The Lesotho Highlands Water Project (2003) and Laos’ Nam Theun 2 Dam (2003 with 2005 updating) (Unpublished T.Scudder Manuscript) Introduction Through 1989 most of my policy-relevant work relating to river basin development had been as a consultant for either United Nations agencies or the US Agency for International Development. That year, however, a new opportunity arose to provide advice to the Lesotho Highlands Development Authority as a member of an independent panel of experts dealing with environmental and social issues. In 1993 I was asked to join a similar panel dealing with China’s Longtan dam followed in 1997 by one on Laos’ Nam Theun 2 (NT2) dam. All three panels were World Bank Group requirements for financial assistance and/or financial guarantees. Only the Lesotho Highlands Water Project will be assessed in detail. Though the Longtan panel made its initial visit in 1993 during the planning phase, subsequently World Bank participation, as well as the panel’s, stopped, with the Government of China relying thereafter on its own resources. I considered that unfortunate since Longtan had the potential to benefit project affected people provided good planning was implemented. Though NT2 construction only began in 2005, the fact that planning is state-of-the-art, and involves a number of important issues like interbasin transfers, warrants analysis. Along with Kariba and Mahaweli, the Lesotho Highlands Water Project (LHWP) is one that I have followed closely over an extended time period, with one or two annual visits until I resigned from the panel in 2002. 1 Initiated by two pariah governments, South Africa’s Nationalist Party and a military dictatorship in Lesotho, I considered LHWP to be controversial and problem-prone. On the other hand, I considered its major goals to be in the macro-economic interests of both countries. That conclusion was reinforced after South Africa’s Independence in 1994 at which time the project received the support of President Mandela and the African National Congress. Though Kader Asmal, the government’s new Minister of Water Affairs and Forests, opposed the project before Independence, he supported it throughout his tenure as Minister. As with Longtan and NT2, my willingness to join expert panels in the Lesotho Highlands Water Project case was based on two assumptions. The first was that each project had the potential to help a majority of affected people. The second was that as a member of a panel I would have more influence than as a consultant. That assumption has proved to be the case to varying extents. Whether or not the single visit to Longtan has been influential remains to be seen. Though the Lesotho Panel can point to some achievements in the environment area, effects on human well being have been disappointing in regard to both 1 I resigned in April 2002 in large part because I suspected that the Panel’s clout, and that of the World Bank, would be significantly reduced after the completion of the Mohale Dam. 1 the Katse Dam (completed in 1995) and the Mohale Dam (completed in 2002). While the NT2 Panel can point to positive achievements, construction only began in 2005. Panels of Independent Experts on Environmental and Social Issues Unlike long standing dam safety panels composed primarily of engineers and geologists, panels dealing with environmental and social issues were only pioneered by the World Bank Group in the late 1980s and then primarily for their more contentious projects, most of which have continued to involve dams. More recently regional banks such as the Asian Development Bank have also begun to require them. Through technical assistance grants, funds are provided to government agencies that select the necessary international expertise. Though the World Bank must approve those selected, as well as their release, each panel reports to the government agency that hires it. While those agencies also provide terms of reference, the panels have the authority to examine whatever other issues their members may consider relevant. All panel reports are expected to become public documents once the project authority’s comments have been considered. Rejected comments should be incorporated within an annex along with the panel’s reasoning. While the strength of such panels is their independence and the expertise of their members, they also have major weaknesses. One is the fact that visits to the project area are limited to one or two a year and are of two, and occasionally three, weeks duration. The short exposure makes it difficult to follow-up on actions taken on previous recommendations and to examine results where such recommendations have been acted upon. Visits invariably are hectic with members working through weekends. During their in-country stay it is rare for panel members to spend more than three to four days in the field. The first few days tend to be spent reading reports, making courtesy calls, and being briefed on what has happened, or not happened, since the previous visit. Following the field trip, reports must be written before members depart so that the results can be discussed with the project authorities. That is important not just because members tend to emphasize other priorities once they leave but also because project authorities themselves are too busy to pay much attention to reports, even if they wanted to, once panel members depart. A panel’s clout is also influenced by its relationship to the funding agency and to how that agency is involved with the project and the project authorities. While the influence of the panel and the funding agency can be considerable when they work together, it is affected by the nature of the funding agency’s financial involvement in the project. With the Lesotho Highlands Water Project, the World Bank’s loans relate only to the construction phase. That is worrisome since project impacts on the environment and on affected people can be expected to continue well after the end of construction. Those impacts require monitoring so that corrective action can be taken where necessary. But where loans have been drawn down and project completion reports submitted, it is to be expected that both the influence of the funder and the panel would be reduced. The obvious solution would be to complement the funding of infrastructure with funding of a project’s environmental and social components. To the Bank’s credit a social and 2 environmental component was initiated within the NT2 project area prior to the appraisal of the main project. The Lesotho Highlands Water Project The main purpose of the binational Lesotho Highlands Water Project is to supply high quality water to South Africa’s Gauteng Province and industrial heartland (focused on Johannesburg and Pretoria) for industrial, commercial and residential use. Worsened by a series of severe droughts since the 1981/82 rainy season, water is South Africa’s scarcest natural resource. 65 percent of the country receives less than 500 mm annually which is the minimum for rain-fed agriculture. Though South Africa suffers from floods during periods of intense rainfall, annual evaporation, on the average, is well in excess of rainfall. Water scarcity is exacerbated by poor aquifers that contribute only about 15 percent of available water supplies (LHDA POE 1995b). I believed the project could play an important role as a supplier of water critically needed to ensure South Africa’s stability and development, and that in turn could play an important role in the stability and development of southern and central Africa. Revenue from the sale of that water, along with remittances from workers laboring in South Africa, could be expected to provide Lesotho with its major source of revenue. Deposited in a trust fund, that revenue is to be used for poverty alleviation and national development. En route to South Africa the water would also provide a second major benefit by generating enough electricity to make Lesotho self-sufficient. Distribution of water to South Africa and generation of electricity for Lesotho were stipulated as the project’s major goals. During their implementation the project authorities “shall effect all measures to ensure that members of local communities in the Kingdom of Lesotho, who will be affected by flooding, construction works, or other similar Project related causes, will be enabled to maintain a standard of living not inferior to that obtaining at the time of first disturbance” (1986 LHWP Treaty: 27). As for the environment, “The Parties agree to take all reasonable measures to ensure that the implementation, operation and maintenance of the Project are compatible with the protection of the existing quality of the environment” (ibid: 71). That wording was compatible with existing World Bank Guidelines. Though I did not realize it at the time, arguments (discussed in detail in the paragraphs that follow) over how to maintain living standards and the existing quality of the environment have continued to threaten the achievement of even those minimal goals. The Project As approved in 1986, the Lesotho Highlands Water Project was to be a thirty-year scheme for exporting surplus Lesotho water 2 to water-scarce South Africa. Five large dams were to be built during three project phases. During Phase 1A the 182 meter high 2 On completion Phase 1would divert to South Africa approximately 25 percent of the water in the Lesotho portion of the Senqu-Orange river system that is the largest in Southern Africa south of the Zambezi. 3 Katse Dam would be built from which 16.8 cubic meters per second (m³/s) of water would be diverted through a 48 kilometer tunnel and hydropower plant that would generate 72 megawatts for distribution within Lesotho. Water emerging from the plant would be channeled into a reservoir backed up behind the second dam – the 55 meter high ‘Muela dam from which water would be delivered through a 16 kilometer delivery tunnel to South Africa’s Ash River and on to Gauteng Province. Total costs were estimated at US $2.4 billion including a $110 million World Bank loan. Katse was completed during 1995, with its reservoir filling during the 1995/96 rainy season. The first water was transferred to South Africa in January 1998 with the first electricity distributed later that year. During Phase 1B the 145 meter high Mohale Dam was built with reservoir water delivered to the Katse reservoir through a 32 kilometer tunnel designed to carry 9.6m³/s. A further 2.2m³/s would be diverted into the Katse reservoir via a 5.6 kilometer tunnel drawing water from a small reservoir backed up behind a 15 meter high weir at Matsoku. Total costs were estimated at $1.124 billion including a $45 million World Bank loan. Construction on Mohale began in March 1998 with dam closure in October 2002. Due to reduced water demand in South Africa, the second and third phases have been postponed indefinitely. If initiated, Phase 2 will focus on the construction of the Mashai Dam on the Senqu River from whose reservoir water would be pumped up into the Katse reservoir. Phase 3 would involve construction of the Tsoelike Dam below Mashai with water pumped into the Mashai Reservoir. No estimates exist as to the number of people who would require physical relocation if all three phases were completed, but the total population affected by Phase 1 approaches 200,000. Of these about three-fourths are residents of downstream communities affected by radically reduced Senqu River flows. Another 30,000 villagers in reservoir catchment basins, though not requiring physical removal, would be adversely affected by loss of winter grazing as well as loss of thatching grass, fuelwood, medicinal plants and other common property resources. Phase 1A affected 133 villages in the Katse and ‘Muela local catchments of which 121 were in the Katse area. Because ‘Muela project works required no physical removal with less than 100 households losing arable land, and because of the scattered nature of the hundreds of households that lost fields to, or had to move back from, project roads and transmission lines, the emphasis in this chapter will be on the Katse and Mohale Dams. 3,357 households, averaging between five and six members, lived within the main Katse impact areas. Approximately one-third lost some arable land to the project with approximately 10 percent losing all their fields. Loss of at least 3,000 hectares of grazing and other common property resources affected approximately 90 percent. Though the large majority of households were poor according to any standard, some were more vulnerable than others. 13 percent, for example, owned no fields, being dependent on share cropping or loan of arable land, while 20 percent owned no livestock. The proportion of female-headed households was approximately 30 percent, with those headed by elderly widows being especially vulnerable. 4 In the main Mohale impact area an estimated 700 households in 84 villages will lose about 725 hectares of arable land, with the Project reducing grazing land, including the most valuable winter grazing, by approximately 1,635 hectares. Katse reservoir filling involved the resettlement of 73 households, while physical removal due to Mohale project works and reservoir filling can be expected to involve up to 400 households. South Africa as the main beneficiary must pay for most project costs aside from the ‘Muela hydropower plant and associated transmission lines and any costs to improve, as opposed to restore, the living standards of affected households. South African costs also include the range of social and environmental impacts caused by water transfer. Project planning and implementation required a complex organizational structure. In Lesotho the responsible agency created under the treaty was the Lesotho Highlands Development Authority (LHDA), while in South Africa the responsible agency was the Trans-Caledon Tunnel Authority. Both reported to the binational Joint Permanent Technical Commission (the Commission) that included three delegates from each nation as well as alternates, a joint secretary, and separate secretariats based in Maseru, the capital of Lesotho. As stipulated in the 1986 Treaty, both Authorities were required to obtain the approval of the Commission for, among other items, budgets (including allocation of costs between the two countries), design of project infrastructure and all tendering procedures, implementation plans for each phase, annual and short term operational and maintenance plans, and appointment of staff, auditors, consultants, contractors and other senior personnel (including members of the World Bank-required Dam Safety and Environmental Panels) In 2000 the Commission was reorganized, though keeping essentially the same personnel, as the Lesotho Highlands Water Commission. Reorganization followed from an organizational study that was contracted to advise on the project’s gradual shift from a constuction to a operations and maintenance mode of activity. Hence forward the Commission was also supposed to be more policy-oriented as opposed to its previous tendency to micro-manage certain LHDA planning and implementation activities, and especially those of the Environment and Social Services Group (ESSG). Lesotho National Setting Lesotho, a small country about the size of Maryland in the United States, is surrounded by South Africa. The terrain is mountainous with more than 80 percent above 1,800 meters. There are, however, three agro-ecological zones: the lowlands along the western border with South Africa, the foothills and the mountains. During the winter months several feet of snow may accumulate in the highlands that are Lesotho’s most characteristic feature and which reach a high point of 3,482 meters. Pasture dominates about two-thirds of the Lesotho landscape with arable land approximately ten percent and restricted primarily to the lowlands. Over 95 percent of a population of 2.2 million belong to a single ethnic group – the predominantly rural Bantu-speaking Basotho who increasingly are moving to the urban 5 centers and peri-urban areas of the lowlands. Livelihoods in the rural areas affected by the Lesotho Highlands Water Project are multi-stranded, with households combining agricultural and herding strategies with wage labor. Though the role of agriculture is declining, with few households growing enough to meet their annual needs, agriculture is still important. So too is livestock management, but there also household reliance on their animals has been reduced by “a rapid increase in stock theft…The result is that the poorest of the rural households lose their insurance policy in animals” (Sechaba Consultants 2000: 28). The third major component of the household economy, wage labor, is also in decline because of South Africa’s gradual replacement of Lesotho’s workers in the mines and elsewhere in the economy with South African labor. Though Lesotho has been able so far to avoid the large peri-urban shanty towns that surround other Southern and Central African countries, poverty has been increasing since 1990 with 68 percent of the population defined as poor in 2000 and two-thirds of the poor living in destitution “with barely enough cash income to satisfy basic food needs” (ibid: 3). Basotho formerly lived primarily in what became the Orange Free State from which they were pushed into Lesotho’s lower elevations by European settlers and military forces. Initially they cultivated the lowlands and grazed their cattle during the summer months in the highlands where the Katse and Mohale dams were to be built. But as the population increased, some villagers began to live throughout the year in the mountains until all the best alluvial deposits in the upper catchments of the Senqu/Orange River system were being utilized. With the arrival of the Highlands Water Project in the 1980s, the population living in the Katse and Mohale catchments, as elsewhere in the mountains, was the poorest in the country (ibid), while such social services as schools and clinics were the least developed. By national standards, out-migration was high with the constituency including the Mohale Dam site having the highest out-migration rate in the country in 1990. Ongoing political turmoil since shortly after independence in 1966 has been partially responsible for increasing national poverty along with major changes in the South African economy that have reduced employment opportunities for migrant laborers. Under such circumstances, a legitimate question is whether or not this small country, which also is one of the 50 poorest in the world, has the institutional capacity to plan, implement and maintain the social and environmental components of one of the five largest infrastructure projects currently under construction in the world. Such doubts concerning institutional capacity partially explain the micro-management approach of the Commission. Feasibility Studies Feasibility studies were completed during the 1983-1985 period with funding from the European Development Fund. They seriously underestimated the population that would require resettlement. Over 3,000 people were to be eventually relocated in connection with Phase 1 alone; the consultants’ estimate was only 495 while their estimate for all three phases was only 1,365 individuals. A major underestimate was of the number of households to be affected by such advanced infrastructure as project works, transmission 6 lines and roads. The Panel noted such discrepancies during its first visit to