Proceedings of Bridge Engineering 2 Conference 2009 April 2009, University of Bath, Bath, UK A CRITICAL OVERVIEW OF THE VERRAZANO-NARROWS BRIDGE W. T. Arnold1 1 rd 3 Year MEng Undergraduate Student, University of Bath Abstract: This conference paper provides a critical analysis of the Verrazano-Narrows Bridge in New York City. It analyses the design aspects of the bridge, along with the finished structure and how it performs today. It looks at the aesthetics, structure, construction and serviceability of the bridge, along with analysing the loading on the bridge in terms of the current British Standards. Keywords: Verrazano-Narrows, New York, suspension, steel, Othmar Ammann Figure 1: The Verrazano-Narrows Bridge 1 Introduction1 The Verrazano-Narrows Bridge is a double-decker suspension bridge that connects the New York City Boroughs of Staten Island and Brooklyn, and is named after Giovanni di Verrazano, the first known explorer to enter New York Harbour. It was the final bridge to be designed by Othmar Hermann Ammann, a Swiss-born structural engineer who was responsible for designing many of the other large-spanning steel bridges in New York and New Jersey, such as the George Washington Bridge and the Bayonne Bridge. 1 Mr. William Thomas Arnold - [email protected] Construction started on the bridge in August 1959, with the upper deck being opened to the public on November 21st 1964 at a cost of $320 million - $100 million over budget [1]. The lower deck was kept closed to the public until June 28th 1969, nearly four years after Ammann’s death, as there was no need for its extra six lanes of capacity until then. The design and construction of this bridge was commissioned for several reasons. The first was to provide a connection between Staten Island and the rest of New York City that would not be hampered by adverse weather conditions in the same way that the current ferry system was. It was also deemed to be desirable as it would form part of an expressway that would link New England, New York and New Jersey together; and form part of a route for express buses to travel along when going between Manhattan, Brooklyn and Staten Island. Finally, the Triborough Bridge and Transport Authority (TBTA) chose to commission a bridge to cross the Narrows rather than a tunnel as it would be quicker and cheaper to build, along with providing a greater traffic capacity. bridge, then the facade would far more flowing and uncluttered, enhancing the appearance of the bridge deck. The fact that the suspender ropes have been designed in groups of four also detracts from the order of this bridge. 2 Aesthetics Whilst every bridge is individual and as such, every bridge has its own unique reasons for why it looks beautiful or ugly, it is widely accepted that in order for a bridge to be as aesthetically pleasing as possible, Fritz Leonhardt’s ten areas of aesthetics should be adhered to. This section analyses the areas relevant to this bridge. Figure 3: Close-up of the deck from a distance 2.1 Fulfilment of Function When viewing the elevation of the bridge from a distance, it is obvious straight away how the bridge works. The strong looking towers at either end of the deck carry all of the compression in the bridge, and the purpose of the suspension cable is very clear to see. However, the deck itself does appear to be superfluously deep, but this is an issue that is unavoidable in a bridge that carries two decks of traffic. Figure 2: Profile of the bridge 2.2 Proportions of the Bridge With a height to length ratio of nearly 1:10, the Verrazano-Narrows Bridge looks slender and efficient. There is a good balance between mass and void under the bridge and it doesn’t look over-engineered. The curve at which the bridge deck rises towards the centre of the span helps to add extra space underneath the bridge that helps add a sense of lightness and efficiency. 2.3 Order within the Structure From a distance, this bridge appears to have very good order about it, with the number of different structural elements being kept to a minimum. However, at closer inspection, the bridge loses this simplicity in its order. The main problem isn’t the truss element of the deck which is a necessity in order for the bridge to carry two levels of traffic, but amount of structure elements emerging from the deck, such as the vertical ties that the hanger cables are attached to in Fig. 3, and the horizontal struts that hanger cables are attached to in Fig. 4. If these were removed from the design of the Figure 4: Close-up of the deck from below 2.4 Integration into the Environment As this bridge crosses the main access into Upper New York Bay and the Hudson River, it was always important that it had a high enough clearance underneath it to allow as much sea-traffic through as possible. For this reason, a suspension bridge was an obvious choice as a simply-supported concrete beam bridge wouldn’t give enough clearance underneath it for huge oil-tankers to pass through. This light grey suspension bridge fits seamlessly into the environment, as it is a continuation of the built up city surrounding it. A long masonry arch bridge, concrete box-section bridge or timber truss bridge would look very out of place as a span of this size demands a bridge that is equally imposing. 