STANDARD SPECIFICATIONS FOR CONSTRUCTION WORKS 2008 Module – 03 – Earthworks Introduction The Standard Specification is published in a series of 21 stand-alone modules, each addressing a single distinct area of the construction process. This stand-alone module 03 addresses the main aspects of earthworks in general. The purpose of the MoW STANDARD SPECIFICATIONS FOR CONSTRUCTION is to provide the design professional with a guide for accepted construction practices for Ministry of Works projects. As an aid to the designer, these Standard Specifications are provided for the inclusion in proposed development projects for ease, efficiency and cost savings. The Standard Specifications are not intended to limit the design responsibility of the design professional. However, they establish a minimum acceptable criterion and/or quality for use within Ministry of Works projects. The design professional may increase the requirements of an item contained in the Standard Specifications to meet job requirements, but when this is done, there should be no reference for that item on the drawings to the Ministry of Works Standard Specifications and a new specification should be included with the drawings or project contract documents. The design professional must review all Standard Specifications to be sure that they are adequate for the proposed project based on the job site conditions; the design professional is solely responsible for the designs submitted under his seal. In order to keep design standards current with changing regulations and improved construction materials and practices this section will be updated and maintained by the concerned authorities of the Ministry of Works. Prior to starting a new project, the design professional should contact the concerned Directorate of the Ministry of Works to verify that he/she has the latest document revisions. Page 1 Module List Module No 1 Module Title Guidance and General Specifications 2 Concrete 3 Earthworks 4 Glass and Glazing 5 Joinery and Carpentry 6 Ironmongery 7 Internal Finishes including Thermal Insulation 8 Painting and Decorating (Internal & External) 9 Metalwork 10 Roofing 11 Structural Steel (and Coatings) 12 Structural Timber 13 Masonry 14 Plumbing and Sanitary 15 Mechanical Installation in Buildings 16 Electrical Installation 17 Sewerage, Pipelines and Pipework 18 Sewerage M&E Works 19 Roadworks 20 Landscaping 21 Dredging, Reclamation and Shoreline Protection Page 2 Table of Contents CLAUSE DESCRIPTION PAGE Introduction 1 Module List 2 Table of Contents 3 Foreword 5 1. PART 1 MATERIAL 6 1.1 Classification………………………………………………………………………. 6 1.2 Definitions………………………………………………………………………….. 6 1.3 General Earthwork Material Requirements…………………………………….. 7 1.4 Water……………………………………………………………………………….. 8 1.5 Geotextiles Used to Separate Earthwork Materials…………………………… 8 1.6 Geogrids…………………………………………………………………………… 9 1.7 Source Approvals…………………………………………………………………. 9 1.8 Routine Sampling and Testing…………………………………………………... 9 1.9 Disposal of Unsuitable Materials………………………………………………… 9 1.10 Materials in Temporary Stockpiles……………………………………………… 9 1.11 Placing……………………………………………………………………………… 9 1.12 Protection…………………………………………………………………………. 10 1.13 Materials in Transit………………………………………………………………. 10 2. PART 2 METHODOLOGY & WORKMANSHIP 2.1 Suitable Plant and Working Methods………………………………………….. 10 2.2 Haulage of Material to Embankments or Other Areas of Fill………………... 10 2.3 Use of Acceptable Material……………………………………………………... 10 2.4 Trial Excavations to Classify and Quantify Excavated Materials…………… 10 2.5 Household Refuse……………………………………………………………….. 10 2.6 Excavation of Acceptable and Unacceptable Fill…………………………….. 11 2.7 Stockpiling of Materials…………………………………………………………. 11 2.8 Safety……………………………………………………………………………... 11 2.9 Topsoil……………………………………………………………………………. 11 2.10 Support to Excavations…………………………………………………………. 11 2.11 Dewatering of Excavations……………………………………………………... 11 2.12 Unacceptable Hazardous Materials…………………………………………… 12 2.13 Disposal of Surplus Material……………………………………………………. 12 2.14 Sequence of Works……………………………………………………………... 12 10 Page 3 2.15 Existing Roads and Services…………………………………………………… 12 2.16 Work in Restricted Areas……………………………………………………….. 12 2.17 Site Preparation………………………………………………………………….. 13 2.18 Excavations………………………………………………………………………. 14 2.19 Construction of Fills……………………………………………………………... 16 2.20 Compaction of Fills……………………………………………………………… 17 2.21 Earthworks Materials Tests…………………………………………………….. 18 3. PART 3 SUMMARY 3.1 Reference Documents………………………………………………………….. 29 3.2 Testing……………………………………………………………………………. 30 Abbreviations 29 31 Page 4 Foreword This specification provides the basis for earthworks. It covers the main requirements for selecting materials, the procedures for controlling the quality and requirements for placing, compaction and testing. This specification must be read in its entirety, as it is structured in order of work-flow, which means that items or activities appear in several places in the specification corresponding to the progression of the construction process. For larger, more complex or special projects, a project-specific Particular Specification for earthworks may also be provided. Absence of clauses for materials and methods does not necessarily signify that they can not be used. Proposals for use of innovative methods and materials are encouraged and are subject to review and approval by the Client. Where the word approved is used in this specification, this means that the Client or Engineer has been consulted and has confirmed that the item or procedure is acceptable in the specific context for which approval has been requested. Page 5 1. PART 1 MATERIAL 1.1 Classification Earthwork material shall fall into one or other of the following general classifications: • • • Acceptable material: material excavated from within the Site or imported on to the Site which meets the requirements of Table 1 for acceptability for use in the Permanent Works; Unacceptable material Class U1 as defined in Sub-clause 1.2.1 of this Clause: material excavated from within the Site which, unless processed so that it meets the requirements of Table 1, shall not be used in the Permanent Works; Unacceptable material Class U2 as defined in Sub-clause 1.2.2 of this Clause: material excavated from within the Site which shall not be used in the Permanent Works. 1.2 Definitions 1.2.1 Unacceptable Material Class U1 Unacceptable material Class U1 shall be: • • Material which does not comply with the permitted constituents and material properties of Table 1 and Table 2 for acceptable material; Material, or constituent materials, composed of the following: o Peat, materials from swamps, marshes and bogs o Logs, stumps and perishable material with an organic content (BS 1377: Part 3, Clause 3) greater than 2%, o Clay having a liquid limit exceeding 80% or plasticity index exceeding 55%, as determined in accordance with BS 1377: Part 2, Clauses 4.3 & 5 respectively. 1.2.2 Unacceptable Material Class U2 Class U2 shall be material having hazardous chemical or physical properties requiring special measures for its excavation, handling, storing, transportation, deposition and disposal. 1.2.3 Argillaceous Rock Argillaceous rock shall mean shales, mudstones, siltstones, slates and micaceous schists composed of particles of clay, silt and mica. 1.2.4 Formation Formation shall be the top surface of the Prepared Subgrade Layer. Where no Prepared Subgrade Layer is required formation shall be the top surface of earthworks at the underside of sub-base, unless otherwise stated on the Drawings. See Figure 1 for details. 