Lesotho in 1989. The feasibility studies also seriously underestimated environmental impacts with the project authority subsequently concluding that “there were no major environmental obstacles to the implementation of the project” (LHDA May 1990: iii). That presumably was a major reason why no Environmental Impact Assessment was completed – a fact which NGOs criticized at a later date. Though my responsibility on the Panel related to resettlement issues, my notes during the Panel’s initial 1989 visit also showed concern about possible adverse impacts of reduced downstream flows on communities below the Katse Dam. William Taylor, LHDA’s environmental adviser, who had formerly been the Project Manager, International, for the UNDP/FAO/Ghanaian Lake Volta Research Project, had similar concerns. My concern was reduced by the feasibility study that minimized adverse impacts, noting, for example, incoming tributaries below the Katse Dam and little downstream irrigation, and other local use, within Lesotho. It was also influenced by the belief of knowledgeable in-country experts, with no involvement in the project, that there was little dependence of downstream communities on existing flows. I should have known better than to trust such assurances having published during the 1980s two articles drawing attention to the adverse impacts of large dams on downstream populations. When the necessary instream flow requirement study was finally available in 2000, an estimated 152,000 villagers were said to be adversely affected to varying degrees by Treaty stipulated releases (METSI 2000). Increasing downstream flows significantly to decrease those costs, on the other hand, would have reduced the financial viability of the project. The Panel of Experts In 1988 my colleague, Jonathan Jenness, and fellow graduate student in the 1950s at Harvard University, recommended me as a candidate for the Highland Water Project’s Panel of Experts on environmental and social issues (hereafter referred to as the Panel). At the time he was the UNDP-supplied rural development adviser to what became the Environment and Social Services Group (ESSG) of the Lesotho Highlands Development Authority. In addition to myself, the other panel members selected were Guillermo Cano, former Minister of Water Affairs in Argentina, and Charles Clay, an engineer, who had recently retired as the Coordinator within FAO’s Department of Fisheries of the various UNDP/FAO African man-made lakes research projects. Cano, a lawyer, had already played a role as adviser on the institutional and legal structure of the Lesotho Highlands Development Authority. We arrived in Maseru in January 1989. The next year the Panel was reconstituted with Cano and Clay replaced by two specialists with more extensive Southern African experience. One was John Ledger, chair of South Africa’s Endangered Wildlife Fund. The other was Robert Hitchcock from the faculty of Anthropology at the University of Nebraska. Along with Mike Mentis, a South African ecologist added to the 7 Panel in 1996, the four of us continued to constitute the Panel’s core, with other experts periodically recruited to work with us as panel members, 3 until my resignation. Because of South Africa’s UN-imposed sanctions and Lesotho’s military coup, both countries were out of touch with the content of recent international covenants. As a result, during the Panel’s first visit it was necessary to familiarize the project authorities with the 1987 report of the Brundtland Commission on Sustainable Development and the 1992 Rio Declaration on Environment and Development as well as recent World Bank guidelines on environmental and resettlement issues. Assistance with planning and budgeting was also emphasized during that year and the next. By 1991 and 1992, concern had shifted to the delayed budgeting and implementation of development activities necessary for restoring living standards. Thereafter the Panel dealt increasingly with Phase 1A implementation. Incorporating lessons learned from the Katse experience, Phase 1B planning was added to the Panel’s responsibilities in 1992, followed by the implementation of those plans. With inadequate time to familiarize itself with the Mohale project during 1992, the Panel recommended two visits a year thereafter that has usually been the case. In addition to evaluating planning and implementation activities dealing with the Katse, ‘Muela and Mohale components, the Panel also advised on the planning of additional studies dealing with such topics as reservoir zoning, catchment management, downstream environmental flows, and natural reserves and tourism. To me the Panel’s effectiveness has been disappointing to date especially in comparison with that of the Panel on Laos’ NT2 Project. Part of the reason is due to the Panel’s appointment after the completion of mid-1980s feasibility studies. Unlike their attitude toward the Dam Safety Panel of engineering experts, the project authorities have been ambivalent toward the Panel. For the first five years, for example, panel member contracts were on an annual basis while those of the panel of engineers were multi-year. Longer contracts were essential for a variety of reasons, including ability to set dates for the next year’s visit. Through 1995 Panel members received notice of forthcoming visits with only a three month lead time at best with the result that only two panel members were able to participate on the two 1995 visits. Another reason for the Panel being less effective than it might have been relates to ESSG’s failure to forward relevant documents to members between visits in spite of constant requests. That deficiency contrasts with the Panel’s relationship with the World Bank, with the Bank forwarding to the Panel the reports of its various supervisory missions. Regardless of the reasons, the Panel’s recommendations dealing with broader management issues and the need for a planning culture within the project authorities and the Government of Lesotho have had little influence. What influence that the Panel has had relates to helping the project authorities take more seriously the need for including 3 While the Panel is supposed to include a public health expert, there have been periodic vacancies over the years with the position re-advertised in 2001 and finally filled in 2003. 8 and funding a range of development activities if treaty obligations to restore living standards are to be met. As a result, perhaps the Panel’s greatest social accomplishment is that affected households, if not able to restore their living standards, are at least less poor than they otherwise would have been. At the planning level the Panel has definitely had an impact on individual studies. One example is the 1997-1999 Katse-Mohale-Matsuko instream flow requirement study where the Panel was able to convince the project authorities and the consultants to expand the study to include how use by communities and their livestock of downstream resources could be altered by reduced flows. The resulting study was not only state of the art but also pioneered a broadening of the methodology for dealing with environmental flows. The Katse Dam Introduction From the Panel’s origin, it was clear to me that even restoring the living standards of a majority of people to be affected by the Katse Dam was going to be very difficult. Three reasons that immediately suggested themselves were the scarcity of arable land and grazing to replace gardens, fields and pastures taken by the project, the policy emphasis on compensation as opposed to development, and the insistence of local chiefs that all resettlement must be within the Katse local catchment. Subsequently the positions taken by the members of the Commission, and their efforts to micro-manage planning and implementation relating to environmental and social issues became a fourth major constraint. Implementation capacity within LHDA and associated Lesotho government and other agencies became a fifth. Initial Constraints: Land Scarcity in the Katse Basin and Overemphasis on Compensation The best arable land was the riverine alluvium that would be inundated by the Katse reservoir. The best winter grazing was also within the reservoir basin which provided in addition important shelter to livestock during the coldest months of the year when freezing weather, strong winds, and periodic deep snow created inhospitable conditions in the upland pastures. Because it was assumed that no replacement land was available, those losing fields and household gardens were to receive either cash compensation or a grain ration (to which other foods were subsequently added) during a fifteen-year period after which it was assumed that people would have found other livelihood options. Lost communal grazing was to be replaced by a fodder ration for five years, with the overall loss of common property to communities to be compensated in cash. Though evolving as experience was gained, a limited compensation approach has continued to the present. Its origin dates back to the enabling act establishing the Lesotho Highlands Development Authority that included no mention of the type of development activities that are necessary if living standards are to be restored. As for the 9 “memorandum on compensation policy” that I was shown in January 1989, the words “poor, poor, poor” in my notebook summed up my reactions. The only good aspect that I noted was that the Government of Lesotho “should make an explicit longterm policy commitment to devote a major portion of its revenues from the sale of water … to the welfare and economic development of the communities affected by the project” (LHDA April 1988). At the insistence of the World Bank such a fund subsequently was established though its focus was to be on poverty alleviation at the national level. Reliable mechanisms to ensure that the revenue is, in fact, used for the stipulated purposes remain to be achieved. In regard to the third constraint, it was understandable that chiefs did not wish to lose followers. At the same time, their insistence that people remain within current jurisdictions may also have been influenced by the global preference of resettlers to remain as close as possible to their former homes and to neighbors not required to move. Honoring those preferences in the Lesotho case, however, meant keeping people in an area in which reduced natural resources would not only make it difficult, and in some cases impossible, for households to continue customary activities, but would also reduce the availability of remaining common property resources, grazing in particular, for the host population. Not withstanding these three constraints, I remained hopeful that a majority of affected people within the Katse catchment, as well as those affected by such other project works as roads and ‘Muela, might benefit from the project. Not only did the Environment and Social Services Group have some experienced officials and advisers, but its organization included rural and regional development as well as compensation. At the time of the first Panel visit in 1989 fifteen rural development activities had already been identified for study by consultants. In addition to infrastructure development dealing with feeder roads, rural electrification, village water supplies and sanitation, and construction communities, the activities proposed included land use planning with the people, animal husbandry and range management, mountain horticulture, community forestry, and reservoir fishery. The intent of the range management approach was to divide the Katse local basin into a number of range management associations run by clusters of villages. Mountain horticulture was to include crop components dealing with mountain maize and seed potatoes, fruit trees, and small scale irrigation based on gravity flow from mountain springs. Plans also called for a rural training center that would prepare highland residents for relevant non-farm jobs during the project’s construction and development phases. The Lesotho Highlands Water Commission The Commission as a Constraint The Commission became a constraint on developing the project in the interests of affected people for a number of reasons. One was organizational. As stipulated in the treaty, the Lesotho Highlands Water Project was clearly identified as a water transfer project. On the other hand, the model proposed for the Lesotho Highlands Development 10 Authority had been the Tennessee Valley Authority. In a 1984 paper M.E. Sole, 4 who subsequently became the first LHDA Chief Executive, had proposed that the Authority should be a regional development agency rather than one merely concerned with water transfer and electricity generation. Though financing implementation would require major assistance from international donors, he and other high officials in the Government wanted affected people to become project beneficiaries. That was fine as far as the South African members of the Commission were concerned so long as funding such improvement remained strictly a Lesotho obligation. The composition of the Commission created another problem. Dominated by engineers, the Commission’s members were primarily concerned with achieving the project’s two principal goals on time and without major cost overruns. Due to their engineering mindset, time and again environment and social issues were either ignored or misunderstood. The first draft of the terms of reference for the Organization and Manpower Study dealt entirely with how to convert the Highlands Development Authority from an initial emphasis on the construction of water transfer infrastructure to its operation and maintenance. How to address ongoing environmental issues and responsibilities to restore the living standards of affected people after the termination of the construction phase was ignored, as were the organizational needs of the Environment and Social Services Group. It was the Panel that insisted that those needs be addressed and that the personnel on the study include environmental and social scientists. Where environment and social issues arose, the Commission’s tendency was to view them as engineering problems that could be solved by sticking to predetermined blueprints and budgets. Not realizing, for example, that household formation was a process whereby numbers changed through time and could be expected to increase through marriage and fission, members found it difficult to understand why estimates of numbers of resettling households increased from year to year, while preferences as to where to resettle changed. With their views shared to a certain extent by expatriate members of the Lesotho delegation, as well as expatriate engineers within the Lesotho Highlands Development Authority, the South African delegation also appeared to be primarily interested in the timely physical removal of local villagers from the reservoir basins and associated project works rather than in their rehabilitation. I vividly recall one occasion where one of the South African delegation’s senior advisers and I got into a shouting match during a wrap up meeting because of my insistence that World Bank guidelines, with which he and the Commission were unfamiliar and which included not just physical removal but the rehabilitation of all project affected people, must be followed. Compensation versus Development for Meeting Treaty Goals The biggest problem that the Panel had with the Commission concerned the extent to which compensation alone would suffice to restore living standards as required by the 4 Sole was convicted later of taking bribes and sentenced to 15 years in prison. Subsequently two major firms – Canada’s ACRES International and Germany’s Lahmeyer International – were convicted by the Lesotho judiciary of giving bribes. Trials of other firms continue. 11 1986 Treaty. Jenness and his colleagues in rural development and regional planning insisted that both compensation and rural development initiatives were essential if the Treaty requirements were to be met. In that position they were strongly backed by the Panel. Even though all environmental, resettlement and rehabilitation costs at that time came to less than five percent of project costs, the South African delegation initially rejected the position that South Africa had any responsibility for financing part of LHDA’s Rural Development Plan. The South African delegation claimed that compensation alone would be sufficient to meet their obligations under the Treaty. ESSG’s rural development initiatives, their members claimed, were designed to improve the living standards of affected people and hence their financing should be the responsibility of the Government of Lesotho. They also claimed that certain overall project benefits, such as an improved road system into the Highlands, should be valued as a household restoration benefit, with their cost subtracted from the compensation budget that South Africa was required to finance. They also hired consultants whose terms of reference included careful scrutiny, and cost reduction wherever possible, of all resettlement and rehabilitation activities. That included trying to reduce the amount of grain offered to households losing productive land, even though that compensation package initially was inadequate because it did not include other important dietary components that households received from their fields and gardens. Since the Lesotho authorities did want affected people to become project beneficiaries, confusion existed over the extent to which rural development activities were necessary for restoring living standards. That confusion, in my opinion, made it easier for the South African delegation to dominate policy in ways that seriously disadvantaged affected people. Disagreements that adversely affected the planning, budgeting and implementation of essential development activities for meeting Treaty obligations began before the first Panel visit, when the South African delegation rejected funding any of the 15 rural development planning studies. In hopes of changing that attitude, Panel reports starting in 1989 have regularly explained why restoration of living standards requires both compensation and development. The 1989 report, for example, emphasized that policies which merely attempt to restore living standards at the time of first disturbance, in fact “tend to leave the majority of the population worse off in the short run (three to five years) and a significant proportion (which may continue to be a majority) worse off in the long run.” The report then noted “the tendency to underestimate the complexity of the compensation and rural development components” as well as “the ‘Grey Area’ between compensation and development” that referred to the rehabilitation process “whereby impacted people regain their previous living standard and income at the earliest possible time…It is very difficult to define where compensation costs stop and development costs should begin. Rarely do compensation costs cover rehabilitation. They certainly do not in the LHWP” where the ‘Grey Area’ became a major source of contention between the two delegations. That was because “The Republic of South Africa wishes to keep project 12 costs, including compensation costs, as small as possible, while the Government of Lesotho would like to pass on additional costs wherever possible” (ibid). Panel reports in 1990 and 1991 sounded a much stronger alarm. According to the 1990 report the “Commission …, the Government of Lesotho and the World Bank must all share responsibility for the unsatisfactory start of the compensation and rural development programs. Bearing in mind the proportionately low costs (relative to project costs) of implementing satisfactory environment, compensation and rural development programs, and the unfavorable international public relations impacts that can be expected to follow implementation of unsatisfactory programs, the attempts by the South African delegation and their consultants to reduce, and in some cases eliminate, what are legitimate Republic of South Africa … water transfer costs relating to rehabilitation of the catchment populations, are unacceptable in terms of the World Bank Guidelines but also the LHWP treaty.” Commission and Panel Relationships Relationships Deteriorate: 1991 In 1991 the Panel stated that “…unnecessary delays have stalled implementation of various RDP projects for more than a year…delays in implementing such components … as Rural Sanitation, Village Water Supply, and Construction Communities have actually caused worsening living conditions in certain villages.” Though such delays were attributed to both LHDA and the Commission, the Panel concluded “that protracted arguments within the JPTC [the Commission] 5 over what is compensation and what is rural development have not only been non-productive but also counter-productive because of resulting delays in approval, assignment of financial responsibility, and, especially, initiation of implementation.” The Panel also referred to “unwarranted interference, pressure and criticism from individuals and other divisions within LHDA, and from within the Commission, upon the Environment Division” which were having an adverse effect on morale. Less than a month after receiving the Panel’s August 1991 report both delegations of the Commission asked LHDA to withdraw and repudiate it. The argument given was that “The report clearly demonstrates that the panel was inadequately and wrongly briefed, resulting in unwarranted negative and untrue statements about the Commission” (JPTC 1991). Early in 1992 Panel members also received a letter from the Commission’s Secretariat “to put on record that the Commission takes the strongest exception to the…Panel’s unwarranted criticism of and derogatory comments aimed at the Commission” and that “The Commission dissociates itself from the report, and has requested the LHDA to follow suit” (JPTC 1992). By then, however, LHDA had essentially refused to withdraw the report, requesting instead that the Commission work closely with the Authority in implementing Panel recommendations. 