2.5 Texture and Colour Rather than paint the Verrazano-Narrows Bridge in striking colours to help it stand out on the horizon, the whole bridge is painted a light grey-blue colour. Part of the reason for this monotony of textures and colours is that the bridge is only used by road traffic. As there is no pedestrian or bicycle traffic allowed over the bridge, there is no need for details which would only be experienced by a slow moving pedestrian or cyclist. Instead, it makes more sense to save time and money by painting the entire bridge in one colour. Ammann has carefully used shadows on the bridge towers to make these look more slender than they actually are. This effect is apparent in Fig. 3, where it can be seen how the shape of the towers gives makes them look thinner on the outside of the bridge than they look on the side nearest the deck. harsh urban city in which the it sits. And whilst there is no way to blend a bridge of this size into its surroundings, the grey painted steel finish does fit in with the majority of ships that pass under it every day. 2.6 Character Whether a bridge has character or not is not necessarily a matter of fact, and is often more one of opinion. Calatrava’s bridges are often referenced when talking about character, because of their individualism and uniqueness when compared to other bridges of their time. However, a logic-defying form of a bridge is not the only thing that gives it character. 2.9 Aesthetics Summary This is a bridge that is both beautiful and majestic, because of its size and position. However, Mies van der Rohe famously said that “God is in the details” [2] and sadly, in the Verrazano-Narrows Bridge these beautiful details are lacking, resulting in a bridge that is less well ordered than it could have been. 3 Loading When this bridge was first designed, it will have been designed to cope with loading cases outlined in the standards set by AASHTO – the American equivalent of the British Standards. However, for the purposes of this paper, I am going to analyse the loading on the bridge to BS5400-2:2006 [3]. As the bridge has no facilities for pedestrians, no pedestrian loading has been taken into account in these calculations. There is a possibility that this will become an issue in the future, but compared to the traffic loads, it would still only make up a very small percentage of the overall loading. Figure 5: Satellite image of New York Bay This bridge has great character because of its size and position. Anyone who travels into New York Harbour by ship will have to pass under this colossal man-made structure that acts as a gateway to the world’s financial capital. It’s the longest suspension bridge in the USA, and can be seen from various points all over New York City. There is no doubting the impact that this bridge has made on the skyline of New York Bay. Figure 6: Load path diagram 3.1 Dead Loading 2.7 Complexity in Variety The Verrazano-Narrows Bridge has very little complexity to it as it just a large-span suspension bridge. However, this should not be seen as a bad thing, as its simplicity is what makes it such a graceful bridge when viewed from afar. Without this simplicity, the order of the bridge (see section 2.3) would not be as easy to see, and as such the bridge would not look as graceful as it currently does. 2.8 Incorporation of Nature Whilst nature doesn’t influence this bridge in as obvious a sense as many other bridges the world over, it could be argued that for a bridge as un-natural and prominent as this, the nature which has been incorporated into the design of the bridge is that of the Figure 7: Section through bridge deck Reference [4] states that the total dead weight of the suspended structure is 51,000tons, or 454MN. With a total suspended bridge length of 2039m, this equates to an un-factored dead load of 223kN/m. 3.2 Superimposed Dead Loading 3.4 Wind Loading On top of the dead load that is provided by the structural elements of the bridge, a superimposed dead load needs to be assumed. As this is so difficult to accurately predict, BS5400-2 gives very high safety factors. These factors can be found in Table 1 of Ref. [3]. The superimposed dead load on the VerrazanoNarrows Bridge is assumed to be made up from the following: 50mm of bituminous asphalt (23kN/m3), 200mm of saturated sand fill (21kN/m3), and an added 1kN/m2 for services. The road surface and fill are assumed to be covering a carriageway width of 28m in total (see section 3.3), and the services cover a 31m width. This gives a total un-factored superimposed dead load of 181kN/m. 3.3 Vehicular Live Loading The total width of the bridge deck is 31m [1]. From this and satellite images, it is fair to assume that the total carriageway width is about 28m. The total length of the Verrazano-Narrows Bridge is 2040m. According to clause 6.2.1 of Ref. [3], for a loaded bridge length over 1600m, the HA UDL needs to be agreed with the relevant authority. However, as this is not possible, for this analysis the HA UDL will be calculated from the following equation: The maximum wind gust is calculated as being: (2) Due to a lack of sufficient data, the mean hourly wind speed, v is assumed to be 30m/s. The bridge’s height above ground level is 70m [4], and the total wind-loaded length of the bridge is 2040m. This gives a wind coefficient, K1 of 1.53 and a gust factor, S2 of 1.39. The funnelling factor, S1 is taken as 1.00 as funnelling is highly unlikely to occur for this bridge. As Fig. 4b) in Ref. [3] explains, due to the cross section of this bridge, wind tunnel tests would be required in order to calculate the forces acting upon it. However for the purposes of this report, all forces shall be calculated using the equations that are applicable to the bridge sections shown in Fig. 4a) of Ref. [3]. 