ODOT DESIGN BUILD SCOPE OF SERVICES PID

ODOT
DESIGN BUILD
SCOPE OF SERVICES
PID: _94460_____ State Project Number: _467278________
County:_FRA____ Route:___70____ Section:_Hilliard-Rome Interchange__
Table of Contents:
Section
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
April 2013
Page
Project Identification
Pre-bid Meeting
Addenda Process
Pre-qualification
Design Consultant
Scope of Work
Field Office
General Provisions for The Work
Hazardous Materials
Environmental
Right of Way (ROW)
Utilities
Design and Construction Requirements: Maintenance Of Traffic (MOT)
Design and Construction Requirements: Location & Design
Design and Construction Requirements: Traffic Control
Design and Construction Requirements: Project Bill of Materials
Project Schedule Requirements
Plan Submittals and Review Requirements
Buildable Units
Index of Attachments
Page 1 of 32
2
2
2
2
3
4
5
5
11
12
15
15
16
20
23
27
28
28
30
32
1.
PROJECT IDENTIFICATION
PID: _94460_____ State Project Number: _467278___
County: _FRA_______ Route: ___70______ Section: _Hilliard-Rome Interchange__
Local Route Name: _Hilliard-Rome Road_________________________________
Highway Functional Classification & Federal Aid System: _Urban Principal Arterial___
Structure Identification: Bridge Number: ___N/A______ Over: ___________
Structure File Number: __N/A_______
1.1
Design Designation: See Attachment C-1 for traffic information
Location: Hilliard-Rome Road Interchange
Hilliard Rome Road
Design Speed: 45 mph
Legal Speed: 45 mph
Design Functional Classification: Urban
Principal Arterial
NHS
1.2
I-70
70 mph
65 mph
Design Functional Classification: Urban
Interstate
NHS
Existing plans: Existing plans are available for review at the following ftp site:
ftp://ftp.dot.state.oh.us/pub/Districts/D06/download/FRA94460/
Please contact
Dirk Gross (614.752.5576); [email protected]
These are NOT as-built plans. The Design-Build Team (DBT) is advised to verify the
preceding referenced plans to determine if they accurately depict existing field
conditions.
2
PRE-BID MEETING
This meeting is to discuss and clarify all issues that the project may have.
Location: ODOT District 6 Office, Columbus Pike Conference Room, 400 E. William
Street, Delaware, Ohio 43015
Date:
__TBD_________________________________
Time:
__TBD ________________________________
3
ADDENDA PROCESS
All questions prior to the letting date shall be directed to: Web submittal form:
http://www.dot.state.oh.us/Divisions/ContractAdmin/Contracts/Pages/PBQs.aspx
4
PRE-QUALIFICATION
It is required that the bidder be an ODOT pre-qualified Contractor who has engaged the
services of an ODOT pre-qualified Consultant to perform all the design and construction
work required in these Conceptual Documents. If the Consultant and/or the Sub-
April 2013
Page 2 of 32
Consultant(s) submitted do not meet all the required qualifications, the Office of
Contracts may reject the bid.
5
CONTRACTOR’S CONSULTANT
The Contractor must name the Consultant and all Sub-Consultant(s) in the space(s)
provided below. If the Contractor is going to submit an electronic bid, then the
Consultant and all Sub-Consultant(s) must be listed on the following web-page:
http://www.dot.state.oh.us/DIVISIONS/PRODMGT/CONSULTANT/Pages/default.aspx .
The Contractor must list relevant prequalification categories for prime and subconsultants to show that the prequalification requirements listed below are satisfied. All
Consultant names and addresses must be the same as that on file with the Department.
The following work types must be performed by members of the Consultant Team
(combination of Consultant and Sub-Consultant(s)):
Roadway Design - Complex
Traffic Signal Design – Basic
Highway Lighting Design - Limited
Consultant
Firm Name: _________________________________________________
Address:
_________________________________________________
List work types the Consultant will perform:
_______________________________________________________________________
_______________________________________________________________________
_______________________________________________________________________
Sub-Consultant
Firm Name:
_________________________________________________
Address:
_________________________________________________
List work types the Sub-Consultant will perform:
_______________________________________________________________________
_______________________________________________________________________
Sub-Consultant
Firm Name:
_________________________________________________
Address:
_________________________________________________
List work types the Sub-Consultant will perform:
_______________________________________________________________________
_______________________________________________________________________
April 2013
Page 3 of 32
Restrictions on Participation in Design-Build Contracts:
Any Consultant who provided services to the Department that have been directly utilized
in this design-build proposal or Scope of Services document will NOT be eligible to
participate in this design-build contract for this project, either as a prime consultant or as
a sub-consultant. This includes following firms: Mead & Hunt, Inc., TranSystems
Corporation of Ohio, and Lawhon & Associates.
6
SCOPE OF WORK
Project Limits: From
Project Length:
I-70
2800’
To Westchester Woods Blvd.
.
.
Work Length shall be determined by the DBT.
The Consultant shall provide for the engineering services, design, and preparation of
detail construction plans for the construction of the proposed project.
The Contractor shall provide for the furnishing of materials, construction and completion
in every detail of all the work described in the Conceptual Documents in order to fulfill
the intent of the contract.
Project Description: This project is part of ODOT’s ramp clear initiative, which has
been created to eliminate mainline queuing at ramp diverge locations. The primary
purpose of this project is to provide capacity improvements to address queuing on the
WB exit ramps from I-70 to Hilliard-Rome Road, which backs up traffic onto mainline I70. As described in Attachment C-2, this project involves the following key elements:
· Realignment of the WB exit ramp to NB Hilliard-Rome Road
· Widening the WB exit ramp to NB Hilliard-Rome Road from 1 to 3 lanes
· Realignment of the WB exit ramp to SB Hilliard-Rome Road
· Widening the WB exit ramp to SB Hilliard-Rome Road from 1 to 2 lanes
· Installation of new traffic signal @ the WB ramps intersection
· Modified signal @ Renner Road intersection
· Modified signal @ Meijer/Walmart drive
· The alignment of Hilliard-Rome Road must be designed in such a way to avoid
right-of-way impacts and provide the number of lanes as shown in
Attachment R-1.
· Widening Hilliard-Rome Road with full depth asphalt, including shoulders
· Resurfacing Hilliard-Rome Road - The remainder of the existing lanes shall be
resurfaced in accordance with Section 14.3. The limits of the resurfacing work
shall be from the north approach slab of the I-70 bridge (STA 102+50 from FRA70-5.25 plans) to the south edge of Westchester Woods Blvd (STA 145+50 from
FRA-CR3-14.06 plans).
Completion date:
Warranties:
April 2013
October 15, 2014
None
Page 4 of 32
7
FIELD OFFICE
Field office Type C , as required by Construction and Material Specification Item
619, shall be available and completely functional no later than 1 week prior to the start of
construction work.
8
GENERAL PROVISIONS FOR THE WORK
8.1
Governing Regulations: All services, including but not limited to survey, design and
construction work, performed by the DBT and all subcontractors (including subconsultants), shall be in compliance with all applicable ODOT Manuals and Guidelines.
The fact that the bid items for this Design-Build project are general rather than specific
shall not relieve the DBT of the requirement that all work performed and all materials
furnished shall be in reasonable conformity with the specifications. The Contractor’s
Consultant shall reference in the plans the appropriate Construction and Material
Specifications Item Number for all work to be performed and all materials to be
furnished.
The attention of the Bidder is directed to the provisions of section 100 of the
Construction and Material Specifications as modified in the design-build proposal.
It will be the responsibility of the DBT to acquire and utilize the necessary ODOT
manuals that apply to the design and construction work required to complete this project.
