Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 1 of 47 TRANSMISSION GREEN ENERGY PLAN 1 2 INDEX 3 4 1.0 THE OBJECTIVES OF THE GREEN ENERGY AND GREEN ECONOMY ACT AND HYDRO ONE’S GREEN ENERGY PLAN 7 2.0 DETERMINING NEED FOR GREEN ENERGY PROJECTS 8 3.0 TRANSMISSION PLANNING 9 4.0 MAJOR GREEN PROJECTS 10 5.0 OTHER GREEN PROJECTS 11 6.0 INFRASTRUCTURE INVESTMENT INCENTIVE APPROACH FOR 5 6 GREEN ENERGY 12 13 7.0 DEVELOPMENT WORK FOR GREEN PROJECTS 14 8.0 RECOVERY OF OM&A DEVELOPMENT COSTS Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 2 of 47 1 2 1.0 THE OBJECTIVES OF THE GREEN ENERGY AND GREEN ECONOMY ACT AND HYDRO ONE’S GREEN ENERGY PLAN 3 4 This Green Energy Plan (the “Plan”) outlines Hydro One’s strategy to implement the 5 Government of Ontario’s policy objectives in the Green Energy and Green Economy Act, 6 2009 (“GEGEA”). All of the Green Energy Projects (“GE Projects”) discussed in this 7 Plan are included in a letter dated September 21, 2009 from the Minister of Energy and 8 Infrastructure to Hydro One. A copy of the Minister’s letter is attached in Appendix A to 9 this exhibit. The letter noted that “the Ontario Power Authority (OPA) and Hydro One 10 have worked together to identify areas in the province that would benefit from specific 11 transmission and distribution upgrades to enable renewable generation likely to be 12 forthcoming through the feed-in tariff program.” The letter went on to ask Hydro One to 13 “immediately proceed with the planning, development and implementation of 14 Transmission Projects outlined in the attached Schedule A, including seeking approvals 15 for the upgrades as soon as there is a reasonable basis to do so.” 16 17 Facilitating the Connection of Renewable Power 18 19 With respect to the connection of renewable energy generation facilities, the GE Projects 20 are required to connect new renewable generation facilities procured through the Feed-In 21 Tariff (“FIT”) program and other means. While the timing and nature of some GE 22 Projects will depend on the results of the FIT program, this Plan encompasses 23 transmission investments that will form the backbone of an electricity system re-designed 24 to integrate up to 10,000 MW and beyond of potential renewable generation. 25 26 On a long-term integrated basis, the transmission investments required to enable the 27 renewable potential in the province would significantly expand the transmission network. 28 These projects represent a major renovation of Ontario’s power system and are required Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 3 of 47 1 because: 2 • grid and/or the Province’s load centres; 3 4 The vast majority of potential renewable generation is remote from the transmission • The present capability of the transmission system is inadequate for the incorporation and transfer of the additional power; 5 6 • New generators will require connection to the bulk system (enabler lines); and 7 • Existing stations will require upgrades so that the necessary transformation, voltage 8 support and short-circuit capability is available to accommodate distributed 9 generation and to ensure appropriate power quality for load customers. 10 11 2.0 DETERMINING NEED FOR GREEN ENERGY PROJECTS 12 13 Hydro One continues to consult collaboratively with the Ontario Power Authority 14 (“OPA”) in defining the scope of work associated with the GE Projects. The OPA 15 performed the Transmission Availability Test (TAT) to determine which FIT applications 16 could connect using existing transmission capacity. Renewable generation that did not 17 qualify under TAT would require additional transmission facilities. In this regard the 18 OPA is developing the Economic Connection Test (ECT) analysis. The ECT will assist 19 in assessing where transmission facilities will be required to connect FIT applicants who 20 cannot connect to the existing transmission network due to lack of available capacity. 21 Hydro One’s plans for new GE projects will be based on the OPA’s identification of need 22 or direction from the government. 23 24 Hydro One’s strategy is to begin the preliminary Development Work on priority GE 25 Projects, those with the highest need as identified in consultation with the OPA and based 26 on the information presently available. Development Work involves all the work that 27 must be completed prior to construction, including: evaluating alternatives; consulting Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 4 of 47 1 with stakeholders; obtaining the necessary approvals; and identifying impacted 2 properties. 3 4 The early commencement of these priority projects is necessary to meet the in-service 5 dates for new generation. Development Work for major transmission projects can take 6 up to five or six years – significantly more than the time required to actually build the 7 new generation. This is discussed more fully in section 7.0. 8 9 When the project development work has obtained sufficient information to move forward 10 with a specific project, the formal identification of need is presented through a Section 92 11 application or a future cost of service proceeding before the Board. Hydro One will bring 12 forward Section 92 applications on the line construction projects that it is developing. 13 Some of the Schedule B projects, Enabling TS’s, SVC’s and In-Line Circuit Breakers 14 will not require Section 92 applications. Determination of need will be developed in 15 consultation with the OPA and Board approval for these projects will be sought through 16 cost of service rate applications. 17 18 3.0 TRANSMISSION PLANNING 19 20 Hydro One’s Green Energy Plan must be integrated within the context of Hydro One’s 21 overall approach to planning and managing its system. Hydro One manages its 22 transmission assets within the framework of an asset management system. This approach 23 involves systematic and coordinated activities and practices through which Hydro One 24 optimally and sustainably manages the transmission assets and asset systems, their 25 associated performance, risks and expenditures over their life cycles for the purpose of 26 achieving the corporate strategic plan. Further details about Hydro One’s Transmission 27 planning process can be found in Exhibit A, Tab 4, Schedule 1. 28 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 5 of 47 1 Hydro One primarily uses two concurrent approaches when managing its transmission 2 system and will need to broaden this approach to include the Green Energy projects: 3 1. A forward looking approach with respect to anticipated transmission system needs 4 and developments. Such outlook typically goes beyond the current business planning 5 period. 6 2. A life cycle management approach which considers and balances asset performance, 7 costs and associated risks during the asset service life in order to achieve asset 8 optimization. 9 10 1) The forward looking approach takes a longer term view for the transmission system 11 and shows that the scope and scale of anticipated needs and developments that Hydro 12 One will face are unprecedented with respect to magnitude and timeframe required for 13 implementation. There are two primary drivers for this: 14 • Electricity System Transformation: The electricity system in Ontario is undergoing 15 major transformation as new clean energy initiatives as well as new technologies and 16 innovation are introduced. Aging generation resources must be replaced with a new 17 generation mix to include more renewable resources and distributed generation; and 18 conservation and demand management is emphasized in the journey towards a 19 greener and more environmentally sustainable province. This transformation is being 20 influenced to a large extent by the policies and priorities set by the Ontario 21 government as reflected in the GEGEA. In addition to the current FIT applications 22 under review by the OPA, many more applications are expected to be submitted in 23 the future. It is also anticipated that additional economic investments similar to the 24 Korean Consortium (Samsung) initiative will be pursued by the Government. 25 • Aging Assets: Many of the transmission assets are aging and there are increasing 26 requirements to sustain the existing asset base in order to maintain reliable 27 performance. This will require new approaches to project prioritization to properly 28 assess the importance of aging asset issues relative to the Green Energy projects. Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 6 of 47 1 2 2) The life cycle management approach will create the need to sustain the transmission 3 asset base including the changing electricity system in Ontario. 4 challenges and demands on the transmission system but it will also present opportunities 5 for leadership and innovation to meet the needs of load and generator customers and 6 ensure continued safe, reliable and cost effective operation of the transmission system. This will present 7 8 The Green projects will require Hydro One to adjust its Sustaining and Operations work 9 programs in the future to maintain and operate assets but the main integration of the 10 Green Energy projects will be required in the Transmission Development work area. 11 12 Impact on Transmission Development: Going forward, the transmission development 13 work program will, to a large extent, be influenced by the policies and priorities set by 14 the Ontario government as reflected in the GEGEA. 15 development will be driven by the need to connect and incorporate large numbers and 16 amounts of Renewable Energy Resources. Over the long-term, Hydro One investments 17 for incorporating potential renewable generation with the vast majority being remote 18 from the transmission grid and/or the Province’s load centres will focus on the following. 19 • In particular, transmission Projects to Increase Network Transfer Capability & Enable Connection of 20 Renewable Energy Facilities: The 20 projects identified in Schedule A of the 21 Minister’s letter of September 21, 2009 are crucial for connecting anticipated 22 renewable generation facilities and the Minister asked Hydro One to “immediately 23 proceed with the planning, development and implementation of the 20 Green 24 Transmission Projects, including seeking approvals for the upgrades as soon as there 25 is a reasonable basis to do so”. 26 • Projects to Facilitate Generation Connections to the Distribution System: Schedule 27 B of the Minister’s letter identified a number of other investments that will be 28 required to remove constraints on the transmission system that currently limit the Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 7 of 47 1 amount of new Distributed Generation (DG) that can be accommodated. These 2 investments include the Hearn, Leaside and Manby TS upgrades, as well as building 3 enabling TSs, In-Line Circuit Breakers and other transmission facilities to enable 4 more DG to be connected downstream from TSs. These investments also cover the 5 development of standards, enhancements, modifications, and replacement of 6 protection and control equipment to allow mass deployment of Distributed Generators 7 on the Hydro One system. 8 9 Hydro One will need to be prepared to adapt to changes in plans brought about by the 10 GEGEA. The FIT program is essentially a customer driven program so that project 11 location and sizes are not predetermined. The economic development objectives of the 12 GEGEA will lead to commercial arrangements such as the Korean Consortium 13 (Samsung) agreement where in exchange for job creation and other economic benefits 14 some companies may be guaranteed capacity on the Transmission system and Hydro One 15 will have to accommodate these needs. 16 17 On a long-term basis, investments for incorporating potential renewable generation are 18 expected to be a significant component of the Transmission Development budget. As 19 explained above, the present capability of the transmission system is inadequate for the 20 incorporation and transfer of the additional capacity new generators will require to 21 connect to the bulk system and existing stations will require upgrades so that the 22 necessary transformation, voltage support and short-circuit capability is in place to 23 accommodate renewable generation and to ensure appropriate power quality for load 24 customers. These investments represent a major renovation of Ontario’s power system 25 and such unprecedented renewal of the transmission system is expected to result in a very 26 significant increase in the transmission network. 27 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 8 of 47 1 Ten Year Transmission Development Expenditure Levels 2 3 Projects driven by this Green Energy Plan will constitute a major portion of the 4 Transmission Development capital work program in the near term, 2010 – 2014 and over 5 the longer term, 2015 – 2020. Hydro One expects to spend $2.5B in the 2010 – 2014 6 timeframe and an additional $4.5B in the 2015 – 2020 period on these investments. 7 8 4.0 MAJOR GREEN PROJECTS 9 10 Descriptions of the Major Green Projects are provided in this section. Preliminary 11 Development Work is underway for the projects where the OPA has indicated there is the 12 highest indication of need. Table 1 below lists the projects from Schedule A of the 13 Minister’s Sept. 21, 2009 letter. The projects are grouped in three categories: 14 1. Projects where Preliminary Development Work is Underway 15 2. Projects where Development Work will begin once OPA Confirms Project Need 16 3. Projects where Development Work is Not Planned in the Test Years 17 18 The Item Number as per Schedule A of the Minister’s letter is indicated in column 3 of 19 the table. The development costs associated with these projects are provided in Section 20 8.0. Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 9 of 47 Table 1 1 2 Summary of Major Green Projects 3 4 Item Item Number as per Investment Description # Schedule A Projects where Preliminary Development Work is Underway 1 East-West Tie Expansion 1 2 Transmission Reinforcement West of London 5 3 North-South Transmission Expansion 2&3 4 Manitoulin Island Enabler 8 5 Algoma x Sudbury Transmission Expansion 4 6 Goderich & Huron South Area Enablers 7&9 7 Northwest Transmission Reinforcement 14 Projects where Development Work will begin once OPA Confirms Project Need 8 9 10 11 12 13 14 15 Sudbury North - Pinard TS x Hanmer TS Pembroke Area Enabler Parry Sound Enabler North Bay Enabler Thunder Bay Enabler St. Lawrence TS x Merivale TS (Cornwall x Ottawa) Selby Junction x Belleville TS Chenaux TS x Galetta Junction 18 10 11 12 13 15 16 17 Projects where Development Work is Not Planned in the Test Years 16 17 18 5 Longwood TS x Middleport TS Bowmanville SS x GTA Kenora x Thunder Bay Transmission Expansion 19 6 20 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 10 of 47 1 4.1 Projects where Development Work is Underway 2 3 1) East-West Tie Expansion 4 5 6 7 To provide an additional 300-500 MW of transfer capacity, Hydro One plans to build a 8 280 km 230 kV transmission line by widening an existing right-of-way. A 120 km 9 extension of the line to Lakehead is under consideration. In addition to facilitating the 10 transfer of new renewable generation from Northwestern Ontario to the load centres in 11 the province, this project is also expected to alleviate westbound congestion upon the 12 closure of the coal-generating facilities in the Northwest. 13 14 15 OM&A Development Work Capital Expenditures ($ Millions) ($ Millions) 12.0 511.0 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 11 of 47 1 2) Transmission Reinforcement West of London (formerly London x Sarnia) 2 3 4 5 Hydro One will begin to identify transmission solutions that accommodate the significant 6 interest in wind generation development in the area west of London. The interest here 7 could exceed 1,000 MW, and based on the capacity of the existing system, it will be 8 necessary to build new transmission lines to incorporate it. 9 10 To provide an additional 1000 MW of transfer capacity, Hydro One plans to build three 11 single-circuit 500 kV or 230 kV transmission lines from: 12 1) Lambton TS to Longwood TS, 2) Lambton TS to Chatham SS, and 3) Chatham SS to 13 Longwood TS 14 This project is primarily aimed at facilitating the connection of renewable energy. 15 OM&A Development Work Capital Expenditures ($ Millions) ($ Millions) 22.5 706.0 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 12 of 47 1 3) North-South Transmission Expansion 2 3 To provide an additional 1500-2000 MW of transfer capacity, Hydro One plans to build a 4 350 km 500 kV transmission line on an existing right-of-way from Sudbury to the GTA. 5 All the planned generation for Northern Ontario will need to be funnelled through this 6 North-South corridor, and the existing facilities are fully utilized. The additional capacity 7 created by other planned projects (e.g. SVCs) has already been allocated. Therefore, this 8 project is required for the development for any additional generation in Northern Ontario. 