Bill of Quantities - Process Plant

The Chief Estimator Software
Process Plant Bill of Quantities
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
10000
Description
Unit
Process Plant Direct Costs
Civil Work
Site Investigation
Soil Investigation,Boring
Monitoring Well, Depth=3.3m, with Cap & Post , Dia=150mm
Nos
10020
228,270.00
1.00
228,270.00
228,270.00
30.00
8,120.00
243,600.00
931.00
180.00
167,580.00
931.00
441.65
411,180.00
m3
3,000.00
95.00
285,000.00
m3
44,500.00
55.00
2,447,500.00
m3
3,000.00
11.00
33,000.00
m3
3,000.00
220.00
660,000.00
Sub Total Earthworks: m3
47,500.00
72.12
3,425,500.00
m3
14,697.00
42.00
617,274.00
m3
10,724.00
54.00
579,096.00
Piliing Works
Pile Driving, Sheet Pile, W 400 x W 400, 75 x 8t x 12m (with
waling and horizontal struts)
Pile Head Treatment,Misc. Special Piles,Bored-and-CIPwith_Casing
Dia=600mm
10050
Earthworks
Excavation,Normal Soil,Back Hoe
ncluding surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )
10060
Crushed Stone Spreading with compaction,Machine
10040
Amount
76,090.00
m
Nos
Sub Total Piliing Works: ea
10030
Rate
3.00
Sub Total Site Investigation: LS
10010
Quantity
10090
Sewer/Drainage
Exavation & Backfill
Excavation,Normal Soil,Back Hoe
ncluding surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )
m3
2,055.68
11.00
22,612.48
10100
Sand filling and Compaction,Machine,T=15cm ( Compacted ) m3
1,919.25
86.00
165,055.50
10110
Excavation,Normal Soil,Back Hoe
ncluding surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )
m3
14,676.09
65.00
953,945.85
m3
9,491.44
54.00
512,537.76
m3
4,635.13
11.00
50,986.43
10140
Crushed Stone Back-filling and Compaction,Machine,T=15cm m3
( Compacted )
41.00
86.00
3,526.00
10150
Sand filling and Compaction,Machine,T=15cm ( Compacted ) m3
551.40
110.00
60,654.00
10160
Excavation,Normal Soil,Back Hoe
including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
m3
2,030.51
66.00
134,013.66
m3
1,001.01
54.00
54,054.54
10070
10080
10120
10130
10170
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
Description
Unit
Quantity
Rate
Amount
10180
Disposal,Machine,0-10km ( Distance )
m3
1,029.50
11.00
11,324.50
10190
m3
4,138.13
97.00
401,398.61
m3
3,294.11
54.00
177,881.94
10210
Excavation,Normal Soil,Back Hoe
including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )
m3
845.98
11.00
9,305.78
10220
Crushed Stone Spreading with compaction,Machine
m3
14.00
86.00
1,204.00
Sub Total Exavation & Backfill: LS
1.00
3,754,871.05
3,754,871.05
10200
10230
Drainage & Sewer Pipe
Pipe Installation,Laying Hume Pipe,Socket Type,DIA 300
m
30.00
88.00
2,640.00
10240
Pipe Installation,Laying Hume Pipe,Socket Type,DIA 400
m
50.00
120.00
6,000.00
10250
Pipe Installation,Laying Hume Pipe,Socket Type,DIA 500
m
10.00
150.00
1,500.00
10260
Pipe Installation,Laying Hume Pipe,Socket Type,DIA 700
m
10.00
210.00
2,100.00
10270
Pipe Installation,Laying Hume Pipe,Socket Type,DIA 800
m
100.00
230.00
23,000.00
10280
Pipe Installation,Laying Hume Pipe,Socket Type,DIA 900
m
30.00
260.00
7,800.00
10290
Pipe Installation,PVC Pipe
dia.=150, for sanitary sewer, UPVC Class V 3inch Piping,
Flexible Coupling 41ea
m
100.00
86.00
8,600.00
Sub Total Drainage & Sewer Pipe: m
330.00
156.48
51,640.00
m2
10,273.38
81.00
832,143.78
m2
789.59
81.00
63,956.79
m2
3,525.08
81.00
285,531.48
Sub Total Formwork: m2
14,588.05
81.00
1,181,632.05
m3
2,202.19
610.00
1,343,335.90
m3
156.96
440.00
69,062.40
m3
754.64
610.00
460,330.40
10300
10310
10320
10330
10340
10350
Drainage Structures
Cast in Place Concrete Culverts
Formwork
Forming Work,Ply Wood,3 Times
- Structure 1
Forming Work,Ply Wood,3 Times
- Structure 2
Forming Work,Ply Wood,3 Times
- Structure 3
Concrete
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
10360
10370
10380
10390
10400
10410
10420
10430
10440
10450
Description
Unit
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Quantity
Rate
Amount
m3
26.40
440.00
11,616.00
m3
470.83
610.00
287,206.30
m3
25.53
440.00
11,233.20
Sub Total Concrete: m3
3,636.55
600.23
2,182,784.20
ton
32.30
6,770.00
218,671.00
ton
150.14
6,770.00
1,016,447.80
ton
15.14
6,770.00
102,497.80
ton
53.33
6,770.00
361,044.10
ton
0.38
6,770.00
2,572.60
ton
42.53
6,770.00
287,928.10
Sub Total Reinforcing Steel: ton
293.82
6,770.00
1,989,161.40
m2
2,300.00
62.00
142,600.00
Sub Total Wiremesh: LS
1.00
142,600.00
142,600.00
3,344.80
37.00
123,757.60
Reinforcing Steel
Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D22 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Wiremesh
Wire Mesh,F6x150x150
Epoxy Coated
10460
Concrete Accessories
Water Stop,B=200
m
10470
Mortar Grouting,Non Shrinkage
m3
3.60
7,040.00
25,351.04
10480
Mortar Grouting,Epoxy Grout,Water Proofing
m3
17.02
24,430.00
415,798.60
Sub Total Concrete Accessories: LS
1.00
564,907.24
564,907.24
Sub Total Cast in Place Concrete Culverts: m3
3,637.00
1,666.51
6,061,084.89
Structural Steel
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
10490
10500
10510
10520
10530
10540
10550
10560
10570
10580
10590
10600
10610
10620
10630
10640
10650
10660
10670
10680
10690
10700
Description
Steel Item,Misc.Steel Fabrication,Steel
with HDG
Steel Item,Insert Plate,Steel
with HDG
Steel Item 1,Misc.Steel Fabrication,Steel
with HDG
Steel Item 2,Misc.Steel Fabrication,Steel
with HDG
Steel Item 3,Misc.Steel Fabrication,Steel
with HDG
Unit
Quantity
Rate
Amount
ton
5.60
13,310.00
74,536.00
ton
24.13
13,310.00
321,170.30
ton
7.01
13,310.00
93,303.10
ton
0.02
13,310.00
266.20
ton
12.09
13,310.00
160,917.90
Sub Total Structural Steel: ton
48.85
13,310.00
650,193.50
m2
694.00
450.00
312,300.00
m2
59.00
820.00
48,380.00
m2
55.28
450.00
24,876.00
m2
700.00
820.00
574,000.00
Sub Total Steel Gratings: m2
1,508.28
636.19
959,556.00
Nos
109.00
1,690.00
184,210.00
EA
294.00
19.00
5,586.00
Sub Total Manhole Accessories: LS
1.00
189,796.00
189,796.00
m2
806.40
55.00
44,352.00
m2
10,595.00
55.00
582,725.00
m2
5,400.25
4.86
26,245.22
m2
2,337.50
53.00
123,887.50
m2
466.00
4.86
2,264.76
m2
514.00
55.00
28,270.00
m2
30.00
130.00
3,900.00
m2
30.00
54.00
1,620.00
m2
1,796.49
54.00
97,010.46
m2
555.52
4.65
2,583.17
m2
1,449.77
52.00
75,388.04
Steel Gratings
Grating,I-32
with HDG
Grating,I-50
with HDG
Grating,I-32
with HDG
Grating,I-50
with HDG
Manhole Accessories
Man Hole,Cover
Cast Iron Cover,D=600,Heavy Duty with Lock
Pipe Sleeve,Sleeeve Pipe,Installation Only
Waterproofinjg
Proofing,Epoxy Waterproofing
Coal Tar Epoxy Coating, THK=1000 Microns
Proofing,Epoxy Waterproofing, T=0.4 mm
Coal Tar Epoxy Coating, THK=400 Microns
(200 x 2 coats)
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Epoxy Waterproofing, T=0.4 mm
Coal Tar Epoxy Coating, THK=400 Microns
(200 x 2 coats)
Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)
Proofing,Epoxy Waterproofing
Coal Tar Epoxy Coating, THK=1000 Microns
Proofing,Epoxy Waterproofing, T=0.5 mm
Coal Tar Epoxy Coating, THK=500 Microns
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
Description
Unit
Quantity
Rate
Amount
Sub Total Waterproofinjg: LS
1.00
988,246.14
988,246.14
Sub Total Drainage Structures: LS
1.00
8,848,876.53
8,848,876.53
Sub Total Sewer/Drainage: LS
1.00
12,655,387.58
12,655,387.58
m3
4,300.00
40.00
172,000.00
m3
4,300.00
11.00
47,300.00
Sub Total Grading: m3
4,300.00
51.00
219,300.00
m2
61,400.00
0.06
3,684.00
Sub Total Subgrade Preparation: m2
61,400.00
0.06
3,684.00
m2
21,580.00
0.92
19,853.60
m2
21,580.00
9.89
213,426.20
10760
Base Course,Crused Stone ( Lower than 8 cm ),T=20CM
Well graded Aggregate, 97% compaction ratio, CBR>70%
Gravel Paving,Crused Stone ( Lower than 8 cm ),T=10CM
m2
22,426.00
34.00
762,484.00
10770
Subbase Course,Crused Stone ( Lower than 8 cm ),T=30CM
m2
17,690.90
34.00
601,490.60
Sub Total Granular Base Coarse: m2
83,276.90
19.18
1,597,254.40
m2
21,580.00
22.00
474,760.00
m2
21,580.00
22.00
474,760.00
m2
21,580.00
3.38
72,940.40
m2
21,580.00
3.38
72,940.40
m2
17,690.90
0.87
15,391.08
m2
636.00
100.00
63,600.00
Sub Total Asphalt Paving: m2
21,580.00
54.42
1,174,391.88
m2
218.92
73.00
15,981.16
10710
10720
10730
10740
10750
Road/Paving
Grading
Excavation,Normal Soil,Back Hoe
including surfacing and compaction 95 %, excavation
depth=0~-2meters
Disposal,Machine,0-10km ( Distance )
Subgrade Preparation
Surfacing and Compaction
Granular Base Coarse
Subbase Course,Crused Stone ( Lower than 150 mm
),T=80CM
10820
Asphalt Paving
Wearing Course,#78,T=5 CM
maximum aggregate size = 50 mm, detailed specification SES
C04-S02
Binder Course,#467,T=5CM
Maximum aggregate size = 3/4 inch, Detailed specification
SES C04-S02
Tack Coating
detailed specification SES C04-S02
Prime Coating
detailed specification SES C04-S02
Surfacing and Cleaning
10830
Lane Marking, Normal Temperature Type, Manual Type
10780
10790
10800
10810
10840
Concrete Flatwork
Forming Work,Ply Wood,3 Times
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
10850
10860
10870
10880
Description
Unit
2,437.89
510.00
1,243,323.90
m
m
7,480.09
3,552.62
17.00
47.00
127,161.53
166,973.14
Isolation Joint, Thk=12mm,Bituminous Joint Filler with Joint
Sealant
m
6,870.00
37.00
254,190.00
1.00
1,807,629.73
1,807,629.73
m
86.40
1,320.00
114,048.00
Sub Total Guiderail: m
86.40
1,320.00
114,048.00
m2
30,350.00
28.00
849,800.00
m2
17,690.90
8.67
153,380.10
m2
m2
108.00
100.00
180.00
170.00
19,440.00
17,000.00
Sub Total Paving Accessories: LS
1.00
1,039,620.10
1,039,620.10
50.00
2,260.00
113,000.00
Sub Total Signage: LS
1.00
113,000.00
113,000.00
Sub Total Road/Paving: m2
44,006.00
137.91
6,068,928.12
m3
1,258.25
150.00
188,737.50
m3
883.20
54.00
47,692.80
m3
375.06
11.00
4,125.66
Excavation,Normal Soil,Back Hoe
including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )
m3
218.00
270.00
58,860.00
m3
135.00
54.00
7,290.00
m3
84.00
11.00
924.00
Excavation,Normal Soil,Back Hoe
including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )
m3
8,696.00
56.00
486,976.00
m3
4,471.50
54.00
241,461.00
m3
2,815.00
11.00
30,965.00
Guiderail
Guard Rail Installation
10910
10920
10930
Acid Proofing Tile
Alkali Proofing Tile
10940
10950
10960
10970
10980
10990
11000
11010
11020
11030
Amount
m3
Paving Accessories
Wire Mesh,F6x150x150
Epoxy Coated
PE Film,T=0.25 mm
10900
Rate
Concrete Pouring,Remicon, D=25mm,Fc=300kg/cm2,Slump
12cm
Cement Type I with Minimum Cement Content 360kg/m3,
Max. W/C Ratio 0.40, pouring height=-3~+3meters
Contraction Joint, SES-C01-F01-03, with Sealant
Expansion Joint, SES-C01-F01-03, with Sealant and Dowel
Bar
Sub Total Concrete Flatwork: LS
10890
Quantity
Signage
Traffic Sign Work,Guide Sign Pole
Safety & Information Board, Height 2.8m, Board Size
600x600mm
Equipment Foundations
Structural Excavation & Backfill
Excavation,Normal Soil,Back Hoe
including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )
Nos
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
11040
Description
Unit
Quantity
Rate
Amount
Excavation,Normal Soil,Back Hoe
including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )
m3
2,526.00
56.00
141,456.00
m3
9,091.00
54.00
490,914.00
m3
498.00
11.00
5,478.00
Excavation,Normal Soil,Back Hoe
including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )
m3
435.56
140.00
60,978.40
m3
384.79
54.00
20,778.66
m3
50.77
11.00
558.47
m3
3,722.96
57.00
212,208.72
m3
1,969.81
54.00
106,369.74
11120
Excavation,Normal Soil,Back Hoe
including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )
m3
1,754.16
11.00
19,295.76
11130
Sand filling and Compaction,Machine,T=15cm ( Compacted ) m3
1,431.54
110.00
157,469.40
11140
Oily Sand,Machine,T=10cm (Compacted), Asphalt Concrete m3
with Prime Coat
Gravel filling and Compaction,Machine,T=15cm ( Compacted m3
)
155.46
120.00
18,655.20
14.40
86.00
1,238.40
m3
2,098.20
65.00
136,383.00
m3
1,302.31
54.00
70,324.74
m3
793.90
11.00
8,732.90
Sub Total Structural Excavation & Backfill: LS
1.00
2,517,873.35
2,517,873.35
11050
11060
11070
11080
11090
11100
11110
11150
11160
11170
11180
Excavation,Normal Soil,Back Hoe
including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )
11190
Cast in Situ Concrete
Formwork
Forming Work,Ply Wood,3 Times
m2
487.27
81.00
39,468.87
11200
Forming Work,Ply Wood,3 Times
m2
135.00
81.00
10,935.00
11210
Forming Work,Ply Wood,3 Times
m2
2,273.00
81.00
184,113.00
11220
Forming Work,Ply Wood,3 Times
m2
1,449.00
81.00
117,369.00
11230
Forming Work,Ply Wood,3 Times
m2
106.89
82.00
8,764.98
11240
Forming Work,Ply Wood,3 Times
m2
2,221.08
81.00
179,907.48
11250
Forming Work,Ply Wood,3 Times
m2
1,349.34
81.00
109,296.54
Sub Total Formwork: m2
8,021.58
81.01
649,854.87
Concrete
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
11260
11270
11280
11290
11300
11310
11320
11330
11340
11350
11360
11370
11380
11390
Description
Unit
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Reinforcing Steel
Quantity
Rate
Amount
m3
439.50
610.00
268,095.00
m3
47.37
440.00
20,842.80
m3
1,568.00
610.00
956,480.00
m3
101.00
610.00
61,610.00
m3
2.20
440.00
968.00
m3
15.66
440.00
6,890.40
m3
25.62
440.00
11,272.80
m3
609.10
610.00
371,551.00
m3
31.24
440.00
13,745.60
m3
51.24
610.00
31,256.40
m3
3.98
440.00
1,751.20
m3
1,837.12
610.00
1,120,643.20
m3
101.01
430.00
43,434.30
m3
848.52
610.00
517,597.20
Sub Total Concrete: m3
5,681.56
603.03
3,426,137.90
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
11400
11410
11420
11430
11440
11450
11460
11470
11480
11490
11500
11510
11520
11530
11540
Description
Re-bar,Deformed Bar Normal Bending,SD40,D10 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D10 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D19 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D22 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D25 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D10 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Unit
Quantity
Rate
Amount
ton
0.34
6,770.00
2,301.80
ton
2.02
6,770.00
13,675.40
ton
8.63
6,770.00
58,425.10
ton
4.04
6,770.00
27,350.80
ton
7.80
6,770.00
52,806.00
ton
0.40
6,770.00
2,708.00
ton
0.79
6,770.00
5,348.30
ton
73.70
6,770.00
498,949.00
ton
1.90
6,770.00
12,863.00
ton
9.40
6,770.00
63,638.00
ton
33.00
6,770.00
223,410.00
ton
42.63
6,770.00
288,605.10
ton
0.06
6,770.00
406.20
ton
0.45
6,770.00
3,046.50
ton
2.61
6,770.00
17,669.70
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
11550
11560
11570
11580
11590
11600
11610
11620
11630
11640
11650
11660
11670
11680
Description
Re-bar,Deformed Bar Normal Bending,SD40,D19 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D25 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D10 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D19 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D22 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D25 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D19 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D22 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Unit
Quantity
Rate
Amount
ton
0.26
6,770.00
1,760.20
ton
0.37
6,850.00
2,507.10
ton
1.68
6,790.00
11,380.04
ton
14.60
6,770.00
98,814.92
ton
53.63
6,770.00
363,075.10
ton
9.10
6,770.00
61,607.00
ton
53.00
6,770.00
358,810.00
ton
80.76
6,770.00
546,745.20
ton
4.90
6,770.00
33,173.00
ton
43.25
6,770.00
292,802.50
ton
7.86
6,770.00
53,212.20
ton
7.72
6,770.00
52,264.40
Sub Total Reinforcing Steel: ton
464.89
6,770.14
3,147,354.56
Sub Total Cast in Situ Concrete: m3
5,682.00
1,271.27
7,223,347.33
Nos
124.00
4.28
530.72
Nos
28.00
110.00
3,080.00
Structural Steel
Anchor Bolts
Anchor Bolt Installation,M24
Installation Only
Anchor Box Installation,150x150x450(WxLxD)(mm)
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
11690
Description
Unit
Quantity
Rate
Amount
Nos
20.00
3.34
66.80
Nos
106.00
4.28
453.68
Nos
80.00
4.55
364.00
Nos
20.00
6.42
128.40
Nos
48.00
8.03
385.44
11740
Anchor Bolt Installation,M16
Installation Only
Anchor Bolt Installation,M24
Installation Only
Anchor Bolt Installation,M32
Installation Only
Anchor Bolt Installation,M42
Installation Only
Anchor Bolt Installation,M48
Installation Only
Anchor Box Installation,150x150x600(WxLxD)(mm)
Nos
16.00
130.00
2,080.00
11750
Anchor Box Installation,150x150x900(WxLxD)(mm)
Nos
20.00
1,150.00
23,000.00
11760
Anchor Box Installation,150x150x450(WxLxD)(mm)
Nos
70.00
110.00
7,700.00
11770
Nos
24.00
3.34
80.16
Nos
80.00
4.28
342.40
11790
Anchor Bolt Installation,M16
Installation Only
Anchor Bolt Installation,M24
Installation Only
Anchor Box Installation,150x150x450(WxLxD)(mm)
Nos
8.00
130.00
1,040.00
11800
Anchor Box Installation,150x150x900(WxLxD)(mm)
Nos
12.00
180.00
2,160.00
11810
Nos
44.00
4.28
188.32
Nos
36.00
4.55
163.80
11830
Anchor Bolt Installation,M24
Installation Only
Anchor Bolt Installation,M32
Installation Only
Anchor Box Installation,150x150x600(WxLxD)(mm)
Nos
244.00
130.00
31,720.00
11840
Anchor Box Installation,150x150x900(WxLxD)(mm)
Nos
294.00
160.00
47,040.00
11850
Nos
85.00
4.71
400.35
11860
Anchor Bolt Installation,M24
Installation Only
Anchor Box Installation,150x150x600(WxLxD)(mm)
Nos
16.00
130.00
2,080.00
11870
Anchor Box Installation,150x150x450(WxLxD)(mm)
Nos
418.00
110.00
45,980.00
Sub Total Anchor Bolts: Nos
1,793.00
94.25
168,984.07
ton
0.03
13,310.00
399.30
ton
0.64
13,310.00
8,518.40
ton
2.80
13,310.00
37,268.00
ton
0.40
13,310.00
5,324.00
ton
7.00
13,310.00
93,170.00
Sub Total Steel: LS
1.00
144,679.70
144,679.70
Sub Total Structural Steel: LS
1.00
313,663.77
313,663.77
11700
11710
11720
11730
11780
11820
11880
11890
11900
11910
11920
Steel
Steel Item,Misc.Steel Fabrication,Steel
with HDG
Steel Item,Misc.Steel Fabrication,Steel
with HDG
Steel Item,Misc.Steel Fabrication,Steel
Steel Item,Misc.Steel Fabrication,Steel
with HDG
Steel Item,Insert Plate,Steel
with HDG
Waterproofing
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
11930
11940
11950
11960
11970
11980
11990
12000
12010
12020
12030
12040
12050
12060
12070
12080
12090
12100
12110
12120
12130
12140
12150
12160
Description
Proofing,Epoxy Waterproofing, T=0.4 mm
Coal Tar Epoxy Coating, THK=400 Microns
(200 x 2 coats)
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)
Proofing,Epoxy Waterproofing, T=0.4 mm
Coal Tar Epoxy Coating, THK=400 Microns
(200 x 2 coats)
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)
Proofing,Protection Board
3.5 mm bitumen impregnated fibreboard or 12 mm thickness
bitumen impregnated soft board
Proofing,Epoxy Waterproofing, T=0.5 mm
Coal Tar Epoxy Coating, THK=500 Microns
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Protection Board
3.5 mm bitumen impregnated fibreboard or 12 mm thickness
bitumen impregnated soft board
Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)
Proofing,Epoxy Waterproofing, T=0.5 mm
Coal Tar Epoxy Coating, THK=500 Microns
Proofing,Epoxy Waterproofing, T=0.4 mm
Coal Tar Epoxy Coating, THK=400 Microns
(200 x 2coats)
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)
Proofing,Epoxy Waterproofing, T=0.5 mm
Coal Tar Epoxy Coating, THK=500 Microns
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)
Proofing,HDPE Film
THK = 750 microns
Proofing,Epoxy Waterproofing, T=0.4 mm
Coal Tar Epoxy Coating, THK=400 Microns
(200 x 2 coats)
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,HDPE Film
THK = 750 microns
Unit
Quantity
Rate
Amount
m2
758.68
54.00
40,968.72
m2
373.18
4.65
1,735.29
m2
162.44
52.00
8,446.88
m2
86.00
54.00
4,644.00
m2
24.00
4.65
111.60
m2
10.00
52.00
520.00
m2
163.24
30.00
4,897.20
m2
1,638.44
55.00
90,114.20
m2
1,266.00
4.86
6,152.76
m2
120.00
41.00
4,920.00
m2
289.78
52.00
15,068.56
m2
445.63
54.00
24,064.02
m2
1,604.20
55.00
88,231.00
m2
764.00
4.86
3,713.04
m2
335.00
53.00
17,755.00
m2
294.45
4.65
1,369.19
m2
88.43
52.00
4,598.36
m2
135.38
54.00
7,310.52
m2
63.12
4.65
293.51
m2
27.80
52.00
1,445.60
m2
520.00
35.00
18,200.00
m2
1,163.00
54.00
62,802.00
m2
862.00
4.65
4,008.30
m2
927.00
35.00
32,445.00
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
12170
Description
Unit
Rate
Amount
m2
211.00
52.00
10,972.00
Sub Total Waterproofing: m2
12,332.77
36.88
454,786.75
12180
Mortar Grouting
Mortar Grouting,Non Shrinkage
m3
5.38
7,040.00
37,875.20
12190
Mortar Grouting,Non Shrinkage
m3
26.50
6,820.00
180,730.00
12200
m3
3.10
24,440.00
75,764.00
12210
Mortar Grouting,Epoxy Grout
minimum compressive strength at 7 days = 96 MPa
Mortar Grouting,Non Shrinkage
m3
6.24
7,050.00
43,992.00
12220
Mortar Grouting,Non Shrinkage
m3
0.11
7,050.00
775.50
12230
Mortar Grouting,Non Shrinkage
m3
16.62
6,810.00
113,182.20
Sub Total Mortar Grouting: m3
57.95
7,805.33
452,318.90
Sub Total Equipment Foundations: m3
5,650.00
1,940.18
10,961,990.10
m3
5,466.71
180.00
984,007.80
m3
2,541.25
54.00
137,227.50
m3
2,926.06
11.00
32,186.66
m3
3,088.38
170.00
525,024.60
m3
1,645.81
54.00
88,873.74
m3
1,442.57
11.00
15,868.27
Sub Total Structural Excavation & Backfill: LS
1.00
1,783,188.57
1,783,188.57
12240
12250
12260
12270
12280
12290
Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)
Quantity
Pit/Dike/Cooling Tower
Structural Excavation & Backfill
Excavation,Normal Soil,Back Hoe
including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )
Excavation,Normal Soil,Back Hoe
including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )
12300
Cast in Situ Concrete
Formwork
Forming Work,Ply Wood,3 Times
m2
2,234.09
81.00
180,961.29
12310
Forming Work,Ply Wood,3 Times
m2
3,409.80
81.00
276,193.80
Sub Total Formwork: m2
5,643.89
81.00
457,155.09
973.37
590.00
574,288.30
12320
Concrete
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
m3
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
12330
12340
12350
12360
12370
12380
12390
12400
12410
12420
12430
12440
Description
Unit
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Quantity
Rate
Amount
m3
38.20
440.00
16,808.00
m3
1,160.16
610.00
707,697.60
m3
63.76
440.00
28,054.40
Sub Total Concrete: m3
2,235.49
593.54
1,326,848.30
ton
1.25
6,770.00
8,462.50
ton
1.22
6,770.00
8,259.40
ton
72.10
6,770.00
488,117.00
ton
15.95
6,770.00
107,981.50
ton
9.50
6,770.00
64,315.00
ton
6.30
6,770.00
42,651.00
ton
21.76
6,770.00
147,315.20
ton
58.49
6,770.00
395,977.30
ton
20.21
6,770.00
136,821.70
Sub Total Reinforcing Steel: ton
206.78
6,770.00
1,399,900.60
Reinforcing Steel
Re-bar,Deformed Bar Normal Bending,SD40,D10 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D19 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D22 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D25 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D19 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
12450
Concrete Accessories
Water Stop,B=200
m
248.00
37.00
9,176.00
12460
Expansion Joint, Gelacreyl Superflex AR
m
115.00
42.00
4,830.00
Sub Total Concrete Accessories: m
363.00
38.58
14,006.00
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
Description
Unit
Sub Total Cast in Situ Concrete: LS
12470
12480
12490
12500
12510
12520
12530
12540
12550
12560
12570
12580
12590
12600
Rate
Amount
1.00
3,197,909.99
3,197,909.99
ton
1.37
13,310.00
18,234.70
ton
2.73
13,310.00
36,336.30
ton
5.65
13,310.00
75,201.50
Sub Total Steel: ton
9.75
13,310.00
129,772.50
m2
22.11
450.00
9,949.50
m
201.00
15,750.00
3,165,750.00
Sub Total Misc Metal: LS
1.00
3,175,699.50
3,175,699.50
Sub Total Structural Steel: LS
1.00
3,305,472.00
3,305,472.00
m2
1,425.62
55.00
78,409.10
m2
1,304.69
55.00
71,757.95
m2
828.72
4.86
4,027.58
m2
155.30
53.00
8,230.90
m2
785.00
41.00
32,185.00
m2
3,959.20
55.00
217,756.00
m2
1,912.80
4.86
9,296.21
m2
1,044.60
53.00
55,363.80
Sub Total Waterproofing: m2
11,415.93
41.79
477,026.54
m3
1.43
6,820.00
9,752.60
Sub Total Mortar Grouting: LS
1.00
9,752.60
9,752.60
Sub Total Pit/Dike/Cooling Tower: m3
2,172.00
4,039.30
8,773,349.70
Structural Steel
Steel
Steel Item,Misc.Steel Fabrication,Steel
with HDG
Steel Item,Insert Plate,Steel
with HDG
Steel Item,Checked Plate
with HDG
Misc Metal
Grating,I-32
with HDG
Hand Rail,Steel,H=1.2m
Hot-Dip-Galvanized
Pipe Type
Waterproofing
Proofing,Epoxy Waterproofing
Coal Tar Epoxy Coating, THK=1000 Microns
Proofing,Epoxy Waterproofing, T=0.4 mm
Coal Tar Epoxy Coating, THK=400 Microns
(200 x 2coats)
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)
Proofing,Protection Board
3.5 mm bitumen impregnated fibreboard or 12 mm thickness
bitumen impregnated soft board
Proofing,Epoxy Waterproofing, T=0.4 mm
Coal Tar Epoxy Coating, THK=400 Microns
(200 x 2coats)
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)
Mortar Grouting
Mortar Grouting,Non Shrinkage
Cable Trench/Duct Bank
Quantity
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
Description
Unit
Quantity
Rate
Amount
12630
Structural Excavation & Backfill
Excavation,Normal Soil,Back Hoe
including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )
m3
6,590.70
11.00
72,497.70
12640
Sand filling and Compaction,Machine,T=15cm ( Compacted ) m3
10,638.84
110.00
1,170,272.40
12650
Excavation,Normal Soil,Back Hoe
including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )
m3
2,544.00
150.00
381,600.00
m3
1,957.40
54.00
105,699.60
m3
588.10
11.00
6,469.10
m3
508.00
130.00
66,040.00
m3
382.00
54.00
20,628.00
12700
Excavation,Normal Soil,Back Hoe
including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )
m3
145.00
11.00
1,595.00
12710
Crushed Stone Spreading with compaction,Machine
m3
134.00
83.00
11,122.00
Sub Total Structural Excavation & Backfill: LS
1.00
3,427,520.72
3,427,520.72
m
8,607.40
0.00
0.00
4,701.00
237.00
48.00
48.00
225,648.00
11,376.00
12610
12620
12660
12670
12680
12690
12720
Conduit
Warning Tape
m3
21,313.57
50.00
1,065,678.50
m3
9,739.23
54.00
525,918.42
12730
12740
HI PVC Conduit, SCH. 40, Size : 6 Inches
HI PVC CONDUIT FOR CONCRETE DUCT BANK.
