Vogtle units 3 & 4 Thirteenth Semi-annual Vogtle Construction Monitoring Report August 2015 • Docket No. 29849 The CA01 module is lifted into the Vogtle Unit 3 containment vessel Vogtle Units 3 and 4 Thirteenth Semi-Annual Construction Monitoring Report Table of Contents Page Executive Summary 3 Responses to Stipulated Questions 5 Unit 3 Nuclear and Turbine Islands As of July 2015 2 EXECUTIVE SUMMARY I. Highlights Georgia Power Company as itself (“Georgia Power”) and Southern Nuclear Operating Company (“SNC”) as agent of Georgia Power (collectively, the “Company”) is fulfilling its commitment to safety and quality. During the reporting period of January 1, 2015 to June 30, 2015 (the “Reporting Period”), approximately 6.6 million work hours were performed safely with no lost time injuries. The Company received no Notices of Violation and remained in favorable standing with the Nuclear Regulatory Commission (“NRC”) as indicated by its green status under the NRC’s Construction Reactor Oversight Process. Georgia Power is requesting verification and approval of $148 million of actual expenditures incurred during the Reporting Period. 13th VCM Expenditures Dollars in Millions EPC Quality Assurance, Compliance and Operations & EPC Scope Change Ad Valorem Tax Transmission Total 13th VCM Expenditures 78 55 9 6 $148 The Total Construction and Capital Cost Forecast and in-service target dates remain unchanged since the 12th Vogtle Construction Monitoring (“VCM”) Report. Completing Vogtle Units 3 and 4 remains the best cost option for our customers. The 60+ year Vogtle Units 3 and 4 nuclear facility (“Facility”) represents the best cost option for our customers even without yet considering the value that nuclear adds to the state of Georgia’s future regarding pending environmental regulation. The EPC Agreement continues to protect customers. Our customers continue to be protected by the fixed and firm nature of the Engineering, Procurement and Construction (“EPC”) Agreement which assigns significant construction cost risks to the Contractor. 3 The assignment of these risks to Contractors has saved customers hundreds of millions of dollars over a “time and materials” form of contract. Georgia Power customers are protected, with very limited and specific exceptions, from a large portion of traditional construction cost risks such as Contractor’s increased construction costs including lower production and productivity, increased cost of bulk materials and commodities and Contractor’s own cost of delays. The Contractors are Westinghouse Electric Company LLC (“Westinghouse”) and Stone & Webster, Inc., a subsidiary of The Shaw Group Inc., which was acquired by Chicago Bridge & Iron Company N.V. (“CB&I”), (collectively, “Contractor”). 4 RESPONSES TO STIPULATED QUESTIONS As agreed in the Stipulation that was incorporated into the Certification Order, Georgia Power responds below to the 15 specified items in the order in which they appear in Section 2(d)(1-15) of the Stipulation. In this 13th VCM Report, and in accordance with the Commission’s Order on the Ninth/Tenth VCM Report (“9th/10th VCM Order”), Georgia Power has omitted Items 4, 10 and 13. 1. The reasons for any additional change in the estimated costs of the units since the process began. The Total Construction and Capital Cost of the Facility is forecasted to remain the same as the previous reporting period. This forecast represents the Company’s estimate of the amount that the Company will spend to complete the Facility and, if deemed prudent by the Commission, will be put into rate base when the Facility goes into service. The current cost and forecast reports are provided in Tables 1.1 and 1.1a. The tables reflect the forecasted changes to the schedule and capital expenditures as well as shifts in timing of costs and minor movement between cost categories that typically occur in management of a project of this scale. 