Proceedings of Bridge Engineering 2 Conference 2009 April 2009, University of Bath, Bath, UK CRITICAL ANALYSIS OF THE FIRST BOSPORUS BRIDGE, ISTANBUL, TURKEY Matthew Smith1 1 University of Bath Abstract: This paper presents a critical analysis of the First Bosporus Bridge. The bridge crosses the Bosporus Straits, uniting the two banks of Istanbul with a road crossing for the first time. The bridge was completed in 1973 and has a main span of 1074 m. This paper considers aspects of aesthetics, loading, strength, construction and future requirements. Keywords: Istanbul, Bosporus, Suspension Bridge, Aerodynamic Deck, Steel, Fig 1.1 Elevation of the First Bosporus Bridge at night showing the coloured lighting [4] 1 Introduction The First Bosporus Bridge is a steel suspension bridge located in Istanbul, Turkey. The bridge is a well used road bridge that has had a significant effect on Istanbul [3]. Until the construction of the First Bosporus Bridge there was no dry crossing between the European and Asian sections of Istanbul. All transport between the main city on the Europeans side and the suburbs on the Asian side was done by boat, creating huge queues [3] at rush hours effectively costing the country millions. The First Bosporus Bridge was designed by Freeman Fox & Partners, also responsible for the Severn Bridge and the Humber Bridge and the similarity is visible in all sections of design. The design life of the bridge is likely to have been 100 years because the durability and cost of the materials is relatively high as is the future requirement for a crossing of the straits. The bridge has been in operation for 36 years and has not encountered any serious problems. The success of bridges designed in similar ways by the same company inspires confidence that this bridge will remain operational until the end of the design life. The bridge is more than just a way of getting from one side of the straits to the other. It has become a tourist attraction in its own right. During the night the bridge is illuminated in coloured light [Fig. 1.1] (different colours on different nights). Freeman Fox & Partners were famous for their use of an aerodynamic deck to produce long-spanning suspension bridges. The Tacoma Narrows disaster of 1940 prompted the deck design to become very heavy to reduce the effect of the wind however Freeman Fox & Partners did not follow this trend in their bridges, giving the elegant deck seen above and on the First Severn Crossing. The bridge cost £15M in 1973; it was funded partly by the Turkish government and partly by a European Investment bank, backed by several European governments and the EEC. To recoup the money spent on the bridge a toll was (and still is) required to cross. 2 Aesthetics 2.1 Introduction To better analyse the aesthetics of a bridge the 10 points set out in F. Leonhardt’s book ‘Bridges’ should be considered [1][6]. These 10 points cover the main areas which affect the aesthetics of a bridge and are used by the majority of designers as a guideline to producing beautiful bridges. These points are: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. Fulfilment of Function Proportions Order Refinement of Design Integration into the Environment Surface Texture Colour of Components Character Complexity in Variety Incorporation of Nature It is not necessary for a bridge to comply with all 10 points to be considered beautiful as many are subjective, especially character. 2.2 Analysis 2.2.1 Fulfillment of Function The function of the bridge can be clearly seen as a highway suspension bridge supported by the cables which hang between the towers. The function is made more obvious by the thin aerodynamic deck that could not act as a beam. 2.2.2Proportions The bridge has a very large span and a thin deck giving it a very slender look in elevation. The towers are large and bold, therefore compliment the thin deck. The proportions of the approach viaducts on either side of the main suspension bridge are less desirable as the supports look too slender, especially in contrast to the large tower. In general the proportions of this bridge are very good as with all of the Freeman Fox bridges. 2.2.3Order The Order of the bridge is very good as the entire deck is uniform and the spacing between the hangers is also uniform. The approach viaducts have a thicker deck, as this section is a multi span beam bridge; however this change occurs in the tower and does not negatively affect the aesthetics. The absence of cables from the approach viaduct has a negative influence on the order. 2.2.4Refinement of design The towers are tapered in the tradition of the Greeks which improves the aesthetics of the bridge [9]. Although done for structural efficiency the zigzag hangers and the aerodynamic deck are refinements that are very pleasing aesthetically. The choice to conceal all changes in deck depth to the tower makes the change less obvious and therefore a useful refinement. 