SCHEDULE 40
M
M
12750
PVC CONDUIT SPACER
SIZE : 8"
UNIT : EA
SET
475.00
34.00
16,150.00
12760
PVC CONDUIT SPACER
SIZE : 6"
UNIT : EA
SET
5,234.00
34.00
177,956.00
Sub Total Conduit: LS
1.00
431,130.00
431,130.00
12770
Cast in Situ Concrete
Formwork
Forming Work,Ply Wood,3 Times
m2
5,040.87
81.00
408,310.47
12780
Forming Work,Ply Wood,3 Times
m2
477.45
81.00
38,673.45
12790
Forming Work,Ply Wood,3 Times
m2
492.00
81.00
39,852.00
Sub Total Formwork: m2
6,010.32
81.00
486,835.92
Concrete
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
12800
12810
12820
12830
12840
12850
12860
12870
12880
12890
12900
12910
12920
Description
Unit
Concrete Pouring,Remicon, D=25mm,Fc=300kg/cm2,Slump
12cm
Cement Type I with Minimum Cement Content 360kg/m3,
Max. W/C Ratio 0.40, pouring height=-3~+3meters
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete Pouring,Remicon, D=25mm,Fc=170kg/cm2,Slump
12cm
Red Color Powder Added 1kg/100kg cement, Cement Type I
with Minimum Cement Content 354kg/m3, Max. W/C Ratio
0.40, pouring height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Rate
Amount
m3
60.00
550.00
33,000.00
m3
1,174.44
590.00
692,919.60
m3
73.68
440.00
32,419.20
m3
395.22
440.00
173,896.80
m3
50.80
440.00
22,352.00
m3
149.00
590.00
87,910.00
m3
19.00
440.00
8,360.00
Sub Total Concrete: m3
1,922.14
546.71
1,050,857.60
ton
6.00
6,770.00
40,620.00
ton
117.45
6,770.00
795,136.50
ton
23.00
6,770.00
155,710.00
ton
0.48
6,770.00
3,249.60
ton
23.00
6,770.00
155,710.00
Sub Total Reinforcing Steel: ton
169.93
6,770.00
1,150,426.10
117.00
37.00
4,329.00
1.00
4,329.00
4,329.00
Reinforcing Steel
Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Concrete Accessories
Water Stop,B=200
Quantity
m
Sub Total Concrete Accessories: LS
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
Description
Unit
Sub Total Cast in Situ Concrete: LS
12930
12940
12950
12960
12970
12980
12990
13000
13010
13020
13030
13040
Quantity
Rate
Amount
1.00
2,692,448.62
2,692,448.62
m2
1,808.92
4.86
8,791.35
m2
4,696.13
55.00
258,287.15
m2
1,061.25
4.86
5,157.68
m2
1,401.20
54.00
75,664.80
m2
389.00
54.00
21,006.00
m2
170.00
55.00
9,350.00
m2
104.00
66.00
6,864.00
Sub Total Waterproofing: m2
9,630.50
39.99
385,120.98
ton
0.06
13,310.00
798.60
ton
0.01
13,310.00
133.10
Nos
13.00
1,810.00
23,530.00
Sub Total Misc Metal: LS
1.00
24,461.70
24,461.70
m2
7,575.74
47.00
356,059.78
m2
56.97
3,830.00
218,195.10
Sub Total Brick Masonry: m2
7,632.71
75.24
574,254.88
Sub Total Cable Trench/Duct Bank: m3
748.00
10,073.45
7,534,936.90
m3
306.00
18.00
5,508.00
m3
270.00
54.00
14,580.00
m3
36.00
11.00
396.00
m3
24.00
18.00
432.00
m3
20.00
53.00
1,060.00
Waterproofing
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Epoxy Waterproofing, T=0.4 mm
Coal Tar Epoxy Coating, THK=400 Microns
(200 x 2 coats)
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Epoxy Waterproofing, T=0.4 mm
Coal Tar Epoxy Coating, THK=400 Microns
(200 x 2 coats)
Proofing,Epoxy Waterproofing, T=0.4 mm
Coal Tar Epoxy Coating, THK=400 Microns
(200 x 2 coats)
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Polyurethane
Min. THK=500 microns, Water Proof (250 x 2 coats)
Misc Metal
Steel Item,Misc.Steel Fabrication,Steel
with HDG
Steel Item,Misc.Steel Fabrication,Steel
with HDG
Man Hole,Cover
Cast Iron Cover
Brick Masonry
Laying Brick,Both Side
Red Concrete Tile, 305x305x50
Laying Brick,Both Side
Fence/Gate & Miscellaneous Works
Line item no. 1075 is a Subcontract Work by
13050
13060
13070
13080
13090
Structural Excavation & Backfill
Excavation,Normal Soil,Back Hoe
including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )
Excavation,Normal Soil,Back Hoe
including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
Description
Unit
Quantity
Rate
Amount
13100
Disposal,Machine,0-10km ( Distance )
m3
4.00
11.00
44.00
13110
EXCAVATION (GRAVEL & SOIL)
Including surfacing & compacyion 95%
BACKFILLING & COMPACTION
T=150
DISPOSAL (10KM)
Unfactored soil, Disposal area(10km far)
GRAVEL COMPACT.
Aggregate base course,THK=150mm
m3
30,535.78
18.00
549,644.04
m3
26,947.97
54.00
1,455,190.38
m3
3,527.79
11.00
38,805.69
m3
92.50
94.00
8,695.00
Sub Total Structural Excavation & Backfill: LS
1.00
2,074,355.11
2,074,355.11
13120
13130
13140
13150
Cast in Situ Concrete
Formwork
Forming Work,Ply Wood,3 Times
m2
270.00
81.00
21,870.00
13160
Forming Work,Ply Wood,3 Times
m2
20.00
86.00
1,720.00
13170
FORM (PLYWOOD)
for U/G concrete
m2
11,345.98
81.00
919,024.38
Sub Total Formwork: m2
11,635.98
81.01
942,614.38
m3
33.00
610.00
20,130.00
m3
3.90
440.00
1,716.00
m3
2.60
610.00
1,586.00
m3
0.30
440.00
132.00
m3
234.68
440.00
103,259.20
m3
2,878.91
620.00
1,784,924.20
m3
308.60
8,580.00
2,647,788.00
Sub Total Concrete: m3
3,461.99
1,317.03
4,559,535.40
7.20
6,770.00
48,744.00
13180
13190
13200
13210
13220
13230
13240
13250
Concrete
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
CONCRETE 1
For U/G Plain Con'c.,ASTM 17MPa,ASTM C150 TYPE V
minimum Cement Content 275kg/cm3 Max W/C Ratio 0.45
CONCRETE 3
For U/G RC,ASTM 35MPa,ASTM C150 TYPE I + Micro silica
6% Minimum Cement Content 364kg/cm3 Max W/C Ratio 0.4,
Caicium Nitrite shall be added(min. 10 liters/m3 for 30%
solution)
CONCRETE ENCASEMENT
Included FORM & MISC. WORK & Material
Reinforcing Steel
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
ton
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
13260
13270
13280
13290
13300
13310
13320
13330
13340
13350
13360
13370
13380
13390
13400
13410
13420
13430
Description
Unit
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
RE-BAR 2
Dia.10~32,ASTM A615 Grade 60, Fusion bonded epoxy
coating,thick.180~300micron
Quantity
Rate
Amount
ton
0.60
6,770.00
4,062.00
ton
326.56
6,770.00
2,210,811.20
Sub Total Reinforcing Steel: ton
334.36
6,770.00
2,263,617.20
Sub Total Cast in Situ Concrete: m3
3,462.00
2,243.14
7,765,766.98
Ton
13.00
13,310.00
173,030.00
EA
200.00
2.99
598.00
m2
57.02
53.00
3,022.06
Sub Total Misc Metal: LS
1.00
176,650.06
176,650.06
m2
216.00
54.00
11,664.00
m2
78.00
4.86
379.08
m2
16.80
54.00
907.20
m2
6.00
55.00
330.00
m2
16.80
53.00
890.40
m2
4,699.61
110.00
516,957.10
m2
m2
m2
537.35
630.02
12,070.75
63.00
66.00
52.00
33,853.05
41,581.32
627,679.00
Sub Total Waterproofing: m2
18,271.33
67.55
1,234,241.15
EA
2,492.00
98.00
244,216.00
EA
290.00
36.00
10,440.00
Sub Total Anchor Bolts: ea
2,782.00
91.54
254,656.00
400.00
480.00
192,000.00
1,599.00
460.00
735,540.00
1,999.00
464.00
927,540.00
Misc Metal
Metal Work/FAB. & Installation of MISC. Steel for Embeded
steel w/hot-dip-galvanized
Nut welding for Fireproofing (for fixing WWF)
ASTM A 563
w.w.f 50x50x2.5mm
including material and installation work
Waterproofing
Proofing,Epoxy Waterproofing, T=0.4 mm
Coal Tar Epoxy Coating, THK=400 Microns
(200 x 2 coats)
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Epoxy Waterproofing, T=0.5 mm
Coal Tar Epoxy Coating, THK=500 Microns
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)
LAYING PE FILM
FLOOR.(0.25MMX1PLIES)
Chemical resistant
One Pack Moisture cured, 500micr(250mic X 2Plys)
400micro(200micro X 2Plys)
Fence
Anchor Bolts
ANCHOR BOLT
M25~M35, Hot Dip Galvanized
ANCHOR BOLT
hot dip galvarnize
Fencing
Fence,Bared Wire Fence
m
Post Space=2m,H=1.55m,Gavanised
Installation and Disposal of Site Perimeter Fence (Temporary m
Purpose)
Sub Total Fencing: m
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
13440
13450
13460
13470
13480
13490
13500
13510
20000
20010
20020
20030
20040
20050
20060
20070
Description
Unit
Gates
Gate,Gate with Rail
W=8m,H=2.5m, Auto Sliding
Gate for temporary fence, 6 m width
Quantity
Rate
Amount
EA
2.00
103,040.00
206,080.00
EA
5.00
6,050.00
30,250.00
Sub Total Gates: ea
7.00
33,761.43
236,330.00
EA
1,070.00
70.00
74,900.00
Sub Total Piles: ea
1.00
74,900.00
74,900.00
D/I
D/I
D/I
414.00
1,220.00
1,996.00
460.00
1,270.00
2,210.00
190,440.00
1,549,400.00
4,411,160.00
Sub Total Sockets: DI
3,630.00
1,694.49
6,151,000.00
m3
10.30
6,560.00
67,568.00
Sub Total Grout: LS
1.00
67,568.00
67,568.00
Sub Total Fence: LS
1.00
7,711,994.00
7,711,994.00
m2
7,515.72
370.00
2,780,816.40
Sub Total Fendolite: LS
1.00
2,780,816.40
2,780,816.40
Sub Total Fence/Gate & Miscellaneous Works: m3
3,458.00
6,287.98
21,743,823.70
Sub Total Civil Work: LS
1.00
71,803,366.09
71,803,366.09
m3
7,868.73
63.00
495,729.99
m3
3,429.75
71.00
243,512.25
m3
m3
6,073.74
1,403.14
71.00
11.00
431,235.54
15,434.54
m3
784.39
120.00
94,126.80
m3
1,148.85
61.00
70,079.85
m2
6,907.93
3.85
26,595.53
m2
927.08
12.00
11,124.96
Piles
PILE HEAD TREATMENT
Dia.=600mm, L=14m & 18m
Sockets
Non Internal Lined. Non External Lined. Socket (Fillet)Joint
Non Internal Lined. Non External Lined. Socket (Fillet)Joint
Non Internal Lined. Non External Lined. Socket (Fillet)Joint
Grout
GROUT
Min.35MPa(7 days) : ASTM C1107
Fendolite
FENDOLITE
For 2 hrs fire resistance,including w.w.f 50x50x2.5mm and
required(stud)bolt@300 & final urethane coating
Building Work
Sitework
EXCAVATION (GRAVEL & SOIL)
Including surfacing & compacyion 95%
BACKFILLING & COMPACTION
w/imported soil, 50mm sieve 100% passing, #200 sieve
0~20% passing, LL=Max.35, PL=Max.12
BACKFILLING & COMPACTION
DISPOSAL (10KM)
Unfactored soil, Disposal area(10km far)
GRAVEL COMPACT.
Aggregate base course,THK=150mm
SAND POURING & COMPACTION
Imported sand for sand bedding(w/Soil compaction
underneath the bedding
LAYING PE FILM
FLOOR.(0.25MMX1PLIES)
GRAVEL PAVING
THK=100
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
20080
20090
20100
20110
20120
20130
20140
20150
20160
20170
20180
20190
20200
Description
Unit
FENCE (P.V.C COATING)
Havy duty expanded metal mesh - Hot dip
galvanized(including Fence Door),removable, 8~12 gage
13mm Max.gap
Rate
Amount
923.95
730.00
674,483.50
Sub Total Sitework: LS
1.00
2,062,322.96
2,062,322.96
m2
12,326.21
110.00
1,355,883.10
m2
3,897.14
110.00
428,685.40
Sub Total Formwork: m2
16,223.35
110.00
1,784,568.50
m3
317.49
420.00
133,345.80
m3
1,703.25
690.00
1,175,242.50
m3
2,797.70
690.00
1,930,413.00
m3
1,703.25
31.00
52,800.75
m3
3,115.19
23.00
71,649.37
Sub Total Concrete: m3
9,636.88
349.02
3,363,451.42
ton
438.84
4,690.00
2,058,159.60
ton
153.24
6,470.00
991,462.80
ton
592.08
300.00
177,624.00
Sub Total Rebar: ton
1,184.16
2,725.35
3,227,246.40
Sub Total Reinforced Concrete: m3
9,637.00
869.07
8,375,266.32
m2
66.36
150.00
9,954.00
m2
647.52
180.00
116,553.60
Reinforced Concrete
Formwork
FORM (PLYWOOD)
above ground
FORM (PLYWOOD)
for U/G concrete
Concrete
CONCRETE 1
For U/G Plain Con'c.,ASTM 17MPa,ASTM C150 TYPE I
minimum Cement Content 275kg/cm3 Max W/C Ratio 0.45
CONCRETE 2
For A/G RC,ASTM 35MPa,ASTM C150 TYPE I + Micro silica
Fume 6% Minimum Cement Content 364kg/cm3 Max W/C
Ratio 0.4, Calcium Nitrite shall be added (min. 10 litres/m3 for
30% solution)
CONCRETE 3
For U/G RC,ASTM 35MPa,ASTM C150 TYPE I + Micro silica
6% Minimum Cement Content 364kg/cm3 Max W/C Ratio 0.4,
Caicium Nitrite shall be added(min. 10 liters/m3 for 30%
solution)
CON'C POURING ( PUMPCAR)
CON'C POURING (REMICON)
for U/G Concrete
Rebar
RE-BAR 1
Dia.10~32mm,ASTM A615/A615M Grade 60, Uncoated
RE-BAR 2
Dia.10~32,ASTM A615 Grade 60, Fusion bonded epoxy
coating,thick.180~300micron
RE-BAR MANUFACTURING AND FITTING
Masonry Work
CONCRETE BLOCK WORK
(ASTM C129,TYPE?),Including solid concrete fill,12mm
vertical reinforcement & tooled finish(Min. 2hr. fire rated)
including block mesh
CONCRETE BLOCK WORK
(ASTM C129,TYPE?),Including solid concrete fill,12mm
vertical reinforcement & tooled finish(Min. 2hr. fire rated)
including block mesh
m
Quantity
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
20210
20220
20230
20240
20250
20260
20270
20280
20290
Description
Unit
CONCRETE BLOCK WORK
(ASTM C129,TYPE?),Including solid concrete fill,12mm
vertical reinforcement & tooled finish(Min. 2hr. fire rated)
including block mesh
LINTEL FAB.& INSTALL
PC Lintel, 250 x 300mm
RE-BAR
Dia.10~32mm,ASTM A615/A615M Grade 60, Uncoated
GRANITE
T=50(W=450)
Rate
Amount
1,800.00
220.00
396,000.00
m
11.50
170.00
1,955.00
ton
17.94
6,770.00
121,453.80
m2
96.88
1,350.00
130,788.00
Sub Total Masonry Work: m2
2,414.00
321.75
776,704.40
EA
276.00
260.00
71,760.00
EA
396.00
260.00
102,960.00
Sub Total Anchor Bolts: ea
672.00
260.00
174,720.00
ton
10.35
15,510.00
160,528.50
ton
42.80
10,900.00
466,520.00
ton
42.80
9,060.00
387,768.00
Sub Total Miscellaneous Metal: ton
95.95
10,576.51
1,014,816.50
Metal Work
Anchor Bolts
ANCHOR BOLT
M25~M35, Hot Dip Galvanized
ANCHOR BOLT
hot dip galvarnize
Miscellaneous Metal
INSERT PLATE
ASTM A36
MISC. STEEL
hot dip galvanized material
FAB. & INSTALL. OF MISC. STEEL
m2
Quantity
20300
Metal Trim
AL. MOULDING
m
464.58
190.00
88,270.20
20310
SETTING NON-SLIP
m
115.63
170.00
19,657.10
Sub Total Metal Trim: m
580.21
186.01
107,927.30
m3
8.26
5,210.00
43,034.60
Sub Total Grouting: LS
1.00
43,034.60
43,034.60
56.00
23,937.47
1,340,498.40
1,376.70
180.00
247,806.00
1,460.50
180.00
262,890.00
20320
Grouting
GROUT
Min.35MPa(7 days) : ASTM C1107
Sub Total Metal Work: t
20330
20340
Thermal & Mosture Protection
Waterproofing
Waterproofing
SHEET WATERPROOFING
m2
300*300*50thl. Cement Leight Weight Tiles or
Gravel(50mm)+Alyaf 140Gm/m2 Seperation layer+insulation :
Thk=50 Extruded polystyrene board+Thk.=0.2 P.E
Film+Waterproof membrane : Torchseal membrane 4mm
Thk.(2Layer)+Asphalt primer+Steel t
SHEET-APPLIED MEMBRANE WATERPROOFING
PU Waterproof Membrane
m2
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
20350
20360
20370
20380
20390
20400
20410
20420
20430
20440
20450
20460
Description
WATERPROOF MORTAR
For wall,T=30
WATERPROOF MORTAR
Unit
Quantity
Rate
Amount
m2
257.92
81.00
20,891.52
m2
385.66
89.00
34,323.74
LIQUID WATERPROOFING
m2
For floor & Wall
WATERPROOF PROTECTION BOARD
m2
Waterproof gypsum board(For wall), Waterproof plywood 9t +
Waterproofed gypsumboard 9t
28.52
240.00
6,844.80
331.20
270.00
89,424.00
Sub Total Waterproofing: m2
3,840.50
172.42
662,180.06
m
700.00
51.00
35,700.00
m
255.30
60.00
15,318.00
m
40.25
130.00
5,232.50
Sub Total Joint Sealing: LS
1.00
56,250.50
56,250.50
Sub Total Waterproofing: m2
2,866.00
250.67
718,430.56
m2
1,926.25
23.00
44,303.75
Sub Total Insulation: LS
1.00
44,303.75
44,303.75
602.80
60.00
36,168.00
Sub Total Caulking & Sealing: LS
1.00
36,168.00
36,168.00
Sub Total Thermal & Mosture Protection: LS
1.00
798,902.31
798,902.31
9.00
3,980.00
35,820.00
27.00
5,420.00
146,340.00
7.00
5,960.00
41,720.00
Joint Sealing
CAULKING
Around Doors & Windows
CONTROL JOINT
WATER DRIP
Water stop
Insulation
ROCK WOOL
Wall (T=50)
Caulking & Sealing
EXPANSION JOINT/CAULKING
m
Doors & Windows
Steel Doors
STEEL DOOR
EA
(Size 0.8x2.1) Steel door on lightweight partition-Including
Alkyd painting/Accessories/Grouting for the frames(If
necessory), 10mmTHK.(ext.)/3mmTHK(int.) Cold rolled sheet
door leaf(Both sides) & 100x65x2 Door frame
STEEL DOOR
EA
(Size 1.0x2.2) Including Alkyd painting/Accessories/Grouting
for the frames(if necessary). 45mm thick, grade2, heavy dyty,
model2, seamless design 1.5mm thick colorolled steel sheet
faces
STEEL DOOR
EA
(Size 1.1x2.2) Including Alkyd painting/Accessories/Grouting
for the frames(if necessary). 45mm thick, grade2, heavy dyty,
model2, seamless design 1.5mm thick colorolled steel sheet
faces
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
Description
Unit
Quantity
Rate
Amount
20470
STEEL DOOR
(Size 1.8x2.4)Including Alkyd painting/Accessories/Grouting
for the frames(if necessary),45mm thick,grade?,Heavy
duty,model2,seamless design 1.5mm thick cold rolled steel
sheet faces
EA
2.00
10,750.00
21,500.00
20480
STEEL DOOR
EA
(Size 2.2x2.6) Including Alkyd painting/Accessories/Grouting
for the frames(if necessary). 45mm thick, grade2, heavy dyty,
model2, seamless design 1.5mm thick colorolled steel sheet
faces
STEEL DOOR
EA
(Size 2.7x3.1) Including Alkyd painting/Accessories/Grouting
for the frames(if necessary). 45mm thick, grade2, heavy dyty,
model2, seamless design 1.5mm thick colorolled steel sheet
faces
2.00
14,200.00
28,400.00
2.00
20,720.00
41,440.00
Sub Total Steel Doors: ea
49.00
6,433.06
315,220.00
EA
1.00
16,330.00
16,330.00
EA
1.00
21,360.00
21,360.00
EA
2.00
21,250.00
42,500.00
Sub Total Glass Doors: ea
4.00
20,047.50
80,190.00
EA
3.00
35,320.00
105,960.00
EA
1.00
129,320.00
129,320.00
Sub Total Special Doors: ea
4.00
58,820.00
235,280.00
EA
61.00
1,650.00
100,650.00
EA
61.00
1,040.00
63,440.00
EA
61.00
110.00
6,710.00
EA
18.00
16,970.00
305,460.00
7.00
1.00
880.00
1,650.00
6,160.00
1,650.00
1.00
484,070.00
484,070.00
EA
2.00
6,970.00
13,940.00
EA
13.00
46,930.00
610,090.00
20490
20500
20510
20520
20530
20540
20550
20560
20570
20580
20590
20600
Glass Doors
TEMPERED GLASS DOOR
1.8*2.1 W/ACCESSORIES
TEMPERED GLASS DOOR
2.0 X 2.4 W/ACCESORRIES
TEMPERED GLASS DOOR
1.8 X 2.7 W/ACCESSORIES
Special Doors
BLAST RESISTANT DOOR
(Size 1.0x2.2) Resisting against 2ton/m2(suction),including
door accessories
BLAST RESISTANT DOOR
(Size 2.0x2.4) Resisting against 2ton/m2(suction),including
door accessories
Door Hardware
LOCK SET
3 keys for each door, 3 keys for each building, 3 keys for each
group, 3 keys for master
DOOR CLOSER
FOR GENERAL USE K-1630, for Heavy duty steel door"
DOOR STOP
FOR OPERATED FRICTION DOOR HOLDER
PANIC DEVICE
Stainless steel
PIVOT HINGE
DOOR KNOB
SET
EA
Sub Total Door Hardware: LS
20610
20620
Windows
AL. WINDOW/FRAME
(Size 0.9x1.8) Including accessories Extruded aluminum
complying with ASTM B221 alloy 6063-T5
AL. WINDOW/FRAME
(Size 0.9x12) Including accessories Extruded aluminum
complying with ASTM B221 alloy 6063-T5
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
20630
20640
20650
20660
20670
20680
20690
20700
20710
20720
20730
20740
20750
20760
20770
20780
20790
20800
Description
Unit
AL. WINDOW/FRAME
(Size 1.2x0.6) Including accessories Extruded aluminum
complying with ASTM B221 alloy 6063-T5
AL. WINDOW/FRAME
(Size 0.9x12) Including accessories Extruded aluminum
complying with ASTM B221 alloy 6063-T5
AL. WINDOW/FRAME
(Size 1.2x1.5) Including accessories Extruded aluminum
complying with ASTM B221 alloy 6063-T5
AL. WINDOW/FRAME
(Size 1.2x3.0) Including accessories Extruded aluminum
complying with ASTM B221 alloy 6063-T5
AL. WINDOW/FRAME
(Size 2.0x1.5) Including accessories Extruded aluminum
complying with ASTM B221 alloy 6063-T5
AL. WINDOW/FRAME
(Size 0.9x3.0) Including accessories Extruded aluminum
complying with ASTM B221 alloy 6063-T5
AL. WINDOW/FRAME
(Size 1.2x4.0) Including accessories Extruded aluminum
complying with ASTM B221 alloy 6063-T5
AL. WINDOW/FRAME
(Size 0.9x6.0) Including accessories Extruded aluminum
complying with ASTM B221 alloy 6063-T5
Quantity
Rate
Amount
EA
1.00
3,160.00
3,160.00
EA
3.00
46,930.00
140,790.00
EA
3.00
7,730.00
23,190.00
EA
3.00
15,450.00
46,350.00
EA
2.00
13,000.00
26,000.00
EA
2.00
11,710.00
23,420.00
EA
3.00
20,610.00
61,830.00
EA
4.00
23,360.00
93,440.00
Sub Total Windows: ea
36.00
28,950.28
1,042,210.00
m2
223.97
1,550.00
347,153.50
m2
16.39
4,270.00
69,985.30
m2
3.04
2,080.00
6,323.20
m2
13.70
3,090.00
42,333.00
m2
8.19
880.00
7,207.20
Sub Total Glazing: m2
265.29
1,782.96
473,002.20
EA
1.00
14,790.00
14,790.00
EA
4.00
33,110.00
132,440.00
EA
1.00
33,110.00
33,110.00
EA
5.00
50,550.00
252,750.00
Sub Total Shutters: ea
11.00
39,371.82
433,090.00
EA
36.00
6,180.00
222,480.00
Sub Total Louvres: LS
1.00
222,480.00
222,480.00
Sub Total Doors & Windows: ea
140.00
23,468.16
3,285,542.20
Glazing
CLEAR GLASS
Type I,Class 1, Quality Q4
PAIR GLASS
Tempered Glass 6T + Air space 13T + Clear Glass 6T
WIRED GLASS
T=8
TEMPERED GLASS
DAMP PROOFING MIRROR
For toilet
Shutters
SHUTTER (ELECTRICAL)
(Size 1.8x2.5) Steel, Galv.
