RAJASTHAN ELECTRICITY REGULATORY COMMISSION Petition No. RERC/257/11, RERC/323/12 In the matter of determination of ARR & Tariff for FY 2010-11 (20 days), FY 2011-12 & 2012-13 in respect of Giral Lignite Thermal power Station(RVUN) Unit-2 (125 MW). Coram : Sh. D.C. Samant, Chairman Sh. S. Dhawan, Member Petitioner (RVUNL) : M/s Rajasthan Rajya Vidyut Utpadan Nigam Ltd Respondents : Dates of Hearings : 19.08.2011, 15.11.2011, 13.04.2012, 15.05.2012, 29.05.2012, 14.06.2012, 07.08.2012, 04.10.2012, 08.01.2013 Present : 1. 2. 3. 4. 5. 6. 7. 8. 9. Sh. N.C. Gupta, MD, GLPL, Barmer Sh. R.K. Gaur, ACE (PPC&F), RVUN, Jaipur Sh. M.K. Khandelwal, CAO (W&M), RVUN, Jaipur Sh. Ashok Parakh, XEn, GLPL, Barmer Sh. Dinesh Singh, XEn (Commercial), RVUNL, Jaipur Sh. K.K. Yadav, AEn, GLPL, Barmer. Sh. G.L. Sharma, Stakeholder Sh. R.L. Chechani, Consultant, RVUNL Sh. Piyush Lohia, Consultant, RVUNL Date of Order Jaipur Vidyut Vitran Nigam Ltd. (JVVNL) Ajmer Vidyut Vitran Nigam Ltd. (AVVNL) Jodhpur Vidyut Vitran Nigam Ltd. (JdVVNL) : 24.02.2014 ORDER SECTION-I 1. Background:Rajasthan Rajya Vidyut Utpadan Nigam Ltd (RVUNL) filed petition no. 257/11 on 15.04.2011 for determination of Tariff for FY 2010-11 (20 Days), FY 2011-12 and ARR for MYT Control Period from FY 2010-11 to FY 2013-14 and petition no. 323/12 on 19.04.2012 for determination of Tariff for FY 2012-13 (1) in respect of Unit-2 (1 X 125 MW) of Giral Lignite Thermal Lignite Power Station, Barmer. 2. The petitioner also prayed for allowing provisional tariff in respect of GLTPS (RVUN) Unit-2 to be applicable immediately after actual COD w.e.f.12.03.2011 as proposed in the petition till final tariff order was issued. 3. Public Notice with salient features of the petitions inviting objections/ comments/ suggestions from any desirous person in respect of petition no.257/11 was published in Rajasthan Patrika and Rashtradoot on 08.06.2011 and Times of India on 09.06.2011 and in respect of petition no.323/12 was published in Rajasthan Patrika and Rashtradoot on 04.09.2012 and Times of India on 05.09.2012. 4. The petitions were made available in the RERC Office as well as in the office of the petitioner. These were also placed on the websites of Commission and the petitioner. Comments/ suggestions were required to be furnished within 21 days from the date of public notice. 5. The audio-visual presentation in respect of the petition no. 257/11 & 323/12 was made on 13.06.2011 and 10.09.2012 respectively at Vidyut Bhawan, Jaipur. 6. All the three members of the Commission were present during the hearings. However, one member namely Sh. S.K.Mittal has since demitted office on completion of his tenure. This order, therefore, is being passed by two members, including Chairman of the Commission. 7. The objections/ comments/ suggestions were received from following stakeholders: (1) Ajmer Vidyut Vitran Nigam Ltd. (AVVNL) (2) Sh. G.L. Sharma (3) Jaipur Vidyut Vitran Nigam Ltd. (JVVNL) (4) Sh. D.P.Chirania (5) Rajasthan Vidyut Vikas Sansthan (R.V.V.S.) (6) Samta power RVUN vide letter dt. 13.07.2011 again requested the Commission to allow provisional tariff w.e.f. 12.03.2011, as proposed in the petition, as detailed below: Table No.1: Interim Tariff as proposed 8. Parameter FY 2010-11 FY 2011-12 Fixed Charges (Rs./unit) 2.2276 2.2101 Variable Charges (Rs./unit) 1.0748 1.1822 Total Tariff (Rs./unit) 3.3024 3.3923 (2) 9. The Commission pointed out some data gaps in the petition no.257/11 vide letter dt. 19.07.2011 and in respect of the petition no.323/12 vide letter dt. 31.07.2012 and directed the petitioner to submit the required information/clarifications. The petitioner submitted its response vide their letter dt. 03.08.2011 in respect of the petition no.257/11and vide their letter dt. 27.09.2012 in respect of the petition no.323/12. 10. The petitioner submitted supplementary petition on 09.08.2011 for FY 201011 & 2011-12 after revising fixed cost on account of Special O&M expenses and Insurance charges and requested for approval of tariff, ARR and provisional tariff in respect of GLTPS (RVUN) Unit-2 after considering the revised data. RVUN requested the Commission to allow the revised tariff as per supplementary petition as under: Table No.2: Interim Tariff as proposed (As per supplementary petition) Parameter FY 2010-11 FY 2011-12 Fixed Charges (Rs./unit) 2.2686 2.2553 Variable Charges (Rs./unit) 1.0748 1.1822 Total Tariff (Rs./unit) 3.3434 3.4375 11. Objections were received from Sh. G.L. Sharma on the supplementary petition vide letter dt.16.08.2011. 12. Public hearing was held on 19.08.2011in respect of interim tariff. It was seen that the capital cost considered in the petition (Rs. 901 cr.) was much higher than the cost envisaged in the DPR (Rs. 618 cr.). The Commission, thus, considered 65% and 85% of fixed and variable charges respectively for allowing ad-hoc interim tariff. 13. Accordingly, the Commission vide its order dt. 13.09.2011 approved the interim tariff as under: Table No.3: Interim Tariff as approved Parameter FY 2010-11 FY 2011-12 Fixed Charges 1.4746 1.4659 Variable Charges 0.9136 1.0049 Total Tariff 2.3882 2.4708 14. The next public hearing was held on 11.10.2011. The Commission observed that the apportionment of common assets between two units is not clear due to which capital cost of units could not be finalised. The petitioner was directed to furnish some additional information within three weeks and the matter was listed for hearing on 15.11.2011. 15. The next public hearing was held on 15.11.2011. The petitioner requested to allow some time enabling them to submit replies and further data. The Commission vide order dated 16.11.2011 allowed one month time to RVUN (3) for furnishing all the replies and information. It was also decided that the matter shall be listed for hearing after having received replies and information. 16. The next public hearing was held on 13.04.2012. The petitioner prayed to allow tariff as petitioned and also that the interim tariff allowed for FY 201112 be extended for FY 2012-13. The Commission observed that the information sought earlier regarding apportionment of common assets between two units with proper justification, reasons and justification for abnormal delay in commissioning of the plant and liquidated damages charged/ proposed to be charged from suppliers etc. have not yet been furnished by the petitioner and therefore, the Commission, vide order dt. 17.04.2012 allowed one month time to furnish the required information as sought by the Commission and stakeholders. 17. The next public hearing was held on 29.05.2012. The petitioner again prayed to allow tariff as petitioned and also requested for the interim tariff allowed for FY 2011-12 to be extended for FY 2012-13. The Commission vide order dated 31.05.2012 allowed the same interim tariff for the year 2012-13 as already allowed for the year 2011-12 vide order dated 13.09.2011 as under subject to adjustment as per final order on the petition:Table No.4: Provisional Tariff, as approved, for the year 2012-13: Parameter FY 2012-13 Fixed Charges 1.4659 Variable Charges 1.0049 Total Tariff 2.4708 18. The case was again heard on 14.06.2012. The Commission observed that capital expenditure actually incurred up to the date of commercial operation duly audited and certified Statutory Auditors have yet not been furnished by the petitioner and the commission allowed one month time to furnish the same. 19. The case was again heard on 07.08.2012. The Commission, vide its order dated 08.08.2012 adjourned the proceedings due to non submission of information regarding capital cost actually incurred up to the COD duly certified by Statutory Auditors, as sought earlier. 20. The petitioner vide its letter dated 30.08.2012 submitted the statement of actual capital expenditure up to 11.03.2011, duly certified by the Statutory Auditors. 21. The case was heard on 04.10.2012. The Commission observed that the petition for determination of ARR and tariff for Giral II for FY 13 have also been filed by petitioner and many issues are common in petitions for FY 12 (4) & FY 13, therefore it would be appropriate to hear the petitions for FY 12 & FY 13 together. Meanwhile, the petitioner was directed to analyze the reasons for disproportionate increase in IDC and finance charges and also to examine as to why part of these charges is not recoverable from the suppliers/ contractors. The case was adjourned for next date of hearing. 22. The Petitioner vide its letter dated 06.12.2012 also submitted the reasons for delay in commissioning of the unit and disproportionate increase in IDC. 23. In the meantime, during the hearing for petition no. 352/12 for determination of ARR and tariff for FY 13-14, one of the stakeholder Sh. G. L. Sharma, vide its letter dated 23.09.2012, raised certain issues and submitted that the COD of GLTPS Unit-2 had not been declared strictly as per provision of RERC Tariff Regulations, 2009. The Commission, therefore, decided to first finalize the issue of COD and pending that, this order was kept on hold. The Commission, considering the importance of the issue of COD, heard the matter on 15.10.2013 & 05.12.2013 and decided the same vide its order dated 23.12.2013 wherein the Commission has decided not to interfere with the COD declared by the petitioner. As the COD issue stands finalized, this order is now being issued. 24. In the process of prudent checking of capital cost, the Commission observed that the details of actual capital expenditure as per the certificate of statutory auditor and allocation of common assets between unit-I and II was not complete. In view of the incomplete details, the representative of RVUN and GLPL were called to explain the matter and furnish the requisite details. 25. Written submissions of the stakeholders on the proposal with their elaboration during hearing and reply as well as oral submissions by the petitioner are discussed in subsequent paras. The abbreviations used in this order are as per “Annexure-1” 26. The Commission under this order has taken up determination of tariff and ARR for FY 2010-11, 2011-12 and 2012-13 only. For FY 2013-14, since separate petition has been filed by the petitioner based on updated data for determination of tariff and ARR, the same will be decided through separate order. The subject matters dealt with in subsequent sections are as under: Section-II -Summary of objections/ comments/ suggestions, petitioner’s response and Commission’s views. Section-III – Determination of ARR & Tariff. (5) SECTION-II Summary of objections/ comments/ suggestions, petitioner’s response and Commission’s views: 27. 28. 29. 30. 31. 