The current edition, including updates released on or before the prebid meeting date, of
the following ODOT Manuals and Guidelines shall be met or exceeded in the
performance of the design and construction work required to complete this project:
Bridge Design Manual
Location and Design Manuals
Volume One - Roadway Design
Volume Two - Drainage Design
Volume Three - Plan Preparation
Pavement Design & Rehabilitation Manual
Specifications for Geotechnical Explorations
Survey Manual
Construction and Material Specifications
Proposal Notes for Construction and Material Specifications
Supplemental Specifications for Construction and Material Specifications
Item Master
Manual for Abandoned Underground Mines - Inventory and Risk Assessment
Pavement Design and Rehabilitation Manual
State Highway Access Management Manual
Standard Construction Drawings
April 2013
Page 5 of 32
Plan Insert Sheets
Traffic Engineering Manual
Ohio Manual of Uniform Traffic Control Devices
Real Estate Administration Policies and Procedures Manual:
Appraisal
Acquisition Property Management
Relocation
ROW Plans
Utilities
Wireless Communication Tower Manual
Environmental Services Handbooks and Guidelines
Waterway Permit Manual
Design Mapping Specifications
CADD Engineering Standards Manual
Geotechnical Bulletins
Project Development Process Manual (Appendix B)
8.2
Basis of Payment: All Items covered by Construction and Material Specifications,
Supplemental Specifications, Proposal and Special Provision notes with unit price as a
basis of payment will be paid for under the appropriate Lump Sum bid item, unless a unit
line price item has been established in the Scope Of Services.
The DBT shall be required to furnish the Department with a complete breakdown of the
lump sum bid items. The breakdown shall include materials to be used in the work, and
shall be in sufficient detail to provide ODOT with a means to check partial payment
requests. The DBT shall provide subsummaries and a general summary with the final
construction plans. The units of work used to perform the cost breakdown shall be
correlated to the CPM schedule. Evidence of “Front-Cost Loading” will be grounds for
rejection of a submittal.
The following is the list of bid items and what is to be included in each. Please note this
is not all inclusive and additional pay items may be included as required. Work not
specifically itemized in the bid documents will be included in Item 690E20240 SpecialRoadway.
203E99000 SPECIAL-EARTHWORK
1
LS
This item includes the embankment, excavation, subgrade stabilization and subgrade
preparation.
690E20240 SPECIAL-MISC: ROADWAY
1
LS
This item includes the guardrail, permanent erosion control (including final top soil), curb
ramps, and other items associated with the construction.
832E15000 STORM WATER POLLUTION PREVENTION PLAN
April 2013
Page 6 of 32
1
LS
This item includes all work associated with development, design, NPDES required
inspection, modification, revision, updates, amendments and reporting related to the
SWPPP.
832E99100 SPECIAL- CONSTRUCTION EROSION CONTROL 300,000 EACH
Provide temporary sediment and erosion controls as per Supplemental Specification 832.
611E97800 SPECIAL- DRAINAGE
1
LS
This item includes underdrains, manholes, inlets, all drainage pipes and associated items.
442E99000 SPECIAL- FLEXIBLE PAVEMENT
1
LS
This item includes all subbase, base and pavement and any associated items used in the
construction of the flexible pavement.
452E99000 SPECIAL-NON-REINFORCED CONCRETE PAVEMENT 1
LS
This item includes all subbase, base and pavement and any associated items used in the
construction of the concrete pavement.
630E99000 SPECIAL-SIGNS AND SUPPORTS
1
This item includes all work described in Attachment C-4, Conceptual Signing Plan.
LS
632E99000
SPECIAL-TRAFFIC SIGNALS
1
LS
This item includes installation of the new signal at the westbound I-70 ramp intersection,
and modification of other signals. Also includes establishing signal coordination between
the new and existing signals.
625E99000 SPECIAL-LIGHTING
1
LS
This item includes all work associated with modifications to existing roadway lighting.
641E99000 SPECIAL-PAVEMENT MARKING
1
This item includes all work associated with striping the new lane configuration.
LS
614E99000 SPECIAL-MAINTAINING TRAFFIC
1
LS
This item includes all work associated with the maintenance of traffic on the ramps,
primary and secondary roads including temporary pavement, barrier and temporary
signing, striping and signals, maintenance of existing pavement within the work limits
(including areas within traffic shifted areas), and any other items needed to properly
maintain traffic within the work zone. The DBT shall take over maintenance
responsibility of existing/proposed pavement within the entire work limits (to include
shifts, tapers, etc. outside the project limits) at the point in time when they do any work
impacting traffic. Once the DBT takes over the maintenance responsibility of pavement
as described above they will retain maintenance responsibility of pavement for the
remaining life of the contract.
8.3
Final Payment: The DBT shall prepare and submit the following prior to the request for
final payment:
April 2013
Page 7 of 32
1.
2.
8.4
All original project files and notes utilized in the preparation of the survey, design
and construction of the project
Record-Drawings Plans as required in section 8.4 below.
Record-Drawing Plans:
A. General: At the completion of the work, prior to final acceptance of the construction,
the Consultant shall furnish the Department Record-Drawing construction plans. When
the Record-Drawing plans are completed the Consultant shall professionally endorse
(sign and seal) the title sheet.
Record-Drawing plans shall be submitted using the following method:
- Tiff Images created according to the documentation on the Office of Contracts website
(http://www.dot.state.oh.us/DIVISIONS/CONTRACTADMIN/CONTRACTS/Pages/TIF
F.aspx)
In addition to the information shown on the construction plans, the Record-Drawing
plans shall show the following:
1.
2.
3.
4.
All deviations from the original approved construction plans which result in a
change of location, material, type or size of work.
Any utilities, pipes, wellheads, abandoned pavements, foundations or other major
obstructions discovered and remaining in place which are not shown, or do not
conform to locations or depths shown in the plans. Underground features shall be
shown and labeled on the Record-Drawing plan in terms of station, offset and
elevation.
The final option and specification number selected for those items which allow
several material options under the specification (e.g., conduit).
Additional plan sheets may be needed if necessary to show work not included in
the construction plans.
Notation shall also be made of locations and the extent of use of materials, other than
soil, for embankment construction (rock, broken concrete without reinforcing steel, etc.).
The Plan index shall show the plan sheets which have changes appearing on them.
Two copies of the Record-Drawing plans shall be delivered to the Project Engineer for
approval upon completion of the physical work but prior to the request for final payment.
After the Department has approved the Record-Drawing plans, the original tracings and
the associated electronic files shall be delivered to the District Production Administrator.
Acceptance of these plans and delivery of the original tracings and the associated
electronic files is required prior to the work being accepted and the final estimate
approved.
April 2013
Page 8 of 32
The delivered original tracings shall be prepared in conformance with the Location and
Design Manual, Volume 3, Section 1200 - Plan Preparation.
B. CADD files supplied by Consultant:
X Yes
No
If marked yes, the Consultant shall comply with ODOT’s CADD Standards, and supply
files in accordance with the CADD Engineering Standards Manual. All data shall be
provided to the Department according to the provisions as detailed under the appropriate
CADD links accessed from the Department’s Office of Production’s web site. This
includes, but is not limited to, the level assignments, symbols, lines and line styles that
are to be used, line weights, cells, placement of text and file naming conventions. The
web site can be accessed at the following URL address:
http://www.dot.state.oh.us/Divisions/ProdMgt/Production/CADD/Pages/default.aspx
http://www.dot.state.oh.us/Divisions/ProdMgt/Production/Pages/default.aspx
The following can be accessed from the above URL addresses:
1.
2.
3.
ODOT CADD Standard files by selecting the “Microstation Downloads” link
ODOT’s Location and Design, Volume 3 by selecting the “L&D Manual Vol. 3"
link
ODOT’s GEOPAK Standards by selecting the “GEOPAK Downloads” link
The Department will accept CADD files on CD ROM or DVD electronic media.
1.
The Consultant shall submit all CADD information produced in the process of
plan development. All CADD information shall be submitted in the current
version of MicroStation (*.dgn) format as indicated in the CADD Engineering
Standards Manual. This requirement ensures that ODOT receives an end product
that is directly usable on ODOT’s CADD systems without additional work. The
responsibility to provide the Department with correct and complete CADD data
rests with the consultant.
2.
The Consultant shall submit all GEOPAK information produced in the process of
plan development according to L&D Volume 3, Section 1500. The submission
shall include all files generated by GEOPAK as the result of the plan processing
and these files shall include but are not limited to the following:
a.
Coordinate databases (*.gpk)
b.
Digital terrain models (*.tin)
c.
Original cross section (XS) cell design files
d.