5 Table 1.1 Vogtle 3&4 Facility Georgia Power Company Cost - Subject to Commission Verification and Approval Project To Date Through Period Ending June 30, 2015 Total Project Capital Certified Cost ($ millions) Project to Date Capital Total Current Forecast ($ millions) Variance ($ millions) Footnote Forecast To Date (4) ($ millions) Actual To Date ($ millions) Variance ($ millions) Construction & Capital Cost EPC Base Fixed Semi Annual Escalation Indexed Escalation Other Fixed Escalation Total EPC Base 1,978 468 670 3,116 1,976 470 674 3,121 -2 2 4 4 EPC Escalation Fixed Semi Annual Escalation Indexed Escalation Other Fixed Escalation Total EPC Escalation 431 142 108 681 355 117 110 582 -76 -25 2 -99 477 141 -34 37 621 1,094 241 -49 56 1,342 617 100 -15 19 721 4,418 5,045 0 0 0 Quality Assurance, Compliance and Operations & EPC Scope Change Ad Valorem & Other Fees Test Fuel Offsets Transmission Interconnection Total Construction & Capital Cost 1 1,446 171 661 2,278 1,400 151 656 2,207 -46 -20 -5 -71 187 23 104 314 176 19 103 297 -11 -5 -2 -17 514 55 0 48 617 509 54 0 47 610 -5 -2 0 -1 -8 627 3,209 3,113 -96 0 6 0 6 2 3 2 3 0 0 6 6 5 5 0 2 5 3 Other Capital Cost Certification & Independent Evaluator Fees Construction Monitor Total Other Capital Cost Vogtle 3&4 Facility Georgia Power Company Financing Cost - Recovered Pursuant to O.C.G.A. 46-2-25 (c.1) Project To Date Through Period Ending June 30, 2015 Total Project Financing Estimated at Certification ($ millions) Project to Date Financing Total Current Forecast ($ millions) Variance ($ millions) 1,545 111 39 2,298 91 18 753 -20 -21 Total Project Schedule Financing 1,695 2,408 Total Capital Cost and Financing 6,113 7,453 Footnote Forecast To Date (4) ($ millions) Actual To Date ($ millions) Variance ($ millions) Project Schedule Financing Return on CWIP in Rate Base AFUDC - Accrued through Dec 2010 Return on Unamortized AFUDC Balance 758 91 18 757 91 18 -1 0 0 713 867 866 -1 1,340 4,077 3,980 -97 Footnotes: 1. Includes $28 million for EPC Joint Use Buildings (that benefits Vogtle 1&2). 2. Includes Regulation Changes of $62 million and Owner's Cost for Training Facility of $4 million. 3. Includes $23 million for Transmission that benefits Units 1 and 2. 4. The Forecast to Date includes actual costs through the previously filed report, plus forecasted costs through the Thirteenth VCM Reporting Period. 5. Includes Dues and Fees. Taxes and other fees are paid regardless of whether units are under construction or in operation. 6. The Total Current Forecast for Return on CWIP in Rate Base includes $55 million of AFUDC accrued on CWIP above the original certified cost. Note: Details may not add to totals due to rounding. 6 6 Table 1.1.a (Trend) Vogtle 3&4 Project Georgia Power Company Cost Forecast - Subject to Commission Verification and Approval Through Period Ending June 30, 2015 Certified Cost ($ millions) Jun 2009 Forecast ($ millions) Dec 2009 Forecast ($ millions) Jun 2010 Forecast ($ millions) Dec 2010 Forecast ($ millions) Jun 2011 Forecast ($ millions) Dec 2011 Forecast ($ millions) Jun 2012 Forecast ($ millions) Dec 2012 Forecast ($ millions) Dec 2013 Forecast ($ millions) Jun 2014 Forecast ($ millions) Dec 2014 Jun 2015 Forecast Forecast ($ millions) ($ millions) Construction & Capital Cost EPC Base Fixed Semi Annual Escalation Indexed Escalation Other Fixed Escalation Total EPC Base 1,978 468 670 3,116 1,978 468 670 3,116 1,976 470 674 3,121 1,976 470 674 3,121 1,976 470 674 3,121 1,976 470 674 3,121 1,976 470 674 3,121 1,976 470 674 3,121 1,976 470 674 3,121 1,976 470 674 3,121 1,976 470 674 3,121 1,976 470 674 3,121 1,976 470 674 3,121 EPC Escalation Fixed Semi Annual Escalation Indexed Escalation Other Fixed Escalation Total EPC Escalation 431 142 108 681 431 142 108 681 336 142 109 586 336 142 109 587 337 142 109 589 344 119 110 573 343 118 110 572 353 120 111 585 355 117 110 582 355 117 110 582 355 117 110 582 355 117 110 582 355 117 110 582 507 111 -34 37 621 507 111 -34 37 621 576 111 -34 37 689 589 111 -34 40 706 582 111 -34 40 699 675 111 -60 40 766 675 111 -60 40 766 727 125 -60 41 833 930 159 -49 56 1,096 930 159 -49 56 1,096 930 159 -49 56 1,096 1,094 241 -49 56 1,342 1,094 241 -49 56 1,342 4,418 4,418 4,395 4,414 4,408 4,460 4,459 4,539 4,799 4,799 4,799 5,045 5,045 0 5 5 5 4 4 4 4 4 5 6 6 6 0 5 5 5 4 4 4 4 4 5 6 6 6 Quality Assurance, Compliance and Operations & EPC Scope Change Ad Valorem & Other Fees Test Fuel Offsets