FY 2016-2025 Statewide Transportation Improvement Program

NewJersey
StatewideTransportation
ImprovementProgram
FiscalYears20162025
ChrisChristie,Governor
KimGuadagno,Lt.Governor
JamieFox,Commissioner
October1,2015
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
TableofContents
INTRODUCTION
SectionI
Introduction
SectionII
FinancialTables
STIPFY20162020
SectionIII
NJDOTProjectDescriptions
SectionIV
NJTRANSITProjectDescriptions
SectionV
MPOLocalProjectDescriptions
SectionVI
DRPAPATCOProjectDescriptions
SectionVII
PANYNJPATHProjectDescriptions
SectionVIII
TransportationAuthoritiesProjectDescriptions
STIPDEVELOPMENT
SectionIX
EarmarkProjectList
SectionX
FY20162017StudyandDevelopmentProgram
SectionXI
FY2015MajorProjectStatus
APPENDIX
SectionXII
Glossary
SECTIONȱIȱ
ȱ
INTRODUCTIONȱ
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
INTRODUCTION
a.
Overview
ThisdocumentistheStatewideTransportationImprovementProgram(STIP)fortheStateofNew
Jerseyforfederalfiscalyears2016(beginningOctober1,2015)through2025(endingSeptember
30,2025).
The STIPserves two purposes.First,itpresentsa comprehensive,onevolume guide to major
transportation improvements planned in the State of New Jersey. Second, it serves as the
referencedocument,requiredunderfederalregulations(23CFR450.216),forusebytheFederal
HighwayAdministration(FHWA)andtheFederalTransitAdministration(FTA)inapproving
theexpenditureoffederalfundsfortransportationprojectsinNewJersey.TheSTIPisavaluable
reference for implementing agencies such as the New Jersey Department of Transportation
(NJDOT)andtheNewJerseyTransitCorporation(NJTRANSIT),andallotherpartiesinterested
intransportationissuesinthestate.
Federallegislation requires thateach state developone multimodal STIP forall areasof their
state.InNewJersey,theSTIPconsistsofalistingofstatewidelineitemsandprograms,aswell
asthreeregionalTransportationImprovementPrograms(TIPs),whichweredevelopedbythree
MetropolitanPlanningOrganizations(MPOs)coveringthestate.ThosethreeTIPscontainlocal
andstatehighwayprojects,statewidelineitemsandprograms,andpublictransitandauthority
sponsoredprojects.
This STIP conforms to, and in many cases exceeds, the specific requirements of the federal
regulations:
1. Itliststhepriorityprojectsprogrammedforthefirstfour(4)yearsoftheplanningperiod.
Italsoincludesaprioritylistofprojectstobefundedoveranadditionalsix(6)years.
2. Itisfiscallyconstrainedfortheentire10years(Adetaileddiscussionoffiscalconstraint
issuesisfoundinsubsection“i”).
3. Itcontainsallregionallysignificantprojects,regardlessoffundingsource.
4. Itcontainsallprojectsprogrammedforfederalfunds.
5. Itcontains,forinformation,statefundedprojects.
6. Itcontainsexpansivedescriptiveinformation.
Finally,theSTIPisa10yearplanthatisfiscallyconstrainedbasedonfederalresourcesremaining
flatfortheNJDOTandNJTRANSIT.StateresourceswereassumedtoremainflatinFYs2016
through2025.StatefundingconsistsoftheTransportationTrustFund(TTF),andPortAuthority
ofNewYorkandNewJersey(PANYNJ)fundingresources.
b.
PerformancebasedPlanningandAssetManagement
InJanuary2008,theNJDOTimplementedanAssetManagementpolicy.Thispolicyistheofficial
institutional approach to managing infrastructure assets, and making capital investment
SectionIPage1
decisionsrelatedtotheseassets.Thisapproachservestosupportandcomplementthe10year
CapitalInvestmentStrategy(CIS),the10yearSTIP,theannualTransportationCapitalProgram,
andthebiennialStudyandDevelopmentProgram.
The NJDOT recognizes that there are everincreasing challenges to funding transportation
improvements. Asset management offers an alternative to focusing solely on problem spots
and/ortheworstconditions.TheNJDOTdefinesassetmanagementas,“thesystematicprocess
ofmaintaining,upgrading,andoperatingphysicalassetscosteffectively”.
Recently,PerformancebasedPlanningandPerformanceManagementaretermsusedinrelation
to the broader use of performance to manage and improve the transportation system. Asset
Management focuses on the subset of Performancebased Planning and Performance
Managementrelatedtophysicalassets.However,theNJDOThasused,andiscontinuingtouse,
a Performancebased Planning approach to make capital investment choices. The NJDOT
continuestoseekout,andutilize,thebestdataandpredictivemodels,tomakethemosteffective,
efficientandinformedinvestmentchoices.
c.
PublicParticipationProcess
New Jersey iscompletely covered by its three MPOs:theDelaware ValleyRegional Planning
Commission(DVRPC);theSouthJerseyTransportationPlanningOrganization(SJTPO);andthe
NorthJerseyTransportationPlanningAuthorityInc.(NJTPA).ThisSTIPincorporatestheirthree
separateTIPswithoutmodification.
Each MPO has a public participation process for their regional transportation plan, TIP and
conformity determination. The state makes copies of the STIP available at each MPO public
meeting,andrepresentativesfromtheNJDOTandNJTRANSITarepresenttoanswerquestions
andconcernsraisedbythepublicabouttheprograms.ThepubliccommentperiodforeachMPO
TIP,andtheSTIP,runsfor30days.
d.
StatewideTransportationPlan
ThefederalstatewideplanningrulerequiresthattheSTIPcontainprojectsconsistentwiththe
statewide Long Range Transportation Plan (LRTP). New Jersey’s LRTP, Transportation Choices
2030,waspreparedandmadeavailabletothepublicinOctober2008,andwassubmittedtothe
FHWA and theFTAin January 2010,followinga periodofpublic review andfor addressing
comments.
TheNJDOTandNJTRANSITcollaboratedtopreparetheLRTP,TransportationChoices2030.The
agencies conducted extensive public outreach and interagency coordination, along with
technical assessments to: examine the state’s transportation system; describe a vision for the
future;identifygoals,objectives,strategiesandactions,and;identifyneedsandresources.The
resultsofthatworkhavebeenpostedonthewww.njchoices.comwebsite,sotheyareaneasily
accessiblesourceofinformationonthedevelopmentoftheLRTP.Thewebsitealsoprovidesan
opportunityforthepublictooffercommentsontheLRTPtotheNJDOTandNJTRANSIT.
SectionIPage2
Transportation Choices 2030 provided thefoundation for developmentof the StatewideCapital
Investment Strategy (SCIS), which shaped the investment priorities for this STIP. The SCIS
functionsasaninstrumentthatlinkstheLRTPtothe10yearcapitalplan(STIP),byconnecting
broadgoalstospecificinvestmentchoices.Withinthecontextofanassetmanagementapproach,
theSCISguidestheselectionofprojectsandprogramstoreducethebacklogofdeficiencies,to
improvetheconditionofthetransportationsystemandtoachievethebestpossibleperformance.
Thus,boththeSCISandtheSTIPserveasmechanismstoachievethevisionoftheLRTPand,
therefore, the projects and programs in the STIP are consistent with the LRTP, Transportation
Choices2030.
e.
ConformityforMPOPlansandPrograms
The MPO Regional Transportation Plans are subjected to conformity analysis in order to
demonstratethateachplanconformstotheStateImplementationPlan(SIP).EachMPOTIPmust
beconsistentwiththeirconformingplan,suchthattheregionalemissionanalysisperformedon
theplanappliestotheirTIP.Thisdeterminationmeansthattheimplementationofprojectsand
programsintheMPOTIPswillhaveapositiveimpact,intheaggregate,onairquality.Sincethe
STIPcontainsthethreeMPOTIPswithoutmodification,theimplementationoftheSTIPconforms
totheregionaltransportationplansandwillalsohaveapositiveimpactonairquality.
f.
CongestionManagementProcess
AllprojectsinthisSTIPthatwillresultinasignificantincreaseincarryingcapacityforsingle
occupantvehiclesaresupportedbyafullyoperationalcongestionmanagementprocess,inplace
ateachMPO.
g.
DevelopmentoftheSTIP
ThisSTIPistheproductofmonthsofstaffwork,anddeliberations,involvingtheNJDOT,NJ
TRANSIT, county and municipal transportation planners and engineers, other transportation
providingagencies,thepublic,andelectedofficialsatthestate,county,andmunicipallevels.The
maindecisionmakingforumsforselectingprojectsforthisprogramwerethestate’sthreeMPOs:
x NJTPA, covering Bergen, Essex, Hudson, Hunterdon, Middlesex, Monmouth, Morris,
Ocean,Passaic,Somerset,Sussex,Union,andWarrencounties;
x DVRPC,coveringBurlington,Camden,Gloucester,andMercercounties;
x SJTPO,coveringAtlantic,CapeMay,Cumberland,andSalemcounties.
TheprocessofbuildingthecurrentSTIPbeganinthefallof2014,withintensivestaffworkbythe
NJDOT,NJTRANSIT,andtheMPOs.
AllprojectsthatwereidentifiedaspotentialcandidatesforinclusionintheregionalTIPsofeach
ofthethreeMPOsweresubjectedtointensivescreeningtoverifyprojectscope,status,schedule,
and cost. The resulting “pool” of projects was analyzed independently by the NJDOT, NJ
TRANSIT,andtheMPOs.Eachprojectwasthenassignedapriorityranking,basedontheextent
towhichitwouldadvanceidentifiedregionalandstatewideobjectives.Suchobjectivesareset
SectionIPage3
forthin;theSTIP,theLRTP(TransportationChoices2030),thethreeMPORegionalTransportation
Plans, the SCIS, air quality objectives, and the broad social and economic goals of the state
DevelopmentandRedevelopmentPlan.TheNJDOTandNJTRANSITdevelopedandcirculated
revenue projections, for planning purposes, to each of the MPOs, based on the best current
assessmentofavailablestate,federal,andotherfunds.TheNJDOT,NJTRANSITandeachofthe
three MPOs enteredintointensive discussions to negotiate alistof deliverable transportation
projects that best fit the composite statewide and regional priorities within a financially
constrainedprogram. These negotiatedproject lists were usedas the basis for publishing the
DraftTransportationCapitalProgramFiscalYear2016bytheNJDOTandNJTRANSITinMarch
2015,andforpreparingTIPsforfurtheranalysisbyeachoftheMPOs.ProjectsintheSTIPand
threeMPO’sTIPsareconsistentwiththethreeMPORegionalTransportationPlans.
h.
STIPModificationsandAmendments
TheSTIPmaybemodifiedoramendedaccordingtotheproceduressetforthintheMemorandum
ofUnderstanding(MOU)forTIP/STIPchangesbetweenthethreeMPOs,NJTRANSIT,andthe
NJDOT. The MOU was fully executed in October 2012. STIP changes, once approved by the
MPOsinconcertwitheitherNJTRANSITortheNJDOT,areforwardedtotheFHWAand/orthe
FTAfortheirapproval,whennecessary.ThemodifiedandamendedSTIPisavailableforviewing
throughtheeSTIPsystem,whichisavailableontheNJDOTwebsite.
i.
FinancialPlan
FederallawandregulationsrequirethattheSTIPbefiscallyconstrainedforthefirstfouryears.
Specifically,“plannedfederalaidexpenditures”cannotexceed“projectedrevenues.”Themajor
sources of funding identified in this document are; the FHWA, the FTA, the TTF and the
PANYNJ.TheNJDOTanditstransportationplanningpartners(NJTRANSIT,NJTPA,DVRPC,
SJTPO, FHWA, and FTA) have developed an estimate of $14,154.2 million in available state,
federal and other revenues to support the state’s transportation budget during the four fiscal
yearsfrom2016through2019.(Forplanningpurposes,staterevenuesareestimatedonthebasis
ofstatefiscalyears,whichbeginonJuly1,andfederalrevenuesareestimatedonthebasisof
federalfiscalyears,whichbeginonOctober1.)
In addition, the NJDOT and NJ TRANSIT have incorporated an additional six (6) years of
constrainedresourcesintothe10yearSTIP.The10yeartotalisestimatedtobe$32,618.3million.
ThisamountconstitutesthefundingexpectedtobeavailabletosupportthewholeFY2016FY
2025STIP.TheserevenueestimatesweredevelopedcooperativelybytheNJDOT,NJTRANSIT,
andNewJersey’sthreeMPOs,infullconsultationwiththeFHWAandtheFTA,atameeting
heldonOctober28,2014.
Tables1through5listtheseamountsbyyearandbyfundingcategory,andcomparesthemto
theactualamountsprogrammedintheTIPsandSTIP.Followingaretherevenueassumptions
usedindevelopingthesetables.
SectionIPage4
1. Dollaramountsshowninfederalfundingcategoriesarebased,exceptasotherwisenoted
below, on the Moving Ahead for Progress in the 21st Century Act (MAP21) federalaid
apportionment tables, or equivalent data, obtained from the FHWA, the FTA, and the
Federal Aviation Administration (FAA), as appropriate. It should be noted that the
apportionment tables are greater than the obligation authority that will ultimately be
provided. Obligation authority applies only to FHWA formula funds, and has been
approximately8to10percentbelowappropriatedlevels.
2. Constructioncostestimatesareescalatedtothemidpointofconstructiontoaddress“year
ofexpendituredollars.”TheNJDOTusesseveralmethodsandtoolstodevelopconstruction
costestimatesincluding;historicalbidbasedestimating,historicalpercentagesestimating,
andtheAmericanAssociationofStateHighwayandTransportationOfficials(AASHTO)
project cost estimation software, to prepare detailed and long range cost estimates. The
AASHTOWareprojectcostestimationsoftwareincludestheabilitytousehistoricalpricing
informationinestimatingnewprojectcosts.Thishistoricalpricingincludesaprogrammed
generaldefaultinflationfactorthatautomaticallycalculatesbasedonpastpricinghistory.
TheNJDOTemploysthisfeaturewherepossible.
3. Funds in the Surface Transportation Program (STP) and Transportation Alternatives
Program(TAP)categoriesarebrokendownintotheallocationsandminimumsrequired
byfederallaw.
4. “High Priority” funds and “demo” funds are shown only as authorized by federal
legislation.TheseCongressionalearmarkprojectsareshownwiththefundtype“DEMO”
intheSTIP.
5. Thestatewillprovide$1.6billioninFY2016andFY2017tosupportthecapitalprogram.
Forprogrammingpurposes,itisassumedthattheNJDOT’sshareofstatefundsis$743.5
millionofTTFand$353millionofPANYNJinFY2016,and$1,017.5millionofTTFinFY
2017.NJTRANSIT’sshareoftheTTFis$503.5millioninFY2016and$582.5millionFY
2017.
6. ThefollowingtransfersareprogrammedbetweentheNJDOTandNJTRANSIT:
a. ForFYs20162019,$50millionofFHWACongestionManagementAirQuality
(CMAQ)funds,$50millionofSTPfunds,and$1millionofTAPfundsaretobe
transferredannuallyforusebyNJTRANSIT;
b. For FYs 20162018, $86 million of FHWA STP suballocated funds are to be
flexedannuallytoNJTRANSITinreturnfor$86millionofTTFfundsforlocal
projectsupportbytheNJDOT;
c. InFY2016,$32.5millionofFHWASTPfundsaretobeflexedtoNJTRANSIT
inreturnfor$32.5millionofTTFfundsforusebytheNJDOT.
7. In FY 2006, the NJDOT used afederalfinancingprogram (Grant Anticipation Revenue
Vehicles, or “GARVEEs”) to finance Route 52, Causeway Replacement Contract A in
OceanCity.ThisprojectwasselectedforGARVEEfundingbecauseof;thepoorcondition
of the four bridges, the delay in construction that would be caused by waiting for
conventionalfinancing,thecostandannoyanceofcontinualemergencyrepairs,andthe
importanceofthecausewayasanemergencyevacuationroute.ThisproposedSTIPfunds
thefinaltwoyearsofbondpaymentsrelatedtothatproject.
SectionIPage5
8. TheRoute278GoethalsbridgereplacementisaPublicPrivatePartnership(P3),awarded
bythePANYNJtotheNYNJLinkPartnership,whichprovidesfora40yeardesignbuild
financemaintaincontracttoreplacethe80plusyearoldbridgewithanewstateoftheart
cablestayedbridge.
BecauseNewJerseyisclassifiedasa“nonattainment”areawithregardtoairquality,certain
projectfundingmustmeetafederalstandardof“availableorcommitted”revenueinFY2016and
FY 2017 to be considered fiscally constrained. Such projects are those which are funded with
federalresources,andallother“projectsofregionalsignificance”regardlessoffundingsource.
Allfederalfundsin FY 2016 andFY 2017 are basedon thecurrentfederalaid apportionment
tables allocations or equivalent data obtained from the FHWA, the FTA and the FAA, as
appropriate, and are therefore considered available. All TTF funding for FY 2016 will be
appropriatedJuly1,2015.Sufficientfundsareavailableorcommittedtocoverfundingofprojects
andprogramsintheFY2016FY2017period.NewJersey’stransportationauthoritiesalsouse
theirownrevenuestofundvariousprojectsclassifiedas“projectsofregionalsignificance.”These
projectsarelistedinSectionVIII.
The stateof New Jersey has made a significantcommitment to publictransportation through
continuedoperatingsupportfromthestate’sgeneralfund.SincetheinceptionofNJTRANSIT,
thestatehascontributednearly$7.3billionofoperatingassistance,over$3.0billioninthelast10
years alone. During the same 10year period, the state also has chosen to supplement that
operatingassistancewithover$1billionoffunding,allocatedtotransportationoperationsfrom
thestate’sgeneralfundcontribution,totheTTF.
Withtwonotableexceptions,federalandstatefundsarenot“allocated”to—thatis,requiredto
bespentwithintheboundariesof—thestate’sthreeMPOs.ThefirstexceptionisforSTPfunds,
someofwhicharerequiredunderaformulainfederalregulationstobeallocatedtoMPOs.These
allocatedfundsareshowninthefollowingtablesas“STPNJTPA,”“STPDVRPC,”“STPSJTPO,”
and “TAP.” The second exception for is Trust Fund stateaid funds, which are allocated on a
countybycountybasisunderastatutoryandregulatoryformula.
TheactualbudgetingoffederalandstatefundsforprojectswithintheMPOareasisaproductof
the development of the three regional TIPs, the STIP, and legislative approval of the annual
transportation capital program. On a statewide basis, the cost of projects programmed for a
particularfiscalyearmustequaltheplannedresourcesforthatyear.Eachprojectmustalsobe
assignedtoafundingcategorythatisappropriatefortheproject,andforwhichadequatefunding
isavailable.Fromyeartoyeartheremaybesignificantvariationsintheamountoffundsactually
programmed within an MPO area, as needs and specific project implementation schedules
dictate.Theseprogrammingdecisionsaremadeonacooperativebasiswiththeparticipationof
the NJDOT, NJ TRANSIT, local government representatives, other agencies (all of whom are
membersoftheMPOs),theStateLegislature,citizens’groups,andthegeneralpublic.
ForthepurposeofdefiningaprojectlineitemestimateintheSTIP,eachitemincludesanestimate
ofindependentcontractorcoststoproducetheproject,anestimateofimplementingagencycosts
SectionIPage6
anticipatedinsupportofthedevelopmentanddeliveryoftheproject,andanypaymentstothird
partiesregardingmattersofrightofwayandutilityrelocations.Theimplementingagencycosts
includeactivitiessuchas;inspection,testing,equipmentandsalarycosts.
The current STIP and Capital Program provides funding for the NJDOT and NJ TRANSIT
employee salaries, leave and fringe benefits, overhead, and other administrative costs which
benefitthedevelopmentanddeliveryoftheirtransportationprograms.Thisfundingisprovided
from bothfederalaid and state TTF sources, and these funds are allocatedfor multiyear and
previouslyauthorizedprojectcosts.Federalaidinsupportofemployeeandadministrativecosts
isprogrammedonanindividualprojectbasis.TTFfundingisprogrammedasasingleitemunder
the heading of “Program Implementation Costs, NJDOT”. For NJ TRANSIT, TTF funding is
allocatedtospecificprograms.
Table6showstheoveralldistributionoffundswithintheSTIP,byMPO.Tables7through10
providedetailedbreakdownsofexpenditures,byfundingcategory,foreachofthethreeMPOs,
andforstatewideprograms.
j.
AdvanceConstructionProjects
AdvanceConstruction(AC)isaproceduretoadvanceafederallyfundedprojectphaseintothe
current fiscal year andimplement thatphase withother thanfederal funds. Theuseof ACis
subjecttotheavailabilityofotherthanfederalfunds(e.g.,statefunds)intheyearinwhichthe
projectistobeimplemented,andtheavailabilityoffederalfundsintheyearinwhichtheAC
projectistobeconvertedtoaregularfederalaidproject.ACprojectsaretobelistedindividually
intheTIPsandSTIPinboththeyearthattheprojectistobeimplementedandtheyearinwhich
theconversionistotakeplace.AppropriatenotificationwillbeprovidedintheTIPsandSTIPso
itisclearlyunderstoodthatthese“otherfunds”areavailableandthatfuturefederalfundsmay
becommittedtotheseACprojects.Fiscalconstraintmustbemaintainedthroughoutthisprocess
forboththeimplementingandconversionyears.TheMPOsandthestateagreethattheinclusion
ofanACprojectintheTIP/STIP,intheyeartheprojectistobeimplemented,signifiesthatthe
projectcanbeconvertedtofederalfundingwhenfederalfundsbecomeavailableandthedecision
ismadetoconvert.
k.
MultiYearFunding
Multiyear funding is an innovative financing technique to program and authorize only that
portionofagivenprojectphasenecessarytosupportreimbursementofplannedcashoutlaysfor
agivenyear.Remainingportionsoftheprojectphaseareprogrammedinsubsequentyears.In
thefirstfiscalyearoffundingforamultiyearfundedphaseofwork,theNJDOTwillonlyseek
federalauthorizationforthatportionofthefederalfundsshowninthatfiscalyearintheSTIP.
Theremainingbalanceoffunds,forthatparticularphaseofwork,willappearintheSTIPinthe
fiscal year that the NJDOT intends to request federal authorization for the remaining funds
needed for continuation/completion of the phase/project. Each multiyear federally funded
projectwillbesubmittedtotheFHWAwiththeconditionthatauthorizationtoproceedisnota
SectionIPage7
commitmentorobligationtoprovidefederalfundsforthatportionoftheundertakingnotfully
fundedherein.Fiscalconstraintwillbemaintainedatalltimesthroughoutthisprocess.
Intheeventthatsufficientfederalfundingisnotavailableinanyfiscalyeartocompleteamulti
yearfundedphaseofwork,theNJDOTwilltakefullresponsibilitytofundthatportionofthe
phaseofwork,inaccordancewithapplicablefederalandNewJerseyStatelaw.Intheeventthat
stateorotherfundingwouldnotbeavailabletocompleteaproject,theprojectmaybeterminated
orplacedonholduntilsuchtimeasfundingismadeavailable.Insuchcases,theNJDOTwould
needtocomplywithapplicablefederalandNewJerseyStatelaw,including,whereapplicable,
providingarevisedairqualityconformitydeterminationtotheFHWA/FTA,andreimbursing
theFHWA/FTAforanyfederalfundsexpendedontheproject.
Table11showscurrent,andfuture,fiscalyearfundingneededtocompletemultiyearfederally
fundedhighwayprojects.Table11containsNJDOTledconstructionprojects,rangingfromjust
over$10milliontoover$200millioninvalue.Thefederalmultiyearconstructionlevelpeaksin
FY2019,withapproximately$310millionofpaymentsdue.Table12showscurrent,andfuture,
fiscalyearfundingneededtocompletemultiyearstatefundedhighwayprojects.Theindividual
projectpagesintheSTIPcontainspecificinformationfortheseprojects,suchas;adetailedproject
description,projectfundingsourceandatotalestimatedprojectcost.Table13showscurrent,and
future,fiscalyearfundingandtheestimatedtotalfundingneededtocompletefederalequipment
leasepaymentsfortransitprojects.
l.
NonFederalMatch–TollCredit
TollCreditswerecreatedintheTransportationEquityActforthe21stCentury(TEA21),andareto
be used ascredits towardthenonfederal matching shareof programs authorized by Title 23
(exceptfortheemergencyreliefprogram)andfortransitprogramsauthorizedbyChapter53of
Title49.
Theamountofcreditearnedisbasedonrevenuesgeneratedbythetollauthority(i.e.,tollreceipts,
concessionsales,rightofwayleasesorinterest),includingborrowedfunds(i.e.,bonds,loans)
supported by this revenue stream, that are used by the toll authority to build, improve or
maintain highways, bridges and/or tunnels that serve interstate commerce. The federal
governmenthasallowedstateandlocalgovernmentstousetollcreditsaspartofthe20%local
matching funds in regard to transit grants. This allowance results from the recognition that
differentmodesoftransportationareinterconnected.Capitalexpenditurestoreducecongestion
inaparticularcorridorbenefitallmodesoftransportationinthatcorridor,betheyautomobiles,
transitbuses,orarailsystem.
NewJerseyestimatesthatitwillbeginfederalFY2016withabalanceof$4,007millioninavailable
tollcredits.BoththeNJDOTandNJTRANSITuseapproximately$275millionintollcreditseach
year,andearn$900millioninadditionaltollcreditsannually.BytheendoffederalFY2019an
estimatedbalanceof$6,507millionintollcreditsisexpectedtobeavailable.
SectionIPage8
TollCreditsAvailabilityforSoftMatch *
($inmillions)
TollCreditStartingBalance
NewTollCreditsEarned
TollCreditsUsedforSoftMatch
TollCreditEndingBalance
FFY
2016
FFY
2017
$4,007
$900
($275)
$4,632
$4,632
$900
($275)
$5,257
FFY
2018
$5,257
$900
($275)
$5,882
FFY
2019
$5,882
$900
($275)
$6,507
*ProjectedamountsfortheNJDOTandNJTRANSIT,assumingfederalapportionmentsremainflatand
requestsfornewtollcreditsremainsteady.
Withtheassumptionthatfederalfundsapportionmentswillcontinuetoremainflatandasteady
orincreasingrequestforadditionalcreditswillcontinue,thereisanexpectationfortheavailable
balanceoftollcreditstoaccrueoverthenext10years.Withnewcreditsoutpacingusage,New
Jerseyexpectstohavesufficienttollcreditstocontinuetoutilizethesoftmatchoffederalfunds
overtheentire10yearplan.
m.
MaintainingtheFederalAidHighwaySystem
TheFHWAandtheFTAexpectstatestoadequatelymaintainfacilitiesonthedesignatedfederal
aid system. In New Jersey, the federalaid system includes transportation facilities under the
jurisdiction of many agencies, including; the NJDOT, NJ TRANSIT, counties, certain
municipalitiesandauthorities.Todate,theFHWA/FTAhasnotspecifiedthelevelsatwhichthe
system(s)need(s)tobemaintained.PriortoMAP21,theFHWAandtheFTAleftthatdecisionto
the state agencies, MPOs, and local decision making processes. MAP21 initiates a process to
defineassetmanagementstandards.
TheNJDOTinspectsallbridgesinNewJerseyover20feetinlengtheverytwoyears.Standards
formeasuringtheconditionofbridgeshavebeenestablishednationally,andtheprogramcarried
outbytheNJDOTprovidesaverygoodassessmentofthehealthofallthestate’sbridgesgreater
thantwentyfeetlong,regardlessofowner.UnderMAP21legislation,itisexpectedthatstates
willbechargedwithmeetingormakingprogresstowardaminimumperformancelevelof90%
sufficiencyforbridgesontheNationalHighwaySystem(NHS).BridgesontheNHSincludenot
onlyNJDOTownedbridges,butalsobridgesownedbycountiesandotherjurisdictions.
Thereare6,657highwaycarryingbridgesover20feetlonginthestate.TheNJDOTandcounty
and municipalgovernmentsown thelargest portionof thispopulation,followed by the New
Jersey Turnpike Authority (NJTA) and NJ TRANSIT. Statewide, there are 577, or 8.7%,
“structurallydeficient”bridges,withtheremaining91.3%ofbridgesclassifiedas“structurally
acceptable”condition.Itisimportanttonotethata“structurallydeficient”bridgedoesnotequate
toanunsafebridge.Ifanybridgeweredeemedunsafe,thestatewouldtakeimmediateactionto
bringthebridgetoasafeconditionorclosethebridgetotraffic.
Annualinvestments,ofapproximately$1billion,overthenexttenyearsareplannedforbridge
rehabilitation and replacement projects. This work includes, but is not limited to; redecking,
SectionIPage9
seismicretrofitting,securitymeasures,cleaningandrepaintingofstructuralsteel,substructure
repairs andotherimprovements.Additionally,preservation and maintenancefunding will be
providedforbridgerepairs.
Performance at this investment level is expected to reduce the growth rate of the structural
deterioration backlog, and maintain the present system condition level. Capital maintenance
investmentsarealsodesignatedtoimprovethestructuralintegrityofstateownedbridgeassets.
The state’s road network consists of approximately 38,566 centerline miles of pavement. The
NJDOT, the NJTA, and the SJTA maintain approximately 2,684 centerline miles, with the
remainingpavementundertheresponsibilityofcounties,municipalitiesandotherjurisdictions.
Pavementsystemassetsareplacedintosubclassesdefinedbytheconditionlevelsof“Good,”
“Fair,”and“Deficient(Poor).”Approximately60%oftheNJDOT’s,theNJTA’sandtheSJTA’s
pavementlanemilesareinanacceptablecondition.
Countyowned roads make up alarge portionof thefederalaid system, however, thereis no
comprehensive data available on the condition of the countyowned network. Each county is
responsibleformanagingitsownnetworkofroads,whichincludefacilitiesbothonandoffthe
federalaidsystem,andeachcountymayhaveitsownwaytomeasureperformance.Asimilar
situationappliestothetollfacilities.
To get an adequate picture of the condition of pavement on the federalaid system, it will be
necessarytoestablishastandardofmeasure(s)thatwouldbeused,acrossalljurisdictions,and
toinitiateanefforttocollectdatausingsuchameasure(s).WhiletheFHWAhasyettoestablish
MAP21performancemeasuresandtargets,theNJDOTanditsregionalplanningpartnersarein
consultationwitheachotherinpreparationforthosemeasuresbeingestablished.
Bridges and pavements make up the largest investments on the federalaid system, but it is
importanttorecognizethatthereareotherassetsthatneedtobemaintained,suchassigning,
lighting, guiderail andother roadway appurtenances. Theseassets are ina verygood stateof
repair,andtheNJDOTdoesnotexpectthemtodegradesignificantlyoverthenext10years.The
NJDOTmakesaconcertedefforttoaddressanyitemsthatareinastateofdisrepairasquicklyas
possible.
n.
MaintainingtheTransitSystem
TheFTAoverseesNJTRANSIT’ssystemwithrespecttostateofgoodrepair.In2009,theFTA
conductedathoroughreviewofNJTRANSIT’sstateofgoodrepaireffortsaspartoftheFTA’s
financialcapacityassessmentoftheagency.Thateffort,forwhichtheFTAengagedconsultant
support, included both a review of NJ TRANSIT’s current infrastructure condition and the
agency’s20yearcapitalprogram.ThereviewconcludedthatNJTRANSIT’sinfrastructureand
rollingstockare,generally,inastateofgoodrepair.
SectionIPage10
o.
Howtousethisdocument
Theindividualdescriptions,foundinSectionsIIIthroughVII,providedetailedinformationfor
eachprojectorprograminthe10yearplan.Thetopportionforeachproject/programliststhe
project/programname(routeandsection)andthelocationoftheproject/program.TheProjectID
reference number is assigned at project inception and remains with that project until its
completion. These are the same reference numbers used by the MPOs in their TIPs. Specific
information contained within the detailed project/program description includes; county,
municipality, MPO jurisdiction, mileposts (for state highway projects), structure number (for
bridge projects), project sponsor, asset management category, air quality code used in the
conformitydeterminationprocess,andfinancialplanrequirement.Anexplanationoftheasset
managementcategoriesandairqualitycodescanbefoundintheGlossary,locatedinSectionXII
ofthisdocument.Theanticipatedfundingscheduleforeachproject/programisdisplayedinthe
columnsatthebottomofeachprojectpage.Thephasesofworkandtypesoffundsarefurther
definedintheGlossary.
SectionIPage11
SECTIONȱIIȱ
ȱ
FINANCIALȱTABLESȱ
Tableȱ1
Expenditures
NJDOTȱ&ȱNJȱTRANSIT
($ȱmillions)
FundingȱCategory
FYȱ2016
FYȱ2017
FYȱ2018
FYȱ2019
FYȱ2020
FYȱ2021
FYȱ2022
FYȱ2023
FYȱ2024
FYȱ2025
Total
NJDOT
Federal
Other
TransportationȱTrustȱFund
SubtotalȱNJDOT
$795.9
$815.2
$814.0
$897.3
$899.0
$897.3
$897.3
$897.3
$897.3
$897.3
$8,708.0
$1,345.1
$235.0
$9.2
$215.0
$150.0
$100.0
$0.0
$0.0
$0.0
$0.0
$2,054.3
$743.5
$1,017.5
$1,018.0
$928.0
$928.0
$928.0
$928.0
$928.0
$928.0
$928.0
$9,275.0
$2,884.5
$2,067.7
$1,841.2
$2,040.3
$1,977.0
$1,925.3
$1,825.3
$1,825.3
$1,825.3
$1,558.3
$1,026.1
$633.5
$543.5
$543.5
$543.5
$543.5
$543.5
$543.4
$543.4
$7,021.9
$1,825.3 $20,037.3
NJȱTransit
Federal
MatchȱFunds
$12.3
$12.3
$12.3
$12.3
$12.3
$12.3
$12.3
$12.3
$12.3
$12.3
$123.2
Other
$25.4
$23.8
$23.8
$23.8
$23.8
$23.8
$23.8
$23.8
$23.8
$23.8
$239.7
$503.5
$582.5
$582.0
$672.0
$672.0
$672.0
$672.0
$672.0
$672.0
$672.0
$6,372.0
SubtotalȱNJȱTransit
$2,099.5
$1,644.7
$1,251.6
$1,251.6
$1,251.6
$1,251.6
$1,251.6
$1,251.6
$1,251.5
$1,251.5 $13,756.8
Total
$4,984.0
$3,712.4
$3,092.7
$3,291.9
$3,228.6
$3,176.9
$3,076.9
$3,076.9
$3,076.9
$3,076.9 $33,794.1
TransportationȱTrustȱFund
Table2
NJDOTResources
($millions)
FundingCategory
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
$51.0
$26.0
$26.0
$26.0
$26.0
$26.0
$26.0
$26.0
$26.0
$26.0
$284.9
$2.0
$2.0
$2.0
$2.0
$2.0
$2.0
$2.0
$2.0
$2.0
$2.0
$20.0
Federal
FHWA:CMAQ
FHWA:Ferry
FHWA:HighPriority
$42.1
$7.4
$6.6
$0.0
$1.6
$0.0
$0.0
$0.0
$0.0
$0.0
$57.7
$524.3
$524.3
$524.3
$524.3
$524.3
$524.3
$524.3
$524.3
$524.3
$524.3
$5,243.4
FHWA:OtherFunds
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$10.4
FHWA:RailHwyCrossing
$4.0
$4.0
$4.0
$4.0
$4.0
$4.0
$4.0
$4.0
$4.0
$4.0
$40.3
FHWA:NHPP
FHWA:Safety
$54.1
$54.1
$54.1
$54.1
$54.1
$54.1
$54.1
$54.1
$54.1
$54.1
$540.7
FHWA:SPR/PL
$30.9
$30.9
$30.9
$30.9
$30.9
$30.9
$30.9
$30.9
$30.9
$30.9
$309.5
FHWA:STPDVRPC
$11.9
$8.4
$7.9
$19.9
$19.9
$19.9
$19.9
$19.9
$19.9
$19.9
$167.0
FHWA:STPNJTPA
$14.4
$14.4
$14.4
$84.9
$84.9
$84.9
$84.9
$84.9
$84.9
$84.9
$637.8
$2.6
$2.6
$2.6
$10.1
$10.1
$10.1
$10.1
$10.1
$10.1
$10.1
$79.0
FHWA:STPStatewide
FHWA:STPSJTPO
$38.1
$120.6
$120.6
$120.6
$120.6
$120.6
$120.6
$120.6
$120.6
$120.6
$1,123.9
FHWA:TAP
$15.5
$15.5
$15.5
$15.5
$15.5
$15.5
$15.5
$15.5
$15.5
$15.5
$154.7
FTA:SPR/PL
$3.9
$3.9
$3.9
$3.9
$3.9
$3.9
$3.9
$3.9
$3.9
$3.9
$38.9
$795.9
$815.2
$814.0
$897.3
$899.0
$897.3
$897.3
$897.3
$897.3
$897.3
$8,708.0
$1,345.1
$235.0
$9.2
$65.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$1,654.3
$1,345.1
$235.0
$9.2
$65.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$1,654.3
$743.5
$1,017.5
$1,018.0
$928.0
$928.0
$928.0
$928.0
$928.0
$928.0
$928.0
$9,275.0
SubtotalTTF
$743.5
$1,017.5
$1,018.0
$928.0
$928.0
$928.0
$928.0
$928.0
$928.0
$928.0
$9,275.0
NJDOTTotal
$2,884.5
$2,067.7
$1,841.2
$1,890.3
$1,827.0
$1,825.3
$1,825.3
$1,825.3
$1,825.3
SubtotalFederal
Other
OtherFunds
SubtotalOther
TTF
State:TTF
$1,825.3 $19,637.3
Table3
NJDOTExpenditures
($millions)
FundingCategory
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
$20.0
$20.3
$29.3
$31.3
$36.3
$34.3
$18.3
$18.3
$18.3
$18.3
$244.9
$2.0
$2.0
$2.0
$2.0
$2.0
$2.0
$2.0
$2.0
$2.0
$2.0
$20.0
Federal
FHWA:CMAQ
FHWA:Ferry
FHWA:HighPriority
FHWA:NHPP
FHWA:OtherFunds
FHWA:RailHwyCrossing
$42.1
$7.4
$6.6
$0.0
$1.6
$0.0
$0.0
$0.0
$0.0
$0.0
$57.7
$478.0
$541.1
$539.4
$544.7
$516.1
$522.3
$564.0
$555.0
$561.5
$552.4
$5,374.6
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$10.4
$11.3
$11.3
$11.3
$11.3
$12.2
$12.7
$13.6
$14.1
$15.0
$15.5
$128.3
FHWA:Safety
$39.6
$37.0
$56.8
$36.2
$43.8
$40.2
$40.2
$40.2
$40.2
$40.2
$414.2
FHWA:SPR/PL
$30.9
$30.9
$30.9
$30.9
$30.9
$30.9
$30.9
$30.9
$30.9
$30.9
$309.2
FHWA:STPDVRPC
$14.6
$11.3
$10.6
$22.8
$22.6
$22.8
$22.6
$22.8
$22.6
$22.8
$195.0
FHWA:STPNJTPA
$21.5
$22.7
$21.5
$93.2
$92.0
$93.2
$92.0
$93.2
$92.0
$93.2
$715.0
FHWA:STPSJTPO
$2.9
$3.0
$2.9
$9.0
$10.4
$10.5
$10.4
$10.5
$10.4
$10.5
$80.7
$108.7
$103.9
$78.3
$91.6
$106.8
$101.9
$76.8
$83.8
$77.9
$85.0
$914.8
FHWA:TAP
$19.3
$19.3
$19.3
$19.3
$19.3
$21.6
$21.6
$21.6
$21.6
$21.6
$204.4
FTA:SPR/PL
$3.9
$3.9
$3.9
$3.9
$3.9
$3.9
$3.9
$3.9
$3.9
$3.9
$38.9
$795.9
$815.2
$814.0
$897.3
$899.0
$897.3
$897.3
$897.3
$897.3
$897.3
$8,708.0
$1,345.1
$235.0
$9.2
$215.0
$150.0
$100.0
$0.0
$0.0
$0.0
$0.0
$2,054.3
$1,345.1
$235.0
$9.2
$215.0
$150.0
$100.0
$0.0
$0.0
$0.0
$0.0
$2,054.3
$743.5
$1,017.5
$1,018.0
$928.0
$928.0
$928.0
$928.0
$928.0
$928.0
$928.0
$9,275.0
SubtotalTTF
$743.5
$1,017.5
$1,018.0
$928.0
$928.0
$928.0
$928.0
$928.0
$928.0
$928.0
$9,275.0
NJDOTTotal
$2,884.5
$2,067.7
$1,841.2
$2,040.3
$1,977.0
$1,925.3
$1,825.3
$1,825.3
$1,825.3
FHWA:STPStatewide
SubtotalFederal
Other
OtherFunds
SubtotalOther
TTF
State:TTF
$1,825.3 $20,037.3
Table4
NJTRANSITResources
($millions)
FundingCategory
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
$50.0
$75.0
$75.0
$75.0
$75.0
$75.0
$75.0
$75.0
$75.0
$75.0
$725.0
FHWA:STPDVRPC
$8.0
$11.5
$12.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$31.5
FHWA:STPNJTPA
$70.5
$70.5
$70.5
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$211.5
FHWA:STPSJTPO
$7.5
$7.5
$7.5
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$22.5
$82.5
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$82.5
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$10.0
Federal
FHWA:CMAQ
FHWA:STPStatewide
FHWA:TAP
FTA:Section5307
$281.3
$281.3
$281.6
$281.6
$281.6
$281.6
$281.6
$281.6
$281.3
$281.3
$2,814.5
FTA:Section5307TE
$2.7
$2.7
$2.7
$2.7
$2.7
$2.7
$2.7
$2.7
$2.7
$2.7
$27.0
FTA:Section5310
$7.2
$7.2
$7.2
$7.2
$7.2
$7.2
$7.2
$7.2
$7.2
$7.2
$72.0
FTA:Section5311
$4.2
$4.2
$4.2
$4.2
$4.2
$4.2
$4.2
$4.2
$4.2
$4.2
$42.0
FTA:Section5324
$871.4
$393.2
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$1,264.6
FTA:Section5337
$157.0
$157.0
$154.5
$154.5
$154.5
$154.5
$154.5
$154.5
$157.0
$157.0
$1,555.0
$15.0
$15.0
$17.3
$17.3
$17.3
$17.3
$17.3
$17.3
$15.0
$15.0
$163.8
$1,558.3
$1,026.1
$633.5
$543.5
$543.5
$543.5
$543.5
$543.5
$543.4
$543.4
$7,021.9
FTA:Section5339/5307
SubtotalFederal
Other
CasinoRevenue
$18.8
$18.8
$18.8
$18.8
$18.8
$18.8
$18.8
$18.8
$18.8
$18.8
$188.2
MatchFunds
$12.3
$12.3
$12.3
$12.3
$12.3
$12.3
$12.3
$12.3
$12.3
$12.3
$123.2
MetroNorth
$0.7
$0.7
$0.7
$0.7
$0.7
$0.7
$0.7
$0.7
$0.7
$0.7
$6.9
Operating
$5.9
$4.3
$4.3
$4.3
$4.3
$4.3
$4.3
$4.3
$4.3
$4.3
$44.6
$37.7
$36.1
$36.1
$36.1
$36.1
$36.1
$36.1
$36.1
$36.1
$36.1
$363.0
$503.5
$582.5
$582.0
$672.0
$672.0
$672.0
$672.0
$672.0
$672.0
$672.0
$6,372.0
$503.5
$582.5
$582.0
$672.0
$672.0
$672.0
$672.0
$672.0
$672.0
$672.0
$6,372.0
$2,099.5
$1,644.7
$1,251.6
$1,251.6
$1,251.6
$1,251.6
$1,251.6
$1,251.6
$1,251.5
SubtotalOther
TTF
TransportationTrustFund
SubtotalTTF
NJTransitTotal
$1,251.5 $13,756.8
Table5
NJTRANSITExpenditures
($millions)
FundingCategory
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
$50.0
$75.0
$75.0
$75.0
$75.0
$75.0
$75.0
$75.0
$75.0
$75.0
$725.0
FHWA:STPDVRPC
$8.0
$11.5
$12.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$31.5
FHWA:STPNJTPA
$70.5
$70.5
$70.5
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$211.5
FHWA:STPSJTPO
$7.5
$7.5
$7.5
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$22.5
$82.5
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$82.5
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$10.0
Federal
FHWA:CMAQ
FHWA:STPStatewide
FHWA:TAP
FTA:Section5307
$281.3
$281.3
$281.6
$281.6
$281.6
$281.6
$281.6
$281.6
$281.3
$281.3
$2,814.5
FTA:Section5307TE
$2.7
$2.7
$2.7
$2.7
$2.7
$2.7
$2.7
$2.7
$2.7
$2.7
$27.0
FTA:Section5310
$7.2
$7.2
$7.2
$7.2
$7.2
$7.2
$7.2
$7.2
$7.2
$7.2
$72.0
FTA:Section5311
$4.2
$4.2
$4.2
$4.2
$4.2
$4.2
$4.2
$4.2
$4.2
$4.2
$42.0
FTA:Section5324
$871.4
$393.2
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$1,264.6
FTA:Section5337
$157.0
$157.0
$154.5
$154.5
$154.5
$154.5
$154.5
$154.5
$157.0
$157.0
$1,555.0
$15.0
$15.0
$17.3
$17.3
$17.3
$17.3
$17.3
$17.3
$15.0
$15.0
$163.8
$1,558.3
$1,026.1
$633.5
$543.5
$543.5
$543.5
$543.5
$543.5
$543.4
$543.4
$7,021.9
FTA:Section5339/5307
SubtotalFederal
Other
CasinoRevenue
$18.8
$18.8
$18.8
$18.8
$18.8
$18.8
$18.8
$18.8
$18.8
$18.8
$188.2
MatchFunds
$12.3
$12.3
$12.3
$12.3
$12.3
$12.3
$12.3
$12.3
$12.3
$12.3
$123.2
MetroNorth
$0.7
$0.7
$0.7
$0.7
$0.7
$0.7
$0.7
$0.7
$0.7
$0.7
$6.9
Operating
$5.9
$4.3
$4.3
$4.3
$4.3
$4.3
$4.3
$4.3
$4.3
$4.3
$44.6
$37.7
$36.1
$36.1
$36.1
$36.1
$36.1
$36.1
$36.1
$36.1
$36.1
$363.0
$503.5
$582.5
$582.0
$672.0
$672.0
$672.0
$672.0
$672.0
$672.0
$672.0
$6,372.0
$503.5
$582.5
$582.0
$672.0
$672.0
$672.0
$672.0
$672.0
$672.0
$672.0
$6,372.0
$2,099.5
$1,644.7
$1,251.6
$1,251.6
$1,251.6
$1,251.6
$1,251.6
$1,251.6
$1,251.5
SubtotalOther
TTF
TransportationTrustFund
SubtotalTTF
NJTransitTotal
$1,251.5 $13,756.8
Table6
DistributionofFundsbyMetropolitanPlanningOrganization(MPO)
NJDOT
($millions)
MPO
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total Total(%) Total*(%)
$195.9
$252.3
$260.9
$343.9
$249.7
$237.4
$89.7
$99.9
$99.9
$100.1
$1,929.8
9.6%
19.5%
NJTPA
$1,921.7
$879.2
$686.3
$802.9
$791.4
$660.8
$465.3
$380.0
$346.3
$348.0
$7,282.0
36.3%
73.6%
SJTPO
$88.0
$95.0
$90.1
$65.5
$64.7
$58.3
$54.9
$53.9
$54.0
$54.1
$678.6
3.4%
6.9%
$2,205.5
$1,226.5
$1,037.3
$1,212.4
$1,105.8
$956.5
$609.9
$533.9
$500.3
$502.3
$9,890.4
49.4%
100.0%
$679.0
$841.2
$803.9
$827.9
$871.2
$968.8
$1,215.5
$1,291.5
$1,325.1
$1,323.1
$10,146.9
50.6%
100.0%
$679.0
$841.2
$803.9
$827.9
$871.2
$968.8
$1,215.5
$1,291.5
$1,325.1
$1,323.1 $10,146.9
50.6%
100.0%
$2,884.5
$2,067.7
$1,841.2
$2,040.3
$1,977.0
$1,925.3
$1,825.3
$1,825.3
$1,825.3
$1,825.3 $20,037.3
100.0%
100.0%
MPODistribution
DVRPC
StatewideDistribution
Statewide
Total
*ExcludingStatewidePrograms
Table7
Page1of2
DelawareValleyRegionalPlanningCommission(DVRPC)
DistributionofFundsNJDOT&NJTRANSIT
(Note:DoesnotincludeexpendituresfromStatewideProgramswithinregion)
($millions)
FundingCategory
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
FHWA:CMAQ
$1.2
$1.2
$1.2
$1.2
$1.2
$1.2
$1.2
$1.2
$1.2
$1.2
$11.7
FHWA:HighPriority
$9.5
$4.5
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$13.9
NJDOT
$108.4
$158.6
$169.5
$228.8
$172.1
$143.4
$24.0
$34.0
$34.0
$34.0
$1,106.8
FHWA:RailHwyCrossing
FHWA:NHPP
$2.8
$2.8
$2.8
$2.8
$3.0
$3.0
$3.2
$3.2
$3.4
$3.4
$30.4
FHWA:Safety
$3.2
$3.0
$5.2
$3.0
$3.0
$4.0
$4.0
$4.0
$4.0
$4.0
$37.4
FHWA:SPR/PL
$2.2
$2.2
$2.2
$2.2
$2.2
$2.2
$2.2
$2.2
$2.2
$2.2
$22.4
$14.6
$11.3
$10.6
$22.8
$22.6
$22.8
$22.6
$22.8
$22.6
$22.8
$195.0
FHWA:STPStatewide
FHWA:STPDVRPC
$0.0
$4.3
$0.0
$7.9
$13.0
$0.0
$0.0
$0.0
$0.0
$0.0
$25.2
FHWA:TAP
$1.5
$1.5
$1.5
$1.5
$1.5
$1.5
$1.5
$1.5
$1.5
$1.5
$15.0
FTA:SPR/PL
$0.8
$0.8
$0.8
$0.8
$0.8
$0.8
$0.8
$0.8
$0.8
$0.8
$7.7
$51.7
$62.2
$67.2
$73.0
$30.3
$58.6
$30.3
$30.3
$30.3
$30.3
$464.2
$195.9
$252.3
$260.9
$343.9
$249.7
$237.4
$89.7
$99.9
$99.9
$100.1
$1,929.8
TransportationTrustFund
TotalNJDOT
Table7
Page2of2
DelawareValleyRegionalPlanningCommission(DVRPC)
DistributionofFundsNJDOT&NJTRANSIT
(Note:DoesnotincludeexpendituresfromStatewideProgramswithinregion)
($millions)
FundingCategory
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
FHWA:CMAQ
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$7.5
$7.5
$15.0
FHWA:STPDVRPC
$8.0
$11.5
$12.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$31.5
NJTransit
$47.3
$47.3
$46.1
$46.4
$46.4
$46.4
$46.4
$46.4
$40.0
$40.0
$452.8
FTA:Section5307TE
FTA:Section5307
$0.2
$0.2
$0.2
$0.2
$0.2
$0.2
$0.2
$0.2
$0.2
$0.2
$1.6
FTA:Section5310
$1.7
$1.7
$1.7
$1.7
$1.7
$1.7
$1.7
$1.7
$1.7
$1.7
$16.6
FTA:Section5311
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$9.7
FTA:Section5337
$9.2
$9.2
$13.6
$13.6
$13.6
$13.6
$13.6
$13.6
$9.2
$9.2
$118.4
FTA:Section5339/5307
$0.7
$0.7
$2.8
$2.8
$2.8
$2.8
$2.8
$2.8
$0.4
$0.4
$18.9
CasinoRevenue
$4.3
$4.3
$4.3
$4.3
$4.3
$4.3
$4.3
$4.3
$4.3
$4.3
$43.3
MatchFunds
$2.8
$2.8
$2.8
$2.8
$2.8
$2.8
$2.8
$2.8
$2.8
$2.8
$28.3
Operating
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$9.9
$103.4
$118.6
$118.5
$124.6
$90.3
$88.9
$92.0
$90.8
$86.9
$86.9
$1,001.0
TotalNJTransit
$179.4
$198.2
$203.9
$198.4
$164.1
$162.7
$165.8
$164.5
$154.9
$154.9
$1,746.9
Total
$375.3
$450.5
$464.9
$542.3
$413.8
$400.1
$255.5
$264.5
$254.9
$255.1
$3,676.8
TransportationTrustFund
Table8
Page1of2
NorthJerseyTransportationPlanningAuthority(NJTPA)
DistributionofFundsNJDOT&NJTRANSIT
(Note:DoesnotincludeexpendituresfromStatewideProgramswithinregion)
($millions)
FundingCategory
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
$5.5
$6.0
$12.2
$5.0
$10.0
$21.0
$5.0
$5.0
$5.0
$5.0
$79.7
$32.6
$2.9
$6.6
$0.0
$1.6
$0.0
$0.0
$0.0
$0.0
$0.0
$43.7
$241.3
$279.3
$253.3
$205.6
$225.5
$251.5
$220.0
$133.0
$100.0
$100.0
$2,009.5
$6.5
$6.5
$6.5
$6.5
$7.0
$7.5
$8.0
$8.5
$9.0
$9.5
$75.5
FHWA:Safety
$18.3
$15.8
$33.4
$15.0
$22.6
$18.0
$18.0
$18.0
$18.0
$18.0
$195.0
FHWA:SPR/PL
$8.8
$8.8
$8.8
$8.8
$8.8
$8.8
$8.8
$8.8
$8.8
$8.8
$87.8
FHWA:STPNJTPA
$21.5
$22.7
$21.5
$93.2
$92.0
$93.2
$92.0
$93.2
$92.0
$93.2
$715.0
FHWA:STPStatewide
$29.8
$12.1
$6.8
$8.2
$22.8
$18.7
$0.0
$0.0
$0.0
$0.0
$98.4
FHWA:TAP
$6.2
$6.2
$6.2
$6.2
$6.2
$6.2
$6.2
$6.2
$6.2
$6.2
$62.2
FTA:SPR/PL
$2.7
$2.7
$2.7
$2.7
$2.7
$2.7
$2.7
$2.7
$2.7
$2.7
$26.9
OtherFunds
$1,345.1
$235.0
$9.2
$215.0
$150.0
$100.0
$0.0
$0.0
$0.0
$0.0
$2,054.3
$203.4
$281.2
$319.1
$236.7
$242.1
$133.1
$104.6
$104.6
$104.6
$104.6
$1,834.0
$1,921.7
$879.2
$686.3
$802.9
$791.4
$660.8
$465.3
$380.0
$346.3
$348.0
$7,282.0
NJDOT
FHWA:CMAQ
FHWA:HighPriority
FHWA:NHPP
FHWA:RailHwyCrossing
TransportationTrustFund
TotalNJDOT
Table8
Page2of2
NorthJerseyTransportationPlanningAuthority(NJTPA)
DistributionofFundsNJDOT&NJTRANSIT
(Note:DoesnotincludeexpendituresfromStatewideProgramswithinregion)
($millions)
FundingCategory
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
FHWA:CMAQ
$50.0
$75.0
$75.0
$75.0
$75.0
$75.0
$75.0
$75.0
$67.5
$67.5
$710.0
FHWA:STPNJTPA
$70.5
$70.5
$70.5
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$211.5
FHWA:STPStatewide
$82.5
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$82.5
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$10.0
$218.0
$218.0
$220.6
$220.3
$220.3
$220.3
$220.3
$220.3
$231.5
$231.5
$2,220.8
$2.5
$2.5
$2.5
$2.5
$2.5
$2.5
$2.5
$2.5
$2.5
$2.5
$24.9
FTA:Section5310
$5.0
$5.0
$5.0
$5.0
$5.0
$5.0
$5.0
$5.0
$5.0
$5.0
$50.4
FTA:Section5311
$2.9
$2.9
$2.9
$2.9
$2.9
$2.9
$2.9
$2.9
$2.9
$2.9
$29.4
FTA:Section5324
$871.4
$393.2
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$1,264.6
FTA:Section5337
$145.9
$145.9
$138.7
$138.7
$138.7
$138.7
$138.7
$138.7
$145.9
$145.9
$1,415.6
FTA:Section5339/5307
$13.2
$13.2
$13.6
$13.6
$13.6
$13.6
$13.6
$13.6
$14.5
$14.5
$136.9
CasinoRevenue
$13.2
$13.2
$13.2
$13.2
$13.2
$13.2
$13.2
$13.2
$13.2
$13.2
$131.8
MatchFunds
$8.6
$8.6
$8.6
$8.6
$8.6
$8.6
$8.6
$8.6
$8.6
$8.6
$86.3
MetroNorth
$0.7
$0.7
$0.7
$0.7
$0.7
$0.7
$0.7
$0.7
$0.7
$0.7
$6.9
NJTransit
FHWA:TAP
FTA:Section5307
FTA:Section5307TE
Operating
$4.6
$3.0
$3.0
$3.0
$3.0
$3.0
$3.0
$3.0
$3.0
$3.0
$31.7
$386.6
$446.5
$444.9
$524.8
$559.2
$560.9
$556.7
$558.2
$565.0
$565.0
$5,167.6
TotalNJTransit
$1,876.5
$1,399.1
$1,000.2
$1,009.3
$1,043.8
$1,045.5
$1,041.2
$1,042.7
$1,061.2
$1,061.2 $11,580.8
Total
$3,798.2
$2,278.3
$1,686.5
$1,812.2
$1,835.1
$1,706.3
$1,506.5
$1,422.7
$1,407.6
$1,409.3 $18,862.8
TransportationTrustFund
Table9
Page1of2
SouthJerseyTransportationPlanningOrganization(SJTPO)
DistributionofFundsNJDOT&NJTRANSIT
(Note:DoesnotincludeexpendituresfromStatewideProgramswithinregion)
($millions)
FundingCategory
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
FHWA:CMAQ
$2.1
$1.9
$5.7
$1.9
$1.9
$1.9
$1.9
$1.9
$1.9
$1.9
$23.0
FHWA:NHPP
$41.9
$21.9
$31.6
$19.5
$26.4
$20.5
$11.0
$16.0
$16.0
$16.0
$220.9
NJDOT
FHWA:RailHwyCrossing
$2.0
$2.0
$2.0
$2.0
$2.2
$2.2
$2.4
$2.4
$2.6
$2.6
$22.4
FHWA:Safety
$2.0
$2.0
$2.0
$2.0
$2.0
$2.0
$2.0
$2.0
$2.0
$2.0
$20.0
FHWA:SPR/PL
$0.9
$0.9
$0.9
$0.9
$0.9
$0.9
$0.9
$0.9
$0.9
$0.9
$9.4
FHWA:STPSJTPO
$2.9
$3.0
$2.9
$9.0
$10.4
$10.5
$10.4
$10.5
$10.4
$10.5
$80.7
FHWA:STPStatewide
$4.0
$12.6
$1.7
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$18.3
FHWA:TAP
$0.5
$0.5
$0.5
$0.5
$0.5
$0.5
$0.5
$0.5
$0.5
$0.5
$5.2
FTA:SPR/PL
$0.4
$0.4
$0.4
$0.4
$0.4
$0.4
$0.4
$0.4
$0.4
$0.4
$4.3
$31.1
$49.7
$42.3
$29.2
$19.9
$19.3
$25.3
$19.2
$19.2
$19.2
$274.4
$88.0
$95.0
$90.1
$65.5
$64.7
$58.3
$54.9
$53.9
$54.0
$54.1
$678.6
TransportationTrustFund
TotalNJDOT
Table9
Page2of2
SouthJerseyTransportationPlanningOrganization(SJTPO)
DistributionofFundsNJDOT&NJTRANSIT
(Note:DoesnotincludeexpendituresfromStatewideProgramswithinregion)
($millions)
FundingCategory
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
$7.5
$7.5
$7.5
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$22.5
$16.1
$16.1
$14.9
$14.9
$14.9
$14.9
$14.9
$14.9
$9.8
$9.8
$141.0
FTA:Section5307TE
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.5
FTA:Section5310
$0.5
$0.5
$0.5
$0.5
$0.5
$0.5
$0.5
$0.5
$0.5
$0.5
$5.0
FTA:Section5311
$0.3
$0.3
$0.3
$0.3
$0.3
$0.3
$0.3
$0.3
$0.3
$0.3
$2.9
FTA:Section5337
$2.0
$2.0
$2.2
$2.2
$2.2
$2.2
$2.2
$2.2
$1.9
$1.9
$21.0
FTA:Section5339/5307
$1.1
$1.1
$0.9
$0.9
$0.9
$0.9
$0.9
$0.9
$0.1
$0.1
$7.9
CasinoRevenue
$1.3
$1.3
$1.3
$1.3
$1.3
$1.3
$1.3
$1.3
$1.3
$1.3
$13.2
MatchFunds
$0.9
$0.9
$0.9
$0.9
$0.9
$0.9
$0.9
$0.9
$0.9
$0.9
$8.6
Operating
$0.3
$0.3
$0.3
$0.3
$0.3
$0.3
$0.3
$0.3
$0.3
$0.3
$3.0
$13.6
$17.4
$18.6
$22.6
$22.4
$22.1
$23.3
$23.1
$20.1
$20.1
$203.4
$43.6
$47.4
$47.4
$43.9
$43.7
$43.4
$44.6
$44.3
$35.4
$35.4
$429.1
$131.5
$142.4
$137.5
$109.4
$108.4
$101.7
$99.5
$98.3
$89.4
$89.5
$1,107.6
NJTransit
FHWA:STPSJTPO
FTA:Section5307
TransportationTrustFund
TotalNJTransit
Total
Table10
StatewidePrograms
DistributionofFundsNJDOT
($millions)
FundingCategory
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
$11.3
$11.3
$10.3
$23.3
$23.3
$10.3
$10.3
$10.3
$10.3
$10.3
$130.5
FHWA:Ferry
$2.0
$2.0
$2.0
$2.0
$2.0
$2.0
$2.0
$2.0
$2.0
$2.0
$20.0
FHWA:NHPP
$86.3
$81.4
$85.1
$90.8
$92.1
$106.8
$309.0
$372.0
$411.5
$402.4
$2,037.5
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$1.0
$10.4
FHWA:Safety
$16.2
$16.2
$16.2
$16.2
$16.2
$16.2
$16.2
$16.2
$16.2
$16.2
$161.8
FHWA:SPR/PL
$19.0
$19.0
$19.0
$19.0
$19.0
$19.0
$19.0
$19.0
$19.0
$19.0
$189.6
NJDOT
FHWA:CMAQ
FHWA:OtherFunds
FHWA:STPStatewide
$74.9
$74.9
$69.9
$75.6
$71.0
$83.2
$76.8
$83.8
$77.9
$85.0
$772.8
FHWA:TAP
$11.1
$11.1
$11.1
$11.1
$11.1
$13.3
$13.3
$13.3
$13.3
$13.3
$122.0
$457.3
$624.4
$589.4
$589.1
$635.7
$717.0
$767.8
$773.9
$773.9
$773.9
$6,702.4
$679.0
$841.2
$803.9
$827.9
$871.2
$968.8
$1,215.5
$1,291.5
$1,325.1
TransportationTrustFund
TotalNJDOT
$1,323.1 $10,146.9
Table11
Page1of4
NJDOTMultiyearFundedFederalProjects
($millions)
ProjectName(ID#) MPO
PriorFYs
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
FederalFunds
AutomaticTrafficManagementSystem(ATMS)(DBNUM:13303;UPC:133030)
Statewide
$1.000
$1.000
$13.000
$13.000
$28.000
PrincetonHightstownRoadImprovements,CR571(DBNUM:D0701;UPC:078036)
DVRPC
$4.500
$5.500
$10.000
RumsonRoadovertheShrewsburyRiver,CR520(DBNUM:NS9706;UPC:950628)
NJTPA
$45.725
$14.275
$60.000
SouthPembertonRoad,CR530,Phase2(DBNUM:D9912A;UPC:123210)
DVRPC
$11.849
$8.716
$6.435
$27.000
TrentonAmtrakBridges(DBNUM:99362;UPC:993620)
DVRPC
$4.000
$4.000
$4.000
$4.000
$4.000
$20.000
Route1,Southbound,NassauParkBoulevardtoQuakerBridgeMallOverpass(DBNUM:01330A;UPC:013301)
DVRPC
$7.000
$7.150
$14.150
Route3&Route495Interchange(DBNUM:12386;UPC:123860)
NJTPA
$18.000
$22.000
$40.000
$7.900
$11.000
$18.900
Route4,GrandAvenueBridge(DBNUM:08410;UPC:084100)
NJTPA
Route4,HackensackRiverBridge(DBNUM:02346;UPC:023460)
NJTPA
$13.500
$13.500
$27.000
Route4,Route20toRoute1&9(DBNUM:12431;UPC:124310)
NJTPA
$10.000
$20.000
$30.000
Route9/35,MainStreetInterchange(DBNUM:079A;UPC:088032)
NJTPA
$10.100
$12.500
$22.600
Route22,BloyStreettoLibertyAvenue(DBNUM:658C;UPC:058004)
NJTPA
$3.200
$5.000
$8.200
Table11
Page2of4
NJDOTMultiyearFundedFederalProjects
($millions)
ProjectName(ID#) MPO
PriorFYs
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
Route22,ChestnutStreetBridgeReplacement(CR626)(DBNUM:04361;UPC:043610)
NJTPA
$10.000
$10.000
$20.000
Route23,BridgeoverPequannockRiver/HamburgTurnpike(DBNUM:08347;UPC:083470)
NJTPA
$10.000
$20.000
$30.000
Route23/80,LongtermInterchangeImprovements(DBNUM:9233B6;UPC:009234)
NJTPA
$11.500
$13.000
$24.500
Route31,BridgeoverCSXRailroad(DBNUM:08355;UPC:083550)
DVRPC
$7.000
$5.500
$12.500
Route34,CR537toWashingtonAve.,Pavement(DBNUM:11307;UPC:113070)
NJTPA
$1.000
$10.450
$11.450
Route35,PerthAmboyConnector,BridgeSuperstructureReplacement(DBNUM:04360;UPC:043600)
NJTPA
$7.000
$7.000
$14.000
Route42,ArdmoreAvetoCamdenCountyLine,Pavement(DBNUM:12306;UPC:123060)
DVRPC
$6.000
$8.000
$14.000
Route46,PassaicAvenuetoWillowbrookMall(DBNUM:9233B3;UPC:009231)
NJTPA
$10.000
$14.200
$24.200
Route47,GroveSt.toRoute130,Pavement(DBNUM:12305;UPC:123050)
DVRPC
$7.900
$13.000
$20.900
Route70,RedLionRoad(CR685)toDakotaTrail,Pavement(DBNUM:11411;UPC:114110)
DVRPC
$4.000
$7.754
$11.754
Route70,Route38toCropwellRoad(DBNUM:11338;UPC:113380)
DVRPC
$18.430
$18.277
$36.707
Route72,EastRoad(DBNUM:94071A;UPC:001010)
NJTPA
$0.500
$11.000
$11.500
Route72,ManahawkinBayBridges,Contract4(DBNUM:00357C;UPC:118014)
NJTPA
$7.632
$36.753
$32.269
$23.221
$5.991
$105.866
Table11
Page3of4
NJDOTMultiyearFundedFederalProjects
($millions)
ProjectName(ID#) MPO
PriorFYs
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
$8.000
$7.000
$32.000
FY2022
FY2023
FY2024
FY2025
Total
Route76/676,BridgeDeckReplacements(DBNUM:11326;UPC:113260)
DVRPC
$47.000
Route80,Route15Interchange(DBNUM:93139;UPC:950442)
NJTPA
$18.900
$19.500
$38.400
Route206,ValleyRoadtoBrownAvenue(DBNUM:780A;UPC:108021)
NJTPA
$20.000
$25.000
$45.000
Route280,Route21InterchangeImprovements(DBNUM:00314;UPC:003140)
NJTPA
$34.700
$42.150
$20.550
$26.750
$1.350
$125.500
Route287/78,I287/202/206InterchangeImprovements(DBNUM:04389;UPC:043890)
NJTPA
$10.000
$10.000
$12.200
$32.200
Route295/42,MissingMoves,Bellmawr(DBNUM:355A;UPC:950541)
DVRPC
$21.535
$28.975
$40.000
$30.000
$29.380
$149.890
Route295/42/I76,DirectConnection,Contract3(DBNUM:355D;UPC:113020)
DVRPC
$60.000
$70.000
$63.000
$37.000
$230.000
Route295/42/I76,DirectConnection,Contract4(DBNUM:355E;UPC:113030)
DVRPC
$80.000
$60.000
$60.000
$200.000
Route495,Route1&9/PatersonPlankRoadBridge(DBNUM:06373;UPC:063730)
NJTPA
SubtotalFederal
$46.5
$29.933
$25.451
$12.116
$188.4
$249.0
$211.3
$67.500
$320.1
$213.5
$192.9
$119.9
$37.0
$0.0
$0.0
$1,578.7
FederalGarveeFunds
Route52,CausewayReplacement,ContractA(DBNUM:244;UPC:961653)
SJTPO
$169.120
$14.900
$8.900
SubtotalFederalGarvee
$169.1
$14.9
$8.9
$192.920
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$192.9
Table11
Page4of4
NJDOTMultiyearFundedFederalProjects
($millions)
ProjectName(ID#) MPO
PriorFYs
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
FederalOtherFunds
Route278,GoethalsBridgeReplacement(DBNUM:N1205;UPC:123770)
NJTPA
$700.000
$705.000
$1,405.000
Route440,BayonneBridgeNavigationalClearanceProject(DBNUM:N1301;UPC:133420)
NJTPA
$540.000
$230.000
$230.000
$1,000.000
SubtotalFederalOther
$1,240.0
$935.0
$230.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$2,405.0
MultiyearFundingTotal
$1,455.7
$1,138.3
$487.9
$211.3
$320.1
$213.5
$192.9
$119.9
$37.0
$0.0
$0.0
$4,176.6
Table12
Page1of2
NJDOTMultiyearFundedStateProjects
($millions)
ProjectName(ID#) MPO
PriorFYs
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
$1.504
$1.504
$1.504
$1.504
FY2024
FY2025
Total
StateFunds
SouthInletTransportationImprovementProject(DBNUM:09361;UPC:093610)
SJTPO
$8.763
$1.504
$1.504
$1.504
$1.504
$23.803
Route1&9,HaynesAve.OperationalImprovements(DBNUM:94047;UPC:960974)
NJTPA
$15.000
$5.000
$20.000
Route3,Route46,ValleyRoadandNotch/RifleCampRoadInterchange,ContractB(DBNUM:059B;UPC:123020)
NJTPA
$31.000
$31.200
$42.500
$24.000
$128.700
Route4,BridgeoverPalisadeAvenue,WindsorRoadandCSXRailroad(DBNUM:065C;UPC:078044)
NJTPA
$21.500
$21.500
$43.000
Route18,EastBrunswick,DrainageandPavementRehabilitation(DBNUM:10354;UPC:103540)
NJTPA
$10.000
$16.800
$26.800
Route30,ElmwoodRd/WeymounthRd(CR623)toHaddonAve.(DBNUM:11337;UPC:113370)
SJTPO
$9.500
$10.000
$19.500
Route57,Route22toRoute31(DBNUM:14372;UPC:143720)
NJTPA
$2.900
$4.800
$7.700
Route72,ManahawkinBayBridges,Contract1A&1B(DBNUM:11385;UPC:113850)
NJTPA
$16.219
$19.116
$4.126
$39.461
Route206Bypass,MountainViewRoadtoOldSomervilleRoad(Sections14A&15A)ContractB(DBNUM:779;UPC:960597)
NJTPA
$27.500
$19.600
$47.100
Route322,CorridorCongestionReliefProject(DBNUM:07369;UPC:073690)
DVRPC
SubtotalState
$12.500
$1.000
$1.500
$1.000
$21.3
$5.4
$50.3
$93.8
$16.000
$100.1
$69.6
$25.5
$1.5
$1.5
$0.0
$0.0
$372.1
Table12
Page2of2
NJDOTMultiyearFundedStateProjects
($millions)
ProjectName(ID#) MPO
PriorFYs
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
StatePANYNJFunds
PANY&NJNJDOTProjectProgram(DBNUM:11407;UPC:114070)
NJTPA
$1,447.000
$353.000
$1,800.000
SubtotalStatePANYNJ
$1,447.0
$353.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$1,800.0
MultiyearFundingTotal
$1,468.3
$358.4
$50.3
$93.8
$100.1
$69.6
$25.5
$1.5
$1.5
$0.0
$0.0
$2,172.1
Table13
NJTRANSITFederalEquipmentLeasePayments
($millions)
ProjectName(ID#)
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
BusAcquisitionProgram(DBNUM:T111)
Note:Annualleasepayments1371CruiserbusesthroughFY2016.
$1.000
$1.000
HudsonBergenLRTSystemMOSII(DBNUM:T89)
Note:CostsanticipatedtorunthroughFY2016forvehicleleases.
$17.000
$17.000
RailRollingStockProcurement(DBNUM:T112)
Note:AnnualLeasepaymentsfor200CometVthroughFY2016,29ElectricLocomotivesthroughFY2016,33DieselLocomotivesthroughFY2016,22
DualPowerLocomotivesthrough2022.
$104.000
$48.000
$48.000
$48.000
$48.000
$48.000
$21.000
$365.000
SECTIONȱIIIȱ
ȱ
NJDOTȱȱ
PROJECT/PROGRAMȱDESCRIPTIONSȱ
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
AcquisitionofRightofWay
DBNUM:X12/UPC:800009
Advanceacquisitionanddemolitionofkeyrightofwayparcels,easements,transportationfacilities,andaccessanddevelopmentrightstopreserve
transportationcorridorsforfuturetransportationuse.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10C(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(CapitalProgramDelivery:RightofWayandUtility)
MPO
Phase
Fund
Statewide
ROW
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.250
$0.500
$0.500
$0.500
SectionIIIPage1
$0.500
$0.500
$0.500
$0.500
$0.500
$0.500
Total
$4.750
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
ADACurbRampImplementation
DBNUM:11344/UPC:113440
TheFederalHighwayAdministrationrequestedNJDOTtocompleteanAmericanswithDisabilitiesAct(ADA)CurbRampInventoryanddevelopan
ImplementationProgram.AprioritylistoflocationsthataremissingADAcurbrampswasdevelopedandthisfundingwillbeappliedtoprojectsthat
aremissingADAcurbrampsstatewide.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): A2,S6(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:Bicycle/PedestrianSafety)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
Statewide
ERC
STATE
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$10.000
Statewide
ERC
STP
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$10.000
SectionIIIPage2
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
AirportImprovementProgram
DBNUM:08415/UPC:084150
ThisprogramfundsgrantstobeawardedbytheCommissionerofNJDOTpursuanttoacompetitiveprojectapplicationprocessforprojects,including
butnotlimitedto,safety,preservation,rehabilitationandcapitalimprovements(suchasrunway,taxiwayandapronimprovements,airportlighting
andnavigationalaids,aviationfuelfarms,automatedweatherobservationsystems,airportsecurity,airportaccessroads,etc.)atpublicusegeneral
aviationairports,aviationplanningpurposes,aviationeducationandpromotionprograms,aviationstudies,airportfeasibilitystudies,andalsoto
providefundstohelpmatchandcapturefederalfunds.Theprogrammayalsofundcapitalimprovementstoairportsownedbythestate.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10A(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(AirportAssets:Aviation)
MPO
Phase
Fund
Statewide
ERC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$4.000
$4.000
$4.000
$4.000
SectionIIIPage3
$4.000
$4.000
$4.000
$4.000
$4.000
$4.000
Total
$40.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
AsbestosSurveysandAbatements
DBNUM:04311/UPC:043110
Thisprogramprovidesinitialfundingfortermagreementsforadvanceddesignserviceswhichincludeasbestossurveying,preparationofplansand
specificationsfortheasbestosabatement,andtheairmonitoringprocessneededonconstructioncontracts.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O1(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(CapitalProgramDelivery:ProjectScopingandDesign)
MPO
Phase
Fund
Statewide
DES
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.500
$0.500
$0.500
$0.500
SectionIIIPage4
$0.500
$0.500
$0.500
$0.500
$0.500
$0.500
Total
$5.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
AutomaticTrafficManagementSystem(ATMS)
DBNUM:13303/UPC:133030
ThisprogramwillprovidefundingforthedeploymentprogramforthefirstAutomaticTrafficmanagementSystem(ATMS)intheStateincludingall
phasesofdesign.ThisprogramwillincludefundingforthecompletedeliveryoftheFinalDesigndocumentforAutomaticTrafficManagement
System(ATMS)foracandidatehighway(I80,I295orI78).Thedesigndocumentwillbeusedtodeployandcarryouttheactualconstructionofthis
technologyforautomaticoperationandhandlingoftraffic.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O7,S7,X1(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:IntelligentTransportationSystems)
MPO
Phase
Fund
Statewide
ERC
CMAQ
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
$1.000
$13.000
SectionIIIPage5
$13.000
Total
$28.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Betterments,Dams
DBNUM:01335/UPC:013350
ThisprogramprovidesfundingforNJDepartmentofEnvironmentalProtectionmandatedcyclic(2year)inspectionsandthepreparationand
maintenanceofEmergencyActionPlans(EAP),OperationsandMaintenanceManuals(O&M)andHydrologyandHydraulics(H&H)engineering
studiesforNJDOTowneddams.Ifneeded,minorimprovementswillbeprovidedforhydraulicallyinadequatedamslocatedonthestatehighway
system.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O1,X1(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:Dams)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.350
$0.100
$0.375
$0.100
SectionIIIPage6
$0.375
$0.100
$0.400
$0.100
$0.400
$0.100
Total
$2.400
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Betterments,RoadwayPreservation
DBNUM:X72B
Thisisanongoingprogramofminorimprovementstothestatehighwaysystemformiscellaneousmaintenancerepaircontracts,repairparts,
miscellaneousneedsforemergentprojects,handicapramps,anddrainagerehabilitation/maintenance.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,S4(Exempt)
ASSETMANAGEMENTCATEGORY: OperatingandMaintenance(RoadAssets:HighwayCapitalMaintenanceO&M)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$10.195
$10.195
$10.195
$10.195
SectionIIIPage7
$10.195
$10.195
$10.195
$10.195
$10.195
$10.195
Total
$101.950
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Betterments,Safety
DBNUM:X72C
Thisisanongoingprogramofminorimprovementstothestatehighwaysystemsuchasbeamguiderailandimpactattenuators,aswellassafety
fencing.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,S9(Exempt)
ASSETMANAGEMENTCATEGORY: OperatingandMaintenance(SafetyManagement:SafetyCapitalMaintenanceO&M)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$7.000
$7.000
$7.000
$7.000
SectionIIIPage8
$7.000
$7.000
$7.000
$7.000
$7.000
$7.000
Total
$70.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Bicycle&PedestrianFacilities/Accommodations
DBNUM:X185
ThisisacomprehensiveprogramtoinsurethebroadimplementationoftheStatewideBicycleandPedestrianMasterPlan,CompleteStreetsPolicyand
theimplementationoffederalandstatepoliciesandprocedurespertainingtobicycle,pedestrian,transitandADAaccessandsafety.Thisprogram
includesaddressingbicycle,pedestrian,transitandADAtravelneedsthroughthedevelopmentofimprovementsonstate,countyandlocalsystem
eitherbyindependentcapitalprojectsorthroughgrantstocountiesandmunicipalities.Projectsmustmakefullconsiderationfortheneedsofall
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): AQ2,NRS(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:Bicycle/PedestrianSafety)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
Statewide
ERC
CMAQ
$5.000
$5.000
$5.000
$5.000
$5.000
$5.000
$5.000
$5.000
$5.000
$5.000
$50.000
Statewide
ERC
STATE
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$10.000
SectionIIIPage9
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
BridgeDeck/SuperstructureReplacementProgram
DBNUM:03304/UPC:033040
Thisprogramwillprovidefundingfordesignandconstructionofdeckpreservation,deckreplacementandsuperstructurereplacementprojectsin
variouslocationsthroughoutthestate.Thisisastatewideprogramwhichwilladdressanapprovedprioritylistingofdeficientbridgedecks.This
programwillalsoprovidefundingforrecommendations,survey,aerialphotography,photogrammetry,basemappingandengineering.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:DeckRehabandReplacement)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
ERC
NHPP
$4.000
$4.000
$4.000
$4.000
$4.000
$4.000
$4.000
$4.000
$4.000
$4.000
$40.000
NJTPA
ERC
NHPP
$30.000
$30.000
$30.000
$30.000
$30.000
$30.000
$30.000
$30.000
$30.000
$30.000
$300.000
SJTPO
ERC
NHPP
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$10.000
Statewide
ERC
NHPP
$5.000
$5.000
$5.000
$5.000
$5.000
$5.000
$5.000
$5.000
$5.000
$5.000
$50.000
SectionIIIPage10
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
BridgeEmergencyRepair
DBNUM:98315
ThisprogramallowsNJDOTtoobtainemergencybridgerepairs(throughvariousBridgeMaintenanceContractsi.e.ConcreteStructuralRepair,
StructuralSteelRepair,TimberStructureRepairContracts).ThisprogramalsoallowstheNJDOTtoobtainemergencytechnicalconsultantassistance
forinspectionandrepairdesignwhenthesafetyofabridge(s)iscompromisedduetoacollisionorflooddamage,etc.Theseconsultantswillbe
availabletoassistDepartmentpersonnelonanasneededbasis.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O9(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeCapitalMaintenance)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$17.000
$20.000
$20.000
$20.000
SectionIIIPage11
$20.000
$20.000
$20.000
$20.000
$20.000
$20.000
Total
$197.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
BridgeInspection
DBNUM:X07A/UPC:800002
Thisprogramprovidesregularstructuralinspectionofstatehighway,NJTransithighwaycarryingbridgesandlocalbridgesasrequiredbyfederal
law.Thisprogramalsoenablestheindepthscourevaluationofpotentiallyscoursusceptiblebridges.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S1,S19,X3(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeManagement)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
Statewide
EC
NHPP
$11.500
$9.800
$12.500
$10.800
$12.500
$11.510
$14.380
$12.840
$13.620
$12.510
$121.960
Statewide
EC
STP
$9.900
$15.900
$9.900
$16.600
$10.920
$18.350
$11.610
$19.210
$11.880
$19.910
$144.180
SectionIIIPage12
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
BridgeMaintenanceandRepair,MovableBridges
DBNUM:14404/UPC:144040
ThisOperationsprogramallowstheNJDOTtoobtainemergencymovablebridgeandtunnelrepairsona24/7basis.Furthermore,thiscontract
fundingwillbeutilizedtoaddressprioritystructuralrepairdeficienciesandPEOSHAviolationsthatareidentifiedduringindepthinspections.These
assetsarerequiredtooperateondemandandadheretodrawbridgeoperationregulationspursuanttotitle33,CodeofFederalRegulations.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,S6(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeCapitalMaintenance)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$21.000
$22.000
$22.000
$22.000
SectionIIIPage13
$23.000
$23.000
$24.000
$24.000
$25.000
$25.000
Total
$231.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
BridgeManagementSystem
DBNUM:X70/UPC:800018
Thisisaprogramforthedevelopment,improvement,andimplementationofNewJerseysBridgeManagementSystem,acomputerizedsystemof
analyzingbridgerehabilitationandreplacementneeds.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeManagement)
MPO
Phase
Fund
Statewide
EC
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.800
$0.800
$0.800
$0.800
SectionIIIPage14
$0.900
$0.900
$0.900
$1.000
$1.000
$1.000
Total
$8.900
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
BridgePreventiveMaintenance
DBNUM:13323/UPC:133230
Thisprogramprovidesfundingforbridgepreservationactivitiesincludingpaintingaswellasdeckrepairsandsubstructurerepairsasameansof
extendingstructurelife.Paintingcontractsshallbeawardedtoincludepaintingsteelonvariousstructuresasananticorrosionandwillbeconstituted
fromanapprovedlistofbridgesbasedontheavailabilityandregionalbreakdownoffunding.Preventivemaintenancecontractsshallincludedeck
repairs,headerreconstruction,curbreconstruction,jointresealing,substructureconcreterepairs,andsealingoftheentirestructure,withstructures
systematicallyprioritizedbycorridororgeographicalarea.Bothpaintingandpreventivemaintenancecontractsshallbeawardedtopreserveand
prolongtheusefulservicelifeofbridgesinaccordancewiththeNJDOTBridgePreventiveMaintenanceProgram.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeCapitalMaintenance)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
Statewide
EC
NHPP
$13.000
$13.000
$13.000
$13.000
$13.000
$13.000
$13.000
$13.000
$13.000
$13.000
$130.000
Statewide
EC
STATE
$22.000
$22.000
$22.000
$22.000
$22.000
$22.000
$22.000
$22.000
$22.000
$22.000
$220.000
Statewide
EC
STP
$7.000
$7.000
$7.000
$7.000
$7.000
$7.000
$7.000
$7.000
$7.000
$7.000
$70.000
SectionIIIPage15
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
BridgeReplacement,FutureProjects
DBNUM:08381/UPC:083810
Futureprojectsrelatedtobridgerehabilitationsandreplacements,Statewide.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
Statewide
ERC
NHPP
Statewide
ERC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
$1.700
$3.675
$6.693
$35.000
$35.000
$35.000
SectionIIIPage16
$11.144
Total
$26.929 $219.759 $287.799 $326.449 $318.479 $1,203.627
$35.000 $165.144 $165.144 $165.144 $165.144 $165.144
$965.720
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
BridgeScourCountermeasures
DBNUM:98316
Bridgescourcountermeasurecontractswillprovidetheneededprotectiontovarioussubstructureelementstoextendthelifeofstatebridgesover
waterways.Thebridgescourcountermeasurecontractswillbeconstitutedfromanapprovedlistofbridgesandwillbebasedontheavailabilityand
regionalbreakdownoffunding.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O5(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeCapitalMaintenance)
MPO
Phase
Fund
Statewide
ERC
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.500
$0.500
$0.500
$0.500
SectionIIIPage17
$0.500
$0.500
$0.500
$0.500
$0.500
$0.500
Total
$5.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
BurlingtonCountyRoadwaySafetyImprovements
DBNUM:D0302
Thisprogramwillprovidefortheinstallationofimprovedsafetyitemsincludingreflectivepavementmarkings(includingbothstripingandraised
reflectivemarkers),reflectiveobjectmarkers,reflectiveroadwaydelineators,guiderail,andothertreatmentsthatimprovetheoverallsafetyand
visibilityofvariousroadwaysinthecounty.
