The Chief Estimator Software Process Plant Bill of Quantities Bill Of Quantities Process Plant Project Bill of Quantities Item 10000 Description Unit Process Plant Direct Costs Civil Work Site Investigation Soil Investigation,Boring Monitoring Well, Depth=3.3m, with Cap & Post , Dia=150mm Nos 10020 228,270.00 1.00 228,270.00 228,270.00 30.00 8,120.00 243,600.00 931.00 180.00 167,580.00 931.00 441.65 411,180.00 m3 3,000.00 95.00 285,000.00 m3 44,500.00 55.00 2,447,500.00 m3 3,000.00 11.00 33,000.00 m3 3,000.00 220.00 660,000.00 Sub Total Earthworks: m3 47,500.00 72.12 3,425,500.00 m3 14,697.00 42.00 617,274.00 m3 10,724.00 54.00 579,096.00 Piliing Works Pile Driving, Sheet Pile, W 400 x W 400, 75 x 8t x 12m (with waling and horizontal struts) Pile Head Treatment,Misc. Special Piles,Bored-and-CIPwith_Casing Dia=600mm 10050 Earthworks Excavation,Normal Soil,Back Hoe ncluding surfacing and compaction 95 %, excavation depth=0~-2meters Back-filling and Compaction,Machine,T=15cm compaction ratio 95% of maximum dry density Disposal,Machine,0-10km ( Distance ) 10060 Crushed Stone Spreading with compaction,Machine 10040 Amount 76,090.00 m Nos Sub Total Piliing Works: ea 10030 Rate 3.00 Sub Total Site Investigation: LS 10010 Quantity 10090 Sewer/Drainage Exavation & Backfill Excavation,Normal Soil,Back Hoe ncluding surfacing and compaction 95 %, excavation depth=0~-2meters Back-filling and Compaction,Machine,T=15cm compaction ratio 95% of maximum dry density Disposal,Machine,0-10km ( Distance ) m3 2,055.68 11.00 22,612.48 10100 Sand filling and Compaction,Machine,T=15cm ( Compacted ) m3 1,919.25 86.00 165,055.50 10110 Excavation,Normal Soil,Back Hoe ncluding surfacing and compaction 95 %, excavation depth=0~-2meters Back-filling and Compaction,Machine,T=15cm compaction ratio 95% of maximum dry density Disposal,Machine,0-10km ( Distance ) m3 14,676.09 65.00 953,945.85 m3 9,491.44 54.00 512,537.76 m3 4,635.13 11.00 50,986.43 10140 Crushed Stone Back-filling and Compaction,Machine,T=15cm m3 ( Compacted ) 41.00 86.00 3,526.00 10150 Sand filling and Compaction,Machine,T=15cm ( Compacted ) m3 551.40 110.00 60,654.00 10160 Excavation,Normal Soil,Back Hoe including surfacing and compaction 95 %, excavation depth=0~-2meters Back-filling and Compaction,Machine,T=15cm compaction ratio 95% of maximum dry density m3 2,030.51 66.00 134,013.66 m3 1,001.01 54.00 54,054.54 10070 10080 10120 10130 10170 Bill Of Quantities Process Plant Project Bill of Quantities Item Description Unit Quantity Rate Amount 10180 Disposal,Machine,0-10km ( Distance ) m3 1,029.50 11.00 11,324.50 10190 m3 4,138.13 97.00 401,398.61 m3 3,294.11 54.00 177,881.94 10210 Excavation,Normal Soil,Back Hoe including surfacing and compaction 95 %, excavation depth=0~-2meters Back-filling and Compaction,Machine,T=15cm compaction ratio 95% of maximum dry density Disposal,Machine,0-10km ( Distance ) m3 845.98 11.00 9,305.78 10220 Crushed Stone Spreading with compaction,Machine m3 14.00 86.00 1,204.00 Sub Total Exavation & Backfill: LS 1.00 3,754,871.05 3,754,871.05 10200 10230 Drainage & Sewer Pipe Pipe Installation,Laying Hume Pipe,Socket Type,DIA 300 m 30.00 88.00 2,640.00 10240 Pipe Installation,Laying Hume Pipe,Socket Type,DIA 400 m 50.00 120.00 6,000.00 10250 Pipe Installation,Laying Hume Pipe,Socket Type,DIA 500 m 10.00 150.00 1,500.00 10260 Pipe Installation,Laying Hume Pipe,Socket Type,DIA 700 m 10.00 210.00 2,100.00 10270 Pipe Installation,Laying Hume Pipe,Socket Type,DIA 800 m 100.00 230.00 23,000.00 10280 Pipe Installation,Laying Hume Pipe,Socket Type,DIA 900 m 30.00 260.00 7,800.00 10290 Pipe Installation,PVC Pipe dia.