Transmission Interconnection Total Construction & Capital Cost Other Capital Cost Construction Monitor Total Other Capital Cost Vogtle 3&4 Facility Georgia Power Company Financing Cost Forecast - Recovered Pursuant to O.C.G.A. 46-2-25 (c.1) Project To Date Through Period Ending June 30, 2015 Estimated at Jun 2009 Certification Forecast ($ millions) ($ millions) Dec 2009 Forecast ($ millions) Jun 2010 Forecast ($ millions) Dec 2010 Forecast ($ millions) Jun 2011 Forecast ($ millions) Dec 2011 Forecast ($ millions) Jun 2012 Forecast ($ millions) Dec 2012 Forecast ($ millions) Dec 2013 Forecast ($ millions) Jun 2014 Forecast ($ millions) Dec 2014 Jun 2015 Forecast Forecast ($ millions) ($ millions) Project Schedule Financing Return on CWIP in Rate Base AFUDC - Accrued through Dec 2010 Return on Unamortized AFUDC Balance 1,545 111 39 1,507 97 32 1,505 99 33 1,546 99 33 1,553 91 31 1,524 91 19 1,516 91 19 1,552 91 18 1,942 91 18 1,851 91 18 1,796 91 18 2,364 91 18 2,298 * 91 18 Total Project Schedule Financing 1,695 1,636 1,637 1,678 1,675 1,635 1,626 1,662 2,051 1,960 1,905 2,473 2,408 Total Capital Cost and Financing 6,113 6,054 6,032 6,092 6,083 6,095 6,085 6,201 6,850 6,759 6,704 7,518 7,453 Notes: No reforecast was filed in June 2013. Details may not add to totals due to rounding. * The Total Current Forecast for Return on CWIP in Rate Base includes $55 million of AFUDC accrued on CWIP above the original certified cost. 7 2. A description of any cooperative actions between other builders of nuclear units in the southeast to address labor, crafts, engineering and management requirements. As reported in previous VCM reports, SNC continues to actively participate as a member of APOG LLC (“APOG”) with other members, Progress Energy Carolinas, Florida Power & Light, Duke Energy, NextEra and South Carolina Electric and Gas Company (“SCE&G”) to support multiple engineering, licensing, quality assurance, operational readiness and training initiatives. To the extent allowed by the restrictions of the EPC Agreement, the Company has also engaged with SCE&G on the peer-to-peer level in each functional area of the oversight organization to ensure alignment and to utilize lessons learned and best practices. For example, SNC and SCE&G often participate in joint quality assurance audits and oversight surveillances of the Contractor. SNC and SCE&G construction personnel share construction lessons learned and best practices. Engineering and licensing personnel from the two companies communicate regularly to ensure alignment on resolution to standard design challenges, and also communicate potential impacts to licensing requirements. Collaboration with the SCE&G Inspections, Tests, Analyses, and Acceptance Criteria (“ITAAC”) team is ongoing and is resulting in identification and sharing of best practices to support implementation of an effective and streamlined ITAAC program. The level/status of cooperative actions between SNC and SCE&G on cyber security is currently being evaluated, and will be incorporated in a future VCM report once it is more clearly defined. 8 3. An explanation of how the indices used in the EPC contract are tracking. There has been no change in the status of this item since the Eighth VCM Report. 9 4. Omitted per 9th/10th VCM Order. 10 5. The status of the Company’s loan guarantee application at the Department of Energy and to the extent that application is granted, then the Company shall also report on the impact it has or would have on the final expected in-service cost of the units. Available $3.46 Billion Received $1.80 Billion Remaining $1.66 Billion The Department of Energy (“DOE”) Loan Guarantee does not have a material impact on the inservice cost of the units, but it does provide benefits to customers through lower financing costs during construction and for many years beyond. 11 6. Whether the Company is using trust preferred financing and the impact it has or would have on the expected in-service cost of the units. There has been no change in the status of this item since the Sixth VCM Report. 12 7. The extent to which the Company is using short term debt and the impact it has or would have on the expected in-service cost of the units. There has been no change in the status of this item since the Third VCM Report. 