1.2.5 Sub-formation Sub-formation shall be the top surface of earthworks at the underside of the Prepared Subgrade Layer. See Figure 1 for details. Page 6 Figure 1: Earthworks terminology (refer to Sub-clauses 1.2.4 & 1.2.5) Asphalt concrete wearing course Asphalt concrete base course Road base Sub-base (Type B) Formation Level Prepared subgrade layer (Fill Material) Sub-formation Level Natural Ground (Subgrade Layer) 1.2.6 Recycled Aggregate Recycled aggregate shall be aggregate resulting from the processing of material used in a construction process. The aggregate shall have material properties that meet the requirements of Table 1. The content of all foreign materials (including wood, plastic and metal) shall not exceed 1% by mass. 1.2.7 Rock and Hard Material in Excavation Rock is defined as natural material that is so hard that, in the opinion of the Engineer, it can not be removed by the ordinary methods of hand or machine excavation without undue difficulty, or without preliminary work to break or loosen the material by use of rippers, pneumatic tools or similar procedures. Hard Material is similarly defined as artificial material such as blockwork, brickwork or concrete that, in the opinion of the Engineer, is so hard that it cannot be removed by the ordinary methods of hand or machine excavation without undue difficulty or without preliminary work to break or loosen the material. In both cases, use of such preliminary procedures shall not in itself justify rock or hard material classification. 1.3 General Earthwork Material Requirements 1.3.1 Maximum Particle Size In addition to any grading requirements the maximum particle size of any fill material shall be no more than two-thirds of the compacted layer thickness. 1.3.2 Sulphate Content Exceeding 2% Materials with a water soluble sulphate content exceeding 2% of sulphate (expressed as SO3) when tested in accordance with BS 1377: Part 3, Clause 5.3 shall not be deposited within 500 mm, or other distances detailed on Drawings, of concrete, cement bound materials, or other cementitious materials forming part of the Permanent Works. 1.3.3 Sulphate Content Exceeding 0.25% Materials with water soluble sulphate content exceeding 0.25 % (Expressed as SO3) when tested in accordance with BS 1377: Part 3, Clause 5.3 shall not be deposited within 500 mm, Page 7 or other distances detailed on the Drawings, of metallic items forming part of the Permanent Works. 1.3.4 Chlorides The total chloride content of fill shall not exceed 2% when tested in accordance with BS 1377: Part 3, Clause 7.3. 1.3.5 Maximum Water Soluble Salt Content of General Fill Unless otherwise indicated in the Contract, the maximum water soluble salt content of general fill shall be 2%. 1.4 Water Water used to increase the moisture content of fills prior to compaction shall have a sulphate (SO3) content not exceeding 2,500 mg/l when tested in accordance with BS 1377: Part 3, clause , and the chloride ion content shall not exceed 2,500 mg/l when tested in accordance with BS 1377: Part 3, Clause 7.2. For material within 300 mm of the underside of concrete slabs, within 3 m of buildings or for backfill around concrete structures, sweet water shall be used for which the sulphate (SO3) content shall not exceed 500 mg/l, and the chloride ion content shall not exceed 350 mg/l. 1.5 Geotextiles Used to Separate Earthwork Materials Geotextiles required as part of the Permanent Works to separate earthworks materials shall be in the form of thin permeable membranes and shall conform to the requirements shown on the Drawings. The geotextile fabric shall be a woven or non-woven fabric consisting only of long chain polymeric filaments or yarns formed into a stable network such that the filaments or yarns retain their relative position to each other. The fabric shall be stored and protected in accordance with the manufacturer’s instructions, shall be inert to commonly encountered chemicals and the chemical properties of the in-situ soil and water, and shall conform to the minimum requirements given in Sub-clause 1.5.3. 1.5.1 Certification The Contractor shall provide the Engineer with the manufacturer’s certificates for the geotextiles intended for use in the Permanent Works, including the results of tests on the physical and chemical properties of the geotextiles to show that these will be sufficiently durable, when installed in the materials to be separated, as to maintain its integrity. 1.5.2 Protection Geotextiles shall be protected at all times against mechanical or chemical damage. Geotextiles susceptible to damage by light shall not be uncovered between manufacture and incorporation into the Permanent Works. Temporary exposure shall not exceed 5 hours. 1.5.3 Samples Samples shall be taken from the consignment of geotextile to be used in the Permanent Works. Samples and test pieces cut from them shall be tested at a laboratory approved by the Engineer to prove that the geotextile meets the following criteria. The geotextile shall:• Sustain a tensile load, of not less than 2.5 kN/m at 5% axial strain determined in a “widewidth” tensile test carried out in accordance with BS EN ISO 10319. The characteristic strength shall be taken as the value of the strength of the material below which not more than 5% of the test results may be expected to fall. This represents the strength at 1.64 standard deviations below the mean strength. Page 8 1.5.4 • Allow water to flow through it at right angles to its principal plane, in either direction, at a 2 rate of not less than 10 l/m /s under a constant head of water of 100 mm determined in accordance with BS EN ISO 11058, Clause 5. The flow rate determined in the test shall be corrected to that applicable to a temperature of 20°C using published data on the variation in viscosity of water with temperature. • Have a size distribution of pore openings such that O90 (the size of opening at which 90% of the openings are smaller), is between 100 microns and 300 microns, determined in accordance with BS EN ISO 12956. Testing Prior to determination of pore size and tensile strength, test pieces shall be conditioned and brought to equilibrium to a temperature of 20°C ± 2°C, and a relative humidity of 65 ± 5%. The dry weight of the geotextile tested shall be quoted in g/m2. 1.6 Geogrids Any geogrids to be used for earthworks stability and/or earthworks improvement shall be as shown on the Drawings. The Contractor shall provide the Engineer with the manufacturer’s certificates for the geogrids intended for use in the Permanent Works, including the results of tests on the physical and chemical properties of the geogrids to show that these will be sufficiently durable, when installed in the permanent works, as to maintain its integrity. 1.7 Source Approvals Prior to commencement of the works, the Contractor shall obtain the Engineer’s approval for all sources and suppliers of materials to be used in earthworks in compliance with the requirements of the Contract. Although the Engineer shall have access to all sources of materials, for the purpose of inspecting the materials at source, all samples to be taken for routine testing in accordance with the Contract shall be from loads delivered to the site, to be included in the Permanent Works. Earthworks materials testing to satisfy the classification requirements shall be carried out and assessed in accordance with the provisions in Table 1 and Table 2. 1.8 Routine Sampling and Testing Following initial approval of the sources and materials, the Contractor shall continue the routine sampling and testing of the various properties of materials delivered to site at the frequency specified in Table 3. 1.9 Disposal of Unsuitable Materials Unless otherwise indicated in the Contract, excavated material deemed to be unsuitable for subsequent re-use in the Permanent Works shall be removed from site by the Contractor to disposal sites authorized by the Engineer and the relevant Local Authorities. 1.10 Materials in Temporary Stockpiles All materials excavated from within the Site and required for subsequent re-use shall be stored in temporary stockpiles by the Contractor at locations subject to the approval of the Engineer. The Contractor shall provide for stockpiling different classes of fill to ensure that suitable materials are not contaminated by unsuitable materials. 1.11 Placing Wherever possible, the Contractor shall import fill materials and place these directly at the point of final deposition at the rate that can be managed, by the provided resources, to place, spread, compact and test the material at the specified frequency. Where it is necessary to place imported materials in temporary stockpiles, different classes of fill must be kept Page 9 separately at locations to be agreed on by the Engineer to minimize the risk of damage to structures and obstruction to footpaths or carriageways. 1.12 Protection All temporary earthwork material stockpiles that may be subject to wind erosion shall be protected to minimize wind erosion and uncontrolled access by members of the public. 