COUNTY: Burlington
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: BurlingtonCounty
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S6(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(LocalSystemSupport:LocalSafetyImprovements)
MPO
Phase
Fund
DVRPC
CON
STPSTU
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.800
SectionIIIPage18
$0.800
$0.800
Total
$2.400
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
CamdenCountyBusPurchase
DBNUM:D0601/UPC:068082
IntheDVRPCregion,acombinationoffixedroute,subscription,anddemandresponsivetransitservicesareprovidedinCamdenCountybySenior
CitizensUnitedCommunityServices(SCUCS)/SenHanTransitandSouthJerseyTransportationAuthority(SJTA).Avarietyoftrippurposesare
servedbythesespecialtransitprovidersincludingemployment,nonemergencymedical,nutrition,personalbusiness,andshoppingtrips.This
projectprovidesfundsforpurchasingnewcapitalequipment,usuallyliftequippedvehicles.
COUNTY: Camden
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: CamdenCounty
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M10(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(LocalSystemSupport:LocalAid,OtherPrograms)
MPO
Phase
Fund
DVRPC
EC
CMAQ
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.100
$0.100
$0.100
$0.100
SectionIIIPage19
$0.100
$0.100
$0.100
$0.100
$0.100
$0.100
Total
$1.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
CamdenCountyRoadwaySafetyImprovements
DBNUM:D0410/UPC:048038
Thisprogramwillprovidefortheinstallationofimprovedsafetyitemsincludingreflectivepavementmarkings(includingbothstripingandraised
reflectivemarkers),reflectiveobjectmarkers,reflectiveroadwaydelineators,guiderail,andothertreatmentsthatimprovetheoverallsafetyand
visibilityofvariousroadwaysinthecounty.
COUNTY: Camden
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: CamdenCounty
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S11(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(LocalSystemSupport:LocalMobilityImprovements)
MPO
Phase
Fund
DVRPC
DES
STPSTU
DVRPC
CON
STPSTU
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.100
Total
$0.100
$0.800
SectionIIIPage20
$0.800
$0.800
$0.800
$3.200
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
CampMeetingAvenueBridgeoverTrentonLine,CR602
DBNUM:99405/UPC:994050
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacetheorphanstructure,whichisincriticalcondition.Thereplacementofthis
structurewillbedesignedsoasnottoprecludeimprovementsneededtoreintroducepassengerservicetotheWestTrentonLine,aswellasincreasing
theheightofthebridgetoallowthecurrenttrackstoberaisedtoaddressongoingrailroadoperationalissues,asidentifiedintheNJTPAGrade
CrossingAssessmentStudy.Thecurrentbridgeprovidesasinglelaneoftraffic,hassteepgradesontheapproachesandhassubstandardverticalsight
distance.Thenewbridgewillbewidertoaccommodatetwotrafficlanes,andthegradeandverticalsightdistancewillalsobeimproved.
Totalconstructionfundingneededisexpectedtobe$5,500,000.
COUNTY: Somerset
LEGISLATIVEDISTRICT: 16
MUNICIPALITY: MontgomeryTwp
SPONSOR: NJDOT
MILEPOST(S): 0.50.56
STRUCTURENO.: 1850160
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:RailroadOverheadBridges)
MPO
Phase
Fund
NJTPA
DES
STP
NJTPA
ROW
STP
NJTPA
CON
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.550
Total
$0.550
$0.500
$0.500
$5.500
SectionIIIPage21
$5.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
CapitalContractPaymentAudits
DBNUM:98319
Thisprogramprovidesfundingfortheauditingofcapitalprojectcontractinvoicesthatinvolvereimbursementofdirectandoverheadcosts.The
FederalHighwayAdministrationrequiressuchauditsonallengineeringfirmsdoingbusinesswiththeNJDOTinordertoensureaccuratebillingof
projectcosts.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10A(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(CapitalProgramDelivery:ProgramImplementationCosts)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.500
$1.500
$1.500
$1.500
SectionIIIPage22
$1.500
$1.500
$1.500
$1.500
$1.500
$1.500
Total
$15.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
ChurchStreetBridge,CR579
DBNUM:NS9806/UPC:058011
TheChurchStreet(CR579)overtheLehighValleyMainLinebridgeprojectproposesthereplacementoftheexistingfunctionallyobsoletebridgeinan
efforttoimprovesubstandardsightdistanceandinadequatedeckgeometry.Theproposedundertakingwouldreplacetheexistingbridgewithanew
twolanebridgetotheeastandthebridgeapproacheswillbeimproved.
Totalconstructionfundingneededisexpectedtobe$3,800,000.
COUNTY: Hunterdon
LEGISLATIVEDISTRICT: 23
MUNICIPALITY: BloomsburyBoro,BethlehemTwp
SPONSOR: HunterdonCounty
MILEPOST(S): 36.71
STRUCTURENO.: 1050161
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:LocalBridges)
MPO
Phase
Fund
NJTPA
CON
STPNJ
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.800
SectionIIIPage23
Total
$3.800
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
CongestionRelief,IntelligentTransportationSystemImprovements(SmartMoveProgram)
DBNUM:02379/UPC:023790
Thisisaprogramoflowcost,quickturnaroundintelligenttransportationsystem(ITS)improvementstoimprovetrafficflowandprovidetraveler
informationonthestatestransportationsystem.ThisprogramwillprovideforthedeploymentofthesethroughseparateITSprojectsorbeadded
withinotherroadwayandbridgeinfrastructurepreservationprojectstoeffectivelycompletetheseattheminimumcostanddisruptiontotraffic
duringconstruction.DesignsupporttoaddITScomponentsand/orstandardsmaybeaccomplishedthroughusingconsultants.ITSequipmentare
longleadtimeitemsandthisprogramwillallowprocurementtoproceedinadvanceandthentobeinstalledinthefirststagestoalsoassistinthe
mitigationoftrafficimpactsduringconstructionofthoseprojects.ITSequipmentcouldincludeDynamicMessageSignstoproviderealtimetraffic
conditionsinstrategiclocationstoallowthemotoringpublictomakeinformeddecisionsonpossiblealternatives.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,S7(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:IntelligentTransportationSystems)
MPO
Phase
Fund
Statewide
ERC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$2.000
$2.000
$2.000
$2.000
SectionIIIPage24
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
Total
$20.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
CongestionRelief,OperationalImprovements(FastMoveProgram)
DBNUM:02378/UPC:023780
Thisisaprogramoflowcost,quickturnaroundcapitalimprovementstorelievecongestionatkeybottlenecklocationsthroughoutthestate.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10A(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
$1.000
$1.000
$1.000
SectionIIIPage25
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
Total
$10.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
ConstructionInspection
DBNUM:X180/UPC:800029
Inordertoprovideinspectionofconstructionprojectsonanasneededbasis,theNJDOTprovidestermagreements.Thisservicealsoprovides
materialsinspectionofstructuralsteelandprecastconcreteproducedatoutofstatefabricationfacilities.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10A(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(CapitalProgramDelivery:Construction)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$8.000
$11.500
$11.500
$11.500
SectionIIIPage26
$11.500
$11.500
$11.500
$11.500
$11.500
$11.500
Total
$111.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
ConstructionProgramITSystem(TRNS.PORT)
DBNUM:05304/UPC:053040
Thisprogramwillprovideareplacementsystemforthecurrentinformationtechnology(IT)systemssupportingtheEstimatingthroughAwardingof
ConstructionProjects.ItwillalsoimplementITsystemsforConstructionManagement,MaterialsandCivilRightsincludingannuallicensingfees.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10B(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(CapitalProgramDelivery:Construction)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.500
$0.700
$0.700
$0.700
SectionIIIPage27
$0.700
$0.700
$0.700
$0.700
$0.700
$0.750
Total
$6.850
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
CorsonsTavernRoad(CR628),ResurfacingWoodbineOceanViewRoadtoUSRoute9
DBNUM:S1004/UPC:108025
RoadwayresurfacinganddrainageimprovementsfromWoodbineOceanViewRoad(CR550)toRt.US9.
Totalconstructionfundingneededisexpectedtobe$1,682,000.
COUNTY: CapeMay
LEGISLATIVEDISTRICT: 1
MUNICIPALITY: UpperTwp,DennisTwp
SPONSOR: CapeMayCounty
MILEPOST(S): 4.716.75
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:LocalRoadwayImprovements)
MPO
Phase
Fund
SJTPO
CON
STPSJ
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.682
SectionIIIPage28
Total
$1.682
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
CorsonsTavernRoad,Resurfacing(CR628)
DBNUM:S0902/UPC:098002
RoadwayresurfacinganddrainageimprovementsresultfromOceanViewOperationalStudy.Limits:1,000ftsouthofTattlerRoadtoWoodbine
OceanViewRd(CR550).
Totalconstructionfundingneededisexpectedtobe$1,723,000.
COUNTY: CapeMay
LEGISLATIVEDISTRICT: 1
MUNICIPALITY: DennisTwp
SPONSOR: CapeMayCounty
MILEPOST(S): 2.354.70
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:LocalRoadwayImprovements)
MPO
Phase
Fund
SJTPO
CON
STPSJ
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.723
SectionIIIPage29
Total
$1.723
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
CountyRoute537Corridor,SectionA,NJRt.33BusinessandGravelHillRoad
DBNUM:NS0403
CR537servesregionaltravelbetweenBurlington,OceanandMonmouthCounties.Thisroadwayalsoservesasalinkbetweenrapidlydeveloping
areasofMercerandOceanCountiestorecreationalandcommercialactivitieswithinMonmouthCounty.Asaresult,trafficvolumesalongthis
corridorhavesignificantlyincreased,resultinginhighcongestionalongthissectionofCR537.TheCountywillinvestigateimprovementalternatives
resultingfromtherecenttechnicalstudypreparedforthissectionofthecorridor.
Totalconstructionfundingneededisexpectedtobe$20,700,000.
COUNTY: Monmouth
LEGISLATIVEDISTRICT: 11
MUNICIPALITY: FreeholdBoro,FreeholdTwp
SPONSOR: MonmouthCounty
MILEPOST(S): 48.9351.56
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10A(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(LocalSystemSupport:LocalMobilityImprovements)
MPO
Phase
Fund
NJTPA
ROW
STPNJ
NJTPA
CON
STPNJ
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$7.000
$7.000
$20.700
SectionIIIPage30
Total
$20.700
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
CrashReductionProgram
DBNUM:X242
State’sStrategicHighwaySafetyPlaninfluencesthedecisionsforinvestmentplanning.SHSPemphasisareasguideproblemidentificationintheHSIP.
CrashReductionProgramisacomprehensiveprogramofsafetyimprovementsdesignedtoimproveconditionsandlocationsidentifiedbythe
HighwaySafetyImprovementProgram.Thesetreatmentsmayincludepavementimprovements,protectionorremovaloffixedobjects,andutility
polerelocationorreplacement.Thisprogramwillalsodevelopandimplementasystemicapproachtotheinstallationoflaneandroadwaydeparture
technologiessuchasrumblestripsandrumblestripes,signing,stripingandhighfrictionsurfacetreatmenttopreventvehiclesfromleavingtheir
respectivelanesandcausingcrashes,injuries,anddeaths.Additionally,thisprogramwillalsoprovideforthedevelopmentandimplementationof
quickturnaroundprojectsatlocationswhichshowanexcessiveoccurrenceofcrashesaswellasremediationofthoselocations.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S6(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:SafetyImprovements)
MPO
Phase
Fund
Statewide
EC
HSIP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$5.000
$5.000
$5.000
$5.000
SectionIIIPage31
$5.000
$5.000
$5.000
$5.000
$5.000
$5.000
Total
$50.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
CulvertInspectionProgram,LocallyownedStructures
DBNUM:99322A/UPC:048018
Thisprogramwillprovideforregularstructuralinspectionofcountyownedandlocallyownedhighwaybridgesoflessthan20feet.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:Culverts)
MPO
Phase
Fund
Statewide
EC
STATE
Statewide
EC
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.000
$4.800
$4.800
$4.800
SectionIIIPage32
$4.800
Total
$2.400
$2.400
$2.400
$2.400
$2.400
$34.200
$2.400
$2.400
$2.400
$2.400
$2.400
$12.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
CulvertInspectionProgram,StateownedStructures
DBNUM:99322
Thisprogramprovidesfortheinspectionofstateownedhighwaybridgeslessthan20feetinlength.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:Culverts)
MPO
Phase
Fund
Statewide
EC
STATE
Statewide
EC
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.700
$1.400
$1.350
$1.400
$1.350
$6.200
$1.400
SectionIIIPage33
Total
$0.750
$1.000
$1.500
$1.550
$6.200
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
CulvertReplacementProgram
DBNUM:09316/UPC:093160
Culvertreplacementswillbeinitiatedbasedontheresultsoftheculvertinspectionprogram.Itisanticipatedthattheseculvertswillbereplacedinthe
samelocationwithbasicallythesamewaterwayopeningsizeandwillrequireminimalutilityinvolvement.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,S4(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:Culverts)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
Statewide
ERC
STATE
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
$20.000
Statewide
ERC
STP
$2.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$11.000
SectionIIIPage34
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
DBESupportiveServicesProgram
DBNUM:X142
ThisisafederalgrantprogramwhichprovidessupporttoindividualDisadvantagedBusinessEnterprise(DBE)contractorsthroughtechnical
assistance,onsitevisits,DBEconferences,newsletters,andsimilartypesofassistance.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10B(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(CapitalProgramDelivery:ContractorSupport)
MPO
Phase
Fund
Statewide
EC
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.250
$0.250
$0.250
$0.250
SectionIIIPage35
$0.250
$0.250
$0.250
$0.250
$0.250
$0.250
Total
$2.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Delaware&RaritanCanalBridges
DBNUM:15322/UPC:153220
InitiatedbytheBridgeManagementSystem,thisprojectprovidesforConceptDevelopmentstudiesonthefollowingstructuresalongtheDelaware
andRaritanCanal:CarnegieRoad,BridgeoverD&RFeederCanal;CountyRoute571(WashingtonRoad),BridgeoverD&RCanal;LandingLane(CR
609),BridgeoverD&RCanal;Route206,BridgeoverD&RFeederCanal;HermitageAvenue,BridgeoverD&RFeederCanal;RiverDrive,Bridgeover
D&RFeederCanal;BridgeoverD&RFeederCanalatLockNo.3;CoryellStreet,BridgeoverD&RFeederCanal;CR533(QuakerRoad),Bridgeover
D&RCanal;ManvilleCauseway(CR623),BridgeoverD&RCanal;ChapelDriveatCR623,BridgeoverD&RCanal.Theprojectalsoprovides
emergencysuperstructurereplacementandsubstructurerehabilitationforCR518(GeorgetownFranklinRd),BridgeoverD&RCanalandan
emergencytotalstructurereplacementofCR514(AmwellRoad),BridgeoverD&RCanal.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$11,850,000.
COUNTY: Mercer,Hunterdon,Middlesex,Somerset
LEGISLATIVEDISTRICT: 15,16,17
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: Various
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10A,S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
PE
STATE
$0.200
$0.200
NJTPA
PE
STATE
$0.200
$0.200
DVRPC
DES
STATE
$0.375
$0.375
NJTPA
DES
STATE
$0.375
$0.375
DVRPC
CON
STATE
$4.546
$4.546
NJTPA
CON
STATE
$5.304
$5.304
NJTPA
ERC
STATE
$2.000
$2.000
SectionIIIPage36
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Design,EmergingProjects
DBNUM:X106/UPC:800021
ThisprogramprovidesinitialfundingforCapitalProgramManagementtaskorderagreementsaswellasprojectsemergingfromconcept
development.Fundingisalsoprovidedforreviewofprojectsandforadvanceddesignserviceswhichinclude,butarenotlimitedtothefollowing
functions:developmentofbaseplanforfinaldesign;locationofexistingfeatureswithinfootprints,suchasprojectmonumentation,topography,
utilitiesanddrainage,usingSubsurfaceUtilityEngineering(SUE),GeneralFieldsurvey,GlobalPositioningSystemsurvey,PrimaryControlsurveyand
Aerialphotography;geotechnicalwork,specificallysoilborings;administrativeworkneededtosetbudgetsandmanpowerforrightofway
acquisition;asbestossurveyingorplans,specificationsandairmonitoringforabatementprocess.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10C,X1(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(CapitalProgramDelivery:ProjectScopingandDesign)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
Statewide
DES
STATE
$6.500
$6.500
$5.000
$5.000
$5.000
$5.000
$5.000
$5.000
$5.000
$5.000
$53.000
Statewide
DES
STP
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$10.000
SectionIIIPage37
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Design,GeotechnicalEngineeringTasks
DBNUM:05342/UPC:053420
ThisprogramwillprovidefundingfortermagreementstoobtainconsultantservicestoperformGeotechnicalServicesforvariousprojectswithinthe
geographicalconfinesofthestateofNewJersey.TheworkcoveredbythisagreementwillbelimitedtoGeotechnicalEngineeringServicesand
consistsoftwomajortasks:conductingsubsurfaceexplorationprogramsandprovidinggeotechnicaldesignsandanalysisforbridgeandstructure
foundations,roadwayengineeringandrockengineering.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O1,O10A,X5(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(CapitalProgramDelivery:ProjectScopingandDesign)
MPO
Phase
Fund
Statewide
DES
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.500
$0.500
$0.500
SectionIIIPage38
$0.500
$0.500
$0.500
$0.500
Total
$3.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
DisadvantagedBusinessEnterprise
DBNUM:X197
ThisisafederalgranttoprovideanintegratedprogramoftrainingandbusinessdevelopmentservicestoexpandthecapacityofDisadvantaged
BusinessEnterprise(DBE)firmstomoreequitablycompeteforpublicworkscontractsintheState.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10C(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(CapitalProgramDelivery:ContractorSupport)
MPO
Phase
Fund
Statewide
EC
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.100
$0.100
$0.100
$0.100
SectionIIIPage39
$0.100
$0.100
$0.100
$0.100
$0.100
$0.100
Total
$1.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
DrainageRehabilitation&Improvements
DBNUM:X154D
Thisprogramfundslowcost/highvaluedrainageprojectsonthestatehighwaydrainagesystem.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,S4(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:Drainage)
MPO
Phase
Fund
Statewide
EC
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$8.000
$5.000
$5.000
$5.000
SectionIIIPage40
$5.000
$5.000
$5.000
$5.000
$5.000
$5.000
Total
$53.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
DrainageRehabilitationandMaintenance,State
DBNUM:X154
Thisprogramprovidesfundingfortherehabilitationandmaintenanceofstatehighwaydrainagesystems,whichmayinclude:removalofmaterial,
videoinspection,contractsalarycosts,retrofittinginletcoversduetoStormwaterManagementRegulations,acquisitionandmaintenanceof
specializeddrainageequipment.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,S4(Exempt)
ASSETMANAGEMENTCATEGORY: OperatingandMaintenance(RoadAssets:DrainageO&M)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$10.000
$16.000
$16.000
$16.000
SectionIIIPage41
$16.000
$16.000
$16.000
$16.000
$16.000
$16.000
Total
$154.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
DuckIslandLandfill,SiteRemediation
DBNUM:99334/UPC:993340
TheNJDOTcompletedconstructionthatproperlysealedthesiteofthelandfillin2001.NJDepartmentofEnvironmentalProtectionrequires
continuedmonitoringofthesiteduetocontaminationlevelsatthelandfill.Thismonitoringrequirementistypicalforalandfillwithcontamination.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$1,000,000.
COUNTY: Mercer
LEGISLATIVEDISTRICT: 14
MUNICIPALITY: HamiltonTwp
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S2(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:EnvironmentalRemediation)
MPO
Phase
Fund
DVRPC
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.100
$0.100
$0.100
$0.100
SectionIIIPage42
$0.100
$0.100
$0.100
$0.100
$0.100
$0.100
Total
$1.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
DVRPC,FutureProjects
DBNUM:D026/UPC:058026
ThisprogramprovidesfundingforlocalprojectstobeselectedbytheDelawareValleyRegionalPlanningCommission,thedesignatedMetropolitan
PlanningOrganizationforBurlington,Gloucester,MercerandCamdencounties.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: DVRPC
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): X3(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:RegPlngandProjectDevelopment)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
MPO
Phase
Fund
DVRPC
ERC
STATE
$8.000
$11.500
$12.000
DVRPC
ERC
STPSTU
$0.546
$0.074
$0.881
Total
$31.500
$7.681
SectionIIIPage43
$10.981
$13.181
$10.981
$13.181
$14.781
$17.181
$89.471
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
ElectricalFacilities
DBNUM:X241
Thisprogramprovidesfundingforpurchasingmaterialsinadditiontoreplacement,repair,preservation,andinstallationofelectricalfacilitiesalong
thestatehighwaysystem.Includedinthisprogramarehighwaylighting,signlighting,cathodicprotectionforbridges,roadweatherinformation
systemsandtrafficcounting/monitoringsites.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O7,S18(Exempt)
ASSETMANAGEMENTCATEGORY: OperatingandMaintenance(RoadAssets:HighwayCapitalMaintenanceO&M)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$5.446
$5.446
$5.446
$5.446
SectionIIIPage44
$5.446
$5.446
$5.446
$5.446
$5.446
$5.446
Total
$54.460
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
ElectricalLoadCenterReplacement,Statewide
DBNUM:04324/UPC:043240
Thisprojectwillprovideforthebettermentoftheexistinghighwaylightingfacilities.Theexistingfacilitiesdonotcomplywithcurrentelectricalcode
andreplacementequipmentisnotavailable.Duetohightrafficvolumes,maintenanceoftheexistingfacilitiesishazardoustoNJDOTpersonnel.The
useofhighmastlightingwillbeinvestigated.ROWacquisitionmayberequired.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,S18(Exempt)
ASSETMANAGEMENTCATEGORY: OperatingandMaintenance(TransportationSupportFacilities:FacilitiesandEquipment)
MPO
Phase
Fund
Statewide
ERC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$2.000
$4.000
$4.000
$4.000
SectionIIIPage45
$4.000
$4.000
$4.000
$4.000
$4.000
$4.000
Total
$38.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
EnvironmentalInvestigations
DBNUM:X75/UPC:800030
Thisprogramprovidesfundingforenvironmentalassessmentworkproductsprovidedonaquickresponsebasisthroughspecializedtaskorder
consultantagreementsinsuchareasasecology,hazardouswasteinvestigations,culturalresourceinvestigationsandNationalEnvironmentalPolicy
Act,andSection4(f)documentation.Fundingisalsoprovidedforenvironmentalpermitfees,laboratoryfees,andotherenvironmentalconsultant
agreementsrequiring100%statefunding.Thisgeneralprogramwillalsoprovideforcleanupofgasolinedischargefromundergroundstoragetanks.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O1,X1(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(CapitalProgramDelivery:PlanningStudies)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.000
$4.500
$4.500
$4.500
SectionIIIPage46
$4.500
$4.500
$4.500
$4.500
$4.500
$4.500
Total
$43.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
EnvironmentalProjectSupport
DBNUM:03309
Thisprogramprovidesforenvironmentalservicesforthefollowingactivities:LandUseRegulationProgrampermitandpreparationpayments;
wetlanddelineations;wetlandmitigationmonitoring;wetlandmitigationremediation;culturalresourcesmitigation;hazardouswasteinvestigations
andstudiesandpayments;hydrology/hydraulicinvestigationsandstudies,permitsandpayments;andAir/Noisestudies.Theseactivitiesarein
supportofmeetingenvironmentalcommitmentsandpreventcostlyviolations.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O1,X1(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(CapitalProgramDelivery:ProjectScopingandDesign)
MPO
Phase
Fund
Statewide
ERC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.400
$0.500
$0.500
$0.500
SectionIIIPage47
$0.500
$0.600
$0.600
$0.600
$0.600
$0.600
Total
$5.400
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Equipment(Vehicles,Construction,Safety)
DBNUM:X15
Thisprogramprovidesfundingforthedirectpurchaseorlease/rentalofreplacementornewequipmenttoinclude,butnotlimitedtothefollowing:
constructionequipment,snowplowtrucks,lightdutytrucks,passengervehiclesincludingvans&cars,radios,rollers,concretemixers,asphalt
spreaders,trailermountedarrowboards,safetytrucks,portablelighttowers,truckmountedattenuators,portablemessageboards,emergencyservice
patrolvehicles,incidentmanagementresponsetrucks,vehiclefuelsystemhardwareandsoftware,HARstrailersfordiversionrouteplanningand
implementation(andallpartsassociatedwiththisequipment).Thisequipmentwillsupporttheexpandedcapital,safetyandmaintenanceprograms.
Partofthisfundingshouldbeusedtoreplaceequipmentthatisoverageandthathasfallenbehindtheplannedlifecycleduetorecurringbudget
shortfallsandbudgetcutsintheequipmentarea.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10C(Exempt)
ASSETMANAGEMENTCATEGORY: OperatingandMaintenance(TransportationSupportFacilities:FacilitiesandEquipment)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$12.000
$15.000
$15.000
$15.000
SectionIIIPage48
$15.000
$15.000
$15.000
$15.000
$15.000
$15.000
Total
$147.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Equipment,SnowandIceRemoval
DBNUM:X15A/UPC:158080
AstablefundingsourcetobeusedsolelyforthecontinuousimprovementoftheState’sabilitytoeffectivelyandefficientlyremovesnowandiceoffof
theStateownedhighwaysandbyways.Thisprogramwillprovidedirectpurchaseorreplacementofsnowandiceremovalequipment.Examplesof
equipmentandorstationaryassetstoincludebutnotlimitedto;brinemanufacturingunits,brinedistributionequipment,snowplows,saltspreaders,
specializedsnowfightingequipment,brinemanufacturingandcalciumdispenserCapitalimprovements.Partofthefundingwillbeusedtoreplace
agingsnowequipmentthatisbeyonditsfunctionalorusefullife.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,S6(Exempt)
ASSETMANAGEMENTCATEGORY: OperatingandMaintenance(TransportationSupportFacilities:FacilitiesandEquipment)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$5.000
$7.000
$7.000
$7.000
SectionIIIPage49
$7.000
$7.000
$7.000
$7.000
$7.000
$7.000
Total
$68.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
FerryProgram
DBNUM:00377/UPC:003770
Thisprogramprovidesfederalfunding,distributedannuallybyformulatostates,toconstructferryboatsandferryterminalfacilities.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10A(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(MultimodalPrograms:Ferries)
MPO
Phase
Fund
Statewide
ERC
FBP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$2.000
$2.000
$2.000
$2.000
SectionIIIPage50
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
Total
$20.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
FreightProgram
DBNUM:X34
ThisprogramprovidesfundingfortherehabilitationandimprovementofkeyelementsoftheNJrailfreightnetwork,includingacquisition,
rehabilitation,facilityconstruction,andsubstituteserviceassistanceundertheStateFreightAssistanceProgram,matchingoffederalfunds,and
participationinotherprojectsandprogramsforimprovementoftheintermodalgoodsmovementnetworkandsupportofeconomicdevelopment
initiatives.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O8(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(MultimodalPrograms:GoodsMovement)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$8.000
$8.000
$10.000
$10.000
SectionIIIPage51
$10.000
$10.000
$10.000
$10.000
$10.000
$10.000
Total
$96.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
GloucesterCountyBusPurchase
DBNUM:D9807/UPC:950795
IntheDVRPCregion,acombinationoffixedroute,subscription,anddemandresponsivetransitservicesareprovidedinGloucesterCountybythe
GloucesterDivisionofTransportationServices(DTS).Allareindependentcommunitytransportationservicesmeetingavarietyofneedsoftheir
residents.Trippurposesservedbythesecommunitytransitprovidersincludeemployment,nonemergencymedical,nutrition,personalbusiness,and
shoppingtrips.Thisprojectprovidesfundsforpurchasingnewcapitalequipment,usuallyliftequippedvehicles.
COUNTY: Gloucester
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: GloucesterCounty
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M10(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(LocalSystemSupport:LocalAid,OtherPrograms)
MPO
Phase
Fund
DVRPC
CON
CMAQ
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.070
$0.070
$0.070
$0.070
SectionIIIPage52
$0.070
$0.070
$0.070
$0.070
$0.070
$0.070
Total
$0.700
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
GloucesterCountyRoadwaySafetyImprovements
DBNUM:D0401/UPC:048000
Thisprogramwillprovidefortheinstallationofimprovedsafetyitemsincludingreflectivepavementmarkings(includingbothstripingandraised
reflectivemarkers),reflectiveobjectmarkers,reflectiveroadwaydelineators,guiderail,andothertreatmentsthatimprovetheoverallsafetyand
visibilityofvariousroadwaysinthecounty.
COUNTY: Gloucester
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: GloucesterCounty
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S11(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(LocalSystemSupport:LocalSafetyImprovements)
MPO
Phase
Fund
DVRPC
CON
STPSTU
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.800
SectionIIIPage53
$0.800
$1.000
Total
$2.600
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
HallsMillRoad
DBNUM:HP01002/UPC:018090
ImprovementstoHallsMillRoadfromRt.33BypasstoCR524willincluderealignmentandwideningtofourtravellanesaswellasother
improvements.
Totalconstructionfundingneededisexpectedtobe$16,399,728.Thefollowingspecialfederalappropriationshavebeenallocatedforthisproject
$7,982,400(NJ067);$1,000,000(NJA1).
COUNTY: Monmouth
LEGISLATIVEDISTRICT: 11
MUNICIPALITY: FreeholdTwp
SPONSOR: MonmouthCounty
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): 2020M(NonExempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(LocalSystemSupport:LocalMobilityImprovements)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
NJTPA
ROW
DEMO
NJTPA
CON
DEMO
$6.415
$6.415
NJTPA
CON
OTHER
$9.200
$9.200
NJTPA
CON
STPNJ
$0.785
$0.785
$1.000
$1.000
SectionIIIPage54
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
HamiltonRoad,BridgeoverConrailRR
DBNUM:14416/UPC:144160
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethebridge,builtin1918.
Totalconstructionfundingneededisexpectedtobe$4,500,000.
COUNTY: Somerset
LEGISLATIVEDISTRICT: 16
MUNICIPALITY: HillsboroughTwp
SPONSOR: NJDOT
MILEPOST(S): 0.97
STRUCTURENO.: 1850166
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
PE
STATE
NJTPA
DES
STATE
NJTPA
ROW
STATE
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.360
Total
$0.360
$0.440
$0.440
$0.400
$0.400
$4.500
SectionIIIPage55
$4.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
HighwaySafetyImprovementProgramPlanning
DBNUM:09388/UPC:093880
Thisitemconsistsoftwoprograms:SafetyManagementSystem(SMS)safetyimprovementprojectsandRailHighwaysafetyimprovementprojects.
SMS,throughguidanceoftheHSIP(23CFR924),identifies,prioritizesandimplementssafetyprogramsandprojectsassociatedwithsafecorridors
andintersectionimprovementprogramsinanefforttoreducecrashesandcrashseverityonNewJerseysroadways.SafeCorridorProgramcurrently
includesportionsofRt.1,9,22,40,46,47,73and206.TheIntersectionImprovementProgramincludesrightangle,leftturn,samedirectionand
pedestriancrashintersectionlocations.RailHighwayProgramwillcontinueonsiteinspectionofpublicgradecrossingtoidentifyrailhighwaygrade
crossinghazardstodevelopandimplementrailhighwaygradecrossingsafetyimprovements.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,S6(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:SafetyImprovements)
MPO
Phase
Fund
Statewide
EC
HSIP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$4.000
$4.000
$4.000
$4.000
SectionIIIPage56
$4.000
$4.000
$4.000
$4.000
$4.000
$4.000
Total
$40.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
IntelligentTrafficSignalSystems
DBNUM:15343/UPC:153430
ThisprogramwillseektoimprovemobilityonNewJersey’sarterialhighways.Arterialscontributealmost70%oftotalcongestionthatoccursinNew
Jersey.ThisprogramwillfocusondynamicallymanagingNJ’sarterialsfromNJDOT’sArterialManagementCenter.Existingtrafficsignalswillbe
strategically,systematicallyandprogrammaticallyupgradedfromstandalonesignalstohighlysophisticated,coordinated,realtimetrafficresponse
trafficsignals.Thisupgradewillconsistofinstallingnewcontrollers,intelligentsoftwareandalgorithms,robustdetectionandcommunication.Thisis
aplantoupgrademostofthesignalsonNJDOTownedhighwaysonly.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NR2,NRS(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:IntelligentTransportationSystems)
MPO
Phase
Fund
Statewide
ERC
CMAQ
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$5.000
$5.000
$5.000
$5.000
SectionIIIPage57
$5.000
$5.000
$5.000
$5.000
$5.000
$5.000
Total
$50.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
IntelligentTransportationSystemResourceCenter
DBNUM:13304/UPC:133040
ThisprogramincludesthedevelopmentofastatewideIntelligentTransportationSystems(ITS)StrategicPlan,ITSDeploymentPlan,andaWorkZone
MobilityMonitoringProgram.Thecenterwillalsoconductresearch,operationaltests,evaluationofdeploymentscenariosandstrategies,trainingand
outreachtodevelopbestpracticesforimplementationofITS.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10B(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:IntelligentTransportationSystems)
MPO
Phase
Fund
Statewide
EC
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.100
$3.100
$3.100
$3.100
SectionIIIPage58
$3.100
$3.100
$3.100
$3.100
$3.100
$3.100
Total
$31.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
IntersectionImprovementProgram(ProjectImplementation)
DBNUM:98333
ThisprogramprovidesfortheimplementationofsafetyandoperationalimprovementsatintersectionsidentifiedbytheHighwaySafetyImprovement
Programashavingsignificantsafetyproblems.Thisprogramalsoincludesrightangle,leftturnandpedestriancrashoccurrencesatintersection
locations.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,S6(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:SafetyImprovements)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
Statewide
ERC
HSIP
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$10.000
Statewide
ERC
STATE
$0.250
$0.250
$0.250
$0.250
$0.250
$0.250
$0.250
$0.250
$0.250
$0.250
$2.500
SectionIIIPage59
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
InterstateServiceFacilities
DBNUM:X151
Thisprogramprovidesforthedevelopmentandimplementationofimprovementsandlandscapingtothenetworkofinterstatehighwayservice
facilities.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,S15(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:QualityofLife)
MPO
Phase
Fund
Statewide
EC
NHPP
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
$0.500
$0.600
Total
$1.000
$0.100
$0.100
SectionIIIPage60
$0.100
$0.100
$0.100
$0.100
$0.100
$0.100
$1.900
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
IrvingtonCenterStreetscape
DBNUM:08443/UPC:084430
ThisprojectisforthedesignandconstructionofstreetscapeimprovementsforSpringfieldAvenueinIrvington.ProjectlimitsareClintonAvenueto
thewestandCivicSquare(east).Theareaneedsnewcurbs,sidewalks,lighting,benches,andbusshelters.Theprojectwillalsoaddresssignageand
pedestriansafetytrafficcalmingissues.
Thefollowingspecialfederalappropriationwasallocatedtothisproject:FY05SAFETEALU/HPPSAFETEALUearmark,$800,000.Billline#2869,
NJ214.
Totalconstructionfundingneededisexpectedtobe$1,440,000.Thefollowingspecialfederalappropriationshavebeenallocatedforthisproject
$801,180(NJ214).
COUNTY: Essex
LEGISLATIVEDISTRICT: 28
MUNICIPALITY: IrvingtonTwp
SPONSOR: IrvingtonTwp.
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): AQ2,MT7,O5(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(LocalSystemSupport:TransportationEnhancements)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
NJTPA
CON
DEMO
$0.720
$0.720
NJTPA
ERC
DEMO
$0.720
$0.720
SectionIIIPage61
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
JobOrderContractingInfrastructureRepairs,Statewide
DBNUM:13305/UPC:133050
UtilizeJobOrderContractingtobettermanageandcontrolcostassociatedwithtransportationinfrustructurerepairs(e.g.fixedbridge;movable
bridge;roadwaydrainagesystems;roadwayrepair;lightingetc.).Thisprojectutilizesa3rdpartyvendortocontrolthebidawardprocessfor
transportationprojectswithanestimatedrepaircostunder$1Mperproject.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeCapitalMaintenance)
MPO
Phase
Fund
Statewide
EC
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$7.000
$7.000
$7.000
$7.000
SectionIIIPage62
$7.000
$7.000
$7.000
$7.000
$7.000
$7.000
Total
$70.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
LandisAvenue,PhaseIII,ConeyAvenuetoWestAvenue
DBNUM:S1122/UPC:118029
Thisprojectprovidesformillingandresurfacingoftheroadwaywithingtheexistingrightofwayinadditiontoremovalandreplacementofconcrete
itemsandrehabilitationsoftheexistingstormsewerinfrastructureasneeded.
Totalconstructionfundingneededisexpectedtobe$670,000.
COUNTY: Cumberland
LEGISLATIVEDISTRICT: 1
MUNICIPALITY: VinelandCity
SPONSOR: VinelandCity
MILEPOST(S): 0.070.41
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:LocalRoadwayImprovements)
MPO
Phase
Fund
SJTPO
CON
STPSJ
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.670
Total
$0.670
SectionIIIPage63
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
LandisAvenue,PhaseIV,OrchardRoad(CR628)toMoyerStreet
DBNUM:S1124/UPC:118031
Thisprojectprovidesformillingandresurfacingoftheroadwaywithingtheexistingrightofwayinadditiontoremovalandreplacementofconcrete
itemsandrehabilitationsoftheexistingstormsewerinfrastructureasneeded.
Totalconstructionfundingneededisexpectedtobe$609,000.
COUNTY: Cumberland
LEGISLATIVEDISTRICT: 1
MUNICIPALITY: VinelandCity
SPONSOR: VinelandCity
MILEPOST(S): 8.699.09
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:LocalRoadwayImprovements)
MPO
Phase
Fund
SJTPO
CON
STPSJ
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.609
SectionIIIPage64
Total
$0.609
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
LandisAvenue,PhaseV,MillRoadtoOrchardRoad(CR628)
DBNUM:S1407/UPC:143920
Mill&OverlayRoadwaywithinexistingRightofWayfromMillRoadtoOrchardRoad.
Totalconstructionfundingneededisexpectedtobe$700,000.
COUNTY: Cumberland
LEGISLATIVEDISTRICT: 1
MUNICIPALITY: VinelandCity
SPONSOR: CityofVineland
MILEPOST(S): 8.218.69
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
SJTPO
DES
STPSJ
SJTPO
CON
STPSJ
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.050
Total
$0.050
$0.700
SectionIIIPage65
$0.700
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
LegalCostsforRightofWayCondemnation
DBNUM:X137
ThisprogramprovidesreimbursementtotheDivisionofLawforlegalworkperformedinconnectionwithrightofwaycondemnationandcapital
projectlitigation.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O3(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(CapitalProgramDelivery:RightofWayandUtility)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.600
$1.600
$1.600
$1.600
SectionIIIPage66
$1.600
$1.600
$1.600
$1.600
$1.600
$1.600
Total
$16.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
LocalAidConsultantServices
DBNUM:10347/UPC:103470
FundingforconsultantservicestoassistlocalpublicagenciesinadministeringprojectsandprovidingoversighttorecipientsreceivingLocalAid
funds.Servicesalsoincludeprovidingoverallqualityassuranceandqualitycontrolfortheprojectdeliveryprocess.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10A,X1(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:RegPlngandProjectDevelopment)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
EC
STPSTU
$0.200
$0.200
$0.200
$0.200
$0.200
$1.000
NJTPA
EC
STPNJ
$1.200
$1.200
$1.200
$1.200
$1.200
$6.000
SJTPO
EC
STPSJ
$0.100
$0.100
$0.100
$0.100
$0.100
$0.500
SectionIIIPage67
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
LocalAidGrantManagementSystem
DBNUM:06327/UPC:063270
Thisprogramprovidesforthedevelopmentandimplementationofawebbasedgrantmanagementsystemtofacilitatecustomerservicetograntees
andenablebettermanagementofgrantfunds,bothstateandfederal.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10A(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:RegPlngandProjectDevelopment)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.165
$0.165
$0.165
$0.165
SectionIIIPage68
$0.165
$0.165
$0.165
$0.165
$0.165
$0.165
Total
$1.650
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
LocalAid,InfrastructureFund
DBNUM:X186
ThisprogramprovideslocalaidfundingforcountiesandmunicipalitiesinadditiontofundingprovidedbythebasicTrustFundActprogram.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: LocalLead
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10C(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:LocalAid,Discretionary)
MPO
Phase
Fund
Statewide
ERC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$7.500
$7.500
$7.500
$7.500
SectionIIIPage69
$7.500
$7.500
$7.500
$7.500
$7.500
$7.500
Total
$75.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
LocalBridges,FutureNeeds
DBNUM:08387/UPC:083870
Formulabasedandcompetitivebasedfundingisprovidedtocountiesforfutureneedsrelatedtothelocalbridgesystem.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:LocalBridges)
MPO
Phase
Fund
Statewide
ERC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$25.000
$25.000
$25.000
$25.000
SectionIIIPage70
$25.000
$25.000
$25.000
$25.000
$25.000
$25.000
Total
$250.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
LocalCMAQInitiatives
DBNUM:X065
UndertheguidanceoftheMetropolitanPlanningOrganizations,localprojectswillbedevelopedthatwillenhanceairquality.CongestionMitigation
andAirQualityImprovementProgram(CMAQ)fundsareallocatedtothestatesforuseinnonattainmentandmaintenanceareasforprojectsthat
contributetotheattainmentoftheCleanAirActstandardsbyreducingemissionsfromhighwaysources.TheDVRPCprogramwillcontributetothe
followingprojectsselectedaspartoftheDVRPCcompetitiveCMAQProgram:DieselEngineLocomotiveRetrofits,GloucesterCountyCNGTransit
Vehicles,GloucesterMarineTerminalTruckEngineRetrofit,ProvinceLineRoadBikeTrail,andHaddonAvenueRoadwayImprovements.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: LocalLead
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): 2014NMNRS,2015NMNRS(NonExempt),X3(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:DemandManagement)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
EC
CMAQ
$0.910
$0.910
$0.910
$0.910
$0.910
$0.910
$0.910
$0.910
$0.910
$0.910
$9.100
NJTPA
EC
CMAQ
$5.000
$5.000
$5.000
$5.000
$5.000
$5.000
$5.000
$5.000
$5.000
$5.000
$50.000
SJTPO
EC
CMAQ
$1.900
$1.900
$1.900
$1.900
$1.900
$1.900
$1.900
$1.900
$1.900
$1.900
$19.000
SectionIIIPage71
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
LocalCountyAid,DVRPC
DBNUM:X41C1
ThisprogramprovidesfundsallocatedtothecountieswithintheDVRPCMPOareafortransportationimprovementsundertheNJTransportation
TrustFundAct.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: LocalLead
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): X12(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:LocalAidtoCounties)
MPO
Phase
Fund
DVRPC
ERC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$15.955
$15.955
$15.955
$15.955
SectionIIIPage72
$15.955
$15.955
$15.955
$15.955
$15.955
$15.955
Total
$159.550
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
LocalCountyAid,NJTPA
DBNUM:X41B1
ThisprogramprovidesfundsallocatedtothecountieswithintheNJTPAMPOareafortransportationimprovementsundertheNJTransportation
TrustFundAct.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: LocalLead
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10A(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:LocalAidtoCounties)
MPO
Phase
Fund
NJTPA
ERC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$51.524
$51.524
$51.524
$51.524
SectionIIIPage73
$51.524
$51.524
$51.524
$51.524
$51.524
$51.524
Total
$515.240
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
LocalCountyAid,SJTPO
DBNUM:X41A1
ThisprogramprovidesfundsallocatedtothecountieswithintheSJTPOMPOareafortransportationimprovementsundertheNJTransportation
TrustFundAct.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: LocalLead
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10B(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:LocalAidtoCounties)
MPO
Phase
Fund
SJTPO
ERC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$11.271
$11.271
$11.271
$11.271
SectionIIIPage74
$11.271
$11.271
$11.271
$11.271
$11.271
$11.271
Total
$112.710
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
LocalMunicipalAid,DVRPC
DBNUM:X98C1
ThisprogramprovidesfundsallocatedtomunicipalitiesintheDVRPCareafortransportationimprovementsundertheNJTransportationTrustFund
Act.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: LocalLead
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): X12(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:LocalAidtoMunicipalities)
MPO
Phase
Fund
DVRPC
ERC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$14.234
$14.234
$14.234
$14.234
SectionIIIPage75
$14.234
$14.234
$14.234
$14.234
$14.234
$14.234
Total
$142.340
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
LocalMunicipalAid,NJTPA
DBNUM:X98B1
ThisprogramprovidesfundsallocatedtomunicipalitiesintheNJTPAareafortransportationimprovementsundertheNJTransportationTrustFund
Act.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: LocalLead
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10C(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:LocalAidtoMunicipalities)
MPO
Phase
Fund
NJTPA
ERC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$53.082
$53.082
$53.082
$53.082
SectionIIIPage76
$53.082
$53.082
$53.082
$53.082
$53.082
$53.082
Total
$530.820
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
LocalMunicipalAid,SJTPO
DBNUM:X98A1
ThisprogramprovidesfundsallocatedtomunicipalitiesintheSJTPOareafortransportationimprovementsundertheNJTransportationTrustFund
Act.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: LocalLead
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10B(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:LocalAidtoMunicipalities)
MPO
Phase
Fund
SJTPO
ERC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$6.434
$6.434
$6.434
$6.434
SectionIIIPage77
$6.434
$6.434
$6.434
$6.434
$6.434
$6.434
Total
$64.340
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
LocalMunicipalAid,UrbanAid
DBNUM:X98Z
ThisprogramprovidesfundsallocatedtoUrbanAidfortransportationimprovementsundertheNJTransportationTrustFundAct.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: LocalLead
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10C(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:LocalAidtoMunicipalities)
MPO
Phase
Fund
Statewide
ERC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$5.000
$5.000
$5.000
$5.000
SectionIIIPage78
$5.000
$5.000
$5.000
$5.000
$5.000
$5.000
Total
$50.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
LocalPreliminaryEngineering
DBNUM:N1202/UPC:123530
ThisprogramprovidesfundingforprojectsthathavegraduatedfromtheLocalCapitalProjectDeliveryProgramsLocalConceptDevelopmentPhase.
Theseprojectswillbefurtherdevelopedandrefinedtoalevelofdetailnecessarytosecuretheapprovaloftheenvironmentaldocument.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJTPA
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10A(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:RegPlngandProjectDevelopment)
MPO
Phase
Fund
NJTPA
ERC
STPNJ
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$2.000
$1.985
$1.400
$2.000
SectionIIIPage79
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
Total
$19.385
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
LocalProjectDevelopmentSupport
DBNUM:06326/UPC:063260
ThisprogramprovidesNJDOTprojectmanagementandenvironmentalsupporttolocalgovernments.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O1,O10A,X1(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:RegPlngandProjectDevelopment)
MPO
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
Phase
Fund
DVRPC
PLS
STPSTU
$0.700
$0.700
$0.700
$0.700
$0.700
$0.700
$0.700
$0.700
$0.700
$0.700
$7.000
NJTPA
PLS
STPNJ
$2.925
$2.925
$2.925
$2.925
$2.925
$2.925
$2.925
$2.925
$2.925
$2.925
$29.250
SJTPO
PLS
STPSJ
$0.275
$0.275
$0.275
$0.275
$0.275
$0.275
$0.275
$0.275
$0.275
$0.275
$2.750
SectionIIIPage80
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
LocalSafety/HighRiskRuralRoadsProgram
DBNUM:04314/UPC:043140
TheLocalSafetyProgramprovidesfundstocountiesandmunicipalitiesfortheimprovementofdangerousintersectionsandotherroad
improvements,focusingonpedestrianandvehicularsafetyimprovementsofcriticalneedthatcanbedeliveredinarelativelyshortperiodoftime,
generallylessthantwoyearsfromproblemidentificationtocompletionofconstruction.Thisprogramalsoincludesdesignassistanceofferedto
countiesandmunicipalitiesfortheLSPprojects.Dependinguponthepreviousyearcrashhistory,thisprogrammayencompasscertainsetaside
fundingperyearforHighRiskRuralRoads,forsafetycountermeasuresonruralmajororminorroads,oronrurallocalroads.NJDOTdesignatesas
AdvanceConstructionallprojectsfundedfromthisprogram.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: LocalLead
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S3,S6(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(LocalSystemSupport:LocalSafetyImprovements)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
ERC
HSIP
$3.000
$3.000
$3.000
$3.000
$3.000
$4.000
$4.000
$4.000
$4.000
$4.000
$35.000
NJTPA
ERC
HSIP
$15.000
$15.000
$15.000
$15.000
$15.000
$18.000
$18.000
$18.000
$18.000
$18.000
$165.000
SJTPO
ERC
HSIP
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
$20.000
SectionIIIPage81
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Maintenance&FleetManagementSystem
DBNUM:X196
ThisprogramprovidesforthecontinuedoperationandsystemupgradesoftheMaintenance&FleetManagementSystems.Thesesystemsprovide
enhanceddataaccumulationandcostmanagementdisseminationcapabilitiesformaintenanceoperationsandarequiredcompatibledatasourcefor
relatedsystemsthatarerequiredforfederalfundingjustification(PavementandBridgeManagementSystems).Alsoincludedwillbethepurchaseof
equipmentfortheNJDOTfleetandfundingformonthlyairtimefees.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10C(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayCapitalMaintenance)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.750
$2.000
$2.000
$1.000
SectionIIIPage82
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
Total
$11.750
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
MaritimeTransportationSystem
DBNUM:01309/UPC:013090
ThisprogramprovidesfundingtosupportNewJersey’sMaritimeIndustryandMarineTransportationSystem.Thesystemincludes;navigable
channels,theStateChannelDredgingProgramanddredgedmaterialmanagementtechnologies,marineenvironmentenhancements,berthand
terminalstructures,relatedintermodaltransportationfacilitiesandcorridors,shipping,receivingandcargomovementtrackingsystems,GPS/GIS,
VesselTrafficandPortInformationSystems,PhysicalOceanographicRealTimeSystems,science,technologyandeducationprograms.Navigation
aides,boatbuildingtechnologies,oceanhabitattrackingsystemsandothernewtechnologiesinteracttocreateaseamlesssystemlinkingallaspectsof
themaritimeindustryintoasingletransportationmatrix.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10A(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(MultimodalPrograms:Maritime)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
$1.000
$1.000
$1.000
SectionIIIPage83
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
Total
$10.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
MarketStreet/EssexStreet/RochelleAvenue
DBNUM:98546/UPC:985460
Fundingisprovidedforascopingstudytosecurerecommendedimprovementstotheintersectionandbridgeatthislocation.
Thefollowingspecialfederalappropriationswereallocatedtothisproject.TEA21/Q92,ID#NJ023,$3,844,123
Totalconstructionfundingneededisexpectedtobe$9,000,000.Thefollowingspecialfederalappropriationshavebeenallocatedforthisproject
$3,844,123(NJ023).
COUNTY: Bergen
LEGISLATIVEDISTRICT: 38
MUNICIPALITY: MaywoodBoro,LodiBoro
SPONSOR: BergenCounty
MILEPOST(S): N/A
STRUCTURENO.: Bergen31A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10A(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(LocalSystemSupport:LocalSafetyImprovements)
MPO
Phase
Fund
NJTPA
PE
DEMO
NJTPA
DES
DEMO
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.602
Total
$0.602
$1.000
$1.000
NJTPA
ROW
DEMO
NJTPA
CON
DEMO
$0.200
$1.640
$1.640
NJTPA
CON
STPNJ
$7.360
$7.360
SectionIIIPage84
$0.200
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
MercerCountyRoadwaySafetyImprovements
DBNUM:D0412/UPC:048075
Thisprogramwillprovidefortheinstallationofimprovedsafetyitemsincludingreflectivepavementmarkings(includingbothstripingandraised
reflectivemarkers),reflectiveobjectmarkers,reflectiveroadwaydelineators,guiderail,andothertreatmentsthatimprovetheoverallsafetyand
visibilityofvariousroadwaysinthecounty.
COUNTY: Mercer
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: MercerCounty
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S11(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(LocalSystemSupport:LocalSafetyImprovements)
MPO
Phase
Fund
DVRPC
CON
STPSTU
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.800
SectionIIIPage85
$0.800
$0.800
Total
$2.400
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
MetropolitanPlanning
DBNUM:X30A
NJDOTsupportsthefederallymandatedMetropolitanPlanningOrganizationtransportationplanningprocess.NewJerseyMetropolitanPlanning
Organizationscarryouta3Ctransportationplanningprocesswherebyplanningactivitiesareconductedonacontinuousbasiswhilealsoproviding
aforumforcooperativedecisionmakingamongresponsiblestateandlocalofficials,publicandprivatetransitoperatorsandthegeneralpublic.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: MPO
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10A,O10C,X1(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:RegPlngandProjectDevelopment)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
PLS
PL
$2.244
$2.244
$2.244
$2.244
$2.244
$2.244
$2.244
$2.244
$2.244
$2.244
$22.440
DVRPC
PLS
PLFTA
$0.773
$0.773
$0.773
$0.773
$0.773
$0.773
$0.773
$0.773
$0.773
$0.773
$7.730
DVRPC
PLS
STPSTU
$1.578
$1.531
$1.572
$1.572
$1.572
$1.572
$1.572
$1.572
$1.572
$1.572
$15.682
NJTPA
PLS
PL
$8.780
$8.780
$8.780
$8.780
$8.780
$8.780
$8.780
$8.780
$8.780
$8.780
$87.800
NJTPA
PLS
PLFTA
$2.691
$2.691
$2.691
$2.691
$2.691
$2.691
$2.691
$2.691
$2.691
$2.691
$26.910
NJTPA
PLS
STPNJ
$5.000
$7.200
$5.000
$7.200
$5.000
$7.200
$5.000
$7.200
$5.000
$7.200
$61.000
SJTPO
PLS
PL
$0.937
$0.937
$0.937
$0.937
$0.937
$0.937
$0.937
$0.937
$0.937
$0.937
$9.370
SJTPO
PLS
PLFTA
$0.430
$0.430
$0.430
$0.430
$0.430
$0.430
$0.430
$0.430
$0.430
$0.430
$4.300
SJTPO
PLS
STPSJ
$0.265
$0.265
$0.265
$0.265
$0.265
$0.265
$0.265
$0.265
$0.265
$0.265
$2.650
SectionIIIPage86
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
MiddlesexCountyRoadwayImprovements
DBNUM:908A/UPC:154400
ThisprogramwillprovidefundingforasupplementalagreementbetweenNJDOTandMiddlesexCountyforthefollowingtransportation
improvements:ProspectPlainsRoad,inMonroeTownship;RiversideDriveatMacLaneandatClearviewRoad,inWoodbridgeTownship;theRamp
fromMiddlesexCountyRoute514toClearviewRoad,inEdisonTownship;andreplacementoftheParkAvenueBridge,inSouthPlainfield.Funding
appropriatedinpreviouscapitalprogramsunder“RaritanCenterRoadwayImprovements”and“WoodbridgeCenter,CR514”willbeeligibleforuse
ontheprojectsoutlinedinthisprogramitem.
Totalconstructionfundingneededisexpectedtobe$100,000.
COUNTY: Middlesex
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: MiddlesexCounty
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10,S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:LocalRoadwayImprovements)
MPO
Phase
Fund
NJTPA
ERC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.100
Total
$0.100
SectionIIIPage87
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
MinorityandWomenWorkforceTrainingSetAside
DBNUM:07332/UPC:073320
StatelawrequiresthatanallocationofonehalfofonepercentforStateconstructioncontractsover$1millionissetasideforminorityandwomen
outreachandtrainingpurposes.Trainingandoutreachactivitieswillhaveparticularemphasisoncontractorswhodonotmeetworkforcegoals.This
requirementisdelineatedunderNJAC17:277.4.NJDOTiscommittingtothetrainingrequirementonaprogrammaticlevelratherthanonaproject
byprojectlevel.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10B(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(CapitalProgramDelivery:ContractorSupport)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
$1.000
$1.000
$1.000
SectionIIIPage88
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
Total
$10.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
MobilityandSystemsEngineeringProgram
DBNUM:13306/UPC:133060
ThiscombinedprogramseekstoimprovemobilityinclusiveofbutnotlimitedtoIntelligentTransportationSystems(ITS),TrafficSignalTimingand
Optimization,monitoringWorkzoneMobilityandAdvancedTravelerInformationSystem(ATIS)programs.Acombinedprogramwillallowfor
improved,cohesiveandsustainableplanning,design,procurementanddeploymentofoperationsstrategiessuchasITStechnologiesandATIS.
Federalmandatessuchas:(a)followingandmaintainingITSArchitecture,(b)preparingTMPsformajorconstructionprojects,(c)motorists
informationsharing(511),(d)EveryDayCountsinitiatives,(e)incorporationofadaptivesignalsystems,(f)hardshoulderuse,(g)performance
measuresand,(h)maintenance/upgrade/enhancementofexistingITSinfrastructureandhardwarearecoveredunderthisprogram.Thisprogramalso
includesreviewanddevelopmentofnewtechnologyandthepossibleapplication,design,procurement,testinganddeploymentofsuchtechnologies.
ThedevelopmentofcontractdocumentsandengineeringplansforvariousprojectsandITScontractsisalsoincluded.Thisprogramincludes
technicalandengineeringsupportneededfortheTrafficOperationsCenters;development,enhancementandmaintenanceoftheexistingITS
infrastructure,ATISassociateddatabase;andfundingforMultimodalTransportationCoordinationandInformationRelatedServices.Thisprogram
willsupportNJDOTstrafficsignaloptimizationeffortsandtheArterialManagementCenter.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O7,O10B,S7(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:IntelligentTransportationSystems)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
MPO
Phase
Fund
Statewide
EC
NHPP
Statewide
EC
STATE
$1.700
$1.700
$1.700
$1.700
$1.700
$1.700
$1.700
$1.700
Statewide
EC
STP
$4.000
$4.000
$4.000
$4.000
$4.000
$4.000
$4.000
$4.000
$10.000
$10.000
$10.000
$10.000
SectionIIIPage89
$10.000
$10.000
$10.000
$10.000
$10.000
Total
$10.000
$100.000
$1.700
$1.700
$17.000
$4.000
$4.000
$40.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
MonmouthCountyBridgesW7,W8,W9overGlimmerGlassandDebbiesCreek
DBNUM:NS9306/UPC:950607
Thisprojectiscomprisedoftherehabilitationorreplacementofthreeexistingdeficientbridges,whichcarryBrielleRoadoverGlimmerGlassCreek
andGreenAvenueoverDebbiesCreek.Duetoitsthreecomponentperpendicularconfiguration,theprojectsiteislocallyknownasThreeBridges.
Allthreestructures,whethermovableorfixed,willberehabilitatedorreplacedinkindwithbridgesmeetingcurrentdesignstandardsandthus
improveroadwaygeometrics.
Totalconstructionfundingneededisexpectedtobe$30,000,000.Thefollowingspecialfederalappropriationshavebeenallocatedforthisproject
$2,403,540(NJ157).
COUNTY: Monmouth
LEGISLATIVEDISTRICT: 30
MUNICIPALITY: BrielleBoro,ManasquanBoro
SPONSOR: MonmouthCounty
MILEPOST(S): N/A
STRUCTURENO.: 13000W7,13000W8,13000W9
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:LocalBridges)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
MPO
Phase
Fund
NJTPA
DES
DEMO
$2.160
NJTPA
DES
STPNJ
$1.000
NJTPA
CON
STPNJ
Total
$2.160
$1.000
$30.000
SectionIIIPage90
$30.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
MotorVehicleCrashRecordProcessing
DBNUM:X233
ThisprogramprovidestheinhouseCrashRecordsunitwithupgradedequipmentandnewmethodology.Thecomprehensivecrashrecorddatabase
willincludedriver/crashcorrelation,crashlocation,datafordriverupdates,anddatabasecleaning(correction)process.Dataentry,scanningand
imagingwillbeperformedbyaprivatecontractor.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,S12(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:SafetyManagement)
MPO
Phase
Fund
Statewide
EC
HSIP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$2.000
$2.000
$2.000
$2.000
SectionIIIPage91
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
Total
$20.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
NewJerseyScenicBywaysProgram
DBNUM:X200C
ThisprogramwillassistintheadvancementoftheNJScenicBywaysProgram,thedevelopment,designationandimplementationneededforan
organization,grouporcommunitytobecomeastateornationalscenicbyway,andthemaintenanceandenhancementofthescenic,recreational,
archaeological,natural,culturalandhistoricintrinsicqualitiesassociatedwiththedesignatedbyways.Fundingwillbeutilizedforplanning,design
anddevelopmentofthestateprogramandforplanning,design,development,marketing,andimplementationofthestatebywayswithinthestate
program.Planning,designanddevelopmentofthestateprogramincludesbutisnotlimitedto:researchleadingtothedevelopmentofthemesfor
bywaysonastatewidebasis;technicalassistancetospecificallyprovideawarenessandeducationaboutthemanagement,operationanddevelopment
ofthescenicbywayprogram,activitiesassociatedwithidentifyingandplanningtouristamenitiesonscenicbywaysonastatewidebasis,activities
associatedwithassessingtheeconomicimpactsofanindividualbywayorastatewideprogramofbyways.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O4(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:Landscape)
MPO
Phase
Fund
Statewide
ERC
TAP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.500
$0.500
$0.500
$0.500
SectionIIIPage92
$0.500
$0.500
$0.500
$0.500
$0.500
$0.500
Total
$5.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
NewProvidenceDowntownStreetscape
DBNUM:09341/UPC:093410
TheDowntownImprovementProjectPhase2willbeexecutedatmultiplelocationsalongPassaicStreet,SouthStreetandSpringfieldAvenueinorder
toimprovepedestriansafety.Theworkincludesinstallationofflashinglightsintheroadways,additionalsignage,newcurbing,concretesidewalk,
pavers,drivewaymodification,drainagemodifications,lightingfoundations,lightsandpoles,banners,trees,landscapingandinstallationofrelated
siteappurtenances.
Totalconstructionfundingneededisexpectedtobe$245,000.Thefollowingspecialfederalappropriationshavebeenallocatedforthisproject
$245,000(NJ287).
COUNTY: Union
LEGISLATIVEDISTRICT: 21
MUNICIPALITY: NewProvidenceBoro
SPONSOR: NewProvidence
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): AQ2,O5(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(LocalSystemSupport:TransportationEnhancements)
MPO
Phase
Fund
NJTPA
CON
DEMO
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.245
Total
$0.245
SectionIIIPage93
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
NJTPA,FutureProjects
DBNUM:N063/UPC:058027
Thisprogramprovidesfundingforunanticipatedprojectneedsassociatedwiththedesign,rightofWayorconstructionofNJTPAselectedlocal
projects.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJTPA
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10C(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:RegPlngandProjectDevelopment)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
MPO
Phase
Fund
NJTPA
ERC
STATE
$70.500
$70.500
$70.500
NJTPA
ERC
STPNJ
$6.425
$0.240
$0.240
Total
$211.500
$0.000
SectionIIIPage94
$45.490
$75.725
$57.225
$75.725
$77.925
$75.725
$414.720
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
NorthPlainfieldDowntownStreetscapeandPedestrianImprovements(FinalPhase)
DBNUM:N1125/UPC:118032
TheprojectwillextendthecurrentstreetscapenorthonSomersetStreet.Theimprovementswillincludetheconstructionofconcretecurbing,ADA
rampsandcoloredstampedsidewalks,theinstallationofsomebenchesandstreettrees.
Thisprojectisfundedthroughthefollowingspecialappropriations:FY2010AppropriationsAct$300,000(ID#NJ295).
Totalconstructionfundingneededisexpectedtobe$300,000.Thefollowingspecialfederalappropriationshavebeenallocatedforthisproject
$299,949(NJ295).
COUNTY: Somerset
LEGISLATIVEDISTRICT: 22
MUNICIPALITY: NorthPlainfieldBoro
SPONSOR: SomersetCounty
MILEPOST(S): 9.519.57
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O5(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(MultimodalPrograms:Bicycle/Pedestrian)
MPO
Phase
Fund
NJTPA
ERC
DEMO
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.300
Total
$0.300
SectionIIIPage95
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
NYSusquehannaandWesternRailLineBicycle/PedestrianPath
DBNUM:NS9803/UPC:058018
The4.8mileNewYork,Susquehanna,andWesternRailway(NYS&W)BicycleandPedestrianPathrunsalongtheNYS&WRightofWay(ROW)from
RiverDrive,PequannockTownship(MorrisCounty)totheMountainViewrailstationinWayneTownship(PassaicCounty).
Totalconstructionfundingneededisexpectedtobe$7,000,000.
COUNTY: Morris,Passaic
LEGISLATIVEDISTRICT: 40
MUNICIPALITY: PequannockTwp,WayneTwp
SPONSOR: MorrisCounty
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): AQ2(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:Bicycle/PedestrianSafety)
MPO
Phase
Fund
NJTPA
CON
STPNJ
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$7.000
SectionIIIPage96
Total
$7.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
OakTreeRoadBridge,CR604
DBNUM:99316/UPC:993160
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethestructurallydeficientandfunctionallyobsoletebridgeoverConrailLehigh
ValleyRR,builtin1931.Thebridgewillbewidenedtoaccommodateincreasedtrafficvolumeandtomeetwiderapproachroadwaywidth.Thebridge
actsasamajorlinkbetweenSouthPlainfieldBoroughandEdisonandWoodbridgeTownships.
Totalconstructionfundingneededisexpectedtobe$11,850,000.
COUNTY: Middlesex
LEGISLATIVEDISTRICT: 18
MUNICIPALITY: EdisonTwp
SPONSOR: NJDOT
MILEPOST(S): 0.45
STRUCTURENO.: 1253164
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:RailroadOverheadBridges)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.750
$0.750
$11.850
SectionIIIPage97
Total
$11.850
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
OrphanBridgeReconstruction
DBNUM:99372/UPC:993720
Thisprogramprovidesfortheengineeringandconstructionoforphanbridges.Thesebridgeswillbedesignedutilizinginhouseandtaskorder
designers.Thebridgeswillbereconstructedintheexistingfootprint,withtheabutmentsbeingrepairedandthesuperstructuresbeingreplacedwith
prefabricated/precastsystemswheneverpossible.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.500
$3.000
$3.000
$3.000
SectionIIIPage98
$3.000
$3.000
$3.000
$3.000
$3.000
$3.000
Total
$28.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
OzoneActionPrograminNewJersey
DBNUM:D0407/UPC:048014
Throughuseofpublicserviceannouncements,promotionalitemsandevents,OzoneActionstrivestoimprovetheregionsairqualitybyencouraging
theuseofmobilityalternativesthatwillreducecongestion,warningindividualsinadvanceofOzoneActionDays,andpubliceducationaboutozone
andactionsthatwillreducecontributionstoregionalemissions.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: DVRPC
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): A1(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:DemandManagement)
MPO
Phase
Fund
DVRPC
EC
CMAQ
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.040
$0.040
$0.040
$0.040
SectionIIIPage99
$0.040
$0.040
$0.040
$0.040
$0.040
$0.040
Total
$0.400
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
PANY&NJNJDOTProjectProgram
DBNUM:11407/UPC:114070
Underthisprogram,thePortAuthoritywillprovidefundingsupportforimprovementstofourNJDOTfacilities:Route7,HackensackRiver
(Wittpenn)Bridge,Route139(HobokenandConrailViaducts),Route1&9TExtension,andRoute1&9PulaskiSkyway.Thisprogramwillprovidea
totalof$1.8billionfromFY2012throughFY2016forthesefourprojects.
TheRoute7WittpennBridgewillbereplacedwithanewverticalliftbridge.Thetotalprojectcostisestimatedat$650to$700million.Theprojectis
locatedinKearnyandJerseyCity,HudsonCounty.
TheRoute139Contract3projectwillrehabilitatetheHobokenViaduct,aswellasreplacethedeckandrehabilitatethesuperstructureoftheConrail
Viaduct.Thetotalprojectcostisestimatedat$180to$200million.TheprojectislocatedinJerseyCity,HudsonCounty.
TheRoute1&9TExtensionproject,willprovideanewroadwayparalleltoRoute1&9alongtherailroadrightofwayinJerseyCity.Itwillprovide
intermodalconnectionstotherailyardsanddiverttrucksofftheTonnelleCircleandRoute1&9,helpingtoeasecongestionandfacilitatinggoods
movementthroughouttheregion.Thetotalprojectcostisestimatedat$70to$80million.TheprojectislocatedinJerseyCity,HudsonCounty.
TheRoute1&9PulaskiSkywayprojectwillrehabilitatethe3.5milelongstructurethatcarriesRoute1&9overtheHackensackandPassaicRivers,the
NewJerseyTurnpike,severalrailroadsandindustrialfacilities.Thetotalprojectcostisestimatedat$1.2to$1.5billion.TheprojectislocatedinJersey
City,Kearny,andNewarkinHudsonandEssexCounties.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$2,200,000,000.
COUNTY: Hudson,Essex
LEGISLATIVEDISTRICT: 31,33,32,29
MUNICIPALITY: JerseyCity,NewarkCity,KearnyTown
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: 0909150,0704150,0901150,0904151
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): 2020M(NonExempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
ERC
OTHER
NJTPA
ERC
PANY&NJ
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$150.000 $150.000 $100.000
$353.000
Total
$400.000
$353.000
SectionIIIPage100
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
ParkandRide/TransportationDemandManagementProgram
DBNUM:X28B
ThisprogramsupportsTDMoptionsforcarpooling,vanpooling,andtransitbyprovidingfundingforleasesforparkandridesinareaswithhigh
demandareasthroughoutthestate.Thedepartmentcontinuestosupportfundingforapproximately15leasedparkandridesstatewidetoassistwith
reducingairpollution,congestionandimproveairquality.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): A1,O10C(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:DemandManagement)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
$1.000
$1.000
$1.000
SectionIIIPage101
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
Total
$10.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
PavementPreservation
DBNUM:X51
ThisprogramwillallowNJDOTtoaccomplisheligiblefederalpavementpreservationactivitiesonNewJerseysInterstatehighwaysystemandwill
alsoallowforpavementpreservationonallotherstatemaintainedroads,whichhelptokeepNewJerseyshighwaysysteminastateofgoodrepair.
Withtimelypreservation,theNJDOTcanprovidethetravelingpublicwithimprovedsafetyandmobility,reducedcongestionandsmoother,longer
lastingpavements.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayCapitalMaintenance)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
Statewide
EC
NHPP
$6.000
$6.000
$6.000
$6.000
$6.000
$6.000
$6.000
$6.000
$6.000
$6.000
$60.000
Statewide
EC
STP
$4.000
$4.000
$4.000
$4.000
$4.000
$4.000
$4.000
$4.000
$4.000
$4.000
$40.000
SectionIIIPage102
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
PedestrianSafetyImprovementDesignandConstruction
DBNUM:06403/UPC:064030
Thisisadedicatedfundinglineitemforpedestriansafetyprojectsinhighcrashcorridorsandneartransitfacilities.Thesefundsarebeingusedfor
pedestriansafetyenhancementsatintersections,sidewalkinstallation,andtrafficcalmingmeasures,newstateofthearttechnologiesforsafe
pedestriancrossings,signageandstriping.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): A2,AQ2(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:SafetyImprovements)
MPO
Phase
Fund
Statewide
ERC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.500
$1.500
$1.500
$1.500
SectionIIIPage103
$1.500
$1.500
$1.500
$1.500
$1.500
$1.500
Total
$15.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
PedestrianSafetyImprovementProgram
DBNUM:06401/UPC:064010
Thisisanapproachtoreducepedestriancrashesand/orfatalities.Eachlocation/segmentwouldbeidentifiedthroughcrashhistorydataand
estimatedratesofexposuretomotorvehicles/pedestrianconflicts.Eachlocation/segmentwouldbeexaminedbyNJDOT’SpedestrianSafetyImpact
TeamswhowillconductRoadSafetyAuditsandmakerecommendationsforimprovements.Thisincludestheimplementationofrecommendationsas
well.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): A2,O10B,S6(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:SafetyImprovements)
MPO
Phase
Fund
Statewide
ERC
HSIP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.000
$3.000
$3.000
$3.000
SectionIIIPage104
$3.000
$3.000
$3.000
$3.000
$3.000
$3.000
Total
$30.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
PerkintownRoad(CR644),BridgeoverRoute295
DBNUM:15316/UPC:153160
InitiatedbytheBridgeManagementSystem,thisprojectwillbeginastudytoreplacethebridgedeckandpossiblyraisethesuperstructure.Thebridge
isstructurallydeficientduetotheconditionofthedeck.Itisfunctionallyobsoleteduetosubstandardverticalclearance.Theexistingminimum
clearancedoesnotmeetthecurrentstandard.Thestudywillincludejackingandsupport,abutmentandpiermodification/reconstructionand
approachroadwayreconstruction.Guiderailupgradeswillbeincluded,aswell.
Totalconstructionfundingneededisexpectedtobe$6,050,000.
COUNTY: Salem
LEGISLATIVEDISTRICT: 3
MUNICIPALITY: OldsmanTwp
SPONSOR: NJDOT
MILEPOST(S): 6.54
STRUCTURENO.: 1712157
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
SJTPO
PE
STATE
SJTPO
DES
STATE
SJTPO
ROW
STATE
SJTPO
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.500
$0.500
$0.700
$0.700
$0.100
$0.100
$6.050
SectionIIIPage105
Total
$6.050
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
PhysicalPlant
DBNUM:X29
Thisprogramwillprovideformajorrepairs,rehabilitation,andreplacementoftheNJDOTphysicalplantfacilitieswhicharenotincompliancewith
fireandsafetystandards,donotmeetbuildingcodes,orwhicharefunctionallyobsoleteforsupportingcurrentmaintenance,construction,and
engineeringactivities.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10C(Exempt)
ASSETMANAGEMENTCATEGORY: OperatingandMaintenance(TransportationSupportFacilities:FacilitiesandEquipment)
MPO
Phase
Fund
Statewide
ERC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$10.000
$10.000
$10.000
$10.000
SectionIIIPage106
$10.000
$10.000
$10.000
$10.000
$10.000
$10.000
Total
$100.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
PlanningandResearch,FederalAid
DBNUM:X30
NJDOTwillcontinuetoaddressplanningandresearchneedsinacomprehensiveprogramofstudiesandproposaldevelopmentinordertomaximize
theuseoffinancialresourcesandstaff.Activitieswillincludedatacollection,intergovernmentalplanningcoordination,planningworkinsupportof
themanagementsystems,researchinitiativesandLocalTechnicalAssistanceProgram.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10B,X1(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CapitalProgramDelivery:PlanningProgramsandStudies)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
Statewide
PLS
LTAP
$0.140
$0.140
$0.140
$0.140
$0.140
$0.140
$0.140
$0.140
$0.140
$0.140
$1.400
Statewide
PLS
SPR
$18.960
$18.960
$18.960
$18.960
$18.960
$18.960
$18.960
$18.960
$18.960
$18.960
$189.600
Statewide
PLS
STP
$6.600
$6.600
$6.600
$6.600
$6.600
$6.600
$6.600
$6.600
$6.600
$6.600
$66.000
SectionIIIPage107
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
PlanningandResearch,State
DBNUM:X140
Thisprogramwillprovideforplanningactivitieswhichincludeneedsassessments,geometricdeficiencies,localaidassistance,congestion
management,travelmarketanalysis,formulationofanewstatewideplan,facilitating/implementingintermodalism,demographics,access
managementplans,transportationpolicy,equipment,modeling,cleanairinitiatives,datacollectionequipment,deploymentofnewtechnology
initiatives,andresearchinitiatives.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10B,X1(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CapitalProgramDelivery:PlanningProgramsandStudies)
MPO
Phase
Fund
Statewide
PLS
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
$1.000
$1.000
$1.000
SectionIIIPage108
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
Total
$10.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
PortNewarkContainerTerminal(PNCT)AccessImprovementandExpansionProject
DBNUM:N1501/UPC:154370
Thisprojectwilldemolishbothdryandrefrigeratedwarehousesandgatefacilities,thenpaveallareasandconstructnewgatesthatincludetruck
comfortandservicestationsatthePortofNewark.Itwillcombinemodernfacilitieswithnewtechnologiesandwillsignificantlyupdatethestorage
capacityofthePortNewarkContainerTerminalforcontainerizedgoods.Theprojectwillconsideroptionstoaccommodatefuturesealevelrise.This
projectwillbefundedwitha2014USDOTTransportationInvestmentGeneratingEconomicRecovery(TIGER)grantintheamountof$14.8M.
Totalconstructionfundingneededisexpectedtobe$48,997,000.Thefollowingspecialfederalappropriationshavebeenallocatedforthisproject().
COUNTY: Essex
LEGISLATIVEDISTRICT: 28,29
MUNICIPALITY: NewarkCity
SPONSOR: EssexCounty
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NA(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(MultimodalPrograms:GoodsMovement)
Fund
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
NJTPA
CON
DEMO
$14.800
$14.800
NJTPA
CON
OTHER
$34.197
$34.197
SectionIIIPage109
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Portway,FishHouseRoad/PennsylvaniaAvenue,CR659
DBNUM:97005B/UPC:028041
Thisprojectprovidesroadwayreconstruction.Theprojectincludestwo12ftlanes,anda12ftshoulder,EastboundandWestbound,along
PennsylvaniaAve/FishHouseRd.SidewalkswillbeprovidedalongtheEastboundsideofCentralAvetoapproximately250feetEastofthe
intersectionofthetworoadways.
Totalconstructionfundingneededisexpectedtobe$10,000,000.
COUNTY: Hudson
LEGISLATIVEDISTRICT: 32
MUNICIPALITY: KearnyTown
SPONSOR: NJDOT
MILEPOST(S): 0.51.4
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S4,S7(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(LocalSystemSupport:EconomicDevelopment)
MPO
Phase
Fund
NJTPA
DES
STP
NJTPA
ROW
STP
NJTPA
CON
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.500
Total
$1.500
$3.200
$3.200
$10.000
SectionIIIPage110
$10.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
PreApprenticeshipTrainingProgramforMinoritiesandWomen
DBNUM:X135
Thisprogramwillprovidefundingforapreapprenticeshipprogramtotrainminoritiesandwomentoqualifyforentryintounionapprenticeship
programsandemploymentonNJDOTconstructionprojects.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10C(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(CapitalProgramDelivery:ContractorSupport)
MPO
Phase
Fund
Statewide
EC
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.500
$0.500
$0.500
$0.500
SectionIIIPage111
$0.500
$0.500
$0.500
$0.500
$0.500
$0.500
Total
$5.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
PrincetonHightstownRoadImprovements,CR571
DBNUM:D0701/UPC:078036
TheprojectlimitsincludetheintersectionsofCR571withClarksvilleRoad(CR638)andWallaceCranburyRoad(CR615),andtheapproximately1
milesegmentconnectingthem.CR571isamajoreastwestcorridoratthenorthernedgeofMercerCountyandtheCentralJerseyTransportation
Forumhasendorsedtheimprovementconcept.Thisisaseveresafetyconcernregardingtheareawheretheroadwaydropsfromfourlanestotwo.
MercerCountyandWestWindsorTownshiphopetomakeMainStreetpedestrian,bicycle,andsiteaccessimprovements,includingsidewalks,
protectedturnlanesandnoadditionalthroughtravellanes.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$10,000,000.
COUNTY: Mercer
LEGISLATIVEDISTRICT: 15
MUNICIPALITY: WestWindsorTwp
SPONSOR: MercerCounty
MILEPOST(S): 40.3240.97
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S6(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(LocalSystemSupport:LocalSafetyImprovements)
MPO
Phase
Fund
DVRPC
CON
STPSTU
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$4.500
$5.500
SectionIIIPage112
Total
$10.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
ProgramImplementationCosts,NJDOT
DBNUM:X10
ThisprogramwillprovidefundingforsalariesandotheradministrativeexpenseswhichdirectlyrelatetodevelopinganddeliveringtheCapital
Program.Thisfundingisallocatedformultiyearandpreviouslyauthorizedprojectcosts.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10C(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(CapitalProgramDelivery:ProgramImplementationCosts)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$95.000
$95.000
$95.000
$95.000
SectionIIIPage113
$95.000
$95.000
$95.000
$95.000
$95.000
$95.000
Total
$950.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
ProjectDevelopment:ConceptDevelopmentandPreliminaryEngineering
DBNUM:10344/UPC:103440
ThisprogramwillprovidefundingforConceptDevelopmentandPreliminaryEngineeringworkonvariousidentifiedprojectsonthestate
transportationsystem.Functionstobeperformedinclude,butarenotlimitedto,datacollectionincludingtrafficcountsandreviewofasbuiltplans,
evaluationofexistingdeficiencies,evaluationofexistingsafetyconditions,environmentalscreenings,assessmentofrightofwayandaccessimpacts,
assessmentofenvironmentalimpacts,identificationofaPreliminaryPreferredAlternative,NationalEnvironmentalProtectionAgencyclassification,
estimates,technicalenvironmentalstudies,basemapping/surveying,utilityinvestigations,rightofwayresearchandestimates,drainage
investigations,geotechnicalinvestigations,engineeringinsupportoftheenvironmentaldocument,anapprovedenvironmentaldocument,cost
estimatesandcommunityoutreach/involvement.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10A(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(CapitalProgramDelivery:ProjectScopingandDesign)
MPO
Phase
Fund
Statewide
CD
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$5.000
$5.000
$5.000
$5.000
SectionIIIPage114
$5.000
$5.000
$5.000
$5.000
$5.000
$5.000
Total
$50.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
ProjectReportingSystem(PRS)Replacement
DBNUM:05341/UPC:053410
ThisprojectwillprovideacollaborativeenvironmentforalldepartmentstakeholderstoutilizeoneProjectReportingSystemtomanageprojectsfrom
starttofinish,thus,facilitatingaccesstoallpartiesandallowforeveryonetohaveinputintotheprocess.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10A(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(CapitalProgramDelivery:QualityAssurance)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.600
$0.350
$0.350
$0.350
SectionIIIPage115
$0.350
$0.350
$0.350
$0.350
$0.350
$0.350
Total
$3.750
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
RailReplacementonConrailsPortReadingSecondary(LibertyCorridor)
DBNUM:06318G/UPC:168000
Replace6.26milesofrailalongConrailsPortReadingSecondarybetweenBoundBrookandPortReading,NJ.Thisimprovementhelpsthesecondary
retainitstatusasaheavyhaulfreightmainlinethatcanaccommodatealltypesoftraffic.
Totalconstructionfundingneededisexpectedtobe$4,850,000.
COUNTY: Somerset
LEGISLATIVEDISTRICT: 16,23
MUNICIPALITY: ManvilleBoro,BoundBrookBoro
SPONSOR: CONRAIL
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NA(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(MultimodalPrograms:GoodsMovement)
MPO
Phase
Fund
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
NJTPA
ERC
DEMO
$1.500
$1.500
NJTPA
ERC
OTHER
$3.350
$3.350
SectionIIIPage116
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
RailHighwayGradeCrossingProgram,Federal
DBNUM:X35A1/UPC:800027
Thisprogramwillprovidefundingfortheeliminationofhazardsatrailhighwaygradecrossings,therehabilitationofgradecrossingsurfaces,andthe
installationofprotectivewarningdevicesforroadwaysbothonandoffthefederalaidsystem.Fundingwillalsobeprovidedforthetrafficcontrol
itemsrequiredduringtheconstructionworkandtheinstallationofadvancewarningsignsandpavementmarkingsatallhighwayrailgradecrossings.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S1,S8(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:SafetyImprovements)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
EC
RHC
$2.800
$2.800
$2.800
$2.800
$3.000
$3.000
$3.200
$3.200
$3.400
$3.400
$30.400
NJTPA
EC
RHC
$6.500
$6.500
$6.500
$6.500
$7.000
$7.500
$8.000
$8.500
$9.000
$9.500
$75.500
SJTPO
EC
RHC
$2.000
$2.000
$2.000
$2.000
$2.200
$2.200
$2.400
$2.400
$2.600
$2.600
$22.400
SectionIIIPage117
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
RailHighwayGradeCrossingProgram,State
DBNUM:X35A
Thisprogramwillprovidestatefundingfortheeliminationofhazardsatrailhighwaygradecrossingsbytheclosureofcrossingsorthe
upgrade/improvementofprotectivewarningdevicesforroadsthroughoutthestate.Thisfundingwillallowflexibilityinallocatingmoniesfor
emergencyrepairsaswellastotheareasinneedregardlessoftheirgeographiclocation(MPO).Thisprogramwillalsoallowgradecrossingclosures
withoutdrawingdownthefederalfundsusedforgradecrossingimprovements.Fundingwillalsobeprovidedforthedesignoftrafficdetours
requiredforthecrossingsurfacereconstructionprojects.