32. Annual Audited Accounts: Comments of stakeholders/objectors: AVVNL & JVVNL submitted that the petitioner should provide the audited annual accounts for last three years i.e. FY 08-09, FY 09-10 and FY 10-11. Petitioner’s response: The petitioner provided the audited annual accounts for FY 2007-08, FY 2008-09 and 2009-10 and a statement of actual capital expenditure up to (11.03.2011),duly certified by the Statutory Auditors. Commission’s Views: Regulation 44(5) of RERC Tariff Regulations,2009 reads as under: “A generating company shall make a fresh petition as per these Regulations, for determination of final tariff based on actual capital expenditure incurred up to the date of commercial operation of the generating station duly certified by the Statutory Auditors based on audited annual accounts” whereas the petitioner has furnished the annual accounts for FY 2008-09 and FY 2009-10 and a certificate of the Statutory Auditors certifying the capital expenditure incurred up to 11.03.2011. As per Regulation 12(2) of RERC (Terms and conditions for determination of Tariff) Regulations 2009, the information for the previous year should be based on audited accounts and in case audited accounts for previous year are not available, audited accounts for the year immediately preceding the previous year should be filed along with unaudited accounts for preceding year as far as for determination of tariff for FY 1213 is concerned. RVUN has failed to provide the audited accounts of previous year or the year immediately preceding the previous year. The Commission directs RVUN to ensure that the provisions of Regulation 12(2) of RERC (Terms and conditions for determination of Tariff) Regulations, 2009 should invariably be complied with while filing the next tariff petition. Delay in declaration of Commercial Operation Date (COD): Comments of stakeholders/objectors: AVVNL and JVVNL submitted that the petitioner should provide the Scheduled Date of Operation (Date of Manufacturing of Plant) and Scheduled COD as approved by the sanctioning authority. Sh. G.L. Sharma submitted that the COD has been declared after a period of 2 years & 9 months from the original scheduled date. It is not understood as to why such a long time was taken to declare the COD. (6) The petitioner may provide the capital cost that would have been in case the COD of the unit would have been in Dec., 2008 itself. The amount of IDC as on 31.12.2008, as shown originally in DPR and year wise addition thereafter may also be provided. Sh. G.L.Sharma also requested to provide the information of year wise quantum of energy loss. He further submitted that the petitioner should also provide the amount of Liquidated Damages (L.D.) recovered or to be recovered as per the decision of BoD. 33. Sh. G.L. Sharma further submitted that the petitioner should indicate whether the plant, after being commissioned on 26.12.2008, has ever attained full installed capacity during the trial run continuously for 72 hours or more. If so, the petitioner should provide the dates when full capacity was achieved. Further, the petitioner should also submit the defects (manufacturing defect in any of the BTG or construction work) that were noticed for declaring the COD and the costs to rectify the defects. 34. Sh. G.L. Sharma further submitted that the petitioner has not stated whether any notice was given to Discoms prior to demonstrating MCR or IC through successful trial run of 72 hours. Further, the declaration of COD has been done by GLPL and not by RVUN. 35. Petitioner’s response: The petitioner submitted the following details regarding the Scheduled Date of Operation and COD. Table No.5: Details regarding scheduled & actual dates Particulars Zero Date (Date of LOI to BHEL) Scheduled Date of Commissioning (30 months from LOI) Actual Commissioning Date COD Date 30.11.2005 29.05.2008 26.12.2008 12.03.2011 36. The petitioner submitted that the delay in commissioning of the plant was due to delay in environment clearance which was issued on 5.1.2006 and the subsequent consent to establish which was given on 28.1.2006. The actual physical work started thereafter only. Further, the construction work of the plant was also delayed due to heavy rains and flood in Barmer District in the year 2006 due to which the road approaching the plant site was blocked. 37. The petitioner submitted that GLTPS Unit-2 was synchronized on dt. 26.12.2008 and on a/c of high content of sulphur in lignite and increasing lime quantity; full load operation was not possible due to choking of back pass, where major heat transfer tubes were located. After various modifications carried out by M/s BHEL, consistent full load was achieved just before the COD on dt.12.03.2011. Till such date, the Unit was operated on part load for which lignite & lime was consumed. The capital cost (7) would have been Rs. 750 cr., if the unit would have started in Dec., 2008. The amount of IDC in DPR was Rs. 45.44 crores. The petitioner also submitted that there was no energy loss as unit could not be started on commercial operation due to technical reasons. Energy generated after commissioning up to COD was sent to the Grid / Discoms. 38. It was also submitted that Rs. 14.36 cr. had been withheld from M/s BHEL bills and Rs. 25.14 cr. from bills of BoP contractors on a/c of L.D., as per provisions of the contract. Details of L.D. withheld are, as under: Table No. 6: Details of L.D. Withheld S. No. 1 2 3 4 5 6 Name of Package BHEL TPL Zubery K.S. Construction J.R. Construction I.L. Kota Total Amount (Rs. Lakhs) 1436 2432 81.59 0.64 3950.23 39. The petitioner further submitted that this project is based on CFBC technology which is useful for fuel of low calorific value and high sulphur content. However, due to high variation in sulphur and ash content found in lignite, boiler was not found to be adequately compatible. Hence, BHEL had to make many modifications such as addition of 8 high pressure Soot Blower, adjustment in back-pass dome to separate fly ash and clinkers, etc. to run the unit on full load capacity. Since, these modifications were carried out by BHEL at their own cost; penalties on account of deficiencies were not imposed. However, L.D. has been withheld, as explained above. The petitioner also submitted that there were some pending works which were attended by M/s BHEL free of cost. No other major defects were noted during COD period & no additional cost was required to rectify the defects. 40. The petitioner further submitted that GLTPP is a part of RVUN and employees of GLTPP are part of RVUN employee. The COD has been declared as per RERC regulation, 2009 after 72 hours of trial run as mentioned in the said annexure also. 41. 42. Commission’s Views: The matter related to declaration of COD stands decided vide Commission’s order dt. 23.12.2013. The Commission noted that there was a delay of 7 months in synchronization/commissioning of the project due to delay in obtaining environment clearances and road blockage due to heavy rainfall in Barmer District in August, 2006. The Scheduled date of synchronization/ (8) commissioning was May 2008. The Commission observed that obtaining of environmental clearances in time was responsibility of the petitioner although delay by concerned agency cannot be ruled out and hence cost overrun on account of the same cannot be passed entirely on to the consumers. Further, delay due to heavy rainfall is beyond the control of the petitioner. 43. The Commission also observes that there was abnormal delay in declaring COD after commissioning of the unit on dt. 26.12.2008. As per DPR, sulphur content of lignite was envisaged to be in the range of 3-6%. Also, as per Fuel Supply Agreement, sulphur content was envisaged to be between 35%. Actual sulphur content as per the certificate of sample analysis by M/s Mitra SK Pvt. Ltd. was found to be 6.04% which is close to the highest value envisaged in the DPR and the fuel supply agreement. Although, the choice of appropriate equipment to cater to the available fuel supply is the responsibility of the petitioner, but the fact that the sulphur content was high in the lignite cannot be overlooked. Hence, delay on this account, cannot be entirely attributable to the petitioner. The matter related to delay in declaring COD and treatment of IDC for delayed period has been dealt with in the Section for “determination of capital cost”. 44. The Commission observed that the L.D. amount has been withheld provisionally. The petitioner has not finally determined the amount recoverable from suppliers/contractors. The BoD of RVUN has also issued directions, in its meeting held on dt. 14.12.2011 to recover the L.D. amount as per provisions of the contract. The Commission directs RVUN to finally determine the amount to be recovered from the suppliers/contractors and report the compliance to the Commission in petition for determination of final capital cost and tariff for FY 2010-11. The Commission provisionally reduced 50% amount of Misc. deposit on account of L.D. & other reasons while determining the provisional capital cost. 45. Capital Cost: Comments of stakeholders/objectors: Sh. G.L. Sharma, JVVNL & AVVNL submitted that the petitioner should provide the audited figures of item wise capital expenditure including yearly details of Capital Work in Progress (CWIP) starting from 01.04.2006. 46. Sh. G.L. Sharma also submitted that petitioner should provide the details of the common facilities used by GLPL Unit-1 and GLTPS (RVUN) Unit-2. 47. Sh. G.L. Sharma further submitted that the capital cost for GLTPS (RVUN) Unit-2 includes cost of raw water reservoir (8.83 cr.) but as the objector understands, the water would be brought through water conductor (9) system laid down for GLPL Unit-1. Hence, the petitioner should provide a justification regarding the same. It is also not clear from the petition as to from which source and by what means, the water will be brought for power station. 48. Sh. G.L. Sharma also submitted that the petitioner should provide information regarding approval of capital cost by the Commission. He further submitted that capital cost of Rs. 901.92 cr. implies cost of Rs. 7.21 cr./MW, which is very high as compared to capital cost of Rajwest (Rs.4.80 cr./MW) and Neyveli (Rs.6.5cr./MW) power plants. The petitioner should provide a clarification regarding the same. 49. Sh. G.L. Sharma submitted that the petitioner should provide details regarding the following: Break-up of the capital cost of Rs. 618 cr., 650 cr., 750 cr., 908 cr., & 901.92 cr. Dates on which orders of the equipment were placed, cost at which they were placed, date of supply and whether there were any delays in supply of equipment. Whether the cost of equipment was inclusive of the spares and any additional spares were purchased? What were the terms & conditions for supply of these plants? The dates on which the supplies were received and in case of delay, what is the period of delay? Whether any deductions/ refund have been made as per instructions of BoD in their resolution? Whether there was any clause regarding penal charges in case of delay in supply of equipment and amount of penal charges recovered from suppliers, if any? Whether the cost of equipment increased due to delay in supply of equipment? Whether the delay in commissioning of the project was due to delay in supply of equipment and what its implication on overall project cost was? 50. Sh. G.L.Sharma further submitted that the major civil works & that of colony, which will be a common colony for both the units, have already been carried out under the works of GLPL unit-1. Thus, the cost of the same is to be proportionately apportioned. Hence, justification for the provision of Rs. 5.43 cr. for Misc. civil works is required. 51. Sh. G.L. Sharma further submitted that as per DPR, the capital cost of Unit2 is Rs. 618 crores. The State Govt. has approved the revised cost of Rs. 650 crores with equity contribution of Rs. 185 crores. As per petitioner, the final (10) cost as on COD approved by their BoD IS Rs. 901.92 crores while as per chartered Accountant, it is Rs. 900.49 crores and as per Statutory Auditors’ statement, it is only Rs. 744.38 crores. As we are to go as per Statutory Auditors, the capital cost is to be taken as Rs. 744.38 crores only. 52. Sh. G.L.Sharma further submitted that as per project schedule given in DPR, the commissioning of the Unit has been 33 months from the Zero date reckoned from the date of L.O.I. for main SG & TG packages. The date of L.O.I. of SG & TG packages is 30.11.2005 and accordingly date of commissioning comes as 29.8.2008. As per agreement dated 30.04.2005, 28.09.2006 and 07.06.07 executed by RVUN with Discoms, it is June,2008, whereas RVUN unit has declared COD as on 12.03.2011 i.e after a period of about more than 2 ½ years from the scheduled commissioning date. This has resulted in increase in cost and IDC. 53. Sh. D.P.Chirania submitted that the capital cost of the Unit has increased to Rs. 901.92 crores from the revised cost of Rs. 750 crores, mainly due to loading of IDC. Thus, the loading of IDC of an amount of Rs. 149.10 crores due to delay in declaring of COD should be disallowed. 