9 This project is primarily aimed at facilitating the connection of renewable energy. 10 11 OM&A Development Work Capital Expenditures ($ Millions) ($ Millions) 18.5 884.0 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 13 of 47 1 4) Manitoulin Island Enabler 2 3 Manitoulin Island has the potential for a large amount of wind generation. Presently, the 4 transmission access to Manitoulin Island is provided by a single 115 kV, 50 km line from 5 Espanola TS (located between Algoma station near Blind River and Martindale station in 6 Sudbury) to Manitoulin TS (near Little Current). To provide an additional 400 MW of 7 transfer capacity, Hydro One plans to build a 80-120 km 230 kV transmission line. A 8 new switching station at Espanola is also needed. The actual length and terminal points 9 for the Enabler Line would be determined on the basis of the generation need as 10 articulated by the OPA and the EA Approval work. This project is aimed at facilitating 11 the connection of renewable energy. 12 13 OM&A Development Work Capital Expenditures ($ Millions) ($ Millions) 7.5 169.0 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 14 of 47 1 5) Algoma x Sudbury Transmission Expansion 2 3 The Ontario Power Authority’s “Integrated Power System Plan” (Section E-3-2) has 4 identified 1,000 MW of wind generation in the Sault Ste. Marie/Algoma area. Major 5 transmission reinforcement will be required for this level of development. To meet this 6 need the IPSP had recommended a second 500 kV Hanmer TS to Mississagi transmission 7 line (approximately 210 km). The new line would be located on an existing Right of 8 Way. Because the EA Approval for the new line was obtained earlier (when the first 500 9 kV line, initially operated at 230kV, was built on the Right of Way), it is expected that 10 only a confirmation of the EA approval will be required. The new line would provide a 11 transfer capability of about 1,400 MW assuming that the existing companion line could 12 be converted to operation at 500 kV. These reinforcements can be coordinated to match 13 resource developments in the Sault/Algoma area. This project is aimed at facilitating the 14 connection of renewable energy. 15 16 OM&A Development Work Capital Expenditures ($ Millions) ($ Millions) 5.5 431.6 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 15 of 47 1 6) Goderich and Huron South Area Enablers 2 3 4 The OPA has identified Goderich and Huron South as areas with substantial renewable 5 development potential. Based on the latest information received from the OPA regarding 6 the possible location of the renewable generator proponents, two main options are under 7 consideration. 8 currently serves Goderich TS to 230 kV line. The second involves the creation of a 9 500/230 kV autotransformer station from which 230 kV enabler lines will extend towards 10 the predominant clusters of renewable projects. This plan is subject to change as further 11 information is provided by the OPA and as the environmental assessment and preliminary 12 engineering work is carried out. Both of these are scalable and able to accommodate the 13 400 to 800 MW of projects expected in the area. These projects are aimed at facilitating 14 the connection of renewable energy. The first involves the conversion of an existing 115 kV line which 15 16 OM&A Development Work Capital Expenditures ($ Millions) ($ Millions) 6.0 164.0 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 16 of 47 1 7) Northwest Transmission Reinforcement (formerly Pickle Lake x Nipigon) 2 3 4 There is potential to develop 85 MW of economic hydroelectric generation on the Little 5 Jackfish River north of Lake Nipigon. In addition, there is potential development of up 6 to 278 MW of wind generation along the eastern shore of Lake Nipigon that will become 7 economical if transmission is available to connect them to the network. There is also 8 potential for approximately 580 MW of wind generation on the west side of the lake. The 9 Ontario Power Authority’s “Integrated Power System Plan” (Section E-3-7) had 10 identified these wind and hydro developments as preferred options to meet the 2025 11 Renewable Generation Target of the Ontario Minster of Energy’s directive to the OPA. 12 Ontario Power Generation is preparing plans for development of Little Jackfish 13 generation for coming in-service by the end of 2014. 14 15 In addition, there is growing demand from the mining industry, First Nations and other 16 remote communities in the Patricia District for additional supply. The additional supply 17 capacity in the district is required by the end of 2013 or earlier. 18 19 To enable the development of the renewable resources of Lake Nipigon and to reinforce Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 17 of 47 1 the transmission network in the Patricia District (and the East-West interties in the 2 future), a new single circuit 230 kV transmission line is proposed from Nipigon TS to 3 Little Jackfish and Crow River DS near Pickle Lake. 4 5 This project is aimed at both facilitating the connection of renewable energy and 6 facilitating economic development. This project also supports Northern Development. 7 8 OM&A Development Work Capital Expenditures ($ Millions) ($ Millions) 21.7 399.5 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 18 of 47 1 2 4.2 Projects where Development Work will begin once OPA Confirms Project Need 3 4 8) Sudbury North - Pinard TS x Hanmer TS 5 6 Most of the major hydroelectric generation opportunities in Ontario are located in an area 7 north of Sudbury. Currently, as much as 2,400 MW of hydroelectric generation 8 development has been committed or planned (in the long term) in this region. To 9 facilitate the development and integration of these generators into the Ontario power grid, 10 the need for an adequate transmission capacity north of Sudbury has been identified by 11 the Ontario Power Authority in the Integrated Power System Plan (Section E-3-3). The 12 reference plan calls for one new 370 km single circuit 500 kV transmission line from 13 Pinard TS to Hanmer TS in Sudbury. Additional lines may be required if extensive 14 Hydroelectric Generation development were to materialize in the north. This project is 15 aimed at facilitating the connection of renewable energy. 16 OM&A Development Work Capital Expenditures ($ Millions) ($ Millions) 5.0 1,234.0 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 19 of 47 1 9) Pembroke Cluster Enabler 2 3 4 The OPA has identified 200 MW of renewable generation potential west of Barry’s Bay. 5 To accommodate this generation, a new 45 km 230 kV single-circuit line may be 6 required. 7 8 The actual length and terminal points for the Enabler Line would be determined on the 9 basis of FIT Applications received by the OPA and the EA Approval work. This project 10 is primarily aimed at facilitating the connection of renewable energy. 11 12 OM&A Development Work Capital Expenditures ($ Millions) ($ Millions) 8.0 137.0 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 20 of 47 1 10) Parry Sound Enabler 2 3 4 An enabler line is identified for connecting a large pocket of renewable resources located 5 north of Parry Sound. A single-circuit 230 kV line, 75 km in length, would allow 240 6 MW of wind generation to be incorporated from the Parry Sound area. This line may use 7 the existing 500 kV corridor and connect to Parry sound TS. 8 9 The actual length and terminal points for the Enabler Line would be determined on the 10 basis of FIT Applications received by the OPA and the EA Approval work. This project 11 is aimed at the connection of renewable energy. 12 13 OM&A Development Work Capital Expenditures ($ Millions) ($ Millions) 5.5 121.0 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 21 of 47 1 11) North Bay Enabler 2 3 4 An enabler line is identified for connecting a large pocket of renewable resources located 5 south of North Bay. A single-circuit 230 kV line, 54 km in length would allow 400 MW 6 of wind generation to be incorporated. The line would connect to Trout Lake TS. 7 8 The actual length and terminal points for the Enabler Line would be determined on the 9 basis of FIT Applications received by the OPA and the EA Approval work. This project 10 is aimed at facilitating the connection of renewable energy. 