2.2.5 Integration into the Environment The local environment is urban on both sides of the straits and therefore a modern bridge, constructed using metal, fits well into the surroundings. The tall towers and sweeping cables fit well rolling hills and large expanse of water. 2.2.6 Surface Texture The deck of this bridge is a smoother texture than the tower which is widely recognized as a good aesthetic choice [9]. The deck is not so smooth to be shiny but combined with its slenderness works well with the surroundings giving the hint of a reflection of the water without looking too unnatural. 2.2.7 Colour of Components The dark colour of the towers, cables and deck work very well with the surrounding area and makes the hangers seem almost invisible during the day. There is nothing particularly impressive with the colouring until the night when the bridge is illuminated in a variety of different colours, Red and Purple work to the greatest extent giving a modern, sleek and attractive look to a 35 year old bridge. One reason for the effectiveness of the lighting is the integration into the structure, giving the lighting a less forced feel [7]. Despite being an old bridge it is well maintained and has not been too badly affected through discolouring as some bridges are. 2.2.8 Character There is nothing about this bridge that gives it great character, in its structural system it is a simple suspension bridge and blends well enough into the cityscape during the day to mean it does not require character. During the night however, the coloured lighting makes it into an interesting and attractive bridge that does have character. 2.2.9 Complexity in Variety Being a suspension bridge there is little that can be added structurally and so anything extra would be solely to add complexity and would ruin the functionality and order of the bridge. This bridge works well in its simplicity. 2.2.10 Incorporation of Nature The First Bosporus Bridge does not relate to nature any more than any other bridge and does not need to; it is situated in the middle of a city and is above a busy trade lane, it is likely that to try to incorporate nature into this design would make it look out of place and absurd. 2.3 Summary of Aesthetics In the key areas of aesthetics this bridge succeeds, it is a simple and elegant bridge that exhibits the structure clearly. The change in colour of the bridge between day and night is almost like the bridge is changing its mood and because of this, the character changes as well, from the calm functionality of the day to the vibrant excitement of the night. It is because of the bridges performance in these points that it is a well placed and beautiful bridge. To the lay person the curve of the cable improves the aesthetics of the bridge [7] which may be another reason for its success amongst the local people of Istanbul. 3 Dimensions 3 Loading 3.1 Introduction 3.1 Introduction This information has been taken from The Bosporus Bridge [3] or assumed. Determining the loading on a bridge is a key part of design and is well documented in BS 5400-2:2006 [2]. The major loading can be split into dead, super-imposed dead, traffic, wind and temperature. This bridge was designed with the intention of being a lightweight and aerodynamic bridge to counter the large wind loads that suspension bridges take. To carry out some rough calculations into the efficiency of the bridge the loadings on the main span will be estimated. 3.2 Deck The cross section below [Fig 3.1] shows the dimension of the deck. 3.2 Dead Loads The dead loading includes all the structure of the bridge and is always present during operation. The dead loads are known values and should not be subject to change and therefore a lower factor of safety is required. The dead loading (unfactored) on the First Bosporus Bridge can be estimated as follows: Fig 3.1 A cross section of the deck, dimensions in mm [3] Steel Deck Steel Cable Steel Hangers 299 69.9 1.0 kN/m kN/m kN/m 3.3 Towers Both towers stand on two legs, each with their own piers. The European side uses round piers with a diameter of 18 m and begin at 17 m and 24 m below sea level. The Turkish side however uses rectangular piers of 15 m x 19 m, beginning at just 5 m and 10 m respectively below sea level. The reason for this difference is the difference in soil materials on either side. The first 10 m of European soil is too soft to support the huge structure of the bridge. The towers are 165 m high have the rectangular plan of 7 m by 5.3 m at the base. The towers are tapered from 5.3 m to 3.0 m at the top (viewed from the bridge). The towers are connected by three horizontal members to increase lateral stability. The cross section below [Fig. 3.2] shows the dimensions of the towers. 