=150, for sanitary sewer, UPVC Class V 3inch Piping, Flexible Coupling 41ea m 100.00 86.00 8,600.00 Sub Total Drainage & Sewer Pipe: m 330.00 156.48 51,640.00 m2 10,273.38 81.00 832,143.78 m2 789.59 81.00 63,956.79 m2 3,525.08 81.00 285,531.48 Sub Total Formwork: m2 14,588.05 81.00 1,181,632.05 m3 2,202.19 610.00 1,343,335.90 m3 156.96 440.00 69,062.40 m3 754.64 610.00 460,330.40 10300 10310 10320 10330 10340 10350 Drainage Structures Cast in Place Concrete Culverts Formwork Forming Work,Ply Wood,3 Times - Structure 1 Forming Work,Ply Wood,3 Times - Structure 2 Forming Work,Ply Wood,3 Times - Structure 3 Concrete Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump 12cm Cement Type I with Silica Fume 6% of Cement,Minimum Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring height=-3~+3meters Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm Cement Type I,Minimum Cement Content 275kg/m3, Max W/C Ratio 0.45 Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump 12cm Cement Type I with Silica Fume 6% of Cement,Minimum Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring height=-3~+3meters Bill Of Quantities Process Plant Project Bill of Quantities Item 10360 10370 10380 10390 10400 10410 10420 10430 10440 10450 Description Unit Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm Cement Type I,Minimum Cement Content 275kg/m3, Max W/C Ratio 0.45 Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump 12cm Cement Type I with Silica Fume 6% of Cement,Minimum Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring height=-3~+3meters Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm Cement Type I,Minimum Cement Content 275kg/m3, Max W/C Ratio 0.45 Quantity Rate Amount m3 26.40 440.00 11,616.00 m3 470.83 610.00 287,206.30 m3 25.53 440.00 11,233.20 Sub Total Concrete: m3 3,636.55 600.23 2,182,784.20 ton 32.30 6,770.00 218,671.00 ton 150.14 6,770.00 1,016,447.80 ton 15.14 6,770.00 102,497.80 ton 53.33 6,770.00 361,044.10 ton 0.38 6,770.00 2,572.60 ton 42.53 6,770.00 287,928.10 Sub Total Reinforcing Steel: ton 293.82 6,770.00 1,989,161.40 m2 2,300.00 62.00 142,600.00 Sub Total Wiremesh: LS 1.00 142,600.00 142,600.00 3,344.80 37.00 123,757.60 Reinforcing Steel Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D22 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Wiremesh Wire Mesh,F6x150x150 Epoxy Coated 10460 Concrete Accessories Water Stop,B=200 m 10470 Mortar Grouting,Non Shrinkage m3 3.60 7,040.00 25,351.04 10480 Mortar Grouting,Epoxy Grout,Water Proofing m3 17.02 24,430.00 415,798.60 Sub Total Concrete Accessories: LS 1.00 564,907.24 564,907.24 Sub Total Cast in Place Concrete Culverts: m3 3,637.00 1,666.51 6,061,084.89 Structural Steel Bill Of Quantities Process Plant Project Bill of Quantities Item 10490 10500 10510 10520 10530 10540 10550 10560 10570 10580 10590 10600 10610 10620 10630 10640 10650 10660 10670 10680 10690 10700 Description Steel Item,Misc.Steel Fabrication,Steel with HDG Steel Item,Insert Plate,Steel with HDG Steel Item 1,Misc.Steel Fabrication,Steel with HDG Steel Item 2,Misc.Steel Fabrication,Steel with HDG Steel Item 3,Misc.Steel Fabrication,Steel with HDG Unit Quantity Rate Amount ton 5.60 13,310.00 74,536.00 ton 24.13 13,310.00 321,170.30 ton 7.01 13,310.00 93,303.10 ton 0.02 13,310.00 266.20 ton 12.09 