SHUTTER (ELECTRICAL)
3.0x3.5 (Steel Galvanized)
SHUTTER (ELECTRICAL)
3.0x3.5 (Steel Galvanized)
SHUTTER (ELECTRICAL)
(Size 4.0x4.0) Steel, Galv.
Louvres
LOUVER(AL)
(Size 1.2x1.2) Including accessories
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
20810
20820
20830
Description
Unit
Finishing
Flooring
CARPET TILE
Modular carpet tile
ACCESS FLOOR
Rubber tile finish(H=600) - Galvanized steel frame filled with
cement grout H=600mm,including accessories & anchor bolt
including the 2% of the spare material supply
BASE BOARD VINYL (H=100)
20850
20860
20870
20880
20890
20900
20910
20920
20930
20940
20950
20960
20970
20980
Rate
Amount
m2
43.70
90.00
3,933.00
m2
354.20
820.00
290,444.00
m
597.10
76.00
45,379.60
1.00
339,756.60
339,756.60
m2
2,196.50
96.00
210,864.00
m2
697.04
98.00
68,309.92
m2
3,686.50
88.00
324,412.00
m2
687.75
120.00
82,530.00
m2
360.87
100.00
36,087.00
m2
2,415.71
88.00
212,582.48
m2
24.15
75.00
1,811.25
m2
4,396.40
75.00
329,730.00
m2
279.45
77.00
21,517.65
m2
5,252.81
66.00
346,685.46
m2
769.43
81.00
62,323.83
m2
350.68
96.00
33,665.28
m
667.87
22.00
14,693.14
m
m
163.30
22.99
19.00
25.00
3,102.70
574.75
Sub Total Painting: m2
21,117.29
82.82
1,748,889.46
Sub Total Flooring: LS
20840
Quantity
Painting
ACRYLIC PAINT
On gypsum board - Fenomastic 04 flat emulsion
w/Fenomastic 20 semi Gloss emulsion finish coat Acrylic
emulsion Paint conforming to SASO SSA 470 for exterior
emulsion
ACRYLIC PAINT
DOOR & WINDOW, Polyamide, Oil Paint 2 Plies
ACRYLIC PAINT
Fenomastic 04 flat emulsion w/Fenomastic 20 semi Gloss
emulsion finish coat Acrylic emulsion Paint conforming to
SASO SSA 470 for exterior emulsion
ACRYLIC PAINT
On exposed Con'c celing - Fenomastic 04 flat emulsion 2
coats Acrylic emulsion Paint conforming to SASO SSA 470 for
exterior emulsion
ACRYLIC PAINT
Acrylic latex paint for exposed Conc.(WeatherProofing)
ACRYLIC PAINT
Block filler & Fenomastic 04 flat emulsion Acrylic emulsion
paint cinforming to SASO SSA 470 for Exterior emulsion
EPOXY COATING
T=0.2mm Dust-proofing
EPOXY COATING
T=0.2mm Dust-proofing
EPOXY COATING
T=0.2mm For dust-proofing, under access floor
Coaltar Epoxy,for U/G RC Surface,400micro (250mic.x 2plys)
URETHANE COATING
One Pack Moisture cured, 500micro 1 Ply
VINYL TILE
Resilient Vinyl Tile,300x300x3T,Homogenious type
BASE BOARD SELLAMIN PAINT
base board enamel paint(H=100)
ARCRLIC PAINT (H=100)
BASE BOARD EPOXY PAINT
20990
Tile
CERAMIC TILE (INT.- WALL)
m2
291.87
450.00
131,341.50
21000
CERAMIC TILE (FLOOR)
m2
91.38
390.00
35,638.20
21010
ACIDPROOF TILE
m2
26.45
650.00
17,192.50
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
Description
Unit
Sub Total Tile: m2
21020
21030
21040
Gypsum Board
SETTING GYPSUM BOARD
m2
16mm,for wall,including 22 gage steel stud frame(64) & runner
& bead & sealant on the other side of the steel framed metal
sheet wall cladding
GYPSUM BOARD
m2
GYPSUM PARTITION
m2
Sub Total Gypsum Board: m2
Quantity
Rate
Amount
409.70
449.53
184,172.20
2,196.50
160.00
351,440.00
41.90
7.04
180.00
170.00
7,542.00
1,196.80
2,245.44
160.40
360,178.80
187.22
1,080.00
202,197.60
21060
Plastering
METAL LATH
m2
Heavy duty expanded metal mesh - Hot dip
galvanized(excluding the steel frames),removable, 8~12 gage
13mm Max.gap
CEMENT MORTAR
m2
1,522.98
59.00
89,855.82
21070
CEMENT MORTAR
m2
4,408.77
30.00
132,263.10
21080
CEMENT MORTAR
m2
2,415.71
30.00
72,471.30
21090
LEVELLING MORTAR
For roof
STEEL TROWEL FINISH
m2
963.60
57.00
54,925.20
m2
1,944.42
10.00
19,444.20
HARDENER
Metallic,aggregate dry-shake floor hardener(including water
soluble inorganic silicate based compound finish)
MORTAR GROUTING AROUND WINDOW FRAME
m2
752.25
55.00
41,373.75
m
38.64
47.00
1,816.08
9,312.00
65.97
614,347.05
m2
888.95
130.00
115,563.50
m2
407.10
27.00
10,991.70
m2
481.85
36.00
17,346.60
Sub Total Ceilings: LS
1.00
143,901.80
143,901.80
Sub Total Finishing: LS
1.00
3,391,245.91
3,391,245.91
m2
6.73
3,460.00
23,285.80
EA
1.00
35,370.00
35,370.00
21050
21100
21110
21120
Sub Total Plastering : m2
21130
21140
21150
Ceilings
ACOUSTIC BOARD
15x600x600 - For ceiling,including paint including the 2% of
the spare material supply
CEILING SYSTEM 2
Lightweight ceiling frame - T bar
CEILING SYSTEM 2
Lightweight ceiling frame - M bar
21170
Accessories
TOILET PARTITION
Including partition door and accessories
FRP SEPTIC TANK
21180
FRP SEPTIC TANK
EA
2.00
35,370.00
70,740.00
21190
FRP SEPTIC TANK
50 PERSON
EA
1.00
52,280.00
52,280.00
Sub Total Accessories: LS
1.00
181,675.80
181,675.80
21160
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
21200
Description
Unit
Furniture
CURTAIN BOX
Quantity
Rate
Amount
m2
11.22
250.00
2,805.00
Sub Total Furniture: LS
1.00
2,805.00
2,805.00
Sub Total Building Work: LS
1.00
20,214,963.30
20,214,963.30
Ton
2,420.88
2,450.00
5,931,156.00
30010
CHK'D PLATE
Ton
Steel angle framed including painting works, HOT DIP GALV.
5.18
6,690.00
34,654.20
30020
Fabrication and Erection of Access Platform for Operation and Ton
Maintenance Purpose
50.00
18,410.00
920,500.00
Sub Total Structural Steel: ton
2,476.06
2,781.16
6,886,310.20
m2
5,657.25
260.00
1,470,885.00
m2
540.00
110.00
59,400.00
Sub Total Grating & Deck Plate: m2
6,197.25
246.93
1,530,285.00
3,015.41
300.00
904,623.00
11.50
320.00
3,680.00
7.25
260.00
1,885.00
m
477.86
390.00
186,365.40
m
412.14
1,150.00
473,961.00
Sub Total Handrail, Ladders & Stairs: m
3,924.16
400.22
1,570,514.40
EA
850.00
21.00
17,850.00
EA
102.00
41.00
4,182.00
Sub Total Anchor Bolts: ea
952.00
23.14
22,032.00
m2
2,661.84
31.00
82,516.89
Sub Total Field Painting: LS
1.00
82,516.89
82,516.89
30000
30030
30040
30050
30060
30070
30080
30090
30100
30110
30120
Structural Steel Work
Structural Steel
Structural Steel
STEEL ERECTION
Grating & Deck Plate
GRATING (SERRATED)
F-32 (HOT DIP GALV. )
DECK PLATE
Handrail, Ladders & Stairs
HANDRAIL (SECL STANDARD)
m
Including Hot dip galvanizing(25kg/m)+POLYURETHANE
COATING 50 MIC. H=1.1(Post&Top/Middle Rail Pipe)
HANDRAIL (SECL STANDARD)
m
Removable Type, Including Hot dip galvanized H=1.1(Post &
Top/Middle Rail Pipe)
STEEL LADDER WITHOUT CAGE
m
STEEL LADDER WITH CAGE
Hop Dip Galvanizing
STEEL STAIR(SECL STD'D)
w/ HANDRAIL (Hop Dip Galvanized) W=800~900
FL:GRTG.F-32
Anchor Bolts
SET ANCHOR BOLT
Expansion stud anchor
SET ANCHOR BOLT
Expansion Stud anchor
Field Painting
TOUCH UP PAINT
Grouting
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
30130
Description
Unit
NON-SHRINK GROUT
Quantity
Rate
Amount
m3
11.54
5,210.00
60,123.40
Sub Total Grouting: LS
1.00
60,123.40
60,123.40
Sub Total Structural Steel: ton
2,847.00
3,565.78
10,151,781.89
30140
Roofing & Siding Work
Roofing & Siding
F.M SHEET (V-115) : FOR ROOFING
m2
1,807.45
380.00
686,831.00
30150
F.M SHEET (V-115) : FOR SIDING
m2
1,937.70
360.00
697,572.00
30160
S/W PANEL (GLASS WOOL) : FOR ROOFING
Roof : C/S(0.6)+75+C/S(0.7)
S/W PANEL (GLASS WOOL) : FOR SIDING
Wall : C/S(0.6)+50+C/S(0.7)
m2
37.98
27.00
1,025.46
m2
113.40
27.00
3,061.80
Sub Total Roofing & Siding: LS
1.00
1,388,490.26
1,388,490.26
m
469.52
170.00
79,818.40
m
364.30
280.00
102,004.00
m
360.41
450.00
162,184.50
Sub Total Flashing: m
1,194.23
288.06
344,006.90
m
408.98
100.00
40,898.00
m
246.73
370.00
91,290.10
Sub Total Gutter: m
655.71
201.60
132,188.10
30170
30180
30190
30200
30210
30220
Flashing
FLASHING (COLOR SHEET)
Factory painted galvanized steel
FLASHING (COLOR SHEET)
Factory painted galvanized steel
FLASHING (COLOR SHEET)
Factory painted galvanized steel
Gutter
STEEL DOWNSPOUT
Galvanized alkyd painted
GUTTER
Gal.2.3t+Epoxy coating 2plys
30230
Drains
ROOF DRAIN
EA
19.00
830.00
15,770.00
30240
ROOF DRAIN
EA
50.00
790.00
39,500.00
30250
FLOOR DRAIN
Dia.250, Stainless steel
SPLASH BLOCK
EA
10.00
1,030.00
10,300.00
EA
50.00
2,090.00
104,500.00
LEADER HEAD
t=0.7 Factory painted galvanized steel
EA
50.00
2,440.00
122,000.00
Sub Total Drains: LS
1.00
292,070.00
292,070.00
Sub Total Roofing & Siding Work: m2
3,614.00
596.78
2,156,755.26
Sub Total Structural Steel Work: LS
1.00
12,308,537.15
12,308,537.15
30260
30270
Process Piping Work
Underground Piping Installation
Pipe
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
40000
40010
40020
40030
40040
40050
40060
40070
40080
41140
41150
40090
40100
40110
40120
40130
40140
40150
40160
40170
40180
40190
40200
40210
40220
40230
40240
40250
40260
40270
40280
Description
Unit
Flange to Flange connection, Installation of In-line
components such as PIV etc.
3" ~ 6" (STD) FBE Coated Steel Pipes (3-Layer (FBE+PP)
Coated)
8" ~ 10" (STD) FBE Coated Steel Pipes (3-Layer (FBE+PP)
Coated)
12" ~ 24" (Over 7.93 ~ 9.53T) FBE Coated Steel Pipes (3Layer (FBE+PP) Coated)
26" ~ 48" (Over 7.93 ~ 9.53T) FBE Coated Steel Pipes (3Layer (FBE+PP) Coated)
26" ~ 48" (Over 9.53 ~ 12.70T) FBE Coated Steel Pipes (3Layer (FBE+PP) Coated)
Quantity
Rate
Amount
D/I
781.50
25.00
19,537.50
D/I
1,560.00
120.00
187,200.00
D/I
98.00
68.00
6,664.00
D/I
7,608.00
98.00
745,584.00
D/I
2,982.00
120.00
357,840.00
D/I
356.00
130.00
46,280.00
Sub Total Pipe: D/I
13,385.50
101.83
1,363,105.50
m2
76.00
2,200.00
167,200.00
Sub Total Wrapping: LS
1.00
167,200.00
167,200.00
774.00
78.00
470.00
310.00
363,780.00
24,180.00
Sub Total Testing: LS
1.00
387,960.00
387,960.00
Sub Total Underground Piping Installation: DI
13,386.00
143.30
1,918,265.50
m3
m3
12.00
6.00
580.00
6,670.00
6,960.00
40,020.00
Sub Total Piping Civil Work: LS
1.00
46,980.00
46,980.00
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
2.00
31,937.30
3.00
25.00
21,647.40
23,029.25
4.00
5,652.00
7,562.00
26.00
1,124.00
5,851.50
4.00
22.00
23,029.25
4.00
5,652.00
7,562.00
26.00
1,124.00
73.00
68.00
75.00
75.00
110.00
110.00
110.00
90.00
66.00
96.00
95.00
120.00
120.00
120.00
110.00
130.00
64.00
70.00
100.00
100.00
146.00
2,171,736.40
225.00
1,875.00
2,381,214.00
2,533,217.50
440.00
508,680.00
499,092.00
2,496.00
106,780.00
702,180.00
480.00
2,640.00
2,533,217.50
520.00
361,728.00
529,340.00
2,600.00
112,400.00
Sub Total Carbon Steel Pipe: DI
134,286.70
92.72
12,451,007.40
Wrapping
Wrapping/Coating For Welding Joint ALL Size (Included
wrapping material)
Testing
NDT/PMI/Thick Test Shop NDT Radiographic Test
NDT/PMI/Thick Test Shop NDT Liquid Penetration Test
Above Ground Piping
Piping Civil Work
Local Foundation Installation Con'c only
Local Foundation Installation Grouting only
Piping Installation
Carbon Steel Pipe
Up to 2.1/2" Carbon Steel
Up to 2.1/2" Carbon Steel Class 3000 & Below
Up to 2.1/2" Carbon Steel Class 6000 & Over
Up to 2.1/2" Carbon Steel Class 3000 ~ 9000
Up to 2.1/2" Carbon Steel STD
3" ~ 6" Carbon Steel STD
3" ~ 6" Carbon Steel SCH XS
8" ~ 10" Carbon Steel STD
12" ~ 24" Carbon Steel Over 7.93 ~ 9.53T
12" ~ 24" Carbon Steel Over 12.70T ~ 15.88T
12" ~ 24" Carbon Steel Over 7.93 ~ 9.53T
Up to 2.1/2" Carbon Steel SCH XS
Up to 2.1/2" Carbon Steel SCH XXS
Up to 2.1/2" Carbon Steel SCH160
3" ~ 6" Carbon Steel STD
3" ~ 6" Carbon Steel SCH XS
8" ~ 10" Carbon Steel STD
12" ~ 24" Carbon Steel Over 7.93 ~ 9.53T
12" ~ 24" Carbon Steel Over 12.70T ~ 15.88T
26" ~ 48" Carbon Steel Over 7.93 ~ 9.53T
SHT
Point
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
40290
40300
40310
40320
40330
40340
40350
40360
40370
40380
40390
40400
40410
40420
40430
40440
40450
40460
40470
40480
40490
40500
40510
40520
40530
40540
40550
40560
40570
40580
40590
40600
40610
40620
40630
40640
40650
40660
40670
40680
40690
40700
Description
Unit
Stainless Steel Pipe
Up to 2.1/2" Stainless Steel SCH10S
Up to 2.1/2" Stainless Steel SCH40S
Up to 2.1/2" Stainless Steel SCH80S
Up to 2.1/2" Stainless Steel SCH40S
Up to 2.1/2" Stainless Steel SCH80S
Up to 2.1/2" Stainless Steel Class 3000 & Below
3" ~ 6" Stainless Steel SCH10S
3" ~ 6" Stainless Steel SCH40S
3" ~ 6" Stainless Steel SCH80S
3" ~ 6" Stainless Steel SCH80S
3" ~ 6" Stainless Steel SCH10S
3" ~ 6" Stainless Steel SCH40S
8" ~ 10" Stainless Steel Below than SCH 40
8" ~ 10" Stainless Steel SCH10S
8" ~ 10" Stainless Steel SCH80S
8" ~ 10" Stainless Steel Below than SCH 40
8" ~ 10" Stainless Steel SCH10S
8" ~ 10" Stainless Steel SCH80S
12" ~ 24" Stainless Steel Up to 7.93T
12" ~ 24" Stainless Steel Over 7.93 ~ 9.53T
12" ~ 24" Stainless Steel Over 9.53T ~ 12.70T
12" ~ 24" Stainless Steel Up to 7.93T
12" ~ 24" Stainless Steel Over 7.93 ~ 9.53T
12" ~ 24" Stainless Steel Over 9.53T ~ 12.70T
26" ~ 48" Stainless Steel Over 7.93 ~ 9.53T
26" ~ 48" Stainless Steel Over 7.93 ~ 9.53T
Quantity
Rate
Amount
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
18,058.50
1,473.30
480.50
2,044.00
125.50
12,606.60
28,109.75
91.50
179.00
179.00
28,109.75
91.50
1,406.00
1,342.00
243.00
1,406.00
1,342.00
243.00
1,637.00
397.00
106.00
1,637.00
397.00
106.00
140.00
140.00
90.00
94.00
110.00
40.00
49.00
51.00
160.00
160.00
220.00
99.00
85.00
85.00
130.00
140.00
170.00
59.00
58.00
77.00
150.00
160.00
230.00
84.00
100.00
150.00
240.00
170.00
1,625,265.00
138,490.20
52,855.00
81,760.00
6,149.50
642,936.60
4,497,560.00
14,640.00
39,380.00
17,721.00
2,389,328.75
7,777.50
182,780.00
187,880.00
41,310.00
82,954.00
77,836.00
18,711.00
245,550.00
63,520.00
24,380.00
137,508.00
39,700.00
15,900.00
33,600.00
23,800.00
Sub Total Stainless Steel Pipe: DI
102,090.90
104.70
10,689,292.55
DI
DI
DI
DI
DI
DI
3,314.60
4,458.70
2,726.50
2,736.50
697.00
2,458.50
9.85
15.00
11.00
11.00
11.00
11.00
32,648.81
66,880.50
29,991.50
30,101.50
7,667.00
27,043.50
Sub Total Screw Joint Pipe: DI
16,391.80
11.86
194,332.81
DI
210.00
8.46
1,776.60
Sub Total PVC Pipe: DI
210.00
8.46
1,776.60
1,178.00
48.00
56,544.00
EA
DI
5.00
24.00
190.00
260.00
950.00
6,240.00
DI
DI
30.00
2.00
15.00
56.00
450.00
112.00
DI
DI
11.00
16.00
26.00
380.00
286.00
6,080.00
DI
DI
1,411.00
598.00
25.00
25.00
35,275.00
14,950.00
Screw Joint Pipe
Screw Joint
Screw Joint Cast Iron
Screw Joint Carbon Steel
Screw Joint Carbon Steel
Screw Joint Cooper
Screw Joint Stainless Steel
PVC Pipe
Glass Fiber/PVC
Appurtenances
Appurtenaces Installation Multi Side Mounting Hose/Tube(W/
Connection)
Apputenaces installation Multi Side Mounting Sight Glass
Appurtenaces Installation Multi Side Mounting Safety(Eye)
Shower
Appurtenaces Installation Single Side Mounting pot
Appurtenaces Installation Single Side Mounting Injection
Nozzle
Appurtenaces Installation Single Side Mounting Silencer
Appurtenaces Installation Single Side Mounting Sampling
System
Appurtenaces Installation Single Side Mounting Strainer
Appurtenaces Installation Single Side Mounting Steam Trap
DI
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
40710
40720
40730
40740
40830
40840
40850
Description
Unit
40890
40900
40910
40920
40930
40940
40950
40960
40970
40980
40990
41000
41010
41020
41030
Rate
Amount
Sub Total Appurtenances: DI
3,275.00
36.91
120,887.00
DI
DI
DI
DI
19,007.40
220.80
252.00
7,333.00
25.00
23.00
25.00
38.00
475,185.00
5,078.40
6,300.00
278,654.00
Sub Total Bolt Up All Material: DI
26,813.20
28.54
765,217.40
Sub Total Piping Installation: DI
283,067.60
85.57
24,222,513.76
5.40
122.20
15,030.00
13,850.00
81,162.00
1,692,470.00
3.30
8,910.00
29,403.00
130.90
13,774.14
1,803,035.00
EA
EA
EA
31.00
12.00
18.00
140.00
140.00
1,640.00
4,340.00
1,680.00
29,520.00
Sub Total Fire Hydrant: ea
61.00
582.62
35,540.00
EA
EA
EA
EA
12.00
200.00
200.00
200.00
55.00
37.00
37.00
37.00
660.00
7,400.00
7,400.00
7,400.00
Sub Total Sprinkers: ea
612.00
37.35
22,860.00
EA
EA
EA
4.00
2.00
2.00
170.00
140.00
94.00
680.00
280.00
188.00
Sub Total Deluge Valves: ea
8.00
143.50
1,148.00
EA
EA
EA
EA
1.00
1.00
2.00
2.00
230.00
170.00
140.00
94.00
230.00
170.00
280.00
188.00
Sub Total Strainer Baskets: ea
6.00
144.67
868.00
EA
EA
EA
EA
120.00
12.00
40.00
6.00
120.00
240.00
120.00
240.00
14,400.00
2,880.00
4,800.00
1,440.00
Sub Total Extinguishers: ea
178.00
132.13
23,520.00
Bolt Up All Material
Bolting Up for Flange All Material
Bolting Up for Flange All Material
Bolting Up All Material
Bolting Up for Valve All Material
Pipe Supports
Spring hanger/Support Installation ALL Size
M/T
Fabrication & Installation of Piping Support - Carbon Steel with M/T
H.D.G (including U-bolts and clamps)
Fabrication & Installation of Piping Support - Stainless Steel
M/T
(including U-bolts and clamps)
Sub Total Pipe Supports: M/T
40860
40870
40880
Quantity
Fire Accessories
Fire Hydrant
FIRE HYDRANT (4 WAY)
FIRE HYDRANT WITH MONITOR (5 WAY)
FIRE HOSE RACK
Sprinkers
NOZZLE FOR MONITOR
WATER SPRAY NOZZLE
SPRINKLER PILOT HEAD
SPRINKLER HEAD(CLOSED TYPE)
Deluge Valves
DELUGE VALVE ASSEMBLY
DELUGE VALVE ASSEMBLY
DELUGE VALVE ASSEMBLY
Strainer Baskets
STRAINER(BASKET TYPE)
STRAINER(BASKET TYPE)
STRAINER(BASKET TYPE)
STRAINER(BASKET TYPE)
Extinguishers
PORTABLE DRY CHEMCIAL EXTINGUISHER (7.7 kg)
WHEELED DRY CHEMICAL EXTINGUISHER (56.7 kg)
PORTABLE CO2 EXTINGUISHER (6.9 kg)
WHEELED CO2 EXTINGUISHER (45.3 kg)
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
Description
Unit
Sub Total Fire Accessories: LS
41040
41050
41060
41070
41080
41090
41100
41110
41120
41130
41160
41170
41180
41190
41200
41210
41220
41230
41240
41250
40750
40760
40770
40780
40790
40800
40810
40820
Quantity
Rate
Amount
1.00
83,936.00
83,936.00
EA
EA
65.00
65.00
58.00
58.00
3,770.00
3,770.00
Sub Total Steam Manifolds: ea
130.00
58.00
7,540.00
5,942.00
3,512.00
30.00
36.00
178,260.00
126,432.00
Sub Total Steam Tracing: LS
1.00
304,692.00
304,692.00
Sub Total Steam Accessories: LS
1.00
312,232.00
312,232.00
EA
EA
EA
EA
EA
EA
158.00
13.00
2.00
158.00
13.00
2.00
58.00
85.00
280.00
1,210.00
1,580.00
1,940.00
9,164.00
1,105.00
560.00
191,180.00
20,540.00
3,880.00
Sub Total PSV: LS
1.00
226,429.00
226,429.00
1,728.00
17,500.00
1,728.00
17,307.00
1,412.00
14,319.00
1,412.00
14,158.00
1,074.40
300.00
360.00
300.00
470.00
300.00
360.00
300.00
470.00
270.00
518,400.00
6,300,000.00
518,400.00
8,134,290.00
423,600.00
5,154,840.00
423,600.00
6,654,260.00
290,088.00
Sub Total Testing: LS
1.00
28,417,478.00
28,417,478.00
DI
5,103.10
130.00
663,403.00
Sub Total In Line Instruments: LS
1.00
663,403.00
663,403.00
5,060.00
35.00
12.00
2.00
3.00
7.00
50.00
18.00
300.00
140.00
458,370.00
1,710.00
1,130.00
34,400.00
91,080.00
10,500.00
1,680.00
916,740.00
5,130.00
7,910.00
1,720,000.00
300.00
160.00
48,000.00
Steam Accessories
Steam Manifolds
Installation of Steam Manifold, CM 8, 2"x1500 long
Installation of Steam Manifold, SM 8, 2"x1500 long
Steam Tracing
Steam tracing, 1/2", Tube, A269 GR. TP316/316L
Steam tracing, 1/2", Pre-insulated tube, A269 GR.
TP316/316L
PSV
PSV PSV Installation Up to ND2.1/2"
PSV PSV Installation ND5" ~ ND6"
PSV PSV Installation ND5" ~ ND6"
PSV PSV Popping Test Up to ND2.1/2"
PSV PSV Popping Test ND3" ~ ND4"
PSV PSV Popping Test ND5" ~ ND6"
Testing
NDT/PMI/Thick Test Field NDT Magnetic Test
NDT/PMI/Thick Test Field NDT PMI Test
NDT/PMI/Thick Test Field NDT Liquid Penetration Test
NDT/PMI/Thick Test Field NDT Radiographic Test
NDT/PMI/Thick Test Shop NDT Magnetic Test
NDT/PMI/Thick Test Shop NDT PMI Test
NDT/PMI/Thick Test Shop NDT Liquid Penetration Test
NDT/PMI/Thick Test Shop NDT Radiographic Test
Post Weld Heat Treatment (Included hardness test)
In Line Instruments
In-Line Instrument
Miscellaneous
Earth Bonding Lug Fabrication & Installation ALL Size
Post Indicator Valve
MONITOR
Fabrication & Installation of Temporary Silencer
Fabrication & Installation of Funnel
Fabrication & Installation of Bird Screen
Temp. piping for flushing, CW Passivation, Chemical cleaning
(including pipes, fittings, valves, supports, etc.)
Opening on grating for pipe and support Under 8" Refer to
information "Standard Drawing for Bldg & Strl Grating Detail.