Edited observation files (*.obs)
e.
ASCII text files containing all raw point data (PT #, X, Y, Z, Linking
Code/Mapping Code)
f.
ASCII text files containing all adjusted point data (PT #, X, Y, Z, Linking
Code/Mapping Code, Attribute data if any)
April 2013
Page 9 of 32
g.
h.
i.
ASCII text file(s) listing chain data for all existing and proposed
horizontal alignments; including the centerline of construction, the
centerline of right of way and ramp baselines.
ASCII text file(s) listing vertical alignment data for all existing and
proposed profiles.
ASCII text files listing the Northing, easting, station, offset and elevation
for all existing and proposed monuments.
A separate file name should be used for each horizontal or vertical alignment. The
CADD Engineering Standards Manual provides specific requirements for the
content of the required ASCII reports and provides directions on how to create
these reports using GEOPAK software.
These requirements and procedures may be updated from time to time with notification in
the Design Reference Resource Center (DRRC) website which is located at the following
URL, http://www.dot.state.oh.us/drrc/. Organizations exchanging ODOT CADD data are
responsible for ensuring they are using the current version of these requirements, CADD
reference manuals, ODOT cell files and ODOT seed files.
8.5
Post-Letting Conference: Within 7 days after bid opening, the apparent low bidder DBT
shall contact the Office of Estimating of the Division of Construction Management to
discuss the Lump Sum estimate with the Department.
8.6
Partnering Agreement: The Contractor is invited to enter into an informal cooperative
partnership agreement with the Department on this project. The objective of this
agreement is the timely completion of the work and a quality product that will be a source
of pride to both the Department and the Contractor. This Partnering Agreement will not
affect the terms and conditions of the contract. It is a document which is solely intended
to establish an environment of cooperation between the parties.
8.7
Communication: All communication during design and construction shall be with the
District Project Manager and the District Project Engineer.
District’s Project Manager’s Name: Dirk Gross
Phone number: 614-752-5576
E-mail: [email protected]
Fax: 740-833-8100
.
The District Project Engineer shall be named at the pre-design meeting.
At the pre-design meeting, the Contractor shall name a Project Manager who will act as a
liaison between the DBT and the Department.
8.8
Permits: Contractor will be required to obtain a permit from the State or local
government having jurisdiction, to perform any non-construction work within the
existing Right of Way and/or limited access.
April 2013
Page 10 of 32
8.9
Entry On Private Property: The DBT, acting as The Department’s agent, may enter
upon any lands within the State for the purpose of inspecting, surveying, leveling,
digging, drilling, or doing any work deemed necessary in the execution of any survey
authorized by the Director of Transportation in accordance with Section 5517.01 of the
Ohio Revised Code and Section 102.6 (inclusive of Sections 102.61 through 102.66) of
ODOT’s Survey Manual. Prior to performing said survey, the DBT will send notification
letters indicating the date and duration of entry to the affected property owners no less
than forty-eight hours nor more than 30 days prior to the date of entry for said survey in
accordance with 102.6 of ODOT’s Survey Manual. The DBT shall forward copies of all
notification letters distributed to ODOT’s Project Manager. Any subsequent claims for
compensation due to damages incurred while said survey was being performed will be
negotiated between the DBT and the affected property owners with final approval from
ODOT’s Project Manager. Crop and property damage minimization and reimbursement
information, together with the crop damage reimbursement formula and Special Waiver
of Damage form, will be provided to the DBT by ODOT’s Project Manager. Any
subsequent entries onto private property for the purpose of obtaining additional survey or
soil information prior to the submission of the bid will be made in accordance with the
procedures outlined in this section.
9
HAZARDOUS MATERIALS
An ESA Screening, in accordance with the ODOT Environmental Site Assessment
Guidelines (ODOT, 2009), was completed to determine the likelihood of hazardous
substances within the project area. The ESA Screening report is provided to the DBT as
Attachment R-2.
Environmental studies have shown petroleum contaminated soil (PCS) are present on the
following properties:
· 5660 Trabue Road,
· 1520 HilliardǦRome Road, and
· 1499Ǧ1515 HilliardǦRome Road
The Contractor is required to manage PCS in accordance with the following:
·
·
·
April 2013
All excavations within the aforementioned limits shall be paid for under the
original plan bid items.
The Contractor shall provide the Engineer with ten (10) days’ notice prior to any
excavations within the aforementioned limits to permit arranging for the
necessary testing services.
All excavated materials generated from the properties listed above require
characterization by the Engineer. The Engineer will characterize the excavated
material and determine how the PCS will be handled, managed and disposed of.
The Engineer will provide the Contractor with the characterization laboratory test
results.
Page 11 of 32
All material excavated form the properties listed above may be stored in any of the
following ways provided the contractor develops and implements an acceptable
containment and storage plan to the engineer for approval:
o Temporary storage of the excavated material in a lined and covered roll-off box.
o On an impermeable membrane. The membrane shall be surrounded by bales of
straw to prevent the stockpiled materials from coming in contact with surrounding
soils. Place an impermeable membrane over the stockpile to prevent contact with
precipitation and/or surface run-off.
o Direct load the excavated contaminated material into trucks for disposal at an
appropriate facility.
The contractor is required to legally dispose of all regulated waste generated as a result of
the work. Disposal includes any required permits, approvals, or fees related to the
materials handled on the properties listed above. Any additional testing or
characterization required by the disposal facility is included in the items of work
occurring on the properties listed above.
Regulated materials will be paid at the LS Bid Item:
203E99100 Special Earthwork – Misc:PCS disposal
10
ENVIRONMENTAL
The Department has obtained Environmental Clearance for this project. The complete
Categorical Exclusion is provided as Attachment R-3.
10.1
Waterway Permits:
The 404/401waterway permits for this project have yet to be authorized by the US Army
Corps of Engineers and/or the Ohio Environmental Protection Agency. The DBT shall
not perform any work in and/or place any fill in streams or wetlands until permits are
authorized by the US Army Corps of Engineers and the Ohio Environmental Protection
Agency. The permits will be provided to the DBT by ODOT as soon as they become
available. The DBT shall perform the work per the 404/401 permits including all special
conditions of the permits. Any work outside the limits covered under 404/401 permit
obtained by ODOT shall require additional permitting. Any additional permitting will be
the responsibility of the DBT to obtain.
As indicated in the Ecological Survey Report (Attachment R-4), there are two
jurisdictional ditches within the project area. These are indicated as Ditch 1 and Ditch 2.
It has been determined that the project should meet the requirements of the US Army
Corps of Engineers (USACE) Nationwide Permit Program due to the minor impacts to
Jurisdictional Ditch 1 at the southeast corner of Hilliard-Rome and Renner roads, as well
as Jurisdictional Ditch 2 at the northwest quadrant of the WB entrance ramp to I-70.
The environmental coordination and permitting for the project assumes that impacts to
Ditch 1 and Ditch 2 are limited to the amount of disturbance and fill necessary to replace
and/or extend the existing culverts to accommodate widened pavement. The remainder of
April 2013
Page 12 of 32
these ditches is assumed to remain in their current location and elevation. Therefore,
these ditches may not be relocated, filled, or excavated. Any work adjacent to the ditch
must not extend below the Ordinary High Water Mark (OHWM) of the ditch channel.
The OHWM can be calculated using the 2 year depth of flow in the stream as required by
Section 1105.6.13 of the L&D Manual.
It is required that the bidder be aware of Section 404/401 Permits/Certifications for all
projects impacting "waters of the US". The level of permit, that is Nationwide versus
Individual 404 and 401, is determined by the exact amount of impact to "waters of the
US", (i.e., acreage of fill activities in a stream or wetland or linear feet of work in a
stream) and in some cases the waters impacted. All individual 404 Permits require 401
Water Quality Certification. Nationwide Permits are activity specific permits used to
authorize projects with minor impacts. Projects with more than minor impacts require
individual review by the U.S. Army Corps of Engineers and the Ohio Environmental
Protection Agency.
The DBT should be aware of the Nationwide Permits and conditions as issued for the
State of Ohio and should design projects to meet the requirements of these permits to
avoid the requirements for Individual 404/401 Permits if possible. The Nationwide
Permits for the State of Ohio can be found at the various Corps of Engineers' web sites.
