites and expansion of existing sites will be accomplished if the need and demand arises. Figure 1 shows the pool elevation at the end of recreation season. Water Quality. - Diversion of the Applegate River for irrigation during the summer months leaves the lower reaches below the settlement of Applegate virtually dry or in stagnant pools. This has an adverse effect on recreational use and development and lowers property values of riverfront lands. With increased flows resulting from reservoir withdrawals, attendance in the public and private parks (existing and 7 RIVATE '-4 L44 tow,' 0 Z '200 4000' APPLEGATE RIVER future) along the Applegate, downstream of the dam, is expected to increase. Real estate studies show that the private lands suitable for homesites along this reach of the Applegate River can be increased in value and that these lands would be enhanced with augmented flows from Applegate Lake. Area Redevelopment is based on the value of wage payments to otherwise unemployed local unskilled and semi-skilled laborers who will work on the construction of the project. Also included are wage payments to otherwise unemployed unskilled and semi-skilled laborers who will be engaged in operation and maintenance of the project. Irrigation. - Rainfall deficiency in the valley areas of the Rogue River Basin during the growing season makes a supplemental water supply a necessity for successful crop and orchard production. The U.S. Bureau of Reclamation has indicated that there are 1,300 acres of new lands that can be supplied from the Applegate storage site. At the present time 8,371 acres are being irrigated from natural flows. At some future time, it is anticipated that an irrigation distribution system will be developed by the Bureau of Reclamation. Meanwhile, it is anticipated that a procedure for the furnishing of supplemental water could be worked out between the Bureau of Reclamation, the Applegate Valley Irrigation District, and interested landowners to use the stored water for irrigation purposes. BASIN PLAN OF RESERVOIR OPERATIONS The seasonal climate of the Rogue River Basin is such that joint-use storage is feasible. Major floods occur only during the winter months, at which time storage space will be reserved for flood regulation. Following the major flood season, the storage space will be filled gradually between 1 February and 1 May as the storm activity decreases. The stored water will then be used as required for conservation needs during the summer and early fall. By 15 November the reservoir must be drawn down to provide the maximum space reserved for flood regulation. The reservoir may be drawn below the scheduled flood control pool elevations at any particular time if the conservation situation requires the stored water. There is 10,000 acre-feet of exclusive conservation storage space between minimum flood control pool and minimum conservation pool. The following table shows areas of the pool and exposed ground for the most probable reservoir drawdown. 9 Date Pool elevation Area of pool Ground area exposed acres acres acres acres acres acres Jul Aug Sep Oct Nov Dec 1 1 1 1 1 I 1,987 1,976 1,964 1,948 1,920 1,889 988 910 834 735 535 361 0 78 154 253 453 627 Mar ' 1,925 565 423 acres 1,950 1,970 1,987 750 873 988 238 acres 115 acres 0 acres Apr 1 May 1 Jun 1 The figures on the following page show the reservoir storage and drawdown curve. PROJECT ECONOMIC BENEFITS Flood Damages. - Benefits from flood control consist primarily of reduction of damages attributable to the project. Agricultural damages include: 1. Damages to orchards and various crops such as row crops, hay. and grain, 2. Damages to soils due to leaching, scour, and erosion loss of topsoil, debris overlay, and weed infestation. 3. Damages to farm roads, bridges, fences, and utilities. 4. Damages to farm residences, utility buildings, farm equipment, and machinery. Urban flood damages consist of damages to commercial and industrial structures and contents, business losses, transportation losses, residential damages, damages to roads, streets, bridges, and utilities. As far as possible, damages are based on field appraisals made of actual flood damages following major floods such as those which occurred in 1955, 1964, and 1974. Flood control benefits are: $1,796,800. Fish and Wildlife Enhancement. - Fish and wildlife enhancement benefits consist of reservoir fishing, downstream sport fishing, ocean commercial fish catch, and wildlife hunting. The resources have been evaluated by the Fish and Wildlife Service based on the project providing a reservoir fishing site, minimum flow downstream releases, and low water temperature control. The reservoir fishery day use benefit is based on 10 a Mx 1987 Full Pool >-30,000 Acre-Feet w rc. Port No. / (/#53) 25,000 Acre-Feet VT.C. Port A.2 (/92) -/0,000 Acre-Feet -65,000 Acre-Feet L I in. F C. Pool p/0,000 Acro-Feet 1889 1854 ,990 0 -j I in. Conservation Poo/ 1770 - -/0,000 p 34' 0 4 1' 1 z Acre-Feet 4 I 142'I'- 27,000 Acre -Feet- I w a Acre-Feet (Inactive) -egotion Out/et Invert t _______ 10/0 Acre-Feet j (Dead) 1760L RESERVOIR STORAGE w FIGURE 0 2 4 I- w w T ZUUW . I I I l U. z z 0 I95a0 19401I- 1940 -- _ _5- w -j w .N or,Fno/ Drowdown /#*$- -1910O WTC. Port No. 2 (19/21 el Flood Contro -= -I Roserv Wton I el-l s isa0 Minimum I- -4 - Conservation Pool ----1-- A--tA- 1854 r t - -1-- 1120 1760 - . JAN FEB MAR Reulating IOutle-tI/ie rt (/p77) - -1--- 1--I f-t-APR MAY JUL JUN AUG SEP MONTHLY RESERVOIR LEVELS (MOST PROBABLE POOL ELEVATIONS) FIGURE 11 3 w U- l OCT NOV DEC a value of $2 per fisherman-day with attendance estimated at 25,000 angler-days initially and increasing to 50,000 angler-days in 1.0 years and remaining at that rate for the balance of project life. The downstream fishery benefit is based on an increase in sportsman angler-days due to the project and evaluated at $9 per angler-day for spring and fall chinook and steelhead; and increased angler-days of resident trout fishing evaluated at $5 per angler-day less stocking costs; and increased ocean commercial catch of spring and fall chinook evaluated at $1.10 per pound. The fish and wildlife benefits adjusted to equivalent annual values during project life are: Anadromous sport Anadromous commercial Resident trout Reservoir sport $57,200 298,300 74,400 93,200 $523,100 Total Reservoir Recreation. - The recreation resource to be created by Applegate Lake is based on an annual attendance expected at the various reservoir recreation sites amounting to 220,000 user-days in 3 years, 330,000 in 10 years, 455,000 in 50 years, and increasing to 730,000 in 100 years. Benefits attributable to the general recreation use of the project are based on the unit value of $1.25 per user-day. The U.S. Fish and Wildlife Service has evaluated reservoir fishery user-days and has assigned a value of $2 per angler-day for reservoir fishing. It is anticipated that 20 percent of the general recreation use will be attributable to reservoir fishing. Benefits are: $357,000. Those benefits exclude reservoir fishing which is included in the fish and wildlife enhancement benefits. The U.S. Forest Service is to construct, operate, and maintain these recreation areas. Water Quality. - Diversion of the Applegate River for irrigation during the summer months leaves the lower reaches below the settlement of Applegate virtually dry or in stagnant pools. This has an adverse effect on recreational use and development and depresses property values of riverfront lands. With increased flows resulting from reservoir withdrawals, increased attendance in recreational use could be expected in the existing public and private parks along Applegate River. The total increase in recreational day use attributable to increased flows is estimated at 190,000 at the start of project operation and is expected to increase to 262,000, 300,000, and 350,000 within 25, 50, and 100 years, respectively. Benefits are based on an increase in user-days and an increase in value per user-day from 50¢ to $1.00. Real estate studies show that the private lands suitable for homesites along this reach of the Applegate River are depressed in value and that these lands would be enhanced by about $53,000 with augmented flows from Applegate project. Ownership of these lands is widespread, and in determining benefits 12 it was assumed that the enhancement would take place over a period of some 20 years on a straight line basis. Benefits are as follows: Recreation downstream of the project Enhancement of riverfront lands $330,000 53,000 Total benefits attributable to water quality $383,000 Area Redevelopment Benefits. - These benefits are based on the value of wage payments to otherwise unemployed local unskilled and semi-skilled laborers who will work on the construction of Applegate project. Also included are wage payments to otherwise unemployed unskilled and semiskilled laborers who will be engaged in operation and maintenance of the project. Irrigation. - Preliminary estimates of benefits attributable to the use of Applegate storage for irrigation purposes amounting to $20,600 have been furnished by the U.S. Bureau of Reclamation. These benefits were based on supplying stored water to serve 1,300 acres of new farmlands. Other Benefits. - Project access roads will be utilized in future logging operations which will reduce the cost of movement of harvested timber by $5,900 annually. Other benefits consist of: Reduced cost of timber haul Loss of timber productivity Total $5,900 -500 $5,400 13 COST-BENEFIT SUMMARY (July 1973 base, 100-year life, and 3-1/4 percent) Construction Cost Interest during construction - Federal Net value of lands transferred without cost U.S. F.S. - recreation Initial Future - present worth Investment cost - Federal Non-Federal - recreation Initial Future - present worth Subtotal Total project investment $45,500,000 2,957,500 1,468,300 4,125,000 2,870,000 56,920,800 305,700 133,700 439,400 57,360,200 Annual Cost Federal Interest and amortization Operation and maintenance Replacements Total - Federal Less: nonreimbursable roads Total annual - Federal 1,928,500 334,000 46,600 2,309,100 -69,400 2,239,700 Non-Federal Interest and amortization Operation and maintenance Replacements Total - non-Federal Total annual costs 14,900 65,300 4,700 84,900 2,324,600 Annual Benefits by Project Functions Flood Control Fish and Wildlife Recreation Water Quality Area Redevelopment Irrigation Other Uses Total annual benefits 1,796,800 523,100 357,000 383 ,000 250,000 20,600 5,400 $3,335,900 1.43 to 1 Benefit-cost ratio 14 53.9% of ann. total 15.7% 10.7% 11.5% 7.5% 0.6% 0.1% PERTINENT PROJECT DATA Lands - Project requires 5,495 acres of land, of which 2,810 acres are federally owned and under the control of the Forest Service. Approximately 36 private ownerships. Improvements: 9 farms, 18 residences, and Copper store. General Applegate River Jackson, Oregon Section 25, . ...... T. 40 S., R. 4 W., WM 45.7 River mile above mouth, Applegate River ............ 223 sq. mi. Drainage area ...................................... 29,000 c.f.s. ....... Maximum discharge, observed (22 Dec 64) . Mean annual discharge (1929-1965) . . .... 437 c.f.s. . . ..... 20 c.f.s. Minimum discharge (Sep 1939) Mean annual runoff (1929-1965) ..................... 317,200 acre-feet Stream ......... County, State Dam location ......... . . Storage and Principal Elevations Usable storage (1,987-1,854)...................... Flood control storage (1,987-1,889)............... Conservation storage (1,889-1,854)................ Inactive storage (1,854-1,770).................... Dead storage (1,770-1,760)........................ Total storage (1,987-1,760)....................... 75,000 acre-feet 65,000 acre-feet 10,000 acre-feet 6,990 acre-feet 10 acre-feet 82,000 acre-feet Elevation - maximum (full pool) .................... 1 ,987 feet, m.s.l. Elevation - minimum flood control pool ............. 1 ,889 feet, m.s.l. Elevation - minimum conservation pool .............. 1 ,854 feet, m.s.l. Reservoir 988 360 205 4.6 1 Area - maximum pool (full pool).......... Area - minimum flood control pool........ Area - minimum conservation pool......... Length................................... Width.................................... acres acres acres miles mile Dam Rockfill embankment Type ....................... Height - streambed to crest ...................... Length ....................... Embankment volume ....................... Concrete volume ....................... Elevation - top of dam....................... Elevation - full pool ....................... Q1TWHER 234 feet 1,200 feet 2,720,000 cubic yards 55,000 cubic yards 1,994 feet, m.s.l. 1,987 feet, m.s.l. rC!:CO STATE COGLECr L!ERANYr 1i5LAIO, OfkEGON 97520 Spillway Type . Concrete gravity, gates, ogee section, right bank Crest elevation............................. 1,942 feet Crest length................................ 97 feett Control gates (Tainter)..................... Two - 48'-6" x 48' Design discharge........................... 93,800 c.f.s. * ........... Outlet Works Type....................................... Conduit - size.............................. Conduit - length.............................. Operating Emergency Discharge Discharge slide gates......................... slide gates...................... capacity at minimum flood control capacity at maximum flood control Multiple-use, intake tower, discharge conduits, stilling basin Two - 5' x 10' concrete rectangular 1,000 feet Two - 5' x 7' Two - 5' x 7' 4,200 c.f.s. 5,700 c.f.s. Temperature Control System Number, parts and size...................... Five - 4' x 5.5' Design discharge........................... rectangular 300 c.f.s. Diversion .................................... Fish Facilities ........... Unlined channel with control weir collection The facil ities to stop and collect upstream adult migrants. The facilities consist of a fish barrier weir across downstream end of primary stilling basin, a fish ladder, collection pool, holding pool, sorting facilities, and transfer facility. 16 Response to Questions on Applegate Lake Question: Will there be water quality problems, such as algal blooms in the reservoir? Answer: Algal blooms, or other related problems are not expected. Nourishment of the type usually associated with algal blooms from agricultural or urban wastes will not occur upstream of the reservoir to any significant extent. Annual replacement of almost all stored water will further reduce any problems of that nature. Question: What effect will the temperature of water released from the project have on the downstream fishery? Answer: The increase in downstream flows will provide benefits to anadromous and resident fish. The benefits of $523,100 annually to the fishery are discussed under question on benefits. Question: What steps are being taken to minimize the initial reservoir impact? Answer: The reservoir area will be cleared of fences, buildings, brush, and trees to an elevation 3 feet above maximum pool. Tree stumps will be cut low and parallel to the ground. Stumps will be removed entirely on