5 The original name of the Commission will continue to be used where it occurs within quotations from references. 13 As the Panel’s senior member and the member responsible for rehabilitation issues (for Hitchcock’s terms of reference related to compensation and cultural heritage), I felt a personal responsibility to clarify to the Commission what I referred to “as misunderstandings.” The main misunderstanding concerned the Commission’s belief that the Panel was merely a pawn of LHDA with no capacity to reach its own conclusions. That I rejected, pointing out that the Panel’s assessment was based not on a single visit but on an ongoing series of visits which provided ample opportunity for the Panel to form its own independent views. I also noted that in addressing our obligation to monitor how the project authorities were following Treaty obligations and World Bank Guidelines, the panel had not singled out just the Commission for criticism but had also included LHDA’s environment section, LHDA itself and the World Bank. One benefit of this dispute was to bring the Panel’s concerns to the attention of senior officials within the World Bank. Though fortuitous, the timing was good since the Bank was still in the process of appraising the Phase 1B project for possible funding. While LHDA was obligated to send Panel Reports to the Bank, the Panel had yet to meet the Bank’s Task Manager responsible for the Highlands Water Project nor had the Panel ever received any comments from the Bank. When I replied to the Commission, I sent, with a covering letter, my letter and the various Commission memos to the Bank’s Senior Sociologist (Michael Cernea), Environmental Adviser (Robert Goodland), and Chief, Infrastructure Operations, Southern Africa Department (Isaac Sam). In his April 1992 reply to me, Isaac Sam wrote “I can assure you that the Bank fully shares the Panel’s concerns regarding the slow implementation of the Environmental Action Plan for this project. To underline our position, I am planning to make a personal visit to Lesotho in the next month to discuss these matters with LHDA management. We are also keeping this issue alive in our country dialogue with both parties to the JPTC.” Relationships Improve: 1992 - 1994 The 1990-1991 period was the low point in the relationship between the Commission and the Panel. During that period, the Commission appointed its own Environmental Advisory Committee 6. Though more critical of Lesotho incapacity (with lack of Lesotho Government funding singled out for special criticism in the Draft Minutes of their October 1992 meeting), their reports tended to support the Panel’s broader concerns such as affected people in Phase 1A becoming worse off as a result of the incapacity of the project authorities to get on with implementation of the rural development program. Panel relationships improved with the Commission during 1992. According to the Lesotho delegation the Panel had played an important role in helping the Commission understand the importance of the rural development component of the resettlement process, the delayed implementation of which was now worrying both sides. A major step forward was the 1992 appointment of Wynand Maartins as alternate delegate to the South African delegation with special responsibility for environment, resettlement and rehabilitation issues. Maartins, an engineer, was a quick learner with whom Panel 6 The Commission’s Environmental Advisory Panel met only a limited number of time before it was phased out. 14 members developed a warm relationship. He attended appropriate ESSG meetings and encouraged ESSG to work closely with the Commission. In the meantime Panel reports continued to criticize slow implementation of the necessary rural development components. The 1992 report noted that “Expected implementation has now fallen two to three years behind schedule,” with the 1993 Report referring to a three year delay in implementing most components. Such delays in the ability of the project authorities to deliver on “promises” were responsible, according to the Panel, for deteriorating relationships with affected people. In April 1995 the Panel reported “Once again the Panel must reiterate its view that even with implementation of the Rural Development Plan, it will not be easy to meet the requirements of the LHWP Treaty and LHDA Order. Each potential development option that is ignored, and especially options that deal with arable land, significantly increases the chances of failure.” The same point was reiterated in June 1996:“Implementation of the Rural Development Plan has been deficient to date in terms of LHDA and Commission responsibilities under the 1986 LHDA Order. This is especially true in regard to restoring the living standards of villages, households and individuals more adversely affected by LHWP implementation.” What influence, if any, the Panel had on the Commission during the 1989 – 1994 period is difficult to pinpoint. Ironically, in the 1991 report to which the Commission objected the Panel had praised the South African Delegation for finally agreeing to fund half of the rural development program. Although still critical of delaying arguments within the Commission as to which government would fund which component and for how much, thereafter the Panel was more critical of the Government of Lesotho’s delays in funding their portion of the program. A major shift in the Commission’s attitude toward the Panel occurred during and following the April and December 1995 missions. At that time the dam was scheduled to be closed in October. New housing for some of the 25 households living in the reservoir basin, however, had yet to be completed. Commission, Panel and NGO Relationships: 1995 Arguing that the likelihood of people being flooded out during the 1995/96 rainy season was slight, the project authorities requested permission from the World Bank to seal the dam on schedule so that a full year’s rainy season inflow would not be lost. The Bank, strongly backed by the Panel, refused: the dam was not to be closed until the replacement houses for all basin residents had been completed and occupied. With the requested closure date only six months away, that was the situation at the time of the Panel’s April 1995 visit during which the Panel played a major role in working out a possible solution. That involved greater participation of Katse villagers in the construction of at least some of their houses. The situation was still lamentable since what was being belatedly achieved was merely the physical removal of affected villages without the necessary social services and development to restore living standards. It was a situation which the Panel later insisted should not be repeated during resettlement and rehabilitation associated with Phase 1B. 15 In the meanwhile local and international NGOs in Lesotho, Europe, South Africa and the United States had requested the World Bank not to proceed with Phase 1B 7 because of the Project’s unsatisfactory record with the resettlement and rehabilitation of Phase 1A households. Referring to local complaints, as well as quoting criticism from Panel reports, the International Rivers Network (IRN) and Environmental Defense (ED), in a September 28, 1995 letter to the World Bank’s Vice President for the Africa Region, also requested that the legitimate concerns of affected villagers be “rectified before impoundment commences.” They ended by stating that “there is an urgent need to halt the LHWP until an independent and cumulative assessment of environmental, social and economic, and technical aspects of the project is brought into compliance with World Bank policies.” I received my copy of the IRN-ED letter shortly after arrival in Lesotho in early October. Though the project authorities had claimed that the necessary houses had been completed, the World Bank insisted on inspecting them before allowing closure to occur. The Bank also wanted an inspection team to include local NGO and Panel representatives, with John Ledger and me representing the Panel. In the field all 25 houses were inspected (I personally visited 24) and proclaimed adequate. The dam was closed on October 20th with the reservoir filling in one year owing to heavy rains. I was very concerned by the content of the IRN-ED letter. While such an assessment was unlikely to add to existing knowledge about the project’s strengths and weaknesses, it would cause long delays in implementation at the expense of South Africa’s water needs. On the other hand, I agreed with most of the letter’s critique that had been taken from Panel reports as well as from legitimate complaints from Phase 1A villagers and the most active local NGO which was the Highlands Church Action Group. During an earlier Panel visit I had sought out local NGOs, including helping the Highland Church Action Group get financial support, and had urged closer cooperation between the project authorities and the NGO community that was belatedly institutionalized in 1999. Especially helpful during those years had been John Gay who was helping Lesotho’s Transformation Resource Centre become a coordinator of the work of local NGOs in the Project area as well as throughout Lesotho. Because I valued their ability to influence project outcomes, I had also established contact with the key people in ED and IRN, sending them copies of Panel reports once they became public documents. On getting the IRN-ED letter I immediately telephoned John Gay at his Maseru home to obtain his opinion and to request that the two of us email EDF and IRN explaining why their request to reassess the project was a mistake. Gay also knew the letter writers, having been visited by them during their trips to Lesotho. The email that he sent warrants detailed quotation because of the skill in which the issues were presented as they relate to large projects like LHWP as well as to NGO involvement. 7 The Panel had recommended that the World Bank proceed with Phase 1B in its August 1994 report. 16 “I am writing you at the urgent behest of Ted Scudder, with whom I just completed a 40minute telephone conversation. He is, as I am, still unhappy about the slow pace of response to the social and economic problems of the people. He is unhappy that it seems to require continual pressure from outside the country to get LHDA to move. That, however, is not Ted’s present concern. He feels that you have moved from a position like his and mine to a position which says, in effect, ‘Kill the whole project.’ He feels, furthermore, that you have gone against what he felt was a community of concern between you, EDF, IRN, himself, and others of us, to support what is basically a sound and helpful project by ensuring that it keeps its promises to people who are being adversely affected.” “Why is the project sound? In our view, the big issue is the economic stability and viability and vitality of the South African economy. If the present experiment (and it is still very much an experiment) of the new South Africa to create a living multi-cultural, multi-racial political economy in the midst of an ailing African continent were to fail, then Africa stands little chance of coming back to its pre-independence or even precolonial economic and political health. Success in South Africa is critical to success in the neighboring economies.” Asking how the preceding relates to the Project, Gay commented on the role that water must play in a developing South African economy: “Ted and I see water as one of the keys to success of the great South African experiment, and we see the LHDA as a critical element in that success… (I)t does not help to take what I call the ‘little Lesotho’ position, in which all that matters is the situation in the mountains of Lesotho. There is an old tradition in Lesotho which looks inward rather than outward, a tradition which tries to ignore the economic and political realities of the larger southern African region. I fear that some of the advice that you are getting relates to the ‘little Lesotho’ tradition. It certainly does not represent a national consensus.” John Gay’s words sum up, I believe, the essential weakness of the stand of NGOs against all large projects. In the Panel’s report on its October visit, Ledger and I also included a similar section on “LHWP in the Context of Southern African Development” in which we quoted President Mandela as stating that “The modern economy of this country could not have grown to what it is today without its large dams…We rely largely on surface water, requiring storage for river flow regulation” (1994). Capacity Issues Capacity issues relate to the Panel as well as to the project authorities and the governments of South Africa and Lesotho. In regard to my own participation, it is one thing, as a scholar, to document the adverse impacts of development-induced resettlement and to produce an analysis that shows that a majority of affected people can become beneficiaries if appropriate opportunities are available. It is another thing to translate that knowledge into appropriate plans and to have the influence to help ensure that those plans are implemented, appropriately monitored, and modified where necessary. More specifically, I failed to apply my knowledge that downstream impacts can be assumed to 17 be negative for affected people in late industrializing countries to the Lesotho case. In 1989 I should have emphasized the necessity for downstream studies. In that regard, Guilliermo Cano was more alert than I when he wrote that “the environmental rights of the Basotho living downstream and outside the LHWP Project area must also be protected by law and by internal rules of LHDA.” In was not until 1996 that a Panel report emphasized the urgent need for commissioning an instream flow requirement study relating to both Phase 1A and 1B, and even then the Panel’s initial emphasis was on ecosystems rather than on both ecosystems and downstream affected communities along with their livestock. Part of the problem in 1989 was that each of us wrote separate report sections under our respective names so that the type of synergism that began with the writing of joint reports in 1992 was weak. As for the Government of South Africa, inadequate capacity within the lead LHWP ministry (the Ministry of Water Affairs and Forestry) to deal with environment and social issues has been an ongoing problem. Another issue about which I feel strongly has been the failure of that ministry and other government agencies to address how LHWP water can be best used in South Africa for employment generation in a country with one of the highest unemployment rates in the world. The Lesotho Highlands Development Authority and the Government of Lesotho have so little capacity that they may well be incapable of dealing with environmental issues and the resettlement and rehabilitation process. Institutional issues may be partly responsible. Back in the mid-1980s both Sole and Cano recommended that LHDA should have been placed within the Office of the Prime Minister to whom its board would report directly. That was a recommendation that Cano repeated during our 1989 visit when he emphasized that LHDA should be placed directly under the Chairman of the Council of Ministers and it is one that my own research supports. Where a single development project dwarfs all others within a country and has major regional development potential, it needs this kind of supervision. Rather than accepting the Sole-Cano recommendation, LHDA was placed under the Minister of Natural Resources. Regardless of the Minister’s competence, such an organizational structure can be predicted to have major liabilities simply because one ministry does not have the clout or the resources to ensure the cooperation of other ministries. When a task force of permanent secretaries from relevant ministries was established in 1992, it was unable to provide the necessary government support because it met infrequently and had no secretariat to keep busy members well informed. Its effectiveness was further diminished by inter-ministerial jealousies due partly to LHDA using higher salaries and the project’s visibility to hire away staff from other government agencies. In the Environment and Social Services Group, for example, three senior staff had been hired away from the Ministry of Agriculture. Another serious problem has been ongoing political instability arising from internal political differences. The 1986 LHWP Treaty and LHDA Order were signed following a military coup in January with no effort made by the government “to allow the public to debate the merits of the massive project and thus gain its support and good will” (Gill 18 1993: 240-41). Though electoral politics were restored with the 1993 election, political crises have continued “that virtually paralysed Government at critical times…Well-laid plans for development were undermined as struggles for political survival took precedence.” This culminated during 1998 in “rioting and looting that seriously damaged the economy” (Sechaba 2000:7). Under such circumstances LHWP, and especially its resettlement and rehabilitation activities, has suffered. Though the Lesotho Highlands Development Authority had been in existence for two years at the time of the Panel’s 1989 visit, the compensation policy had yet-to-be approved by the Government, let alone explained to affected people, even though the first land and houses had been acquired by 1987. Nor had the territorial boundaries of even the Katse portion of the LHWP been agreed upon because of jurisdictional arguments involving other ministries. 