3.4.1 Transverse Wind Load The horizontal transverse wind load is given by: (3) where (1) HA loading = 16.8kN/m of notional lane KEL = 120 kN (placed for most adverse effect) (4) This means that the dynamic pressure head, q is equal to 2495N/m2. Figure. 10 shows the profile of the deck when viewed from the side. Due to this bridge’s size, a full HB loading of 45 units will be used in the analysis. This is a loading of 112.5kN per wheel. Figure 10: Sketches of deck elevation [5] Figure 8: HA and HB loading on upper deck Figure. 8 shows the loading layout on one of the bridge decks only. It is highly unlikely that the bridge would be designed to cope with HB loadings acting on both decks at once, so the loading layout on the other deck is shown in Fig. 9 below. Figure 9: HA and HB loading on lower deck Both A1 and CD depend on the depth of the section, and this value depends on whether or not live load is included in the calculations. The left half of Fig. 6 shows the elevation of the deck with no live load, and the right half shows it with an added live load. With no live load, the depth of the section equals 9m, and the projected surface appears to be approximately 50% solid. When the live load is considered to be acting on both decks of the bridge, the depth of the section can be increased by adding a 2.5m high vehicle to both upper and lower decks. This would increase the section depth to 10.5m, with the projected surface increasing in solidity to about 75%. The largest transverse wind force acting on the bridge is obviously going to occur when live load is present, due to the much higher depth and solidity of the section. load (where the depth of live load is 2.5m) and CD changes to 1.45, as outline in clause 5.3.4.3 of BS54002 [3]. m2 3.4.4 Wind Load Combinations There are four combinations of wind load, all that must be considered to find the worst case scenario. These are outlined in the table below. The transverse load acting on the piers should also be taken into account, also using Eq. (3). The piers t/b ratio has been assumed as 1. The breadth of the piers has been taken conservatively as 14m as there is insufficient data available. Data available from Refs. [1, 5] give the maximum clearance at the centre of the bridge, the maximum longitudinal grade of the bridge, and the length of the main span. From these, the pier height can be assumed to be about 55m. Table 9 of BS5400-2 [3] therefore gives the coefficient of drag for the piers as 1.4. So, ignoring shielding effects of the upwind piers on the downwind piers, the transverse wind load on each pier is 3.4.2 Nominal Vertical Wind Load The vertical downward force caused by the wind is calculated as (5) Where the plan area, A3 is 57120m2 and the coefficient of lift, CL is ±0.64, found from Fig. 6 of Ref. [3]. 3.4.3 Longitudinal Wind Load Due to the solidity of the bridge deck’s elevation being so high (75% when live load is included), the longitudinal wind load, PL is calculated using equations that refer to bridges with solid elevations, rather than bridges with truss girder superstructures. (6) (7) (8) In Eq. (7), q, A1 and CD are all the same as in Eq. (3). However, in Eq. (8), A1 is purely the area of live 1 2 3 4 Table 1: Wind loading combinations Pt alone 68.9MN Pt ± Pv 160.1MN or -22.3MN PL alone 32.9MN 0.5Pt ± 0.5PL 50.9MN or 18.0MN Taking the worst case combination of wind loads, the un-factored wind loading for this bridge is 160.1MN total. 3.5 Temperature Loads Because of the bridge’s size and orientation, during the day one side of the bridge often warms up more than the other, causing unequal expansion throughout the bridge. To ensure that this didn’t affect the surveying of the construction, all precision measuring of the bridge took place during the night, when the bridge was at a constant temperature throughout [4]. 