gently sloping ground in front of recreation areas suitable for swimming or boating activities. Merchantable timber will be salvaged. Other material will be stacked and burned in accordance with then current rules of the governmental agencies with jurisdiction in the area. No disposal by burial or dumping into water or on flood plain lands will be permitted. Cesspools, septic tanks, or other sources of bacterial contamination will be treated with lime and covered with soil. Question: With all the large cuts and fills required for the roads and dam plus the wave action on the banks of the reservoir, won't there be a lot of bank erosion and slides? Answer: Slides and bank erosion will not be a problem. The Applegate Reservoir location is within the Klamath Mountain Geologic Province. The rocks are metamorphics and granitic intrusive types. Rock is frequently exposed on the surface alonq the steep hillsides. The soil cover generally consists of a thin cover of talus and rock fragments with a small percentage of 17 sand and silt fines. No deep deposits of soil or unstable slide areas have been located along the reservoir slopes. Carberry Creek slide is beyond the influence of the reservoir. Road construction will be mostly in rock cuts and granular type soils. Cut and embankment slopes of these materials are stable and erosion resistant. Erosion of reservoir slopes will be quickly arrested due to the shallow depth and rock fragment content of the soil cover. A revetment cover of rock fragments will be self-forming. The silt and sand fines contain little or no colloidal clay and will quickly settle out of suspension in the reservoir. When will the studies be Question: Will the reservoir be turbid? completed? Answer: Non-settling turbidity problems are caused primarily by swelling colloidal clays, usually derived from soft tuffaceous rock of pyroclastic origin. The Geologic and Soil mapping of the Applegate Reservoir and watershed area has not located any areas of pyroclastic origin, tuffaceous sediments, or swelling clay soils with appreciable clay fines. Most of the watershed has a thin, rocky soil cover. Even the major unstable areas such as Carberry Creek slide and Sturgis Fork or Bigelow Creek slide have a small proportion of colloidal clay fines. The Applegate River and all of its major tributaries are flowing on rock which is partially covered with gravel. The Applegate River and its tributaries are normally relatively clear except during high rainfall or when turbidity is caused by other events. A milky appearance during normal flow conditions, typical of streams carrying colloidal clay fines,has not been observed. Mineral identification tests performed on the suspended solids obtained from Applegate and tributary streams during December 1972 high water indicated the suspended sediment either did not contain colloidal clay fines, or if present, it is a minor component. Time-settlement observations of the water samples obtained during these high-water events confirmed that nonsettling colloidal clay are a minor part of the turbidity producing sediments. The geology, soils, and water test data all indicate conditions-that are favorable and that turbidity will not be aggravated by the reservoir or intended long-term beyond 18 flood events. In fact, settlement of silts in the reservoir will appreciably reduce the transport of turbidity downstream. This will be of benefit in trapping the major portion of sediments produced by slide events in the watershed area such as has occurred at Bigelow Creek. Such an event would occur during the winter or spring and although turbidity would occur in the reservoir and downstream releases, the test data indicates the condition would be temporary. We have found that selective release of water from multilevel outlets has an important influence on the storage and downstream release of turbid water. A mathematical simulation model for prediction of turbidities and temperatures in the reservoir and downstream releases has been developed and verified. This model has shown for other projects that selective release from low level outlets can be very beneficial in reducing the storage of turbidity in a reservoir without conflict with downstream temperature control. Due to an unusually dry winter we did not obtain sufficient turbidity data for the Applegate at high flows for use of this model. Except for continued monitoring to obtain data for the model study which will determine the optimum operation for turbidity control consistent with other objectives of the reservoir, our basic turbidity studies are complete. We are confident that the model will indicate that the minor amount of colloidal clay contained in winter floods can be flushed through low level outlets within a week or two following the flood events and that the downstream releases can be controlled to high standards without conflict with downstream temperature control. Question: What irrigation will be provided by Applegate and when? Answer: Irrigation is one of the authorized purposes