3.3 Super-Imposed Dead Loads The super-imposed dead loads include all nonstructural permanent loading. These have higher factors of safety due to the greater uncertainty in the materials and the possibility of replacements being heavier than the originals as the design life of these materials is lower than the permanent structure. Below are estimations for the main types of super-imposed dead loads (unfactored). Mastic Surface Handrails Services and Finishings 22.6 2.0 2.0 kN/m kN/m kN/m 3.4 Traffic Loads The main live loads that the bridge must withstand are primarily vehicle loading as this is a road bridge. There are many load combinations which need to be analysed to get the most onerous cases of stress in the bridge, both hogging and sagging must be investigated. Vehicle loads can be split into HA and HB loading. HA loading is a uniformly distributed load (UDL) acting over a notional lane in conjunction with a knifeedge load (KEL). HA loading is the design loading for heavy fast-moving traffic including bouncing factors [6]. Figure 10 and Table 13 of [2] are used to get the nominal value for the UDL per lane of 18 kN/m. The KEL is taken as 120 kN per notional lane (both unfactored) The HA loading is taken over two lanes and then 1/3 of HA is taken over all additional lanes to give the worst case scenario. The First Bosporus Bridge has 4 notional lanes on each side of the central reservation. HB loading accounts for abnormal truck loading. The unfactored load is taken as 10kN per axle per unit, with the maximum number of units being 45 [2][6]. HB Fig 3.2 Cross section of the tower, dimensions in mm [3] loading is used together with HA loading to create several load cases which should all be investigated. There are also secondary traffic loads which should be considered on any highway bridge, these include longitudinal forces from acceleration or braking, taken as 8 kN/m along a single notional lane [2][6]. Collision loading on the parapets equal to 25 units of HB loading and accidental skidding which can be modelled as a point load of 250 kN acting horizontally [6]. Fatigue loading is also linked with traffic loading and requires consideration. BS 5400-10:1980 is a guideline to fatigue checks [6]. 3.5 Wind Loads Suspension bridges are very badly affected by wind loading because large spans and minimal lateral resistance. It is not just the horizontal force which can damage the bridge; wind could trigger the bridge to vibrate at its natural frequency, leading to severe damage and collapse as demonstrated in during the Tacoma Narrows disaster of 1940. To combat the effects of wind loading on the First Bosporus Bridge, an aerodynamic deck was designed which reduces the wind loading. In addition to the aerodynamic deck the hangers are inclined in a zigzag pattern which gives extra lateral stability. The estimated wind loading acting on the bridge is taken from [2] section 5.3. The aerodynamic deck of this bridge sets it apart from many other bridges of the time (especially in USA) which, to combat the effects of natural frequency and coupling use far heavier decks which generally detracts from the structural efficiency, cost efficiency and aesthetics the design using approximate values estimated in section 3. These calculations are based on BS 5400-3:2000[5]. The load from the deck is carried through the hangers into the cable which pass the load into the tower and the anchorage. All loading on the approach viaduct is taken by the columns. To be sure that the bridge is able to withstand the most onerous bending moments numerous load cases need to be looked at. A fully loaded bridge does not necessarily give the most onerous case. All bridges designed to BS 5400 must be checked in both ultimate limit state (ULS) and serviceability limit state (SLS). The factors given in Table 1 of BS 54002:2006 [2] are different for ULS and SLS, with ULS being greater. 4.2 Ultimate Limit State of Bridge Components 4.2.1 Hangers The hangers are subjected to the dead, super-imposed dead and live loading from the deck as well as their own self weight. Each pair of hangers supports one 18 m section of deck and 4 nominal lanes. The highest possible live load is given by HA loading, full in two lanes and one third in the other two lanes. The diameter of the hangers has been assumed to be 150 mm, T460 grade steel and γm = 1.15 this gives σdesign = 400 N/mm2 3.6 Temperature Loads Temperature loading can be very detrimental to the life of a bridge of this size. A change in temperature will result in an expansion of the bridge and without expansion joints a stress would be induced. The First Bosporus Bridge uses ‘rolling leaf’ expansion joints which need to be well maintained and kept free of blockages to avoid the induction of stresses in the bridge. The temperature on the bottom of the bridge is likely to be far lower than the temperature on the top on a sunny day, creating differential expansion which is far more damaging. 3.7 Earthquake Loads The First Bosporus Bridge is located in an earthquake zone and therefore must be able to survive an earthquake. The movement joints help to alleviate some of the forces which the deck would experience in an earthquake. 