11 12 OM&A Development Work Capital Expenditures ($ Millions) ($ Millions) 5.5 84.0 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 22 of 47 1 12) Thunder Bay Enabler 2 3 4 A new 80km single-circuit 230 kV line running west from the Thunder Bay area is 5 needed to incorporate 300 MW of renewable generation. The actual length and terminal 6 points for the Enabler Line would be determined on the basis of FIT Applications 7 received by the OPA and the EA Approval work. This project is aimed at facilitating the 8 connection of renewable energy. 9 10 OM&A Development Work Capital Expenditures ($ Millions) ($ Millions) 12.0 119.0 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 23 of 47 1 13) St. Lawrence TS x Merivale TS (Cornwall x Ottawa) 2 3 4 Construction of an 82 km double circuit 230 kV line between Merivale TS and St 5 Lawrence TS is needed to incorporate 350 MW of renewable generation. This new 6 double circuit line will replace the existing 115kV transmission line (L1MB) and will be 7 located along the same ROW. 8 connection of renewable energy. This project is primarily aimed at facilitating the 9 10 OM&A Development Work Capital Expenditures ($ Millions) ($ Millions) 1.0 289.0 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 24 of 47 1 14) Selby Junction x Belleville TS 2 3 4 Construction of new 230kV line facilities to connect the 230kV circuits B23C/H23B at 5 Belleville TS with the X21 circuit at Selby Junction is planned in order to accommodate 6 renewable energy generation. This project is aimed at facilitating the connection of 7 renewable energy. 8 9 OM&A Development Work Capital Expenditures ($ Millions) ($ Millions) 1.0 105.0 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 25 of 47 1 15) Chenaux TS x Galetta Junction 2 3 4 Construction of a 45km double circuit 230 kV line from Chenaux TS to line C27P at 5 Galetta Junction would allow for the incorporation of 200 MW of wind generation in the 6 Chenaux-Pembroke area. This new double circuit line would be along the Arnprior GS 7 line tap of C27P and involves the re-termination of the Arnprior GS tap to one of the 8 lines of the new circuit. This project is primarily aimed at facilitating the connection of 9 renewable energy. 10 11 12 OM&A Development Work Capital Expenditures ($ Millions) ($ Millions) 1.0 104.0 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 26 of 47 1 4.3 Projects where Development Work is Not Planned in the Test Years 2 3 16) Longwood TS x Middleport TS 4 5 6 The West of London project previously described will enable renewable generation in 7 south western Ontario to be transmitted to London. To allow this generation to reach the 8 GTA, the transmission capability between London and Hamilton must be increased. In 9 order to increase power transfer capability from south western Ontario to the GTA, a new 10 single-circuit 500 kV line is required and, for the reference plan, is planned to stretch 11 from Buchanan TS to Middleport TS. The new right of way may be located next to the 12 existing Longwood x Nanticoke ROW. This project is primarily aimed at facilitating the 13 connection of renewable energy. 14 15 OM&A Development Work Capital Expenditures ($ Millions) ($ Millions) 9.5 306.0 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 27 of 47 1 17) Bowmanville x GTA 2 3 4 The Ontario Power Generation’s (OPG) existing Darlington NGS site has been selected 5 as the location for the next new nuclear plant under the Government of Ontario nuclear 6 procurement project. Infrastructure Ontario has requested AECL, Areva NP and 7 Westinghouse to submit bids for the OPG New Nuclear at Darlington GS project. 8 Options for proposed unit sizes for a 2-unit station range from 1100 MW to 1600 MW 9 per unit. The transmission facilities required to incorporate the OPG New Nuclear at 10 Darlington GS into the network are as follows: 11 • a new 500 kV Bowmanville “B” SS (Switchyard), adjacent to existing Bowmanville SS 12 • a new double circuit line between Bowmanville “B” SS and Cherrywood TS (46 km) 13 14 OM&A Development Work Capital Expenditures ($ Millions) ($ Millions) 11.5 167.0 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 28 of 47 1 18) Kenora x Thunder Bay Transmission Expansion 2 3 4 The reference plan includes the construction of a new 500km 230 kV double-circuit line 5 from Kenora to Thunder Bay with 3 new 230 kV breakers at each terminal station. 6 7 8 OM&A Development Work Capital Expenditures ($ Millions) ($ Millions) 5.0 1,006 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 29 of 47 1 5.0 OTHER GREEN PROJECTS 5.1 Transmission Facilities to Enable Distribution Connected Generation & 2 3 4 Protection, Control and Telecom Investments 5 6 The Minister’s letter of September 21, 2009 also identified a number of Transmission 7 Projects in Schedule B of the letter. These Schedule B items comprise new projects on 8 the transmission system that will be required to accommodate increasing connections of 9 generators on the Province’s distribution systems. Other than the Hearn, Leaside and 10 Manby TS upgrades, these projects are not site specific at this time as they are intended 11 to respond to the uptake of the FIT program and will be required where high 12 concentrations of applications occur. These projects include new Enabling Transmission 13 Stations (TS’s), Static Var Compensators (SVC’s), In-Line Circuit Breakers and 14 Protection, Control and Telecom investments that will be required to provide sufficient 15 capacity on the transmission system to accommodate the FIT proponents. These projects 16 also include upgrading of Stations in the City of Toronto in order to enable generation to 17 be connected to the distribution system of Toronto Hydro. 18 19 These projects are listed in Table 2 below and show the capital expenditures required and 20 the target in-service years. 21 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 30 of 47 1 Table 2 2 Expenditures for Schedule B Projects 3 ($Millions) 4 Capital Item Project # 1 2 3 4 5 Expenditures Target In-service ($ Millions) Upgrade Short Circuit Capability of Toronto Area Stations (Hearn TS, Manby TS, Leaside TS) Install 3 SVCs at 230kV +300/-100 MVAR (short term) Install up to 7 Enabling TS Install in-line circuit breakers at up to 7 locations to enable generation connections Protection, Control and Telecom Year 152.7 2012 – 2013 249 2013 - 2015 236 2013 - 2015 148 2012 - 2015 51.3 2009 – 2012 5 6 7 Item 1: Toronto Area Station Upgrades for Short Circuit Capability 8 The first of the Green Energy projects to be constructed and placed in service will be the 9 projects to Upgrade Short Circuit Capability at three Toronto area stations: Hearn TS, 10 Leaside TS and Manby TS. These projects will not require Section 92 applications. 11 Therefore, Hydro One is requesting approval of these projects as part of this application. 12 These projects are required to allow distributed generation in the City of Toronto to be 13 connected to the Transmission system and the Toronto Hydro (THESL) distribution 14 network. 15 16 17 The capital cost for these projects is provided in more detail in Table 3 below. Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 31 of 47 1 Table 3 2 Capital Costs of Toronto Short Circuit Upgrade Projects 3 ($Millions) 4 Project 2010 2011 2012 Total In Service Hearn TS 3.0 54.6 27.0 84.9 2012 Leaside TS 2.0 13.5 21.9 37.4 2012 Manby TS 0 9.0 9.2 30.4* 2013 5.0 77.1 58.1 152.7 Total 5 * Total Project Cost as In-service date is 2013 6 7 The cost of these projects is also provided in Table 3 of Exhibit D1, Tab 3, Schedule 3, 8 Appendix A. Project descriptions (ISDs) of these projects are found in Exhibit D2, Tab 9 2, Schedule 3, see Items D11, D12 and D13. 10 11 Need for the Toronto Area Stations Projects 12 13 In order to enable connections of new green generation facilities, the short circuit 14 withstand ratings at these three Stations – Hearn SS, Leaside TS and Manby TS – need to 15 be increased. Development work to upgrade the Short Circuit capability at these stations 16 is underway. These upgrades will remove constraints whereby, as a result of relatively 17 lower, existing interrupting capability of circuit breakers and station structures, it is not 18 possible to connect medium and large sized generation to the distribution system owned 19 by Toronto Hydro. 20 21 22 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 32 of 47 1 Hearn TS 2 Hearn TS has a 115 kV switchyard with lines connecting to Leaside TS, Esplanade TS, 3 John TS, and the new Portlands Generation Station. Hearn is a critical element of supply 4 to the City of Toronto. 