of Applegate Lake project; however, the Corps of Engineers is authorized only to store the water for irrigation. All other irrigation development is the responsibility of the Bureau of Reclamation. Studies prepared by the Bureau for the Applegate Division identified some 1,300 acres of new land that could be irrigated with water stored in Applegate Lake. They have not, however, been able to justify construction of the irrigation project at this time. Nevertheless, neither the Bureau nor the Corps believe that the irrigation purpose of Applegate should be deauthorized and the water be made available for some other purpose. We will, therefore, continue to plan for storage of water for irrigation in Applegate Reservoir until such time as the use develops or a change in authorization is made in recognition of some other greater need for that portion of stored water. The presently listed project benefit 19 for irrigation is quite small and has very little effect on project economics. Question: Will there be additional water rights available for new lands or for increase to existing water rights? Answer: As discussed above, there will be additional water available for irrigation. However, water from storage cannot be used for irrigation until contracted for with the Bureau of Reclamation. Owners of existing water rights have a right to use water from natural flow in accordance with State of Oregon laws. Those owners do not have a right to use water from storage until contracts are entered into as noted above. Question: Will the dam ruin the pastoral beauty of Applegate Valley? Answer: The pastoral beauty of the Applegate Valley has been undergoing changes since the early 1850's. First the gold miners, then the farmers and ranchers, and more recently by land subdivision with resulting increases in homes, cabins, and people. In addition to those changes there has been logging, consumptive use of water from the river, and changes made by the river during floodflows. Let us consider specifically that portion of the valley that will be within the reservoir and adjacent areas. Approximately 95 percent of the lands within the reservoir area are privately owned and lands publicly owned touch the river along a couple of short stretches only. In other words those lands are not open to the public and they are subject to subdividing and home construction. Lands adjacent to the reservoir are more evenly divided between private and public ownership. The public lands are managed according to multiple use concepts but the private lands are managed by the private owners in their best interests. With Applegate Lake project the reservoir lands and lands adjacent thereto will be managed for public use. What does this all add up to? In our judgment, and the judgment of many, the pastoral beauty of the valley is undergoing and will continue to undergo change and many of those changes will result in less beauty and less possibility for the public to take advantage of the area. The project will preserve one area for public use and even though we may not all agree, that area will have beauty. Question: Won't the reservoir ruin wildlife habitat for the deer and reduce the herd by 250 to 300 deer? Answer: It is true that some wildlife habitat for deer will be ruined. The project will reduce the habitat of wild animals and wildfowl in the project area by about 1,500 acres, about 988 acres 20 from inundation by the reservoir; the balance from relocations and other project uses. Most of this is considered to be valuable winter range area for blacktail deer. According to the Forest Service, a herd reduction of 250 to 350 animals would be expected to occur if no mitigation measures involving vegetation management on the approximately 4,000 acres of land peripheral to the project were instituted. Plans for habitat improvement on project lands and adjacent national forest lands have been formulated by the Bureau of Sports Fisheries and Wildlife and the Oregon Wildlife Commission in cooperation with the Forest Service. The preliminary plan for wildlife mitigation at Applegate has been reviewed and approved by the California Department of Fish and Game. Filling the reservoir will force the displacement of animals in the area. They will be forced to share the habitat surrounding the reservoir with the animals already there. Some natural depopulation will probably occur. Those effects on some of the larger wildlife will be reduced in part by elimination of cattle and other domestic animal populations presently supported by the perimeter lands. Without the project private lands may be gradually lost for deer winter range if the land is developed for homes and cabins. We are hopeful that the public lands adjacent to the reservoir can be managed to supply the needed winter range. Question: What is the basis for benefits and costs used in the annual benefits for the project functions? Answer: Benefits are a measure of what the project will produce if looked at from a national point of view. The ground rules are