3.5.1 Effective Temperature Loading This loading is due to an overall increase or decrease in temperature between night and day. The maximum and minimum temperatures for this location have been taken as 40o and -20o Celsius respectively, for a 120-year return period. However, these maximum and minimum temperatures take place over a whole year, whereas we are primarily interested in the diurnal temperature difference of the bridge. This is taken as 25oC. The coefficient of thermal expansion for both steel and concrete is 12 x 10-6 /oC. Assuming that thermal expansion joints are in place where the deck crosses each tower, the effective length of deck is 1300m. From these, the change in length can be found from Eq. (9) provided that the expansion joints are fully working. The apparent compressive stress that the deck will experience can be calculated from Eq. (10), and will occur if the expansion joints are prevented from moving at all (and δ = 0). (9) (10) An overall temperature change will also affect the length of the main cables and suspender ropes throughout the year. Using Eq. (9) again, but with ∆T set to 60oC (the difference between the maximum and minimum temperatures over a 120-year return period), we can see that the length of the main cable can change by up to 1.6m. 3.5.2 Temperature Difference Loading Temperature difference loading is the loading caused by a variation in temperature between the top and bottom surfaces of the bridge deck. Figure. 11 below shows the difference in temperature throughout the deck section. The two parts of Fig. 9 show how the top of the deck will be approx. 21oC hotter in the morning and 5oC cooler in the evening than the bottom of the deck is. It also shows how the temperature gradient varies throughout the steel deck and girders. These variations in temperature will also cause apparent loads and moments to be felt by the deck. Whilst only the top deck is shown in the figure, the bottom deck will follow a similar patter, though with less of a difference in temperatures due to the shading provided by the upper deck. 3.6.4 Parapet Collisions This is based on 25 units of HB loading, i.e. 1000kN colliding with the parapet. Analysis of this loading based on momentum and impulse forces is required in order to calculate the actual force “felt” by the parapet during a collision. 3.6.5 Substructure Impacts Due to the size of the ships passing under the bridge every day, it is vital that the tower piers are well protected, as one impact from a passing ship could render the entire bridge unsafe. For that reason, the base of the piers are very well protected by artificial islands of rocks designed to absorb the impact of a ship to a level where the bridge will not be affected by a collision. Figure 12: Impact protection around the substructure 3.7 Load Combinations Figure 11: Temperature difference diagram 3.6 Secondary Live Loads The secondary live loads all occur due to the acceleration and collision of traffic in different directions. The effects of these secondary live loads are used in load combination 4 (see section 3.7) and include the following. 3.6.1 Horizontal Centrifugal Loading This can be ignored for the Verrazano-Narrows Bridge as the bridge is straight in plan. 3.6.2 Longitudinal Braking Loading This load consists of a horizontal force of 8kN/m applied over one notional lane, plus a single 200kN force. It also includes 25% of the total HB loading applied over two axles. So in this case, the total longitudinal breaking load applied to the bridge is 16.5MN and the total vertical breaking load is 450kN applied over two axles. 3.6.3 Accidental Skidding This load is modelled as a point load of 250kN acting horizontally in any direction in one notional lane, plus the associated HA loading. The five different combinations of load that need to be checked are outlined in the table below. These each need to be checked at serviceability limit state (SLS) and ultimate limit state (ULS) to find the worst case loading combination. To do this, the loads need to be multiplied by two partial factors, γfl and γf3. These safety factors can be found from Table 1 of BS5400-2 [3]. 1 2 3 4 5 Table 2: Loading combinations All dead loads plus primary live loads Combination 1 plus wind loads Combination 1 plus temperature loads All dead loads plus secondary live loads and associated primary live loads All dead loads plus loads due to friction at the supports 3.8 Loads in the Cables The worst case loading scenario can then be used to calculate the maximum tensile forces experienced by the suspender and main cables. Note that in Fig. 13, the sets of suspender cables (of which there would be eight under each pair of main cables) have been simplified to show one support at either side of the deck. Taking moments about V2 (Fig. 13): 4.1 Materials (11) The main structural elements of the bridge are constructed out of steel due to its high strength and easy workability. The foundations and anchorages are all made out of concrete, a large proportion of which is reinforced. Table 3 shows a rough distribution of the amount of each material used in construction. Most of the data is taken from Ref. [1], but Ref. [4] provided a better idea of the breakdown of the use of steel in the towers and suspended structure. Table 3: Approximate material quantities Steel Tonnes Towers 92,000 Suspended structure 15,000 Reinforcing steel 31,000 Approaches 18,000 Concrete Cubic meters Anchorages 289,000 Tower piers 150,000 Approaches 99,000 Bridge deck roadway 15,000 Figure 13: Typical loading condition These values are total UDLs for the pairs of cables on either side of the bridge. Dividing the larger of the values (V1) by two to share the load between the two main cables on that side; the maximum tension in the main cables