54. Sh. R.G. Gupta of RVVS submitted to clarify about the following points : Whether in principle approval of the capital cost has been obtained by the petitioner from the Commission? The petitioner has not mentioned the approved capital cost by the Commission and has submitted the petition on the basis of capital cost which has been approved by their BoD or by the Government which is not lawfully valid as per Tariff Regulations. Whether the petitioner has ever submitted project feasibility report to the Commission and whether the Commission has done the prudent check? If so, what was the capital cost of the project in the initial project feasibility report? As per regulation 8(7)(a), variation in the capital expenditure on account of time/cost overrun is to be considered as a controllable factor and accordingly as per regulation 10, 50% of the loss can only be transferred to be borne by other than petitioner. 55. Petitioner’s response: The petitioner provided the break-up of capital cost including details of original project cost, revised project cost as on COD, and a statement of actual capital expenditure up to 11.03.2011, duly certified by the Statutory Auditors, as under: (11) Table No.7: Break up of capital cost as per petition Revised Govt. Approved Cost As per DPR Name of the package Preliminary Investment including land and site development Main plant BTG Package Initial/Capital Spare (BHEL) Station C&I (IL) Mech. Package Electrical Package Civil Works Oil handling plants and equipment’s, material handling equipment bulldozer, miscellaneous civil works, etc. Consultancy & Engineering Administrative and other charges L/L Augmentation work Raw water reservoir and external water supply system IDC and Financing charges Project Cost (Rs. cr.) Revised project cost as on COD (11.03.2011) Project cost up to 11.03.2011 as per Statutory Auditor Statement* 6.88 0.02 364.80 20.00 14.54 121.00 53.92 61.92 624.88 310.00 - 364.80 20.00 13.85 251.80 243.27 - 25.24 18.00 10.59 1.75 9.00 - 1.43 6.00 21.50 1.43 35.16 21.50 0.96 12.77 21.58 - - 8.83 10.87 45.44 617.99 54.00 750.09 173.94 901.92 62.70 744.37 * IDC has been considered up to 31.03.2009 56. Further, the petitioner also submitted the year-wise details of CWIP (Rs. in cr.) starting from FY 2005-06, as provided below: Table No.8: Details of CWIP Year 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 Opening 0.00 12.90 187.20 534.64 697.76 730.87 Addition 12.90 174.29 347.44 163.11 33.11 2.45 (Rs.cr.) Closing 12.90 187.20 534.64 697.76 730.87 733.32 57. The petitioner clarified that the capacity of reservoir for Unit-1 was not sufficient to store water for Unit-1 (GLPL) and Unit-2 (RVUN) both. So, additional reservoir was required for Unit-2. 58. The petitioner submitted that RERC had provisionally approved the capital cost as Rs. 618 cr. vide its order dt. 21.03.2007. Further, capital cost of Rs. 750 cr. was approved by the State Govt. on 11.08.2009. The final capital cost of Rs. 901.92 cr. considering IDC up to COD (12.03.2011) is under process of approval. The petitioner also submitted that enhancement in the capital cost was mainly due to the rise in IDC which was beyond the control of the petitioner. It was also mentioned that GLTPS (RVUN) is the first plant in the world which is utilizing lignite with high sulphur content because of which the unit required some modifications. It was only after (12) that, the full load could be achieved. This led to increase in the project cost. 59. The petitioner furnished the copies of work orders with terms and conditions for supply along with date of placement of orders and price at which they were placed. The petitioner also submitted that in most of the cases, cost of spares was included in work package but in case of M/s BHEL, initial spares were not included. Hence spares amounting to Rs 20 cr. were purchased. There was delay in scheduled completion of BTG and BoP packages due to which Rs 14.36 cr. and Rs 24.32 cr. have been withheld on a/c of L.D. due to delay in commissioning of the unit from M/s BHEL for BTG package and M/s TPL for BoP package, respectively. Further, an amount of Rs 82.23 lakhs has also been withheld from other contractors. The petitioner also submitted that the cost of equipment did not increase due to delay in supply and all the payments have been made as per the terms and conditions stipulated in respective contracts. The petitioner also submitted that mobilization advance was given to M/s BHEL & TPL @ 10% of order value. The petitioner further submitted that in the 159th meeting of BoD held on dt. 29.07.2009, a decision was taken not to deduct 10% amount from running bills on a/c of delay in completion of work from BoP contractor till 31.03.2010. Hence, no refund has been made to the contractor. 60. The petitioner submitted that there are two colonies in Barmer. Expenditure of 1st colony (Vidyut Vihar) has been booked in cost of GLPL Unit-1 and Expenditure of 2nd colony (Urja Vihar) has been booked in cost of GLTPS Unit-2. 61. The petitioner submitted that the increase in capital cost of GLTPP Unit-2 is mainly attributed to delay in commissioning by BTG contractor M/s. BHEL and BOP contractors due to various reasons for failure to adhere completion schedule in terms of their respective contracts. This has resulted in cost escalation of preoperative expenses comprising of establishment, administrative and contingency expenses, frequent trial for lighting and synchronization till the period up to final COD of the unit. 62. The petitioner submitted that the details of the project are submitted along with the data gap of the original petition FY 2011-12 as detailed project report which contain all the information needed by the objector. The petitioner further submitted investment approval of the project cost has not been taken. The determination of capital cost is under consideration of the Commission and the petitioner had submitted all the required documents/data as desired by the Commission for their prudent checking. (13) 63. 64. 65. The petitioner, in response to the meeting with Commission provided the details of adjusted capital cost of Unit-1 and Unit-2 after bifurcation of cost of common assets utilized by both the units, as mentioned here as under: Table No.9: Adjusted capital cost after allocation of common facilities as furnished by petitioner: (Rs.cr.) Description Unit-1 Unit-2 Preliminary Expenses 1.3057 0.4712 Main Plant (BTG) Package including Taxes, Duties, Freight, Price Variation 340.52 364.80 Mechanical Package 92.52 124.40 Electrical Package Control & instrumentation Civil Work Water Supply system including reservoir Augmentation works Total Pre- Operative Expenses, contingency, audit and accounts, legal expenses, development & adm. charges IDC & Financing Cost Total project cost 29.68 10.07 71.58 45.13 11.50 602.30 63.12 14.54 73.95 35.17 21.40 698.15 1.87 13.6869 115.38 719.56 62.6989 774.53 Commission’s Views: The petitioner had submitted a statement of package-wise actual capital expenditure (Rs. 744.37 cr. including IDC of Rs. 62.70 cr. (charged up to 31.03.2009)) incurred up to 11.03.2011 duly, certified by the Statutory Auditors. The matter related to determination of capital cost of the unit has been dealt with in the relevant section. The petitioner has submitted a certificate by the Statuary Auditors of actual capital expenditure incurred up to 11.03.2011 and audited accounts for FY 2009-10. The Commission observed that in the certificate, the IDC has not been included up to COD and the details of item wise capital expenditure are not matching with the package wise capital expenditure furnished by the petitioner. The petitioner, however, submitted the bifurcation of the hard cost as certified by the Statuary Auditor in major heads as provided in DPR. It has been observed that bifurcation of the hard cost is certified by the whole time Directors of GLPL & RVUN but the same is not certified by the Statutory Auditor. In view of the above, prudent check of package wise capital cost on the basis of actual expenditure certified by the statutory auditor is not possible. The determination of capital cost of the unit has been dealt with in the relevant section keeping in view the said position. (14) 66. Lignite Price: Comments of stakeholders/ objectors: Sh. G.L. Sharma submitted that the petitioner should provide details regarding approval of lignite price by the State Govt. or approval of mechanism used for determination of lignite prices. He further submitted that the petitioner should provide reasons for not filing necessary petition for seeking approval of lignite prices to the Commission as per Regulation No. 12(7) of Tariff Regulations, 2009, in case the lignite prices were not approved by the State Govt. nor estimated on the basis of Govt. approved mechanism. 67. Sh. G.L. Sharma also submitted that the petitioner should provide the details for calculation of lignite prices of Rs. 765.93 per MT and Rs. 842.523 per MT for FY 2010-11 and FY 2011-12, respectively. 68. Sh. G.L. Sharma further submitted that the lignite price for FY 2010-11 has been escalated by 10% for taking the price for next FY 2011-12. Such practice should not be adopted as the escalation is covered under F.A.C. clause. 69. Petitioner’s response: The petitioner submitted that price of lignite is based on recommendations of Sh. Shyamal Ghosh, IAS (Retd.), appointed by GoR for evaluation of base lignite transfer price for GLPL Unit-1 and GLTPS Unit-2 both. 70. The petitioner also submitted that the price of lignite for FY 2010-11 was estimated as Rs. 765.93 per MT on the basis of average receipt of lignite during previous three months i.e. Dec 2010, Jan 2011 and Feb 2011. However, in the FSA, basic rate was calculated considering Diesel rate @ Rs. 31.43 per liter and service tax, royalty and VAT were added to the base rate. The price for FY 2010-11 was escalated by10% to estimate the price for FY 2011-12 as Rs. 842.52 per MT. 71. The petitioner also submitted that escalation has been considered in MYT in view of anticipated rise of the lignite. However, tariff for every FY is to be got approved by RERC subject to F.A.C. clause. 