13,310.00 160,917.90 Sub Total Structural Steel: ton 48.85 13,310.00 650,193.50 m2 694.00 450.00 312,300.00 m2 59.00 820.00 48,380.00 m2 55.28 450.00 24,876.00 m2 700.00 820.00 574,000.00 Sub Total Steel Gratings: m2 1,508.28 636.19 959,556.00 Nos 109.00 1,690.00 184,210.00 EA 294.00 19.00 5,586.00 Sub Total Manhole Accessories: LS 1.00 189,796.00 189,796.00 m2 806.40 55.00 44,352.00 m2 10,595.00 55.00 582,725.00 m2 5,400.25 4.86 26,245.22 m2 2,337.50 53.00 123,887.50 m2 466.00 4.86 2,264.76 m2 514.00 55.00 28,270.00 m2 30.00 130.00 3,900.00 m2 30.00 54.00 1,620.00 m2 1,796.49 54.00 97,010.46 m2 555.52 4.65 2,583.17 m2 1,449.77 52.00 75,388.04 Steel Gratings Grating,I-32 with HDG Grating,I-50 with HDG Grating,I-32 with HDG Grating,I-50 with HDG Manhole Accessories Man Hole,Cover Cast Iron Cover,D=600,Heavy Duty with Lock Pipe Sleeve,Sleeeve Pipe,Installation Only Waterproofinjg Proofing,Epoxy Waterproofing Coal Tar Epoxy Coating, THK=1000 Microns Proofing,Epoxy Waterproofing, T=0.4 mm Coal Tar Epoxy Coating, THK=400 Microns (200 x 2 coats) Proofing,PE Film THK=0.25mm PE Membrane Proofing,Polyurethane Min. THK=500 microns, Water Proof (250 x 2 coats) Proofing,PE Film THK=0.25mm PE Membrane Proofing,Epoxy Waterproofing, T=0.4 mm Coal Tar Epoxy Coating, THK=400 Microns (200 x 2 coats) Proofing,Polyurethane Min. THK=500 microns, Water Proof (250 x 2 coats) Proofing,Epoxy Waterproofing Coal Tar Epoxy Coating, THK=1000 Microns Proofing,Epoxy Waterproofing, T=0.5 mm Coal Tar Epoxy Coating, THK=500 Microns Proofing,PE Film THK=0.25mm PE Membrane Proofing,Polyurethane Min. THK=500 microns, Water Proof (250 x 2 coats) Bill Of Quantities Process Plant Project Bill of Quantities Item Description Unit Quantity Rate Amount Sub Total Waterproofinjg: LS 1.00 988,246.14 988,246.14 Sub Total Drainage Structures: LS 1.00 8,848,876.53 8,848,876.53 Sub Total Sewer/Drainage: LS 1.00 12,655,387.58 12,655,387.58 m3 4,300.00 40.00 172,000.00 m3 4,300.00 11.00 47,300.00 Sub Total Grading: m3 4,300.00 51.00 219,300.00 m2 61,400.00 0.06 3,684.00 Sub Total Subgrade Preparation: m2 61,400.00 0.06 3,684.00 m2 21,580.00 0.92 19,853.60 m2 21,580.00 9.89 213,426.20 10760 Base Course,Crused Stone ( Lower than 8 cm ),T=20CM Well graded Aggregate, 97% compaction ratio, CBR>70% Gravel Paving,Crused Stone ( Lower than 8 cm ),T=10CM m2 22,426.00 34.00 762,484.00 10770 Subbase Course,Crused Stone ( Lower than 8 cm ),T=30CM m2 17,690.90 34.00 601,490.60 Sub Total Granular Base Coarse: m2 83,276.90 19.18 1,597,254.40 m2 21,580.00 22.00 474,760.00 m2 21,580.00 22.00 474,760.00 m2 21,580.00 3.38 72,940.40 m2 21,580.00 3.38 72,940.40 m2 17,690.90 0.87 15,391.08 m2 636.00 100.00 63,600.00 Sub Total Asphalt Paving: m2 21,580.00 54.42 1,174,391.88 m2 218.92 73.00 15,981.16 10710 10720 10730 10740 10750 Road/Paving Grading Excavation,Normal Soil,Back Hoe including surfacing and compaction 95 %, excavation depth=0~-2meters Disposal,Machine,0-10km ( Distance ) Subgrade Preparation Surfacing and Compaction Granular Base Coarse Subbase Course,Crused Stone ( Lower than 150 mm ),T=80CM 10820 Asphalt Paving Wearing Course,#78,T=5 CM maximum aggregate size = 50 mm, detailed specification SES C04-S02 Binder Course,#467,T=5CM Maximum aggregate size = 3/4 inch, Detailed specification SES C04-S02 Tack Coating detailed specification SES C04-S02 Prime Coating detailed specification SES C04-S02 Surfacing and Cleaning 10830 Lane Marking, Normal Temperature Type, Manual Type 