Thisprogramwillalsoprovidefundingforemergencyrepairstotheridingsurfaceofhighwayrailgradecrossingsidentifiedduringinspectionsor
fromcomplaintsreceived.TheserepairswillbeaccomplishedbyanNJDOTcontractorasprioritysituationsareidentified.Theserepairswillbe
limitedtosurfacerepairsthatdonotrequirerailroadinfrastructurework,orreconstructionofthecrossing.Thisprogramwillalsoincludethe
installationofroadwayrelateditems(signs,pavementmarkings)thathavebeenidentifiedasmissingorneedingreplacementorarerequired
(outstandingworkfrommunicipalitiesandcounties)tocloseoutfederallyfundedgradecrossingprojectsfrompreviousyears.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S1,S8(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:SafetyImprovements)
MPO
Phase
Fund
Statewide
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$4.600
$5.000
$5.200
$5.400
SectionIIIPage118
$5.600
$5.800
$6.000
$6.200
$6.200
$6.200
Total
$56.200
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
RecreationalTrailsProgram
DBNUM:99409/UPC:994090
NewJerseysRecreationalTrailsProgramprovidesgrantstopublicagenciesandnonprofitorganizationsforavarietyoftrailprojects.Theprogramis
administeredbytheNJDepartmentofEnvironmentalProtection,DivisionofParksandForestry.Undertheprogram,aminimumof30percentofthe
projectfundingmustbeprovidedformotorizedtrailprojects(ATVs,dirtbikes,snowmobiles),30percentfornonmotorized(hiking,biking,
horsebackriding),and40percentfordiverseuse,whichisanycombinationofmotorizedandnonmotorizedtrailusertypes.NewJerseyhas
establishedamaximumgrantawardof$25,000fornonmotorizedanddiverseprojects.Granteesmustmatch20percentofthetotalprojectcosts.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDEP
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): A1,AQ2(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(MultimodalPrograms:Bicycle/PedestrianMobility)
MPO
Phase
Fund
Statewide
ERC
RTP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.900
$0.900
$0.900
$0.900
SectionIIIPage119
$0.900
$0.900
$0.900
$0.900
$0.900
$0.900
Total
$9.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
RegionalActionProgram
DBNUM:X144
Thisisaprogramoflowcost,quickturnaroundcapitalimprovementstobeaccomplishedunderthemanagementoftheNJDOTOfficeofLandscape
ArchitectureandtheRegionalDirectorforRegionalOperationsineachoftheNJDOTregions.Alsoincludedisfundingforsmallscalelandscape
contractstominimizeadverseeffectsofahighwaywhereengineeringsolutionsareprohibitive.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10C,X9(Exempt)
ASSETMANAGEMENTCATEGORY: OperatingandMaintenance(RoadAssets:LandscapeO&M)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
$1.000
$1.000
$1.000
SectionIIIPage120
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
Total
$10.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
RestripingProgram&LineReflectivityManagementSystem
DBNUM:X03A
ThisprogramisadministeredbyNJDOTandwillprovidefortheapplicationoflonglifepavementmarkingsandraisedpavementmarkersonthe
statehighwaysystem.Inaddition,anewLineReflectivityManagementUnitwasformedwithinMaintenanceEngineeringandOperations,totake
reflectivityreadingsofpavementmarkingsinordertomoreefficientlydeveloptheannualstripingprogramforNJDOT.Allequipmentpurchaseswill
befundedbytheNJDOTequipmentlineitem.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10,S11(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:SafetyCapitalMaintenance)
MPO
Phase
Fund
Statewide
EC
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$14.000
$14.000
$14.000
$14.000
SectionIIIPage121
$14.000
$14.000
$14.000
$14.000
$14.000
$14.000
Total
$140.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
ResurfacingProgram
DBNUM:X03E
Thisisacomprehensiveprogramofprovidingrenewedridingsurfacestostatehighwaystoprolongthelifeofthepavementandprovideasmoother
rideforusersofthesystem.TheresurfacingprogramisakeycomponentofNJDOTsbroaderPavementManagementProgram,whichisaimedat
preservingandextendingthelifeofstatehighways.Individualhighwaysegmentsareselectedforresurfacingorothertreatmentsthroughthe
NJDOTspavementmanagementsystem.Theprogramconsistsprimarilyoftheresurfacingofhighwaysegments,butmayalsoincludeselectedrepair
activities,minorupgradessuchascurbing,applicationoflonglifepavementmarkingsandraisedpavementmarkersonthestatehighwaysystemand
acquisitionofessentialequipmentandmaterials.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$80.000
$80.000
$80.000
$80.000
SectionIIIPage122
$80.000
$80.000
$80.000
$80.000
$80.000
$80.000
Total
$800.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Resurfacing,Federal
DBNUM:99327A
Thisprogramprovidesforthedesignandconstructionofpavementresurfacingprojects.Thislineitemwillbeutilizedtoprovidepavement
recommendations,survey,aerialphotography,photogrammetry,basemappingandengineeringneededtopreparecontractdocumentstoadvertise
resurfacingprojectsaswellasprovideforcontractorservicestoconstructresurfacingprojects.ProjectlistswillbedevelopedbyusingthePavement
ManagementSystemandvisualinspectionoftheroadwaysegmentsinneedofrepair.Thislineitemalsofundspreliminaryengineeringforpavement
reconstructionprojects.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S1,S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
ERC
NHPP
$15.000
$15.000
$15.000
$15.000
$15.000
$30.000
$30.000
$30.000
$165.000
NJTPA
ERC
NHPP
$25.000
$50.000
$50.000
$50.000
$50.000
$70.000
$70.000
$70.000
$435.000
SJTPO
ERC
NHPP
$10.000
$10.000
$10.000
$10.000
$10.000
$15.000
$15.000
$15.000
$95.000
Statewide
ERC
NHPP
Statewide
ERC
STATE
$5.000
$5.000
$5.000
$5.000
$5.000
$5.000
$5.000
$8.000
$8.000
$8.000
$59.000
$30.000
$30.000
$30.000
$30.000
$30.000
$30.000
$30.000
$30.000
$240.000
SectionIIIPage123
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
RideECOMassMarketingEffortsNewJersey
DBNUM:D0406/UPC:048013
ThisprogramexpandsoutreachtothegeneralpublicaboutthebenefitsofusingtransitandtheTransitChekProgram,focusingonsouthernNew
Jerseymediaoutlets.Thisprogramseekstoreinforceriderandemployerdirectedadvertisingandalsotoreachbeyondthosetraditionalmarketsin
ordertoattractmoreriderstoareatransitservices.TransitChekisacommuterbenefitprogramofferedbyparticipatingemployersandprovides
vouchersthatcanbeusedtopurchasepasses,ticketsortokensfortransitfares.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: DVRPC
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): A1(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:DemandManagement)
MPO
Phase
Fund
DVRPC
EC
CMAQ
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.050
$0.050
$0.050
$0.050
SectionIIIPage124
$0.050
$0.050
$0.050
$0.050
$0.050
$0.050
Total
$0.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
RidgeRoad,andOrientWay,BridgesoverRt.3
DBNUM:799D/UPC:148120
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethetwobridges.TheRidgeRoadoverRoute3Bridgeisconsideredfunctionally
obsolete.TheOrientWayoverRoute3Bridgeisconsideredstructurallydeficient.
Totalconstructionfundingneededisexpectedtobe$33,150,000.
COUNTY: Bergen
LEGISLATIVEDISTRICT: 36
MUNICIPALITY: RutherfordBoro
SPONSOR: NJDOT
MILEPOST(S): 5.675.93
STRUCTURENO.: 0203152,0203153
FINANCIALPLANREQUIREMENT: Thisprojectispartofaprojectwithatotalcostbetween$100and$500millionprogrammedtoreceivefederal
financialassistanceandanannualfinancialplanisrequiredtobeprepared.
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
UTI
STATE
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
Total
$1.000
$33.150
SectionIIIPage125
$33.150
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
RightofWayDatabase/DocumentManagementSystem
DBNUM:05339/UPC:053390
ThisprogramprovidesfundingtoupdatetheexistingAccessdatabasewithasystemthatisapprovedandsupportedbytheDivisionofInformation
Technology.Thisnextgenerationsystemwillhavescheduling,documentproduction,managementcontrol,GISandextensivereporting
capabilities.AllinformationoftheproposedsystemhasbeenpresentedtoInformationTechnologyandhastheadvocacyofCPMssenior
managementaswellastheDepartmentsOfficeoftheInspectorGeneral.Occasionalupgradesmayberequired.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10A(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(CapitalProgramDelivery:RightofWayandUtility)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.100
$0.095
$0.090
$0.090
SectionIIIPage126
$0.090
$0.090
$0.095
$0.095
$0.095
$0.100
Total
$0.940
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
RightofWayFullServiceConsultantTermAgreements
DBNUM:05340/UPC:053400
ThisprogramwillallowfortheincreasedutilizationoffullserviceROWconsultantfirmstoaddresspeakworkloaddemandsintherightofway
componentofthecapitalprogramdeliveryprocess.
Duetostaffreduction,itmaybenecessarytoincreaseconsultantforce.Theagreementswillbeestablishedbasedoninitialbindingamountsof
$10,000,withthefundingofindividualtaskorderassignmentsreferencedtoprojectspecificstateandfederalrightofwayaccounts.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O3(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(CapitalProgramDelivery:RightofWayandUtility)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
Statewide
ROW
STATE
$0.050
$0.050
$0.050
$0.050
$0.050
$0.050
$0.050
$0.050
$0.100
$0.050
$0.550
Statewide
ROW
STP
$0.100
$0.100
$0.100
$0.100
$0.100
$0.100
$0.100
$0.100
$0.100
$0.100
$1.000
SectionIIIPage127
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
RIMISPhaseIIImplementation
DBNUM:01300/UPC:013000
PhaseIIinstallationandoperationsofRegionalIntegratedMultimodalInformationSharing(RIMIS),acomputermessage/digitalsystemtonotify
agenciesaboutincidentsorunusualconditionsthataffectthem.ThisprojectalsohelpstoextendRIMIStoincludeDVRPCcountyroadways.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: DVRPC
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S7(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:IntelligentTransportationSystems)
MPO
Phase
Fund
DVRPC
EC
STPSTU
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.234
$0.234
$0.221
$0.221
SectionIIIPage128
$0.221
$0.221
$0.221
$0.221
$0.221
$0.221
Total
$2.236
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
RiverRoadImprovements,CramerHill
DBNUM:D0902/UPC:098008
ThisprojectwillhelpimplementamultiphaseefforttoaddressthelongstandingissueofheavytrucktrafficalongRiverRoad/RiverAvenuethrough
CramerHillintheCityofCamden.ItwillremovetrucktrafficfromtheCramerHillneighborhood’scommercialandresidentialstreetstoimprovethe
qualityoflifeforresidentsandbusinesses,suchasreducingairandnoisepollutionandimprovingpublicsafety.Aseriesoftrafficcontrol,traffic
calming,andpedestrianmeasuresrecommendedbytheRiverRoadTruckTrafficManagementStudywillbeimplementedbetweentheintersections
ofRiverRoadandStateStreetinCamden,NewJerseytoRiverRoadandShermanAvenueinPennsauken,NewJersey.Measuresinclude:high
visibilitycrosswalks,truckroutesignage,signaltimingchangestoslowareatraffic,bulbouts,mediansandintersectiongeometricimprovements.
Totalconstructionfundingneededisexpectedtobe$3,975,000.Thefollowingspecialfederalappropriationshavebeenallocatedforthisproject
$4,005,900(NJ253);$1,002,341(NJ268).
COUNTY: Camden
LEGISLATIVEDISTRICT: 5
MUNICIPALITY: CamdenCity
SPONSOR: CamdenCity
MILEPOST(S):
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): A2(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(LocalSystemSupport:LocalMobilityImprovements)
MPO
Phase
Fund
DVRPC
ERC
DEMO
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.975
Total
$3.975
SectionIIIPage129
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
RiverbankParkBikeTrail
DBNUM:08440/UPC:084400
ThepurposeoftheprojectistoimprovetheareaoftheRiverbankParktrailalongPassaicAvenuefromBergenAvenuetotheBellevilleTurnpike.
Totalconstructionfundingneededisexpectedtobe$1,677,000.Thefollowingspecialfederalappropriationshavebeenallocatedforthisproject
$2,002,950(NJ169).
COUNTY: Hudson
LEGISLATIVEDISTRICT: 32
MUNICIPALITY: KearnyTown
SPONSOR: KearnyTown
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): AQ2(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(MultimodalPrograms:Bicycle/Pedestrian)
MPO
Phase
Fund
NJTPA
ERC
DEMO
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.677
Total
$1.677
SectionIIIPage130
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
RockfallMitigation
DBNUM:X152/UPC:068066
Thisprogramwillprovidefortheengineeringandconstructionofprojectstoreducethepotentialofrockfallontohighways,creatingsafetyproblems
whichcouldpotentiallycausepersonalinjuryorpropertydamage.ThisprogramwillalsobeutilizedtoupdateandmaintaintheRockfallHazard
MitigationSystem(RHMS),whichevaluatesallhighwayrockcutsandidentifiespotentialrockfallissues.Theseactivitieswillbeperformedutilizing
bothinhouseandconsultantengineeringforces.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O5,X13(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:RockfallMitigation)
MPO
Phase
Fund
Statewide
ERC
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$2.000
$1.000
$1.000
$1.000
SectionIIIPage131
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
Total
$11.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
RumsonRoadovertheShrewsburyRiver,CR520
DBNUM:NS9706/UPC:950628
BridgeS32carriesCR520,RumsonRoad,acrosstheShrewsburyRiverbetweentheBoroughsofRumsonandSeaBright.Thisbridgeservesasoneof
twoevacuationandemergencyroutesintimesoftidalfloodingandcoastalstorms.Theexistingstructureisinpoorcondition,withdeteriorationof
majorbridgecomponents.Possibleimprovementssuchasrehabilitationorreconstructionofthestructurewillbestudied.
Thisprojectismultiyearfunded.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$60,000,000.
COUNTY: Monmouth
LEGISLATIVEDISTRICT: 13
MUNICIPALITY: RumsonBoro,SeaBrightBoro
SPONSOR: MonmouthCounty
MILEPOST(S): 22.31
STRUCTURENO.: 1300S32
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10A(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:LocalBridges)
MPO
Phase
Fund
NJTPA
DES
STPNJ
NJTPA
CON
STPNJ
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$5.000
Total
$5.000
$45.725
SectionIIIPage132
$14.275
$60.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
SafeRoutestoSchoolProgram
DBNUM:99358
Thisprogramprovidesfundingforlocallyinitiatedpedestrianaccessandsafetyprojectstoprovidesafeaccesstoschools.
FundingisprovidedtothestatestoundertakeaSafeRoutestoSchoolsprogram.Tentothirtypercentofthemoneymustfundenforcement,education
andencourageprograms.Theremainingfundingmustfundprogramsleadingtotheconstructionofbicycleandpedestrianfacilitiesaswellasthe
salaryofafulltimeprogramcoordinator.NJDOTdesignatesasAdvanceConstructionallprojectsfundedfromthisprogram.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: LocalLead
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): A2,AQ2(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:Bicycle/PedestrianSafety)
MPO
Phase
Fund
Statewide
ERC
TAP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$5.587
$5.587
$5.587
$5.587
SectionIIIPage133
$5.587
$5.587
$5.587
$5.587
$5.587
$5.587
Total
$55.870
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
SafeStreetstoTransitProgram
DBNUM:06402/UPC:064020
Thisprogramidentifiesareasaroundtrainstationsorbusstopsandanalyzestheriskbasedoncrashhistoryandexposure.Oncetheareasare
identified,thisprogramdevelopsmultimodalimprovementplanstoaddresstheissues.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): A2,S6(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:Bicycle/PedestrianSafety)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
$1.000
$1.000
$1.000
SectionIIIPage134
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
Total
$10.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
SaltStorageFacilitiesStatewide
DBNUM:13307/UPC:133070
ConstructionofnewsaltbarnsatvariousmaintenanceyardsacrosstheState(1perRegion)toimprovesnowandiceremovalcapabilitiesand
responsetime.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,S2(Exempt)
ASSETMANAGEMENTCATEGORY: OperatingandMaintenance(TransportationSupportFacilities:FacilitiesandEquipment)
MPO
Phase
Fund
Statewide
ERC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.500
$2.500
$2.500
$1.500
SectionIIIPage135
Total
$10.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
SegmentImprovementProgram
DBNUM:15807/UPC:158070
Thisprogramwillprovidefortheidentificationandimplementationofsafetyimprovementsalongsegmentswhichshowcrashratesabovethe
statewideaverage.Thesafetyimprovementsproposedare;striping,signage,crosswalks,busshelters,handicapramps,bicycleaccommodations,
travellanemodifications,resurfacing,changesinaccommodating“U”turns,pedestrianrefugeislands,designingformaturedrivers,corner
modificationsandinnovativetechnologyi.e.pedestrian/bicycledetectors,etc.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.:
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): A2,S6(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:SafetyImprovements)
MPO
Phase
Fund
Statewide
ERC
HSIP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
$1.000
$1.000
$1.000
SectionIIIPage136
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
Total
$10.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
SignStructureInspectionProgram
DBNUM:X239/UPC:800008
Fundingisbeingprovidedfortheinspectionofoverheadandcantileversignstructuresonstateroadways.Thereareover1,700signstructures,
includingoverhead,cantileverandvariablemessagestructuresonstateroutes.
Thisprogramalsoprovidesfortheinspectionofapproximately200highmastlightpolestructuresonstateroadways.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O7(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeCapitalMaintenance)
MPO
Phase
Fund
Statewide
EC
STATE
Statewide
EC
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.800
$1.800
$1.800
$1.800
$1.800
$9.000
$2.000
SectionIIIPage137
Total
$2.000
$2.000
$2.000
$2.000
$10.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
SignStructureRehabilitation/ReplacementProgram
DBNUM:X239A
ThisprogramfundstherehabilitationandreplacementofexistingVMS(variablemessagesigns),overheadandcantileversignstructureslocatedon
statehighways.Thisprogramwillalsoprovidefundingforrecommendations,survey,aerialphotography,photogrammetry,basemappingand
engineering.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O6,O7(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeCapitalMaintenance)
MPO
Phase
Fund
Statewide
ERC
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.000
$2.000
$2.000
$2.000
SectionIIIPage138
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
Total
$21.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
SignStructureReplacementContract20131
DBNUM:13347/UPC:133470
InitiatedbytheBridgeManagementSystem,thisprojectwillincluderemovalofexistingsignstructuresandreplacementwithnewsignstructuresthat
meetallcurrentstandards.
Totalconstructionfundingneededisexpectedtobe$7,200,000.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: StructuralEvaluationandBridgeManagement
Bureau
MILEPOST(S): N/A
STRUCTURENO.: Various
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O6,O7(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeCapitalMaintenance)
MPO
Phase
Fund
Statewide
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$7.200
SectionIIIPage139
Total
$7.200
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
SignStructureReplacementContract20132
DBNUM:13348/UPC:133480
InitiatedbytheBridgeManagementSystem,thisprojectwillincluderemovalofexistingsignstructuresandreplacementwithnewsignstructuresthat
meetallcurrentstandards.
Totalconstructionfundingneededisexpectedtobe$8,300,000.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: StructuralEvaluationandBridgeManagement
Bureau
MILEPOST(S): N/A
STRUCTURENO.: Various
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O6,O7(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeCapitalMaintenance)
MPO
Phase
Fund
Statewide
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$8.300
SectionIIIPage140
Total
$8.300
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
SignStructureReplacementContract20151
DBNUM:14402/UPC:144020
InitiatedbytheBridgeManagementSystem,thisprojectwillincluderemovalofexistingsignstructuresandreplacementwithnewsignstructuresthat
meetallcurrentstandards.
Totalconstructionfundingneededisexpectedtobe$11,200,000.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O6,O7(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeCapitalMaintenance)
MPO
Phase
Fund
Statewide
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$11.200
SectionIIIPage141
Total
$11.200
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
SignStructureReplacementContract20162
DBNUM:15334/UPC:153340
InitiatedbytheBridgeManagementSystem,thisprojectwillincluderemovalofexistingsignstructuresandreplacementwithnewsignstructuresthat
meetallcurrentstandards.
Totalconstructionfundingneededisexpectedtobe$13,003,000.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: Various
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O6,O7(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeCapitalMaintenance)
MPO
Phase
Fund
Statewide
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$13.003
SectionIIIPage142
Total
$13.003
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
SignStructureReplacementContract20164
DBNUM:15336/UPC:153360
InitiatedbytheBridgeManagementSystem,thisprojectwillincluderemovalofexistingsignstructuresandreplacementwithnewsignstructuresthat
meetallcurrentstandards.
Totalconstructionfundingneededisexpectedtobe$10,450,000.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: Various
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O6,O7(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeCapitalMaintenance)
MPO
Phase
Fund
Statewide
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$10.450
SectionIIIPage143
Total
$10.450
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
SignStructureReplacementContract20165
DBNUM:15337/UPC:153370
InitiatedbytheBridgeManagementSystem,thisprojectwillincluderemovalofexistingsignstructuresandreplacementwithnewsignstructuresthat
meetallcurrentstandards.
Totalconstructionfundingneededisexpectedtobe$7,800,000.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: Various
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O6,O7(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeCapitalMaintenance)
MPO
Phase
Fund
Statewide
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$7.800
SectionIIIPage144
Total
$7.800
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
SignsProgram,Statewide
DBNUM:X39
Thisprogramprovidesfundingforthesystematicupgradeofstatehighwaysigns,includingrefurbishingofdeterioratedsigns,installationofnew
signs,andimprovementandupdatingofmessages.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O7(Exempt)
ASSETMANAGEMENTCATEGORY: OperatingandMaintenance(RoadAssets:SignsO&M)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
MPO
Phase
Fund
Statewide
EC
NHPP
$0.500
$0.500
$0.500
Statewide
EC
STATE
$1.500
$2.000
$2.000
Total
$1.500
$3.000
SectionIIIPage145
$3.000
$3.000
$3.000
$3.000
$3.000
$3.000
$26.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
SJTPO,FutureProjects
DBNUM:S044/UPC:058025
ThisprogramprovidesfundingforlocalprojectstobeselectedbytheSouthJerseyTransportationPlanningOrganization,thedesignatedMetropolitan
PlanningOrganizationforSalem,Cumberland,CapeMayandAtlanticcounties.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: SJTPO
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10A(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:RegPlngandProjectDevelopment)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
MPO
Phase
Fund
SJTPO
ERC
STATE
$7.500
$7.500
$7.500
SJTPO
ERC
STPSJ
$0.000
$0.000
$0.000
Total
$22.500
$8.382
SectionIIIPage146
$9.882
$9.882
$9.882
$9.882
$9.882
$9.882
$67.674
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
SolidandHazardousWasteCleanup,ReductionandDisposal
DBNUM:X160
Thisprogramwillprovideforthecleanup,reduction,anddisposalofsolidandhazardouswastematerialsfromstatehighwaysystempreservation
operationsandprivatedisposalsitesusedduringconstructionandsubsequentmaintenanceofthetransportationfacility.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NA,NRS(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CapitalProgramDelivery:OperationalSupport)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.330
$1.330
$1.330
$1.330
SectionIIIPage147
$1.330
$1.330
$1.330
$1.330
$1.330
$1.330
Total
$13.300
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
SouthInletTransportationImprovementProject
DBNUM:09361/UPC:093610
TheCasinoRedevelopmentAuthority(CRDA)hasidentifiedcertainroadimprovementstobeperformedinAtlanticCityoncertainfeederroads,that
willmaintain,operateandsupportAtlanticCityExpresswayProjectsoftheSouthJerseyTransportationAuthority,includingonMelroseAvenuein
betweenDelawareandConnecticutAvenues,onConnecticutAvenuefromMelrosetoOrientalAvenues,andonMassachusettsAvenueandvarious
otherintersectionandcapitalimprovementsinconnectionwiththe“SouthInletTransportationImprovementProject”.NJDOThasagreedtoprovide
onethirdoftheeligiblecostsupto$17M,plustheadditionalneededtofinancebonds.Approximately$1.5MTTFfundingwillbeprovidedtoSJTA
byNJDOTannuallyfor20yearsforthispurpose,exceptforthefirstyearwhichwillbe$1.7MTTF.SJTAwillissuedebtbasedonNJDOT’sfunding
guaranteeandprovidethefundingtoCRDA.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$24,996,000.
COUNTY: Atlantic
LEGISLATIVEDISTRICT: 2
MUNICIPALITY: AtlanticCity
SPONSOR: SJTA/CRDA
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): 2015(NonExempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(LocalSystemSupport:LocalMobilityImprovements)
MPO
Phase
Fund
SJTPO
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.504
$1.504
$1.504
$1.504
SectionIIIPage148
$1.504
$1.504
$1.504
$1.504
$1.504
$1.504
Total
$16.233
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
SouthPembertonRoad,CR530,Phase2
DBNUM:D9912A/UPC:123210
Thisprojectwillreconstructandprovidelaneandshoulderwideningapproximately2.7milesofCR530(S.PembertonRd.)fromHanoverSt.(CR616)
inPembertonBoroughtoUSRoute206inSouthamptonTownship.Thewideningoftheroadwayisnotanadditionalthroughlane,butwillincludea
5lanecrosssectionthatcontainsafourteenfootcontinuousturnlane,newsixfootshoulders,andfourtwelvefoottravellanes.Therearemany
driveways/accesspointsalongthecorridor,andthecontinuousturnlaneistoprovideasafeareatogetoutofthemainflowoftrafficandreduce
collisionsduringturnsoffoftheroadway.Overthelasttenyearstherehavebeentwelvefatalitiesonthisstretchofroadway.Crashdataoverthelast
fiveyears(20062010)documents348crashesinthissegment,including94injurycrashes.Theroadwaysegmentisaheavilytraveledcorridordueto
thefactthatitisacontinuationofStateHighwayRoute38.Route38endsatRoute206(TheSouthPembertonRoadwesternmostlimit)andbecomes
CR530/SouthPembertonRoad,whichcarriesatrafficvolumeofover25,000AADT.Thisprojectprovidesfortheacquisitionofeasementsand/orfull
takingsofover90parcelsandprovidesfortheenvironmentalcleanupanddemolishingofallstructures.Thisprojectwillalsoincludetreeclearingto
accommodateroadwayandshoulderwidth.ThisprojectisabreakoutofSouthPembertonRoad,CR530,Phase1(DB#D9912).
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$27,000,000.
COUNTY: Burlington
LEGISLATIVEDISTRICT: 8
MUNICIPALITY: PembertonBoro,PembertonTwp,SouthamptonTwp
SPONSOR: BurlingtonCounty
MILEPOST(S): 0.02.68
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): 2020M(NonExempt)
ASSETMANAGEMENTCATEGORY: Safety(LocalSystemSupport:LocalSafetyImprovements)
MPO
Phase
Fund
DVRPC
CON
STPSTU
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$8.716
$6.435
SectionIIIPage149
Total
$15.151
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
St.GeorgesAvenueImprovements
DBNUM:08434/UPC:084340
ImprovementsforSt.GeorgesAvenuebetweenEastBaltimoreAve.onthesouthwestandChandlerAve.onthenortheast,inUnionCounty.
Thefollowingspecialfederalappropriationwasallocatedtothisproject:FY05SAFETEALU/HPP$400,000.Billline#301,ID#NJ124.
Totalconstructionfundingneededisexpectedtobe$360,000.Thefollowingspecialfederalappropriationshavebeenallocatedforthisproject
$400,590(NJ124).
COUNTY: Union
LEGISLATIVEDISTRICT: 22,20
MUNICIPALITY: LindenCity,RoselleBoro
SPONSOR: LindenCity/RoselleBoro.
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NR2(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:LocalRoadwayImprovements)
MPO
Phase
Fund
NJTPA
ERC
DEMO
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.360
Total
$0.360
SectionIIIPage150
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
StatePoliceEnforcementandSafetyServices
DBNUM:X150
ThisprogramprovidesreimbursementforStatePoliceservicesforenforcementandtrafficcontrolinconstructionworkzones.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,S6(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(CapitalProgramDelivery:Construction)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$4.000
$4.000
$4.000
$4.000
SectionIIIPage151
$4.000
$4.000
$4.000
$4.000
$4.000
$4.000
Total
$40.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
StatewideTrafficOperationsandSupportProgram
DBNUM:13308/UPC:133080
ThiscomprehensiveStatewideTrafficOperationsandsupportstrategiesprogramfocusesonreducingnonrecurringdelaysduetoincidents,work
zones,weatheremergencies,poorsignaltimings,specialevents,etc.TheprogramincludesaStatewideTrafficManagementCenter(STMC),aTraffic
OperationsCenterSouth(TOCS),aSafetyServicePatrol(SSP),aNJDOT/NJSPTrafficIncidentManagement(TIM)UnitandaCentralDispatchUnit
(CDU).The24/7StatewideTrafficManagementCenter(STMC)servesthreeprimaryfunctions:(1)ItistheTrafficOperationsCenter(TOC)forthe
northernhalfofthestate,(2)Itprovidesforevening/weekend/holidayoperationscoveragefortheentirestateand(3)NJDOTiscolocatedwiththe
NewJerseyStatePoliceandtheNewJerseyTurnpikeAuthorityattheSTMCtoprovideforacoordinatedapproachtohandlingtrafficoperations
statewide.The16/5TrafficOperationsCenterSouth(TOCS)isresponsibleforcoverageforthesouthernhalfofthestateandmonitorstheRoute29
tunnel.TheSTMChandlescoverageforTOCSduringweeknights(after8:30pm)andonweekendsandholidays.TheSafetyServicePatrol(SSP)is
deployedoncongestedcorridorsstatewidetorapidlydetectandclearincidentsbyprovidingsafetyforfirstrespondersandmotorists.SSPalso
providesemergencyassistancetodisabledmotorists.The24/7CentralDispatchUnit(CDU)isNJDOTsEmergencyCallCenter.TheTrafficIncident
Management(TIM)programisaimedatreducingdelaysduetotrafficincidents.Itprovidesfor:(1)equipmentandtrainingforNJDOTsIncident
ManagementResponseTeam(IMRT);(2)trainingandoutreachforcountyandlocalemergencyrespondersonmethodstoreducetrafficdelayscaused
byincidents;(3)developing,printinganddistributingdiversionroutemanuals;(4)developingpartnershipsandoutreachwithlocalandstatelaw
enforcementorganizations;and(5)maintainingaStatePoliceTrafficIncidentManagementUnit.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O7,S6,S7(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:IntelligentTransportationSystems)
MPO
Phase
Fund
Statewide
EC
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$15.000
$15.000
$15.000
$15.000
SectionIIIPage152
$15.000
$15.000
$15.000
$15.000
$15.000
$15.000
Total
$150.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
TitleVIandNondiscriminationSupportingActivities
DBNUM:14300/UPC:143000
ThisisaStatefundedprogramthatwillsupporttheactivitiesrequiredtoensurenondiscriminationinthedeliveryoftheNJDOTCapitalProgramand
relatedprojects.Activitiesinclude,butarenotlimitedtoinformationaltrainingsessions,translationservicesandthedevelopmentofinformational
material(e.g.,pamphlets,brochures,trainingguidesandletters)disseminatedtothepublicandinlanguagesotherthanEnglishasnecessary.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10A(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(CapitalProgramDelivery:ProgramImplementationCosts)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.150
$0.150
$0.150
$0.150
SectionIIIPage153
$0.150
$0.150
$0.150
$0.150
$0.150
$0.150
Total
$1.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
TrafficMonitoringSystems
DBNUM:X66/UPC:990031
Thisprogramprovidesforthecollectionofessentialtrafficandroadwayinventorydataincludingtrafficcounts,vehicleclassifications,truckweights,
roadwayvideo,automatedmappingandvariousothergeographicalinformationsystemactivities.Includedinthisitemaretheconstruction,
reconstructionandrestorationofTrafficMonitoringSystems(TMS)andcontinuoustrafficcountinginstallations;andacquisitionofequipmentto
upgradeandtoreplaceequipmentwhichhasfailed.SiteselectionismadeinaccordancewithfederalrequirementsfortheTrafficMonitoringGuide
andtheNJDOTsTrafficMonitoringSystemimplementationplanthathasbeenapprovedbytheFederalHighwayAdministration.Fundingisusedfor
professionalservicestocarryouttheshorttermtrafficmonitoringprogram,updatesoftheStraightLineDiagrams;andlocalroadinventorydatabase
updates;forconstructionservicesforacontractortoreplaceinroadtrafficmonitoringsensors;tocontinueDataWarehouseMaintenanceactivities;
andtoinitiate/updateaRoadwayDigitalImagingProgram.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10B,X1(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CapitalProgramDelivery:PlanningProgramsandStudies)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
Statewide
PLS
NHPP
$12.910
$12.910
$12.910
$12.910
$12.910
$12.910
$12.910
$12.910
$12.910
$12.910
$129.100
Statewide
PLS
STATE
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$10.000
Statewide
EC
NHPP
$3.900
Statewide
EC
STATE
$4.900
$1.000
SectionIIIPage154
$6.500
$15.300
$1.200
$2.200
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
TrafficSignalReplacement
DBNUM:X47
Thisprogramprovidesforthepurchaseofmaterialsandinstallationofnewandupgradedtrafficsignalsstatewideandrelatedimprovementstothe
operationofsignals.Thisprogramwillprovideforthereplacementoftrafficsignalsonanannualbasisandassistregionaloperationsinthe
rehabilitationandmaintenanceofourhighwaylightingsystem.ItalsoincludesthereplacementofenergyefficientLEDindicatorsandinstallationof
generatorstoprovideauxiliarypowertoenabletrafficsignalizationduringtimesofextendedpoweroutages.Throughatrafficsignalmanagement
systemthatwillprovideaconditionratingofthesignalequipmentintegratedwithcrashdataandcongestionmanagementsystemdata,thisprogram
(tobedevelopedviaconsultantRFP,analyzingcorridorsegmentsandcreatingasafetyrankingbasedonMUTCDcompliance,pedestrianfacilities,
controllercapabilities,methodofdetection,accessibility,andotherfactors)willprioritizethesignalsforreplacementbasedontheabovedata.The
resultsoftheprioritylocationswillbetosystematicallyreplaceagingsignalequipment,optimizetheoperationofthesignal,andprovidemaximum
efficiencyoftheintersection.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S7,X1(Exempt)
ASSETMANAGEMENTCATEGORY: OperatingandMaintenance(SafetyManagement:SafetyCapitalMaintenanceO&M)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$9.000
$9.000
$9.000
$9.000
SectionIIIPage155
$9.000
$9.000
$9.000
$9.000
$9.000
$9.000
Total
$90.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
TrainingandEmployeeDevelopment
DBNUM:X244
Thisprogramprovidesfortheassessment,planning,developmentanddeliveryoftrainingandemployeedevelopmentprogramsinclusiveof
equipment,materialsandsoftwarenecessarytoadvancetheskillsandknowledgeofDepartmentemployeestoimplementtheCapitalProgram.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10B,X1(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(CapitalProgramDelivery:ProgramImplementationCosts)
MPO
Phase
Fund
Statewide
EC
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
$1.000
SectionIIIPage156
$1.000
$1.000
$1.000
Total
$5.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
TransitVillageProgram
DBNUM:01316/UPC:013160
ThisprogramwillprovidededicatedfundingtolocalgovernmentsthathavebeenselectedforinclusionintheTransitVillageProgram.Projectswhich
maybefundedunderthisprogramarebikepaths,sidewalks,streetscaping,andsignage.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): AQ1,NRS,O7(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(LocalSystemSupport:LocalAid,OtherPrograms)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
$1.000
$1.000
$1.000
SectionIIIPage157
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
Total
$10.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
TransportationAlternativesProgram
DBNUM:X107
Thisprogramprovidesfederalfundingforprojectssuchasscenicenhancements,historicpreservation,andbicycleandpedestrianimprovements.
NJDOTdesignatesasAdvanceConstructionallprojectsfundedfromthisprogram.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O8,X12(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(LocalSystemSupport:TransportationEnhancements)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
ERC
TAP
$1.501
$1.501
$1.501
$1.501
$1.501
$1.501
$1.501
$1.501
$1.501
$1.501
$15.010
NJTPA
ERC
TAP
$6.216
$6.216
$6.216
$6.216
$6.216
$6.216
$6.216
$6.216
$6.216
$6.216
$62.160
SJTPO
ERC
TAP
$0.518
$0.518
$0.518
$0.518
$0.518
$0.518
$0.518
$0.518
$0.518
$0.518
$5.180
Statewide
ERC
TAP
$5.000
$5.000
$5.000
$5.000
$5.000
$7.235
$7.235
$7.235
$7.235
$7.235
$61.175
SectionIIIPage158
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
TransportationandCommunityDevelopmentInitiative(TCDI)DVRPC
DBNUM:D0204
TheTransportationandCommunityDevelopmentInitiativeisaproposedDVRPCfundingprogramtargetedtothosecommunitiesmostinneedof
revitalizationassistance.Theprogramwouldservetosupportlocalplanning,design,feasibilitystudiesorotheranalysesthatincreasethedemandor
improvethemarketforredevelopmentandimprovetheefficiencyorenhancetheregionaltransportationnetwork.Thefundamentalideaisto
supportearlystageprojectideaswhicharenototherwiseeligibleforfundingthroughothersources.ThisprogramisacomponentoftheDVRPC
WorkProgram.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: DVRPC
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): X3(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:RegPlngandProjectDevelopment)
MPO
Phase
Fund
DVRPC
EC
STPSTU
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.680
$0.080
$0.680
$0.080
SectionIIIPage159
$0.680
$0.080
$0.680
$0.080
$0.680
$0.080
Total
$3.800
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
TransportationDemandManagementProgramSupport
DBNUM:X43
ThisfundingisutilizedtocontinuethemanagementoftheOwnedandLeasedParkandRideProgramandtheremainingeffortsastheyrelatetothe
1800CARPOOLprogramwhichalsoincludesmaintainingtheRideProridematchingsoftwareprogram.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): AQ1,NRS(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:DemandManagement)
MPO
Phase
Fund
Statewide
PLS
CMAQ
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.250
$0.250
$0.250
$0.250
SectionIIIPage160
$0.250
$0.250
$0.250
$0.250
$0.250
$0.250
Total
$2.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
TransportationManagementAssociations
DBNUM:11383/UPC:113830
ThisprogramwillprovideannualfundingtothefollowingTransportationManagementAssociations(TMAs):KeepMiddlesexMoving;Hudson,
Meadowlink,TransOptions;Ridewise;HARTCommuterInformationServices;CrossCountyConnection;andGreaterMercer.TheroleoftheTMAsis
topromotestatewideTransportationDemandManagement(TDM)initiativestoreducecommuterworktrips.TheTMAswillalsodeliverprograms
thatincludebutarenotlimitedtothefollowing;RidesharingInformationServices,EmployerTDMServices,CorridorManagementSupport,Parkand
RidePromotion,TrafficMitigationProjects,SmartWorkplacesNewJersey,coordinationoftransportationservicesfortransportationdisadvantaged
populations,TransitDevelopmentandPromotion,BicycleandPedestrianSafetyPrograms,aswellasotherincentiveanddemonstrationprogramsin
transportationdemandmanagementforcommuters.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): A1,AQ1(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:DemandManagement)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
EC
STPSTU
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
$20.000
NJTPA
EC
STPNJ
$4.195
$4.195
$4.195
$4.195
$4.195
$4.195
$4.195
$4.195
$4.195
$4.195
$41.950
SectionIIIPage161
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
TransportationResearchTechnology
DBNUM:X126
Thisprogramprovidesfundingforconsultantanduniversityresearchcontractstoconductmultimodaltransportationrelatedresearchandknowledge
andtechnologytransferactivitiesonbehalfofNJDOT,MVCandNJTransit.AquickresponseTreasuryselectedresearchconsultantaswellasbasic
agreementswithuniversitiesprovidesthemechanismtoconductresearch.FederalStatePlanningandResearch,SPR,fundsmaybesupplemented
withstatefundsinordertomeetfederalmatchingrequirements.IncludedinthislineitemarefundsforAmericanAssociationofStateHighway
TransportationOfficials,(AASHTO),technicalserviceprogramsandinnovativeproductssuchas:ProductEvaluationListing;Technology
ImplementationGroup;TechnicalAssistanceforClimateChange,MaterialStandards,andMaterialsReferenceLaboratory;SHRPproduct
implementation.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10C,X1(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CapitalProgramDelivery:PlanningProgramsandStudies)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.500
$0.750
$0.775
$0.800
SectionIIIPage162
$0.900
$1.000
$1.100
$1.200
$1.700
$2.200
Total
$10.925
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
TransportationSafetyResourceCenter(TSRC)
DBNUM:04364/UPC:043640
Thisprogramincludesreducingtrafficrelatedfatalities,injuriesandcrashesbyprovidingtrafficandsafetyengineeringservices,trainingactivities,
andtrafficrecordsdatabasesupport.ThecenterwillalsoprovidesupporttootherestablishedprogramssuchasSafetyConsciousPlanning(SCP),
ComprehensiveStrategicHighwaySafetyPlan(CSHSP),SeniorSafetyandtheSafetyManagementTaskForce(SMTF).
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,S6(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:SafetyManagement)
MPO
Phase
Fund
Statewide
EC
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.200
$1.200
$1.200
$1.200
SectionIIIPage163
$1.200
$1.200
$1.200
$1.200
$1.200
$1.200
Total
$12.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
TrentonAmtrakBridges
DBNUM:99362/UPC:993620
Thethreeorphanbridges,carryingChestnutAve.,E.StateStreetandMonmouthSt.overAmtrak,areinpoorcondition.Allthreebridgesare
structurallydeficientandfunctionallyobsolete.Thebridgesandapproachroadwaysfeaturevarioussubstandarddesignelements,including
substandardverticalandhorizontalclearances,intersectionsightdistancesandunprotectedbridgegirders.NJDOTisworkingwithTheCityof
TrentononarevisedconcepttoreplacetheE.StateSt.BridgeandremovetheChestnutAve.andMonmouthSt.Bridges.Anewconnectorroad
proposedwiththeconceptmaintainsallcurrentturningmovements.Thesinglebridgeoptionisaviableplan,giventheconstructioncostestimateof
approximately$35M.Replacementofthethreeexistingbridgespresentsfundingissues,givenconstraintsoftheMPO.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$20,000,000.
COUNTY: Mercer
LEGISLATIVEDISTRICT: 15
MUNICIPALITY: TrentonCity
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: 1149163,1149164,1149165
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:RailroadOverheadBridges)
MPO
Phase
Fund
DVRPC
CON
STPSTU
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$4.000
SectionIIIPage164
$4.000
$4.000
$4.000
$4.000
Total
$20.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
UnanticipatedDesign,RightofWayandConstructionExpenses,State
DBNUM:X11
Thisprogramprovidesfundingforunanticipatedprojectneeds,contractchangeorders,consultantagreementmodifications,utilityreadjustments,
elementsoffederalaidprojectsforwhichfederalfundingisnotavailableunderfederalregulations,courtorderedcondemnationawards,acceleration
offederalaidprojectsthroughmultiyearfundingagreementswithFederalHighwayAdministrationsettlementofprojectaccountingdiscrepancies
withFederalHighwayAdministration,andminorworkidentifiedduringtheyear.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10C(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(CapitalProgramDelivery:UnanticipatedExpenses)
MPO
Phase
Fund
Statewide
ERC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$23.850
$59.250
$52.285
$46.454
SectionIIIPage165
$89.019
$46.126
$94.871
$99.721
$99.571
$98.866
Total
$710.013
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
UtilityPoleMitigation
DBNUM:15344/UPC:153440
Thisprojectseekstoidentifyandmitigatelocationswithincidentsofhighrecurringutilitypoleaccidents.Themitigationprojectislimitedinscope
andresourcesandencompasses3to5crashlocationsperyear.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,S2,S6(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(CapitalProgramDelivery:RightofWayandUtility)
MPO
Phase
Fund
Statewide
EC
HSIP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.175
$0.175
$0.175
$0.175
SectionIIIPage166
$0.175
$0.175
$0.175
$0.175
$0.175
$0.175
Total
$1.750
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
UtilityReconnaissanceandRelocation
DBNUM:X182/UPC:800025
Thisprogramreimbursesutilitycompaniesfordesignandconstructioncostsincurredwhentheutilitycompaniesarerequiredtorelocatefacilitiesdue
toatransportationimprovementproject.Thisprogramalsofundssubsurfacetestingasamitigationmeasuretoaccuratelylocateandidentify
undergroundutilitiestomoderateorlessentheimpactwithutilitylocationsduringthedesignandconstructionphasesofatransportation
improvementproject.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NRS,O10C(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayRehabandRecon)
MPO
Phase
Fund
Statewide
EC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$7.000
$18.200
$18.200
$23.200
SectionIIIPage167
$28.200
$28.200
$28.200
$28.200
$28.200
$28.200
Total
$235.800
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
WrightDebowRoad,BridgeoverRoute195
DBNUM:15311/UPC:153110
BInitiatedbytheBridgeManagementSystem,thisprojectwillreplacethebridgedeckandsuperstructure.
Totalconstructionfundingneededisexpectedtobe$4,100,000.
COUNTY: Ocean
LEGISLATIVEDISTRICT: 12
MUNICIPALITY: JacksonTwp
SPONSOR: NJDOT
MILEPOST(S): 18.8
STRUCTURENO.: 1517156
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
DES
STP
NJTPA
CON
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.750
Total
$0.750
$4.100
SectionIIIPage168
$4.100
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
YouthEmploymentandTRACPrograms
DBNUM:X199
ThisisafederalgrantprogramthatprovidesemploymentandtrainingopportunitiestoatriskyouthsinNJ,especiallythoseinurbanareas,during
annualimplementationoftheNJDOTUrbanYouthCorpsProgram.ThisgrantalsoprovidesfundingtosupporttheTRACProgram,whichlinks
schoolsystemstotheNJDOTbyhavingdepartmentengineersvolunteerasmentorstointroducestudentstocareersincivilengineering.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10C,X1(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(CapitalProgramDelivery:ContractorSupport)
MPO
Phase
Fund
Statewide
EC
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.300
$0.300
$0.300
$0.300
SectionIIIPage169
$0.300
$0.300
$0.300
$0.300
$0.300
$0.300
Total
$3.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route1,CR533(QuakerbridgeRoad)toRidgeRoad
DBNUM:12406/UPC:124060
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$13,363,900.
COUNTY: Mercer,Middlesex
LEGISLATIVEDISTRICT: 14,15,16
MUNICIPALITY: PlainsboroTwp,WestWindsor,SouthBrunswickTwp
SPONSOR: NJDOT
MILEPOST(S): NB:7.909.22&12.0014.50;SB8.509.22&9.6010.80&12.1014.00 STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
CON
NHPP
$5.667
$5.667
NJTPA
CON
NHPP
$7.696
$7.696
SectionIIIPage170
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route1,Southbound,NassauParkBoulevardtoQuakerBridgeMallOverpass
DBNUM:01330A/UPC:013301
ThisprojectresultedfromaCongestionManagementStudy.Criticalconcernsaresafety/efficiencyintheseparationofthroughandlocaltraffic.
WideningofRt.1Southboundto3throughlaneswitha2laneCollectorDistributor(CD)Roadisproposed.Drivewayaccessrevisionsarealso
includedtominimizeconflicts.
Operationalandsafetyimprovementsareproposedinthesouthbounddirection.Criticalconcernsincludethesafety/efficiencyintheseparationofthe
throughandlocaltraffic;safetyoftheweavingandmergeoperationsontheCDroadway;densityofroadsidedrivewaysandassociatedvehicle
conflicts;andtheinadequateorlackofacceleration/decelerationlanesatQuakerBridgeMallramps.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$14,150,000.
COUNTY: Mercer
LEGISLATIVEDISTRICT: 15
MUNICIPALITY: LawrenceTwp,WestWindsorTwp
SPONSOR: NJDOT
MILEPOST(S): 7.618.69;8.94;9.25
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): 2020M(NonExempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:SafetyImprovements)
MPO
Phase
Fund
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$7.000
$7.150
SectionIIIPage171
Total
$14.150
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route1&9,AvenueCtoSylvanStreet
DBNUM:12311/UPC:123110
Therearefixedobjectcrashesatthislocation.Route1&9attheCSAOrailroadoverpassisfrequentlyhitbyheavyvehicletrafficbecausetheposted
clearance(13feet6inches)maybeincorrect.Also,theexistingstructureconsistutesasafetyproblemforpedestriansthatmusttraverseanarrow
passagewaybetweentheexistingabutmentandguiderail.
Totalconstructionfundingneededisexpectedtobe$2,700,000.
COUNTY: Union
LEGISLATIVEDISTRICT: 22
MUNICIPALITY: LindenCity
SPONSOR: NJDOT
MILEPOST(S): 40.0140.07
STRUCTURENO.: 2001153
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): AQ2,O10A,S1(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:SafetyImprovements)
MPO
Phase
Fund
NJTPA
PE
NHPP
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.300
Total
$0.300
$0.500
$0.500
$0.200
$0.200
$2.700
SectionIIIPage172
$2.700
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route1&9,HaynesAve.OperationalImprovements
DBNUM:94047/UPC:960974
TheprojectwilleliminatethesubstandardgeometricfeaturesthatcurrentlyexistconnectingRoute1&9southboundtoHaynesAvenue.Theaddition
ofacceleration/deceleration/weavinglanealongsouthboundRoute1&9willimprovesafetyandtrafficflow.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$20,000,000.
COUNTY: Essex
LEGISLATIVEDISTRICT: 29
MUNICIPALITY: NewarkCity
SPONSOR: NJDOT
MILEPOST(S): 0.00.5
STRUCTURENO.: 0749160
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NR3(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$15.000
$5.000
SectionIIIPage173
Total
$20.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route1&9,InterchangeatRouteI278
DBNUM:95023/UPC:950177
Proposedinterchangeimprovementstoaddressproblemofmissingramps.
Totalconstructionfundingneededisexpectedtobe$65,000,000.
COUNTY: Union
LEGISLATIVEDISTRICT: 22
MUNICIPALITY: LindenCity
SPONSOR: NJDOT
MILEPOST(S): 42.20
STRUCTURENO.: 2015153
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NR3(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
NJTPA
DES
OTHER
NJTPA
ROW
OTHER
NJTPA
CON
OTHER
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$2.000
Total
$2.000
$5.000
$5.000
$65.000
SectionIIIPage174
$65.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route3&Route495Interchange
DBNUM:12386/UPC:123860
InitiatedfromtheBridgeManagementSystem,thisprojectwillreplace;theRoute495EastboundandRampBoverRoute3structure;andthebridge
deckfortheRoute3EastboundandSouthServiceRoadstructureoverRoute495RampJ.Theprojectalsoincludessafetyandoperational
improvementswithintheRoutes3and495interchange.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$40,000,000.
COUNTY: Hudson
LEGISLATIVEDISTRICT: 32
MUNICIPALITY: NorthBergenTwp
SPONSOR: NJDOT
MILEPOST(S): 10.33
STRUCTURENO.: 0908152,0916150
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10A(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
PE
NHPP
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.500
Total
$3.500
$3.500
$3.500
$0.500
$0.500
$18.000
SectionIIIPage175
$22.000
$40.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route3,BridgeoverNorthernSecondary&RampA
DBNUM:08346/UPC:083460
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethefunctionallyobsoletebridge,builtin1929.
Totalconstructionfundingneededisexpectedtobe$19,400,000.
COUNTY: Hudson
LEGISLATIVEDISTRICT: 32
MUNICIPALITY: NorthBergenTwp
SPONSOR: NJDOT
MILEPOST(S): 10.6210.84
STRUCTURENO.: 0908153
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$19.400
SectionIIIPage176
Total
$19.400
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route3,Route46,ValleyRoadandNotch/RifleCampRoadInterchange,ContractB
DBNUM:059B/UPC:123020
FromNotch/RifleCampRoadtojusteastoftheValleyRoadIntersection,Route46willbewidenedtoprovidestandardshouldersand
acceleration/deceleration/auxiliarylanes,andwillberealignedasneededtoimprovesightdistance.AttheintersectionofRoute46andRoute3,a
threelanesectionwillreplacetheexistingtwolaneconnections.Route46willberealignedtoconvergewithRoute3fromtherightside(nottheleftas
presentlyexists).Completeinterchangeupgradeswillbemade.FromRoute46toGroveStreet,Route3willbewidenedtoprovideauxiliarylanesand
standardshoulders.Theprojectwillrequiretheremovalofthreebridgestructuresandreplacingthemwithfournewbridgestructures.Eachofthese
structureswillbedesignedtoprovideaminimumverticalunderclearanceof15feet6inches.Culvertswillbeimpactedaswell.BridgeStructuresto
bereplaced:1606172,1607151,160150(tobereplacedwithtwostructures);Culvertstobereplaced:1606173;Culvertstobeextended:1606168.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$128,700,000.
COUNTY: Passaic
LEGISLATIVEDISTRICT: 40,34
MUNICIPALITY: LittleFallsTwp,CliftonCity
SPONSOR: NJDOT
MILEPOST(S): Rt.300.50Rt.4659.260.6
STRUCTURENO.: Various
FINANCIALPLANREQUIREMENT: Thisprojectispartofaprojectwithatotalcostbetween$100and$500millionprogrammedtoreceivefederal
financialassistanceandanannualfinancialmanagementplanisrequiredtobeprepared.
AIRQUALITYCODE(NONEXEMPT/EXEMPT): 2020M(NonExempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$31.000
$31.200
SectionIIIPage177
$42.500
$24.000
Total
$128.700
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route4,BridgeoverPalisadeAvenue,WindsorRoadandCSXRailroad
DBNUM:065C/UPC:078044
ThisisabreakoutoftheRoute4CorridorMultiBridgesandRoadwayImprovementproject.TheprojectwillreplacetheexistingRoute4Bridgeover
PalisadeAvenue,WindsorRoad,andCSXRailroad.ApproachroadwayworkandimprovementofBelleAvenueintersectionwillbepartoftheproject
aswell.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$43,000,000.
COUNTY: Bergen
LEGISLATIVEDISTRICT: 37
MUNICIPALITY: TeaneckTwp
SPONSOR: NJDOT
MILEPOST(S): 6.807.20
STRUCTURENO.: 0206169
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
UTI
NHPP
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.500
Total
$3.500
$1.500
$1.500
$6.000
$6.000
$21.500
SectionIIIPage178
$21.500
$43.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route4,GrandAvenueBridge
DBNUM:08410/UPC:084100
Thisprojectwillreplacethedeckofstructure0206179inordertoremovethebridgefromthestructurallydeficientlist.TheWBrightthroughlane
throughtheintersectionwillbeeliminated.Theexistingthroughlanewillbeusedtoprovideadecelerationlane,anexclusivemergelaneandan
accelerationlanethatwillintroducetherightthroughlaneaftertheinterchangetoimprovesafetyattheramptermini.Abusshelterwillbeprovided
attheexistingbusstop,alongwithADAcompliantcurbrampsandsidewalks.Gapsinexistingsidewalkwillbeeliminated.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$18,900,000.
COUNTY: Bergen
LEGISLATIVEDISTRICT: 37
MUNICIPALITY: EnglewoodCity
SPONSOR: NJDOT
MILEPOST(S): 8.89.3
STRUCTURENO.: 0206179
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.500
Total
$1.500
$2.000
$2.000
$7.900
SectionIIIPage179
$11.000
$18.900
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route4,HackensackRiverBridge
DBNUM:02346/UPC:023460
InitiatedfromtheBridgeManagementSystem,thisprojectwillrehabilitate/replacethisstructurallydeficientandfunctionallyobsoletebridge,builtin
1931.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$27,000,000.
COUNTY: Bergen
LEGISLATIVEDISTRICT: 37
MUNICIPALITY: HackensackCity,TeaneckTwp
SPONSOR: NJDOT
MILEPOST(S): 5.706.10
STRUCTURENO.: 0206166
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
PE
NHPP
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$2.000
Total
$2.000
$2.500
$2.500
$1.500
$1.500
$13.500
SectionIIIPage180
$13.500
$27.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route4,JonesRoadBridge
DBNUM:94064/UPC:950194
InitiatedfromtheBridgeManagementSystem,thisprojectwillrehabilitate/replacethisstructurallydeficientandfunctionallyobsoletebridge,builtin
1931.
Totalconstructionfundingneededisexpectedtobe$8,000,000.
COUNTY: Bergen
LEGISLATIVEDISTRICT: 37
MUNICIPALITY: EnglewoodCity
SPONSOR: NJDOT
MILEPOST(S): 9.629.7
STRUCTURENO.: 0206182
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.500
Total
$0.500
$8.000
SectionIIIPage181
$8.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route4,Route20toRoute1&9
DBNUM:12431/UPC:124310
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$30,000,000.
COUNTY: Bergen,Passaic
LEGISLATIVEDISTRICT: 38,37
MUNICIPALITY: FairLawnBoro,ParamusBoro,RiverEdgeBoro,PattersonCity SPONSOR: NJDOT
MILEPOST(S): 0.010.8
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$10.000
SectionIIIPage182
$20.000
Total
$30.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route4,TeaneckRoadBridge
DBNUM:93134/UPC:950198
InitiatedfromtheBridgeManagementsystem,thisprojectwillreplacethebridge.OperationalandsafetyimprovementstoRoute4willbeprovided
byaddingacceleration/decelerationlanesandbusturnoutsinbothdirections.
Totalconstructionfundingneededisexpectedtobe$11,400,000.
COUNTY: Bergen
LEGISLATIVEDISTRICT: 37
MUNICIPALITY: TeaneckTwp
SPONSOR: NJDOT
MILEPOST(S): 7.277.86
STRUCTURENO.: 0206173
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
UTI
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$2.000
Total
$2.000
$0.600
$0.600
$0.600
$0.600
$11.400
SectionIIIPage183
$11.400
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route7,Kearny,DrainageImprovements
DBNUM:93186/UPC:950652
ThissectionofRoute7isgenerallyuncurbedandfrequentlyfloodedduetolowelevationandlackofsufficienthighwaydrainagesystem.Roadway
runoffiscollectedthroughinletsorsheetflow,dischargingdirectlyintothemarshlands.Duringmoderateandheavystorms,inadditiontohightide,
therunoffoverflowsthebanksontotheroadwayandadjacentproperties.Thiscausesthehighwaytobeclosedandtrafficisdetoured.Thisprojectwill
providehighwaydrainagesystemimprovementsincluding;pumpingstations,raisingroadprofileandsheetpilingtopreventtidalwatertofloodthe
roadway.
Totalconstructionfundingneededisexpectedtobe$32,000,000.
COUNTY: Hudson
LEGISLATIVEDISTRICT: 32
MUNICIPALITY: KearnyTown
SPONSOR: NJDOT
MILEPOST(S): 1.73.6
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S4(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:Drainage)
MPO
Phase
Fund
NJTPA
ROW
STATE
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
$1.000
$32.000
SectionIIIPage184
Total
$32.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route7,MillStreet(CR672)toParkAvenue(CR646)
DBNUM:12408B/UPC:158100
Afulldepthpavementreconstructionisrecommendedforadistanceof9ft.offsetfrombothsidesofthecenterlineoftheroadway.Amill‘x’–pave
‘x’pavementresurfacingisrecommendedfortheremainderoftheroadsurfaceandcurbtocurb.ADAcompliantcurbrampsshouldalsobeinstalled
atcurbramplocationswithinthelimits.Initiatedasapavementproject,afterfurtheranalysis,theprojecthassinceevolvedintosafetyproject.
Totalconstructionfundingneededisexpectedtobe$10,000,000.
COUNTY: Essex
LEGISLATIVEDISTRICT: 29,28
MUNICIPALITY: BellevilleTwp,NutleyTwp
SPONSOR: NJDOT
MILEPOST(S): 6.508.26
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): AQ2,S10(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:SafetyImprovements)
MPO
Phase
Fund
NJTPA
DES
HSIP
NJTPA
CON
HSIP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.500
Total
$1.500
$10.000
SectionIIIPage185
$10.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route7,SchuylerAvenuetoWebsterAvenue
DBNUM:12408A/UPC:158090
Thepavementrecommendationistoperformamill‘x’–pave‘x’pavementresurfacingcurbtocurbfortheentirelimits.ADAcompliantcurbramps
shouldalsobeinstalledatcurbramplocationswithinthelimits.Alt.3and4arerecommendedforimplementationattheRidgeRd/KearnyAve.and
SchuylerAve.intersectionsrespectively.Alt.3includesintersectionsafetyimprovementsatRidgeRd/KearnyAve.(MP4.74).Alt.4,leadleftturn
phaseswillbeprovidedformotoriststurningleftontoRt.7fromSchuylerAve.
Totalconstructionfundingneededisexpectedtobe$2,500,000.
COUNTY: Bergen,Hudson
LEGISLATIVEDISTRICT: 26,32
MUNICIPALITY: NorthArlingtonBoro,KearnyTown
SPONSOR: NJDOT
MILEPOST(S): 4.205.16
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): AQ2,S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$2.500
Total
$2.500
SectionIIIPage186
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route9,BridgeoverWaretownCreek
DBNUM:08316/UPC:083160
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethebridge,builtin1925.
Totalconstructionfundingneededisexpectedtobe$3,430,000.
COUNTY: Ocean
LEGISLATIVEDISTRICT: 9
MUNICIPALITY: OceanTwp
SPONSOR: NJDOT
MILEPOST(S): 78.29
STRUCTURENO.: 1502152
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.430
Total
$3.430
SectionIIIPage187
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route9,GardenStateParkwayRamptoWestecunkCreek
DBNUM:14365/UPC:143650
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$7,500,000.
COUNTY: Burlington,Ocean
LEGISLATIVEDISTRICT: 9
MUNICIPALITY: BassRiverTwp,LittleEggHarborTwp,TuckertonBoro,
EagleswoodTwp
SPONSOR: NJDOT
MILEPOST(S): 55.2366
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$7.500
Total
$7.500
SectionIIIPage188
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route9,IndianHeadRoadtoCentralAve/HurleyAve,Pavement
DBNUM:11418/UPC:114180
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.Projectwillincludesafetyimprovementsand
FederalADAcompliance.
Totalconstructionfundingneededisexpectedtobe$8,100,000.
COUNTY: Ocean
LEGISLATIVEDISTRICT: 10,30
MUNICIPALITY: TomsRiverTwp,LakewoodTwp
SPONSOR: NJDOT
MILEPOST(S): 94.8101.4
STRUCTURENO.: 1504150,1504151,1504153
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayRehabandRecon)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.750
Total
$0.750
$8.100
SectionIIIPage189
$8.100
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route9,JobsCreekBridge
DBNUM:11368/UPC:113680
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethefunctionallyobsoleteandstructurallydeficientbridgewithanewtwolane
singlespanstructurewithshoulders.Approachroadswillbereconstructedandsafetyfeatureswillbeincluded.
Totalconstructionfundingneededisexpectedtobe$5,830,000.
COUNTY: Burlington
LEGISLATIVEDISTRICT: 9
MUNICIPALITY: BassRiverTwp
SPONSOR: NJDOT
MILEPOST(S): 57.858.3
STRUCTURENO.: 0302151
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$5.830
SectionIIIPage190
Total
$5.830
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route9,JonesRdtoLongboatAve
DBNUM:11330/UPC:113300
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacebothdirectionswithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$7,750,000.
COUNTY: Ocean
LEGISLATIVEDISTRICT: 9
MUNICIPALITY: LaceyTwp,BerkeleyTwp,BeachwoodBoro,PineBeachBoro
SPONSOR: NJDOT
MILEPOST(S): 81.889.62
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$7.750
SectionIIIPage191
Total
$7.750
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route9/35,MainStreetInterchange
DBNUM:079A/UPC:088032
Rt.9/35overMainStreetInterchangeisabreakoutfromtheRt9/35overMainSt.Bridge.ThelackofanaccelerationlanefromRt.9NorthboundtoRt.
9/35Northboundramphascreatedasafetyconditionforvehiclesattemptingtomerge.Furthermore,thetightradiusandheavytrucktrafficfromthis
ramphavecontributedtothecongestionandthequeueonRt.9Northboundwhichextendsforaboutamilecausingmoresafetyconcerns.Rt.9/35
SouthboundtoRt.9Southboundrampisaalsoasafetyproblematthisinterchange,asthisrampisalsosubstandardandiscontributingtothe
extensivequeuewhichextendsfromRt.9/35totheEdisonBridge.Bothrampswillbeinvestigatedseparatelyandmaygraduateastwoindividual
projects.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$22,600,000.
COUNTY: Middlesex
LEGISLATIVEDISTRICT: 19
MUNICIPALITY: SayrevilleBoro,SouthAmboyCity
SPONSOR: NJDOT
MILEPOST(S): 129.82
STRUCTURENO.: 1208150
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10A(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
NJTPA
PE
NHPP
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$2.000
Total
$2.000
$2.500
$2.500
$2.000
$2.000
$10.100
SectionIIIPage192
$12.500
$22.600
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route9W,PalisadesAvenuetoNewYorkStateLine
DBNUM:11406/UPC:114060
TheRoute9WAssessmentforBicycleandPedestrianNeedsidentifiedsafetydeficienciesintermsoftheabilityoftheroadwaytoaccommodatebicycle
trafficandpedestriancrossingsatNJTransitbusstops.Bicycleandpedestriancompatibilitysigning,striping,anddrainagegrateimprovementsare
expectedtoaddressthesedeficiencieswiththeintentiontobeimplementedbymaintenanceengineering.
Totalconstructionfundingneededisexpectedtobe$16,000,000.
COUNTY: Bergen
LEGISLATIVEDISTRICT: 37
MUNICIPALITY: EnglewoodCliffsBoro,AlpineBoro
SPONSOR: NJDOT
MILEPOST(S): 2.1911.17
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): AQ2(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:Bicycle/PedestrianSafety)
MPO
Phase
Fund
NJTPA
PE
CMAQ
NJTPA
DES
CMAQ
NJTPA
ROW
CMAQ
NJTPA
CON
CMAQ
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
Total
$1.000
$1.200
$1.200
$5.000
$5.000
$16.000
SectionIIIPage193
$16.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route10,CR508(W.NorthfieldAve)toMerklinAvenue/KelleyDrive
DBNUM:14369/UPC:143690
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$3,700,000.
COUNTY: Essex
LEGISLATIVEDISTRICT: 27,34
MUNICIPALITY: LivingstonTwp,WestOrangeTwp
SPONSOR: NJDOT
MILEPOST(S): 18.821.8
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.700
Total
$3.700
SectionIIIPage194
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route10,EBwideningfromRoute202toRoute53
DBNUM:12303/UPC:123030
ThisprojectisaConceptDevelopmentStudytodeterminetheviabilityofwideningRoute10Eastbound.FromBoroughperspective,theproblem
locationisthehighestpriorityintermsofreducingtrafficcongestion,increasinghighwaycapacityandimprovingtrafficsafety.
Totalconstructionfundingneededisexpectedtobe$2,100,000.
COUNTY: Morris
LEGISLATIVEDISTRICT: 26
MUNICIPALITY: MorrisPlainsBoro
SPONSOR:
MILEPOST(S): 10.711.3
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10A(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:MajorCapacityIncrease)
MPO
Phase
Fund
NJTPA
PE
NHPP
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
Total
$1.000
$1.600
$1.600
$3.800
$3.800
$2.100
SectionIIIPage195
$2.100
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route10,HillsideAve(CR619)toMt.PleasantTpk(CR665)
DBNUM:11339/UPC:113390
InitiatedbythePavementManagementSystem,Thisprojectconsistsofreconstructing,millingandoverlayingexistingpavement,rehabilitatingthe
deterioratedconcrete,minimizingscourdownstreamatIndianBrookculvertandintersectionmodificationstoimprovetrafficflow.
Totalconstructionfundingneededisexpectedtobe$15,000,000.
COUNTY: Morris
LEGISLATIVEDISTRICT: 25
MUNICIPALITY: RoxburyTwp,RandolphTwp
SPONSOR: NJDOT
MILEPOST(S): 0.937.20
STRUCTURENO.: 1401153
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S4,S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.500
Total
$1.500
$1.000
$1.000
$15.000
SectionIIIPage196
$15.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route10,WBRt287toJeffersonRd
DBNUM:12436/UPC:124360
InitiatedfromthePavementManagementSystem,thisprojectwillreconstructpavementwithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$2,400,000.
COUNTY: Morris
LEGISLATIVEDISTRICT: 27
MUNICIPALITY: HanoverTwp
SPONSOR: NJDOT
MILEPOST(S): 12.7913.19
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.900
Total
$0.900
$2.400
SectionIIIPage197
$2.400
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route15NB,BridgeoverLakeHopatcong
DBNUM:14334/UPC:143340
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethebridgedeckandprovidescourcountermeasurestoaddressthisscourcritical
structure.
Totalconstructionfundingneededisexpectedtobe$1,700,000.
COUNTY: Morris
LEGISLATIVEDISTRICT: 26
MUNICIPALITY: JeffersonTwp
SPONSOR: NJDOT
MILEPOST(S): 6.706.70
STRUCTURENO.: 1424150
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:DeckRehabandReplacement)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.700
Total
$1.700
SectionIIIPage198
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route15,BridgeoverBeaverRun
DBNUM:09319/UPC:093190
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethebridge,builtin1915.
Totalconstructionfundingneededisexpectedtobe$3,250,000.
COUNTY: Sussex
LEGISLATIVEDISTRICT: 24
MUNICIPALITY: LafayetteTwp
SPONSOR: NJDOT
MILEPOST(S): 17.56
STRUCTURENO.: 1922150
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.200
Total
$1.200
$0.250
$0.250
$3.250
SectionIIIPage199
$3.250
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route15andBerkshireValleyRoad(CR699)
DBNUM:13350/UPC:133500
Thisprojectwilladdresscongestionandsafetyatthesignalizedintersection,andasecondleftturnlanewillbeaddedfromBerkshireValleyRd.toRt.
15Southbound.
Totalconstructionfundingneededisexpectedtobe$2,000,000.
COUNTY: Morris
LEGISLATIVEDISTRICT: 26
MUNICIPALITY: JeffersonTwp
SPONSOR: NJDOT
MILEPOST(S): 3.913.91
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NR1,NR2(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
NJTPA
PE
NHPP
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.300
Total
$0.300
$0.850
$0.850
$0.250
$0.250
$2.000
SectionIIIPage200
$2.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route17,SproutBrook,CulvertReplacement
DBNUM:11357/UPC:113570
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacetheculvertwithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$3,100,000.
COUNTY: Bergen
LEGISLATIVEDISTRICT: 38
MUNICIPALITY: ParamusBoro
SPONSOR: NJDOT
MILEPOST(S): 15.015.1
STRUCTURENO.: 0216158
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S4,S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:Culverts)
MPO
Phase
Fund
NJTPA
PE
NHPP
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.300
Total
$0.300
$0.450
$0.450
$0.300
$0.300
$3.100
SectionIIIPage201
$3.100
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route18,EastBrunswick,DrainageandPavementRehabilitation
DBNUM:10354/UPC:103540
ThisprojectconsistsofpavementreconstructionandresurfacingofNJRoute18,andwillalsoincludemitigatingfloodinganddrainageproblems.This
projectprovidesrepairandreplacementofcurbsandsidewalks,andmillingandresurfacingofmostoftheroadwaywithintheprojectlimits.Full
reconstructionoftherightlanes,inbothdirections,atvariouslocationsisincluded.Inaddition,upgradeswillbemadetoallcurbramps,and
midblockcrosswalks,thatdonotmeetcurrentADAcriteria.ImprovementstoRoute18andEdgeboroRoad,andRoute18andTicesLane
intersectionsarealsoproposed.Ifwarranted,theprojectwillincludeupgradingoftrafficsignalsandlightingwithintheprojectlimits.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$26,800,000.
COUNTY: Middlesex
LEGISLATIVEDISTRICT: 18
MUNICIPALITY: EastBrunswickTwp
SPONSOR: NJDOT
MILEPOST(S): NB:35.439.5,SB:35.539.2
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S4,S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayRehabandRecon)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$2.400
Total
$2.400
$0.400
$0.400
$10.000
$16.800
SectionIIIPage202
$26.800
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route18,SouthofTexasRoadtoRuesLane,Pavement
DBNUM:11408/UPC:114080
InitiatedfromthePavementManagementSystem,thisprojectwillrehabilitatepavementwithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$14,400,000.
COUNTY: Monmouth,Middlesex
LEGISLATIVEDISTRICT: 12,13,18
MUNICIPALITY: MarlboroTwp,OldBridgeTwp,EastBrunswickTwp
SPONSOR: NJDOT
MILEPOST(S): NB29.535.4;SB30.535.5
STRUCTURENO.: Various
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayRehabandRecon)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$2.000
Total
$2.000
$14.400
SectionIIIPage203
$14.400
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route19,ColfaxAve(CR609)toMarshallStreet
DBNUM:12419/UPC:124190
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$3,175,000.
COUNTY: Passaic
LEGISLATIVEDISTRICT: 34,35
MUNICIPALITY: CliftonCity,PatersonCity
SPONSOR: NJDOT
MILEPOST(S): NB0.01.16&2.32.9;SB0.02.9
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.175
SectionIIIPage204
Total
$3.175
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route20,PatersonSafety,DrainageandResurfacing
DBNUM:08372/UPC:083720
Thisproject,acombiningof;Rt.20Paterson,Drainage,Rt.20EdwardAve.IntersectionImprovementsandRt.205thAve.(CR652)Intersection
Improvements,addressessafetyanddrainageissuesandprovidespavementresurfacingwithintheprojectlimits.Currently,roadwayfloodingis
causedbyinadequatestormwaterdrainagepipes.Theprojectwillinstalladditionalinletsandlargerdrainagepipesalongsevencriticalareasandlow
pointsonRoute20.Theroadwayat5thAvenuewillberaisedinordertoprotectRoute20fromthe10YearPassaicRiverflood.Theprojectwill
improvesafetyandgeometricdeficienciesattheintersectionofRt.20andEdwardAvenue,including;sightdistance,signalsandsignage.TheRoute
20SouthboundjuncturewithEdwardsAvenuewillbereconfiguredforrightin/rightouttrafficmovements.Theleftturnbarrieropening,from
Route20NorthboundtoEdwardAvenue,willbeclosed,andtrafficwillberedirectedtotheRoute4East(East43rdStreetwillbeaddedtosigns)exit
tothesouth.TheintersectionofEast43rdStreetandRoute4(Broadway)andtheendofthatexitrampwillbereconfiguredwithatrafficsignaladded.
TheprojectwillalsoimprovesafetyandgeometricdeficienciesattheintersectionofRoute20and5thAvenue(CR652).Installation/updatingof
regulatoryandadvancedwarningsigns,removaloftrees,andraisingoftheprofileofRoute20alongthelengthoftheentireinterchangewillbe
performed.TherampfromRoute20Northboundto5thAvenuewillbereconfigured,withincreasedleftturnstorageonRoute20.Thetrafficsignalat
thatrampwillbesynchronizedwiththesignalat5thAvenue.
Totalconstructionfundingneededisexpectedtobe$13,951,000.
COUNTY: Passaic
LEGISLATIVEDISTRICT: 35
MUNICIPALITY: PatersonCity
SPONSOR: NJDOT
MILEPOST(S): 0.14.0
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S4(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:Drainage)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$2.500
Total
$2.500
$0.223
$0.223
$13.951
SectionIIIPage205
$13.951
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route21,DaytonStreettoRoute46West
DBNUM:12400/UPC:124000
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$4,165,000.
COUNTY: Passaic
LEGISLATIVEDISTRICT: 36,34
MUNICIPALITY: PassaicCity,CliftonCity
SPONSOR: NJDOT
MILEPOST(S): 12.714.4
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$4.165
SectionIIIPage206
Total
$4.165
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route21,NewarkNeedsAnalysis,MurrayStreettoEdisonPlace
DBNUM:99381/UPC:993810
TheFeasibilityAssessmentwillproviderecommendationstorelievetrafficcongestionviapotentialwideningaswellasprovidingforsafetyand
pedestrianimprovements.
Totalconstructionfundingneededisexpectedtobe$24,000,000.
COUNTY: Essex
LEGISLATIVEDISTRICT: 29
MUNICIPALITY: NewarkCity
SPONSOR: NJDOT
MILEPOST(S): 1.202.25
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10A(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
NJTPA
PE
NHPP
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.500
Total
$1.500
$2.500
$2.500
$1.000
$1.000
$24.000
SectionIIIPage207
$24.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route21,NewarkRiverfrontPedestrianandBicycleAccess
DBNUM:98540/UPC:985400
ThisprojectproposestoimprovepedestrianandbicycleconnectionsbetweenBroadStandMcCarterHighway(Route21).Theprojectwouldimprove
pedestrianandbicycleaccessbetweenDowntownNewarkandtheRiverfront,viaCenterStreet/ParkPlacebetweenBroadStreetandMcCarter
Highway(Route21).Theprojectwouldalsoincludenewcurbandsidewalks,ADAcurbramps,trafficsignals,streetlighting,streetfurnitureandbike
lanes.TheprojectwillreplacetheexistingtrafficsignalsatBroadStreetandRectorStreet,BroadStandCentralAve,ParkPlaceandRectorStreet,
CenterStreetandParkPlace,CenterStreetandMulberryStreet.
Thefollowingspecialfederalappropriationshavebeenallocatedtothisproject:FY05SAFETEALU:$1,200,000(ID#NJ139);$1,500,000(ID#NJ269);
$2,000,000(ID#NJ254).
Totalconstructionfundingneededisexpectedtobe$4,700,000.Thefollowingspecialfederalappropriationshavebeenallocatedforthisproject
$1,025,100(NJ042);$1,201,770(NJ139);$2,002,950(NJ254);$1,503,512(NJ269).
COUNTY: Essex
LEGISLATIVEDISTRICT: 29
MUNICIPALITY: NewarkCity
SPONSOR: CityofNewark
MILEPOST(S): 4.14.3
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): AQ2(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(MultimodalPrograms:Bicycle/Pedestrian)
MPO
Phase
Fund
NJTPA
ERC
DEMO
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$4.700
Total
$4.700
SectionIIIPage208
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route22,BatesAvenuetoRoute57
DBNUM:11369/UPC:113690
InitiatedfromtheDrainageManagementSystem,thisprojectprovidesforadrainagealternativesstudy.In2012DrainageManagementSystem,this
locationwasranked46/232forfloodingand100/131forIcingincidents.
Totalconstructionfundingneededisexpectedtobe$4,750,000.
COUNTY: Warren
LEGISLATIVEDISTRICT: 23
MUNICIPALITY: PhillipsburgTown,LopatcongTwp
SPONSOR: NJDOT
MILEPOST(S): 1.12.1
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S4(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:Drainage)
MPO
Phase
Fund
NJTPA
PE
NHPP
NJTPA
DES
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.300
$0.300
$0.750
$0.750
$4.750
SectionIIIPage209
Total
$4.750
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route22,BloyStreettoLibertyAvenue
DBNUM:658C/UPC:058004
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethestructurallydeficientandfunctionallyobsoletebridge,builtin1940.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$8,200,000.
COUNTY: Union
LEGISLATIVEDISTRICT: 20
MUNICIPALITY: HillsideTwp
SPONSOR: NJDOT
MILEPOST(S): 56.9057.30
STRUCTURENO.: 2004152
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.200
$5.000
SectionIIIPage210
Total
$8.200
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route22,BridgeoverCentralRR
DBNUM:14425/UPC:144250
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethestructurallydeficientbridge.
Totalconstructionfundingneededisexpectedtobe$8,400,000.
COUNTY: Hunterdon
LEGISLATIVEDISTRICT: 23
MUNICIPALITY: ClintonTwp
SPONSOR: NJDOT
MILEPOST(S): 20.08
STRUCTURENO.: 1005151
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
PE
NHPP
NJTPA
DES
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.800
Total
$0.800
$1.100
$1.100
$8.400
SectionIIIPage211
$8.400
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route22,BridgeoverEchoLake
DBNUM:14330/UPC:143300
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethestructurallydeficientbridge.
Totalconstructionfundingneededisexpectedtobe$3,250,000.
COUNTY: Union
LEGISLATIVEDISTRICT: 21
MUNICIPALITY: MountainsideBoro
SPONSOR: NJDOT
MILEPOST(S): 50.7450.74
STRUCTURENO.: 2003157
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:DeckRehabandReplacement)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
MPO
Phase
Fund
NJTPA
PE
NHPP
NJTPA
DES
NHPP
$0.450
NJTPA
ROW
NHPP
$0.150
NJTPA
CON
NHPP
$0.250
Total
$0.250
$0.450
$0.150
$3.250
SectionIIIPage212
$3.250
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route22,ChestnutStreetBridgeReplacement(CR626)
DBNUM:04361/UPC:043610
InitiatedbytheBridgeManagementSystem,thisprojectwillrehabilitatethestructurallydeficientandfunctionallyobsoletebridge,builtin1929.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$20,000,000.
COUNTY: Union
LEGISLATIVEDISTRICT: 20
MUNICIPALITY: UnionTwp
SPONSOR: NJDOT
MILEPOST(S): 54.7055.24
STRUCTURENO.: 2003166
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.770
Total
$1.770
$10.000
$10.000
SectionIIIPage213
$20.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route22,CommonsWaytoRoute287
DBNUM:14356/UPC:143560
InitiatedfromthePavementManagementSystem,thisprojectwillprovideConcretePavementRepairwithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$4,700,000.
COUNTY: Somerset
LEGISLATIVEDISTRICT: 23
MUNICIPALITY: BridgewaterTwp
SPONSOR: NJDOT
MILEPOST(S): 34.336.87
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
PE
NHPP
NJTPA
DES
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.250
Total
$0.250
$0.400
$0.400
$4.700
SectionIIIPage214
$4.700
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route22,EB,Route78InterchangetoCountryClubRoad
DBNUM:11409/UPC:114090
InitiatedfromthePavementManagementSystem,thisprojectwillrehabilitate/resurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$10,300,000.
COUNTY: Hunterdon,Somerset
LEGISLATIVEDISTRICT: 16,23
MUNICIPALITY: ClintonTwp,LebanonBoro,ReadingtonTwp,BranchburgTwp SPONSOR: NJDOT
MILEPOST(S): EB19.2532.53
STRUCTURENO.: 1005154,1005153,1005151,Various
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$10.300
SectionIIIPage215
Total
$10.300
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route22,HilldalePlace/NorthBroadStreet
DBNUM:658E/UPC:058006
ThisprojectaddressestheRt.22HilldalePlaceRampConnectionBridgewhichisinpoorconditionduetothedeckandsubstructurecondition.The
projectwillcorrectexistinggeometricdeficiencies,thesubstandardmainlinecurveandnegativesuperelevation,whichcausecrashes.Toaddress
accessissuesaneastboundentrancerampwillbeconstructed.
Totalconstructionfundingneededisexpectedtobe$8,100,000.
COUNTY: Union
LEGISLATIVEDISTRICT: 20
MUNICIPALITY: HillsideTwp
SPONSOR: NJDOT
MILEPOST(S): 58.0058.10
STRUCTURENO.: 2004155,2004157,2004156
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
Total
$1.000
$8.100
SectionIIIPage216
$8.100
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route22,Westbound,VicinityofVauxHallRoadtoWestofBloyStreet
DBNUM:658B/UPC:058003
ProjectconsistsofsafetyandoperationalimprovementsbyprovidingaforeshorteneddecelerationlaneforRoute22westboundexitramptoVauxhall
RoadandaddingeastboundaccelerationlanefromSayreRoadthatwillallowtraffictosafelyexit/mergewithmainlinetraffic.Upgradestoramp
radiuswillbeinvestigated.
Totalconstructionfundingneededisexpectedtobe$3,250,000.
COUNTY: Union
LEGISLATIVEDISTRICT: 20
MUNICIPALITY: UnionTwp
SPONSOR: NJDOT
MILEPOST(S): 56.0056.43
STRUCTURENO.: 2004150
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NR4,S5(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:SafetyImprovements)
MPO
Phase
Fund
NJTPA
ROW
HSIP
NJTPA
CON
HSIP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.350
Total
$0.350
$3.250
SectionIIIPage217
$3.250
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route22/Route82/GardenStateParkwayInterchange
DBNUM:658A/UPC:058002
Thisprojectwillimprovesafetyandgeometricdeficienciesandstreamlineaccesswithintheinterchangebyremovingweavingsections.Theproject
willalsoincludewideninganddeckreplacementfortheRoute22WestboundBridgeoverRoute82.
Totalconstructionfundingneededisexpectedtobe$15,000,000.
COUNTY: Union
LEGISLATIVEDISTRICT: 20
MUNICIPALITY: UnionTwp
SPONSOR: NJDOT
MILEPOST(S): 55.2656.16
STRUCTURENO.: 2004159,2004160
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10A(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:SafetyImprovements)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$2.500
Total
$2.500
$0.591
$0.591
$15.000
SectionIIIPage218
$15.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route23,AlexanderRoadtoMapleLakeRoad
DBNUM:11424/UPC:114240
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.ADAupgradesandguiderailrepairwillbe
included.
Totalconstructionfundingneededisexpectedtobe$14,170,000.
COUNTY: Morris
LEGISLATIVEDISTRICT: 26,40
MUNICIPALITY: PequannockTwp,RiverdaleBoro,KinnelonBoro,ButlerBoro
SPONSOR: NJDOT
MILEPOST(S): 10.216.8
STRUCTURENO.: Various
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$14.170
Total
$14.170
SectionIIIPage219
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route23,BloomfieldAvenue(CR506)toBridgeoverNJTransit
DBNUM:12420/UPC:124200
PavementResurfacingProject
Totalconstructionfundingneededisexpectedtobe$8,000,000.
COUNTY: Essex,Passaic
LEGISLATIVEDISTRICT: 26,40
MUNICIPALITY: VeronaTwp,CedarGroveTwp,LittleFallsTwp,WayneTwp
SPONSOR: NJDOT
MILEPOST(S): 0.04.9
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$8.000
Total
$8.000
SectionIIIPage220
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route23,BridgeoverBranchofWallkillRiver
DBNUM:08348/UPC:083480
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethestructurallydeficientbridge,builtin1926.
Totalconstructionfundingneededisexpectedtobe$2,352,000.
COUNTY: Sussex
LEGISLATIVEDISTRICT: 24
MUNICIPALITY: WantageTwp
SPONSOR: NJDOT
MILEPOST(S): 37.5037.67
STRUCTURENO.: 1904153
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$2.352
Total
$2.352
SectionIIIPage221
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route23,BridgeoverPequannockRiver/HamburgTurnpike
DBNUM:08347/UPC:083470
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethebridgeandprovidescourcountermeasurestoaddressthisscourcritical
structure.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$30,000,000.
COUNTY: Morris,Passaic
LEGISLATIVEDISTRICT: 26
MUNICIPALITY: KinnelonBoro,WestMilfordTwp
SPONSOR: NJDOT
MILEPOST(S): 16.88
STRUCTURENO.: 1405156
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.000
Total
$3.000
$3.900
$3.900
$10.000
SectionIIIPage222
$20.000
$30.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route23,HardystonTownshipImprovements
DBNUM:96039/UPC:950262
Thisprojectprovidessafety,operationalanddrainageimprovementswithinthreesectionsofRoute23inHardystonTwp.,SussexCounty;
Northern/LaceytownRoad,EastShoreRoad,andHollandMountainRoad.WithintheNorthern/LaceytownRoadandtheEastShoreRoadsections,
localizedoperationalandsafetyenhancementswillbeimplementedwith;minorgeometricimprovements,drainageupgrades,pavementresurfacing,
pavementstripingandmarkingandothersafetycountermeasures.TheHollandMountainRoadsectionwillbeextensivelyreconstructedtoimprove
intersectionoperationandenhancesafety.ThisworkwillconsistofwideningRoute23andHollandMountainRoadtoaccommodatethroughtraffic
andallturningmovementsattheintersection.AtwowayleftturnlanewillbeconstructedonRoute23,attheHollandMountainintersection,
extendingapproximately2,500feet(0.45mile)northoftheintersection.AportionofSnufftownRoadwillalsobereconstructedtoimprovethe
intersectionalignmentwithRoute23andHollandMountainRoad.AnewtrafficsignalattheRoute23/HollandMountainRoad/SnufftownRoad
intersectionwillalsobeconstructed.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$10,066,000.Thefollowingspecialfederalappropriations
havebeenallocatedforthisproject$3,445,074(NJ179);$1,683,000(NJ278).
COUNTY: Sussex
LEGISLATIVEDISTRICT: 24
MUNICIPALITY: HardystonTwp
SPONSOR: NJDOT
MILEPOST(S): 27.0031.20
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S4(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:SafetyImprovements)
MPO
Phase
Fund
NJTPA
ROW
DEMO
NJTPA
CON
DEMO
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.200
Total
$1.200
$1.896
$1.896
$8.170
SectionIIIPage223
$8.170
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route23,HighCrestDrivetoMacopinRiver
DBNUM:11424A/UPC:153000
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimitsandreconstructtheNorthboundshoulder.Safety
concernsraisedbylocalofficials(knownastheScurves)willbeevaluated.
Totalconstructionfundingneededisexpectedtobe$7,575,000.
COUNTY: Passaic
LEGISLATIVEDISTRICT: 26
MUNICIPALITY: WestMillfordTwp
SPONSOR: NJDOT
MILEPOST(S): 17.219.8
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10A,S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayRehabandRecon)
MPO
Phase
Fund
NJTPA
PE
HSIP
NJTPA
DES
HSIP
NJTPA
ROW
HSIP
NJTPA
CON
HSIP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.800
Total
$0.800
$0.800
$0.800
$0.100
$0.100
$7.575
SectionIIIPage224
$7.575
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route23/80,LongtermInterchangeImprovements
DBNUM:9233B6/UPC:009234
Theproposedlongtermimprovementsmayinvolveamajorconstructionprojectthataddressesexistingweekdayandweekend
congestionproblemsandprovidesforacriticalmissinglinkinthehighwaynetwork.