72. Commission’s Views: It may be observed that the Giral lignite thermal power project does not have a captive mine. In view of this, lignite transfer price under Regulation 12(7) of RERC Tariff Regulations, 2009 is not required to be determined by the Commission. However, as part of prudent check, the Commission has looked at the reasonability of lignite price claimed by the petitioner. (15) 73. The petitioner has submitted that the lignite prices were based on recommendations of Sh. Shyamal Ghosh, IAS (Retd.) appointed by GoR for evaluation of base lignite transfer price. A Memorandum of Understanding (MoU) was entered into between Rajasthan State Mineral Development Corporation Limited (now merged with RSMML) and RVUNL for development of the Giral Lignite deposits for the Giral Lignite power project in January, 2003. According to clauses of the MoU, the lignite price was to be determined by a committee consisting of Chief Secretary, GOR as Chairman and Mines Secretary and Energy Secretary (GOR) and the CMD’s of RSMDC and RVUNL. The committee took a view that the committee could take a decision based on the report of an expert who would recommend the price based on the objective assessment of claims made by both RSMML and RVUNL. Accordingly, Sh. Shyamal Ghosh and former Chairman of Telecom Commission of India and former Chairman of Gujarat State Petroleum Corporation was appointed as an expert for advising on the price of lignite for supply by the RSMML to RVUNL. Sh. Shyamal Ghosh vide his letter dated 21.11.2005 addressed to Principal Secretary Finance submitted his report on transfer price of lignite. Subsequently, a Fuel Supply Agreement (FSA) was entered into between RSMML and RVUNL based on the transfer price recommended by Sh. Shyamal Ghosh. 74. The Commission has looked at the reasonability of prices as agreed by the petitioner & RSMML based on the recommendation by the expert Sh. Shyamal Ghosh. Shri Ghosh has arrived at sale/transfer price of Lignite based on the mining cost discovered through competitive tendering process. Shri Ghosh in his report at page 27 has stated that the price of Rs. 558/- per M.T. compares favorably with prices in other Lignite Projects. The table at annexure VI of the report shows that sale/ transfer price for Giral Lignite project even at Rs. 650/- per M.T. demanded by the RSMML is lower than lignite prices of other projects like NLC, GIPCL, Surat and NLC’s Barsingsar projects except that of G.M.D.C., where the overburden ratio is more favorable. To further check the reasonability of the rate recommended by Shri Shyamal Ghosh, the Commission finds that the excavation rate per cubic meter of Giral mine works out to Rs. 26.61/cubic meter as compared to Rs. 45.51/ cubic meter of NLC’s Barsingsar mines. In the light of the above discussed position, the lignite price claimed is considered reasonable. Annual escalation of 5% in RSMML expenses such as Site operating expenses and administrative expenses besides actual escalation in diesel price considered by Shri Ghosh is also reasonable. 75. The petitioner has claimed transfer price of lignite as per provisions of Fuel Supply Agreement. In the price component of the lignite, the Diesel escalation is admissible as per actual and among the RSMML expenses, the site operating expenses and administrative expenses are subject to escalation @ 5% per annum. Service Tax, Royalty & VAT is extra at actual. The lignite price of Rs. 765.93 per M.T. based on weighted average of the (16) lignite price for three months (December 2010 to February 2011) as per Shri Shyamal Ghosh’s report is considered by the Commission for FY 2010-11. The Commission has considered the lignite price of Rs. 777.44 per M.T. for the year 2011-12 & 2012-13. 76. The Commission has noted that the petitioner has not clarified whether the petitioner has approached the State Govt. for waival of Royalty and sales tax in compliance of the Commission’s direction vide order dt. 17.07.2006. The petitioner is directed to submit a detailed compliance report along with tariff petition for final determination of tariff for the year 2010-11 & 2011-12. 77. Interest During Construction (IDC): Comments of stakeholders/objectors: Sh. G.L. Sharma submitted that petitioner should provide the amount of IDC in the original cost of Rs. 618 cr. and year wise details of IDC from the year of start of work of the project. 78. Petitioner’s response: The petitioner submitted that the year wise amount of IDC of GLTPP Unit#2 is given as below: Table No.10: Details of IDC Year Amount (Lakhs Rs.) 79. 80. 81. 2006-07 0.93 2007-08 2204.84 2008-09 4065.04 2009-10 5479.91 2010-11 5634.95 Total 17394.00 Commission’s Views: The Commission noted that the petitioner has furnished the details as desired by the stakeholder. The matter related to treatment of IDC for determination of capital cost has been dealt with in relevant section of this order. Fuel Supply Agreement: Comments of stakeholders/objectors: Sh. G.L. Sharma submitted that Fuel Supply Agreement, dt. 19.05.2009, between RVUN and RSMML is for supply of lignite for Unit-1. Thus, the petitioner should provide clarification for using supplies of lignite from RSMML for Unit-2. The petitioner should also clarify as to whether the quantum of lignite to be supplied by RSMML would be sufficient or the position of these units will remain as in the case of RGTPS. Sh. G.L. Sharma further submitted that the petitioner should confirm that as per FSA Clause No. 3.3(I), the lignite consumed during the infirm power period was obtained on cost basis. Petitioner’s response: (17) 82. The petitioner clarified that lignite for Unit-2 was proposed to be delivered from Soneri block and it was proposed to execute FSA for Unit-2 from Soneri block but due to delay in start of mining activities at Soneri block, it was decided mutually, between RSMML and RVUN that RSMML will supply lignite for Unit-2 as well. The petitioner also submitted that RSMML has sufficient lignite to supply for both the units. 83. The petitioner further submitted that as per clause 3.3(I) of FSA dt. 19.05.2009,”the seller shall provide on cost the necessary quantity of lignite and limestone as requested by the buyer for the successful trial operations of the power plant, before the actual commencement of commercial generation of power”. Accordingly, RVUNL claim actual fuel cost during the infirm period from Discoms. 84. 85. Commission’s Views: The Commission observed that Fuel Supply agreement dt. 19.05.2009 has been executed between RVUN & RSMML for unit-1 & no FSA has been executed, so far, for unit-2. Since, the unit-1 has now been transferred to GLPL, the FSA for unit-1 should be transferred in favor of GLPL and a fresh FSA should be entered into by RVUN for Unit-2. Depreciation: Comments of Stakeholders/objectors: Sh. G.L. Sharma submitted that as per form no. 6.1 attached with the petition, the GFA for Building & civil works has been shown as Rs.113.45 cr. and other civil works has been shown as Rs. 15.18 cr., thus totaling to Rs.128.63 cr. Whereas, in the break-up of capital cost of Rs. 901.92 cr., the amount of civil works is only Rs. 5.43 cr.. The petitioner should justify the two figures. 86. Sh. G.L. Sharma also submitted that as per form no. 6.1, the GFA for furniture & fixtures has been shown as ‘Nil’. The position seems beyond imagination. The petitioner should clarify. 87. Sh. G.L. Sharma further submitted that as per form no. 6.1, the cost of spares has been shown as Rs. 30.99 cr., whereas in the break-up of capital cost, the same has been shown as Rs. 20.00 cr. only. 88. Sh. G.L. Sharma further submitted that as per form no. 6.1, available at page 31 of the petition, it may be perused that at the beginning of FY 2010-11, gross assets were to the tune of Rs. 8.119 crores and addition during the year has been shown as Rs. 893.803 crores and thus total at the end of the year has been shown as Rs. 901.922 crores. As per Statutory Auditor’s certificate, the total expenditure has been shown as Rs.744.38 crores and as such how the RVUN justifies the total gross assets of Rs.901.922 crores as on 31.03.2011 and has claimed/ calculated the depreciation accordingly. Further, as per statement at page 31, the (18) depreciation to the tune of Rs. 0.798 crore has been claimed in FY 2009-10 i.e. prior to the date of so called COD. RUUN has to clarify the position. 89. Petitioner’s response: The petitioner submitted that the heads of break-up of capital cost and form no.6.1 are different. So, no comparison is possible. 90. The petitioner also submitted that the Vehicles and furniture & fixtures of unit-1 are utilized for unit-2 also, no separate Vehicles and furniture was purchased for unit-2. 91. The petitioner further submitted that the cost of spares in breakup of capital cost is only for M/s BHEL initial spares and in form no. 6.1; the amount is for initial spares of the whole plant. 92. The petitioner further submitted that the depreciation for tariff computation has been considered as per RERC Tariff Regulations, 2009. The depreciation charges are subject to truing up based on actual capital expenditure as per audited accounts for 2010-11. 93. 94. Commission’s Views: As per the RERC Tariff Regulation, 2009, regulation 23 (6), depreciation shall be chargeable from the first year of commercial operation. Hence depreciation charged before the COD cannot be allowed. Station Heat Rate (SHR): Comments of stakeholders/objectors: Sh. G.L. Sharma submitted that the petitioner should provide details of calculation for Station Heat Rate including turbine cycle heat rate, boiler efficiency rate, and percentage of moisture content in the lignite. He also submitted that the petitioner should provide basis for calculation of design heat rate of 2483.9 kcal/ kWh. 95. Sh. G.L. Sharma also submitted that the petitioner has taken the moisture content as 40%, but vide its letter dated 25.10.2011 (Para 21 thereof) has intimated the Moisture content as 31 to 34% on the basis of samples of fuel received. The fuel being the same, percentage of moisture content of lignite cannot be changed. 96. Sh.D.P.Chirania submitted that SHR for FY 2012-13 has been projected as 2602.97 Kcal/Kwh on normative basis as against the actual of 3599.39 Kcal/Kwh for FY 2011-12, which seems hardly to be achievable. As such, realistic figure should be taken for consideration for approval of ARR. 97. Petitioner’s response: The petitioner submitted that the moisture content of lignite is taken as 40% as per Fuel Supply Agreement with RSMML. (19) 98. The petitioner provided the detailed calculation of Station Heat Rate as shown in table below: Table No.11: Calculation of SHR as per petition Gross heat rate Design boiler efficiency Design turbine heat rate Design unit heat rate kcal/kwh (Turbine heat rate/boiler eff.)*100 Gross heat rate (1.065 x DHR) 99. 100. 101. 102. Gross heat rate at 100% TMCR 80.30% 1994 2483.9 2645.39 Kcal/kwh Commission’s Views: The Commission has allowed station heat rate as per Regulations. Special O&M charges: Comments of stakeholders/objectors: Sh. G.L. Sharma submitted that the special O&M charges are admissible only when the process water is required to be transported over a distance of more than 50 K.M. The petitioner should provide the details regarding source, distance and means for transportation of water. He also submitted that the petitioner should provide details regarding consumption of electricity towards pumping operation up to the distance of 50 km. and beyond 50 km. of distance. Sh. G.L. Sharma submitted that petitioner should provide justification for claiming special O&M charges even though there is no independent water supply system for Unit-2. Petitioner’s response: The petitioner submitted that Giral Lignite Power Plant is transporting water from IGNP Zero head at Mohangarh by pipeline of 600 NB dia. For this, pipeline of about 168 km had been laid from Mohangarh to Giral and a reservoir had been constructed at Mohangarh for collecting water. They also submitted that there are four pumping stations for transporting water to Giral namely Mohangarh (as intake) and Kanod, Aakal and Devikot (as boosting station). 103. The petitioner submitted that average of electricity consumption had been considered in tariff petition for all the 4 pumping stations. 