5 decommissioned Hearn Generation Station, and numerous components have reached the 6 end of their useful lives. Furthermore, the 21 existing 115 kV breakers are constraining 7 the connection of new distributed generation, and replacement breakers will be rated at 8 50 kA symmetrical. The new Hearn station is to be rebuilt adjacent to the existing Hearn 9 switchyard on lands to be acquired from Ontario Power Generation. It was built in the early 1950s to connect the now- 10 11 Leaside TS 12 Leaside TS is a 230/115 kV autotransformer station that supplies the eastern section of 13 central Toronto. Replacing the existing 115 kV oil circuit breakers with breakers rated at 14 50 kA symmetrical will accommodate an additional 300 MVA of new generation on 15 Leaside’s 115 kV service area. This project involves the replacement of 28 oil circuit 16 breakers, which are 46 years old, and sections of the buswork. 17 18 Manby TS 19 Manby TS is a 230/115 kV autotransformer station supplying the western section of the 20 central area of the City of Toronto. The station has two 115 kV switchyards, Manby East 21 and Manby West, which are equipped with 115 kV oil circuit breakers. It is planned to 22 uprate the station fault current withstand capability to 50 kA. This will permit 23 incorporation of up to 300 MVA of new generation in the Manby 115 kV service area. 24 The proposed work covers replacement of 16 existing 115 kV oil breakers, which average 25 49 years old, at Manby TS with new SF6 breakers, uprating any limiting bus structure 26 components and replacement of other end of life equipment. 27 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 33 of 47 1 The OPA has recommended that Hydro One proceed with these projects in the supporting 2 evidence they have provided for this application. See Exhibit D1, Tab 3, Schedule 3, 3 Appendix B. Hydro One has also received a considerable amount of support for these 4 projects from organizations in the City of Toronto. 5 organizations are attached in Exhibit D1, Tab 3, Schedule 3, Appendix C. Letters of support from these 6 7 Other Projects in Schedule B of the Minister’s Letter 8 9 Item 2: Install 3 Static Var Compensators 10 The Static Var Compensator (SVC) installations enable distributed generation by 11 providing voltage support so that the distributed generation can supply reverse power 12 through the transformer stations to which they are connected. The specific station 13 locations where these SVC installations will take place will be determined based on FIT 14 uptake and detailed system studies. 15 16 Item 3: Install up to 7 Enabling Transformer Stations in Areas of High FIT Interest 17 New transformer stations will be required to enable distributed generation in areas of 18 high FIT interest but limited transformer availability. The specific locations for these 19 stations will be determined based on FIT applications. New sites may be required. 20 21 Item 4: Install In-Line Circuit Breakers 22 From the perspective of system protection, there is a limit to the number of generating 23 stations or transformer stations (TS) feeding power back into the system that can be 24 tapped to high-voltage transmission circuits. Without carrying out detailed power system 25 studies, it is estimated that no more than two generating stations or reverse-feeding TS’s 26 can be connected to such circuits. When more than two such tap points are established on 27 the high-voltage circuits, then it becomes necessary to install high voltage in-line circuit 28 breakers in order to enable more generators to be connected to the circuits. The specific Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 34 of 47 1 locations where such installations would be installed will be determined on the basis of 2 FIT uptake and system studies. 3 4 Item 5 Protection, Control, & Telecom 5 Investments in Protection, Control and Telecom facilities will be required to maintain the 6 safety, reliability and integrity of the Transmission system while enabling connection of 7 distributed generation. These investments include: 8 • transmission and distribution networks 9 10 • Expansion of Hydro One’s Control Centre to monitor and operate its transmission and rural distribution network and accommodate connected generation 11 12 Installation and/or upgrades to protection and control systems on Hydro One’s • Establishment of a telecom network needed to support enhanced protection, control & operating capabilities 13 14 15 16 6.0 INFRASTRUCTURE INVESTMENT INCENTIVE APPROACH FOR GREEN ENERGY PROJECTS 17 18 As explained in Exhibit A, Tab 11, Schedule 5, Hydro One is proposing a new approach 19 to cost recovery for the green energy projects, the “Accelerated Cost Recovery of CWIP” 20 mechanism. This proposed treatment is consistent with the methodology outlined by the 21 Board in its EB-2009-0152 “Report of the Board – The Regulatory Treatment of 22 Infrastructure Investment in connection with the Rate-regulated Activities of Distributors 23 and Transmitters in Ontario”, issued on January 15, 2010 (“the Report”) and in 24 discussions with stakeholders. One alternative approach suggested by the Board in EB- 25 2009-0152 was the accelerated cost recovery mechanism for construction work in 26 progress (“CWIP”) and pre-commercial expenses, and adjusting depreciation. 27 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 35 of 47 1 As discussed in Section 3.0 above, the projects included in this Green Energy and Green 2 Economy Plan represent a multibillion dollar investment in new transmission 3 infrastructure in Ontario. 4 Infrastructure Investment to address the unique challenges that have been created by new 5 Government policies and the GEGEA. As outlined in this Plan, Hydro One is responding 6 to an unprecedented level of investment in new facilities and an alternative funding 7 mechanism is appropriate. The Board issued its report on Regulatory Treatment of 8 9 In addition to the large cost of the Plan, the green projects also have a high degree of risk 10 associated with them. This also supports the need for an alternative funding mechanism. 11 Building such large, complex and multi year projects will present very significant 12 challenges: 13 1) In almost all cases involving new line construction there will be the need for 14 consultation with First Nations & Metis communities and a number of issues to be 15 resolved around access to the land, financial settlements and compensation and 16 creation of jobs for the communities. 17 2) There will be major property acquisition issues. In the case of larger projects there 18 will be hundreds of landowners to negotiate with. Most landowners will want to 19 maximize the value of their land. This has been demonstrated in the Bruce to Milton 20 project where even after a very protracted negotiation period expropriation of many 21 properties is required. 22 3) There will be environmental risks with all of the projects. Most of the projects will 23 require Environmental Assessments and there are numerous issues associated with 24 potential contamination and land remediation, preservation of water bodies and wet 25 lands, protection of cultural and heritage sites and protection of endangered species. 26 4) There will be timing risks with all the green projects but especially the longer term 27 construction projects. Projects that are initiated under the current policy objectives of Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 36 of 47 1 the government may be subject to delay, changes or even cancellation if the policy 2 objectives change in future years. 3 4 Bruce to Milton and other recent line construction projects have been able to utilize 5 existing or widened corridors and yet the issues encountered as noted above have been 6 substantial. A number of the Green Energy projects will involve true Greenfield projects. 7 The property acquisition and Environmental risks will be significantly multiplied for 8 Greenfield projects. 9 projects will be more complicated and will take at least two years to complete. The 10 project development activities associated with these risks are explained in more detail in 11 Section 7.0 below. It is expected that Environmental Assessments for Greenfield 12 13 The combination of extraordinary expenditure levels for the Green Energy projects and 14 the significant risk of delays or changes to the projects bring about the need for an 15 alternative funding mechanism. 