ThefollowingspecialFederalappropriationwasallocatedtothisproject.FY06SAFETEALU,HPP$1,200,000,ID#NJ202,(available20%peryear).
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$24,500,000.Thefollowingspecialfederalappropriations
havebeenallocatedforthisproject$1,201,770(NJ202).
COUNTY: Passaic,Essex
LEGISLATIVEDISTRICT: 40,26
MUNICIPALITY: WayneTwp,FairfieldTwp
SPONSOR: NJDOT
MILEPOST(S): 23:5.15.7;80:52.853.75
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10A(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
NJTPA
PE
DEMO
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.500
Total
$1.500
$2.500
$2.500
$0.500
$0.500
$11.500
SectionIIIPage225
$13.000
$24.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route27ADARamps,EvergreenSttoElizabethRiver
DBNUM:10316A/UPC:158110
ThepurposeoftheprojectistoadvanceADAcompliantrampsat125intersections,34ofwhicharesignalizedandapproximately40drivewaysand
alongRt.27.TheprojectwilladdresstheADArampdeficienciesontheprojectsite.ProvidereasonableADAcompliantrampsatintersectionswithin
theprojectsite.AddresstheneedforROWacquisition,utilityrelocations,andtrafficsignalrelocationsinordertoprovidereasonableADAcompliant
ramps.
Totalconstructionfundingneededisexpectedtobe$7,600,000.
COUNTY: Middlesex,Union
LEGISLATIVEDISTRICT: 18,19,22
MUNICIPALITY: EdisonTwp,WoodbridgeTwp,RahwayCity
SPONSOR: NJDOT
MILEPOST(S): 23.833.4
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): AQ2(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(MultimodalPrograms:Bicycle/Pedestrian)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.200
Total
$1.200
$1.600
$1.600
$7.600
SectionIIIPage226
$7.600
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route27,BridgeStreet(CR669)toFredericStreet
DBNUM:12434/UPC:124340
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$3,300,000.
COUNTY: Middlesex
LEGISLATIVEDISTRICT: 18
MUNICIPALITY: MetuchenBoro,EdisonTwp
SPONSOR: NJDOT
MILEPOST(S): 20.923.8
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.300
SectionIIIPage227
Total
$3.300
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route27,GrandStreetNBIntersection
DBNUM:12437/UPC:124370
Thisprojectwillprovideimprovementswhichinclude;fulltrafficsignalreplacementwithpedestrianaccommodations,signageupgradesand
reconstructionofallcurbrampstomeetADAcompliancestandards.Millingandpavingwithintheintersectionlimits,andimprovedcrosswalk
markings,willalsobeincluded.
Totalconstructionfundingneededisexpectedtobe$1,250,000.
COUNTY: Union
LEGISLATIVEDISTRICT: 20
MUNICIPALITY: ElizabethCity
SPONSOR: NJDOT
MILEPOST(S): 33.96
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): AQ2,O10A,S10(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:SafetyImprovements)
MPO
Phase
Fund
NJTPA
CON
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.250
SectionIIIPage228
Total
$1.250
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route28,GroveStreettoHighlandAvenue
DBNUM:12421/UPC:124210
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$6,487,000.
COUNTY: Union
LEGISLATIVEDISTRICT: 21,20
MUNICIPALITY: RoselleParkBoro,ElizabethCity
SPONSOR: NJDOT
MILEPOST(S): 23.325.3
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$6.487
Total
$6.487
SectionIIIPage229
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route29,AlexaukenCreekRoadtoWashingtonStreet
DBNUM:11413C/UPC:158030
InitiatedfromthePavementManagementSystem,thisprojectwillreconstruct(includingcoldinplacerecycling)andresurfacewithintheproject
limits.TheprojectwillbeMillXPaveX+1,andwillincludedrainageimprovementstoeliminateroadway,shoulderandborderponding.
Totalconstructionfundingneededisexpectedtobe$5,610,000.
COUNTY: Hunterdon
LEGISLATIVEDISTRICT: 15,16,23
MUNICIPALITY: LambertvilleCity,DelawareTwp,KingwoodTwp,Frenchtown SPONSOR: NJDOT
Boro
MILEPOST(S): 19.824.5&33.734.3
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S4,S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayRehabandRecon)
MPO
Phase
Fund
NJTPA
PE
STP
NJTPA
DES
STP
NJTPA
ROW
STP
NJTPA
CON
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.200
Total
$0.200
$0.350
$0.350
$0.100
$0.100
$5.610
SectionIIIPage230
$5.610
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route29,CassStreettoCalhounStreet,Drainage
DBNUM:07319B/UPC:123660
ThisprojectisabreakoutofRoute29,DrainageImprovements(DB#07319).FloodinganddrainageproblemshavebeenreportedalongRoute29inthe
southernsectionoftheoriginalparentproject.Basedonavailableinformation,itisperceivedthatstormsewersystemsandtheDelawareRiverare
primarycausesoftheflooding.Approximately14Tideflexvalvesandafloodwallextensionofabout200feetinlengthwouldaddressfloodingby
preventingtheDelawareRiverfrombackingupintotheexistingstormsewerpipesystemswithintheRoute29rightofway.Withthese
improvements,variouslocationsoftheroadwaywillbeprotectedfromeventsrangingbetweenthe15and50yearfloodsintheriver’smainchannel.
Totalconstructionfundingneededisexpectedtobe$5,086,200.
COUNTY: Mercer
LEGISLATIVEDISTRICT: 15
MUNICIPALITY: TrentonCity
SPONSOR: NJDOT
MILEPOST(S): 2.944.34
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S2(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:Drainage)
MPO
Phase
Fund
DVRPC
ROW
NHPP
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.150
$0.150
$5.086
SectionIIIPage231
Total
$5.086
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route29,LockatongCreektoD&RCanalStatePark
DBNUM:11413A/UPC:158010
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.Inaddition,substandardguiderailend
treatmentswillbeupgradedatsomeofthestructureslocatedwithintheprojectlimits,inlets,pipesandgrateswillbeclearedfromdebrisand
substandardgrateswillbereplacedwithbicyclesafegrates.
Totalconstructionfundingneededisexpectedtobe$4,100,000.
COUNTY: Hunterdon
LEGISLATIVEDISTRICT: 16,23
MUNICIPALITY: DelawareTwp,KingwoodTwp
SPONSOR: NJDOT
MILEPOST(S): 24.527.4&30.433.7
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$4.100
SectionIIIPage232
Total
$4.100
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route29,RockfallMitigation,KingwoodTwp
DBNUM:11413B/UPC:158020
InitiatedbytheRockfallHazardManagementSystem,theprojectwillproviderockfallmitigationwithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$12,150,000.
COUNTY: Hunterdon
LEGISLATIVEDISTRICT: 23
MUNICIPALITY: KingwoodTwp
SPONSOR: NJDOT
MILEPOST(S): 27.430.4
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S2,S4(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:RockfallMitigation)
MPO
Phase
Fund
NJTPA
ROW
STP
NJTPA
CON
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.150
$0.150
$12.150
SectionIIIPage233
Total
$12.150
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route30,AtcoAvenuetoRoute206
DBNUM:11416/UPC:114160
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.Theprojectwillincludeguiderailreplacement,
installationofhandicappedrampsandcrosswalksandupgradingoftrafficsignals.
Totalconstructionfundingneededisexpectedtobe$13,821,100.
COUNTY: Camden,Atlantic
LEGISLATIVEDISTRICT: 8,4
MUNICIPALITY: WaterfordTwp,ChesilhurstBoro,WinslowTwp,Hammonton SPONSOR: NJDOT
Town
MILEPOST(S): 19.5129.70
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
CON
STATE
$11.448
$11.448
SJTPO
CON
STATE
$2.373
$2.373
SectionIIIPage234
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route30,BridgeoverDuckThorofare
DBNUM:14428/UPC:144280
InitiatedfromtheBridgeManagementSystem,theprojectwillrehabilitate/replacethebridge.
Totalconstructionfundingneededisexpectedtobe$9,500,000.
COUNTY: Atlantic
LEGISLATIVEDISTRICT: 2
MUNICIPALITY: AtlanticCity
SPONSOR: NJDOT
MILEPOST(S): 56.25
STRUCTURENO.: 0103153
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
SJTPO
PE
NHPP
SJTPO
DES
NHPP
SJTPO
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.700
$0.700
$1.000
$1.000
$9.500
SectionIIIPage235
Total
$9.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route30,ElmwoodRd/WeymounthRd(CR623)toHaddonAve.
DBNUM:11337/UPC:113370
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.Theprojectincludes;correctionsmadeto
deficienciesinthesidewalks,curbing,curbramps,intersections,andswalesandsomeinletswillbeconstructedtoeliminateponding.Guiderailwill
bebroughtuptocurrent
standards.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$19,500,000.
COUNTY: Atlantic
LEGISLATIVEDISTRICT: 2,9
MUNICIPALITY: MullicaTwp,AbseconCity,GallowayTwp
SPONSOR: NJDOT
MILEPOST(S): 36.450.82
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayRehabandRecon)
MPO
Phase
Fund
SJTPO
DES
NHPP
SJTPO
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.900
Total
$1.900
$9.500
$10.000
SectionIIIPage236
$19.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route30,IllinoisAvenue(CR631)toGrammercyAvenue
DBNUM:12403/UPC:124030
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$5,075,000.
COUNTY: Atlantic
LEGISLATIVEDISTRICT: 2
MUNICIPALITY: AbseconCity,AtlanticCity
SPONSOR: NJDOT
MILEPOST(S): 52.356.7
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
SJTPO
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$5.075
Total
$5.075
SectionIIIPage237
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route31,BridgeoverCSXRailroad
DBNUM:08355/UPC:083550
TheprojectincludesreplacementofthebridgeoverCSXRailroad,anewpavementboxwillbeconstructedseveralhundredfeeteithersideofthe
bridgeandreplacementoftheculvertatSeminaryCreek.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$12,500,000.
COUNTY: Mercer
LEGISLATIVEDISTRICT: 15
MUNICIPALITY: HopewellTwp,PenningtonBoro
SPONSOR: NJDOT
MILEPOST(S): 6.847.33
STRUCTURENO.: 1119150,1119151
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$7.000
$5.500
SectionIIIPage238
Total
$12.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route31,BridgeoverFurnaceBrook
DBNUM:09325/UPC:093250
TheproposedprojectconsistsoftotalreplacementofexistingRoute31bridgeoverFurnaceBrook.Inaddition,pedestrianfacilitiesonthebridgeand
attheadjacentRoute31/WallStreetintersectionwillbeupgradedtomeetthecurrentstandardsandADAcompliance.
Totalconstructionfundingneededisexpectedtobe$3,500,000.
COUNTY: Warren
LEGISLATIVEDISTRICT: 24
MUNICIPALITY: OxfordTwp
SPONSOR: NJDOT
MILEPOST(S): 46.83
STRUCTURENO.: 2111154
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.400
Total
$0.400
$0.250
$0.250
$3.500
SectionIIIPage239
$3.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route31,BryantsRoad(CR634)toRoute46
DBNUM:12422/UPC:124220
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$7,316,000.
COUNTY: Warren
LEGISLATIVEDISTRICT: 23,24
MUNICIPALITY: WashingtonTwp,WashingtonBoro,OxfordTwp,WhiteTwp
SPONSOR: NJDOT
MILEPOST(S): 40.943.2&46.148.9
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$7.316
Total
$7.316
SectionIIIPage240
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route31,BullRunRoadtoBranchofStoneyBrook
DBNUM:12401/UPC:124010
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$6,550,000.
COUNTY: Mercer,Hunterdon
LEGISLATIVEDISTRICT: 15
MUNICIPALITY: HopewellTwp,PenningtonBoro,EastAmwellTwp,West
AmwellTwp
SPONSOR: NJDOT
MILEPOST(S): 4.714.3
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
DVRPC
CON
NHPP
$5.472
$5.472
NJTPA
CON
NHPP
$1.078
$1.078
SectionIIIPage241
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route31,ChurchStreettoRiverRoad
DBNUM:08327/UPC:083270
WideningRt.31inbothdirectionsfromChurchSt.toRiverRd.Typicalcrosssectionwouldbetwolanesineachdirectionwithacenterturninglane.
ThisprojectalongwiththescaleddownFlemingtonBypass,nowknownastheSouthBranchParkway,arekeyelementsoftheRt.31IntegratedLand
Use&TransportationPlan(ILUTP).ImplementingtheRt.31WideningfirstdelaystheneedforthemoreexpensiveSouthBranchParkway,butinall
likelihooddoesnoteliminatethisneed.
Totalconstructionfundingneededisexpectedtobe$4,450,000.
COUNTY: Hunterdon
LEGISLATIVEDISTRICT: 16
MUNICIPALITY: RaritanTwp
SPONSOR: NJDOT
MILEPOST(S): 22.3025.30
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10A(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.750
Total
$0.750
$0.200
$0.200
$4.450
SectionIIIPage242
$4.450
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route31,FlemingtonCircletoPayneRoad
DBNUM:12409/UPC:124090
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$8,650,000.
COUNTY: Hunterdon
LEGISLATIVEDISTRICT: 23,16
MUNICIPALITY: ClintonTwp,FlemingtonBoro,RaritanTwp,ReadingtonTwp
SPONSOR: NJDOT
MILEPOST(S): NB:22.0223.84;SB:22.0225.13;27.0628.80
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$8.650
SectionIIIPage243
Total
$8.650
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route31,Route78/22toGraysrockRoad
DBNUM:11342A/UPC:148010
InitiatedfromthePavementManagementSystem,thisprojectwillreconstructpavementwithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$7,300,000.
COUNTY: Hunterdon
LEGISLATIVEDISTRICT: 23
MUNICIPALITY: ClintonTwp
SPONSOR: NJDOT
MILEPOST(S): 31.832.5
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayRehabandRecon)
MPO
Phase
Fund
NJTPA
PE
NHPP
NJTPA
DES
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.600
Total
$0.600
$0.600
$0.600
$7.300
SectionIIIPage244
$7.300
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route33&E.SanMarcoBoulevard
DBNUM:13338/UPC:133380
AProblemStatementwassubmittedtoNJDOTbyHowellTownshipinvolvingthelackofatrafficcontroldeviceattheTIntersectionofRoute33and
SanMarcoBoulevard(MP33.15),whichleadsintoanagerestrictedprivatedevelopment.
Totalconstructionfundingneededisexpectedtobe$3,130,000.
COUNTY: Monmouth
LEGISLATIVEDISTRICT: 30
MUNICIPALITY: HowellTwp
SPONSOR: NJDOT
MILEPOST(S): 33.1033.20
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NR2(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:SafetyImprovements)
MPO
Phase
Fund
NJTPA
PE
NHPP
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.400
Total
$0.400
$0.550
$0.550
$0.500
$0.500
$3.130
SectionIIIPage245
$3.130
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route33Business,BridgeoverConrailFreeholdSecondaryBranch
DBNUM:12379/UPC:123790
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethestructurallydeficientbridge.
Totalconstructionfundingneededisexpectedtobe$7,900,000.
COUNTY: Monmouth
LEGISLATIVEDISTRICT: 16
MUNICIPALITY: FreeholdTwp
SPONSOR: NJDOT
MILEPOST(S): 4.3004.400
STRUCTURENO.: 1336150
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
PE
NHPP
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.800
Total
$0.800
$0.800
$0.800
$0.500
$0.500
$7.900
SectionIIIPage246
$7.900
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route33,BentleyRoadtoManalapanBrook
DBNUM:12425/UPC:124250
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$9,200,000.
COUNTY: Middlesex,Monmouth
LEGISLATIVEDISTRICT: 14,12
MUNICIPALITY: MonroeTwp,MillstoneTwp,ManalapanTwp
SPONSOR: NJDOT
MILEPOST(S): EB17.721.9;WB17.720.7
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$9.200
SectionIIIPage247
Total
$9.200
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route33,BridgeoverMillstoneRiver
DBNUM:14422/UPC:144220
InitiatedfromtheBridgeManagementSystem,theprojectwillrehabilitate/replacethebridge.
Totalconstructionfundingneededisexpectedtobe$3,050,000.
COUNTY: Monmouth
LEGISLATIVEDISTRICT: 12
MUNICIPALITY: MillstoneTwp
SPONSOR: NJDOT
MILEPOST(S): 19.8
STRUCTURENO.: 1304151
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
PE
NHPP
NJTPA
DES
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.220
Total
$0.220
$0.450
$0.450
$3.050
SectionIIIPage248
$3.050
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route33,OperationalandPedestrianImprovements,Neptune
DBNUM:N09670/UPC:096700
Severalintersectionswarrantattention,asdoesthesegmentasawhole.Thebusyfourlaneundividedroadwaywithinaconstrainedrightofway
limitstheuniformapplicationofleftturnlanes.ImprovementsaresuggestedattheOxfordWay,WakefieldRoad,JerseyShoreMedicalCentermain
entranceandNeptuneBlvd.intersections,aswellasasegmentwideimprovementtopedestrianfacilitiesincludingrestriped,crosshatchedcrosswalks
andpedestriancountdownheads.Afurther
corridorwidetrafficstudyofNJSR33todeterminewhetherlanereconfigurationmightaidsafetyandprovideturnlanecapacityisalsosuggested.
Totalconstructionfundingneededisexpectedtobe$1,880,000.
COUNTY: Monmouth
LEGISLATIVEDISTRICT: 11
MUNICIPALITY: NeptuneCityBoro,NeptuneTwp
SPONSOR: NJDOT
MILEPOST(S): 40.4241.82
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): AQ2,O10A,NR2(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:SafetyImprovements)
MPO
Phase
Fund
NJTPA
CON
HSIP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.880
SectionIIIPage249
Total
$1.880
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route33,SchoolHouseRoadtoFortunatoPlace
DBNUM:12405/UPC:124050
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$1,880,000.
COUNTY: Monmouth
LEGISLATIVEDISTRICT: 11
MUNICIPALITY: NeptuneTwp
SPONSOR: NJDOT
MILEPOST(S): 37.939.9
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.880
SectionIIIPage250
Total
$1.880
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route33B,KondrupWaytoFairfieldRd
DBNUM:12410/UPC:124100
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$4,200,000.
COUNTY: Monmouth
LEGISLATIVEDISTRICT: 11,30
MUNICIPALITY: FreeholdTwp,HowellTwp
SPONSOR: NJDOT
MILEPOST(S): 3.996.89
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$4.200
SectionIIIPage251
Total
$4.200
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route34,BridgeoverformerFreeholdandJamesburgRailroad
DBNUM:11315/UPC:113150
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethestructurallydeficientandfunctionallyobsoletebridge,builtin1935.The
bridgeisaroadwaybottleneckatthislocationasRoute34narrowsatthebridgeresultinginsubstandardroadwaydimensionsacrossthebridge.
Roadwayapproachworkincludescorrectingsubstandardroadwaycrosssectionfeatures,aswellas,theverticalroadwayprofile.
Totalconstructionfundingneededisexpectedtobe$7,854,000.
COUNTY: Monmouth
LEGISLATIVEDISTRICT: 30
MUNICIPALITY: WallTwp
SPONSOR: NJDOT
MILEPOST(S): 1.431.85
STRUCTURENO.: 1307150
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
Total
$1.000
$0.489
$0.489
$7.854
SectionIIIPage252
$7.854
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route34,ColtsNeck,IntersectionImprovements(CR537)
DBNUM:96040/UPC:950315
InsupportoftheAccessManagementPlanforRt.34inColtsNeck,thisprojectwillprovideforoperational/safetyimprovementstotheintersectionof
StateRt.34andCountyRt.537.Thiswillincludeconsiderationsforbicycleandpedestrianactivities.Pleasenote:Thisisarevisit.Previouseffortsto
provideoperationalimprovementsatthisintersectionresultedinaschemethathadprohibitiveenvironmentalimpactsandveryhighcosts.
Totalconstructionfundingneededisexpectedtobe$10,037,000.
COUNTY: Monmouth
LEGISLATIVEDISTRICT: 11
MUNICIPALITY: ColtsNeckTwp
SPONSOR: NJDOT
MILEPOST(S): 12.9013.60
STRUCTURENO.: 1308152,1300A18
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NR1,NR2(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
NJTPA
CON
NHPP
$7.528
$7.528
NJTPA
CON
OTHER
$2.509
$2.509
SectionIIIPage253
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route34,CR537toWashingtonAve.,Pavement
DBNUM:11307/UPC:113070
InitiatedfromthePavementManagementSystem,thisprojectwillprovideafulldepthreconstructionandaddressguiderailsanddrainageissues.It
willincluderoadsideworktorestorethebermareasbacktoumbrellasections,earthworktoreestablisherodingslopesbehindtheguiderails,
upgradingofguiderails,repairingdamageddrainageandoutfallstructures,upgradingtrafficsignals,andsomebridgerepairwork.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$11,450,000.
COUNTY: Monmouth
LEGISLATIVEDISTRICT: 11,13,12
MUNICIPALITY: DealBoro,InterlakenBoro,AberdeenTwp
SPONSOR: NJDOT
MILEPOST(S): 13.226.5
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
$10.450
SectionIIIPage254
Total
$11.450
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route35,HeardsBrookandWoodbridgeCreek,CulvertReplacement
DBNUM:10381/UPC:103810
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacetheculvertwithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$4,000,000.
COUNTY: Middlesex
LEGISLATIVEDISTRICT: 19
MUNICIPALITY: WoodbridgeTwp,PerthAmboyCity
SPONSOR: NJDOT
MILEPOST(S): 55.24
STRUCTURENO.: 1224150,1224154
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:Culverts)
MPO
Phase
Fund
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.300
$0.300
$4.000
SectionIIIPage255
Total
$4.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route35,NorthofLincolnDrtoNavesinkRiverBridge
DBNUM:12308/UPC:123080
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacebothdirectionswithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$4,100,000.
COUNTY: Monmouth
LEGISLATIVEDISTRICT: 11
MUNICIPALITY: OceanTwp,ShrewsburyBoro,EatontownBoro,RedBankBoro SPONSOR: NJDOT
MILEPOST(S): 24.934.3
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$4.100
Total
$4.100
SectionIIIPage256
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route35,PerthAmboyConnector,BridgeSuperstructureReplacement
DBNUM:04360/UPC:043600
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethestructurallydeficientbridge.Incidentalroadwayapproachwork,including
milling&pavingandthereplacementoftheguiderail,inordertoupgradetocurrentstandardsasrequired,willalsobeincludedintheprojectas
needed.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$14,000,000.
COUNTY: Middlesex
LEGISLATIVEDISTRICT: 19
MUNICIPALITY: PerthAmboyCity
SPONSOR: NJDOT
MILEPOST(S): 52.1552.75
STRUCTURENO.: 1223153
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$7.000
$7.000
SectionIIIPage257
Total
$14.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route37,EBThomasSttoFisherBlvd
DBNUM:12404/UPC:124040
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$4,200,000.
COUNTY: Ocean
LEGISLATIVEDISTRICT: 10
MUNICIPALITY: TomsRiverTwp,IslandHeightsBoro
SPONSOR: NJDOT
MILEPOST(S): 6.8110.89
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$4.200
SectionIIIPage258
Total
$4.200
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route38,SouthChurchStreet(CR607)toFellowshipRoad(CR673),Operationaland
SafetyImprovements
DBNUM:12307/UPC:123070
ThepurposeofthisprojectistoreconfiguretheRoute38andSouthChurchStreet/FellowshipRd.intersectionlayout,improvecongestion,improve
safety,andensureADAcompliancethroughouttheintersection.InadditiontheexistingS.ChurchSt.Bridgewillbereplacedandwidened,
deficienciesinsidewalk,curbsandcurbrampswillbeaddressed.Theexistingshouldersandauxiliarylaneswillbebroughtintocompliancewith
NJDOTstandards.
Totalconstructionfundingneededisexpectedtobe$5,000,000.
COUNTY: Burlington
LEGISLATIVEDISTRICT: 7
MUNICIPALITY: MoorestownTwp
SPONSOR: NJDOT
MILEPOST(S): 7.537.59
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): 2025M(NonExempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
DVRPC
PE
NHPP
DVRPC
DES
NHPP
DVRPC
ROW
NHPP
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.500
Total
$1.500
$2.500
$2.500
$3.000
$3.000
$5.000
SectionIIIPage259
$5.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route40,AtlanticCounty,Drainage
DBNUM:08371/UPC:083710
ApproximatelyonemileofRt40/322willberaisedfrom2.5to4feetaboveexistingtoreduceflooding.Constructionwillincludenewpavement,new
curbsandsidewalks,relocationofaerialandundergroundutilitiesandnewdrainage.AtMilePost63.4,steelsheetingandnewdrainagewillbe
installed.
Totalconstructionfundingneededisexpectedtobe$10,200,000.
COUNTY: Atlantic
LEGISLATIVEDISTRICT: 2
MUNICIPALITY: EggHarborTwp,AtlanticCity
SPONSOR: NJDOT
MILEPOST(S): 60.463.5
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:Drainage)
MPO
Phase
Fund
SJTPO
PE
NHPP
SJTPO
DES
NHPP
SJTPO
ROW
NHPP
SJTPO
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.200
Total
$1.200
$1.400
$1.400
$1.000
$1.000
$10.200
SectionIIIPage260
$10.200
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route40,CR555Intersection,Operational&SafetyImprovements
DBNUM:12383/UPC:123830
Theoverallpurposeofthisprojectistoaddressoperational,physical,andsafetydeficienciesattheexistingintersection.Proposedimprovementsto
reconstructcornertogivelargerradiustoimproveright&Leftturnmovement&ConstructIslandtoprovidechannelizationaswellasincreasethe
shoulderwidth.
Totalconstructionfundingneededisexpectedtobe$2,100,000.
COUNTY: Gloucester
LEGISLATIVEDISTRICT: 3
MUNICIPALITY: FranklinTwp
SPONSOR: FranklinTownship(Gloucester)
MILEPOST(S): Rt40:30.130.4,CR555:21.421.6
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): R1(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
DVRPC
PE
NHPP
DVRPC
DES
NHPP
DVRPC
ROW
NHPP
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
Total
$1.000
$1.500
$1.500
$1.000
$1.000
$2.100
SectionIIIPage261
$2.100
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route40,ElmerLaketoElmwoodAvenue
DBNUM:12413/UPC:124130
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$6,650,000.
COUNTY: Gloucester,Salem
LEGISLATIVEDISTRICT: 3
MUNICIPALITY: UpperPittsgroveTwp,FranklinTwp
SPONSOR: NJDOT
MILEPOST(S): 20.624.8&26.027.4
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
CON
NHPP
$1.959
$1.959
SJTPO
CON
NHPP
$4.691
$4.691
SectionIIIPage262
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route40,NJTurnpiketoEQuillytownRd
DBNUM:12411/UPC:124110
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$3,410,000.
COUNTY: Salem
LEGISLATIVEDISTRICT: 3
MUNICIPALITY: CarneysPointTwp
SPONSOR: NJDOT
MILEPOST(S): EB3.45.7;WB1.75.7
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
SJTPO
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.410
SectionIIIPage263
Total
$3.410
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route40,WilsonAvenuetoRoute77
DBNUM:11421/UPC:114210
InitiatedfromthePavementManagementSystem,thisprojectwillreconstructandresurfacewithintheprojectlimits.Theprojectincludes;ADA
ramps,minorcurbrepair,bicyclecompatibilityimprovements,minordrainagework,signalupgradesandstriping.
Totalconstructionfundingneededisexpectedtobe$17,000,000.
COUNTY: Salem
LEGISLATIVEDISTRICT: 3
MUNICIPALITY: WoodstownBoro,PilesgroveTwp,UpperPittsgroveTwp
SPONSOR: NJDOT
MILEPOST(S): 10.8716.4
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayRehabandRecon)
MPO
Phase
Fund
SJTPO
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$17.000
SectionIIIPage264
Total
$17.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route40,WoodstownIntersectionImprovements
DBNUM:04308/UPC:043080
Thisprojectisdesignedtoimprovethesafetyandoperationoftheintersectionandpotentialworkwillincludetrafficsignalupgrade,islandremoval,
andsidewalks.Apreferredalternativeforbettertruckaccelerationthroughthesignalizedintersectionhasbeenselectedbythecommunity.
Totalconstructionfundingneededisexpectedtobe$1,380,000.
COUNTY: Salem
LEGISLATIVEDISTRICT: 3
MUNICIPALITY: WoodstownBoro
SPONSOR: NJDOT
MILEPOST(S): 10.4610.87
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NR1(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
SJTPO
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.380
SectionIIIPage265
Total
$1.380
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route40/322,MedianClosures,DelilahRoadtoEastFireRoad
DBNUM:196A5/UPC:068095
ThisprojectisabreakoutfromRoute40/322CologneAvetoFireRoad.ArecentcrashanalysisforRoute40/322MedianClosureDelilahRd.toFire
Rd.projectfromtheBureauofSafetyProgramsforyears20102012wascompleted.TheanalysisrevealstheneedforaConceptDevelopmentstudyto
addresssafetyconcernsfortheremainingpartoftheRoute40/322DelilahRd.toFireRd.
Totalconstructionfundingneededisexpectedtobe$4,200,000.
COUNTY: Atlantic
LEGISLATIVEDISTRICT: 2
MUNICIPALITY: HamiltonTwp,EggHarborTwp
SPONSOR: NJDOT
MILEPOST(S): 53.2158.11
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S6(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
SJTPO
PE
NHPP
SJTPO
DES
NHPP
SJTPO
ROW
NHPP
SJTPO
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.300
Total
$0.300
$0.700
$0.700
$0.100
$0.100
$4.200
SectionIIIPage266
$4.200
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route42,ArdmoreAvetoCamdenCountyLine,Pavement
DBNUM:12306/UPC:123060
InitiatedfromthePavementManagementSystem,thisprojectwillresurface,rehabilitateandreconstructwithintheprojectlimits.ADAcompliance
improvementswillbeincluded.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$14,000,000.
COUNTY: Gloucester
LEGISLATIVEDISTRICT: 4
MUNICIPALITY: WashingtonTwp
SPONSOR: NJDOT
MILEPOST(S): 3.46.6;3.46.1
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayRehabandRecon)
MPO
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
Phase
Fund
DVRPC
DES
NHPP
$2.500
$2.500
DVRPC
ROW
NHPP
$0.500
$0.500
DVRPC
CON
NHPP
$6.000
SectionIIIPage267
$8.000
$14.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route42,BridgesoverBlackwoodRailroadTrail
DBNUM:12313/UPC:123130
InitiatedfromtheBridgeManagementSystem,thetwoexistingthreespanbridges(Northbound&Southbound)willberemovedandreplacedwitha
precastarchsystem.Retainingwallswillbeconstructedtomaintainandlimitembankmentslope.Theprojectwillextendandwidentheacceleration
anddecelerationlanesandprovideshoulders.ITSfeatures,pedestrian/underpasslighting,andasecuritycamerawillbealsoprovidedinthisproject.
Totalconstructionfundingneededisexpectedtobe$7,000,000.
COUNTY: Camden
LEGISLATIVEDISTRICT: 4
MUNICIPALITY: GloucesterTwp
SPONSOR: NJDOT
MILEPOST(S): 10.21010.210
STRUCTURENO.: 0411162,0411161,0411160,0411159
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
DVRPC
DES
STATE
DVRPC
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$2.500
Total
$2.500
$7.000
SectionIIIPage268
$7.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route45,BridgeoverRaccoonCreek
DBNUM:14328/UPC:143280
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethebridgedeckandsuperstructureandprovidescourcountermeasuresto
addressthisscourcriticalstructure.
Totalconstructionfundingneededisexpectedtobe$1,574,000.
COUNTY: Gloucester
LEGISLATIVEDISTRICT: 5
MUNICIPALITY: HarrisonTwp
SPONSOR: NJDOT
MILEPOST(S): 17.73
STRUCTURENO.: 0807152
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:DeckRehabandReplacement)
MPO
Phase
Fund
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
DVRPC
DES
NHPP
$0.420
$0.420
DVRPC
ROW
NHPP
$0.080
$0.080
DVRPC
CON
STATE
$1.574
SectionIIIPage269
$1.574
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route45,BridgeoverWoodburyCreek
DBNUM:14348/UPC:143480
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethestructurallydeficientandfunctionallyobsoletebridge,builtin1892.
Totalconstructionfundingneededisexpectedtobe$3,500,000.
COUNTY: Gloucester
LEGISLATIVEDISTRICT: 5
MUNICIPALITY: WoodburyCity
SPONSOR: NJDOT
MILEPOST(S): 26.21
STRUCTURENO.: 0810150
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
DVRPC
PE
NHPP
DVRPC
DES
STATE
DVRPC
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.400
Total
$0.400
$0.800
$0.800
$3.500
SectionIIIPage270
$3.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route45,MainStreet(CR672)toChestnutStreet
DBNUM:14363/UPC:143630
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$10,900,000.
COUNTY: Gloucester,Salem
LEGISLATIVEDISTRICT: 3,5
MUNICIPALITY: WoodstownBoro,PilesgroveTwp,SouthHarrisonTwp,
HarrisonTwp
SPONSOR: NJDOT
MILEPOST(S): 9.5222.50
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
Fund
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
DVRPC
CON
STATE
$8.355
$8.355
SJTPO
CON
STATE
$2.545
$2.545
SectionIIIPage271
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route46,BergenBoulevardtoRoute124(BergenTurnpike)
DBNUM:12428/UPC:124280
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$4,530,000.
COUNTY: Bergen
LEGISLATIVEDISTRICT: 38,36
MUNICIPALITY: LodiBoro,HasbrouckHeightsBoro,TeterboroBoro,South
HackensackTwp
SPONSOR: NJDOT
MILEPOST(S): 66.9569.91
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$4.530
SectionIIIPage272
Total
$4.530
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route46,CanfieldAvenue
DBNUM:13316/UPC:133160
TheproposedprojectistowidenRoute46toaccommodatestandardlanewidthsandtoprovideanexclusiveleftturnlaneonthewestapproachof
theintersection(forturnsintotheshoppingcenter).Inaddition,theTownshiprequestedenhancedsafetyforpedestriancrossingoftheintersectionas
thereisaschoollocatednearby.
Totalconstructionfundingneededisexpectedtobe$2,500,000.
COUNTY: Morris
LEGISLATIVEDISTRICT: 25
MUNICIPALITY: MineHillTwp
SPONSOR: NJDOT
MILEPOST(S): 35.91
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10A(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(MultimodalPrograms:Bicycle/Pedestrian)
MPO
Phase
Fund
NJTPA
PE
STP
NJTPA
DES
STP
NJTPA
ROW
STP
NJTPA
CON
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.500
Total
$0.500
$1.000
$1.000
$0.200
$0.200
$2.500
SectionIIIPage273
$2.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route46,MainStreet/WoodstoneRoad(CR644)toRoute287,ITS
DBNUM:06366A/UPC:148040
Tobettermanageandimprovetrafficconditionsalongthecorridor,thefollowingconceptswillbeevaluatedintheCDphase:deploymentofITS
devicesthatwillcomplementpresentITSequipment,minorimprovementstoaddressroadwayconstraintswithoutrightofwayacquisition,and
updates/upgradestoexistingtrafficsignalequipment.
Totalconstructionfundingneededisexpectedtobe$5,750,000.
COUNTY: Morris
LEGISLATIVEDISTRICT: 25,26
MUNICIPALITY: RockawayBoro,DenvilleTwp,MountainLakesBoro,
ParsippanyTroyHillsTwp
SPONSOR: NJDOT
MILEPOST(S): 41.8746.47
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NR2,O7(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:IntelligentTransportationSystems)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.500
Total
$0.500
$5.750
SectionIIIPage274
$5.750
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route46,MainStreet/WoodstoneRoad(CR644)toRoute80
DBNUM:06366D/UPC:148070
InitiatedbytheBureauofITSEngineering,thisprojectisabreakoutfromRoute46,I80toI80/280,ITSImprovementsstudy.Thisprojectwillprovide
operationalandsafetyimprovementswithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$1,700,000.
COUNTY: Morris
LEGISLATIVEDISTRICT: 25
MUNICIPALITY: DenvilleTwp
SPONSOR: NJDOT
MILEPOST(S): 41.8742.29
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S7(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
ROW
STATE
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.800
Total
$0.800
$0.500
$0.500
$1.700
SectionIIIPage275
$1.700
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route46,PassaicAvenuetoWillowbrookMall
DBNUM:9233B3/UPC:009231
Route46willbewidenedbetweenPassaicAvenueandWillowbrookMall,fromfourlanestosixlanes,toaddressexistingtrafficoperations
deficiencies.TheRt.46eastboundbridgeoverthePassaicRiverwillbereplacedtoaddressstructural,trafficoperationalandsafetydeficiencies.Four
signstructuresalsowillbeconstructed.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$24,200,000.
COUNTY: Essex,Passaic
LEGISLATIVEDISTRICT: 26,40
MUNICIPALITY: FairfieldTwp,WayneTwp
SPONSOR: NJDOT
MILEPOST(S): 54.9655.56
STRUCTURENO.: 0722156,0722157,0722158,1606411
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): 2020M(NonExempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:BottleneckWidening)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$10.000
$14.200
SectionIIIPage276
Total
$24.200
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route46,Route163toWaterStreet(CR620)
DBNUM:11340/UPC:113400
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacebothdirectionswithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$5,000,000.
COUNTY: Warren
LEGISLATIVEDISTRICT: 24
MUNICIPALITY: KnowltonTwp,WhiteTwp
SPONSOR: NJDOT
MILEPOST(S): 2.47.05
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$5.000
Total
$5.000
SectionIIIPage277
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route46,Route23(PomptonAvenue)toRoute20,ITS
DBNUM:06366C/UPC:148060
Tobettermanageandimprovetrafficconditionsalongthecorridor,thefollowingconceptswillbeevaluatedintheCDphase:deploymentofITS
devicesthatwillcomplementpresentITSequipment,minorimprovementstoaddressroadwayconstraintswithoutrightofwayacquisition,and
updates/upgradestoexistingtrafficsignalequipment.
Totalconstructionfundingneededisexpectedtobe$5,750,000.
COUNTY: Passaic
LEGISLATIVEDISTRICT: 40,36,34
MUNICIPALITY: WayneTwp,TotowaBoro,LittleFallsTwp,CliftonCity
SPONSOR: NJDOT
MILEPOST(S): 55.9863.85
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NR2,O7(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:IntelligentTransportationSystems)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.500
Total
$0.500
$5.750
SectionIIIPage278
$5.750
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route46,Route287toRoute23(PomptonAvenue),ITS
DBNUM:06366B/UPC:148050
Tobettermanageandimprovetrafficconditionsalongthecorridor,thefollowingconceptswillbeevaluatedintheCDphase:deploymentofITS
devicesthatwillcomplementpresentITSequipment,minorimprovementstoaddressroadwayconstraintswithoutrightofwayacquisition,and
updates/upgradestoexistingtrafficsignalequipment.
Totalconstructionfundingneededisexpectedtobe$5,750,000.
COUNTY: Morris,Essex,Passaic
LEGISLATIVEDISTRICT: 26,40
MUNICIPALITY: ParsippanyTroyHillsTwp,MontvilleTwp,FairfieldBoro,
WayneTwp
SPONSOR: NJDOT
MILEPOST(S): 46.4755.98
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NR2,O7(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:IntelligentTransportationSystems)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.500
Total
$0.500
$5.750
SectionIIIPage279
$5.750
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route46,Route80toWalnutRoad
DBNUM:11340A/UPC:148100
InitiatedfromthePavementManagementSystem,thisprojectwillreconstructpavementwithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$7,500,000.
COUNTY: Warren
LEGISLATIVEDISTRICT: 24
MUNICIPALITY: KnowltonTwp
SPONSOR: NJDOT
MILEPOST(S): 01.4
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayRehabandRecon)
MPO
Phase
Fund
NJTPA
PE
NHPP
NJTPA
DES
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.600
Total
$0.600
$0.800
$0.800
$7.500
SectionIIIPage280
$7.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route46,SandShoreRoad/NaughrightRoadtoWoodsEdgeAv(CR649)
DBNUM:14368/UPC:143680
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$3,550,000.
COUNTY: Morris
LEGISLATIVEDISTRICT: 24
MUNICIPALITY: MountOliveTwp
SPONSOR: NJDOT
MILEPOST(S): 24.627.11
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.550
Total
$3.550
SectionIIIPage281
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route46,ValleyRoad(CR621)toPassaicRiver,Drainage
DBNUM:11367/UPC:113670
ThisprojectisaConceptDevelopmentstudytodeterminethemostefficientandeffectivemethodsforaddressingchronicfloodingproblems.This
location;hashad62floodingincidentsin6years,isranked22outof232forfloodingand94outof131(@MP61.6)foricingincidentsinthe2012
DrainageManagementSystem.
Totalconstructionfundingneededisexpectedtobe$4,750,000.
COUNTY: Passaic
LEGISLATIVEDISTRICT: 34
MUNICIPALITY: CliftonCity
SPONSOR: NJDOT
MILEPOST(S): 59.9863.95
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S4(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:Drainage)
MPO
Phase
Fund
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.100
$0.100
$4.750
SectionIIIPage282
Total
$4.750
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route47(RioGrandeAvenue),ParkBoulevardtoGeorgeReddingBridge
DBNUM:S1414/UPC:143990
Roadwayresurfacinganddrainageimprovementswithintheexistingrightofway.
Totalconstructionfundingneededisexpectedtobe$1,712,000.
COUNTY: CapeMay
LEGISLATIVEDISTRICT: 1
MUNICIPALITY: WildwoodCity,LowerTwp
SPONSOR: CapeMayCounty
MILEPOST(S): 0.400.80
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
SJTPO
CON
STPSJ
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.712
Total
$1.712
SectionIIIPage283
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route47,BridgeoverRoute295
DBNUM:15310/UPC:153100
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethebridgesuperstructure.
Totalconstructionfundingneededisexpectedtobe$6,400,000.
COUNTY: Gloucester
LEGISLATIVEDISTRICT: 21
MUNICIPALITY: WestvilleBoro
SPONSOR: NJDOT
MILEPOST(S): 74
STRUCTURENO.: 0815150
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): SDX(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
DVRPC
PE
NHPP
DVRPC
DES
NHPP
DVRPC
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.500
Total
$0.500
$1.500
$1.500
$6.400
SectionIIIPage284
$6.400
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route47,CR552(W.ShermanAvenue)toRoute56(LandisAvenue)
DBNUM:14374/UPC:143740
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$2,100,000.
COUNTY: Cumberland
LEGISLATIVEDISTRICT: 1
MUNICIPALITY: VinelandCity
SPONSOR: NJDOT
MILEPOST(S): 43.8546.60
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
SJTPO
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$2.100
SectionIIIPage285
Total
$2.100
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route47,GroveSt.toRoute130,Pavement
DBNUM:12305/UPC:123050
InitiatedfromthePavementManagementSystem,thisprojectwillresurface,rehabilitateandreconstructwithintheprojectlimits.Theprojectwill
updatetheADArequirements,andcorrectaculvertwhichcausesafloodingcondition.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$20,900,000.
COUNTY: Gloucester
LEGISLATIVEDISTRICT: 3,4,5
MUNICIPALITY: GlassboroBoro,WestvilleBoro,DeptfordTwp
SPONSOR: NJDOT
MILEPOST(S): 62.375.2
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayRehabandRecon)
MPO
Phase
Fund
DVRPC
DES
STP
DVRPC
CON
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$2.500
Total
$2.500
$7.900
SectionIIIPage286
$13.000
$20.900
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route47,NummytownMillPondDam
DBNUM:12320/UPC:123200
InitiatedfromtheBridgeManagementSystem,thisclass2damhasinsufficientspillwaycapacity,asrequiredbytheNewJerseysafetystandards,and
isasignificanthazard.ThedamrequiresrehabilitationtoachievecompliancewiththeNewJerseyDamSafetystandards.
Totalconstructionfundingneededisexpectedtobe$1,400,000.
COUNTY: CapeMay
LEGISLATIVEDISTRICT: 1
MUNICIPALITY: MiddleTwp
SPONSOR: NJDOT
MILEPOST(S): 5.245.24
STRUCTURENO.: 0507199
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:Dams)
MPO
Phase
Fund
SJTPO
DES
NHPP
SJTPO
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.425
Total
$0.425
$1.400
SectionIIIPage287
$1.400
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route47/130,Drainage&BigTimberCreekBridgeReplacement
DBNUM:11371/UPC:113710
Thisprojectwilladdressdrainageissues(identifiedbytheDrainageManagementSystem)withintheprojectlimits,andwillprovideforthe
replacementsoftheRoute47andRoute130bridgesoverBigTimberCreek,builtin1934and1928,respectively.
Totalconstructionfundingneededisexpectedtobe$28,300,000.
COUNTY: Gloucester,Camden
LEGISLATIVEDISTRICT: 5
MUNICIPALITY: WestvilleBoro,BrooklawnBoro
SPONSOR: NJDOT
MILEPOST(S): 74.875.2
STRUCTURENO.: 1203153
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
DVRPC
DES
STATE
DVRPC
ROW
STATE
DVRPC
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.000
Total
$3.000
$3.300
$3.300
$28.300
SectionIIIPage288
$28.300
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route47/347andRoute49/50CorridorEnhancement
DBNUM:2149F1/UPC:018291
ThisprojectwillimplementIntelligentTransportationSystem(ITS)strategiesandalleviatesummertrafficcongestionintheRt.47/347andRt.49/50
Corridors.Theproposedprojectincludetheconstructionof9DynamicMessagesignsand3CCTVCamerasalongroadwaysinCapeMayand
CumberlandCounty.Inaddition,theprojectincludetheinterconnectionoftrafficlightsalongRoute47inDennisTownship.
Totalconstructionfundingneededisexpectedtobe$3,800,000.
COUNTY: CapeMay,Cumberland
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): Rt.47:17.522;3235;Rt.347:08.33
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10A(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
SJTPO
ROW
CMAQ
SJTPO
CON
CMAQ
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.200
Total
$0.200
$3.800
SectionIIIPage289
$3.800
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route49,BridgeoverMauriceRiver
DBNUM:15314/UPC:153140
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethebridge.
Totalconstructionfundingneededisexpectedtobe$7,430,000.
COUNTY: Cumberland
LEGISLATIVEDISTRICT: 1
MUNICIPALITY: MillvilleCity
SPONSOR: NJDOT
MILEPOST(S): 36.2
STRUCTURENO.: 0605151
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
SJTPO
PE
NHPP
SJTPO
DES
NHPP
SJTPO
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.800
Total
$0.800
$0.800
$0.800
$7.430
SectionIIIPage290
$7.430
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route49,BuckshutemRoad,IntersectionImprovements(CR670)
DBNUM:95017/UPC:950390
TheRt.49projectlocationisasixleggedintersectionexhibitingsubstandardgeometricfeatures,safetyandoperationalproblems.Theproposed
projectcreatesanew4leggedintersectionandrealigns2localroutes,thatoriginallyconnectedtoRt.49,toimprovesafety.
Totalconstructionfundingneededisexpectedtobe$5,550,000.
COUNTY: Cumberland
LEGISLATIVEDISTRICT: 3
MUNICIPALITY: BridgetonCity
SPONSOR: NJDOT
MILEPOST(S): 26.2526.70
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): 2020(NonExempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:SafetyImprovements)
MPO
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
Phase
Fund
SJTPO
DES
STP
$0.850
$0.850
SJTPO
ROW
STP
$2.200
$2.200
SJTPO
UTI
STATE
SJTPO
CON
STATE
$1.000
$1.000
$5.550
SectionIIIPage291
$5.550
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route49,SarahRunDrivetoGarrisonLane,Pavement
DBNUM:11423/UPC:114230
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$9,240,000.
COUNTY: Cumberland
LEGISLATIVEDISTRICT: 1,3
MUNICIPALITY: Various
SPONSOR: NJDOT
MILEPOST(S): 18.7827.00;31.4040.12
STRUCTURENO.: Various
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
SJTPO
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$9.240
Total
$9.240
SectionIIIPage292
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route49,EstelleManorDrivetoDamRoad
DBNUM:14367/UPC:143670
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.ThisisaMillXPaveXproject.
Totalconstructionfundingneededisexpectedtobe$3,200,000.
COUNTY: Atlantic,Cumberland
LEGISLATIVEDISTRICT: 1
MUNICIPALITY: MauriceRiverTwp,EstellManorCity
SPONSOR: NJDOT
MILEPOST(S): 44.249.8
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
SJTPO
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.200
SectionIIIPage293
Total
$3.200
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route52,CausewayReplacement,ContractA
DBNUM:244/UPC:961653
Thisprojectwillprovideforthereplacementof1.2milesoftheinteriorportionoftheexistingRt.52CausewaybetweenElbowIslandandVisitor
CenterIslandinbothdirections.ThebridgesbeingreplacedinthiscontractareElbowThorofareandRainbowThorofare.Thisportionofthenew
bridgewillbealowerlevelstructure(i.e.approximately15feetto20feetabovethewater).Inaddition,aspartofthisproject,accessrampswillbe
constructeddownontoRainbowIslandinbothdirectionsforfishingandrecreationalaccess.ThesouthboundbridgetowardOceanCitywillcontaina
10footmultiusesidewalkforbicycleaswellaspedestrianuseandwillbeseparatedfromtrafficwithanapprovedtrafficbarriersystem.
TheconstructionofContractAisfundedunderthefederalGARVEEprogram.StateBondshavebeenissuedtoprovidethenecessarycashtoaward
thecontract.Repaymentofthebonds(plusinterest)willbeprovidedfromanticipatedfuturefederalapportionmentsovera12yearperiod.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$192,920,000.
COUNTY: CapeMay
LEGISLATIVEDISTRICT: 1
MUNICIPALITY: OceanCity
SPONSOR: NJDOT
MILEPOST(S): 0.211.76
STRUCTURENO.: 0511152,0511151
FINANCIALPLANREQUIREMENT: Thisprojectispartofaprojectwithatotalcostbetween$100and$500millionprogrammedtoreceivefederal
financialassistanceandanannualfinancialmanagementplanisrequiredtobeprepared.
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
SJTPO
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$14.900
$8.900
SectionIIIPage294
Total
$23.800
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route53,PondviewRoadtoHallAvenue
DBNUM:12424/UPC:124240
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$3,125,000.
COUNTY: Morris
LEGISLATIVEDISTRICT: 26,25
MUNICIPALITY: ParsippanyTroyHillsTwp,DenvilleTwp
SPONSOR: NJDOT
MILEPOST(S): 1.94.5
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
PE
STP
NJTPA
DES
STP
NJTPA
CON
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.500
Total
$0.500
$0.750
$0.750
$3.125
SectionIIIPage295
$3.125
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route54,Route322overCapeMayPointBranch,ContractB
DBNUM:01339A/UPC:148020
EnvironmentalmitigationforRoute54,Route322overCapeMayPointBranchproject.Duetoprojectassociatedimpacts,requirestheNJDOTto
purchaselandforplantingsofvegetationandtreesduetooveralllanddisturbancesduetotheprojectinaccordancewithNJDEPriparianand
reforstationmitigationrequirements.
Totalconstructionfundingneededisexpectedtobe$784,000.
COUNTY: Atlantic
LEGISLATIVEDISTRICT: 2
MUNICIPALITY: FolsomBoro
SPONSOR: NJDOT
MILEPOST(S): 6.26.9
STRUCTURENO.:
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O5(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
SJTPO
CON
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.784
Total
$0.784
SectionIIIPage296
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route55,SBSchoonerLandingRoadtoShermanAvenue
DBNUM:11343A/UPC:138010
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacebothdirectionswithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$8,204,000.
COUNTY: Cumberland
LEGISLATIVEDISTRICT: 1
MUNICIPALITY: MillvilleCity,VinelandCity
SPONSOR: NJDOT
MILEPOST(S): 21.826.5
STRUCTURENO.: 0609152,0609154,0609156,0609058
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayRehabandRecon)
MPO
Phase
Fund
SJTPO
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$8.204
Total
$8.204
SectionIIIPage297
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route57,CR519IntersectionImprovement
DBNUM:97062B/UPC:028091
TheprojectwillprovideoperationalandsafetyimprovementsattheRt.57andCR519intersection.Theintersectionapproacheswillbewidenedto
provideturninglanesandshoulders.TheprojectincludesreplacementoftwostructuresovertheLopatcongCreek;theexistingbridges,onRt.57,
immediatelytotheeastoftheintersectionandonRt.519,immediatelytothenorthoftheintersectionwillbedemolishedandreconstructedfurther
awayfromtheimmediatevicinityoftheintersection.Inordertoaccomplishthis,theLopatcongCreekwillalsoberelocated.
Totalconstructionfundingneededisexpectedtobe$9,300,000.Thefollowingspecialfederalappropriationshavebeenallocatedforthisproject
$1,300,000(NJ088);$2,163,186(NJ225).
COUNTY: Warren
LEGISLATIVEDISTRICT: 23
MUNICIPALITY: LopatcongTwp
SPONSOR: NJDOT
MILEPOST(S): 1.401.60
STRUCTURENO.: 2101031,2105152
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NR3(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
NJTPA
DES
DEMO
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.600
Total
$0.600
$0.900
$0.900
$0.900
$0.900
$9.300
SectionIIIPage298
$9.300
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route57,LopatcongCreek,CulvertReplacement
DBNUM:11351/UPC:113510
Theexistingculvert(structurenumber2105151)(onatributarytoLopatcongCreek),isafoursided,reinforcedconcreteculvert,whichwas
constructedin1921.Theculvertisinneedofrepairorreplacementgivenitspoorstructuralcondition.Giventhepoorconditionoftheculvertsroof
slab,theculverthaslowloadratings.Theculvertalsohasinadequatedeckgeometryandsubstandardguiderailendterminals.ThroughtheConcept
Developmentphase,theDepartmentisidentifyingandevaluatingoptions,suchasculvertreplacement(e.g.,threesidedversusfoursidedculverts)
andrepairoptions,toaddressthoseidentifieddeficiencies.
Totalconstructionfundingneededisexpectedtobe$1,750,000.
COUNTY: Warren
LEGISLATIVEDISTRICT: 23
MUNICIPALITY: LopatcongTwp
SPONSOR: NJDOT
MILEPOST(S): 0.20.3
STRUCTURENO.: 2105151
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S4(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:Culverts)
MPO
Phase
Fund
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.200
$0.200
$1.750
SectionIIIPage299
Total
$1.750
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route57,PortMurrayRd(CR629)toClaremontRd
DBNUM:12423/UPC:124230
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$3,150,000.
COUNTY: Warren
LEGISLATIVEDISTRICT: 23
MUNICIPALITY: MansfieldTwp
SPONSOR: NJDOT
MILEPOST(S): 14.518.7
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.150
Total
$3.150
SectionIIIPage300
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route57,Route22toRoute31
DBNUM:14372/UPC:143720
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$7,700,000.
COUNTY: Warren
LEGISLATIVEDISTRICT: 23
MUNICIPALITY: LopatcongTwp,GreenwichTwp,FranklinTwp,Washington
Twp
SPONSOR: NJDOT
MILEPOST(S): 0.011.06
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$2.900
$4.800
SectionIIIPage301
Total
$7.700
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route57/182/46,HackettstownMobilityImprovements
DBNUM:9237/UPC:950409
TheprojectwillhelprelievecongestionatfourintersectionslocatedonacongestedcommutercorridorinWarrenCounty.SubstandardADAfeatures
ateachintersectionwillalsobeupgraded.ThreeoftheintersectionsareontheCongestionManagementSystem(CMS)listofhighneedintersections.
US46andEastAve.CurbradiuswillbewidenedontheSoutheastquadrantoftheintersection.Revisedsignalphasingwillprovidearightturn
overlapphasefortheNorthboundEastAve.approachrightturnmovementontoUS46.
US46andNJ182(MountainAve.)/WillowGroveSt./WarrenSt.Trafficsignalswillberetimed.
US46andHighStreet/GrandAve.RealigntheHighSt.Southboundapproachtoimprovetrafficflow.
NJ57andNJ182Willbereconfiguredtoallowaleftturnlaneandasharedleft/through/rightturnlaneontheEastboundNJ57approachtothe
intersection.
Totalconstructionfundingneededisexpectedtobe$4,000,000.
COUNTY: Warren,Morris
LEGISLATIVEDISTRICT: 23,25
MUNICIPALITY: HackettstownTown,WashingtonTwp
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10A(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
NJTPA
ROW
CMAQ
NJTPA
CON
CMAQ
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.500
Total
$0.500
$4.000
SectionIIIPage302
$4.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route66,JumpingBrookRoadtoBowneRoad/WaysideRoad
DBNUM:14357/UPC:143570
IdentifiedbythePavement,Congestion,andSafetyManagementSystems,thisprojectwilladdresspavementdeficiencies,andimprovetraffic
operationsandsafety,withintheprojectlimits.Theroadwaywillbewidenedtoestablishtwolanesineachdirection,withconstructionofagrass
median,tobeconsistentwiththerestoftheRt.66Corridor.
Totalconstructionfundingneededisexpectedtobe$5,700,000.
COUNTY: Monmouth
LEGISLATIVEDISTRICT: 11
MUNICIPALITY: NeptuneTwp
SPONSOR: NJDOT
MILEPOST(S): 0.972.45
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
PE
NHPP
NJTPA
DES
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.100
Total
$1.100
$1.200
$1.200
$5.700
SectionIIIPage303
$5.700
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route70,BridgeoverMountMiseryBrook
DBNUM:15321/UPC:153210
InitiatedbytheBridgeManagementSystem,thisstudywilldeterminewhethertheprojectwillbealimitedscopedeck/superstructure,orfullscope
bridge,replacement.
Totalconstructionfundingneededisexpectedtobe$6,500,000.
COUNTY: Burlington
LEGISLATIVEDISTRICT: 8
MUNICIPALITY: PembertonTwp
SPONSOR: NJDOT
MILEPOST(S): 30.6
STRUCTURENO.: 0311151
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
DVRPC
DES
NHPP
DVRPC
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.890
Total
$0.890
$6.500
SectionIIIPage304
$6.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route70,EastofNorthBranchRoadtoCR539
DBNUM:10307/UPC:103070
InitiatedbythePavementManagementSystem,thisprojectproposesapavementrehabilitationstrategythatwillprovideformillingandoverlayto
eithermatchexistinggradeorprovidea2to3inchincrease.
Totalconstructionfundingneededisexpectedtobe$16,500,000.
COUNTY: Burlington,Ocean
LEGISLATIVEDISTRICT: 8,10
MUNICIPALITY: PembertonTwp,ManchesterTwp
SPONSOR: NJDOT
MILEPOST(S): 31.238.45
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayRehabandRecon)
MPO
Phase
Fund
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
DVRPC
DES
NHPP
$0.369
$0.369
NJTPA
DES
NHPP
$0.831
$0.831
DVRPC
CON
NHPP
$5.075
$5.075
NJTPA
CON
NHPP
$11.425
$11.425
SectionIIIPage305
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route70,RedLionRoad(CR685)toDakotaTrail,Pavement
DBNUM:11411/UPC:114110
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.Theprojectincludescenterlinerumblestripsand
improvementstoguiderails,paintedcrosswalks,trafficsignalsandhandicappedramps.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$11,754,000.
COUNTY: Burlington
LEGISLATIVEDISTRICT: 8
MUNICIPALITY: SouthamptonTwp,WoodlandTwp
SPONSOR: NJDOT
MILEPOST(S): 18.027.7
STRUCTURENO.: 0310154,0310155,0311150
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayRehabandRecon)
MPO
Phase
Fund
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$4.000
$7.754
SectionIIIPage306
Total
$11.754
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route70,Route38toCropwellRoad
DBNUM:11338/UPC:113380
Thisprojectconsistsofmilling,resurfacing,reconstructing,andrehabilitatingthemainlineandshoulderpavementinboththeEastboundand
Westbounddirections.Rampsandcrossroadswithintheprojectlimitsarealsoincludedinthescopeorwork.Theprojectistomillandresurfacethe
majorityofRt.70withafulldepthpavementreconstructionforcertainsectionsoftheroadwaywherethepavementisinpoorcondition.
Inaddition,theexistingculvertatCropwellsBrookistobereplaced.Theproposedculvertwillaccommodatea25yearstorm.Drainage
improvementsincludetheconstructionofadditionalinletsandpiping,increasingthesizeofexistingpiping,installationofunderdrainsinselectareas,
andtheinstallationofatidecontrolcheckvalve.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$36,707,000.
COUNTY: Camden,Burlington
LEGISLATIVEDISTRICT: 6,8
MUNICIPALITY: PennsaukenTwp,CherryHillTwp,EveshamTwp
SPONSOR: NJDOT
MILEPOST(S): 0.007.7
STRUCTURENO.: 0414150
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayRehabandRecon)
MPO
Phase
Fund
DVRPC
DES
NHPP
DVRPC
ROW
NHPP
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$4.000
Total
$4.000
$2.000
$2.000
$18.430
SectionIIIPage307
$18.277
$36.707
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route71,MainAvetoCedarAve,Pavement
DBNUM:11379/UPC:113790
InitiatedfromthePavementManagementSystem.Theexistingpavementconditionisgenerallyverypoorexhibitingverylargedeflectionsinsome
sectionsandseverelydeterioratedpatches,potholes,fatiquecrackinginothersections.Theproposedpavementrecommendationconsistsofremoving
theexistingpavementandreconstructingvariouslocationsandresurfacingthecentersection.
Totalconstructionfundingneededisexpectedtobe$9,800,000.
COUNTY: Monmouth
LEGISLATIVEDISTRICT: 11
MUNICIPALITY: AsburyParkCity,LochArbourVillage,AllenhurstBoro,
NeptuneCity
SPONSOR: NJDOT
MILEPOST(S): 7.879.92
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayRehabandRecon)
MPO
Phase
Fund
NJTPA
CON
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$9.800
Total
$9.800
SectionIIIPage308
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route71,WyckoffRoad,CR547
DBNUM:HP01001/UPC:018080
ThisprojectwillprovideintersectionimprovementsatRt.71andWycoffRoad.ImprovementswillincludewideningofRt.71andtheprovisionofa
trafficsignal.Theoutsidelaneswillbemadebicyclecompatible.Sidewalkswillbereconstructed.
ThefollowingspecialFederalappropriationwasallocatedtothisproject.FY2001/Section378/45A$149,670
Totalconstructionfundingneededisexpectedtobe$3,400,000.
COUNTY: Monmouth
LEGISLATIVEDISTRICT: 11
MUNICIPALITY: EatontownBoro
SPONSOR: NJDOT
MILEPOST(S): 15.6215.84
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NR3(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
NJTPA
DES
STP
NJTPA
ROW
STP
NJTPA
CON
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.500
Total
$0.500
$0.600
$0.600
$3.400
SectionIIIPage309
$3.400
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route72,AshRoadtoMarshaDrive
DBNUM:12427/UPC:124270
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$7,621,000.
COUNTY: Ocean
LEGISLATIVEDISTRICT: 9
MUNICIPALITY: StaffordTwp
SPONSOR: NJDOT
MILEPOST(S): 18.521.73&22.5425.38
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$7.621
SectionIIIPage310
Total
$7.621
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route72,EastRoad
DBNUM:94071A/UPC:001010
Initiatedbythe(former)BureauofTransportationandCorridorAnalysiswithintheDivisionofStatewidePlanning,thisprojectwillinclude;barrier
curbing,medianwidening,10footshoulders,andintersectionimprovementstoimprovegeometry,whileminimizingRightofWayimpacts.Anew
reversejughandlewillbeconstructedfromRoute72WestboundtotherelocatedEastRd.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$12,000,000.Thefollowingspecialfederalappropriations
havebeenallocatedforthisproject$499,915(NJ303).
COUNTY: Ocean
LEGISLATIVEDISTRICT: 9
MUNICIPALITY: StaffordTwp
SPONSOR: NJDOT
MILEPOST(S): 21.7322.54
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): 2020M(NonExempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
NJTPA
UTI
NHPP
$4.200
$4.200
NJTPA
CON
DEMO
$0.500
$0.500
NJTPA
CON
NHPP
$0.500
$11.000
SectionIIIPage311
$11.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route72,ManahawkinBayBridges,Contract1A&1B
DBNUM:11385/UPC:113850
Contract1AwillincludeRt.72andMarshaDriveIntersectionImprovements,reconstructionandwideningofRt.72andMarshaDrive,and
reconstructionofatrafficsignal.Theprojectalsoincludestheinstallationofnewstormdrainagesystems,adetentionbasin,ITSimprovements,
highwaylightingandutilityrelocations.
Contract1BwillincludeoperationalandsafetyimprovementsinShipBottomBorough,onLongBeachIsland.Approx.3000’feetofRt.72(locally
knownas8thand9thStreets)andthreecrossroads(BarnegatAvenue,CentralAvenueandLongBeachBoulevard)willbewidened.Twowaytraffic
willberestoredalongBarnegatAvenue,CentralAvenueandLongBeachBoulevard.Fivetrafficsignalswillbereconstructed.Anewtrafficsignalwill
beinstalledattheintersectionof8thStreetandLongBeachBoulevard.InordertoreducefrequentfloodingalongRt.72andtheintersections,anew
stormdrainagesystemandapumpstationalongwithasandfilterwillbeinstalled.Theprojectalsoincludestheinstallationofbicycleandpedestrian
accommodations,ITSimprovements,highwaylightingandutilityrelocations.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$39,461,000.
COUNTY: Ocean
LEGISLATIVEDISTRICT: 9
MUNICIPALITY: StaffordTwp,BarnegatTwp,ShipBottomBoro
SPONSOR: NJDOT
MILEPOST(S): 25.3826.14
28.2428.74
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT: Thisprojectispartofaprojectwithatotalcostbetween$100and$500millionprogrammedtoreceivefederal
financialassistanceandanannualfinancialmanagementplanisrequiredtobeprepared.
AIRQUALITYCODE(NONEXEMPT/EXEMPT): 2020M(NonExempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$16.219
$19.116
SectionIIIPage312
$4.126
Total
$39.461
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route72,ManahawkinBayBridges,Contract4
DBNUM:00357C/UPC:118014
Contract4willincludemajorRehabilitationoftheexistingRoute72BridgeoverManahawkinBay.TheentireexistingsuperstructureforBayBridge
willberemovedandreplaced,whileretainingandrehabilitatingtheexistingsubstructure.Thesuperstructurewidthwillbereducedasitwill
primarilybeusedforwestboundtrafficonly.Theprojectwillalsoincludethereconstructionofbridgeapproachroadways,bicycleandpedestrian
accommodations,newstormdrainagesystems,ITSimprovements,highwaylighting,fendersystems,bulkheadrepairs,andutilityrelocations.The
trestlebridgestructure#1513151overHillardsThorofarewillalsoberehabilitatedunderthiscontract.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$105,866,000.
COUNTY: Ocean
LEGISLATIVEDISTRICT: 9
MUNICIPALITY: StaffordTwp
SPONSOR: NJDOT
MILEPOST(S): 26.1427.50
STRUCTURENO.: 1513151,1513152
FINANCIALPLANREQUIREMENT: Thisprojectispartofaprojectwithatotalcostbetween$100and$500millionprogrammedtoreceivefederal
financialassistanceandanannualfinancialmanagementplanisrequiredtobeprepared.
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$7.632
$36.753
$32.269
$23.221
SectionIIIPage313
$5.991
Total
$105.866
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route73,CR721toNJTransitBridge
DBNUM:12418/UPC:124180
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.Guiderailwillbereplaced,handicappedramps
andcrosswalkswillbeinstalledandtrafficsignalswillbeupgraded.
Totalconstructionfundingneededisexpectedtobe$12,429,000.
COUNTY: Camden
LEGISLATIVEDISTRICT: 4
MUNICIPALITY: WinslowTwp
SPONSOR: NJDOT
MILEPOST(S): 8.915.90
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$12.429
SectionIIIPage314
Total
$12.429
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route76,BridgesoverRoute130
DBNUM:11326A/UPC:148090
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethebridgedeckontheRoute76overRoute130Northboundbridgeandreplace
thesuperstructuresoftheRamptoRoute76NorthboundoverRoute130SouthboundandtheRoute76over130Southboundbridge.
Totalconstructionfundingneededisexpectedtobe$19,500,000.
COUNTY: Camden
LEGISLATIVEDISTRICT: 5
MUNICIPALITY: GloucesterCity
SPONSOR: NJDOT
MILEPOST(S): 0.71.2
STRUCTURENO.: 0417155,0417156,0417157
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
DVRPC
PE
NHPP
DVRPC
DES
NHPP
DVRPC
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.500
Total
$1.500
$3.500
$3.500
$19.500
SectionIIIPage315
$19.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route76/676,BridgeDeckReplacements
DBNUM:11326/UPC:113260
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethebridgedecksonthreestructures:76/676overtheMainBranchoftheNewton
Creek;Route76overNicholsonRoad;and676SouthboundovertheMainBranchoftheNewtonCreek.ThesuperstructureofRoute76overtheSouth
BranchoftheNewtonCreek,ConrailandLemmAvenuewillalsobereplaced.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$47,000,000.
COUNTY: Camden
LEGISLATIVEDISTRICT: 5
MUNICIPALITY: CamdenCity,GloucesterCity
SPONSOR: NJDOT
MILEPOST(S): Rt76:0.701.7,Rt676:01.0
STRUCTURENO.: 0417158,0418162,0418163
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$8.000
SectionIIIPage316
$7.000
$32.000
Total
$47.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route77,ElmerShirleyRoad(CR611)toGangemiLane
DBNUM:12429/UPC:124290
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$5,484,000.
COUNTY: Gloucester,Salem
LEGISLATIVEDISTRICT: 3,5
MUNICIPALITY: UpperPittsgroveTwp,ElkTwp,HarrisonTwp
SPONSOR: NJDOT
MILEPOST(S): 10.6221.0
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
CON
STP
$1.844
$1.844
SJTPO
CON
STP
$3.640
$3.640
SectionIIIPage317
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route80,EB,Route23toRoute19
DBNUM:11341/UPC:113410
BasedontheNJDOTsPavementManagementSystem,thissectionoftheroadwayhasbeenidentifiedforpavementresurfacingandshoulder
reconstruction.MinordeckrepairisincludedasisdrainageworkidentifiedthroughtheDainageManagementSystemquery.
Totalconstructionfundingneededisexpectedtobe$18,595,000.
COUNTY: Passaic
LEGISLATIVEDISTRICT: 40,35
MUNICIPALITY: WayneTwp,PatersonCity,WoodlandParkBoro
SPONSOR: NJDOT
MILEPOST(S): 53.4858.2
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayRehabandRecon)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.800
Total
$0.800
$18.595
SectionIIIPage318
$18.595
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route80,Route15Interchange
DBNUM:93139/UPC:950442
Thisprojectwill:providethemissingRt.15Northbound/SouthboundtoI80Eastbound/WestboundramptoreducecongestionwithinWhartonandto
providedirectaccesstotheinterstate;improvetheaccelerationlanefromRt.15toI80Westboundtoimproveitssafetyandoperation;reconstructthe
intersectionofRt.15&DeweyAve.toimproveitslevelofservice;improvetheweavinglengthbetweenNorthMainSt.&Ramp“K”;improvethe
geometryofRamp“I”toenhancetruckmovements;andimprovethelanewidthandaddshouldersatthemergeofRt.15NorthboundandI80
Westboundtoimproveitsoperationandsafety.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$38,400,000.
COUNTY: Morris
LEGISLATIVEDISTRICT: 25,26
MUNICIPALITY: WhartonBoro,RockawayTwp
SPONSOR: NJDOT
MILEPOST(S): Rt80:33.3034.02,Rt15:1.612.80
STRUCTURENO.: 1412178,1412179,1413150,1413151
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10A(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
NJTPA
PE
NHPP
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.800
Total
$3.800
$4.200
$4.200
$0.600
$0.600
$18.900
SectionIIIPage319
$19.500
$38.400
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route80,TotowaBoro.,PassaicCo.,CulvertReplacement
DBNUM:11362/UPC:113620
ThisisaculvertrehabilitationprojectidentifiedbytheBridgeManagementSystem.Theculvertisasinglebarrelcorrugatedmetalpipe5indiameter
and345inlength.Itisinfaircondition.Therearetwobowedsectionsofpipewhicharetobereplacedandthepipethenlined.
Totalconstructionfundingneededisexpectedtobe$1,125,000.
COUNTY: Passaic
LEGISLATIVEDISTRICT: 40
MUNICIPALITY: TotowaBoro
SPONSOR: NJDOT
MILEPOST(S): 54.854.9
STRUCTURENO.: 1609161
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S4(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:Culverts)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.125
SectionIIIPage320
Total
$1.125
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route80,WBRockfallMitigation,HardwickTownship
DBNUM:09545/UPC:095450
InitiatedfromtheRockfallHazzardManagementSystem,thisprojectwillstabilizetheexistingrockoutcropareaadjacenttoI80Westboundatfour
locationswithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$12,100,000.
COUNTY: Warren
LEGISLATIVEDISTRICT: 24
MUNICIPALITY: HardwickTwp
SPONSOR: NJDOT
MILEPOST(S): 1.041.35
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S4(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:RockfallMitigation)
MPO
Phase
Fund
NJTPA
ROW
NHPP
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.100
Total
$0.100
$12.100
SectionIIIPage321
$12.100
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route82,CaldwellAvenuetoLehighAvenue
DBNUM:11404/UPC:114040
ThePedestrianSafetyEvaluationforRoute82,aspartofthePedestrianSafeCorridorProgram,identifiedspecificpedestriansafetydeficienciesand
countermeasurestoremovebarriersthatprohibitsafewalkingprimarilyatintersections.Atappropriatelocations,thesemeasuresinclude;installing
pedestriancountdownsignalheads,installingADAcompliantramps,revisingtrafficsignaltimingsforappropriatepedestrianclearancetimes,clearly
definingschoolzones,etc.Pavementresurfacingwillalsobeperformedwithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$3,150,000.
COUNTY: Union
LEGISLATIVEDISTRICT: 20
MUNICIPALITY: UnionTwp
SPONSOR: NJDOT
MILEPOST(S): 1.874.00
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): AQ2(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:Bicycle/PedestrianSafety)
MPO
Phase
Fund
NJTPA
DES
HSIP
NJTPA
CON
HSIP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.600
Total
$0.600
$3.150
SectionIIIPage322
$3.150
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route82,RahwayRiverBridge
DBNUM:94019/UPC:950452
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethestructurallydeficientandfunctionallyobsoletebridge,builtin1872.The
bridgealsohasfloodingproblems.
Totalconstructionfundingneededisexpectedtobe$6,200,000.
COUNTY: Union
LEGISLATIVEDISTRICT: 21
MUNICIPALITY: SpringfieldTwp
SPONSOR: NJDOT
MILEPOST(S): 0.38
STRUCTURENO.: 2012150
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
PE
NHPP
NJTPA
DES
STATE
NJTPA
ROW
STATE
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
Total
$1.000
$1.500
$1.500
$0.500
$0.500
$6.200
SectionIIIPage323
$6.200
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route83,Route47toRoute9
DBNUM:14373/UPC:143730
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$1,850,000.
COUNTY: CapeMay
LEGISLATIVEDISTRICT: 1
MUNICIPALITY: DennisTwp
SPONSOR: NJDOT
MILEPOST(S): 0.03.81
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
SJTPO
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.850
Total
$1.850
SectionIIIPage324
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route88,BridgeoverBeaverDamCreek
DBNUM:09322/UPC:093220
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethestructurallydeficientandfuntionallyobsoletebridge,builtin1923.
Totalconstructionfundingneededisexpectedtobe$3,250,000.
COUNTY: Ocean
LEGISLATIVEDISTRICT: 10
MUNICIPALITY: BrickTwp,PointPleasantBoro
SPONSOR: NJDOT
MILEPOST(S): 7.60
STRUCTURENO.: 1515150
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.200
Total
$1.200
$1.500
$1.500
$3.250
SectionIIIPage325
$3.250
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route94,BridgeoverJacksonburgCreek
DBNUM:11322/UPC:113220
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethestructurallydeficientandfunctionallyobsoletebridge,builtin1872.Incidental
roadwayapproachwork,includingmilling&pavingandthereplacementoftheguiderailinordertoupgradetocurrentstandardsasrequired,will
alsobeincludedintheproject.
Totalconstructionfundingneededisexpectedtobe$2,650,000.
COUNTY: Warren
LEGISLATIVEDISTRICT: 24
MUNICIPALITY: BlairstownTwp
SPONSOR: NJDOT
MILEPOST(S): 7.9467.954
STRUCTURENO.: 2117157
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
DES
STP
NJTPA
ROW
STP
NJTPA
CON
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.450
Total
$0.450
$0.100
$0.100
$2.650
SectionIIIPage326
$2.650
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route94,Route15(LafayetteRoad)toBayberryLane
DBNUM:14366/UPC:143660
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$2,000,000.
COUNTY: Sussex
LEGISLATIVEDISTRICT: 24
MUNICIPALITY: LafayetteTwp,SpartaTwp,HardystonTwp
SPONSOR: NJDOT
MILEPOST(S): 28.032.8
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$2.000
Total
$2.000
SectionIIIPage327
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route94,MohicanRoadtoKerrRoad
DBNUM:14364/UPC:143640
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$3,300,000.
COUNTY: Warren
LEGISLATIVEDISTRICT: 24
MUNICIPALITY: BlairstownTwp,FrelinghuysenTwp
SPONSOR: NJDOT
MILEPOST(S): 8.2313.8
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.300
Total
$3.300
SectionIIIPage328
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route95M,Route175toRailroadBridge
DBNUM:12412/UPC:124120
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$7,640,000.
COUNTY: Mercer
LEGISLATIVEDISTRICT: 15
MUNICIPALITY: EwingTwp,HopewellTwp
SPONSOR: NJDOT
MILEPOST(S): 0.23.4
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$7.640
SectionIIIPage329
Total
$7.640
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route130,ColumbusRoad/JonesStreet
DBNUM:02397/UPC:023970
Thisprojectwilladdressoperational,physicalandsafetyproblems.Theproposedprojectincludesthefollowing:Designatedleftturnlanewillbe
providedfornorthboundRoute130ontoJonesStreet;MedianopeningatCourtDrivewillbeclosed,butallowingfortheuseofemergencyvehicles;
Theexistingtrafficsignalattheintersectionwillbereplaced;ADAcompatiblepedestriancrosswalkandsidewalkswillbeprovidedattheintersection;
AleadsignalphasewillbeprovidedforthenorthboundRoute130leftturnandforwestboundColumbusRoad.Theprojectwillincludemillingand
resurfacingattheintersection.
Totalconstructionfundingneededisexpectedtobe$1,080,000.
COUNTY: Burlington
LEGISLATIVEDISTRICT: 7
MUNICIPALITY: BurlingtonCity
SPONSOR: NJDOT
MILEPOST(S): 46.847.9
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): R1(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:SafetyImprovements)
MPO
Phase
Fund
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.080
SectionIIIPage330
Total
$1.080
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route130,CR545(FarnsworthAvenue)
DBNUM:12346A/UPC:148030
InitiatedfromtheOfficeofBicycleandPedestrianPrograms,thisproject,abreakoutfromRoute130/206,CR528(CrosswicksRd)toRoute206at
AmboyRd,willaddresspedestrianandbicycledeficiencieswithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$3,600,000.
COUNTY: Burlington
LEGISLATIVEDISTRICT: 7
MUNICIPALITY: BordentownTwp
SPONSOR: NJDOT
MILEPOST(S): 55.46
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): A2(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(MultimodalPrograms:Bicycle/Pedestrian)
MPO
Phase
Fund
DVRPC
PE
NHPP
DVRPC
DES
NHPP
DVRPC
ROW
NHPP
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.500
Total
$0.500
$0.950
$0.950
$1.800
$1.800
$3.600
SectionIIIPage331
$3.600
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route130,HollywoodAvenue(CR618)
DBNUM:93216/UPC:950469
Thisprojectprovidesforsafetyandoperationalimprovementstoaddressproblemscausedbythesevereacuteangleoftheintersection.Ahorizontal
curvealsocausessightdistanceproblemsforRt.130northboundtraffic.Localbusinessdrivewaysarebelievedtocontributetoaccidents.Scopeof
projecttobedetermined.
Totalconstructionfundingneededisexpectedtobe$1,690,000.
COUNTY: Salem
LEGISLATIVEDISTRICT: 3
MUNICIPALITY: CarneysPointTwp
SPONSOR: NJDOT
MILEPOST(S): 2.20
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NR1(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:SafetyImprovements)
MPO
Phase
Fund
SJTPO
ROW
STP
SJTPO
CON
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.178
Total
$0.178
$1.690
SectionIIIPage332
$1.690
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route130,PlantStreettoHighHillRoad(CR662)
DBNUM:11414/UPC:114140
InitiatedbythePavementManagementSystem,thisprojectconsistsofmilling,resurfacing,reconstructingandrehabilitatingcertainsectionswithin
theprojectlimits,replacingsubstandardguiderail,installingADAcompliantcurbrampsandcorrectingsubstandardgeometricdeficiencies.The
pavementwillberesurfacedwithintheentireprojectlimits,withmillingandpavingonthemainlineandshoulders.Asmallportionoftheroadwayis
identifiedforreconstructionandtheUS130overSalemCanalconcreteculvertwillalsoberepaired.
Totalconstructionfundingneededisexpectedtobe$11,237,000.
LEGISLATIVEDISTRICT: 3
COUNTY: Salem,Gloucester
MUNICIPALITY: LoganTwp,PennsvilleTwp,OldmansTwp,CarneysPointTwp SPONSOR: NJDOT
MILEPOST(S): 0.210.98
STRUCTURENO.: Various
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayRehabandRecon)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
CON
STATE
$2.231
$2.231
SJTPO
CON
STATE
$9.006
$9.006
SectionIIIPage333
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route130,SharonRoadtoMeadowbrookRoad
DBNUM:12430/UPC:124300
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$4,700,000.
COUNTY: Mercer
LEGISLATIVEDISTRICT: 14
MUNICIPALITY: RobbinsvilleTwp
SPONSOR: NJDOT
MILEPOST(S): 62.464.9
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$4.700
SectionIIIPage334
Total
$4.700
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route130,VanSciverPkwytoCraftsCreek
DBNUM:12415/UPC:124150
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$12,960,000.
COUNTY: Burlington
LEGISLATIVEDISTRICT: 7
MUNICIPALITY: WillingboroTwp,BurlingtonTwp,BurlingtonCity,Florence
Twp
SPONSOR: NJDOT
MILEPOST(S): NB44.146.73&47.3851.8;SB47.3851.58
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$12.960
Total
$12.960
SectionIIIPage335
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route130,WestfieldAve.toMainStreet
DBNUM:11309/UPC:113090
InitiatedfromthePavementManagementSystem,thisprojectconsistsofmilling,resurfacingandrehabilitatingtheroadwaywithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$6,700,000.
COUNTY: Mercer,Middlesex
LEGISLATIVEDISTRICT: 14,16
MUNICIPALITY: EastWindsorTwp,CranburyTwp
SPONSOR: NJDOT
MILEPOST(S): 67.872.8
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayRehabandRecon)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
DES
NHPP
$0.538
$0.538
NJTPA
DES
NHPP
$0.662
$0.662
DVRPC
ROW
NHPP
$0.100
$0.100
NJTPA
ROW
NHPP
$0.100
$0.100
DVRPC
CON
NHPP
$3.002
$3.002
NJTPA
CON
NHPP
$3.698
$3.698
SectionIIIPage336
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route130/206,CR528(CrosswicksRd)toRt206atAmboyRd
DBNUM:12346/UPC:123460
InitiatedfromtheOfficeofBicycleandPedestrianPrograms,thisprojectwilladdresspedestrianandbicycledeficiencieswithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$4,560,000.
COUNTY: Burlington
LEGISLATIVEDISTRICT: 7
MUNICIPALITY: BordentownTwp,BordentownCity
SPONSOR: NJDOT
MILEPOST(S): 35.6136.76;55.9756.44
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): A2(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(MultimodalPrograms:Bicycle/Pedestrian)
MPO
Phase
Fund
DVRPC
PE
NHPP
DVRPC
DES
NHPP
DVRPC
ROW
NHPP
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.700
Total
$0.700
$0.950
$0.950
$0.100
$0.100
$4.560
SectionIIIPage337
$4.560
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route152,BayAvenuetoSeaviewDrive
DBNUM:14371/UPC:143710
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$5,350,000.
COUNTY: Atlantic
LEGISLATIVEDISTRICT: 2
MUNICIPALITY: SomersPointCity,EggHarborTwp
SPONSOR: NJDOT
MILEPOST(S): 0.03.16
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
SJTPO
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$5.350
SectionIIIPage338
Total
$5.350
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route166,BridgesoverBranchofTomsRiver
DBNUM:14324/UPC:143240
InitiatedbytheBridgeManagementSystem,thisstudywilldeterminewhethertheprojectwillbealimitedscopedeck/superstructure,orfullscope
bridge,replacement.
Totalconstructionfundingneededisexpectedtobe$7,000,000.
COUNTY: Ocean
LEGISLATIVEDISTRICT: 9,10
MUNICIPALITY: SouthTomsRiverBoro,TomsRiverTwp
SPONSOR: NJDOT
MILEPOST(S): 1.13
STRUCTURENO.: 1516152,1516151
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10A(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:DeckRehabandReplacement)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.750
Total
$0.750
$7.000
SectionIIIPage339
$7.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route168,BridgeoverBigTimberCreek
DBNUM:09327/UPC:093270
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacetheexistingbridge.ThenewBridgewillmaintaintheonelane,shoulderand
sidewalkfortheNorthbounddirection,andtwo(2)lanes,shoulderandsidewalkintheSouthbounddirection.
Totalconstructionfundingneededisexpectedtobe$7,300,000.
COUNTY: Gloucester
LEGISLATIVEDISTRICT: 4
MUNICIPALITY: WashingtonTwp
SPONSOR: NJDOT
MILEPOST(S): 0.75
STRUCTURENO.: 0819150
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$7.300
SectionIIIPage340
Total
$7.300
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route168,MerchantStreettoFerryAvenue,Pavement
DBNUM:10341/UPC:103410
Pavementrehabilitationrank#30onthe2008PavementProjectsList.ThepavementprojectisidentifiedasapriorityneedinthePavement
ManagementSystem.
Theprojectrequiresvariouslevelsofpavementreconstructionandresurfacing.Allsectionswillbepavedwithasphalt.Significantsectionsofthe
projectwillrequireonlymillingandpaving.Theothersectionsrequirefullreconstruction.Thereconstructioninvolvestheremovaloftheexisting
pavementand9”thickconcreteslab,furtherexcavationofthesubbase,andtheinstallationofGeotextile,andRoadwayStabilizationpriortobaseand
surfacecourses.
Totalconstructionfundingneededisexpectedtobe$12,750,000.
COUNTY: Camden
LEGISLATIVEDISTRICT: 5
MUNICIPALITY: AudubonParkBoro,WoodlynneBoro,CamdenCity
SPONSOR: NJDOT
MILEPOST(S): 8.5610.75
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayRehabandRecon)
MPO
Phase
Fund
DVRPC
DES
NHPP
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
Total
$1.000
$12.750
SectionIIIPage341
$12.750
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route173,BridgeoverPohatcongCreek
DBNUM:09320/UPC:093200
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethebridgeandprovidescourcountermeasurestoaddressthisscourcritical
structure.