1.13 Materials in Transit All loads of materials imported and exported must be covered by heavy tarpaulin or other suitable cover, securely fastened to prevent dust nuisance when the material is in transit. 2. PART 2 METHODOLOGY & WORKMANSHIP 2.1 Suitable Plant and Working Methods The Contractor shall employ only plant and working methods which are suited to the materials to be handled and traversed. The Contractor shall be responsible for maintaining the nature of the acceptable material so that when placed and compacted it remains acceptable in accordance with the Contract. Acceptability shall be determined in accordance with Table 1 and Table 2 and any special requirements stated on the Drawings. 2.2 Haulage of Material to Embankments or Other Areas of Fill Such haulage shall proceed only when sufficient spreading and compaction plant is operating at the place of deposition to ensure compliance with Clause 2.18. 2.3 Use of Acceptable Material No excavated acceptable material or unacceptable material required to be processed, other than that surplus to the requirements of the Contract, shall be removed from the Site unless otherwise agreed to by the Engineer. Where the Contractor is permitted to remove acceptable material, or unacceptable material required to be processed, from Site to suit the Contractor’s operational procedures, then the Contractor shall make good any consequent deficit arising there from. If any acceptable material is used by the Contractor for purposes other than for general fill, a sufficient volume of acceptable fill material corresponding to the volume of that removed by the Contractor shall be provided by the Contractor at his cost. 2.4 Trial Excavations to Classify and Quantify Excavated Materials Prior to commencement of the works on contracts that include significant cuttings and fill areas, the Contractor shall carry out preliminary trial pitting, sampling and testing of the deposits to be excavated, under the supervision of a qualified geotechnical engineer, in order to quantify and classify their suitability for re-use in fill areas of the Permanent Works. The Contractor shall provide to the Engineer a report, in a form to be agreed upon, summarizing the findings and proposals for providing for any shortfall of the various classes of fill by importing from approved sources of fill in order to balance the cut and fill volume of earthworks. 2.5 Household Refuse Where household refuse is found covering either areas of excavation or at the formation level of proposed fill areas on the Site, the Contractor shall provide for its removal and disposal in approved licensed tips. Page 10 2.6 Excavation of Acceptable and Unacceptable Fill Where an excavation reveals a combination of acceptable and unacceptable materials, the Contractor shall, unless otherwise directed by the Engineer, carry out the excavation in such a manner that the acceptable materials are excavated separately for use in the Permanent Works without contamination by the unacceptable materials. Unless otherwise described in the Contract, classes of fill material required to be deposited separately shall be excavated separately without contamination by other Classes of material. 2.7 Stockpiling of Materials The Contractor shall make his own arrangements for stockpiling acceptable material, and unacceptable material to be processed, and for the provision of areas for this purpose. 2.8 Safety The Contractor shall ensure that he does not adversely affect the stability of excavations or fills by his methods of stockpiling materials, use of plant or the location of temporary buildings or structures. 2.9 Topsoil Existing topsoil material shall, except where it is to be left in place at the locations indicated on Drawings, be stripped from all areas of cuttings and from all areas to be covered by embankment or any other areas of fill and stockpiled for subsequent re-use in the Permanent Works. 2.10 Support to Excavations Excavations for foundations and trenches shall be adequately supported at all times, except where otherwise agreed upon in writing by the Engineer. Where excavations are permitted to be battered they shall be benched as agreed to by the Engineer prior to backfilling and compaction. Any additional work and materials shall be provided by the Contractor. Sheeting and other excavation support systems shall be removed as filling proceeds except where Drawings or the Contractor’s method of work requires that they are to be left in position. Excavations requiring backfill shall remain open only for the minimum period necessary unless otherwise instructed by the Engineer. Trench Supports shall be so arranged to permit withdrawal during the placing of the pipe bedding and trench backfill so as to prevent the formation of voids in the ground. Excavations requiring backfilling in existing paved or other surfaces, including those paved areas to be reconstructed or repaired, shall be carried out and reinstated in compliance with the requirements of the Contract. All excavations shall be carried out so as to avoid disturbance to the surrounding ground and any adjacent structures and installations. Where required by the Engineer, the Contractor shall provide stability calculations for any temporary excavations but approval of such calculations shall not relieve the Contractor of his responsibility for adequately supporting and maintaining such supports for any excavation. 2.11 Dewatering of Excavations The Contractor shall keep earthworks free of water including: • Arranging for the rapid removal of water shed on to the earthworks or entering the earthworks from any source; Page 11 • Lowering and maintaining, by appropriate measures, the water level in excavations, sufficiently to enable the Permanent Works to be constructed. The Contractor shall: • • • • Form and maintain cuttings, embankments and other areas of fill with appropriate falls and gradient and sealed surfaces; Provide where necessary temporary watercourses, drains, pumping and the like; Discharge accumulated water and groundwater into the permanent outfalls of the drainage system where practicable and permissible; Provide adequate means for trapping silt on temporary systems discharging into permanent drainage systems. The Contractor shall obtain all necessary permits from the Statutory Authorities prior to using any existing permanent drainage systems for his use as described above. The Contractor shall also carry out and maintain any groundwater lowering or other treatment as required on the Drawings. 2.12 Unacceptable Hazardous Materials Where materials are designated in the Contract as Class U2 hazardous material or where such materials are encountered during the progress of the Works, the Contractor shall carry out chemical testing to characterize the materials encountered. The Contractor shall take any special measures for their safe handling as detailed in the Contract and shall make all necessary arrangements for their safe handling and disposal as Class U2 material after consultation with the environmental authority. 2.13 Disposal of Surplus Material The disposal of surplus excavated material shall be carried out by the Contractor to disposal sites approved by the Engineer and relevant Local Authorities. 2.14 Sequence of Works Where detailed on the Drawings or as directed by the Engineer, the Contractor shall plan earthwork operations to satisfy the indicated sequence of working to minimize interference or damage to ongoing or completed sections of work. Earthworks at approaches to bridges, culverts and drains may be required to be executed in a specific sequence to minimize differential settlement and damage to these structures. 2.15 Existing Roads and Services The Contractor shall take precautions and measures as agreed upon with the Engineer to protect from damage and to ensure the uninterrupted operation of all existing roads and services which are on the line of or adjacent to the works and shall maintain these until, in the opinion of the Engineer, the general progress of the work renders further protection unnecessary. In the event that any existing roads or services are damaged, the Contractor shall inform the concerned Authority and shall carry out the necessary repairs. 