can be found as so: (12) (13) (14) 4.2 Bridge Design 4.2.1 Anchorages The two anchorages are each 40m high, 49m wide and 91m long. However, due to differences in the ground conditions at each end of the bridge, the Brooklyn anchorage contains 158,000m3 of concrete, whilst the Staten Island one only contains 131,000m3. The anchorages exist to house the ends of the four main suspension cables that carry the enormous weight of the bridge deck, as well as supporting the two approaching decks of bridge on the landward ends. Where the maximum UDL on the cable, w = 147.5kN/m; the plan length of the cable, L = 1300m; and the midspan sag in the cable, f = 140m. This gives values of Vmax = 191.8MN, Hmax = 222.6MN, and therefore Tmax = 294MN. Note that asymmetric loading does not give a worse case of loading on one side of cables, this is because the total load on the bridge has decreased dramatically enough to counter-act the increase in loading on the side in question. 4 Design and Construction Whilst the Verrazano-Narrows Bridge was a pioneering bridge in terms of its sheer size, the construction of it did not stray too far from the tried and tested methods that were at that time well known by the thousands of construction workers who built the bridge. This section discusses the design and construction of each of the bridge’s components. Figure 14: Inside one of the anchorages [7] The anchorages resist the total lateral load from the cables purely because their weight is high enough to prevent them from slipping at all. As can be see in Fig. 6, the main cables enter the anchorages and are then split up into their 66 individual strands. These strands are each individually attached to the anchorages by inclined steel girders, buried deep within the concrete. The strands are firmly attached to these girders by the steel ‘shoes’ that are bolted on the ends of them. This is shown in Fig. 13. The anchorages also contain rollers for the main cables to pass over on the side nearest the river. They allow the cables to expand and contract freely when there are changes in temperature or loading on the bridge, without exerting any extra forces on the wrong parts of the anchorages. 4.2.2 Piers The piers and foundations were designed to support the 2.5GN provided by the loads on the bridge, and to complicate the design of the foundations further, no bedrock could be found underneath the Narrows, even as deep as 100m below the surface [6] Instead of founding the bridge on rock, it is founded on a deep compacted band of glacial clay. Caissons were sunk into the ground whilst protected from the water pressures by steel cofferdams. This is shown in Fig. 15. These caissons are pressurised chambers that allow workers access to the material under the river, whilst keeping out river water by use of pressurised air. Muck and sand could then be dug up and removed from the caisson through a separate shaft (known as muck tubes). Once a suitable depth of ground had been removed, the caisson could slowly be lowered down, with concrete being added on top in 3m depth increments [6]. Once the predetermined depth had been reached for the caisson (52m for the Brooklyn foundation and 32m on the Staten Island side), the muck tubes (of which there were 66 for each foundation) could each be filled with water. The caissons were then sealed with concrete [4]. It took nearly two years to fully construct the two foundations for the Verrazano-Narrows Bridge, but by 1961, the construction of the bridge towers could begin. Figure 15: Typical caisson schematic 4.3.3 Towers The two 211m tall towers were each constructed by a different steelworks company. The Brooklyn tower was constructed by Harris Structural Steel Co. Inc. and the Staten Island tower by Bethlehem Steel Co. The towers were prefabricated in large sections and bought to site by barges. The bottom three sections of tower were lifted into place by floating derricks that were anchored alongside the tower piers. Once these three sections were in place, towering about 37m above the piers, the floating derricks were removed and replaced by “creepers”. These were derricks that were attached to the towers by rails bolted to the side of them. The creepers could then lift the next tier of tower up the existing structure, allowing it to then be bolted in place at the top. When finished in 1962, the top of each towers stood 212m above the mean water level. 