M
M
Points
Points
Points
SHT
Points
Points
Points
SHT
DI
EA
EA
EA
EA
EA
EA
M/T
Points
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
50460
50470
50480
50490
50500
50510
50520
50530
50540
50550
50560
50570
50580
50590
50600
50610
50620
50630
50640
50650
50660
50670
50680
50690
50700
50710
50720
50730
50740
50750
50760
50770
Description
Unit
Quantity
Rate
Amount
Sub Total Miscellaneous: LS
1.00
2,801,040.00
2,801,040.00
Sub Total Above Ground Piping: LS
1.00
58,577,046.76
58,577,046.76
Sub Total Process Piping Work: LS
1.00
60,495,312.26
60,495,312.26
Ton
Ton
Ton
M3
M3
M3
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
M3
M3
Ton
35.00
26.00
28.00
55.00
17.60
16.50
2.50
0.04
6.00
0.04
6.00
0.02
2.49
56.00
54.00
0.13
0.54
48.00
37.00
0.15
3,110.00
3,240.00
3,150.00
2,040.00
2,040.00
2,040.00
3,560.00
28,080.00
2,380.00
28,110.00
2,380.00
50,990.00
4,420.00
5,340.00
4,860.00
6,400.00
3,850.00
2,040.00
2,040.00
9,390.00
108,850.00
84,240.00
88,200.00
112,200.00
35,904.00
33,660.00
8,900.00
1,123.20
14,280.00
1,124.40
14,280.00
1,019.80
11,005.80
299,040.00
262,440.00
832.00
2,079.00
97,920.00
75,480.00
1,399.11
Sub Total Columns: Ton
391.01
3,207.03
1,253,977.31
Ton
1.00
7,860.00
7,860.00
Ton
1.00
9,390.00
9,390.00
Ton
4.50
4,640.00
20,880.00
Ton
6.50
3,950.00
25,675.00
Ton
25.40
4,240.00
107,696.00
Ton
5.00
4,020.00
20,100.00
Ton
3.00
4,080.00
12,240.00
Ton
8.00
3,610.00
28,880.00
Ton
6.00
3,950.00
23,700.00
Sub Total Vacuum System: Ton
60.40
4,245.38
256,421.00
67.00
82.00
11.80
12,040.00
11,870.00
1,740.00
806,680.00
973,340.00
20,532.00
Mechanical Erection
Process Equipment Installation
Heating Cooling Drying Equipment
Columns
DRYING COLUMN
MEA COLUMN
DEA SPLITTER COLUMN
DRYING COLUMN
MEA COLUMN
DEA SPLITTER COLUMN
DEA SPLITTER COLUMN
DEA COLUMN
DEA COLUMN
TEA COLUMN
TEA COLUMN
MEA COLUMN
MEA COLUMN
DEA COLUMN
TEA COLUMN
DRYING COLUMN
DRYING COLUMN
DEA COLUMN
TEA COLUMN
DEA SPLITTER COLUMN
Vacuum System
DRYING COLUMN VACUUM SYSTEM
(Refer to informative document attached)
MEA COLUMN VACUUM SYSTEM
(Refer to informative document attached)
DEA SPLITTER VACUUM SYSTEM
(Refer to informative document attached)
DEA COLUMN VACUUM SYSTEM
(Refer to informative document attached)
TEA COLUMN VACUUM SYSTEM
(Refer to informative document attached)
REACTOR 120 VACUUM SYSTEM
(Refer to informative document attached)
POST TREATMENT VACUUM SYSTEM
(Refer to informative document attached)
REACTOR 220 VACUUM SYSTEM
(Refer to informative document attached)
REACTOR 320 VACUUM SYSTEM
(Refer to informative document attached)
Condenser
DEA COLUMN CONDENSER
TEA COLUMN CONDENSER
AMMONIA STRIPPER MAIN CONDENSER
Ton
Ton
Ton
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
50780
50790
50800
50810
50820
50830
50840
50850
50860
50870
50880
50000
50010
50020
50030
50040
50050
50060
50070
50080
50090
50100
50110
50120
50130
50140
50150
50160
50170
50180
50190
50200
50210
50220
50230
50240
50250
50260
50270
50280
50290
50300
50310
50320
50330
50340
50350
50360
50370
50380
50390
Description
Unit
AMMONIA STRIPPER AUXILIARY CONDENSER
DRYING COLUMN CONDENSER
MEA COLUMN CONDENSER
DEA SPLITTER COLUMN CONDENSER
ATMOSPHERIC STEAM CONDENSER
REACTOR 120 CONDENSER
POST TREATMENT CONDENSER
REACTOR 220 CONDENSER
REACTOR 320 CONDENSER
ATM STEAM CONDENSER
EFFLUENT CONDENSER
Quantity
Rate
Amount
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
15.00
20.80
23.00
28.00
4.50
1.50
1.40
1.40
1.10
1.20
1.30
2,350.00
3,710.00
3,520.00
2,380.00
2,340.00
3,850.00
3,450.00
3,450.00
3,940.00
3,940.00
3,450.00
35,250.00
77,168.00
80,960.00
66,640.00
10,530.00
5,775.00
4,830.00
4,830.00
4,334.00
4,728.00
4,485.00
Sub Total Condenser: Ton
260.00
8,077.24
2,100,082.00
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
0.20
0.20
0.20
0.20
4.00
0.20
0.60
0.60
2.10
0.20
0.60
0.60
2.00
0.20
1.90
0.50
18,750.00
18,750.00
18,750.00
18,750.00
2,340.00
8,950.00
3,370.00
3,370.00
3,220.00
11,260.00
4,200.00
4,200.00
1,130.00
7,670.00
3,220.00
5,650.00
3,750.00
3,750.00
3,750.00
3,750.00
9,360.00
1,790.00
2,022.00
2,022.00
6,762.00
2,252.00
2,520.00
2,520.00
2,260.00
1,534.00
6,118.00
2,825.00
Sub Total Heater: Ton
14.30
3,984.97
56,985.00
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
4.10
4.10
4.10
4.10
4.10
2.70
0.20
1.00
1.00
1.40
1.60
0.50
0.10
5.90
1.80
1.50
5.90
1.40
1.20
0.20
2.80
0.80
0.20
0.20
2,340.00
2,340.00
2,340.00
2,340.00
2,460.00
3,450.00
10,480.00
3,940.00
3,940.00
3,450.00
3,430.00
5,400.00
19,140.00
2,320.00
3,120.00
1,260.00
5,900.00
3,450.00
3,450.00
7,670.00
2,890.00
3,180.00
2,930.00
6,400.00
9,594.00
9,594.00
9,594.00
9,594.00
10,086.00
9,315.00
2,096.00
3,940.00
3,940.00
4,830.00
5,488.00
2,700.00
1,914.00
13,688.00
5,616.00
1,890.00
34,810.00
4,830.00
4,140.00
1,534.00
8,092.00
2,544.00
586.00
1,280.00
Sub Total Cooler: Ton
50.90
3,176.72
161,695.00
Heater
Utility Station Steam Desuperheater
MS DESUPERHEATER
MS DESUPERHEATER
LS DESUPERHEATER
AMMONIA STRIPPER PRE-HEATER
WASTE WATER HEATER
NP PREHEATER
FA PREHEATER
WATER CIRCULATION HEATER I
TEMPERED WATER HEATER I
DEG PREHEATER
SMO PREHEATER
WATER CIRCULATION HEATER II
TEMPERED WATER HEATER II
WATER CIRCULATION HEATER III
TEMPERED WATER HEATER III
Cooler
FIRST REACTOR INTERCOOLER
SECOND REACTOR INTERCOOLER
THIRD REACTOR INTERCOOLER
FOUTH REACTOR INTERCOOLER
FIFTH REACTOR INTERCOOLER
AMMONIA SOLUTION COOLER
RECYCLE WATER COOLER
MEA PRODUCT COOLER
AMINES RECYCLE COOLER
DEA PRODUCT COOLER
TEA PRODUCT COOLER
HEAVY AMINES COOLER
LEAN WATER COOLER
WATER CIRCULATION COOLER I
POST TREATMENT CIRCULATION COOLER
PRODUCT COOLER I
WATER CIRCULATION COOLER II
POLYSORBATE COOLER
PEGs COOLER
PEG 600 I COOLER
WATER CIRCULATION COOLER III
PRODUCT COOLER III
C-67920 COOLER
EFFLUENT COOLER
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
50400
50410
50420
50430
50440
50450
Description
Unit
Reboiler
AMMONIA STRIPPER REBOILER
DRYING COLUMN REBOILER
MEA COLUMN REBOILER
DEA SPLITTER COLUMN REBOILER
DEA COLUMN REBOILER
TEA COLUMN REBOILER
50920
50930
50940
50950
50960
50970
50980
50990
51000
51010
51020
51030
51040
51050
51060
51070
Rate
Amount
Ton
Ton
Ton
Ton
Ton
Ton
16.00
20.50
8.30
17.20
23.50
22.50
2,350.00
3,730.00
1,900.00
2,440.00
3,570.00
3,630.00
37,600.00
76,465.00
15,770.00
41,968.00
83,895.00
81,675.00
Sub Total Reboiler: Ton
108.00
3,123.82
337,373.00
1.00
4,166,533.31
4,166,533.31
Ton
Ton
Ton
6.10
6.00
2.50
2,320.00
5,900.00
2,890.00
14,152.00
35,400.00
7,225.00
Sub Total Exchanger: Ton
14.60
3,888.84
56,777.00
Ton
Ton
Ton
Ton
Ton
Ton
0.30
0.50
0.30
0.50
0.30
0.50
6,280.00
3,670.00
5,590.00
4,200.00
5,590.00
4,200.00
1,884.00
1,835.00
1,677.00
2,100.00
1,677.00
2,100.00
Sub Total Filter: Ton
2.40
4,697.08
11,273.00
Ton
Ton
Ton
Ton
Ton
0.10
0.10
0.10
0.10
0.10
23,430.00
23,430.00
23,430.00
23,430.00
23,430.00
2,343.00
2,343.00
2,343.00
2,343.00
2,343.00
Sub Total Eductor: Ton
0.50
23,430.00
11,715.00
Ton
11.00
127,390.00
1,401,290.00
Ton
Ton
0.10
0.10
23,430.00
23,430.00
2,343.00
2,343.00
Sub Total Compressor: Ton
11.20
125,533.57
1,405,976.00
Ton
9.40
1,820.00
17,108.00
Sub Total Receiver: Ton
9.40
1,820.00
17,108.00
Ton
15.00
9,610.00
144,150.00
1.00
144,150.00
144,150.00
Sub Total Heating Cooling Drying Equipment: LS
50890
50900
50910
Quantity
Gas & Liquid Handling Equipment
Gas Handling Equipment
Exchanger
REACTOR 120 EXCHANGER
REATOR 220 EXCHANGER
REACTOR 320 EXCHANGER
Filter
BASKET FILTER I
CARTRIDGE FILTER I
BASKET FILTER II
CARTRIDGE FILTER II
BASKET FILTER III
CARTRIDGE FILTER III
Eductor
STEAM EDUCTOR
STEAM EDUCTOR
STEAM EDUCTOR
STEAM EDUCTOR
STEAM EDUCTOR
Compressor
HP Nitrogen Compressor Package
(Refer to informative document attached)
5 Ton Geared Trolley with Chain Block
2 Ton Manual Geared Trolley Chain Hoist
Receiver
HP Nitrogen Compressor Discharge Receiver
Evaporator
EVAPORATOR
(Refer to informative document attached)
Sub Total Evaporator: LS
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
51080
51090
51100
51110
Description
Unit
Reactor
ETHANOLAMINES REACTORS
ETHOXYLATION I REACTOR
ETHOXYLATION II REACTOR
ETHOXYLATION III REACTOR
Rate
Amount
Ton
Ton
Ton
Ton
80.00
23.70
23.70
10.30
1,990.00
2,730.00
2,730.00
1,830.00
159,200.00
64,701.00
64,701.00
18,849.00
Sub Total Reactor: Ton
137.70
2,232.76
307,451.00
1.00
1,954,450.00
1,954,450.00
0.20
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
1.60
0.60
0.60
1.20
0.80
1.60
0.10
1.80
0.06
3.00
1.00
1.08
1.60
1.60
1.80
0.30
0.60
0.30
0.60
1.00
3.00
1.00
9.00
2.60
4.40
1.40
0.40
0.40
4.60
0.80
2.40
1.60
1.20
1.80
0.24
15,960.00
15,960.00
15,960.00
15,940.00
15,960.00
15,960.00
15,960.00
15,960.00
15,960.00
15,960.00
15,960.00
15,960.00
15,960.00
6,400.00
9,080.00
9,080.00
9,590.00
9,590.00
4,260.00
15,960.00
3,630.00
22,330.00
6,400.00
10,600.00
9,590.00
9,590.00
9,590.00
15,960.00
23,430.00
23,430.00
23,430.00
23,430.00
14,070.00
9,390.00
15,560.00
9,390.00
13,680.00
9,390.00
13,680.00
22,210.00
23,430.00
9,390.00
15,560.00
14,070.00
14,070.00
13,300.00
14,070.00
23,430.00
3,192.00
4,788.00
4,788.00
4,782.00
4,788.00
4,788.00
4,788.00
4,788.00
4,788.00
4,788.00
4,788.00
4,788.00
4,788.00
10,240.00
5,448.00
5,448.00
11,508.00
7,672.00
6,816.00
1,596.00
6,534.00
1,339.80
19,200.00
10,600.00
10,357.20
15,344.00
15,344.00
28,728.00
7,029.00
14,058.00
7,029.00
14,058.00
14,070.00
28,170.00
15,560.00
84,510.00
35,568.00
41,316.00
19,152.00
8,884.00
9,372.00
43,194.00
12,448.00
33,768.00
22,512.00
15,960.00
25,326.00
5,623.20
Sub Total Gas Handling Equipment: LS
51120
51130
51140
51150
51160
51170
51180
51190
51200
51210
51220
51230
51240
51250
51260
51270
51280
51290
51300
51310
51320
51330
51340
51350
51360
51370
51380
51390
51400
51410
51420
51430
51440
51450
51460
51470
51480
51490
51500
51510
51520
51530
51540
51550
51560
51570
51580
51590
Quantity
Liquid Handling Equipment
Pumps
NP PROCESS FEED PUMP II
AE3EO TRANSFER PUMP
AE7EO TRANSFER PUMP
AE9EO TRANSFER PUMP
AE12EO TRANSFER PUMP
NP3EO TRANSFER PUMP
NP7EO TRANSFER PUMP
NP9EO TRANSFER PUMP
NP15EO/NP20EO TRANSFER PUMP
NP25EO/NP30EO TRANSFER PUMP
PEG 200 TRANSFER PUMP
PEG 400/ PEG 600 TRANSFER PUMP
PEG 1200/ PEG 1500 TRANSFER PUMP
CONDENSATE RETURN PUMP
CATALYST PUMP
NEUTRALIZER PUMP
SCRUBBER RECIRCULATION PUMP
ORGANIC BLOW DOWN PUMP
AQUEOUS EFFLUENT TRANSFER PUMP
20% NaOH Feed Pump
TK-67930 RECIRCULATION PUMP
ACID PUMP I
DELUGE WATER PUMP
Amines Storage Area PCS Sump Pump
MEA Loading Pumps
DEA Loading Pumps
TEA 99 Loading Pump
SANITARY PUMP (Including Startup Panel)
ETHOXYLATE DRUMMING PUMP
FA UNLOADING PUMP
NP UNLOADING PUMP
Eye Wash/Safety Shower Water Supply Pump
Ammonia Transfer Pumps
Deluge Water Pump - 1
Potentially Contaminated Surface Water Sump Pump - 1
EO FEED PUMPS
AMMONIA SOLUTION CIRCULATION PUMPS
AMMONIA SOLUTION FEED PUMPS
AMINES RERUN PUMP
RICH WATER HOT WELL PUMPS
LEAN WATER HOT WELL PUMPS
DRYING COLUMN BOTTOM PUMPS
CYCLE WATER PUMPS
MEA COLUMN BOTTOM PUMPS
MEA PRODUCT PUMPS
MEA TRANSFER PUMPS
DEA SPLITTER BOTTOM PUMPS
AMINES RECYCLE PUMPS
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
51600
51610
51620
51630
51640
51650
51660
51670
51680
51690
51700
51710
51720
51730
51740
51750
51760
51770
51780
51790
51800
51810
51820
51830
51840
51850
51860
51870
51880
51890
51900
51910
51920
51930
51940
51950
51960
51970
51980
51990
52000
52010
52020
52030
52040
52050
52060
52070
52080
52090
Description
Unit
DEA COLUMN BOTTOM PUMPS
DEA PRODUCT PUMPS
DEA TRANSFER PUMPS
TEA COLUMN BOTTOM PUMPS
TEA PRODUCT PUMPS
TEA TRANSFER PUMPS
TEA TOP COLUMN PURGE PUMP
HEAVIES TRANSFER PUMP
CONDENSATE RETURN PUMPS
COLD COOLING WATER BOOSTER PUMPS
WASTE WATER PUMPS
DELUGE WATER PUMP
BLOW DOWN DRUM PUMP
REACTOR 120 RECIRCULATION PUMP
WATER CIRCULATION PUMP I
POST TREATMENT CIRCULATION PUMP
EFFLUENT TRANSFER PUMP I
HOLDING VESSEL I TRANSFER PUMP
TEMPERED WATER RECIRCULATION PUMP I
REACTOR 220 RECIRCULATION PUMP
WATER CIRCULATION PUMP II
EFFLUENT TRANSFER PUMP II
POLYSORBATE TRANSFER PUMP
PEGS TRANSFER PUMP
PEG 600 I TRANSFER PUMP
TEMPERED WATER RECIRCULATION PUMP II
REACTOR 320 RECIRCULATION PUMP
WATER CIRCULATION PUMP III
HOLDING VESSEL III TRANSFER PUMP
TA UNLOADING PUMP
SMO UNLOADING PUMP
CAO UNLOADING PUMP
RAW MATERIAL BLOW DOWN PUMP
FA PROCESS FEED PUMP I
FA PROCESS FEED PUMP II
FA PROCESS FEED PUMP III
FA PROCESS FEED PUMP IV
NP PROCESS FEED PUMP I
Quantity
Rate
Amount
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
2.80
1.20
1.40
3.20
1.20
1.40
0.07
0.90
2.20
9.90
1.00
0.20
0.70
2.30
1.50
2.90
0.20
0.70
0.20
2.40
0.50
0.20
0.30
0.40
0.20
0.20
1.90
1.40
0.30
0.20
0.30
0.20
0.70
0.20
0.20
0.20
0.20
0.30
13,680.00
13,300.00
12,850.00
9,390.00
13,320.00
12,850.00
19,140.00
9,590.00
9,590.00
6,400.00
10,600.00
15,960.00
8,760.00
6,400.00
9,330.00
6,400.00
15,960.00
8,760.00
15,960.00
6,400.00
10,600.00
15,960.00
15,960.00
10,600.00
19,140.00
19,140.00
6,400.00
9,330.00
15,960.00
15,960.00
15,960.00
15,960.00
8,760.00
15,960.00
15,960.00
15,960.00
15,960.00
15,960.00
38,304.00
15,960.00
17,990.00
30,048.00
15,984.00
17,990.00
1,339.80
8,631.00
21,098.00
63,360.00
10,600.00
3,192.00
6,132.00
14,720.00
13,995.00
18,560.00
3,192.00
6,132.00
3,192.00
15,360.00
5,300.00
3,192.00
4,788.00
4,240.00
3,828.00
3,828.00
12,160.00
13,062.00
4,788.00
3,192.00
4,788.00
3,192.00
6,132.00
3,192.00
3,192.00
3,192.00
3,192.00
4,788.00
Sub Total Pumps: Ton
104.15
10,468.07
1,090,250.00
Ton
Ton
46.18
32.30
410.00
330.00
18,933.80
10,659.00
Sub Total Chemical Handling Equipment: Ton
78.48
377.07
29,592.80
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
0.10
0.10
0.10
0.10
0.10
0.10
1.00
0.10
0.20
0.20
28,110.00
28,110.00
28,110.00
28,110.00
28,110.00
28,110.00
9,390.00
23,430.00
27,530.00
18,750.00
2,811.00
2,811.00
2,811.00
2,811.00
2,811.00
2,811.00
9,390.00
2,343.00
5,506.00
3,750.00
Sub Total Mixer: Ton
2.10
18,026.19
37,855.00
Chemical Handling Equipment
Catalyst Initial Loading (to TK-67911)
Chemical Initial Filling (to TK-67912)
Mixer
STATIC MIXER
STATIC MIXER
STATIC MIXER
STATIC MIXER
STATIC MIXER
STATIC MIXER
REACTOR 120 STATIC MIXER
POST TREATMENT VESSEL STATIC MIXER
REACTOR 220 STATIC MIXER
REACTOR 320 STATIC MIXER
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
Description
Unit
Sub Total Liquid Handling Equipment: LS
52100
52110
52120
52130
52140
52150
52160
52170
52180
52190
52200
52210
52220
52230
52240
52250
52260
52270
52280
52290
52300
52310
52320
52330
52340
52350
52360
52370
52380
52390
52400
52410
52420
52430
52440
52450
52460
52470
52480
Quantity
Rate
Amount
1.00
1,157,697.80
1,157,697.80
Ton
40.00
6,150.00
246,000.00
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
M3
M3
3.30
2.90
27.00
6.60
7.40
3.10
3.30
8.00
3.30
13.60
3.00
0.50
2,380.00
3,450.00
2,660.00
1,990.00
1,990.00
2,380.00
2,380.00
2,120.00
2,380.00
2,210.00
2,040.00
2,040.00
7,854.00
10,005.00
71,820.00
13,134.00
14,726.00
7,378.00
7,854.00
16,960.00
7,854.00
30,056.00
6,120.00
1,020.00
Sub Total Drum: Ton
122.00
3,612.96
440,781.00
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
2.00
7.10
12.00
0.80
2.00
12.00
12.00
12.00
0.70
1.60
8.40
13.40
4.50
3,450.00
1,990.00
1,810.00
4,710.00
3,450.00
1,970.00
1,970.00
1,970.00
5,900.00
3,850.00
1,820.00
2,210.00
2,370.00
6,900.00
14,129.00
21,720.00
3,768.00
6,900.00
23,640.00
23,640.00
23,640.00
4,130.00
6,160.00
15,288.00
29,614.00
10,665.00
Sub Total Vessels: Ton
88.50
2,149.08
190,194.00
Ton
Ton
Ton
2.30
2.20
1.80
3,450.00
3,450.00
3,850.00
7,935.00
7,590.00
6,930.00
Sub Total Hotwell: Ton
6.30
3,564.29
22,455.00
M3
M3
3.00
1.50
7,830.00
7,830.00
23,490.00
11,745.00
Sub Total Disposal System: LS
1.00
35,235.00
35,235.00
5.50
14.60
14.60
14.60
4.80
5.70
5.70
3.40
2,020.00
2,320.00
2,140.00
2,140.00
2,370.00
2,020.00
2,020.00
920.00
11,110.00
33,872.00
31,244.00
31,244.00
11,376.00
11,514.00
11,514.00
3,128.00
Gas Liquid Storage
Drum
DRUM FILLING PACKAGE FACILITY
(Refer to informative document attached)
ORGANIC DRAIN DRUM
EO SURGE DRUM
AMMONIA SOLUTION SURGE DRUM
LOW PRESSURE CONDENSATE FLASH DRUM
ATMOSPHERIC CONDENSATE FLASH DRUM
BLOWDOWN DRUM
RAW MATERIAL BLOW DOWN DRUM
DRUM FOR C-67920
ORGANIC BLOW DOWN DRUM
AQUEOUS EFLUENT BLOW DOWN DRUM
LOW PRESSURE CONDENSATE FLASH DRUM
ATMOSPHERIC CONDENSATE FLASH DRUM
Vessels
WATER EXPANSION VESSEL I
POST TREATMENT VESSEL
HOLDING VESSEL I
KNOCK DOWN VESSEL II
WATER EXPANSION VESSEL II
POLYSORBATE HOLDING VESSEL
PEGS HOLDING VESSEL
PEG 600 I HOLDING VESSEL
KNOCK DOWN VESSEL III
WATER EXPANSION VESSEL III
HOLDING VESSEL III
ATM FLASH
VESSEL
HIGH PRESSURE NITROGEN VESSEL
Hotwell
HOT WELL I
HOT WELL II
EJECTORS HOT WELL
Disposal System
Lube Oil Charge & Flushing & Disposal
Seal Oil Charge & Flushing & Disposal
Tanks
RECYCLE WATER TANK
MEA DAY TANKS
DEA DAY TANKS
TEA DAY TANKS
HEAVIES DAY TANK
CATALYST TANK
NEUTRALIZER TANK
Eye Wash/Safety Shower Water Storage Tank
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
52490
52500
52510
52520
52530
52540
52550
52560
52570
Description
Unit
AQUEOUS EFFLUENT NEUTRALIZATION TANK
ACID TANK
3,430.00
5,640.00
7,546.00
1,974.00
Sub Total Tanks: Ton
71.45
2,162.66
154,522.00
Sub Total Gas Liquid Storage: LS
1.00
843,187.00
843,187.00
Sub Total Gas & Liquid Handling Equipment: LS
1.00
3,955,334.80
3,955,334.80
4.30
2.90
0.01
0.04
0.04
1.00
2.70
2,280.00
2,370.00
90,790.00
19,140.00
19,140.00
2,040.00
2,040.00
9,804.00
6,873.00
726.32
765.60
765.60
2,040.00
5,508.00
1.00
26,482.52
26,482.52
4.30
4.00
0.54
2,340.00
2,040.00
3,850.00
10,062.00
8,160.00
2,079.00
1.00
20,301.00
20,301.00
Ton
Ton
Ton
20.00
1.50
0.18
3,770.00
9,500.00
9,380.00
75,400.00
14,231.00
1,688.40
Sub Total Stripper: Ton
21.68
4,212.54
91,319.40
1.00
138,102.92
138,102.92
Ton
Ton
Ton
Ton
Ton
0.10
0.10
0.10
1.10
0.10
23,430.00
23,430.00
23,430.00
4,710.00
23,430.00
2,343.00
2,343.00
2,343.00
5,181.00
2,343.00
Sub Total Pot: Ton
1.50
9,702.00
14,553.00
Ton
1.00
9,390.00
9,390.00
1.00
9,390.00
9,390.00
Ton
25.00
1,910.00
47,750.00
Ton
3.40
300.00
1,020.00
Pollution Control Equipment
Scrubber
EO SCRUBBER
EO CAUSTIC SCRUBBER
EO SCRUBBER
EO CAUSTIC SCRUBBER
EO CAUSTIC SCRUBBER
EO SCRUBBER
EO CAUSTIC SCRUBBER
Ton
Ton
Ton
Ton
Ton
M3
M3
Absorber
AMMONIA ABSORBER
AMMONIA ABSORBER
AMMONIA ABSORBER
Ton
M3
Ton
Stripper
AMMONIA STRIPPER
AMMONIA STRIPPER
AMMONIA STRIPPER
Sub Total Pollution Control Equipment: LS
52700
52710
52720
52730
52740
52640
Other Equipment
Pot
CORROSION INHIBITOR POT
CORROSION INHIBITOR POT
CORROSION INHIBITOR POT
KNOCK OUT POT
SEAL POT FOR TK-66911
Ejector
EJECTOR
Sub Total Ejector: LS
52650
52660
Amount
2.20
0.35
Sub Total Absorber: LS
52610
52620
52630
Rate
Ton
Ton
Sub Total Scrubber: LS
52580
52590
52600
Quantity
Other
WEIGHING BRIDGES
(Refer to informative document attached)
Eye Wash/Safety Shower Chiller Package
(Refer to informative document attached)
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
52670
52680
52690
52750
52760
52770
52780
60000
60010
60020
60030
60040
60050
60060
60070
60080
60090
60100
60110
60120
60130
60140
Description
Unit
Ammonia Vapour Recovery Package
(Refer to informative document attached)
Safety valve poping test for rotating and package item at the
site
UV STERILIZER
Rate
Amount
Ton
16.00
6,620.00
105,920.00
EA
51.00
940.00
47,940.00
Ton
0.20
9,390.00
1,878.00
Sub Total Other : LS
1.00
204,508.00
204,508.00
Sub Total Other Equipment: LS
1.00
228,451.00
228,451.00
120.00
6,270.00
752,400.00
Sub Total Miscellaneous Metal: LS
1.00
752,400.00
752,400.00
M3
M3
42.00
2.00
2,230.00
2,680.00
93,660.00
5,360.00
Sub Total Grouting: m3
44.00
2,250.45
99,020.00
Sub Total Process Equipment Installation: ton
1,800.00
5,188.80
9,339,842.03
LS
1.00
2,110,050.00
2,110,050.00
Sub Total HVAC & Plumbing: LS
1.00
2,110,050.00
2,110,050.00
Sub Total Mechanical Erection: LS
1.00
11,449,892.03
11,449,892.03
EA
EA
EA
EA
EA
EA
320.00
120.00
180.00
91.00
10.00
37.00
150.00
170.00
730.00
710.00
700.00
1,410.00
48,000.00
20,400.00
131,400.00
64,610.00
7,000.00
52,170.00
Sub Total Lighting Fixtures: ea
758.00
426.89
323,580.00
4.00
8.00
10.00
2.00
5.00
1.00
1.00
3.00
7.00
240.00
240.00
200.00
680.00
680.00
680.00
570.00
570.00
680.00
960.00
1,920.00
2,000.00
1,360.00
3,400.00
680.00
570.00
1,710.00
4,760.00
41.00
423.41
17,360.00
438.00
49.00
21,462.00
Miscellaneous Metal
PLATFORM & LADDER
Ton
Grouting
Non-Shrink Grout
Epoxy Grout
HVAC & Plumbing
HVAC & PLUMBING WORKS
Electrical Systems
Lighting System
Lighting Fixtures
LIGHTING FIXTURE
EMER/STAND-BY LIGHTING FIXTURE
LIGHTING FIXTURE2/36W
LIGHTING FIXTURE4/36W
LIGHTING FIXTURE13W
EXIT LIGHT10W
Lighting Panels
PANEL BOARD( 30 )CKT
PANEL BOARD( 24 )CKT
PANEL BOARD( 24 )CKT
LIGHTING PANELBOARD ( 30 )CKT
RECEPTACLE PANEL ( 30 )CKT
LIGHTING PANELBOARD ( 30 )CKT
RECEPTACLE PANEL BOARD( 12 )CKT
RECEPTACLE PANEL ( 12 )CKT
LIGHTING PANELBOARD ( 30 )CKT
SET
SET
SET
SET
SET
SET
SET
SET
SET
Sub Total Lighting Panels: Set
60150
Quantity
Lighting Junction Boxes
JUNCTION BOX WITH COVER AND GASKETCAST
IRON3/4"
EA
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
Description
Unit
Quantity
Rate
Amount
60160
JUNCTION BOX WITH COVER AND GASKETCAST IRON1" EA
101.00
52.00
5,252.00
60170
60180
60190
60200
60210
JUNCTION BOX WITH COVER AND GASKET3/4"
JUNCTION BOX WITH COVER AND GASKET1"
4" SQUARE BOXZINC ELECTRO PLATE
3"X2" SQUARE BOXFOR OUTLET ZINC ELECTRO PLATE
3"X2" SQUARE BOX FOR SWITCHZINC ELECTRO
PLATE1 GANG
4" SQUARE BOX FOR SWITCHZINC ELECTRO PLATE
BUSHING & LOCK NUT FOR SQUARE BOX3/4"
EA
EA
EA
EA
EA
438.00
101.00
669.00
72.00
16.00
49.00
52.00
49.00
38.00
38.00
21,462.00
5,252.00
32,781.00
2,736.00
608.00
EA
EA
45.00
833.00
49.00
15.00
2,205.00
12,495.00
Sub Total Lighting Junction Boxes: ea
2,713.00
38.43
104,253.00
m
m
m
m
836.00
26,493.00
2,946.00
164.00
13.00
16.00
13.00
13.00
10,868.00
423,888.00
38,298.00
2,132.00
Sub Total Lighting Cable: m
30,439.00
15.61
475,186.00
EA
EA
EA
EA
1,633.00
126.00
1,302.00
81.00
5.07
5.07
5.07
5.07
8,279.31
638.82
6,601.14
410.67
Sub Total Cable Gland: ea
3,142.00
5.07
15,929.94
m
16,597.00
180.00
2,987,460.00
Sub Total Lighting Wire: m
16,597.00
180.00
2,987,460.00
1.00
3,478,575.94
3,478,575.94
2,724.00
34.00
92,616.00
m
m
3,433.00
256.00
43.00
54.00
147,619.00
13,824.00
m
342.00
63.00
21,546.00
Sub Total Rigid Steel Conduit: m
6,755.00
40.80
275,605.00
60370
