MISO ARR/FTR Modeling Practices MO-OP-019-r6 Effective Date: APR-23-2017 1 2 3 4 5 Purpose ................................................................................................................... 2 Scope ....................................................................................................................... 2 Definitions ............................................................................................................... 2 Roles and Responsibilities .................................................................................... 3 Procedure Description ........................................................................................... 3 5.1 Network Topology .............................................................................................. 3 5.2 Contingencies .................................................................................................... 4 5.3 Operating Guides ............................................................................................... 5 5.4 Monitored Branch Constraints ............................................................................ 6 5.5 Monitored Flowgate Constraints......................................................................... 7 5.6 Phase Angle Regulator (PAR) Settings............................................................. 8 5.7 Loopflow Assumptions ....................................................................................... 8 5.8 Nomograms........................................................................................................ 9 5.9 Scheduled Outages.......................................................................................... 10 6 References ............................................................................................................ 10 7 Disclaimer ............................................................................................................. 10 8 Revision History ................................................................................................... 11 Page 1 of 12 ADM-01 Public MISO ARR/FTR Modeling Practices MO-OP-019-r6 Effective Date: APR-23-2017 1 Purpose This document describes the modeling approaches for various elements of the MISO FTR model used in the Simultaneous Feasibility Test for Annual ARR Allocations and FTR Auctions. 2 Scope This procedure applies to the approaches for various elements of the MISO FTR model used for Auction Revenue Right (ARR) allocations and Financial Transmission Right (FTR) Auctions. The Policy applies to the FTR and Pricing Administration (FPA), which administers the FTR and ARR markets. 3 • • • • • • • • • • • • • • • • • • • • • • • • • • • Definitions ARR: Auction Revenue Right BA: Balancing Authority Area CBM: Capacity Benefit Margin CPNode: Commercial Pricing Node DA/RT: Day-Ahead and Real-Time Energy and Operating Reserve Market EMS: Energy Management System FFE: Firm Flow Entitlements FPA: FTR and Pricing Administration FTR: Financial Transmission Right ICCP: Inter-Control Center Protocol IDC: Interchange Distribution Calculator JOA: Joint Operating Agreement (also known as Seams Agreement) LBA: Local Balancing Authority LBA Area: Local Balancing Authority Area LF: Loop Flow LF ARR: Loop Flow Auction Revenue Right MOD: Model on Demand OTDF Flowgate: Outage Transfer Distribution Factor flowgate (with contingency) PAR: Phase Angle Regulator PTDF Flowgate: Power Transfer Distribution Factor flowgate (without contingency) RCF: Reciprocal Coordinated Flowgates RTCA: Real Time Contingency Analysis RTO: Regional Transmission Organization SFT: Simultaneous Feasibility Test TO: Transmission Owners TRM: Transmission Reliability Margin TTC: Total Transfer Capability Page 2 of 12 ADM-01 Public MISO ARR/FTR Modeling Practices MO-OP-019-r6 Effective Date: APR-23-2017 4 Roles and Responsibilities FPA is responsible for administering the ARR/FTR markets, which require building, posting and using models as described in this document. 5 Procedure Description This procedure describes the modeling approaches for various elements of the MISO FTR model used in the Simultaneous Feasibility Test for Auction Revenue Right (ARR) allocations and Financial Transmission Right (FTR) Auctions. 5.1 Network Topology ARR/FTR analysis utilizes a bus-branch Network Model that is derived from a nodebreaker model maintained in the EMS environment. HEDGE™ software used in the ARR/FTR analysis can read the bus-branch model in the PSS/E format. The EMS model is utilized in MISO’s Reliability Coordination applications such as State Estimator and Contingency Analysis. This model is continuously reviewed and updated with the help of MISO’s transmission owning members. A significant portion of the U.S. Eastern Interconnection electricity grid is represented in this model. Real-time ICCP measurements on generation, load, flow, breaker status etc. are obtained and applied on the model. The MISO EMS system is based on Alstom’s Habitat/WebFG environment. The ARR/FTR model is created through the following steps: 1) A current snapshot of the model from the EMS environment is created. 