Totalconstructionfundingneededisexpectedtobe$4,550,000.
COUNTY: Warren
LEGISLATIVEDISTRICT: 23
MUNICIPALITY: GreenwichTwp
SPONSOR: NJDOT
MILEPOST(S): 1.401.60
STRUCTURENO.: 2103152
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
CON
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$4.550
Total
$4.550
SectionIIIPage342
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route173,MusconetcongRiver,CulvertReplacement
DBNUM:11353/UPC:113530
InitiatedfromtheBridgeManagementSystem,thisprojectwillreplacetheculvert.Guiderail,retainingwallsandheadwallimprovementswillalsobe
performed.
Totalconstructionfundingneededisexpectedtobe$1,050,000.
COUNTY: Hunterdon
LEGISLATIVEDISTRICT: 23
MUNICIPALITY: BethlehemTwp
SPONSOR: NJDOT
MILEPOST(S): 6.81
STRUCTURENO.: 1003153
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S4(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:Culverts)
MPO
Phase
Fund
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.050
SectionIIIPage343
Total
$1.050
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route179,Route165toRoute31/202,Pavement
DBNUM:11419/UPC:114190
InitiatedfromthePavementManagementSystem,thisprojectwillrehabilitateandresurfacewithintheprojectlimits.Existingguiderailandcurb
rampdeficiencieswillalsobeaddressedbytheproject.
Totalconstructionfundingneededisexpectedtobe$5,500,000.
COUNTY: Hunterdon
LEGISLATIVEDISTRICT: 15
MUNICIPALITY: LambertvilleCity,WestAmwellTwp,EastAmwellTwp
SPONSOR: NJDOT
MILEPOST(S): 0.47.5
STRUCTURENO.: 1020150,1022150,1023156
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$5.500
SectionIIIPage344
Total
$5.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route195WB,Route295toCR524/539(OldYorkRoad)
DBNUM:14377/UPC:143770
InitiatedfromthePavementManagementSystem,thisprojectwillprovidemicrosurfacingwithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$7,410,000.
COUNTY: Mercer,Monmouth
LEGISLATIVEDISTRICT: 14,12
MUNICIPALITY: HamiltonTwp,RobbinsvilleTwp,UpperFreeholdTwp
SPONSOR: NJDOT
MILEPOST(S): 0.09.25
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$7.410
SectionIIIPage345
Total
$7.410
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route202,BridgeoverNorthBranchofRaritanRiver
DBNUM:14415/UPC:144150
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethestructurallydeficientandfunctionallyobsoletebridge,builtin1922.
Totalconstructionfundingneededisexpectedtobe$4,320,000.
COUNTY: Somerset
LEGISLATIVEDISTRICT: 23
MUNICIPALITY: BedministerTwp
SPONSOR: NJDOT
MILEPOST(S): 32.54
STRUCTURENO.: 1809150
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
PE
NHPP
NJTPA
DES
NHPP
NJTPA
UTI
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.300
Total
$0.300
$0.700
$0.700
$0.300
$0.300
$4.320
SectionIIIPage346
$4.320
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route202,FirstAvenueIntersectionImprovements
DBNUM:02372B/UPC:023722
InitiatedbytheProjectDevelopmentWorkProgram,thisproject,abreakoutfromDBNUM02372,willprovideimprovementstotheexisting
intersection,enhancetheoperationalcapabilities,andreducethechroniccongestion.
Totalconstructionfundingneededisexpectedtobe$1,822,000.
COUNTY: Somerset
LEGISLATIVEDISTRICT: 23
MUNICIPALITY: RaritanBoro
SPONSOR: NJDOT
MILEPOST(S): 23.90
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NR1,NR2(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.500
Total
$0.500
$0.158
$0.158
$1.822
SectionIIIPage347
$1.822
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route202/206,overBranchofPetersBrook,CulvertReplacementatMP27.96
DBNUM:11363/UPC:113630
InitiatedbytheBridgeManagementSystem,thisprojectwillrepair/replacetheculvertwithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$2,400,000.
COUNTY: Somerset
LEGISLATIVEDISTRICT: 23
MUNICIPALITY: BridgewaterTwp
SPONSOR: NJDOT
MILEPOST(S): 27.1327.96
STRUCTURENO.: 1808160,1808158
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S4(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:Culverts)
MPO
Phase
Fund
NJTPA
ROW
STATE
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.020
Total
$0.020
$2.400
SectionIIIPage348
$2.400
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route206,CrusersBrookBridge(41)
DBNUM:94060/UPC:960596
Thisprojectwillprovideforthereplacementoftheexistingstructurewhichisinpoorconditionduetotheconditionofthesuperstructureand
inadequatedeckgeometry.Also,thestructureispotentiallyscourcriticalsincetheexistingabutmentsarenotfoundedonpiles.Thestructurewillbe
widenedfrom30feetto44feettoincludefull8footshouldersinsteadofthecurrent3footshoulders.Thepiersandabutmentswillbefoundedon
piles.Thepierswillbewideenoughtoaccommodateaseparatepedestrianwalkwayonthewestsideofthebridge.
Totalconstructionfundingneededisexpectedtobe$4,900,000.
COUNTY: Somerset
LEGISLATIVEDISTRICT: 16
MUNICIPALITY: MontgomeryTwp
SPONSOR: NJDOT
MILEPOST(S): 61.80
STRUCTURENO.: 1810155
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$4.900
SectionIIIPage349
Total
$4.900
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route206,DoctorsWaytoValleyRoad
DBNUM:780B/UPC:108022
Thisproject,abreakoutofRoute206,OldSomervilleRoadtoBrownAvenue(15N)(Southernsection),willprovidecongestionrelief,andoperational
andsafetyimprovements.Theprojectwillincludewideningfromtwolanestofourlanes,revisionofthreeexistingtrafficsignalsandreplacementof
thebridgeoverRoyceBrook.Thisprojectwillbebicycle/pedestriancompatible.
Totalconstructionfundingneededisexpectedtobe$29,500,000.
COUNTY: Somerset
LEGISLATIVEDISTRICT: 16
MUNICIPALITY: HillsboroughTwp
SPONSOR: NJDOT
MILEPOST(S): 66.3667.5
STRUCTURENO.: 1810165
FINANCIALPLANREQUIREMENT: Thisprojectispartofaprojectwithatotalcostbetween$100and$500millionprogrammedtoreceivefederal
financialassistanceandanannualfinancialplanisrequiredtobeprepared.
AIRQUALITYCODE(NONEXEMPT/EXEMPT): 2030M(NonExempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:MajorWidenings)
MPO
Phase
Fund
NJTPA
DES
CMAQ
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$2.000
$2.000
$29.500
SectionIIIPage350
Total
$29.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route206,HiGlenDrivetoHighStreet
DBNUM:11417/UPC:114170
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$3,400,000.
COUNTY: Sussex
LEGISLATIVEDISTRICT: 24
MUNICIPALITY: ByramTwp,AndoverBoro
SPONSOR: NJDOT
MILEPOST(S): 99.60103.02
STRUCTURENO.: 1911152,1911153,1911154,1911155
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.400
SectionIIIPage351
Total
$3.400
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route206,HilltopDrive
DBNUM:15301/UPC:153010
InitiatedfromtheDrainageManagementSystem,thisstudywillexploredrainageimprovementswithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$1,000,000.
COUNTY: Mercer
LEGISLATIVEDISTRICT: 16
MUNICIPALITY: PrincetonTwp
SPONSOR: NJDOT
MILEPOST(S): 55.7
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:Drainage)
MPO
Phase
Fund
DVRPC
ROW
STATE
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.050
Total
$0.050
$1.000
SectionIIIPage352
$1.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route206,MonmouthRoad/JuliustownRoadIntersectionImprovements(CR537)
DBNUM:9212C/UPC:028112
Thisproject,abreakoutofRoute206,Burlington/AtlanticCounty,Route30toRoute68,willprovideoperationalandsafetyimprovements.The
projectwillprovideheadtoheadleftturnlanesatall4approaches,improvedsignaltimingandgeometricimprovements(includingshoulder
wideningandapproachwork).Inaddition,theexistingfourlanesectionwillbeextendedthroughbothintersectionstoprovidemoreofasafe
distancetotiebackintothetwolanesection.ThisprojectwillalsoincorporaterecommendationsmadeintheRoute206Bicycle/Pedestrian
CompatibilityStudy.
Totalconstructionfundingneededisexpectedtobe$6,050,000.
COUNTY: Burlington
LEGISLATIVEDISTRICT: 8
MUNICIPALITY: SpringfieldTwp
SPONSOR: NJDOT
MILEPOST(S): 26.3727.33
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): R1(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
DVRPC
DES
NHPP
DVRPC
ROW
NHPP
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.950
Total
$0.950
$0.160
$0.160
$6.050
SectionIIIPage353
$6.050
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route206,PinesRoadtoCR521(MontagueRiverRoad)
DBNUM:12398/UPC:123980
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$8,100,000.
COUNTY: Sussex
LEGISLATIVEDISTRICT: 24
MUNICIPALITY: BranchvilleBoro,FrankfordTwp,SandystonTwp,Montague
Twp
SPONSOR: NJDOT
MILEPOST(S): 115.93129.3
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$8.100
SectionIIIPage354
Total
$8.100
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route206,SouthBroadStreetBridgeoverAssunpinkCreek
DBNUM:L064/UPC:950151
InitiatedbytheBridgeManagementSystem,thisprojectwillrehabilitatethestructurallydeficientandfunctionallyobsoletebridge,builtin1843.
Totalconstructionfundingneededisexpectedtobe$6,956,000.
COUNTY: Mercer
LEGISLATIVEDISTRICT: 15
MUNICIPALITY: TrentonCity
SPONSOR: NJDOT
MILEPOST(S): 42.70
STRUCTURENO.: 1100002
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(LocalSystemSupport:LocalBridges)
MPO
Phase
Fund
DVRPC
DES
NHPP
DVRPC
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.750
Total
$0.750
$6.956
SectionIIIPage355
$6.956
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route206,SouthofPatersonAve.toSouthofPineRd.
DBNUM:10333/UPC:103330
InitiatedfromthePavementManagementSystem,theprojectisaMillx,PavexResurfacingProjecttoamaximumof4inches.Theprojectincludes
imagedetectioncameras,upgradedguiderail,curbrepair,ADAramps,andcrosswalkswhereneeded.
Totalconstructionfundingneededisexpectedtobe$12,800,000.
COUNTY: Sussex
LEGISLATIVEDISTRICT: 24
MUNICIPALITY: AndoverTwp,NewtonTown,HamptonTwp,FrankfordTwp
SPONSOR: NJDOT
MILEPOST(S): 107.66115.93
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$12.800
Total
$12.800
SectionIIIPage356
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route206,SouthboundMergeImprovementswithI287Ramp
DBNUM:02372A/UPC:023721
Thisproject,abreakoutofDBNUM02372,willprovideaSouthboundaccelerationlane,wideningofthegrassmedian,advancedsignage,andminor
curbanddrainagemodifications.
Totalconstructionfundingneededisexpectedtobe$700,000.
COUNTY: Somerset
LEGISLATIVEDISTRICT: 23
MUNICIPALITY: BridgewaterTwp
SPONSOR: NJDOT
MILEPOST(S): 25.5025.88
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S4(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
NJTPA
DES
NHPP
$0.300
$0.300
NJTPA
ROW
STATE
$0.050
$0.050
NJTPA
CON
NHPP
$0.700
SectionIIIPage357
$0.700
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route206,ValleyRoadtoBrownAvenue
DBNUM:780A/UPC:108021
Thisproject,abreakoutofRoute206,OldSomervilleRoadtoBrownAvenue(15N)(NorthernSection),willprovidecongestionrelief,and
operationalandsafetyimprovements.Theprojectwillincludewideningfromtwolanestoafourlanedualization,relocationoftwoexistingtraffic
signals(addingtwonewjughandles)andreplacementoftherailroadbridgeoverRoute206.Thisprojectwillbebicycle/pedestriancompatible.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$45,000,000.
COUNTY: Somerset
LEGISLATIVEDISTRICT: 16
MUNICIPALITY: HillsboroughTwp
SPONSOR: NJDOT
MILEPOST(S): 67.568.6
STRUCTURENO.: 1810166,1810167,1810168
FINANCIALPLANREQUIREMENT: Thisprojectispartofaprojectwithatotalcostbetween$100and$500millionprogrammedtoreceivefederal
financialassistanceandanannualfinancialplanisrequiredtobeprepared.
AIRQUALITYCODE(NONEXEMPT/EXEMPT): 2030M(NonExempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:MajorWidenings)
MPO
Phase
Fund
NJTPA
DES
NHPP
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$2.500
Total
$2.500
$10.000
$10.000
$20.000
SectionIIIPage358
$25.000
$45.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route206,WhitehorseCircle(CR533,524)
DBNUM:95040/UPC:950526
InitiatedbytheSafetyManagementSystem,thisprojectwillimprovesafetybyconstructingaroundabouttoeliminatemanyoftheconflictpoints,
therebyreducingthenumberofcrashes,specificallytheanglecrashtype.
Totalconstructionfundingneededisexpectedtobe$2,200,000.
COUNTY: Mercer
LEGISLATIVEDISTRICT: 14
MUNICIPALITY: HamiltonTwp
SPONSOR: NJDOT
MILEPOST(S): 38.8139.95
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S2(Exempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:SafetyImprovements)
MPO
Phase
Fund
DVRPC
ROW
HSIP
DVRPC
CON
HSIP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.200
Total
$0.200
$2.200
SectionIIIPage359
$2.200
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route206Bypass,MountainViewRoadtoOldSomervilleRoad(Sections14A&15A)
ContractB
DBNUM:779/UPC:960597
ThisprojectwillprovidefortheconstructionofasegmentofRt.206onnewalignment,bypassingasegmentofexistinghighwaythathasserious
congestionandsafetyproblems.Thenewsegmentofroadwaywillconsistoffour12foottravellanes,two10footoutsideshoulders,twofivefoot
insideshoulders,aconcretemedianbarrierandtwo15footoutsidebordersbetweenAmwellRoad(CR514)andOldSomervilleRoad.Between
HillsboroughRoadandMountainViewRoad,thenewsegmentofroadwaywillconsistoftwo12foottravellanes,two10footoutsideshoulders,two
threefootinsideshoulders,a15footgrassmedianandtwo15footoutsideborders.
AdvanceutilityworkwillbeperformedontheBuckeyepipelineandAT&Tfacilities.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$47,100,000.
COUNTY: Somerset
LEGISLATIVEDISTRICT: 16
MUNICIPALITY: HillsboroughTwp
SPONSOR: NJDOT
MILEPOST(S): 63.4066.40
STRUCTURENO.: 1810164
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): 2020M(NonExempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:MissingLinks)
MPO
Phase
Fund
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$27.500
$19.600
SectionIIIPage360
Total
$47.100
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route208,BergenCountyDrainageImprovements
DBNUM:11381/UPC:113810
InitiatedbytheDrainageManagementSystem(DMS),thisprojectwilladdressdrainageissueswithintheprojectlimits,includingthreelocations
ranked5,11and37bytheDMS.
Totalconstructionfundingneededisexpectedtobe$5,315,000.
COUNTY: Bergen
LEGISLATIVEDISTRICT: 40
MUNICIPALITY: WyckoffTwp,FranklinLakesBoro
SPONSOR: NJDOT
MILEPOST(S): 5.38.5
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S4(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:Drainage)
MPO
Phase
Fund
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.100
$0.100
$5.315
SectionIIIPage361
Total
$5.315
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route208,WyckoffTwp.,BergenCo.,CulvertReplacement
DBNUM:11355/UPC:113550
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacetheculvert,builtin1950,withintheprojectlimits.Theexistingculvertis
consideredstructurallydeficientandhydraulicallyinadequate.
Totalconstructionfundingneededisexpectedtobe$2,050,000.
COUNTY: Bergen
LEGISLATIVEDISTRICT: 40
MUNICIPALITY: WyckoffTwp
SPONSOR: NJDOT
MILEPOST(S): 6.36.4
STRUCTURENO.: 0233155
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S4(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:Culverts)
MPO
Phase
Fund
NJTPA
ROW
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.104
Total
$0.104
$2.050
SectionIIIPage362
$2.050
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route278,GoethalsBridgeReplacement
DBNUM:N1205/UPC:123770
ThisprojectprovidesforthereplacementoftheexistingGoethalsBridge,betweenElizabeth,NJandStatenIsland,NY,alongtheI278Corridor.
PursuanttotheRecordofDecisionbytheUSCoastGuardinJanuary2011concludingtheNEPAreviewprocess,thePortAuthorityisadvancingplans
forreplacementoftheexistingbridge,openedin1928.Thepreferredalternativeisafullreplacementonanalignmentimmediatelytothesouthofthe
currentbridge,tyingintotheexistingroadwayconnectionsinbothstates.Theexistingbridgewillremaininserviceduringconstructionofthenew
crossing,andwillbedemolishedafterthereplacementbridgeopens.
Theexistingstructurehastwo10footwidelanesineachdirection(eastboundandwestbound)separatedbyamedian,withnoshoulders,andno
pedestrian/bikewayaccommodation.Theexistingfreeflowspeedis45mph.Thenewbridgewillincludeseparateroadwaydecksforeastboundand
westboundtravel,eachprovidingthree12footwidelanes,one12footwideoutershoulder,andone5footwideinnershoulder.Thenewbridgewill
alsoincludeapedestrian/bikeway.Projectspecificationsassurethedesignwillnotprecludeadditionoffuturemasstransitserviceacrossthebridge
(byprovidingsufficientrightofwaybetweentheeastandwestboundroadwaysforapotentialfuturetransitsystem).Thefreeflowspeedforthenew
bridgewillbe60mph.Thenewstructurealsowillincorporateseismicprotection,security,andcomprehensiveITSfeatures.Totalprojectlengthis
approximately1.5miles,betweenNJTurnpikeandtheStatenIslandExpressway.
Totalconstructionfundingneededisexpectedtobe$700,000,000.
COUNTY: Union
LEGISLATIVEDISTRICT: 20
MUNICIPALITY: ElizabethCity
SPONSOR: PANYNJ
MILEPOST(S): NJ:1.3402.00,NY:0.00.850
STRUCTURENO.: 3800001,3800002,3800071,3800072
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): 2020M(NonExempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BiStateBridges)
MPO
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
Phase
Fund
NJTPA
PE
OTHER
$15.000
$15.000
NJTPA
CON
OTHER
$485.000
$485.000
NJTPA
ERC
OTHER
$220.000
$220.000
SectionIIIPage363
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route280WB,Route80toPassaicRiver
DBNUM:14370/UPC:143700
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$2,000,000.
COUNTY: Morris
LEGISLATIVEDISTRICT: 26,27
MUNICIPALITY: ParsippanyTroyHillsTwp,EastHanoverTwp
SPONSOR: NJDOT
MILEPOST(S): 0.03.3
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$2.000
Total
$2.000
SectionIIIPage364
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route280,Route21InterchangeImprovements
DBNUM:00314/UPC:003140
InitiatedbytheBridgeManagementSystem,thisprojectincludesreplacement/rehabilitationofsixstructureswithintheprojectlimits,and
reconfigurationoftheinterchangetoprovidefullmovementsandconsolidateentrancepoints.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$125,500,000.
COUNTY: Essex,Hudson
LEGISLATIVEDISTRICT: 29,32
MUNICIPALITY: NewarkCity,HarrisonTown
SPONSOR: NJDOT
MILEPOST(S): 13.8015.20
STRUCTURENO.: Various
FINANCIALPLANREQUIREMENT: Thisprojectispartofaprojectwithatotalcostbetween$100and$500millionprogrammedtoreceivefederal
financialassistanceandanannualfinancialplanisrequiredtobeprepared.
AIRQUALITYCODE(NONEXEMPT/EXEMPT): 2020M(NonExempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$42.150
$20.550
$26.750
$1.350
SectionIIIPage365
Total
$90.800
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route280,WBRampover1st&OrangeStreets,NewarkSubway&NJTransit
DBNUM:12318/UPC:123180
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethebridgedeck,andwidentheroadwaytoreducecongestionandcrashes.
Totalconstructionfundingneededisexpectedtobe$19,000,000.
COUNTY: Essex
LEGISLATIVEDISTRICT: 29
MUNICIPALITY: NewarkCity
SPONSOR: NJDOT
MILEPOST(S): 13.2813.48
STRUCTURENO.: 0730192
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10A(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:DeckRehabandReplacement)
MPO
Phase
Fund
NJTPA
PE
NHPP
NJTPA
DES
NHPP
NJTPA
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.500
Total
$1.500
$2.500
$2.500
$19.000
SectionIIIPage366
$19.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route287,Interchange10RampImprovements
DBNUM:9169Q/UPC:078021
Thisprojectwillprovideoperationalimprovementstotheonandofframpsto/fromEastonAvenuebylengtheningtheaccelerationlanesalongI287
NB.
Totalconstructionfundingneededisexpectedtobe$6,600,000.
COUNTY: Middlesex,Somerset
LEGISLATIVEDISTRICT: 17
MUNICIPALITY: PiscatawayTwp,FranklinTwp
SPONSOR: NJDOT
MILEPOST(S): 10.2710.6
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NR3,S4(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
NJTPA
PE
NHPP
NJTPA
DES
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.500
Total
$0.500
$0.500
$0.500
$6.600
SectionIIIPage367
$6.600
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route287,RiverRoad(CR622),InterchangeImprovements
DBNUM:9169R/UPC:078015
ThisprojectistomakeoperationalimprovementstotheonrampfromRiverRoadtoreducethenumberofvehiclesinqueueenteringtheinterstate
andweavingconditions.
Totalconstructionfundingneededisexpectedtobe$1,700,000.
COUNTY: Middlesex
LEGISLATIVEDISTRICT: 17
MUNICIPALITY: PiscatawayTwp
SPONSOR: NJDOT
MILEPOST(S): 9.810.2
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NR3(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
NJTPA
PE
NHPP
NJTPA
DES
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.750
Total
$0.750
$0.750
$0.750
$1.700
SectionIIIPage368
$1.700
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route287/78,I287/202/206InterchangeImprovements
DBNUM:04389/UPC:043890
ThisprojectinvolvesinterstateinterchangeimprovementsattheI78andI287InterchangeandattheRampsfromI287totheRt.202/206interchange.
TheI78EBtoI287NBRampwillbeshiftedfromaleftlaneentranceontoI287NBtoarightlaneentranceontoI287NB.Thismodificationwill
eliminatethefivelaneweaverequiredforvehiclestravelingonI78EBwhouseI287NBtoaccessRt.202/206(Pluckemin).
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$32,200,000.
COUNTY: Somerset
LEGISLATIVEDISTRICT: 23
MUNICIPALITY: BedminsterTwp,BridgewaterTwp
SPONSOR: NJDOT
MILEPOST(S): RT28720.522.3
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): 2030M(NonExempt)
ASSETMANAGEMENTCATEGORY: Safety(SafetyManagement:SafetyImprovements)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$10.000
$10.000
$12.200
SectionIIIPage369
Total
$32.200
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route295NB/NJTurnpike&Route40,BridgeoverSalemCanal
DBNUM:15315/UPC:153150
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethebridgedeck.
Totalconstructionfundingneededisexpectedtobe$5,700,000.
COUNTY: Salem
LEGISLATIVEDISTRICT: 3
MUNICIPALITY: CarneysPointTwp
SPONSOR: NJDOT
MILEPOST(S): 1.55
STRUCTURENO.: 1711150
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT):
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
DVRPC
DES
NHPP
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.800
Total
$0.800
$5.700
SectionIIIPage370
$5.700
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route295,Route195/29toRoute1
DBNUM:14378/UPC:143780
InitiatedfromthePavementManagementSystem,thisprojectwillprovidemicrosurfacingwithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$12,010,000.
COUNTY: Mercer
LEGISLATIVEDISTRICT: 14,15
MUNICIPALITY: HamiltonTwp,LawrenceTwp
SPONSOR: NJDOT
MILEPOST(S): 60.467.5
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$12.010
SectionIIIPage371
Total
$12.010
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route295/42,MissingMoves,Bellmawr
DBNUM:355A/UPC:950541
ThisprojectconsistsofnewrampsandrelatedimprovementstoenablemotoriststomakemovementsbetweenI295andRoute42whicharenot
possibleinthecurrentconfiguration.OtherprojectimprovementsincludetherestripingofRoute55Northbound,fromonelanetotwolanes,from
theexistingpoint,whereRoute55Northboundtapersfromtwolanestoonelane,uptothetieinwithRoute42Northbound.Thesecondlaneon
Route55Northboundwillbecomeacontinuousauxiliarylane,uptotheproposedentrancetonewRampA,connectingRoute42NorthboundtoI295
Southbound.TheexistingLeafAvenuerampsoffRoute42Northboundwillberelocatedapproximately750feettotheSouthandwillintersectwith
BenignoBlvd.ThenewexitlocationoffRoute42Northboundrequiresarampconnection,separatedfromthemainline,topreventqueuedtrafficat
thenewintersectionfrommixingwithmainlinetraffic.ThisrampconnectionsplitsofffromtheRampAentranceontheleftandrunsparallelto
Route42tothenewintersection;whichwillbesignalized.BenignoBlvd.willberealignedtomeetEdgewoodAvenue,andWellwoodAvenuewillbe
extendedtoaTintersectionwithBenignoBlvd.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$149,890,000.Thefollowingspecialfederalappropriations
havebeenallocatedforthisproject$14,351,393(NJ063);$4,005,900(NJ119);$15,022,126(NJ246);$10,023,414(NJ262);$1,980,000(NJ279).
COUNTY: Camden
LEGISLATIVEDISTRICT: 5
MUNICIPALITY: BellmawrBoro,MountEphraimBoro
SPONSOR: NJDOT
MILEPOST(S): Rt.295:25.7126.00;Rt.42:13.30
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT: Thisprojectispartofaprojectwithatotalcostbetween$100and$500millionprogrammedtoreceivefederal
financialassistanceandanannualfinancialplanisrequiredtobeprepared.
AIRQUALITYCODE(NONEXEMPT/EXEMPT): 2025M(NonExempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
MPO
Phase
Fund
DVRPC
DES
DEMO
DVRPC
CON
DEMO
$4.459
DVRPC
CON
NHPP
$17.076
$5.500
Total
$5.500
$4.459
$28.975
$40.000
SectionIIIPage372
$30.000
$29.380
$145.431
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route295/42/I76,DirectConnection,Contract3
DBNUM:355D/UPC:113020
ThisprojectrelievestheexistingbottleneckattheinterchangebyconstructingadirectconnectiononI295andotherhighwayimprovementsthatwill
reducecongestionandenhancetrafficoperationsandsafetythroughouttheprojectarea.Theimprovementsincludeasixlanemainlinethroughthe
interchange,eliminationofdangerousmergingandweavingmovements,upgradestorampgeometryandtheadditionofshouldersthroughoutthe
interchange.Contract3willincludethecompletionofthenewI295NorthboundandSouthboundstructuresoverI76,Route42,RampsCandE,and
BrowningRoad;thenewRampA(Route42NorthboundtoI295Northbound)bridgewillbecompletedunderthiscontractalongwithaportionof
RampF(I76EastboundtoI295Southbound);andthenewI295SouthbounddirectconnectionandRampAwillbeopenedtotrafficupon
completionofthiscontract.Contract3isabreakoutofRoute295/42/I76,DirectConnection,CamdenCounty.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$230,000,000.
COUNTY: Camden
LEGISLATIVEDISTRICT: 5
MUNICIPALITY: BellmawrBoro,MountEphraimBoro
SPONSOR: NJDOT
MILEPOST(S): 26.4127.8
STRUCTURENO.: 0427158
FINANCIALPLANREQUIREMENT: ThisprojectispartofaMajorProjectwhichisdefinedasaprojectwithatotalestimatedcostof$500million
ormorethatisreceivingfederalfinancialassistanceandanannualfinancialmanagementplanisrequiredto
beprepared.
AIRQUALITYCODE(NONEXEMPT/EXEMPT): 2025M(NonExempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$60.000
$70.000
$63.000
$37.000
SectionIIIPage373
Total
$230.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route295/42/I76,DirectConnection,Contract4
DBNUM:355E/UPC:113030
Thisprojectrelievestheexistingbottleneckattheinterchangebyconstructing;adirectconnectiononI295andotherhighway
improvementsthatwillreducecongestionandenhancetrafficoperationsandsafetythroughouttheprojectarea.Theimprovementsinclude;asixlane
mainlinethroughtheinterchange,eliminationofdangerousmergingandweavingmovements,upgradestorampgeometryandtheadditionof
shouldersthroughouttheinterchange.Contract4includesthereconstructionofI76andRoute42alongtheentireprojectlimits;thecompletionof
newRampsC&F,andthecompletionthenewI295Northbounddirectconnection.Contract4isabreakoutofRoute295/42/I76,DirectConnection,
CamdenCounty.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$200,000,000.
COUNTY: Camden
LEGISLATIVEDISTRICT: 5
MUNICIPALITY: BellmawrBoro,MountEphraimBoro
SPONSOR: NJDOT
MILEPOST(S): 26.4127.8
STRUCTURENO.: Various
FINANCIALPLANREQUIREMENT: ThisprojectispartofaMajorProjectwhichisdefinedasaprojectwithatotalestimatedcostof$500million
ormorethatisreceivingfederalfinancialassistanceandanannualfinancialmanagementplanisrequiredto
beprepared.
AIRQUALITYCODE(NONEXEMPT/EXEMPT): 2025M(NonExempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$80.000
SectionIIIPage374
$60.000
$60.000
Total
$200.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route322,CorridorCongestionReliefProject
DBNUM:07369/UPC:073690
ThisprojectinvolvesconstructionofabypassroutearoundMullicaHill.Newroadwayonnewalignment.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$16,000,000.
COUNTY: Gloucester
LEGISLATIVEDISTRICT: 5
MUNICIPALITY: HarrisonTwp
SPONSOR: NJDOT
MILEPOST(S): N/A
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): 2020M(NonExempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(LocalSystemSupport:LocalMobilityImprovements)
MPO
Phase
Fund
DVRPC
ERC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
$1.500
$1.000
SectionIIIPage375
Total
$3.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route322,KingsHighway(CR551)
DBNUM:97112B/UPC:048023
ThisintersectionimprovementprojectisabreakoutoftheRoute322(CommodoreBarryBridgetoRoute55)conceptdevelopmentstudy.Theproject
willprovideleftturnmovementsonallapproaches,andaddresstheverticalcurveonRoute322.Thisprojectwillalsobebicycleandpedestrian
compatible.
Totalconstructionfundingneededisexpectedtobe$4,900,000.
COUNTY: Gloucester
LEGISLATIVEDISTRICT: 3
MUNICIPALITY: WoolwichTwp
SPONSOR: NJDOT
MILEPOST(S): 6.727.25
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): R1(Exempt)
ASSETMANAGEMENTCATEGORY: MobilityandCongestionRelief(CongestionRelief:HighwayOperationalImprovements)
MPO
Phase
Fund
DVRPC
DES
NHPP
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.800
Total
$0.800
$4.900
SectionIIIPage376
$4.900
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route322,Route47(DelseaDrive)toCurtisAvenue
DBNUM:14362/UPC:143620
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$3,860,000.
COUNTY: Gloucester
LEGISLATIVEDISTRICT: 3,4
MUNICIPALITY: GlassboroBoro,MonroeTwp
SPONSOR: NJDOT
MILEPOST(S): 18.2524.09
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
DVRPC
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.860
Total
$3.860
SectionIIIPage377
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route322,Route50toLeipzigAvenue
DBNUM:12433/UPC:124330
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$8,980,000.
COUNTY: Atlantic
LEGISLATIVEDISTRICT: 2
MUNICIPALITY: HamiltonTwp
SPONSOR: NJDOT
MILEPOST(S): 45.950.0
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
SJTPO
CON
STP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$8.980
SectionIIIPage378
Total
$8.980
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route322,Rt295toTomlinStationRd(CR607)
DBNUM:12417/UPC:124170
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.Inaddition:pedestrianimprovementsat
signalizedintersectionswillinclude,addingorreconstructingcurbrampsinaccordancewithADAstandards;inletcastingsalongtheroadway
pavementwillbeupgradedtobicyclesafegratesthroughouttheproject;loopdetectorswillbereplacedwithvideodetectionattheRoute322–
PaulsboroSwedesboroRoad(CR653)signalizedintersectionandcountdown“man/hand”typepedestriansignalheadswithpushbuttonassemblies
willbeinstalled;drainageimprovementswillbeperformedincludingreconstructingnonstandardconcretecurbsatinletswhereinletconversionis
notfeasible,andcleaningallinletsandpipes;theexistingConrailrailroadcrossingwillbeupgradedwithaprecastconcreterailcrossingandsignal
warningdevices.Safetyimprovementswillbeinitiatedbyreplacingguiderailandguiderailendtreatmentsthatdonotmeetcurrentdesign
standards,installingRPMsandcenterlineandshoulderedgelinerumblestrips,upgradinglightingatsignalizedintersectionsasrequired,and
upgradingroadwaysignsincompliancewithcurrentMUTCDstandardsorrequirementsforretroreflectivity.Existingcurbwillbereconstructedin
areaswheretheroadwayprofilewillberaisedduetotheoverlay.
Totalconstructionfundingneededisexpectedtobe$4,330,000.
COUNTY: Gloucester
LEGISLATIVEDISTRICT: 3
MUNICIPALITY: WoolwichTwp,LoganTwp
SPONSOR: NJDOT
MILEPOST(S): 3.956.9&7.18.2
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
DVRPC
PE
NHPP
DVRPC
DES
NHPP
DVRPC
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.900
Total
$0.900
$1.300
$1.300
$4.330
SectionIIIPage379
$4.330
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route440,BayonneBridgeNavigationalClearanceProject
DBNUM:N1301/UPC:133420
ThisprojectentailsincreasingtheairdraftoftheBayonneBridgebyraisingtheroadwaywithintheexistingarchspanby64feet,from151feetto215
feet.Additionally,thenewroadwaywillbewider(tobetterconformtoAASHTOstandards),andthe6footwidepedestrianwalkwaywillbewidened
toa12footwidesharedusepathaccommodatingpedestriansandcyclists.Anewhigherroadwaywillbeconstructedwithintheexistingconstraints
onthemainspan.Theexistingapproachroadswillbedemolishedandnew,widerapproacheswillbeconstructed.Thenewapproacheswillhave8
footwideoutsideshouldersand4footwideinsideshoulders.Duringconstruction,themedianwillberemovablechannelizerposts.Oncethefull
bridgeiscompleted,jerseybarrierswillbeusedinthemedian.Theexistingtollplazawillbedemolishedandreplaced.Estimateddurationof
constructionisabout3.5years,duringwhichtimetrafficwillbereducedtoone12.5footlaneperdirection,withnightlyroadclosuresand8full
weekendclosuresperyear.ITSsignstructures(includingVMS,VSLS,CCTVandroadsensors)willbeconstructedalongtherehabilitatedroadway.
(OntheNYsidetheprojectisinTheCityofNewYork,RichmondCounty.)
Totalconstructionfundingneededisexpectedtobe$540,000,000.
COUNTY: Hudson
LEGISLATIVEDISTRICT: 31
MUNICIPALITY: BayonneCity
SPONSOR: PANYNJ
MILEPOST(S): 12.0212.78
STRUCTURENO.:
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BiStateBridges)
MPO
Phase
Fund
NJTPA
ERC
OTHER
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$230.000 $230.000
SectionIIIPage380
Total
$460.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route440,CR514(WoodbridgeAvenue)toKreilAvenue
DBNUM:14355/UPC:143550
ConcretePavementRepair
Totalconstructionfundingneededisexpectedtobe$25,000,000.
COUNTY: Middlesex
LEGISLATIVEDISTRICT: 18,19
MUNICIPALITY: EdisonTwp,WoodbridgeTwp,PerthAmboyCity
SPONSOR: NJDOT
MILEPOST(S): 0.24.0
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
PE
NHPP
NJTPA
DES
NHPP
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
Total
$1.000
$2.500
$2.500
$25.000
SectionIIIPage381
$25.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route440,NBAccessRdtoMinaDrive&SB40thStreettoRoadtoStadium
DBNUM:12416/UPC:124160
PavementResurfacingProjectInitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$5,100,000.
COUNTY: Hudson
LEGISLATIVEDISTRICT: 31,33
MUNICIPALITY: BayonneCity,JerseyCity
SPONSOR: NJDOT
MILEPOST(S): NB21.322.6&23.024.2;SB21.322.6&23.024.9
STRUCTURENO.: N/A
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S10(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(RoadAssets:HighwayResurfacing)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$5.100
SectionIIIPage382
Total
$5.100
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route495,Route1&9/PatersonPlankRoadBridge
DBNUM:06373/UPC:063730
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethebridgedeckanddeterioratedstructuralsteel,andalsoincludessubstructure
repairsandbridgepainting.Thebridgewasbuiltin1939.
Thisprojectismultiyearfunded.Totalconstructionfundingneededisexpectedtobe$67,499,900.
COUNTY: Hudson
LEGISLATIVEDISTRICT: 32
MUNICIPALITY: NorthBergenTwp
SPONSOR: NJDOT
MILEPOST(S): 0.81.0
STRUCTURENO.: 0917150
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:BridgeRehabandReplacement)
MPO
Phase
Fund
NJTPA
CON
NHPP
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$29.933
$25.451
$12.116
SectionIIIPage383
Total
$67.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyDepartmentofTransportationProjectDescriptions
($millions)
Route676,BridgesoverNorthBranchofNewtonCreek
DBNUM:14322/UPC:143220
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethedecksoftheRoute676SouthboundoverNorthBranchofNewtonCreek
structureandtheRoute676NorthboundoverNorthBranchofNewtonCreekstructure.Substructurerepairwillbeperformedonthelatterstructure,
aswell.Theprojectalsoincludespavementresurfacingwithintheprojectlimits.
Totalconstructionfundingneededisexpectedtobe$5,900,000.
COUNTY: Camden
LEGISLATIVEDISTRICT: 5
MUNICIPALITY: CamdenCity
SPONSOR: NJDOT
MILEPOST(S): 0.70
STRUCTURENO.: 0418154
FINANCIALPLANREQUIREMENT:
AIRQUALITYCODE(NONEXEMPT/EXEMPT): S19(Exempt)
ASSETMANAGEMENTCATEGORY: InfrastructurePreservation(BridgeAssets:DeckRehabandReplacement)
MPO
Phase
Fund
DVRPC
DES
NHPP
DVRPC
CON
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.500
Total
$1.500
$5.900
SectionIIIPage384
$5.900
SECTIONȱIVȱ
ȱ
NJȱTRANSITȱ
PROJECT/PROGRAMȱDESCRIPTIONSȱ
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T143
ADAPlatforms/Stations
FundingisprovidedforthedesignandconstructionofnecessaryimprovementstomakeNJTRANSITsrailstations,andsubwaystationscompliant
withtheAmericanswithDisabilitiesAct(ADA)includingrelatedtrackandinfrastructurework.Fundingisrequestedforupgrades,equipment
purchase,platformextensions,andtransitenhancementsthroughoutthesystemandotheraccessibilityimprovementsatnonkeystations.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT8(Exempt)
MPO
Phase
Fund
NJTPA
ERC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.910
$0.910
$0.910
$1.000
SectionIVPage1
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
Total
$9.730
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T05
BridgeandTunnelRehabilitation
Thisprogramprovidesfundsforthedesign,repair,rehabilitation,replacement,painting,inspectionoftunnels/bridges,andotherworksuchas
movablebridgeprogram,drawbridgepowerprogram,andculvert/bridge/tunnelrightofwayimprovementsnecessarytomaintainastateofgood
repair.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Various
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(BridgeAssetsNJTRANSITBridges)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M9,S19(Exempt)
MPO
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
Phase
Fund
DVRPC
ERC
STATE
$0.997
$0.880
$0.998
$1.441
$1.441
$1.441
$1.441
$1.441
$1.677
$1.677
$13.434
NJTPA
ERC
STATE
$27.302
$39.220
$32.070
$22.880
$22.880
$22.880
$22.880
$22.880
$26.597
$26.597
$266.186
SJTPO
ERC
STATE
$0.211
$0.190
$0.209
$0.302
$0.302
$0.302
$0.302
$0.302
$0.355
$0.355
$2.830
SectionIVPage2
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T32
BuildingCapitalLeases
FundingisprovidedforcapitalimprovementsandleasepaymentobligationsatNJTRANSIToperatingandofficeinstallations.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Various
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(TransportationSupportFacilitiesNJTRANSITFacilitiesandEquipment)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M1,MT8(Exempt)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
CAP
STATE
$1.311
$1.311
$2.622
NJTPA
CAP
STATE
$3.990
$3.990
$7.980
SJTPO
CAP
STATE
$0.399
$0.399
$0.798
SectionIVPage3
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T111
BusAcquisitionProgram
Thisprogramprovidesfundsforreplacementoftransit,commuter,accesslink,andsuburbanbusesforNJTRANSITastheyreachtheendoftheir
usefullifeaswellasthepurchaseofadditionalbusestomeetservicedemands.Federalleasepaymentsareprovidedfor1371Cruiserbuses.Payas
yougofundingisprovidedforover2300busesreplacementsoverthenext10years.
TollCreditwillbeusedasthenonfederalmatch.AnexplanationoftollcreditcanbefoundintheIntroductionSectionoftheSTIP.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: Various
COUNTY: Various
LEGISLATIVEDISTRICT: Various
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsBus)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M10,MT3,MT10(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
2013
2014
2015
Total
BusAcquisitionProgram
DVRPC
SECT5339/5307
$0.440
$0.440
BusAcquisitionProgram
NJTPA
SECT5339/5307
$1.340
$1.340
BusAcquisitionProgram
SJTPO
SECT5339/5307
$0.130
$0.130
MPO
Phase
Fund
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
DVRPC
CAP
STATE
$14.836
$39.684
$28.750
$28.750
$328.603
NJTPA
CAP
STATE
$45.152 $103.260 $113.730 $111.400 $105.000 $105.000 $120.779 $120.779
$87.500
$87.500
$1,000.100
SJTPO
CAP
STATE
$8.750
$8.750
$100.009
$4.515
$33.930
$10.330
$37.367
$11.371
$36.602
$11.139
SectionIVPage4
$34.500
$10.500
$34.500
$10.500
$39.684
Total
$12.077
$12.077
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T93
BusMaintenanceFacilities
Thisprogramprovidesfundsforbusmaintenancefacilitiessystemwide.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Various
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsBus)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT8(Exempt)
MPO
Phase
Fund
NJTPA
ERC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.000
$2.000
Total
$3.000
SectionIVPage5
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T06
BusPassengerFacilities/ParkandRide
Thisprogramprovidesfundsforthebusparkandrideprogram,improvementstobuspassengerfacilitiesandthepurchaseandinstallationofbus
stopsignsandshelterssystemwide.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Various
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsBus)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT8,R6(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
BusPassengerFacilities/ParkandRide(FrankR.LautenbergGroundTranps.
ImprovBusLivability)
NJTPA
SECT5307
2013
2014
2015
$2.000
Total
$2.000
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
ERC
STATE
$0.184
$0.180
$0.184
$0.184
$0.184
$0.184
$0.184
$0.184
$0.184
$0.184
$1.836
NJTPA
ERC
STATE
$0.560
$1.060
$0.560
$0.560
$0.560
$0.560
$0.560
$0.560
$0.560
$0.560
$6.100
SJTPO
ERC
STATE
$0.056
$0.060
$0.056
$0.056
$0.056
$0.056
$0.056
$0.056
$0.056
$0.056
$0.564
SectionIVPage6
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T08
BusSupportFacilitiesandEquipment
ThisprogramprovidesfundstomaintainNJTRANSITsbusfleetincludingbutnotlimitedto,bustires,enginesandtransmissionsandotherparts,
supportvehicles\equipment(forbusoperations),maintenanceequipment,andbusmidlifeoverhaulneeds.Alsoincludedismidliferehabilitationof
busfacilities,othercapitalimprovementstovarioussupportfacilitiesandbusmidlifeoverhauls.
ThisprogramalsoinvolvesthereplacementoftwoCNGCompressorfillingstationsatHowellGarage.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: Various
COUNTY: Various
LEGISLATIVEDISTRICT: Various
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsBus)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M5,MT3,MT8(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
BusSupportFacilitiesandEquipment
NJTPA
SECT5339/5307
2013
2014
2015
Total
$2.040
$2.040
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
MPO
Phase
Fund
DVRPC
ERC
SECT5339/5307
DVRPC
ERC
STATE
$1.264
$0.558
NJTPA
ERC
STATE
$3.850
$2.200
SJTPO
ERC
SECT5339/5307
SJTPO
ERC
STATE
$0.384
$0.170
Total
$2.800
$2.800
$2.800
$2.800
$2.800
$2.800
$0.558
$1.478
$1.478
$1.478
$1.478
$1.478
$1.478
$1.478
$12.726
$4.501
$4.501
$43.258
$5.701
$4.501
$4.501
$4.501
$4.501
$4.501
$0.900
$0.900
$0.900
$0.900
$0.900
$0.900
$0.170
$0.450
$0.450
$0.450
$0.450
$0.450
SectionIVPage7
$16.800
$5.400
$0.450
$0.450
$3.874
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T09
BusVehicleandFacilityMaintenance/CapitalMaintenance
Fundingisprovidedforacquisition/installation/rehabilitationofmajorcomponentsassociatedwithcapitalequipmentandfacilitiesinaccordance
withTransportationTrustFundrequirementsandexpandedeligibilitycriteria.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Various
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsBus)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M5,MT8,MT10(Exempt)
MPO
Phase
Fund
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
DVRPC
EC
STATE
$0.184
$0.290
$8.027
$8.027
$8.027
$8.027
$8.027
$8.027
$8.027
$56.663
NJTPA
EC
STATE
$8.560
$5.390
$4.800
$24.430
$24.430
$24.430
$24.430
$24.430
$24.430
$24.430
$189.760
SJTPO
EC
STATE
$0.056
$0.090
$0.000
$2.443
$2.443
$2.443
$2.443
$2.443
$2.443
$2.443
$17.247
SectionIVPage8
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T68
CapitalProgramImplementation
Fundingisprovidedforcapitalprojectmanagementactivitiesassociatedwithcapitalprogram/projectdeliveryincludingprocurementandDBE/SBE
activities.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Various
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M1,MT10,O10A(Exempt)
MPO
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
Phase
Fund
DVRPC
ERC
STATE
$4.938
$4.938
$4.938
$4.938
$4.938
$4.938
$4.938
$4.938
$4.938
$4.938
$49.380
NJTPA
ERC
STATE
$15.030
$15.030
$15.030
$15.030
$15.030
$15.030
$15.030
$15.030
$15.029
$15.029
$150.298
SJTPO
ERC
STATE
$1.502
$1.502
$1.502
$1.502
$1.502
$1.502
$1.502
$1.502
$1.502
$1.502
$15.020
SectionIVPage9
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T515
CasinoRevenueFund
Statelawprovides8.5%oftheCasinoTaxFundtobeappropriatedfortransportationservicesforsenioranddisabledpersons.Thiselementalso
supportscapitalimprovementsthatbenefitthesenioranddisabledpopulations.Thelawprovides85%ofthesefundstobemadeavailabletothe
countiesthroughNJTRANSITforcapital,operating,andadministrativeexpensesfortheprovisionoflocallycoordinatedparatransitservices.The
amounteachcountyreceivesisdeterminedbyutilizinganallocationformulabasedonthenumberofresidents60yearsofageandoverasreflectedin
themostrecentU.S.CensusReport.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
COUNTY: Various
MUNICIPALITY: Various
LEGISLATIVEDISTRICT: Various
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(LocalSystemSupportNJTRANSITLocalSystemSupport)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M1,MT1,MT2(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
2013
2014
2015
Total
CasinoRevenueFund
DVRPC
CASINOREVENUE
$4.677
$4.200
$8.877
CasinoRevenueFund
NJTPA
CASINOREVENUE
$14.243
$12.783
$27.026
CasinoRevenueFund
SJTPO
CASINOREVENUE
$1.423
$1.278
$2.701
MPO
Phase
Fund
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
DVRPC
CAP
CASINOREVENUE
$4.329
$4.329
$4.329
$4.329
$4.329
$4.329
$4.329
$4.329
$4.329
$4.329
$43.292
NJTPA
CAP
CASINOREVENUE
$13.177
$13.177
$13.177
$13.177
$13.177
$13.177
$13.177
$13.177
$13.177
$13.177
$131.775
SJTPO
CAP
CASINOREVENUE
$1.317
$1.317
$1.317
$1.317
$1.317
$1.317
$1.317
$1.317
$1.317
$1.317
$13.174
SectionIVPage10
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T13
Claimssupport
Fundingisprovidedforclaimsrelatedtocapitalprojects,expertwitnesses,courtsettlement,andothercoststodefendNJTRANSITsinterestsasa
resultoflitigation.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Various
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M1,MT1,O10A(Exempt)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
EC
STATE
$0.460
$0.460
$0.460
$0.460
$0.460
$0.460
$0.460
$0.460
$0.460
$0.460
$4.600
NJTPA
EC
STATE
$1.400
$1.400
$1.400
$1.400
$1.400
$1.400
$1.400
$1.400
$1.400
$1.400
$14.000
SJTPO
EC
STATE
$0.140
$0.140
$0.140
$0.140
$0.140
$0.140
$0.140
$0.140
$0.140
$0.140
$1.400
SectionIVPage11
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T170
CumberlandCountyBusProgram
ThisprogramprovidesfundsforcapitalandoperatingassistanceforCumberlandCountyUSA,includingpurchaseofbuses,minivans,support
equipment,facilityimprovementsandcapitalmaintenancecosts.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
TollCreditwillbeusedasthenonfederalmatch.AnexplanationoftollcreditcanbefoundintheIntroductionSectionoftheSTIP.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Cumberland
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(LocalSystemSupportNJTRANSITLocalSystemSupport)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT1(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
CumberlandCountyBusProgram
SJTPO
SECT5307
MPO
Phase
Fund
SJTPO
CAP
SECT5307
2013
2014
2015
Total
$1.020
$1.020
$2.040
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$1.020
$1.020
$1.020
$1.020
SectionIVPage12
$1.020
$1.020
$1.020
$1.020
$1.020
$1.020
Total
$10.200
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T907
DelcoLeadSafeHavenStorageandReinspectionFacilityProject
FundingisprovidedtobuildtheDelcoLeadSafeHavenStorageandReInspectionFacility.TheDelcoLeadprojectislocatedinNorthBrunswick
TownshipandtheCityofNewBrunswickalongtheNortheastCorridor(NEC)raillineadjacenttotheConrail“DelcoSecondary”.TheSafeHaven
Storagewillprovideresilientstoragethatwillprotectequipmentagainstdamageresultingfromastormbyaccommodatingthestorageof
approximately150electrifiedrailpassengercars.Combiningthiswiththereconfigurationandimprovementoftheexistinglongfreighttrack,storage
ofanother260pluspassengerrailcarsmaybepossible.Alsoincludedinthisprojectistheadditionofafacilityforrollingstockinspectionand
smallerrepairs.Theserviceandinspectionfacilitywillfacilitatetherapidreturnofequipmenttoservicefollowingastormevent.
ThesourceofthelocalfundingistheStateTransportationTrustFund(TTF)intheamountof$61,497,970.TheSTIPIDisDB#T44,NEC
Improvements.The$61,497,970includes$30,000,000ofunspentfundingappropriatedinSFY14andprioryearsforNJTRANSITsNEC
Improvementsprogram.Inaddition,NJTRANSITisallocating$31,497,970fromtheNECImprovementsprogramfromtheSFY1524Constrained
CapitalProgram;including$18,000,000inSFY15,$10,000,000inSFY16and$3,497,970inSFY17.
COUNTY: Various
MUNICIPALITY: Various
LEGISLATIVEDISTRICT: Various
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): NA(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
DelcoLeadSafeHavenStorageandReinspectionFacilityProject
NJTPA
SECT5324
MPO
Phase
Fund
NJTPA
ERC
SECT5324
2013
2014
2015
Total
$4.800
$4.800
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$179.694
Total
$179.694
SectionIVPage13
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T16
EnvironmentalCompliance
Fundingisprovidedforcompliancewithenvironmentalregulationsatbothbusandrailfacilitiesincludesbutisnotlimitedtoreplacementofleaking
fueltanks,cleanupofcontaminatedsoilandgroundwater,oil/waterseparators,asbestosremoval,andfuelingstationimprovementsatvarious
facilities.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Various
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M1,MT8,O10A(Exempt)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
ERC
STATE
$0.690
$0.690
$0.690
$0.690
$0.690
$0.690
$0.690
$0.690
$0.690
$0.690
$6.900
NJTPA
ERC
STATE
$2.100
$2.100
$2.100
$2.100
$2.100
$2.100
$2.100
$2.100
$2.100
$2.100
$21.000
SJTPO
ERC
STATE
$0.210
$0.210
$0.210
$0.210
$0.210
$0.210
$0.210
$0.210
$0.210
$0.210
$2.100
SectionIVPage14
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T908
HobokenLongSlipFloodProtectionProject
FundingisprovidedtobuildtheDelcoLeadSafeHavenStorageandReInspectionFacility.TheDelcoLeadprojectislocatedinNorthBrunswick
TownshipandtheCityofNewBrunswickalongtheNortheastCorridor(NEC)raillineadjacenttotheConrail“DelcoSecondary”.TheSafeHaven
Storagewillprovideresilientstoragethatwillprotectequipmentagainstdamageresultingfromastormbyaccommodatingthestorageof
approximately150electrifiedrailpassengercars.Combiningthiswiththereconfigurationandimprovementoftheexistinglongfreighttrack,storage
ofanother260pluspassengerrailcarsmaybepossible.Alsoincludedinthisprojectistheadditionofafacilityforrollingstockinspectionand
smallerrepairs.Theserviceandinspectionfacilitywillfacilitatetherapidreturnofequipmenttoservicefollowingastormevent.
ThesourceofthelocalfundingistheStateTransportationTrustFund(TTF)intheamountof$61,497,970.TheSTIPIDisDB#T44,NEC
Improvements.The$61,497,970includes$30,000,000ofunspentfundingappropriatedinSFY14andprioryearsforNJTRANSITsNEC
Improvementsprogram.Inaddition,NJTRANSITisallocating$31,497,970fromtheNECImprovementsprogramfromtheSFY1524Constrained
CapitalProgram;including$18,000,000inSFY15,$10,000,000inSFY16and$3,497,970inSFY17.
COUNTY: Various
MUNICIPALITY: Various
LEGISLATIVEDISTRICT: Various
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT8(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
HobokenLongSlipFloodProtectHobokenLongSlipFloodProtectionProject
NJTPA
SECT5324
MPO
Phase
Fund
NJTPA
ERC
SECT5324
2013
2014
2015
Total
$2.100
$2.100
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$144.448
Total
$144.448
SectionIVPage15
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T87
HudsonBergenandNewarkLRTSystem
FundingisprovidedforannualHudsonBergenCapitalAssetReplacementimprovements,andotherimprovementsalongtheHudsonBergenand
NewarkLightRailLine,includingrollingstockenhancements.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Hudson
LEGISLATIVEDISTRICT: 31,33
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsLightRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT1(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
HudsonBergenLRTSystem
NJTPA
CMAQ
MPO
Phase
Fund
NJTPA
ERC
STATE
2013
2014
2015
Total
$47.000
$13.000
$60.000
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$7.005
$7.005
$7.005
$7.005
SectionIVPage16
$7.005
$7.005
$7.005
$7.005
$7.005
$7.005
Total
$70.050
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T20
ImmediateActionProgram
Fundingisprovidedforemergencyprojectneedsundertherail,bus,andheadquartersprograms;contractchangeorders;consultantagreement
modifications;andotherunanticipatedworkidentifiedduringthecourseoftheyear,thusallowingtheagencytoberesponsivetoemergencyand
unforeseencircumstanceswhichariseunexpectedly.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Various
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M1,O10A,S12(Exempt)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
ERC
STATE
$4.161
$3.170
$2.420
$2.474
$2.529
$2.586
$2.646
$2.646
$3.106
$3.106
$28.844
NJTPA
ERC
STATE
$6.166
$6.668
$8.890
$9.058
$9.221
$9.398
$9.580
$9.580
$10.976
$10.976
$90.513
SJTPO
ERC
STATE
$1.255
$0.960
$0.725
$0.741
$0.758
$0.775
$0.793
$0.793
$0.933
$0.933
$8.666
SectionIVPage17
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T905
InteroperationalCommunicationsResiliency
Fundingisprovidedforupgradestotelecommunicationssystemsandfacilitiestoensurecriticalpersonnelhavetheabilitytocommunicateandhave
thenecessarycommandandcontrolcapabilitiesduringfuturestorms,andservicerecoveryperiodfollowingstorms,includingupgradestoNJ
TRANSIT’spolicecapabilities.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Various
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsTechnology)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT6(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
InteroperationalCommunicationsResiliency
NJTPA
SECT5324
MPO
Phase
Fund
NJTPA
ERC
SECT5324
2013
2014
2015
$30.000
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
$30.000
Total
SectionIVPage18
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T199
JobAccessandReverseCommuteProgram
FundingisprovidedtocontinuetheJobAccessandReverseCommute(JARC)programwithnonfederalfunds.MovingAheadforProgressinthe
21stCentury(MAP21)eliminatedtherequirementfordedicatedFederalfundingforJARC.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Various
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(LocalSystemSupportNJTRANSITLocalSystemSupport)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT1,O10B,O10C(Exempt),2017O(NonExempt)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
SWI
MATCH
$0.989
$0.989
$0.989
$0.989
$0.989
$0.989
$0.989
$0.989
$0.989
$0.989
$9.890
DVRPC
SWI
OPER
$0.989
$0.989
$0.989
$0.989
$0.989
$0.989
$0.989
$0.989
$0.989
$0.989
$9.890
NJTPA
SWI
MATCH
$3.010
$3.010
$3.010
$3.010
$3.010
$3.010
$3.010
$3.010
$3.010
$3.010
$30.100
NJTPA
SWI
OPER
$4.578
$3.010
$3.010
$3.010
$3.010
$3.010
$3.010
$3.010
$3.010
$3.010
$31.668
SJTPO
SWI
MATCH
$0.301
$0.301
$0.301
$0.301
$0.301
$0.301
$0.301
$0.301
$0.301
$0.301
$3.010
SJTPO
SWI
OPER
$0.301
$0.301
$0.301
$0.301
$0.301
$0.301
$0.301
$0.301
$0.301
$0.301
$3.010
SectionIVPage19
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T535
LackawannaCutoffMOSProject
FundingisprovidedforFY2008NewStartsearmarksfortheLackawannaCutoffRailproject,whichwillprovidean88mile,singletrackcommuter
raillinewithpassingsidingsbetweenScranton,PennsylvaniaandPortMorris,NewJerseywhereitwillconnectwithNJTRANSITs
Boonton/MorristownLine.
TollCreditwillbeusedasthenonfederalmatch.AnexplanationoftollcreditcanbefoundintheIntroductionSectionoftheSTIP.
Thetotalprojectcostofthe7.3mileLackawannaCutoffMOSprojectis$61.624million.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: Various
COUNTY: Morris,Sussex,Warren
LEGISLATIVEDISTRICT: 25,24,23
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(CongestionReliefNJTRANSITCongestionRelief)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): 2020M(NonExempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
LackawannaCutoffMOSProject
NJTPA
SECT5307
MPO
Phase
Fund
NJTPA
ERC
STATE
2013
2014
2015
Total
$2.200
$1.710
$13.000
$16.910
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
SectionIVPage20
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T95
LightRailInfrastructureImprovements
FundingisprovidedforLightRailimprovementsincluding,butnotlimitedto,communicationsystemsupgrade,accessibilityimprovements,vehicle
andfacilityimprovements,andotherinfrastructurerehabilitationimprovements.FundingisalsoprovidedforNLRInfrastructureandRiverLine
capitalassetreplacement.
TollCreditwillbeusedasthenonfederalmatch.AnexplanationoftollcreditcanbefoundintheIntroductionSectionoftheSTIP.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: NewarkCity
COUNTY: Various
LEGISLATIVEDISTRICT: 28,29
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsLightRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M5,MT9(Exempt)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
ERC
STATE
$3.250
$2.000
$2.000
$2.300
$2.300
$2.300
$2.300
$2.300
$2.300
$2.300
$23.350
NJTPA
ERC
STATE
$9.025
$5.275
$5.275
$4.975
$4.975
$4.975
$4.975
$4.975
$4.975
$4.975
$54.400
SectionIVPage21
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T904
LightRailResiliency
FundingisprovidedtoimprovetheresiliencyofHudsonBergenLightRailandNewarkCitySubway.NewarkLightRailwasfloodedatPennStation
duringSuperstormSandy,andHudsonBergenLightRailexperiencedwashouts,downedcatenaryanddebristhroughout.Resiliencyprojectsinclude
raisingsubstations,improvingdrainage,installingpumpsandotherfloodmitigations.Fundingisalsoprovidedforresiliencyofferryfacilities
adjacenttoLightRailatHobokenTerminal.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsLightRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT6,MT8(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
LightRailResiliency
DVRPC
SECT5324
$0.200
$0.200
LightRailResiliency
NJTPA
SECT5324
$13.440
$13.440
MPO
Phase
Fund
NJTPA
ERC
SECT5324
2013
2014
2015
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
Total
SectionIVPage22
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T550
LightRailVehicleRollingStock
FundingisprovidedforannualleasepaymentsforHudsonBergenLightRail,NewarkCitySubwayandNewarkCitySubwayExtensionvehicles.
TollCreditwillbeusedasthenonfederalmatch.AnexplanationoftollcreditcanbefoundintheIntroductionSectionoftheSTIP.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Various
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsLightRailRollingStockDebt)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT10(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
LightRailVehicleRollingStock
NJTPA
SECT5307
MPO
Phase
Fund
NJTPA
ERC
SECT5307
2013
2014
2015
Total
$27.735
$1.540
$29.275
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$43.421
Total
$43.421
SectionIVPage23
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T53E
LocomotiveOverhaul
Fundingisprovidedforthecyclicoverhauloflocomotivesbasedonmanufacturerreplacementstandardstosupporttheequipmentthroughitsuseful
life.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Various
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M3,MT3(Exempt)
MPO
Phase
Fund
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
DVRPC
CAP
STATE
$1.358
$1.704
$0.296
$0.296
$0.296
$0.296
$0.296
$0.296
$0.296
$0.296
$5.430
NJTPA
CAP
STATE
$23.697
$27.022
$4.702
$4.702
$4.702
$4.702
$4.702
$4.702
$4.700
$4.700
$88.331
SJTPO
CAP
STATE
$0.287
$0.359
$0.062
$0.062
$0.062
$0.062
$0.062
$0.062
$0.062
$0.062
$1.142
SectionIVPage24
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T610
LyndhurstIntermodalADAImprovements
FundingisprovidedfortheLyndhurststationconstructiontomakethestationADAaccessible.
TollCreditwillbeusedasthenonfederalmatch.AnexplanationoftollcreditcanbefoundintheintroductionsectionoftheSTIP.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: LyndhurstTwp
SPONSOR: NJTRANSIT
COUNTY: Bergen
LEGISLATIVEDISTRICT: 36
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT8(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
MPO
Description
Fund
2013
2014
2015
$2.000
LyndhurstImprovements
NJTPA
SECT5307
LyndhurstImprovements
NJTPA
SECT5307TAP
$2.000
$2.000
LyndhurstImprovements
NJTPA
STPTAP
$0.500
$2.000
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
MPO
Phase
Fund
NJTPA
ERC
SECT5307TAP
$2.000
$2.000
NJTPA
ERC
STATE
$2.000
$1.000
$2.000
Total
$4.000
$0.500
Total
$6.000
$3.000
SectionIVPage25
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T901
MeadowsMaintenanceComplex(MMC)/RailOperationsCenter(ROC)Resiliency
FundingisprovidedtoimprovetheresiliencyoftheMeadowsMaintenanceComplexandNJTRANSIT’sRailOperationsCenter,Kearny,NJ.The
MMCisNJTRANSIT’sprimarymaintenancefacility,andtheadjacentRailOperationsCentercontrolsNJTRANSIT’sentirenetwork.Whiletheyard
willbeevacuatedforfuturestorms,theMMCandROCbuildingsandshopsmustweatherfuturestormsinplace.Potentialresiliencyprojectsinclude
floodwalls,berms,sparepartssolutions,hardeningoftheROCand/orrelocationofthefacility.
TollCreditwillbeusedasthenonfederalmatch.AnexplanationoftollcreditcanbefoundintheIntroductionSectionoftheSTIP.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Various
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT8(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
MeadowsMaintenanceComplex(MMC)/RailOperationsCenter(ROC)Resiliency
NJTPA
SECT5324
MPO
Phase
Fund
NJTPA
ERC
SECT5324
2013
2014
2015
$31.600
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
$31.600
Total
SectionIVPage26
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T122
Miscellaneous
Fundingisprovidedforthecontinuationofthemandatedvitalrecordsprogramandothermiscellaneousadministrativeexpensessuchas,butnot
limitedto,matchfundsforspecialservicesgrantsandphysicalplantimprovementsincurredthroughouttheyear.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Various
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M1,O10A,O10B(Exempt)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
ERC
STATE
$0.115
$0.115
$0.115
$0.115
$0.115
$0.115
$0.115
$0.115
$0.115
$0.115
$1.150
NJTPA
ERC
STATE
$0.350
$0.350
$0.350
$0.350
$0.350
$0.350
$0.350
$0.350
$0.350
$0.350
$3.500
SJTPO
ERC
STATE
$0.035
$0.035
$0.035
$0.035
$0.035
$0.035
$0.035
$0.035
$0.035
$0.035
$0.350
SectionIVPage27
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T600
NECElizabethIntermodalStationImprovements
FundingisprovidedforthereconstructionofthepassengerplatformsandstationbuildingatElizabethRailStation,including,butnotlimitedtonew
elevatorsandstairs,ticketandoperationalofficespace,andretailspace.
TollCreditwillbeusedasthenonfederalmatch.AnexplanationoftollcreditcanbefoundintheintroductionsectionoftheSTIP.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: ElizabethCity
SPONSOR: NJTRANSIT
COUNTY: Union
LEGISLATIVEDISTRICT: 20
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT8(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
NECElizabethRailStationImprovements
NJTPA
SECT5307
NECElizabethRailStationImprovements
NJTPA
SECT5339/5307
Fund
2013
2014
2015
Total
$2.000
$11.499
$0.350
$13.849
$5.920
$5.920
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
MPO
Phase
NJTPA
ERC
SECT5307
$6.275
NJTPA
ERC
SECT5339/5307
$8.175
Total
$6.275
$5.500
$13.675
SectionIVPage28
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T44
NECImprovements
FundingisprovidedforimprovementstotheNortheastCorridor(NEC)tomaintainstateofgoodrepair,increasecapacity,andimproveefficiency.
FundingisprovidedforAMTRAKjointbenefitprojectsandforNJTRANSITprojectssuchas,MidlineLoopinNorthBrunswick,NewJersey
includingassociatedtrackandstationimprovements;platformextensions;improvementsatNewYorkPennStation;andyardimprovements.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsAMTRAK)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M1,MT9(Exempt)
MPO
Phase
Fund
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
DVRPC
ERC
STATE
$1.700
$6.400
NJTPA
ERC
SECT5307
$13.000
$13.000
$3.000
$2.750
NJTPA
ERC
STATE
$27.300
$64.280 $118.710 $105.435
SectionIVPage29
$9.750
$87.750
$9.750
$87.750
$9.750
$87.750
$9.750
Total
$9.750
$9.750
$72.350
$13.000
$13.000
$52.000
$87.750 $138.342 $138.342
$943.409
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T81
NECNewarkIntermodal
FundingisprovidedforNewarkIntermodalprojects,includinghistoricrestoration,structuralrehabilitationandlightingimprovements,customer
facilityimprovements,pedestrianandtrafficcirculationimprovements,andanyrelatedtrackandrailinfrastructurework.Theseimprovementswill
makethestationmorefunctional,attractiveandmorecustomerfriendly.ImprovementswillallowforcontinuedincreaseinridershipusingNewark
PennStationandhavecleanairandeconomicbenefits.ImprovementstotheNewarkLightRailarealsoincluded.
TollCreditwillbeusedasthenonfederalmatch.AnexplanationoftollcreditcanbefoundintheintroductionsectionoftheSTIP.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: NewarkCity
COUNTY: Essex
LEGISLATIVEDISTRICT: 29
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT8(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
NECNewarkIntermodal
NJTPA
SECT5307
NECNewarkIntermodal
NJTPA
STPTAP
MPO
Phase
Fund
NJTPA
ERC
SECT5307
NJTPA
ERC
SECT5307TAP
NJTPA
ERC
SECT5339/5307
NJTPA
ERC
STATE
NJTPA
ERC
STPTAP
2013
2014
2015
Total
$3.296
$0.950
$4.246
$0.500
$0.500
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.579
$0.240
$17.538
$18.357
$2.000
$1.901
$2.000
$2.000
$2.000
$2.000
$7.700
$2.000
$2.000
$14.000
$13.200
$13.200
$36.001
$0.500
Total
$0.500
$1.000
$1.000
SectionIVPage30
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$9.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T539
NECPortalBridge
ThisprojectinvolvesexpansionofrailcapacityontheNortheastCorridoracrosstheHackensackRiverinthevicinityoftheexistingPortalBridge.
ThePortalBridgeisanalmost100yearold,twotrack,moveableswingspanrailbridgeovertheHackensackRiverinNewJerseybetweenthecitiesof
KearnyandSecaucus.Theprojectwillevaluatealternativesincludingreplacement,rehabilitationormodificationoftheexistingbridgealongwiththe
constructionofanadditionalbridgeforaddedcapacity.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: KearnyTown,Secaucus
SPONSOR: NJTRANSIT
COUNTY: Hudson
LEGISLATIVEDISTRICT: 32
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): 2020NM(NonExempt)
MPO
Phase
Fund
NJTPA
ERC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$4.000
Total
$4.000
SectionIVPage31
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T28
NewarkLightRailImprovements
FundingisprovidedforNewarkLightRailimprovementstopassengerfacilitiesandinfrastructureincluding,butnotlimitedto,stationandplatform
upgrades,communicationsystemsupgrade,accessibilityimprovements,vehicleandfacilityimprovements,andotherinfrastructurerehabilitation
improvements.
TollCreditwillbeusedasthenonfederalmatch.AnexplanationoftollcreditcanbefoundintheIntroductionSectionoftheSTIP.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: NewarkCity
COUNTY: Essex
LEGISLATIVEDISTRICT: 28,29
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsLightRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT3,MT6,MT8(Exempt)
MPO
Phase
Fund
NJTPA
ERC
SECT5339/5307
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$13.600
$13.600
SectionIVPage32
$13.600
$13.600
$13.600
$13.600
Total
$81.600
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T910
NJTRANSITGridProject
Fundingisprovidedtocreateamicrogridpowergenerationanddistributionsystem.NJTRANSITGRIDwillbecapableofsupplyinghighlyreliable
powerduringstormsorothertimeswhenthecentralizedpowergridiscompromised.NJTRANSITGRIDwillincorporaterenewableenergy,
distributedgeneration,andothertechnologiestoprovideresilientpowertokeyNJTRANSITstations,maintenancefacilities,busgarages,andother
buildings.NJTRANSITGRIDwillalsoprovideresilientelectrictractionpowertoallowNJTRANSITtrainsoncriticalcorridors,includingportionsof
theNortheastCorridor,tocontinuetooperateevenwhenthetraditionalgridfails.ThisprojectwilldirectlybenefitNJTRANSITandAmtrak.The
sourceofthelocalfundingistheStateTransportationTrustFund(TTF).
ThesourceoflocalfundingistheStateTransportationTrustFund(TTF)intheamount$144,616,890.TheSTIPIDisDB#T50,Signalsand
Communications/ElectricTractionSystemsprogram(S&CProgram).TheTTFcomponentincludes$45,000,000ofunspentfundingappropriatedin
SFY14andprioryearsforNJTRANSITsfromtheS&CProgram.Inaddition,NJTRANSITisallocating$99,616,890fromtheSFY1524Constrained
CapitalProgram;including$33,881,000inSFY15,$15,640,000inSFY16,$9,381,890inSFY17;$17,464,000inSFY18and$23,250,000inSFYfromtheS&C
program.
COUNTY: Various
MUNICIPALITY: Various
LEGISLATIVEDISTRICT: Various
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT6(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
NJTRANSITGridProject
NJTPA
SECT5324
MPO
Phase
Fund
NJTPA
ERC
SECT5324
2013
2014
2015
Total
$1.300
$1.300
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$15.300 $393.165
Total
$408.465
SectionIVPage33
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T909
NJTRANSITRaritanRiverDrawbridgeReplacementProject
FundingisprovidedtoreplacetheagedanddeterioratedRaritanRiverDrawbridgelocatedinMiddlesexCountyontheNorthJerseyCoastline
(NJCL).TheRaritanRiverDrawbridgewasdamagedbySuperstormSandy.Thedrawbridgewillbereplacedwithamoreresilientstructurethatis
lessvulnerabletostormsurgeandflooding,thusenhancingthereliabilityoftheNJCL.
ThesourceofthelocalfundingistheStateTransportationTrustFund(TTF)intheamountof$148,720,822.TheSTIPIDisDB#T05,BridgeandTunnel
Rehabilitationprogram.The$148,720,822fromtheBridgeandTunnelRehabilitationprogramisfromtheSFY1524ConstrainedCapitalProgram;
including$4,750,000inSFY15,$5,000,000inSFY16,$5,000,000inSFY17,$5,000,000inSFY18,$70,887,000inSFY19and$58,083,822inSFY20.
MUNICIPALITY: Various
COUNTY: Various
LEGISLATIVEDISTRICT: Various
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O9(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
NJTRANSITRaritanRiverDrawbridgeReplacementProject
NJTPA
SECT5324
MPO
Phase
Fund
NJTPA
ERC
SECT5324
2013
2014
2015
Total
$1.650
$1.650
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$444.662
Total
$444.662
SectionIVPage34
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T906
NJTRANSITSystemRepairs/Restoration
FundingisprovidedtooperateandrestoreNJTRANSIT’srail,bus,lightrailandferrysystems,includingcostsforsubstituteservicethatwas
providedwhenrailservicewasunavailable.NJTRANSIT’ssystemwasheavilydamagedbySuperstormSandy,experiencingwashouts,bridge
damage,facilityimpacts,androllingstockdamage.FundingisprovidedtoreimburseNJTRANSITforcostsalreadyincurredandfuturecoststo
repairdamage.
TollCreditwillbeusedasthenonfederalmatch.AnexplanationoftollcreditcanbefoundintheIntroductionSectionoftheSTIP.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Various
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O9(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
NJTRANSITSystemRepairs/Restoration
DVRPC
SECT5324
$0.025
$0.025
NJTRANSITSystemRepairs/Restoration
NJTPA
SECT5324
$119.023
$119.023
NJTRANSITSystemRepairs/Restoration
SJTPO
SECT5324
$0.100
$0.100
MPO
Phase
Fund
NJTPA
ERC
SECT5324
2013
2014
2015
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
Total
SectionIVPage35
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T55
OtherRailStation/TerminalImprovements
Fundingisprovidedforthedesign,landacquisitionandconstructionofvariousstations,platformextensions,parkingandrelatedfacilities,and
upgradesthroughoutthesystemincludingrelatedtrackandrailinfrastructurework.Alsoincludedarestationandfacilityinspectionandrepair,
customerservicestationbikelockerinstallationsystemwide,andSTARSProgram.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Various
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M8,MT3,MT8(Exempt)
MPO
Phase
Fund
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
DVRPC
ERC
STATE
$0.165
$0.160
$0.164
$2.508
$2.508
$2.508
$2.508
$2.508
$2.508
$2.508
$18.045
NJTPA
ERC
STATE
$20.310
$7.460
$2.612
$39.772
$39.772
$39.772
$39.772
$39.772
$39.770
$39.770
$308.782
SJTPO
ERC
STATE
$0.035
$0.030
$0.034
$0.530
$0.530
$0.530
$0.530
$0.530
$0.530
$0.530
$3.809
SectionIVPage36
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T620
PerthAmboyIntermodalADAImprovements
FundingisprovidedfortheconstructionofhighlevelplatformsinordertoenhanceaccesstocommutertrainsinconformancewithADAregulations.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: PerthAmboyCity
SPONSOR: NJTRANSIT
COUNTY: Middlesex
LEGISLATIVEDISTRICT: 19
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT8(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
PerthAmboyStationImprovements
NJTPA
SECT5307
PerthAmboyStationImprovements
NJTPA
SECT5339/5307
PerthAmboyStationImprovements
NJTPA
STPTAP
2013
2014
2015
Total
$6.048
$4.752
$3.410
$14.210
$4.700
$4.700
$0.500
$1.000
$0.500
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
MPO
Phase
Fund
NJTPA
ERC
SECT5307
$2.298
$2.710
Total
$5.008
NJTPA
ERC
SECT5339/5307
$3.125
NJTPA
ERC
STATE
$0.383
$0.091
$3.125
$0.474
NJTPA
ERC
STPTAP
$0.500
$0.500
$1.000
SectionIVPage37
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T121
PhysicalPlant
Fundingisprovidedfordemolitionofoutofservicefacilities,energyconservationprogram,workenvironmentimprovements,replacementof
antiquatedadministrativesupportequipment,purchaseofmaterialwarehouseequipment,replacementofnonrevenuevehicles,andotherminor
improvementstovariousbus/railfacilities.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Various
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(TransportationSupportFacilitiesNJTRANSITFacilitiesandEquipment)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M8,MT1,MT4(Exempt)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
ERC
STATE
$0.383
$0.383
$0.383
$0.383
$0.383
$0.383
$0.383
$0.383
$0.384
$0.384
$3.832
NJTPA
ERC
STATE
$1.171
$1.171
$1.171
$1.171
$1.171
$1.171
$1.171
$1.171
$1.169
$1.169
$11.706
SJTPO
ERC
STATE
$0.116
$0.116
$0.116
$0.116
$0.116
$0.116
$0.116
$0.116
$0.116
$0.116
$1.160
SectionIVPage38
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T135
PreventiveMaintenanceBus
Thisprogramprovidesfundingfortheoverhaulofbusesincludingpreventivemaintenancecostsinaccordancewithfederalguidelinesasdefinedin
theNationalTransitDatabaseReportingManualandfederallaw.
TollCreditwillbeusedasthenonfederalmatch.AnexplanationoftollcreditcanbefoundintheIntroductionSectionoftheSTIP.Inaddition,
expendituresareforcostsofprojectsinspecificyearsonly.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Various
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsBus)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M3,MT3(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
MPO
Fund
PreventiveMaintenanceBus
DVRPC
SECT5307
$41.300
$41.300
PreventiveMaintenanceBus
DVRPC
STPSTU
$16.000
$16.000
PreventiveMaintenanceBus
NJTPA
SECT5307
$68.510
$68.510
PreventiveMaintenanceBus
NJTPA
STP
$33.500
$33.500
PreventiveMaintenanceBus
NJTPA
STPNJ
$20.000
$20.000
PreventiveMaintenanceBus
SJTPO
SECT5307
$14.020
$14.020
PreventiveMaintenanceBus
SJTPO
STPSJ
$7.500
$7.500
Description
2013
2014
2015
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
MPO
Phase
Fund
DVRPC
CAP
SECT5307
DVRPC
CAP
NJTPA
CAP
NJTPA
CAP
STP
$28.240
NJTPA
CAP
STPNJ
SJTPO
CAP
SJTPO
CAP
$42.150
$38.500
$38.324
STPSTU
$8.000
$11.500
$12.000
SECT5307
$55.407
$89.570
$81.306
$20.000
$20.000
$20.000
SECT5307
$14.110
$14.430
$12.228
STPSJ
$7.500
$7.500
$7.500
Total
Total
$37.403
$37.403
$37.402
$37.403
$37.403
$28.123
$28.123
$362.234
$78.506
$78.507
$78.503
$78.506
$78.505
$95.743
$95.743
$810.296
$31.500
$28.240
$60.000
$11.948
SectionIVPage39
$11.948
$11.948
$11.948
$11.948
$8.278
$8.278
$117.064
$22.500
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T39
PreventiveMaintenanceRail
Thisprogramprovidesfundingfortheoverhaulofrailcarsandlocomotivesandotherpreventivemaintenancecostsinaccordancewithfederal
fundingguidelinesasdefinedintheNationalTransitDatabaseReportingManualandfederallaw.
TollCreditwillbeusedasthenonfederalmatch.AnexplanationoftollcreditcanbefoundintheIntroductionSectionoftheSTIP.Inaddition,
expendituresareforcostsofprojectsinspecificyearsonly.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M3,MT3(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
PreventiveMaintenanceRail
DVRPC
SECT5307
$1.410
$1.410
PreventiveMaintenanceRail
DVRPC
SECT5337
$13.600
$13.600
2013
2014
2015
Total
PreventiveMaintenanceRail
NJTPA
SECT5307
$70.400
$70.400
PreventiveMaintenanceRail
NJTPA
SECT5337
$138.700
$138.700
PreventiveMaintenanceRail
NJTPA
STP
$49.000
$49.000
PreventiveMaintenanceRail
NJTPA
STPNJ
$50.500
$50.500
PreventiveMaintenanceRail
SJTPO
SECT5307
$0.300
$0.300
PreventiveMaintenanceRail
SJTPO
SECT5337
$2.200
$2.200
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
CAP
SECT5307
DVRPC
CAP
SECT5337
NJTPA
CAP
SECT5307
NJTPA
CAP
SECT5337
NJTPA
CAP
STP
$54.260
NJTPA
CAP
STPNJ
$50.500
$50.500
$50.500
SJTPO
CAP
SECT5307
$0.300
$0.290
$0.990
$0.990
$0.990
$0.990
$0.990
$0.990
$0.298
$0.298
$7.126
SJTPO
CAP
SECT5337
$1.950
$1.950
$2.200
$2.200
$2.200
$2.200
$2.200
$2.200
$1.946
$1.946
$20.992
$1.410
$6.290
$4.688
$4.684
$4.684
$9.200
$9.200
$13.600
$13.600
$13.600
$43.400
$80.110
$74.340
$74.288
$74.288
$4.684
$4.684
$4.684
$3.203
$3.203
$42.214
$13.600
$13.600
$13.600
$9.200
$9.200
$118.400
$74.289
$74.297
$74.297
$38.524
$38.524
$646.357
$145.850 $145.850 $138.700 $138.700 $138.700 $138.700 $138.700 $138.700 $145.853 $145.853
$1,415.606
$54.260
$151.500
SectionIVPage40
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T106
PrivateCarrierEquipmentProgram
ThisprogramprovidesStatefundsforthePrivateCarrierCapitalImprovementProgram.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Various
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsBus)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT10(Exempt)
MPO
Phase
Fund
NJTPA
CAP
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$3.000
$3.000
$3.000
$3.000
SectionIVPage41
$3.000
$3.000
$3.000
$3.000
$3.000
$3.000
Total
$30.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T34
RailCapitalMaintenance
TheRailCapitalMaintenanceprojectincludesRailMaintenanceofWay(MOW)activitiesandRailMaintenanceofEquipment(MOE)activitiesin
accordancewithTTFeligibilityrequirements.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M9,MT3(Exempt)
MPO
Phase
Fund
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
DVRPC
CAP
STATE
$3.744
$3.744
$3.744
$3.744
$3.744
$3.744
$3.744
$26.208
NJTPA
CAP
STATE
$59.362
$59.362
$59.362
$59.362
$59.362
$59.363
$59.363
$415.536
SJTPO
CAP
STATE
$0.791
$0.791
$0.791
$0.791
$0.791
$0.792
$0.792
$5.539
SectionIVPage42
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T53G
RailFleetOverhaul
Thisprogramprovidesfundsforthemidlifeoverhaulandreliability/safetyimprovementsofrailcarsbasedonmanufacturerrecommendationsand
otherrollingstockmodificationstomeetrecentlyissuedFRAandAPTAmandatedstandards.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Various
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M3,MT3(Exempt)
Fund
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
MPO
Phase
DVRPC
CAP
STATE
NJTPA
CAP
CMAQ
NJTPA
CAP
STATE
$11.011
$0.930
$13.937
$0.930
$25.930
SJTPO
CAP
STATE
$0.090
$0.012
$0.185
$0.012
$0.012
$0.899
$0.058
$0.878
$0.058
SectionIVPage43
$0.058
$0.058
$2.461
$2.461
Total
$0.058
$0.058
$55.000
$75.000
$7.047
$50.930
$70.930
$91.930
$39.018
$39.018
$344.564
$0.012
$0.012
$0.012
$0.520
$0.520
$1.387
$130.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T903
RailInfrastructureResiliency
FundingisprovidedtomakeNJTRANSIT’srailstationsandadjacentyardsandtracksmoreresilienttofuturestorms.HobokenTerminal/Yardand
SecaucusJunctionwereimpactedbySuperstormSandy,aswereotherstationsthroughoutNJTRANSIT’ssystem.Fundingisprovidedforflood
mitigationatthoselocations,includingthepotentialfillingofLongSlipinHobokenYard,constructingfloodwalls,floodproofing,andimproving
stormwaterdetentionsystems.FundingisprovidedforimprovementstocrewquartersinBayhead,Hobokenandotherlocationstoensurethe
availabilityofcrewspoststorms.Fundingisalsoprovidedforrailstationsresiliencysystemwide.
TollCreditwillbeusedasthenonfederalmatch.AnexplanationoftollcreditcanbefoundintheIntroductionSectionoftheSTIP.
COUNTY: Various
MUNICIPALITY: Various
LEGISLATIVEDISTRICT: Various
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT6,MT8,MT9(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
RailInfrastructureResiliency
NJTPA
SECT5324
$78.610
$78.610
RailInfrastructureResiliency
SJTPO
SECT5324
$2.500
$2.500
MPO
Phase
Fund
NJTPA
ERC
SECT5324
2013
2014
2015
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
Total
SectionIVPage44
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T112
RailRollingStockProcurement
Thisprogramprovidefundsforthereplacementofrailrollingstock,includingengineeringassistanceandprojectmanagement,toreplaceoveraged
equipmentincludingrailcars,revenueservicelocomotives,andexpansionofNJTRANSITrollingstockfleet(carsandlocomotives)toaccommodate
projectedridershipgrowthandothersystemenhancementsoverthenexttenyears.Fundingisprovidedtosupportvehicles\equipment(forrail
operations).AnnualfundsareprovidedforCometVsinglelevelcarleasepayments,ElectricLocomotiveleasepayments,DieselLocomotivelease
payments,DualPowerLocomotivesandMultiLevelrailcarleasepaymentsandotherupcomingrollingstockleasepayments.Payasyougo
fundingisalsoprogrammedforMultiLevelvehiclesandotherrollingstock.
TollCreditwillbeusedasthenonfederalmatch.AnexplanationoftollcreditcanbefoundintheIntroductionSectionoftheSTIP.