13 8. An update of the estimated in-service cost and projected date of commercial operation of both units. The in-service Total Construction and Capital Cost forecast and in-service dates did not change since the 12th VCM Report. The in-service Total Construction and Capital Cost forecast remains $5.045 billion and the in-service target dates for Units 3 and 4 are June 2019 and June 2020, respectively. The Contractor stated that it is developing mitigation strategies to overcome the negative float in the most recent IPS. 14 9. A description of all major sources of changes (both increases and decreases) to the in-service cost and sources of change in commercial operation dates, if any. There has been no change in the status of this item since the last reporting period. 15 10. Omitted per 9th/10th VCM Order. 16 11. The status of all other significant permits and licenses required from other governmental agencies. All other required permits and licenses have been approved or are on track to be approved to meet construction need dates as shown in the Permits Update filed monthly with the Commission. The status for the Reporting Period can be found in the June 2015 Monthly Status Report. 17 12. The status of Engineering, Procurement, Construction and Operational Readiness. A. Engineering Westinghouse reported nuclear island civil/mechanical design completion. CB&I continued activities to complete the civil/mechanical design in the following buildings: turbine, annex, radwaste and diesel generator. Contractor continued activities to complete Instrumentation and Controls (“I&C”) and electrical design. Redesign and lack of constructability reviews continue to impact construction activities. Design errors caused delays on critical path items and required the Company to pursue License Amendment Requests (“LARs”). B. Procurement The Company continues its oversight of the fabrication of major equipment at international and domestic vendor locations and directs close attention to challenges associated with design and/or testing to ensure those are adequately resolved before installation. Component Accumulator Tanks Containment Vessel Components Core Makeup Tanks Core Makeup Tanks Deaerators Diesel Generators Integrated Head Package Integrated Head Package Main Step-up Transformers Main Turbine Generator Moisture Separator Reheater Passive Residual Heat Removal Heat Exchanger Polar Crane Pressurizer Reactor Coolant Loop Piping Reactor Coolant Pumps Reactor Vessel Reactor Vessel Internals Reactor Vessel Internals Reserve Auxiliary Transformers Squib Valves Steam Generators Steam Generators Unit 3&4 3&4 3 4 3&4 3&4 3 4 3&4 3&4 3&4 3&4 3&4 3&4 3&4 3&4 3&4 3 4 3&4 3&4 3 4 18 Status On-site On-site On-site In Fabrication On-site On-site On-site In Fabrication On-site On-site On-site In Fabrication In Fabrication On-site On-site In Fabrication On-site On-site In Fabrication On-site In Fabrication On-site In Fabrication Support Schedule Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Reactor Coolant Pumps The engineering and endurance test for China’s first Reactor Coolant Pump (“RCP”) is complete. o Design modifications were incorporated into the pump components and endurance testing showed no indications of bearing material in water samples. o Disassembly and further assessment of the pump is ongoing. Squib Valves Completed eight-inch valve submergence test and functional test. o Inspection found no internal leakage. Photo 1 – Unit 3 Reactor Vessel Internals Arrive at the Site Structural Modules Unit 3 CA01 Completed approximately 25,000 linear feet of welding that supported the setting of CA01 in August 2015. Unit 3 CA03 Eight of the 17 sub-modules have been upended and four weld seams have been completed. Specialty Maintenance & Construction, Incorporated (“SMCI”) remained under Quality Ratings List (“QRL”) restriction that was issued by CB&I. The Company and CB&I continued implementation of enhanced inspections. o The Company is working with the Contractor to establish a mitigation plan to ensure sub-module deliveries meet construction need dates. The Unit 4 CA03 work was transferred to CB&I Lake-Charles who has shown quality improvements. Unit 3 Shield Building 81 of 167 panels on-site. Continued pre-concrete placement activities. Installed 18 shield panel supports for west side shield building transition panels. 