2) Future equipment is incorporated by adding new facilities, removing/outaging the equipment to be retired and implementing network reconfigurations provided by the TO prior to the published deadline. 1 a. Modeling future topology changes: Incorporate new facilities utilizing the information from MISO Model on Demand (MOD) tool and as submitted by the TO through other means of communication. The new facility will be double modeled or configured as a dummy equipment to represent the topology change until the facility is placed in-service. b. Retirement: Remove/open equipment to be retired utilizing the information submitted to MISO by the TO, primarily but not exclusively through MISO Web-tool. c. Network configuration: Incorporate line impedances and ratings utilizing the information submitted through MISO Web-tool and as submitted by TO through other means of communication. 1 Per IRO-010 R3, all modeling information must be submitted in accordance with the MISO IRO-010 R1 Data Specification: RTO-SPEC-006 MISO Reliability Data Specification, Section 3.1 System Modeling and Parameters and within the MISO established modeling timeframe. Page 3 of 12 ADM-01 Public MISO ARR/FTR Modeling Practices MO-OP-019-r6 Effective Date: APR-23-2017 3) The circuit breakers and switches are positioned at their nominal status, but normally open devices may be closed to connect loads or generators as necessary. 4) The bus numbers, PTI bus names and area numbers are mapped to the same numbers and names in an IDC case to the extent possible. 5) MISO reserves the right to make adjustments deemed appropriate and adequate to represent the model based on the best available data when differences exist in the information provided by the TO through various systems. Therefore, the model may be similar but not necessarily identical to the individual TO’s real-time or planning models. 6) Powerflow is executed to ensure relevant facilities are energized and a solved system state is achieved in the EMS powerflow environment. 5.2 Contingencies The following criteria are applied to define contingencies for ARR/FTR Simultaneous Feasibility Test (SFT): • Contingencies associated with OTDF flowgates in the AFC models are selected if o The flowgate is internal to the MISO footprint and/or o The flowgate is included in the list of the Reciprocal Coordinated Flowgates (RCF) from the Joint Operating Agreements with PJM; SPP and other entities. 2 • Non-flowgate contingencies are added only under the following conditions o If it is identified that existing flowgate contingencies do not adequately represent N-1 operating conditions. o If a non-flowgate contingency is identified to cause overloads in realtime or day ahead operations or being active in RTCA. • External lines and transformers that are not associated with RCF are not included in the contingency list. • Contingencies that have operating guides are modeled assuming the operating guides are implemented. 2 These entities include EKPC, TVA, and LGEE. Page 4 of 12 ADM-01 Public MISO ARR/FTR Modeling Practices MO-OP-019-r6 Effective Date: APR-23-2017 5.3 Operating Guides Operating guides provide real time operations with a means of mitigating overloads that may result from unforeseen system conditions or influences external to the MISO market. In some cases operating guides may be developed in response to a planned system outage of transmission or generation facilities. Operating guide development is coordinated by the MISO reliability operations engineering group in cooperation with the affected equipment owners. MISO FTR markets include the use of available operating guides in FTR market analysis where conditions exist that necessitate the use of a mitigation plan. When an operating guide is available, the ARR/FTR market considers the mitigation steps that involve system reconfiguration or reductions in facility limits due to operational issues. Where operating guides eliminate transmission constraints by ultimately removing the overloaded facility from service, the constraint is excluded in the ARR/FTR analysis. Although the implementation of operating guides is subject to system conditions, there is no capability to define a conditional relaxation of constraints, and it is assumed that the operating guide is implemented in real time. By considering the mitigating effects of the operating guide, the results of the FTR market analysis typically result in fewer constraints. In some cases operating guides include voluntary redispatch steps. However, this means of constraint relief is not modeled in the ARR/FTR analysis. Operating guides that use dynamic ratings are problematic for the FTR model since the ratings