8 Those were capacity problems at the Government of Lesotho level. Capacity problems within the project authorities related to interminable delays in reaching decisions (or reversing decisions made), and then in implementing them. One example at the highest level was the many years it took to implement the recommendations of the Organization and Manpower Study. In addition to delays in agreeing upon, funding and implementing the Rural Development Plan, it took years to operationalize the crucial June 1995 proposal to establish field teams in the various project areas. Monitoring project impacts on affected people continues to be inadequate – an especially serious deficiency for the 365 Katse households who lost all their fields to the project and the 441 households with no fields who may have been dependent, as sharecroppers, on fields that were inundated. After discussing and soliciting proposals over several years for handing over the key training facility to a local organization, a decision was made to close it down with no replacement. The Panel summed up such problems in its April 2000 report: “A key constraint of LHWC-LHDA is its ponderous management machinery. Things take far too long to decide, implement and complete. The litany of delays is long.” Capacity problems within the Environmental and Social Services Group of the LHDA were of three sorts. One was institutional; another concerned implementation capacity, and the third related to overall planning. Due to its hierarchical structure, there was insufficient coordination and consultation between the environment (which also included health and cultural heritage), compensation, and rural development sections. The necessary pre-project demographic and socio-economic studies carried out by the compensation section did not include the type of data needed for rural development purposes or for enabling monitors to determine when living standards had been restored. Though assets requiring compensation were carefully documented, detailed information on resources, such as arable land, remaining to each household was not collected. As a result, necessary information that could be built into rehabilitation plans for each household did not exist. Nor were sufficient data gathered for a benchmark study against which restoration of living standards could be measured. 8 The compensation regulations were finally gazetted in April 1990, while the Phase 1A scheme area was approved in February 1990 19 Plan implementation capacity was weakened by the fact that ESSG staff was concentrated in Maseru. No one was stationed in the Katse Project area until the agonizingly slow build-up of several field operations groups during the second half of the 1990s. While the Panel emphasized that constraint early on, we did not pay sufficient attention to the coordination, staffing and administrative problems that could be anticipated when compensation activities, housing construction, and implementation of 15 separate rural development projects began. 9 Compensation and housing construction have continued to be the most satisfactory ESSG activities to date. I believe the Highlands Water Project has been the first major project to accept responsibility for community compensation for loss of such common property resources as grazing, building materials, fuel and medicinal plants as a major project cost. The project authorities also realized early on that initial intentions to provide grain compensation for a 15 year period to households losing fields, and fodder for a five year period to those losing grazing, were insufficient. Subsequently those undertakings were replaced by an agreement to provide cash compensation annually to households over a 50 year period with a minimum threshold established to deal with the most disadvantaged households. Replacement housing, generally speaking, was an improvement over what had previously existed with resettlers having the option to choose between customary housing or ‘modern’ houses. Nonetheless various weaknesses have continued to date which have drawn legitimate complaints from resettlers and NGOs, and which threaten the restoration of living standards. During the early years when the emphasis was on grain compensation, people suffered hunger because delivery often came after the date that initial harvests from lost fields would have brought the annual hunger period to an end. Also it took the project authorities too long to admit that a grain ration alone was insufficient to compensate for the multiple crops, including legumes, which most households had previously planted. Community compensation for lost common property resources had not been received by the end of 2001 because of delayed establishment of an institutional structure for receiving the funds. In regard to replacement housing, correction of defects has been too slow as has been the installation of stoves where resettlers have chosen modern housing. Even if continued over a 50-year period or longer, cash compensation alone cannot be expected to restore living standards without being integrated with effective implementation of the rural development plan. As various consultants and experts had noted, the quality of the individual plans was state of the art. But could they be implemented? The record has been unsatisfactory with budgets unutilized, a few plans dropped or seriously delayed, and the majority inadequately implemented. Because of cost considerations the rural electrification component was soon dropped although the Panel requested in its March 1998 report that the issue be revisited especially as it related to schools and various development options. Though it should have been the first component initiated, “Planning with the People” never was 9 This deficiency was noted at an earlier date by the Commission’s Environmental Advisory Committee in their October 1992 Draft Minutes 20 satisfactorily implemented. The same was the case with the village water supply and sanitation components. Though the intention was to complete provision of water and sanitation facilities throughout the Katse local catchment during 1995, by the end of 2001 only 30 of 114 planned potable water projects had been completed. Equally serious delays were associated with various agricultural components with the unfortunate result that various consultants as well as the World Bank began to question the relevance for rehabilitation and development purposes of agriculture in general. Among Panel members, but with the support of my colleagues, I took strongest exception to this position. Highland households practice a diversified economy that includes crop agriculture, livestock management, wage labor, and a range of small-scale commercial ventures. Since each component makes an important contribution to household living standards, with their proportional importance varying from household to household and within households from year to year, rehabilitation and development strategies must address each. In November 2000 women affected by ‘Muela told the Panel how one dairy cow or a small homelot vegetable garden could provide up to 30 percent of a household’s necessary annual income or money to pay the school fees for two children. The problems with the agricultural components of the rural development plan were planning and implementation problems. Highland yields were not poor; indeed “When rainfall is adequate, yields exceed 800kg of cereals per hectare –twice that reported throughout much of Tropical Africa and enough grain to feed a small family until the next rainy season harvest” (LHDA POE December 1995: 18). When rural development plan budgets were finally approved and implementation finally began in 1991, no food production or income generation components were included. When they were, a major problem related to the lack of attention paid to marketing – both the identification of markets and the implementation of the necessary marketing structures. Hence while dairy cows were distributed especially in the ‘Muela area, the need for an institutional structure and marketing outlets for dealing with production once local markets were saturated was ignored. The same was the case with those farmers producing a significant surplus of vegetables such as peas, carrots and especially cabbage. The best farmer in the Katse area, for example, was the principal of the Khohlontso Village primary school. His inability to market his produce not only resulted in wastage of produce but also discouraged other farmers from following his example. Administrative bungling within ESSG has also discouraged South African entrepreneurs from signing contracts to buy and market a range of high value specialty crops. This was most unfortunate since only such crops could begin to replace the previous importance of marihuana as the most important income generator for that majority of households without employed family members. Though it can be assumed that marihuana will continue to be grown, the closer incorporation of the highlands into the Basotho nation will inevitably reduce production due to closer administrative, and especially police, controls. Through 2000, the artisannal fishery and forestry projects were being effectively implemented by consultants. As their December 2001 termination dates approached, 21 however, the project authorities had yet to act on proposals for their extension. The fishery project was also constrained by the continued inability of LHDA to operationalize the necessary credit program to enable trained fishers to acquire nets and boats. Nor had national laws outlawing the use of nets under all conditions been revised to except reservoir fishing. The Panel has been especially critical of LHDA’s lack of emphasis on education. Educational facilities in the highlands, including the Katse and Mohale basins, are the worst in Lesotho. While schools in the lowlands and foothills have piped water and latrines, most in the highlands do not. According to Sechaba’s Poverty and Livelihoods in Lesotho, 2000, poor school attendance is “intimately related to the deficit in school facilities” (page 8) as well as the lack of trained teachers. Though the highlands also have the highest out-migration rate in the country, those moving have not had the education necessary for getting jobs; as a result “employment levels continue to decline in the remote villages” (ibid). In not emphasizing school improvement and skill upgrading, LHDA is losing a major opportunity for providing individuals with the necessary education and skills to allow them to either develop enterprises in the highlands or obtain jobs elsewhere in the country. This inadequacy has been brought to the Panel’s attention during each successive visit to the headmaster of the Khohlontso school during which he has showed us how the project has yet to restore the school’s sole source of water that was disrupted by road construction. Though eventually LHDA began to provide latrines to schools, and helped establish one secondary school, little effort has been made to improve village schools by, for example, encouraging the type of English language medium curriculum that could have played a major role in the welfare of some households and perhaps the area as a whole. When local initiative started such a school at Katse in an unused project building, the Project and the Ministry of Education shut it down rather than help the school authority to correct sanitation and other deficiencies. Opportunities lost by failure to upgrade educational facilities were increased by the failure of the project’s rural training program. In the early years, optimistic plans were mooted to develop three training centers, as well as satellite centers, that would provide the type of job training that was necessary to take the place of lost arable land and grazing. Such training would provide skills needed by villagers to obtain jobs during the construction phase, and by those who might start local business enterprises. In 1990 the Panel agreed that there was indeed a need for a Skills Training and Entrepreneurial Development Centre to be built at Katse but this never materialized. Instead a Rural Development Centre was developed outside the project area at Thaba Tseka. The RDC as it came to be called was contracted out to a South African consultancy firm whose main accomplishment was to provide the most expensive program of job training in Southern Africa. When the Centre was eventually shut down in 2000, it had accomplished little while consuming more of the rural development plan’s budget than any other component aside from construction of feeder roads that complemented the major project road by completing a network circling the Katse reservoir. 22 In all fairness some of the RDC’s disappointing record was due to factors outside its control. LHDA and the Commission paid insufficient attention to these when they decided not to hand over training to one of a number of Lesotho organizations. 10 Delays by the project authorities slowed the Centre’s opening while poor coordination and administration from ESSG in Maseru was another contributing factor. Another problem was that Centre graduates found it difficult to find jobs with the project since many of the South African contractors brought in their own workers or rejected the training provided by the RDC as being of too short duration to provide the necessary skills. Moreover, at the time the Centre was closed down, LHDA had yet to implement a credit program that could assist artisans with carpentry, masonry, weaving and other skills (and other local entrepreneurs starting such businesses as bakeries and egg and poultry production) with start-up costs. RDC’s own inadequacies, however, contributed to the failure of their graduates to find jobs. It failed to relate its training curriculum to the local and wider market for graduates and it had an inadequate program for following up graduates in order to provide further assistance where necessary and feed back their experience into the curriculum. Another capacity problem of the project authorities has been their inability to deal with planning and implementation suggestions for correcting agreed upon deficiencies. One example relates to the need to bring the Ministry of Agriculture more effectively into the rural development process. During several visits to the major Mohale resettlement area in the foothills, the Panel visited the Ministry’s Matela Farmers Training Institute, the first such institute opened in Lesotho. The capacity of Matela’s well trained and motivated staff to provide training had suffered from major budgetary and infrastructure problems. Housing and other trainee facilities were insufficient as was equipment needed for training purposes. Nevertheless Matela was willing to provide relevant training to the hundreds of Mohale resettlers that had opted for foothill resettlement and was a natural candidate for the type of collaboration that the Lesotho Highlands Development Authority was seeking with other government agencies. The Mohale Dam Preparatory works for the construction of the Mohale Dam began during 1996 with the construction of access roads and township infrastructure. A five volume Environmental Action Plan was issued in October 1997 prior to the commencement of dam construction in 1998. It reflected many lessons learned from Phase 1A. Unlike Phase 1A, it was based on a pre-project Environmental Impact Assessment that “identified a large number of biophysical and socio-economic impacts which require mitigation and/or compensation … The activities designed to carry out this mitigation and compensation, and in some cases enhancement, have been grouped together under the collective category of an Environmental Action Plan”(Executive Summary, EAP 1997:1). Though that wording once again placed insufficient emphasis on the type of development necessary for 10 Several had been suggested. Of two visited by the Panel, one did appear to have the necessary institutional capacity, personnel and curriculum. 23 avoiding further impoverishment, Volume 3 of the Plan was titled Resettlement and Development Action Plan. On the environment, planning for Mohale finally brought proper attention to the question of downstream flows that should have been addressed prior to Katse construction. Adding two members with relevant expertise, the Panel played the key role during 1997 in expanding the consultants’ contract to include “a full health and socio-economic component” (LHDA POE July 1997: 9). In regard to affected people, two lessons learned from Phase 1A included a decision to allow individual households and communities requiring resettlement to either remain within the Mohale reservoir basin or move to any preferred locale within Lesotho. Not only would that remove some pressure from a project-reduced natural resource base, but it would also give resettling households the opportunity to seek a wider range of development opportunities. As the Panel expected, a majority of households opted to resettle at lower altitudes in the foothills and the lowlands including in and round Maseru. 11 The second important lesson learned was to contract one consultant to map resources lost and plan for their replacement through an integrated compensation and development program. The firm picked was Hunting-Consult 4 Joint Venture which prepared under Contract 1012 the Resettlement and Development Study that was incorporated within the Environment Action Plan. 12 Implementation in three stages would be synchronized with the construction schedule. Stage 1 would involve the relocation of 99 households affected by project works prior to the commencement of construction on the dam itself. Stage 2, labeled ‘Pre-Implementation,” would involve the resettlement of another 143 households. Implementation of the third stage would be postponed until after the reservoir reached full storage level. Though the Panel considered the figure too low,13 the Contract 1012 consultants estimated that 168 Stage 3 households would be involved. Some households would be at risk due to proximity to the reservoir. Others might be cut-off by the reservoir from other sections of their village while at least 67-70 households would lose over 50 percent of their arable land to the reservoir. 11 According to data collected by Hunting-Consult 4 during their Resettlement and Development Study, 61 percent of Stage 1-3 households wished to leave the Mohale local catchment if they had to move. 12 Generally speaking the Contract 1012 reports were state of the art. Though implementation exposed weaknesses, they contained, for example, a well-thought out and initially well received “People’s Involvement Programme.” On the other hand, while the development planning for the minority who wished to remain within the Mohale local catchment was well thought-out, the planning for the majority who wished to leave the basin was inadequate. 