104. The petitioner also submitted that main pumps were in the scope of GLPL Unit-1 and secondary booster pumps were in the scope of GLTPS Unit-2. So, there is no independent water transporting system for GLTPS Unit-2. All the expenditure of transporting of water from Mohangarh to power plant is distributed in equal parts, so further justification is not required. (20) 105. 106. 107. Commission’s Views: Petitioner has claimed the water charges, manpower for operation & maintenance and Electricity Charges for pumping station. The Commission has considered only Electricity Charges for pumping station beyond the distance of 50 km from water sources. According to the information the Pump House at Mohangarh and Kanod are within reach of 33917.24 meters i.e. 33.9 Km. The other two Pump Houses are at a distance of more than 50 K.M. distance from the water intake point. The Petitioner has not provided any supporting data for actual expenses for water pumping all the expenses are on expected basis. In view of above, the Commission has considered the electricity consumption at Akalphata and Devikote pumping stations for both the units collectively and provisionally only 50% charges are being allowed. Petitioner is directed to provide the actual expenses on this account in the petition for determination of final capital cost and Tariff for FY 2010-11. Interest on term loan & finance charges: Comments of stakeholders/objectors: AVVNL and JVVNL submitted that as per the agreement between the petitioner and Power Finance Corporation, the petitioner had to make annual payments of around Rs. 48 cr. each year starting from 15.04.2009 towards repayment of loan. However, the petitioner had not repaid any installment in FY 2009-10 and only Rs. 2.47 cr. was repaid in FY 2011-12. Therefore, the petitioner should provide clarification regarding the same. 108. AVVNL also submitted that the average rate of interest @ 11.25% has been considered while calculating the interest on term loan. But from the sanction letters of loans from banks/ financial institutions, it is observed that the rate of interest is lower. The petitioner should also provide the details of steps taken to refinance the loan at less interest rate. 109. Sh. G.L. Sharma submitted that the loan amount of Rs. 565 cr. was sanctioned by PFC, whereas the petitioner had considered term loan of Rs. 716.92 cr. in the petition. The petitioner should provide clarifications regarding the same. 110. Sh. G.L. Sharma submitted that the petitioner should provide the reasons for obtaining working capital loans without achieving COD of the plant and utilizing the same for creation of the fixed assets. 111. Petitioner’s response: The petitioner submitted that as per RERC regulations 2009, repayment is to be considered equal to the depreciation allowed for that year. Thus, repayment of loan has been considered as equal to the depreciation of Rs. 2.47 cr. in the petition. (21) 112. The interest rate mentioned in the sanction letter is as prevailing at the time of sanction but the rate is chargeable as per interest rate as prevailing at the time of actual drawl, which may be lower or higher in comparison to the rate mentioned in the sanction letter. The petitioner has also provided the details of actual payment of interest and weighted average rate of interest of 11.22 % for 2nd quarter of 2012-13. 113. The petitioner submitted that the short term/working capital loans were obtained for the purpose of completion of capital works of Giral Unit-2. Details of State Govt. equity and loans for Unit-2 were also provided as below: Table No.12: Details of Govt. equity & loans as per petition 2006-07 Year Govt. Equity (A) Loans (B) PFC Loan No. 07301015 PFC Loan No. 07301022 Short term Loan Transitional Loan Total Loans 114. 115. 116. Addition Closing 2007-08 2008-09 (Rs cr.) 2009-10 2010-11 Addition Closing Addition Closing Addition Repayment Closing Addition Repayment Closing 35 35 89 124 61 185 - - 185 - - 185 87.51 87.51 194.42 281.94 158.31 440.25 0.74 14.7 426.29 - 29.39 396.89 - - - - - - 124 - 124 - 8.55 115.44 - - - - 100.1 100.1 - 86.48 13.62 138.3 - 151.92 87.51 87.51 194.42 281.94 258.41 540.35 14.7 139.44 101.18 14.7 578.61 35.47 173.78 37.95 50.17 714.44 The petitioner submitted that due to delay in COD of Unit-2, working capital loans have been utilized for up keeping and maintenance of equipment, land, townships, purchase of coal and fuel, etc. It was necessary to run the plant to achieve COD and amount was spent to meet various expenditures to run the plant. It was further submitted that the petitioner was not receiving any amount against the generation except fuel cost. Commission’s Views: The Commission agrees with the petitioner’s view that loan repayment amount is to be considered equal to depreciation for the purpose of tariff determination as per requirement of the regulations and the rate of interest has been considered as claimed in the petition. The Commission has considered the long term loan requirement based on the capital cost determined. The short term loan requirement has been allowed as per norms prescribed for working capital requirement in the Regulations. (22) 117. 118. 119. 120. 121. Debt-Equity Ratio: Comments of stakeholders/objectors: Sh. G.L. Sharma submitted that equity contribution of Rs 185 cr. was considered in the estimated capital cost of Rs 618 cr. resulting in debt equity ratio of 70:30. The project cost was further increased to Rs.901.92 cr. but the amount of equity had remained same resulting in debt-equity ratio of 79.5: 20.5. The petitioner should provide clarifications regarding the same. Petitioner’s response: The petitioner submitted that initially State Government had granted 70:30 as ratio for debt and equity which had been changed to 80: 20 in 2005. Thus it was as per the State Government orders. Commission’s Views: As per RERC Tariff Regulations 2009, Regulation 17 “in case actual equity employed is less than 30%, the actual equity shall be considered”. Equity contribution by the GoR (as approved vide their letter dated 11.04.2005) has been considered as Rs. 185 cr. for Unit-2 which works out to be 23 % of the capital cost, approved by the Commission. Insurance charges: Comments of stakeholders/objectors: Sh. G.L. Sharma mentioned that the petitioner had claimed insurance charges of Rs. 0.04 cr. and Rs. 0.81 cr. for FY 2010-11 and FY 2011-12 respectively but had not submitted any documentary proof in this respect. He further submitted that as per tariff Regulations, such charges are admissible only on actual basis and thus requested the petitioner to submit the information. Petitioner’s response: The petitioner submitted that the actual insurance charges for 2012-13 for Unit-2 is Rs. 0.55 crore and also furnished the copy of plant insurance policies. 122. Commission’s Views: The petitioner in response to the stakeholder’s query has submitted the documentary proof and the same has been considered. 123. Cost of Land: Comments of Stakeholders/objectors: Sh. G.L. Sharma submitted that the petitioner should provide the justification of cost of land that was shown as Rs.8.58 cr. for Unit-1 and Unit2 while the land cost was only Rs. 1.7 cr. (23) 124. Petitioner’s Response: The petitioner submitted that while the land cost for Unit-1 and Unit-2 was Rs. 1.7 cr. only, figure of Rs. 8.58 cr. includes preliminary investment and land & site development expenses. 125. Commission’s Views: The Commission has considered the cost of land as certified by the statutory auditors. 126. CSR Activity: Comments of Stakeholders/objectors: AVVNL and Sh. G.L.Sharma submitted that the amount claimed under the head “CSR Activity” is to be met by the petitioner from his normal O&M Expenses. 127. Petitioner’s Response: The petitioner submitted that the expenditure under the head “CSR Activity” can be considered under O&M expenses. 128. 129. 130. 131. 132. Commission’s Views: The Commission is not allowing any expenditure under the head “CSR Activity”, as the same is to be met from the petitioner’s own sources and this cannot be added to ARR as additional expenditure. Auxiliary Consumption: Comments of Stakeholders/objectors: AVNNL and Sh. D.P.Chirania submitted that the auxiliary consumption for FY 2010-11 has been considered @ 19.40 % whereas the Commission has specified 11.50% in the RERC Tariff Regulations, 2009. It is requested to consider the same suitably in the ARR of the petitioner. Petitioner’s Response: The petitioner submitted that the data for 2011-12 are based on actual/estimates and are for reference and has no impact on tariff of 2012-`13. Commission’s Views: The Commission has considered the percentage of auxiliary consumption as per norms of the regulations. Plant Load Factor: Comments of Stakeholders/objectors: AVNNL submitted that the PLF for FY 2010-11 has been considered @ 26.54 % whereas the Commission has specified 70.00% in the RERC Tariff Regulations, 2009. The reasons for not achieving the targeted norms have not been mentioned in the petition. (24) 133. 134. 135. 136. 137. Sh. D.P.Chirania submitted that actual PLF for FY 2011-12 is only 26.54% and therefore estimating it as 72.60% for FY 2012-13 is not only erroneous but a deliberate attempt of wrong projection, detrimental to consumer’s interest. Petitioner’s Response: The petitioner submitted that the data for 2011-12 are based on actual/estimates and are for reference and has no impact on tariff of 2012-`13. Commission’s Views: The Commission has considered the percentage of PLF as per norms of the regulations. General: Comments of Stakeholders/objectors: Sh. G.L.Sharma queried as to whether the petition in question bears the approval of BoD of RVUN. A copy of BoD’s resolution may be provided by the petitioner. Further, a copy of resolution passed by the BoD authorizing the C.M.D. for filing the petition and/or authorizing any person for the purpose may kindly be made available with the petition. Sh. B.M. Sanadhya of Samta power submitted the following points: Justification for operating of Unit-1 in the name of GLPL and operating of Unit-2 in the name of RVUN, when both the Units are at same place and plant & equipment are also common. To clarify about the efforts made for improvement of lignite mining technology to reduce cost as per clause no 5.2 of NEP-2005. To clarify about the policy of the petitioner in respect of clause no. 5.2.21, 5.2.22 & 5.2.23 of NEP-2005. To clarify about the policy & action plan of the petitioner in respect of clause no. 5.6 of NEP-2005 “Technology Development and R&D. To clarify about the policy & action plan of the petitioner in respect of clause no. 5.11 of NEP-2005 “Training and Human Resource Development”. To clarify about the efforts made for encouraging the competent & sincere engineers & employees to be retained in the organization against offers from private sector. To clarify about technical. Managerial and policy efforts made for improvement in PLF, reduction of the cost and improvement in overall productivity. What are the possible solutions to overcome the problem of high sulphur content? Whether any R&D and comparative economics study has been done in respect of the options. (25) To clarify about the possible solutions for reducing the cost of Rs. 2.43 per unit. To make available the details about cost of advertisement of public notices, number of employees & public men present in the presentation on dated 10/09/2012, numbers of persons who have given their suggestions/ objections on the petition and efforts for ensuring the maximum participations in the presentations & hearings. Justification for non attendance of Directors/ officers, who are competent to take policy decisions. Justification for ignoring of the request for video-graphing of the presentation and public hearings. 