About us
A Joint Venture Between
&
The World leaders in Hoverbarges
with over 30 years experience in the design & manufacture of Hoverbarges
The CTO of HTS has been involved in every Hoverbarge in the following
presentation, designing the first modular one back in the early 1970s.
© Hovertrans Solutions Pte. Ltd. 2014
2
ST Engineering / ST Marine
ST Engineering – rank among the largest companies listed on the Singapore Exchange, and
one of Asia’s largest defence and engineering groups
ST Engineering - global workforce of more than 20,000 with a turnover in 2010 of S$5.98b
($4.79b USD)
ST Marine can provide full spectrum capabilities from design, construction, repair and
maintenance of specialised commercial and naval ships in ultra modern facilities
© Hovertrans Solutions Pte. Ltd. 2014
3
What is a Hoverbarge?
Cargo Deck
Air Lift Fans
Buoyant Steel Structure
Air Cushion
A standard steel barge, built to marine rules with an air cushion system
to provide lift.
Hovering 1.8m in the air, the Hoverbarge is amphibious enabling it to
traverse, wetlands & mudflats etc.
© Hovertrans Solutions Pte. Ltd. 2014
4
What is a Hoverbarge?
Hoverbarge floating
off hover with a 90
tonne payload.
© Hovertrans Solutions Pte. Ltd. 2014
5
Hovercraft v Hoverbarge
Hovercraft reach a speed where the skirt lifts out of the water (over hump) and then hover just
above the water surface.
The Hoverbarge travelling a slower speed of 5 knots will always remain under hump speed with
the tip of the skirts in the water. This results in less spray than high speed Hovercraft.
High speed Hovercraft
Over hump speed =
skirts clear of water surface
© Hovertrans Solutions Pte. Ltd. 2014
Hoverbarge
Always under hump speed =
skirt tips in the water
6
Air is fed into the skirt plenum chamber and
the skirt creates a flexible seal around the
periphery of the barge
© Hovertrans Solutions Pte. Ltd. 2014
7
Air feeds into the skirt that seals the periphery
The base is flat with no feet or
protrusions
© Hovertrans Solutions Pte. Ltd. 2014
8
Previous Hoverbarge Projects
The management team have been
involved in all of these Hoverbarge
projects.
300T Payload 2009
160t Ferry Crossing 1976
50t Bog Drilling 1978
200t Siberian 2009 Cold Weather
330t swamp drilling 2008
50t Core Sampling 1979
Hoverbarge projects conducted by:
Mackace Ltd., Hovertrans Inc. and Hovertrans Ltd.
Ice Breaking Hoverbarge 1980
© Hovertrans Solutions Pte. Ltd. 2014
250t Deep Sea 1976
9
Hoverbarge Advantages
Minimal Environmental Footprint
The Hoverbarge only exerts 1psi ground pressure when on hover, compared to a human footprint
of 7-8psi, thus the Hoverbarge has minimal impact to the terrain it travels over.
Large Flat top deck
The Hoverbarge has a large cargo deck, clear of any equipment, along with being flat top
(rather than in a well deck) the Hoverbarge provides huge flexibility in the type of operations
it can be deployed on.
© Hovertrans Solutions Pte. Ltd. 2014
10
Hoverbarge Advantages
Redundancy
In soft mud / water conditions, the Hoverbarge has 100% redundancy built into its lift fan
capacity, ensuring minimal disruption to operations in the event of an engine failure.
Engine Enclosures
Engine enclosures are designed to ensure the engine, fuel tank and lift fans are protected
from extreme temperature. The housing also reduces sound levels and shore power can
supply heaters in the enclosures whilst the craft is not in service.