16 17 The “Accelerated Cost Recovery of CWIP” mechanism will mitigate the rate impact of 18 the Green Energy Projects on customers by phasing in the costs of major transmission 19 projects over multiple years rather than all at once in the in-service year. It will provide 20 greater up-front regulatory predictability and will minimize the amount of interest that is 21 capitalized on major projects using the current funding approach. This latter benefit will 22 be magnified if project construction work is delayed due to factors outside of Hydro 23 One’s control. 24 25 For the majority of Green Energy projects in Schedule A of the Minister’s letter, Hydro 26 One is proposing to request the accelerated cost recovery of CWIP through a rate rider 27 for each project. This request will be made as part of the Section 92 application process. 28 Hydro One will propose to recover 100% of the CWIP following normal rate base Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 37 of 47 1 treatment. This approach will result in the need for the project and the funding 2 mechanism being presented for approval at the same time. 3 4 Hydro One is planning capital spending in the test years for only two of the projects 5 identified in Schedule A of the Minister’s letter - the Northwest Transmission 6 Reinforcement Project (Pickle Lake to Nipigon) and the Sudbury Area to Algoma Area 7 project (Hanmer to Mississagi). The costs for these projects are included in Exhibit D1, 8 Tab 3, Schedule 3 and individual project descriptions (ISDs) for these projects are found 9 in Exhibit D2, Tab 2, Schedule 3 – see Items D34 and D35. The costs for these projects 10 are also provided in Table 4 below. 11 12 Table 4 13 Projects Proposed for Accelerated Cost Recovery of CWIP in Section 92 Hearings 14 ($Millions) 15 Project Northwest Transmission Reinforcement Algoma x Sudbury Transmission Expansion Total 16 2008 2009 2010 2011a 4.5 2012a 16.9 5.7 Totalb 399 432 0 0 0 4.5 22.6 831 Notes: (a) Excludes AFUDC (b) Total cost including future years 17 18 As per the Board’s guidelines in EB-2009-0152, the Infrastructure Investment Report, it 19 is proposed that depreciation expenses will not be recovered until the individual projects 20 are formally declared in-service. Also, the rate riders will need to be adjusted annually to 21 recover the forecast financial carrying costs for the given year. 22 23 A complete description of the project costs and the associated amounts for accelerated 24 cost recovery of CWIP treatment will be provided in each Section 92 application. Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 38 of 47 1 7.0 DEVELOPMENT WORK FOR GREEN PROJECTS 2 3 Major transmission projects, including these Green Projects, will require First Nation and 4 Métis consultations, other community consultations and regulatory and environmental 5 approvals before construction can commence. 6 7 Development Work includes all activities, consultations, and approvals processes that 8 take place prior to the commencement of construction. This includes applications under 9 the OEB, Environmental Assessments through the MOE, and various other approvals. 10 Development Work consists of: 11 • Regulatory 12 o OEB s.92, s.98, s.99 preparations 13 o Hearings and Intervenors’ costs 14 o Legal advice 15 o Other tribunals, e.g. NEC 16 • Environmental Assessments 17 o Development of reference corridor 18 o Development of Terms of Reference 19 o Field Studies 20 o Preparation of Environmental report 21 • Planning, Scoping, Estimating 22 o Identification and assessment of alternatives 23 o Development of detailed reference plan 24 o Preparation of planning specifications 25 o Preparation of project cost estimates 26 • Consultation 27 o FN & Métis (including capacity funding) 28 o Communities and Landowners Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 39 of 47 o Municipal and Provincial representatives 1 2 • Real Estate 3 o Title searches 4 o Investigative surveys 5 6 Additional details about these components are described below. 7 8 7.1 Process and Timelines for Development Work 9 10 Development Work for large transmission projects can begin as much as six years prior 11 to the desired in-service date to ensure that all the approvals and property rights are 12 acquired. The Development Work for major projects typically takes at least five years, 13 and construction is typically expected to take a further one to three years, and possibly 14 more for larger complex projects. 15 complexity of the project. The need for the project is confirmed by the time a Section 92 16 application is submitted, which is approximately 1.5 years after the project is launched. 17 The diagram below highlights the various phases of the planning and construction 18 timeline. 19 Construction time will depend on the size and Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 40 of 47 1 2 3 The Development Work for all transmission lines projects in this Plan will be carried out 4 according to existing processes. Thus, while the Plan identifies the broad-based 5 conceptual strategy for incorporating renewable generation into the transmission system 6 across the province, the transmission lines projects will be brought before the Ontario 7 Energy Board individually for review and approval through the s.92 applications for 8 leave to construct, and Environmental Assessment approvals will also be sought where 9 required. 10 11 7.2 Strategy 12 13 In his letter of September 21, 2009, the Minister asked Hydro One to immediately 14 proceed with the planning, development, and implementation of 20 Green Projects. To 15 meet this request, Hydro One’s strategy is to: 16 1. Consult with the OPA on the need, timing, and conceptual plans for all 20 17 transmission projects. Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 41 of 47 1 2. Begin the preliminary development work for projects to identify potential variables 2 that will shape the environmental, property, design and construction profiles and give 3 consideration to the potentially affected First Nations and Métis communities. 4 3. Begin the formal Development Work on projects based on the results of the ECT or 5 as identified by the OPA or the Government. 6 environmental feasibility studies; detailing the real estate profiles, developing 7 technical alternatives; initiating pre-public consultations with potentially affected 8 First Nations and Métis communities, municipalities, government ministries, 9 agencies, and other stakeholders; holding Public Information Centers in local 10 This work includes: conducting communities; and conducting the environmental assessment work. 11 12 This strategy allows for timely completion of development work for the projects with the 13 highest probability of realization based on information presently available. It also allows 14 for the staggering of the development work and more efficient use of resources. If the 15 level of need dissipates in the future, there is a risk that some funds are spent on projects 16 that are not required to be constructed by the original timelines. However, in the majority 17 of cases this work will not be wasted as it will be used at a later time when the need does 18 materialize. This risk is further mitigated since the chance of this happening would be 19 confined to only the Green Projects with the highest need and not the entire list of 20 20 Green Projects, and uncertainty about the need is managed through close and regular 21 consultation with the OPA. Furthermore, the Board will have an opportunity to review 22 and test the prudence of these projects when Hydro One files the Section 92 applications 23 for Leave to Construct and when the company files the required Project Completion 24 Reports. 25 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 42 of 47 1 7.3 Some Major Elements of Development Work 2 3 First Nations and Métis Relations 4 5 The Supreme Court of Canada has found that the Crown has a duty to consult before 6 making a decision where Aboriginal and/or treaty rights may be potentially affected. 7 The Crown may delegate procedural aspects of its duty to consult aboriginal peoples to 8 the proponent for a project. 9 10 There are several overarching principles that guide Hydro One’s consultation activities 11 with First Nations & Métis communities, such as ensuring a consistent and thorough 12 approach to consultation and having respect for traditional practices, heritage sites, socio- 13 economic issues, the environment and traditional knowledge. 