are dependent on environmental conditions that cannot accurately be predicted in advance. ARR/FTR analysis uses published ratings while dynamic ratings are reserved for real time operations. Where stability-related operating guides exist, the ARR/FTR analysis software applies the stability limit to the base rating of the facility while the emergency thermal limits are applied to the emergency rating of the facility for contingency analysis. Table 1 below discusses the types of mitigation measures available in operating guides and discusses how each guide is implemented in ARR/FTR analysis. Page 5 of 12 ADM-01 Public MISO ARR/FTR Modeling Practices MO-OP-019-r6 Effective Date: APR-23-2017 Table 1 Mitigation Plan via Op. Guide No pre-contingency or atcontingency mitigation Reconfigure System with Known MW Relief Reconfigure System with Unknown MW Relief Pre-contingency voluntary redispatch At-contingency voluntary redispatch or Generator Runback Dynamic Ratings Stability Limits 5.4 Implementation of Op. Guide in ARR/FTR models None Adjust limit by the amount of MW relief expected One of the following methods is implemented on a case-by-case basis: a) Include reconfiguration in contingency definition, if possible. If reconfiguration causes new violations, choice is made between proceeding with or without guide based on offline studies b) If the guide is expected to relieve all overloads associated with a specific contingency, the contingency is ignored c) If the guide relieves a specific constraint under a particular contingency, the contingency-constraint pair is ignored d) If the guide relieves all overloads on a specific constraint, the constraint is ignored None Selective modeling of runback if redispatch is effective; otherwise contingency is ignored Use published ratings available Apply stability limit to the normal (base case) rating. Use thermal emergency rating for the contingency limit. Monitored Branch Constraints Branch constraints are enforced in the following manner in the ARR/FTR models: 5.4.1 Transmission Lines • • • All Local Balancing Authority (LBA) transmission lines at 100 KV and above are constrained to their limits. Each transmission line that is a tie between an LBA Area and tier 1 control area and at voltage level 100 KV and above is constrained to its limits. LBA and tie transmission lines below 100 KV may be monitored on a case-by-case basis in order to ensure that largest angle across any lines or transformers is less than 90 degrees. Page 6 of 12 ADM-01 Public MISO ARR/FTR Modeling Practices MO-OP-019-r6 Effective Date: APR-23-2017 5.4.2 Transformers • • • All LBA transformers with both ends at 100 KV and above are constrained to their limits. Each transformer that is a tie between an LBA Area and tier 1 control area and with both ends at 100 KV and above is constrained to its limits. 3-winding transformers are constrained to their limits if they are internal or connected to the footprint and if at least two ends are at 100 KV and above. Internal and tie transformers below 100 KV may be monitored on a case-by-case basis in order to ensure that largest angle across any lines or transformers is less than 90 degrees. 5.4.3 Global Limit Set and Low kV Monitoring The thermal and emergency ratings of the monitored transmission lines and transformers are modeled at or above 90% of their original ratings. For modeling a future Spring season, lines and transformers may be modeled at or above 85% of their original ratings. In LBAs where the MISO has reliability coordination function, transmission lines and transformers are monitored at 69kV and above. Any branch will be enforced and the limit set to twice its original limit if all the following conditions are met: 1) The branch is connected to a bus where a single CPNode-EPNode is defined. 2) The sum of all the branches’ emergency limits connecting to this bus is less than 100MW. 3) The branch does not meet the monitored branch inclusion criteria defined above. A few transmission lines and transformer constraints satisfying the above categories are not enforced due to standing operating guides that include post-contingency mitigation schemes. Operating guides modeling criteria are provided in a separate section in this document. 5.5 Monitored Flowgate Constraints All internal PTDF and OTDF flowgates owned by MISO and monitored in the MISO security coordination process are enforced in the ARR/FTR process as obtained through the MISO Flowgate update process. The flowgate ratings are enforced at or above 90%, of their Total Transfer Capability (TTC). The TTC is not reduced for Transmission Reliability Margin (TRM) and Capacity Benefit Margin (CBM). Page 7 of 12 ADM-01 Public MISO ARR/FTR Modeling Practices MO-OP-019-r6 Effective Date: APR-23-2017 All external PTDF and OTDF flowgates that are part of the Reciprocal Coordinated Flowgate (RCF) set are also enforced in the ARR/FTR process. These external RCFs are modeled as generic constraints described in Section 5.8 Nomograms. 