The Huntington District's web site can be found at: http://www.lrh.usace.army.mil/.
Coordination of the waterway permits can take up to nine (9) months for Individual
404/401 permits. Therefore it is imperative that the DBT submit plans (i.e., plan &
profile, cross-section and detail sheets for any bridges, culverts, or fill areas in waters) to
the District, for permit determination, as soon as possible. The review of plans, any
required coordination or the processing of permit applications must be accomplished by
the Office of Environmental Services prior to the commencement of construction
activities. The DBT shall be responsible for completing applications for 404 Permits and
401 Water Quality Certification, if they are required. At no time will the DBT coordinate
waterway permit issues directly with the permitting agencies unless directed to do so by
the Office of Environmental Services.
All Waterway Permit requirements are found in the Waterway Permits Manual.
10.2
National Pollutant Discharge Elimination System (NPDES) permit:
The DBT shall submit to the ODOT Project Manager the total number of acres of earth
disturbance activities for both off project and on project work in a timely manner. This
information will be used to develop the NOI if required. The NOI will be submitted to
the OEPA within 10 days after this information is received from the DBT. Approval from
the OEPA takes 21 days and the ODOT Project Manager has 10 days to file the NOI so
these 31 days will be counted for in the project.
All temporary erosion control is the responsibility of the Contractor even if a SWPPP is
not required. Earth disturbing activity is not permitted prior to the OEPA permit
April 2013
Page 13 of 32
approval. For projects that require an NOI, the SWPPP must be in place prior to the
initiation of any earth disturbing activity. All temporary erosion control work and the
SWPPP if required will be per SS832. For information about OEPA's NPDES permit
requirements see http://www.epa.state.oh.us/dsw/storm/index.html. Items used to
implement the DBT's Erosion Control requirements are paid from an encumbered amount
included in the proposal as a non-bid reference number. The proposal specifies the unit
prices for the erosion control items. Payments for erosion control items that exceed the
encumbered amount will be made by an Extra Work Change Order using the specified
unit prices. The specified unit prices are fixed for the contract and may not be negotiated
or adjusted for inflation or claimed changed condition.
10.3
Removal of Temporary Erosion Control Items
All temporary erosion control items shall be removed before the project is accepted.
Removed materials shall become the property of the Contractor and shall be disposed of
in accordance with the appropriate C&MS specifications.
10.4
ESA
The project is being implemented via design/build contracting method. The design/build
scope will include a plan note referring to the potential for encountering Petroleum
Contaminated Soil (PCS) during soil excavation in the vicinity of the Shell Gas Station
and car wash located at 1500 Hilliard Rome Road.
10.5
Other Resources, Drinking Water
The following plan note will be made to further protect drinking water wells:
This project is located near the Shell Gasoline Station at 1500 Hilliard Rome Road, the
St. James Lutheran Church at 5660 Trabue Road and the Perkins Restaurant at 1451
Hilliard Rome Road. In order to minimize the potential to contamination of these
drinking water resources project related refueling and maintenance activities shall not be
performed within the vicinity of these locations. The Contractor shall immediately take
steps to mitigate any event, such as a spill of fuels, oils, or chemicals, that could threaten
to contaminate the drinking water supply. If the spill is a reportable amount, the
Contractor should contact the Emergency Management Coordinator at the Franklin
County Emergency Management Agency at 614-794-0213 for cleanup of the spill.
10.6
Public Involvement
ODOT will issue a press release describing the initial phase (ramps) of the project.
ODOT will address all comments received with furtherance of project design and
development. Following the initial press release, ODOT will send an informational
mailing to the adjacent property owners or hold a Public Meeting to discuss the other
proposed improvements. ODOT and local officials will continue updating the public
throughout project duration.
April 2013
Page 14 of 32
11
RIGHT OF WAY (ROW)
All necessary construction work for the project will be performed within the existing
right of way.
Existing right of way lines will be located by the DBT based on requirements specified in
Chapter 4733-37 of the Ohio Revised Administrative Code (Board Rules) governed by
regulations outlined in Chapter 4733, Ohio Revised Code (Regulation Laws). It is the
responsibility of the DBT to research existing right of way information from all available
sources including but not limited to ODOT records, County road records,
Commissioners’ Journals and records of other County offices to the extent necessary to
provide an accurate basis for the establishment of the existing right of way.
The DBT will stake and flag the existing right of way in the field prior to the start of
construction and will maintain said stakes and flags throughout the duration of the
project.
The Consultant will identify and show all right of way encroachments on the construction
plans at the Conceptual Review Submission. ODOT’s Project Manager will be
responsible for clearing all encroachments on Federal-aid projects in accordance with
standard encroachment removal
12
UTILITIES
Utilities Special Provisions in addition to the Governing Regulations listed in section 8.1
of this document and section 153.64 of the Ohio Revised Code.
12.1
Existing Utilities: The District Utility Coordinator, in concurrence with the registered
Underground Utility Protection Services- Ohio Underground Protection Service (OUPS)
and Oil and Gas Producers Underground Protection Service (OGPUPS) and other utility
owners that are non-members of any utility protection services, has determined that
utilities are located in the area of the project: See Attachment R-5.
12.2
Utility Coordination Responsibilities: As soon as it is feasible after the final plan is
approved by the Department, the DBT shall stake the existing ROW (and new ROW if
additional is acquired) in the field and shall perform clearing and grubbing within that
ROW as required by the specifications and the proposal documents, in order to allow
utility relocation and reduce potential delays. ROW stakes shall be maintained and
updated as needed throughout the project length.
The DBT shall be cognizant of the project's impact on utility facilities. In the event
utility rearrangements are required, the project shall not be designed to preclude legal
occupancy of the highway ROW by the rearranged utility facilities.
The DBT shall coordinate all existing utilities with construction activities on this project.
The DBT shall insure that potential delays in coordination and relocation of the affected
utilities are minimized. The DBT shall copy the ODOT Project Manager and the District
April 2013
Page 15 of 32
Utility Coordinator on all correspondence or phone calls between the DBT and each
utility. This shall include the submittal of plans to each utility.
A meeting at or near the preliminary review shall be held between the DBT, the District
Utility Coordinator and the utility owners to determine if any significant utility
relocations can be eliminated or mitigated.
Any betterment to the utility's facility and ineligible, or unnecessary, work shall not be a
part of the project's expense but the utility company’s fiscal requirement. Determination
of eligibility can be coordinated through the District Utility Coordinator. Payment for
betterments or ineligible costs shall be made by the appropriated utility through ODOT to
the Contractor.
The cost of all utility coordination shall be bid as a Lump Sum Item.
12.3
Subsurface Utilities Engineering (SUE):
Yes
X
No
If marked yes, the DBT shall use a state approved subsurface utilities engineering
location service to field verify all underground utilities prior to beginning of any design
work and shall incorporate the results in the design.
DBT shall have the SUE perform the following Quality Levels: __________________
Note: ODOT has provided SUE Quality Level B plans (see Attachment R-5).
13
DESIGN AND CONSTRUCTION REQUIREMENTS : MAINTENANCE OF
TRAFFIC (MOT)
Maintenance of Traffic (MOT) Special Provisions: All MOT components proposed by
the DBT shall comply with the applicable Governing Requirements documents contained
in Section 8.1. Any and all costs associated with components that do not comply shall be
borne by the DBT.
13.1
General: Maintenance of Traffic (MOT) for this project shall be implemented in a
manner that minimizes both construction duration and impact to the traveling public.
Section 13 defines specific requirements and restrictions for both travel lanes and ramps.
All temporary MOT devices shall comply with the National Cooperative Highway
Research Program (NCHRP) 350 Hardware report.
13.2
MOT Restrictions/Design Criteria:
A.
Except as described in Note C below, the minimum number of lanes in each
direction to remain open during construction is as follows:
1.
A minimum of two (2) lanes in each direction on Hilliard-Rome Road
shall be maintained at all times except:
·
During off Peak periods (9:00AM - 3:00PM; 7:00PM – 5:00 AM),
when Hilliard-Rome Road may be reduced to one lane in each
direction.
