Port Augusta Solar Thermal Generation Feasibility Study Milestone 4 Report Final Balance of Study July 2015 A project jointly funded by: - Alinta Energy - Australian Renewable Energy Agency, Emerging Renewables Program - Government of South Australia, Enterprise Zone Fund For more information: www.alintaenergy.com.au/Port-Augusta-Solar-Thermal-Generation-Feasibility-Study Table of Contents 1 2 Executive Summary ....................................................................................... 5 Introduction .................................................................................................... 6 2.1 3 4 Review of Assumptions ............................................................................................ 7 Analysis of Measure Progress ...................................................................... 9 3.1 Data Collection ......................................................................................................... 9 3.2 Balance of Study....................................................................................................... 9 3.2.1 Scope of Works ................................................................................................................ 9 3.2.2 Methodology ................................................................................................................... 10 3.2.3 Uncertainties discovered ................................................................................................ 13 Financial Modelling and Assessment ......................................................... 15 4.1 Overview of financial modelling .............................................................................. 15 4.2 Methodology ........................................................................................................... 15 4.3 Input Data ............................................................................................................... 15 4.3.1 Capital Costs .................................................................................................................. 16 4.3.2 Operational Costs........................................................................................................... 16 4.3.3 Electricity Generation ..................................................................................................... 16 4.3.4 Pricing ............................................................................................................................ 17 4.3.5 Other Assumptions ......................................................................................................... 19 4.4 Financial Modelling Outputs ................................................................................... 19 4.5 Cost Uncertainty Analysis ....................................................................................... 21 4.6 Parameter Sensitivity Analysis ............................................................................... 21 4.6.1 LCOE vs. Simple Payback Time .................................................................................... 21 4.6.2 Plant Configuration ......................................................................................................... 21 4.6.3 Market Forecast ............................................................................................................. 23 4.6.4 Time of Day Pricing vs DNI datasets .............................................................................. 24 4.6.5 Dispatch Methodology .................................................................................................... 25 4.7 Project Financial Viability ........................................................................................ 25 4.7.1 Financial parameter benchmarks required for project viability........................................ 26 4.7.2 LCOE Assessment ......................................................................................................... 30 4.8 Unexplored Concepts ............................................................................................. 31 4.8.1 Storage from grid power ................................................................................................. 31 4.8.2 Use of waste heat........................................................................................................... 31 4.8.3 Hybridised solar.............................................................................................................. 31 105-RPT-006-Milestone_4_Summary_Report Page 2 of 33 4.8.4 5 6 7 Alternative location ......................................................................................................... 32 Near Commercial Technologies .................................................................. 32 5.1 Technical Maturity................................................................................................... 32 5.2 Financial Potential .................................................................................................. 32 Further Information ...................................................................................... 33 Conclusion ................................................................................................... 33 Table of Figures Figure 1: AUD:USD exchange rates July 2014 – May 2015 ...................................................................... 11 Figure 2: Financial modelling methodology ................................................................................................ 15 Figure 3: Construction cost curve assumption ........................................................................................... 16 Figure 4: Forecast lifetime electricity production by quarter ....................................................................... 17 Figure 5: Forecast peak and off-peak electricity prices .............................................................................. 18 Figure 6: Forecast LGC price path ............................................................................................................. 18 Figure 7: Project lifetime cashflows ............................................................................................................ 20 Figure 8: LCOE as a function of IRR and CAPEX – Base Case/Reference Curve ................................... 27 Figure 9: LCOE as a function of IRR and CAPEX – Variation 2 ................................................................ 28 Table of Tables Table 4: Cost localisation factors ................................................................................................................ 10 Table 5: CAPEX cost estimate comparison: Options Study vs Balance of Study ...................................... 11 Table 6: Results of further industry consultation ........................................................................................ 12 Table 7: Solar resource data inputs for generation modelling .................................................................... 13 Table 8: Base case financial modelling key outputs ................................................................................... 20 Table 9: +/-30% financial modelling key outputs ........................................................................................ 21 Table 10: Alternate system configurations ................................................................................................. 22 Table 11: Alternate Systems – modelling outputs ...................................................................................... 22 Table 12: Base case vs. forward price curves ............................................................................................ 24 Table 13: IRR as a function of system design & forward price curve ......................................................... 24 Table 14: NPV @ 12% as a function of system design & forward price curve........................................... 24 Table 15: Minimum financial benchmarks for CSP investment at Port Augusta ........................................ 26 Table 16: Sensitivity of IRR & NPV to multiple variables ........................................................................... 29 Table 17: Contributions to LCOE by category and CAPEX vs OPEX ........................................................ 30 Table 18: LCOE contributions by category compared to SunShot targets ................................................. 