14 develop relationships of mutual respect and trust. Such relationships facilitate the two- 15 way exchange of information between the parties respecting any project plans, addressing 16 concerns to the extent possible and ensuring on-going dialogue about the plans and their 17 potential implications and benefits. 18 opportunity to strengthen relationships with First Nations & Métis communities. At all 19 times, Hydro One aims to ensure an open, ongoing dialogue and aims to seek joint 20 resolution of issues that arise wherever reasonably possible. Hydro One aims to Hydro One also sees the consultation as an 21 22 First Nations and Métis communities may have limited resources to effectively engage in 23 consultation and Hydro One considers providing capacity funding to communities to 24 allow them to adequately participate. This funding can cover costs such as wages for 25 liaison staff, travel and meeting attendance, external legal and technical advice, as well as 26 hosting community-wide information sessions. 27 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 43 of 47 1 In addition to capacity funding, Hydro One must consider if, and what, mitigation, 2 accommodation or benefits might be provided to First Nations and Métis communities 3 whose rights are potentially impacted by its projects. Such benefits or accommodation 4 might be defined in a Community Benefits Agreement and can include items such as 5 funding, employment, training, business partnerships, etc. 6 7 Environment 8 9 All Transmission Projects are subject to Environmental Assessment Act approval. The 10 requirements of the Act are very broad and extend beyond prediction of environmental 11 effects and mitigation or elimination of those effects. 12 (“EA”) process must establish the need for the project, consider possible alternatives to 13 the undertaking, and identify alternative methods of carrying out the undertaking. 14 Consultation with all affected parties is a key component of the process. Another key 15 feature is the broad definition of environment in the legislation. Environment includes 16 not only the natural environment but also the socio-economic environment and use of 17 resources. The Environmental Assessment 18 19 All project concerns become EA issues, and the process is the focal point of public, 20 regulatory and Aboriginal community opposition. The EA and OEB processes share 21 some common requirements (e.g. undertaking to be approved, project need, alternatives 22 considered, public notification/consultation) and consequently the respective timing of 23 the approvals has strategic implications. 24 25 1. The EA process has two stages: approval of a Terms of Reference which describes 26 the scope of the process to follow (e.g., route selection, effects prediction, 27 consultation, etc.) and the Environmental Assessment, which presents the result of the 28 process. Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 44 of 47 1 2. The EA document is reviewed first by a multi-agency government team which 2 produces a review of the assessment. A public review period in which comments on 3 the EA and the government review can be submitted in addition to recommendations 4 for a public hearing follows. 5 6 Real Estate 7 8 For new transmission projects, Hydro One will require various forms of land tenure real 9 estate rights for its facilities depending on whether the lands are privately owned, Crown 10 lands, First Nation Reserves, or rail/pipeline/3rd party interests. Land acquisition could 11 entail confirming and/or renegotiating existing rights or acquiring new rights and 12 properties from private property owners before project construction begins. The timeline 13 for acquiring the necessary real estate rights for major transmission projects can be 14 lengthy, and may involve the more formal, legislated expropriation process. This can 15 have a significant impact on project schedule and cost. 16 17 In addition, accurate identification of property owners affected by major transmission 18 projects is necessary to ensure that notification requirements associated with regulatory 19 approval processes (i.e., Ontario Energy Board Leave to Construct – “Section 92”) are 20 met. Inaccuracies in identifying affected property owners can result in significant delays 21 to the regulatory approval processes. 22 23 8.0 DEFERRAL ACCOUNT FOR OM&A DEVELOPMENT COSTS 24 25 In the 2008-0272 Hydro One Networks’ 2009-2010 Transmission Revenue Requirement 26 Decision with Reasons issued on May 28, 2009, the OEB approved the establishment of 27 an “IPSP and Other Preliminary Planning Costs Account”. This deferral account is used 28 to record the Development Costs associated with major projects. Since then, the GEGEA Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 45 of 47 1 has received Royal Assent. Also, on September 21, 2009, the Minister of Energy and 2 Infrastructure sent a letter to Hydro One requesting that it immediately proceed with the 3 planning, development and implementation of a number of transmission and distribution 4 projects which allow the grid to accommodate additional renewable generation as per the 5 policy objectives of the GEGEA, as well as seek the necessary approvals for these 6 projects. 7 8 On December 3 and December 15, 2009 Hydro One submitted requests to the Ontario 9 Energy Board to amend the list of projects associated with the “IPSP and Other 10 Preliminary Planning Costs Account”. This request for the inclusion of additional 11 projects was driven by the GEGEA and the need to commence work on these additional 12 projects to meet the target in-service dates identified in the Minister’s letter. The Board 13 initiated proceeding EB-2009-0416, and on March 25, 2010 the Board issued its Decision 14 approving the inclusion of the additional projects in the deferral account. 15 16 The additional projects included in the deferral account align with Schedule A of the 17 Minister’s Sept. 21, 2009 letter. There will be varying levels of development work in the 18 test years, 2011 and 2012 for seventeen of the twenty projects in Schedule A of the letter. 19 Two of the projects, number 19, Longwood TS x Middleport TS (formerly London to 20 Hamilton Area in the Minister’s letter) and number 20, Kenora to Thunder Bay 21 Transmission Expansion are not included as they are too long term to start development 22 work within the test year period. One other project, number 6, Bowmanville SS to GTA 23 is now considered longer term in nature and while it is one of the projects where early 24 development work was started in prior years there are no dollars in the test years for 25 development work. 26 27 Hydro One’s planned expenditures on the OM&A Development projects are provided in 28 Table 5 below. A similar table of OM&A development expenditures is found in Table 1 Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 46 of 47 1 of Exhibit C1, Tab 2, Schedule 4. The table in that exhibit includes the projects below as 2 well as other OM&A development work. 3 Table 5 4 5 6 Summary of Development Work for Major Green Projects in Bridge and Test Years 7 Ite m # 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 8 9 Cash Flow ($ Millions) Investment Description 2010 2011 2012 Total East-West Tie Expansion (Item #1) North-South Transmission Expansion (Items #2/3) Algoma x Sudbury Transmission Expansion (Item #4) Transmission Reinforcement West of London (Item #5) Goderich Area Enabler (Item #7) Manitoulin Island Enabler (Item #8) Huron South Enabler (Item #9) Pembroke Area Enabler (Item #10) Parry Sound Enabler (Item #11) North Bay Enabler (Item #12) Thunder Bay Enabler (Item #13) Northwest Transmission Reinforcement (Item #14) St. Lawrence TS x Merivale TS (Cornwall x Ottawa) (Item #15) Selby Junction x Belleville TS (Item #16) Chenaux TS x Galetta Junction (Item #17) Sudbury North - Pinard TS x Hanmer TS (Item #18) 0.7 4.1 3.0 12.0 1.5 4.5 3.0 18.5 0.6 2.0 3.0 5.5 0.7 9.0 10.0 22.5 0.4 0.5 0 0 0 0 0 1.0 1.0 0 1.5 0.5 0.5 1.0 2.5 3.0 0.5 3.0 2.5 2.2 4.0 5.0 7.5 1.0 8.0 5.5 5.5 12.0 3.0 10.5 7.0 21.7 0 0 0.5 1.0 0 0 0 0 0.5 0.5 1.0 1.0 0 0.1 1.5 5.0 Total Costs 7.4 35.7 46.7 132.7 Note 1: “Total” costs include cash flows, if any, in years before 2011 and after 2012. Filed: May 19, 2010 EB-2010-0002 Exhibit A Tab 11 Schedule 4 Page 47 of 47 1 Inclusion of a Rate Rider for Recovery of the OM&A Cost in the Deferral Account 2 3 As discussed in Exhibit F1, Tab 1, Schedule 2, Hydro One is requesting recovery of the 4 2009 OM&A development costs of $1.9 million ($2 million with interest). Hydro One is 5 not requesting recovery of the other OM&A costs in this deferral account at this time. 6 However, given the materiality of these development costs, currently projected at $160 7 million in total (see Exhibit C1, Tab 2, Schedule 4) Hydro One is considering the need 8 for a mechanism to recover these costs as incurred and might propose a rate rider 9 mechanism. The rider mechanism would recover the costs in the deferral account each 10 year to mitigate the sudden large rate impact of the deferral account recovery. Filed: May 19, 2010 EB-2010-0002 Exhibit A-11-4 Appendix A Page 1 of 5 -2- 1. Immediately proceed with the planning, development and implementation of Transmission Projects outlined in the attached Schedule A, including seeking approvals for the upgrades as soon as there is a reasonable basis to do so. 2. Collaborate with the OPA in defining the scope of work, including termination points, target capacity, number of lines, technical options and sequencing necessary for the Transmission Projects, as well as collaborating with the Independent Electricity System Operator on System Impact Assessments and reliability impacts. 