10780 10790 10800 10810 10840 Concrete Flatwork Forming Work,Ply Wood,3 Times Bill Of Quantities Process Plant Project Bill of Quantities Item 10850 10860 10870 10880 Description Unit 2,437.89 510.00 1,243,323.90 m m 7,480.09 3,552.62 17.00 47.00 127,161.53 166,973.14 Isolation Joint, Thk=12mm,Bituminous Joint Filler with Joint Sealant m 6,870.00 37.00 254,190.00 1.00 1,807,629.73 1,807,629.73 m 86.40 1,320.00 114,048.00 Sub Total Guiderail: m 86.40 1,320.00 114,048.00 m2 30,350.00 28.00 849,800.00 m2 17,690.90 8.67 153,380.10 m2 m2 108.00 100.00 180.00 170.00 19,440.00 17,000.00 Sub Total Paving Accessories: LS 1.00 1,039,620.10 1,039,620.10 50.00 2,260.00 113,000.00 Sub Total Signage: LS 1.00 113,000.00 113,000.00 Sub Total Road/Paving: m2 44,006.00 137.91 6,068,928.12 m3 1,258.25 150.00 188,737.50 m3 883.20 54.00 47,692.80 m3 375.06 11.00 4,125.66 Excavation,Normal Soil,Back Hoe including surfacing and compaction 95 %, excavation depth=0~-2meters Back-filling and Compaction,Machine,T=15cm compaction ratio 95% of maximum dry density Disposal,Machine,0-10km ( Distance ) m3 218.00 270.00 58,860.00 m3 135.00 54.00 7,290.00 m3 84.00 11.00 924.00 Excavation,Normal Soil,Back Hoe including surfacing and compaction 95 %, excavation depth=0~-2meters Back-filling and Compaction,Machine,T=15cm compaction ratio 95% of maximum dry density Disposal,Machine,0-10km ( Distance ) m3 8,696.00 56.00 486,976.00 m3 4,471.50 54.00 241,461.00 m3 2,815.00 11.00 30,965.00 Guiderail Guard Rail Installation 10910 10920 10930 Acid Proofing Tile Alkali Proofing Tile 10940 10950 10960 10970 10980 10990 11000 11010 11020 11030 Amount m3 Paving Accessories Wire Mesh,F6x150x150 Epoxy Coated PE Film,T=0.25 mm 10900 Rate Concrete Pouring,Remicon, D=25mm,Fc=300kg/cm2,Slump 12cm Cement Type I with Minimum Cement Content 360kg/m3, Max. W/C Ratio 0.40, pouring height=-3~+3meters Contraction Joint, SES-C01-F01-03, with Sealant Expansion Joint, SES-C01-F01-03, with Sealant and Dowel Bar Sub Total Concrete Flatwork: LS 10890 Quantity Signage Traffic Sign Work,Guide Sign Pole Safety & Information Board, Height 2.8m, Board Size 600x600mm Equipment Foundations Structural Excavation & Backfill Excavation,Normal Soil,Back Hoe including surfacing and compaction 95 %, excavation depth=0~-2meters Back-filling and Compaction,Machine,T=15cm compaction ratio 95% of maximum dry density Disposal,Machine,0-10km ( Distance ) Nos Bill Of Quantities Process Plant Project Bill of Quantities Item 11040 Description Unit Quantity Rate Amount Excavation,Normal Soil,Back Hoe including surfacing and compaction 95 %, excavation depth=0~-2meters Back-filling and Compaction,Machine,T=15cm compaction ratio 95% of maximum dry density Disposal,Machine,0-10km ( Distance ) m3 2,526.00 56.00 141,456.00 m3 9,091.00 54.00 490,914.00 m3 498.00 11.00 5,478.00 Excavation,Normal Soil,Back Hoe including surfacing and compaction 95 %, excavation depth=0~-2meters Back-filling and Compaction,Machine,T=15cm compaction ratio 95% of maximum dry density Disposal,Machine,0-10km ( Distance ) m3 435.56 140.00 60,978.40 m3 384.79 54.00 20,778.66 m3 50.77 11.00 558.47 m3 3,722.96 57.00 212,208.72 m3 1,969.81 54.00 106,369.74 11120 Excavation,Normal Soil,Back Hoe including surfacing and compaction 95 %, excavation depth=0~-2meters Back-filling and Compaction,Machine,T=15cm compaction ratio 95% of maximum dry density Disposal,Machine,0-10km ( Distance ) m3 1,754.16 11.00 19,295.76 11130 Sand filling