2.
Lane reductions on Hilliard-Rome Road from 2 to 1 are not allowed
5:00AM – 9:00AM and 3:00PM – 7:00PM.
April 2013
Page 16 of 32
B.
C.
D.
E.
F.
G.
H.
I.
J.
13.3
3.
All turn lanes
Access to all driveways must be maintained at all times.
No lane closures shall be permitted on mainline I-70.
All ramps at I-70 and Hilliard Rome Road shall remain open to traffic for the
duration of the project.
Minimum lane width: 11 ft.
Maximum duration of detour:
No detour required
.
Design Speed for tapers and reverse curves: Existing posted speed limit
Uncurbed Edge of Pavements:
Any existing, temporary, or proposed edges of pavement shall be a minimum of
1.5 feet away from the edge of a travel lane and shall not exceed allowable dropoff conditions set forth in Standard Construction Drawing MT-101.90.
Portable Barriers:
Minimum 1.5 foot clearance between barrier and edge of travel lane.
Crash Compliance:
All work zone traffic control devices shall be compliant with either NCHRP 350
or MASH-08 requirements.
Additional Description of Required Work and special provisions:
The DBT shall prepare and submit, for each buildable unit, a Maintenance of Traffic plan
(MOTP) to the Department for approval at least 7 calendar days prior to beginning
construction on the buildable unit #1, 14 calendar days prior to beginning construction of
subsequent buildable units. The MOTP shall address all aspects of MOT and it shall
contain specific MOT phasing plans and it shall comply with the requirements listed
below.
The MOT requirements, listed below, shall be incorporated into the MOTP.
A. Cover page/title sheet sealed by an Ohio registered professional engineer
B. A schedule showing MOT phases and durations. All long-term (as defined in TEM
606-3) lane closures and lane restrictions shall be included and identified. All
complete directional roadway closures shall also be identified.
C. Discussion of sequence of operations and MOT procedures
D. Plans at 40-scale showing:
a. The work area
b. Begin/end tapers
c. Work in vicinity of entrance ramps, as per TEM 607-13 and TEM 607-15
d. Temporary pavements and/or structures
e. Location of signs (existing, proposed, covered, and modified)
f. Locations of typical sections
g. References to applicable Standard Construction Drawings (SCD), Plan Insert
Sheets (PIS), and Plan Notes
E. Plans at an appropriate scale showing:
a. Detailed detour plans, incorporating detour routes provided in the Appendix
b. PCMS locations
F. Typical sections showing lane widths, pavements markings, drums, portable barrier
(PB), limiting stations, work area, drop-offs, etc.
April 2013
Page 17 of 32
G. Sign details for proposed signs and overlays/modifications of existing signs
H. Haul routes
Any changes to or modifications of the MOTP shall be submitted to the Department for
approval a minimum of 14 calendar days prior to desired implementation of the proposed
change(s). The Department may approve or reject the modifications or request additional
information.
13.4
Traffic Engineering Manual (TEM) Notes shall apply:
642-3 Maintaining Traffic At All Times
642-12 Maintain Traffic
642-14 Trench for Widening
642-15 Overnight Trench Closing (no more than 1.5 inches)
642-19 Dust Control
642-28 Earthwork for Maintaining Traffic
642-29 Floodlighting
642-30 Work Zone Impact Attenuator for 24" wide hazards
642-31 Work Zone Impact Attenuator for hazards over 24" wide but less than 36" wide
642-48 Work Zone Raised Pavement Marker
642-49 Work Zone Raised Pavement Markers on Concrete Surfaces
642-51 Concrete Barrier Delineation
642-52 Guardrail Delineation
642-55 Law Enforcement Officer (with Patrol Car) for assistance during construction
operations
13.5
Other General Maintenance of Traffic Requirements
13.5.1 Traffic Control Devices Quality
The DBT shall provide, erect, and maintain drums, signs, barriers, and other
traffic control devices used for maintenance of traffic in acceptable condition, in
accordance with ODOT‟s Quality Guidelines for Temporary Traffic Control
Devices.
13.5.2 Construction Equipment & Materials
Construction vehicles used by the DBT and truck traffic required by the DBT
shall comply with any and all load restrictions and vehicle delineation
requirements. As per CMS 614.03, contractor equipment and materials shall
always be stored in locations that do not pose a safety risk to the traveling public.
13.5.3 Pavement Markings and Delineation
Existing pavement markings in conflict with the implementation of the MOTP
shall be removed in accordance with CMS 614.11G. Temporary work zone
striping shall be Class I paint except on new permanent surfaces. Removable tape
shall be used on new permanent surfaces.
In addition to meeting the CMS 614 specifications for work zone pavement
markings, work zone pavement markings shall be reapplied at least once per year
April 2013
Page 18 of 32
or as directed by the Engineer. Reapplication of pavement markings shall be
performed prior to each over-winter condition. For the purpose of this project,
“Moving Operation” shall be limited to pavement marking striping.
13.6 Law Enforcement Officers (LEOs)
LEO’s without patrol cars shall be required for the following situations:
·
·
13.7
LEOs shall be provided at a traffic signal when impacting the normal function of the
signal or the flow of traffic, or when traffic needs to be directed through an energized
traffic signal contrary to the signal display (e.g. directing motorists through a red
light). LEOs shall not be used where the OMUTCD intends that flaggers be used.
LEOs shall be used during construction operations at and within 150 feet of signalized
intersections.
Notification and Coordination
13.7.1 MOT Phase Changes: Notification & Coordination Requirements
At least fourteen (14) days prior to any construction activities, lane closures, or road
closures, the contractor shall advise the District Office of Communications via email at
[email protected] and the District Work Zone Traffic Manager via email at
[email protected] of the anticipated start date of any construction activities,
including but not limited to the placing of work zone signs. The notification shall also
include the project number, PID, name and phone number of the contractor, a point of
contact and the anticipated impact on traffic. The contractor shall immediately inform the
District Office of Communications and the District Work Zone Traffic Manager of any
and all delays and/or changes regarding the construction initiation date.
Throughout the duration of the project, the contractor shall notify the project engineer and
the others listed in this section in writing of all traffic restrictions and upcoming
maintenance of traffic changes. The contractor shall ensure the written notification is
submitted in a timely manner to allow the project engineer to meet the required time
frames set forth in the table below. This notification shall be received by the project
engineer prior to the physical setup of any applicable signs or message boards.
Information shall include but is not limited to all construction activities that impact or
interfere with traffic and shall list the specific location, type of work, road status, date and
time of restriction, duration of restriction, number of lanes maintained, detour routes if
applicable, and any other information requested by the project engineer and the District 6
Communications Office.
Any unforeseen conditions not specified in the plans requiring traffic restrictions shall
also be reported to the project engineer, the District 6 Communications Office, and the
District Work Zone Traffic Manager using the Notification Time Frame Table.
13.7.2 Public Outreach and Notification:
April 2013
Page 19 of 32
The District 6 Communications Office will notify the public, the local emergency
services, affected schools and businesses, and any other impacted local public agency of
any of the above mentioned items, via media sources.
13.7.3 Points of Contact
ODOT District 6 Communications Office
Nancy Burton
(740) 833-8063
[email protected]
ODOT District 6, District 6 Work Zone Traffic Manager
Duane Soisson
(740) 833-8162
[email protected]
ODOT District 6, Franklin County Manager
Mitch Blackford
(614) 387-2291
[email protected]
14
DESIGN AND CONSTRUCTION REQUIREMENTS : LOCATION & DESIGN
Location & Design Special Provisions in addition to the Governing Regulations listed
in section 8.1 of this document:
14.1
Survey
A. ODOT Survey Responsibilities: The Department survey crews have provided the
following survey information, listed below:
1.
2.
3.
4.
Centerline control and bench marks
Beginning and ending centerline points for the project
At least two bench marks for the project (the datum used was that which the
project was originally laid out by)
Lidar Generated Aerial Planimetric Drawings, Orthophotos and TIN Files
B. Survey Responsibilities: All survey data shall be submitted using ODOT’s standard
field codes and GEOPAK’s standard mapping codes. Reduced point data, in comma
delimited ASCII text format, will be provided for all surveyed points. This data will
include: point number, x coordinate, y coordinate, elevation and point ID. Customized
GEOPAK information is available on the ODOT CADD web site.