CMAQ:FundingforRailRollingStockProcurementwillincludeCMAQfunds.RailRollingStockProcurementisCMAQeligiblebecauseitmeets
federaleligibilityrequirements.TheprojectwillprovidefundingforthepurchaseofMultiLevelCoachesandMultiLevelEMUvehicles.Forthe
CMAQjustificationseeCMAQReportforNJTRANSIT.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRailRollingStockDebt)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M10,MT3,MT10(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
RailRollingStockProcurement
DVRPC
RailRollingStockProcurement
RailRollingStockProcurement
RailRollingStockProcurement
2015
Total
SECT5307
$4.290
$4.290
NJTPA
CMAQ
$37.000
$37.000
NJTPA
SECT5307
$60.810
$60.810
SJTPO
SECT5307
$0.690
$0.690
SectionIVPage45
2013
2014
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T112
RailRollingStockProcurement
Thisprogramprovidefundsforthereplacementofrailrollingstock,includingengineeringassistanceandprojectmanagement,toreplaceoveraged
equipmentincludingrailcars,revenueservicelocomotives,andexpansionofNJTRANSITrollingstockfleet(carsandlocomotives)toaccommodate
projectedridershipgrowthandothersystemenhancementsoverthenexttenyears.Fundingisprovidedtosupportvehicles\equipment(forrail
operations).AnnualfundsareprovidedforCometVsinglelevelcarleasepayments,ElectricLocomotiveleasepayments,DieselLocomotivelease
payments,DualPowerLocomotivesandMultiLevelrailcarleasepaymentsandotherupcomingrollingstockleasepayments.Payasyougo
fundingisalsoprogrammedforMultiLevelvehiclesandotherrollingstock.
TollCreditwillbeusedasthenonfederalmatch.AnexplanationoftollcreditcanbefoundintheIntroductionSectionoftheSTIP.
CMAQ:FundingforRailRollingStockProcurementwillincludeCMAQfunds.RailRollingStockProcurementisCMAQeligiblebecauseitmeets
federaleligibilityrequirements.TheprojectwillprovidefundingforthepurchaseofMultiLevelCoachesandMultiLevelEMUvehicles.Forthe
CMAQjustificationseeCMAQReportforNJTRANSIT.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRailRollingStockDebt)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M10,MT3,MT10(Exempt)
MPO
Phase
Fund
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
DVRPC
CAP
CMAQ
DVRPC
CAP
SECT5307
DVRPC
CAP
STATE
$0.758
$0.639
$0.724
$0.559
$0.062
$0.062
$0.062
$5.062
$5.062
$13.053
NJTPA
CAP
CMAQ
$50.000
$75.000
$75.000
$75.000
$75.000
$75.000
$20.000
$67.500
$67.500
$580.000
NJTPA
CAP
SECT5307
$53.580
$32.331
$44.238
$44.193
$44.209
$44.168
$19.426
$67.504
$67.504
$417.153
$45.994
$45.994
$138.506
$3.600
$2.376
$2.790
$2.787
$2.788
$2.786
$1.225
NJTPA
CAP
STATE
$12.020
$10.136
$11.505
$8.884
$0.993
$0.993
$0.993
SJTPO
CAP
SECT5307
$0.650
$0.338
$0.590
$0.589
$0.590
$0.589
$0.259
SJTPO
CAP
STATE
$0.160
$0.135
$0.153
$0.118
$0.013
$0.013
$0.013
SectionIVPage46
$0.062
$0.993
$7.500
$7.500
$15.000
$7.500
$7.500
$33.352
$3.605
$0.013
$0.013
$0.013
$0.645
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T900
RailRollingStockResiliency
FundingisprovidedforRailRollingStockResiliencyprojects.ThelargesttwoyardsintheStateofNewJerseyavailabletoNJTRANSIT–Meadows
MaintenanceComplexandHobokenYard–haveexperiencedsevereflooding,andwillrequireevacuationinfutureimpendingstorms.Fundingis
providedtoconstructorpurchase/leasetemporaryandpermanentyardlocations,reinspectionfacilitiesandaccesstracks.Potentialprojectelements
includeneworupgradedyardsinLindenandNewBrunswick,andWestboundWaterfrontConnectiontoimprovetheabilitytoevacuatetrainsfrom
theyardstotheNortheastCorridor.Fundingisalsoprovidedforyardresiliencyprojectssystemwideandemergentstorage.Nearterm
improvementsalsoincludetheGarwoodIndustrialTrack.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT8,MT9(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
RailRollingStockResiliency
NJTPA
SECT5324
MPO
Phase
Fund
NJTPA
ERC
SECT5324
2013
2014
2015
$7.000
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
$7.000
Total
SectionIVPage47
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T902
RailStationResiliency
FundingisprovidedtomakeNJTRANSIT’srailstationsandadjacentyardsandtracksmoreresilienttofuturestorms.HobokenTerminal/Yardand
SecaucusJunctionwereimpactedbySuperstormSandy,aswereotherstationsthroughoutNJTRANSIT’ssystem.Fundingisprovidedforflood
mitigationatthoselocations,includingthepotentialfillingofLongSlipinHobokenYard,constructingfloodwalls,floodproofing,andimproving
stormwaterdetentionsystems.FundingisprovidedforimprovementstocrewquartersinBayhead,Hobokenandotherlocationstoensurethe
availabilityofcrewspoststorms.Fundingisalsoprovidedforrailstationsresiliencysystemwide.
TollCreditwillbeusedasthenonfederalmatch.AnexplanationoftollcreditcanbefoundintheIntroductionSectionoftheSTIP.
COUNTY: Various
MUNICIPALITY: Various
LEGISLATIVEDISTRICT: Various
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT8(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
RailStationResiliency
NJTPA
SECT5324
MPO
Phase
Fund
NJTPA
ERC
SECT5324
2013
2014
2015
$21.278
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
$21.278
Total
SectionIVPage48
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T37
RailSupportFacilitiesandEquipment
Thisprogramprovidesfundsforrehabilitationandconstructionactivitiesforyardimprovementssystemwide,improvementsatsupportfacilities
necessarytoperformmaintenanceworkatrailyardsincludingworkatPortMorrisYard,railcapacityimprovementsincludingpassingsidings,
interlockingsandelectrictractionimprovements,signalandcommunicationimprovementsatsupportfacilities,rightofwayfencing,maintenanceof
wayequipmentandtheinstallationofpedestaltracksnecessarytoperformmaintenanceworkatrailyards.Fundingisprovidedforsystemwidecrew
quarters,theMeadowsMaintenanceComplexupgrade/expansionworkrequiredtosupportthenewrailfleet.AlsoincludedisfundingforNJ
TRANSITscapitalcostsharingobligationsrelatedtouseofAmtrak/Conrailfacilities.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
COUNTY: Various
MUNICIPALITY: Various
LEGISLATIVEDISTRICT: Various
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M9,MT2,MT9(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
RailSupportFacilitiesandEquipment
NJTPA
METRONORTH
2013
2014
2015
Total
$0.690
$0.690
$1.380
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
ERC
SECT5307
$1.303
$1.303
$1.303
$2.033
$3.258
DVRPC
ERC
STATE
$0.215
$0.208
$2.792
$2.478
$5.081
$3.604
$1.810
$0.579
$0.225
$0.225
$17.217
NJTPA
ERC
METRONORTH
$0.690
$0.690
$0.690
$0.690
$0.690
$0.690
$0.690
$0.690
$0.690
$0.690
$6.900
NJTPA
ERC
SECT5307
$20.668
$20.668
$20.668
$32.230
$51.657
NJTPA
ERC
STATE
$40.991
$25.058
$43.951
$38.978
$80.234
$56.821
$28.370
$8.861
$3.237
$3.237
$329.738
SJTPO
ERC
SECT5307
$0.275
$0.275
$0.275
$0.430
$0.689
SJTPO
ERC
STATE
$0.034
$0.033
$0.579
$0.513
$1.064
$0.751
$0.371
$0.111
$0.037
$0.037
$3.530
SectionIVPage49
$9.200
$145.891
$1.944
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T107
RiverLINELRT
ThiselementprovidesfundingfortheRiverLINELRTprojectfromCamdentoTrentonforannualEDAdebtservicepaymentsrequireduntilFY19.
ProjectcostoftheRiverLINEis$1.0billion.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Camden,Burlington,Mercer
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsLightRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M1(Exempt)
MPO
Phase
Fund
DVRPC
ERC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$51.228
$50.616
$49.982
$41.345
SectionIVPage50
Total
$193.171
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T150
Section5310Program
Thisprogramprovidesfundsforthepurchaseofsmallbusesorvantypevehiclesforagenciesthatservetheelderlyandpersonswithdisabilities.
ThiswasformerlyknownastheSection16Program.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.MATCHfundsareprovidedfromtheState.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Various
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(LocalSystemSupportNJTRANSITLocalSystemSupport)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M10,MT1,MT2(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
Section5310Program
DVRPC
MATCH
Section5310Program
DVRPC
SECT5310
$1.104
Section5310Program
DVRPC
SECT5310/STPSTU
$0.396
Section5310Program
NJTPA
MATCH
Section5310Program
NJTPA
SECT5310
Section5310Program
SJTPO
MATCH
Section5310Program
SJTPO
SECT5310
2013
$3.360
$0.336
2014
2015
Total
$0.879
$0.879
$1.758
$1.656
$1.656
$4.416
$0.396
$2.679
$2.679
$5.358
$5.040
$5.040
$13.440
$0.267
$0.267
$0.534
$0.504
$0.504
$1.344
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
CAP
MATCH
$0.880
$0.880
$0.879
$0.879
$0.879
$0.879
$0.879
$0.879
$0.879
$0.879
$8.792
DVRPC
CAP
SECT5310
$1.656
$1.656
$1.656
$1.656
$1.656
$1.656
$1.656
$1.656
$1.656
$1.656
$16.560
DVRPC
CAP
STATE
$0.230
$0.230
$0.230
$0.230
$0.920
NJTPA
CAP
MATCH
$2.678
$2.678
$2.679
$2.679
$2.679
$2.679
$2.679
$2.679
$2.677
$2.677
$26.783
NJTPA
CAP
SECT5310
$5.040
$5.040
$5.040
$5.040
$5.040
$5.040
$5.040
$5.040
$5.040
$5.040
$50.400
NJTPA
CAP
STATE
$0.700
$0.700
$0.700
$0.700
$2.800
SJTPO
CAP
MATCH
$0.268
$0.268
$0.267
$0.267
$0.267
$0.267
$0.267
$0.267
$0.267
$0.267
$2.672
SJTPO
CAP
SECT5310
$0.504
$0.504
$0.504
$0.504
$0.504
$0.504
$0.504
$0.504
$0.504
$0.504
$5.040
SJTPO
CAP
STATE
$0.070
$0.070
$0.070
$0.070
$0.280
SectionIVPage51
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T151
Section5311Program
Thisprogramprovidesfundingforruralpublictransportationprogram.MATCHfundsareprovidedfromNJTRANSITandlocalfunds.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Various
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(LocalSystemSupportNJTRANSITLocalSystemSupport)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M1,MT1,O10C(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
Section5311Program
DVRPC
Section5311Program
Section5311Program
2013
2014
2015
Total
MATCH
$1.449
$0.966
$0.966
$3.381
DVRPC
SECT5311
$1.449
$0.966
$0.966
$3.381
NJTPA
MATCH
$4.410
$2.940
$2.940
$10.290
Section5311Program
NJTPA
SECT5311
$4.410
$2.940
$2.940
$10.290
Section5311Program
SJTPO
MATCH
$0.441
$0.294
$0.294
$1.029
Section5311Program
SJTPO
SECT5311
$0.441
$0.294
$0.294
$1.029
Fund
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
DVRPC
CAP
MATCH
$0.966
$0.966
$0.966
$0.966
$0.966
$0.966
$0.966
$0.966
$0.966
$0.966
$9.660
DVRPC
CAP
SECT5311
$0.966
$0.966
$0.966
$0.966
$0.966
$0.966
$0.966
$0.966
$0.966
$0.966
$9.660
NJTPA
CAP
MATCH
$2.940
$2.940
$2.940
$2.940
$2.940
$2.940
$2.940
$2.940
$2.940
$2.940
$29.400
NJTPA
CAP
SECT5311
$2.940
$2.940
$2.940
$2.940
$2.940
$2.940
$2.940
$2.940
$2.940
$2.940
$29.400
SJTPO
CAP
MATCH
$0.294
$0.294
$0.294
$0.294
$0.294
$0.294
$0.294
$0.294
$0.294
$0.294
$2.940
SJTPO
CAP
SECT5311
$0.294
$0.294
$0.294
$0.294
$0.294
$0.294
$0.294
$0.294
$0.294
$0.294
$2.940
SectionIVPage52
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T508
SecurityImprovements
Thisprogramprovidesfundsforcontinuedmodernization/improvementsofNJTRANSITPoliceandothersecurityimprovements.Today,theNJ
TRANSITPoliceDepartmentistheonlytransitpolicingagencyinthecountrywithstatewideauthorityandjurisdiction.TheDepartmentwascreated
onJanuary1,1983,anditevolvedasaresultofthepassageofthePublicTransportationActof1979andsubsequentlegislationonthestateand
federallevels.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Various
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsHomelandSecurity)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M1,MT1,S6(Exempt)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
SWI
STATE
$0.599
$0.599
$0.599
$0.599
$0.599
$0.599
$0.599
$0.599
$0.600
$0.600
$5.992
NJTPA
SWI
STATE
$1.830
$1.830
$1.830
$1.830
$1.830
$1.830
$1.830
$1.830
$1.827
$1.827
$18.294
SJTPO
SWI
STATE
$0.181
$0.181
$0.181
$0.181
$0.181
$0.181
$0.181
$0.181
$0.182
$0.182
$1.812
SectionIVPage53
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T50
SignalsandCommunications/ElectricTractionSystems
Thisprojectprovidesfundingforcontinuedmodernization/improvementstothesignalandcommunicationssystems,including
signal/communicationupgradeofinterlockings,andothercommunicationimprovements.Thisprojectalsoprovidesfundingforsystemwideelectric
tractiongeneralupgradesincluding:substationreplacement,waysidehotboxdetectionsystem,railmicrowavesystemupgrades,replacementof
substationbatteriesandelectricswitchheaters,emergencypowerbackupsystemwide,rehabilitationofsystemwideoverheadcatenarystructuresand
foundations.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
COUNTY: Various
MUNICIPALITY: Various
LEGISLATIVEDISTRICT: Various
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M6,MT6(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
SignalsandCommunications/ElectricTractionSystems
NJTPA
SECT5307
2013
2014
$13.000
$2.091
2015
Total
$15.091
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
ERC
STATE
$1.639
$3.396
$0.173
$0.643
$0.643
$0.643
$0.643
$0.643
$0.644
$0.644
$9.711
NJTPA
ERC
STATE
$47.627
$74.017
$2.752
$10.221
$10.221
$10.221
$10.221
$10.221
$10.219
$10.219
$195.939
SJTPO
ERC
STATE
$0.347
$0.719
$0.035
$0.136
$0.136
$0.136
$0.136
$0.136
$0.136
$0.136
$2.053
SectionIVPage54
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T120
Small/SpecialServicesProgram
FundingisprovidedforNJTRANSITeffortswhichinitiateorpromotetransitsolutionstoreducecongestion,managetransportationdemandand
improveairquality.IncludedareStatefundsfortheVanpoolSponsorshipProgram,TransportationManagementAssociationProgram,andFederal
fundsforEastWindsorCommunityShuttleoperatingsupport.Fundingisalsoprovidedforcapitalacquisition/operatingexpensesforthe
CommunityShuttleProgram,Bike/Transitfacilitation,andotheractivitiesthatimproveairqualityandhelpreducecongestion.
TollCreditwillbeusedasthenonfederalmatch.AnexplanationoftollcreditcanbefoundintheIntroductionSectionoftheSTIP.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: Various
COUNTY: Various
LEGISLATIVEDISTRICT: Various
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(LocalSystemSupportNJTRANSITLocalSystemSupport)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): A1,MT1,O10C(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
Small/SpecialServicesProgram(LocalDVRPCProject)
DVRPC
CMAQ/5307
Small/SpecialServicesProgram(LocalDVRPCProject)
DVRPC
CMAQ/5310
$0.330
Small/SpecialServicesProgram
DVRPC
SECT5307
$0.100
Small/SpecialServicesProgram(LocalNJTPAProject)
NJTPA
CMAQ/5307
$1.081
$1.081
Small/SpecialServicesProgram
NJTPA
CMAQ/5307
$1.700
$1.700
MPO
Phase
Fund
DVRPC
EC
SECT5307
DVRPC
EC
NJTPA
EC
SJTPO
EC
2013
2014
2015
$0.495
$0.495
$0.330
$0.100
$0.100
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.100
$0.100
$0.100
$0.100
$0.100
$0.100
STATE
$0.316
$1.930
$1.925
STATE
$0.961
$5.860
$5.863
STATE
$0.096
$0.590
$0.585
$1.925
$1.925
$5.863
$5.863
$0.585
$0.585
SectionIVPage55
$0.100
$0.100
$1.925
$1.925
$5.863
$5.863
$0.585
$0.585
Total
$0.300
Total
$0.100
$0.100
$1.000
$1.925
$1.925
$1.925
$17.646
$5.863
$5.861
$5.861
$53.721
$0.585
$0.586
$0.586
$5.368
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T88
StudyandDevelopment
Thiselementprovidesfundsforsystemandinfrastructureplanningstudiestoreadyprojectsfordesign,aswellasdemandforecastingandother
relatedplanningwork.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
COUNTY: Various
LEGISLATIVEDISTRICT: Various
ASSETMANAGEMENTCATEGORY: MassTransit(CongestionReliefNJTRANSITCongestionRelief)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O10A,X1(Exempt)
Fund
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
DVRPC
PLS
STATE
$1.057
$0.999
$0.996
$0.996
$0.996
$0.996
$0.996
$0.996
$0.998
$0.998
$10.028
NJTPA
PLS
STATE
$9.440
$3.511
$3.507
$3.507
$3.507
$3.507
$3.507
$3.507
$3.509
$3.509
$41.011
SJTPO
PLS
STATE
$0.313
$0.301
$0.297
$0.297
$0.297
$0.297
$0.297
$0.297
$0.300
$0.300
$2.996
SectionIVPage56
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T500
TechnologyImprovements
Thiselementfundsimprovementstopassengercommunicationandfarecollectionsystemsandotherinformationtechnologyimprovementstomeet
internalandexternalcustomerneeds.FundingisincludedforPublicAddressUpgrades/OnboardCommunicationSystems,BusRadioSystem
UpgradeProgram,GISSystems,TVMReplacement/Expansion,SmartCardTechnologyandimprovementsatstationssystemwide,computersystems
andservices,photocopyleasepayments,ADAAccessLinkcomputerupgradesandupgradestoincreaseefficiencyandproductivityofNJ
TRANSITstechnologyinfrastructuretosupportservicestocustomers.
HisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: Various
COUNTY: Various
LEGISLATIVEDISTRICT: Various
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsTechnology)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M5,MT5,MT6(Exempt)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
EC
STATE
$9.310
$1.690
$5.749
$5.600
$5.600
$5.600
$6.060
$6.060
$6.290
$6.290
$58.249
NJTPA
EC
STATE
$28.335
$5.150
$17.502
$17.046
$17.046
$17.046
$18.446
$18.446
$19.145
$19.145
$177.307
SJTPO
EC
STATE
$2.833
$0.510
$1.749
$1.704
$1.704
$1.704
$1.844
$1.844
$1.914
$1.914
$17.720
SectionIVPage57
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T42
TrackProgram
Fundingisprovidedforanannualprogramoftrackrehabilitationincludingsystemwidereplacementoflifeexpiredtiesandotherrailimprovements,
rightofwayfencing,equipmentnecessarytomaintainastateofgoodandsaferepair,purchaseoflongleadtimematerialsfornextconstruction
season,maintenanceofwayworkequipment,interlockingimprovements,passingsidingsandotherimprovements.
TollCreditwillbeusedasthenonfederalmatch.AnexplanationoftollcreditcanbefoundintheintroductionsectionoftheSTIP.
ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
MUNICIPALITY: Various
COUNTY: Various
LEGISLATIVEDISTRICT: Various
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M9,MT9(Exempt)
MPO
Phase
Fund
DVRPC
ERC
SECT5307
DVRPC
ERC
STATE
NJTPA
ERC
SECT5307
NJTPA
ERC
STATE
SJTPO
ERC
SECT5307
SJTPO
ERC
STATE
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.199
$0.163
$0.162
$0.165
$1.055
$1.055
$0.797
$0.832
$0.833
$0.830
$3.157
$2.599
$2.581
$2.625
$16.722
$16.722
$12.637
$13.196
$13.214
$13.170
$0.042
$0.034
$0.034
$0.035
$0.223
$0.223
$0.168
$0.176
$0.176
$0.175
SectionIVPage58
$0.996
$0.996
$1.054
$1.054
Total
$4.789
$5.402
$15.793
$15.793
$16.722
$16.722
$75.992
$85.661
$0.210
$0.210
$0.223
$0.223
$1.011
$1.141
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T911
TrainControlsWaysideSignals,Power&CommunicationResiliency
FundingisprovidedfortheTrainControlsinfrastructureresiliencyproject.NJTRANSITstencommuterraillinesandthelightraillineswere
impactedbySuperstormSandy.Thisprojectinvolvesraillineresiliencyeffortsforcertainassetsthatarevulnerabletostormevents,includingcritical
lifesafetysignalandcommunicationssystemslocatedontheMorrisandEssexLine,thePascack/BergenLine,theMainLineandtheHudsonBergen
LightRailLine.Theselineslieincoastalandinlandfloodplainswherestormscouldovertopthetrackbedandpotentiallyfloodanddamagecritical
signal,powerandcommunicationssystemsusedtocontroltrainspeed,switchesandtrackchoice,andfollowingdistancesforsafeoperations.
ThesourceoflocalfundingistheStateTransportationTrustFund(TTF)intheamountof$29,634,396.TheSTIPIDisDB#T50,Signalsand
Communications/ElectricTractionSystems.The$29,634,396fromtheSignalsandCommunications/ElectricTractionSystemsprogramisfromthe
SFY1524ConstrainedCapitalProgram;including$1,000,000inSFY15,$1,000,000inSFY16,$1,000,000inSFY17,$22,536,000inSFY18and$4,098,396in
SFY19.
COUNTY: Various
MUNICIPALITY: Various
LEGISLATIVEDISTRICT: Various
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsRail)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT6(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
Description
MPO
Fund
TrainControlsWaysideSignals,Power&CommunicationResiliency
NJTPA
SECT5324
MPO
Phase
Fund
NJTPA
ERC
SECT5324
2013
2014
2015
Total
$1.600
$1.600
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$87.303
Total
$87.303
SectionIVPage59
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T210
TransitEnhancements/TranspAlternProg(TAP)/AlternTransitImprov(ATI)
Fundingisprovidedforprojectsorprojectelementsthataredesignedtoenhancemasstransportationserviceoruseandarephysicallyor
functionallyrelatedtotransitfacilitiesasoutlinedinFTACircular9030.1C.,includingfundingforaStatewideBusSignsandShelterMaintenance
UpgradeProgramandhistoricrestorationofNJTRANSITfacilities.
TollCreditwillbeusedasthenonfederalmatch.AnexplanationoftollcreditcanbefoundintheintroductionsectionoftheSTIP.Thisproject
isfundedundertheprovisionsofSection13ofP.L.1995,c.108.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(MassTransitAssetsBus)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M8,O8,O10A(Exempt)
UNOBLIGATEDPRIORYEARFUNDING
MPO
Description
Fund
2013
2014
2015
Total
TransitEnhancements
DVRPC
SECT5307TAP
$0.161
$0.161
$0.322
TransitEnhancements
NJTPA
SECT5307TAP
$0.490
$0.490
$0.980
TransportationAlternativesProgram(TAP)
NJTPA
STPTAP
TransitEnhancements
SJTPO
SECT5307TAP
$1.000
$1.000
$0.049
$0.049
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
$0.098
Total
MPO
Phase
Fund
DVRPC
CAP
SECT5339/5307
$0.650
$0.650
NJTPA
CAP
SECT5339/5307
$0.010
$0.010
SJTPO
CAP
SECT5339/5307
$1.140
DVRPC
ERC
SECT5307TAP
$0.161
DVRPC
ERC
SECT5339/5307
NJTPA
ERC
SECT5307TAP
NJTPA
ERC
SECT5339/5307
SJTPO
ERC
SECT5307TAP
SJTPO
ERC
SECT5339/5307
$1.140
$0.161
$0.161
$0.161
$0.161
$0.161
$0.161
$0.161
$0.161
$0.414
$0.414
$1.478
$0.490
$0.490
$0.490
$0.490
$0.490
$0.490
$0.490
$0.490
$4.900
$1.260
$1.260
$2.530
$0.049
$0.049
$0.049
$0.049
$0.049
$0.049
$0.049
$0.049
$0.490
$0.126
$0.126
$1.392
$0.650
$0.490
$0.490
$0.010
$0.049
$0.049
$1.140
SectionIVPage60
$0.161
$1.610
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
NewJerseyTransitProjectDescriptions
($millions)
DBNUM:T300
TransitRailInitiatives
Thisprogramprovidesfundingfortransitexpansionprojects,includingnewstationconstruction,ferryprogram,fixedguidewayimprovements
(Rail,LightRail,BRT,andFerry),andrelatedvehicleandequipmentacquisition.AlsoincludedareFTAnewstartsprojectsauthorizedunderNew
JerseyUrbanCoreorSAFETEALU.Potentialprojectsinthiscategoryinclude(innorankorder):NorthernBranchRail;HBLRExtensionto
Secaucus;HBLRSecaucusMeadowlandsConnector;PassaicBergenrailserviceontheNYS&WeastofHawthorneusingDieselMultipleUnit(DMU)
passengerequipment;RestorationofcommuterrailserviceontheNYS&WwestofHawthorne;PortMorrisImprovements;WestShoreHobokento
WestHaverstraw;NERLElizabethSegmentfromNJTRANSITSNortheastCorridorMidtownElizabethStationtoNewarkLibertyInternational
AirportviatheElizabethWaterfront;RestorationofcommuterrailserviceontheWestTrentonline;RiverLINELRTCapitolExtension;SecondPhase
ofRiverLINELRT/PATCOExtension;Route1BRT,SecondPhaseofNERL(NewarkPennStationtoNewarkLibertyInternationalAirport);
CommuterrailextensioninMonmouthandOceanCounties;LehighThirdTrackCapacityImprovements;ExtensionofCapeMaySeashoreLinenorth
toHammonton(toAtlanticCityRailLine);CommuterRailextensiontoPhillipsburg,improvementsontheAtlanticCityRailLine,newrailstation
improvementssuchasAtlanticCityLine/RiverLINEconnection,MoynihanStation,PennStationNewYorkaccessimprovementsandplatform
extensions,PennStationNewYorkCentralConcourse,PennStationNewYorkWestEndConcourse,Eyardexpansion,BusRapidTransitInitiatives,
ParkandRidesandSmartCardTechnologyProgramalongwithothernewsystemwide,rail,bus,andlightrailinitiativesarisingduringtheyear.
ThenarrativeabovegovernshowthestateTransportationTrustFundsthatareappropriatedinthestatebudgettoTransitRailInitiativescanbe
used.TheTransitRailInitiativesprojectisastatefundedeffortthatisdisplayedhereonlyforinformationpurposesinordertogiveabetter
understandingoftotaltransportationfunding.Asshownbelow,thereisnoFederalfundingallocatedtotheTransitRailInitiativesprojectinthefirst
fourconstrainedyears.Incompliancewiththestatebudgetandthelanguageabove,stateTransitRailInitiativesfundswillbeusedtoadvancethe
projectslistedabove,someofwhicharealsoauthorizedunderFederallaw,butnotyetfundedwithFederaldollars.
Fundingisalsoprovidedtoadvanceprojectsdependentonothernonfederal(includingprivate)funding,and/orstateresourcesavailable
beyondplannedlevels.ThisprojectisfundedundertheprovisionsofSection13ofP.L.1995,c.108.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: NJTRANSIT
ASSETMANAGEMENTCATEGORY: MassTransit(CongestionReliefNJTRANSITCongestionRelief)
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT8,O10A,X1(Exempt)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
ERC
STATE
$0.058
$0.058
$0.287
$1.207
$1.207
$1.207
$1.207
$1.207
$0.057
$0.057
$6.552
NJTPA
ERC
STATE
$2.675
$2.675
$3.376
$6.176
$6.176
$6.176
$6.176
$6.176
$2.675
$2.675
$44.956
SJTPO
ERC
STATE
$0.018
$0.018
$0.087
$0.367
$0.367
$0.367
$0.367
$0.367
$0.017
$0.017
$1.992
SectionIVPage61
SECTIONȱVȱ
ȱ
MPOȱLOCALȱPROJECTȱDESCRIPTIONSȱ
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
MPOProjectDescriptions
SuballocatedSTPFunding($millions)
MPO
PHASE
FUND
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
DVRPC
FHWA:HighPriority
RiverRoadImprovements,CramerHill(DBNUM:D0902;UPC:098008)County:Camden
ThisprojectwillhelpimplementamultiphaseefforttoaddressthelongstandingissueofheavytrucktrafficalongRiverRoad/RiverAvenuethrough
CramerHillintheCityofCamden.ItwillremovetrucktrafficfromtheCramerHillneighborhood’scommercialandresidentialstreetstoimprove
thequalityoflifeforresidentsandbusinesses,suchasreducingairandnoisepollutionandimprovingpublicsafety.Aseriesoftrafficcontrol,traffic
calming,andpedestrianmeasuresrecommendedbytheRiverRoadTruckTrafficManagementStudywillbeimplementedbetweentheintersections
ofRiverRoadandStateStreetinCamden,NewJerseytoRiverRoadandShermanAvenueinPennsauken,NewJersey.Measuresinclude:high
visibilitycrosswalks,truckroutesignage,signaltimingchangestoslowareatraffic,bulbouts,mediansandintersectiongeometricimprovements.
DVRPC
ERC
DEMO
FHWA:HighPriorityTotal
$3.975
$4.0
$3.975
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$4.0
FHWA:STPDVRPC
PrincetonHightstownRoadImprovements,CR571(DBNUM:D0701;UPC:078036)County:Mercer
TheprojectlimitsincludetheintersectionsofCR571withClarksvilleRoad(CR638)andWallaceCranburyRoad(CR615),andtheapproximately1
milesegmentconnectingthem.CR571isamajoreastwestcorridoratthenorthernedgeofMercerCountyandtheCentralJerseyTransportation
Forumhasendorsedtheimprovementconcept.Thisisaseveresafetyconcernregardingtheareawheretheroadwaydropsfromfourlanestotwo.
MercerCountyandWestWindsorTownshiphopetomakeMainStreetpedestrian,bicycle,andsiteaccessimprovements,includingsidewalks,
protectedturnlanesandnoadditionalthroughtravellanes.
DVRPC
CON
STPSTU
$4.500
$5.500
SectionIVPage1
$10.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
MPOProjectDescriptions
SuballocatedSTPFunding($millions)
MPO
PHASE
FUND
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
SouthPembertonRoad,CR530,Phase2(DBNUM:D9912A;UPC:123210)County:Burlington
Thisprojectwillreconstructandprovidelaneandshoulderwideningapproximately2.7milesofCR530(S.PembertonRd.)fromHanoverSt.(CR616)
inPembertonBoroughtoUSRoute206inSouthamptonTownship.Thewideningoftheroadwayisnotanadditionalthroughlane,butwillincludea
5lanecrosssectionthatcontainsafourteenfootcontinuousturnlane,newsixfootshoulders,andfourtwelvefoottravellanes.Therearemany
driveways/accesspointsalongthecorridor,andthecontinuousturnlaneistoprovideasafeareatogetoutofthemainflowoftrafficandreduce
collisionsduringturnsoffoftheroadway.Overthelasttenyearstherehavebeentwelvefatalitiesonthisstretchofroadway.Crashdataoverthelast
fiveyears(20062010)documents348crashesinthissegment,including94injurycrashes.Theroadwaysegmentisaheavilytraveledcorridordueto
thefactthatitisacontinuationofStateHighwayRoute38.Route38endsatRoute206(TheSouthPembertonRoadwesternmostlimit)andbecomes
CR530/SouthPembertonRoad,whichcarriesatrafficvolumeofover25,000AADT.Thisprojectprovidesfortheacquisitionofeasementsand/orfull
takingsofover90parcelsandprovidesfortheenvironmentalcleanupanddemolishingofallstructures.Thisprojectwillalsoincludetreeclearingto
accommodateroadwayandshoulderwidth.ThisprojectisabreakoutofSouthPembertonRoad,CR530,Phase1(DB#D9912).
DVRPC
CON
STPSTU
$8.716
$6.435
$15.151
TrentonAmtrakBridges(DBNUM:99362;UPC:993620)County:Mercer
Thethreeorphanbridges,carryingChestnutAve.,E.StateStreetandMonmouthSt.overAmtrak,areinpoorcondition.Allthreebridgesare
structurallydeficientandfunctionallyobsolete.Thebridgesandapproachroadwaysfeaturevarioussubstandarddesignelements,including
substandardverticalandhorizontalclearances,intersectionsightdistancesandunprotectedbridgegirders.NJDOTisworkingwithTheCityof
TrentononarevisedconcepttoreplacetheE.StateSt.BridgeandremovetheChestnutAve.andMonmouthSt.Bridges.Anewconnectorroad
proposedwiththeconceptmaintainsallcurrentturningmovements.Thesinglebridgeoptionisaviableplan,giventheconstructioncostestimateof
approximately$35M.Replacementofthethreeexistingbridgespresentsfundingissues,givenconstraintsoftheMPO.
DVRPC
CON
STPSTU
$4.000
$4.000
$4.000
$4.000
$4.000
$20.000
BurlingtonCountyRoadwaySafetyImprovements(DBNUM:D0302)County:Burlington
Thisprogramwillprovidefortheinstallationofimprovedsafetyitemsincludingreflectivepavementmarkings(includingbothstripingandraised
reflectivemarkers),reflectiveobjectmarkers,reflectiveroadwaydelineators,guiderail,andothertreatmentsthatimprovetheoverallsafetyand
visibilityofvariousroadwaysinthecounty.
DVRPC
CON
STPSTU
$0.800
SectionIVPage2
$0.800
$0.800
$2.400
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
MPOProjectDescriptions
SuballocatedSTPFunding($millions)
MPO
PHASE
FUND
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
CamdenCountyRoadwaySafetyImprovements(DBNUM:D0410;UPC:048038)County:Camden
Thisprogramwillprovidefortheinstallationofimprovedsafetyitemsincludingreflectivepavementmarkings(includingbothstripingandraised
reflectivemarkers),reflectiveobjectmarkers,reflectiveroadwaydelineators,guiderail,andothertreatmentsthatimprovetheoverallsafetyand
visibilityofvariousroadwaysinthecounty.
DVRPC
DES
STPSTU
DVRPC
CON
STPSTU
$0.100
$0.100
$0.800
$0.800
$0.800
$0.800
$3.200
DVRPC,FutureProjects(DBNUM:D026;UPC:058026)County:Various
ThisprogramprovidesfundingforlocalprojectstobeselectedbytheDelawareValleyRegionalPlanningCommission,thedesignatedMetropolitan
PlanningOrganizationforBurlington,Gloucester,MercerandCamdencounties.
DVRPC
ERC
STPSTU
$0.546
$0.074
$0.881
$7.681
$10.981
$13.181
$10.981
$13.181
$14.781
$17.181
$89.471
GloucesterCountyRoadwaySafetyImprovements(DBNUM:D0401;UPC:048000)County:Gloucester
Thisprogramwillprovidefortheinstallationofimprovedsafetyitemsincludingreflectivepavementmarkings(includingbothstripingandraised
reflectivemarkers),reflectiveobjectmarkers,reflectiveroadwaydelineators,guiderail,andothertreatmentsthatimprovetheoverallsafetyand
visibilityofvariousroadwaysinthecounty.
DVRPC
CON
STPSTU
$0.800
$0.800
$1.000
$2.600
MercerCountyRoadwaySafetyImprovements(DBNUM:D0412;UPC:048075)County:Mercer
Thisprogramwillprovidefortheinstallationofimprovedsafetyitemsincludingreflectivepavementmarkings(includingbothstripingandraised
reflectivemarkers),reflectiveobjectmarkers,reflectiveroadwaydelineators,guiderail,andothertreatmentsthatimprovetheoverallsafetyand
visibilityofvariousroadwaysinthecounty.
DVRPC
CON
STPSTU
$0.800
$0.800
$0.800
$2.400
RIMISPhaseIIImplementation(DBNUM:01300;UPC:013000)County:Various
PhaseIIinstallationandoperationsofRegionalIntegratedMultimodalInformationSharing(RIMIS),acomputermessage/digitalsystemtonotify
agenciesaboutincidentsorunusualconditionsthataffectthem.ThisprojectalsohelpstoextendRIMIStoincludeDVRPCcountyroadways.
DVRPC
EC
STPSTU
$0.234
$0.234
$0.221
$0.221
SectionIVPage3
$0.221
$0.221
$0.221
$0.221
$0.221
$0.221
$2.236
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
MPOProjectDescriptions
SuballocatedSTPFunding($millions)
MPO
PHASE
FUND
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
TransportationandCommunityDevelopmentInitiative(TCDI)DVRPC(DBNUM:D0204)County:Various
TheTransportationandCommunityDevelopmentInitiativeisaproposedDVRPCfundingprogramtargetedtothosecommunitiesmostinneedof
revitalizationassistance.Theprogramwouldservetosupportlocalplanning,design,feasibilitystudiesorotheranalysesthatincreasethedemandor
improvethemarketforredevelopmentandimprovetheefficiencyorenhancetheregionaltransportationnetwork.Thefundamentalideaisto
supportearlystageprojectideaswhicharenototherwiseeligibleforfundingthroughothersources.ThisprogramisacomponentoftheDVRPC
WorkProgram.
DVRPC
EC
STPSTU
$0.680
$0.080
$0.680
$0.080
$0.680
$0.080
$0.680
$0.080
$0.680
$0.080
$3.800
LocalAidConsultantServices(DBNUM:10347;UPC:103470)County:Various
FundingforconsultantservicestoassistlocalpublicagenciesinadministeringprojectsandprovidingoversighttorecipientsreceivingLocalAid
funds.Servicesalsoincludeprovidingoverallqualityassuranceandqualitycontrolfortheprojectdeliveryprocess.
DVRPC
EC
STPSTU
$0.200
$0.200
$0.200
$0.200
$0.200
$1.000
$0.700
$7.000
LocalProjectDevelopmentSupport(DBNUM:06326;UPC:063260)County:Various
ThisprogramprovidesNJDOTprojectmanagementandenvironmentalsupporttolocalgovernments.
DVRPC
PLS
STPSTU
$0.700
$0.700
$0.700
$0.700
$0.700
$0.700
$0.700
$0.700
$0.700
MetropolitanPlanning(DBNUM:X30A)County:Various
NJDOTsupportsthefederallymandatedMetropolitanPlanningOrganizationtransportationplanningprocess.NewJerseyMetropolitanPlanning
Organizationscarryouta3Ctransportationplanningprocesswherebyplanningactivitiesareconductedonacontinuousbasiswhilealsoproviding
aforumforcooperativedecisionmakingamongresponsiblestateandlocalofficials,publicandprivatetransitoperatorsandthegeneralpublic.
DVRPC
PLS
STPSTU
$1.578
$1.531
$1.572
$1.572
$1.572
$1.572
$1.572
$1.572
$1.572
$1.572
$15.682
TransportationManagementAssociations(DBNUM:11383;UPC:113830)County:Various
ThisprogramwillprovideannualfundingtothefollowingTransportationManagementAssociations(TMAs):KeepMiddlesexMoving;Hudson,
Meadowlink,TransOptions;Ridewise;HARTCommuterInformationServices;CrossCountyConnection;andGreaterMercer.TheroleoftheTMAsis
topromotestatewideTransportationDemandManagement(TDM)initiativestoreducecommuterworktrips.TheTMAswillalsodeliverprograms
thatincludebutarenotlimitedtothefollowing;RidesharingInformationServices,EmployerTDMServices,CorridorManagementSupport,Parkand
RidePromotion,TrafficMitigationProjects,SmartWorkplacesNewJersey,coordinationoftransportationservicesfortransportationdisadvantaged
populations,TransitDevelopmentandPromotion,BicycleandPedestrianSafetyPrograms,aswellasotherincentiveanddemonstrationprogramsin
transportationdemandmanagementforcommuters.
DVRPC
EC
FHWA:STPDVRPCTotal
STPSTU
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
$20.000
$14.6
$11.3
$10.6
$22.8
$22.6
$22.8
$22.6
$22.8
$22.6
$22.8
$195.0
SectionIVPage4
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
MPOProjectDescriptions
SuballocatedSTPFunding($millions)
MPO
PHASE
FUND
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
State:TTF
DVRPC,FutureProjects(DBNUM:D026;UPC:058026)County:Various
ThisprogramprovidesfundingforlocalprojectstobeselectedbytheDelawareValleyRegionalPlanningCommission,thedesignatedMetropolitan
PlanningOrganizationforBurlington,Gloucester,MercerandCamdencounties.
DVRPC
ERC
STATE
State:TTFTotal
$8.000
$11.500
$12.000
$8.0
$11.5
$12.0
$31.500
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$31.5
STATEDVRPC
GloucesterCountyMultiPurposeTrailExtensionGlassboroElkTrail(DBNUM:D1203;UPC:123510)County:Gloucester
TheprojectwillextendthemultipurposetrailthatrunsfromGlassborotoWilliamstownalongtheformerrailroadrightofwaytotheElkTownship
recreationalcomplex,andElkTownship’strail(ElephantSwampTrail)thatrunstowardsSalemCounty.Theprojectwouldnotonlylinktothe
existingtrailthatendsatDelseaDriveinGlassborobutalsolooktolinktootherfacilitiessuchasRowanUniversityandtheRowanBoulevardproject.
ThetraillinktoRowanUniversitywouldendoncampusnearGirardAvenueinGlassboroatthefuturesiteofthelightrailtrainstationthatwould
connecttotheCityofWoodburyandonwardtoPhiladelphia.AportionoftheformerrailrightofwayontheeasterlysideofRoute55isowned
largelybyElkTownship.LinkingtotheexistingElkTownshipRecreationalComplexwouldinvolveusingtheexistingbridgeonWhigLaneRoad
(CR619)acrossRoute55,aswellasutilizingaportionoftheStatehighwayrightofwayofRoute55(ontheothersideoftheexistingfenceawayfrom
thehighway,separatedfromanytraffic).AsmalltrailbridgeisplannedacrossabranchofStillRunalongtheRoute55ROW.Thesoutherlylinkto
theElkTownshipRecreationalParkconnectstotheElephantSwampTrailwhichextendsintoSalemCounty.Theprojectwouldhavetheabilityto
linktoexistingandplannedtransitfacilitiessuchas:NJTransit463BusRouteinWilliamstownonanexistingportionofthetrailwhichhas
connectionstoNJTransit’sAvondalefacilityinCamdenCounty(connectionstoCamden,PhiladelphiaandAtlanticCity);NJTransit408BusRoutein
GlassboroattheprojectbeginningofthetrailonRoute47whichconnectsPhiladelphiatoMillville;thenorthernterminusoftheplannedtrailat
RowanUniversityinGlassborowouldprovideafuturelightrailconnectiontotheCityofWoodburyaswellastotheCitiesofCamdenand
Philadelphia;andabikelanelinkisalsoplannedalongalightrailtrailspurbytheBoroughofGlassborototheGlassboroArtsDistrictalongHigh
Street.
DVRPC
CON
STATEDVRPC
$1.500
$1.500
HanoverStreetBridgeoverRancocasCreek,CR616(DBNUM:D9902;UPC:950591)County:Burlington
HanoverStreetbridgeovertheRancocasCreekis0.2milesnorthofCR530.Theexistingbridgeistwonarrowlanes,asidewalkandnoshoulders.
Thebridgewillbereplacedonthesamealignment.Thenewstructurewillbetwotravellanes,sidewalksandshoulders.Thisprojectwill
accommodatebicyclesandpedestrians.
DVRPC
CON
STATEDVRPC
$3.315
$3.315
SectionIVPage5
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
MPOProjectDescriptions
SuballocatedSTPFunding($millions)
MPO
PHASE
FUND
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
SmithvilleRoadBridgeoverRancocasCreek,CR684(DBNUM:D9903;UPC:950629)County:Burlington
SmithvilleRoadBridgeovertheRancocasCreekisonemilenorthoftheintersectionwithCR530.ThistwolanebridgecarriesanAADTofabout
3,200vehicles.TheroadisclassifiedasanUrbanCollector.Thecurrentsufficiencyratingforthebridgeis22.7.Thisbridgewillbereplaced.
DVRPC
CON
STATEDVRPC
$2.121
$0.700
$2.821
TrentonAmtrakBridges(DBNUM:99362;UPC:993620)County:Mercer
Thethreeorphanbridges,carryingChestnutAve.,E.StateStreetandMonmouthSt.overAmtrak,areinpoorcondition.Allthreebridgesare
structurallydeficientandfunctionallyobsolete.Thebridgesandapproachroadwaysfeaturevarioussubstandarddesignelements,including
substandardverticalandhorizontalclearances,intersectionsightdistancesandunprotectedbridgegirders.NJDOTisworkingwithTheCityof
TrentononarevisedconcepttoreplacetheE.StateSt.BridgeandremovetheChestnutAve.andMonmouthSt.Bridges.Anewconnectorroad
proposedwiththeconceptmaintainsallcurrentturningmovements.Thesinglebridgeoptionisaviableplan,giventheconstructioncostestimateof
approximately$35M.Replacementofthethreeexistingbridgespresentsfundingissues,givenconstraintsoftheMPO.
DVRPC
UTI
STATEDVRPC
$6.800
$9.000
$15.800
ADAImprovements(DBNUM:D1505;UPC:153550)County:Camden
Thisprojectwillcompletelyreconstructapproximately1,088existingorconstructnewADAcompliantsidewalk,curbramps,andassociated
structuresatvariouslocationsintheCityofCamden.CrosswalkswillbeconstructedasrequiredorappropriatetoconnectoppositeADAcompliant
rampsatstreetintersections.
DVRPC
CON
STATEDVRPC
$3.114
$3.114
BurlingtonCountyRoadwaySafetyImprovements(DBNUM:D0302)County:Burlington
Thisprogramwillprovidefortheinstallationofimprovedsafetyitemsincludingreflectivepavementmarkings(includingbothstripingandraised
reflectivemarkers),reflectiveobjectmarkers,reflectiveroadwaydelineators,guiderail,andothertreatmentsthatimprovetheoverallsafetyand
visibilityofvariousroadwaysinthecounty.
DVRPC
CON
STATEDVRPC
$0.464
$0.336
$0.700
$1.500
CamdenCountyRoadwaySafetyImprovements(DBNUM:D0410;UPC:048038)County:Camden
Thisprogramwillprovidefortheinstallationofimprovedsafetyitemsincludingreflectivepavementmarkings(includingbothstripingandraised
reflectivemarkers),reflectiveobjectmarkers,reflectiveroadwaydelineators,guiderail,andothertreatmentsthatimprovetheoverallsafetyand
visibilityofvariousroadwaysinthecounty.
DVRPC
CON
STATEDVRPC
$0.550
$0.550
SectionIVPage6
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
MPOProjectDescriptions
SuballocatedSTPFunding($millions)
MPO
PHASE
FUND
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
GloucesterCountyRoadwaySafetyImprovements(DBNUM:D0401;UPC:048000)County:Gloucester
Thisprogramwillprovidefortheinstallationofimprovedsafetyitemsincludingreflectivepavementmarkings(includingbothstripingandraised
reflectivemarkers),reflectiveobjectmarkers,reflectiveroadwaydelineators,guiderail,andothertreatmentsthatimprovetheoverallsafetyand
visibilityofvariousroadwaysinthecounty.
DVRPC
CON
STATEDVRPC
$0.700
$0.700
MercerCountyRoadwaySafetyImprovements(DBNUM:D0412;UPC:048075)County:Mercer
Thisprogramwillprovidefortheinstallationofimprovedsafetyitemsincludingreflectivepavementmarkings(includingbothstripingandraised
reflectivemarkers),reflectiveobjectmarkers,reflectiveroadwaydelineators,guiderail,andothertreatmentsthatimprovetheoverallsafetyand
visibilityofvariousroadwaysinthecounty.
DVRPC
CON
STATEDVRPCTotal
STATEDVRPC
$0.600
$8.0
$0.700
$11.5
$11.1
$1.300
$0.0
SectionIVPage7
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$30.6
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
MPOProjectDescriptions
SuballocatedSTPFunding($millions)
MPO
PHASE
FUND
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
NJTPA
FHWA:HighPriority
MonmouthCountyBridgesW7,W8,W9overGlimmerGlassandDebbiesCreek(DBNUM:NS9306;UPC:950607)County:Monmouth
Thisprojectiscomprisedoftherehabilitationorreplacementofthreeexistingdeficientbridges,whichcarryBrielleRoadoverGlimmerGlassCreek
andGreenAvenueoverDebbiesCreek.Duetoitsthreecomponentperpendicularconfiguration,theprojectsiteislocallyknownasThreeBridges.
Allthreestructures,whethermovableorfixed,willberehabilitatedorreplacedinkindwithbridgesmeetingcurrentdesignstandardsandthus
improveroadwaygeometrics.
NJTPA
DES
DEMO
$2.160
$2.160
NorthPlainfieldDowntownStreetscapeandPedestrianImprovements(FinalPhase)(DBNUM:N1125;UPC:118032)County:Somerset
TheprojectwillextendthecurrentstreetscapenorthonSomersetStreet.Theimprovementswillincludetheconstructionofconcretecurbing,ADA
rampsandcoloredstampedsidewalks,theinstallationofsomebenchesandstreettrees.
Thisprojectisfundedthroughthefollowingspecialappropriations:FY2010AppropriationsAct$300,000(ID#NJ295).
NJTPA
ERC
DEMO
$0.300
$0.300
PortNewarkContainerTerminal(PNCT)AccessImprovementandExpansionProject(DBNUM:N1501;UPC:154370)County:Essex
Thisprojectwilldemolishbothdryandrefrigeratedwarehousesandgatefacilities,thenpaveallareasandconstructnewgatesthatincludetruck
comfortandservicestationsatthePortofNewark.Itwillcombinemodernfacilitieswithnewtechnologiesandwillsignificantlyupdatethestorage
capacityofthePortNewarkContainerTerminalforcontainerizedgoods.Theprojectwillconsideroptionstoaccommodatefuturesealevelrise.This
projectwillbefundedwitha2014USDOTTransportationInvestmentGeneratingEconomicRecovery(TIGER)grantintheamountof$14.8M.
NJTPA
CON
DEMO
FHWA:HighPriorityTotal
$14.800
$17.3
$14.800
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$17.3
FHWA:STPNJTPA
ChurchStreetBridge,CR579(DBNUM:NS9806;UPC:058011)County:Hunterdon
TheChurchStreet(CR579)overtheLehighValleyMainLinebridgeprojectproposesthereplacementoftheexistingfunctionallyobsoletebridgeinan
efforttoimprovesubstandardsightdistanceandinadequatedeckgeometry.Theproposedundertakingwouldreplacetheexistingbridgewithanew
twolanebridgetotheeastandthebridgeapproacheswillbeimproved.
NJTPA
CON
STPNJ
$3.800
SectionIVPage8
$3.800
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
MPOProjectDescriptions
SuballocatedSTPFunding($millions)
MPO
PHASE
FUND
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
CountyRoute537Corridor,SectionA,NJRt.33BusinessandGravelHillRoad(DBNUM:NS0403)County:Monmouth
CR537servesregionaltravelbetweenBurlington,OceanandMonmouthCounties.Thisroadwayalsoservesasalinkbetweenrapidlydeveloping
areasofMercerandOceanCountiestorecreationalandcommercialactivitieswithinMonmouthCounty.Asaresult,trafficvolumesalongthis
corridorhavesignificantlyincreased,resultinginhighcongestionalongthissectionofCR537.TheCountywillinvestigateimprovementalternatives
resultingfromtherecenttechnicalstudypreparedforthissectionofthecorridor.
NJTPA
ROW
STPNJ
NJTPA
CON
STPNJ
$7.000
$7.000
$20.700
$20.700
HallsMillRoad(DBNUM:HP01002;UPC:018090)County:Monmouth
ImprovementstoHallsMillRoadfromRt.33BypasstoCR524willincluderealignmentandwideningtofourtravellanesaswellasother
improvements.
NJTPA
CON
STPNJ
$0.785
$0.785
MarketStreet/EssexStreet/RochelleAvenue(DBNUM:98546;UPC:985460)County:Bergen
Fundingisprovidedforascopingstudytosecurerecommendedimprovementstotheintersectionandbridgeatthislocation.
Thefollowingspecialfederalappropriationswereallocatedtothisproject.TEA21/Q92,ID#NJ023,$3,844,123
NJTPA
CON
STPNJ
$7.360
$7.360
MonmouthCountyBridgesW7,W8,W9overGlimmerGlassandDebbiesCreek(DBNUM:NS9306;UPC:950607)County:Monmouth
Thisprojectiscomprisedoftherehabilitationorreplacementofthreeexistingdeficientbridges,whichcarryBrielleRoadoverGlimmerGlassCreek
andGreenAvenueoverDebbiesCreek.Duetoitsthreecomponentperpendicularconfiguration,theprojectsiteislocallyknownasThreeBridges.
Allthreestructures,whethermovableorfixed,willberehabilitatedorreplacedinkindwithbridgesmeetingcurrentdesignstandardsandthus
improveroadwaygeometrics.
NJTPA
DES
STPNJ
NJTPA
CON
STPNJ
$1.000
$1.000
$30.000
$30.000
NYSusquehannaandWesternRailLineBicycle/PedestrianPath(DBNUM:NS9803;UPC:058018)County:Morris,Passaic
The4.8mileNewYork,Susquehanna,andWesternRailway(NYS&W)BicycleandPedestrianPathrunsalongtheNYS&WRightofWay(ROW)from
RiverDrive,PequannockTownship(MorrisCounty)totheMountainViewrailstationinWayneTownship(PassaicCounty).
NJTPA
CON
STPNJ
$7.000
SectionIVPage9
$7.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
MPOProjectDescriptions
SuballocatedSTPFunding($millions)
MPO
PHASE
FUND
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
RumsonRoadovertheShrewsburyRiver,CR520(DBNUM:NS9706;UPC:950628)County:Monmouth
BridgeS32carriesCR520,RumsonRoad,acrosstheShrewsburyRiverbetweentheBoroughsofRumsonandSeaBright.Thisbridgeservesasoneof
twoevacuationandemergencyroutesintimesoftidalfloodingandcoastalstorms.Theexistingstructureisinpoorcondition,withdeteriorationof
majorbridgecomponents.Possibleimprovementssuchasrehabilitationorreconstructionofthestructurewillbestudied.
Thisprojectismultiyearfunded.
NJTPA
DES
STPNJ
NJTPA
CON
STPNJ
$5.000
$5.000
$45.725
$14.275
$60.000
LocalPreliminaryEngineering(DBNUM:N1202;UPC:123530)County:Various
ThisprogramprovidesfundingforprojectsthathavegraduatedfromtheLocalCapitalProjectDeliveryProgramsLocalConceptDevelopmentPhase.
Theseprojectswillbefurtherdevelopedandrefinedtoalevelofdetailnecessarytosecuretheapprovaloftheenvironmentaldocument.
NJTPA
ERC
STPNJ
$2.000
$1.985
$1.400
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
$2.000
$19.385
NJTPA,FutureProjects(DBNUM:N063;UPC:058027)County:Various
Thisprogramprovidesfundingforunanticipatedprojectneedsassociatedwiththedesign,rightofWayorconstructionofNJTPAselectedlocal
projects.
NJTPA
ERC
STPNJ
$6.425
$0.240
$0.240
$0.000
$45.490
$75.725
$57.225
$75.725
$77.925
$75.725
$414.720
LocalAidConsultantServices(DBNUM:10347;UPC:103470)County:Various
FundingforconsultantservicestoassistlocalpublicagenciesinadministeringprojectsandprovidingoversighttorecipientsreceivingLocalAid
funds.Servicesalsoincludeprovidingoverallqualityassuranceandqualitycontrolfortheprojectdeliveryprocess.
NJTPA
EC
STPNJ
$1.200
$1.200
$1.200
$1.200
$1.200
$6.000
$2.925
$29.250
LocalProjectDevelopmentSupport(DBNUM:06326;UPC:063260)County:Various
ThisprogramprovidesNJDOTprojectmanagementandenvironmentalsupporttolocalgovernments.
NJTPA
PLS
STPNJ
$2.925
$2.925
$2.925
$2.925
$2.925
$2.925
$2.925
$2.925
$2.925
MetropolitanPlanning(DBNUM:X30A)County:Various
NJDOTsupportsthefederallymandatedMetropolitanPlanningOrganizationtransportationplanningprocess.NewJerseyMetropolitanPlanning
Organizationscarryouta3Ctransportationplanningprocesswherebyplanningactivitiesareconductedonacontinuousbasiswhilealsoproviding
aforumforcooperativedecisionmakingamongresponsiblestateandlocalofficials,publicandprivatetransitoperatorsandthegeneralpublic.
NJTPA
PLS
STPNJ
$5.000
$7.200
$5.000
$7.200
SectionIVPage10
$5.000
$7.200
$5.000
$7.200
$5.000
$7.200
$61.000
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
MPOProjectDescriptions
SuballocatedSTPFunding($millions)
MPO
PHASE
FUND
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
TransportationManagementAssociations(DBNUM:11383;UPC:113830)County:Various
ThisprogramwillprovideannualfundingtothefollowingTransportationManagementAssociations(TMAs):KeepMiddlesexMoving;Hudson,
Meadowlink,TransOptions;Ridewise;HARTCommuterInformationServices;CrossCountyConnection;andGreaterMercer.TheroleoftheTMAsis
topromotestatewideTransportationDemandManagement(TDM)initiativestoreducecommuterworktrips.TheTMAswillalsodeliverprograms
thatincludebutarenotlimitedtothefollowing;RidesharingInformationServices,EmployerTDMServices,CorridorManagementSupport,Parkand
RidePromotion,TrafficMitigationProjects,SmartWorkplacesNewJersey,coordinationoftransportationservicesfortransportationdisadvantaged
populations,TransitDevelopmentandPromotion,BicycleandPedestrianSafetyPrograms,aswellasotherincentiveanddemonstrationprogramsin
transportationdemandmanagementforcommuters.
NJTPA
EC
STPNJ
FHWA:STPNJTPATotal
$4.195
$4.195
$4.195
$4.195
$4.195
$4.195
$4.195
$4.195
$4.195
$4.195
$41.950
$21.5
$22.7
$21.5
$93.2
$92.0
$93.2
$92.0
$93.2
$92.0
$93.2
$715.0
State:TTF
NJTPA,FutureProjects(DBNUM:N063;UPC:058027)County:Various
Thisprogramprovidesfundingforunanticipatedprojectneedsassociatedwiththedesign,rightofWayorconstructionofNJTPAselectedlocal
projects.
NJTPA
ERC
STATE
State:TTFTotal
$70.500
$70.500
$70.500
$70.5
$70.5
$70.5
$211.500
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$211.5
STATENJTPA
ChurchStreetBridge,CR579(DBNUM:NS9806;UPC:058011)County:Hunterdon
TheChurchStreet(CR579)overtheLehighValleyMainLinebridgeprojectproposesthereplacementoftheexistingfunctionallyobsoletebridgeinan
efforttoimprovesubstandardsightdistanceandinadequatedeckgeometry.Theproposedundertakingwouldreplacetheexistingbridgewithanew
twolanebridgetotheeastandthebridgeapproacheswillbeimproved.
NJTPA
DES
STATENJTPA
NJTPA
ROW
STATENJTPA
$0.700
$0.700
$0.400
SectionIVPage11
$0.400
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
MPOProjectDescriptions
SuballocatedSTPFunding($millions)
MPO
PHASE
FUND
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
CloveRoad/LongHillRoadImprovements,CR620/631(DBNUM:NS0412)County:Passaic
CloveRoad/LongHillRoadconnectsRt.46toUpperMountainAvenue,whichisamainaccessroutetodowntownMontclair.Despitethepresenceof
severalhighvolumedrivewaysservingMontclairStateUniversitydorms,parkinglots,andaccessroutes,nodedicatedturninglanesexistalongthis
route.Thislackofturninglaneshascausedalargepercentageofrecordedaccidentstoberelatedtoturningmovements.Additionally,thelackof
sidewalkshascreatedsafetyissuesforpedestriansaccessingboththedormsandparkingareas.TheCountywillinvestigatealternativesforthe
improvementofthisroadway.
NJTPA
CON
STATENJTPA
$6.900
$6.900
CountyRoute537Corridor,SectionA,NJRt.33BusinessandGravelHillRoad(DBNUM:NS0403)County:Monmouth
CR537servesregionaltravelbetweenBurlington,OceanandMonmouthCounties.Thisroadwayalsoservesasalinkbetweenrapidlydeveloping
areasofMercerandOceanCountiestorecreationalandcommercialactivitieswithinMonmouthCounty.Asaresult,trafficvolumesalongthis
corridorhavesignificantlyincreased,resultinginhighcongestionalongthissectionofCR537.TheCountywillinvestigateimprovementalternatives
resultingfromtherecenttechnicalstudypreparedforthissectionofthecorridor.
NJTPA
DES
STATENJTPA
$3.000
$3.000
DelancyStreet,AvenueItoAvenueP(DBNUM:NS0504;UPC:058046)County:Essex
TheDelancyStreetcorridoris1.1milesandconnectsfreightrailroadfacilities,intermodalcenterandtruckingandshippingoutfitstoRt.1&9Portway
andtheairport/seaportsupportarea.CurrentlytheroadwayisoperatingatanunacceptableLevelofServiceduringpeakhours.Itfrequentlyfloods,
interruptingpedestrianandvehicularaccesstofreightandbusinesscenters.
NJTPA
ROW
STATENJTPA
NJTPA
CON
STATENJTPA
$1.900
$1.900
$13.500
$13.500
FifthAvenueBridge(AKAFairLawnAvenueBridge)overPassaicRiver(DBNUM:NS9606;UPC:950589)County:Bergen,Passaic
TheFifthAvenueBridgecrossesthePassaicRiverandconnectsRt.20inPatersontoRiverRoadinFairLawn.FifthAvenueBridgeisinverypoor
conditionwithadeterioratingsubstructure,sectionlossinthesuperstructure,andinadequategeometry.Itisheightandweightrestricted,requiring
truckstodetouraroundit.ThebridgeiseligiblefortheNationalRegisterofHistoricPlaces.TheCountyisproposingtoreplacetheexistingbridge
withanewslightlywiderbridgeatthesamelocation.
NJTPA
CON
STATENJTPA
$13.300
$13.300
SectionIVPage12
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
MPOProjectDescriptions
SuballocatedSTPFunding($millions)
MPO
PHASE
FUND
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
GordonStreetoverOutofServiceConrailBranch,Replacement(DBNUM:NS0408)County:Union
Builtin1911,thisorphanbridgenowservesasaconnectortotheRt.28corridor.ItisoneoffourcrossingsbetweenRoselleandRosellePark.Its3
tonweightpostingseverelyrestrictstruckaccesstoRt.28adverselyaffectingtrucktrafficinthiscorridorforanumberofsmallandmedium
businesses.Thisbridgeisstructurallydeficientandfunctionallyobsolete.TheCountywillinvestigatealternativesfortherehabilitationor
replacementofthisstructure.
NJTPA
ROW
STATENJTPA
NJTPA
CON
STATENJTPA
$0.200
$0.200
$7.000
$7.000
LandingRoadBridgeOverMorristownLine,CR631(DBNUM:NS9708;UPC:980131)County:Morris
LandingRoadBridgecrossesoverNJTransitrailroadtracksintheTownshipofRoxbury.Structuraldeterioration,alongwithsubstandarddeck
geometry,makesthisbridgeagoodcandidateforreplacement.Alargerstructureisrequiredduetothecurrentandprojectedtrafficvolumes
traversingfromSussexCountytoI80inMorrisCounty.Asafourlanebridgeisdesired,anewalignmentwouldbeneeded.Inaddition,anew
signalizedintersectionwouldbeneeded.Thestudyisnowinitssecondphaseoffundinghavingreceivedthecommunitysupportnecessaryforthe
scopingprocesstobecompletedsuccessfully.Theexistingbridgesuperstructureandsubstructureexhibitseverespallingandmediumtowidecracks
withlargeareasofleachingandefflorescence.Structurallydeterioratedbridgealongwithsubstandarddeckgeometry,inadequatetocarrycurrent
trafficvolumes,requiresbridgereplacement.Thecountyproposestoreplacetheoldbridgewithnewalignment.Thiswouldenableconstructionfor
fourlanes.
NJTPA
DES
STATENJTPA
NJTPA
ROW
STATENJTPA
NJTPA
CON
STATENJTPA
$1.000
$1.000
$1.000
$1.000
$6.575
$6.575
McClellanStreetUnderpass(DBNUM:NS9812)County:Essex
TheCityofNewarkisproposingimprovementstotheMcClellanStreetUnderpass.Improvementwillincludeimproveddrainageandhorizontaland
verticalclearances.
NJTPA
CON
STATENJTPA
$10.000
$10.000
MilfordWarrenGlenRoad,CR519(DBNUM:NS9703;UPC:950604)County:Hunterdon
CountyRt.519,MilfordWarrenGlenRoad,islocatedinHollandTownship.This1.3milestretchofroadwayconsistsofalong,steepgradeandhas
beenthelocationofseveralrunawaytruckandvehicleaccidents.Theproposedimprovementsincludeimprovingroadwaygeometrytomeet60km/h
(35mph)designspeed,provide23.6meter(12)lanes,13.6meter(12)southboundclimbinglane,a2.4meter(8)northboundshoulder,a1.2meter
(4)southboundshoulderadjacenttoclimbinglane,andanupgradedguiderail.Approximately1.79ha(4.41acres)willbetaken;0.93Ha(2.31acres)
ofwhichwillbetakenfrompublicrecreationlands.
NJTPA
CON
STATENJTPA
$8.300
$8.300
SectionIVPage13
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
MPOProjectDescriptions
SuballocatedSTPFunding($millions)
MPO
PHASE
FUND
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
MonmouthCountyBridgesW7,W8,W9overGlimmerGlassandDebbiesCreek(DBNUM:NS9306;UPC:950607)County:Monmouth
Thisprojectiscomprisedoftherehabilitationorreplacementofthreeexistingdeficientbridges,whichcarryBrielleRoadoverGlimmerGlassCreek
andGreenAvenueoverDebbiesCreek.Duetoitsthreecomponentperpendicularconfiguration,theprojectsiteislocallyknownasThreeBridges.
Allthreestructures,whethermovableorfixed,willberehabilitatedorreplacedinkindwithbridgesmeetingcurrentdesignstandardsandthus
improveroadwaygeometrics.
NJTPA
ROW
STATENJTPA
$1.000
$1.000
NYSusquehannaandWesternRailLineBicycle/PedestrianPath(DBNUM:NS9803;UPC:058018)County:Morris,Passaic
The4.8mileNewYork,Susquehanna,andWesternRailway(NYS&W)BicycleandPedestrianPathrunsalongtheNYS&WRightofWay(ROW)from
RiverDrive,PequannockTownship(MorrisCounty)totheMountainViewrailstationinWayneTownship(PassaicCounty).
NJTPA
ROW
STATENJTPA
$5.000
$5.000
OpenakiRoadBridge(DBNUM:NS9802;UPC:058019)County:Morris
OpenakiRoadbridgeovertheDenBrookinDenvilleTownshipwasbuiltin1924andisnowstructurallydeficientandfunctionallyobsoletedespite
effortsbythecountytosavethestructure.Theexistingbridgeisasinglespanthrutrusswithawoodplankdeck.Thebridgehasnarrowroadway
widthandlowinventoryandoperatingratings.Thecountyplanstowidentheroadwayto32consistingofhighstrengthweatheringsteelstringers
withacompositereinforcedconcretedeckslab.
NJTPA
DES
STATENJTPA
NJTPA
ROW
STATENJTPA
NJTPA
CON
STATENJTPA
$1.000
$1.000
$0.500
$0.500
$6.000
$6.000
RumsonRoadovertheShrewsburyRiver,CR520(DBNUM:NS9706;UPC:950628)County:Monmouth
BridgeS32carriesCR520,RumsonRoad,acrosstheShrewsburyRiverbetweentheBoroughsofRumsonandSeaBright.Thisbridgeservesasoneof
twoevacuationandemergencyroutesintimesoftidalfloodingandcoastalstorms.Theexistingstructureisinpoorcondition,withdeteriorationof
majorbridgecomponents.Possibleimprovementssuchasrehabilitationorreconstructionofthestructurewillbestudied.
Thisprojectismultiyearfunded.
NJTPA
ROW
STATENJTPA
$5.500
$5.500
SectionIVPage14
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
MPOProjectDescriptions
SuballocatedSTPFunding($millions)
MPO
PHASE
FUND
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
SchalksCrossingRoadBridge,CR683(DBNUM:00321;UPC:003210)County:Middlesex
Fundingisbeingprovidedforthereplacementofthebridgedeckthatwillmaintaintheexistingsteelsuperstructureandprovidebicycle/pedestrian
accessibility.Asharedbicycle/pedestriansidewalklanewillbeprovidedthroughcantileveradditiononthethroughgirdersalongboththeeastand
westsidesofSchalksCrossingRoad.Repairswillbemadetothesubstructure.Priortoanybridgerehabilitation,therailroadcatenarysystemwillbe
modified.Roadwayimprovementswouldincludemillingandresurfacingtheexistingroadwayapproachesfortieinstobridge.
NJTPA
CON
STATENJTPA
$10.359
$10.359
SouthAmboyIntermodalCenter(DBNUM:98541;UPC:985410)County:Middlesex
Thisisanintermodalprojectlinkingseveralmajorregionalroutesandmodesoftransportationintoonecentralpointoftransfer.Improvementsinthe
vicinityoftheSouthAmboywaterfrontmayincluderailandbustransitplazas,arterialandsiteaccessroadimprovements,bridgereconfiguration,
bulkheadingandbreakwaterdevelopment,ferryterminal,andpedestrianaccesstorailandbusfacilities.
NJTPA
ERC
STATENJTPA
$3.000
$3.000
TwoBridgesRoadBridgeandWestBeltExtension(DBNUM:NS9801)County:Morris,Passaic,Essex
TwoBridgesRoadoverthePomptonRiverandWestBeltHighwayExtensioninLincolnParkBoroughandWayneTownshipisatricountyproject
withPassaiccountyasthelead.TwoBridgesRoadbridgeisstructurallydeficientandfunctionallyobsolete.Alternativeswillbeexaminedtoreplace
thestructureandprovideamissinglinkfortheWestBeltHighwaybyrelocatingorrealigningthebridge.
NJTPA
CON
STATENJTPA
$18.000
$18.000
WaterlooRoadoverMusconetcongRiver(DBNUM:NS0107;UPC:023670)County:Morris,Sussex
BridgeNo.1401038isinoverallcriticalconditionandisclassifiedasbothstructurallydeficientandfunctionallyobsolete.Thestructuresuffersfrom
deformedbottomchordmemberswithsectionlossesandcrackedweldsatthechordconnections.Thebridgeispostedforagrossloadcarrying
capacityof11tons.TheCountywillreplacetheexistingbridgewithanewtwolanebridge,withtwoshouldersandasidewalk.
NJTPA
ROW
STATENJTPA
NJTPA
CON
STATENJTPA
$0.275
$0.275
$3.000
$3.000
SectionIVPage15
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
MPOProjectDescriptions
SuballocatedSTPFunding($millions)
MPO
PHASE
FUND
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
Route78,PittstownRoad(Exit15),InterchangeImprovements(CR513)(DBNUM:NS0309;UPC:950435)County:Hunterdon
AgraduateoftheNJTPATechnicalStudiesProgram,thisprojectfocusesonthecongestionofthestudyareaatinterchange15onI78.Queuingof
trafficonthewestboundexitrampontotheinterstatecreatesasignificantsafetyissue.CongestionissuesalsoexistonCR513totheentranceofthe
HunterdonDevelopmentCenter.ImprovementsincluderelocationofI78EBrampsatInterchange15;constructionofaSBallturnsjughandleatthe
CR513/SouthServiceRdintersection;reconstructionofSBleftturnsatCR513/SouthServiceRdintersection;andtherestrippingofCR513from
SouthServiceRdtoRt173willbechangedformathreelanesectiontoafourlanesection.
ThefollowingFederalappropriationswereallocatedtothisproject.FY06SAFETEALU/HPP$800,000(ID#NJ222),(available20%peryear).
NJTPA
ROW
STATENJTPA
NJTPA
CON
STATENJTPA
STATENJTPATotal
$1.000
$1.000
$5.000
$45.4
$60.7
$5.000
$27.3
$0.0
SectionIVPage16
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$133.4
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
MPOProjectDescriptions
SuballocatedSTPFunding($millions)
MPO
PHASE
FUND
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
SJTPO
FHWA:STPSJTPO
CorsonsTavernRoad(CR628),ResurfacingWoodbineOceanViewRoadtoUSRoute9(DBNUM:S1004;UPC:108025)County:CapeMay
RoadwayresurfacinganddrainageimprovementsfromWoodbineOceanViewRoad(CR550)toRt.US9.
SJTPO
CON
STPSJ
$1.682
$1.682
CorsonsTavernRoad,Resurfacing(CR628)(DBNUM:S0902;UPC:098002)County:CapeMay
RoadwayresurfacinganddrainageimprovementsresultfromOceanViewOperationalStudy.Limits:1,000ftsouthofTattlerRoadtoWoodbine
OceanViewRd(CR550).
SJTPO
CON
STPSJ
$1.723
$1.723
LandisAvenue,PhaseIII,ConeyAvenuetoWestAvenue(DBNUM:S1122;UPC:118029)County:Cumberland
Thisprojectprovidesformillingandresurfacingoftheroadwaywithingtheexistingrightofwayinadditiontoremovalandreplacementofconcrete
itemsandrehabilitationsoftheexistingstormsewerinfrastructureasneeded.
SJTPO
CON
STPSJ
$0.670
$0.670
LandisAvenue,PhaseIV,OrchardRoad(CR628)toMoyerStreet(DBNUM:S1124;UPC:118031)County:Cumberland
Thisprojectprovidesformillingandresurfacingoftheroadwaywithingtheexistingrightofwayinadditiontoremovalandreplacementofconcrete
itemsandrehabilitationsoftheexistingstormsewerinfrastructureasneeded.
SJTPO
CON
STPSJ
$0.609
$0.609
LandisAvenue,PhaseV,MillRoadtoOrchardRoad(CR628)(DBNUM:S1407;UPC:143920)County:Cumberland
Mill&OverlayRoadwaywithinexistingRightofWayfromMillRoadtoOrchardRoad.
SJTPO
DES
STPSJ
SJTPO
CON
STPSJ
$0.050
$0.050
$0.700
$0.700
Route47(RioGrandeAvenue),ParkBoulevardtoGeorgeReddingBridge(DBNUM:S1414;UPC:143990)County:CapeMay
Roadwayresurfacinganddrainageimprovementswithintheexistingrightofway.
SJTPO
CON
STPSJ
$1.712
$1.712
SJTPO,FutureProjects(DBNUM:S044;UPC:058025)County:Various
ThisprogramprovidesfundingforlocalprojectstobeselectedbytheSouthJerseyTransportationPlanningOrganization,thedesignated
MetropolitanPlanningOrganizationforSalem,Cumberland,CapeMayandAtlanticcounties.
SJTPO
ERC
STPSJ
$0.000
$0.000
$0.000
$8.382
SectionIVPage17
$9.882
$9.882
$9.882
$9.882
$9.882
$9.882
$67.674
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
MPOProjectDescriptions
SuballocatedSTPFunding($millions)
MPO
PHASE
FUND
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
LocalAidConsultantServices(DBNUM:10347;UPC:103470)County:Various
FundingforconsultantservicestoassistlocalpublicagenciesinadministeringprojectsandprovidingoversighttorecipientsreceivingLocalAid
funds.Servicesalsoincludeprovidingoverallqualityassuranceandqualitycontrolfortheprojectdeliveryprocess.
SJTPO
EC
STPSJ
$0.100
$0.100
$0.100
$0.100
$0.100
$0.500
$0.275
$2.750
LocalProjectDevelopmentSupport(DBNUM:06326;UPC:063260)County:Various
ThisprogramprovidesNJDOTprojectmanagementandenvironmentalsupporttolocalgovernments.
SJTPO
PLS
STPSJ
$0.275
$0.275
$0.275
$0.275
$0.275
$0.275
$0.275
$0.275
$0.275
MetropolitanPlanning(DBNUM:X30A)County:Various
NJDOTsupportsthefederallymandatedMetropolitanPlanningOrganizationtransportationplanningprocess.NewJerseyMetropolitanPlanning
Organizationscarryouta3Ctransportationplanningprocesswherebyplanningactivitiesareconductedonacontinuousbasiswhilealsoproviding
aforumforcooperativedecisionmakingamongresponsiblestateandlocalofficials,publicandprivatetransitoperatorsandthegeneralpublic.
SJTPO
PLS
STPSJ
FHWA:STPSJTPOTotal
$0.265
$0.265
$0.265
$0.265
$0.265
$0.265
$0.265
$0.265
$0.265
$0.265
$2.650
$2.9
$3.0
$2.9
$9.0
$10.4
$10.5
$10.4
$10.5
$10.4
$10.5
$80.7
State:TTF
SJTPO,FutureProjects(DBNUM:S044;UPC:058025)County:Various
ThisprogramprovidesfundingforlocalprojectstobeselectedbytheSouthJerseyTransportationPlanningOrganization,thedesignated
MetropolitanPlanningOrganizationforSalem,Cumberland,CapeMayandAtlanticcounties.
SJTPO
ERC
STATE
State:TTFTotal
$7.500
$7.500
$7.500
$7.5
$7.5
$7.5
$22.500
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$22.5
STATESJTPO
AtlanticAvenue,ConnecticutAvenuetoMaineAvenue(DBNUM:S1408;UPC:143930)County:Atlantic
TheresurfacingofthecartwayandmodificationofroadwaydrainagetocomplywithMS4stormwaterregulationsandsidewalkatcrosswalksto
conformtoADArequirements.
SJTPO
DES
STATESJTPO
SJTPO
CON
STATESJTPO
$0.050
$0.050
$1.110
$1.110
BrigantineBlvd.,Sec.1B,Repaving(CR638)(DBNUM:S0914;UPC:098031)County:Atlantic
RepavingofBrigantineBoulevard,fromHarborBeachBoulevardtoBayshoreAvenue;mileposts1.05to1.53.
SJTPO
CON
STATESJTPO
$1.500
$1.500
SectionIVPage18
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
MPOProjectDescriptions
SuballocatedSTPFunding($millions)
MPO
PHASE
FUND
FY2016
FY2017
FY2018
FY2019
FY2020
FY2021
FY2022
FY2023
FY2024
FY2025
Total
CR551(HookRoad),E.PittsfieldStreettoRoute295(DBNUM:S1406;UPC:143910)County:Salem
ResurfacingofHookRoad(CR551)fromEastPittsfieldStreettoI295NBIncludingRaisingofa1000FootLongSectionatMP2.85toAlleviate
Flooding.
SJTPO
DES
STATESJTPO
SJTPO
CON
STATESJTPO
$0.050
$0.050
$1.500
$1.500
CumberlandCountyFederalRoadProgram(DBNUM:S1403;UPC:143880)County:Cumberland
Mill&Overlayofvariousroadwaysthroughoutthecountywithintheexistingrightofway.
SJTPO
ERC
STATESJTPO
$2.250
$2.000
$1.900
$6.150
EleventhAvenue(CR669),MunicipalBordertoRoute50(BroadStreet)(DBNUM:S1410;UPC:143950)County:Atlantic
Millandoverlayoftheroadwaywithintheexistingrightofway.
SJTPO
CON
STATESJTPO
$1.700
$1.700
Route73(BlueAnchorRoad),Route322toRoute54(TwelfthStreet)(DBNUM:S1412;UPC:143970)County:Atlantic
Millandoverlayoftheroadwaywithintheexistingrightofway.
SJTPO
CON
STATESJTPO
$1.500
$1.500
Route73(MaysLandingRoad),Route54(TwelfthStreet)toSherryLane(DBNUM:S1413;UPC:143980)County:Atlantic
Millandoverlayoftheroadwaywithintheexistingrightofway.
SJTPO
CON
STATESJTPO
$1.000
$1.000
SalemCountyMillandOverlayResurfacingProgram(DBNUM:S1501;UPC:153490)County:Salem
ThisprogramprovidesmillingandoverlayresurfacingofvariousroadwaysintheCountyincludingsafetyimprovements.
SJTPO
DES
STATESJTPO
$0.100
SJTPO
CON
STATESJTPO
$1.600
$1.800
$6.6
$6.6
STATESJTPOTotal
$0.100
$3.400
$4.9
$0.0
SectionIVPage19
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$18.1
SECTIONȱVIȱ
ȱ
DRPAȬPATCOȱPROJECTȱDESCRIPTIONSȱ
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
DelawareRiverPortAuthorityofPennsylvaniaandNewJersey(DRPA)
PortAuthorityTransitCorporation(PATCO)ProjectDescriptions
($millions)
DBNUM:DR046
DRPARebuildPATCOCars
ThisprojectwillprovideforthereplacementofPATCOsexistingcareet,throughcompleterebuildingofexistingcars.Thefollowingspecial
Federalappropriationswereallocatedtothisproject.SAFETEALUprovided$10,000,000underSection1934(ID#NJ261,bal.avail.$4,310,000)and
$40,000,000underSection1701.
COUNTY: Camden
LEGISLATIVEDISTRICT: 4
MUNICIPALITY: LindenwoldBorough
SPONSOR: DRPA/PATCO
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M10(Exempt)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
EC
DRPA
$0.800
$0.800
$0.800
$2.400
DVRPC
EC
SECT5307
$3.200
$3.200
$3.200
$9.600
SectionVIPage1
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
DelawareRiverPortAuthorityofPennsylvaniaandNewJersey(DRPA)
PortAuthorityTransitCorporation(PATCO)ProjectDescriptions
($millions)
DBNUM:DR008
ElectricalCableReplacement
Thisprogramwillprovideforsystemwidereplacementofelectricalcabletoimprovereliabilityandfireresistance.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: DRPA/PATCO
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M6(Exempt)
Fund
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
DVRPC
ERC
DRPA
$0.050
$0.160
$0.400
$0.500
$0.500
$1.610
DVRPC
ERC
SECT5337
$0.200
$0.640
$1.600
$2.000
$2.000
$6.440
SectionVIPage2
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
DelawareRiverPortAuthorityofPennsylvaniaandNewJersey(DRPA)
PortAuthorityTransitCorporation(PATCO)ProjectDescriptions
($millions)
DBNUM:DR015
Embankment,Fence,andRetainingWallRestoration/Rehabilitation
Thisprogramwilladdressembankmentrestorationtopreventerosionandpreservedrainagecontrol.Projectincludesfencingandretainingwall
rehabilitationorreplacement.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: DRPA/PATCO
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M9(Exempt)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
ERC
DRPA
$0.100
$0.200
$0.200
$0.300
$0.300
$0.300
$0.300
$0.300
$2.000
DVRPC
ERC
SECT5307
$0.400
$0.800
$0.800
$1.200
$1.200
$1.200
$1.200
$1.200
$8.000
SectionVIPage3
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
DelawareRiverPortAuthorityofPennsylvaniaandNewJersey(DRPA)
PortAuthorityTransitCorporation(PATCO)ProjectDescriptions
($millions)
DBNUM:D0906/UPC:098013
InstallElevators,PATCO
InstallationofADAcompliantelevatorsatPATCOstations.
COUNTY: Camden
LEGISLATIVEDISTRICT: 5
MUNICIPALITY: CamdenCity
SPONSOR: DRPA/PATCO
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M8(Exempt)
Fund
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
DVRPC
EC
DRPA
$1.000
$1.000
$1.000
$0.700
$0.700
$4.400
DVRPC
EC
SECT5337
$4.000
$4.000
$4.000
$2.800
$2.800
$17.600
SectionVIPage4
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
DelawareRiverPortAuthorityofPennsylvaniaandNewJersey(DRPA)
PortAuthorityTransitCorporation(PATCO)ProjectDescriptions
($millions)
LindenwoldYardTieRenewal,LindenwoldViaduct,andOverallImprovements
DBNUM:DR044
Thisprojectincludestherep#lacementofties,railsandturnoutcomponentsatLindenwoldYardandreplacementofdirectfixationsystem,
includingtrackfasteners,anchors,concrete,andguardrailonLindenwoldviaducts.Alsoelectricalsystemsanddistributionofthethirdrailpower
withintheyardwillbemodifiedandimproved.Upto4.5milesoftrackand53turnoutswillbereplaced.