30 Table 19: VAST Solar scaled base case vs. forward price curves ............................................................. 33 105-RPT-006-Milestone_4_Summary_Report Page 3 of 33 Acronyms Alinta Alinta Energy group of companies ARENA Australian Renewable Energy Agency CAPEX Capital Expenditure CPI Consumer Price Index CSP Concentrating Solar Power DNI Direct Normal Insolation GHI Global Horizontal Insolation IRR Internal Rate of Return LCOE Levelised Cost of Energy LRET Large scale Renewable Energy Target LGC Large scale Generation Certificates MW Megawatt MWe Megawatt electric NEM National Electricity Market NPS Northern Power Station NPV Net Present Value OPEX Operational expenditure PPA Power Purchase Agreement SAM System Advisor Model TMY Typical Mean Year WEM Western Electricity Market 105-RPT-006-Milestone_4_Summary_Report Page 4 of 33 1 Executive Summary Alinta has completed the pre-feasibility investigations detailed in the Port Augusta Solar Thermal Generation Feasibility Study. This is the fourth and final milestone report contributing to Stage One of the study. This Milestone Four Report (Final Balance of Study Report) presents the findings of Alinta’s extensive financial modelling and scenario analysis of the potential for a Concentrating Solar Thermal plant in Port Augusta, South Australia. It builds upon the Draft Balance of Study Report previously released. Over the last several months Alinta has given further consideration to a range of additional possibilities including five alternative CSP plant configurations, three additional forward price curves and adjustments to capital cost, operating cost, revenue stream and capital grant funding. The most significant finding presented in this report is that across the range of sensitivities, system types and forward curve assumptions considered, there is no combination which returns a positive Net Present Value in the financial model. Further industry consultation has confirmed the suitability of the cost estimate assumptions made in the Balance of Study Report. Alinta’s internal analysis suggests that in order for a project of this type to attract private sector investment at this time, the costs would need to be reduced by approximately 60%. If CAPEX and OPEX were reduced by 60%, then the LCOE of this type of plant would drop from $201/MWh to $80/MWh. This would be in line with the 2020 target for a drop in the cost of solar thermal technology that is being pursued by the SunShot Initiative funded by the US Department of Energy. While the investigations and options reviewed as part of this study have been robust, thorough and conclusive, there are several unexplored concepts which may have the potential to either reduce costs or increase revenue. None of the concepts identified would have an impact large enough to be material to the viability a CSP plant in Port Augusta at this time, however as the landscape of the electricity industry changes over the next several years, these concepts may begin to play a role in project viability. There is at least one local technology manufacturer which could be offering commercially competitive prices for solar thermal generation in the near to medium term and there may be other investors better positioned in a range of ways to further explore these possibilities. At this time Alinta can definitively conclude that the construction of a 50 MW, molten salt power-tower located in the town of Port Augusta is not an economically feasible option for Alinta. 105-RPT-006-Milestone_4_Summary_Report Page 5 of 33 2 Introduction This report represents the fourth of six milestones which comprise the Port Augusta Solar Thermal Generation Feasibility Study. Milestone One, Project Definition Report, was submitted to ARENA in January 2014 and Milestone Two, Options Study and Siting Study, was submitted to ARENA in May 2014. Milestone Three, Draft Balance of Study, was submitted to ARENA in January 2015. A public version of all of these Milestone Reports has been posted on the Alinta Energy website: www.alintaenergy.com.au/Port-Augusta-Solar-Thermal-Generation-Feasibility-Study 105-RPT-006-Milestone_4_Summary_Report Page 6 of 33 2.1 Review of Assumptions There were several high level assumptions made by Alinta which were inputs into the early stages of the Port Augusta Solar Thermal Feasibility Study. The assumptions first presented in Milestone 1 (Project Definition Report) are shown in Table 1 below along with a current assessment of these assumptions. Table 1: Changes to Assumptions from Milestone 1 Report Initial Assumption The location of the Augusta Power Station, and in the vicinity of the facility, is suitable for the siting and development of a solar thermal facility. Previous changes The site identified as optimal in the Siting Study is now known to be the subject of a Development Application by a third party. The proximity of the CSP plant to the Spencer Gulf raises potential corrosion issues due to salt water spray/deposition. Alinta Energy understands the current arrangements for land tenure permit the siting and development of a potential solar thermal facility on land within the control of Alinta Energy or adjacent to subject to the Sale / Lease arrangements between Flinders Power Partnership and the Government of South Australia. No change The life of the Leigh Creek Mine, which supplies coal to the Augusta Power Stations, would be extended through further investment by Alinta Energy. No change The Augusta Power Stations would remain in operation, in their current form supplied by the Leigh Creek Coal Mine, until at least 2028 to 2032. No change The useable life of the Augusta Power Stations, including re-use of facility components, extends beyond the current expected life of the Leigh Creek Mine. There are significant technical challenges to running NPS on only solar once the coal resource has been exhausted which would require extensive re-engineering of large parts of the plant. Milestone 4 No change No change In June 2015 Alinta Energy announced an intention to cease operating the Northern and Playford power stations and the Leigh Creek Coal Mine by March 2018. No change 105-RPT-006-Milestone_4_Summary_Report Page 7 of 33 Initial Assumption Previous changes The pre-measure activities and studies relied upon in the development of this study which detail the potential value and strength of the solar resource, the potential for hybrid solutions, and the potential utilisation of components from the Playford B Power Station is the best estimate and advice of the respective experts. Use of components from Playford B was determined to be infeasible. Procurement of spares and replacement parts is extremely difficult. The entire facility would require upgrading in order to support the use of usable components. The range of project benefits, fuel diversity opportunities for South Australia, dispatchable energy potential, compatibility with South Australian energy system, network connection options, technology costs and acceptable technology types do not materially deviate from those understood at the commencement of this study. Analysis by the Australian Energy Market Operator suggests that the grid in South Australia is oversupplied which leads to a disincentive for adding generation capacity of any kind. Progress beyond the study will depend on a number of factors outside the scope of this piece of work which have not been estimated or modelled at this point in time. No change Milestone 4 No change The reduction in generating capacity due to the future closure of Northern and Playford is not large enough to negate the oversupply of capacity in the South Australian electricity market. No change 105-RPT-006-Milestone_4_Summary_Report Page 8 of 33 3 Analysis of Measure Progress 3.1 Data Collection On 5 July 2014 Measurement Engineering Australia (MEA) sent two representatives to the Northern Power Station in Port Augusta to install a solar tracker, weather station and data collection equipment. The equipment has since been recording the following variables at one minute intervals: Weather Station Global solar radiation Air temperature Humidity Wind speed (min, max, ave) Wind direction Barometric pressure Solar Data Station Global solar radiation (min, max, ave) Global diffuse radiation (min, max, ave) Direct normal irradiance (DNI) (min, max, ave) Temperature of shaded pyranometer Temperature of un-shaded pyranometer Temperature of pyrheliometer Alinta has made a provision for validation of a full 12 month dataset which will allow for correlation between satellite data and ground station records. 