138. 139. 140. Petitioner’s Response: The petitioner submitted that the petition has been filed after the approval of Whole Time Directors. The Regulations do not provide that the petition should be filed only after approval of BoD. Further, C.M.D., RVUN has authorized the C.E. (PP&M) and CAO (W&M) RVUN for filing the petition in RERC format. A copy of the same is enclosed with the petition. The petitioner submitted that requisite actions are taken by the petitioner, but all these matters are administrative and policy related, which do not pertain directly to the petition under consideration. Commission’s Views: It is noted that stakeholder has raised some questions and sought some information also. The comments relevant for this order have been dealt with appropriately. SECTION-III Determination of Capital Cost 141. 142. Petitioner’s Submission: The petitioner submitted that the initial project cost for Unit-2 of GLTPS as envisaged in the DPR was Rs. 618 cr. and State Govt. conveyed approval for the same vide letter dt. 11.04.2005. It was subsequently revised to Rs. 650 cr. and the State Govt. provided its approval vide its letter dt. 26.04.2008. The project cost was again revised to Rs 750 cr. and approval of the State Government was provided vide letter dt. 11.08.2009. Considering the expected COD as 31.03.2011, the enhanced cost of the project was revised to Rs. 908 cr. However, the actual COD was declared on dt.12.03.2011 and hence the revised capital cost is worked out as Rs 901.92 cr., which includes IDC of Rs.173.94 cr. up to the date of commercial operation. The petitioner has also submitted the capital cost of Unit-2 after apportionment of common facilities as Rs.905.35 Cr. (26) 143. The actual capital expenditure up to 11.03.2011 as per certificate of the Statutory Auditors is Rs. 744.37 Cr. including IDC. The breakup of capital cost as petitioned is as follows : Table No.13: Details of capital cost as per petition S. No Name of the package As per DPR 1 Main plant BTG Package(BHEL) 2 3 Initial/Capital Spare (BHEL) 4 A B C Balance of Plant M/s.TPL Package(Inc.addl.ACW) Bulldozer Supply of 100 MT Weighbridge Modification work of AHP Capacity increase of Guard Pond, Height increasing of administrative Building & other Civil Work. Addl.LDO tank Portable Centrifugal Machine DOT & COT tanks Revised plans of ESP control Room Consultancy & Engineering(Design) D E F G H I 5 6 7 A B 8 (Rs. cr.) Project Cost for Giral Unit-2 Final as on Revised COD Approved approved Cost by BoD As per Statutory auditor statement 310.00 364.80 364.80 - 20.00 20.00 11 13.85 14.54 624.879 232.80 243.27+61.24 7.89 0.35 3.5 243.72 7.61 0.25 3.50 8.0614 5.5 0 0 0.25 0.21 0.31 0.35 0.25 0.21 0.30 0.35 Station C&I (IL) 0 0.29 1.43 Administrative & Other charges Legal Expenses & Development Exp., PreOperative exp., Audit & Accounts, Contingency, O&M Exp. L/L Augmentation Work Misc.Civil Work Raw Water reservoir IDC & Financing Charges Grand Total: 10.64 0.96 7.43 12.792 35.16 53.66 618.00 21.5 6.88 0 54.00 750.00 21.50 5.43 8.83 173.94 901.92 21.59 2.249 10.87 62.698* 744.3894 *IDC has been considered up to 31.03.2009 144. The petitioner also submitted the bifurcation of the hard cost as certified by the Statuary Auditor in major heads as provided in DPR and after bifurcating the common cost between unit-I & unit-II submitted the final adjusted capital cost. The breakup of capital cost, as petitioned as per DPR, revised as on COD and adjusted after bifurcating the common cost is as follows: Table No.14- Details of project cost as submitted by the petitione Description Preliminary Expenses Main Plant (BTG) Package including Taxes, Duties, Freight, Price Variation Mechanical Package Electrical Package Control & instrumentation Revised project cost as on COD (12.03.2011) as petitioned As per DPR (Rs.in cr.) Project cost as on COD after apportionment of common expenditure 0 0 0.47 310 364.80 364.80 116.50 51.00 11.00 243.72 14.54 124.40 63.12 14.54 (27) Civil Work External Water Supply Misc works including L/L augmentation Total – Hard cost PreOperative Expenses, contingency, audit and accounts, legal expenses, development, Design and engineering consultancy services & administrative charges IDC & Financing Cost Project cost 145. 65.30 0 0 8.83 73.95 35.48 0 59.50 21.39 553.80 691.39 698.15 10.64 36.59 13.69 53.56 173.94 62.70 618 901.92 774.54 Commission Analysis: The Commission observes that the petitioner has submitted the revised capital cost amounting to Rs. 901.92 cr. on the CoD including the IDC amounting to Rs. 173.94 cr. up to 12.03.2011. The statement of actual capital expenditure on COD, duly certified by the Statutory Auditors as furnished by the petitioner is for Rs.744.37 cr. only. It has been observed that in the statement of actual capital expenditure on COD, duly certified by the Statutory Auditors, the IDC amount has been considered only up to 31.03.2009 amounting to Rs.62.70 cr. whereas, in the amount of revised project cost on COD, as furnished by the petitioner, the IDC amounting to Rs. 173.94 cr. up to 12.03.2011 has been considered. The Commission has observed that IDC has not been capitalized in the Annual Accounts of FY 09-10 & onwards till COD. 146. The petitioner has also submitted that adjusted capital cost of Unit-2 after apportionment of common facilities being used by both Unit-1 and Unit-2 works out as Rs. 774.53 cr which includes hard cost of Rs. 698.15 cr. As per the statement of the Statutory Auditors, the capital expenditure incurred up to 11.03.2011 in respect of Unit-2 is Rs 744.39 crores. As per the bifurcation of certified capital expenditure incurred up to 11.03.2011,as submitted by petitioner, the hard cost is Rs. 668 cr. 147. The Regulation No.44(4) & 44(5) of RERC Tariff Regulations,2009 provides as under: 44(4): A generating company may make petition for determination of provisional tariff in advance of the anticipated date of commissioning of Unit or Stage or Generating Station as a whole, as the case may be, based on the capital expenditure actually incurred upto the date of making the petition or a date prior to making of the petition, duly audited and certified by the statutory auditors and the provisional tariff shall be charged from the date of commercial operation of such Unit or Stage or Generating Station, as the case may be. (28) 44(5): A generating company shall make a fresh petition as per these Regulations, for determination of final tariff based on actual capital expenditure incurred up to the date of commercial operation of the generating station duly certified by the statutory auditors based on annual audited accounts. 148. The Commission observed that the certificate of actual capital expenditure up to the date of COD issued by the statutory auditor is not based onannual audited accounts. Further, the certificate issued by the statutory auditor does not provide the capital expenditure head wise/package wise as per DPR. The Commission noted that the Statutory Auditors have certified the lump sum figure of Rs. 624.88 cr. against Main plant BTG package, Initial/ capital spare (BHEL), Station C&I (ii), Mechanical package, Electrical package & Civil Works. Also, in the certificate issued by the statutory auditors, the IDC has been included up to 31.03.2009 only not up to the date of commercial operation. 149. In view of above, the Commission is determining the provisional capital cost subject to furnishing of the certificate of actual capital expenditure up to COD based on audited accounts as per requirement of the Regulations for final determination of capital cost. The Commission directs the petitioner to submit the required details along with the head wise/package wise as per DPR actual capital expenditure as on the COD duly certified by the statutory auditors based on audited annual accounts. 150. 151. Cost of BTG, BoP & other packages: The petitioner submitted that the main plant (BTG) package was awarded to M/s. BHEL after series of negotiations for Rs. 262 cr. for supply and Rs. 25.25 cr. for erection, testing & commissioning. The prices were exclusive of all taxes & duties, WCT, ST, freight & price variation. The petitioner also submitted that necessary justification of the cost of BTG package had been examined when the contract on BHEL was awarded by comparing the corresponding costs of various other contracts bagged by BHEL through ICB or through negotiations during bidding. The cost of main plant (BTG) package as per DPR was Rs. 310 crores and the revised cost as on COD as per petition is proposed as Rs. 364.80 crores and cost on COD after allocation of common expenditure is Rs. 364.80 crores. The reason for increase in the cost of BTG package, besides general escalation in the price of Steel and cement was due to heavy booking of orders with BHEL. The BoP contract was awarded to M/s. Tata Projects Ltd. at a total cost of Rs. 139.83 cr. for supply and Rs. 102.67 cr. for erection, testing & commissioning. The prices were inclusive of all taxes & duties, freight etc. The estimated cost of BoP packages as per DPR was Rs. 232.80 crores and as per revised project cost as on COD and cost on COD after allocation of common expenditure is Rs. 243.72 crores & 261.47 crores respectively. (29) 152. 153. 154. 155. 156. Cost of Spares: The petitioner submitted that the total cost of spares included in the capital cost is Rs.30.99 cr. As per Regulation no. 18(6)(a) of Tariff Regulations, 2009, the capital cost may include capitalized initial spares up to 2.5% of original capital cost in case of coal based/lignite based generating stations. Thus, the cost of spares to the value of Rs. 18.75 cr. only is considered in the capital cost. Thus, the balance amount of Rs. 12.24 cr. is reduced from the hard capital cost. As regards, capital expenditure on external water supply system and raw water reservoir, the revised cost as on COD is proposed as Rs. 10.87 crores and cost as on COD after apportionment of common expenditure is proposed as Rs. 35.47 crores. The statutory auditor in its certificate has certified total amount of Rs. 10.87 crores for external water supply system. Treatment of Liquidated damages recovered from Suppliers/Contractors: Since the Commission has considered 50% liability of additional IDC to be included in the capital cost, considering the same principle 50% of the LD amounting to Rs.19.75 cr. recovered by the petitioner is reduced from capital cost. As discussed earlier, the petitioner is directed to work out the final amount of LD recoverable from the suppliers/contractors and report the progress in the petition for determination of final capital cost and Tariff FY 10-11 for final treatment. Total hard cost: The estimated total hard cost (excluding pre-operative & IDC) of the project as per DPR was Rs. 553.80 crores and the revised hard cost as on COD is proposed as Rs. 691.39 crores. As per certificate of the statutory auditors, the hard cost works out to be Rs. 668 crores approximately. Petitioner has submitted the adjusted capital cost of Rs. 698.15 cr. after allocation of common cost between unit -1 & 2. After reducing the cost of initial spares as 12.24 crores and 50% amount of L.D. recovered, the total hard cost comes to Rs. 666.16 crores. The adjusted hard cost of Rs. 666.16 crores as on 12.03.2011 is against the revised hard cost as on COD as Rs. 691.39 crores and estimated hard cost of Rs. 553.80 cr. as per DPR of June, 2005. It may be noted that external water supply system and some common assets were not taken into consideration while preparing the DPR. However, the cost of the external water supply system and common assets are also included in the cost of Rs. 666.16 crores. Thus the hard cost of Rs. 666.16 cr. is considered reasonable and provisionally allowed by the Commission subject to furnishing of the certificate of package wise actual capital expenditure as on COD of the statutory auditor along with petition for determination of final capital cost. (30) 157. 