19 Completed approximately 5,900 feet of seam welding. A focus area continues to be Newport News Industrial (“NNI”) productivity and delivery schedule. Photo 2 – Shield Building Panels Unit 4 CA01 Fabrication scope for CA01 is split between Toshiba and IHI. Four of 47 sub-modules on-site. Fabrication continues on 12 CA01 sub-modules. A focus area continues to be sub-module productivity and delivery schedule. Unit 4 CA20 Photo 3 - Unit 4 CA20 in the MAB Fabrication scope for CA20 is split between CB&I-Lake Charles and Vigor Works, formerly known as Oregon Iron Works. 30 of 72 sub-modules on-site. Commenced upending sub-modules. o Two sub-modules upended. Commenced seam welding. A focus area continues to be submodule productivity and delivery schedule. 20 C. Construction Unit 3 Nuclear Island Photo 4 - Unit 3 Nuclear and Turbine Islands Significant progress made during the Reporting Period. o Placed approximately 1,900 cubic yards of concrete. o Installed approximately 430 tons of rebar. Placed concrete inside the Containment Vessel Bottom Head (“CVBH”) to elevation 83 feet providing the foundation for the CA01 module. Placed concrete in the CA20 construction joint, also known as “the wedge.” Placed concrete outside the CVBH to elevation 87 feet 6 inches. Continued installation of rebar and embeds outside the CVBH in preparation of concrete to elevation 94 feet and 90 feet 6 inches on the west and east sides of the containment vessel, respectively. Commenced floor and wall coatings and setting of mechanical modules in Unit 3 Auxiliary Building. Began Unit 3 Auxiliary Building east Photo 5 – Unit 3 CA01 Being Set in Nuclear Island wall placement to elevation 100 feet to allow for Annex Building construction. Although outside the Reporting Period, a significant milestone was achieved on August 8, 2015 when structural module CA01 was set inside containment. o CA01 will house the steam generators, pressurizer, and refueling canal. o The 70 feet tall and 80 feet wide module is the heaviest module at more than 1,100 tons. Continued concrete placement performance is a focus area. 21 Unit 3 Turbine Island Completed work activities on schedule. o Placed approximately 280 cubic yards of concrete. o Installed approximately 65 tons of rebar and 1,300 tons of structural steel. Set multiple pieces of equipment including the start-up feedwater pumps and the high pressure feedwater heaters. Completed the turbine building structural steel and concrete floors at elevation 120 feet. Commenced rebar installation for first bay walls to elevation 122 feet. Began rebar and form work for the turbine generator pedestal at elevation 160 - 170 feet that supports the beginning of the turbine and generator installation. Photo 6 - Unit 3 Turbine Island Building Unit 3 Annex Building Proactive planning supported significant progress to elevation 154 feet. o Placed approximately 3,550 cubic yards of basemat concrete for Areas 1, 2 and 3. o Installed approximately 740 tons of rebar. o Erected approximately 250 tons of structural steel in Areas 1 and 2. Progress on Annex Building activities support initial energization. Photo 7 - Unit 3 Annex Building 22 Unit 3 Cooling Tower Began installation of the internal precast supports and columns. Completed installation of permanent handrails, permanent lighting and access ladder. Unit 4 Nuclear Island Photo 8 - Unit 4 Nuclear and Turbine Islands Continue to implement lessons learned from Unit 3. o Placed approximately 1,450 cubic yards of concrete. o Installed approximately 45 tons of rebar. Set the reactor vessel cavity module, CA04, inside the CVBH. Continued activities in preparation for interior and exterior concrete wall placements. Continued rebar installation for the exterior walls up to elevation 100 feet. Placed concrete on the north auxiliary building wall to elevation 100 feet to allow turbine building first bay