13 In its July 1997 report the Panel recommended that for planning and budgeting purposes it should be assumed that 400 households might wish to resettle as opposed to the closer to 300 estimate of the Contract 1012 consultants. Without including Stage 3, by 2001 resettlement was estimated to include about 320 households. That number, however, included in Stage 2’s second and third groups households at risk from, or cutoff by, the reservoir; in other words households that were originally in Stage 3. Should households losing over 50 per cent of their land be added under Stage 3, as they should be, the total choosing to resettle could easily reach 400. 24 The consultants recommended that all 168 Stage 3 households should have the option of resettlement. That was a recommendation that the Panel fully endorsed since those households that opted for resettlement not only would have a greater range of opportunities, but their departure from the Mohale local catchment would reduce the pressure on the host population’s use of the remaining resources. That was an argument that the Panel made in a series of reports between 1997 and 1999. Special emphasis was paid to those losing over 50 percent of their land. The rich alluvial soils that will be lost to the Mohale reservoir are literally some of the most fertile land in Lesotho. In other words, loss of under 50 percent (say 30-49 percent) might well entail a lost of 50 percent or more of the productivity of the arable land used by a household, so that the risk of impoverishment from land loss is apt to extend to some households that lose less than 50 percent of their land. Though the Panel believed that the Contract 1012 recommendations that households losing over 50 percent of their arable land would have the option of resettlement had been accepted, the project authorities denied that was the case in their commentary on the Panel’s March 1998 report. On the contrary, loss of over 50 percent of arable land “was not included in the approved compensation policy.” In replying the Panel reiterated that “households who lose over 50 percent of their arable land should have the option of resettling. That is necessary since it will be difficult, if not impossible, to restore the living standards of a majority of such households if they remain in the catchment. In that event, LHDA would not be in compliance with treaty requirements.” The Panel repeated that comment in its March 1999 report as well as stating “The Panel stands by that forecast.” Though the 1997 Compensation Policy did not stipulate land loss as a criterion for resettlement, Volume 3 of the 1997 Environmental Action Plan did mention loss of “over 50% of their arable land and/or productive assets” as “Eligibility for Voluntary Resettlement.” LHDA and the Commission finally agreed that Stage 3 households who lose over 50 percent of their land should have the option of resettlement after the Mohale reservoir fills during a wrap-up meeting with the Panel in April 2002. The World Bank was present and supported the Panel’s position. Following my resignation from the Panel that month, I was informed by the Bank that funds had been budgeted for the possible resettlement of over 100 such households. Since the reservoir was still filling at the time of writing, it remains to be seen whether or not that commitment is honored. Here the experience at the Katse reservoir is of concern. There too a post-inundation stage of further resettlement was accepted policy. Yet no additional households requesting removal have been resettled, including some so close to a cliff above the reservoir that the Panel recommended their resettlement for safety purposes in 1998. The Katse policy was to consider post inundation resettlement on a household-by- household basis. That is a policy that must not be applied to the Mohale reservoir where the much larger number of households at risk requires integrated planning. It also remains to be seen if the World Bank has the clout after the disbursement of its loan to insist on implementation of the Stage 3 resettlement option for those households that wish to move once they have had the opportunity to assess how inundation of over 50 percent of their arable land affects their livelihood. 25 The 1012 contractors only mapped fields lost and fields remaining in the 46 of the 83 Mohale local catchment villages that they considered to be most affected by the project. Their reports contain two conflicting estimates of the number of Stage 3 households that would lose over 50 percent of their land. One is the 67-70 households previously noted. The other is contained in Vol. 4, Adjudication, of the consultants’ 1997 Resettlement and Development Study where 65 households in 24 Stage 3 villages were listed as losing 90100% of their arable land, while another 70 were listed as losing 50-90%. What might be the situation in the 37 villages where land resources were not mapped? The unit for adjudication purposes that Contract 1012 used was the village not the household; hence they were aware that an unknown number of households in the remaining villages could be expected to lose arable land to the reservoir. That was noted in their 1997 Synopsis of Studies that stated that 367 households in 33 of the less affected villages “will lose a substantial portion of their land.” Though no estimates were given, the Panel in its November 1996 report stated that it would not be unreasonable to expect another 35 households to lose over 50 percent of their land. Until Contract 1012 maps of fields lost and fields remaining are updated, it is difficult to know how many additional households should have the option of resettlement. By August 2001, the number of Stage 2 households had been increased from 143 to 226 by including additional households thought to be either too close to, or cut off from, the reservoir and which had previously been placed in Stage 3. Nonetheless I suspect that the number of households remaining to be resettled in Stage 3 could still reach 100. How many of those would wish to remain within the Mohale basin as opposed to resettling elsewhere is another unknown. If most such families remain in the Mohale local catchment, I predict that rather than having their living standards restored, the majority will find themselves further impoverished by the project. Increased impoverishment is already apparent in regard to those Stage 1 households that opted to resettle within the local catchment in Ha Koporale Village. During the Panel’s April 2001 visit there we interviewed seven Stage 1 resettling households. On arrival, all were told that no fields were available for them and none had in fact found any fields. Land for gardens was also scarce with only two of the seven starting small vegetable gardens along the creek below the village. Though some host households were willing to lease out fields and take on sharecroppers, the supply of fields was limited and their use by resettlers would further reduce arable land available for sharecropping by landless host households. Other implementation problems that plagued Phase 1A have continued to adversely affect Phase 1B. Mohale resettlement and rehabilitation, for example, has continued to emphasize housing construction required for physical removal as opposed to other compensation and development activities necessary to restore living standards. As stated in the Panel’s March 1999 report, “While early POE reports (1990 and 1991) explained in detail why restoration of living standards required more development activities as a legitimate project cost, the imbalance between physical resettlement, compensation and 26 development activities has continued to this day…When Katse reservoir resettlement began, emphasis on physical removal and compensation activities continued to take precedence over development activities. The same pattern is now re-emerging with Phase 1B Stage 1 resettlement, where development activities have affected only a small minority of households a full year after their removal…If Treaty obligations are to be met, it is essential that a better balance between necessary compensation activities and necessary development activities be achieved in future years” in regard to both the Katse and Mohale dams. The two reports submitted during 2000 made the same point as did the April 2002 report. As stated in the April 2000 report “The principal problem remains the unsatisfactory nature of the incomplete infrastructure…, and the slow implementation of income generation activities.” At the end of that year, for example, the majority of the Stage 1 resettlers in Mokotoko, the principal resettlement community in the foothills, still had an inadequate water supply nearly three years after removal, while necessary development activities to restore living standards of the majority had still to get underway. In April 2002, the emphasis continued to be placed on the housing construction that was required if dam closure was to occur on schedule at the end of the year. On the other hand, activities required for restoration of living standards were increasing. In the mountains, most impressive was the production of seed potatoes with annual production rising to 220 tons and storage facilities with a 300 ton capacity nearing completion. Plans for 2003 were for double cropping to produce two 300 ton crops. Stage 1 and Stage 2 households that had resettled in the lowlands and the foothills were participating with host villagers in crop and poultry cooperatives. LHDA had finally allocated funds to the Matela Farmers Training Centre that had begun offering courses to both resettlers and hosts. ESSG field personnel had also arranged for a lowland poultry slaughtering cooperative to market resettler and host chickens. Community formation was also underway. In Mokotoko, whose water supply problems had finally been solved, 37 Stage 1 and 2 households had begun to integrate with their hosts, with one host family moving into the resettlement community and others expected to follow. New issues, however, continued to arise, including one in 1999 that threatened the entire Mohale resettlement program. It concerned the general topic of host-resettler relationships that is a delicate one with all types of resettlement that requires sensitive handling. It also involved two powerful politicians who brought to bare on the project personal and political agendas irrelevant to, and disruptive of, the resettlement process – hence illustrating the type of unexpected, yet expectable, events that can threaten resettlement and development outcomes. The largest Stage 1 resettlement from the Mohale basin to the lowlands involved 22 households relocated to form a planned community on the outskirts of Maseru. While the project authority had legally acquired that land from the Lesotho Housing Corporation, it did not discuss the intended resettlement with the adjacent host community of Makhoakhoeng, nor with the community’s most important resident. This was the Minister of Foreign Affairs who was one of Lesotho’s most powerful politicians as well 27 as the surrounding area’s representative to parliament. To make the situation still more complicated his large house with ample grounds was not only next to the resettled community but was burnt to the ground during the political disturbances that swept the country in 1998. Capitalizing on host community feelings that the resettlement site had been improperly acquired at an earlier date by the Housing Corporation, the Minister encouraged hostility toward the resettlers as soon as they arrived. Though Makhoakhoeng was not a rural community, he also influenced the local chief to claim the same benefits that were given to rural host communities in return for their willingness to share their land, grazing and other natural resources with resettlers. While the project authority had already upgraded the road serving both hosts and resettlers and provided a piped water supply, demands for further benefits and harassment and intimidation increased after the resettlers’ arrival in 1999. Not only were their children harassed and chased, but use of the neighborhood burial ground was refused when the first resettlers died that year. The situation worsened in November 2000 when the Minister of Natural Resources, for unexplained reasons, told the 22 households that they must resettle a second time to an undesignated site. As harassment increased including house break-ins, the community became divided between those who agreed to a second resettlement and those, apparently the majority, who did not. As the dispute intensified so too did its implications for the credibility of the Lesotho Highlands Development Authority which felt that resolution of the dispute required a solution at the level of the Prime Minister and his cabinet. The Panel and the World Bank were both drawn into the dispute with the Panel labeling a second resettlement “unnecessary, unacceptable, and undesirable” in its November 2000 report. Two months later the World Bank went on record against a second resettlement that would be out of compliance with its resettlement guidelines. The Bank also sent a special mission to Lesotho during 2001 in an effort to meet with the Ministers of Foreign Affairs and Natural Resources – both of whom were ‘unavailable.’ Repercussions also placed the rest of the Mohale resettlement program in jeopardy with families still to move, and the participatory committees set up under Contract 1012’s People’s Involvement Programme, refusing further cooperation with the project authorities. Local NGOs were becoming increasingly concerned, with that concern spreading quickly to international NGOs. In their 2001 critique of the Highlands Water Project, the International Rivers Network referred to local sources that claimed those who had already been resettled under Stage 1 had told those still to resettle under Stage 2 not to move until the project authorities had implemented all their resettlement responsibilities. The International Rivers Network also quoted the same local NGO as stating that resettler community members were now unanimously opposed to a second resettlement with a community representative stating that if the community cannot “stay in peace, LHDA will never ever resettle anyone in this area” (Hoover 2001: 22). Uncertainty continued until the end of 2002 when the Cabinet passed a resolution disallowing further resettlement of the Makhoakhoeng community. The damage had been 28 done, however, with the World Bank reporting in late October 2002 concern about rumors still circulating about the possibility of further removal. Since the closure of the Mohale Dam in October 2002 the ability of the World Bank and the Panel to influence events has weakened. For example, both the Bank and I expected that my replacement would be appointed in time for the Panel’s September 2002 visit. 14 That did not occur. Nor was a replacement appointed for the Panel’s April and September 2003 visits. Only in December 2003, at Bank insistence, was an appointment made, or rather a re-appointment when Hitchcock’s contract was renewed. That meant that there was no social science expertise on the Panel for 20 months, including throughout 2003. My experience in India and Sri Lanka in connection with the Sardar Sarovar and Mahaweli Projects was that research, consultancy and advisory teams are strengthened when they involve both host country and international expertise. And in the case of panels like LHDA’s that expertise must be both environmental and social. Such was not the case with the Lesotho Panel for a 20 month period during which the Panel was dominated by two South African environmental scientists. It is unreasonable to expect specialists in other fields to understand the stresses and problems associated with involuntary community resettlement so that they are more at risk of making decisions that favor the project authority over the interests of affected people. They also tend to be less aware of a project’s international context. In the LHWP case my colleagues have not insisted, for example, that Panel reports should be distributed as public documents. As a result since my resignation, none of the following three Panel reports have been released in contrast to Panel reports between 1989 and April 2002. That is bound to raise questions concerning the Panel’s independence. Furthermore, they have also made statements that support LHDA and the Commission at the expense of project affected people. Especially serious was their support of the project’s Instream Flow Requirement policy that over 20,000 dispersed households in the more distant downstream areas should only be allowed compensation for reduced river flows if they could prove losses (LHDA POE March 2003). That conclusion was contrary to the LHWP Treaty and World Bank Guidelines that require the project authority to take responsibility for compensating all affected people. Requiring over 20, 000 households to prove that they have been adversely affected is but one of many examples of the inability and/or unwillingness of LHDA and the Commission to deal equitably with affected people. Though development activities to restore living standards were finally improving by 2002, throughout both Phases 1A and 1B the emphasis has continued to be on the physical removal of households as opposed to their rehabilitation. There have also been innumerable compensation inadequacies that are dealt with in detail in the August 2003 report of the Ombudsman (S.S. Mafisa). The position of Ombudsman, 14 An excellent candidate was available. That was Stephen Turner. From England Turner had been brought up in Southern Africa and especially in Lesotho where he learned to speak fluent Sesotho and had completed innumerable assignments including substituting on one occasion for me on the Panel. 