and Compaction,Machine,T=15cm ( Compacted ) m3 1,431.54 110.00 157,469.40 11140 Oily Sand,Machine,T=10cm (Compacted), Asphalt Concrete m3 with Prime Coat Gravel filling and Compaction,Machine,T=15cm ( Compacted m3 ) 155.46 120.00 18,655.20 14.40 86.00 1,238.40 m3 2,098.20 65.00 136,383.00 m3 1,302.31 54.00 70,324.74 m3 793.90 11.00 8,732.90 Sub Total Structural Excavation & Backfill: LS 1.00 2,517,873.35 2,517,873.35 11050 11060 11070 11080 11090 11100 11110 11150 11160 11170 11180 Excavation,Normal Soil,Back Hoe including surfacing and compaction 95 %, excavation depth=0~-2meters Back-filling and Compaction,Machine,T=15cm compaction ratio 95% of maximum dry density Disposal,Machine,0-10km ( Distance ) 11190 Cast in Situ Concrete Formwork Forming Work,Ply Wood,3 Times m2 487.27 81.00 39,468.87 11200 Forming Work,Ply Wood,3 Times m2 135.00 81.00 10,935.00 11210 Forming Work,Ply Wood,3 Times m2 2,273.00 81.00 184,113.00 11220 Forming Work,Ply Wood,3 Times m2 1,449.00 81.00 117,369.00 11230 Forming Work,Ply Wood,3 Times m2 106.89 82.00 8,764.98 11240 Forming Work,Ply Wood,3 Times m2 2,221.08 81.00 179,907.48 11250 Forming Work,Ply Wood,3 Times m2 1,349.34 81.00 109,296.54 Sub Total Formwork: m2 8,021.58 81.01 649,854.87 Concrete Bill Of Quantities Process Plant Project Bill of Quantities Item 11260 11270 11280 11290 11300 11310 11320 11330 11340 11350 11360 11370 11380 11390 Description Unit Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump 12cm Cement Type I with Silica Fume 6% of Cement,Minimum Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring height=-3~+3meters Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm Cement Type I,Minimum Cement Content 275kg/m3, Max W/C Ratio 0.45 Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump 12cm Cement Type I with Silica Fume 6% of Cement,Minimum Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring height=-3~+3meters Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump 12cm Cement Type I with Silica Fume 6% of Cement,Minimum Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring height=-3~+3meters Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm Cement Type I,Minimum Cement Content 275kg/m3, Max W/C Ratio 0.45 Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm Cement Type I,Minimum Cement Content 275kg/m3, Max W/C Ratio 0.45 Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm Cement Type I,Minimum Cement Content 275kg/m3, Max W/C Ratio 0.45 Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump 12cm Cement Type I with Silica Fume 6% of Cement,Minimum Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring height=-3~+3meters Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm Cement Type I,Minimum Cement Content 275kg/m3, Max W/C Ratio 0.45 Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump 12cm Cement Type I with Silica Fume 6% of Cement,Minimum Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring height=-3~+3meters Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm Cement Type I,Minimum Cement Content 275kg/m3, Max W/C Ratio 0.45 Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump 12cm Cement Type I with Silica Fume 6% of Cement,Minimum Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring height=-3~+3meters Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm Cement Type I,Minimum Cement Content 275kg/m3, Max W/C Ratio 0.45 Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump 12cm Cement Type I