3. Develop and implement smart grid infrastructure in accordance with upcoming . government policy, including establishing novel ways of managing network infrastructure for renewables more efficiently. 4. Given the magnitude of work required to complete the Transmission Projects: a. Identify the commercially reasonable opportunities for entering into partnership arrangements with qualified third parties/partners for the execution of the Projects; b. Work with the Shareholder to identify commercially reasonable criteria that will be used to select qualified third parties/partners; c. Use best efforts to enter into those commercially reasonable arrangements; and, d. Identify projects as appropriate where the planning, development and implementation of the project would be better accomplished by a qualified third party oilier than Hydro One. 5. Provide opportunities for participation in the projects by potentially-affected Aboriginal peoples. 6. Immediately proceed with the planning, development and implementation of upgrades to enable distribution system connected generation, as outlined in the attached Schedule B, including collaborating with the OPA and the Independent Electricity System Operator in defining the scope of work necessary for the transmission facilities to enable distribution system connected generation. 7. Begin planning and preliminary development to explore and preserve options for longer-term, high-capacity, transmission link between Thunder Bay and the Greater Toronto Area, including associated collaboration with the OPA for planning. 8. Subject to Crown oversight, engage in consultations with and, where appropriate, accommodate Aboriginal peoples respecting their section 35 rights of the Canadian Constitution Act, potentially affected by transmission and distribution projects listed in the attached Schedules. .../cont'd -3- To be clear, I am seeking your cooperation on these matters as a key enabler for the feed-in tariff program to be implemented under the GEA and in order to establish a more modern and reinforced electricity grid in Ontario. In no way does my request relate to the implem entati on or methods used to carry out the work described in this letter, including following approp riate cons u lta tion and approvals processes. In light of that, I would expect that H ydro One will develop a comp rehensive implementation plan to achi eve these objectives. Furthe rmore, in order to be informed about Hydro One's progress toward implementing and meeting these objectives, and in keeping wi th the purpose of th e Memorandum of Ag reeme n t between Hydro One and the Shareholder, I request that Hydro One report back to m e on a semi-ann ual basis on planning, development and implementation activities undertaken, and progress made in connection with Transmission and Distribution Projects that will enable the feed-in-tariff program. I would appreciate receiving a first report by no later than the end of Nove mber 2009. I am ap preciative of Hydro One's continued leadership in moving towards Ontario's green ene rgy future and look forward to seeing your progress in meeting the government's objectives on transmission and dis tribution system expansio n. On behalf of the Hydro One Board, would you please confirm your understanding of the above, and yo ur concurrence with all that is contemplated, by signing in the space pr ovided below. Thank yo u for your prompt attention to these matters. Since re ly, I concur, ~mes Arne tt Chair of the Board, Hydro One Enclosures Schedule A - Transmission Projects Item # Project Key Driver Target In-Service Year* Core Transmission (Bulk transmission upgrades) 1 East-West Tie: Nipigon x Wawa (230 kV) Bulk Transmission Capability for FIT program 2015 2 North-South Tie: Sudbury Area x Barrie (500 kV) Bulk Transmission Capability for FIT program 2015 3 Barrie x GTA (500 kV) Bulk Transmission Capability for FIT program 2015 4 Sudbury Area x Algoma Area (Mississagi Transformer Station, 70km east of Sault Ste. Marie) (500 kV) Bulk Transmission Capability for FIT program 2014 5 London Area x Sarnia (500 kV or 230 kV) Bulk Transmission Capability for FIT program 2016 6 Bowmanville x GTA (500 kV) Bulk Transmission Capability for reliability and FIT program 2016 Enabling Transmission (Local enabler connection lines for renewable clusters) 7 Goderich Enabler Connections in anticipation of high renewables demand 2013 8 Manitoulin Island Enabler Connections in anticipation of high renewables demand 2014 9 Huron South Enabler (Wanstead Transformer Station) Connections in anticipation of high renewables demand 2016 10 Pembroke Enabler Connections in anticipation of high renewables demand 2014 11 Parry Sound Enabler Connections in anticipation of high renewables demand 2015 12 North Bay Enabler and 230 kV Line Upgrade Connections in anticipation of high renewables demand 2015 13 Thunder Bay Enabler Connections in anticipation of high renewables demand 2015 Regional Transmission (Regional transmission lines for renewables) 14 Pickle Lake x Nipigon Renewables, Reliability, and Load Growth 2013 15 Cornwall x Ottawa Renewables and load growth 2015 16 Belleville x Napanee (Selby Junction) Renewables and load growth 2014 17 Chenaux x Arnprior Area (Galetta Junction) Renewables and reliability 2014 Longer-Term (Post-2016) 18 Sudbury North (500 kV) Bulk Transmission Capability for FIT program 2017 19 London x Hamilton Area (500 kV) Bulk Transmission Capability for FIT program 2020 20 Kenora x Thunder Bay Bulk Transmission Capability for FIT program 2020 * Scope, sequencing and details of implementation subject to detailed Implementation Plan Schedule B - Projects to Enable Distribution System Connected Generation Item # Project Target In-Service Year* Transmission Facilities to Enable Distribution-connected Generation 1 Install 3 Static Var Compensators in Areas of high FIT Uptake 2012-2014 2 Install up to 7 Enabling Transformer Stations in Areas of High FIT Uptake 2012-2015 3 Upgrade Short Circuit Capability of Toronto Area Stations (Hearn TS, Manby TS, Leaside TS) 4 Install in-line Circuit Breakers at up to 7 Locations to Enable Generation Connections 2012 2012-2015 Distribution 5 Targeted Dx Enhancements to Support Distributed Generation -10 New Distribution Feeders (in areas of high FIT uptake) -Other Minor Investments 2009-2012 Protection, Control, and Telecom (enabling distributed generation) 6 DG Connection Cost Reduction -Wide Area Telecommunication Infrastructure -Wide Area Island Detection -Transmission Protection Change for Tap-Connected Generation -Stop-Gap Wireless Remote Trip -GPRS (Cellular) Telemetry -Pulse-signalling Island Detection -OGCC System Changes 7 Protection -Feeder Protection Replacements -Telecom to In-Line Reclosers -TS Bus Protection Replacements 8 TS Capacity Expansion -Generation Trip and Block Scheme -Automated Generation Dispatch System -Transfer Protection Replacements -Tapchanger Control Upgrades -OGCC System Changes 9 Product Quality -Feeder Voltage Regulator Replacement -OGCC System Changes 10 Bulk System Reliability -Distribution Station SCADA and Protection Upgrades -OGCC System Changes -Load Rejection Systems Modifications * Scope, sequencing and details of implementation subject to detailed Implementation Plan 2009-2012
© Copyright 2024 Paperzz