60380
PVC Conduit
PVC CONDUITSCHEDULE 40 WITH RED CONCRETE3/4" m
PVC CONDUITSCHEDULE 40 WITH RED CONCRETE1-1/4" m
1,928.00
12,836.00
0.00
22.00
0.00
282,392.00
60390
PVC CONDUITSCHEDULE 40 WITH RED CONCRETE2-1/2" m
299.00
42.00
12,558.00
Sub Total PVC Conduit: m
15,063.00
19.58
294,950.00
134.00
490.00
65,660.00
60220
60230
60240
60250
60260
60270
60280
60290
60300
60310
60320
Lighting Cabling
Lighting Cable
LIGHTING CABLE5/C * 6mm2
LIGHTING CABLE3/C * 6mm2
LIGHTING CABLE5/C * 10mm2
LIGHTING CABLE4/C * 6mm2
Cable Gland
CABLE GLANDWEATHER PROOF TYPE3/4"
CABLE GLANDWEATHER PROOF TYPE1"
CABLE GLANDEXPLOSION PROOF TYPE3/4"
CABLE GLANDEXPLOSION PROOF TYPE1"
Lighting Wire
LIGHTING WIRE4mm2
Sub Total Lighting Cabling: LS
60330
60340
60350
60360
60400
Lighting Conduit
Rigid Steel Conduit
RIGID STEEL CONDUIT HOT DIP GALVANIZED3/4" (22mm) m
RIGID STEEL CONDUIT HOT DIP GALVANIZED1" (28mm)
RIGID STEEL CONDUIT HOT DIP GALVANIZED1-1/4"
(36mm)
RIGID STEEL CONDUIT HOT DIP GALVANIZED1-1/2"
Conduit Fittings
FLEXIBLE CONDUITLIQUID TIGHT 3/4"
EA
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
Description
Unit
Sub Total Conduit Fittings: LS
60410
60420
60430
60440
60450
60460
60470
60480
60490
60500
60510
60520
60530
60540
60550
60560
60570
60580
60590
60600
60610
60620
60630
60640
60650
60660
60670
60680
60690
60700
60710
60720
60730
60740
Quantity
Rate
Amount
1.00
65,660.00
65,660.00
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
206.00
1,354.00
186.00
922.00
1,905.00
2.00
2.00
197.00
1,905.00
2.00
2.00
197.00
26.00
29.00
35.00
38.00
84.00
94.00
100.00
110.00
8.76
8.76
8.76
8.76
5,356.00
39,266.00
6,510.00
35,036.00
160,020.00
188.00
200.00
21,670.00
16,687.80
17.52
17.52
1,725.72
Sub Total Conduit Clamps: ea
6,880.00
41.67
286,694.56
Sub Total Lighting Conduit: LS
1.00
922,909.56
922,909.56
m
m
m
m
4,957.00
966.00
2,479.00
483.00
19.00
20.00
19.00
90.00
94,183.00
19,320.00
47,101.00
43,470.00
Sub Total Lighting Cable Tray: m
8,885.00
22.97
204,074.00
M
200.00
31.00
6,200.00
Sub Total Lighting Raceway: m
200.00
31.00
6,200.00
EA
EA
EA
EA
EA
EA
EA
EA
1,735.00
412.00
158.00
2,479.00
483.00
1,735.00
412.00
158.00
68.00
71.00
73.00
6.70
6.70
17.00
17.00
17.00
117,980.00
29,252.00
11,534.00
16,609.30
3,236.10
29,495.00
7,004.00
2,686.00
Sub Total Cover Clamps: ea
7,572.00
28.76
217,796.40
Sub Total Lighting Cable Tray: LS
1.00
428,070.40
428,070.40
m
564.00
75.00
42,300.00
EA
m3
SET
SET
SET
SET
SET
SET
0.00
829.00
42.00
0.00
42.00
0.00
74.00
0.00
0.00
67.00
190.00
0.00
160.00
0.00
79.00
0.00
0.00
55,543.00
7,980.00
0.00
6,720.00
0.00
5,846.00
0.00
Conduit Clamps
CONDUIT CLAMP UNISTRUT TYPE3/4"
CONDUIT CLAMP UNISTRUT TYPE 1"
CONDUIT CLAMP UNISTRUT TYPE 1-1/4"
CONDUIT CLAMP UNISTRUT TYPE 1-1/2"
CONDUIT CLAMPUNISTRUT TYPE3/4"
CONDUIT CLAMPUNISTRUT TYPE1"
CONDUIT CLAMPUNISTRUT TYPE1-1/4"
CONDUIT CLAMPUNISTRUT TYPE1-1/2"
CONDUIT CLAMP 3/4"
CONDUIT CLAMP 1"
CONDUIT CLAMP 1-1/4"
CONDUIT CLAMP 1-1/2"
Lighting Cable Tray
Lighting Cable Tray
PERFORATED CABLE TRAY50 X 50
PERFORATED CABLE TRAY100 X 50
PERFORATED CABLE TRAY50mm
PERFORATED CABLE TRAY100mm
Lighting Raceway
RACE WAY100x50x2.6t
Cover Clamps
COVER CLAMP FOR PERFORATED CABLE TRAY50mm
COVER CLAMP FOR PERFORATED CABLE TRAY100mm
COVER CLAMP FOR PERFORATED CABLE TRAY150mm
COVER CLAMP FOR PERFORATED CABLE TRAY50mm
COVER CLAMP FOR PERFORATED CABLE TRAY100mm
COVER CLAMP 50mm
COVER CLAMP 100mm
COVER CLAMP 150mm
Lighting Support
UNISTRUT CHANNELHOT DIP GALVANIZED STEEL 41 x
41 x 2.6t
SUPPORT FOR JUNCTION BOX
EXCAVATION & BACK FILL WORK
SUPPORT FOR LIGHTING TRANSFORMER
SUPPORT FOR LIGHTING TRANSFORMER
SUPPORT FOR LIGHTING/RECEPTACLE PANEL
SUPPORT FOR LIGHTING/RECEPTACLE PANEL
SUPPORT FOR RECEPTACLE
SUPPORT FOR RECEPTACLE
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
60750
60760
60770
60780
60790
60800
60810
60820
60830
60840
60850
60860
60870
Description
Unit
LIGHTING FIXTURE SUPPORT
LIGHTING FIXTURE SUPPORT
SUPPORT FOR JUNCTION BOX
PERFORATED TRAY SUPPORT
ANCHOR BOLT STAINLESS STEEL
MISCELLANEOUS FOR LIGHTING SYSTEM
SHANK BOLT AND NUT FOR PERFORATED CABLE
TRAYSTAINLESS STEEL
STAINLESS SHANK BOLT & NUT
HANGER FITTING FOR RACE WAY110x85x2.6t
THREAD STILL ROD FOR HANGER FITTING3/8"
STRONG ANCHOR NON DRILLING, STAINLESS
STEEL3/8"
UNISTRUT CHANNEL FOR RACE WAY SUPPORT41 X 41 X
2.6t
SHANK BOLT
60920
60930
60940
60950
60960
60970
60980
60990
61000
61010
61020
61030
Rate
Amount
SET
SET
EA
SET
EA
LOT
SET
570.00
0.00
633.00
2,962.00
240.00
1.00
13,777.00
110.00
0.00
87.00
230.00
37.00
122,210.00
17.00
62,700.00
0.00
55,071.00
681,260.00
8,880.00
122,210.00
234,209.00
EA
M
EA
EA
17,769.00
40.00
200.00
200.00
1.52
33.00
38.00
59.00
27,008.88
1,320.00
7,600.00
11,800.00
EA
200.00
70.00
14,000.00
13,777.00
8.76
120,686.52
1.00
1,465,134.40
1,465,134.40
EA
EA
EA
EA
62.00
20.00
34.00
40.00
57.00
55.00
31.00
31.00
3,534.00
1,100.00
1,054.00
1,240.00
Sub Total Lighting Receptacles: ea
156.00
44.41
6,928.00
EA
EA
EA
EA
81.00
20.00
50.00
54.00
0.00
77.00
30.00
29.00
0.00
1,540.00
1,500.00
1,566.00
Sub Total Light Switches: ea
205.00
22.47
4,606.00
Sub Total Lighting Devices: LS
1.00
11,534.00
11,534.00
EA
EA
EA
EA
37.00
1.00
222.00
153.00
6,180.00
5,950.00
2,240.00
1,790.00
228,660.00
5,950.00
497,280.00
273,870.00
Sub Total Light Poles: ea
413.00
2,435.25
1,005,760.00
Sub Total Lighting System: LS
1.00
7,757,177.30
7,757,177.30
EA
EA
EA
EA
14.00
20.00
77.00
23.00
48.00
39.00
48.00
48.00
672.00
780.00
3,696.00
1,104.00
Sub Total Control Switches: ea
134.00
46.66
6,252.00
SET
Sub Total Lighting Support: LS
60880
60890
60900
60910
Quantity
Lighting Devices
Lighting Receptacles
CONVENIENCE RECEPTACLE
CONVENIENCE RECEPTACLE
CONVENIENCE RECEPTACLEOUTDOOR
CONVENIENCE RECEPTACLEOUTDOOR
Light Switches
TUMBLER SWITCHGENERAL PURPOSE
TUMBLER SWITCHGENERAL
TUMBLER SWITCHINDUSTRIAL
TUMBLER SWITCHOUTDOOR
Light Poles
LIGHTING POLE FOR STREET LIGHTING
LIGHTING POLE FOR FLOOD LIGHTING
LIGHTING POLE FOR STANCHION MTD FIXTURE
LIGHTING POLE FOR STANCHION MTD FIXTURE
Power Generation System
Power Generatioin Equipment
Switches
Control Switches
Control SwitchON - OFF W/SEL. SW
Control SwitchON - OFF W/SEL. SW, AMMETER
Control SwitchON - OFF W/SEL. SW
CONTROL SWITCH STATION ON - OFF W/SEL. SW,
AMMETER
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
61040
61050
61060
61070
61080
61090
61100
61110
61120
61130
61140
61150
Description
Unit
Safety Switches
SAFETY SWITCH 3 PH, ( 480 )V, (60)HZ, SIZE : 16AF
SAFETY SWITCH 3 PH, ( 480 )V, (60)HZ, SIZE : 32AF
SAFETY SWITCH 3 PH, ( 480 )V, (60)HZ, SIZE : 100AF
SAFETY SWITCH 3 PH, ( 480 )V, (60)HZ, SIZE : 500AF
SAFETY SWITCH3 PH, ( 480 )V, (60)HZ, SIZE : 150AF
61220
61230
61240
61250
61270
61280
Amount
63.00
4.00
7.00
2.00
1.00
93.00
93.00
93.00
190.00
370.00
5,859.00
372.00
651.00
380.00
370.00
Sub Total Safety Switches: ea
77.00
99.12
7,632.00
Sub Total Switches: LS
1.00
13,884.00
13,884.00
EA
12.00
74.00
888.00
EA
5.00
180.00
900.00
Sub Total Welding Receptacle: ea
17.00
105.18
1,788.00
2.00
2.00
2.00
2.00
1.00
940.00
940.00
940.00
940.00
940.00
1,880.00
1,880.00
1,880.00
1,880.00
940.00
9.00
940.00
8,460.00
1.00
1.00
1.00
1.00
1.00
1.00
430.00
460.00
170.00
170.00
260.00
260.00
430.00
460.00
170.00
170.00
260.00
260.00
Sub Total Dry Type Transformer: Set
6.00
291.67
1,750.00
Sub Total Transformers: LS
1.00
10,210.00
10,210.00
2.00
2.00
2.00
1.00
680.00
590.00
590.00
1,270.00
1,360.00
1,180.00
1,180.00
1,270.00
7.00
712.86
4,990.00
PNL
18.00
1,370.00
24,660.00
PNL
18.00
1,370.00
24,660.00
PNL
11.00
1,480.00
16,280.00
Welding Receptacle
WELDING RECEPTACLE3 PH, ( 480 )V, (60)HZ, 3P + 1E.
WEATHER PROOF
WELDING RECEPTACLE3 PH, ( 480 )V, (60)HZ, 3P + 1E.
CLASS I,ZONE 2 IIC T4
Transformers
Power Transformer
Power Transformer 2000/2300kVA
Power Transformer2000/2300kVA
Power Transformer2000/2300kVA
Power Transformer2000/2300kVA
Power Transformer2000/2300kVA
SET
SET
SET
SET
SET
Dry Type Transformer
Dry Type Transformer90KVA
Dry Type Transformer100KVA
Dry Type Transformer30KVA
Dry Type Transformer: 30KVA
Dry Type Transformer50KVA
Dry Type Transformer50KVA
SET
SET
SET
SET
SET
SET
Power Systems
Power Capacitor
Power Capacitor225 KVA
Power Capacitor 180KVAR
Power Capacitor300KVAR
Power Capacitor( 600 )KVAR
SET
SET
SET
SET
Sub Total Power Capacitor: Set
61260
Rate
EA
EA
EA
EA
EA
Sub Total Power Transformer: ea
61160
61170
61180
61190
61200
61210
Quantity
Switchgear & MCC
L.V. SwitchGear & MCC3 PH,( 0.48 )V,(60)HZ, ( 80
)kA/(1)SEC
L.V. SwitchGear & MCC3 PH,( 0.48 )V,(60)HZ, ( 80
)kA/(1)SEC
L.V. SwitchGear & MCC3 PH,( 0.48 )V,(60)HZ, ( 80
)kA/(1)SEC
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
61290
61300
Description
Unit
L.V. SwitchGear & MCC3 PH,( 0.48 )V,(60)HZ, ( 80
)kA/(1)SEC
61340
1,270.00
16,510.00
Sub Total Switchgear & MCC: PNL
60.00
1,368.50
82,110.00
SET
1.00
1,040.00
1,040.00
1.00
1,040.00
1,040.00
1.00
1.00
1.00
1,220.00
1,220.00
1,220.00
1,220.00
1,220.00
1,220.00
Sub Total UPS & Battery : Set
3.00
1,220.00
3,660.00
Sub Total Power Systems: LS
1.00
91,800.00
91,800.00
3.00
86.00
258.00
1.00
258.00
258.00
1.00
220.00
220.00
1.00
220.00
220.00
PNL
2.00
430.00
860.00
PNL
1.00
430.00
430.00
PNL
1.00
430.00
430.00
PNL
2.00
430.00
860.00
PNL
2.00
430.00
860.00
PNL
1.00
430.00
430.00
Sub Total L.V. Main Distribution Panel: PNL
9.00
430.00
3,870.00
1.00
1.00
1.00
10,230.00
2,870.00
3,750.00
10,230.00
2,870.00
3,750.00
3.00
5,616.67
16,850.00
1.00
300.00
300.00
1.00
300.00
300.00
Battery Charger & Battery
Battery Charger & Battery
UPS & Battery
UPS & BATTERY( 1)PH, AC( 120)V, (60)HZ, (10)KVA
UPS & BATTERY( 1)PH, AC( 120)V, (60)HZ, (80)KVA
UPS & BATTERY( 1)PH, AC( 120)V, (60)HZ, (100)KVA
Panels
Interposing Relay Panel
INTERPOSING RELAY AND MARSHALLING PANELSIZE :
800W X 800D X 2350H X 3PNLS
SET
SET
SET
SET
Signal Concentrator Panel
SIGNAL CONCENTRATOR PANELW1600 x D600 x H1800 x SET
1PNL
Sub Total Signal Concentrator Panel: LS
61360
61370
61380
61390
61400
61410
61420
61430
61440
L.V. Main Distribution Panel
L.V. Main Distribution Panel3 PH,( 4 )W, ( 208-120 )V,60HZ,(
20 )kA, ( 1)SEC
L.V. Main Distribution Panel3 PH,( 4 )W, ( 480-277 )V,60HZ,(
80 )kA, ( 1)SEC
L.V. Main Distribution Panel3 PH,( 3 )W, ( 480 )V,60HZ,( 80
)kA, ( 1)SEC
L.V. Main Distribution Panel 3 PH,( 3 )W, ( 480 )V,60HZ,( 80
)kA, ( 1)SEC
L.V. Main Distribution Panel3 PH,( 3 )W, ( 480 )V,60HZ,( 80
)kA, ( 1)SEC
L.V. Main Distribution Panel3 PH,( 3 )W,
( 480 )V,60HZ,( 80 )kA, ( 1)SEC
VSD Panel
VSD Panel 3 PH, ( 0.48 )KV, 60HZ,
VSD Panel 3 PH, ( 0.48 )KV, 60HZ,
VSD Panel 3 PH, ( 0.48 )KV, 60HZ,
SET
SET
SET
Sub Total VSD Panel: Set
61450
Amount
13.00
Sub Total Interposing Relay Panel: LS
61350
Rate
PNL
Sub Total Battery Charger & Battery: LS
61310
61320
61330
Quantity
Annunciator Panel
ANNUNCIATOR PANEL BOARDSIZE : W800 x D800 x
H2100 x 1PNL
SET
Sub Total Annunciator Panel: LS
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
Description
Unit
Sub Total Panels: LS
61460
61470
61480
61490
61500
61510
61520
61530
61540
61550
61560
61570
61580
61590
61600
61610
61620
61630
61640
61650
61660
61670
61680
61690
61700
61710
61720
61730
61740
61750
61760
61770
61780
Rate
Amount
1.00
21,498.00
21,498.00
11.00
5.00
1.00
1.00
3.00
4.00
69.00
69.00
69.00
69.00
69.00
69.00
759.00
345.00
69.00
69.00
207.00
276.00
Sub Total Power Junction Box: Set
25.00
69.00
1,725.00
Sub Total Power Generatioin Equipment: LS
1.00
140,905.00
140,905.00
EA
EA
EA
EA
EA
EA
EA
EA
2.00
31.00
56.00
79.00
102.00
17.00
17.00
81.00
8.45
8.45
8.45
8.45
8.45
8.45
8.45
8.45
16.90
261.95
473.20
667.55
861.90
143.65
143.65
684.45
Sub Total Multi Cable Transit: ea
385.00
8.45
3,253.25
366.00
42.00
74.00
106.00
72.00
36.00
36.00
92.00
70.00
26.00
30.00
90.00
10.00
80.00
10.00
12.00
10.00
326.00
50.00
310.00
310.00
310.00
310.00
500.00
500.00
2,600.00
2,600.00
2,560.00
2,560.00
2,560.00
2,560.00
390.00
390.00
390.00
2,620.00
3,290.00
7.86
19.00
113,460.00
13,020.00
22,940.00
32,860.00
36,000.00
18,000.00
93,600.00
239,200.00
179,200.00
66,560.00
76,800.00
230,400.00
3,900.00
31,200.00
3,900.00
31,440.00
32,900.00
2,562.36
950.00
1,538.00
799.02
1,228,892.36
140.00
116.00
64.00
28.00
10.00
26.00
7.78
8.69
9.38
7.59
91.00
7.59
1,089.20
1,008.04
600.32
212.52
910.00
197.34
Power Junction Box
POWER JUNCTION BOX610W X 610H X 203D
POWER JUNCTION BOX 610W X 610H X 203D
POWER JUNCTION BOX610W X 610H X 203D
POWER JUNCTION BOX 610W X 610H X 203D
POWER JUNCTION BOX 610W X 610H X 203D
POWER JUNCTION BOX 610W X 610H X 203D
Power Generation Cabling
Multi Cable Transit
MULTI CABLE TRANSIT RM 90
MULTI CABLE TRANSIT RM 60
MULTI CABLE TRANSIT RM 40
MULTI CABLE TRANSIT RM 30
MULTI CABLE TRANSIT RM 20
MULTI CABLE TRANSIT ROX SF SINGLE FRAME SF-6x1
MULTI CABLE TRANSIT ROX WEDGE 120 mm
MULTI CABLE TRANSIT
LV Power Termination Point
POWER TERMINATION POINT
LV POWER TERMINATION POINT 3/C 4mm2
LV POWER TERMINATION POINT 3/C 6mm2
LV POWER TERMINATION POINT 3/C 10mm2
LV POWER TERMINATION POINT 3/C 16mm2
LV POWER TERMINATION POINT 3/C 25mm2
LV POWER TERMINATION POINT 3/C 35mm2
LV POWER TERMINATION POINT 3/C 50mm2
LV POWER TERMINATION POINT 3/C 70mm2
LV POWER TERMINATION POINT 3/C 95mm2
LV POWER TERMINATION POINT 3/C 120mm2
LV POWER TERMINATION POINT 3/C 150mm2
LV POWER TERMINATION POINT 3/C 185mm2
LV POWER TERMINATION POINT 4/C 6mm2
LV POWER TERMINATION POINT 4/C 10mm2
LV POWER TERMINATION POINT 4/C 16mm2
LV POWER TERMINATION POINT 4/C 50+25mm2
LV POWER TERMINATION POINT 4/C 150+70mm2
LV POWER TERMINATION POINT 12/C 2.5mm2
LV POWER TERMINATION POINT 19/C 2.5mm2
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
Sub Total POWER TERMINATION POINT: Set
61790
61800
61810
61820
61830
61840
Quantity
CONTROL TERMINATION POINT
LV CONTROL TERMINATION POINT 3/C 2.5mm2
LV CONTROL TERMINATION POINT 5/C 2.5mm2
LV CONTROL TERMINATION POINT 7/C 2.5mm2
LV CONTROL TERMINATION POINT 2P 0.75mm2
LV CONTROL TERMINATION POINT 24/P 1.00mm2
LV CONTROL TERMINATION POINT 2T 1.0mm2
SET
SET
SET
SET
SET
SET
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
61850
61860
61870
61880
61890
61900
61910
61920
61930
61940
61950
61960
61970
61980
61990
62000
62010
62020
62030
62040
62050
62060
62070
62080
62090
62100
62110
62120
62130
62140
62150
62160
62170
62180
62190
62200
62210
62220
62230
62240
62250
62260
62270
62280
62290
Description
LV CONTROL TERMINATION POINT 1/C 35mm2
LV CONTROL TERMINATION POINT 1/C 70mm2
LV CONTROL TERMINATION POINT 1/C 95mm2
LV CONTROL TERMINATION POINT 1/C 120mm2
LV CONTROL TERMINATION POINT 2/C 4mm2
LV CONTROL TERMINATION POINT 2/C 6mm2
LV CONTROL TERMINATION POINT 2/C 10mm2
LV CONTROL TERMINATION POINT 2/C 16mm2
LV CONTROL TERMINATION POINT 2/C 25mm2
LV CONTROL TERMINATION POINT 8P 1.0mm2
LV CONTROL TERMINATION POINT 9/C 2.5mm2
LV CONTROL TERMINATION POINT 4/C 4mm2
Unit
Rate
Amount
4.00
16.00
4.00
18.00
138.00
40.00
42.00
20.00
8.00
28.00
6.00
4.00
21.00
27.00
35.00
61.00
4.02
5.71
7.52
11.00
190.00
30.00
11.00
8.29
84.00
432.00
140.00
1,098.00
554.76
228.40
315.84
220.00
1,520.00
840.00
66.00
33.16
Sub Total CONTROL TERMINATION POINT: Set
712.00
13.41
9,549.58
Sub Total LV Power Termination Point: Set
2,250.00
550.42
1,238,441.94
EA
EA
EA
EA
25.00
91.00
36.00
5.00
310.00
370.00
2,560.00
4,270.00
7,750.00
33,670.00
92,160.00
21,350.00
Sub Total Motor Connections kit: ea
157.00
986.82
154,930.00
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
118.00
1,139.00
5,759.00
1,460.00
259.00
658.00
435.00
261.00
129.00
143.00
322.00
234.00
118.00
110.00
271.00
1.71
1.71
1.71
2.21
3.23
5.68
7.80
7.80
16.00
18.00
21.00
26.00
32.00
37.00
46.00
201.78
1,947.69
9,847.89
3,226.60
836.57
3,737.44
3,393.00
2,035.80
2,064.00
2,574.00
6,762.00
6,084.00
3,776.00
4,070.00
12,466.00
Sub Total Pressure Terminal: ea
11,416.00
5.52
63,022.77
750.00
1,884.00
408.00
46.00
292.00
2,698.00
5,255.00
559.00
849.00
2,932.00
7,746.00
11,494.00
9,464.00
2,776.00
2.87
4.53
3.35
1.47
1.28
0.77
0.86
0.92
1.03
0.86
0.86
0.86
1.03
1.21
2,152.50
8,534.52
1,366.80
67.62
373.76
2,077.46
4,519.30
514.28
874.47
2,521.52
6,661.56
9,884.84
9,747.92
3,358.96
Motor Connections kit
MOTOR CONNECTION KITS 2.5 ~ 6mm²
MOTOR CONNECTION KITS 4 ~ 25mm²
MOTOR CONNECTION KITS 35 ~ 120mm²
MOTOR CONNECTION KITS 150 ~ 300mm²
Pressure Terminal
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL
0.75mm²
1mm²
2.5mm²
4mm²
6mm²
10mm²
16mm²
25mm²
35mm²
50mm²
70mm²
95mm²
120mm²
150mm²
185mm²
Cable
Power Cable
POWER CABLE, ELECTRIC (MV).1/C * 240mm2
POWER CABLE, ELECTRIC (MV).1/C * 630mm2
POWER CABLE, ELECTRIC (MV).3/C * 240mm2
POWER CABLE, ELECTRIC (LV).1/C * 95mm2
POWER CABLE, ELECTRIC (LV).1/C * 120mm2
POWER CABLE, ELECTRIC (LV).2/C * 4mm2
POWER CABLE, ELECTRIC (LV).2/C * 10mm2
POWER CABLE, ELECTRIC (LV).2/C * 16mm2
POWER CABLE, ELECTRIC (LV).2/C * 25mm2
POWER CABLE, ELECTRIC (LV).2/C * 6mm2
POWER CABLE, ELECTRIC (LV).3/C * 10mm2
POWER CABLE, ELECTRIC (LV).3/C * 16mm2
POWER CABLE, ELECTRIC (LV).3/C * 25mm2
POWER CABLE, ELECTRIC (LV).3/C * 50mm2
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
Quantity
m
m
m
m
m
m
m
m
m
m
m
m
m
m
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
62300
62310
62320
62330
62340
62350
62360
62370
62380
62390
62400
62410
62420
62430
62440
62450
62460
62470
62480
62490
62500
62510
62520
62530
62540
62550
62560
62570
62580
62590
62600
62610
62620
62630
62640
62650
62660
62670
62680
62690
62700
62710
62720
62730
62740
62750
62760
Description
Unit
POWER CABLE, ELECTRIC (LV).3/C * 70mm2
POWER CABLE, ELECTRIC (LV).3/C * 95mm2
POWER CABLE, ELECTRIC (LV).3/C * 120mm2
POWER CABLE, ELECTRIC (LV).3/C * 150mm2
POWER CABLE, ELECTRIC (LV).3/C * 185mm2
POWER CABLE, ELECTRIC (LV).1/C * 35mm2
POWER CABLE, ELECTRIC (LV).1/C * 70mm2
POWER CABLE, ELECTRIC (LV).3/C * 6mm2
POWER CABLE, ELECTRIC (LV).3/C * 35mm2
POWER CABLE, ELECTRIC (LV).4/C * 4mm2
POWER CABLE, ELECTRIC (LV).3.5/C * 150mm2
POWER CABLE, ELECTRIC (LV).4/C * 16mm2
POWER CABLE, ELECTRIC (LV).4/C * 6mm2
POWER CABLE, ELECTRIC (LV).4/C * 10mm2
POWER CABLE, ELECTRIC (LV).3.5/C * 50mm2
POWER CABLE, ELECTRIC (LV).3/C * 4mm2
POWER CABLE, ELECTRIC (LV).4/C * 10mm2
Quantity
Rate
Amount
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
4,692.00
5,534.00
413.00
1,129.00
4,662.00
40.00
332.00
1,941.00
4,387.00
278.00
114.00
582.00
1,089.00
1,016.00
258.00
9,368.00
464.00
1.30
1.47
1.60
1.79
1.94
0.77
0.86
0.77
1.03
0.77
1.82
0.86
0.86
0.86
1.21
0.77
0.86
6,099.60
8,134.98
660.80
2,020.91
9,044.28
30.80
285.52
1,494.57
4,518.61
214.06
207.48
500.52
936.54
873.76
312.18
7,213.36
399.04
Sub Total Power Cable: m
83,452.00
1.15
95,602.52
m
m
m
m
m
m
m
m
m
m
m
m
1,457.00
5,857.00
2,255.00
1,444.00
36,593.00
464.00
3,780.00
1,533.00
816.00
400.00
840.00
376.00
1.82
0.64
0.72
0.79
0.04
1.08
1.08
0.64
0.79
1.08
1.89
1.89
2,651.74
3,748.48
1,623.60
1,140.76
1,463.72
501.12
4,082.40
981.12
644.64
432.00
1,587.60
710.64
Sub Total Control Cable: m
55,815.00
0.35
19,567.82
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
35.00
124.00
144.00
21.00
26.00
16.00
5.00
1,061.00
436.00
148.00
62.00
116.00
131.00
26.00
5.00
2.54
2.54
2.54
2.54
3.42
3.42
2.54
2.54
2.54
2.54
2.54
3.42
3.42
3.80
3.80
88.90
314.96
365.76
53.34
88.92
54.72
12.70
2,694.94
1,107.44
375.92
157.48
396.72
448.02
98.80
19.00
Sub Total Cable Glands: ea
2,356.00
2.66
6,277.62
12.00
4.00
2.00
61.00
81.00
99.00
732.00
324.00
198.00
18.00
69.67
1,254.00
Control Cable
CONTROL CABLE 2.5mm2
CONTROL CABLE 3/C * 2.5mm2
CONTROL CABLE 5/C * 2.5mm2
CONTROL CABLE 7/C * 2.5mm2
CONTROL CABLE 12/C * 2.5mm2
CONTROL CABLE 12/C * 2.5mm2
CONTROL CABLE 2P
CONTROL CABLE 2T 1.00MM2
CONTROL CABLE 8P/1.00MM2
CONTROL CABLE 24P/1.00MM2
CONTROL CABLE, ELECTRIC 7/C * 2.5mm2
CONTROL CABLE, ELECTRIC 19/C * 2.5mm2
Cable Glands
CABLE GLAND 1-1/2" (42mm)
CABLE GLAND 3/4" (22mm)
CABLE GLAND 1" (28mm)
CABLE GLAND 1-1/4" (36mm)
CABLE GLAND 2" (54mm)
CABLE GLAND 2-1/2" (70mm)
CABLE GLAND 1/2"
CABLE GLAND 3/4"
CABLE GLAND 1"
CABLE GLAND 1-1/4"
CABLE GLAND 1-1/2"
CABLE GLAND 2"
CABLE GLAND 2-1/2"
CABLE GLAND 3"
CABLE GLAND 4"
Cable Termination Kits
CABLE TERMINATION KIT.1/C * 240mm2
CABLE TERMINATION KIT.1/C * 630mm2
CABLE TERMINATION KIT.3/C * 240mm2
SET
SET
SET
Sub Total Cable Termination Kits: Set
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
62770
62780
62790
62800
62810
62820
62830
62840
62850
62860
62870
62880
62890
62900
62910
62920
62930
62940
62950
62960
62970
62980
62990
Description
Unit
Variable Speed Drive Cable
VARIABLE SPEED DRIVE CABLE3/C * 150mm2
VARIABLE SPEED DRIVE CABLE3/C * 185mm2
VARIABLE SPEED DRIVE CABLE3/C * 4mm2
VARIABLE SPEED DRIVE CABLE3/C * 10mm2
VARIABLE SPEED DRIVE CABLE3/C * 95mm2
VARIABLE SPEED DRIVE CABLE3/C * 70mm2
Quantity
Rate
Amount
m
m
m
m
m
m
20.00
1,244.00
2,081.00
525.00
666.00
722.00
1.78
1.99
0.77
0.77
1.47
1.30
35.60
2,475.56
1,602.37
404.25
979.02
938.60
Sub Total Variable Speed Drive Cable: m
5,258.00
1.22
6,435.40
Sub Total Cable: LS
1.00
129,137.36
129,137.36
Sub Total Power Generation Cabling: LS
1.00
1,588,785.32
1,588,785.32
m
m
m
m
m
m
m
m
m
M
M
M
m
M
M
1,015.00
231.00
126.00
552.00
95.00
81.00
2,420.00
32.00
89.00
4,826.00
5,127.00
1,192.00
214.00
228.00
21.00
4.22
7.95
10.00
16.00
21.00
3.66
7.82
30.00
55.00
55.00
17.00
17.00
35.00
17.00
17.00
4,283.30
1,836.45
1,260.00
8,832.00
1,995.00
296.46
18,924.40
960.00
4,895.00
265,430.00
87,159.00
20,264.00
7,490.00
3,876.00
357.00
Sub Total PVC Conduit: m
16,249.00
26.33
427,858.61
EA
1,394.00
31.00
43,214.00
EA
68.00
36.00
2,448.00
Sub Total PVC Plugs: ea
1,462.00
31.23
45,662.00
Sub Total PVC Conduit: LS
1.00
473,520.61
473,520.61
427.00
1,432.00
92.00
120.00
39,284.00
171,840.00
Power Generation Conduit
PVC Conduit
PVC Conduit
HI PVC CONDUIT 1" (28mm)
HI PVC CONDUIT 1-1/2" (42mm)
HI PVC CONDUIT 2" (54mm)
HI PVC CONDUIT 2-1/2" (70mm)
HI PVC CONDUIT 3" (82mm)
HI PVC CONDUIT 3/4" (22mm)
HI PVC CONDUIT 1-1/4" (36mm)
HI PVC CONDUIT 3-1/2"
HI PVC CONDUIT 6" (150MM)
PVC CONDUIT 6"
PVC CONDUIT 6"
PVC CONDUIT 6"
PVC CONDUIT 200mm
PVC CONDUIT 200mm
PVC CONDUIT 200mm
PVC Plugs
PVC CONDUIT PLUG
SIZE : 6"
PVC CONDUIT PLUG
SIZE : 8"
Rigid Steel Conduit
Rigid Steel Conduit Straight
SPECIFICATION :
RIGID STEEL CONDUIT HOT DIP GALVANIZED, METRIC
THREADED BOTH ENDS WITH 1-COUPLING, SIZE:
3600mmL X 1" NPT
SUPPLIED By Sub-Con.