3.2 Balance of Study 3.2.1 Scope of Works The scope of works for the Balance of Study is identified in the Agreement and is summarised below: Details of the plant and its operation; Capital and operating and maintenance costing at +/-30%; Energy yield and generation profile; Infrastructure requirements; Environmental studies including land use, profile and identification of environmental issues; Planning and development requirements for a Development Approval; Network connection; 105-RPT-006-Milestone_4_Summary_Report Page 9 of 33 *Stakeholder consultation plan; and *Preliminary financial evaluation. *Sensitivity analysis on the effect on financial viability of a range of parameters The items marked with “*” were determined to be within the core capability and expertise of Alinta personnel and were completed internally. The remaining scope was completed by Parsons Brinkerhoff (PB). 3.2.2 Methodology The majority of the high level plant design was completed and reported in the Options Study Report which comprised one of the deliverables for Milestone 2. Therefore only those aspects that have been further refined or have changed or new challenges which have arisen will be discussed here. Capital Cost Project capital costs were estimated by a combination of scaling the detailed reference plant cost estimate and generating estimates using commercial software and the internal estimating experience of PB personnel. Alinta and PB discussed at length the value of the labour cost multiplier in the context of the Port Augusta economy and local labour-force skills. Variation in this parameter could have a material impact on both the capital and operations cost estimates. While there is a real potential for the labour cost multiplier to be less than that used in the study, it would be well within the +/- 30% accuracy which characterises the pre-feasibility stage. Capital cost multipliers used in this report are show in Table 2 below. Table 2: Cost localisation factors Factor Value Labour cost multiplier 1.14 Material cost multiplier 1.34 Currency exchange rate 1.1 Comments Ratio of Australian union labour rates to Californian union labour rated (from Thermoflow PEACE) further localised to Port Augusta Ratio of Australian to Californian material cost multiplier (from Thermoflow PEACE) further localised to Port Augusta AUD to USD There is a significant reduction in estimated capital cost presented in the Balance of Study Report compared to the cost estimate provided in the Options Study Report. Cost estimates in the Options Study were based entirely on a literature review and desktop investigation. Alinta requested PB to conduct a cost tightening exercise which would draw on direct industry current experience and knowledge as well as consider the relative maturity of the solar thermal industry against well understood technology price curves. The cost estimates provided in the Balance of Study report are informed by conversations with leading industry players and consider more heavily the public knowledge around real costs incurred by reference plants. The overall capital cost estimate dropped approximately $200M following this exercise. The most significant reduction came from the heliostat field. Early estimates using the labour, exchange and 2 material cost multipliers referenced above resulted in an estimated cost of $262/m for the heliostat field. 2 Following discussions with manufactures and installers of heliostats, a revised estimate of $150/m was determined to be realistic. 105-RPT-006-Milestone_4_Summary_Report Page 10 of 33 Another significant reduction in the CAPEX cost estimate was realised by taking a weighted average of contingency values applied to individual components rather than applying the same % contingency to the final project cost. Table 3 below summarises the difference in CAPEX cost estimates by major component. Table 3: CAPEX cost estimate comparison: Options Study vs Balance of Study Component Site Improvements Heliostat Field Tower Receiver Thermal Energy Storage Balance of Plant Contingency EPC & Owner Costs TOTAL Options Study CAPEX $M Balance of Study CAPEX $M 32.3 230.4 26.0 8.2 138.2 21.5 90.4 79.3 129.5 117.6 81.8 787.2 86.0 83.4 118.1 67.9 53.4 577.0 Difference $M -24.1 -92.1 -4.5 -4.4 4.1 -11.1 -49.7 -28.4 -210.2 Clearly the assumptions about foreign exchange rates and labour rates could have a material impact on the CAPEX cost estimate. Preliminary analysis indicates that the CAPEX estimate has an exposure of approximately 30-35% to the labour rate and an exposure in the vicinity of 50% to foreign exchange rates. The current exchange rate is closer to 1.3 rather than 1.1 AUD:USD. This would have an effect of adding ~10% or ~$60M on the CAPEX cost estimate. Figure 1 below shows the movement of the Australian Dollar vs. the US Dollar over the previous 12 months. Figure 1: AUD:USD exchange rates July 2014 – May 2015 105-RPT-006-Milestone_4_Summary_Report Page 11 of 33 Additional Industry Consultation Alinta Energy contacted numerous industry participants in an effort to confirm the cost estimate assumptions used by PB in the Balance of Study report. After this consultation Alinta has concluded that, while there is still a moderate amount of variation in the values used by various suppliers, the values used in the Balance of Study assessment conducted by PB are accurate within the scope of the Study. The exception is the Power Block which appears to have been too conservatively estimated. Table 4 below summarises the information gathered through additional industry consultation and the percent difference between the Balance of Study cost estimate and the recent response from industry. Table 4: Results of further industry consultation Cost Item Full Project Heliostats Salt supply & melting Power Block Industry Response One organization that has previously constructed similar infrastructure undertook a high level review of a cost estimate for a CSP plant as specified in the Alinta study. Another company experienced in construction and operation of solar thermal infrastructure replied to Alinta’s request with a statement that within the context of their experience and the recent study into the feasibility of CSP in Western Australia, the cost estimates in the Draft Balance of Study are of the right order of magnitude and therefore judged to be appropriate at this level of the study. 2 The BoS estimate was $150/m of aperture area. A local South Australian manufacturer of heliostats has separately provided an indicative cost estimate for manufacture, supply and installation of heliostats 2 at a rate of $155/m . Parsons Brinkerhoff inquired to 2 European companies for the supply and melting of 20,000 cubic meters of thermal salts for a CSP plant in Port Augusta. The combined cost estimate came to ~$40M. A high quality engine manufacturer provided an indicative price for a 50MW steam turbine package of approximately $18M. The cost estimate used in the Balance of Study is ~$29M. BoS est. ($M) Industry Response Difference $577 ~$500 -13% ~ ~ $138 ~$143 3% $48 ~$40 -17% $29 ~$18 -38% ~ Six other companies did not respond in writing to Alinta’s request to provide comment on the cost estimates contained in PB’s Balance of Study report. Operational Cost Operating and maintenance costs were also scaled from the reference plant in a manner similar to the capital cost estimate. A burdened labour rate of 30% was assumed. Where there is a support function that could be considered a corporate service, no labour cost was included. These roles, such as IT, finance and human resources are assumed to be provided by existing Alinta Energy personnel. With the decision to close Northern Power Station there will be an increase in annual estimated labour cost as many of the resources that were assumed to be shared with existing operations would no longer be shared. While this would be a material difference in cost it is not expected to be significant and would certainly not stray from the +/- 30% accuracy band. 105-RPT-006-Milestone_4_Summary_Report Page 12 of 33 As with CAPEX, the OPEX cost estimate is also sensitive to labour rates, however less so to foreign exchange rates. The ~$8M annual operational costs has an exposure of approximately 60% to the labour rate. Solar Resource Data For a more accurate assessment of solar resource and generation profile of the plant, Alinta purchased a typical mean year (TMY) data set synthesised