© Hovertrans Solutions Pte. Ltd. 2014
11
Hoverbarge Advantages
Skirt System
The segmented skirt system provides added redundancy, where if a segment is damaged the
one either side balloons out to fill the gap, minimising any air loss. Replacement of damaged
skirts can be done on site and does not require special skills or tools
Missing skirt segment – the
one each side fills the gap
Skirt following contours of the ground
Skirt R&D – Hovertrans Solutions is constantly improving designs for different applications
© Hovertrans Solutions Pte. Ltd. 2014
12
Modular Hoverbarge
 Reduced Shipping Costs
 Access to inland areas via trucks
 Easy to use on different projects
 Use the pontoons as standard
marine pontoons
 Steel Construction
 Easy to assemble on site
The first Modular Hoverbarge was
invented by the CTO of Hovertrans
Solutions in the 1970’s.
© Hovertrans Solutions Pte. Ltd. 2014
13
Mono Hull Hoverbarge
• Increased payload
• Can be built on-site
• Ideal for long term contracts
• Built to certification
© Hovertrans Solutions Pte. Ltd. 2014
14
Launching the Hoverbarge
Once built or re-assembled the Hoverbarge
can be launched direct from a beach or
graded river bank.
© Hovertrans Solutions Pte. Ltd. 2014
15
Large Payloads
• Best application for air cushion
technology
• Moving a 250 ton oil storage tank
soon led to a 4000 ton tank being
relocated
• The Sea Pearl could lift the cross
channel Hovercraft on its back
• Larger deck area = higher payload
© Hovertrans Solutions Pte. Ltd. 2014
16
Size & Cost
• For a small increase in size with little
extra power, the payload increases
significantly
Cost
• As the Hoverbarge size increases, the
cost increases in steps
Increase in Payload
Hoverbarge
Hoverbarge
200t Payload
300t Payload
© Hovertrans Solutions Pte. Ltd. 2014
17
Propulsion
Methods of propulsion
include:
Amphibious Tracked Vehicle
Shallow Draft Tug Boats
•
•
•
•
Amphibious tractors
Tugs
Winching
Ducted Props (for smaller
Hoverbarges)
Pictures on the Right:
Some examples of methods
used to move the non
propelled Hoverbarge
© Hovertrans Solutions Pte. Ltd. 2014
Amphibious Tractor
Shore Based Winch System
Swamp Excavator
18
Self Propelled Hoverbarge
Ducted Propellers – as currently
used on Hovercraft can propel the
Hoverbarge up to speeds of 5
knots
Picture shows the Tiger 40
Hovercraft
© Hovertrans Solutions Pte. Ltd. 2014
19
Self Propelled Hoverbarge
© Hovertrans Solutions Pte. Ltd. 2014
20
Moving Anchor
To move the large Hoverbarges, a smaller Hoverbarge can be used as a
moving anchor point for the larger Hoverbarge to winch up to
© Hovertrans Solutions Pte. Ltd. 2014
21
Example Hoverbarge Applications
© Hovertrans Solutions Pte. Ltd. 2014
22
100 tonne payload self Propelled
Hoverbarge
© Hovertrans Solutions Pte. Ltd. 2014
23
440 tonne Self Propelled Hoverbarge on
frozen lake
© Hovertrans Solutions Pte. Ltd. 2014
24
Moving Modules
• Transport large
prefabricated modules to
remote sites
• Avoid building infrastructure
such as road, rail and bridges
• Avoid dredging
• Use on multiple projects
Length = 177m
Width = 75m
Payload = 2500t
© Hovertrans Solutions Pte. Ltd. 2014
25
Shallow Water Drilling
7000 tonne hover drilling complex, designed for working in 0-5m of water.
Beach can be used as a safe haven.
Hoverbarges can be brought together to form a larger drilling pad
© Hovertrans Solutions Pte. Ltd. 2014
26
Wetlands / Swamp Drilling
330 tonne payload hover drilling barge in Suriname
Keyway drill slot
© Hovertrans Solutions Pte. Ltd. 2014
27
Shallow Water Oil Spill Response
• Shallow water oil spill response
• Environmentally sensitive areas
• Reed beds / Wetlands
• Access when shore based approach is restricted
© Hovertrans Solutions Pte. Ltd. 2014
28
Wind Farms
•Access shallow water
• Operate regardless of
tide – help against limiting
operational factors such as
wildlife seasons
• Transport parts
• Cable laying
• Move equipment such as
excavators
• Offshore support
platform for directional
drilling
© Hovertrans Solutions Pte. Ltd. 2014
No need to stop work
when the tide is out!