construction to commence. Photo 9 - Unit 4 CA04 set in Nuclear Island Containment Island Walls to Elevation 100 feet 23 Unit 4 Turbine Island Made significant vertical progress. o Placed approximately 2,500 cubic yards of concrete. o Installed approximately 500 tons of rebar. o Erected approximately 650 tons of structural steel (CH81A, CH81B and CH82). Set two of three condensers and set the auxiliary boiler on the base slab. Installed condensate pumps and began installation of the main feedwater pumps. Photo 10 - Unit 4 Turbine Island Unit 4 Cooling Tower Transferred formwork from Unit 3 to resume vertical construction activities. Vertical construction is at approximately 150 feet. Balance of Plant SNC personnel transitioned into Office Building (Building 301) after taking ownership from the Contractor. Substantially completed construction on the Engineering and Administrative Building (Building 302) and the Maintenance Building (Building 303). Turnover activities to begin later in the year. Continued construction on the Receiving Warehouse (Building 306) and the Warehouse (Building 307). Transmission/Switchyard Completed work activities on schedule without impacting Vogtle Units 1 and 2. Completed reconstruction of existing Unit 1 230kV and Unit 2 500kV switchyards to facilitate integration of Units 3 and 4 into the overall Plant Vogtle system. Added two 500kV bus tie lines between the Unit 4 switchyard and Unit 2 switchyard. 24 Completed modifications to four existing 230kV lines to provide required clearance for construction of the Unit 3 230kV output line. Commenced overhead construction in the Unit 4 500kV high voltage switchyard. Photo 11 - Unit 4 500kV Switchyard Licensing Company received several LAR acceptance letters from the NRC that support the construction schedule. Company submitted LAR-15-009 to the NRC requesting use of the year 2000 welding code (AWS D1.1-2000) in lieu of the year 1992 welding code (AWS D1.1-1992). o Different versions of steel weld code were used in the Contractor’s design documents (AWS D1.1-2000) as compared to the NRC approved licensing basis (AWS D1.1-1992). o The Company received a no objections letter from the NRC in response to a Preliminary Amendment Request (“PAR”) submitted by the Company. A combined license holder in the construction stage may identify the need for a change that is necessary in a short timeframe in order for the construction to continue to comply with the approved design. The NRC may make a finding of “no objections” to proceeding with the change “at risk.” LAR 111 is being developed in response to a similar issue that was addressed in LAR 15009 involving weldable threaded rebar couplers. o Couplers were not in conformance with ACI 349 code requirements for weld strength. o Contractor issued a self-imposed Stop Work Order on areas affected by this issue and currently releasing work on an as evaluated basis to allow activities to proceed. o Activities are ongoing to submit LAR 111 to the NRC. The Company will likely pursue a PAR. 25 Status of Major Dispute with Contractor On March 10, 2015, the Court of Appeals affirmed that litigation will continue in the Southern District of Georgia. Discovery and other pre-trial preparation activities are ongoing. D. Operational Readiness Building the Operational Readiness Organization Operational readiness continues to manage resources by using personnel for augmented construction compliance oversight and start-up activities, in addition to continuing required operational readiness activities. o This increases knowledge about the Facility’s construction and installed components that will provide benefits during future O&M activities. Four classes comprising a total of 85 reactor operator and senior reactor operator candidates have completed various phases of rigorous classroom and simulator training. The NRC initial examination scheduled to occur in November 2015 has been postponed. The primary factor for postponing is completing the in-plant Job Performance Measures requirement. o Postponing the initial examination does not jeopardize the in-service dates of June 2019 and June 2020 for Units 3 and 4, respectively. Engineering, Maintenance, Chemistry