with Silica Fume 6% of Cement,Minimum Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring height=-3~+3meters Reinforcing Steel Quantity Rate Amount m3 439.50 610.00 268,095.00 m3 47.37 440.00 20,842.80 m3 1,568.00 610.00 956,480.00 m3 101.00 610.00 61,610.00 m3 2.20 440.00 968.00 m3 15.66 440.00 6,890.40 m3 25.62 440.00 11,272.80 m3 609.10 610.00 371,551.00 m3 31.24 440.00 13,745.60 m3 51.24 610.00 31,256.40 m3 3.98 440.00 1,751.20 m3 1,837.12 610.00 1,120,643.20 m3 101.01 430.00 43,434.30 m3 848.52 610.00 517,597.20 Sub Total Concrete: m3 5,681.56 603.03 3,426,137.90 Bill Of Quantities Process Plant Project Bill of Quantities Item 11400 11410 11420 11430 11440 11450 11460 11470 11480 11490 11500 11510 11520 11530 11540 Description Re-bar,Deformed Bar Normal Bending,SD40,D10 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D10 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D19 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D22 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D25 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D10 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Unit Quantity Rate Amount ton 0.34 6,770.00 2,301.80 ton 2.02 6,770.00 13,675.40 ton 8.63 6,770.00 58,425.10 ton 4.04 6,770.00 27,350.80 ton 7.80 6,770.00 52,806.00 ton 0.40 6,770.00 2,708.00 ton 0.79 6,770.00 5,348.30 ton 73.70 6,770.00 498,949.00 ton 1.90 6,770.00 12,863.00 ton 9.40 6,770.00 63,638.00 ton 33.00 6,770.00 223,410.00 ton 42.63 6,770.00 288,605.10 ton 0.06 6,770.00 406.20 ton 0.45 6,770.00 3,046.50 ton 2.61 6,770.00 17,669.70 Bill Of Quantities Process Plant Project Bill of Quantities Item 11550 11560 11570 11580 11590 11600 11610 11620 11630 11640 11650 11660 11670 11680 Description Re-bar,Deformed Bar Normal Bending,SD40,D19 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D25 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D10 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D19 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D22 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D25 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D19 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D22 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Unit Quantity Rate Amount ton 0.26 6,770.00 1,760.20 ton 0.37 6,850.00 2,507.10 ton 1.68 6,790.00 11,380.04 ton 14.60 6,770.00 98,814.92 ton 53.63 6,770.00 363,075.10 ton 9.10 6,770.00 61,607.00 ton 53.00 6,770.00 358,810.00 ton 80.76 6,770.00 546,745.20 ton 4.90 6,770.00 33,173.00 ton 43.25 6,770.00 292,802.50 ton 7.86 6,770.00 53,212.20 ton 7.72 6,770.00 52,264.40 Sub Total Reinforcing Steel: ton 464.89 6,770.14 3,147,354.56 Sub Total Cast in Situ Concrete: m3 5,682.00 1,271.27 7,223,347.33 Nos 124.00 4.28 530.72 Nos 28.00 110.00 3,080.00 Structural Steel Anchor Bolts Anchor Bolt Installation,M24 Installation Only Anchor Box Installation,150x150x450(WxLxD)(mm) Bill Of Quantities Process Plant Project Bill of Quantities Item 11690 Description Unit Quantity Rate Amount Nos 20.00 3.34 66.80 Nos 106.00 4.28 453.68 Nos 80.00 4.55 364.00 Nos 20.00 6.42 128.40 Nos 48.00 8.03 385.44 11740 Anchor Bolt Installation,M16 Installation Only Anchor Bolt Installation,M24 Installation Only Anchor Bolt Installation,M32 Installation Only Anchor Bolt Installation,M42 Installation Only Anchor Bolt Installation,M48 Installation Only Anchor Box Installation,150x150x600(WxLxD)(mm) Nos 16.00 130.00 2,080.00 11750 Anchor Box