Facilities Update

302-332 Center for Brain Health Second Floor Renovation
The University of Texas at Dallas
Executive Summary Report
Project Description
This project consists of the build out of the second floor of the
existing Center for Brain Health. This space will be used to house
students and short term employees associated with contracts and
grants. Additionally, some improvements to the grounds and
other minor building renovations are included in this project.
Current plans are for the space to house 3 major research
initiatives: the BrainHealth Autism Institute (dedicated to training
graduate students in brain imaging research, brain repair
treatment and disease prevention in autism and
Asperger's).
Phase I - 11,159 GSF; 6,453 ASF Phase II 9,609 GSF; 6,246 ASF
Total
20,768GSF; 12,699 ASF
Project Information
Project Status:
Project Delivery Method:
CIP Project Type:
Gross and Assignable Square Feet:
"44 Initiative" Project:
Phase and Estimated % Complete:
OFPC RPM, SPM, PM, RCM, IM:
Architecture Firm:
Construction Firm:
Active
Competitive Sealed Proposals
New
GSF: 20,768
ASF: 12,699
Yes
Construction - 15%
Salcher , Lund , Head/Yauger , Ellis , Connolly
BWR
Turner Construction Company
Project Budget
Construction Services:
Total Project Cost:
$
$
899,000 at
5,000,000 at
$
5,000,000
$43.29 / GSF
$240.76 / GSF
Project Funding
Gifts
Project Schedule
DD Approval Date (by BOR):
NTP For Construction Date:
Substantial Completion:
Operational Occupancy Date:
12/2/2008
4/9/2009
11/16/2009
1/1/2010
Project Remarks
Turner started mobilizing on 5/11/09. Turner has completed the demolition of existing ductwork, walls and ceilings. Eighty
percent of the metal stud walls have been installed and electrical rough-in has started in the walls. HVAC duct work
materials were received and the main duct runs are installed. The new drain lines are installed and ready to be tested.
Sheet rock work has been started on a few walls following in-wall inspections. A majority of the materials submittals have
been received and processed. All the long lead items are on order and in fabrication.
Board Approvals
1. Chancellor letter for approval of Design Development Documents - 12/02/2008. 2. Texas Higher Education
Coordinating Board Approval - 02/24/2009.
Updated By and Date: Jim Ellis 06/10/2009
Report Date: 6/26/2009
302-280 Math, Science and Engineering Teaching-Learning Center
The University of Texas at Dallas
Executive Summary Report
Project Description
The project is a comprehensive facility for providing focused,
research-based, high-quality education in mathematics, science
and engineering for U. T. Dallas students in their freshman and
sophomore years of study. The facility will be equipped to serve
concurrently as a major laboratory for research on effective
teaching and learning techniques in these fields, both at the
college level and through full range from kindergarten through
12th grade. The facility will include a lecture hall, recitation areas,
instructional laboratories, offices for faculty and tutors, and shell
space for future program elements.
Project Information
Project Status:
Project Delivery Method:
CIP Project Type:
Gross and Assignable Square Feet:
"44 Initiative" Project:
Phase and Estimated % Complete:
OFPC RPM, SPM, PM, RCM, IM:
Architecture Firm:
Construction Firm:
Active
Competitive Sealed Proposals
New
GSF: 73,956
ASF: 45,707
Yes
Construction - 16%
Salcher , Lund , Naylor , Jim Ellis , Connoly
Kell Munoz Architects
Adolfson & Peterson Construction
Project Budget
Construction Services:
Total Project Cost:
$
$
24,338,938 at
29,700,000 at
$
$
24,300,000
5,400,000
$329.10 / GSF
$401.59 / GSF
Project Funding
Permanent University Fund Bonds
Revenue Financing System Bonds
Project Schedule
DD Approval Date (by BOR):
NTP For Construction Date:
Substantial Completion:
Operational Occupancy Date:
2/6/2008
10/31/2008
6/25/2010
7/26/2010
Project Remarks
Installed shoring, decking and formwork for Level 3. Placed concrete in the following areas: columns and shear walls
between Level 2 and Level 3, Level 3 slab, the loading dock area gradebeams and started columns between Level 3 and
roof. Set electrical/communication floors boxes in Levels 3. Installed the 12 inch drain line north of the building and set the
precast inlets. Area B structural steel was erected for Level 2, Level 3 and the roof. Started installing metal decking and
roof joist in Area B. Next month Area B concrete slabs on metal deck and Area A roof beams will be placed. This report
was updated on 6/10/09.
Board Approvals
None
Updated By and Date: Jim Ellis 06/10/2009
Report Date: 6/26/2009
302-261 Vivarium and Experimental Space
The University of Texas at Dallas
Executive Summary Report
Project Description
Build-out the current shell space in the basement of the new
Natural Sciences and Engineering Research Laboratory for use
as a vivarium and experimental spaces for neuroscience and
neuron-engineering faculty. This state of the art facility will replace
the current inadequate vivarium facilities. Upon completion and
sterilization of the new vivarium, the animals will be relocated to
the new facility and the old vivarium will be torn down to make
way for the new MSET building.
Project Information
Project Status:
Project Delivery Method:
CIP Project Type:
Gross and Assignable Square Feet:
"44 Initiative" Project:
Phase and Estimated % Complete:
OFPC RPM, SPM, PM, RCM, IM:
Architecture Firm:
Construction Firm:
Active
Competitive Sealed Proposals
Renovation
GSF: 15,291
ASF: 0
Yes
Warranty - 25%
Salcher , Lund , Lund , Yauger , None
Page Southerland Page
Mitchell Enterprises, Ltd.
Project Budget
Construction Services:
Total Project Cost:
$
$
8,655,861 at
14,680,000 at
$
$
2,680,000
12,000,000
$566.08 / GSF
$960.04 / GSF
Project Funding
Permanent University Fund Bonds
Tuition Revenue Bonds
Project Schedule
DD Approval Date (by BOR):
NTP For Construction Date:
Substantial Completion:
Operational Occupancy Date:
12/13/2006
9/28/2007
10/22/2008
12/5/2008
Project Remarks
1. Final pay application to Contractor has been paid. 2. Warranty Phase underway. 3. Miscellaneous warranty repairs in
process.
Board Approvals
None pending.
Updated By and Date: Vince Yauger / RCM 06/10/2009
Report Date: 6/26/2009