Monumentation shall not be disturbed. If the Contractor does disturb the monumentation,
then it shall be replaced, in-kind, by a Registered Surveyor, with a current registration,
recognized by the Ohio State Board of Registration for Professional Engineers and
April 2013
Page 20 of 32
Surveyors. Costs associated for this item shall be borne by the Contractor. Copies of all
monumentation changes shall be forwarded to the District Real Estate Administrator.
All control points, provided by ODOT, shall be included in the ASCII file supplied by the
DBT to ODOT. They should retain the original point numbers and coordinate values as
assigned by ODOT.
The DBT shall provide the following items prior to final acceptance of the RecordDrawing plans:
1.
Copies of all field notes (written or electronic) which shall include the following
information:
a.
DateG
b.
Crew membersG
c.
Weather conditions, including temperature, barometric pressure, etc.G
d.
Instrument(s) used (Serial Number)G
e.
Raw observation field dataG
f.
Other notes as needed
2.
Copies of all Deeds, Plats, Maps and other written evidence used to establish
points related to the project including summaries of all parole evidence acquired
as a part of the survey operation.
3.
Listing of all found monumentation (Horizontal and Vertical).
4.
Listing of all monumentation set as part of the project (Horizontal and Vertical)
including reference ties for recovery.
5.
All monumentation shall be located utilizing NAD 83 (Horizontal Data), NAVD
88 (Vertical Data).
6.
Short report indicating adjustment factors and methods, signed and certified by a
Registered Surveyor (State of Ohio). The Registered Surveyor (State of Ohio)
shall include in the report the datum used and all associated adjustments used.
14.2
Vertical and Horizontal Alignment:
A.
It is the intent of this project to maintain the existing horizontal and vertical
alignment to the greatest extent possible. All vertical and horizontal alignment
shall follow the ODOT Location and Design Manual. The DBT shall refer to the
Preliminary Design Concept.
B.
Cross sections are required at 50’ intervals.
14.3
Pavement:
Initial soil boring logs and subgrade analysis has been provided by the Department and is
included as Attachment R-6:
April 2013
Page 21 of 32
Ramps
10”
Item 452
Non-Reinforced Concrete Pavement
6”
Item 304
Aggregate Base
Note: Shoulders shall be full-depth pavement buildup. Concrete ramp pavement for
Ramp C (westbound I-70 to northbound Hilliard Rome Road) shall continue to where the
theoretical extended edge of paved right shoulder for Hilliard Rome Road meets the edge
of the Ramp C left shoulder, the transition joint then crossing perpendicular to the ramp
lanes to the right shoulder.
Hilliard-Rome widening
1 ½”
Item 442 – Asphalt Concrete Surface Course, 12.5 mm, Type A (446), As Per
Plan.
Add Plan Note: Item 442 asphalt mix shall require a PG76-22M binder.
Item 407 - Tack Coat for Intermediate Course
1 ¾”
Item 442 - Asphalt Concrete Intermediate Course, 19mm (446)
10
Item 301 – Asphalt Concrete Base, PG64-22
6”
Item 304 - Aggregate Base
Note: Shoulders shall be full-depth pavement buildup.
Hilliard-Rome Road
Sawcut at the existing edge line, remove existing shoulder and provide full depth
widening. The remainder of the existing lanes shall be resurfaced by planing off 1.5” of
existing asphalt pavement and placing 1.5” Item 442- Asphalt Concrete Surface Course.
Apply intermediate tack coat. The limits of the resurfacing work shall be from the north
approach slab of the I-70 bridge (STA 102+50 from FRA-70-5.25 plans) to the south
edge of Westchester Woods Blvd (STA 145+50 from FRA-CR3-14.06 plans).
14.4
Roadway: Roadway design will follow the ODOT Location and Design Manual.
The Design Vehicle for the I-70 ramps, Hilliard Rome Road, and Renner Road shall be a
WB-62 Interstate Semi-Trailer. The Design Vehicle for the Meijer Drive, Westpointe
Plaza Drive, and commercial driveways shall be a SU-30 Single Unit Truck. Radius
returns for commercial driveways shall be no less than existing.
SUBGRADE COMPACTION, STABILIZATION, AND PROOF ROLLING
The DBT shall prepare suitable subgrade conforming to C&MS 204. Stable subgrade is
defined as subgrade where proof rolling results in permanent rutting of 1/2 inch or less
and elastic (rebound) movement of 1/2 inch or less. For areas where the proposed
subgrade is at the same elevation as the existing subgrade or is below the existing
subgrade, the DBT shall use the guidelines in ODOT Geotechnical Bulletin 1, Plan
Subgrades, Section H, to identify any unsuitable existing subgrade soil and rock. For
April 2013
Page 22 of 32
areas where the proposed subgrade shall be constructed using embankment materials, the
restrictions listed in C&MS 203.03 on embankment materials shall apply.
The DBT shall determine the method, location and dimensions (including depth) of
subgrade stabilization as necessary to furnish suitable subgrade. The DBT shall utilize
one of the accepted stabilization methods listed in GB-1 when performing subgrade
stabilization. The Department will not require global subgrade stabilization of the entire
project. Where subgrade stabilization is required, stabilize to 18 inches beyond the edge
of the surface of the paved shoulders.
There are no unit price items for subgrade stabilization, excavation and replacement of
subgrade, proof rolling or any other subgrade related work. Therefore all subgrade work
will be paid for under the appropriate ITEM SPECIAL-MISC: ROADWAY.
14.5
Drainage: Yes X ; No
.
All associated materials and work are to be included. The DBT is also to provide the
Notice of Intent (NOI) and Best Management Practices (BMPs) as per current ODOT and
City of Columbus standards.
Existing drainage patterns shall be maintained. This included open ditch drainage along
the ramps and Hilliard-Rome Road between I-70 and Renner Road.
All existing catch basins, inlets and manholes within the work limits shall be
raised/adjusted to accommodate resurfacing.
Any existing drainage conduits that are not in conflict with new construction may be
reused.
14.6
Design Exceptions: Yes
; No X .
14.7
Interchange Modification/Justifications Studies: The Department has completed an
IMS for this project. Please see Attachment R-7a and R-7b.
15
DESIGN AND CONSTRUCTION REQUIREMENTS : TRAFFIC CONTROL
15.1
Pavement Markings and Delineators Special Provisions in addition to the Governing
Regulations listed in section 8.1 of this document:
A. Pavement Marking Requirements and Locations:
Pavement markings shall conform to Section 640 of the CMS and shall be placed in
accordance with current design standards. Pavement markings on Hilliard Rome Road
shall instead use City of Columbus standard widths – 5” for lane and edge lines, 10” for
channelizing line and 20” for stop bars and transverse lines.
Item 646 Epoxy Pavement Marking shall be used for the concrete surfaces. Item 644
Thermoplastic Pavement Marking shall be used on all asphalt surfaces.
April 2013
Page 23 of 32
B. Raised Pavement Markers Requirements and Locations:
All Raised Pavement Markers shall conform to Item 621 and shall be placed in
accordance with current design standards and Standard Construction Drawings.
15.2
Signing Special Provisions in addition to the Governing Regulations listed in section 8.1
of this document:
A.
Flat Sheet Signs: Yes
1.
Remove and reuse or remove and replace all existing flat sheet signs with new
signs within the project limits as indicated on Attachment C-4 Conceptual Signing
Plan. Attachment R-8 Existing Signing and Lighting Inventory has been provided
for reference. Size the signs in accordance with the OMUTCD to match the
proposed lane use configuration.
Removed flat sheet signs shall become the property of the Contractor.
2.
B. Extrusheet Signs: Yes X
X ; No
; No
.
.
1.
Remove and reuse or remove and replace all existing extrusheet sheet signs with
new signs within the project limits as indicated on Attachment C-4 Conceptual
Signing Plan. Attachment R-8 Existing Signing and Lighting Inventory has been
provided for reference. Size the signs in accordance with the OMUTCD.
2.