4 Structure 4.1 Introduction This section aims to replicate the calculations that would have been completed in the design stage. They are simplified calculations that focus on the major details of Fig 4.1 Diagram showing factored loading and maximum force in hangers ߪ = ܲ/ܣ σ = 3.74 x 106 / (π x 752) σ = 211 N/mm2 < 400 N/mm2 (1) This should give the required redundancy in case one hanger requires replacement. 4.2.2 Cables The huge cables must take all the loading from the deck as well as the self weight from the hangers and itself. The angle between the horizontal and the cable at the tower is 17° and the diameter of the cable is 760 mm as explained in section 5.4. The tensile strength of the cables is 160 kg/mm2 [3]. ࡼ࢜ = . × . × ૠ × ૡ × . ૠૢ = . ࡹࡺ Fig 4.2 Diagram showing the factored loading on the entire cable This is a beneficial load and therefore has a factor of 1.00 whereas the horizontal load requires a factor of 1.40 if considered with dead load only and 1.10 which used in conjunction with other loading conditions. The factored Pt load (as a secondary loading condition). . ૡ × . = ૠ. ࡹࡺ 4.4 Temperature Fig 4.3 A free body diagram at the cable-tower connection ߪ = ܲ/ܣ σ = 606 x 106 / (π x 3802) σ = 1371 N/mm2 < 1569 N/mm2 4.3 Wind The steel deck has a coefficient of thermal expansion of 12 x 10-6 /K. Assuming an increase in temperature of 25 K. (5) ∆ࡸ = ࡸ∆ࢀࢻ ∆ࡸ = ૠ × × × ି = . This change in length is acceptable and will be negated by the expansion joints. The stress induced in the deck should the expansion joint fail to work because of blockage or poor maintenance is calculated in equation 6. ࣌ = ࣕࡱ = [2][6] ࢜ࢉ = ࢜࢈ ࡷ ࡿ ࡿ (2) ࣌= ∆ࡸ ࡱ ࡸ (6) . × × = ࡺ/ ૠ vc is the basic wind speed which has been estimated to be 25 m/s. This is a conservative estimate. K1 is the wind coefficient, which equals 1.55. S1 is the funnelling factor which, because of the low lying land surrounding the bridge which makes funnelling very unlikely, is taken as 1.00. S2 is the gust factor which at 64 m is 1.37 [2][6]. This stress must be factored using the loading factors taken from Table 1 [2]. γF3 = 1.30 ࢜ࢉ = × . × . × . ૠ = . /࢙ This stress is acceptable and below the capacity of the steel. This value can be converted in to a horizontal force based on the exposed area of the bridge. It does not account for the aerodynamic reduction [6] which this deck would give, therefore it is conservative. Clause 5.3.3 [2][6] ࡼ࢚ = ࡰ (3) q is the dynamic pressure head is equal to 0.613vc2 [6]. A1 is the area of the bridge which faces the wind. CD is the coefficient of drag which is taken from [2] as a function of the b/d ratio. From figure 5 of [2] CD can be taken as 1.2. ࡼ࢚ = . × . × ૠ × × . = . ૡ ࡹࡺ The vertical force can also be calculated using similar formula. Clause 5.3.5[2] ࡼ࢜ = ࡸ (4) A3 is the area in plan and CL is the coefficient of lift which can be found from figure 6 of [2]. Assuming α = 10° CL is equal to be 0.79 ࣌ = × . = ૠૡ ࡺ/ 4.5 Natural Frequency Using the Rayleigh-Ritz equation the natural frequency of the bridge can be estimated. This value should be above 5 Hz in the vertical direction while unloaded [6]. ாூ ݂ = (ߚ ݈)ଶ ටర (7) (Βnl)2 is 22.37 for this case. E is the young’s modulus of steel, 200000000 kN/m2. I is the second moment of area which has been calculated as 24.4 m4. m is the mass density per unit length of the section at mid span. For the horizontal case dead and superimposed dead loads only are included giving 72600 kg/m. l is the length of the deck, which is 33.4 m 200000000 × 24.4 ݂ = 22.37 ඨ 72600 × 33.4ସ ݂ = 22.37 × 0.23 = 5.19 ݖܪ This value is acceptable falling above the 5 Hz limit stated above and below the 75 Hz that if exceeded is uncomfortable. 4.6 Load Cases The most onerous situation is not necessarily the highest loading and designers must consider many different load cases to be sure that the bridge is suitable. Designers must consider temperature, traffic, wind and dead loads all acting together however to counter the fact that this unlikely BS 5400 lowers the factors of safety on the secondary live loading. This section contains a few of the load cases that will have been considered in design. 4.6.1 Load Case 1 The load case depicted in [Fig. 4.4] is designed to give the maximum sagging moment. Fig 4.5 A drawing showing simplistically the positioning of the primary traffic loads and a moment diagram 4.7 Foundations The European side substructure is founded on contorted mudstone or schistose rocks of the Upper Devonian age [3]. The rock strata have undergone a large amount of folding and it is very difficult to predict the type and strength as the orientation changes every few metres. These folds have also lead to the rock becoming fractured and soft, in particular underneath the anchorages [3]. The unpredictability and the softness of the rock mean that the excavations on the Europeans side are far greater than those on the Asian side where the bedrock is limestone [3]. 