from a 15 year record between 1999-2013. The report provides a retrospective analysis of the past 15 years of solar irradiance, wind and temperature data. The data used is comprised of hourly values, however the long-term average values are only calculated using complete calendar years. The difference between the dataset used during modelling for the Options Study and this purchased dataset is shown in Table 5 below. The differences in these datasets does not make a material difference on the selection of the plant configuration made during the Options Study. The overall increase in solar resource expressed in the dataset purchased by Alinta for the Balance of Study increases the modelled annual generation by the plant and therefore a nominal increase in modelled revenue. Table 5: Solar resource data inputs for generation modelling Parameter Units Data for Options Study Data for Balance of Study Difference Standard Error % 16% <9% -7% Annual average DNI W/m 2 235.5 279.2 +19% Peak DNI W/m 2 886 981 +11% Summer average DNI MJ/day 24.7 28.5 +15% Winter average DNI MJ/day 15.9 19.7 +24% Annual average GHI W/m 215 222.1 +3% 2 Network Connection The obvious location to connect into the network is at the Davenport Substation just to the East of Northern Power Station. There is currently a spare bay inside the substation that could potentially accept the assets that would be required to connect the Augusta Solar Thermal plant. There are various options in the definition of asset ownership and boundaries with ElectraNet, which owns and operates the Davenport substation. The decision on what type of arrangement would suit best would be determined by a commercial and contractual discussion that is detail beyond the scope of this report. The connection of 50 MW of solar thermal power at Davenport substation would also not have a material impact on the Marginal Loss Factor (MLF) of the network. 3.2.3 Uncertainties discovered Plant Siting Since the Siting Study was completed there has been a material change to the availability of land near Northern Power Station. The land parcel identified as Option 1 has since been the subject of a Development Application for a nearby operation and would no longer be available as a location for the 105-RPT-006-Milestone_4_Summary_Report Page 13 of 33 solar thermal plant. The next best location that was part of the siting study is approximately four kilometres further south in the same direction from Northern Power station. This increases the cost of constructing a transmission line to the switchyard and increases the cost and complexity of sharing any infrastructure or services between the solar thermal plant and the existing activities at Northern Power station. Another concern that has arisen is the potential for salt corrosion on the plant components. This is a particular concern for the heliostats, however is relevant to all equipment and materials that would be exposed to salt spray and deposition. Cooling System The proximity to the Spencer Gulf and the existing cooling water loops used for Northern Power Station make a wet cooled condenser an obvious first option. However the expense of constructing adequate pipework is prohibitive and therefore a cooling tower is proposed. The use of salt water in a cooling tower introduces additional complications and has the potential to increase fouling and corrosion on nearby infrastructure. The logical conclusion is to move to an air cooled condenser which is also at additional cost. These issues that have arisen with the plant siting have almost entirely removed the potential benefit that was once thought to exist by co-locating the plant with Northern Power Station. It is Alinta’s opinion, therefore, that the initial constraint of choosing a location in proximity to Northern is now not relevant. For the purposes of the Study Alinta has continued to contemplate the location identified by PB in the Siting Study. Should a full feasibility study of a CSP plant in the vicinity of Port Augusta be undertaken by Alinta or another party in the future, a new location in the region would likely be sought. Time of Day Pricing As part of the preliminary analysis undertaken for the Draft Balance of Study Report, Alinta investigated the relationship between LCOE and simple payback time in the context of different CSP plant configurations. This analysis led to the conclusion that there was the potential for systems with less thermal storage, smaller heliostat field and therefore lower capital cost to have similar payback times to the Base Case. When considering external investment and/or capital grant funding, a reduced CAPEX would mean the same quantum of investment and/or grant would have a proportionally greater effect on the viability of a project. The value of Time of Day pricing becomes more significant as the storage capacity of the plant is reduced, therefore it is important to understand the impact that ToD pricing has on the financial viability of systems with less storage. In the financial model, market prices are represented by peak and off-peak time-weighted average rates. In order to determine the effect of hourly price granularity, an analysis was done comparing the revenue generated by a system with the dispatch optimised to the time weighted average prices versus dispatch optimised to an hourly price profile. The difference in recorded revenue between the two price curves was less than 5%. While this is a material difference, it is not significant and is comfortably covered by the hypothetical scenarios assessed by Alinta. The accuracy benefit gained by this level of modelling does not justify the significant additional effort required. Alinta determined that the use of peak and offpeak time-weighted average price signals is appropriate for this study. 105-RPT-006-Milestone_4_Summary_Report Page 14 of 33 Section 4.6 contains detailed results of further parameter sensitivity analysis and the impact on the financial position of a CSP plant in Port Augusta. 4 Financial Modelling and Assessment 4.1 Overview of financial modelling The financial viability of the proposed 50 MW Solar Thermal Power Station in Port Augusta is a key factor in assessing whether to continue to develop the project business case. Alinta has developed a financial model to analyse the overall financial viability of the project. The evidence from the financial analysis is that commercially the project is unviable. Even selecting for all of the most favourable and optimistic assumptions, the modelled CSP plant does not achieve a 12% IRR. The remainder of this section sets out the financial modelling undertaken and presents the detailed outputs from the financial viability assessment. 4.2 Methodology The financial modelling draws upon a number of information sources in order to calculate the ungeared post tax nominal cash flows associated with the project. The financial modelling is undertaken on a quarterly basis. The modelling methodology is set out in Figure 2: Figure 2: Financial modelling methodology 4.3 Input Data Input data is sourced from independent third party reports wherever possible. A number of the third party reports have been specifically commissioned as part of the Port Augusta Solar Thermal Feasibility Study, whilst others are commissioned by Alinta for use across within its broader business activities and have been leveraged for use in this Study. In some instances, Alinta has made assumptions, drawing upon its internal expertise where required. 