The coming of Europe`s offshore wind energy industry

The coming of Europe’s offshore wind energy industry
Anne-Bénédicte Genachte
Regulatory Affairs Advisor – Offshore Wind Power
European Wind Energy Association
06 December 2011
Presentation outline
•
•
•
•
•
Offshore wind installed capacity
Market shares
Future growth
Trends
Supply chain
First offshore wind farm
Vindeby (DK), online in 1991
Tech. specs.:
- 11 WT of 450 kW (0.45 MW)
- Distance to shore 1.5 km to 3 km
- Water depth 2m to 6m
- Distance between turbines 500m
- Total area 3km²
- Hub height 35m above sea level
- Rotor diameter 35m
Largest offshore wind farm (to date)
Thanet (UK), online in 2010
Tech. specs.:
- 11 WT of 450 kW (0.45 MW)
- Distance to shore 1.5 km to 3 km
- Water depth 2m to 6m
- Distance between turbines 500m
- Total area 3km²
Production 11.2 GWh per year
Capacity factor 21.1%
Hub height 35m above sea level
Rotor diameter 35m
Tech. specs.:
- 100 WT of 3MW
- Distance to shore 7km to 8.5km
- Water depth 20m to 25m
- Distance between turbines 800m
- Total area 35km²
- Hub height 70m above sea
- Rotor diameter 90m
Installed capacity
Global cumulative installed capacity
Donghai Daquiao
(China)
Vindeby
Tech. specs.:
- 100 WT of 3MW
- Distance to shore 7km to 8.5km
- Water depth 20m to 25m
- Distance between turbines 800m
- Total area 35km²
- Hub height 70m above sea
- Rotor diameter 90m
Thanet
Installed capacity
Share of new offshore capacity and share of new onshore capacity
Tech. specs.:
- 100 WT of 3MW
- Distance to shore 7km to 8.5km
- Water depth 20m to 25m
- Distance between turbines 800m
- Total area 35km²
- Hub height 70m above sea
- Rotor diameter 90m
Presentation outline
•
•
•
•
•
Offshore wind installed capacity
Market shares
Future growth
Trends
Supply chain
Market shares
1991
total 4.95 MW
1995
total 11.95 MW
0%
0%
0%
DK
100
%
0%
DK
83%
2000
total 35.5 MW
0%
NL
17%
2005
total 695 MW
SE
8% UK
0% 0%
DE NL SE
1% 3% 3% EI
3%
11%
NL
53%
DK
28%
DK
59%
UK
31%
Market shares
2010
total 2,946 MW
NO
0%
2011 (30 June)
total 3,295 MW
IE FI
DE
1% 1%
3%
NO IE FI
0% 1% 1%
SE
5% DE
6%
SE
6% BE
7%
UK
45%
NL
8%
DK
29%
UK
48%
BE
6%
NL
7%
DK
26%
Presentation outline
•
•
•
•
•
Offshore wind installed capacity
Market shares
Future growth
Trends
Supply chain
Future growth
EU cumulative installations onshore/offshore to 2030
Tech. specs.:
- 100 WT of 3MW
- Distance to shore 7km to 8.5km
- Water depth 20m to 25m
- Distance between turbines40GW
800m
- Total area 35km²
- Hub height 70m above sea
- Rotor diameter 90m
150GW
EWEA SCENARIOS FOR 2020 & 2030
Summary of offshore wind energy in 2020
• 40GW offshore installed capacity
• Meeting 4% of EU electricity demand
• Offshore wind energy’s share of EU wind energy
production increasing to 25.5%
• Annual installations of 6.9 GW (28% of wind installations)
• Annual investments of €10.4 bn (39.1% of wind
investments)
Future growth
Historical onshore growth compared to EWEA offshore projection
Tech. specs.:
- 100 WT of 3MW
- Distance to shore 7km to 8.5km
- Water depth 20m to 25m
- Distance between turbines 800m
- Total area 35km²
- Hub height 70m above sea
- Rotor diameter 90m
Summary of offshore wind energy in 2030
• 150GW offshore installed capacity
• Meeting between 12.8% and 16.7% of EU electricity
demand
• Annual installations of 13.7 GW (58% of wind
installations)
• Annual investments of €17.1 bn offshore (67% of wind
investments)
Total offshore wind capacity installed, under construction, consented,
planned at 30 June 2011 and per sea basin in MW
Presentation outline
•
•
•
•
•
Offshore wind installed capacity
Market shares
Future growth
Trends
Supply chain
Trends
Distance and water depth of wind farms
BARD 1 (DE)
Alpha Ventus (DE)
Thanet
Vindeby
East Anglia Array (UK)
Tech. specs.:
- 100 WT of 3MW
- Distance to shore 7km to 8.5km
- WaterBeatrice
depth 20m
to 25m
(UK)
- Distance between turbines 800m
Prinses Amalia (NL)
- Total area 35km²
- Hub height 70m above sea
- Rotor diameter 90m
Trends
Distance and water depth of wind farms
H2-20 (DE)
Hornsea (UK)
Tech. specs.:
- 100 WT of 3MW
Palamos (ES)
- Distance to shore 7km to 8.5km
Dogger Bank- (UK)
Water depth 20m to 25m
- Distance between turbines 800m
- Total area 35km²
- Hub height 70m above sea
- Rotor diameter 90m
Roses (ES)
Presentation outline
•
•
•
•
•
Offshore wind installed capacity
Market shares
Future growth
Trends
Supply chain
Supply chain – Wind in our Sails – key elements
• Supply chain is dynamic and responding to challenges
through investments in innovation:
–
–
–
–
–
Turbines
Substructures
Electrical infrastructure
Vessels
Ports
KEY MESSAGES
• The European Union leads the world in offshore wind
power with 4,000MW already installed
• This major industrial development will bring a significant
number of jobs and create development opportunities for
European companies
• However, there are still challenges ahead and support is
needed:
– Favourable national framework conditions: NREAPs,
licensing and permitting procedures, maritime spatial
planning, reinforcement of onshore networks
– Support from the EU: stable post-2020 legislative
framework, offshore grid
Thank you for your attention
www.ewea.org
EWEA