5 Construction 5.1 Introduction Fig 4.4 A drawing showing simplistically the positioning of the primary traffic loads and a moment diagram 4.6.2Load Case 2 This load case is an attempt to find the greatest hogging moment in the deck. The factor of the live traffic loads have been reduced to 1.30 for both HA and HB in accordance with [2]. Bridge construction is unlike almost all other types of construction because there is no firm place to rest machinery and plant cranes. In the case of the First Bosporus Bridge barges were used to put the deck into position. The towers were constructed first, followed by the cables and then the deck, connected to the hangers in stages, starting in the centre and working out towards the towers. Much of the information for this section was gathered from [3] The Bosporus Bridge, Sheridan Group. 5.2 Foundations and Anchorages The cables carry large horizontal loads and this must be transferred into the ground at a point behind the tower. The anchorages on each end take a 15400 tonnes per cable [3] which is a huge force and requires significant foundations. It is important that these are situated in a position where the ground has good geotechnical properties. When the cables reach the anchorages they splay into their separate strands, each of which is connected into a shoe which is bolted with steel slabs into the prestressed concrete anchor slabs. The trenches (up to 28 m deep) are stepped [Fig. 5.3] and crosswalls are constructed [Fig. 5.4] to increase the sliding resistance. The Ortakoy (European) anchorage contains 60000 tonnes of concrete as a counter load to the cable force. The Beylerbeyi (Asian) side anchorage contains 50000 tonnes [3] of concrete which gives a factor of safety for the anchorages of over 3 in both cases. Fig. 5.1 The anchorage block during construction [3] Fig. 5.6 The connection between the anchorage and the cable showing the reinforcement [3] The piers for the towers were excavated into the bedrock to get a firm footing. The soil conditions on the European side of the bridge are far worse than the Asian side. The European side required steel cofferdams to be constructed to exclude the water while removing the soft soil. All piers are close to the edge of the water to reduce the span as much as possible. Fig. 5.2 The anchorage during construction showing the cables [3] Fig. 5.7 One pier on the European side ready for insertion of the pre-fabricated tower [3] 5.3 Towers Fig. 5.3 (Right) One side of an anchorage after excavation, showing the trenched system [3] Fig. 5.4 (left) The same side of an anchorage during construction, the crosswalls are almost complete [3] The hollow rectangular cross sections of the legs were constructed in Italy and were preassembled on arrival in Turkey. This was considered the best method of construction because of the added control the contractors had over the situation, the tolerances of the straightness of the tower were very low and no allowance for inaccuracy in erection was made. The small margin for error which the designers required meant that the greatest care had to be taken when assembling and erecting the lowest section of the towers [3]. Climbing cranes were required to lift each section’s four panels into position [Fig. 5.8]. The crane started at the bottom and worked up, connecting each panel to the one below. Grip bolts and tension bolts have been used to hold these in place. 5.4 Cables The main cables have been formed through spinning parallel-wires which is common to most suspension bridges. This method was chosen over pre-formed parallel-wire strands. The cables are made up of 19 strands of 550 wires, each with a diameter of 5mm. The resulting main cable has a finished diameter of 760mm after the spinning process. Fig 5.8 A tower under construction showing the climbing cranes at the top [3] Fig 5.10 The beginning of the spinning process showing one strand of 550 wires [3] Fig 5.11 The process continues, joining strands [3] Fig 5.9 The inside of one leg of the tower showing the extensive steelwork [3] Fig 5.12 A hydraulic compacter is used to give the cable a circular shape [3] Fig 5.13 The completed and loaded cable gets coated in red lead paste for protection [3] To put the wires into position two catwalks had to be erected from the anchorages, through the towers, following the proposed route of the cables, when the cables were being lifted into position the Bosporus shipping lane to be closed. The hangers are then fixed to the cables using two semi-cylindrical steel casings. These are then clamped into place. To protect the wires from corrosion the cables are coated in red lead paste and wrapped in a protective casing of galvanised annealed steel wire once the full dead load was attached. Fig 5.15 The centre section is lifted into place [3] 5.5 Deck The deck was attached to the hangers in sections, starting in the centre. These sections consist of 18 m length of the deck prefabricated 2 miles north of the bridge in Göksu. Stiffened steel panels, typically 18 m by 2.5 m are used, imported from England or Italy and assembled using automatic welding machines. As with the towers the allowable inaccuracies were small and therefore it was important that the deck boxes fitted together perfectly. To achieve this each box was assembled