29 to be appointed by the King on the advice of the Prime Minister, is a requirement of the Lesotho Constitution. During December 2002 and January 2003 the Ombudsman received numerous written complaints from project affected people that he decided warranted a formal enquiry. The largest number of complaints were about compensation issues including delayed payment, general inadequacy of payment, non-payment for loss of communal assets, compensation for household gardens and fields, and the minimum threshold allowance. But complaints were also received concerning failure on the part of the project authorities to provide access roads, water supplies, health facilities and schools. The Ombudsman’s main conclusion was that prompt payment of full compensation as required by law had not been paid , with LHDA conceding that “it had failed to make prompt payment in many, if not all, cases because of its own internal problems” (Gov’t of Lesotho 2003: 54). Moreover, though the Ombudsman concluded that a small minority of people had tried to defraud LHDA (eight were mentioned by name), “the inquiry concludes that on the whole the complainants have proved their case against LHDA” (page 56). Summary Bearing in mind that the Lesotho Highlands Water Project is not only a contemporary one, but one of the largest under construction today as well as being World Bankfinanced, both environmental and social results to date have been disappointing. Among other conclusions, the LHWP case study shows why it is essential for resettlement policies to stress improvement as opposed to restoration of living standards and for project authorities to have the political will and capacity adequately to fund and implement those policies. Without such commitments, future dams should not be funded by multilateral donors like the World Bank or by bilateral donors. The range of problems involved also raise the legitimate question as to whether the implementation issues associated with large dams are just too complex for realizing outcomes that are equitable and sustainable environmentally, economically, institutionally and culturally. And if the answer is “no”, should the dams in question be replaced by other alternatives? In some cases, I am convinced that the answer is “yes,” but I do not consider LHWP to be one of those cases simply because the potential overall benefits to South Africa, Lesotho, and Southern Africa as a whole are so great. While my conclusion here sets my position apart from many international NGOs, they are more unified against the project than the most directly involved local NGOs who, like the Panel, see the macro benefits to Lesotho and South Africa while hoping that the project can at least restore the living standards of the most directly affected households and communities. Is such an outcome possible? For many, including the majority of the 150,000 affected by reduced downstream flows, the most likely answer is ‘no’. Although significant, at least their losses do not include arable land and grazing. For the majority affected by the ‘Muela Project the most likely answer is “yes.” With no households forced to move and 30 loss of land affecting about 25 percent of a population of about 400 households, the majority can expect to benefit from improved roads and water and sanitation services. More accessible to tourists and day visitors from Lesotho’s lowland cities and towns, they can also expect to benefit from visitors to the ‘Muela dam, reservoir, and visitor center as well as to two reserves in which surrounding communities have a degree of ownership. For the majority affected by the Katse and Mohale dams, the verdict remains in doubt. That is especially the case for the over 700 Katse and Mohale households that will have lost over 50 percent of their fields. On the other hand, outcomes can still be favorable for a significant number of households (perhaps even a majority) if the political will is present within the project authorities and the government for local people to achieve a degree of ownership over existing resources and if the necessary plans and intentions are integrated and implemented. By 2001 ESSG had begun a re-planning exercise because of discrepancies between actual Phase 1A and 1B outcomes and those recommended in the respective Environment Action Plans. Panel recommendations concerning the need for a more integrated development paradigm were being seriously considered as shown by the integration of compensation and development in the re-planning process. A general strategy that could benefit reservoir inhabitants is outlined in the Panel’s March 1999 Report in relationship to “Hotel and public recreation development,” “Fishing opportunities,” “Feeder Roads,” and “Environmental Reserves.” The first three categories fall under the purview of the zoning study for the two reservoirs in which local communities are supposed to participate fully. Adjacent communities are custodians of the land, including reservoir-inundated land. Zoning the reservoir and surrounding land should allocate to them fishery rights and maintenance rights to the feeder roads that encircle each reservoir. Fishery rights would include not just training to catch fish but also rights to revenue received from outsiders who come to camp, boat on and sport fish the reservoir. Under intended environmental reserves, the Panel recommended that those communities who provide land for such reserves “must be involved throughout in formulating the legal framework for future reserve management and administration…Local communities must perceive that they have ownership over all processes.” Because of capital requirements and national elites (including some in the project authorities), the Lesotho Tourism Board, and outside entrepreneurs interested in high class hotels and 18 hole golf course possibilities, only incorporating members of local communities in low paid custodial, housekeeping and gardening jobs is a definite risk. Should that happen “tourism will emerge as ‘islands’ of luxury and wealth in a ‘sea’ of rural poverty. Profits will be exported and there will be little trickle down to local communities” (LHDA POE March 1999). In terms of capital, surrounding communities are not as impoverished as one might expect. This is because of the significant sums that communities will receive for loss of common property resources, the LHWP being one of the few existing projects where major compensation is being provided for loss of access. Should a number of 31 communities close to each reservoir join forces, the capital involved could be a major incentive to an outside entrepreneur to enter into a joint venture as has been the case in Botswana’s Okavango Delta. In the Okavango region the local resource has been wildlife and scenery. In the reservoir basins it could be taking over and developing construction camps on, or near, the edges of the Katse and Mohale reservoirs as tourist facilities. The potential is certainly there. But now that the construction phase is over, and the clout of the World Bank and influence of the Panel reduced, the chances are less that it will be realized. The most spectacular site in the Mohale reservoir basin is a spectacular island in the middle of the reservoir. While the long-delayed LHDA zoning study was still underway, a joint venture that involved several ministers began to develop the site, with no local involvement and without the necessary environmental impact assessment, as a high altitude training and tourism facility contrary to LHDA regulations. Moreover, both LHDA and the Commission remain out of compliance with a number of World Bank conditionalities. Nam Theun 2 Introduction Laos’ Nam Theun 2 (NT2) project warrants attention for a number of reasons. Largely meeting World Commission on Dams criteria, environmental and social planning is stateof-the art. This was due to the desire of the Government of Laos and of the project consortium for World Bank Group involvement, with the consortium’s private sector participants insisting on a World Bank partial guarantee as a condition for initiating construction. Applying lessons learned from the Bank Groups’ involvement in such projects as India’s Sardar Sarovar, Nepal’s Arun III and Chile’s Panque, the World Bank in turn required more studies and commitments from the Government of Laos than has been the case with past projects. In addition, the Bank established its own International Advisory Group (IAG) to provide guidance on how the Bank “can improve its handling of environmental and social issues in the hydropower projects it supports world wide” (IAG Terms of Reference 1997) with NT2 being the IAG’s first assignment. National Context With an estimated population of 5.7 million in 2005 and a 2.6 percent annual rate of population growth, the Lao Peoples Democratic Republic is one of the poorest countries in the world with annual per capita income estimates ranging from $300 to $400. The economy is still predominantly rural with over 80 percent of the labor force employed in agriculture. Social indicators are closer to those in tropical Africa than in much of Asia with a life expectancy according to World Development Indicators of about 53 years, a 43 percent literacy rate and only 39 percent of the population with access to safe drinking water. Laos is also one of the most beautiful countries in the world in terms of landscape and biological and cultural diversity. Approximately 60 percent of the population belong to a 32 wide range of ethnic minorities and linguistic communities. Closer to the Mekong River the majority are lowland Lao Loum who are predominantly Buddhist. As with neighboring Vietnam the government is run by a communist regime which has been experimenting with a market economy since the 1986 implementation of its New Economic Mechanism. While the economy grew rapidly in the mid 1990s, it was badly hit by the Asian crisis with the local currency losing over 70 percent of its value by early 1999 and inflation increasing significantly. Since 1999, however, the economy has begun to recover. Like the Lesotho Highlands Water Project and Sri Lanka’s Mahaweli Project, Laos’ Nam Theun 2 project is by far the largest development project in the country. Stretching from the Vietnam border to the Mekong River and the border with Thailand, the project has major regional development implications as well as national ones. With its over twenty major tributaries, Laos contributes nearly 40 percent of the Mekong’s flow. Rising in upland and mountainous areas along the border with Vietnam, the energy generating potential of those tributaries makes them Laos’ number one natural resource for generating foreign exchange. Already the government has negotiated an agreement to provide Thailand with 3,000 MW of power. That makes sense, with hydropower development hopefully replacing the export of timber, and hence the too rapid reduction of Lao forest cover, as the country’s primary source of foreign exchange. What does not make sense are the 20 odd memoranda of understanding that the government has signed with various governments and companies to build dams on most of those tributaries. A more sustainable strategy would be to build a cascade of dams on a small number of tributaries, including the Nam Theun and the Nam Ngum which have already been dammed, with the majority maintaining their natural regimes. Whether the government has the foresight to implement such a policy, which our NT2 Panel has recommended, remains to be seen. The Project The centerpiece of binational cooperation with Thailand, NT2 is primarily a hydroelectric project for the export of peaking power. But as planning has proceeded the project has also come to emphasize other goals. As a major source of foreign exchange, it is expected to provide revenue for poverty alleviation at the national level and for environmental enhancement and living standard improvement within the project area. NT2 is a very complex project in regard to its environmental and social impacts as its scope extends from the Vietnam border to the Mekong River and involves interbasin transfers from the upland Nam Theun River to the lowland Xe Bang Fai. On completion scheduled for 2009, a 48 meter high dam will create a shallow 450 km² reservoir that will inundate approximately 40 percent of the Nakai Plateau in Central Laos. Aside from a mixed population of less than a thousand people who live in, and surrounding, Nakai town and district headquarters, which will not be inundated, the large majority of the village population on the plateau will require relocation. Classified as indigenous people, they number approximately 6,000 people living in 17 communities. 33 Approximately 40 km up the reservoir, water will be diverted down the southern escarpment, falling 335 meters to a power station with a capacity of 1070 megawatts. Approximately 95 percent will be exported to Thailand, with the remainder delivered to the Lao grid. Outflow from the turbines will enter a regulating reservoir from which water will flow down a 27 km channel and waterway to the Xe Bang Fai approximately 80 km above its junction with the Mekong. From the regulating reservoir, water can also be released down another tributary to provide water for irrigation and domestic purposes to 20 villages. Roughly similar to that of the Nam Theun, the Xe Bang Fai’s average annual flow will be nearly doubled on receiving project water. Especially during the dry season, radically increased flows can be expected to adversely affect the flood recession agriculture and fishing of a riverine population estimated at well over 50,000 people. Including five tributaries that enter the Nam Theun reservoir basin, in addition to the upper reaches of the Nam Theun itself, the project’s watershed is approximately 4,000 km². Its upper boundary is the crest of the Annamite Mountains that forms the international border with Vietnam. Close to the future reservoir, and running parallel to it and the Annamite Mountains, are the Dividing Hills through which the tributaries pass via a series of rapids before reaching the Nam Theun floodplain. Both edges of the watershed between the Annamite crest and the Dividing Hills drop off to lowlands with a fringing population of at least 20,000 people. Approximately 6,000 indigenous people, belonging to a large number of ethnic groups and two different language families, live in villages along the five catchment tributaries and the upper Nam Theun. Small numbers were foragers prior to their involuntary sedentarization in consolidated communities during the past 30 years. Like the inhabitants of the Nakai Plateau, villagers currently practice a diversified production system that includes shifting cultivation, fishing, gathering and hunting with a small amount of paddy rice cultivation in a minority of communities. Though rain-fed rice is the preferred crop, yields seldom last more than three to six months, with maize and cassava more reliable staples. Vegetation and wildlife on the Nakai Plateau have been adversely effected by the Vietnam war, post war land use by a traumatized and impoverished population, and indiscriminate and project-related logging between 1993 and 1995 after which logging outside the reservoir basin was prohibited. One of the most extensive pine forests in South East Asia remains at the upper end of the plateau that is not settled, while mixed deciduous and some riverine forest remain at the lower end. The lower reaches of the Dividing Hills are also well forested. Otherwise “most of the terrestrial area of the plateau is considered to be substantially modified by human activity and from a biodiversity standpoint substantially degraded from its original status” (NT2 POE 1997). Land in the upper reaches of the tributaries, and between them, supports perhaps the most intact contiguous forest in South East Asia. It varies from different types of evergreen broadleaf forest to upper montane forest in which a valuable cypress grows in scattered pockets above 2,000 meters. Though threatened by commercial hunters from Vietnam, 34 wildlife is still prolific, with the watershed considered one of the most valuable biodiversity areas remaining in South East Asia (IUCN 1997). In addition to at least 430 species of birds, mammals include elephant, tiger and several recently discovered species. One is an endemic bovid, the Saola (Pseudoryx nghetinhensis) (Robichaud 1997). Another is a member of the deer family. Recognizing the importance of the area, the government incorporated it in 1993 within what was called the Nakai Nam Theun National Biodiversity Conservation Area (NNT NBCA). The project authority, Nam Theun 2 Power Company Limited (the Company), is a private sector-government joint venture that will build, own, and operate the project during a 25 year period after which it will be handed over to the Government of Laos. The overseeing partner is the parastatal Electricté de France (EDF) with a 35 percent share. A subsidiary of the the Electricity Generating Authority of Thailand (EGAT) has a 25 percent share as does Laos’ Electricité de Laos which has the option of increasing its share to 40 percent after fifteen years. The fourth partner is Italian-Thai Development Company with 15 percent. Current cost is estimated at US $1.5 billion, with the Company’s commitment to the project based on the assumption that the World Bank Group would provide financial guarantees. As approved in March 2005 they include an IDA partial risk guarantee up to US $50 million and a MIGA guarantee up to US $ 200 million. World Bank Group involvement also includes a $20 million IDA grant for a Nam Theun 2 Social and Environment Project. Planning Planning for the Nam Theun 2 project has involved the World Bank since the mid-1980s with the Bank early on advising the government to built it on a ‘Build, Own, Operate and Transfer’ basis so as to avoid acquiring a heavy debt load from the project’s construction. Financed by the United Nations Development Programme through the World Bank a feasibility study by Australia’s Snowy Mountains Engineering Corporation (SMEC) identified NT2 as Laos’ most viable hydro project based on technical and economic criteria but without dealing in detail with necessary environmental and social issues. In 1993 SMEC joined forces with another Australia firm – Transfield Holdings Ltd – to propose that the two firms take on the project. Proceeding alone Transfield submitted a full proposal in August, with the Government agreeing a few months later to sole source the project to Transfield that then put together the Company. 15 The decision of the government to proceed with NT2 before a consideration of environmental and social issues had occurred was a mistake since it gave project critics an opportunity to challenge later studies, no matter how competent, as mere justifications for a decision already taken. Because of its earlier funding through the Government of Laos of the initial SMEC feasibility study, the World Bank also was put in an awkward position which helps explain the extreme caution with which the Bank has proceeded since 1993 and its delayed decision to proceed to project appraisal. 15 Subsequently Transfield pulled out of the Company, in part because of delayed appraisal on the part of the World Bank 35 Environment and social issues came to the fore in 1995 when the private sector firms and the Government of Laos asked the Bank to provide a partial-risk guarantee. A major World Bank technical mission visited Laos during November, outlining in its report the terms of reference for various studies dealing with consultation at district, provincial and national levels and with economic, environmental, and social issues. During the 1995 visit, World Bank officials recognized from the start that the project would involve major environmental and social impacts that had yet to be adequately addressed. One decision made was to establish a panel of environmental and social experts to advise the government. I received a query in December 1995 as to my availability as a nominee, with a panel of three finalized during 1996. Lee Talbot, a wildlife ecologist and former Director General of IUCN, and Tim Whitmore, an expert on tropical forests, became the other members. 