105-RPT-006-Milestone_4_Summary_Report Page 15 of 33 4.3.1 Capital Costs The $577M capital cost of the project used in the financial modelling is based upon the Balance of Study Report prepared by PB. Alinta has supplemented the total capital cost estimate prepared by PB with a construction cost curve, to forecast the potential actual expenditure over an assumed 2 year build period. It is assumed, that construction starts on 1 January 2017. The resulting quarterly construction expenditure curve is shown in Figure 3. Figure 3: Construction cost curve assumption 4.3.2 Operational Costs The $7.89M of annual operating costs in the financial modelling are based upon the Balance of Study Report prepared by PB. Alinta has supplemented the estimated annual operating costs with the assumption that the operating costs will escalate each July by CPI, and will be incurred equally across the year. 4.3.3 Electricity Generation The PB Balance of Study Report estimates the energy production capability of the project over its expected life. Importantly, the financial model converts the information in the PB report into peak (7:00 to 22:00 workdays) and off-peak for each calendar quarter. Specifically, the model calculates: Average proportion of peak and off-peak energy production for each month (based upon average daily production profiles in each month ) Average proportion of peak and off-peak energy production for each quarter (based upon total monthly production profiles ) Energy production during peak and off-peak times for each quarter for each forecast year. This utilises the forecast total annual production for each year of operation from the report (which 105-RPT-006-Milestone_4_Summary_Report Page 16 of 33 takes into account degradation) and applies the average quarterly peak and off-peak proportions (calculated in 2) above) The total forecast peak and off-peak production by quarter is shown in Figure 4 below. Figure 4: Forecast lifetime electricity production by quarter 4.3.4 Pricing South Australian pool prices are based upon the forecasts contained in Acil Allen Consulting’s Australian Energy Market, Analysis of the National Electricity Market (NEM), Western Electricity Market (WEM) and Large scale Renewable Energy Target (LRET) report. The time weighted nominal quarterly forecast peak and off-peak prices to Dec 2030 have been utilised. The price path is then interpolated between 2030 and 2035, and also 2035 to 2040. Beyond 2040, it is assumed that prices remain flat. 105-RPT-006-Milestone_4_Summary_Report Page 17 of 33 Figure 5: Forecast peak and off-peak electricity prices Forecast large scale generating unit certificate (LGC) prices are also sourced from Acil Allen Consulting’s Australian Energy Market, Analysis of the NEM, WEM and LRET report. Acil Allen’s reference case is adopted for the base financial viability assessment. LGC prices are only forecast to 2030, when the LRET scheme is currently scheduled to end. The forecast price path is shown in Figure 6 below and was generated on the basis of the original RET target of 41,000 GWh. The outcome of the recent RET Review was not known in time to be incorporated into this analysis. The expected effect would be a small, downward pressure on LGCs. Figure 6: Forecast LGC price path 105-RPT-006-Milestone_4_Summary_Report Page 18 of 33 4.3.5 Other Assumptions A number of generic assumptions have been adopted in the financial modelling: Tax assumptions: o To calculate the post-tax cashflows of the project, we have adopted the current company tax rate of 30% o Tax depreciation is based upon the diminishing value methodology, with a 200% multiplier and an assumed asset useful life of 25 years from construction completion A number of costs and prices are assumed to escalate by CPI. Within the model it is assumed that CPI increases by 2.5% per annum, with adjustments occurring on 1 July in each of the forecast years. The Acil Allen reference curve assumes the current policy that there is no price on carbon. 4.4 Financial Modelling Outputs During an internal audit of the financial model, Alinta discovered that nominal values had been used for forecast revenue instead of real values. This had the effect of applying CPI twice to the forecast revenue and thereby over-estimating the revenue that would be generated during the lifetime of the modelled plant. The updated results of the model are presented below. The forecast annual cashflows of the project are shown in the chart below. Figure 7 shows that once the facility is operational, it would be profitable. However, based upon the metrics presented in Table 6 below, the level of expected future profitability does not justify the large capital investment required to build the facility. 105-RPT-006-Milestone_4_Summary_Report Page 19 of 33 Figure 7: Project lifetime cashflows Table 6: Base case financial modelling key outputs Value Metric Net Present Value -$359.8M Internal Rate of Return Levelised Cost of 1 Energy Realised revenue 1% $201/MWh 2 $96/MWh Comments Based upon a target post tax cashflow discount rate of 12% (ungeared). Represents the size of the shortfall of the project from being commercially viable. Indicates that the project does not generate a return on the capital invested in the project, as it does not meet a hurdle rate of 12%. Represents the revenue that would be required per MWh for the project to achieve the required return metrics. Represents the revenue that is forecast to be realised per MWh produced. 1 Levelised Cost of Energy is calculated as [NPV of Capital Costs and Operating Costs (excluding any tax payments)] divided by the [NPV of Demand escalated CPI] 2 Realised Revenue is calculated as [NPV of Total Revenue] divided by the [NPV of Demand escalated CPI] 105-RPT-006-Milestone_4_Summary_Report Page 20 of 33 4.5 Cost Uncertainty Analysis The scope of this (Milestone 4 report) is to identify the cost of the project to within a tolerance of +/- 30%. The financial evaluation has been based upon the expected costs estimated by PB to within this level of accuracy. Given the level of accuracy with in the costs, it is prudent to undertake a sensitivity analysis to confirm whether, across the plausible range of cost estimates (i.e. +/- 30%), the project could be considered to be commercially viable. As the metrics in the table below indicate, even if the capital costs have been over-estimated by 30%, the project would still be unviable, with a Net Present Value (NPV) of -$180M, and an Internal Rate of Return (IRR) of 3.4%. It is on this basis that it is considered that the project is unlikely to be commercial under any plausible cost estimate. Table 7: +/-30% financial modelling key outputs Metric Capital costs Net Present Value (@ 12% IRR) Internal Rate of Return Levelised Cost of Energy Realised revenue -30% +30% $403.9 $750.1M -$182.3M -$515.6 3.4% -0.4% $149/MWh $253/MWh $96/MWh $96/MWh 4.6 Parameter Sensitivity Analysis 4.6.1 LCOE vs. Simple Payback Time During the early phases of the Study, Alinta and Parsons Brinkerhoff selected LCOE as the defining metric for use in optimising storage hours and solar multiple of each system under consideration. Use of this metric is ubiquitous and fundamental to all investment decisions in generation infrastructure. Alinta uses LCOE to rank the internal portfolio of potential projects in order of investment priority. Some analysis undertaken for Milestone 3 suggested that LCOE may not be the most accurate metric for evaluating a CSP plant against competing technology options. The lowest LCOE system with 15 hours of storage effectively performs as a baseload plant. This leads to electricity generation at times of lowest prices as well as highest prices. Systems with between 1-7 hours of storage offer a small but material improvement in simple payback time. This is due to the ability of these systems to regularly generate during the higher priced, late-afternoon/early-evening peak periods while avoiding generation during the late-night/early-morning trough. Reduction in hours of storage and a proportional amount of heliostats translates to a significant reduction in CAPEX. A plant with 4 hours storage reduces CAPEX to ~65% of the cost of the reference plant with 15 hours storage. 4.6.2 Plant Configuration In order to explore more fully the potential impact of plant configuration on financial viability, five additional plant configurations were interrogated. The selection of storage hours and solar multiple was 105-RPT-006-Milestone_4_Summary_Report Page 21 of 33 recommended by IT Power to cover the entire range of systems that were thought to have the potential for better economic performance than the Base Case. In order to align with the boundary condition set by Alinta at the outset of this study, the size of the power block was held at 50MW. The hours of thermal storage and the size of the heliostat field were varied as presented in Table 8 below. Table 8: Alternate system configurations Alternate System Power Block Storage hours Solar Multiple Base case 50 MW 15 3.5 AS 1 50 MW 4 1.8 AS 2 50 MW 6 1.7 AS 3 50 MW 6 2.2 AS 4 50 MW 6 2.5 AS 5 50 MW 8 2.4 Each of these systems was created in SAM and the output simulated against the same TMY file that was used when modelling the base case. Hourly generation profiles were created out of SAM and each generation profile was inserted into Alinta’s financial model. Effect on LCOE & IRR Key metrics for each of the alternate systems are presented in Table 9 below. Table 9: Alternate Systems – modelling outputs Alternate System CAPEX $M Annual GWh % peak % off peak LCOE (10%) IRR Base case $577 301 %50 %50 $201 % 1.1 AS 1 $357 167 %72 %28 $230 % 0.0 AS 2 $362 166 %72 %28 $235 % -0.2 AS 3 $402 199 %70 %30 $215 % 0.7 AS 4 $431 205 %70 %30 $224 % 0.4 AS 5 $439 220 %66 %34 $214 % 0.6 The single metric which will determine the viability of an investment is the IRR. In Table 9 one can see the IRR of the alternate systems is less in each case than the IRR of the base case. This indicates that, once all factors are introduced into the calculation determining the economic payback, LCOE (ultimately 105-RPT-006-Milestone_4_Summary_Report Page 22 of 33 driven by capacity factor) is still an appropriate metric to use for ranking the economic performance of CSP systems in Port Augusta. 