63000
63010
RIGID STEEL CONDUIT3/4" (22mm)
RIGID STEEL CONDUIT1" (28mm)
m
m
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
63020
63030
63040
63050
63060
63070
63080
Description
RIGID STEEL CONDUIT1-1/4" (36mm)
RIGID STEEL CONDUIT1-1/2" (42mm)
RIGID STEEL CONDUIT2-1/2" (70mm)
RIGID STEEL CONDUIT3" (82mm)
RIGID STEEL CONDUIT3-1/2" (92mm)
RIGID STEEL CONDUIT 2"
RIGID STEEL CONDUIT 6"
Unit
Quantity
Rate
Amount
m
m
m
m
m
m
m
1,223.00
95.00
570.00
86.00
5.00
13.00
21.00
190.00
200.00
370.00
510.00
630.00
260.00
1,000.00
232,370.00
19,000.00
210,900.00
43,860.00
3,150.00
3,380.00
21,000.00
Sub Total Rigid Steel Conduit Straight: m
3,872.00
192.35
744,784.00
EA
EA
EA
EA
EA
EA
EA
EA
EA
116.00
73.00
9.00
55.00
426.00
394.00
45.00
30.00
13.00
110.00
140.00
200.00
14.00
20.00
38.00
43.00
59.00
990.00
12,760.00
10,220.00
1,800.00
770.00
8,520.00
14,972.00
1,935.00
1,770.00
12,870.00
Sub Total Rigid Steel Elbow: ea
1,161.00
56.52
65,617.00
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
186.00
623.00
532.00
41.00
6.00
248.00
37.00
2.00
9.00
18.00
14.00
21.00
35.00
47.00
34.00
34.00
34.00
34.00
34.00
34.00
2,604.00
13,083.00
18,620.00
1,927.00
204.00
8,432.00
1,258.00
68.00
306.00
612.00
Sub Total Rigid Steel Conduit Clamps: ea
1,702.00
27.68
47,114.00
Sub Total Rigid Steel Conduit: m
3,872.00
221.47
857,515.00
Sub Total Power Generation Conduit: LS
1.00
1,331,035.61
1,331,035.61
63280
63290
Power Generation Cable Tray
Cable Tray Elbow
CABLE TRAY VERT. ELBOW(90 DEGREE-IN) * 600mmW
EA
CABLE TRAY VERT. ELBOW(90 DEGREE-OUT) * 600mmW EA
2.00
2.00
33.00
33.00
66.00
66.00
63300
63310
63320
63330
CABLE TRAY TEE * 900mmW
CABLE TRAY HORIZ. ELBOW(90 DEGREE) * 900mmW
CABLE TRAY VERT. ELBOW(90 DEGREE-IN) * 450mmW
CABLE TRAYVERT. ELBOW(90 DEGREE-OUT) * 300mmW
EA
EA
EA
EA
5.00
4.00
2.00
3.00
38.00
38.00
33.00
32.00
190.00
152.00
66.00
96.00
63340
CABLE TRAYVERT. ELBOW(90 DEGREE-OUT) * 450mmW EA
2.00
33.00
66.00
63350
63360
CABLE TRAYVERT. ELBOW(90 DEGREE-IN) * 300mmW
EA
COVER FOR CABLE TRAYVERT. ELBOW(90 DEGREE-IN) * ea
300mmW
2.00
2.00
32.00
32.00
64.00
64.00
63090
63100
63110
63120
63130
63140
63150
63160
63170
Rigid Steel Elbow
RIGID STEEL ELBOW2-1/2" (70mm)
RIGID STEEL ELBOW3" (82mm)
RIGID STEEL ELBOW3-1/2" (92mm)
RIGID STEEL ELBOW3/4" (22mm)
RIGID STEEL ELBOW1" (28mm)
RIGID STEEL ELBOW1-1/4" (36mm)
RIGID STEEL ELBOW 1-1/2" (42mm)
RIGID STEEL ELBOW 2"
RIGID STEEL ELBOW 6"
Rigid Steel Conduit Clamps
I STOP HERE, TO BE CONTINUED ON
SATURDAY..................
63180
63190
63200
63210
63220
63230
63240
63250
63260
63270
CONDUIT CLAMP 3/4"
CONDUIT CLAMP 1"
CONDUIT CLAMP 1-1/4"
CONDUIT CLAMP 1-1/2"
CONDUIT CLAMP 2"
CONDUIT CLAMP 2-1/2"
CONDUIT CLAMP 3"
CONDUIT CLAMP 3-1/2"
CONDUIT CLAMP 4"
CONDUIT CLAMP 1-1/4"
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
63370
63380
63390
63400
63410
63420
63430
63440
63450
63460
63470
63480
63490
63500
63510
63520
63530
63540
63550
63560
63570
63580
63590
63600
63610
63620
63630
63640
63650
Description
COVER FOR CABLE TRAYHORIZ. ELBOW(90 DEGREE) *
300mmW
COVER FOR CABLE TRAYVERT. ELBOW(90 DEGREE-IN) *
450mmW
COVER FOR CABLE TRAYVERT. ELBOW(90 DEGREEOUT) * 300mmW
COVER FOR CABLE TRAYVERT. ELBOW(90 DEGREEOUT) * 450mmW
CABLE TRAY TEE * 600mmW
CABLE TRAY HORIZ. ELBOW(90 DEGREE) * 300mmW
CABLE TRAY HORIZ. ELBOW(90 DEGREE) * 450mmW
CABLE TRAY HORIZ. ELBOW(90 DEGREE) * 600mmW
COVER FOR CABLE TRAY HORIZ. ELBOW(90 DEGREE) *
450mmW
Unit
Rate
Amount
ea
6.00
32.00
192.00
ea
2.00
33.00
66.00
ea
3.00
32.00
96.00
ea
2.00
33.00
66.00
EA
EA
EA
EA
m
1.00
6.00
2.00
2.00
2.00
33.00
32.00
33.00
33.00
33.00
33.00
192.00
66.00
66.00
66.00
Sub Total Cable Tray Elbow: ea
50.00
33.46
1,673.00
EA
EA
EA
EA
EA
2.00
5.00
1.00
24.00
69.00
2.54
1.78
1.78
3.17
1.27
5.08
8.90
1.78
76.08
87.63
EA
10.00
1.27
12.70
EA
EA
EA
EA
EA
EA
EA
1,078.00
104.00
132.00
14.00
40.00
40.00
304.00
0.25
0.25
0.25
0.25
0.38
0.38
0.38
269.50
26.00
33.00
3.50
15.20
15.20
115.52
Sub Total Cable Tray Fittings: ea
1,823.00
0.37
670.09
m
m
m
m
m
m
m
96.00
240.00
72.00
108.00
12.00
72.00
108.00
33.00
38.00
41.00
33.00
33.00
33.00
33.00
3,168.00
9,120.00
2,952.00
3,564.00
396.00
2,376.00
3,564.00
Sub Total Cable Tray Straight: m
708.00
35.51
25,140.00
1.00
27,483.09
27,483.09
m3
m3
m3
m3
EA
20,273.00
12,159.00
7,652.26
930.00
52,912.00
1.90
69.00
44.00
1.90
3.16
38,518.70
838,971.00
336,699.40
1,767.00
167,201.92
Sub Total Power Generation Civil Works: LS
1.00
1,383,158.02
1,383,158.02
Cable Tray Fittings
BLIND END PLATEEND BLIND PLATE * 600mmW
BLIND END PLATEEND BLIND PLATE * 300mmW
BLIND END PLATEEND BLIND PLATE * 450mmW
BLIND END PLATEEND BLIND PLATE * 900mmW
SEPERATOR FOR CABLE TRAY150 mmH *
STRAIGHT(3000MML)
SEPERATOR FOR CABLE TRAY150 mmH * VERT.
ELBOW(600)
CABLE TRAY HOLE DOWN CLAMPS
CABLE TRAY COVER CLAMPS W: 300mm
CABLE TRAY COVER CLAMPS W: 450mm
CABLE TRAY COVER CLAMPS W: 600mm
ADJUSTABLE RISER CONNECTOR VERTICAL TYPE
ADJUSTABLE RISER CONNECTOR HORIZONTAL TYPE
JOINT CONNECTOR THICKNESS : 2.6t(8 HOLES)
Cable Tray Straight
CABLE TRAY STRAIGHT * 600mmW
CABLE TRAY STRAIGHT * 900mmW
CABLE TRAYSTRAIGHT * 300mmW
CABLE TRAYSTRAIGHT * 450mmW
COVER FOR CABLE TRAYSTRAIGHT * 600mmW
COVER FOR CABLE TRAYSTRAIGHT * 300mmW
COVER FOR CABLE TRAYSTRAIGHT * 450mmW
Sub Total Power Generation Cable Tray: LS
63660
63670
63680
63690
63700
Quantity
Power Generation Civil Works
EXCAVATION WORK
BACK FILLING AND COMPACTION
SAND FILLING AND COMPACTION
EXCAVATION & BACK FILL WORK
RED CONCRETE
Power Generation Bus
Bus Duct
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
63710
63720
63730
63740
63750
63760
63770
63780
63790
Description
Unit
BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA
BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA
BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA
BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA
BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA
BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA
BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA
BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA
BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA
SET
SET
SET
SET
SET
SET
SET
SET
SET
63810
63820
63830
63840
63850
63860
63870
63880
63890
63900
63910
63920
63930
780.00
780.00
780.00
780.00
500.00
780.00
720.00
500.00
780.00
9.00
711.11
6,400.00
1,200.00
1.88
2,256.00
Sub Total Modular Bus: LS
1.00
2,256.00
2,256.00
Sub Total Power Generation Bus: LS
1.00
8,656.00
8,656.00
m
m
m
m
m
869.00
86.00
86.00
86.00
86.00
65.00
150.00
160.00
180.00
190.00
56,485.00
12,900.00
13,760.00
15,480.00
16,340.00
Sub Total Steel Angle: m
1,213.00
94.78
114,965.00
m
SET
EA
333.00
53.00
212.00
73.00
96.00
55.00
24,309.00
5,088.00
11,660.00
SET
SET
SET
SET
SET
211.00
25.00
17.00
30.00
9.00
520.00
520.00
97.00
1,100.00
1,100.00
109,720.00
13,000.00
1,649.00
33,000.00
9,900.00
1.00
208,326.00
208,326.00
2,176.00
6,488.00
30.00
55.00
143.00
40.00
1,166.00
949.00
111.00
474.00
157.00
3.00
91.00
58.00
24.00
17.00
69.00
71.00
75.00
73.00
24.00
26.00
29.00
36.00
44.00
50.00
16.00
91.00
52,224.00
110,296.00
2,070.00
3,905.00
10,725.00
2,920.00
27,984.00
24,674.00
3,219.00
17,064.00
6,908.00
150.00
1,456.00
5,278.00
Modular Bus
RSS485(MODBUS)SHIELDED TWIST PAIR CABLE
Power Generation Support
Steel Angle
STEEL ANGLE 50 x 50 x 6t
STEEL ANGLE 200 x 2.6t
STEEL ANGLE 300 x 2.6t
STEEL ANGLE 500 x 2.6t
STEEL ANGLE 800 x 2.6t
Support
CABLE TRAY SUPPORT 100 * 50 * 5T
CABLE TRAY SUPPORT STEEL(0.75M/SET)
BASE STEEL PLATE FOR CABLE TRAY SUPPORT 260 x
160 x 12t
CONTROL STATION SUPPORT
POWER JUNCTION BOX SUPPORT
WELDING RECEPTACLE SUPPORT
SUPPORT FOR BUS DUCT
SUPPORT FOR BUS DUCT
Clamps
HOLD DOWN CLAMP
SHANK BOLT AND NUT
COVER CLAMPBAND TYPE
COVER CLAMPBAND TYPE
COVER CLAMPBAND TYPE
COVER CLAMPBAND TYPE
UNISTRUT CLAMP1" (28mm)
UNISTRUT CLAMP1-1/4" (36mm)
UNISTRUT CLAMP1-1/2" (42mm)
UNISTRUT CLAMP2-1/2" (70mm)
UNISTRUT CLAMP3" (82mm)
UNISTRUT CLAMP3-1/2" (92mm)
UNISTRUT CLAMP3/4" (22mm)
CONDUIT CLAMP FOR OUTSIDE RAIL TRAY
1" (28mm)
Amount
780.00
780.00
780.00
780.00
500.00
780.00
720.00
500.00
780.00
M
Sub Total Support: LS
63940
63950
63960
63970
63980
63990
64000
64010
64020
64030
64040
64050
64060
64070
Rate
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
Sub Total Bus Duct: Set
63800
Quantity
EA
SET
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
Description
Unit
Quantity
Rate
Amount
64080
CONDUIT CLAMP FOR OUTSIDE RAIL TRAY
EA
213.00
100.00
21,300.00
64090
1-1/4" (36mm)
CONDUIT CLAMP FOR OUTSIDE RAIL TRAY
EA
5.00
170.00
850.00
64100
2-1/2" (70mm)
CONDUIT CLAMP FOR OUTSIDE RAIL TRAY
EA
24.00
180.00
4,320.00
64110
3" (82mm)
CONDUIT CLAMP FOR OUTSIDE RAIL TRAY
EA
6.00
82.00
492.00
Sub Total Clamps: LS
1.00
295,835.00
295,835.00
EA
EA
EA
508.00
55.00
44.00
110.00
140.00
95.00
55,880.00
7,700.00
4,180.00
EA
44.00
120.00
5,280.00
Sub Total Connectors: ea
651.00
112.20
73,040.00
2,358.00
28.00
66,024.00
3/4" (22mm)
64120
64130
64140
64150
Connectors
JOINT CONNECTOR150mmH
EXPANSION CONNECTOR
ADJUSTABLE CONNECTOR 150mmH * HORIZONTAL
TYPE
ADJUSTABLE CONNECTOR 150mmH * VERTICAL TYPE
64160
Other
EXPANSION ANCHOR FOR TRAY SUPPORT STAINLESS
STEEL (4EA /SET)
EA
64170
WARNING TAPE 3" wide x 305m length x 2.5mm th'k
Roll
483.00
430.00
207,690.00
64180
64190
CABLE ROUTE MARKER
GROUNDING BONDING JUMPER WITH TERMINAL
LUG35mm2
UNISTRUT CHANNELSTRAIGHT(3000mmL)
MISCELLANEOUS FOR POWER SYSTEM
STRONG ANCHOR BOLT M12xL75
NUT M12xL50
ANCHOR BOL M20xL500
WARNING SIGN
SCREWS BOLT 1/4"
CABLE ROUTE MARKER
EXPANSION ANCHOR 1/2"- 30
SHANK BOLT STEEL 8 mm DIA /19mmL
EXPANSION CONNECTOR THICKNESS : 2.6t(8 HOLES)
EA
EA
239.00
192.00
270.00
0.46
64,530.00
88.32
EA
LOT
EA
57.00
1.00
188.00
180.00
551,850.00
4.14
10,260.00
551,850.00
778.32
EA
EA
EA
EA
EA
EA
EA
52.00
11.00
6,880.00
1,659.00
938.00
3,883.00
33.00
4.99
9.22
2.66
250.00
220.00
5.24
85.00
259.48
101.42
18,300.80
414,750.00
206,360.00
20,346.92
2,805.00
Sub Total Other: LS
1.00
1,564,144.26
1,564,144.26
Sub Total Power Generation Support: LS
1.00
2,256,310.26
2,256,310.26
M/D
M/D
540.00
270.00
160.00
190.00
86,400.00
51,300.00
Sub Total Power Generation Commissioning: M/D
810.00
170.00
137,700.00
1.00
6,874,033.30
6,874,033.30
64200
64210
64220
64230
64240
64250
64260
64270
64280
64290
64300
64310
Power Generation Commissioning
Commissioning & Start-up Assist (LABOR)
Commissioning & Start-up Assist (TECHNICIANS)
Sub Total Power Generation System: LS
Cathodic Protection System
Cathodic Protection Anodes
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
64320
64330
64340
64350
64360
64370
64380
64390
64400
64410
64420
64430
64440
64450
64460
64470
64480
64490
64500
64510
64520
64530
64540
64550
64560
64570
Description
Standard Anode
IMPRESSED CURRENT ANODE MMO(MIXED METAL
OXIDE)
SACRIFICIAL ANODE TEMPORARY CATHODIC
PROTECTION
SACRIFICIAL ANODE TEMPORARY CATHODIC
PROTECTION
Unit
Quantity
Rate
Amount
EA
116.00
43,860.00
5,087,760.00
EA
116.00
4,690.00
544,040.00
EA
44.00
47,770.00
2,101,880.00
Sub Total Standard Anode: ea
276.00
28,020.58
7,733,680.00
M
M
1,200.00
1,200.00
13.00
96.00
15,600.00
115,200.00
Sub Total Ribbon Anode: m
2,400.00
54.50
130,800.00
EA
104.00
4,350.00
452,400.00
Sub Total Reference Electrodes: LS
1.00
452,400.00
452,400.00
EA
10.00
200.00
2,000.00
EA
10.00
120.00
1,200.00
Sub Total Anode Power Feed Connectors: ea
20.00
160.00
3,200.00
Sub Total Cathodic Protection Anodes: ea
1.00
8,320,080.00
8,320,080.00
EA
EA
518.00
518.00
25.00
430.00
12,950.00
222,740.00
Sub Total Cathodic Protection CADWelding: ea
1,036.00
227.50
235,690.00
M
M
700.00
700.00
36.00
250.00
25,200.00
175,000.00
Sub Total Cathodic Protection Conductor Bar: m
1,400.00
143.00
200,200.00
M
M
M
M
M
M
M
M
M
M
M
M
M
M
800.00
1,600.00
1,550.00
375.00
400.00
4,500.00
375.00
800.00
1,600.00
1,550.00
375.00
400.00
4,500.00
375.00
48.00
250.00
250.00
59.00
81.00
81.00
58.00
17.00
42.00
42.00
72.00
100.00
51.00
72.00
38,400.00
400,000.00
387,500.00
22,125.00
32,400.00
364,500.00
21,750.00
13,600.00
67,200.00
65,100.00
27,000.00
40,000.00
229,500.00
27,000.00
Sub Total Cathodic Protection Cabling: m
19,200.00
90.42
1,736,075.00
Ribbon Anode
MMO RIBBON ANODE 6.4MM X 0.64T
MMO RIBBON ANODE 6.4MM X 0.64T
Reference Electrodes
REFERFNCE ELECTRODE PERMANENT TYPE
Anode Power Feed Connectors
ANODE POWER FEEDER CONNECTOR 3MM Ti ROD X
25M/ROLL
ANODE POWER FEEDER CONNECTOR 3MM Ti ROD X
25M/ROLL
Cathodic Protection CADWelding
CAD WELD WIRE TO STEEL SURFACE TYPE
CAD WELD
Cathodic Protection Conductor Bar
CONDUCTOR BAR, 12.7MM X 0.89T
CONDUCTOR BAR, 12.7MM X 0.89T
Cathodic Protection Cabling
TEST LEAD CABLE HMWPE CABLE 1C 10MM2
MONITORING CABLE HMWPE CABLE 1C 16MM2
ANOD LEAD CABLE HMWPE CABLE 16MM2 1C
NEGATIVE CABLE HMWPE CABLE 1C 35MM2
NEGATIVE CABLE HMWPE CABLE 1C 50MM2
POSITIVE CABLE HMWPE-CV-IC-25MM2
POSITIVE CABLE HMWPE-CV-1C-35MM2
TEST LEAD CABLE 1C 10MM2
MONITORING CABLE 1C 16MM2
ANOD LEAD CABLE 16MM2 1C
NEGATIVE CABLE 1C 35MM2
NEGATIVE CABLE 1C 50MM2
POSITIVE CABLE 25MM2
POSITIVE CABLE 35MM2
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
64580
Description
Unit
Cathodic Protection Conduit
Conduit
RIGID STEEL CONDUITHOT DIP GALVANIZED, NPT
THREADED BOTH ENDSWITH 1-COUPLING, 4"
RIGID STEEL CONDUIT 4"
Quantity
Rate
Amount
m
2,500.00
63.00
157,500.00
m
2,500.00
230.00
575,000.00
Sub Total Conduit: m
5,000.00
146.50
732,500.00
m
69.00
57.00
3,933.00
EA
104.00
130.00
13,520.00
EA
104.00
31.00
3,224.00
EA
65.00
34.00
2,210.00
m
EA
EA
EA
69.00
104.00
104.00
65.00
280.00
510.00
17.00
29.00
19,320.00
53,040.00
1,768.00
1,885.00
Sub Total Fittings: LS
1.00
98,900.00
98,900.00
1.00
831,400.00
831,400.00
22.00
22.00
25.00
81.00
5,050.00
4,660.00
3,740.00
1,340.00
111,100.00
102,520.00
93,500.00
108,540.00
150.00
2,771.07
415,660.00
SET
9.00
47,770.00
429,930.00
EA
1.00
47,770.00
47,770.00
EA
3.00
47,770.00
143,310.00
EA
1.00
47,770.00
47,770.00
Sub Total Cathodic Protection Equipment: Set
14.00
47,770.00
668,780.00
EA
EA
EA
EA
244.00
202.00
244.00
202.00
770.00
770.00
840.00
540.00
187,880.00
155,540.00
204,960.00
109,080.00
Sub Total Cathodic Protection Markers: ea
892.00
737.06
657,460.00
64800
Cathodic Protection Miscellaneous
MISCELLANEOUS FOR CATHODIC PROTECTION SYSTEM EA
1.00
144,570.00
144,570.00
64810
DESK FOR COMPUTER OPERATION
1.00
2,600.00
2,600.00
64590
64600
64610
64620
64630
64640
64650
64660
64670
Fittings
CONDUIT ELBOW 90' HOT DIP GALVANIZED, NPT
THREADED BOTH ENDS WITH 2-COULING 1"
SEALING FITTINGFLAME EXPLOSION PROOF TYPE,
UNIVERSAL
CONDUIT CLAMP WITH 304SS BOLT & NUT UNISTRUT
TYPE STAINLESS STEEL(304SS), 41 X 41 X 2.6t
3M LONG 2" DEA. SLOTTED PVC PIPE INSERTED IN GEOTEXTILE SOCK
CONDUIT ELBOW 90' 1"
SEALING FITTING
CONDUIT CLAMP 4" (104mm)
PVC PIPE 3M LONG 2" DEA.