4.3.4 Cables Each of the four cables are 910mm in diameter and are made up of 61 strands. These strands are each made from 428 galvanised steel wires, each 5mm in diameter. Figure 16: Suspender ropes connections [8] The spinning of these wires was carried out in the usual manner of passing the wires back and forth between each end of the bridge on a 1.2m diameter wheel. On a good day, the wheel would pass back and forth 50 times. Workers would grab the wire as it passed and clamp them into place, laying them side-by-side and on top of each other. Once all 428 wires had been carried across the bridge by the wheel, these would be bound together into a strand. When all 61 strands had been bound, they were squeezed into a cylindrical shape by hydraulic jacks and permanently encased in steel castings that provided the saddles for the suspender ropes to sit in. Once all four main cables had been constructed, 262 suspender ropes were attached on to the cable. These steel ropes were prefabricated off-site, so that each one had been correctly cut to length before it even reached the site. 4.3.5 Bridge Deck The final phase of the construction process was the installation of the prefabricated bridge deck. The steel structure of the deck had already been constructed at the American Bridge Company’s steel yard that was four miles upstream in New Jersey. Each of these 60 sections was floated to site by large barges before being lifted into position by hoisting machines on top of the towers. The deck sections were lifted one at a time, starting with the central piece and working outwards towards the towers. This was done so that the cables would keep a roughly symmetrical shape throughout the construction process, and the deflections in the towers would be kept to a minimum. The prefabricated deck sections followed a conventional double-decker design, with vertical stiffening trusses separating the two decks, and lateral braces giving lateral stability. The decks themselves are supported by longitudinally spanning steel I-beams. The depth provided by the second deck means that the rigidity of the bridge is greatly increased over that of a single deck – an issue which had been at the front of ever bridge designer’s mind since the 1940 collapse of the Tacoma Narrows Bridge. Once construction of the steel deck had been completed, the final part of the construction process was to install the concrete roadway and add the finishing touches, such as the road surface, services and painting the steelwork. 5 Strength Othmar Ammann designed all of his bridges in steel because of its low weight when compared to other materials such as concrete. The bridges he created were all very light and inexpensive compared to other bridges of the time and this was due to his use of deflection theory in his designs. From this theory, he believed that the dead load provided by the deck and cables would provide enough structural strength against the effects of other loads applied to the bridge such as wind loading and live loading. This meant that he was able to design a bridge with relatively small stiffening trusses compared to other suspension bridges on the time. The main areas of strength that the bridge needs to be checked for are strength in bending and shear in the deck, and tensile forces in the main and suspender cables. 5.1.1 Bending moments and shear forces To analyse the moments in the deck of this bridge, it is easiest to consider the bridge as a continuous beam, with fixed supports at the anchorages and piers, and flexible supports positioned where the suspender cables would be supporting the deck. It’s fair to say that once the steel structural deck elements were bolted in position, there were very little moments within the deck structure caused by its self weight, due to the fact that the deck was raised into position in sections with the suspender cables elastically deforming under its weight and thus eliminating any moments in the deck. For that reason, the only loads that need to be considered when analysing the bending moments in the deck are those provided by the live load, the superimposed dead load, and also the concrete that was poured onto the deck after the prefabricated steel had been lifted into place. Figure. 17 shows how a bending moment diagram for the bridge might look. As can be seen, the maximum moments in each span follow the same pattern that would be expected from a beam if the intermediate supports were all removed, but of a far smaller magnitude. A good way to get an approximation of the bending moments in the deck is using Table 3.5 of BS8110-1 [9]. This table gives the ultimate bending moments and shear forces in a multi-span beam. The table states that the maximum bending moment in a multi-span continuous beam will occur above the first interior support, and will be equal to 0.11Fl, where F is the total ULS load and l is the effective span between hanger cables. The maximum shear force also occurs at the first interior span, and is equal to 0.6F. When F = 51MN and l = 35m, Mmax = 196MNm and Smax = 30.6MN. 5.1.2 Tensile strength of the cables The maximum stress induced in each of the cables due to the tension applied in them is given in Eq. (15) below. (15) For the main cables, Tmax is given by Eq. (12) and for the suspender ropes, it is the value of w in Eqs. (13,14), multiplied by the distance between two suspender ropes, 34m. In both cases, A is the cross sectional area of the cables in question, 0.66m2 for the main cables, and 0.018m2 for the suspender ropes (with an assumed diameter of 150mm). 