quite simple and apply to all categories of benefits; they are: a. Compare the situation with and without the project. b. Include all costs and all benefits wherever and to whomever they accrue. c. Use a discount rate to reduce all costs and benefits to a common time basis. Methods The details of methodology used to evaluate benefits for each category (flood control, recreation, irrigation, water quality, and fish enhancement) are different but each strictly adheres to the general ground rules listed abcve. The reason the methods differ is that each benefit category poses special 21 problems in identifying the value of the project's output. Benefits are measured as follows and as given herein are based on 1973 prices and conditions. Flood Control Compare against Average storing the average annual the average annual annual damages are floodwater reduces flood damages without the project flood damages with the project. less with flood storage because the frequency of damages downstream. The comparison must include economic growth in the value of flood damageable property during the project's economic life, with the project and without it. Benefits are also claimed for enhancement of lands due to reduced flood risk. These benefits represent increased income resulting from lands being put to more intensive use. Recreation Compare the average annual quantity and quality of recreation use without the project to that with the project. The comparison must include increases (or decreases) in future boating, swimming, camping, picnicking, winter sports, hiking, horseback riding, sightseeing, and similar outdoor activities under both conditions. Projection of future recreational use is based on consideration of regional population trends, presence of other competing recreation areas, project access, project amenities, recreation use season, and facilities to be provided. The value of a user-day is applied as described in Supplement No. 1, Senate Document 97, which provides a range of values and notes the factors to be considered in selecting a particular value. In the absence of market prices, values for specific recreational activities may be derived or estimated on the basis of a simulated market considering prices recreationists would be willing to pay and to actual charges being made at other installations or on the basis of justifiable alternative cost. The above benefits exclude reservoir fishing which is included in the fish and wildlife enhancement benefits. The U.S. Forest Service is to construct, operate, and maintain these recreation areas and these costs have been included in the Corps' economic analysis. 22 Irrigation Irrigation benefits and supporting data are supplied to the Corps from studies performed by the USBR and represent the increased net income of agricultural production resulting from an increase in the moisture content of the soil through the application of water or decrease in damage from drought. Fish Enhancement A comparison, by State and Federal fish and wildlife agencies, of conditions without the project against conditions with the project is used to identify the project's contribution to net increases in recreational and commercial fisheries production. The value of sport fishing is established on a user-day basis as described for recreation benefits. The value of commercial fishing uses an average market value per pound of fish caught commercially as the basic unit value for evaluation. The project's net contribution to number of sport fishing user-days and pounds of commercial fish caught during the entire life of the project is taken into account. Replacement of project-caused losses, (hatchery to replace lost spawning grounds) is not included as a benefit. Water Quality The water quality benefit is based on the net contribution to public use and enjoyment of water for all purposes made possible by virtue of a change in water quality. A comparison of the downstream area with and without the project indicates recreation would be more highly valued and more popular, and public use would increase. The same comparison also showed would be more highly valued due sites. The annual value of the more intensive land use make up that lands along the stream to more intensive use as homeincreased recreation use and the water quality benefit. Project Economic Costs Project economic costs include the value of all goods and services used in constructing, operating, and maintaining a project. Project economic costs are the sum of investment costs; operation, maintenance, and replacement costs; and induced costs as defined below: Investment costs. - The value of goods and services necessary for the establishment of the project, including: land, 23 easements, rights-of-way, and water rights; capital outlays to relocate facilities or prevent damages; and all other expenditures for investigations and surveys, and designing, planning, and constructing a project after its authorization. Operation, maintenance, and replacement costs. - The value of goods and services