16 Our first two visits to Laos were in January and August 1997 with the first scheduled to coincide with the first major national consultation. Also during 1996 the Government of Laos contracted three major studies with World Bank funding. One was a study of alternatives for electricity generation to be undertaken by Lahmeyer International - Worley International. The second was an analysis of the economic impacts of the NT2 project contracted to Louis Berger International. The third was a broad study for formulating an environmental and social management plan for the Nam Theun watershed as well as for a corridor important for elephant migrations that would connect the Nakai Plateau via the dam site with the Khammouane Limestone conservation area to the southwest. That study was contracted to IUCN and the Wildlife Conservation Society both of which had a long history of advising the government on biodiversity management issues and had access to researchers familiar with the study area. At the same time the Company funded two major studies. One dealt with reservoir basin resettlement and involved Company staff and consultants working with government officials. The other was for an environmental assessment and management plan that became the responsibility of a consortium headed by SEATEC International. Draft results of the first two government studies were presented at the January 1997 national consultation. According to the study of alternatives, NT2 still ranked higher than other hydro and thermal projects, even with environmental and social impacts included. Though the International Rivers Network and other NGOs have questioned the results, the Louis Berger study showed a favorable economic impact. IUCN/WCS’ two volume Environmental and Social Management Plan was published in June, followed by a final report in July 1997 in time for the second major national consultation. Drafts of the Company’s Resettlement Action Plan and Environmental Assessment and Management Plan had been published the previous May. The IUCN/WCS study was first rate. The same is true for the Company’s Resettlement Action Plan as it has evolved over the years through collaboration with the government’s Resettlement Committee and Resettlement Management Unit. The Environmental Assessment and Management Plan also continued to be updated. Also in 1996 the World Bank decided to complement any financial guarantee with a stand-alone International Development Agency credit to finance a social and 16 Tim Whitmore’s death from cancer in 2002 left a major gap in the Panel that has yet to be filled. 36 environmental capacity building and management project. This I see as a major step forward as an indicator that the Bank is willing to provide funding for implementing its guidelines that relate to project components other than infrastructure construction. The identification mission for what has become the Nam Theun Social and Environment Project (NTSEP) was fielded in November 1996. Due to satisfactory progress with overall NT2 planning, in October 1997 the World Bank decided to proceed from its project identification stage to its project preparation stage. That required new government initiatives such as the creation of a national poverty alleviation fund into which NT2 project revenue – estimated at US $28 - 33 million a year over the first ten years and averaging US $73 million a year thereafter – would be placed. Preparation would also require further elaboration of the Company’s evolving Resettlement Action Plan and the Environmental Assessment and Management Plan and government planning for the management of the Nakai Nam Theun (NNT) conservation area. Utilizing a small World Bank grant that included funds for consultation, an operational plan for a watershed authority covering the NNT conservation area was submitted through the government’s Ministry of Agriculture and Forestry in May 2000 with a work program and budget. Also with World Bank funding, IUCN carried out an innovative program in the conservation area from May 1998 through July 1999 that concentrated on economic development and conservation in three pilot villages located on three of the six rivers. Preliminary results were encouraging, including “the development of cooperative patrols to conserve biodiversity,” with special emphasis on transboundary poaching and non-sustainable collection of non-timber forest products (NT2 POE 2001). Thereafter, most unfortunately, funding gaps caused continuity to be lost, momentum slowed, and initial village enthusiasm tempered. A small bridging World Bank project was approved during 1999. Called the District Upland Development and Conservation Project, it involved a $2 million credit for a three-year period that covered several objectives. One was to increase the capacity of government personnel at the Nakai District and Khammouane Province levels to facilitate the necessary integrated process of poverty alleviation and conservation in the NT2 conservation area. At the community level, three pilot villages, including one of IUCN’s, would be helped to place less emphasis on shifting cultivation by intensifing their system of land use and to support biodiversity and sustainable use of natural resources. Within those villages emphasis would also be placed on literacy and numeracy with special emphasis on women. At the end of 2002, the District Upland Development and Conservation Project was handed over to the Government. Though little appears to have been accomplished through 2001, the World Bank’s November Supervision Mission reported progress during 2002 due primarily to staff that were now stationed in the pilot villages. From each village, men and women were trained as teachers and health personnel, and two Village Conservation and Monitoring Units were carrying out regular patrolling in the surrounding zones. Initial mistrust and non-cooperation was reported to have been 37 overcome, “with project activities beginning to stabilize the swidden (shifting cultivation) system and to reduce the number of very poor and poor households in each village” (NT2 POE: 2003). At the Government level a Prime Ministerial decree in December 2000 formalized the boundaries of the Nakai Nam Theun National Biodiversity Conservation Area that now included the corridor to the Khammouane limestone conservation area. Government approval was also given through a Prime Ministerial Decree signed in February 2001 to institutionalize the conservation area’s management plan within an autonomous government Watershed Management and Protection Authority to be chaired by the Minister of Agriculture with the Governor of the encompassing province as vice-chair. At the Project level, the Government and NTEC initialed the Concession Agreement for the project on December 19, 2001. The day before the Power Purchase Agreement between Laos and Thailand was to be signed in July 2003, EDF unexpectedly announced its withdrawal from the Company. Uncertainly continued until October when the Government of France announced that the decision to withdraw EDF had been reversed. On November 10 the Power Purchase Agreement was signed. Affected Communities and Their Environmental Surroundings Introduction Both the Government of Laos and the project consortium have committed themselves to policies that meet the criteria of the World Commission on Dams and that go beyond World Bank Guidelines. Affected communities, for example, should be project beneficiaries as shown by improved living standards. The sections that follow are intended to shown how that goal could be achieved if approved planning is successfully implemented. Dealt with in order are affected communities on the Nakai Plateau, in the watershed conservation area, and within the Xe Bang Fai basin. The Nakai Plateau The Existing Situation Aside from the odd household, all members of the 17 project affected villages are indigenous people according to World Bank guidelines. Brou are the largest single ethnic group, followed by Bo and various Vietic groups. Though the population can be split “into twenty-eight ethnic sub-groups on the basis of linguistics” (NTEC 1997:4-2), all have been affected by intermarriage, the dominant Lao lowland culture, including language, and war. According to Sparkes, “One can speak of a Nakai culture, a kind of ‘melting-pot’ culture consisting of a shared material culture, common socio-religious beliefs and agricultural practices” (1997: 11). That does not mean, however, that very distinctive cultural variations do not exist within and between communities, as Chamberlain has pointed out (communication to the author). Indeed, as Sparkes notes each group defines itself as a distinct cultural group by name in spite of a tendency for 38 villagers to classify themselves as ‘highlanders’ (Lao Thung) in contrast to the dominant lowland Lao Loum (ibid: 12). Agriculture remains the dominant component of each household’s diversified economy. Soils are poor, however, with an estimated cultivation area for the 17 villages of only 471 hectares – “less than 0.10 ha per inhabitant” (NTEC 1997: 4-6). Though rain fed rice is the preferred crop, in 16 villages surveyed by CARE in 1996, only 17 percent of households could produce enough to last a full year, with nearly half having a rice deficiency for over six months. While a few villages have begun to experiment with dry season paddy rice, the CARE survey reported only 78 hectares in 1996 and that was confined to four of the sixteen villages. Livestock and non-timber forest products provide the cash or bartering capacity that is needed to acquire rice and other basic needs staples. 3,100 water buffalo are the most important livestock. Ownership is skewed with half owned by households in two villages, while a “significant proportion of households” own none (RAP op.cit.). Aside from a school and hospital in the district headquarters, social infrastructure is poor to nonexistent in all villages. Where schools do exist, they are restricted to the lower grades while morale among poorly and infrequently paid teachers is low. During my first visit to the Nakai Plateau in January 1997 I was struck not only by the poverty of the people living in project affected communities but by the scarcity of wildlife and the general degradation of much of the area. Initially trained as an ornithologist, I was especially aware of the general absence of birds which reminded me of the civil war-ravished areas that I had traveled through in Mozambique in 1993. The per capita income was estimated to be only about 60 percent of the national average. The Vietnam war caused much of the poverty. From 1964 to 1973 United States dropped over two million tons of ordinance on Laos “during 580,344 bombing missions, or the equivalent of one planeload of bombs every eight minutes around the clock for nine years” (UXO Lao PDR Trust Fund 1995). Because the Ho Chi Minh Trail traversed the length of the Nakai Plateau, all 17 villages would have been under attack from aerial bombardment with the area around Nakai District Headquarters and the Nam Sot confluence with the Nam Theun most heavily hit. Under such circumstances, reports by villagers that the number of their water buffaloes was drastically reduced, with some families losing all their animals, must be taken seriously. Since domestic stock constitute the villager’s bank account to be drawn upon during times of misfortune such as crop failure, sickness and death, the war’s impoverishing effect was serious. One result has been increased reliance on gathering and hunting which would help explain the degradation of biodiversity that the Panel observed. Other factors have also contributed to the area’s current degradation and the impoverishment of its population. Both are project related. Most significant was commercial logging by the military parastatal responsible for the administration and development of Laos’ central highlands. Following the Government’s decision to sole source the project to the Company in 1993, commercial logging is reported to have increased from 30,000 cubic meters annually to 300,000 until it was restricted to the 39 future reservoir basin in 1996 as a World Bank requirement. Though the central government received royalties, few benefits reached local people. Logging was largely carried out by Vietnamese companies with Vietnamese crews who also exploited the plateau’s natural resources. In addition to loss of wildlife, especially serious for the village population was the further reduction of such non-timber forest products as resin, rattan, and cardamom which, along with livestock, had been an important source of income for purchasing food and other essential goods and services. Another impoverishing factor has been the delayed implementation of the project. Partially responsible was the 1996-1999 Asian economic downturn which reduced Thailand’s demand for energy, caused a serious devaluation of Lao currency, and slowed project activities. Convinced that the project’s potential can best be realized with the active involvement of the World Bank Group, the Panel has also been critical of the length of time that it had taken the World Bank to move from project identification to project approval. As stated in its January 2001 report, “The POE is aware of no other World Bank-assisted hydropower project where a member country has been asked to meet such a large, indeed escalating, number of requirements over such an extended period of time.” Resettlement and Development Plans for Making the 17 Communities Project Beneficiaries. The best such plan that I have seen, the Resettlement Action Plan – if implemented – has the potential of helping the large majority of the population to significantly raise their living standards. The word “significantly” is important. The people’s current poverty is so great that implementation of even a mediocre plan could reduce their impoverishment. But they would still be poor. The intent of the Resettlement Action Plan is to help those involved end their impoverishment. During extensive in-village consultations, members of all 17 villages made it clear that, aside from individual families who would use resettlement to join kin elsewhere or for other purposes, the large majority wished to remain not only on the Nakai Plateau but within their current spirit territories. That desire has been largely honored, hence reducing the host-resettler problem that characterizes the Lesotho Highlands Water Project as well as many other dam-induced resettlements. Furthermore, in two cases only part of a village is required to shift to higher ground. Villagers were actively involved in planning the resettlement process, with anthropologist Stephen Sparkes asking separate groups of men and women to map their “dream villages” (Sparkes 1997) in regard to layout and infrastructure. A range of gendersensitive household livelihood options have been developed, which take into consideration both income generation and household labor resources. Each option is based on a “high degree of diversification and flexibility …to allow for changes over time” (RAP 1997: E-8). Seven major components are involved, none of which is required to generate more than 20 percent of a household’s income. 40 In addition to cultivation of rice and fruits and vegetables, they include livestock management, wage labor, fishing, collection of non-timber forest products and participation in the management of community pine and deciduous forests. In addition to the remaining forests, the reservoir will also be utilized as a resource. Because the reservoir depth averages less than 10 meters at full storage level, an extensive drawdown area will be available for recession cultivation and grazing. Fishing, the Panel has recommended, should be restricted to members of affected communities, while fish processing and marketing should be open to all comers rather than restricted to a single concessionaire as has been the case on the Nan Ngum reservoir. The Panel feels strongly on this issue because of the importance of reservoir fishing and fish marketing as a source of employment and income generation for other dam reservoirs in the tropics. Should the various livelihood components be implemented as planned, total family income could be expected to exceed the country’s poverty datum line almost by a factor of two. An all-weather road will be constructed through the resettlement area which currently is served by tracks - significant portions of which are impassable during the rainy season or when churned up by logging trucks. Electricity will be extended to the edge of each village, with a piped water supply, along with wells, provided within the village. Each family will be provided with 0.5 hectares of cleared land before moving, along with housing, tools and seedlings. Though land for irrigated paddy is scarce, where available families will receive 0.15 ha. To test such livelihood components as stall fed livestock, and fruit and vegetable cultivation, an experimental farm has been in operation since 1996 with three pilot families settled in 1997 to experiment with the different livelihood options. For training purposes and propagation a nursery was established in 1998. By 2000 a village near the district headquarters had been selected to pilot the resettlement action plan along with an adjacent irrigation project large enough to incorporate households from a number of villages on small plots that could produce the paddy component of their livelihood plan. At the time of the Panel’s January 2003 visit several households had moved into new houses, while others were clearing new fields and cultivating vegetable gardens along a small stream. Their main complaint concerned ongoing delays in the project’s implementation. The Nam Theun Watershed between the Dividing Hills and the Annamite Mountains The Current Situation Human settlement in the watershed area is located along the different tributaries immediately upriver from the hills that offset the NT2 reservoir from the Proposed Protected Area. What evidence is available suggests that living standards among a population of at least 6,000 people are somewhat higher than on the Plateau due to less Vietnam War and project impact. Though included within Nakai District, much of the area, however, is more isolated with the three southeastern most tributary villages reachable only by foot. To reduce the watershed’s isolation and to open the area for logging, the responsible military parastatal had begun building a road into the area from the highway system in the neighboring province to the northeast. By the time 41 construction was stopped as a 1996 World Bank project-related requirement it had reached the village of Ban Navang on the Mon River. From there a logging road had been built at right angles to gain better access to the cypress pockets in the Annamite Mountains from where cut timber was lifted by helicopter to the logging road terminus. That too was stopped as a World Bank requirement in 1996. At least ten distinct ethnic minorities live within the Nam Theun watershed conservation area. The earliest arrivals were Vietic speakers whose “ethnic diversity represents a critical dimension of biodiversity” (Chamberlain 1997: 1-6). Separated by ridges between tributary valleys, they developed different cultures with economies varying from foraging to sedentary cultivation of a variety of crops including paddy rice. Aside from the most recent foraging groups, most interesting from an anthropological perspective were the Kri who lived close to the border with Vietnam. Located on a trade route, their economy was based on trade as well as a system of shifting cultivation based on rotation between a series of fixed village sites. As recently as the early 1970s several groups of Vietic speakers, each containing less than 50 families, were still nomadic foragers with invaluable indigenous knowledge of the upper reaches of the tributaries and associated forests where they lived. In Chamberlain’s words “their intimate relationship between nature and culture” represents “a resource of inestimable value for Laos, a cultural type that is practically extinct in South East Asia, and that is found nowhere else on the planet” (ibid: 7). Tragically, starting in the mid 1970s, the government rounded them up for involuntary settlement in existing communities within and without the conservation area. Mortality rates were excessive so that all such groups are threatened with extinction unless they develop ties of intermarriage with each other. The largest group, and culturally the one with the best chance at survival, are the Themarou. Settled primarily in the furthermost village up the Nam Theun in the conservation area they numbered 200 individuals living in 39 households in the mid-1990s. When visited by the Panel, a few families had begun to experiment with dry season paddy cultivation. Yet their foraging past was sufficiently recent that they still had their no longer worn bark clothing. The next arrivals were the Sek. Claiming to have emigrated into the conservation area early in the 18th century, they numbered about 600 in the mid-1990s and lived in three villages along the upper reaches of the two conservation area tributaries southeast of the upper Nam Theun. They brought with them a sophisticated system of dry season paddy rice cultivation with water diverted by small weirs through canals and bamboo piping to their paddies. As with the various communities of Vietic speakers, the Sek economy appeared to be in balance with the natural resource base. That is not the case with the Brou who are the latest and largest group of immigrants. Numbering over 3,000 individuals they have established villages along all six rivers where the basis of their economy is an expansive system of bush fallow agriculture. Due to the highest rate of population increase within the conservation area, estimated time for a doubling of their numbers is less than twenty years. 