Sub Total Cathodic Protection Conduit: m
64680
64690
64700
64710
Cathodic Protection Junction Boxes
ANODE JUNCTIION BOX EXPLOSION PROOF TYPE
NEGATIVE JUNCTION BOX WEATHER PROOF
BONDIN BOX WEATHER PROOF TYPE
TEST BOX FOR CATHODIC PROTECTION EXPLOSION
PROOF TYPE
EA
EA
ea
SET
Sub Total Cathodic Protection Junction Boxes: ea
64720
64730
64740
64750
64760
64770
64780
64790
Cathodic Protection Equipment
TRANSFORMER RECTIFIER FOR CATHODIC
PROTECTION WEATHER PROOF TYPE
TRANSFORMER RECTIFIER FOR CATHODIC
PROTECTION WEATHER PROOF TYPE
TRANSFOMER RECTIFIER FOR CATHODIC PROTECTION
WEATHER PROOF TYPE
TRANSFOMER RECTIFIER FOR CATHODIC PROTECTION
WEATHER PROOF TYPE
Cathodic Protection Markers
ANODE MARKER
CABLE MARKER
ANODE MARKER
CABLE MARKER
EA
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
64820
64830
64840
64850
64860
64870
64880
64890
Description
Unit
PERSONAL COMPUTER AND MONITOR FOR CP SYSTEM EA
MONITORING
DIRECT BURIAL CABLE TRENCH FOR ANODE CATHODE M
REFERENCE ELECTRODE CABLES 600mmW X 715mmD
64940
64950
64960
64970
64980
64990
65000
Rate
Amount
1.00
57.00
57.00
7,000.00
48.00
336,000.00
CATHODIC PROTECTION
EA
DESK FOR COMPUTER OPERATION
EA
PERSONAL COMPUTER AND MONITOR FOR CP SYSTEM EA
MONITORING
1.00
1.00
1.00
92,320.00
17,090.00
17,090.00
92,320.00
17,090.00
17,090.00
Sub Total Cathodic Protection Miscellaneous: ea
7,006.00
87.03
609,727.00
Sub Total Cathodic Protection System: LS
1.00
13,675,072.00
13,675,072.00
SET
2.00
2,870.00
5,740.00
SET
SET
8.00
8.00
2,930.00
460.00
23,440.00
3,680.00
18.00
1,825.56
32,860.00
m
m
m
m
2,227.00
2,169.00
210.00
80.00
15.00
12.00
12.00
12.00
33,405.00
26,028.00
2,520.00
960.00
Sub Total Cable: m
4,686.00
13.43
62,913.00
EA
EA
12.00
36.00
6.34
6.34
76.08
228.24
Sub Total Cable Gland: ea
48.00
6.34
304.32
Sub Total CCTV Cabling: LS
1.00
63,217.32
63,217.32
m
m
129.00
269.00
34.00
22.00
4,386.00
5,918.00
Sub Total Conduit: m
398.00
25.89
10,304.00
m
EA
EA
65.00
80.00
80.00
25.00
16.00
8.76
1,625.00
1,280.00
700.80
Sub Total Clamp: LS
1.00
3,605.80
3,605.80
Sub Total CCTV Conduit: LS
1.00
13,909.80
13,909.80
CCTV System
CCTV Equipment
CCTV SYSTEM EQUIPMENT19" 42U EQUIPMENT
CABINETINDOOR
COLOR CAMERA SONY'S MODEL FCB-EX SERIES
WASHER TANK FOR COLOR CAMERA
Sub Total CCTV Equipment: Set
64900
64910
64920
64930
Quantity
CCTV Cabling
Cable
POWER CABLE, ELECTRIC 3/C * 4mm2
FIBER OPTIC CABLE4C SINGLE MODE
FIBER OPTIC ABLE4C SINGLE MODE
COMPOSITE CABLE FOR CCTV CAMERA
Cable Gland
CABLE GLANDEXPLOSION PROOF TYPE3/4"
CABLE GLANDWEATHER PROOF3/4"
CCTV Conduit
Conduit
RIGID STEEL CONDUIT 3/4"
PVC CONDUITSCHEDULE 40
Clamp
CONDUIT CLAMP 3/4"
CONDUIT CLAMPUNISTRUT TYPE 3/4"
CONDUIT CLAMP
CCTV Cable Tray
Tray
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
65010
65020
Description
Unit
PERFORATED CABLE TRAYSTRAIGHT
PERFORATED CABLE TRAY SUPPORT
m
SET
65070
65080
65090
65140
65150
65160
4,407.00
9,890.00
1.00
14,297.00
14,297.00
EA
EA
EA
EA
170.00
170.00
204.00
204.00
10.00
6.70
69.00
17.00
1,700.00
1,139.00
14,076.00
3,468.00
Sub Total Clamps: LS
1.00
20,383.00
20,383.00
Sub Total CCTV Cable Tray: LS
1.00
34,680.00
34,680.00
EA
8.00
100.00
800.00
Sub Total CCTV Junction Boxes: LS
1.00
800.00
800.00
1.00
1.00
1,180.00
1,400.00
1,180.00
1,400.00
1.00
2,580.00
2,580.00
EA
EA
m
m
8.00
1,019.00
16.00
20.00
1,700.00
17.00
70.00
75.00
13,600.00
17,323.00
1,120.00
1,500.00
EA
8.00
78.00
624.00
1,219.00
1,219.00
17.00
8.76
20,723.00
10,678.44
1.00
65,568.44
65,568.44
1.00
86,900.00
86,900.00
Sub Total CCTV Miscellaneous: LS
1.00
86,900.00
86,900.00
Sub Total CCTV System: LS
1.00
300,515.56
300,515.56
m3
EA
EA
456.00
12.00
11.00
67.00
420.00
420.00
30,552.00
5,040.00
4,620.00
Sub Total Fire Alarm Civil Work: LS
1.00
40,212.00
40,212.00
400.00
2,382.00
11.00
11.00
4,400.00
26,202.00
Clamps
JOINT CONNECTOR
COVER CLAMP FOR PERFORATED CT
COVER CLAMP FOR PERFORATED CABLE TRAY50MM
COVER CLAMP
CCTV Junction Boxes
JUNCTION BOX WITH COVER AND GASKET
CCTV Computer Equipment
24 PORT LAN SWITCH, CISCO, WS-C3750E
WORK STATION WITH KEYBOARD
SET
SET
CCTV Support
POLE FOR CCTV CAMERA SET
STAINLESS SHANK BOLT & NUT
STEEL ANGLE HOT DIP GALVANIZED STEEL
UNISTRUT CHANNELHOT DIP GALVANIZED STEEL41 X
41 X 2.6t
STEEL PLATE HOT DIP GALVANIZED STEEL 500 X 300 X
6t
SHANK BOLT AND NUT
SHANK BOLT
SET
SET
Sub Total CCTV Support: LS
65170
65180
65190
65200
65210
65220
Amount
13.00
230.00
Sub Total CCTV Computer Equipment: LS
65100
65110
65120
65130
Rate
339.00
43.00
Sub Total Tray: LS
65030
65040
65050
65060
Quantity
CCTV Miscellaneous
MISCELLANEOUS FOR CCTV SYSTEM
Fire Alarm System
Fire Alarm Civil Work
EXCAVATION & BACK FILL WORK
FOUNDATION FOR MPS POLEW305 x D305 x H914
FOUNDATION FOR MPS POLEW305 x D305 x H510
Fire Alarm Cabling
Cable
LINEAR HEAT DETECTOR CABLE
FIRE ALARM CABLE, ELECTRIC.
1P-1.5mm2
LOT
m
m
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
65230
65240
65250
65260
65270
65280
65290
65300
65310
65320
65330
65340
65350
65360
65370
65380
65390
65400
65410
65420
Description
Unit
FIRE ALARM CABLE, ELECTRIC.
6C-2.5mm2
FIRE ALARM CABLE, ELECTRIC.
2C-2.5mm2
FIRE ALARM CABLE, ELECTRIC.
3C-2.5mm2
FIRE ALARM CABLE, ELECTRIC.
4C-2.5mm2
FIRE ALARM CABLE, ELECTRIC.
12C-2.5mm2
FIRE ALARM CABLE, ELECTRIC.
19C-2.5mm2
FIRE ALARM CABLE, ELECTRIC.
30C-2.5mm2
CABLE FOR GAS DETECTOR1P-1.0mm2
FIRE ALARM CABLE, ELECTRIC.
10C-2.5mm2
65440
65450
Rate
Amount
m
95.00
11.00
1,045.00
m
7,743.00
11.00
85,173.00
m
285.00
11.00
3,135.00
m
520.00
11.00
5,720.00
m
1,330.00
11.00
14,630.00
m
4,233.00
11.00
46,563.00
m
505.00
11.00
5,555.00
m
m
42.00
24.00
11.00
11.00
462.00
264.00
Sub Total Cable: m
17,559.00
11.00
193,149.00
EA
258.00
16.00
4,128.00
EA
2.00
20.00
40.00
EA
6.00
22.00
132.00
EA
1.00
26.00
26.00
EA
140.00
16.00
2,240.00
EA
4.00
20.00
80.00
EA
13.00
22.00
286.00
Sub Total Cable Gland: ea
424.00
16.35
6,932.00
Sub Total Fire Alarm Cabling: LS
1.00
200,081.00
200,081.00
m
5,368.00
42.00
225,456.00
m
565.00
56.00
31,640.00
m
317.00
27.00
8,559.00
m
35.00
76.00
2,660.00
1.00
268,315.00
268,315.00
m
1,642.00
24.00
39,408.00
m
45.00
26.00
1,170.00
m
568.00
28.00
15,904.00
Cable Gland
CABLE GLAND
3/4"
CABLE GLAND
1"
CABLE GLAND
1-1/2"
CABLE GLAND
2"
CABLE GLAND
3/4"
CABLE GLAND
1"
CABLE GLAND
1-1/2"
Fire Alarm Conduit
Rigid Steel Conduit
RIGID STEEL CONDUIT
HOT DIP GALVANIZED, NPT THREADED BOTH ENDS1"
RIGID STEEL CONDUIT
1-1/4"
RIGID STEEL CONDUIT
1-1/2"
RIGID STEEL CONDUIT
2"
Sub Total Rigid Steel Conduit: LS
65430
Quantity
PVC Conduit
PVC CONDUIT (SCHEDULE 40)
1"
PVC CONDUIT (SCHEDULE 40)
1-1/4"
PVC CONDUIT (SCHEDULE 40)
1-1/2"
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
65460
65470
65480
65490
65500
65510
65520
65530
65540
65550
65560
65570
65580
65590
Description
Unit
PVC CONDUIT (SCHEDULE 40)
2"
Quantity
Rate
Amount
m
23.00
38.00
874.00
Sub Total PVC Conduit: m
2,278.00
25.18
57,356.00
m
38.00
110.00
4,180.00
Sub Total Flexible Metal Conduit: m
38.00
110.00
4,180.00
EA
EA
EA
EA
EA
EA
EA
EA
EA
1,398.00
90.00
149.00
2,000.00
3,957.00
754.00
2,000.00
3,957.00
754.00
29.00
35.00
38.00
25.00
29.00
35.00
97.00
130.00
160.00
40,542.00
3,150.00
5,662.00
50,000.00
114,753.00
26,390.00
194,000.00
514,410.00
120,640.00
Sub Total Conduit Clamp: ea
15,059.00
71.02
1,069,547.00
Sub Total Fire Alarm Conduit: LS
1.00
1,399,398.00
1,399,398.00
M
M
60.00
30.00
20.00
59.00
1,200.00
1,770.00
Sub Total Tray: m
90.00
33.00
2,970.00
EA
30.00
6.70
201.00
Sub Total Clamps: ea
30.00
6.70
201.00
Sub Total Fire Alarm Cable Tray: LS
1.00
3,171.00
3,171.00
Flexible Metal Conduit
FLEXIBLE METALLIC CONDUIT
3/4"
Conduit Clamp
CONDUIT CLAMP1"
CONDUIT CLAMP1-1/4"
CONDUIT CLAMP1-1/2"
CONDUIT CLAMP 3/4"
CONDUIT CLAMP 1"
CONDUIT CLAMP 1 1/4"
CONDUIT CLAMP 3/4"
CONDUIT CLAMP 1"
CONDUIT CLAMP 1-1/4"
Fire Alarm Cable Tray
Tray
PERFORATED CABLE TRAY100 X 50
PERFORATED CABLE TRAY100MM
Clamps
COVER CLAMP100MM
65600
Fire Alarm Devices
Fire Alarm Stations
FIRE ALARM MANUAL STATION
EA
30.00
150.00
4,500.00
65610
FIRE ALARM MANUAL STATION
EA
18.00
140.00
2,520.00
65620
FIRE ALARM MANUAL STATION
EA
14.00
120.00
1,680.00
65630
CO2 DISCHARGE MANUAL STATION
EA
1.00
140.00
140.00
Sub Total Fire Alarm Stations: ea
63.00
140.32
8,840.00
65640
Warning Devices
FIRE ALARM SIREN (MEDC DB3 RANGE)
SET
38.00
190.00
7,220.00
65650
FIRE ALARM SIREN (MEDC DB3 RANGE)
SET
44.00
190.00
8,360.00
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
Description
Unit
Quantity
Rate
Amount
65660
FIRE ALARM HORN/STROBE
EA
12.00
340.00
4,080.00
65670
FIRE ALARM HORN/STROBE
EA
6.00
340.00
2,040.00
65680
FLASH LIGHT FOR FIRE ALARM(BEACON)
EA
8.00
250.00
2,000.00
65690
FLASH LIGHT FOR FIRE ALARM(BEACON)
EA
8.00
250.00
2,000.00
65700
CO2 DISCHARGE WARNING LIGHT (LAMP)
EA
1.00
250.00
250.00
65710
CO2 DISCHARGE WARNING SIREN
EA
1.00
320.00
320.00
Sub Total Warning Devices: LS
1.00
26,270.00
26,270.00
65720
Fire Alarm Detectors
FIRE DETECTOR
EA
41.00
320.00
13,120.00
65730
DUCT SMOKE DETECTOR
EA
12.00
320.00
3,840.00
65740
FIRE DETECTOR
EA
1.00
110.00
110.00
65750
FIRE DETECTOR
EA
62.00
110.00
6,820.00
65760
BEAM DETECTOR
EA
5.00
110.00
550.00
Sub Total Fire Alarm Detectors: ea
121.00
201.98
24,440.00
EA
1.00
140.00
140.00
Sub Total Fire Alarm Switches: ea
1.00
140.00
140.00
Sub Total Fire Alarm Devices: LS
1.00
59,690.00
59,690.00
m
532.00
75.00
39,900.00
m
35.00
140.00
4,900.00
1,641.00
180.00
6.00
22.00
17.00
230.00
36,102.00
3,060.00
1,380.00
1.00
85,342.00
85,342.00
EA
1.00
450.00
450.00
EA
15.00
380.00
5,700.00
EA
16.00
380.00
6,080.00
EA
1.00
310.00
310.00
Sub Total Termination Boxes: ea
33.00
380.00
12,540.00
65770
65780
65790
65800
65810
65820
Fire Alarm Switches
CO2 DISCHARGE ABORT SWITCH
Fire Alarm Support
UNISTRUT CHANNEL HOT DIP GALVANIZED STEEL41 X
41 X 2.6t
STEEL CHANNEL HOT DIP GALVANIZED STEEL100 x 50 x
5t
EXPANSION ANCHOR3/8"
STAINLESS SHANK BOLT & NUT
PERFORATED CABLE TRAY SUPPORT
EA
EA
SET
Sub Total Fire Alarm Support: LS
65830
65840
65850
65860
Fire Alarm Panels & Boxes
Termination Boxes
TERMINAL BOX FOR FIRE ALARM
40TB
TERMINAL BOX FOR FIRE ALARM
20TB
TERMINAL BOX FOR FIRE ALARM
20TB
TERMINAL BOX FOR FIRE ALARM
5TB
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
Description
Unit
Quantity
Rate
Amount
65870
Junction Boxes
4" SQUARE BOX
EA
45.00
49.00
2,205.00
65880
4" SQUARE BOX
EA
77.00
49.00
3,773.00
65890
65900
BUSHING & LOCK NUT FOR SQUARE BOX 1"
BUSHING & LOCK NUT FOR SQUARE BOX 1-1/4"
EA
EA
220.00
24.00
15.00
16.00
3,300.00
384.00
Sub Total Junction Boxes: ea
366.00
26.40
9,662.00
3.00
2,740.00
8,220.00
3.00
2,740.00
8,220.00
4.00
2,740.00
10,960.00
Sub Total Fire Alarm Cabinets: LS
1.00
10,960.00
10,960.00
Sub Total Fire Alarm Panels & Boxes: LS
1.00
41,382.00
41,382.00
65910
Fire Alarm Panels
ADDRESSABLE FIRE ALARM PANEL
SET
Sub Total Fire Alarm Panels: Set
65920
Fire Alarm Cabinets
EDIO CABINET WITH 4 EDIO MODULES(400)W X (150)D X SET
(405)H
65930
Fire Alarm Miscellaneous
LINEAR HEAT DETECTOR WITH INTERFACE MODULE
SET
1.00
2,740.00
2,740.00
65940
MISCELLANEOUS FOR FIRE ALRAM SYSTEM
LOT
1.00
136,870.00
136,870.00
Sub Total Fire Alarm Miscellaneous: LS
1.00
139,610.00
139,610.00
Sub Total Fire Alarm System: LS
1.00
1,968,886.00
1,968,886.00
EA
EA
11.00
11.00
120.00
73.00
1,320.00
803.00
Sub Total Grounding Reels: ea
22.00
96.50
2,123.00
161.00
180.00
28,980.00
161.00
180.00
28,980.00
m
m
m
m
5,258.00
8,844.00
2,089.00
435.00
38.00
81.00
38.00
96.00
199,804.00
716,364.00
79,382.00
41,760.00
Sub Total Ground Wire: m
16,626.00
62.39
1,037,310.00
65950
65960
65970
Grounding System
Grounding Reels
GROUND REEL(EXPLOSION PROOF15m LONG
STEEL PLATE FOR GROUND REEL203 x 203 x 13t
Ground Conductors
Ground Rods
GROUNDING ROD WITH CONNECTOR38mmDIA *
1520mmL
SET
Sub Total Ground Rods: Set
65980
65990
66000
66010
Ground Wire
GROUNDING WIRE, ELECTRIC35mm2
GROUNDING WIRE, ELECTRIC.70mm2
GROUNDING WIRE, ELECTRIC.35mm2
GROUNDING WIRE, ELECTRIC.120mm2
Bus Bar
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
66020
66030
66040
66050
66060
66070
66080
66090
66100
66110
66120
66130
66140
66150
66160
66170
Description
Unit
TINNED COPPER GROUNDING BUS BAR6mmT X 50mmW SET
X 356mmL
Quantity
Rate
Amount
67.00
520.00
34,840.00
Sub Total Bus Bar: LS
1.00
34,840.00
34,840.00
Sub Total Ground Conductors: LS
1.00
1,101,130.00
1,101,130.00
EA
59.00
630.00
37,170.00
EA
21.00
630.00
13,230.00
EA
1.00
630.00
630.00
EA
6.00
640.00
3,840.00
EA
EA
EA
2.00
2.00
1.00
630.00
630.00
630.00
1,260.00
1,260.00
630.00
Sub Total Thermal Moulds: ea
92.00
630.65
58,020.00
EA
1,395.00
42.00
58,590.00
EA
344.00
45.00
15,480.00
EA
7.00
53.00
371.00
EA
104.00
56.00
5,824.00
EA
EA
EA
24.00
19.00
4.00
56.00
61.00
56.00
1,344.00
1,159.00
224.00
Sub Total Thermal Welding Powder: ea
1,897.00
43.75
82,992.00
Sub Total Grounding Thermal Welds: LS
1.00
141,012.00
141,012.00
m
3,515.00
28.00
98,420.00
Sub Total Conduit: m
3,515.00
28.00
98,420.00
866.00
1,130.00
1,130.00
26.00
25.00
8.76
22,516.00
28,250.00
9,898.80
Sub Total Clamps: LS
1.00
60,664.80
60,664.80
Sub Total Grounding System Conduit: LS
1.00
159,084.80
159,084.80
Grounding Thermal Welds
Thermal Moulds
MOLD WITH FRAME FOR GROUND WIRE
CONNECTIONMAIN: 70mm2 * TAP: 35mm2
MOLD WITH FRAME FOR GROUND WIRE
CONNECTIONMAIN: 70mm2 * TAP: 70mm2
MOLD WITH FRAME FOR GROUND WIRE
CONNECTIONMAIN: 120mm2 * TAP: 70mm2
MOLD WITH FRAME FOR GROUND WIRE
CONNECTIONMAIN: 240mm2 * TAP: 240mm2
MOLD WITH FRAMEMAIN: 240mm2 * TAP: 70mm2
MOLD WITH FRAMEMAIN: 240mm2 * TAP: 240mm2
MOLD WITH FRAME MAIN: 70mm2 * TAP: 70mm2
Thermal Welding Powder
THERMAL WELDING POWDER FOR GROUND WIRE
CONNECTION # 45
THERMAL WELDING POWDERFOR GROUND WIRE
CONNECTION# 115
THERMAL WELDING POWDER FOR GROUND WIRE
CONNECTION# 150
THERMAL WELDING POWDER FOR GROUND WIRE
CONNECTION# 150
THERMAL WELDING POWDER# 150
THERMAL WELDING POWDER# 500
THERMAL WELDING POWDER# 150
Grounding System Conduit
Conduit
PVC CONDUIT SCHEDULE 40 PVC
3/4" (22mm)
66180
66190
66200
Clamps
CONDUIT CLAMP ONE HOLE
CONDUIT CLAMP
CONDUIT CLAMP 3/4"
Grounding Support
EA
SET
SET
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
66210
66220
66230
66240
Description
Unit
UNISTRUT CHANNEL
UNISTRUT CHANNEL
STEEL CHANNEL FOR GROUND REEL100 * 50 * 5T
UNISTRUT CLAMP3/4" (22mm)
75.00
75.00
81.00
16.00
13,500.00
675.00
2,187.00
22,336.00
Sub Total Grounding Support: LS
1.00
38,698.00
38,698.00
2,385.00
67.00
159,795.00
11.00
7.00
88.00
270.00
968.00
1,890.00
1.00
162,653.00
162,653.00
58.00
850.00
49,300.00
1.00
49,300.00
49,300.00
2.00
840.00
1,680.00
Sub Total Bonding Boxes: LS
1.00
1,680.00
1,680.00
Sub Total Grounding Boxes: LS
1.00
50,980.00
50,980.00
EA
EA
1,365.00
335.00
46.00
54.00
62,790.00
18,090.00
EA
18.00
46.00
828.00
Sub Total Servit Posts: ea
1,718.00
47.56
81,708.00
EA
EA
58.00
12.00
120.00
93.00
6,960.00
1,116.00
Sub Total Fence Post Grounding Connector: ea
70.00
115.37
8,076.00
EA
12.00
730.00
8,760.00
Sub Total Copper Braid: ea
12.00
730.00
8,760.00
Sub Total Grounding Connectors: LS
1.00
98,544.00
98,544.00
SET
198.00
320.00
63,360.00
SET
2,089.00
54.00
112,806.00
EA
SET
145.00
44.00
51.00
25.00
7,395.00
1,100.00
m3
66260
66270
BASE CONCRETE FOR GROUND REEL305 x 305 x 5t
GROUNDING CABLE ROUTE MARKERSHEET
EA
SET
Sub Total Grounding System Civil Work: LS
Grounding Boxes
Concrete Boxes
GROUND WELLCONCRETE BOX TYPE267mm 438mm
305mm (EA)
SET
Sub Total Concrete Boxes: LS
66300
66310
66320
66330
66340
66350
66360
66370
66380
66390
Amount
180.00
9.00
27.00
1,396.00
Grounding System Civil Work
EXCAVATION & BACK FILL WORK
66290
Rate
EA
EA
m
EA
66250
66280
Quantity
Bonding Boxes
GROUND BONDING BOX
SET
Grounding Connectors
Servit Posts
CONNECTION SERVIT POST
CONNECTION SERVIT POST 25-70 mm²1/2"-13 x 3/4"
STUD
CONNECTION SERVIT POST FOR TRANSFORMER
Fence Post Grounding Connector
FENCE POST GROUNDING CONECTOR2"
FENCE POST GROUNDING CONECTOR1-1/2"
Copper Braid
COPPER BRAID FOR FENCE GATE GROUND1"W x 12"L
Grounding Accessories
AIR TERMINALCOPPER WITH NICKEL 5/8"(DIA) 1'(LONG)
(EA)
SUPPORT FOR LIGHTNING CONDUCTOR CLIP TYPE 35
mm2
GROUND LUG (WITH/15mm HOLE)128 x 50 x 6t
HEX HEAD BOLT, SPRING NUT AND LOCK WASHER1/4" x
20mm
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
66400
66410
66420
66430
66440
66450
66460
66470
66480
66490
66500
66510
66520
66530
66540
66550
66560
66570
66580
66590
66600
66610
66620
66630
66640
66650
66660
Description
Unit
MOUNTING BASE250 x 250 x 6T
WARINING SIGN STEEL PLATE 76 x 76 x 6t
MISCELLANEOUS FOR GROUNDING SYSTEM
EXPANSION ANCHOR,1/2" - 30
STANDOFF INSULATOR FOR GROUNDING BUS BAR
ALL THREAD ROD1/2"-13 x 4"L
EXPANSION ANCKOR,1/2"-20
1/2" MACHINE BOLT1/2"-20
1/2" NUT, HEX1/2"-13
1/2" LOCKWASHER
1/2" LOCKWASHER
PARALLEC CLAMP FOR LIGHTNING DOWN
CONDUCTOR35 mm²
SUPPORT FOR AIR TERMINAL(OUTSIDE)
MACHINE BOLT1/2" x 20mm
ANCHOR BOLT
ANCHOR BOLT
MACHINE BOLT 1/2" x 20mm
ANCHOR BOLT 1/2" x 30mm
ANCHOR BOLT 1/2" x 30mm
66710
66720
66730
66740
66750
Rate
Amount
EA
EA
LOT
EA
EA
EA
EA
EA
EA
EA
EA
EA
198.00
11.00
1.00
44.00
84.00
84.00
134.00
134.00
335.00
413.00
80.00
48.00
230.00
57.00
41,760.00
24.00
63.00
18.00
17.00
9.72
9.72
8.96
8.96
51.00
45,540.00
627.00
41,760.00
1,056.00
5,292.00
1,512.00
2,278.00
1,302.48
3,256.20
3,700.48
716.80
2,448.00
SET
SET
EA
EA
SET
EA
EA
8.00
96.00
33.00
59.00
96.00
33.00
59.00
510.00
9.72
37.00
37.00
8.76
8.76
8.76
4,080.00
933.12
1,221.00
2,183.00
840.96
289.08
516.84
Sub Total Grounding Accessories: LS
1.00
304,213.96
304,213.96
Sub Total Grounding System: LS
1.00
2,058,438.76
2,058,438.76
1.00
1.00
2.00
2.00
4.00
20.00
69.00
4.00
2,180.00
2,180.00
2,180.00
2,180.00
190.00
92.00
300.00
300.00
2,180.00
2,180.00
4,360.00
4,360.00
760.00
1,840.00
20,700.00
1,200.00
1.00
37,580.00
37,580.00
m
m
m
m
129.00
352.00
261.00
3,028.00
29.00
20.00
20.00
14.00
3,741.00
7,040.00
5,220.00
42,392.00
Sub Total Telephone System Cabling: m
3,770.00
15.49
58,393.00
m
m
1,550.00
146.00
34.00
28.00
52,700.00
4,088.00
Sub Total Conduit: m
1,696.00
33.48
56,788.00
EA
EA
EA
74.00
776.00
74.00
8.76
16.00
17.00
648.24
12,416.00
1,258.00
Sub Total Clamps: ea
924.00
15.50
14,322.24
Communications System
Telephone System
Telephone System Equipment
19" EQPT CABINET
19" EQPT CABINET
19" EQPT CABINET
19" EQUT CABINET
TELEPHONE HANDSET ASSEMBLY
INDOOR TELEPHONE HANDSET
STATION TERMINAL OUTLET4 PORT TYPE, RJ45
TELEPHONE OUTLETINDOOR 4 PORT
SET
SET
SET
SET
EA
EA
EA
EA
Sub Total Telephone System Equipment: LS
66670
66680
66690
66700
Quantity
Telephone System Cabling
TELEPHONE CABLE, ELECTRIC50P-0.75mm2
TELEPHONE CABLE, ELECTRIC10P-0.75mm2
TELEPHONE CABLE, ELECTRIC4P-0.75mm2