2.16 Work in Restricted Areas In planning his operations, the Contractor shall provide for working within restricted areas utilizing suitable plant and methods of work to the approval of the Engineer. Unless otherwise identified in the Contract, restricted areas shall be deemed to be areas where: • • • The horizontal distance between solid obstructions is less than 3 m; The vertical distance between the commencing surface and any overhead obstruction is less than 3 m; Authorities responsible for utilities in the ground impose limits on machine excavation and/or compaction; Page 12 • • Excavation is required within 1 m of the edge of existing buried structures or foundations; Archaeological sites are identified. 2.17 Site Preparation 2.17.1 Scope Site preparation includes clearing the project area of all above-ground obstructions and buildings to be demolished as scheduled on the Drawings; the removal of existing trees, vegetation and fences; the excavation and removal of any abandoned pipelines, shallow foundations and any other obstructions which are not designated or permitted to remain; the stripping of any topsoil; and the setting out and installation of fixed survey points for control and setting out surveys. 2.17.2 Pre-construction Surveys Prior to commencing any site clearance work, the Contractor shall carry out a detailed survey of any buildings, structures, fences trees and vegetation that are within the Site. The results of the survey shall be provided to the Engineer in both hard and soft formats. The results of this survey and the amount and extent of demolition and site clearance detailed on the Drawings shall then be agreed to by the Engineer. Where required on the Drawings or directed by the Engineer and prior to the commencement of bulk excavations, the Contractor shall excavate by hand trial pits and/or pilot trenches to confirm the location of services in and around the area of the proposed Works. Records shall be submitted by the Contractor detailing the information obtained from each trial excavation in a form to be agreed upon by the Engineer together with proposals to protect or divert any existing utilities that may be affected by the Contractor’s temporary works or by the Permanent Works. Where required on the Drawings or directed by the Engineer, the Contractor shall assist in the preparation of condition surveys on existing infrastructure and structures that are likely to be affected by the works. Where necessary, such surveys shall include photographs, drawings and sketches with levels and dimensions illustrating the existing condition of adjacent buildings and other structures and in particular recording any existing damage or structural defect. The Contractor shall liaise with the Engineer, and where appropriate with the owners and occupiers, in preparing such records. 2.17.3 Trees and Vegetation The Contractor shall obtain the written approval of the Engineer before initiating the removal of any trees, stumps and other vegetation. Trees and vegetation are to be removed down to a minimum depth of 500 mm below ground level and taken to an approved disposal site. The burning of trees, vegetation and other construction waste is not permitted on the Site. Unless directed otherwise in the Contract, selected trees may be required to be uprooted and laid aside for removal and transplantation by others. Trees and areas of vegetation shown on the Drawings and required to be protected shall be adequately protected and preserved to the satisfaction of the Engineer. 2.17.4 Existing Surface Materials Turf, topsoil, paving and other surface materials shall be stripped separately from the subsoil and stored separately for re-use or disposal as detailed on the Drawings or directed by the Engineer. 2.17.5 Demolition of Existing Structures Where the demolition of existing structures or buildings is detailed on the Drawings, the Contractor shall, in a safe manner, plan, demolish and remove off site to an approved tip or Page 13 recycling plant all buildings and foundations or other underground structures. Prior to any demolition work commencing, the Contractor shall ensure that all utilities are disconnected and/or diverted to suit the Work requirements. Unless otherwise indicated on the Drawings, foundations of building structures shall generally be removed to a depth of 1 m below ground level. Where shown on the Drawings or otherwise directed by the Engineer, underground structures, culverts and chambers shall be removed to the levels shown on the Drawings or as directed by the Engineer. 2.17.6 Demolition Works All demolition works shall be carried out in accordance with a method statement approved by the Engineer. If required, the Contractor shall take appropriate protective measures to protect structures and buildings adjacent to the works before commencement of site works. 2.17.7 Materials to be Salvaged A schedule of any material or equipment to be salvaged from structures or buildings to be demolished shall be provided by the Engineer. The Contractor shall inspect structures or buildings to be demolished and shall take all necessary measures to recover such items prior to demolition. The recovered materials shall be placed in a storage area to be agreed upon by the Engineer. 2.17.8 Excavations to be Backfilled All excavations formed by the removal of underground structures or foundations, or by the removal of trees or other unsuitable materials encountered during the site clearance, shall be backfilled with acceptable materials and shall follow the compaction requirements in Table 1. 2.18 Excavations 2.18.1 Use of Explosives The use of explosives for blasting to assist excavation is not permitted. 2.18.2 Forming of Cuttings and Cutting Slopes Cuttings shall be excavated to the lines and levels detailed on the Drawings. Cutting slopes or toes of cuttings shall only be undercut when required in the Contract for trench or other excavations and where they require backfilling, they shall remain open only for the minimum period necessary, so as to prevent risk to the Permanent Works. Final faces of cuttings which are not to receive topsoil shall wherever possible be left without scars or damage from construction plant. Faces of cuttings which are to receive topsoil shall be benched to retain topsoil and/or harrowed to a depth of 50 mm immediately prior to top soiling, diagonally at an angle between 5 degrees and 45 degrees to the line of the toe (see Figure 2). Page 14 Figure 2: Facings of cuttings to receive topsoil (refer to Sub-clause 2.19.2) Harrowing (50 mm minimum depth) or Benching 5° to 45° Plan 2.18.3 Toe of slope Section Excavations for Foundations The bottom of all foundation excavations shall be formed to the lines and levels shown on the Drawings. Unless otherwise indicated on the Drawings, the excavations for foundations may be halted at any stage providing at least 300 mm of material is left in place above the formation level as weather or surface water protection. The last 150 mm of soil above formation level shall be achieved by hand or by an excavator with a ditching bucket to minimize disturbance to the foundation soil. For the excavation for foundations in previously compacted fill the excavation shall be carried out as though in undisturbed ground. On completion of each excavation, the Contractor shall notify the Engineer of the depth of excavation and nature of material at formation level and seek the Engineer’s approval to place the concrete blinding. The formation shall be inspected by a qualified engineer to confirm that the ground conditions are as anticipated and that these are suitable for the support of the foundations. Pockets of soft soil or loose rock shall be removed and the resulting voids shall be filled by concrete or other material as required by the Engineer. Any additional excavation at or below the bottom of the foundations, including that resulting from the removal of material which the Contractor has allowed to deteriorate, shall be made good with concrete. After placing of any blinding concrete, no trimming of the sides of the excavation shall be carried out for at least 24 hours. The Contractor shall make good any lateral over-excavation with material of the same Class as used for filling above structural concrete foundations or, where the excavation is too narrow to allow the compaction of earthworks materials, to backfill with concrete. It is the Contractor’s responsibility to ensure the safety and maintenance of all excavated areas until the permanent works are completed. The Contractor shall erect all necessary warning signs, lights and barriers around all excavations. Page 15 2.19 Construction of Fills 2.19.1 General All fills, including embankments, shall be constructed: • • • To the locations, lines and levels detailed on the Drawings Of Classes of materials required or permitted in Table 1. By deposition, as soon as practicable after excavation, in layers to meet the compaction requirements of Clause 2.20 as required for each Class of material in Table 1, except that: o material requiring end-product compaction shall be deposited in layers not exceeding 200 mm un-compacted thickness o material placed into open water shall be deposited by end tipping without compaction o materials deposited in areas to receive ground improvement by dynamic compaction shall be deposited and compacted to the specific requirements of that process. The construction of any section of embankment shall not be commenced until the preparation for that section has been inspected and accepted by the Engineer. 