Installation,150x150x900(WxLxD)(mm) Nos 20.00 1,150.00 23,000.00 11760 Anchor Box Installation,150x150x450(WxLxD)(mm) Nos 70.00 110.00 7,700.00 11770 Nos 24.00 3.34 80.16 Nos 80.00 4.28 342.40 11790 Anchor Bolt Installation,M16 Installation Only Anchor Bolt Installation,M24 Installation Only Anchor Box Installation,150x150x450(WxLxD)(mm) Nos 8.00 130.00 1,040.00 11800 Anchor Box Installation,150x150x900(WxLxD)(mm) Nos 12.00 180.00 2,160.00 11810 Nos 44.00 4.28 188.32 Nos 36.00 4.55 163.80 11830 Anchor Bolt Installation,M24 Installation Only Anchor Bolt Installation,M32 Installation Only Anchor Box Installation,150x150x600(WxLxD)(mm) Nos 244.00 130.00 31,720.00 11840 Anchor Box Installation,150x150x900(WxLxD)(mm) Nos 294.00 160.00 47,040.00 11850 Nos 85.00 4.71 400.35 11860 Anchor Bolt Installation,M24 Installation Only Anchor Box Installation,150x150x600(WxLxD)(mm) Nos 16.00 130.00 2,080.00 11870 Anchor Box Installation,150x150x450(WxLxD)(mm) Nos 418.00 110.00 45,980.00 Sub Total Anchor Bolts: Nos 1,793.00 94.25 168,984.07 ton 0.03 13,310.00 399.30 ton 0.64 13,310.00 8,518.40 ton 2.80 13,310.00 37,268.00 ton 0.40 13,310.00 5,324.00 ton 7.00 13,310.00 93,170.00 Sub Total Steel: LS 1.00 144,679.70 144,679.70 Sub Total Structural Steel: LS 1.00 313,663.77 313,663.77 11700 11710 11720 11730 11780 11820 11880 11890 11900 11910 11920 Steel Steel Item,Misc.Steel Fabrication,Steel with HDG Steel Item,Misc.Steel Fabrication,Steel with HDG Steel Item,Misc.Steel Fabrication,Steel Steel Item,Misc.Steel Fabrication,Steel with HDG Steel Item,Insert Plate,Steel with HDG Waterproofing Bill Of Quantities Process Plant Project Bill of Quantities Item 11930 11940 11950 11960 11970 11980 11990 12000 12010 12020 12030 12040 12050 12060 12070 12080 12090 12100 12110 12120 12130 12140 12150 12160 Description Proofing,Epoxy Waterproofing, T=0.4 mm Coal Tar Epoxy Coating, THK=400 Microns (200 x 2 coats) Proofing,PE Film THK=0.25mm PE Membrane Proofing,Polyurethane Min. THK=500 microns, Water Proof (250 x 2 coats) Proofing,Epoxy Waterproofing, T=0.4 mm Coal Tar Epoxy Coating, THK=400 Microns (200 x 2 coats) Proofing,PE Film THK=0.25mm PE Membrane Proofing,Polyurethane Min. THK=500 microns, Water Proof (250 x 2 coats) Proofing,Protection Board 3.5 mm bitumen impregnated fibreboard or 12 mm thickness bitumen impregnated soft board Proofing,Epoxy Waterproofing, T=0.5 mm Coal Tar Epoxy Coating, THK=500 Microns Proofing,PE Film THK=0.25mm PE Membrane Proofing,Protection Board 3.5 mm bitumen impregnated fibreboard or 12 mm thickness bitumen impregnated soft board Proofing,Polyurethane Min. THK=500 microns, Water Proof (250 x 2 coats) Proofing,Epoxy Waterproofing, T=0.5 mm Coal Tar Epoxy Coating, THK=500 Microns Proofing,Epoxy Waterproofing, T=0.4 mm Coal Tar Epoxy Coating, THK=400 Microns (200 x 2coats) Proofing,PE Film THK=0.25mm PE Membrane Proofing,Polyurethane Min. THK=500 microns, Water Proof (250 x 2 coats) Proofing,PE Film THK=0.25mm PE Membrane Proofing,Polyurethane Min. THK=500 microns, Water Proof (250 x 2 coats) Proofing,Epoxy Waterproofing, T=0.5 mm Coal Tar Epoxy Coating, THK=500 Microns Proofing,PE Film THK=0.25mm PE Membrane Proofing,Polyurethane Min. THK=500 microns, Water Proof (250 x 2 coats) Proofing,HDPE Film THK = 750 microns Proofing,Epoxy Waterproofing, T=0.4 mm Coal Tar Epoxy Coating, THK=400 Microns (200 x 2 coats) Proofing,PE Film THK=0.25mm PE Membrane Proofing,HDPE Film THK = 750 microns Unit Quantity Rate Amount m2 758.68 54.00 