4.6.3 Market Forecast In order to better understand the potential effects of forecast prices on the financial viability of a CSP plant of this type, Alinta commissioned Acil Allen to create three forward curves for the spot price in the South Australian market. Each of these forward curves incorporated different assumptions about variables that were considered likely to impact the market: Renewable Energy Target policy, future carbon price and rate of uptake of domestic PV. The impact that these variables have on the expected future price of electricity in South Australia is complex, however it is heavily dominated by assumptions about a future price on carbon. Forecast price curves The forward curve used in the reference case for the financial model in the Draft Balance of Study report was commissioned by the Alinta Energy Wholesale department as part of strategy and planning for the coming years. The alternative forward curves used in the modelling for this study are based on the reference case with changes to one or more key assumptions that were thought to have the potential to have a material impact on the financial viability of a CSP plant in Port Augusta. The three alternative forward curves are described below. Forward Curve 1 – Assumes a price on carbon is reintroduced into the market from July 2020 with prices based on the current forward curve for emissions abatement permits in the EU. Forward Curve 2 – Assumes a price on carbon is reintroduced by July 2020. Prices are based on the assumption that there is a global agreement to reduce emissions by 2050 by 80 per cent on 2000 levels. This scenario also assumes that the Large Scale Renewable Energy Target is unchanged from the original target with a target of 41,000 GWh by 2020. Forward Curve 3 – Assumes the same carbon prices as forward curve 2 but also assumes the RET is changed so that the target equals 30% of demand by 2030 with the scheme expiring in 2040. Forward curve 3 also assumes a stronger uptake in rooftop PV in line with the Rapid scenario presented in the 2014 National Electricity Forecasting Report published by AEMO. Each of the Alternate System was modelled against these three additional forward curves to calculate potential revenue Effect on IRR Unsurprisingly, the variable that has the most significant impact on the future market price of electricity is the price of carbon. This is seen in the analysis where all scenarios have a greater IRR when run against Forward Curve 2 and Forward Curve 3 where carbon prices drive a national target to reduce carbon emissions to -80% of 2000 levels by 2050. This is much more ambitious than the current policy target of -5% by 2020 and beyond most expectations of any near-term policy. Table 10 below presents the financial metrics of the base case when the different forward curves are assumed. As the forward curve affects only revenue, not expenses, there is no change to the LCOE of the system ($201/MWh). 105-RPT-006-Milestone_4_Summary_Report Page 23 of 33 Table 10: Base case vs. forward price curves Forward Curve IRR NPV (12%) $M Reference curve 1.07% -$360 FC 1 0.80% -$352 FC 2 2.10% -$336 FC 3 1.96% -$337 When the various alternate system configurations are also considered in the context of the different forward curves there are two things that become apparent: 1. Shown by the data in Table 11, the capacity factor at which a CSP plant is run has more effect on the IRR than altering system design to maximise the ratio of on-peak to off-peak generation. As the storage component of the system increases, so does the capacity factor and the IRR. 2. Shown by the data in Table 12, the most significant factor driving the NPV of a CSP system in this study is the capital cost. The Base Case has the highest CAPEX. CAPEX reduces from AS 5 down to the lowest for AS 1. Table 11: IRR as a function of system design & forward price curve Forward demand curve Reference curve FC 1 FC 2 FC 3 System configuration Base Case 1.07% 0.80% 2.10% 1.96% AS 1 0.00% -0.37% 1.05% 0.88% AS 2 -0.16% -0.53% 0.87% 0.70% AS 3 0.66% 0.34% 1.72% 1.56% AS 4 0.35% 0.02% 1.41% 1.25% AS 5 0.55% 0.22% 1.64% 1.48% Table 12: NPV @ 12% as a function of system design & forward price curve Forward demand curve Reference curve FC 1 FC 2 FC 3 System configuration Base Case - $ 359,792 - $ 351,537 - $ 335,773 - $ 337,413 AS 1 - $ 239,732 - $ 234,767 - $ 224,322 - $ 225,638 AS 2 - $ 245,552 - $ 240,670 - $ 230,289 - $ 231,626 AS 3 - $ 258,191 - $ 252,303 - $ 240,546 - $ 241,965 AS 4 - $ 282,880 -$ 276,648 - $ 264,028 - $ 265,544 AS 5 - $ 284,082 - $ 277,495 - $ 264,377 - $ 265,889 4.6.4 Time of Day Pricing vs DNI datasets The revenue stream in the financial model assumes that the CSP plant would receive spot prices for all electricity delivered to the grid during the lifetime of the plant. As both spot price and DNI are variables which can move dramatically over short periods, Alinta commissioned an analysis of the correlation between spot price and DNI. The significance of a correlation would be seen in an (assumed) increase in 105-RPT-006-Milestone_4_Summary_Report Page 24 of 33 revenue when running historical spot price record against historical DNI data as opposed to a TMY file of DNI data. The results of this investigation show that: There does not appear to be a real time correlation between spot price and DNI There is a correlation between cumulative daily DNI and ambient temperature There is a correlation between ambient temperature and spot price Therefore, while DNI has a direct impact on the temperature of the day and the temperature of the day does correlate to the spot price for electricity, at least during summer months, the short term fluctuations in DNI which will be different between a TMY file and a real data file are not material when considering their impact on the behaviour of the spot market. Therefore a TMY file is appropriate for modelling the performance of a CSP system and potential revenue streams in a dynamic electricity market. 4.6.5 Dispatch Methodology It is not possible to implement sophisticated plant dispatch routines within SAM. When modelling a CSP system that operates in a base-load pattern this is not a significant constraint to the model. However, when the system is not designed as a base load and more closely resembles a peaking plant, the ability to optimise the dispatch can have a significant impact on the financial performance by enabling a better match between the electricity sent out and peaks in the market price. Alinta engaged Solar Reserve in order to understand better the potential gains in revenue that could be possible through optimising the plant dispatch. A CSP plant of the same configuration and capacity as the Alinta base case was run through a dispatching protocol with perfect foresight of the spot market prices. The revenue forecast through the perfect foresight model was approximately 18% higher than the revenue forecast with the SAM dispatch regime. There are two key assumptions that inform this analysis and must be noted here: 1. All electricity exported can be sold at the market rate; and 2. Dispatch of the CSP plant is done with full knowledge of all future market prices. Both of these assumptions are unrealistically optimistic, however this exercise leads to the conclusion that there is a material gain to be made by optimising the dispatch of a CSP plant, which cannot be effectively done in SAM. It would be reasonable to assume that half (~10%) of this gain could be captured by virtue of detailed market knowledge and understanding without having perfect foresight of future market prices. 