Tourist-Oriented Directional Signs (TODS) and logo signs are installed and
maintained by Ohio Logos, Inc., under contract with and in locations approved by
ODOT. Under the terms of the contract, Ohio Logos can be required to
temporarily remove or relocate the signs during construction. They can also be
required to permanently remove or relocate the signs. Contact Ohio Logos at 1800-860-5646 to coordinate removals or relocations of TODS and logo signs.
3.
Removed extrusheet signs shall become the property of the Contractor.
C. Ground Mounted Post Supports: Yes X
; No
.
1.
Replace all existing ground mounted post supports with new supports within the
project limits as indicated on Attachment C-4 Conceptual Signing Plan.
Attachment R-8 Existing Signing and Lighting Inventory has been provided for
reference. New sign installations shall be on new supports. No reuse of existing
ground mounted supports shall be allowed. Post supports shall comply with City
of Columbus specifications (see attachment C-5).
2.
Removed ground mounted supports shall become the property of the Contractor.
D. Ground Mounted Beam Supports: Yes X ; No
April 2013
Page 24 of 32
.
1.
Replace all existing ground mounted beam supports with new ones, except at the
locations indicated below:
2.
Supports subject to multidirectional impacts at intersections shall use the alternate
connection on sizes larger than S4 x 7.7.
3.
Removed ground mounted beam supports shall become the property of the
Contractor.
E. Overhead Supports: Yes
15.3
X ; No
.
1.
Location of all supports shall be as per the Traffic Engineering Manual
2.
3.
As indicated on Attachment C-4, one overhead support shall be relocated.
At all locations, a minimum vertical clearance of seventeen feet shall be
maintained.
4.
All sign attachment assemblies shall be replaced.
Lighting Special Provisions in addition to the Governing Regulations listed in Section
8.1 of this document: Attachment R-8 Existing Signing and Lighting Inventory has been
provided for reference.
It is anticipated that the following existing lighting will be affected by the construction of
this project and relocated as necessary. This shall be verified for final design by the DBT.
The existing poles may be reused.
· 3 poles
· 1 combination
· Power supply
15.4
Traffic Signals Special Provisions in addition to the Governing Regulations listed in
Section 8.1of this document:
A. Signal Supports: Yes X ; No
1.
2.
4.
5.
April 2013
.
Shall be per City of Columbus specifications (see attachment C-5). No wood
poles, except for use at temporary signal constructed in BU 1.
Shall be span wire. Pole height shall provide required signal head clearance above
the pavement.
Location of the supports shall be as per City of Columbus requirements.
Clearance from overhead electric wires shall be as per utility company
requirements.
Page 25 of 32
B. Vehicle Signal Heads:
1.
2.
3.
4.
5.
6.
7.
8.
9.
Shall be made of Polycarbonate or Aluminum, but must be designed for
Aluminum.
Lenses shall be 12 inch LED.
Shall be completely Yellow except for the inside of visors which shall be black.
Tri-stud wire entrance fitting
Far side mounting of signal heads shall be used as much as practical.
For protected/permissive operation of a 5-section signal head (either left or right
turn), the recommended location of the signal head is over an extension of the
channelizing line, through the intersection, that separates the turn lane and the
through lane.
Shall have backplates with reflective borders.
Shall be tethered on span wires.
Optically Programmed Vehicular Signal Heads shall be used for the westbound to
northbound I-70 ramp approach, and northbound Hilliard Rome Road at the
westbound I-70 ramp intersection.
C. Pull box:
1.
2.
3.
Shall be concrete, CMS 725.08, 18 inch minimum opening size. Pull boxes for
interconnect conduit bank and for entry into controller cabinet shall be 32” and
concrete. Pull boxes at signalized intersections shall be 27” concrete. City of
Columbus specified for all others (see attachment C-5).
Shall not be located in curb ramp areas.
Shall not be located where subject to vehicular traffic.
D. Conduit:
1.
2.
3.
4.
5.
Maximum conduit run length between pull boxes and/or poles is 500 feet.
Conduit under roadway pavement shall be 3 inch diameter minimum.
Conduit must be sized for the number and size of the conductors contained in the
conduit. Cable fill should not exceed 40% of the inside cross sectional area of the
conduit.
Conduit shall be CMS 725.051.
Install concrete encased conduit bank either 4-3” & 1-1.5” or 2-3” & 1-1.5”
through limits of the project (see attachment C-5).
E. Cable and Wire:
1.
2.
3.
April 2013
Unswitched power cable shall not be run inside of conduit, poles or pull boxes
containing other signal cables.
Lighting cables operating at voltages higher than 120 volts shall not be run inside
of conduit, poles or pull boxes with signal cables.
Utility company approval shall be obtained for the attachment of any interconnect
cables to utility poles, and for the location of power sources.
Page 26 of 32
4.
5.
All abandoned cables shall be removed from aerial spans, conduit and pull boxes.
Direct burial cables will be abandoned in place.
Signal messenger wire size shall be 3/8 inch diameter.
F. General:
1.
2.
3.
4.
G.
16
The existing signal controllers are Econolite and operate on a closed loop system.
The system includes the signals from Feder Road to Roberts Road. The EB ramp
and the Feder Road signal are coordinated. The controller shall be provided with
the latest ASC3 software.
All signal installations shall be designed and installed per City of Columbus
specifications.
The new traffic signal @ the WB ramps intersection shall be coordinated with the
adjacent Hilliard-Rome Road traffic signals.
The DBT shall generate signal coordination timing for Renner Road and the
signalized WB I-70 ramp intersection. The plan shall be submitted to ODOT for
review and approval prior to commencing signalized ramp operation.
Signal(s) is part of an Intelligent Transportation System (as defined by the
Traffic Engineering Manual, Part 13): Yes
; No__X__
DESIGN AND CONSTRUCTION REQUIREMENTS: PROJECT BILL OF
MATERIALS
1.
As a component of each progress payment, the DBT shall submit a Project Bill of
Material that shall include, but not limited to, the following data for material
incorporated into the work: Line Item, Primary or Component, Material Code,
Material Name, Material Unit, Placed Item Quantity, Assigned Material Quantity,
Total Quantity, Conversion Factor, Discrepancies Between Placed Quantity and
Assigned Quantity, Basis of Acceptance, and Description of document supplied to
the Department.
2.
Prior to the Department's approval of the progress payment, the DBT shall
remedy all discrepancies between placed material quantity and assigned material
quantity
3.
The project bill of materials is a supplement to the DBT's responsibility for
material certification and substantiation, and does not waive any requirements for
the DBT to comply with the testing material documentation submissions in any
governing regulations, for example and not limited to: TE24, Material Tickets,
QPL, and Certified Test Data.
4.
The DBT shall receive the standard bill of materials from ODOT upon receipt of
the General and Subsummary quantities spreadsheets as a part of the DBT’s
“Approved for Construction” plan set as described in section 18 Plan Submittals
and Review requirement.
April 2013
Page 27 of 32
17
PROJECT SCHEDULE REQUIREMENTS
The current edition of Proposal Note 107, including updates released on or before the
prebid meeting date, shall be met or exceeded.
18
PLAN SUBMITTALS AND REVIEW REQUIREMENTS
18.1
Plan Components: All plans submitted by the DBT shall be in conformance with the
following ODOT manuals:
1.
2.
3.
18.2
Real Estate Policies and Procedures Manual Section 3100.
The DBT shall also identify all topographic features within the existing and
proposed Right-Of-Way limits, including underground utilities.
Bridge Design Manual.
Location and Design Manual, Volume 3:
Quality Control: The DBT will be responsible for the professional quality, technical
accuracy and adherence to the Governing Regulations listed in section 8.1 of this
document, for all plan submittals required under this contract.
The DBT shall immediately notify the Department of any apparent discrepancy between
the various design and construction manuals and the Conceptual Documents.
Unless stated otherwise, review comments do not revise the scope or intent of the project
and do not constitute a request for changes beyond the current contracted Scope of
Services.
In the event the Department determines that any required submission is incomplete,
contains inaccuracies which preclude a meaningful review, or does not adhere to the
Governing Regulations listed in section 8.1 of this document, the Department will advise
the DBT of the shortcomings and direct the DBT to revise and resubmit the plan. No
time extension will be granted as a result of such action. The Department will schedule a
review meeting or issue review comments as appropriate.