2.19.2 Placement of Fill Where required on the Drawings, starter layers of the specified material Class shall be deposited as the first layer or layers of fill above existing ground level or any areas of ground improvement. Prior to the commencement of filling, the embankment formation shall be proof rolled and inspected for any unsuitable material naturally occurring on the site or encountered in the sub-grade. Any unsuitable material shall be excavated and, with the agreement of the Engineer, the resultant excavation shall be backfilled with acceptable material, placed and compacted in accordance with Table 1. Embankments and other areas of fill shall, unless otherwise required in the Contract, be constructed evenly over the full width and to their fullest possible extent and the Contractor shall control and direct construction plant and other vehicular traffic uniformly over them. Damage by constructional plant and other vehicular traffic shall be made good by the Contractor with material having the same characteristics and strength as the material had before it was damaged. Embankments and other areas of unsupported fills shall not be constructed with steeper side slopes or to greater widths than those indicated on the Drawings, except to permit adequate compaction at the edges before trimming back, or to obtain the final profile following any settlement of the fill and the underlying material. However any over-steepening or increase in width shall remain only for the minimum period necessary consistent with the safety of the Permanent Works. Staged construction of fills and any controlled rates of filling, shall be carried out, in accordance with any requirements detailed on the Drawings. Also where required, the Contractor shall surcharge embankments or other areas of fill, for the periods stated on the Drawings. Acceptable material shall be used to bring the resultant level up to formation or sub-formation as appropriate. The last 600 mm of depth of fill up to sub-formation level, or formation level as appropriate, shall, unless otherwise required in the Contract, be carried out for the full width of embankments or between the outer extremities of the verges in other areas of fill in a continuous operation. Page 16 Whenever fill is to be deposited against the face of natural slope or sloping earthworks face, including embankments, cuttings other fills and excavations, such faces shall be benched or otherwise shaped as detailed on the Drawings or directed by the Engineer immediately before placing the subsequent fill. All permanent faces of side slopes of embankments, shall, subsequent to any trimming operations, be re-worked and sealed by tracking with a suitable tracked vehicle. 2.19.3 Placement of Geotextiles and Geogrids Geotextiles and geogrids shall be laid and lapped as described in this Clause and on the Drawings. Where lapping is employed, adjacent sheets or strips of geotextile/geogrid shall be overlapped by at least 300 mm, or other dimension detailed on the Drawings or the manufacturer’s data sheets. The layer of material on which the geotextile/geogrid is to be placed shall not have protrusions or sharp projections which are likely to damage the geotextile/geogrid during installation or in service. The method of installation shall ensure that the geotextile/geogrid is in continuous contact with the surface on which it is to be placed and the geotextile/geogrid shall not be stretched or bridged over hollows or humps. Operation of construction plant directly on the installed geotextile/geogrid will not be permitted and covering of the geotextile / geogrid with fill material shall take place immediately after its laying. 2.19.4 Fill to Structures Where specified on the Drawings, fill material complying with the requirements of Table 1 shall be used as fill to structures. The Contractor shall compact, in compliance with Sub-clause 2.20.2, the Classes of materials specified on the Drawings to satisfy the compaction requirements in Table 1 but subject to the restrictions of this Sub-clause. The Contractor shall not backfill around structures until the structural elements have attained adequate strength and the Engineer has agreed to the backfilling work proceeding. Where fill to structures is required to the same level on more than one side of a structural element or buried structure it shall be maintained at heights not different by more than 250 mm after compaction on opposing sides of the structural element as filling proceeds. The Contractor shall restrict compaction plant used on fill to structures, within 2 m of a structure, to the following items: • • • Vibratory rollers having a mass per meter width of roll, not exceeding 1,300 kg with a total mass not exceeding 1,000 kg; Vibrating plate compactor having a mass not exceeding 1,000 kg; Vibro-tamper having a mass not exceeding 75 kg. Where fill is to be placed and compacted adjacent to the structure’s waterproofing system, care shall be taken to ensure that no damage is caused to the waterproofing or the protective layers. 2.20 Compaction of Fills 2.20.1 Timing of Compaction The Contractor shall carry out compaction immediately after deposition of the fill, on all Classes of fill in Table 1 which require compaction. Page 17 2.20.2 End-product Compaction Unless otherwise indicated, compaction shall be to an end-product as required for the Class of fill in Table 1, using plant appropriate to the Class of fill and to the site conditions. The Contractor shall, at least 7 days before commencement of end-product compaction, make available to the Engineer the following: • • The values of maximum dry density and the optimum moisture content obtained in accordance with BS 1377: Part 4 using the 4.5 kg rammer method or vibrating hammer method as appropriate for each of the fills he intends to use, which meet the requirements of the permitted Class or Classes and variations thereof. A graph of dry density plotted against moisture content from which each of the values in the above item of maximum dry density and optimum moisture content were determined. The information from the above items provided by the Contractor to the Engineer shall form the basis for compaction methodology. Fill compacted to end-product requirements shall have an in situ density, measured using appropriate field equipment, equal to or greater than the percentage given in Table 1 of the maximum dry density for the relevant Class of fill previously made available to the Engineer in accordance with the above. The in situ density referred to above shall be measured in accordance with BS 1377: Part 9, Clause 2.1, unless the Engineer permits the nuclear methods to be used. Where nuclear methods are permitted, BS 1377: Part 9, Clause 2.5 shall be followed. 