4.7 Project Financial Viability All organisations will select investments based on different benchmarks and therefore an investment that may not be attractive to one organisation may be considered a worthy investment by another. Some variables that are key to a company’s decision whether to invest include, but are not limited to: Requirement for minimum return on investment (Internal Rate of Return - IRR); Organisational risk profile; Access to and cost of capital; and Logical synergies with existing assets and/or business strategies. 105-RPT-006-Milestone_4_Summary_Report Page 25 of 33 These metrics and others will typically act as a filter and those potential projects which meet the minimum criteria will then be ranked against each other to create a priority listing. Depending on the capital and other resources which may be available, access to finance and other potential constraints. One or more of the potential projects may be pursued. Therefore it may be the case that a contemplated project is thought to be profitable but there are logistical or other constraints that prevent an investment being made by a particular organisation. 4.7.1 Financial parameter benchmarks required for project viability Any potential project investment will be determined by many and varied factors which are prioritised and valued differently by different organisations. There are several different perspectives that can be taken on how to make a CSP plant at Port Augusta a financially viable investment. The simplest approach is to define the decrease in CAPEX that would be required to give the project a minimum IRR of 10%. This level of IRR does not represent a benchmark for Alinta’s investment decisions, rather it represents the lowest benchmark IRR that some companies may contemplate when shortlisting potential investments. Holding all other parameters fixed, the reduction in CAPEX would need to be approximately 60% as shown in Table 13 below. Table 13: Minimum financial benchmarks for CSP investment at Port Augusta Parameter Modelled Value Required Value LCOE $201 / MWh $80 / MWh Installed cost $10.5M / MW gross $4.2M / MW gross CAPEX $577M $231M CAPEX / kWh / yr $1.86 $0.745 Difference - 60% This is presented graphically in Figure 8 below. Each of the three coloured lines represents a given IRR (10, 12 & 15%). The green line represents the levelised revenue while the LCOE is determined by the point on the IRR curve corresponding to the CAPEX of the project. The difference between the LCOE and the levelised revenue is the shortfall which would need to be recovered in some form in order for the investment to appear economic. 105-RPT-006-Milestone_4_Summary_Report Page 26 of 33 Figure 8: LCOE as a function of IRR and CAPEX – Base Case/Reference Curve 105-RPT-006-Milestone_4_Summary_Report Page 27 of 33 Running multiple sensitivity analyses on the variables under consideration shows that, while there could be a significant difference in the shortfall depending on assumptions about cost and revenue, no combination of assumptions considered makes the project appear economic. Making the most optimistic assumption on all variables on the base case is represented graphically in Figure 9. The assumptions behind this scenario include: CAPEX is 30% less than estimated; OPEX is 30% less than estimated; An up-front grant of $100M is applied to CAPEX; and Dispatch optimisation provides a revenue uplift of 10% over modelled value; Figure 9: LCOE as a function of IRR and CAPEX – Variation 2 Table 14 on the following page contains the results of a range of sensitivity analyses that were run using different combinations of cost assumptions and forward curves. It should be noted that there is equal probability of the actual cost being 30% more than the estimate as being 30% less than the estimate. No scenario with an increased capital cost has been explored. In this case, no combination of assumptions about system design, forward curve and CAPEX/OPEX combinations result in a system that is a viable investment. 105-RPT-006-Milestone_4_Summary_Report Page 28 of 33 Table 14: Sensitivity of IRR & NPV to multiple variables Scenario Reference Variation 1 Variation 2 Variation 3 Variation 4 Variation 5 Variation 6 Variation 7 Variation 8 Variation 9 Variation 10 Variation 11 Variation 12 Variation 13 Variation 14 Variation 15 Variation 16 Variation 17 Variation 18 Variation 19 Variation 20 Variation 21 Variation 22 Variation 23 Variation 24 Variation 25 Variation 26 Variation 27 Variation 28 Variation 29 Variation 30 Variation 31 Variation 32 Forward Curve Reference Reference Reference Reference Reference FC 1 FC 1 FC 2 FC 2 Reference Reference FC 1 FC 1 FC 2 FC 2 Reference Reference FC 1 FC 1 FC 2 FC 2 Reference Reference FC 1 FC 1 FC 2 FC 2 Reference Reference FC 1 FC 1 FC 2 FC 2 System Base case Base case Base case AS 1 AS 1 AS 1 AS 1 AS 1 AS 1 AS 2 AS 2 AS 2 AS 2 AS 2 AS 2 AS 3 AS 3 AS 3 AS 3 AS 3 AS 3 AS 4 AS 4 AS 4 AS 4 AS 4 AS 4 AS 5 AS 5 AS 5 AS 5 AS 5 AS 5 CAPEX $M 577 577 -30% 577 -30% 357 -15% 357 -30% 357 -15% 357 -30% 357 -15% 357 -30% 362 -15% 362 -30% 362 -15% 362 -30% 362 -15% 362 -30% 402 -15% 402 -30% 402 -15% 402 -30% 402 -15% 402 -30% 431 -15% 431 -30% 431 -15% 431 -30% 431 -15% 431 -30% 439 -15% 439 -30% 439 -15% 439 -30% 439 -15% 439 -30% 577 404 404 303 250 303 250 303 250 308 253 308 253 308 253 342 281 342 281 342 281 366 302 366 302 366 302 373 307 373 307 373 307 Capital Grant $M $ $ 50 $ 100 $ 50 $ 100 $ 50 $ 100 $ 50 $ 100 $ 50 $ 100 $ 50 $ 100 $ 50 $ 100 $ 50 $ 100 $ 50 $ 100 $ 50 $ 100 $ 50 $ 100 $ 50 $ 100 $ 50 $ 100 $ 50 $ 100 $ 50 $ 100 $ 50 $ 100 OPEX $M/yr 7.9 7.9 -30% 7.9 -30% 6.0 -15% 6.0 -30% 6.0 -15% 6.0 -30% 6.0 -15% 6.0 -30% 6.0 -15% 6.0 -30% 6.0 -15% 6.0 -30% 6.0 -15% 6.0 -30% 6.3 -15% 6.3 -30% 6.3 -15% 6.3 -30% 6.3 -15% 6.3 -30% 6.7 -15% 6.7 -30% 6.7 -15% 6.7 -30% 6.7 -15% 6.7 -30% 7.2 -15% 7.2 -30% 7.2 -15% 7.2 -30% 7.2 -15% 7.2 -30% 7.9 5.5 5.5 5.1 4.2 5.1 4.2 5.1 4.2 5.1 4.2 5.1 4.2 5.1 4.2 5.4 4.4 5.4 4.4 5.4 4.4 5.7 4.7 5.7 4.7 5.7 4.7 6.1 5.0 6.1 5.0 6.1 5.0 Revenue uplift 0% 10% 10% 0% 10% 0% 10% 0% 10% 0% 10% 0% 10% 0% 10% 0% 10% 0% 10% 0% 10% 0% 10% 0% 10% 0% 10% 0% 10% 0% 10% 0% 10% IRR 1.1% 6.1% 7.4% 2.5% 8.2% 2.3% 8.4% 3.7% 9.7% 2.3% 7.9% 2.1% 8.0% 3.5% 9.3% 3.1% 8.4% 2.9% 8.5% 4.3% 9.8% 2.7% 7.6% 2.5% 7.7% 3.9% 9.0% 2.9% 7.9% 2.7% 8.0% 4.1% 9.3% LCOE $/MWh $ 201 $ 125 $ 110 $ 169 $ 107 $ 169 $ 107 $ 169 $ 107 $ 172 $ 110 $ 172 $ 110 $ 172 $ 110 $ 160 $ 105 $ 160 $ 105 $ 160 $ 105 $ 168 $ 113 $ 168 $ 113 $ 168 $ 113 $ 162 $ 109 $ 162 $ 109 $ 162 $ 109 NPV $M (12%) -$360 -$134 -$93 -$141 -$38 -$137 -$35 -$128 -$25 -$146 -$42 -$142 -$39 -$133 -$29 -$154 -$45 -$150 -$40 -$139 -$28 -$174 -$59 -$169 -$55 -$158 -$42 -$174 -$57 -$169 -$53 -$157 -$39 Note: LCOE is calculated on a 10% IRR 105-RPT-006-Milestone_4_Summary_Report Page 29 of 33 4.7.2 LCOE Assessment When breaking down the component contributions to LCOE as determined by Alinta’s financial model, it is apparent that the findings are well aligned with existing literature. Alinta found that, in the context of the base case, capital costs contribute approximately two-thirds to LCOE. As expected, the heliostat field makes the single largest contribution in both CAPEX and OPEX. Table 15 below shows the contribution the OPEX and CAPEX costs make to the LCOE of the base case plant modelled at Port Augusta. Table 15: Contributions to LCOE by category and CAPEX vs OPEX Category CAPEX contribution OPEX contribution Total $/MWh Solar Field 43 32 75 Receiver / HTF 31 7 39 Power Plant 35 23 57 Thermal Energy Storage 24 6 30 TOTAL $/MWh 133 68 201 Table 16 identifies the contributions that the major component categories make to the total LCOE modelled. The four categories were chosen to align with the metrics use by the SunShot Initiative which is being run by the Department of Energy in the United States. The SunShot Initiative has the aim of reducing LCOE of CSP technologies by approximately 70% between 2010 and 2020. Also in Table 16 is the 2013 technology costs achieved by SunShot and the 2020 target costs. The sum of CAPEX expenses that were not clearly associated with one of these categories was allocated according to the percentage of the known CAPEX costs for each category. General OPEX costs were divided evenly among the four categories. Table 16: LCOE contributions by category compared to SunShot targets Category Port Augusta Sunshot 2013* Sunshot target 2020* Solar Field 75 68 27 Receiver / HTF 39 27 14 Power Plant 57 55 27 Thermal Energy Storage 30 27 14 TOTAL $/MWh 201 177 82 *converted from 2010 USD to 2014 AUD at exchange rate of $0.8 USD:AUD and inflation at 1.09 105-RPT-006-Milestone_4_Summary_Report Page 30 of 33 If the SunShot Initiative is successful in reducing the technology costs in line with the targets summarised above, a CSP plant as modelled in this study has the potential to be independently economic not long after the year 2020. 