In the event the DBT believes that any review comment, or orders issued by the
Department, require a change to the scope of the agreed work, the DBT shall first contact
the Department for clarification and shall, within 10 days of receipt of the comments or
orders, provide written notice to the District Project Manager and Project Engineer
concerning the reasons why the DBT believes the scope has been changed.
18.3
Stage 1 Plan Review Submission: The DBT shall submit the Stage 1 detailed design
plan submissions as per Location & Design Manual, Volume 3 for review by ODOT.
These submission milestones must be shown on the Progress Schedule.
April 2013
Page 28 of 32
Unless indicated below, the Department shall have 21 calendar days from receipt to
review complete submissions. This review time must be shown on the required Progress
Schedule.
Following this review, the DBT shall correct any errors, incorporate modifications,
perform required investigations and make related changes to the plans and supporting
documents prior to submitting the plans for final review.
Plan Review Distribution: The DBT shall supply 4 half size (11" x 17") paper prints to
ODOT District 6 Project Engineer and to the parties indicated below. Each affected
utility company shall also receive one full size (22"x34") plans.
18.4
Major Design Decision: Separate submittals for concurrence with major design
decisions made after the Stage 1 Review are required. Major design decisions involve
significant utility relocation, unforeseen acquisition of ROW, traffic operation or
geometric decisions that involve two or more viable solutions, and any other decision that
impacts the public, operation of the facility or future maintenance.
When the DBT becomes aware of additional decisions during the course of the design,
they must advise the District Project Manager in writing.
18.5
Stage 2 Plan Review Submission: For each Buildable Unit the Consultant shall submit
Stage 2 detailed design plans as per Location & Design Manual, Volume 3 for review by
ODOT. All submissions must be shown on the required Progress Schedule.
The Department shall have 21 calendar days from receipt to review complete
submissions. This review time must be shown on the required Progress Schedule.
Following the review the Department will return to the DBT marked plans noted
‘ACCEPTED’, ‘ACCEPTED AS NOTED’ or ‘NOT ACCEPTED’ as described in
section 105.02 of the Construction and Material Specifications. The DBT shall correct
errors, incorporate changes, perform investigations and make related changes to the plans
and supporting documents prior to submitting construction plans.
Plan Review Distribution: The DBT shall supply 4 half size (11" x 17") paper prints to
ODOT District 6 Project Engineer and to the parties indicated below. Each affected
utility company shall also receive one full size (22"x34") plans.
18.6
Construction Plans: After the review comments for the final plan review submission
have been complied with, and following approval of the design documentation, the DBT
shall prepare plan sets for use during construction. All review comments shall be resolved
in writing by the DBT to the satisfaction of the Department before the DBT submits the
construction plans. Each plan sheet shall have its last revised date noted on the sheet and
clearly marked ‘Approved For Construction’. The ‘Approved For Construction’ plan set
shall be signed, dated and sealed by a Professional Engineer. Physical construction shall
April 2013
Page 29 of 32
not begin until the plans marked ‘Approved For Construction’ are delivered to each party
on the Plan Distribution Table below. No time extensions will be approved by the
District Construction Engineer if the plan distribution is not completed and project delays
occur as a result.
18.7
Plan Distribution Addresses: to be provided at pre-con
19
BUILDABLE UNITS (BU)
Definition: Buildable Units are portions of the projects which can be designed, reviewed
and built with only limited controls and assumptions coming from the design of other
portions of the project. Often a Buildable Unit will be defined by a geographic area
within the plan, but it may also be defined by types of work or construction stages which
may require or permit similar, nearby work to be divided into separate Buildable Units.
All Buildable Units shall summarize the materials required to construct that portion of the
project. The summary shall include the Construction and Material Specifications Item
Number, and a description of the materials to be used.
General: For the Stage 1 and Stage 2 submittals, the DBT may break the project work
into two or more separate BU which can be progressed through design and construction
with minimal or known effect on each other and/or which can be dealt with sequentially
such that sufficient data is available for design and review of each BU. In order that the
design and construction of one BU may proceed without significant approved
information from an associated BU, the DBT may develop and propose assumptions
which will allow for the first BU to proceed through design and/or construction. These
assumptions shall be submitted for review and comment but their accuracy and effort
upon the final design are the sole responsibility of the DBT. Should error in these
assumptions result in additional work, remedial work or other changes to assure an
acceptable design or should they result in the need to remove work and substitute
additional work, the Contractor shall be responsible for all such costs including, removal
of unacceptable materials from the site, modification, additional work, repairs, etc. as
necessary to produce an acceptable result.
If the DBT elects to develop Buildable Units, the DBT shall prepare, for review by the
Department, a table of Buildable Units for the project with each BU described in detail.
If the table is approved, the DBT shall modify the Progress Schedule to show a separate
group of activities for BU and these activities shall encompass all of the design and
construction work in each BU. Work activities shall be further separated in the Progress
Schedule to show a meaningful completion status (i.e. separate activities comprising the
placement of a bridge deck on steel beams shall describe; shoring, form building, steel
placement, placement of conduit & joints, pouring concrete, forming parapets, pouring or
slip forming parapets, provision of membranes, provision of wearing surfaces, curing,
repair, form removal, cleaning, etc.).
The Final Review Submission and construction plans shall specifically be identified by
the Buildable Unit code. If the design of a BU requires input information from an
April 2013
Page 30 of 32
adjacent or related BU, the source for that information in previously approved plans shall
be cited or the DBT shall provide an estimated value of the data. The input data shall
also be carefully identified. In the same way any assumption, calculations or results from
the stage and BU which are used as input to another BU shall be similarly identified, and
where appropriate, compared back to that BU to verify previous assumptions. Should
assumptions not match values calculated later, the DBT shall re-analyze all affected
components and determine appropriate changes. Should those elements have already
been constructed, the DBT shall recommend repairs, adjustments, modifications or
replacement of the existing work as necessary to comply with the Scope of Work. All
costs for re-design, re-submissions, modifications, removals, disposal of materials and
new work needed to remedy the project and bring it to compliance shall be borne by the
Contractor and no time extensions shall be approved for this.
April 2013
Page 31 of 32
20
INDEX OF ATTACHMENTS
All Attachments have been placed on the D6 FTP server at the following location:
ftp://ftp.dot.state.oh.us/pub/Districts/D06/download/FRA94460/
Contractual Documents
Attachment C-1 – Certified Traffic/Design Designation
Attachment C-2 – Lane Lengths and Descriptions
Attachment C-3 – Conceptual Signing Plan
Attachment C-4 – City of Columbus Specifications
Reference Documents
Attachment R-1 – Preliminary Design Concept
Attachment R-2 – ESA Screening
Attachment R-3 – Categorical Exclusion
Attachment R-4 – Ecological Survey Report
Attachment R-5 – Subsurface Utility Engineering (level B) Plans
Attachment R-6 – Geotechnical Investigation
Attachment R-7 – Interchange Modification Study
Attachment R-8 – Existing Signing and Lighting Inventory
Attachment R-9 – Ramp C Concrete to Asphalt Transition Detail
Attachment R-10 – Survey Data
The Attachments are provided for informational purposes to assist the Proposers in
preparing their proposals, but the Attachments do not represent requirements binding on
the Design-Builder with the exception of the Contractual Documents Attachments
(Attachments C-1, C-2, C-3, C-4) which are contractual and must be followed in the
design build process. The Department makes no representation or warranty as to the
accuracy, adequacy, applicability, or completeness of the Reference Documents
Attachments (R-1 through R-10). Except to the extent set forth to the contrary in the
contract, reliance upon the Reference Documents Attachments shall be at the Proposers
risk, and the Department shall have no liability or obligation as a result of the inaccuracy,
inadequacy, inapplicability, or incompleteness of the Reference Documents, regardless of
the contents thereof. The Design-Builder shall be solely responsible for Project design
and construction in accordance with the Contract.
Note: The file size of all attachments exceeds 3.6 Gigabytes. A DVD of all Attachments
can be made available upon request.
April 2013
Page 32 of 32