158. Preoperative The petitioner has claimed an amount of Rs.36.59 crores as per final cost as on COD on account of pre-operative expenses, contingency, audit and accounts, legal expenses, development, Design & engineering consultancy and administrative charges. The petitioner submitted that due to delay in achieving the COD, the same expenses have increased significantly. In absence of the actual expenditure based on audited accounts, Commission is considering pre-operative expenses equal to 5% of hard cost of Rs. 685.91 crores i.e. Rs.34.30 crores. Treatment of IDC due to delay in COD of the unit: The Commission noted that there has been a major increase in capital expenditure on account of increase in IDC due to delay in COD because of the various factors, as discussed above. The petitioner has submitted that delay in commissioning is on a/c of delay in obtaining environment clearances and road blockage due to flood. 159. The petitioner submitted that Giral Lignite project is based on CFBC technology, which is useful for low calorific value and significant sulphur content. However, constraints of such Boiler and variation in Ash and sulphur contents found in Giral Lignite could not be made adequately compatible with boiler equipments. BHEL consulted various external agencies and carried out research on the problems faced to run the unit on full load capacity and enable GLPL declare Unit on commercial operation. 160. The Commission observes from the information furnished by the petitioner that the entire delay in achieving COD cannot be attributed to the petitioner. Hence, following the principle laid down by APTEL in its order dt.27.4.2011; the Commission allows 50% of additional IDC in the capital cost. As per DPR, the IDC is Rs. 53.56 crores and the petitioner has claimed IDC of Rs. 173.94 crores as per revised project cost. The Commission deems it appropriate to allow the IDC amount of Rs. 53.56 crores as envisaged in DPR. The petitioner has claimed an additional IDC of Rs.120.38 crores over and above of IDC envisaged in DPR. The Commission deems it appropriate to further allow as IDC an amount of Rs. 60.19 crores being the 50% of additional IDC totaling to Rs. 113.75 crores. Thus, an amount of Rs. 113.75 crores is provisionally considered as IDC. 161. The petitioner has not submitted the capital expenditure incurred till the COD (12.03.2011) based on audited accounts. In absence of actual capital expenditure up to date of commercial operation duly certified by the Statutory Auditors based on annual audited accounts as per regulation 44(5), the final tariff cannot be determined at this stage. Hence in absence of the sufficient information, the Commission has provisionally considered the capital expenditure subject to determination of capital (31) cost based on audited accounts duly certified by the Statutory Auditors in the petition for determination of final capital cost & tariff for FY 2011-12. 162. Thus the capital cost finally determined by the Commission is as under: Table No15: Capital Cost provisionally allowed by the Commission Description Preliminary Expenses Main Plant (BTG) Package including Taxes, Duties, Freight, Price Variation Mechanical Package Electrical Package Control & instrumentation Civil Work External Water Supply Misc works including L/L augmentation Less: reduction on a/c of initial spares Less: 50% of L.D. recovered Total – Hard cost PreOperative Expenses, contingency, audit and accounts, legal expenses, development, Design and engineering consultancy services & administrative charges IDC & Financing Cost Project cost 163. Revised project cost as on COD (12.03.2011) as petitioned As per DPR 0 0 Project cost as on COD after apportionment of common expenditure 0.47 (Rs. cr.) Project cost provisionally allowed by the Commission 0.47 364.80 310 364.80 116.50 51.00 11.00 65.30 0 0 14.54 0 8.83 124.40 63.12 14.54 73.95 35.48 59.50 21.39 243.72 0 364.80 0 124.40 63.12 14.54 73.95 35.48 21.39 0 12.24 691.39 0 698.15 19.75 666.16 10.64 36.59 13.69 34.30 53.56 173.94 62.70 113.75 618 901.92 774.54 814.21 0 553.80 0 Financing Plan & Debt/ Equity Ratio: Out of approved capital cost of Rs. 814.21 cr., an amount of Rs. 185 cr. is considered as equity and the balance amount of Rs. 629.21 cr. is considered as term loans. The Debt/Equity ratio of approved financing plan works out to 77:23, which is provisionally approved as per Tariff Regulations, 2009. SECTION-IV Determination of fixed and variable charges of generation for MYT period: 164. Fixed charges: Operation & Maintenance (O&M) Expenses: Petitioner’s Submission: Petitioner has claimed O&M expenses including special O&M expenses, as per RERC Tariff Regulations, 2009, as under: (32) Table No. 16: O&M Expenses as claimed in petitions: (Rs. cr.) Particulars As claimed in petitions 165. 166. 167. FY 2010-11 1.26 FY 2011-12 FY 2012-13 24.49 25.99 O&M expenses for 2010-11 have been considered for 20 days considering COD as 12.03.2011. O&M expenses have been escalated at 5.72% in each year. Petitioner has also claimed special O&M expenses for water transportation. Commission Analysis: As per Regulation 48 of RERC Tariff Regulations, 2009, O&M expenses for lignite based generating stations are “Rs. 16 lakh per MW for 2009-10” and as per Regulation 25 (4) the same shall be escalated @ 5.72% per annum. The Commission has considered the same for allowing of O&M expenses. As regards special O&M expenses, the Commission as discussed earlier allowed electricity consumption at Akalphata and Devikote pumping stations amounting to Rs. 2.12 cr for both the units collectively. The Commission considered Rs. 1.06 cr as electricity consumption for unit –II and provisionally allowed Rs. 0.53 cr being 50% charges. The details of O&M Expenses including Special O&M allowed by the Commission are as under: Table No.17: O&M Expenses allowed by the Commission (Rs.cr.) Year Allowed by Commission 168. the FY 2010-11 FY 2011-12 FY 2012-13 1.19 22.88 24.47 Depreciation: Petitioner’s Submission: The depreciation claimed by the petitioner is as under: Table No. 18: Depreciation as claimed in petitions 169. 170. (Rs. cr.) Year FY 2010-11 FY 2011-12 FY 2012-13 As claimed in petitions 2.47 45.13 45.13 Petitioner has claimed depreciation on the total project cost of Rs.901.92 cr. at the rates specified in RERC Tariff Regulations 2009 for a period of 20 days during the year 2010-11 considering the commissioning of the unit on 12.03.2011. For the subsequent years, the depreciation has been charged for the full year. Commission Analysis: Depreciation allowed by the Commission is on the basis of provisionally approved capital cost. In absence of complete details, assets have been (33) categorized broadly under Building & Civil works of Power plant, Plant & machinery and land. The plant and machinery has been depreciated @ 5.28% and Building & Civil works of Power plant has been depreciated @ 3.34%. Land has not been depreciated as per the RERC Tariff Regulations, 2009. The details of depreciation allowed by the Commission are as under: Table No. 19: Depreciation allowed by the Commission (Rs. cr.) Year Allowed by Commission 171. the FY 2010-11 2.22 FY 2011-12 40.41 FY 2012-13 40.41 Interest on Term Loan and finance charges: Petitioner’s Submission: The Interest on term loan and finance charges claimed by the petitioner is as under: Table No.20: Interest on term loan as claimed in petition (Rs.cr.) Year As claimed in petitions 172. 173. FY 2010-11 4.41 FY 2011-12 77.84 FY 2012-13 73.50 Commission Analysis: As per RERC Tariff Regulations 2009, Regulation 17 “in case actual equity employed is less than 30%, the actual equity shall be considered”. Equity contribution by the Government of Rajasthan has been considered as Rs. 185 cr. for Unit-2 which works out to be 22% of the approved capital cost by the Commission, as discussed above. Based on this, loan amount has been considered as Rs. 648.96 crores. The loans were sanctioned with the proviso that actual rate of interest shall be as prevailing on the date of disbursement. Petitioner has claimed weighted average rate of interest @11.25% which is accepted by the Commission. The details of interest on Term Loan and finance charges approved by the Commission is as under: Table No. 21: Interest on term loan allowed by the Commission (Rs cr.) Particulars Opening Balance Repayment During the year Addition during the year Closing Balance Average rate of interest Finance Charges Int. on loan 174. As approved by Commission 2010-11 2011-12 2012-13 629.21 626.99 586.52 2.22 40.47 40.47 626.99 586.52 546.05 11.25% 0 3.87 11.25% 0.78 69.04 11.25% 0.74 64.45 Interest on Working Capital Loans: Petitioner’s Submission: Petitioner has computed interest on working capital loan as per norms defined under Regulation 49 of RERC (Tariff) Regulations, 2009. Rate of (34) interest on working capital loans has been considered as equal to prime lending interest rate of SBI as on 1st April of the respective year. Interest on working capital loans as claimed by the petitioner is as under:Table No. 22: Interest on WCL as claimed in petitions: (Rs. Cr.) 175. Year FY 2010-11 FY 2011-12 FY 2012-13 As claimed in petitions 0.23 5.48 6.33 Commission Analysis: The rate of interest has been claimed @ 11.75% & 13.00% for the year 201011 & 2011-12 respectively and the same is being allowed as per Regulations. 176. The rate of interest has been claimed @ 14.75% for the year 2012-13. As per amendment dated 31.08.2012 in RERC Tariff Regulations, 2009, the rate of Interest on working capital loan shall be 250 points higher from SBI base rate prevalent during first 6 months of previous year. Accordingly for working out interest rate on working capital, weighted rate of interest has been considered as per admissible rates during the year. The same works out to be 13.27% p.a. for FY 2012-13. 177. The interest on working capital as approved by the Commission, has been provided in the table below: Table No.23: Interest on WCL allowed by the Commission 178. (Rs. cr.) Year FY 2010-11 FY 2011-12 FY 2012-13 Allowed by the Commission 0.21 4.38 4.53 Recovery of ARR and Tariff Petition Fee: Petitioner’s Submission: The ARR and Tariff Petition Fee as projected by the petitioner is as under: Table No. 24: Recovery of ARR and Tariff Petition Fee as claimed in petitions (Rs. cr.) Year FY 2010-11 FY 2011-12 FY 2012-13 0.06 0.06 0.06 As claimed in petitions 179. Commission Analysis: The ARR and Tariff Petition Fee have been allowed by the Commission as claimed by the petitioner. The details of AAR and Tariff petition fee allowed by the Commission are as under: Table No.25: Recovery of ARR and Tariff Petition Fee allowed by the Commission Year Allowed by the Commission (Rs. cr.) FY 2010-11 FY 2011-12 FY 2012-13 0.06 0.06 0.06 (35) 180. Insurance charges: Petitioner’s Submission: The insurance charges as claimed by the petitioner are as under: Table No.26: Insurance charges as claimed in petition (Rs. cr.) Year As claimed in petition 181. FY 2010-11 FY 2011-12 0.04 FY 2012-13 0.81 0.56 Commission Analysis: The insurance charges have been allowed by the Commission as per details provided by the petitioner on 03.01.2013. The details of insurance charges allowed by the Commission are as under: Table No.27: Insurance charges allowed by the Commission :(Rs. cr.) 182. Year FY 2010-11 FY 2011-12 FY 2012-13 Allowed by the Commission 0.04 0.79 0.51 CSR Activity: Petitioner’s Submission: The petitioner has claimed expenditure on account of CSR Activity, as under; Table No.28: CSR Activity as claimed in petitions (Rs. cr.) Year As claimed in petitions 183. FY 2010-11 - FY 2011-12 - FY 2012-13 0.06 Commission Analysis: The Commission is not considering any expenditure on account of CSR Activity for the year 2012-13, as discussed earlier:Table No.29: CSR Activity, as allowed by the Commission (Rs. cr.) 184. 