UTPCAT NO.6, 4 PAIRS, UNARMORED
Telephone System Conduit
Conduit
RIGID STEEL CONDUITHOT DIP GALVANIZED3/4"
PVC CONDUIT SCHEDULE 40WITH3/4"
Clamps
UNISTRUT CLAMP 3/4"
UNISTRUT CLAMP HOT DIP GALVANIZED3/4"
UNISTRUT CLAMP
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
Description
Unit
Sub Total Telephone System Conduit: LS
66760
66770
66790
66800
66810
66820
66830
66840
66850
66860
66870
66880
66890
66900
66910
Rate
Amount
1.00
71,110.24
71,110.24
m3
589.00
67.00
39,463.00
Sub Total Telephone System Civil Work: LS
1.00
39,463.00
39,463.00
73.00
49.00
3,577.00
73.00
49.00
3,577.00
m
79.00
75.00
5,925.00
EA
405.00
37.00
14,985.00
Sub Total Telephone System Support: LS
1.00
20,910.00
20,910.00
1.00
65,920.00
65,920.00
Sub Total Telephone System Miscellaneous: LS
1.00
65,920.00
65,920.00
Sub Total Telephone System: LS
1.00
296,953.24
296,953.24
SET
SET
SET
4.00
4.00
4.00
2,870.00
2,870.00
1,990.00
11,480.00
11,480.00
7,960.00
SET
SET
5.00
1.00
1,990.00
1,990.00
9,950.00
1,990.00
EA
1.00
350.00
350.00
Sub Total Computer Equipment: LS
1.00
43,210.00
43,210.00
m
m
897.00
299.00
11.00
23.00
9,867.00
6,877.00
Sub Total Computer Cabling: m
1,196.00
14.00
16,744.00
Computer Panels
FIBER OPTIC PATCH PANELW800 X D630 X H2000
EA
FIBER OPTIC PATCH PANELINDOOR USEFOPP MODULE EA
1.00
12.00
2,870.00
1,990.00
2,870.00
23,880.00
Sub Total Computer Panels: LS
1.00
26,750.00
26,750.00
1.00
61,620.00
61,620.00
1.00
61,620.00
61,620.00
Telephone System Civil Work
EXCAVATION & BACK FILL WORK
Telephone System Junction Boxes
4" SQUARE BOXZINC ELECTRO PLATE
SET
Sub Total Telephone System Junction Boxes: Set
66780
Quantity
Telephone System Support
UNISTRUT CHANNELHOT DIP GALVANIZED STEEL41 X
41 X 2.6t
EXPANSION ANCHOR3/8"
Telephone System Miscellaneous
MISCELLANEOUS FOR TELEPHONE SYSTEM
Computer System
Computer Equipment
LAN/IP SYSTEM COMPONENTINDOOR
LAN/IP SYSTEM COMPONENT48PORT ACCESS SWITCH
LAN/IP SYSTEM COMPONENT24PORT UTP PATCH
PANEL
LAN/IP SYSTEM COMPONENTUPS MODULEADELMO
LAN/IP SYSTEM COMPONENTANALOGUE PHONE
GATEWAYCISCO
PERSONAL COMPUTERFOR WEATHER MONITRING
SYSTEM
Computer Cabling
FIBER OPTIC CABLESINGLE MODE4C
FIBER OPTIC CABLESINGLE MODE, PVC INSULATED,
STEEL WIRE ARMOURED48C
Computer Miscellaneous
MISCELLANEOUS FOR LAN SYSTEM
LOT
LOT
Sub Total Computer Miscellaneous: LS
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
Description
Unit
Sub Total Computer System: LS
66920
66930
66940
66950
66960
66970
66980
66990
67000
67010
67020
67060
67070
67080
67090
67100
67110
67120
67130
Amount
148,324.00
148,324.00
SET
1.00
8,980.00
8,980.00
SET
1.00
8,390.00
8,390.00
EA
EA
EA
1.00
2.00
17.00
3,040.00
2,150.00
380.00
3,040.00
4,300.00
6,460.00
EA
33.00
340.00
11,220.00
EA
EA
SET
SET
SET
47.00
1.00
10.00
2.00
2.00
340.00
200.00
170.00
2,650.00
1,700.00
15,980.00
200.00
1,700.00
5,300.00
3,400.00
1.00
68,970.00
68,970.00
m
m
m
6,655.00
228.00
285.00
16.00
40.00
47.00
106,480.00
9,120.00
13,395.00
Sub Total Cable: m
7,168.00
18.00
128,995.00
EA
EA
45.00
45.00
6.34
6.34
285.30
285.30
Sub Total Cable Gland: ea
90.00
6.34
570.60
Sub Total Paging System Cabling: LS
1.00
129,565.60
129,565.60
m
m
EA
1,785.00
703.00
36.00
34.00
28.00
0.00
60,690.00
19,684.00
0.00
Sub Total Conduit: LS
1.00
80,374.00
80,374.00
m
EA
EA
893.00
1,207.00
1,207.00
16.00
17.00
8.76
14,288.00
20,519.00
10,573.32
Sub Total Clamps: LS
1.00
45,380.32
45,380.32
Sub Total Paging System Conduit: LS
1.00
125,754.32
125,754.32
Paging System
Paging System Equipment
CENTRAL PAGING EQUIPMENTTYCO MODEL NO.ACE
100INDOOR
REMOTE PAGING EQUIPMENTTYCO MODEL NO.ACE
100RAINDOOR
EE872 DIGITAL HAND SET MASTER STATION
HAND SET STATION EXPLOSION PROOF
CONE SPEAKER ASSEMBLY (FOR PAGING)INDOOR
USE6W
CONE SPEAKER ASSEMBLY (FOR PAGING)INDOOR
USE6W
HORN SPEAKER ASSEMBLY15W
BEACON LAMP
HAND HELD RADIOOUTDOOR USE
MOBILE RADIOVEHICLES USETRANSMITTER
BATTERY CHARGER FOR RADIO SYSTEMINDOOR
Paging System Cabling
Cable
COMMUNICATION CABLE, ELECTRIC1P-2.5mm2
COMMUNICATION CABLE, ELECTRIC 2C - 2.5mm2
COMMUNICATION CABLE, ELECTRIC2P- 1.5mm2
Cable Gland
CABLE GLAND, NICKEL PLATEWEATHER PROOF3/4"
CABLE GLAND, NICKEL PLATEEXPLOSION PROOF3/4"
Paging System Conduit
Conduit
RIGID STEEL CONDUIT HOT DIP GALVANIZED3/4"
PVC CONDUITSCHEDULE 40 3/4"
FLEXIBLE METALLIC CONDUIT INDOOR 3/4"
Clamps
UNISTRUT CLAMP HOT DIP GALVANIZED 3/4"
UNISTRUT CLAMP HOT DIP GALVANIZED STEEL
CLAMP 3/4"
Paging System Support
Rate
1.00
Sub Total Paging System Equipment: LS
67030
67040
67050
Quantity
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
67140
67150
67160
67170
67180
Description
Unit
UNISTRUT CHANNEL HOT DIP GALVANIZED STEEL41 X
41 X 2.6t
HANDSET SUPPORT
SPEAKER SUPPORTWITH
67200
67210
67220
67230
67240
67250
67260
67270
67280
67290
Amount
75.00
17,475.00
2.00
4.00
530.00
250.00
1,060.00
1,000.00
Sub Total Paging System Support: LS
1.00
19,535.00
19,535.00
Paging System Civil Work
EXCAVATION & BACK FILL WORK FOR PAGING SYSTEM m3
130.00
67.00
8,710.00
Sub Total Paging System Civil Work: LS
1.00
8,710.00
8,710.00
82.00
49.00
4,018.00
1.00
4,018.00
4,018.00
1.00
73,980.00
73,980.00
Sub Total Paging System Miscellaneous: LS
1.00
73,980.00
73,980.00
Sub Total Paging System: LS
1.00
430,532.92
430,532.92
Sub Total Communications System: LS
1.00
875,810.16
875,810.16
9.00
970.00
8,730.00
EA
EA
EA
854.00
848.00
58.00
44.00
12.00
12.00
37,576.00
10,176.00
696.00
Sub Total Heat Tracing Equipment: LS
1.00
57,178.00
57,178.00
m
m
19,120.00
167.00
12.00
12.00
229,440.00
2,004.00
m
37,820.00
35.00
1,323,700.00
Sub Total Cable: m
57,107.00
27.23
1,555,144.00
6.00
70.00
4,800.00
44.00
22.00
7.37
264.00
1,540.00
35,376.00
Sub Total Cable Accessories: LS
1.00
37,180.00
37,180.00
Sub Total Heat Tracing Cabling: LS
1.00
1,592,324.00
1,592,324.00
SET
SET
SET
Sub Total Paging System Junction Boxes: LS
67190
Rate
233.00
Paging System Junction Boxes
4" SQUARE BOXZINC ELECTRO PLATE
m
Quantity
Paging System Miscellaneous
MISCELLANEOUS FOR PA SYSTEM
LOT
Heat Tracing System
Heat Tracing Equipment
TRANSFORMER ( ELECTRICAL HAET TRACING
SYSTEM)DRY TYPE
THERMOSTAT SENSOR
CIRCUIT FABRICATION KIT
POWER TERMINATION KITOUTDOOR
Heat Tracing Cabling
Cable
SELF REGULATING HEATING CABLE
MINERAL INSULATED CABLE THERMON CAT NO. MIQ
SERIES
POWER CABLE, ELECTRIC 3/C * 4mm2
Cable Accessories
COLD & HOT LEAD FOR MI CABLE
ALUMINUM TAPE THERMON
CAUTION LABELTHERMON
Heat Tracing Cable Tray
Cable Tray
SET
EA
ROLL
EA
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
67300
67310
67320
67330
67340
67350
67360
67370
67380
67390
67400
67410
67420
Description
Unit
PERFORATED CABLE TRAYPUNCHED TYPE100mmW X
50mmH X
67480
67490
67500
Amount
12,810.00
32.00
409,920.00
Sub Total Cable Tray: m
12,810.00
32.00
409,920.00
EA
EA
35.00
70.00
57.00
12.00
1,995.00
840.00
EA
13.00
18.00
234.00
EA
4.00
18.00
72.00
EA
4.00
18.00
72.00
EA
13.00
12.00
156.00
EA
4.00
12.00
48.00
EA
EA
EA
4.00
252.00
286.00
12.00
8.54
22.00
48.00
2,152.08
6,292.00
Sub Total Cable Tray Accessories: LS
1.00
11,909.08
11,909.08
Sub Total Heat Tracing Cable Tray: LS
1.00
421,829.08
421,829.08
M3
10.00
5,210.00
52,100.00
Sub Total Heat Tracing Civil Work: LS
1.00
52,100.00
52,100.00
9.00
750.00
6,750.00
1.00
6,750.00
6,750.00
35.00
600.00
144.00
520.00
230.00
37.00
18,200.00
138,000.00
5,328.00
1.00
161,528.00
161,528.00
EA
EA
244.00
4.00
100.00
44.00
24,400.00
176.00
Sub Total Heat Tracing Junction Boxes: LS
1.00
24,576.00
24,576.00
95.00
1,300.00
1.00
11.00
12.00
42,110.00
1,045.00
15,600.00
42,110.00
1.00
58,755.00
58,755.00
Cable Tray Accessories
CABLE TRAYSTRAIGHT600mmW
TRAY COVER (FOR STRAIGHT) VENTILATED
TYPE600mmW
VERTICAL ELBOW (90°),(R = 600 mm),(OUTSIDE
TYPE)600mmW
VERTICAL ELBOW (90°),(R = 600 mm),(IN SIDE
TYPE)600mmW
HORIZONTAL ELBOW (90°),(R = 600 mm)
TRAY COVER (FOR VERTICAL ELBOW OUTSIDE TYPE)
600mmW
TRAY COVER (FOR VERTICAL ELBOW INSIDE
TYPE)600mmW
TRAY COVER (FOR HORIZONTAL ELBOW)600mmW
CABLE TRAY COVER CLAMPS
CABLE TRAY HOLE DOWN CLAMPS
Heat Tracing Civil Work
NON-SHRINK GROUT
Heat Tracing Panels
ELECTRICAL HEAT TRACING CONTROL PANEL( 36 )CKT SET
Heat Tracing Support
CABLE TRAY SUPPORT
PERFORATED CABLE TRAY SUPPORT
ANCHOR BOLT STAINLESS STEEL, M12, 600mmL
SET
SET
EA
Sub Total Heat Tracing Support: LS
67460
67470
Rate
m
Sub Total Heat Tracing Panels: LS
67430
67440
67450
Quantity
Heat Tracing Junction Boxes
JUNCTION BOX EXPLOSION PROOF
BLIND END PLATES600mmW
Heat Tracing Miscellaneous
METALLIC TEE CONNECTION KITOUTDOOR
POLYESTER FIBER TAPE THERMON
MISCELLANEOUS FOR ELECTRICAL HAET TRACING
SYSTEM
EA
ROLL
LOT
Sub Total Heat Tracing Miscellaneous: LS
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
70000
70010
70020
70030
70040
70050
70060
70070
70080
70090
70100
70110
70120
70130
70140
70150
70160
70170
70180
70190
70200
70210
70220
70230
70240
70250
70260
70270
70280
70290
70300
70310
70320
70330
70340
70350
70360
Description
Unit
Amount
1.00
2,375,040.08
2,375,040.08
Sub Total Electrical Systems: LS
1.00
35,884,973.16
35,884,973.16
EA
EA
EA
EA
EA
EA
EA
EA
EA
3.00
3.00
3.00
1.00
1.00
80.00
20.00
3.00
10.00
1,370.00
980.00
1,060.00
1,060.00
1,060.00
160.00
160.00
160.00
1,370.00
4,110.00
2,940.00
3,180.00
1,060.00
1,060.00
12,800.00
3,200.00
480.00
13,700.00
Sub Total Analyzer: ea
124.00
342.98
42,530.00
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
105.00
107.00
12.00
4.00
53.00
5.00
108.00
5.00
32.00
19.00
97.00
213.00
179.00
188.00
54.00
54.00
225.00
475.00
17.00
210.00
120.00
220.00
230.00
230.00
230.00
210.00
360.00
360.00
400.00
210.00
140.00
210.00
210.00
75.00
67.00
260.00
260.00
260.00
22,050.00
12,840.00
2,640.00
920.00
12,190.00
1,150.00
22,680.00
1,800.00
11,520.00
7,600.00
20,370.00
29,820.00
37,590.00
39,480.00
4,050.00
3,618.00
58,500.00
123,500.00
4,420.00
Sub Total Field Instruments: ea
1,952.00
213.49
416,738.00
87.00
50.00
2.00
1,040.00
490.00
490.00
90,480.00
24,500.00
980.00
Sub Total Computer System: LS
1.00
115,960.00
115,960.00
Sub Total Instrument Equipment: LS
1.00
575,228.00
575,228.00
52,500.00
7,500.00
7,500.00
15,000.00
34,000.00
2,800.00
1.62
1.62
1.62
22.00
24.00
11.00
85,050.00
12,150.00
12,150.00
330,000.00
816,000.00
30,800.00
Field Instruments
ORIFICE PLATE & ASSEMBLY
ORIFICE PLATE ONLY
INTEGRAL ORIFICE
PITOT TUBE, ANNUBAR
FLOWMETER
VARIABLE AREA METER
PRESSURE & D/P TRANSMITTER
CAPACITANCE TYPE LEVEL
LEVEL GAUGE
RADAR TYPE LEVEL
PRESSURE & D/P TRANSMITTER
PRESSURE GAUGE
PRESSURE & D/P TRANSMITTER
TEMPERATURE INSTRUMENT
BIMETALLIC THERMOMETER
TEST THERMOWELL
CONTROL VALVE
ON-OFF VALVE
PRESSURE REGULATING
Instrument Cable
Cable
SIGNAL CABLES
SIGNAL CABLES
SIGNAL CABLES
MULTI CABLE
MULTI CABLE
FIBER OPTICAL
Rate
Sub Total Heat Tracing System: LS
Instrumentation Work
Instrument Equipment
Analyzer
ANALYZER
ELECTROCHEMICAL ANALYZER
CONDUCTIVITY ANALYZER
OXYGEN ANALYZER
DENSITY ANALYZER
GAS DETECTOR
FLAME DETECTOR
INDICATOR
MISCELLANEOUS FOR RECEIVER INST.
Computer System
COMPUTER SYSTEM
LOCAL CONTROL BOX
MMS, PDC
Quantity
set
EA
SET
m
m
m
m
m
m
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
70370
70380
70390
70400
70410
70420
70430
70440
70450
70460
70470
70480
70490
70500
70510
70520
70530
70540
70550
70560
70570
Description
MULTI CABLE
MULTI CABLE
MULTI CABLE
MULTI CABLE
MULTI CABLE
MULTI CORE
MULTI CORE
MULTI CORE
MULTI CORE
SINGLE CORE
SINGLE CORE
MULTI CORE
MULTI CORE
Unit
m
m
m
m
m
m
m
m
m
m
m
m
m
70600
70610
70620
70630
70640
70650
70660
70670
70680
70690
Amount
21.00
5.66
21.00
9.61
10.00
2.59
7.30
11.00
17.00
3.33
3.36
4.65
4.65
147,000.00
186,780.00
147,000.00
19,220.00
40,000.00
97,125.00
36,500.00
55,000.00
136,000.00
14,985.00
5,040.00
125,550.00
6,975.00
Sub Total Cable: LS
262,300.00
8.78
2,303,325.00
EA
EA
EA
EA
EA
EA
4,449.00
1,438.00
94.00
86.00
118.00
55.00
23.00
26.00
29.00
31.00
48.00
56.00
102,327.00
37,388.00
2,726.00
2,666.00
5,664.00
3,080.00
Sub Total Cable Gland: ea
6,240.00
24.66
153,851.00
Sub Total Instrument Cable: LS
1.00
2,457,176.00
2,457,176.00
610.00
580.00
29.00
85.00
17,690.00
49,300.00
1.00
66,990.00
66,990.00
m
m
5.00
279.00
17.00
24.00
85.00
6,696.00
Sub Total Pipe Straight: m
284.00
23.88
6,781.00
EA
EA
EA
EA
42.00
68.00
62.00
211.00
580.00
670.00
40.00
40.00
24,360.00
45,560.00
2,480.00
8,440.00
Sub Total Pipe Fittings: LS
1.00
80,840.00
80,840.00
Sub Total Pipe: LS
1.00
87,621.00
87,621.00
4,712.00
36.00
102.00
1,464.00
16,872.00
760.00
24.00
20.00
26.00
16.00
24.00
25.00
113,088.00
720.00
2,652.00
23,424.00
404,928.00
19,000.00
Cable Gland
CABLE GLAND, 1/2"
CABLE GLAND, 3/4"
CABLE GLAND, 1-1/4"
CABLE GLAND, 1-1/2"
CABLE GLAND, 2"
CABLE GLAND, 2-1/2"
Instrument Conduit & Tubing
Conduit
PVC CONDUIT
PVC CONDUIT
Pipe
Pipe Straight
PIPE, 1/2"
PIPE, 1"
Pipe Fittings
AIR MANIFOLD HEADER, 8 POLE
AIR MANIFOLD HEADER, 12 POLE
SEAL POT
DRIP POT
Tubing
TUBE, 1/2"
TUBE, 1/4"
TUBE, 3/4"
TUBE, 3/8"
TUBE, 1/2"
TUBE, PRE-INSULATED, 3/8"
Rate
7,000.00
33,000.00
7,000.00
2,000.00
4,000.00
37,500.00
5,000.00
5,000.00
8,000.00
4,500.00
1,500.00
27,000.00
1,500.00
PCS
m
Sub Total Conduit: LS
70580
70590
Quantity
m
m
m
m
m
m
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
70700
Description
TUBE, PRE-INSULATED, 3/8"
Unit
70940
70950
70960
70970
70980
70990
71000
71010
71020
71030
71040
Amount
260.00
25.00
6,500.00
Sub Total Tubing: m
24,206.00
23.56
570,312.00
1.00
724,923.00
724,923.00
110.00
15.00
90.00
52.00
224.00
127.00
440.00
3,903.00
3,191.00
1,890.00
1,417.00
1,980.00
70.00
70.00
70.00
70.00
70.00
70.00
70.00
36.00
39.00
41.00
44.00
46.00
7,700.00
1,050.00
6,300.00
3,640.00
15,680.00
8,890.00
30,800.00
140,508.00
124,449.00
77,490.00
62,348.00
91,080.00
1.00
569,935.00
569,935.00
EA
3.00
4.00
1.00
4.00
11.00
12.00
102.00
804.00
240.00
261.00
151.00
350.00
380.00
450.00
500.00
550.00
590.00
67.00
67.00
67.00
67.00
67.00
1,050.00
1,520.00
450.00
2,000.00
6,050.00
7,080.00
6,834.00
53,868.00
16,080.00
17,487.00
10,117.00
Sub Total Cable Transit: LS
1.00
122,536.00
122,536.00
EA
EA
EA
EA
EA
EA
13.00
68.00
5.00
32.00
36.00
102.00
170.00
230.00
300.00
370.00
430.00
500.00
2,210.00
15,640.00
1,500.00
11,840.00
15,480.00
51,000.00
Sub Total Junction Box: ea
256.00
381.52
97,670.00
EA
EA
EA
EA
EA
1.00
6.00
4.00
9.00
26.00
270.00
380.00
610.00
730.00
840.00
270.00
2,280.00
2,440.00
6,570.00
21,840.00
Sub Total Enclosures: ea
46.00
726.09
33,400.00
Sub Total Junction Box & Enclosures: LS
1.00
131,070.00
131,070.00
Cable Tray & Fitting
CABLE TRAY, LADDER TYPE
CABLE TRAY, LADDER TYPE
CABLE TRAY, LADDER TYPE
CABLE TRAY, LADDER TYPE
CABLE TRAY, LADDER TYPE
CABLE TRAY, LADDER TYPE
CABLE TRAY, LADDER TYPE
CABLE TRAY,PERFORATED TYPE
CABLE TRAY,PERFORATED TYPE
CABLE TRAY,PERFORATED TYPE
CABLE TRAY,PERFORATED TYPE
CABLE TRAY,PERFORATED TYPE
PCS
PCS
PCS
PCS
PCS
PCS
PCS
PCS
PCS
PCS
PCS
PCS
Sub Total Cable Tray & Fitting: LS
70830
70840
70850
70860
70870
70880
70890
70900
70910
70920
70930
Rate
m
Sub Total Instrument Conduit & Tubing: LS
70710
70720
70730
70740
70750
70760
70770
70780
70790
70800
70810
70820
Quantity
Cable Transit
CABLE TRANSIT, SF-6
CABLE TRANSIT, SF-6x2
CABLE TRANSIT, SF-6x3
CABLE TRANSIT, SF-6x4
CABLE TRANSIT, SF-6+6x5
CABLE TRANSIT, SF-6+6x6
MCT BLOCK, 20Wx20HX60D
MCT BLOCK, 30Wx30HX60D
MCT BLOCK, 40Wx40HX60D
MCT BLOCK, 60Wx60HX60D
MCT BLOCK, 90Wx90HX60D
Junction Box & Enclosures
Junction Box
JUNCTION BOX, 16P
JUNCTION BOX, 28P
JUNCTION BOX, 36P
JUNCTION BOX, 40P
JUNCTION BOX, 54P
JUNCTION BOX, 80P
Enclosures
FIRE PROOFING ENCLOSURE, 16P
FIRE PROOFING ENCLOSURE, 28P
FIRE PROOFING ENCLOSURE, 40P
FIRE PROOFING ENCLOSURE, 54P
FIRE PROOFING ENCLOSURE, 80P
EA
LOT
EA
EA
EA
EA
EA
EA
EA
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
71050
71060
71070
71080
71090
71100
71110
71120
71130
71140
71150
71160
71170
71180
Description
Unit
Support & Hardware
STANCHION, 2" PIPE, HDG
STANCHION, 2" PIPE, HDG
ANGLE, STEEL FOR TRAY
ANGLE, STEEL FOR PIPE, TUBE
ANGLE, STEEL FOR JB
CHANNEL, STEEL
SUNSHADE
SUPPORTING MISCELLANEOUS
NON SHRINK GROUT
EXCAVATION & BACKFILLING WORK
SANDFILLING & COMPACTION WORK
RED CONCRETE PROTECTIVE COVER
WARNING TAPE
SUPPORTING MISCELLANEOUS
EA
EA
m
m
m
m
EA
EA
M3
M3
M3
EA
SET
LOT
80000
90000
Rate
Amount
976.00
70.00
10,212.00
1,162.00
2,640.00
22,265.00
1,010.00
5,000.00
10.00
2,552.00
850.25
7,362.20
48.30
1.00
1,180.00
900.00
200.00
200.00
200.00
310.00
750.00
85.00
10,570.00
13.00
47.00
7.39
8.76
1,557,850.00
1,151,680.00
63,000.00
2,042,400.00
232,400.00
528,000.00
6,902,150.00
757,500.00
425,000.00
105,700.00
33,176.00
39,961.75
54,406.66
423.11
1,557,850.00
1.00
13,893,647.52
13,893,647.52
4,882.00
230.00
1,122,860.00
Sub Total Loop Test : LS
1.00
1,122,860.00
1,122,860.00
Sub Total Instrumentation Work: LS
1.00
19,597,375.52
19,597,375.52
LS
1.00
31,534,920.00
31,534,920.00
Sub Total Insulation Work: LS
1.00
31,534,920.00
31,534,920.00
m2
13,395.50
15.00
200,932.50
Sub Total Cleaning: m2
13,395.50
15.00
200,932.50
Sub Total Support & Hardware: LS
71190
Quantity
Loop Test
LOOP TEST
Loop
Insulation Work
SUBCONTRACT INSULATIOM WORKS
Painting Work
Cleaning
Solvent cleaning
90010
90020
90030
90040
90050
90060
90070
90080
90090
90100
Painting
Sa 2 1/2 Painting
SP, Surface tolerant, Epoxy Mastic, self priming, high solid
Acrylic Polyurethane-Gloss
Epoxy High Build Polyamide with Micaecous Iron Oxide
Acylic Polyurethane-Gloss
HT one pack Silicone coating
Sa 3 Painting
SP/HS Epoxy Phenolic
Inorganic Zinc Silicate(IZS) primer
SP, Surface tolerant, Epoxy Mastic, self priming, high solids
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
19,500.00
1,031.70
1,031.70
3,611.00
3,611.00
958.00
2,549.90
8,400.00
13,200.00
13,395.50
71.00
19.00
8.39
19.00
8.39
7.64
74.00
15.00
13.00
19.00
1,384,500.00
19,602.30
8,655.96
68,609.00
30,296.29
7,319.12
188,692.60
126,000.00
171,600.00
254,514.50
90110
90120
Acrylic Polyurethane-Gloss
All Systems Paint
m2
m2
13,395.50
3,325.00
8.39
18.00
112,388.25
59,850.00
Sub Total Painting: m2
84,009.30
28.95
2,432,028.02
36.00
6,810.00
245,160.00
1.00
245,160.00
245,160.00
90130
Galvanizing
HDG after shop fabrication, Galvanizing
Ton
Sub Total Galvanizing: LS
Line Marking
Bill Of Quantities
Process Plant Project Bill of Quantities
Item
90140
Description
Unit
[Line marking, Identification & Lettering for piping,
Equipment(including insulation items)
Quantity
Rate
Amount
Lot
1.00
227,770.00
227,770.00
Sub Total Line Marking: LS
1.00
227,770.00
227,770.00
Sub Total Painting Work: LS
1.00
3,105,890.52
3,105,890.52
Sub Total Process Plant Direct Costs: LS
1.00
266,395,230.02
266,395,230.02
Grand Total: LS
1.00
266,395,230.02
266,395,230.02