needed to operate a constructed project and make repairs and replacements necessary to maintain the project in sound operating condition during its economic life. Induced costs. - All uncompensated adverse effects caused by the construction and operation of a program or project, whether tangible or intangible. These include estimated net increases, if any, in the cost of Government services directly resulting from the project and net adverse effects on the economy such as increased transportation costs. Induced costs may be accounted for either by addition to project economic costs or deduction from primary benefits. Associated costs. - The value of goods and services over and above those included in project costs needed to make the immediate products or services of the project available for use or sale. Associated costs are deducted from the value of goods and services resulting from a project to obtain primary benefits. Question: What is the status of the PZethodon stormi? Answer: The Siskiyou Mountain Salamander (PZethodon stormi) is a species only recently described by herpetologists. Limited collecting efforts have indicated that it may be rare or uncommon and that it occupies a small geographical range in the Applegate area. In 1972, some members of the Sierra Club and others pointed out the possible effects of Applegate Dam and Reservoir on P. stormi. In response, the Corps contracted with the University of Michigan to investigate the natural history of P. stormi, its validity as a distinct species, and its vulnerability to environmental changes brought about by dam construction. The "Salamander Study" is to culminate in a final report in December 1974. No detailed information has been provided yet, but the principal investigator, Dr. Ronald Nussbaum, has indicated that the known range of the species has been considerably expanded. Results of the study will be available to the public. Any proposed measures for management of project lands, or other Corps proposals to reduce project impacts on P. stormi, will be set forth in a supplement to the existing environmental impact statement. The supplement will be distributed to the public in mid-1975. 24 Question: Does the Corps of Engineers recognize the effect of downstream tributary inflows? Answer: Yes, all of its studies of flood control effects have taken those inflows into account. Specific stage reduction figures, for Applegate project operated as planned and authorized, are: Flood of Without project 1955 1964 1972 1974 18.0 19.6 12.4 20.4 At Applegate 1/ Project With stage project reduction 13.0 15.2 7.7 16.2 5.0 4.4 4.7 4.2 Bankfull stage or the point of zero damage is 11.9 feet. 1/ Based on recurrence under present channel conditions as reflected by current rating curves prepared by U.S. Geological Survey With a bankfull stage of about 11.9 feet, the 1964 flood crest at Applegate represented about 7.7 feet of flooding depth along the bankline, and lesser depths with increased distance from the river. Thus, the 4.4-foot stage reduction would have represented more than a 57 percent reduction in maximum depth of flooding, and complete elimination of all flooding in areas where depths were 4.4 feet or less. Although those reductions represent considerably less than complete flood control, the result is a very significant reduction in flood damages. As residents along the river know from experience, total flood damages are not directly proportional to depth of inundation. A comparison of damages along Applegate River with stages at Applegate is as follows: Stage, feet Discharge, c.f.s. Damages, $ millions 14 16 18 20 19,300 26,400 35,700 48,700 0.6 0.9 1.7 4.4 In consideration of the above, it is obvious that complete control of floods at Applegate is not necessary for achievement of major damage reductions. 25 Question: Will mercury pollution result from construction of the reservoir? Answer: In order to evaluate the possibility of mercury pollution, the Corps has gathered information concerning the known mercury production and prospects within the Applegate Lake area. A field reconnaissance by Corps of Engineers' geologists has been made. Available data concerning areas where mercury has been mined within the reservoir catchment basin have been reviewed. A paper which reviews the above data has been drafted. The above information indicates that mercury pollution will not result from the construction of the reservoir. However, this information currently is being reviewed. We expect to have this review accomplished and a decision made as to the need for and type of further studies that may be required by the end of November. No irreversible action will be taken on the Applegate project until we have satisfied ourselves and State and Federal agencies which have expertise in the field that mercury pollution will not be a problem in Applegate Lake. 26 ,I V ! I IV !I IV !I IV !I IV !I IV D !I IV !I IV !I IV !I IV !I IV !I IV !I IV !I IV ! I IV !I IV !I IV !I IV !I IV !I IV !I IV !I IV !I IV !I I!
© Copyright 2026 Paperzz