6 Foundations and Geotechnics As discussed in section 4 of this report, the ground conditions at the bridge’s location are very poor, even at great depths under the ground. For that reason it is quite a feat of engineering that this bridge stands up at all. Whilst the tower foundations had to be built to depths of over 30m in order to create massive amounts of friction to help support the loads, they also rely on the strength of the glacial clay on which they stand to hold them up. The anchorages however, work entirely on friction being generated by the huge mass of concrete involved at both ends to keep them stable. Because the primary ground condition for these foundations was clay, which has a very low settlement rate, it is important that differential settlement was also considered during the design of the bridge. 7 Durability 7.1 Serviceability Whilst a bridge can be checked under its ULS and proved to be safe enough for use, that doesn’t necessarily mean that it will be perceived as safe by the public. Extreme oscillations and vibrations caused by wind loading or moving traffic can cause the bridge to sway and move in ways that would make its users feel unsafe. Most suspension bridges are designed to be far stiffer than needed to avoid this, as the public perception of what is safe is often very different from what is actually structurally sound (a good example of this being the Millenium Bridge in London when it was first opened). Having said that, it is important to recognise the potential issues caused by a flexible bridge, and it is important to ensure that enough stiffness is built into a bridge to prevent it from collapsing due to it oscillating at its natural frequency, as occurred on the Tacoma Narrows Bridge in 1940. In the case of the VerrazanoNarrows Bridge, the truss separating the decks and the horizontal bracing is sufficient to keep its natural frequency high enough to prevent these kinds of oscillation from occurring. that covers the whole of the other four boroughs. If this link is made, it is very likely that the cheapest and therefore most viable option will be to connect these along the Verrazano-Narrows Bridge, as has already been done with the Manhattan Bridge and Williamsburg Bridge. There is also currently a lot of discussion about the possibility of adding a cycle path onto the bridge, running along the gap between the two main cables and their suspender cables. 9 Conclusion The Verrazano-Narrows Bridge was, and still is a magnificent feat of engineering. It was not only the longest suspension bridge in the world when it was constructed, but is still the longest one in the USA today. Whilst it is neither the most refined nor elegant of suspension bridges to have been built, it is definitely one of the most prominent and impressive due to its size and position. The fact that it is still standing nearly 50 years after its construction with very little modification is a credit to the people that designed and built it. 10 References 7.2 Repainting Because of its size and position, the bridge has to be scraped of rust and dirt and repainted every ten years, a process which usually takes five years to complete [3]. Various different sources quote this as costing different amounts of money, but they all range around the $50 million mark, which is the equivalent of about $10 for every square foot of bridge. During repainting, only small parts of the bridge are closed at once. As the bridge has 12 lanes in total, this means that the repainting works cause very little disturbance to the traffic flow. 7.3 Access Access is provided to the inside of the anchorages so that the condition of the strands that make up the main cables can be checked on a regular basis. These anchorages underwent a $31M rehabilitation in 2002 along with the bridge approaches. As part of this rehabilitation, the anchorages were sealed to protect the concrete from deteriorating, and complex dehumidifying systems were installed to prolong the life of the cables. It can be assumed that access to the towers is also available, as it is important to check the condition of the steel in the towers regularly. 8 The Future of the Bridge As Staten Island is currently the only borough in New York not to be linked to the New York Subway, it is quite likely that at some point in the future, the Staten Island Railway will be linked to the existing subway [1] ANDERSON, S. Verrazano Narrows Bridge Historic Overview [online]. Eastern Roads. Available from: http://tinyurl.com/dgfqah [Accessed 30th March 2009]. [2] THE NEW YORK HERALD TRIBUNE. 1959. Restraint in Design, the New York Herald Tribune, 28 June. [3] BS 5400-2:2006. Steel, concrete and composite bridges – Part 2: Specification for loads. BSI. [4] TALESE, G. 1964. The Bridge. New York: Walker Publishing Company, Inc. [5] FAUST, S.F. 1976. A Bicycle / Pedestrian Path for the Verrazano-Narrows Bridge: A Demand and Feasibility Study [online] New York: Unknown publisher. Available from http://tinyurl.com/ccmwtm [Accessed 18th March 2009]. [6] SCOTT, R. 2001. In the Wake of Tacoma (Illustrated Ed.). Reston: ASCE Publications. [7] JANBERG, N. 2009. Structurae: Verrazano Narrows Bridge [online]. Ratingen: Nicholas Janberg ICS. Available from http://tinyurl.com/crblpy [Accessed 2nd April 2009]. [8] O’DONNEL, P.S. 1994. Bridgemeister [online]. Unknown publisher. Available from http://tinyurl.com/dmkrwf [Accessed 31st March 2009]. [9] BS 8110-1:1997. Structural use of concrete – Part 1: Code of practice for design and construction. BSI.
© Copyright 2026 Paperzz