29
Ship to Shore
• Access tidal zones
• No need for docks / port
• No need to dredge
• Gain access quickly
without having to build
infrastructure
• Operate over mudflats
and shallow water
© Hovertrans Solutions Pte. Ltd. 2014
30
The Hoverbarge Fleet
Workboat Hoverbarge
Piling Hoverbarge
© Hovertrans Solutions Pte. Ltd. 2014
31
The Hover Onshore Pipeline Fleet
Construction onshore
© Hovertrans Solutions Pte. Ltd. 2014
32
Hoverbarge Flexibility Covers all Phases
Equipment delivery
Piling
© Hovertrans Solutions Pte. Ltd. 2014
Oil spill response 24/7
Repair and maintenance
33
Ice Road Alternative
• Access sites all year
• Operates at 1 psi ground pressure
• Avoid damage to the tundra
• Transport heavy loads
• Eliminate the need for long term
storage
• Use in emergencies
© Hovertrans Solutions Pte. Ltd. 2014
34
Tidal / Mudflat Access
• Access 24 hours a day
• Operates at 1 psi ground pressure
• Avoid damage to the soft mud
• Transport heavy loads
© Hovertrans Solutions Pte. Ltd. 2014
35
HOVER90TM – Charter Hoverbarge
A new 90 tonne payload modular Hoverbarge has just been built ready for
chartering.
Dimensions
34m (111’)
17m (56’)
24m (80’) L x 7m (24’) W
1.52m (5’)
1.8m (6’)
Outside Length
Outside Width
Cargo Deck Area
Depth (Hull)
Hover Height
Technical Details
Payload
Deck Loading
Max Speed
Certification
Construction
Lift Engines
Engine Emissions
Approx Fuel
Consumption
Range
Lift Fans
Skirt Type
90 tonnes
10t/m2
5 knots (towed)
ABS: A1
EH 36 Steel
MAN Diesel (Qty 2)
Tier 2
308 l/hr (81 US Gallons per hour) excludes
generator
120 miles (approx) at 5 knots
2 x Hovertrans Solutions Centrifugal lift fans
Hovertrans Solutions Hoverbarge segmented
skirt system
© Hovertrans Solutions Pte. Ltd. 2014
36
HOVER90TM – Charter Hoverbarge
© Hovertrans Solutions Pte. Ltd. 2014
37
HOVER90TM – Charter Hoverbarge
© Hovertrans Solutions Pte. Ltd. 2014
38
HOVER90TM – Charter Hoverbarge
http://youtu.be/cmB9gU5PWxc
© Hovertrans Solutions Pte. Ltd. 2014
39
Summary
• Hovertrans Solutions Pte. Ltd. has the most experienced Hoverbarge design team in the
World with the infrastructure support of ST Marine enabling us to offer:
–
–
–
–
Route Surveys / viability reports
Full Feasibility Studies
Hoverbarge Design & Manufacture
New 90 tonne demonstrator/charter Modular Hoverbarge being built in 2011
• Heavy loads can be transported to sites using Hoverbarges
• Smaller self propelled Hoverbarges can be used for supplies
• Eliminates the need for infrastructure
© Hovertrans Solutions Pte. Ltd. 2014
40
Contact
Dan Turner, Chief Technology Officer
Tel: + 44 (0) 1794 519239 (UK)
[email protected]
Jim Ireland, Regional Director Business Development
Tel: (1) 832-431-3026 (USA)
[email protected]
www.hovertranssolutions.com
Hoverbarge pictures used within this presentation are of Hoverbarges
built by Mackace Ltd. Hovertrans Inc., Hovertrans Ltd. & ST Marine
© Hovertrans Solutions Pte. Ltd. 2014
41
Thank You
© Hovertrans Solutions Pte. Ltd. 2014
42