4.8 Unexplored Concepts Through internal workshops and through discussions with other industry participants, several concepts have been identified that would be worthy of further investigation in Stage Two of the Study. These concepts are not considered to be significant enough to overcome the financial viability gaps identified thus far in the Study. 4.8.1 Storage from grid power It would be possible to build in the capability to heat the thermal storage tanks with power imported from the grid. This would give the flexibility to purchase electricity at low or negative prices and return electricity to the grid during higher prices. There are several factors which would limit the benefit of this concept: Upgrade of the interconnection to Victoria is likely to flatten market fluctuations therefore raising the minimum market prices and reducing peak prices; The round trip efficiency of this process will be limited by the efficiency of the power block which would be on the order of 40%; As the thermal storage capacity of a CSP plant increases, the window for profitable purchase and re-selling through this mechanism decreases; The complexity that is introduced by this functionality could be very high. A deeper understanding of the details would be required before knowing whether this idea would actually be of benefit. 4.8.2 Use of waste heat In many settings, the economics of a CSP plant are enhanced because the useful energy is not just the electricity that is generated, but the low grade waste heat from the system is also beneficial to some other end user or industrial process. This is the case with the smaller solar thermal plant that is being constructed by Sundrop Farms in Port Augusta. In the context of the CSP plant modeled by Alinta at Port Augusta there is no obvious beneficial use for waste heat from the power block. 4.8.3 Hybridised solar Linear Fresnel is a cheaper technology than the central receiver with molten salt. The potential for using a Linear Fresnel field to pre-heat the heat transfer fluid prior to entering the main receiver at the top of the tower could be considered. This may reduce the overall area of the heliostats required. There have been CSP plants recently commissioned which include a PV component. These plants are cheaper per unit of installed capacity and therefore also in terms of LCOE. As discovered earlier, capacity factor appears to drive LCOE more strongly than all other variables. Therefore, adding PV capacity may reduce the average LCOE of a hybrid PV/CSP plant but presumably only if there were additional CAPEX invested in adding PV to the design. The addition of PV capacity would not economically replace thermal capacity, but would augment it. 105-RPT-006-Milestone_4_Summary_Report Page 31 of 33 4.8.4 Alternative location While Port Augusta is a convenient site in terms of infrastructure availability and solar resource, there are other locations in South Australia which offer a better solar resource. Depending on the additional cost to install a substation and/or high voltage transmission line, an alternative location could increase the output of an identical CSP plant by a material amount. 5 Near Commercial Technologies Of the inquiries made by Alinta into technologies that are expected to be commercial in the near term, most were met with a reluctance to reveal information. Any technology that is under an advanced stage of development would be expected to have an impact on the market and competitive influence of the company developing the technology. This may be the motivation for the lack of information sharing in this area. The only company to respond with any information of substance was Vast Solar. 5.1 Technical Maturity Alinta visited the Vast Solar demonstration facility in Jemmalong NSW in March 2015. This facility, once operational, will have a 1.1 MWe capacity and is intended to prove the integrated operation of the hardware and software developed by Vast Solar. While Alinta understands that the individual components of Vast’s technology have all been trialed and tested, it is the successful operation of the entire system that will encourage energy companies and developers to invest in Vast Solar. Without making a thorough engineering analysis of the Vast Solar CSP System, Alinta’s view is that the key items which will require rigorous testing and data records to verify performance will be the operation of the heliostats, the material durability of the mirrored surfaces, the heat transfer properties/efficiency of the receiver and storage system and the use of sodium as a heat transfer fluid. Vast Solar technology has not yet proven itself to a stage that would make Alinta comfortable investing substantially in the company, however Alinta believes there is promise in the path Vast Solar is taking. 5.2 Financial Potential The cost estimates provided by Vast Solar for the purposes of this study have not been developed for a CSP plant matching the Base Case in the study. Rather, Vast Solar have taken a cost estimation, which they believe to be +/-10%, developed for a 30MW plant with 4 hours storage and scaled those cost estimates to a CSP plant that is equivalent to Alinta’s Base Case. Based on the assumption that the output from a Vast Solar plant with the same sized power block and thermal storage would deliver the same electricity generation profile as the power tower in Alinta’s Base Case, the revenue from a Vast Solar plant would be the same. Table 17 below presents the results of Alinta’s financial model when the CAPEX and OPEX provided by Vast Solar are used as primary inputs. Based on these results, if costs prove to be as projected, the Vast Solar technology appears to be close to commercial. 105-RPT-006-Milestone_4_Summary_Report Page 32 of 33 Table 17: VAST Solar scaled base case vs. forward price curves Forward Curve 6 IRR NPV (12%) $M Reference case 9.7% -$35.8 FC 1 10.0% -$30.5 FC 2 11.1% -$15.2 FC 3 10.9% -$17.1 Further Information A dedicated public webpage has been established on Alinta Energy’s website: http://alintaenergy.com.au/about-us/power-generation/port-augusta-solar-thermal. All milestone reports and media releases have been publicly-available on this website through the course of the study. Also free to the public will be the data that Alinta has collected since the installation of the solar tracker and weather station in early June, 2014. Monthly files containing all solar data and weather station data will be freely available to the public upon request. On Thursday 23 April 2015 Alinta held a public information session in Port Augusta. There were approximately 50 attendees which included local and federal politicians, representatives of NGOs and South Australian Government agencies as well as interested individuals. At this session Alinta presented a comprehensive summary of the progress and findings of the study to date. The session was well attended and attracted significant media. The presentation given on the day is available on the website referenced above. 7 Conclusion The cost of Stage One has been approximately ~$950,000. The forecast cost to undertake Stage Two of the feasibility study is ~$1,160,000. The outcome of Stage Two would be better certainty about the present day cost for the construction of a CSP plant in Port Augusta. In Table 14 Alinta presented the results of thorough sensitivity analysis including scenarios where all assumptions were at the extreme optimistic margin. Even in these scenarios this potential project does not meet Alinta’s minimum benchmarks for further investment consideration. Alinta has an expectation on investment returns that is likely more aggressive than many other organisations. Another proponent with a different appetite for risk, lower minimum investment returns and potentially other strategic interests would be better placed to pursue a full feasibility stage of this study or a similar study. Based on the information compiled over the last 18 months of Stage 1 of the Port Augusta Solar Thermal Generation Feasibility Study and the anticipated costs and benefits of refining the current level of knowledge, Alinta has decided not continue into Stage Two. 105-RPT-006-Milestone_4_Summary_Report Page 33 of 33
© Copyright 2026 Paperzz