and Training staff continue to perform work activities and maintain proper qualifications. Digital Instrumentation and Controls Completed Integrated System Validation (“ISV”) testing. o Test program that lasted eight weeks validated the Human System Interface (“HSI”) design of the AP1000 main control room. o ISV demonstrated that plant personnel can perform required operator actions within the HSI design. o Issues identified during ISV are being evaluated for characterization and resolution. The current status of the ISV resolution prevents the Plant Reference Simulator (“PRS”) from supporting the NRC license examinations. SNC is pursuing the allowed NRC Commission Approved Simulator (“CAS”) option that supports the first NRC license examination. Continued factory acceptance testing of the digital control system. Cyber Security The NRC issued a new cyber-security rule in 2009. The new rule imposes new requirements aimed at protecting the nuclear plant digital computer and communication systems and networks against cyber attacks and will result in a number of first-of-a-kind activities. 26 Efforts are ongoing to develop and implement required protections, as well as mitigate potential impacts to the project cost and schedule resulting from compliance with the cyber security rule. Commercial arrangements are in progress to perform the work. The cyber security team initiated planning meetings with the NRC during the first half of 2015; the focus of these meetings is to provide input to industry guidance documents for implementation of the cyber security rule. Interaction and alignment with the NRC will continue through implementation of the cyber security program. Programs, Processes and Procedures The Company has developed an integrated operational readiness schedule that contains over 50,000 activities representing training, program development, and procedure development. o Programs, processes and procedures are being developed and completed. o Initial scoping and classification of over 70 percent of the station systems has been completed for the Equipment Reliability Program. The configuration management software that aids the design authority transition was placed into service. Testing, Turnover, and Start-up The Joint Test Working Group approved procedures that make up the Vogtle ITP Administration Manual (“VIAM”). Readiness review challenge for Pumphouse and Switchgear Building (Building 315) turnover and acceptance was performed. ITP personnel observed Hot Functional Testing at Watts Bar Unit 2. Maintenance Technicians, System Engineers, and Reactor Operators are preparing to begin observations of Chinese AP1000 units testing and start-up during the fourth quarter of 2015. Integrate the Four Unit Site Progress was made on the Vogtle 1-4 emergency plan with submittal to the NRC scheduled for August 31, 2015. Continued development of emergency planning training material. Continued development of security target sets and defensive strategies. Developing the interface design changes necessary to tie civil, electrical and mechanical systems between Vogtle 1-4. 27 13. Omitted per 9/10 VCM Order. 28 14. An updated comparison of the economics of the certified project to other capacity options. The economic evaluation presented in this 13th VCM Report is based on the same underlying major planning assumptions used in the 12th VCM Report. The estimate of the capital cost to complete the Facility has been updated from the 12th VCM Report along with pre-in-service O&M and post-in-service O&M. Projected post-in-service ongoing capital additions, nuclear fuel, spent fuel storage cost estimates, decommissioning costs and the assumed operating characteristics of the Facility have not changed. The long-term marginal financing rates for debt and preferred stock have been updated to reflect current expectations. The analysis demonstrates that completing the Facility remains the best cost option for our customers. Table 14.1 Relative Savings of the Facility versus CC as of August 31, 2015 “Incremental Cost to Complete” (In 2016 Dollars) (Net present value of lifetime costs of CC minus the Facility) Fuel \ CO2 Existing CO2 Moderate CO2 Substantial CO2 High $4,429,000,000 $5,247,000,000 $6,397,000,000 Moderate $2,272,000,000 $3,338,000,000 $4,460,000,000 Low $1,339,000,000 $2,456,000,000 $3,541,000,000 Positive number means the Facility is less costly than the gas-fired CC alternative. 