COUNTY: Camden
LEGISLATIVEDISTRICT: 4
MUNICIPALITY: LindenwoldBorough
SPONSOR: DRPA/PATCO
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M9(Exempt)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
ERC
DRPA
$0.500
$0.700
$0.500
$0.800
$0.800
$3.300
DVRPC
ERC
SECT5337
$2.000
$2.800
$2.000
$3.200
$3.200
$13.200
SectionVIPage5
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
DelawareRiverPortAuthorityofPennsylvaniaandNewJersey(DRPA)
PortAuthorityTransitCorporation(PATCO)ProjectDescriptions
($millions)
DBNUM:DR1501
PATCOInterlocking&TrackRehabilitation
Thisprogramincludesrehabilitationandreplacementofinterlockings,railbed,andotherrailimprovementstoensureoverallsystemsafety,
reliability,andminimalservicedisruptions.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: DRPA/PATCO
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M9(Exempt)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
EC
DRPA
$0.600
$0.600
$0.500
$0.500
$0.500
$2.700
DVRPC
EC
SECT5307
$2.400
$2.400
$2.000
$2.000
$2.000
$10.800
SectionVIPage6
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
DelawareRiverPortAuthorityofPennsylvaniaandNewJersey(DRPA)
PortAuthorityTransitCorporation(PATCO)ProjectDescriptions
($millions)
DBNUM:D1305/UPC:133450
PedestrianBridgeandTunnelRehabilitation
ThisprogramwillprovideforpreventiverepairsofpedestrianbridgesandtunnelsownedbyPATCO,includingmiscellaneoussteelrepair,concrete
repair,jointfiller,andspotpaint.StructurestoincludeHaddonfieldStationpedestrianbridge(overPATCO);AshlandStationpedestrianbridge
(overEveshamRoad);FerryStationWestpedestriantunnel;FerryStationEastpedestriantunnel;LindenwoldStationpedestriantunnel;Lindenwold
Stationpedestrianbridge.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: DRPA/PATCO
AIRQUALITYCODE(NONEXEMPT/EXEMPT): A2(Exempt)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
EC
DRPA
$0.300
$0.300
SECT5337
$1.200
$1.200
DVRPC
EC
SectionVIPage7
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
DelawareRiverPortAuthorityofPennsylvaniaandNewJersey(DRPA)
PortAuthorityTransitCorporation(PATCO)ProjectDescriptions
($millions)
DBNUM:DR034
PreventiveMaintenance
Thisprojectwillprovideforpreventivemaintenanceexpensespertainingtoactivitiesperformedonvehiclesandfacilities.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: DRPA/PATCO
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M3(Exempt)
Fund
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
DVRPC
ERC
DRPA
$0.395
$0.395
$0.520
$0.520
$0.520
$0.520
$0.520
$0.520
$3.910
DVRPC
ERC
SECT5307
$0.700
$0.700
$0.700
$0.700
$0.700
$0.700
$0.700
$0.700
$5.600
DVRPC
ERC
SECT5337
$0.600
$0.600
$1.000
$1.000
$1.000
$1.000
$1.000
$1.000
$7.200
SectionVIPage8
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
DelawareRiverPortAuthorityofPennsylvaniaandNewJersey(DRPA)
PortAuthorityTransitCorporation(PATCO)ProjectDescriptions
($millions)
DBNUM:DR038
RelocationofCenterTower/SCADAModernization
ThisprogramwillprovideforthefitoutofthesecondfloorofanexistingAdministration/CenterTowerbuildingatLindenwoldforthepurposeof
relocatingCenterTowerfromCamdentoLindenwold.Additionally,itwillprovideforthepurchaseandinstallationofnewequipmentfor
centralizedtraincontrol,tractionpowercontrol,andintegratedcustomerservice/communication.ThisprojectcontainsITSelementsand
SupervisoryControlandDataAcquisition(SCADA)modernization.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: DRPA/PATCO
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M8(Exempt)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
DVRPC
ERC
DRPA
$0.160
$0.075
$0.075
$0.310
SECT5337
$0.640
$0.225
$0.225
$1.090
DVRPC
ERC
SectionVIPage9
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
DelawareRiverPortAuthorityofPennsylvaniaandNewJersey(DRPA)
PortAuthorityTransitCorporation(PATCO)ProjectDescriptions
($millions)
DBNUM:DR019
SmokeandFireControl
Thisprogramwillprovidesmokeandfirecontrolforevacuationofpatronsinemergenciesandventilationimprovements.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: DRPA/PATCO
AIRQUALITYCODE(NONEXEMPT/EXEMPT): M6(Exempt)
Fund
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
DVRPC
ERC
DRPA
$0.060
$0.080
$0.160
$0.200
$0.100
$0.100
$0.100
$0.100
$0.900
DVRPC
ERC
SECT5337
$0.240
$0.320
$0.640
$0.800
$0.400
$0.400
$0.400
$0.400
$3.600
SectionVIPage10
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
DelawareRiverPortAuthorityofPennsylvaniaandNewJersey(DRPA)
PortAuthorityTransitCorporation(PATCO)ProjectDescriptions
($millions)
DBNUM:DR036
TransitEnhancements
Thisprogramwillsupporttransitenhancements.
COUNTY: Various
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: DRPA/PATCO
AIRQUALITYCODE(NONEXEMPT/EXEMPT): X12(Exempt)
Fund
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
DVRPC
ERC
DRPA
$0.014
$0.014
$0.014
$0.014
$0.014
$0.014
$0.014
$0.014
$0.112
DVRPC
ERC
SECT5307
$0.056
$0.056
$0.056
$0.056
$0.056
$0.056
$0.056
$0.056
$0.448
SectionVIPage11
SECTIONȱVIIȱ
ȱ
PANYNJȬPATHȱPROJECTȱDESCRIPTIONSȱ
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
PortAuthorityofNewYorkandNewJersey(PANYNJ)
PortAuthorityTransHudson(PATH)ProjectDescriptions
($millions)
DBNUM:PA1414/UPC:143090
Ductbanks
Fundingisprovidedforductbankreplacementprojects.ReplacementofthePATHDuctBanksystemassociatedpowercablesinTunnelsA,Tunnel
B,TunnelE1,andTunnelF1.Thetunnelswerecompletelyfloodedtothecrowninsomeareasandtheductbankswerepartiallyorcompletely
submergedinsaltwater.Theexistingductbankswereinfiltratedbysaltwatercausingthemtodeteriorateandduetotheageoftheductbanks,salt
waterwasabletoseepintowherethecablesarelocated.Theexistingductbanksmustbedemolishedandnewductbanksmustbebuiltinorderto
protectthepowercables.Theexistingductbankshavereachedtheendoftheirusefullifeandareinstagesofcollapse.Theconstructionofnew
concreteductbankswillprovidemoreprotectiontothecables,fromwaterandotherimpacts,allowingproperoperationofthesystem.
COUNTY: Hudson,Essex
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: PANYNJ
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT6,O9(Exempt)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
NJTPA
CON
PANYNJ
$12.340
$12.340
NJTPA
CON
SECT5324
$111.120
$111.120
SectionVIIPage1
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
PortAuthorityofNewYorkandNewJersey(PANYNJ)
PortAuthorityTransHudson(PATH)ProjectDescriptions
($millions)
ExchangePlace,NewportStation,andGroveSt.StationHeadHouseProtection
DBNUM:PA1422/UPC:154070
PANYNJwillreceivefundingtofloodproofmajorabovegroundPATHfacilitiesandequipmenttopreventfloodingofundergroundassets.These
siteswerefloodedduringHurricaneSandyandarecurrentlyprotectedbytemporarybarriers.Thetotaleligibleamountis$49,446,200.TheFTA
shareis$37,084,650.ThePAshareis$12,361,550.
COUNTY: Hudson
LEGISLATIVEDISTRICT: 31,33
MUNICIPALITY: JerseyCity
SPONSOR: PANYNJ
AIRQUALITYCODE(NONEXEMPT/EXEMPT): O9(Exempt)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
NJTPA
CON
PANYNJ
$12.362
$12.362
NJTPA
CON
SECT5324
$37.085
$37.085
SectionVIIPage2
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
PortAuthorityofNewYorkandNewJersey(PANYNJ)
PortAuthorityTransHudson(PATH)ProjectDescriptions
($millions)
DBNUM:PA1420/UPC:143150
RailRollingStockResiliency
Fundingisprovidedforrailrollingstockresiliency.ThefundswillbeusedtopurchasepropertyinJerseyCity,NJtoconstructnewstoragetrack
locationstostorerollingstockabovetheadvisoryfloodelevation.
COUNTY: Hudson
LEGISLATIVEDISTRICT: 31
MUNICIPALITY: JerseyCity
SPONSOR: PANYNJ
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT8(Exempt)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
NJTPA
CON
PANYNJ
$0.970
$0.970
NJTPA
CON
SECT5324
$8.770
$8.770
SectionVIIPage3
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
PortAuthorityofNewYorkandNewJersey(PANYNJ)
PortAuthorityTransHudson(PATH)ProjectDescriptions
($millions)
DBNUM:PA1418/UPC:143130
SignalsReplacementProgram
ThesefundswillbeusedtosupplementPANYNJfundingfortheongoingPATHSignalsReplacementProgram,limitedtoelementsthatareeligible
forfederalEmergencyRelieffundsbasedondamageincurredduringSuperstormSandy.Theoverallprojectscopereplacestheexistingsignals
system,incorporatingfederallycompliantAutomaticTrainControlcapabilityandincreasedfloodresiliency.
COUNTY: Hudson,Essex
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: PANYNJ
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT6,O9(Exempt)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
NJTPA
CON
PANYNJ
$2.300
$2.300
NJTPA
CON
SECT5324
$20.700
$20.700
SectionVIIPage4
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
PortAuthorityofNewYorkandNewJersey(PANYNJ)
PortAuthorityTransHudson(PATH)ProjectDescriptions
($millions)
DBNUM:PA1413/UPC:143080
Substations
Replacementandupgradesoffoursubstations,whichprovidepowertothePATHSystem.Fundingisprovidedforsubstationreplacement
projects.Thesesubstationsweredamagedbystormsurgesandflooding.Equipmentwasdamagedandnotoperationalandhasbeenreplacedor
refurbished.Theoutdoorswitchyardandbuildingwerealsounderminedduetostormsurge.Theexistingsubstationshavereachedtheendoftheir
usefullife.Thenewsubstationswillbeconstructedabovetheadvisoryfloodelevation.Landacquisitionisnecessaryinmultiplelocationssothatthe
currentsubstationcancontinuetooperateduringtheconstructionperiodwithoutanyinterruptiontoservice.TunnelA,TunnelB,TunnelE,and
COUNTY: Hudson,Essex
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: PANYNJ
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT6,O9(Exempt)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
NJTPA
CON
PANYNJ
$0.098
$0.098
NJTPA
CON
SECT5324
$0.885
$0.885
SectionVIIPage5
FY20162025STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
PortAuthorityofNewYorkandNewJersey(PANYNJ)
PortAuthorityTransHudson(PATH)ProjectDescriptions
($millions)
DBNUM:PA1419/UPC:143140
TrackworkRepairandRestoration
FundingisprovidedforTrackworkrepairandrestoration.Thefundswillbeusedtorepairorreplacetrackwork,ties,weldedrail,powerrail,
breakers,cabling,heaters,crossovers,drainageandrelatedequipmentdamagedbyfloodwatersandrelateddebrisaswellassaltwaterdamage.
COUNTY: Hudson,Essex
LEGISLATIVEDISTRICT: Various
MUNICIPALITY: Various
SPONSOR: PANYNJ
AIRQUALITYCODE(NONEXEMPT/EXEMPT): MT9,O9(Exempt)
FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 FY2025
Total
MPO
Phase
Fund
NJTPA
CON
PANYNJ
$17.442
$17.442
NJTPA
CON
SECT5324
$156.980
$156.980
SectionVIIPage6
SECTIONȱVIIIȱ
ȱ
TRANSPORTATIONȱAUTHORITIESȱ
PROJECTȱDESCRIPTIONSȱ
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
TransportationAuthoritiesProjectDescriptions
BurlingtonCountyBridgeCommission
BurlingtonBristolBridge
BridgeElectricalUpgrades
Thisprojectincludesthereplacementoftheexisting480voltpowerfeedfromthePennsylvaniapower
housetotheliftspanandtheinstallationofanewdatacenter(fitout).Thisprojectalsoincludesan
annualelectricalmaintenancecontract.
ROUTE(MILEPOSTS): NJ413
COUNTY: BurlingtonCounty
Cost($Millions)
Construction(Year)
$3.250
20162019
BridgeRehabilitation
Thisprojectincludesthereplacementoftheexistingspandecks,repairstotheexistingwalkway,railing
andladdersystem,paintingofthesteelstructures,rehabilitationofthebridgemountedstructures,
repairstotheexistingcounterweights,gatewayimprovementstheinstallationofwarninggates.This
projectalsoincludesanannualmaintenance.
ROUTE(MILEPOSTS): NJ413
COUNTY: BurlingtonCounty
Cost($Millions)
Construction(Year)
$25.475
20162019
RiversideDelancoBridge
BridgeElectricalUpgrades
Thisprojectincludesthereplacementoftheexistingelectricalsystemandthereplacementoftheexisting
submarinecable.Thisprojectalsoincludesanannualelectricalmaintenancecontract.
ROUTE(MILEPOSTS): CR543(10.8)
COUNTY: BurlingtonCounty
Cost($Millions)
Construction(Year)
$2.825
20162019
BridgeRehabilitation
Thisprojectincludesthereplacementandupgradeofexistingmechanicalequipmentandgateway
improvements.Thisprojectalsoincludesanannualmaintenancecontract.
ROUTE(MILEPOSTS): CR543
COUNTY: BurlingtonCounty
SectionVIIIPage1
Cost($Millions)
Construction(Year)
$2.975
20162019
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
TransportationAuthoritiesProjectDescriptions
BurlingtonCountyBridgeCommission
TaconyPalmyraBridge
BridgeElectricalUpgrades
Thisprojectincludestheinstallationofadatasystem,installationofatrafficcontrolsystem,replacement
ofexistingwiringconduitandjunctionboxesandtheinstallationofsolarpanels.Thisprojectalso
includesthereplacementoftheexistingsubmarinecablesandthefestooncables.Thisprojectalso
includesanannualelectricalmaintenancecontract.
ROUTE(MILEPOSTS): NJ73
Cost($Millions)
Construction(Year)
COUNTY: BurlingtonCounty
$13.125
20162019
BridgeRehabilitation
Thisprojectincludesthepaintingofthesteelstructures,installationofamaintenance/inspectiontraveler
system,replacementoftheexistingfendersystems,rehabilitationoftherackandpinionsystemandthe
installationofwarninggates.Thisprojectalsoincludesanannualmaintenancecontract.
ROUTE(MILEPOSTS): NJ73
Cost($Millions)
Construction(Year)
COUNTY: BurlingtonCounty
$28.025
20162019
SectionVIIIPage2
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
TransportationAuthoritiesProjectDescriptions
DelawareRiverandBayAuthority
CapeMayLewesFerry
RehabilitationofCapeMayLewesFerryapproachroads
Thisprojectwillincludeadjustmentstotheroadgeometryatthefacilityentrancealongwithre
constructionoftheexistingpavement,andupgradingsafetyfeaturestomeetpresentstandards(i.e.
guiderail,lighting,drainage,signage).
ROUTE(MILEPOSTS): US9(01)
COUNTY: CapeMayCounty
Cost($Millions)
Construction(Year)
$7.000
20162016
DelawareMemorialBridge
TollPlazaImprovements/ElectronicTollCollectionDMB
ThisprojectprovidesforanElectronicTollcollectionSystemreplacement.Upgradesarerequiredto
safeguardagainstunplannedinterruptionstothesystem,andtoprovideareliableandsafetollplaza.
Thisworkinvolves,butisnotlimitedto;completereplacementofallelectronictollequipment,
installationofanewintercomsystem,andothermiscellaneousimprovements.
ROUTE(MILEPOSTS): NJTurnpike
COUNTY: SalemCounty
SectionVIIIPage3
Cost($Millions)
Construction(Year)
$7.500
20152016
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
TransportationAuthoritiesProjectDescriptions
DelawareRiverJointTollBridgeCommissionAuthority
ScudderFallsBridge
I95ScudderFallsBridgeImprovement
UnderaMemorandumofAgreementthattheDelawareRiverJointTollBridgeCommission(DRJTBC)
enteredintowiththeNewJerseyDepartmentofTransportation(NJDOT)andthePennsylvania
DepartmentofTransportation(PennDOT),theprojectslimitsareI95fromPARoute332inBucks
County,PAtoBearTavernRoadinMercerCounty,NJ.
Thisprojectisplannedto:(1)WidenI95fromPA332totheinsidebyaddingonetravellaneineach
directionthroughutilizationofthecurrentgrassmedianalongthatroadwaystretch.(2)Reconfigurethe
TaylorsvilleRoadInterchangeinLowerMakefieldTwp.,PAbyeliminatingtheexistingwestern
southboundofframpandmodificationstoI95accelerationanddecelerationlanes.(3)Replacethe
existingoutdatedfourlaneScudderFallsBridgewithanentirelynewstructureontheupstreamside
withoverlappingofthecurrentbridgefootprint.Thenewstructurewouldhavesixlanesofthrough
traffic(threeineachdirection)withtwoauxiliarynorthboundlanesforentry/exittravelandoneauxiliary
southboundlaneentry/exittravel.Therecommendedoptioncallsforfullinsideandoutsideroadway
shouldersandbicycleandpedestrianfacilityontheupstreamsideofthebridgessouthboundspan;and
(4)ReconstructandreconfiguretheRoute29interchangethroughtheuseofroundabouts.Thisoption
wouldavoidtrafficsignals,resultinginafoldeddiamondinterchangewithtworoundaboutintersections
attherampswithI95.BypassesforNJRoute29northboundandsouthboundtrafficwouldberetained
andimprovedaccelerationanddecelerationlaneswillbeprovidedontoI95.
ROUTE(MILEPOSTS): I95Mercer(02)
COUNTY: MercerCounty
SectionVIIIPage4
Cost($Millions)
Construction(Year)
$328.600
20162018
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
TransportationAuthoritiesProjectDescriptions
DelawareRiverPortAuthorityofPennsylvaniaandNewJersey
BenjaminFranklinBridge
BridgeDeckResurfacing
Thisprojectincludesrehabilitationoftheapproachspansoneachsideofthebridge(Philadelphiaand
Camden);repairofsteelcomponents(columns/beams)withinthebridgesupportsystem;andadditional
drainageandelectricalimprovements.
ROUTE(MILEPOSTS): I676(3.84.75)
COUNTY: CamdenCounty
Cost($Millions)
Construction(Year)
$10.500
20182019
MasonryRehabilitation
Thisprojectwillrepair,rehabilitate,andpreservethegranitefacadesontheanchorages,piers,
abutments,andretainingwalls.Weatheringandagehavecausedthefacadestodeteriorate.
ROUTE(MILEPOSTS): I676(3.84.75)
COUNTY: CamdenCounty
Cost($Millions)
Construction(Year)
$5.800
20172019
ReplaceMoveableBarrier
Thisprojectwillreplaceexistingmoveablebarriersystem.Thebridgehasamoveablebarrierwallalong
thebridgeroadwaydeckthatseparatestheopposingdirectionsoftrafficandismovedmultipletimeson
adailybasisthroughouttheyearusingamoveablebarriermachine.
ROUTE(MILEPOSTS): I676(3.84.75)
COUNTY: CamdenCounty
Cost($Millions)
Construction(Year)
$7.200
20152019
TowerExpansionJointRehabilitation
Thisprojectwillperformstructuralrehabilitationofthemaintowerexpansionjoints.Thetypesofrepairs
includebearingreplacement,fingerplatereplacement,belowdecktransversewalkwayrehabilitation
cleaningandsealing,drainagerepairs,pinreplacement,andstructuralsteelrepairs.
ROUTE(MILEPOSTS): I676(3.84.75)
COUNTY: CamdenCounty
Cost($Millions)
Construction(Year)
$7.000
20162019
BetsyRossBridge
BridgeDeckResurfacing
Thisprojectwillmillandrepavetheexistingbridgeoverlay.Theapproachestothebridgewillbe
includedfromthetolltothewestofRichmondStreetalongwithdrainageandotherimprovements.
ROUTE(MILEPOSTS): NJ90(02)
COUNTY: CamdenCounty
SectionVIIIPage5
Cost($Millions)
Construction(Year)
$18.800
20152016
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
TransportationAuthoritiesProjectDescriptions
DelawareRiverPortAuthorityofPennsylvaniaandNewJersey
CommodoreBarryBridge
DeleadingandRepainting
ThisprojectwillentailtheblastcleaningandpaintingoftheentireCommodoreBarryBridgealongwith
substructureconcreterehabilitation.Underthisparticularproject,protectiveshieldingatsuspender
locationsandalongthemaincableareplannedtobeinstalled.
ROUTE(MILEPOSTS): US322(02.2)
COUNTY: GloucesterCounty
Cost($Millions)
Construction(Year)
$100.000
20152019
StructuralRehabilitationPhaseII
Thisprojectreplacestheoutofservicetransversemaintenancewalkwaysattachedtothebridge
approachpiers.Itwillalsoperformvariousconcreteandsteelrepairstothebridgeasidentifiedinrecent
biennialandinteriminspections.
ROUTE(MILEPOSTS): US322(02.2)
COUNTY: GloucesterCounty
SectionVIIIPage6
Cost($Millions)
Construction(Year)
$9.400
20152019
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
TransportationAuthoritiesProjectDescriptions
DelawareRiverPortAuthorityofPennsylvaniaandNewJersey
PATCO
EmbankmentRestoration
Thisprojectwillrehabilitateandrestoreembankmentsandretainingwallsatseverallocationsalong
PATCOrightofwaytopreventerosionandpreservedrainagecontroltomaintainthesysteminasafe
andfunctionalcondition.Theworkincludesstabilizingdeterioratedembankmentslopes,constructing
drainageimprovements,andrepairingretainingwallsbetweenCamdenandLinenwold.
ROUTE(MILEPOSTS):
COUNTY: CamdenCounty
Cost($Millions)
Construction(Year)
$8.550
20152017
HallandWayInterlockingRehabilitation
ThisprojectwillreplacethetrackandswitchesatHallandWayInterlockingsintheCamdensubway.
Theworkincludesreplacementofexistingturnoutsandcrossingdiamondsandinstallationofsignaland
electricalcomponents.
ROUTE(MILEPOSTS):
COUNTY: CamdenCounty
Cost($Millions)
Construction(Year)
$6.750
20152018
InstallElevatorsatStations
Thisprojectwillinstallnewelevatorsatsix(6)PATCOstationsnotcurrentlyservedbyelevators.The
locationsincludeAshland,Haddonfield,Westmont,Collingswood,CityHall,and12th13thandLocust
stations.AllstationsonthePATCOsystemwillbecompliantwiththeAmericanswithDisabilitiesAct
(ADA)whentheprojectiscompleted.
ROUTE(MILEPOSTS):
COUNTY: CamdenCounty
Cost($Millions)
Construction(Year)
$20.000
20152019
InterlockingandTrackRehabilitationPhaseII
ThiseffortistoperformarehabilitationofLocustHallWay,East/WestFerryandEastCrestInterlockings.
Theprojectwillinvolvetheremovalandreplacementofswitches,frogs,ties,andsignal,communication
andpowercabling.
ROUTE(MILEPOSTS):
COUNTY: CamdenCounty
Cost($Millions)
Construction(Year)
$11.250
20182019
LindenwoldTrackandViaduct
ThiseffortistoperformarehabilitationofthetracksinPATCOsLindenwoldYard.Theprojectwill
involvetheremovalandreplacementofindividualyardtracks,switches,signals,lighting,andviaduct
trackstructure.
ROUTE(MILEPOSTS):
COUNTY: CamdenCounty
SectionVIIIPage7
Cost($Millions)
Construction(Year)
$44.500
20152018
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
TransportationAuthoritiesProjectDescriptions
DelawareRiverPortAuthorityofPennsylvaniaandNewJersey
PATCO
RehabilitationofPATCOFleet
Thisprojectisoverhaulingthe120vehiclePATCOTransitCarfleet.Thefleetisover40yearsoldand
requiresincreasedmaintenanceforservicereliability.Anevaluationofthecarfleetdeterminedthata
majoroverhaultothefleetwaswarrantedandmorecosteffectivethannewcareprocurement.
ROUTE(MILEPOSTS):
COUNTY: CamdenCounty
Cost($Millions)
Construction(Year)
$194.000
20112017
RehabilitationofTrackStructureonViaductatWestmont
Thiseffortistoreplacetheexistingstructurewhichsecurestherailtotheviaducts.Theworkinvolves
thedemolitionoftheexistingconcreteplinths,anchoringsystemsandrailfasteningsystem.
ROUTE(MILEPOSTS):
COUNTY: CamdenCounty
Cost($Millions)
Construction(Year)
$14.500
20152017
ReplaceElectricalCablesinSubways
Replacepowerandsignalcommunicationcablesinsubways.Existingcablesinserviceareover40+years
andhaveexceededexpectedservicelife.Replacementisrequiredtoensurereliabilityoftractionpower
andsignalsystems.
ROUTE(MILEPOSTS):
COUNTY: CamdenCounty
Cost($Millions)
Construction(Year)
$9.500
20172019
TrackRehabilitationAcrossBenjaminFranklinBridge
ThisprojectisrehabilitatingthePATCOtrackstructureontheBenjaminFranklinBridge.The
rehabilitationworkincludestrackreplacement:power,signal,andcommunicationinfrastructure
improvements;andstructuralimprovements.
ROUTE(MILEPOSTS):
COUNTY: CamdenCounty
SectionVIIIPage8
Cost($Millions)
Construction(Year)
$102.800
20132016
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
TransportationAuthoritiesProjectDescriptions
DelawareRiverPortAuthorityofPennsylvaniaandNewJersey
WaltWhitmanBridge
DeleadingandRepaintingPhase3
Thisprojectwillentailthepaintingofthesuspensionspan,stiffeningtrusstowers,andanchoragesteel.
ROUTE(MILEPOSTS): I76(23.08)
COUNTY: GloucesterCounty
Cost($Millions)
Construction(Year)
$72.000
20152019
ReplacementofPADMSBoards
ThisprojectwillreplacetheexistingDynamicMessageSign(DMS)boardsofthePennsylvaniaapproach
tothebridge.TheseDMSareoutdatedandhaveoutlivedtheirlifeexpectancy.
ROUTE(MILEPOSTS): I76(23.08)
COUNTY: GloucesterCounty
SectionVIIIPage9
Cost($Millions)
Construction(Year)
$6.250
20172019
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
TransportationAuthoritiesProjectDescriptions
FHWAEasternFederalLandsHighwayDivision
NationalParkService,NortheastRegion
DelawareWaterGapNationalRecreationArea
Bridgerepair/rehab&1superstructurereplacement
ROUTE(MILEPOSTS):
COUNTY: SussexCounty
Cost($Millions)
Construction(Year)
$5.000
20162016
Cost($Millions)
Construction(Year)
$0.500
20162016
Cost($Millions)
Construction(Year)
$1.000
20162016
EdwinB.ForsytheNationalWildlifeRefuge
ReconstructHeadquartersParkingLot
ROUTE(MILEPOSTS):
COUNTY: AtlanticCounty
StatueofLibertyIsland
Repair/RehabofEllisIslandAccessBridge
ROUTE(MILEPOSTS):
COUNTY: HudsonCounty
SectionVIIIPage10
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
TransportationAuthoritiesProjectDescriptions
NewJerseyTurnpikeAuthority
NewJerseyTurnpike
Interchange14AImprovements
Theinterchangewillbereconfiguredtoaccommodateexistingtrafficvolumesandthefuturegrowthin
trafficvolumeresultingfromtheexpansionofanadjacentportfacilityandalargeresidential/commercial
development.
ROUTE(MILEPOSTS): I78(3.5)
COUNTY: HudsonCounty
Cost($Millions)
Construction(Year)
$400.000
20142018
Interchange15W/16WImprovements
Theinterchangerampswillbemodifiedtoimprovetrafficoperationsandsafety.Theimprovementswill
includewideningtherampfromthetollplazatothesouthboundTurnpiketoprovidefortwo
accelerationlanesandsigningimprovementstoaddresstruckoverturns.
ROUTE(MILEPOSTS): I95,NJTurnpikeWesternAlignment(108.8
112.7)
Cost($Millions)
Construction(Year)
$10.000
20142016
COUNTY: HudsonCounty,BergenCounty
NewarkBayHudsonCountyExtensionBridgeDeckReconstructionbetweenInterchange14Cand
JerseyAve
Thisprojectwillreplacethebridgedeckandbarrieralongthewestboundroadwaywithintheproject
limits.Inadditiontothereplacementofthebridgedeck,theapproachpavementtotheInterchange14C
tollplazawillberehabilitated,andlightinganddrainageimprovementswillbeincluded.
ROUTE(MILEPOSTS): I78(68.2)
COUNTY: HudsonCounty
Cost($Millions)
Construction(Year)
$44.000
20122016
NewarkBayHudsonCountyExtensionBridgeDeckReconstructionbetweenInterchanges14and
14A
Thebridgedeckisbeingreplacedintwophases.Thisprojectisthesecondphase.
ROUTE(MILEPOSTS): I78(1.52.9)
COUNTY: EssexCounty,HudsonCounty
SectionVIIIPage11
Cost($Millions)
Construction(Year)
$103.300
20162020
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
TransportationAuthoritiesProjectDescriptions
NewJerseyTurnpikeAuthority
GardenStateParkway
GreatEggHarborBridgeImprovements
AnewsouthboundspanwillbebuilttothewestoftheexistingsouthboundspanoverGreatEggHarbor
andDragChannel.Thenewbridgewillincludeamultiusepathway.Theexistingsouthboundspanwill
bedemolished.ThenearbyBeasley’sPointBridgeonRoute9willalsobedemolishedaspartofthis
project.
ROUTE(MILEPOSTS): GardenStateParkway(2728.8)
COUNTY: AtlanticCounty,CapeMayCounty
Cost($Millions)
Construction(Year)
$210.000
20132016
Interchange0Improvements
ThisprojectwillprovidereconstructionofthesignalizedintersectionoftheGardenSateParkwaywith
Route109,andoftheintersectionofRoute109withShoreDrive(CountyRoad621).
ROUTE(MILEPOSTS): GardenStateParkway
COUNTY: CapeMayCounty
Cost($Millions)
Construction(Year)
$10.500
20152016
Interchange105Improvements
ThisprojectisintendedtoimproveaccesstoandfromtheParkwayatInterchange105aswellassafety
andoperationsattheHopeRoad/NJRoute36intersection.Theimprovementsincludeanewsouthbound
connectionfromtheParkwayouterroadwaytoWaysideRoad,theadditionofasecondnorthbound
decelerationlanefromtheParkwayouterroadwaytoInterchange105andthereconstructionoftheHope
Road/NJRoute36intersection.
ROUTE(MILEPOSTS): GardenStateParkway(105.5106.6)
COUNTY: MonmouthCounty
Cost($Millions)
Construction(Year)
$40.000
20132017
Interchange125Improvements
Theinterchangewillbereconfiguredtoaccommodateexistingtrafficvolumesandthefuturegrowth
resultingfromthedevelopmentofthewaterfront.NewrampsfromtheParkwaysouthboundandtothe
ParkwaynorthboundwillprovidefullaccesstoChevalierAvenueandthewaterfrontdevelopment.
ROUTE(MILEPOSTS): GardenStateParkway(126126.4)
COUNTY: MiddlesexCounty
Cost($Millions)
Construction(Year)
$75.000
20142016
Interchange145Improvements
ThisprojectwillprovideforthereplacementoftheCentralAvenuebridgeovertheGSPmainlineto
providesufficientroomfora2lanesouthboundentranceramptotheSBGSPanda2lanenorthbound
exitrampfromtheNBGSPatInterchange145.
ROUTE(MILEPOSTS): GardenStateParkway(146.5147.5)
COUNTY: EssexCounty
SectionVIIIPage12
Cost($Millions)
Construction(Year)
$30.000
20142016
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
TransportationAuthoritiesProjectDescriptions
NewJerseyTurnpikeAuthority
GardenStateParkway
Interchange163Improvements
Inordertoimprovetrafficoperations,thisprojectwillrelocatetheexitsontoRoute17fromtheleftside
oftheroadtotherightsideoftheroadbyrealigningtheParkwayintotheexistingmedianinthevicinity
ofInterchange163.
ROUTE(MILEPOSTS): GardenStateParkway(162.5163.7)
COUNTY: BergenCounty
Cost($Millions)
Construction(Year)
$82.000
20142016
Interchange36,37&38improvements
ThisprojectwillimproveoperationsatInterchange36,37and38byprovidingfulldecelandaccellanes
atInterchange36withTiltonRoad,andeliminatingthesouthboundweavebetweentrafficenteringthe
GSPfromtheAtlanticCityExpresswayeastboundrampandthetrafficexitingtheGSPatInterchange37
withWashingtonAvenue.TheimprovementsincludewideningtheAtlanticCityExpresswayentrance
ramptotwolanes,addingonelaneineachdirectionandfullshouldersontheGSPtoaccommodatethe
wideningfromInterchange30to80improvementproject.Thecontractforthisprojectincludesthe
Parkwaywideningbetweenmileposts34.5and38.
ROUTE(MILEPOSTS): GardenStateParkway(3538)
COUNTY: AtlanticCounty
Cost($Millions)
Construction(Year)
$84.100
20142018
Interchange91Improvements(BurntTavernRoad)
AjointeffortbetweentheTurnpikeAuthorityandOceanCounty,thisprojectwillprovideramp
movementscurrentlymissingattheinterchange,reconstructionandsafetyimprovementstotheexisting
northboundramptollplaza,constructionoftwoextendedserviceroads,andimprovementstonearby
countyroadstosimplifythetrafficflowpatternandrelievecongestiononlocalroads.
ROUTE(MILEPOSTS): GardenStateParkway(92)
COUNTY: OceanCounty
Cost($Millions)
Construction(Year)
$4.800
20132016
Interchanges30to80widening(Phase3MP38toMP48)
Thethird,andfinal,phaseoftheGardenStateParkway(GSP)Wideningbetweenmileposts30and80
program.TheprojectwillwidentheNorthboundandSouthboundGSPmainlinefromtwolaneswith
nominalshoulderstothreelaneswithfullshoulders.Themajorityofthewideningwillbeintheinside
median.Theproposedhighwaytypicalsectionwillprovidea10ft.leftshoulder,three12ft.thrutravel
lanesanda12ft.rightshoulder.Otherimprovementsincludenewoverheadguidesigns,ramplighting,
guiderail,utilityrelocations,andretentionswales.ExceptforaneasementoverthePennReading
SeashoreLineatmilepost39.9,theproposedwideningwillbeaccommodatedwithintheexistingGSP
rightofway.Constructionalongthemainlinewillbeaccomplishedinmultiplestages.Twolanesof
travel,ineachdirection,willbemaintainedontheGSPduringpeaktraveltimes.
ROUTE(MILEPOSTS): GardenStateParkway(3848)
COUNTY: AtlanticCounty
SectionVIIIPage13
Cost($Millions)
Construction(Year)
$84.400
20142017
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
TransportationAuthoritiesProjectDescriptions
PennsylvaniaTurnpikeAuthority
I95/I195/I295
I95RedesignationinNewJersey
ThisprojectprovidesforNJDOTsigningchanges,inNewJersey,toaccommodatetheredesignation
associatedwiththeI95interchangeprojectinPennsylvania.
ROUTE(MILEPOSTS):
COUNTY: MercerCounty
Cost($Millions)
Construction(Year)
$2.000
20172017
PATurnpike/I95Interchange
PATurnpike/I95InterchangeProject
TheinterstatecompletionprojectwillconnectI95andI276inPennsylvania,facilitatearevisedrouting
ofI95inPennsylvaniaandNewJersey,andmakeI95continuousalongtheeastCoastfromFloridato
Maine.
Stage1oftheprojectinvolvestheconstructionoftheI95mainlineflyoversoftheinterchangebetweenI
95andthePATurnpike,anewmainlinetollplazawestofthisinterchange,replacementoftheexisting
RiverBridgetollplazawithanallelectronic(AET)onroadtollfacilityinthewestbounddirection,and
removaloftheexistingUS13interchangetollfacility.ThisprojectisintegraltotheDelawareValley
FreightCorridorsinitiative.
Stage1constructionisbrokendownintoseveralcontractsandexpectedcompletionisin2018.
CompletedworkincludestheoverheadbridgescarryingGallowayandBristolOxfordValleyRoadsover
theTurnpike;theoverheadbridgecarryingRichlieuRoad,thePATurnpikesNorthwestQuadrant
WetlandMitigationSite;advancedIntelligentTransportationSystemdeployment;andconstructionof
thenewmainlinetollplazabetweenRichlieuandGallowayRoads.
TheI95mainlineflyoverconnectionsoftheInterchangewillbeconstructedsothatI95canbe
redesignatedontotheexistingPATurnpiketotheNJTurnpike.Atthattime,I95northoftheTurnpike
wouldbecomeI195.Signing,lightingandtrafficoperationsworkwillbedoneinphasesthroughoutthe
constructionperiodinordertomanagetrafficduringandafterconstruction.
Stage1willoperateindependentlyuntilfuturestatesarecompleted.Noadditionalthroughlanesare
beingconstructedonI95aspartofStage1.ThetotalestimatedcostofPhase1(allphases)is$424million.
ROUTE(MILEPOSTS): I95Mercer
COUNTY: BucksCounty
SectionVIIIPage14
Cost($Millions)
Construction(Year)
$424.000
20102018
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
TransportationAuthoritiesProjectDescriptions
PortAuthorityofNewYork&NewJersey
BayonneBridge
Route440,BayonneBridgeNavigationalClearanceProject
ThisprojectentailsincreasingtheairdraftoftheBayonneBridgebyraisingtheroadwaywithinthe
existingarchspanby64feet,from151feetto215feet.Additionally,thenewroadwaywillbewider(to
betterconformtoAASHTOstandards),andthe6footwidepedestrianwalkwaywillbewidenedtoa12
footwidesharedusepathaccommodatingpedestriansandcyclists.Anewhigherroadwaywillbe
constructedwithintheexistingconstraintsonthemainspan.Theexistingapproachroadswillbe
demolishedandnew,widerapproacheswillbeconstructed.Thenewapproacheswillhave8footwide
outsideshouldersand4footwideinsideshoulders.Duringconstruction,themedianwillberemovable
channelizerposts.Oncethefullbridgeiscompleted,jerseybarrierswillbeusedinthemedian.The
existingtollplazawillbedemolishedandreplaced.Estimateddurationofconstructionisabout3.5years,
duringwhichtimetrafficwillbereducedtoone12.5footlaneperdirection,withnightlyroadclosures
and8fullweekendclosuresperyear.ITSsignstructures(includingVMS,VSLS,CCTVandroadsensors)
willbeconstructedalongtherehabilitatedroadway.
ROUTE(MILEPOSTS): NJ440(1818.82)
COUNTY: HudsonCounty
SectionVIIIPage15
Cost($Millions)
Construction(Year)
$1,000.000
20132017
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
TransportationAuthoritiesProjectDescriptions
PortAuthorityofNewYork&NewJersey
GoethalsBridge
Route278,GoethalsBridgeReplacement
ReplacementoftheexistingGoethalsBridgebetweenElizabeth,NJandStatenIsland,NYalongtheI278
Corridor.ThePortAuthorityisadvancingplansforreplacementoftheexistingbridgeopenedin1928.
Thepreferredalternativeisafullreplacementonanalignmentimmediatelytothesouthofthecurrent
bridge,tyingintotheexistingroadwayconnectionsinbothstates.Theexistingbridgewillremainin
serviceduringconstructionofthenewcrossing,andwillbedemolishedafterthereplacementbridge
opens.
Theexistingstructurehastwo10footwidelanesineachdirection(eastboundandwestbound)separated
byamedian,withnoshoulders,andnopedestrian/bikewayaccommodation.Theexistingfreeflow
speedis45mph.Thenewbridgewillincludeseparateroadwaydecksforeastboundandwestbound
travel,eachprovidingthree12–footwidelanes,one12footwideoutershoulder,andone5footwide
innershoulder.
Thenewbridgewillalsoincludeapedestrian/bikeway.Projectspecificationsassurethedesignwillnot
precludeadditionoffuturemasstransitserviceacrossthebridge(byprovidingsufficientrightofway
betweentheeastandwestboundroadwaysforapotentialfuturetransitsystem).Thefreeflowspeedfor
thenewbridgewillbe60mph.Thenewstructurealsowillincorporateseismicprotection,security,and
comprehensiveITSfeatures.Totalprojectlengthisapproximately1.5miles,betweenNJTurnpikeand
theStatenIslandExpressway.
ConsistentwiththePortAuthoritycommitmentforselffinancingitssurfacetransportationprojects,the
projecthasbeenincludedintheNJTPATIPAppendixandintheregionaltransportationnetworkfor
conformitypurposes.Subsequently,theagency’sBoardofCommissionersauthorizedapublicprivate
partnershipoptiontoimplementtheprojectthroughaninnovativeDesignBuildFinanceMaintain
(DBFM)approach.PANYNJwassuccessfulinsecuringafederalTIFIAloanof$473.674Millionaspartof
theP3bridgedeveloper’sfinancingpackage.TheprojecthasbeenincludedintheTIPfortheNewYork
MetropolitanTransportationCouncil,andintheNewYorkStateSTIP.Theprojectcurrentlyisunder
construction.
ROUTE(MILEPOSTS): I278(1.342)
COUNTY: UnionCounty
SectionVIIIPage16
Cost($Millions)
Construction(Year)
$1,500.000
20142018
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
TransportationAuthoritiesProjectDescriptions
SouthJerseyTransportationAuthority
AtlanticCityAirport
AtlanticCityExpressway/AtlanticCityAirportDirectConnector
DesignandconstructionofdirectconnectroadwayfromtheAtlanticCityExpresswaytotheAtlantic
CityAirport
ROUTE(MILEPOSTS): AtlanticCityExpressway(8.79.2)
COUNTY: AtlanticCounty
Cost($Millions)
Construction(Year)
$50.000
20142016
AtlanticCityExpressway
ElectronicTolling
Thisprojectwillupgradethetollcollectionsystembyusinginnovativetechnologythroughelectronic
tolling.
ROUTE(MILEPOSTS): AtlanticCityExpressway(044)
COUNTY: AtlanticCounty,CamdenCounty,GloucesterCounty
Cost($Millions)
Construction(Year)
$50.000
20182018
ThirdLaneWidening(bothdirections)
ConstructiontowidentheAtlanticCityExpresswaywithathirdlaneinbothdirections.
ROUTE(MILEPOSTS): AtlanticCityExpressway(3144)
COUNTY: AtlanticCounty,CamdenCounty,GloucesterCounty
SectionVIIIPage17
Cost($Millions)
Construction(Year)
$150.000
20172020
SECTIONȱIXȱ
ȱ
EARMARKȱPROJECTȱLISTȱ
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
EARMARKPROJECTLIST
MPO/COUNTY
EarmarkID
PublicLaw
Federal
Appropriation
Obligations
Balance
$700,590.00
$478,060.00
$151,251.97
$700,590.00
$478,060.00
$151,251.97
$477,762.88
$353,756.00
$75,549.00
$477,762.88
$353,756.00
$75,549.00
$498,900.00
$0.00
$498,900.00
$498,900.00
$0.00
$498,900.00
DVRPC/Camden
ClementsBridgeRoadStreetscape(CR573),Phases13
D0801
088007
NJ207
10959
Totals
LaurelSpringsStreetscapeImprovementProject
D0901
098007
NJ182
10959
Totals
DVRPC/Mercer
PrincetonTownshipRoadwayImprovements
HP01010
018170
NJ078
106346
Totals
Route29Boulevard,CassStreettoNorthofCalhounStreet(SouthernSection)
02396B
023962
NJ252
10959
$4,005,900.00
$1,648,135.00
$1,950,533.00
NJ267
10959
$2,505,854.00
$460,629.00
$1,804,719.00
NJ289
110161
$735,000.00
$716,957.00
$18,043.00
$7,246,754.00
$2,825,721.00
$3,773,295.00
Totals
Route29Boulevard,NorthofCalhounStreettoSullivanWay(NorthernSection)
02396A
023961
NJ252
10959
$4,005,900.00
$1,648,135.00
$1,950,533.00
NJ267
10959
$2,505,854.00
$460,629.00
$1,804,719.00
NJ289
110161
$735,000.00
$716,957.00
$18,043.00
$7,246,754.00
$2,825,721.00
$3,773,295.00
$940,149.00
Totals
Route29,DelawareRiverPedestrian/BikePath,StacyParktoAssunpinkCreek
551B
950281
04NJ001
NJ041
TCSP2004
$940,149.00
$0.00
105178
$4,228,536.00
$4,182,144.90
$46,391.10
$5,168,685.00
$4,182,144.90
$986,540.10
Totals
SectionIXPage1
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
EARMARKPROJECTLIST
MPO/COUNTY
EarmarkID
PublicLaw
Federal
Appropriation
Obligations
Balance
111117
$973,834.00
$0.00
$973,834.00
$973,834.00
$0.00
$973,834.00
$1,602,360.00
$0.00
$1,439,840.00
$1,602,360.00
$0.00
$1,439,840.00
NJTPA/Bergen
BergenCounty,SpecializedBusTransit
N1129
118036
NJ306
Totals
HackensackRiverWalkway
07368
073680
NJ201
10959
Totals
Route17,WilliamsAvenuetoI80
103A2
098021
NJ093
108199
$1,000,000.00
$882,071.00
$60,267.00
NJ128
10959
$4,406,490.00
$0.00
$3,959,560.00
NJ159
10959
$9,614,161.00
$0.00
$8,639,042.00
$15,020,651.00
$882,071.00
$12,658,869.00
$192,283.00
$0.00
$172,780.00
$192,283.00
$0.00
$172,780.00
$600,885.00
$451,772.00
$88,168.00
$600,885.00
$451,772.00
$88,168.00
$486,917.00
$0.00
$486,917.00
$486,917.00
$0.00
$486,917.00
$1,201,770.00
$679,199.00
$400,680.00
$1,201,770.00
$679,199.00
$400,680.00
Totals
NJTPA/Essex
EdisonNationalHistoricSite,TrafficImprovements
08447
084470
NJ224
10959
Totals
MillburnTownwalk,adjacenttotheWestBranchoftheRahwayRiver
07329
073290
NJ155
10959
Totals
NorthBroadStreetRedevelopmentProject
N1126
118033
NJ297
111117
Totals
RahwayRiverCorridorGreenwayBicycleandPedestrianPath
04390
043900
NJ121
10959
Totals
SectionIXPage2
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
EARMARKPROJECTLIST
MPO/COUNTY
EarmarkID
PublicLaw
Federal
Appropriation
Obligations
Balance
10959
$1,602,360.00
$0.00
$1,439,840.00
$1,602,360.00
$0.00
$1,439,840.00
$1,964,400.00
$0.00
$1,964,400.00
$1,964,400.00
$0.00
$1,964,400.00
NJTPA/Hudson
6thStreetViaductPedestrianandBicyclePathway
06322
063220
NJ241
Totals
CanalCrossingInfrastructurePlanningProject
N1102
TIGERII
111117
Totals
IntermodalAccessImprovementstothePeninsulaatBayonne
09344
093440
NJ037
105178
$3,061,663.00
$3,036,714.00
$24,949.00
NJ147
10959
$1,602,360.00
$0.00
$1,439,840.00
$4,664,023.00
$3,036,714.00
$1,464,789.00
$841,239.00
$0.00
$755,916.00
$841,239.00
$0.00
$755,916.00
Totals
McGinleySquareParkingFacility
06321
063210
NJ237
10959
Totals
PeninsulaatBayonneHarbor,IntermodalAccessImprovements
10393
103930
NJ037
105178
$3,061,663.00
$3,036,714.00
$24,949.00
NJ147
10959
$1,602,360.00
$0.00
$1,439,840.00
$4,664,023.00
$3,036,714.00
$1,464,789.00
$299,949.00
$0.00
$299,949.00
$299,949.00
$0.00
$299,949.00
Totals
UnionCity,StreetImprovements&TrafficSignalReplacement
08436
084360
NJ305
111117
Totals
Route280,HarrisonTownshipOperationalImprovements
04305
043050
NJ210
10959
$8,011,800.00
$904,224.00
$6,294,976.00
NJ249
10959
$2,002,950.00
$0.00
$1,799,301.00
NJ265
10959
$3,007,024.00
$0.00
$2,718,416.00
NJA39
IMD2005
$661,333.00
$0.00
$661,333.00
NJA49
2005
$1,282,000.00
$0.00
$1,282,000.00
$14,965,107.00
$904,224.00
$12,756,026.00
Totals
SectionIXPage3
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
EARMARKPROJECTLIST
MPO/COUNTY
EarmarkID
Federal
Appropriation
Obligations
Balance
$3,204,720.00
$0.00
$2,339,681.00
$3,204,720.00
$0.00
$2,339,681.00
10959
$801,180.00
$652,901.00
$67,000.00
10959
$1,001,475.00
$619,896.97
$280,002.03
$1,802,655.00
$1,272,797.97
$347,002.03
PublicLaw
NJTPA/Hudson
Route440,NJTurnpikeInterchangeUpgrade,JerseyCity
09350
093500
NJ220
10959
Totals
Route440/1&9,BoulevardthroughJerseyCity
06307
063070
NJ130
NJ243
Totals
SectionIXPage4
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
EARMARKPROJECTLIST
MPO/COUNTY
EarmarkID
PublicLaw
Federal
Appropriation
Obligations
Balance
NJ038
105178
$3,075,299.00
$2,020,187.00
$1,055,112.00
NJ215
10959
$2,433,584.25
$0.00
$2,186,187.08
$5,508,883.25
$2,020,187.00
$3,241,299.08
$801,180.00
$0.00
$719,921.00
$801,180.00
$0.00
$719,921.00
$1,602,360.00
$0.00
$1,439,840.00
$1,602,360.00
$0.00
$1,439,840.00
NJTPA/Middlesex
CarteretFerryServiceTerminal
06316
063160
Totals
EastCoastGreenway,Middlesex/UnionCounties
04327B
043272
NJ156
10959
Totals
RobertWoodJohnsonUniversityHospitalParkingFacility
08449
084490
NJ235
10959
Totals
SouthAmboyIntermodalCenter
98541
985410
NJ047
105178
$12,301,193.00
$2,936,843.00
$9,364,350.00
NJA17
TCSP2002
$991,307.00
$944,500.00
$46,807.00
NJA4
TCSP2000
$217,750.00
$0.00
$217,750.00
$13,510,250.00
$3,881,343.00
$9,628,907.00
$10,000,000.00
$0.00
$9,061,390.00
$10,000,000.00
$0.00
$9,061,390.00
$4,005,900.00
$2,110,779.00
$1,488,822.00
$4,005,900.00
$2,110,779.00
$1,488,822.00
Totals
TremleyPointConnectorRoad
9324A
058050
NJ272
10959
Totals
Route440,HighStreetConnector
99379
993790
NJ165
10959
Totals
SectionIXPage5
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
EARMARKPROJECTLIST
MPO/COUNTY
EarmarkID
PublicLaw
Federal
Appropriation
Obligations
Balance
111117
$749,872.00
$0.00
$749,872.00
$749,872.00
$0.00
$749,872.00
$801,180.00
$0.00
$719,921.00
$801,180.00
$0.00
$719,921.00
NJTPA/Monmouth
EnglishtownBorough,RoadImprovements
N1128
118035
NJ300
Totals
LaurelAvenueNJTransitBridgeReplacement
08379
083790
NJ118
10959
Totals
Route35,EatontownBoroughDowntownRedevelopment
98539B
068004
NJ074
106346
$498,900.00
$0.00
$498,900.00
NJ075
106346
$498,900.00
$390,195.00
$108,705.00
$997,800.00
$390,195.00
$607,605.00
Totals
Route35,EatontownBoroughIntersectionImprovements
98539A
068003
NJ074
106346
$498,900.00
$0.00
$498,900.00
NJ075
106346
$498,900.00
$390,195.00
$108,705.00
$997,800.00
$390,195.00
$607,605.00
$801,180.00
$0.00
$719,921.00
$801,180.00
$0.00
$719,921.00
$3,204,720.00
$705,347.00
$2,174,334.00
$3,204,720.00
$705,347.00
$2,174,334.00
$400,590.00
$269,012.00
$90,948.00
$400,590.00
$269,012.00
$90,948.00
Totals
NJTPA/Morris
LongValleySafetyProject
NP0301
058016
NJ120
10959
Totals
NJTPA/Ocean
WesternBoulevardExtension
10392
103920
NJ228
10959
Totals
NJTPA/Passaic
BelmontAvenueGatewayCommunityEnhancementProject(CR675)
07356
073560
NJ232
10959
Totals
SectionIXPage6
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
EARMARKPROJECTLIST
MPO/COUNTY
EarmarkID
PublicLaw
Federal
Appropriation
Obligations
Balance
NJ219
10959
$845,245.00
$0.00
$759,515.00
$845,245.00
$0.00
$759,515.00
$2,403,540.00
$1,938,594.00
$221,166.00
NJTPA/Somerset
LehighRailLineSeparation
08445
084450
Totals
Route22,SustainableCorridorLongtermImprovements
03318
033180
NJ166
10959
NJ294
1118
$570,000.00
$0.00
$570,000.00
NJ301
111117
$1,249,786.00
$0.00
$1,249,786.00
$4,223,326.00
$1,938,594.00
$2,040,952.00
$801,180.00
$0.00
$719,921.00
$801,180.00
$0.00
$719,921.00
Totals
NJTPA/Union
EastCoastGreenway,Middlesex/UnionCounties
04327B
043272
NJ156
10959
Totals
NorthAvenueCorridorImprovementProject(NACI)
06318F
088005
NJ027
105178
$2,050,199.00
$2,048,332.83
$1,866.17
NJ200
10959
$4,566,726.00
$0.00
$4,103,546.00
NJ258
10959
$1,001,475.00
$0.00
$899,667.00
NJ272
10959
$10,000,000.00
$0.00
$9,061,390.00
$17,618,400.00
$2,048,332.83
$14,066,469.17
$60,088.00
$0.00
$53,993.00
$60,088.00
$0.00
$53,993.00
Totals
NorthAvenue,ElizabethPedestrianandBicycleProject
08439
084390
NJ167
10959
Totals
TremleyPointConnectorRoad
9324A
058050
NJ272
10959
Totals
$10,000,000.00
$0.00
$9,061,390.00
$10,000,000.00
$0.00
$9,061,390.00
NJTPA/Various
NJUndergroundRailroad
09345
093450
NJ194
10959
$256,378.00
$0.00
$230,375.00
NJ256
10959
$100,148.00
$0.00
$89,967.00
$356,526.00
$0.00
$320,342.00
Totals
SectionIXPage7
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
EARMARKPROJECTLIST
MPO/COUNTY
EarmarkID
PublicLaw
Federal
Appropriation
Obligations
Balance
$1,602,360.00
$273,123.00
$1,166,717.00
$1,602,360.00
$273,123.00
$1,166,717.00
SJTPO/CapeMay
MiddleThorofare,MillCreek,UpperThorofareBridges,CR621
S0002
950126
NJ226
10959
Totals
SectionIXPage8
SECTIONX
FY20162017
STUDY&DEVELOPMENTPROGRAM
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:N1402
ClayStreetBridgeoverthePassaicRiver
ThisstudywilllookatalternativesofanexistingmovableswingbridgeatClayStreetwhichis
structurallydeficient.
COUNTY: Hudson,Essex
MUNICIPALITY: NewarkCity,EastNewark
MILEPOSTS: 0.00.07
STRUCTURENO.: 0700H01
LEGISLATIVEDISTRICT: 28,29,32
SPONSOR: Hudson
ASSETMANAGEMENTCATEGORY: LocalSystemSupport:LocalBridges
MPO
Phase
Year
NJTPA
LCD
2016
DB#:14350
UPC#:143500
CR514(AmwellRoad),BridgeoverD&RCanal
TheCR514(AmwellRoad)BridgeoverD&RCanalisafourspantimberbridge,originally
constructedin1953.Thebridgecarriestwolanesoftrafficwithacurbtocurbwidthof28.6feet.
Thebridgeisstructurallydeficientduetotheseriousconditionofthestructureandlowinventory
ratings.Thesubstructureisinpoorconditionwithheavilydeterioratedpiles,sectionlossatthe
timbersheeting,andmissingsheeting.Itisfunctionallyobsoleteduetothesubstandarddeck
geometry.
COUNTY: Somerset
MUNICIPALITY: FranklinTwp
MILEPOSTS: 16.72
STRUCTURENO.: 3000165
LEGISLATIVEDISTRICT: 17
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: BridgeAssets:BridgeRehabandReplacement
MPO
Phase
Year
NJTPA
CD
2016
SectionXPage1
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:14417
UPC#:144170
CR531(ParkAvenue),BridgeoverLehighValleyMainLine
InitiatedbytheBridgeManagementSystem,thisprojectwillrehabilitate/replacethebridge.The
bridgedeckandsuperstructureareinseriouscondition.Thebridgeisalsofunctionallyobsolete
duetoitsdeckgeometry.
COUNTY: Middlesex
MUNICIPALITY: SouthPlainfieldBoro
MILEPOSTS: 5.04
STRUCTURENO.: 1253163
LEGISLATIVEDISTRICT: 18
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: BridgeAssets:BridgeRehabandReplacement
MPO
Phase
Year
NJTPA
CD
2016
DB#:15322
UPC#:153220
Delaware&RaritanCanalBridges
InitiatedbytheBridgeManagementSystem,thisprojectprovidesforConceptDevelopmentstudies
onthefollowingstructuresalongtheDelawareandRaritanCanal:CarnegieRoad,Bridgeover
D&RFeederCanal;CountyRoute571(WashingtonRoad),BridgeoverD&RCanal;LandingLane
(CR609),BridgeoverD&RCanal;Route206,BridgeoverD&RFeederCanal;HermitageAvenue,
BridgeoverD&RFeederCanal;RiverDrive,BridgeoverD&RFeederCanal;BridgeoverD&R
FeederCanalatLockNo.3;CoryellStreet,BridgeoverD&RFeederCanal;CR533(QuakerRoad),
BridgeoverD&RCanal;ManvilleCauseway(CR623),BridgeoverD&RCanal;ChapelDriveatCR
623,BridgeoverD&RCanal.Theprojectalsoprovidesemergencysuperstructurereplacementand
substructurerehabilitationforCR518(GeorgetownFranklinRd),BridgeoverD&RCanalandan
emergencytotalstructurereplacementofCR514(AmwellRoad),BridgeoverD&RCanal.
COUNTY: Mercer,Hunterdon,Middlesex,Somerset
MUNICIPALITY: Various
MILEPOSTS: N/A
STRUCTURENO.: Various
LEGISLATIVEDISTRICT: 15,16,17
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: BridgeAssets:BridgeRehabandReplacement
MPO
Phase
Year
DVRPC
CD
2016
NJTPA
CD
2016
SectionXPage2
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:15323
UPC#:153230
F.R.E.C.AccessRoad,BridgeoverTomsRiver
InitiatedbytheBridgeManagementSystem,thisprojectwillrehabilitate/replacethebridge.The
structureisstructurallydeficientandfunctionallyobsolete.Theoverallconditionofthestructureis
critical.
COUNTY: Ocean
MUNICIPALITY: JacksonTwp
MILEPOSTS: 0.30
STRUCTURENO.: 3489001
LEGISLATIVEDISTRICT: 12
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: BridgeAssets:BridgeRehabandReplacement
MPO
Phase
Year
NJTPA
CD
2016
DB#:N1405
GardenStateParkwayInterchange83Improvements
ThisstudywillassessalternativestoprovideanewsouthboundGardenStateParkwayexitto
CountyRoute571andimprovementsnearbyinterchangeofRoute9andCR571.
COUNTY: Ocean
MUNICIPALITY: TomsRiverTwp
MILEPOSTS: CR571:6.056.10&GSP:84.4084.80
STRUCTURENO.:
LEGISLATIVEDISTRICT: 10
SPONSOR: OceanCounty
ASSETMANAGEMENTCATEGORY: LocalSystemSupport:LocalRoadwayImprovements
MPO
Phase
Year
NJTPA
LCD
2016
SectionXPage3
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:14423
UPC#:144230
GroveAvenue,BridgeoverPortReadingRR
InitiatedbytheBridgeManagementSystem,thisprojectwillrehabilitate/replacethebridge.The
bridgehasbeendeterminedtobestructurallydeficientandfunctionallyobsolete.Thebridgeisa
120fttimberstructuresupportedbytimberpiers,builtin1900.
COUNTY: Middlesex
MUNICIPALITY: MetuchenBoro
MILEPOSTS: 0.87
STRUCTURENO.: 1252162
LEGISLATIVEDISTRICT: 18
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: BridgeAssets:BridgeRehabandReplacement
MPO
Phase
Year
NJTPA
CD
2016
DB#:NS9603
UPC#:950606
MonmouthCountyBridgeS31(AKABinghamAvenueBridge)over
NavesinkRiver,CR8A
BridgeS31carriesCR8AacrosstheNavesinkRiverbetweenMiddletownandRumson.Itisa
primaryaccessroutetothedenselypopulatedareasnorthandsouthoftheriver.Thestructureis
inpoorconditionandthemajorbridgecomponentsaredeteriorating.Thebridgeiseligibleforthe
NationalRegisterofHistoricPlaces.Possibleimprovementssuchasrehabilitationorreplacement
ofthestructurewillbestudied.
COUNTY: Monmouth
MUNICIPALITY: MiddletownTwp,RumsonBoro
MILEPOSTS: N/A
STRUCTURENO.: 1300S31
LEGISLATIVEDISTRICT: 13
SPONSOR: MonmouthCounty
ASSETMANAGEMENTCATEGORY: LocalSystemSupport:LocalBridges
MPO
Phase
Year
NJTPA
LCD
2016
SectionXPage4
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:15333
UPC#:153330
SignStructureReplacementContract20161
Someofthesesignstructurehaddevelopedfatiguecracksandareinhazardousconditionto
vehiculartraffic.OthersonthelistswereconstructedusingAluminummaterial.Ithasbeen
determinedthatthesetypesofstructuresaremorepronetofatiguethanoriginallyknownandare
neartheendoftheirservicelife.
COUNTY: Various
MUNICIPALITY: Various
MILEPOSTS: N/A
STRUCTURENO.: Various
LEGISLATIVEDISTRICT: Various
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: BridgeAssets:BridgeCapitalMaintenance
MPO
Phase
Year
Statewide
CD
2016
DB#:15334
UPC#:153340
SignStructureReplacementContract20162
InitiatedbytheBridgeManagementSystem,thisprojectwillincluderemovalofexistingsign
structuresandreplacementwithnewsignstructuresthatmeetallcurrentstandards.
COUNTY: Various
MUNICIPALITY: Various
MILEPOSTS: N/A
STRUCTURENO.: Various
LEGISLATIVEDISTRICT: Various
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: BridgeAssets:BridgeCapitalMaintenance
MPO
Phase
Year
Statewide
CD
2016
SectionXPage5
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:15335
UPC#:153350
SignStructureReplacementContract20163
Someofthesesignstructurehaddevelopedfatiguecracksandareinhazardousconditionto
vehiculartraffic.OthersonthelistswereconstructedusingAluminummaterial.Ithasbeen
determinedthatthesetypesofstructuresaremorepronetofatiguethanoriginallyknownandare
neartheendoftheirservicelife.
COUNTY: Various
MUNICIPALITY: Various
MILEPOSTS: N/A
STRUCTURENO.: Various
LEGISLATIVEDISTRICT: Various
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: BridgeAssets:BridgeCapitalMaintenance
MPO
Phase
Year
Statewide
CD
2016
DB#:15336
UPC#:153360
SignStructureReplacementContract20164
InitiatedbytheBridgeManagementSystem,thisprojectwillincluderemovalofexistingsign
structuresandreplacementwithnewsignstructuresthatmeetallcurrentstandards.
COUNTY: Various
MUNICIPALITY: Various
MILEPOSTS: N/A
STRUCTURENO.: Various
LEGISLATIVEDISTRICT: Various
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: BridgeAssets:BridgeCapitalMaintenance
MPO
Phase
Year
Statewide
CD
2016
SectionXPage6
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:15337
UPC#:153370
SignStructureReplacementContract20165
InitiatedbytheBridgeManagementSystem,thisprojectwillincluderemovalofexistingsign
structuresandreplacementwithnewsignstructuresthatmeetallcurrentstandards.
COUNTY: Various
MUNICIPALITY: Various
MILEPOSTS: N/A
STRUCTURENO.: Various
LEGISLATIVEDISTRICT: Various
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: BridgeAssets:BridgeCapitalMaintenance
MPO
Phase
Year
Statewide
CD
2016
DB#:N1409
SouthFrontStreetBridgeovertheElizabethRiver
Thisstudywilllookatalternativesofanexistingmovablebridgewhichiscurrentlyclosedtotraffic
COUNTY: Union
MUNICIPALITY: ElizabethCity
MILEPOSTS: 0.75
STRUCTURENO.: 2004001
LEGISLATIVEDISTRICT: 20
SPONSOR: UnionCounty
ASSETMANAGEMENTCATEGORY: LocalSystemSupport:LocalBridges
MPO
Phase
Year
NJTPA
LCD
2016
SectionXPage7
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:08417
UPC#:084170
Route1,ForrestalRoadtoAaronRoad
AprojecttoaddressthedeficienciesalongtheportionofRoute1inSouthBrunswickbetweenMP
13.30and22.50.Thisstretchoftheroadwaycurrentlyaccommodatesonlytwotravellanesineach
direction.SectionsofRoute1bothnorthandsouthcarrythreelanesoftravel.The3Intersectionsof
RidgeRoad,NewRoad,andDeansLane/HendersonRoadwillbeadvancedintoConcept
Developmentunderthisagreement.
COUNTY: Middlesex
MUNICIPALITY: PlainsboroTwp,SouthBrunswickTwp,NorthBrunswickTwp
MILEPOSTS: 13.3022.50
STRUCTURENO.: Various,(SeeDescript.)
LEGISLATIVEDISTRICT: 14,16,17
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: CongestionRelief:MajorWidenings
MPO
Phase
Year
NJTPA
CD
2016
DB#:15303
UPC#:153030
Route1,NBBridgeoverRaritanRiver
ProblemStatementsubmittedbyBMSforTier1Screening.Theoverallconditionofthestructureis
fairduetotheconditionofsuperstructureandsubstructure.Ithasasufficiencyratingof77.0.The
deckisinsatisfactorycondition.Thesuperstructureisinfairconditionduetoseverallargespalls
withexposedrebars,largeincipientspalls,&numerousmediumtowidecracksthroughout.Theeast
andthewestspandrelwallshaveextensivemapcrackingwithefflorescencethroughout.The
substructureisinfairconditionduetoseverallargespallswithexposedrebars&numerous
mediumtowidecracksthroughout.ThisbridgeisconsideredPrioritizationCatagoryNumber3
andisalowpriorityforastageIIindepthScourEvaluation.BMShasrequestedaTier1Screening
butisrecommendingtomakepriorityrepairstoretardfurtherdeterioration,preservethestructural
integrityofthebridge,improvesafetyandextenditsusefullife.
COUNTY: Middlesex
MUNICIPALITY: EdisonTwp,NewBrunswickCity
MILEPOSTS: 27.7528.05
STRUCTURENO.: 1203150
LEGISLATIVEDISTRICT: 18,17
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: BridgeAssets:BridgeRehabandReplacement
MPO
Phase
Year
NJTPA
CD
2016
SectionXPage8
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:15376
UPC#:153760
Route1,Route3to46thStreet
FederalResurfacing/Rehabproject.
COUNTY: Hudson
MUNICIPALITY: NorthBergenTwp
MILEPOSTS: 57.058.2
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 32
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
NJTPA
CD
2016
DB#:12311
UPC#:123110
Route1&9,AvenueCtoSylvanStreet
Therearefixedobjectcrashesatthislocation.Route1&9attheCSAOrailroadoverpassis
frequentlyhitbyheavyvehicletrafficbecausethepostedclearance(13feet6inches)maybe
incorrect.Also,theexistingstructureconsistutesasafetyproblemforpedestriansthatmusttraverse
anarrowpassagewaybetweentheexistingabutmentandguiderail.
COUNTY: Union
MUNICIPALITY: LindenCity
MILEPOSTS: 40.0140.07
STRUCTURENO.: 2001153
LEGISLATIVEDISTRICT: 22
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: SafetyManagement:SafetyImprovements
MPO
Phase
Year
NJTPA
CD
2016
SectionXPage9
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:97005E
UPC#:078008
Route1&9T,SecaucusRoadtoLittleFerry
Thisproject,formerlyknownasNewRoadExtension,istheproposedextensionofNewRoadnorth
ofSecaucusRoadtotheCSXfacilityatLittleFerryand/oraconnectiontotheNJTurnpike.New
RoadextensionwillcreateadirectconnectiontoCroxtonYardanditsvicinity,therebyreducing
portgeneratedtrucktrafficontheparallelsectionofRt.1&9.ThiswillreducecongestiononRt.1
&9,especiallyduringpeakhours.
COUNTY: Hudson
MUNICIPALITY: JerseyCity
MILEPOSTS: N/A
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 31,33
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: LocalSystemSupport:EconomicDevelopment
MPO
Phase
Year
NJTPA
CD
2016
DB#:15397
UPC#:153970
Route9,AtkinsonAvenuetoBayviewDrive
FederalResurfacing/Rehabproject.MP32.434.23,42.7643.8
COUNTY: Atlantic
MUNICIPALITY: SomersPointCity,AbseconCity
MILEPOSTS: 32.443.8
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 2
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
SJTPO
CD
2016
SectionXPage10
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:07350
UPC#:073500
Route9,BusRapidTransit
TheRt.9BusRapidTransitprojectisprojectedtobeanextensionofthebusshoulderlanethathas
completedconstruction.NJTransitproposestoextendtheshoulderuseforbusesfromthe
Howell/LakewoodbordertoOldBridgeinbothdirections.
COUNTY: Ocean,Monmouth
MUNICIPALITY: LakewoodTwp,HowellTwp,FreeholdTwp,ManalapanTwp
MILEPOSTS: 103.0122.46
STRUCTURENO.: Various
LEGISLATIVEDISTRICT: 30,11,13,12
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: CongestionRelief:DemandManagement
MPO
Phase
Year
NJTPA
CD
2016
DB#:076C
UPC#:088035
Route9,Lakewood/TomsRiver,CongestionRelief
Underexistingconditions,thiscorridorconsistentlyexperienceshighlevelsofcongestionand
crashesbothweekdaysandweekend.Growthcontinuesinthesetwotownsandtheassociated
trafficwillexacerbatetheseconditionsovertime.The7.2milesegmentrunsparalleltotheGarden
StateParkway(totheeast)andprovidesanalternateroutefornorth–southtrafficinthisarea
duringincidentsontheGardenStateParkway.
COUNTY: Ocean
MUNICIPALITY: LakewoodTwp,TomsRiverTwp
MILEPOSTS: 94.8101.7
STRUCTURENO.: 1504150,1504151,1504153
LEGISLATIVEDISTRICT: 30,10
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: CongestionRelief:MajorWidenings
MPO
Phase
Year
NJTPA
CD
2016
SectionXPage11
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:97080N
UPC#:068001
Route9,MizzenAvenueandWashingtonAvenue,Intersection
Improvements
ThesignalizedMizzenAvenueintersectionislocatedveryclosetotheunsignalizedWashington
Avenueintersection.Thesetwointersectionsareattemptingtooperateasone.Thegeometry
combinedwiththetrafficvolumescreateseveredelaysattheseintersections.ATownCenteris
proposedadjacenttothislocation.
COUNTY: Ocean
MUNICIPALITY: PineBeachBoro,BerkeleyTwp
MILEPOSTS: 89.4189.44
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 9
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: CongestionRelief:HighwayOperationalImprovements
MPO
Phase
Year
NJTPA
CD
2016
DB#:15400
UPC#:154000
Route9,WrightsLanetoHarborRoad
FederalResurfacing/Rehabproject.MP23.424.1,25.330.7
COUNTY: CapeMay
MUNICIPALITY: UpperTwp
MILEPOSTS: 23.430.7
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 1
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
SJTPO
CD
2016
DB#:14424
UPC#:144240
Route9W,BridgeoverRoute95,1&9,46,and4
ProblemstatementsubmittedbyBMSforTier1Screening.Itisrecommendedforrehabilitationor
replacement.
COUNTY: Bergen
MUNICIPALITY: FortLeeBoro
MILEPOSTS: 0.05
STRUCTURENO.: 0209150
LEGISLATIVEDISTRICT: 37
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: BridgeAssets:BridgeRehabandReplacement
MPO
Phase
Year
NJTPA
CD
2016
SectionXPage12
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:11406
UPC#:114060
Route9W,PalisadesAvenuetoNewYorkStateLine
TheRoute9WAssessmentforBicycleandPedestrianNeedsidentifiedsafetydeficienciesinterms
oftheabilityoftheroadwaytoaccommodatebicycletrafficandpedestriancrossingsatNJTransit
busstops.Bicycleandpedestriancompatibilitysigning,striping,anddrainagegrateimprovements
areexpectedtoaddressthesedeficiencieswiththeintentiontobeimplementedbymaintenance
engineering.
COUNTY: Bergen
MUNICIPALITY: EnglewoodCliffsBoro,AlpineBoro
MILEPOSTS: 2.1911.17
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 37
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: SafetyManagement:Bicycle/PedestrianSafety
MPO
Phase
Year
NJTPA
CD
2016
DB#:15441
UPC#:154410
Route15Corridor,RockfallMitigation
Thissectionofrockcutsincludesthe2highestrankedcutslopeswithintheRockfallHazard
ManagementSystem(RHMS)yettobeassignedformitigationdesign;thegroupcontainsseveral
othercutslopesrankedwithinthetop12%.Theslopesexhibitmanyloosebouldersand
overhangingblocks,which,inconjunctionwiththelimitedcatchareas,presentthepotentialfor
fallingmaterialtoimpactthetraveledroadway.Inaddition,withinthelastyear,onelocationhada
Rockfalleventwherea20tonboulderfelluponguiderail.
COUNTY: Morris,Sussex
MUNICIPALITY: JeffersonTwp,LafayetteTwp,SpartaTwp
MILEPOSTS: 3.019.53
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 26,24
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: SafetyManagement:RockfallMitigation
MPO
Phase
Year
NJTPA
CD
2016
SectionXPage13
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:14414
UPC#:144140
Route15SB,BridgeoverRockawayRiver
ProblemstatementsubmittedbyBMSforTier1Screening.Itisrecommendedforrehabilitationor
replacement.
COUNTY: Morris
MUNICIPALITY: JeffersonTwp
MILEPOSTS: 4.2
STRUCTURENO.: 1404158
LEGISLATIVEDISTRICT: 26
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: BridgeAssets:BridgeRehabandReplacement
MPO
Phase
Year
NJTPA
CD
2016
DB#:13350
UPC#:133500
Route15andBerkshireValleyRoad(CR699)
Thisprojectwilladdresscongestionandsafetyatthesignalizedintersection,andasecondleftturn
lanewillbeaddedfromBerkshireValleyRd.toRt.15Southbound.
COUNTY: Morris
MUNICIPALITY: JeffersonTwp
MILEPOSTS: 3.913.91
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 26
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: CongestionRelief:HighwayOperationalImprovements
MPO
Phase
Year
NJTPA
CD
2016
DB#:94056
UPC#:950236
Route17,CentralAvenueBridge,RochellePark
Thisprojectwillprovidefortheproposedbridgereplacement,whichwasidentifiedbyBridge
ManagementSystem.Theoverallconditionofthebridgeisserious,withlowappraisalratingsfor
structuralevaluationandtheinadequatedeckgeometry.
COUNTY: Bergen
MUNICIPALITY: RochelleParkTwp
MILEPOSTS: 10.90
STRUCTURENO.: 0214159
LEGISLATIVEDISTRICT: 38
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: BridgeAssets:BridgeRehabandReplacement
MPO
Phase
Year
NJTPA
CD
2016
SectionXPage14
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:103A1
UPC#:088034
Route17,EssexStreettoSouthofRoute4
WideningofRt.17toprovidesixlanesofthroughtraffic,someofwhichisonstructureswithinthe
projectlimits.Theprojectwillincludestructurereplacementsandatgradecrossingsatvarious
intersections.
COUNTY: Bergen
MUNICIPALITY: Various
MILEPOSTS: 10.1912.04
STRUCTURENO.: 0214157,0214158,0214159,1221151
LEGISLATIVEDISTRICT: Various
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: CongestionRelief:MajorWidenings
MPO
Phase
Year
NJTPA
LPE
2016
DB#:94057
UPC#:950242
Route17,NYS&WBridge
Thisprojectwillprovidefortheproposedbridgereplacement,whichwasidentifiedbyBridge
ManagementSystem.Theoverallconditionofthebridgeisserious,withlowappraisalratingsfor
structuralelevationandtheinadequatedeckgeometry.
COUNTY: Bergen
MUNICIPALITY: RochelleParkTwp
MILEPOSTS: 10.90
STRUCTURENO.: 0214157
LEGISLATIVEDISTRICT: 38
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: BridgeAssets:BridgeRehabandReplacement
MPO
Phase
Year
NJTPA
CD
2016
DB#:15383
UPC#:153830
Route17,PierrepontAvetoTerraceAve/PolifyRd(CR55)
FederalResurfacing/Rehabproject.MPNB4.545.87,7.58.85;SB4.495.4,7.58.48
COUNTY: Bergen
MUNICIPALITY: RutherfordBoro,EastRutherfordBoro,HasbrouckHeightsBoro
MILEPOSTS: 4.498.85
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 36,38
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
NJTPA
CD
2016
SectionXPage15
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:11357
UPC#:113570
Route17,SproutBrook,CulvertReplacement
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacetheculvertwithintheproject
limits.
COUNTY: Bergen
MUNICIPALITY: ParamusBoro
MILEPOSTS: 15.015.1
STRUCTURENO.: 0216158
LEGISLATIVEDISTRICT: 38
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: BridgeAssets:Culverts
MPO
Phase
Year
NJTPA
CD
2016
DB#:103A2
UPC#:098021
Route17,WilliamsAvenuetoI80
ThisstudywillinvestigatethewideningofRt.17toprovidesixlanesofthroughtraffic.Structural
replacementswillbeincluded.
Thefollowingspecialfederalappropriationshavebeenallocatedtothisproject:1)FY2004/Section
115/H17$1,000,000,ID#NJ093);2)FY05/Section11/H66,$2,000,000(ID#NJ111);3)FY06SAFETEA
LU,HPP$4,400,000(ID#NJ128);4)FY06SAFETEALU,HPP$9,600,000(ID#NJ159)(available20%
peryear);5)FY2004Sec.115/H17,PL108199,$1,000,000(ID#NJ094).
COUNTY: Bergen
MUNICIPALITY: HasbrouckHeightsBoro,HackensackCity
MILEPOSTS: 8.39.9
STRUCTURENO.: 0221150,0221151,0221153
LEGISLATIVEDISTRICT: 38,37
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: CongestionRelief:MajorWidenings
MPO
Phase
Year
NJTPA
CD
2016
SectionXPage16
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:15377
UPC#:153770
Route21,CherryStreettoOnRampatInterchange7
FederalResurfacing/Rehabproject.MP2.44.0;NB4.67.1;SB6.27.1
COUNTY: Essex
MUNICIPALITY: NewarkCity,BellevilleTwp
MILEPOSTS: 2.47.1
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 28,29
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
NJTPA
CD
2016
DB#:11369
UPC#:113690
Route22,BatesAvenuetoRoute57
InitiatedfromtheDrainageManagementSystem,thisprojectprovidesforadrainagealternatives
study.In2012DrainageManagementSystem,thislocationwasranked46/232forfloodingand
100/131forIcingincidents.
COUNTY: Warren
MUNICIPALITY: PhillipsburgTown,LopatcongTwp
MILEPOSTS: 1.12.1
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 23
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:Drainage
MPO
Phase
Year
NJTPA
CD
2016
DB#:14330
UPC#:143300
Route22,BridgeoverEchoLake
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethestructurallydeficient
bridge.
COUNTY: Union
MUNICIPALITY: MountainsideBoro
MILEPOSTS: 50.7450.74
STRUCTURENO.: 2003157
LEGISLATIVEDISTRICT: 21
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: BridgeAssets:DeckRehabandReplacement
MPO
Phase
Year
NJTPA
CD
2016
SectionXPage17
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:15442
UPC#:154420
Route22,RockfallMitigation,Phillipsburg
Thissectionconsistsof2maincutslopes,oneofwhichislocatedadjacenttotheDRJTBCEaston
Philipsburgtollbridge;therearemanylargeblocksandlimitedsightdistancealongtheEBcurve
fromthebridge.TheotherrockcutslopeislocatedalongthenearbyRt.22WBexitramp,directly
adjacenttoapedestriansidewalkthatisatravelwayforstudentsofPhillipsburgHighSchool.
TherehavebeenseveralrecentreportsofRockfallalongthiscutandinterimactionhasbeen
recommended.Apermanentimprovementisrequired.
COUNTY: Warren
MUNICIPALITY: PhillipsburgTown
MILEPOSTS: 0.20.6
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 23
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: SafetyManagement:RockfallMitigation
MPO
Phase
Year
NJTPA
CD
2016
DB#:03318
UPC#:033180
Route22,SustainableCorridorLongtermImprovements
ThisproposedprojectwillinvestigatelongtermimprovementsbetweenRt.202/206andChimney
RockRoad.Proposedimprovementsshouldaddressthehighaccidentratesaswellaseliminate
congestioninthisarea.AfullalternativesanalysisistobeundertakenbySomersetCountyinorder
tofullydeterminetheneedsandthemostcosteffectivesolution.
ThefollowingspecialFederalappropriationwasallocatedtothisproject.FY08Omnibus
AppropriationsBill,$4,000,000,ID#NJ288,NJ109,NJ284,NJ227,NJ166,(SeealsoDB03319)
COUNTY: Somerset
MUNICIPALITY: BridgewaterTwp
MILEPOSTS: 33.8837.14
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 23
SPONSOR: SomersetCounty
ASSETMANAGEMENTCATEGORY: CongestionRelief:HighwayOperationalImprovements
MPO
Phase
Year
NJTPA
LCD
2016
SectionXPage18
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:15433
UPC#:154330
Route24,EBRamptoCR510(ColumbiaTurnpike)
Developrecommendationsthatwouldimprovethetrafficflowbetweentherampandthe
intersectionalongwithprovidingimprovementstotheoperationoftheintersectionthatcouldbe
investigatedfurther.TheRoute24EBrampmergeswithColumbiaTurnpikeWBapproximately650
feeteastofthesignalizedintersectionofColumbiaTurnpikeandParkAvenue.Atthisintersection
thereisaheavyAMleftturnmovementontheColumbiaTurnpikeWBapproachthatcurrently
utilizesadoubleleftturnlane.
COUNTY: Morris
MUNICIPALITY: MorrisTwp,HanoverTwp
MILEPOSTS: 2.09
STRUCTURENO.: NA
LEGISLATIVEDISTRICT: 27,25
SPONSOR: MorrisCounty
ASSETMANAGEMENTCATEGORY: CongestionRelief:HighwayOperationalImprovements
MPO
Phase
Year
NJTPA
CD
2016
DB#:15398
UPC#:153980
Route26,CoxRoadtoNassauStreet
FederalResurfacing/Rehabproject.
COUNTY: Middlesex
MUNICIPALITY: NorthBrunswickTwp
MILEPOSTS: 1.642.54
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 17
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
NJTPA
CD
2016
SectionXPage19
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:15371
UPC#:153710
Route27,DehartPlacetoRoute21
FederalResurfacing/Rehabproject.
COUNTY: Union,Essex
MUNICIPALITY: ElizabethCity,NewarkCity
MILEPOSTS: 33.438.53
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 20,28,29
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
NJTPA
CD
2016
DB#:11413C
UPC#:158030
Route29,AlexaukenCreekRoadtoWashingtonStreet
InitiatedfromthePavementManagementSystem,thisprojectwillreconstruct(includingcoldin
placerecycling)andresurfacewithintheprojectlimits.TheprojectwillbeMillXPaveX+1,and
willincludedrainageimprovementstoeliminateroadway,shoulderandborderponding.
COUNTY: Hunterdon
MUNICIPALITY: LambertvilleCity,DelawareTwp,KingwoodTwp,FrenchtownBoro
MILEPOSTS: 19.824.5&33.734.3
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 15,16,23
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayRehabandRecon
MPO
Phase
Year
NJTPA
CD
2016
SectionXPage20
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:15443
UPC#:154430
Route29,RockfallMitigation,WestAmwell&Lambertville
TheslopesalongthissectionofRt.29containmanylargeblocksandboulders,whichare
intermingledwithsoilareasandhistoricrockblockretainingstructures;thereisessentiallyno
catchareaalongtheNBshoulder;fallingrockislikelytoimpacttheroadway,whichhaslimited
sightdistance.Thissectioncontainsthe4thhighestrankedcutyettobeassignedformitigation
design.Inaddition,pavementconditionsarepoorandneedtobeassessed.
COUNTY: Hunterdon
MUNICIPALITY: LambertvilleCity,WestAmwellTwp
MILEPOSTS: 17.018.25
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 15
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: SafetyManagement:RockfallMitigation
MPO
Phase
Year
NJTPA
CD
2016
DB#:14428
UPC#:144280
Route30,BridgeoverDuckThorofare
InitiatedfromtheBridgeManagementSystem,theprojectwillrehabilitate/replacethebridge.
COUNTY: Atlantic
MUNICIPALITY: AtlanticCity
MILEPOSTS: 56.25
STRUCTURENO.: 0103153
LEGISLATIVEDISTRICT: 2
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: BridgeAssets:BridgeRehabandReplacement
MPO
Phase
Year
SJTPO
CD
2016
DB#:15375
UPC#:153750
Route30,CooperStreettoGroveStreet
FederalResurfacing/Rehabproject.MP1.473.5,4.17.8
COUNTY: Camden
MUNICIPALITY: CamdenCity,CollingswoodBoro,AudubonBoro,HaddonHeightsBoro
MILEPOSTS: 1.477.8
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 5,6
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
DVRPC
CD
2016
SectionXPage21
FY20162017STUDYANDDEVELOPMENTPROGRAM
Route30,CR542(SeaGroveAve/CentralAve)toWeymouthRd(CR640)
DB#:15382
UPC#:153820
FederalResurfacing/Rehabproject.
COUNTY: Atlantic
MUNICIPALITY: HammontonTown
MILEPOSTS: 31.0832.0
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 8
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
SJTPO
CD
2016
DB#:12369
UPC#:123690
Route31,EwingvilleRoad(CR636)
Thisprojectwillprovideamodifiedroaddietandsignalimprovementsattheintersection.Crash
analysisatthisintersectionindicatesarateapproximatelydoublethestatewideaverage.
COUNTY: Mercer
MUNICIPALITY: EwingTwp
MILEPOSTS: 3.827
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 15
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: SafetyManagement:SafetyImprovements
MPO
Phase
Year
DVRPC
CD
2016
SectionXPage22
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:403A
UPC#:961458
Route31,IntegratedLandUse&TransportationPlan
TheRt.31IntegratedLandUse&TransportationStudyisforthecompletionoftheSouthBranch
Parkway(SBP)andotherelementsoftheplanasneeded.TheSouthBranchParkwayisthetwo
lane,atgraderoadwayonthealignmentoftheproposedFlemingtonBypass.The$2.2000ofFY
2007PEDEMOfundswasnotintendedfortheSBP.Itisintendedforoneofthebreakouts,such
astheFlemingtonCircletoRoundaboutproject,ortheSouthMainSt.CircletoRoundaboutproject.
ThefollowingspecialFederalappropriationswereallocatedtothisproject.TEA21/Q92
$11,839,898;FY2004/Section115/H17$150,000;FY06SAFETEALU,HPP$2,000,000(available20%
peryear).
ContinuetoworkwithDeveloperstopreservefuturealignmentofSouthBranchParkway.No
otheractivity.
COUNTY: Hunterdon
MUNICIPALITY: FlemingtonBoro,RaritanTwp
MILEPOSTS: 22.0225.30
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 16
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: CongestionRelief:MissingLinks
MPO
Phase
Year
NJTPA
CD
2016
DB#:11342A
UPC#:148010
Route31,Route78/22toGraysrockRoad
InitiatedfromthePavementManagementSystem,thisprojectwillreconstructpavementwithinthe
projectlimits.
COUNTY: Hunterdon
MUNICIPALITY: ClintonTwp
MILEPOSTS: 31.832.5
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 23
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayRehabandRecon
MPO
Phase
Year
NJTPA
CD
2016
SectionXPage23
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:15393
UPC#:153930
Route32EB,Route130toNJTurnpike
FederalResurfacing/Rehabproject.