2.20.3 Method Compaction Where method compaction is required to be adopted, this shall be undertaken using plant and methods appropriate to the compaction requirements in Table 1 for the Class of fill being compacted. The Contractor shall provide to the Engineer for his approval his detailed proposal for the method of compaction including, but not limited to, information on Class of fill to be compacted, layer thickness, compaction plant to be used and number of passes to be applied to each layer. Where required by the Engineer, the Contractor shall carry out in situ density tests on materials compacted to the proposed method requirements to prove the achieved compaction. If the results of such field tests show densities which indicate the state of compaction to be inadequate, then the Contractor shall carry out such further works as may be required by the Engineer to ensure compliance with the Contract. 2.20.4 Landscaped Areas Landscaped areas shall be constructed in the locations shown on the Drawings with Class 4 material complying with Table 1. Unless an end-product compaction is required, the degree of compaction of Class 4 material shall be that sufficient to remove large voids and to produce a coherent mass whilst preventing over-compaction. Following completion of filling of landscaped areas, Class 5 material complying with Table 1 shall be shaped as detailed on the Drawings. 2.21 Earthworks Materials Tests Unless otherwise described in the Contract, sampling and testing of earthworks materials shall be carried out in accordance with BS 1377: Parts 1 to 9 inclusive (also see Part 3 of this Specification). Page 18 Notes for Table 1: (1) “omc” is the ‘optimum moisture content. “MDD” is the ‘maximum dry density” (2) 10% Fines Value. The minimum value given shall be for tests carried out in accordance with BS 812: Part 111 except that samples shall be soaked in water at room temperature for 48 hours before testing without having been over-dried. (3) Where undrained shear strength is specified as the method of material classification and control, a Hand Vane may be used provided that it is calibrated against Unconsolidated Undrained Shear Strength tests to BS 1377: Part 7, Clause 8 on 110 mm nominal diameter samples. In this case the Contractor shall submit details of his proposed Hand Vane and calibration method to the Engineer for acceptance prior to the start of the earthworks. (4) Laboratory CBR Value. The minimum CBR value shall be that from fully-saturated tests on samples compacted to a density of 95% of the maximum dry density and when tested in accordance with BS 1377: Part 4: Clause 7 using 3 annular surcharge rings. (5) In situ CBR Value shall be the value achieved from in situ tests carried out in accordance with BS 1377: Part 7: Clause 4.3 using 3 annular surcharge rings. Page 19 TABLE 1: Requirements for Acceptability and Testing of Earthworks Part 1 – General Granular Fill Class General Material Description Typical Use Permitted Constituents (All subject to the requirements of Parts 1& 2 of this Specification) Compaction Requirements Material Properties PROPERTY TEST see cl 3.2 for test method 1A 1B 1C Well graded granular material General fill. Uniformly graded granular material General fill Coarse granular material General fill. Any material or combination of materials, excavated from site, recycled aggregate or dredged materials. Any material or combination of materials, excavated from site, recycled aggregate or dredged materials. Any material or combination of materials, excavated from site recycled aggregate or dredged materials. Grading Uniformity coefficient Moisture content Grading Uniformity coefficient Moisture content Grading Uniformity coefficient Moisture content LIMITS UPPER Table 2 BS 1377: Part 2 LOWER Table 2 ratio of D60 to D10 10 - BS 1377: Part 2 BS 1377: Part 2 omc - 2% Table 2 omc + 2% Table 2 ratio of D60 to D10 - 10 BS 1377: Part 2 BS 1377: Part 2 omc - 2% Table 2 omc + 2% Table 2 ratio of D60 to D10 10 - BS 1377: Part 2 omc - 2% omc + 2% End Product 95% of maximum dry density of BS 1377: Part 4 (4.5kg rammer). End product 95% of maximum dry density of BS 1377: Part 4 (4.5kg rammer) End Product 95% of maximum dry density of BS 1377: Part 4 (4.5kg rammer). Page 20 TABLE 1: Requirements for Acceptability and Testing of Earthworks (cont.) Part 2 – General Cohesive Fill Class General Material Description Typical Use Permitted Constituents (All subject to the requirements of Parts 1& 2 of this Specification) Compaction Requirements Material Properties PROPERTY TEST see cl 3.2 for test method 2A 2B 2C 2D Wet cohesive material Dry cohesive material Stony cohesive material Silty cohesive material General fill. General fill. General fill. General fill. Any material or combination of materials, excavated from Site. Any material or combination of materials excavated from the Site. Any material or combination of materials, excavated from Site. Any material or combination of materials, excavated from Site. Grading Plastic limit (PL) Moisture content Undrained Shear Strength Grading Plastic limit (PL) Moisture content Undrained shear strength Grading Plastic limit (PL) Moisture content Undrained shear strength Grading Plastic limit (PL) Moisture content BS 1377: Part 2 BS 1377: Part 2 BS 1377: Part 2 BS 1377: Part 7 (See notes) BS 1377: Part 2 BS 1377: Part 2 BS 1377: Part 2 BS 1377: Part 7 (See notes) BS 1377: Part 2 BS 1377: Part 2 BS 1377: Part 2 BS 1377: Part 7 (See notes) BS 1377: Part 2 BS 1377: Part 2 BS 1377: Part 2 LOWER Table 2 - LIMITS UPPER Table 2 6% 0.9 x PL 60 kPa Table 2 - - End Product 95% of maximum dry density of BS 1377: Part 4 (4.5kg rammer). Table 2 6% 0.9 PL - End product 95% of maximum density of BS1377: Part 4 (4.5kg rammer). 60 kPa Table 2 6% 0.9 PL - End Product 95% of maximum dry density of BS 1377: Part 4 (4.5kg rammer). Table 2 omc - 3% Table 2 6% omc + 3% End Product 95% of maximum dry density of BS 1377: Part 4 (4.5kg rammer). 60 kPa Table 2 - Page 21 TABLE 1: Requirements for Acceptability and Testing of Earthworks (cont.) Part 3 – Not Used Class General Material Description Typical Use Permitted Constituents (All subject to the requirements of Parts 1& 2 of this Specification) Compaction Requirements Material Properties PROPERTY TEST see cl 3.2 for test method 3 LOWER LIMITS UPPER Not used TABLE 1: Requirements for Acceptability and Testing of Earthworks (cont.) Part 4 – Land-raise Fill Class General Material Description Typical Use Permitted Constituents (All subject to the requirements of Parts 1& 2 of this Specification) Compaction Requirements Material Properties PROPERTY TEST see cl 3.3 for test method 4 Various Land-raise fill Any acceptable material or combination of materials imported to site or from site. Grading Moisture content BS 1377: Part 2 BS 1377: Part 2 LOWER - LIMITS UPPER - Clause 2.21.4 TABLE 1: Requirements for Acceptability and Testing of Earthworks (cont.) Part 5 – Topsoil Class General Material Description Typical Use Permitted Constituents (All subject to the requirements of Parts 1& 2 of this Specification) Compaction Requirements Material Properties PROPERTY TEST see cl 3.2 for test method 5A Topsoil, or turf, existing on Site Top soiling Any material designated as topsoil in the Contract. See Landscape Specification 5B Imported Topsoil Top soiling Material complying with BS 3882. See Landscape Specification See Landscape Specification (Module 20) See Landscape Specification (Module 20) LOWER LIMITS UPPER Compaction not required Page 22 TABLE 1: Requirements for Acceptability and Testing of Earthworks (cont.) Part 6 – Selected Granular Fill Class General Material Description Typical Use Permitted Constituents (All subject to the requirements of Parts 1& 2 of this Specification) Compaction Requirements Material Properties PROPERTY TEST see cl 3.2 for test method 6A 6B 6C 6D Selected well graded granular material Selected coarse granular material Selected uniformly graded granular material Screened Crusher material Fill below water Fill starter layer Fill starter layer. Blinding layer Natural sand, natural gravel, crushed rock other than argillaceous rock, crushed concrete. Grading Uniformity coefficient Plasticity Index 10 % Fines Value Natural sand, natural gravel, crushed rock other than argillaceous rock, crushed concrete. Grading Uniformity coefficient Plasticity Index 10% Fines Value Natural sand, natural gravel, crushed rock other than argillaceous rock, crushed concrete. Grading Uniformity coefficient Plasticity Index Moisture content 10% Fines Value Crushed gravel, crushed rock or crushed concrete fines. Grading Plasticity Index BS 1377: Part 2 ratio of D60 to