5.6 Phase Angle Regulator (PAR) Settings HEDGE™ provides simple linear models for Phase Angle Regulator (PAR), also called phase shifters, for use with DC analysis. Nonlinear PAR models are also possible but the computational time would drastically increase since the process would need to iterate and recalculate distribution factors at each iteration. Hence, linear network models and DC analysis are used for ARR allocation and FTR Auction analysis. Linearity of the optimization problem is maintained as long as each PAR is modeled with a fixed phase angle or a fixed MW flow but not optimized in the solution process to switch between modes. The PAR model, including the initial angle setting, the angle and flow limits and the impedance correction data, are specified in the network data. The PARs are modeled in ARR/FTR analysis either at fixed angle and local control or optimized mode. The control modes and parameter settings are determined based on feedback from transmission providers regarding nominal operation of these phase shifters. Feedback from DA/RT operations is also considered. 5.7 Loopflow Assumptions Loop flows consist of the flows on the MISO footprint caused by external transactions. The modeling of loopflow is to produce representative flows by explicitly modeling transactions of external entities with a set of Point-to-Point fixed ARRs for tier 1 BAs. These ARRs/FTRs are termed as Loop Flow (LF) ARRs/FTRs. LF ARRs/FTRs are split into three groups: 1) Generation Loopflows – These represent the intra-BA network generation of the tier 1 balancing areas. The source points for these transactions are defined on generation loop flow nodes available in MISO’s Commercial Model which are defined using generators of the corresponding tier 1 BA with its Pmax as the weighting factors. The sink loop flow node representing all generation loopflows will be chosen within the MISO Commercial Model, traditionally a large HUB. 2) Load Loopflows – These represent the intra-BA network load of the tier 1 balancing areas. The sink points for these transactions are defined on load loop flow nodes available in MISO’s Commercial Model which are defined using load points of the corresponding tier 1 BA with its MW (from a specific time stamp) as the weighting factors. The source loop flow node representing Page 8 of 12 ADM-01 Public MISO ARR/FTR Modeling Practices MO-OP-019-r6 Effective Date: APR-23-2017 all load loopflows will be the node chosen as sink loop flow node for all generation loopflows. 3) Interface Loopflows – These represent the net interchange of the tier 1 balancing areas. Depending on if the BA has a net negative or positive interchange value, these loopflows will either source at the interface loopflow nodes defined in MISO’s Commercial Model which are defined using generators of the corresponding tier 1 BA with equal weighting factors, and sink at the node chosen as sink loop flow node for all generation loop flow or they will source at the node chosen as loop flow node for all generation loop flow and sink at the interface loopflow node. All generation, load, and interface loopflows will source or sink from the same HUB node. Loopflow MWs are normalized in such a way as to ensure that the net injection/withdrawal MW is equal to zero at the HUB node, which guarantees that the choice of HUB node has no impact on the outcomes of the ARR/FTR SFT process. These LF ARRs are modeled as fixed Obligations. The MW quantities are obtained from the loopflow modeling in MISO’s Day-Ahead Market and seasonal planning models, as appropriate. 5.8 Nomograms Nomograms modeled in the FTR/ARR process are constraints that monitor and enforce commercial flows, estimated from historical data, through the underlying monitored elements under a certain contingency (or base case) in the definition. Flows from loopflow modeling and other network modeling such as PARs etc., have no impact on nomograms. The day-ahead and real-time constraints are included as nomograms in the ARR/FTR process when a non-trivial contribution to Day-Ahead and Real-Time Energy and Operating Reserve Market (DA/RT) congestion, and/or FTR shortfall in a single season during the year(s) before the upcoming allocation period, has occurred. In addition, binding constraints that have non-trivial contribution to DA congestion and/or FTR shortfall in the last few weeks just prior to the effective date of the allocations/auctions will also be evaluated and included as needed. Various criteria include, but are not limited to, total shadow price, total binding hours, total days of binding life span, etc. Additional criteria may be used during the verification process and outage review to identify and address constraints based on isolated events. Page 9 of 12 ADM-01 Public MISO ARR/FTR Modeling Practices MO-OP-019-r6 Effective Date: APR-23-2017 Nomograms modeled in the FTR/ARR process represent the additional constraints that are developed based on typically, the historical commercial flow during the hours when they were binding in the DA/RT during the year before the upcoming allocation period. 