next to the box that it would be next to during operation. Barges were used to transport the completed box units. As mentioned previously the centre section was the first to be attached and then the boxes to either side of that were attached simultaneously. Once a box had been attached to the hangers it was temporarily bolted to the adjacent box. This was designed to incorporate a lagging procedure which harnessed the changing profile of the bridge (especially the joint) while other boxes were being connected. The final connection was made using welds. Fig 5.14 The sections of deck are independently lifted off barges to be put into position [3] Fig 5.16 The box units under construction [3] The 40mm thick mastic surface which the vehicles would travel over was put down along the carriageway once the welding was complete. The super-imposed dead loads such as barriers and lampposts were attached afterwards. At the join between the deck, approach viaduct and tower there is an expansion joint on both sides of the main span. A ‘rolling leaf’ style joint was used [3]. The expansion joint is not just to alleviate temperature induced stresses in the structure but also acts to absorb earthquake movement. Fig 5.17 A ‘rolling leaf’ expansion joint [3] 5.6 Approach Viaducts The approach viaducts are supported by columns. A cantilever construction system is used starting at the anchorages in the direction of the tower. The steeply sloping sides of the bank mean that floating cranes are required to bring the boxes into the foot of the tower. Gantries running up and down the backstays are used to lift them into their position [3]. growing. The format of the city, with the suburbs on one side of the straits and the main city on the other, means that the demand to cross is increasing. Due to the increased traffic loading and the age of the bridge it is unlikely that it would be feasible to expand the existing bridge short of making the two emergency lanes permanently for ordinary traffic. Should the demand increase enough to make crossing the straits very time consuming it is likely that the Turkish government would opt to construct another bridge. 7 Conclusion Fig 5.18 The Approach Viaduct under construction [3] The First Bosporus Bridge was one of a series of suspension bridges which has created a new, popular and effective style of suspension bridge design. The bridge, after completion, significantly improved the transport situation in Istanbul [3] by removing the large queues for ferries that had tainted so many commuters journey. The bridge is aesthetically pleasing; complying with many of the rules set out by Leonhardt [1] and continues to be a spectacle at night becoming a tourist attraction as well as a transportation device. The Bridge appears to be well maintained and should continue to serve without requiring large scale repair for many years to come. The construction process was quick and relatively problem free. The methods had been tried on previous projects (First Severn Crossing) and have, due to their success, been carried forward onto many more constructions since. 8 Acknowledgements This paper could not have been completed without the assistance of Sian O’Keefe at Hyder Consulting who has provided vital information. 9 References [1] Leonhardt F. 1982. Bruecken/Bridges. Deutsche Verags-Anstalt. Fig 5.19 The finished bridge during the day [3] [2] BS 5400-2:2006. British Standards Institute. 6 Future Requirements [3] The Sheridan Group. The Bosporus Bridge. L. Bell & Co. Ltd. 6.1 Introduction [4] Wow Turkey website – Night Photographs http://wowturkey.com/forum/viewtopic.php?t=4552 &start=120 It is difficult to predict the usage a bridge will get especially when there is no method of dry transport and therefore the Bosporus Bridge was designed to be flexible in terms of traffic movement. Some lanes are reversed in peak flow to cope with the demand and extra lanes, originally for emergency vehicles are sometimes used in peak traffic. Pedestrians have been prevented from walking across the bridge making it solely a transport bridge for vehicles. The high demand for a road crossing meant that Freeman Fox & Partners were again commissioned by the Turkish government to building another road crossing over the Bosporus, The Fatih Sultan Mehmet Bridge was completed in 1988 with a similar design to alleviate the congestion and spread the demand of the First Bosporus Bridge. Istanbul is the largest city in Turkey and is still [5] BS 5400-3:2000. British Standards Institute. [6] Ibell T. Bridge Engineering. Department of Architecture and Civil Engineering, University of Bath [7] Highways Agency. 1996. The Appearance of Bridges and Other Highway Structures. Chapters 8 and 22. The Stationary Office. ISBN 011 5518045. [8] Ray S.S. Barr J. Clark L. 1996. Bridges – Design for Improved Buildability. CIRIA Report 155. [9] Highways Agency. 1998. Design Manual for Roads and Bridges - Design and Appearance of Bridges. The Stationary Office. ISBN 011 5520287.
© Copyright 2026 Paperzz