185. Year FY 2010-11 FY 2011-12 FY 2012-13 Allowed by the Commission - - 0 Return on Equity: Petitioner’s Submission: The petitioner has not claimed any Return on Equity. Commission Analysis: Regulation 21 of RERC Tariff Regulations, 2009 provides for allowing Return on Equity Capital. However, as the petitioner has not claimed any Return on Equity, the Commission has not considered the same while approving the fixed cost of generation. (36) 186. Non Tariff Income: Petitioner’s Submission: The non-tariff income as projected by the petitioner is as under:Table No.30: Non Tariff Income as projected in petitions (Rs.cr.) Year As projected in the petitions 187. FY 2011-12 0.10 FY 2012-13 0.05 Commission Analysis: Since, the petitioner has proposed the Non- tariff income for FY 12-13 as Rs. 0.05 crores and the same has been allowed. Since the Unit has run only for 20 days in FY 10-11, the Non- tariff income, being insignificant has been ignored. Further for FY 11-12, the amount equal to the amount of FY 12-13 has been allowed. The details of Non- tariff income approved by the Commission are as under: Table No. 31: Non-tariff income allowed by the Commission (Rs.cr). Year Allowed by the Commission 188. FY 2010-11 0.05 FY 2010-11 FY 2011-12 FY 2012-13 0.00 0.05 0.05 Total Annual Fixed Charge component of tariff for FY 2010-11, 2011-12 & 2012-13 : Based on various components of fixed charges as discussed above, the annual fixed charges proposed by the petitioner and approved by the Commission for the various years is given in the following table: Table No.32: Total annual fixed charges allowed by the Commission (Rs. Cr.) Particulars O&M Expenses (Rs Cr.) Depreciation (Rs Cr.) Interest on Term Loans and Finance Charges (Rs Cr.) Interest on WCL (Rs Cr.) Recovery of ARR and Tariff Petition Fee (Rs Cr.) Insurance charges (Rs Cr.) CSR Activity Total Capacity (Fixed) Charge (Rs Cr.) Less Non-Tariff Income (Rs Cr.) Net Capacity (Fixed) Charge (Rs Cr.) Unit Sent Out (MU) Capacity Charge (Rs. per kWh sent out) 189. As Per Petition 2010-11 2011-12 2012-13 As per Commission 2010-11 2011-12 2012-13 1.26 2.47 24.49 45.13 25.99 45.13 1.19 2.22 22.88 40.47 24.47 40.47 4.41 78.62 73.50 3.87 69.04 64.45 0.23 5.48 6.33 0.21 4.38 4.53 0.06 0.06 0.06 0.06 0.06 0.06 0.04 0 0.81 0 0.56 0.06 0.04 0 0.79 0 0.51 0 8.47 153.81 151.63 7.59 137.62 134.49 0.05 0.10 0.10 0.00 0.05 0.05 8.42 153.71 151.53 7.59 137.57 134.42 37.17 681.54 703.91 37.17 681.54 703.91 2.27 2.26 2.15 2.04 2.02 1.91 As per Regulation no. 46 of RERC Tariff Regulations, 2009, the norms for target availability for recovery of full capacity charges for lignite based thermal power stations are prescribed as under and the same has been considered:For the First year of operation : 70% For second year of operation : 72.5% For third year of operation : 75.0% (37) For fourth year of operation : 77.5% For fifth year of operation : 80.0% Accordingly, the target availability for recovery of full capacity charges for FY 2010-11, 2011-12 & 2012-13 works out to 70%, 70.10% & 72.60% respectively. 190. 191. Determination of Variable Charges of Generation for MYT period: While determining the variable charges of generation for FY2010-11,201112 & 2012-13, the following factors have been taken into consideration by the Commission: The petitioner has claimed the variable charges considering the SHR as 2645.39 kCal/ kWh for FY 2010-11 to FY 2013-14. The Commission has considered the maximum Design Heat Rate applicable to plants having temperature and pressure ratings similar to this generating station using sub-bituminous coal as 2300 kcal/kwh and the moisture content has been considered as 32.41% as provided in the certificate of sampling and analysis done by M/s Mitra SK Pvt. Ltd. Detailed calculations are shown below: Table No.33: Calculation of SHR approved by the Commission Description Unit As approved by Commission Design Unit Heat Rate (Turbine Heat rate/Boiler Eff)*100 kcal/kwh 2300.00 Gross Heat Rate (1.065*DHR) kcal/kwh 2449.50 % 32.41% Moisture content Pro-rated multiplying factor SHR 1.04723 kcal/kwh 2565.19 192. The petitioner has considered the price of lignite as Rs. 765.93 per MT for FY 2010-11 & price escalation of 10% has been considered for subsequent years. The Commission has considered the price of lignite as Rs. 765.93 per MT for FY 2010-11 and Rs. 777.44 per MT for FY 2011-12 & FY 2012-13. 193. The cost of primary fuel for FY 2010-11 is considered on the basis of receipts of previous three months (December 2010- February 2011) and for FY 201112 are considered on the basis of receipts of previous three months (December 2011- February 2012). The petitioner has considered the price of lime as Rs. 607.84 per MT for FY 2011-12 & FY 2012-13 on the basis of receipts of three months during Dec, 11 to Feb, 12. The Commission has considered the price of lime as Rs. 577.13 per M.T. for FY 2010-11 and Rs. 607.84 per M.T. for FY 2011-12 & FY 2012-13 as claimed by the petitioner. 194. The petitioner has considered the Gross calorific value (GCV) of lignite for FY2010-11and 2011-12 as 3063.06 kcal/kg based on the receipts of three months during Dec., 2010, Jan., 2011 and Feb., 2011. However, in the petition no. 323/12 for FY 2012-13, the actual GCV for FY 2011-12 has been shown as 3040 kcal/kg. The Commission has considered the GCV as 3040 (38) kcal/kg for FY 2010-11 and 2011-12. The petitioner has considered the GCV of lignite as 2984.06 kcal/kg for FY2012-13, based on the receipts of three months during Dec. ,2011, Jan.,2012 and Feb., 2012. The Commission has considered the GCV as 2984.06 kcal/kg for FY 2012-13. 195. The Commission has approved the PLF and Auxiliary Consumption as per RERC Tariff Regulations, 2009. Accordingly, the variable charges determined for FY 2010-11 (applicable w.e.f. 12.03.2011 i.e. after date of commercial operation), 2011-12 and FY 2012-13 is as under: Table No.34 : Total annual variable charges allowed by the Commission (Rs.cr.) Particulars Capacity PLF Gross Generation Auxiliary Consumption Auxiliary Consumption Net Generation SHR Specific FO consumption Specific HSD consumption Sp. Lignite consumption Sp. Lime consumption GCV of FO GCV of HSD GCV of Lignite Heat contributed by FO Heat contributed by HSD Heat contributed by Lignite Price of lime Price of lignite Price of FO price of HSD lignite Cost Cost of FO Cost of HSD Lime Cost Total Variable Cost Variable Cost 196. Unit MW % MU % MU MU (kcal/kWh) ml/kWh ml/kWh Kg/kWh Kg/kWh Kcal/litre Kcal/litre Kcal/kg (Kcal/KWh) (Kcal/KWh) (Kcal/KWh) (Rs./MT) (Rs. / MT) (Rs. / kL.) (Rs. / kL.) (Rs. cr.) (Rs. cr.) (Rs. cr.) (Rs. cr.) (Rs. cr.) (Rs/KWh sent out) FY 2010-11 125 70 42.00 11.5% 4.83 37.17 2565.19 3.00 0.0 0.835 0.275 9010 9500 3040.00 27.03 0 2538.16 577.13 765.93 48212 30536 2.69 0.6 0.0 0.67 3.96 1.0651 FY 2011-12 125 70.10 770.10 11.5% 88.56 681.54 2565.19 3.00 0.0 0.835 0.267 9010 9500 3040.00 27.03 0 2538.16 607.84 777.44 61324 33589.6 50.0 14.2 0.0 12.48 76.63 1.1244 FY 2012-13 125 72.60 795.38 11.5% 91.47 703.91 2565.19 3.00 0.0 0.851 0.272 9010 9500 3040.00 27.03 0 2538.16 607.84 777.44 61324 33589.6 52.6 14.6 0.0 13.13 80.36 1.1416 The total Provisional tariff for FY10-11 to 12-13 is summarized as under: Table No. 35: Details of Provisional fixed & variable charges per kWh approved (Rs.) Parameter FY 2010-11 FY 2011-12 FY 2012-13 Fixed Charges (Rs./unit) 2.04 2.02 1.91 Variable Charges (Rs./unit) 1.07 1.12 1.14 Total Tariff (Rs./unit) 3.11 3.14 3.05 (39) 197. The interim tariff allowed by the Commission vide order dated 13.09.2011 for FY 2010-2011 & 2011-12 and order dated 31.05.2012 for FY 2012-13 shall stand modified as above. The net revenue surplus/shortfall sustained by GLPL as per this provisional tariff shall be adjusted in next three months from the date of this order. 198. As regard the further course of action and to expedite the process of tariff determination based on the completed cost the Commission directs GLPL to file a separate petition for determination of final capital cost and tariff for FY 2010-11 along with the information indicated in this order based on actual capital expenditure incurred up to the date of commercial operation duly certified by Statutory Auditors based on annual audited accounts in accordance with the provisions of Regulation 44(5) of RERC (Terms and Conditions of Tariff) Regulations, 2009 within three months of this order. 199. Copy of this order may be sent to the petitioners, respondents, CEA and Government of Rajasthan. (S. Dhawan) Member (D.C.Samant) Chairman (40) Annexure-1 ABBREVIATIONS AAD ABT Act APR APTEL ARR AS AVVNL BHEL BoD BoP BTG C&AG CEA C&I CHP COD cr. CSR CTPP CWIP DHR DPR DCCPP Discoms ETC FPA FY GCV GFA GoR GT GLPL GLTPS Advance against Depreciation Availability Based Tariff Electricity Act, 2003 Annual Performance Review Appellate Tribunal for Electricity Aggregate Revenue Requirement Accounting Standard Ajmer Vidyut Vitran Nigam Limited Bharat Heavy Electricals Ltd. Board of Directors Balance of Plant Boiler, Turbine & Generator Comptroller & Auditor General Central Electricity Authority Control & Instrumentation Coal Handling Plant Commercial Operation Date Crores Corporate Social Responsibility CTPP Thermal Power Station Capital Works in Progress Design Heat Rate Detail Project Report Dholpur Combined Circle Power Station Distribution Companies Erection Testing & Commissioning Fuel Price Adjustment Financial Year Gross Calorific Value Gross Fixed Assets Government of Rajasthan Generator Transformer Giral Lignite Power Ltd. Giral Lignite Thermal Power Station GIPCL HFO HSD IDC I.L. JVVNL Jd.VVNL Kcal KL KTPS KW kWh Gujarat Industrial Power Company Ltd. High Furnace Oil High Speed Diesel Interest during Construction Instrumentation Ltd. Jaipur Vidyut Vitran Nigam Limited Jodhpur Vidyut Vitran Nigam Limited Kilo Calorie Kilo Liter Kota Thermal Power Station Kilo Watt Kilo Watt Hour (41) LD LOI LDO MMH MT MU MW MYT MCR NLC O&M PLF PPA PV RSMML RERC RGTPS ROE RVUN RVPN RVVS SBI Scm SHR SLDC STPS TPL TPS VAT WCL WCT Liquidated Damages Letter of Intent Light Diesel Oil Mini Micro Hydel Stations Metric Ton Million Units Mega Watt Multi Year Tariff Maximum Current Rating Neyveli Lignite Ltd. Operation & Maintenance Plant Load Factor Power Purchase Agreement Price Variation Rajasthan State Mines & Minerals Ltd. Rajasthan Electricity Regulatory Commission Ramgarh Gas Thermal Power Station Return on Equity Rajasthan Vidyut Utpadan Nigam Limited Rajasthan Vidyut Prasaran Nigam Limited Rajasthan Vidyut Vikas Sansthan State Bank of India Standard cubic meter Station Heat Rate State Load Despatch Centre Suratgarh Thermal Power Station Tata Projects Ltd. Thermal Power Station Value Added Tax Working Capital Loan Works Contract Tax (42)
© Copyright 2025 Paperzz