3 In addition to constraints binding in the DA/RT markets, all the external RCFs will be modeled as nomograms. The limits of such constraints are based on typically, the historical MISO entitled commercial flow usage for the given flowgates during the year before the upcoming allocation period. 5.9 Scheduled Outages Scheduled outages are composed of outages from the MISO CROW system regardless of the outages’ status (proposed, submitted, study, as well as accepted), pending evaluation and review with DA/RT groups. In Annual ARR Allocation and Annual FTR Auction, scheduled outages also include outages submitted by MISO Transmission Owners as supplemental outages in response to the data request sent out by FTR and Pricing Administration and Outage Coordination Group in order to better incorporate future topology changes. Any critical outages coming through internal or external notifications might be reviewed by FTR and Pricing Administration and included in the ARR/FTR process at any time. The scheduled outages inclusion criteria are determined as follows: Seasonal Cases • 5 calendar days or longer in the season Monthly Cases • 3 calendar days or longer in the month Outages may have to be restored for various reasons that include but are not limited to: 1. When outages in different time frames within the same season cause an islanding or phase islanding effect. 2. When the case solution cannot be reached due to multiple outages. 3. When PAR angles become extremely large. 6 • References RTO-SPEC-006 Reliability Data Specification 7 Disclaimer This document is prepared for informational purposes only to support the application of the provisions of the MISO Tariff and the services provided thereunder. MISO may revise or terminate this document at any time at its discretion without notice. While 3 Global limit reduction is not applied to generic constraints. Page 10 of 12 ADM-01 Public MISO ARR/FTR Modeling Practices MO-OP-019-r6 Effective Date: APR-23-2017 every effort will be made by MISO to update this document and inform its users of changes as soon as practicable, it is the user’s responsibility to ensure you are using the most recent version of this document in conjunction with the MISO Tariff and other applicable documents, including, but not limited to, the applicable NERC Reliability Standards. Nothing in this document shall be interpreted to contradict, amend, or supersede the MISO Tariff, and MISO is not responsible for any reliance on this document by others, or for any errors or omissions or misleading information contained herein. In the event of a conflict between this document, including any definitions, and either the Tariff or a NERC standard, the Tariff or NERC Reliability Standard shall prevail. In the event of a conflict between the Tariff and the NERC standard, the Tariff shall prevail until or unless the Commission orders otherwise. Any perceived conflicts or questions should be directed to the Legal Department. 8 Revision History Doc Number MO-OP-019-r6 MO-OP-019-r5 MO-OP-019-r4 MO-OP-019-r3 MO-OP-019-r2 Description Annual Review completed a) Revised language under section 5.4.2, to describe a transformer that may be a tie to an external LBA (in lieu of previous description of jointly owned transformers). b) Made capitalization, terminology, typographical and grammatical corrections. c) Specified primacy of Tariff definitions. d) Deleted outdated reference to MAPP.Added clarity to the node chosen as the sink node for the Loopflow assumptions Annual Review completed. a) Typographical errors b) Revised limit requirements from 90% to 85% in section 5.4.3. c) Clarified Network topology modeling steps d) Simplified description of outage gathering criteria in Section 5.9, worded as calendar days and removed secondary criteria as it was included in primary criteria description Annual Review completed. Revised limit requirements from 95% to 90% or greater in section 6.4.3, Included the outage status of proposed as an example of outages considered. Access Level revised from Protected to Public. Annual Review completed. No Changes. Annual Review completed. Edited document for Revised by: N. Kirk P.Nathan Effective Date APR-23-2017 N. Kirk P. Nathan APR-23-2016 N. Kirk APR-23-2015 S. Singh N. Kirk APR-23-2014 APR-23-2013 Page 11 of 12 ADM-01 Public MISO ARR/FTR Modeling Practices MO-OP-019-r6 Effective Date: APR-23-2017 MO-OP-019-r1 MO-OP-019 Clarity Revised the document, specifically for Generic Constraints(changed to Nomograms), Loopflow Assumptions and PARs sections Original document Xiaoming Wang MAR-01-2012 Greg Leach AUG-30-2011 Page 12 of 12 ADM-01 Public
© Copyright 2025 Paperzz