D10 BS 1377: Part 2 BS 812: Part 111 (See notes) BS 1377: Part 2 ratio of D60 to D10 BS 1377: Part 2 BS 812: Part 111 (See notes) BS 1377: Part 2 ratio of D60 to D10 BS 1377: Part 2 BS 1377: Part 2 BS 812: Part 111 (See notes) BS 1377: Part 2 BS 1377: Part 2 LOWER Table 2 10 LIMITS UPPER Table 2 - Non Plastic 50 kN Table 2 10 Table 2 - Non Plastic 50 kN Table 2 - No compaction required when placed below water. Method compaction approved by the Engineer when above water. Method compaction approved by the Engineer. Table 2 10 Non Plastic omc - 2% omc + 2% 50 kN - End Product 95% of maximum dry density of BS 1377: Part 4 (4.5kg rammer). Table 2 Table 2 Non Plastic Method compaction approved by the Engineer. Page 23 TABLE 1: Requirements for Acceptability and Testing of Earthworks (cont.) Part 6 – Selected Granular Fill (cont.) Class General Material Description Typical Use Permitted Constituents (All subject to the requirements of Parts 1& 2 of this Specification) Compaction Requirements Material Properties PROPERTY TEST see cl 3.2 for test method 6N 6P Selected well graded granular material Selected granular material Fill to Structures Fill to Structures Natural gravel, natural sand, crushed gravel, crushed rock other than argillaceous rock, crushed concrete, or any combination thereof. Natural gravel, natural sand, crushed gravel, crushed rock other than argillaceous rock, crushed concrete, any combination thereof. LIMITS UPPER Table 2 BS 1377: Part 2 LOWER Table 2 ratio of D60 to D10 10 - 10% Fines Value BS 812: Part 111 (See notes) 100 kN - Effective angle of internal friction BS 1377: Part 7 Permeability BS 1377 Grading Uniformity coefficient Grading Uniformity coefficient 10% Fines Value BS 1377: Part 2 40 degrees 5 x 10-5 m/sec Table 2 Table 2 ratio of D60 to D10 5 - BS 812: Part 111 (See notes) 100 kN - Effective angle of internal friction BS 1377: Part 7 Permeability BS 1377: Part 5 35 degrees 5 x 10-5 m/sec - - End Product 95% of maximum dry density of BS 1377: Part 4 (vibrating hammer method). Compacted fill layers not to exceed 250mm thickness End Product 95% of maximum dry density of BS 1377: Part 4 (vibrating hammer method). Compacted fill layers not to exceed 250mm thickness - Page 24 Table 2: Grading Requirements for Acceptable Earthworks Materials Class 1A 1B 1C 2A & 2B 2C 2D 6A 6B 6C 6D 6N & 6P Size (mm) 500 300 100 100 100 125 100 100 100 100 100 90 75 37.5 90-100 Percentage by Mass Passing the Size Sieve Size (mm) BS Series 28 20 14 10 63 5 3.35 20-95 80-100 15-80 0-100 0-10 100 0-100 100 2 100 0 -85 0-100 95-100 0-35 0-10 1.18 Size (microns) BS Series 300 150 63 2 < 15 < 15 0-25 < 15 15-100 15-80 80-100 0-20 0-45 <5 600 0-2 < 10 < 15 Page 25 Table 3: Frequency of Testing to be Carried out by the Contractor Item Work, Goods or Materials Test Frequency of Testing Test Certificate Comments Material excavated from Tests for contaminants within the Site other than from made ground Required Initially one of each test per 1,000,m³ per cut area. If initial five tests give consistent results, frequency may be reduced with acceptance of the Engineer to one of each test per 5 000 m³ per cut area. Contaminants for which testing is required to be identified in Contract or as directed by the Engineer. Material excavated from Tests for contaminants made ground from within the Site identified on the drawings as unacceptable material Class U1 Initially one of each test per 100 Required m³ of made ground per cut area. If initial five tests give consistent results, frequency may be reduced with acceptance of the Engineer to one of each test per 1,000 m3 of made ground per cut area. Contaminants for which testing is required to be identified in Contract or as directed by the Engineer. Material excavated from Tests for contaminants areas identified on the drawings as unacceptable material Class U2 Contractor to propose frequency Required of testing for acceptance by the Engineer. Contaminants for which testing is required to be identified in Contract or as directed by the Engineer. Acceptable material Class General Description Grading Uniformity Coefficient Moisture Content Total Sulphate content 1A 1B 1C Total Chloride content General granular fill Optimum Moisture Content / MDD (4.5 kg rammer) One per 1,000 m³ per source, minimum one per day per source One per 250 m³ per source, minimum two per day per source One per source then weekly Required Cross refer to Table 1 Weekly per source Particle density In situ density 3 No per 100 m2 per layer 2 3 No per 500 m per layer In excavations or trenches In large fill areas such as in embankments Page 26 Table 3: Frequency of Testing to be Carried Out by the Contractor (Contd.) Clause Work, Goods or Materials Test Grading Frequency of Testing Test Certificate One per 1,000 m³ per source, minimum one per week per source Liquid Limit, Plastic Limit and Plasticity Index Moisture Content 2A, 2B General cohesive fill 2C 2D Optimum Moisture Content / MDD (4.5kg rammer) Cross refer to Table 1 One per 250 m³ per source, minimum 3 per day per source Required Undrained shear strength Once per source then every two weeks Particle density Weekly per source In situ density 3 No per 100 m2 per layer In excavations or trenches 2 3 No per 500 m per layer 4 Landscape Fill Grading Daily Moisture Content Three per day per cut area Grading One per 250 m³ or minimum one per day 6A Selected granular fill Uniformity Coefficient Plasticity Index One per week per source 10% Fines Values One per 500 m3 or minimum one per week per source Grading One per 250 m³ or minimum one per day Uniformity Coefficient Plasticity Index 10% Fines Values Total sulphate content 6B Total chloride content 6C Selected granular fill Moisture Content 6D Optimum Moisture Content / MDD (vibrating hammer) Comments In embankments Required Cross refer to Table 1 Source to be accepted by the Engineer in advance Required One per 500 m3 or minimum one per week per source One per source and then weekly One per 250 m³ or minimum one per day Required Cross refer to Table 1 Once per 1 000 m3 or minimum one per week per source Particle density In situ density 3 No per 100 m2 per layer Backfill to structures, excavations or trenches 3 No per 500 m2 per layer Fill in embankments Page 27 Table 3: Frequency of Testing to be Carried Out by the Contractor (Contd.) Clause Work, Goods or Materials Test Frequency of Testing Test Certificate Grading Comments Source to be accepted by the Engineer in advance One per 250m³ or minimum one per day Uniformity Coefficient Moisture Content Optimum Moisture Content /MDD (vibrating hammer) 6N & Selected granular 6P material – backfill to Particle density structures One per 250 m³ or minimum one per day Once per week per source Required Cross refer to Table 1 Plasticity Index Effective angle of internal friction Permeability Once per source then every two months 10% Fines Value Once per week per source In situ density Three per layer per structure element Geotextiles Tensile load Permeability Pore size Water added to fill Sulphate & Chloride Content 1 per 400 m2 Required Once per source then weekly Required Notes for Table 3: (1) Tests comparable to those specified in this Table will be necessary for any equivalent work, goods or materials proposed by the Contractor. (2) Unless specifically stated to the contrary, all samples used in the testing shall be taken from materials after delivery to the site for incorporation into the works. (3) The indicated time related frequency (that is, day, week or month) relates to periods or part periods of time that the material is used in the works. Testing is not required for the periods of time that the material is not in use. (4) The specified frequency of testing is the minimum required. The Contractor may seek the Engineer’s review of this specified frequency only where his method of work, test results and/or the consistency of quality of the sources of material being used justifies a relaxation to these specified requirements. Page 28 3. PART 3 SUMMARY 3.1 Reference Documents 3.1.1 Earthwork Materials Reference Title BS 812: Part 111 Testing Aggregates, Methods for determination of ten per cent fines value (TFV) Methods of test for soils for civil engineering purposes. General requirements and sample preparation Methods of test for soils for civil engineering