29 Table 14.2 Relative Savings of the Facility versus CC as of August 31, 2015 “Break-Even Cost to Complete” (In 2016 Dollars) (Maximum Cost to Complete the Facility and Remain Economic) Fuel \ CO2 Existing CO2 Moderate CO2 Substantial CO2 High $5,826,000,000 $6,455,000,000 $7,340,000,000 Moderate $4,166,000,000 $4,986,000,000 $5,850,000,000 Low $3,449,000,000 $4,308,000,000 $5,143,000,000 If the value is higher than the current estimated cost to complete of $2.4 billion of in-service and construction financing costs, the Facility benefits customers. On an expected value basis, the Company’s results indicate that the cost to complete the Facility could increase by $2.9 billion over the current estimated cost to complete the Facility before becoming uneconomic. (This value can be derived by averaging the results from the nine scenarios above and then subtracting the current estimated cost to complete). Table 14.3 Relative Savings of the Facility versus CC as of August 31, 2015 June 2021 / June 2022 In-service (24 Month Delay) Scenario “Break-Even Cost to Complete” (In 2016 Dollars) (Maximum Cost to Complete the Facility and Remain Economic) Fuel \ CO2 Existing CO2 Moderate CO2 Substantial CO2 High $5,782,000,000 $6,379,000,000 $7,217,000,000 Moderate $4,200,000,000 $4,966,000,000 $5,779,000,000 Low $3,504,000,000 $4,315,000,000 $5,092,000,000 If the value is higher than this scenario’s estimated cost to complete of $3.1 billion of in-service and construction financing costs, the Facility benefits customers. 30 Table 14.4 Relative Savings of the Facility versus CC as of August 31, 2015 June 2022 / June 2023 In-service (36 Month Delay) Scenario “Break-Even Cost to Complete” (In 2016 Dollars) (Maximum Cost to Complete the Facility and Remain Economic) Fuel \ CO2 Existing CO2 Moderate CO2 Substantial CO2 High $5,896,000,000 $6,491,000,000 $7,299,000,000 Moderate $4,362,000,000 $5,105,000,000 $5,894,000,000 Low $3,674,000,000 $4,467,000,000 $5,213,000,000 If the value is higher than this scenario’s estimated cost to complete of $3.4 billion of in-service and construction financing costs, the Facility benefits customers. Table 14.5 Relative Savings of the Facility versus CC as of August 31, 2015 June 2023 / June 2024 In-service (48 Month Delay) Scenario “Break-Even Cost to Complete” (In 2016 Dollars) (Maximum Cost to Complete the Facility and Remain Economic) Fuel \ CO2 Existing CO2 Moderate CO2 Substantial CO2 High $5,999,000,000 $6,599,000,000 $7,381,000,000 Moderate $4,523,000,000 $5,245,000,000 $6,008,000,000 Low $3,843,000,000 $4,624,000,000 $5,340,000,000 If the value is higher than this scenario’s estimated cost to complete of $3.7 billion of in-service and construction financing costs, the Facility benefits customers. Economic Analysis Conclusion / Summary of Results In summary, all scenario studies indicate that the Facility would remain economic despite the additional costs associated with the delay scenarios. In the delay scenarios, the Facility remains less costly than the next best fuel alternative and will continue to benefit customers. These scenarios do not represent the Company’s projection for the ultimate outcome of the project but instead represent the delay scenarios ordered by the Commission in the Eighth VCM proceeding. 31 15. The Company will be under a continuing obligation to supplement its response to PIA Staff DR STF-TN-1-2 by ensuring that the financing data reflected in the schedules attached to that DR response reflect the most current and updated information at the time of each semiannual monitoring report. In addition, the Company will provide the most current information shared with each of the Rating Agencies. Simultaneous with this filing, Georgia Power has filed supplemental PIA Staff DR STF-TN-1-2, and has included in that filing the most current information shared with each of the Rating Agencies. 32 33
© Copyright 2026 Paperzz