42 The more densely settled areas along the watershed rivers were also bombed during the Vietnam war, though to a lesser degree than on the plateau. The same applies to adverse impacts caused by the long period of NT2 project planning. Adverse impacts were of two sorts. Though beneficial in the long run if current plans are implemented, stopping the road construction efforts of the military parastatal has kept the area in isolation. Though the roads were primarily to open the area to logging, they were also intended to reduce the isolation and improve the social services of all five tributary areas by connecting them with a road that would run the width of the conservation area. The lack of continuity in the pilot development and conservation activities that raised village expectations during the 1998-99 period of IUCN activities has caused confusion and adversely affected morale. The Nakai-Nam Theun conservation area has also suffered in recent years from intense rainfall that has caused flooding, as well as some land slippage and tributary siltation. Riverside fields have been eroded with crops destroyed. Severe pest infestation has also been a major problem with a “plague” of rats also adversely affecting crop yields. Though explanations vary as to causality, the extent and form of shifting cultivation is not considered to be a significant factor. Whether or not global warming is involved as opposed to natural variation in rainfall remains a question. As for the ‘plague’ of rats two explanations exist. One is a natural increase in the rodent population associated with the “hundred year” flowering of the dominant species of bamboo. The other is reduction in the population of small predators due to hunting pressure from local villagers as well as transboundary poachers who at any one time may dominate residents within a 20 kilometer distance from the joint border with Vietnam. Development Plans for Making the Conservation Area People Project Beneficiaries. The most important immediate development need is to implement the autonomous Watershed Management and Protection Authority. A major strength of the Authority as planned is the way the development of the 6,000 residents is integrated with landform and biodiversity conservation. Unlike the situation in other parts of the country where government policy has been to move upland minorities to the lowlands, a project requirement for the conservation area is that no involuntary resettlement is acceptable. That includes both resettlement from the area and village consolidation within the area; indeed, one recommendation of the Panel has been that the former foraging groups should be allowed to return to their former habitats should they so wish. Landform and biodiversity conservation must be intricately integrated with stabilization of village production systems. That will not be easy especially in the case of the Brou who constitute the majority of the population. The outlines of an approach have been piloted by IUCN, EcoLao and more recently the District Upland Development and Conservation Project with special emphasis on the Brou village of Mak Pheuang on the Nam Theun a short distance upriver from the Dividing Hills. The key component is the intensification of crop agriculture through water diversion for dry season paddy rice cultivation so as to reduce emphasis on shifting cultivation. During successive visits, the 43 Panel has not only been told of requests from villages in different tributary valleys for assistance with irrigated dry season cultivation, but has also seen its gradual expansion within a number of Brou villages. Without pressuring people, one still-to-be resolved issue is how to accommodate households who may wish to leave the conservation area. Though exceeding inmigration, to date out-migration has been on a small scale. Should development plans for the Plateau and for the lowlands along the Xe Bang Fai be implemented as intended, one can anticipate more households wanting to join kin or villages in both areas because of their higher level of social services and income generation. Releases of water for irrigation from the regulating reservoir below the power station, for example, will be for a area from which Chamberlain believes Brou immigrants came. Thought the project consortium sees its resettlement responsibilities restricted to Nakai Plateau households and villages directly affected by project works, development with conservation can be expected to depend on the extent to which the area affected by the project is incorporated within an overall development plan that stretches from the Vietnam border to the Mekong. That will require closer integration of the Resettlement Action Plan and the Watershed Management and Projection Authority, as well as with on-going planning along the Xe Bang Fai by the Department of Irrigation than has occurred so far. Just as development activities are urgently needed now, so too are conservation activities throughout the area under the Watershed Conservation and Protection Authority. Especially important is the integration of the type of village biodiversity awareness program and village-based biodiversity patrols piloted by IUCN with the activities of the Lao security forces that must play an increasingly important role, especially along the international border, if the illegal wildlife trade is to be controlled. In addition to implementing the Watershed Management and Conservation Authority and the necessary development and conservation activities, another important project benefit will be the extension of Nakai District responsibilities into the conservation area. Currently there are only five primary schools for a population of over 6,000, three of which are single room structures covering the first two grades with teachers who are irregularly in residence. A two-room building, the fourth school was built by the military parastatal at Ban Thameuang close to where the military’s road crossed the first tributary. The fifth and largest school has recently been completed as a result of World Bankassisted project influence at Mak Pheuang. While Nakai District has facilities on the plateau including a hospital, two health centers and a Malaria Station, there are no health facilities in the conservation area (IUCN 1997.Part II: 19). As a substitute for the previously planned road crossing the width of the conservation area that would tie communities closer to the neighboring province rather than to Nakai District headquarters, current plans are to link the plateau headquarters to the three subdistricts by tracks paralleling the tributaries that would be wide enough for the passage of ox carts and two wheeled tractors but not for four wheeled vehicles. 44 The Xe Bang Fai River Basin The Existing Situation Aside from Brou living along the Nam Khatang tributary in Gnommalath District immediately below the escarpment, villagers close to the Xe Bang Fei are largely lowland Lao. Five of the project’s 12 zones lie within the Xe Bang Fai Basin. Zones 7-9 cover different parts of the Gnommalath Plain, while Zone 10, called Upper Xe Bang Fai, includes the next district downstream. Zones 11 and 12 include the Middle and Lower Xe Bang Fai. Though the riverine population probably exceeds 70,000 people in all five zones, their current life styles, including degree of dependence on the river, have been less extensively surveyed than is the case with the population on the Nakai Plateau and in the Nakai Nam Theun conservation area. As elsewhere in the lowlands their economy is dominated by the rain-fed rice cultivation complemented by a slowly increasing amount of dry season irrigation. Gravity fed into a community irrigation project on the Gnommalath Plain, water elsewhere is lifted by diesel operated pumps that slowly are being electrified. Where river banks are not too steep, flood recession dry season gardens are an important source of maize and vegetables. Next in importance to rice as a food, fish is the major source of protein. Development Plans for the Xe Bang Fai Villages to Become Project Beneficiaries. The current annual flow of the Xe Bang Fai will be almost doubled once the power station commences operation. Impacts on the river’s natural regime will be greatest during the dry season when water levels in the upper zone channel will be increased 3.4 to 4 meters. Though the draft Environmental Assessment and Management Plan states that impacts on riverine communities will only be “slight to moderate” (SEATEC 2000), they will be heaviest on communities most dependent on flood recession cultivation. The Panel is also of the opinion that such radical changes in river flows will also have an adverse effect on fisheries – an opinion held by the most knowledgeable fishery experts as opposed to the belief of the project authorities and their consultants that ‘more water means more fish.’ As a result of a panel recommendation, a program of annual pre- and post-project completion fishery surveys was started in 2001 which will document what impacts actually occur. During 2001 independent and project consortium livelihood surveys were also completed. The best approach for mitigating project impacts, on the one hand, and improving livelihoods, on the other hand, is hydrological and socioeconomic. As a mitigation effect, the turbines will be shut down when water levels reach a predetermined height in the upper zone so as to avoid increased flooding of irrigated floodplains. In the irrigated areas of the delta the backwater effect of the Mekong will be somewhat lessened due to reduced Mekong flows from the Nam Theun. At an increase in project cost, another mitigation measure was to select a less densely settled route for channeling the turbined water from the regulating reservoir 27 km to the Xe Bang Fai. 45 If affected communities are to benefit it will be necessary to use turbined water to increase significantly the area under dry season irrigation. If implemented, existing plans for the use of project water and electricity have that potential in all project zones. While passing through the Gnommalath Plain, one fourth of the 27 km channel will be sufficiently raised above ground level to allow double cropping in the local irrigation project. Though designed to irrigate 2,400 hectares, during the 2000-2001 dryseason only 335 hectares were cultivated (Vientiane Times, January 12-15, 2001). Outflows from the regulating reservoir are also designed to release 15 m³/s into another Xe Bang Fai tributary which can be used for irrigation and domestic purposes by 20 riverine villages. Further downstream, natural regime water levels falling as low as 3 m³/s in the upper zone are a major constraint to an estimated dry season irrigation potential of over 20,000 ha. Even the 3,000 ha. that have been developed to date are adversely affected by low water levels which increase pumping costs and may stop pump operations entirely. Greatly increased project flows during the dry season will not only reduce those pumping costs but will provide the opportunity to increase greatly the area under dry season irrigation. Already the Department of Irrigation has drawn up plans to use turbined waters for that purpose (2002 communication from Robert Goodland). Increased electrification of pumps can be expected to follow the ongoing electrification of the area by the World Bank-funded Southern Provinces Electrification project. Using electricity the Bank is also considering irrigation development in the uppermost zones (SEATEC 2000). It is very much in the interests of the Company and the government to integrate those plans into an overall regional development plan for the entire project area. Such a plan should also combine aquaculture with irrigation along lines proposed by the Department of Fisheries and address the fishery implications of the new Xe Bang Fai regime. With the potential to raise living standards such an approach also has the major benefit of addressing what I believe could otherwise be the most serious costs of the NT2 Project. Risks Introduction Unless the plans previously described are adequately implemented, the Nam Theun 2 project has the potential to be a disaster for the environment of the Nakai Plateau and the Nam Theun watershed, as well as for affected communities from the Vietnam border to the Mekong River. Of various risks, two are potentially serious. One is lack of political will on the part of the government; the other is lack of implementation capacity. Political Will With large dams one never knows whether governments and project authorities have the necessary political will until environmental and social plans are actually implemented. Though some critics believe that the communist government of Laos has no intention of implementing the NT2 Project as planned, the history of how affected communities are dealt with does not appear to be influenced by form of government. The record, for 46 example, of Canada and the United States is poor in regard to large dams requiring the resettlement of ethnic minorities. On the other hand, two of the best planned and implemented projects are associated with a socialist government (Egypt in regard to Aswan High Dam resettlement) and a communist one (China in regard to Shuikou Dam resettlement). In the NT2 case, of more concern are a number of past and present government policies which if applied in the Nam Theun project area would run counter to current plans. One such policy relates to past attempts to resettle ethnic minorities from the uplands to the lowlands, in some cases incorporating them within larger Lao host communities. Few such relocations, if any, can be considered successful from the point of view of the resettling communities (UNESCO/UNDP 1997). Top down government control of rural land, water and other natural resources is another worrisome policy since it has interfered with the ability of the government to implement World Bank-financed community forestry projects. That inability raises the question as to the government’s political will not just to implement such projects within the context of the Resettlement Action Plan for the Nakai Plateau but also to allow the population of the Nam Theun conservation area to play a major role in the Watershed Conservation and Protection Authority. Capacity Since I believe both the government and the project consortium are committed to implement existing plans, the most serious risk I believe to be inadequate implementation capacity. The most serious capacity problem relates to the Watershed Management and Protection Authority which must be able quickly to control the currently unsustainable transboundary poaching of wildlife and collection of non-timber forest products. As recommended by IUCN, staff of the Authority would number 197 members “at full operational capacity” (July 1997. Part IV: 8). The largest number would be concerned with protection functions (30 percent) and with village development and ethnic minority preservation (also 30 percent). Piloted by IUCN between 1998 and 1999, after a two year gap the District Upland Development and Conservation Project has recommenced the type of training that is necessary to staff the Nakai District office as well as the Authority. Because of the active involvement of the Company and the nature of the resettlement program, staffing capacity, while less serious than with the Watershed Conservation and Protection Authority, will still stretch government resources. A high level Resettlement Committee will report to the Vice Prime Minister on the work of its Resettlement Management Unit. The Unit staff dealing with technical, administrative and financial issues will work closely with Nakai District staff and where necessary with provincial and central government technical and administrative officials. Development along the Xe Bang Fei will be largely the responsibility of district staff working with provincial and central government Department of Fisheries and Department of Irrigation personnel. The government’s ongoing prohibition against independent environmental and community development NGOs is unfortunate since they could have played an important role, as in other countries, in capacity building activities. 47 In addition to staffing another capacity problem is coordination. As with the Lesotho Highlands Water Project, the NT2 project falls under a single ministry (the Ministry of Industry and Handicraft) and within that Ministry under the Laos National Committee on Energy. In the Panel’s experience responsibility for such a complex project with major regional and national development implications is “too much for a single ministry” (NT2 POE 1997: 7). The active involvement of the Deputy Prime Minister in NT2 planning and his ongoing interest in the project as well as the interest of the Prime Minister may enable the Minister of Industry and Handicraft to obtain the necessary cooperation from other ministries and agencies through a central working committee that he chairs. Because that remains to be seen the Panel recommended that the effectiveness of such an institutional setup should be “re-evaluated at regular intervals” (ibid). Project components such as the Resettlement Action Plan, the Environmental Assessment and Management Plan, and the Watershed Management and Conservation Authority all have their own coordination problems with other government agencies. The Authority’s effectiveness, for example, will depend in good part on its ability to work with the military parastatal for the central region and other security forces in patrolling the international border and upper portion of the watershed. 48
© Copyright 2026 Paperzz