purposes. Classification tests Methods of test for soils for civil engineering purposes. Chemical and electro-chemical tests Methods of test for soils for civil engineering purposes. Compactionrelated tests Methods of test for soils for civil engineering purposes. Compressibility, permeability and durability tests Methods of test for soils for civil engineering purposes. Consolidation and permeability tests in hydraulic cells and with pore pressure measurement Methods of test for soils for civil engineering purposes. Shear strength tests (total stress) Methods of test for soils for civil engineering purposes. Shear strength tests (effective stress) Methods for test for soils for civil engineering purposes. In-situ tests BS 1377: Part 1 BS 1377: Part 2 BS 1377: Part 3 BS 1377: Part 4 BS 1377: Part 5 BS 1377: Part 6 BS 1377: Part 7 BS 1377: Part 8 BS 1377: Part 9 3.1.2 Geotextiles Reference Title BS EN ISO 10319 BS EN ISO 11058 Geotextiles. Wide-width tensile test Geotextiles and geotextile-related products. Determination of water permeability characteristics normal to the plane, without load Geotextiles and geotextile-related products. Determination of the characteristic opening size BS EN ISO 12956 3.1.3 Geogrids Reference Title BS EN 13251 Geotextiles and geotextile-related products. Characteristics required for use in earthworks, foundations and retaining structures Geosynthetics. Determination of friction characteristics. Direct shear test Geotextiles and geotextile-related products. Determination of tensile creep and creep rupture behaviour BS EN ISO 12957: Part 1 BS EN ISO 13431 3.1.4 Compaction of Fills Reference Title BS 1377: Part 4 Methods of test for soils for civil engineering purposes. Compactionrelated tests Methods for test for soils for civil engineering purposes. In-situ tests BS 1377: Part 9 Page 29 3.2 Testing The test methods outlined in Table 1 are fully defined below: 3.2.1 Earthwork Materials Liquid Limit (LL) Plastic Limit (PL) Plasticity Index (PI) Chloride Content of soil Sulphate Content of soil Chloride Content of water Sulphate Content of water Organic matter content Grading Particle density Moisture content Optimum moisture content / MDD Uniformity coefficient (calculated from) Undrained shear strength 10% Fines Value Laboratory California Bearing Ratio In situ California Bearing Ratio In situ density In situ density (nuclear methods) Permeability Effective angle of internal friction 3.2.2 BS 1377: Part 2, Clause 4.3 BS 1377: Part 2, Clause 5.3 BS 1377: Part 2, Clause 5 BS 1377: Part 3, Clause 7.3 BS 1377: Part 3, Clause 5.3 BS 1377: Part 3, Clause 7.2 BS 1377: Part 3, Clause 5.4 BS 1377: Part 2, Clause 3 BS 1377: Part 2, Clause 9.2 BS 1377: Part 2, Clause 8.2 BS 1377: Part 2, Clause 3.2 BS 1377: Part 4, Clause 3.5 BS 1377: Part 2, Clause 9.2 BS 1377: Part 7, Clause 8 BS 812: Part 111 BS 1377: Part 4, Clause 7 BS 1377: Part 9, Clause 4.3 BS 1377: Part 9, Clause 2.1 BS 1377: Part 9, Clause 2.5 BS 1377: Part 5, Clause 5 BS 1377: Part 7, Clause 4 Compaction Maximum dry density Optimum moisture content In situ density BS 1377: Part 4, Clause 4 BS 1377: Part 4, Clause 3.5 BS 1377: Part 9, Clause 2.1 Page 30 Abbreviations ACB ACOP ACRIB Air Circuit Breakers Approved Code of Practice Air Conditioning and Refrigeration Industry Board Acoustic Doppler Current Meters ADCM AFMA Australian Fisheries Management Authority American Gear Manufacturers’ Association AGMA AISI American Iron and Steel Institute AS Acceptance Strength Association of Short-circuit Testing ASTA Authorities ASTM American Society for Testing Materials ATS Automatic Transfer Switch AWS American Welding Society British Approval Service for Electric Cables BASEC BOCA Building Officials and Code Administrators BRE Building Research Establishment Ltd. British Standards BS Building Service Research and Information BSRIA Association CBR California Bearing Ratio CCTV Close Circuit Television CECOMAF Comité Européen des Constructeurs de Matériel Frigorifique CENELEC Comité Européen de Normalisation Electrotechnique CFC Chlorofluorocarbons CIBSE Chartered Institution of Building Services Engineers CHW Chilled Water CI Cast Iron CLW Cooling Water CM Current Margin / Communication cable CMP Communication cable (Plenum) CP Code of Practice CPC Circuit Protection Conductor CPT Cone Penetration Testing Categorised Required Strength CRS Cathode Ray Tube CRT CRZ Capillary Rise Zone CT Current Transformer c(UL) Underwriters Laboratories Incorporated (Canada) DEO Defence Estate Organisation DFT Dry Film Thickness DI Ductile Iron DIN Deutsches Institut für Normung DPC Damp Proof Course DPDT Differential Pressure, Differential Temperature DS Durability Strength DVR Digital Video Recorder DW Ductwork Specification EA Exhaust Air ECMA European Computer Manufacturers Association EA Exhaust Air ECMA European Computer Manufacturers Association ECR Extra Chemical Resistant EIA Environmental Impact Assessment/ Electronic Industries Alliance EMC EPDM FA FBA FRP FSC GANA GGBS GMS GRC GRP HCFC HDPE HEPA HFC HPL HPPE HRC HSE HSFG HV HVCA ICBO IGCC IGE/UP IP ISAT ISO ITP KD kVA LCD LED LPG LS0H LSF LV MCB MCC MCCB MDF MDD MDPE MEP MICC MIO MMI MOD MS MSDS MSRPC N NDFT NEMA NFPA NRC NS Electromagnetic Compatibility Ethylene-propylene-diene-monomer copolymer Fresh Air Factory Built Assembly Fibre Reinforced Polymer Forest Stewardship Council Glass Association of North America Ground Granulated Blast-furnace Slag Galvanized Mild Steel Glass Reinforced Cement/Glass Reinforced Concrete Glass Reinforced Plastics Hydrofluorocarbons High Density Polyethylene High Efficiency Particulate Air HydroFluoroCarbon High Pressure Laminate Higher Performance Polyethylene High Rupturing Capacity Health and Safety Executive High Strength Friction Grip High Voltage Heating and Ventilating Contractors’ Association International Conference of Building Officials Insulating Glass Certification Council Institution of Gas Engineers – Utilization Procedures Ingress Protection Initial Surface Absorption Test International Standard Organization Inspection Testing Plan Kiln Dried Kilovolt Ampere Liquid Crystal Display Light Emitting Diode Liquid Petroleum Gas Low Smoke Zero Halogen Low Smoke and Fume Low Voltage Miniature Circuit Breaker Motor Control Centre Moulded Case Circuit Breakers Medium Density Fireboard Maximum Dry Density Medium Density Polyethylene Mechanical Electrical Plumbing Mineral Insulated Copper Covered Cable Micaceous Iron Oxide Man Machine Interface Ministry of Defence Micro-silica Material Safety Data Sheet Moderate Sulphate Resistance Portland Cement Nitrogen Nominal Dry Film Thickness National Electrical Manufacturers’ Association National Fire Protection Association Noise Reduction Coefficient Norwegian Standard Page 31 O/D ODP OFS OFTEC O&M OPC PD PE PFA PFC PM PTFE PVC PVC-u PWTAG QA/QC RA RCCD RCD R&D REFCOM RPM RPZ RTD RTR SA SBCCI SDR SIS SP SPDT SRPC SS SSPC TIA TRA UL ULPA UP UPS UTP UV VC VR WBP W/C WIS WP WRAS XLPE Outside Diameter Ozone Depletion Potential Oil Fired (Appliance/Equipment) Standard Oil Firing Technical Association Operation and Maintenance Ordinary Portland Cement Published Documents Polyethylene Pulverised Fuel Ash Power Factor Correction Project Manager Polytetrafluoroethylene Polyvinylchloride Unplasticised Polyvinylchloride Pool Water Treatment Advisory Group Quality Assurance/Quality Control Return/Recycled Air Residual Current Circuit Breaker Residual Current Device Research and Development Register of Companies Competent to handle refrigerants Reinforced Plastic Mortar Reduced Pressure Zone Resistant Temperature Detector Reinforced Thermosetting Resin Supply Air Southern Building Code Congress International (Incorporated) Standard Dimension Ratio Swedish Institute of Standards Super-plasticizing Single Pole Double Throw Sulphate Resistance Portland Cement Structural Strength Steel Structures Painting Council Telecommunication Industry Association Trussed Rafter Association Underwriters Laboratories Incorporated Ultra Low Penetration Air Unsaturated Polyester Resin Uninterruptible Power Supply Unshielded Twisted Pair Ultra Violet Vitrified Clay Video Recorder Weather and Boil Proof Water Cement Ratio Water Industry Specification Water Proofing Water Regulations Advisory Scheme Cross Linked Polyethylene Page 32
© Copyright 2026 Paperzz