COUNTY: Middlesex
MUNICIPALITY: SouthBrunswickTwp
MILEPOSTS: 0.01.18
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 16
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
NJTPA
CD
2016
DB#:13338
UPC#:133380
Route33&E.SanMarcoBoulevard
AProblemStatementwassubmittedtoNJDOTbyHowellTownshipinvolvingthelackofatraffic
controldeviceattheTIntersectionofRoute33andSanMarcoBoulevard(MP33.15),whichleads
intoanagerestrictedprivatedevelopment.
COUNTY: Monmouth
MUNICIPALITY: HowellTwp
MILEPOSTS: 33.1033.20
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 30
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: SafetyManagement:SafetyImprovements
MPO
Phase
Year
NJTPA
CD
2016
DB#:14422
UPC#:144220
Route33,BridgeoverMillstoneRiver
InitiatedfromtheBridgeManagementSystem,theprojectwillrehabilitate/replacethebridge.
COUNTY: Monmouth
MUNICIPALITY: MillstoneTwp
MILEPOSTS: 19.8
STRUCTURENO.: 1304151
LEGISLATIVEDISTRICT: 12
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: BridgeAssets:BridgeRehabandReplacement
MPO
Phase
Year
NJTPA
CD
2016
SectionXPage24
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:15374
UPC#:153740
Route33,ClevelandAvenuetoPaxonAvenue
FederalResurfacing/Rehabproject.
COUNTY: Mercer
MUNICIPALITY: TrentonCity,HamiltonTwp
MILEPOSTS: 1.45.0
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 15,14
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
DVRPC
CD
2016
DB#:15402
UPC#:154020
Route34,Route35&70toRoute195/138
FederalResurfacing/Rehabproject.MPNB0.04.1;SB0.01.6,2.62.7
COUNTY: Monmouth
MUNICIPALITY: WallTwp
MILEPOSTS: 0.04.1
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 30
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
NJTPA
CD
2016
DB#:14429
UPC#:144290
Route35,BridgeoverNorthBranchofWreckPond
ProblemstatementsubmittedbyBMSforTier1Screening.Itisrecommendedforrehabilitationor
replacement.
COUNTY: Monmouth
MUNICIPALITY: WallTwp
MILEPOSTS: 18.2
STRUCTURENO.: 1310155
LEGISLATIVEDISTRICT: 30
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: BridgeAssets:BridgeRehabandReplacement
MPO
Phase
Year
NJTPA
CD
2016
SectionXPage25
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:15389
UPC#:153890
Route35,DelawareAvenuetoRoute34&Route70
FederalResurfacing/Rehabproject.MPBoth12.512.88;NB12.8813.0,14.2914.52,15.7716.1;SB
12.8814.52,15.7716.1
COUNTY: Ocean,Monmouth
MUNICIPALITY: PointPleasantBeachBoro,WallTwp
MILEPOSTS: 12.516.1
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 10,30
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
NJTPA
CD
2016
DB#:15392
UPC#:153920
Route35,Route9toColoniaBoulevard
FederalResurfacing/Rehabproject.MP50.650.9,52.7558.07
COUNTY: Middlesex,Union
MUNICIPALITY: SayrevilleBoro,PerthAmboyCity,WoodbridgeTwp,RahwayCity
MILEPOSTS: 50.658.07
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 19,22
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
NJTPA
CD
2016
DB#:15388
UPC#:153880
Route35,WoodlandAvenuetoCR516(CherryTreeFarmRoad)
FederalResurfacing/Rehabproject.MP22.6723.6;SB34.539.4
COUNTY: Monmouth
MUNICIPALITY: NeptuneCityBoro,NeptuneTwp,MiddletonTwp
MILEPOSTS: 22.6739.4
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 11,13
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
NJTPA
CD
2016
SectionXPage26
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:15384
UPC#:153840
Route36,CliftonAve/JamesSttoCR520(RumsonRd)
FederalResurfacing/Rehabproject.
COUNTY: Monmouth
MUNICIPALITY: LongBranchCity,MonmouthBeachBoro,SeaBrightBoro
MILEPOSTS: 5.79.4
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 11,13
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
NJTPA
CD
2016
DB#:15385
UPC#:153850
Route38,NixonDrivetoPembertonRoad
FederalResurfacing/Rehabproject.MPEB6.559.53,13.6516.74;WB6.559.6
COUNTY: Burlington
MUNICIPALITY: MoorestownTwp,MountLaurelTwp,LumbertonTwp,MountHollyTwp
MILEPOSTS: 6.5516.74
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 7,8
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
DVRPC
CD
2016
DB#:15370
UPC#:153700
Route40,HamiltonCommonDrivetoWestEndAvenue(CR629)
FederalResurfacing/Rehabproject.MP52.254.3,59.763.5;EB56.557.1;WB55.557.1
COUNTY: Atlantic
MUNICIPALITY: HamiltonTwp,EggHarborTwp,PleasantvilleCity,AtlanticCity
MILEPOSTS: 52.263.5
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 2
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
SJTPO
CD
2016
SectionXPage27
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:196A5
UPC#:068095
Route40/322,MedianClosures,DelilahRoadtoEastFireRoad
ThisprojectisabreakoutfromRoute40/322CologneAvetoFireRoad.Arecentcrashanalysis
forRoute40/322MedianClosureDelilahRd.toFireRd.projectfromtheBureauofSafetyPrograms
foryears20102012wascompleted.TheanalysisrevealstheneedforaConceptDevelopmentstudy
toaddresssafetyconcernsfortheremainingpartoftheRoute40/322DelilahRd.toFireRd.
COUNTY: Atlantic
MUNICIPALITY: HamiltonTwp,EggHarborTwp
MILEPOSTS: 53.2158.11
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 2
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: CongestionRelief:HighwayOperationalImprovements
MPO
Phase
Year
SJTPO
CD
2016
DB#:11340A
UPC#:148100
Route46,Route80toWalnutRoad
InitiatedfromthePavementManagementSystem,thisprojectwillreconstructpavementwithinthe
projectlimits.
COUNTY: Warren
MUNICIPALITY: KnowltonTwp
MILEPOSTS: 01.4
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 24
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayRehabandRecon
MPO
Phase
Year
NJTPA
CD
2016
DB#:15387
UPC#:153870
Route46,StigerSttoSandShoreRd/NaughrightRoad
FederalResurfacing/Rehabproject.
COUNTY: Morris,Warren
MUNICIPALITY: HackettstownTown,MountOliveTwp,WashingtonTwp
MILEPOSTS: 21.024.6
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 23,24
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
NJTPA
CD
2016
SectionXPage28
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:15310
UPC#:153100
Route47,BridgeoverRoute295
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethebridgesuperstructure.
COUNTY: Gloucester
MUNICIPALITY: WestvilleBoro
MILEPOSTS: 74
STRUCTURENO.: 0815150
LEGISLATIVEDISTRICT: 21
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: BridgeAssets:BridgeRehabandReplacement
MPO
Phase
Year
DVRPC
CD
2016
DB#:15314
UPC#:153140
Route49,BridgeoverMauriceRiver
InitiatedbytheBridgeManagementSystem,thisprojectwillreplacethebridge.
COUNTY: Cumberland
MUNICIPALITY: MillvilleCity
MILEPOSTS: 36.2
STRUCTURENO.: 0605151
LEGISLATIVEDISTRICT: 1
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: BridgeAssets:BridgeRehabandReplacement
MPO
Phase
Year
SJTPO
CD
2016
DB#:15386
UPC#:153860
Route49,CapeMayAvenue(CR666)toRoute50
FederalResurfacing/Rehabproject.
COUNTY: CapeMay
MUNICIPALITY: UpperTwp
MILEPOSTS: 49.853.8
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 1
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
SJTPO
CD
2016
SectionXPage29
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:12424
UPC#:124240
Route53,PondviewRoadtoHallAvenue
InitiatedfromthePavementManagementSystem,thisprojectwillresurfacewithintheproject
limits.
COUNTY: Morris
MUNICIPALITY: ParsippanyTroyHillsTwp,DenvilleTwp
MILEPOSTS: 1.94.5
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 26,25
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
NJTPA
CD
2016
DB#:15379
UPC#:153790
Route54,Rt40(HardingHighway)toRt30(WhitehorsePike)
FederalResurfacing/Rehabproject.MP0.06.2,8.4911.86
COUNTY: Atlantic
MUNICIPALITY: BuenaBoro,BuenaVistaTwp,HammontonTown
MILEPOSTS: 0.011.86
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 2,8
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
SJTPO
CD
2016
DB#:08329
UPC#:083290
Route66,WestofJumpingBrookRoadtoEastofWaysideAvenue
ThissectionofRt.66experiencesseverecongestionduringpeakperiods.Intersection
improvementsatWaysideAvenueandAsburyAvenueandawideningtoaddacenterlaneora
fulllaneineachdirectionisrecommendedforinvestigation.
COUNTY: Monmouth
MUNICIPALITY: NeptuneTwp
MILEPOSTS: 0.92.6
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 11
SPONSOR: NJTPA
ASSETMANAGEMENTCATEGORY: CongestionRelief:HighwayOperationalImprovements
MPO
Phase
Year
NJTPA
LCD
2016
SectionXPage30
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:15372
UPC#:153720
Route70,DakotaTrailtoRiverviewDrive(CR48)
FederalResurfacing/Rehabproject.MP27.931.2,38.4550.58,57.858.7
COUNTY: Burlington,Ocean,Monmouth
MUNICIPALITY: PembertonTwp,ManchesterTwp,BrickTwp,BrielleBoro
MILEPOSTS: 27.958.53
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 8,10,30
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
NJTPA
CD
2016
Route73,ChurchRoad(CR616)andFellowshipRoad(CR673)Intersections DB#:12380
UPC#:123800
TrafficdelaysformultiplesignalcyclesoccuronNJ73NBandSBduringtheAMandPMpeakson
weekdays.InbothdirectionsthequeuesblocktheprevioussignalizedintersectionsatAtriumWay
andHowardBlvd./RogersAve.respectively.Trafficdelaysformultiplesignalcyclesoccuron
ChurchRd.EBinthePMwithqueuesblockingtheprevioussignalatArborWay.Delaysofover
fiveminutespervehiclewereobserved.
COUNTY: Burlington
MUNICIPALITY: MountLaurelTwp
MILEPOSTS: 26.4727.42
STRUCTURENO.: 1606178
LEGISLATIVEDISTRICT: 7
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: CongestionRelief:HighwayOperationalImprovements
MPO
Phase
Year
DVRPC
CD
2016
SectionXPage31
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:13319
UPC#:133190
Route73,CR544(EveshamRd/MarltonParkway)
ThisprojectseekstoexaminethefeasibilityofimprovementstotheintersectionofRoute73and
EveshamRoad.Numerousproblemsassociatedwithcapacity,operationsandsafetyhavebeen
reportedinthearea,andwouldbeaddressedwithintersectionimprovements.
COUNTY: Burlington
MUNICIPALITY: EveshamTwp
MILEPOSTS: 22.7522.85
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 8
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: CongestionRelief:HighwayOperationalImprovements
MPO
Phase
Year
DVRPC
CD
2016
DB#:15390
UPC#:153900
Route77,Route49toFriesburgRoad(CR640)
FederalResurfacing/Rehabproject.MP0.01.4,2.573.21,6.828.03
COUNTY: Cumberland
MUNICIPALITY: BridgetonCity,UpperDeerfieldTwp
MILEPOSTS: 0.08.03
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 3
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
SJTPO
CD
2016
SectionXPage32
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:15338
UPC#:153380
Route78RockfallMitigation,BethlehemTownship
Theexistingrockcutsexhibitoversteepenedslopeanglesandareinahighlyfracturedand
weatheredcondition.Theslopesaverageover100’inheight,andexhibitmanyloosebouldersand
overhangingblocks.Thelimitedcatchareaatthetoe(average5’wide)doesnotsufficientlyretain
fallingrock.Inaddition,theEBcutslopebecomescompletelyicecoveredduringwinter,causing
icejackinganddisplacementoflargerockblocks.Fallingrockoftenreachestheroadwaysurface.
Rockfallmitigationmeasuresareanticipatedtoincludemassexcavation,scaling,rockbolting,wire
meshdrapes,androckcatchfences.
COUNTY: Hunterdon
MUNICIPALITY: BethlehamTwp
MILEPOSTS: 10.110.3
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 23
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: SafetyManagement:RockfallMitigation
MPO
Phase
Year
NJTPA
CD
2016
DB#:9137A
UPC#:038039
Route78,EdnaMahanFrontageRoad
TheexistingfrontageroadalongI78eastboundwillbeextendedtomeettheexistingprisonaccess
road.TheprisonaccessroadextendstothewestandterminatesattheEdnaMahanWomens
CorrectionalFacility.Thiswillallowasignificantworkforceatthecorrectionalfacilitydirectaccess
toI78eastbound.
COUNTY: Hunterdon
MUNICIPALITY: UnionTwp
MILEPOSTS: 15.0015.40
STRUCTURENO.: 1018150,1018151,1015156,1015162
LEGISLATIVEDISTRICT: 23
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: CongestionRelief:HighwayOperationalImprovements
MPO
Phase
Year
NJTPA
CD
2016
SectionXPage33
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:93141
UPC#:950436
Route78,InterchangeStudyatRoute31
HunterdonCountyperformedaplanningstudyoftheI78corridorfromInterchange15to
Interchange20.ThisstudyisthebasisforDOTworkefforts.Thefindingswillberefinedand
conceptsdevelopedthatbestaddresstheplanningneedsaswellasthephysicaloperationaland
safetydeficiencieswithinthestudylimits.Bothlongtermaswellasshortrangeimprovements
identifiedintheNJTPAI78TransitAssessmentPhaseIIStudycompletedin2009shouldbe
considered.
COUNTY: Hunterdon
MUNICIPALITY: ClintonTwp
MILEPOSTS: Rt.78:16.517.7;Rt.31:31.7033.50
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 23
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: CongestionRelief:HighwayOperationalImprovements
MPO
Phase
Year
NJTPA
CD
2016
DB#:15380
UPC#:153800
Route79,Route9toRoute34(MiddlesexStreet)
FederalResurfacing/Rehabproject.
COUNTY: Monmouth
MUNICIPALITY: FreeholdTwp,FreeholdBoro,MarlboroTwp,MatawantBoro
MILEPOSTS: 0.012.13
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 11,13,12
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
NJTPA
CD
2016
SectionXPage34
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:15404
UPC#:154040
Route80EB,WestShoreAvenuetoRoute95
FederalResurfacing/Rehabproject.
COUNTY: Bergen
MUNICIPALITY: RidgefieldParkVillage,BogotaBoro,TeaneckTwp
MILEPOSTS: 67.1368.54
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 36,37
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
NJTPA
CD
2016
DB#:15351
UPC#:153510
Route80,BridgesoverHowardBoulevard(CR615)
BoththeRt80EBandRt80WBstructuresoverHowardBlvd.willbeevaluatedforeither
rehabilitationorreplacement.Inadditionoperationimprovementswithintheinterchangedueto
theadditionoftheHerculestruckingfacilitywillbeexploredalongwithimprovementsto
accelerationanddecelerationlanes.
COUNTY: Morris
MUNICIPALITY: MountArlingtonBoro
MILEPOSTS: 30.61
STRUCTURENO.: 1412169,1412168
LEGISLATIVEDISTRICT: 25
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: BridgeAssets:BridgeRehabandReplacement
MPO
Phase
Year
NJTPA
CD
2016
SectionXPage35
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:15444
UPC#:154440
Route80,RockfallMitigation,Rockaway,Denville,ParTroy
Thisthroughcutsection(MP41.0EB&WB)isthe3rdhighestoverallyettobeassignedfor
mitigationdesign.Thereareseveralextremelylargebouldersandrockwedgeswhich,intheevent
ofafall,willlikelyreachthepavementoftheInterstatehighwaywithhighdailyvehiculartraffic.
Theprojectlimitscontainseveralothercutslopesrankedwithinthetop10%.
COUNTY: Morris
MUNICIPALITY: RockawayTwp,DenvilleTwp,ParsippanyTroyHillsTwp
MILEPOSTS: 37.042.0
STRUCTURENO.: NA
LEGISLATIVEDISTRICT: 25,26
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: SafetyManagement:RockfallMitigation
MPO
Phase
Year
NJTPA
CD
2016
DB#:11415
UPC#:114150
Route80,WB,Pavement,Bergen&PassaicCounties
InitiatedfromthePavementManagementSystem,thisprojectwillreconstructapproximately7.6
milesofI80WestboundpavementinPassaicCounty(WoodlandParkBoroughandtheCityof
Paterson)andinBergenCounty(ElmwoodParkBorough,SaddleBrookTownship,LodiBorough
andtheCityofHackensack).
Theprojectlimitsarefromapproximately0.2mileeastoftheSquirrelwoodRoad(CR636)
InterchangeinWoodlandParkBorough,PassaicCountytoapproximately0.1milewestoftheS.
SummitRd(CR57)InterchangeintheCityofHackensack,BergenCounty.
COUNTY: Passaic,Bergen
MUNICIPALITY: Various
MILEPOSTS: 56.4365.4
STRUCTURENO.: Various
LEGISLATIVEDISTRICT: 35,37,38,40
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayRehabandRecon
MPO
Phase
Year
NJTPA
CD
2016
SectionXPage36
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:15391
UPC#:153910
Route94,PleasantValleyDrivetoMapleGrangeRoad
FederalResurfacing/Rehabproject.MP38.040.5,40.943.0
COUNTY: Sussex
MUNICIPALITY: VernonTwp
MILEPOSTS: 38.043.0
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 24
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
NJTPA
CD
2016
DB#:14426
UPC#:144260
Route130,BridgeoverBigTimberCreek
ProblemstatementsubmittedbyBMSforTier1Screening.Itisrecommendedforrehabilitationor
replacement.
COUNTY: Camden,Gloucester
MUNICIPALITY: BrooklawnBoro,WestvilleBoro
MILEPOSTS: 25.3525.58
STRUCTURENO.: 0818151
LEGISLATIVEDISTRICT: 5
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: BridgeAssets:BridgeRehabandReplacement
MPO
Phase
Year
DVRPC
CD
2016
DB#:15401
UPC#:154010
Route138,GardenStateParkwaytoRoute35
FederalResurfacing/Rehabproject.
COUNTY: Monmouth
MUNICIPALITY: WallTwp
MILEPOSTS: 0.373.52
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 30
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
NJTPA
CD
2016
SectionXPage37
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:X227A2
UPC#:048006
Route168,I295InterchangeImprovements
Theneedforthestudyistoaddresstheseverecongestionandaccidentsattheinterchange.The
geometryattheinterchangeisdeficient:Rampshaveinsufficientdecelerationlanelength.Allfour
rampshaveasubstandardexitcurveradiusof150`anddesignspeedof25MPH.Thereis
insufficientstoppingsightdistanceduetosubstandardcrestverticalcurvelengthbetweenWest
MapleAvenueandBrowningAvenue.Geometricimprovementmayberequired.Representatives
ofBoroughofBellmawrhavereportedadrainageproblemattherampconnectingRt.168Northto
Rt.295North.AfieldmeetingisplannedtomeetwiththeSuperintendentoftheBellmawr
HighwayDepartment.
COUNTY: Camden
MUNICIPALITY: MountEphraimBoro,HaddonHeightsBoro,BellmawrBoro
MILEPOSTS: 7.177.73
STRUCTURENO.: 0426151
LEGISLATIVEDISTRICT: 5
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: SafetyManagement:SafetyImprovements
MPO
Phase
Year
DVRPC
CD
2016
DB#:15396
UPC#:153960
Route168,Route42toCR544(EveshamRoad)
FederalResurfacing/Rehabproject.
COUNTY: Camden,Gloucester
MUNICIPALITY: WashingtonTwp,GloucesterTwp,RunnemedeBoro
MILEPOSTS: 0.05.41
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 4,5
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
DVRPC
CD
2016
SectionXPage38
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:15378
UPC#:153780
Route181,EspanogRoadtoProspectPointRoad
FederalResurfacing/Rehabproject.
COUNTY: Morris
MUNICIPALITY: JeffersonTwp
MILEPOSTS: 0.01.52
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 26
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
NJTPA
CD
2016
DB#:15381
UPC#:153810
Route202,ChildsRd/NMapleAve(CR613)toAcademyRoad
FederalResurfacing/Rehabproject.
COUNTY: Morris,Somerset
MUNICIPALITY: BernardsTwp,HardingTwp,MorristownTwp,MorrisPlainsBoro
MILEPOSTS: 39.046.7
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 21,27,25,26
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
NJTPA
CD
2016
Route202/206andRoute22Interchange,NorthThompsonStreettoCommons DB#:02372
UPC#:023720
Way,OperationalandSafetyImprovements
ThisstudywillprovideoperationalandsafetyimprovementstotheRt.202/206/22Interchange
complexfromNorthThomsonSt.toCommonsWay.Theimprovementswillfocusonreducingthe
congestionandweavingproblemsthatoccurinthevicinityofRt.202/206andRt.22interchange.
COUNTY: Somerset
MUNICIPALITY: SomervilleBoro,RaritanBoro
MILEPOSTS: Rt.202/206:24.1425.50;Rt.22:33.88
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 16,23
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: CongestionRelief:HighwayOperationalImprovements
MPO
Phase
Year
NJTPA
CD
2016
SectionXPage39
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:14421
UPC#:144210
Route206,BridgeoverStonyBrookFloodChannel
ProblemstatementsubmittedbyBMSforTier1Screening.Itisrecommendedforrehabilitationor
replacement.
COUNTY: Mercer
MUNICIPALITY: PrincetonTwp
MILEPOSTS: 52.5
STRUCTURENO.: 1129154
LEGISLATIVEDISTRICT: 16
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: BridgeAssets:BridgeRehabandReplacement
MPO
Phase
Year
DVRPC
CD
2016
DB#:11381
UPC#:113810
Route208,BergenCountyDrainageImprovements
InitiatedbytheDrainageManagementSystem(DMS),thisprojectwilladdressdrainageissues
withintheprojectlimits,includingthreelocationsranked5,11and37bytheDMS.
COUNTY: Bergen
MUNICIPALITY: WyckoffTwp,FranklinLakesBoro
MILEPOSTS: 5.38.5
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 40
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:Drainage
MPO
Phase
Year
NJTPA
CD
2016
DB#:15405
UPC#:154050
Route287NB,Route202/206toSouthStreet(CR601)
FederalResurfacing/Rehabproject.
COUNTY: Somerset,Morris
MUNICIPALITY: BedminsterTwp,FarHillsBoro,HardingTwp,MorrisTwp
MILEPOSTS: 23.035.57
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 23,21,27,28
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
NJTPA
CD
2016
SectionXPage40
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:858
UPC#:960647
Route287,TruckWeighStation,BergenCounty
ThisprojectconsistsofconstructionofatruckweighstationfacilityonthesouthboundsideofI
287.ItwillweightrucksdestinedforI287southbound.Theprojectwillincludeweighinmotion
scales,staticweighscales,paving,grading,drainage,utilities(relocationandnewservices),
striping,electric,lightingandlandscaping.Thefacilitywillconsistofinternalroadways,
approximately11parkingstallsfortrucksandautomobiles,acommercialvehicleinspection
buildingandacontrolbuilding.Adecelerationlaneintoandaccelerationlanefromtheweigh
stationwillneedtobeprovidedalongI287southbound.
COUNTY: Bergen
MUNICIPALITY: MahwahTwp
MILEPOSTS: Tobedetermined
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 39
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:TruckSizeandWeightControl
MPO
Phase
Year
NJTPA
CD
2016
Route295,NorthboundApproachtoRoute1Exits,ITSImprovements
DB#:06358
UPC#:063580
Duringrushhours,especiallytheAMpeakhours,theexitfromI295northboundtoRt.1is
insufficientfortheamountoftraffic,causingbackupsinthethroughlanesofI295northbound
whichcreatesanoperationalandsafetyproblem.Reconstructionoftheinterchangeandinterstate
toexpandthecapacityoftheexitcouldbecostlyandadverselyimpacttheenvironmentaswellas
adjacentproperties.AninterimimprovementisproposedtoallowtheuseoftheI295northbound
shouldertoextendthestorageforthedecelerationlane.Tominimizethelossoftheshoulder,itis
proposedtouseITStechnologiestoopentheshoulderfordecelerationuseonlywhenneededand
thenreturnittouseasashoulderwhennotneeded.Technologieswouldincludemethodsof
detectionwhenbackupsareimminentandprovidingtheinformationtothetravelingpublicthat
theshoulderisopenforuse.
COUNTY: Mercer
MUNICIPALITY: LawrenceTwp
MILEPOSTS: 67.0067.50
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 15
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: CongestionRelief:IntelligentTransportationSystems
MPO
Phase
Year
DVRPC
CD
2016
SectionXPage41
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:15395
UPC#:153950
Route439,BakerPlacetoRoute27
FederalResurfacing/Rehabproject.
COUNTY: Union
MUNICIPALITY: ElizabethCity,UnionTwp,HillsideTwp
MILEPOSTS: 2.23.95
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 20,33
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
NJTPA
CD
2016
DB#:14355
UPC#:143550
Route440,CR514(WoodbridgeAvenue)toKreilAvenue
ConcretePavementRepair
COUNTY: Middlesex
MUNICIPALITY: EdisonTwp,WoodbridgeTwp,PerthAmboyCity
MILEPOSTS: 0.24.0
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 18,19
SPONSOR: NJDOT
ASSETMANAGEMENTCATEGORY: RoadAssets:HighwayResurfacing
MPO
Phase
Year
NJTPA
CD
2016
SectionXPage42
FY20162017STUDYANDDEVELOPMENTPROGRAM
DB#:06307
UPC#:063070
Route440/1&9,BoulevardthroughJerseyCity
ThisprojectintendstoallowRt.440/Rt.1&9tofunctionasaprincipalarterialandasa
neighborhoodmainstreet.Theprojectwillimproveconnectionsbetweenthelocalstreetnetwork
andaddresssafetyconcernsforpedestriansandbicyclists.Partoftheplanisthecreationofan
urbanboulevardalongRt.440/1&9inordertoseparatelocalandexpresstraffic.Lightrail
expansionandotheraestheticimprovementswillbeincludedinthestudy.
ThefederalSAFETEALUlegislationprovidedaspecialappropriationforconceptdevelopment
designs.AboulevardonRt.440andRt.1&9throughJerseyCityisplanned.
Thefollowingspecialfederalappropriationswereallocatedtothisproject:FY05SAFETEA
LU/HPP$1,800,000.Billlines#350and#3567,(ID#NJ130andID#NJ243).
CDStudycompletionanticipatedin2016,futurephasesnotfunded.JerseyCityisLeadAgency.
COUNTY: Hudson
MUNICIPALITY: JerseyCity
MILEPOSTS: Rt.44024.1026.18Rt.1&9T2.303.80
STRUCTURENO.: N/A
LEGISLATIVEDISTRICT: 31
SPONSOR: JerseyCity
ASSETMANAGEMENTCATEGORY: LocalSystemSupport:TransportationEnhancements
MPO
Phase
Year
NJTPA
LCD
2016
SectionXPage43
SECTIONXI
FY2015MAJORPROJECTSTATUS
FY2015MAJORPROJECTSTATUS
DVRPC
PrincetonHightstownRoadImprovements,CR571
COUNTY: Mercer
MUNICIPALITY: WestWindsorTwp
STATUS:
Constructionisprogrammedfor$10milliontotalinFY18andFY19oftheFY2016NJTIP.
SouthPembertonRoad,CR530,Phase2
COUNTY: Burlington
MUNICIPALITY: PembertonBoro,PembertonTwp,SouthamptonTwp
CountywillbesubmittingafinalPS&EpackageandanERtoNJDOTLocalAidatthe
STATUS:
endofAugust2015.CountyalsosubmittedNJDEPpermits.TheNJPinelandspermithas
beenissuedtothecounty.NotethatthisprojectsPhase1constructionhasbeencompleted.
$15.151millionSTPSTUfundsareprogrammedintheFY2016NJTIPforconstructioninFY16
andFY17.
TrentonAmtrakBridges
COUNTY: Mercer
MUNICIPALITY: TrentonCity
STATUS:
ThisprojectappearsontheFY2016NJTIP.EnvironmentaldocumentandRightofWay
authorizationhavebeencompletedinJuly2015.Adraftconceptwasdevelopedtoreplacethe
EastStateStreetBridge.Therevisedscopeofworkcosts$32milliontoconstruct.Ameeting
withTrentonofficialswasconducted,andNJDOThasrequestedsupportforthesinglebridge
optionfromtheCityofTrenton.Projectexpectstoreceiveauthorizationtoadvertiseonorafter
May2020andbesubstantiallycompletedonorafterOctober2021.
Route1,Southbound,NassauParkBoulevardtoQuakerBridgeMallOverpass
COUNTY: Mercer
MUNICIPALITY: LawrenceTwp,WestWindsorTwp
ThisprojectappearsontheFY2016NJTIPwitha$14.150millionfederallyfunded
STATUS:
constructionphaseinFY16andFY17.RightofWaywasauthorizedinlateSeptember2014.
ProjectexpectstoreceiveauthorizationtoadvertiseinlateAugust2016andawardthecontract
towardstheendof2016.
Route30,AtcoAvenuetoRoute206
COUNTY: Camden,Atlantic
MUNICIPALITY: WaterfordTwp,ChesilhurstBoro,WinslowTwp,HammontonTown
ConceptDevelopmentwascompletedonJune15,2015.Constructionwillbedelayedby
STATUS:
ayearandhasbeenprogrammedfor$11.448MillionSTATEfundsintheFY2016NJTIP.Project
expectstoreceiveauthorizationtoadvertiseinmidJanuary2018,awardthecontractaround
theendofMarch2018,andbesubstantiallycompletedinMarch2020.
SectionXIPage1
FY2015MAJORPROJECTSTATUS
DVRPC
Route30,BlueAnchorDam
COUNTY: Camden
MUNICIPALITY: WinslowTwp
STATUS:
ProjectreceivedauthorizationtoadvertiseonAugust29,2014andawardedthecontract
onNovember26,2014.ItwillbesubstantiallycompletedbyendofOctober2015.
Route38,Route30/130toNixonDrive
COUNTY: Burlington,Camden
MUNICIPALITY: MapleShadeTwp,CherryHillTwp,PennsaukenTwp,Moorestown
ProjectreceivedauthorizationtoadvertiseonDecember15,2014andasofJune3,2015,
STATUS:
hasbeensubstantiallycompleted.
Route38,Rt295toRt206
COUNTY: Burlington
MUNICIPALITY: MountLaurelTwp,HainesportTwp,LumbertonTwp,MountHollyTwp
STATUS:
ProjectreceivedauthorizationtoadvertiseonJuly14,2014;awardedthecontractonJuly
31,2014,andhasbeensubstantiallycompleted.ConceptDevelopmetnhasalsobeencompleted.
Route38,SouthChurchStreet(CR607)toFellowshipRoad(CR673),OperationalandSafety
Improvements
COUNTY: Burlington
MUNICIPALITY: MoorestownTwp
ThisprojectappearsontheFY2016NJTIPwithPreliminaryEngineeringphaseinFY16
STATUS:
andFinalDesign,RightofWay,andConstructioninthelaterfiscalyears.Concept
Developmenthasbeencompleted.APublicInformationCenterwillbeheldinNovember2016.
Environmentaldocumentisexpectedtobecompletedinlatesummer2020followedbyFinal
Designauthorizationattheendof2020.Projectexpectstoreceiveauthorizationtoadvertisein
2021andawardthecontractinJune2023.Itisestimatedthatthisprojectwillbesubstantially
completedbylateAugust2024.
Route42,ArdmoreAvetoCamdenCountyLine,Pavement
COUNTY: Gloucester
MUNICIPALITY: WashingtonTwp
ThisprojectappearsontheFY2016NJTIPwithaFinalDesignphaseinFY17,Rightof
STATUS:
WayphaseinFY17,andConstructionphasecashflowedtoFY19andFY20.Concept
DevelopmentwascompletedinJune2015.Itisexpectedthattheprojectwillhavecompleted
environmentdocumentsinNovember2015,authorizeFinalDesigninJuly2016,receive
authorizationtoadvertiseinthebeginningof2017,authorizeRightofWayinMarch2017,
authorizeUtilityWorkduringlatesummer2017,awardthecontractinearlyJuly2018,andbe
substantiallycompletedbyonorafter2019.
SectionXIPage2
FY2015MAJORPROJECTSTATUS
DVRPC
Route42,BridgesoverBlackwoodRailroadTrail
COUNTY: Camden
MUNICIPALITY: GloucesterTwp
STATUS:
ProjectisonscheduleandappearsontheFY2016NJTIP.AuthorizationofPreliminary
EngineeringisexpectedtooccuronAugust24,2015.ConceptDevelopmentwillbecompleted
inOctober2015.Apubilcinformationcenterwillbeheldlatefall2016.Projectexpectsto
completeenvironmentaldocumentsmidOctober2020,followbyauthorizationofFinalDesign
inmidFebruary2021,receiveauthorizationtoadvertiselatesummer2021,awardthecontract
inJuly2023,andbesubstantiallycompletedbyendofOctober2024.
Route42,NorthboundBridgeoverConrail(Abandoned)
COUNTY: Camden
MUNICIPALITY: GloucesterTwp
OnSeptember25,2014,thisprojectwascombinedintoRoute42,Bridgesover
STATUS:
BlackwoodRailroadTrail(DB#12313)(seeDVRPCTIPActionNJ1431).
Route47,GroveSt.toRoute130,Pavement
COUNTY: Gloucester
MUNICIPALITY: GlassboroBoro,WestvilleBoro,DeptfordTwp
ThisprojectappearsontheFY2016NJTIPforFinalDesigninFY17andConstruction
STATUS:
thatiscashflowedinFY19andFY20.ConceptDevelopmentwillbecompletedinOctober2015
andapublicinformationcenterwillbeheldonOctober28,2015.Itwillcomplete
environmentaldocumentationattheendofNovember2016,authorizeFinalDesigninmid
October2017,authorizeRightofWayinsummerof2018.Projectexpectstoreceive
authorizationtoadvertiseinApril2018,awardthecontractattheendofMarch2020,andbe
substantiallycompletedattheendofJune2021.
Route70,RedLionRoad(CR685)toDakotaTrail,Pavement
COUNTY: Burlington
MUNICIPALITY: SouthamptonTwp,WoodlandTwp
STATUS:
ConceptDevelopmentwascompletedonOctober15,2013.FundingforPreliminary
EngineeringandFinalDesignhavebeenauthorized.ProjectappearsontheFY2016NJTIPfor
constructioninFY16andFY17.ProjectexpectstoreceiveauthorizationtoadvertiseearlyJune
2016,awardthecontractmidAugust2016,andbesubstantiallycompletedinfall2017.
SectionXIPage3
FY2015MAJORPROJECTSTATUS
DVRPC
Route70,Route38toCropwellRoad
COUNTY: Camden,Burlington
MUNICIPALITY: PennsaukenTwp,CherryHillTwp,EveshamTwp
STATUS:
ThisprojectappearsintheFY2016NJTIPforFinalDesigninFY16,RightofWayin
FY18,andConstructioncashflowedinFY18andFY19.APublicInformationCenterwasheld
onJune15,2015.Environmentdocumentationisexpectedtobecompletedtowardstheendof
2015.AuthorizationofFinalDesignisexpectedinMay2016.RightofWaywillbecompletedin
2018.ContractwillbeawardedinOctober2018.Projectisestimatedtobesubstantially
completedinJanuary2020.
Route76/676,BridgeDeckReplacements
COUNTY: Camden
MUNICIPALITY: CamdenCity,GloucesterCity
ThisprojectappearsontheFY2016NJTIP.ConceptDevelopment(CD)wasinitiatedin
STATUS:
December2013fordeckreplacementsofthreebridgestructures:Rt76overKlemm
Ave/Conrail/S.Branch(structure1),Rt76overMainBranch(structure2),andRt676SBover
MainBranch(structure3).DuringCD,however,KlemmAvestructure(#1)wasfoundto
requireasuperstructurereplacement.Sincethen,CDwasreinitiatedfortheKlemmAve
structure(#1)andreinitiatedforanewstructure(#4),I76overNicholsonRoadthathas
substandardcrossslopesandtheroadwaycenterlinethatneededtoberevised.Asaresult,this
projectnowencompassesthesuperstructurereplacementandthreebridgedeckreplacements(I
76NB/SBovertheMainBranchofNewtonCreekandI76overNicholsonRoad).Ithasalso
resultedintwonewprojectsthatarerelatedtothisprojectthatappearsintheFY2016–2019NJ
TIP,whichmustalsocompleteConceptDevelopment:Route76,BridgesoverRoute130(DB
#11326A)andRoute676,BridgesoverNorthBranchofNewtonCreek(DB#14322).TheCD
reportsareexpectedtobecompletedtowardstheendof2015.ItisanticipatedthataFinal
DesigndesignerwillbeselectedfortheRt676bridges(DB#14322).Itisanticipatedthata
PreliminaryEngineeringdesignerwillbeselectedfortheRt76overRt130structures(DB
#11326A).
Route130,BrooklawnCircles
COUNTY: Camden
MUNICIPALITY: BrooklawnBoro
RightofWayhasbeenauthorized.Projectexpectstoreceiveauthorizationtoadvertise
STATUS:
inSeptember2015,awardcontractbytheendofOctober2015,andbesubstantiallycompleted
aroundmidJanuary2017.
SectionXIPage4
FY2015MAJORPROJECTSTATUS
DVRPC
Route130,CamdenCounty,Drainage
COUNTY: Camden
MUNICIPALITY: CollingswoodBoro
STATUS:
OnMay27,2014,theNJDOTCapitalProgramCommitteeterminatedtheproject.
DVRPCandCamdenCountyreachedouttoCollingswoodonMay16,2014butnoreceived
response.DVRPChasnotifiedthisCPCdecisiontobothcountyandmunicipality.Municipality
alsodidnotprovideNJDOTwithsupportingdatatoshowtheroadhadfrequentclosures.
Route130,RaccoonCreekBridgeReplacementandPavementRehabilitation
COUNTY: Gloucester
MUNICIPALITY: LoganTwp
ProjectwillreceiveauthorizationtoadvertiseinSeptember2015,awardcontractin
STATUS:
November2015,andbesubstantiallycompletedinApril2017.
Route130,WestfieldAve.toMainStreet
COUNTY: Mercer,Middlesex
MUNICIPALITY: EastWindsorTwp,CranburyTwp
STATUS:
ProjectisonscheduleandappearsontheFY2016NJTIP.FinalDesignisexpectedtobe
authorizedlateSeptember2015.RightofWayandUtilityworkisneeded.Constructionwillnot
occuruntil2019orlater.
Route168,BridgeoverBigTimberCreek
COUNTY: Gloucester
MUNICIPALITY: WashingtonTwp
FinalDesignandRightofWayhavebeenauthorized.ProjectappearsontheFY2016NJ
STATUS:
TIPwithconstructionstillprogrammedinFY18.Itisexpectedtobesubstantiallycompletedby
theendofApril2018.
Route168,MerchantStreettoFerryAvenue,Pavement
COUNTY: Camden
MUNICIPALITY: AudubonParkBoro,WoodlynneBoro,CamdenCity
ThisprojectappearsontheFY2016NJTIPforFinalDesigninFY17andconstructionin
STATUS:
FY18.ConceptDevelopmentandauthorizationforPreliminaryEngineeringhavebeen
completed.AsecondpublicinformationcenterwasheldonJuly14,2015.Environment
documentsareanticipatedtobecompletedinmidOctober2015.Projectexpectstoreceive
authorizationtoadvertiselateAugust2017,awardthecontractinlateNovember2017,andbe
substantiallycompletedaroundlateJanuary2019.
Route168,NewtonLakeDam
COUNTY: Camden
MUNICIPALITY: OaklynBoro,CamdenCity
ProjectwillreceiveauthorizationtoadvertiseonAugust24,2015,awardthecontract
STATUS:
endofOctober2015,andbesubstantiallycompletedinJanuary2017.
SectionXIPage5
FY2015MAJORPROJECTSTATUS
DVRPC
Route206,SouthBroadStreetBridgeoverAssunpinkCreek
COUNTY: Mercer
MUNICIPALITY: TrentonCity
STATUS:
ProjectisonscheduleandappearsontheFY2016NJTIP.FinalDesignisexpectedtobe
authorizedbytheendof2015.ProjectanticipatesreceivingauthorizationtoadvertiseonApril
26,2017,awardingthecontractonJune8,2017,andbesubstantiallycompletedbymidJuly
2018.
Route295/42,MissingMoves,Bellmawr
COUNTY: Camden
MUNICIPALITY: BellmawrBoro,MountEphraimBoro
ThisprojectappearsontheFY2016NJTIPforConstructionfromFY17toFY21at$155.4
STATUS:
milliontotal(almost$5millionofthetotalareearmarkfunds).Theenvironmentaldocument
wascompletedinSeptember2003.PreliminaryEngineeringandRightofWayhavebeen
authorized.FinalDesignisexpectedtobeauthorizedinAugust2015.Utilityworkisexpected
tobeauthorizedinFebruary2016.ProjectexpectstoreceiveauthorizationtoadvertiseinMay
2017withasubstantialcompletiondateofJanuary12,2021.
Route295/42/I76,DirectConnection,Contract2
COUNTY: Camden
MUNICIPALITY: BellmawrBoro,MountEphraimBoro
Contract2wasawardedinFebruary2014andexpectstobesubstantiallycompletedin
STATUS:
April2018.
Route295/42/I76,DirectConnection,Contract3
COUNTY: Camden
MUNICIPALITY: BellmawrBoro,MountEphraimBoro
STATUS:
Contract3oftheDirectConnectionprojectappearsontheFY2016NJTIPwith
ConstructionprogrammedfromFY16toFY19atatotalof$230million.Itreceived
authorizationtoadvertiseonAugust5,2016.Contract3isexpectedtobeawardedattheendof
October2016andtobesubstantiallycompletedinAprilof2020.
Route295/42/I76,DirectConnection,Contract4
COUNTY: Camden
MUNICIPALITY: BellmawrBoro,MountEphraimBoro
Contract4appearsintheFY2016NJTIPwithConstructionprogrammedfromFY19to
STATUS:
FY21foratotalof$200million.EnvironmentaldocumentswerecompletedinMarch2009and
FinalDesignwasauthorizedinSeptember2011.Authorizationtoadvertiseisexpectedtooccur
inNovember2018;contractawardisanticipatedinFebruary2019;andsubstantialcompletion
dateisestimatedtobeMarch2022.
SectionXIPage6
FY2015MAJORPROJECTSTATUS
NJTPA
GreenvilleYardandLiftBridge–StateofGoodRepair
COUNTY: Hudson
MUNICIPALITY: JerseyCity
STATUS:
InvestmentscontinuetorehabilitateinfrastructureatGreenvilleandinBrooklynthat
supportstheexistingCrossHarborrailcarfloatservice.ThePortAuthoritysNYNJRailroad
hasreceivedthefirsttwoofthreenewlocomotivesforfinaltesting.PANYNJexpectstoaward
contractsthissummertoconstructtwonewcarfloatbargesandapermanentreplacementfor
thefloatbridgeatGreenvillethatwasdestroyedbyHurricaneSandy.
NorthAvenueCorridorImprovementProject(NACI)
COUNTY: Union
MUNICIPALITY: ElizabethCity
Projectimplementationawaitingintergovernmentalagreement.
STATUS:
PANY&NJNJDOTProjectProgram
COUNTY: Hudson,Essex
MUNICIPALITY: JerseyCity,NewarkCity,KearnyTown
Route7WittpennBridge:Contract1complete.Contract2complete.Contract3
STATUS:
(underconstruction)12/2014bidcompletionanticipated10/2017.Contract3ACON
authorizationrequested6/2015completionanticipated4/2018.Contract4PS&Eanticipated
5/2016CONauthorization6/2016.Route139:Contract3complete.Route1&9TExtension:
complete.Route1&9PulaskiSkyway:Contract1complete.Contract2(underconstruction)
6/2013award3/2017completion.Contract3(underconstruction)6/2013award6/2015
completion.Contract4(underconstruction)3/2014bid6/2016completion.
RumsonRoadovertheShrewsburyRiver,CR520
COUNTY: Monmouth
MUNICIPALITY: RumsonBoro,SeaBrightBoro
STATUS:
ProjectisinthePreliminaryEngineeringphaseofwork.
Route3,Route46,ValleyRoadandNotch/RifleCampRoadInterchange,ContractA
COUNTY: Passaic
MUNICIPALITY: LittleFallsTwp,CliftonCity
Environment:AllDEPpermitscompletedin7/2014.
STATUS:
Plan:Theproject(ContractA)designworkwascompletedin9/2014.
Row:TheROWwasclearedin1/2015.
Schedule:Authorizationdateanticipated9/2015.CONcomplete1/2018.
SectionXIPage7
FY2015MAJORPROJECTSTATUS
NJTPA
Route3,Route46,ValleyRoadandNotch/RifleCampRoadInterchange,ContractB
COUNTY: Passaic
MUNICIPALITY: LittleFallsTwp,CliftonCity
STATUS:
Environment:AllDEPrelatedpermitsobtainedin7/2014(aspartofContractAwork).
Plan:Thisprojectisinfinaldesign.
Schedule:CONAuthorizationanticipatedon10/2017.CONcomplete3/2020.
Route37,MathisBridgeEastboundoverBarnegatBay
COUNTY: Ocean
MUNICIPALITY: TomsRiverTwp
Underconstruction.CONauthorizedin9/2014and2/2015.Completionanticipatedin
STATUS:
4/2019.
Route72,ManahawkinBayBridges,Contract4
COUNTY: Ocean
MUNICIPALITY: StaffordTwp
STATUS:
Contract4:Awardandconstructionwillbedoneafterthetrafficisdivertedontothe
newbridge(Contract2)CONanticipatedin2/2016withcompletionin11/2018.Contract5
(underconstruction)12/2014awardedcompletionin12/2017.Contract1(under
construction)12/2014awardedcompletionin7/2017.
Route80,WB,Pavement,Bergen&PassaicCounties
COUNTY: Passaic,Bergen
MUNICIPALITY: Various
Environment:AportionofI80inLodiisconstructedovertheMaywoodSuperfund
STATUS:
site.
ProjectisintheConceptDevelopmentphase.Theprojectwillreconstructapproximately9
milesofRouteI80Westboundpavement.PEauthorizationanticipated6/2017.
Route206,ValleyRoadtoBrownAvenue
COUNTY: Somerset
MUNICIPALITY: HillsboroughTwp
FinalDesignauthorizationanticipatedin11/2015,withcompletionin12/2018.
STATUS:
SectionXIPage8
FY2015MAJORPROJECTSTATUS
NJTPA
Route206Bypass,MountainViewRoadtoOldSomervilleRoad(Sections14A&15A)ContractB
COUNTY: Somerset
MUNICIPALITY: HillsboroughTwp
STATUS:
ThisprojectaddressestheareasimmediatelynorthandsouthoftheRoute206Bypass
ContractAbreakoutprojectandincludestheareabetweenMountainViewRoadand
HillsboroughRoadaswellastheareabetweenAmwellRoad(CR514)andOldSomerville
Road.
Row:Therightofwayacquisitionprocessisunderway.Fivenewparcelswillberequiredto
accommodatetheSmartSolutionschanges.AsixthparcelhasbeenplacedontheNational
andStateRegistersofHistoricPlacesandisalsoontheGreenAcresRecreationalandOpen
SpaceInventory.AGreenAcresscopinghearingwasheldin8/2010.
Schedule:AdvancedUtilityRelocationconstructionforContractBstartedinthesummerof
2013.CONauthorizationexpectedin3/2017withcompletionin8/2020.
Route278,GoethalsBridgeReplacement
COUNTY: Union
MUNICIPALITY: ElizabethCity
PermanentconstructionbeganinMay2014ofthereplacementbridge,whichwillhave
STATUS:
separateeastboundandwestboundroadwaydecks.Eastandwestboundtrafficwillbe
switchedoverfromtheexistingGoethalsBridgetothefirstcompletedspanofthereplacement
bridgebyyearend2016,withsubstantialcompletionofthenewcrossingbyyearend2017.
Demolitionoftheexistingbridgein2018willcompletetheproject.
Route280,Route21InterchangeImprovements
COUNTY: Essex,Hudson
MUNICIPALITY: NewarkCity,HarrisonTown
Environment:Ripariangrantrequiredtorebuildbulkhead.Permitapproved.
STATUS:
FinalDesignSubmission12/2013.
PS&ESubmission3/2015.
CONAdvertisement4/2015;2/2019completion.
Route440,BayonneBridgeNavigationalClearanceProject
COUNTY: Hudson
MUNICIPALITY: BayonneCity
ConstructioncontinuestorehabilitatetheBayonneBridgeroadway,includingprovision
STATUS:
of12footlanes,mediansafetydivider,emergencyshoulders,accelerationanddeceleration
lanes,fulllengthwalkway/bikeway,futuretransitpotential,andtoimprovethenavigational
clearance.Theprojectisapproximately40percentcompleteasofmid2015.ThePortAuthority
iscommittedtomaximizingtheenvironmentalandeconomicbenefitsofprovidingportaccess
forcleaner,moreefficient,PostPanamaxships.Theprojectgoalistoremovethenavigational
obstructionassoonaspossible,consistentwiththescheduledcompletionofthePanamaCanal
in2016.Fullprojectcompletionisscheduledtofollowin2018.
SectionXIPage9
FY2015MAJORPROJECTSTATUS
SJTPO
Route48,LaytonLakeDam
COUNTY: Salem
MUNICIPALITY: CarneysPointTwp
STATUS:
Underconstruction,anticipatedcompletiondateJune2018.
Route54,Route322overCapeMayPointBranch,ContractA
COUNTY: Atlantic
MUNICIPALITY: FolsomBoro
Underconstruction;anticipatedcompletiondateSeptember2016.
STATUS:
SectionXIPage10
FY2015MAJORPROJECTSTATUS
NJTRANSIT
BusAcquisitionProgram
COUNTY: Various
MUNICIPALITY: Various
CruiserBusPurchase(102in)(1371)(DebtService)
ProjectComplete
STATUS:
CruiserBusPurchaseDieselElectricHybrid(37)
Firstbusreceived:CurrentCompletiondate:8/15.Lastbusreceived:CurrentCompletion
STATUS:
date:2/16.
BusPassengerFacilities/ParkandRide
COUNTY: Various
MUNICIPALITY: Various
FrankR.LautenbergGroundTransp.Improv(BusLivability)
CurrentCompletiondate:12/15.
STATUS:
BusSupportFacilitiesandEquipment
COUNTY: Various
MUNICIPALITY: Various
HowellGarageCNGFillStationExpansion
CurrentCompletionDate4/16
STATUS:
CumberlandCountyBusProgram
COUNTY: Cumberland
MUNICIPALITY: Various
LocalCumberlandCtyBusProg(OperAssist)Outyears
AnticipateFY14andFY15funds.
STATUS:
DelcoLeadSafeHavenStorageandReinspectionFacilityProject
COUNTY: Various
MUNICIPALITY: Various
SANDYDelcoVehicleStorage
CurrentCompletiondate:6/21
STATUS:
HobokenLongSlipFloodProtectionProject
COUNTY: Various
MUNICIPALITY: Various
SANDYHobokenLongSlipFillImprovement
CurrentCompletiondate:12/18
STATUS:
SectionXIPage11
FY2015MAJORPROJECTSTATUS
NJTRANSIT
LackawannaCutoffMOSProject
COUNTY: Morris,Sussex,Warren
MUNICIPALITY: Various
LyndhurstStationReconstruction
Thisprojectiscurrentlyinthedesignphase.CurrentCompletiondateis2/19.
STATUS:
LackawannaCutoffPortMorrisAndover
CurrentCompletiondate:12/17.
STATUS:
LightRailVehicleRollingStock
COUNTY: Various
MUNICIPALITY: Various
LightRailVehicleCapacityExtendersHBLR(25),NLR(10)
Currentcompletiondate:11/16.
STATUS:
HudsonBergenLRTMOSII
ProjectComplete.
STATUS:
HudsonBergenLRTMOSI
STATUS:
ProjectComplete.
NLRCarLeasePayment(17)
Debtservicepaymentsongoing
STATUS:
NECElizabethIntermodalStationImprovements
COUNTY: Union
MUNICIPALITY: ElizabethCity
STATUS:
Theanticipatedadvertisementdateis2/2016withtheprojectcompletiondatein12/2018.
ElizabethIntermodalStationReconstruction
STATUS:
Thisprojectiscurrentlyinthedesignphase.CurrentCompletiondateis12/18.
NECNewarkIntermodal
COUNTY: Essex
MUNICIPALITY: NewarkCity
STATUS:
TheanticipatedprojectcompletiondateforPlatformContract2is4/2016.TheRoof
Contract2wascompletedin11/2013.
NewarkPennSta.PltfrmA,B,C,DRoof,ITS,PsngrAmenImprv
STATUS:
Thisprojectiscompleteandiscurrentlyinthecloseoutphase.
SectionXIPage12
FY2015MAJORPROJECTSTATUS
NJTRANSIT
NJTRANSITGridProject
COUNTY: Various
MUNICIPALITY: Various
SANDYNJTRANSITGRID
CurrentCompletiondate:11/21
STATUS:
NJTRANSITRaritanRiverDrawbridgeReplacementProject
COUNTY: Various
MUNICIPALITY: Various
SANDYRaritanRiverBridge
CurrentCompletiondate:2/22
STATUS:
PerthAmboyIntermodalADAImprovements
COUNTY: Middlesex
MUNICIPALITY: PerthAmboyCity
PerthAmboyHighLevelPlatformConstruction
CurrentCompletiondate4/19
STATUS:
PreventiveMaintenanceBus
COUNTY: Various
MUNICIPALITY: Various
MultiLevelCoachesOptionE,F(Additional50)(DebtService)
Debtservicepaymentsongoing
STATUS:
DualPowerLocoPurchase(4)(DebtService)
Debtservicepaymentsongoing
STATUS:
SFY14PreventiveMaintenanceRail(JARCPassThrough)
Ongoing
STATUS:
SFY16andBeyondPreventiveMaintenanceBus
Ongoing
STATUS:
SectionXIPage13
FY2015MAJORPROJECTSTATUS
NJTRANSIT
PreventiveMaintenanceRail
COUNTY: Various
MUNICIPALITY: Various
SFY16andBeyondPreventiveMaintenanceRail
Ongoing
STATUS:
MultiLevelCoachesOptionD(Additional37)(DebtService)
Debtservicepaymentsongoing
STATUS:
ElectricLocoPurchase(27)(DebtService)
Debtservicepaymentsongoing
STATUS:
MultiLevelCoachesOptionA,B,C(Additional131)(DebtService)
Debtservicepaymentsongoing
STATUS:
RailRollingStockProcurement
COUNTY: Various
MUNICIPALITY: Various
CometVPurchase(265Cars)(DebtService)
Debtservicepaymentsongoing
STATUS:
DualPowerLocoPurchase(22)(DebtService)
Debtservicepaymentsongoing
STATUS:
DieselLocoPurchase(33)(DebtService)
Debtservicepaymentsongoing
STATUS:
ElectricALP46LocomotivePurchase(29)(DebtService)
Debtservicepaymentsongoing
STATUS:
MultiLevelPowerCars(50)
ProjectComplete5/22
STATUS:
Section5310Program
COUNTY: Various
MUNICIPALITY: Various
LocalEandDBusPurchProgOutyears
AnticipateFY14andFY15funds.
STATUS:
Section5311Program
COUNTY: Various
MUNICIPALITY: Various
LocalRuralTransitProgramContractsOutyears
AnticipateFY14andFY15funds.
STATUS:
SectionXIPage14
FY2015MAJORPROJECTSTATUS
NJTRANSIT
SignalsandCommunications/ElectricTractionSystems
COUNTY: Various
MUNICIPALITY: Various
AutomaticEngineStartStopSystem(AESS)PL42
ProjectComplete2/15
STATUS:
SignalRenewalLongBranchtoBayHead
Installationisprogressing:Completiondateis9/18.
STATUS:
GladstoneCatenaryPoleResiliency
CurrentCompletionDate1/18
STATUS:
SJBRT/AvandaleParkRide
COUNTY: Camden
MUNICIPALITY: WinslowTwp
SJBRT/AvandaleParkRide(BusLivability)
Currentcompletiondate:7/17.
STATUS:
Small/SpecialServicesProgram
COUNTY: Various
MUNICIPALITY: Various
LocalEastWindsorCommShuttleOperSppt(FY1114)
CurrentCompletiondate:6/15.
STATUS:
TrainControlsWaysideSignals,Power&CommunicationResiliency
COUNTY: Various
MUNICIPALITY: Various
SANDYTrainControlsResilience
CurrentCompletiondate:12/20
STATUS:
TransitEnhancements/TranspAlternProg(TAP)/AlternTransitImprov(ATI)
COUNTY: Various
MUNICIPALITY: Various
BusSigns/SheltersMaint/UpgradeProg(FY1417)
CurrentCompletiondate:6/17.
STATUS:
SectionXIPage15
ȱȱ
SECTIONȱXIIȱ
ȱ
GLOSSARYȱ
FY20162025
STATEWIDETRANSPORTATIONIMPROVEMENTPROGRAM
Glossary
TableofContents
Section1
CapitalInvestmentStrategyCategories/AssetCategories
Section2
CoreMissions
Section3
PhasesofWork
Section4
FundingCategories
a.
NJDOT
b.
NJTRANSIT
Section5
MetropolitanPlanningOrganizations
Section6
AirQualityCodes
GLOSSARY
The following serves as a guide to terms used in the Statewide Transportation Improvement
Program:
SECTION1 CAPITALINVESTMENTSTRATEGYCATEGORIES/
ASSETCATEGORIES
TheNewJerseyStatewideCapitalInvestmentStrategy(SCIS)classifiesprojectsaccordingtothe
typeofworktobedone.
AirportAssets
Thisclassificationincludesworkthatisanticipatedtopreserve,maintainandimprove
NJAviationfacilitiesforthedevelopmentofanefficientairtransportationsystemthat
respondstotheneedsofitsusersandthepublic.AdministrationofNJAviationSystem
includes PublicUse Airports that consistof acomplexsystemoffacilitiesoperated by
State,County,Municipalandprivateentities.
BridgeAssets
This classification includes projects which are designed to keep existing bridges
functioningandinastateofgoodrepair,includingworkwhichrehabilitatesorreplaces
existing bridges to current design standards. Examples of work included within this
classificationare:
x Bridgerehabilitationandreplacement
x Bridgedeckrehabilitationandreplacement
x Bridgecapitalmaintenance
x Bridgemanagement
x Dams
CapitalProgramDelivery
Thisclassificationincludesprogramimplementationcostsforvariousphasesofprojects,
includingconstruction,contractorsupport,planningprogramsandstudies,scopingand
design,rightofwayandutilitywork,andqualityassurance.
CongestionRelief
Thisclassificationencompassesworkthatimprovestheflowofpeopleandgoodsalong
transportation corridors. Specific programs under this heading include highway
operational improvements, bottleneck widening, missing links, major widening,
intelligenttransportationsystemsandtraveldemandmanagement.
LocalSystemsSupport
This classification provides for development and implementation of transportation
improvementsonthelocalroadwaynetwork.Examplesofprogramcategorieswithin
this classification are local aid to counties and local aid to municipalities,
bicycle/pedestrian,regionalplanningandprojectdevelopment.
SectionXIIPage1
MassTransitAssets
Thisclassification includeslight rail, rail and bus physical assets required to bring the
transit system to a stateofgoodrepair. Examples of work within this classification
include:
x Track
x Structures
x ElectricTraction
x Signaling
x RollingStock,railcarsandbuses
x RailStations,busterminals,shelters
MultimodalPrograms
Thisclassificationincludesworkthataddressesimprovements/provisionsforalternative
modes of transportation. Program categories within this classification include goods
movement, bicycle/pedestrian, ferries, paratransit, intermodal connections, rail,
maritimeandothermodes.
RoadAssets
This classification includes projects which are designed to keep the existing highway
system functioning and in a state of good repair, including work which upgrades
segmentsofthesystemtocurrentdesignstandards(e.g.safetytreatmentsthatarepart
of a general roadway project such as signs, guiderail, barrier curb, traffic signals as
opposedtoindividuallineitemprogramsthatexclusivelyincludesignsortrafficsignals
only).Examplesofworkincludedinthisclassificationare:
x Resurfacing
x HighwayRehabilitationandReconstruction
x PavementManagementSystem
x DrainageManagement
x Landscape
x EnvironmentalRemediation
SafetyManagement
This classification includes safety programs aimed at reducing the frequency and
severity of crashes and promoting the allround engineering, education, and
enforcementapproachofSafetyFirst.“SafetyFirst”isfurtherreflectedinseveralother
NJDOT supported projects that utilize the 4E’s (Engineering, Education, Enforcement,
and Emergency Medical Services (quicker response and care) and other measures to
enhancesafetyandreducecrashes.Examplesofsafetymanagementprogramsare:
x IntersectionImprovementProgram
x SafeCorridors
x AccidentReduction
x CrossMedianCrashPrevention
x RailHighwayGradeCrossing,CapeMay
x RailHighwayGradeCrossing,State
SectionXIIPage2
x
x
x
x
x
x
x
x
x
x
RailHighwayGradeCrossing,Federal
TrainPreemptionforTrafficSignalsNorth
SafetyProjects
SafetyCapitalMaintenance
Betterments,Safety
RestripingProgram
TrafficSignalReplacement
SafetyManagementSystem
MotorVehicleCrashRecords
RockfallMitigation
TransportationSupportFacilitiesAssets
This classification includes projects designed to preserve, maintain and improve
physicalplantinfrastructureincludingofficebuildings,restareas,maintenancefacilities,
toll plazas and existing park and ride locations. Bus stops and train stations are
includedunderMassTransitAssets.
SECTION2 COREMISSION
The Departments mission has been broken up into five Core Missions as part of Governor
ChristiesPerformanceBudgetingInitiative.Performancedataandexpendituresaretiedtothe
CoreMissionslistedbelow.
10InfrastructurePreservation
Projects and programs with a primary focus on preserving, rehabilitating, or
reconstructingexistingphysicalassets,suchasroadsandbridges.
20Safety
Projects and programs with aprimary focuson improving publichealth and safetyof
motorists, pedestrians, cyclists and other users of the transportation network by
reducingtransportationrelatedfatalitiesandinjuries.
30OperationsandMaintenance
Routine and regular expenditures required to keep the highway surfaces, shoulders,
roadsides,structures,andtrafficcontroldevicesinusablecondition;maintainfacilities;
purchase winteroperations equipment,light trucks,cars, and construction equipment;
and respond to winter storms and emergencies. This core mission also include
administrative operations such as human resources, budget and accounting, which
supportmorethanoneofthecoremissions.
40MobilityandCongestionRelief
Projectsandprogramswithaprimaryfocusonmaintainingorincreasingthemovement
of passengers and goods. Projects and programs that are not safety or infrastructure
preservation,butthatimprovequalityoflife.
SectionXIIPage3
50MassTransit
Passenger transportationservicesoperatingon established schedules along designated
routesorlineswithspecificstopsandisdesignedtomoverelativelylargenumbersof
peopleatonetime.
SECTION3 PHASESOFWORK
Thisclassificationindicatesthestageofdevelopmentofaprojectasitmovesthroughtheproject
deliveryprocess.Thephasesoffeasibilityassessment(FA)andpreliminarydesign(PD)areno
longer being conductedon new projects, butsome projects have beengrandfathered through
completionofthesephases.ThecurrentNJDOTprojectdeliveryprocessinorderofoccurrence
is problem statement (PS), concept development (CD), preliminary engineering (PE), final
design (DES), rightof way (ROW), utilities (UTI), and construction (CON). The terms below
definevariousphasesofwork.
CAPCapitalAcquisition
Term used to denote the acquisition of rolling stock by NJ TRANSIT. Statewide
Investment (SWI)—NJ TRANSIT uses this designation to describe a series of
coordinatedsmallerscaleprojectsinmultiplelocations,andinmultiplephasesofwork,
thataddressaspecificmobilityissue.
CD/LCDConceptDevelopment
The Concept Development Phase purpose is to identify and compare reasonable
alternatives and strategies that address a welldefined and welljustified Purpose and
Need Statement and select a Preliminary Preferred Alternative (PPA). The PPA is
selectedbasedonseveralfactors,includingenvironmentalimpacts,constructability,cost
effectiveness, and if the project can be constructed in a timely manner. This phase
involvesdatacollection,internalandexternalstakeholdercoordination,andalternatives
analysis.AlongwiththePPA,keyproductsthatareproducedinthisPhaseincludethe
Purpose and Need Statement, the National Environmental Policy Act (NEPA)
Classification, and the Concept Development Report. CD denotes NJDOT Concept
DevelopmentPhase;LCDdenotesconceptdevelopmentbyalocalentity(MPO,county,
municipality).
CONConstruction
Theconstructionphasereferstothephaseortypeofworkinvolvingtheactualbuilding
ofaproject.
DESFinalDesign
ThepurposeoftheFinalDesignPhaseistoproducetheproject’sconstructioncontract
documents (i.e., Final Plans, Specifications, and Cost Estimate (PS&E) for use in
soliciting bids from prospective contractors, and advancing the project to the
Construction Phase. This Phase includes the continuation and completion of
environmental and engineering tasks initiated in the Preliminary Engineering Phase,
such as roadway design, bridge design, right of way and access engineering, utility
SectionXIIPage4
engineering, environmental permits and clearances, and community outreach. The
completionofthosetaskswillinvolvevariousinternalandexternalprojectstakeholders.
Stakeholder coordination ranges from onboard project review meetings with internal
offices to efforts with local officials, the general public and other State and federal
agencies. Efforts with the public and local officials are guided by a projectspecific
publicinvolvementactionplan.TheFinalDesignPhaseiscompletedwhentheproject
isauthorizedforconstruction,whichinitiatestheConstructionPhaseofprojectdelivery.
ECDesignandConstruction
Fundingisprovidedforbothdesignandconstructioncosts.
ERCDesign,RightofWayandConstruction
Fundingisprovidedfordesign,rightofway,and/orconstructioncosts.
FA/LFAFeasibilityAssessment
A phase of work intended to develop feasible project proposals that produce the best
balance among transportation needs, environmental values, public concerns andcosts.
Theendproductsofscopingare:arecommendedschemewitharealisticcostestimate;
an approved environmental document; reasonable assurance that environmental
permits can be obtained; community support, or documentation explaining why such
supportcannotreasonablybeobtained;andidentificationofrightofway(ROW)needs
and costs. Scopingconsists of twophasesin NJDOT: Feasibility assessment and final
scope development. FA denotes feasibility assessment by NJDOT; LFA denotes local
feasibilityassessmentbyalocalentity(MPO,county,municipality).
PD/LPDPreliminaryDesign
Preliminary designis the processof advancingpreliminary engineering and obtaining
formal community and environmental approval of the Initially Preferred Alternative.
PDdenotespreliminarydesignbyNJDOT;LPDdenoteslocalpreliminarydesignbya
localentity(MPO,county,municipality).
PE/LPEPreliminaryEngineering
ThePreliminaryEngineeringPhaseinvolvesperformingengineeringtasksandtechnical
environmental studies to obtain formal community consensus (through a public
information center) of the study and to secure the approval of the environmental
document.Ifadesignexceptionisnecessaryonaproject,preparationandapprovalof
the Design Exception Report will occur during this Phase. During the Preliminary
EngineeringPhaseanumberofactivitiesaresimultaneouslysetinmotionbasedonthe
PPA such as community involvement (meetings with affected property, business
owners),agencyconsultation,environmentaldocumentation,designlevelmapping,and
the development of geometric design. PE denotes NJDOT Preliminary Engineering
Phase; LCD denotes preliminary engineering by a local entity (MPO, county,
municipality).
SectionXIIPage5
PLSPlanningStudy
Aphaseortypeofworkinvolvingtrafficstudiesneedsanalyses,corridorstudies,and
otherworkpreparatorytoprojectdevelopment.Seealso“ConceptDevelopment.”
PRDProjectDevelopment
A phase or type of work used by NJ TRANSIT which is intended to develop feasible
project proposals that produce the best balance among transportation needs,
environmentalvalues,publicconcernsandcosts.
PSProblemScreening
TheProblemScreeningPhaseistheentranceintothedeliveryprocessforanypotential
project.Thepurposeofthephaseistoinvestigateapotentialtransportationproblem.A
potentialproblemisdevelopedintoaProblemStatement(PS)andsubmittedtoCapital
InvestmentStrategies(CIS).ThesourcesoftheProblemStatementmayincludeNJDOT
Management Systems, Planning Studies, a Metropolitan Planning Organization, or
internal and external stakeholders. This phase involves a Tier 1 Screening, a Tier 2
ScreeningoraManagementSystemInitiativeScreening.Iftheproblemisvalidated,a
recommendationisadvancedforreviewandapprovalbytheCapitalProgramScreening
Committee(CPSC)andtheCapitalProgramCommittee(CPC).
The objective of the Problem Screening Phase is to effectively, efficiently, and
consistently screen transportation problems in agreement with the Statewide Capital
Investment Strategy (SCIS) and project prioritization criteria. Achieving this goal is
expected toproduceselectiveproposals that areconsistent with the SCIS performance
related goals, objectives and investment targets for potential advancement while
conformingtoStateandfederalrequirements.
ROWRightofWay
Ageneraltermdenotingland,property,orinteresttherein,usuallyinastripacquired
forordevotedtotransportationpurposes.
UTILUtility
Insomecases,theutilityrelocationworkassociatedwithaprojectmustbeprogrammed
separatelyfromtheactualconstructionphaseofwork.Theseitemsareshownunderthe
“Utility”category.
SECTION4 FUNDINGCATEGORIES
Projectsarefundedundervariousfundingcategories,dependingonthetypeofwork.
a. NJDOTFUNDINGCATEGORIES
BRIDGEOFF
This federalaid funding category provides funds for the rehabilitation or
replacementofbridgesdefinedasstructurallydeficientand/orfunctionallyobsolete
SectionXIIPage6
according to federal definitions. This funding is used for bridges that are off the
federalaidsystem.
CMAQCongestionMitigationandAirQuality
This federalaid funding category was established under the federal Intermodal
SurfaceTransportationEfficiencyActof1991(ISTEA)toprovidefundingforprojects
that improve air quality and/or relieve congestion without adding new highway
capacity. This program was designed to help states meet their Clean Air Act
obligations.ThefederalMovingAheadforProgressinthe21stCenturyAct(MAP
21)hasanincreasedfocusonaddressingPM2.5.
DEMODemonstrationFunds
Federal transportation acts sometimes target specific projects in various states in
addition to general programs for federal support. This funding category includes
“demonstration”fundingprovidedunderISTEA,aswellas“highpriorityproject”
funding provided under Transportation Equity Act for the 21st Century (TEA21)
and Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for
Users (SAFETEALU). These projects, with “demonstration” or “high priority
project”fundingoftenhavespecialrulesofuse.
FBP–FHWAFerryBoatProgram
Federal funds are allocated for improvements to ferry boats and ferry terminal
facilitiesthroughoutthestate.
HSIPHighwaySafetyImprovementProgram
This federalaid funding category was established under SAFETEALU with the
purpose ofsignificantly reducing trafficfatalities and serious injurieson all public
roadsinacomprehensiveandstrategicmannerconsistentwiththeState’sStrategic
Highway Safety Plan. MAP21 has continued this program with a focus on
performancemeasuresandtargets.
LTAP–LocalTechnicalAssistanceProgram
Federal funds are allocatedfor the center that provides information and training to
local governments and agencies to foster a safe, efficient, and environmentally sound
surface transportation system by improving skills and increasing knowledge of the
transportation workforce and decision makers.
NHPPNationalHighwayPerformanceProgram
As established by MAP21, the National Highway Performance Program provides
support for the construction of new facilities on the National Highway System
(NHS), the condition and performance of the NHS, and achieving performance
targets,assetbythatState’sassetmanagementplan.
OTHER
Thisrepresentsfundingprovidedfromothersources,includingbutnotlimitedto,
SectionXIIPage7
bistateandautonomousauthorities,privateentities,andlocalgovernments.
PANY&NJ
ThisrepresentsfundingprovidedPortAuthorityofNewYorkandNewJersey.
PL/PLFTAPlanning
This federalaid funding category provides funds for the federally mandated
transportation planning process conducted within each Metropolitan Planning
Organization.
RHCRailHighwayGradeCrossingsProgram
This is a federal funding category which is intended to develop and implement
safetyimprovementprojectstoreducethenumberandseverityofcrashesatpublic
highwayrail grade crossings. Eligible activities include: signing and pavement
markingsatcrossings;activewarningdevices;crossingsurfaceimprovements;sight
distance improvements; grade separations; and the closing and consolidation of
crossings.
RTPRecreationalTrailsProgram
New Jersey’s Recreational Trails Program provides grants to public agencies and
nonprofit organizations for a variety of trail projects. The NJ Department of
EnvironmentalProtection,DivisionofParksandForestry,istheadministratorofthe
program.
SPR/SPRFTAStatewidePlanningandResearch
Federal law requires a percentage of funds allocated to states for highway
improvementstobedevotedtoplanningandresearchactivities.
STPSurfaceTransportationProgram
The Surface Transportation Program is a federalaid funding category established
underISTEA,whichencompassesfundingpreviouslymadeavailableundervarious
smallerfederalaidcategoriesaswellasabroad,flexiblecomponent.Fundingmust
besetasidefortransportationenhancement(STPTE).Suballocationsmustbemade
to urbanized and nonurbanized areas (STPNJ, funding provided to NJTPA; STP
STU,fundingprovidedtoDVRPC;STPSJ,fundingprovidedtoSJTPO).
STATE
The“STATE”or“TTF”categoryisusedtoshowthedispositionoffundingreceived
fromtheNewJerseyTransportationTrustFund.
TBDToBeDetermined
Funding has not yet been determined for the unconstrained years of the Capital
Program.
TAPTransportationAlternativesProgram
The Transportation Alternatives Program provides funding for programs and
SectionXIIPage8
projectsdefinedastransportationalternatives,includingonandoffroadpedestrian
and bicycle facilities, infrastructure projects for improving nondriver access to
public transportation and enhanced mobility, community improvement activities,
and environmental mitigation; recreational trail program projects; safe routes to
schoolprojects;andprojectsfortheplanning,designorconstructionofboulevards
andotherroadwayslargelyintherightofwayofformerInterstateSystemroutesor
otherdividedhighways.
b. NJTRANSITFUNDINGCATEGORIES
NJ Transit funding categories are indicated generally by reference to federal
statutorycategoriesandareidentifiedasfollows:
CASINOREVENUE
Annual allocation of the 8.5% of the Casino Revenue Fund appropriated for
transportationservicesforseniorcitizenanddisabledresidents.
COPSCertificatesofParticipation
Funds freed up on existing COPS Notes substituting insurance policy for a cash
reservefundtoguaranteepaymenttothenoteholders.
CMAQCongestionMitigationandAirQuality
This federalaid funding category was established under the federal Intermodal
SurfaceTransportationEfficiencyAct(ISTEA)tosupportprojectswhichimproveair
quality and/or relieve congestion without adding new highway capacity. These
funds are especially targeted for states like New Jersey with serious air quality
problems.
FFGAFullFundingGrantAgreements
FFGAs are authorized under Federal transit law and are the designate means for
providingnewstartsfundstoprojects.
MATCH
These are local funds that are needed to match federal funding (JARC and SECT
5311).
METRONORTH
Funding received from the MetroNorth Commuter Railroad of the New York
MetropolitanTransportationAuthority.
OPEROperating
Thesearefareboxrevenuefunds.
OTHER
Thirdpartyfundsrepresentfundingprovidedfromothersources,includingbutnot
limited to, bistate and autonomous authorities, private entities, and local
governments.
SectionXIIPage9
PANYNJ
ThisrepresentsfundingprovidedPortAuthorityofNewYorkandNewJersey.
SECT5307Section5307
Under MAP21 this program has been consolidated to include the Job Access and
Reverse Commute (JARC) program (formally SECT 5316). Federal Transit
Administration Urbanized Area Formula Program, including funding for
TransportationEnhancements(SECT5307TE),TransportationAlternativesProgram
(SECT5307TAP),andAssociatedTransitImprovements(SECT5307ATI).
SECT5309Section5309
SeeSECT5339(BusandBusFacilitiesProgram).
SECT5310Section5310
Enhanced Mobility of Seniors and Individuals with Disabilities. This program
provides formula funding to increase the mobility of seniors and persons with
disabilities. The former New Freedom Program (SECT 5317) is folded into this
program.
SECT5311Section5311
Nonurbanized Area Formula Program — Federal funding is provided for rural
public transportation programs (formerly known as the Section 18 Program). Job
Access and Reverse Commute (JARC) program funds are also eligible under the
RuralAreaFormulaProgram.
SECT5324Section5324
Assists States and public transportation systems with emergencyrelated expenses.
Emergenciesare defined asnatural disasters affecting a wide areaora catastrophic
failure from an external cause for which the governor of a State has declared an
emergencyorthePresidenthasdeclaredamajordisaster.Theprogramfundscapital
projects to protect, repair, reconstruct or replace equipment and facilities. It also
funds transit agency operating costs related to evacuation, rescue operations,
temporary public transportation service or changing public transportation route
servicebefore,duringorafteranemergencyinanareadirectlyaffected.
SECT5326Section5326
TransitAssetManagement.MAP21requiresFTAtodefinetheterm“stateofgood
repair” andcreateobjective standards for measuring theconditionofcapital assets,
including equipment, rolling stock, infrastructure, and facilities. All FTA grantees
andtheirsubrecipientsarerequiredtodeveloptransitassetmanagementplans.FTA
willsupportthiseffortthroughtechnicalassistance,includingthedevelopmentofan
analytical process or decision support tool that allows recipients to estimate their
capitalinvestmentneedsovertimeandassistswithassetinvestmentprioritization.
SectionXIIPage10
SECT5337Section5337
MAP21 establishes a new formulabased State of Good Repair grant program
dedicated to repairing and upgrading the nation’s rail transit systems along with
highintensity motor bus systems that use highoccupancy vehicle lanes, including
budrapidtransit(BRT).ThisprogramreplacestheFixedGuidewayModernization
program (SECT 5309). Projects are limited to replacement and rehabilitation, or
capitalprojectsrequiredtomaintainpublictransportationsystemsinastateofgood
repair. Projects must be included in a Transit Asset Management Plan to receive
funding.Thenewformulacomprises:(1)theformerFixedGuidewayModernization
formula;(2)anewservicebasedformula;and(3)anewformulaforbusesonHOV
lanes.
SECT5339Section5339
BusandBusFacilitiesFormulagrantprogram.Anewformulagrantprogramwhich
replacesSection5309.Thiscapitalprogramprovidesfundingtoreplace,rehabilitate,
and purchase buses and related equipment, and to construct busrelated facilities.
Funds are eligible to be transferred by the state to supplement urban and rural
formulagrantprograms(SECT5307andSECT5311,respectively).
SECT5340Section5340
HighDensityandGrowingStateApportionments.
STATE
The“STATE”categoryisusedtoshowthedispositionoffundingreceivedfromthe
NewJerseyTransportationTrustFund.
STPSurfaceTransportationProgram
The Surface Transportation Program is a federalaid funding category established
underISTEA,whichencompassesfundingpreviouslymadeavailableundervarious
smallerfederalaidcategoriesaswellasabroad,flexiblecomponent.Fundingmust
besetasidefortransportationenhancement(STPTE).Suballocationsmustbemade
to urbanized and nonurbanized areas (STPNJ, funding provided to NJTPA; STP
STU,fundingprovidedtoDVRPC;STPSJ,fundingprovidedtoSJTPO).
TAPTransportationAlternativesProgram
TheTransportationAlternativesProgramconsolidatesfundingfromFHWA’sformer
Transportation Enhancements, Recreational Trails, and Safe Routes to School
programs. MAP21 eliminates the 10 percent setaside under the Surface
TransportationProgramfor“transportationenhancements”andreplacesitwiththe
new “transportation alternatives” program. Eligible activities are broadly defined
and with respect to transit include construction, planning and design of
infrastructurerelated projects and systems that will provide safe routes for non
drivers, including children, older adults and individuals with disabilities to access
daily needs, and historic preservation and rehabilitation of historic transportation
facilities.
SectionXIIPage11
TODTransitOrientedDevelopment
MAP21createsanewdiscretionarypilotprogramforTransitOrientedDevelopment
planninggrants.Eligibleactivitiesincludecomprehensiveplanningincorridorswith
newrail,busrapidtransitorcorecapacityprojects.
SECTION5 METROPOLITANPLANNINGORGANIZATIONS
Metropolitan Planning Organizations (MPOs) are planning organizations that serve as the
forum for cooperative transportation decision making for metropolitan planning areas as
requiredbyfederalregulations.MPOsconsistofrepresentativesofstateandlocalgovernments
andmajortransportationagencies.TherearethreeMPOsinNewJersey:
DVRPCDelawareValleyRegionalPlanningCommission
TheMPOcoveringthecountiesofMercer,Burlington,Camden,andGloucester.
NJTPANorthJerseyTransportationPlanningAuthority
The MPO covering the counties of Bergen, Essex, Hudson, Hunterdon, Middlesex,
Monmouth,Morris,Ocean,Passaic,Somerset,Sussex,UnionandWarren.
SJTPOSouthJerseyTransportationPlanningOrganization
TheMPOcoveringthecountiesofCapeMay,Atlantic,Cumberland,andSalem.
SECTION6AIRQUALITYCODES
An alphanumeric air quality (AQ) coding scheme has been developed for projects and
programs.TheAQcodeisappliedbytheMPOsaspartoftheconformitydeterminationand
exempteligibilityidentificationprocess.
For nonexempt projects (projects for which no exemption code applies), the first conformity
analysisyearfollowingtheproject’sopeningorprojectedcompletionislisted(analysisyearsin
the current conformity determination include 2014, 2015, 2020, 2030, and 2040). The letter
followingtheyearindicateswhethertheprojectwasmodeled(M)ornotmodeled(NM)inthe
regionaltraveldemandmodeloriftheprojectwasanalyzedusinganoffmodeltechnique(O).
Offmodeltechniquesarecommonlyusedforprojectsthatcannotbeadequatelyrepresentedin
thetraveldemandmodel.
TheCleanAirActregulationsalsoprovideforprojectsthatmaybeexemptfromtheconformity
analysis.Anexemptprojectisdefinedasaprojectthatprimarilyenhancessafetyoraesthetics,
maintainsmasstransit,continuescurrentlevelsofridesharing,orbuildsbicycleandpedestrian
facilities. There are several categories of exempt projects, and each STIP page indicates the
specific exemption code (note that multiple exemption codes may apply to a particular
project/program). Exempt projects in design phases are classified under the planning and
technicalstudiescategory.Alistofexemptcategoriesisshownbelow.
Even though projects may be exempt, theMPOs mayinclude those that representchangesin
thetraveldemandmodelandthoseforwhichVMToremissionssavingshavebeenestimated,
where possible. Theseprojects are noted by including the analysis year and modeling status
SectionXIIPage12
within parentheses following the exemption code(s). Projects for which conformity does not
apply (e.g., freight rail projects) have been labeled “NA”. Projects determined to be “Not
RegionallySignificant”anddonotfitintoanexemptcategoryhavebeenlabeled“NRS”.
AirQualityCodes
AQCode
ExemptProjectCategory
AirQuality
A1,AQ1
Continuationofridesharingandvanpoolingpromotionactivitiesatcurrentlevels
A2,AQ2
Bicycleandpedestrianfacilities
ExemptfromRegionalEmissionAnalysis
NR1,R1
Intersectionchannelizationprojects
NR2,R2
Intersectionsignalizationprojectsatindividualintersections
NR3,R3
Interchangereconfigurationprojects
NR4,R4
Changesinverticalandhorizontalalignment
NR5,R5
Trucksizeandweightinspectionstations
NR6,R6
Busterminalsandtransferpoints
MassTransit
M1,MT1
Operatingassistancetotransitagencies
M2,MT2
Purchaseofsupportvehicles
M3,MT3
Rehabilitationoftransitvehicles
M4,MT4
Purchaseofoffice,shop,andoperatingequipmentforexistingfacilities
M5,MT5
Purchaseofoperatingequipmentforvehicles(e.g.,radios,fareboxes,lifts,etc.)
M6,MT6
Constructionorrenovationofpower,signal,andcommunicationssystems
M7,MT7
Constructionofsmallpassengersheltersandinformationkiosks
Reconstructionorrenovationoftransitbuildingsandstructures(e.g.,railorbus
M8,MT8 buildings,storageandmaintenancefacilities,stations,terminals,andancillary
structures)
Rehabilitationorreconstructionoftrackstructures,track,andtrackbedinexisting
M9,MT9
rightsofway
Purchaseofnewbusesandrailcarstoreplaceexistingvehiclesorforminorexpansions
M10,MT10
ofthefleet
Constructionofnewbusorrailstorage/maintenancefacilitiescategoricallyexcludedin
M11,MT11
23CFR771
SectionXIIPage13
AQCode
ExemptProjectCategory
Other
O1,X5
Engineeringtoassesssocial,economic,andenvironmentaleffectsoftheproposed
actionoralternativestothataction
O2,X6
Noiseattenuation
O3,X7
Advancelandacquisitions(23CFR712or23CFR771)
O4,X8
Acquisitionofsceniceasements
O5,X9
Plantings,landscaping,etc.
O6,X10
Signremoval
O7,X11
Directionalandinformationalsigns
Transportationenhancementactivities(exceptrehabilitationandoperationofhistoric
O8,X12
O9transportationbuildings,structures,orfacilities)
Repairofdamagecausedbynaturaldisasters,civilunrest,orterroristacts,except
O9,X13
projectsinvolvingsubstantialfunctional,locationorcapacitychanges
PlanningandTechnicalStudies
O10a,X1
Planningandtechnicalstudies
O10b,X2
Grantsfortrainingandresearchprograms
O10c,X3
Planningactivitiesconductedpursuanttotitles23and49U.S.C
O10d,X4
Federalaidsystemsrevisions
Safety
S1
Railroad/highwaycrossing
S2
Hazardeliminationprogram
S3
SafernonFederalaidsystemroads
S4
Shoulderimprovements
S5
Increasingsightdistance
S6
Safetyimprovementprogram
S7
Trafficcontroldevicesandoperatingassistanceotherthansignalizationprojects
S8
Railroad/highwaycrossingwarningdevices
S9
Guardrails,medianbarriers,crashcushions
S10
Pavementresurfacingand/orrehabilitation
S11
Pavementmarkingdemonstration
S12
Emergencyrelief(23U.S.C.125)
S13
Fencing
S14
Skidtreatments
S15
Safetyroadsiderestareas
S16
Addingmedians
S17
Truckclimbinglanesoutsidetheurbanizedarea
S18
Lightingimprovements
S19
Wideningnarrowpavementsorreconstructingbridges(noadditionaltravellanes)
S20
Emergencytruckpullovers
SectionXIIPage14