40,968.72 m2 373.18 4.65 1,735.29 m2 162.44 52.00 8,446.88 m2 86.00 54.00 4,644.00 m2 24.00 4.65 111.60 m2 10.00 52.00 520.00 m2 163.24 30.00 4,897.20 m2 1,638.44 55.00 90,114.20 m2 1,266.00 4.86 6,152.76 m2 120.00 41.00 4,920.00 m2 289.78 52.00 15,068.56 m2 445.63 54.00 24,064.02 m2 1,604.20 55.00 88,231.00 m2 764.00 4.86 3,713.04 m2 335.00 53.00 17,755.00 m2 294.45 4.65 1,369.19 m2 88.43 52.00 4,598.36 m2 135.38 54.00 7,310.52 m2 63.12 4.65 293.51 m2 27.80 52.00 1,445.60 m2 520.00 35.00 18,200.00 m2 1,163.00 54.00 62,802.00 m2 862.00 4.65 4,008.30 m2 927.00 35.00 32,445.00 Bill Of Quantities Process Plant Project Bill of Quantities Item 12170 Description Unit Rate Amount m2 211.00 52.00 10,972.00 Sub Total Waterproofing: m2 12,332.77 36.88 454,786.75 12180 Mortar Grouting Mortar Grouting,Non Shrinkage m3 5.38 7,040.00 37,875.20 12190 Mortar Grouting,Non Shrinkage m3 26.50 6,820.00 180,730.00 12200 m3 3.10 24,440.00 75,764.00 12210 Mortar Grouting,Epoxy Grout minimum compressive strength at 7 days = 96 MPa Mortar Grouting,Non Shrinkage m3 6.24 7,050.00 43,992.00 12220 Mortar Grouting,Non Shrinkage m3 0.11 7,050.00 775.50 12230 Mortar Grouting,Non Shrinkage m3 16.62 6,810.00 113,182.20 Sub Total Mortar Grouting: m3 57.95 7,805.33 452,318.90 Sub Total Equipment Foundations: m3 5,650.00 1,940.18 10,961,990.10 m3 5,466.71 180.00 984,007.80 m3 2,541.25 54.00 137,227.50 m3 2,926.06 11.00 32,186.66 m3 3,088.38 170.00 525,024.60 m3 1,645.81 54.00 88,873.74 m3 1,442.57 11.00 15,868.27 Sub Total Structural Excavation & Backfill: LS 1.00 1,783,188.57 1,783,188.57 12240 12250 12260 12270 12280 12290 Proofing,Polyurethane Min. THK=500 microns, Water Proof (250 x 2 coats) Quantity Pit/Dike/Cooling Tower Structural Excavation & Backfill Excavation,Normal Soil,Back Hoe including surfacing and compaction 95 %, excavation depth=0~-2meters Back-filling and Compaction,Machine,T=15cm compaction ratio 95% of maximum dry density Disposal,Machine,0-10km ( Distance ) Excavation,Normal Soil,Back Hoe including surfacing and compaction 95 %, excavation depth=0~-2meters Back-filling and Compaction,Machine,T=15cm compaction ratio 95% of maximum dry density Disposal,Machine,0-10km ( Distance ) 12300 Cast in Situ Concrete Formwork Forming Work,Ply Wood,3 Times m2 2,234.09 81.00 180,961.29 12310 Forming Work,Ply Wood,3 Times m2 3,409.80 81.00 276,193.80 Sub Total Formwork: m2 5,643.89 81.00 457,155.09 973.37 590.00 574,288.30 12320 Concrete Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump 12cm Cement Type I with Silica Fume 6% of Cement,Minimum Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring height=-3~+3meters m3 Bill Of Quantities Process Plant Project Bill of Quantities Item 12330 12340 12350 12360 12370 12380 12390 12400 12410 12420 12430 12440 Description Unit Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm Cement Type I,Minimum Cement Content 275kg/m3, Max W/C Ratio 0.45 Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump 12cm Cement Type I with Silica Fume 6% of Cement,Minimum Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring height=-3~+3meters Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm Cement Type I,Minimum Cement Content 275kg/m3, Max W/C Ratio 0.45 Quantity Rate Amount m3 38.20 440.00 16,808.00 m3 1,160.16 610.00 707,697.60 m3 63.76 440.00 28,054.40 Sub Total Concrete: m3 2,235.49 593.54 1,326,848.30 ton 1.25 6,770.00 8,462.50 ton 1.22 6,770.00 8,259.40 ton 72.10 6,770.00 488,117.00 ton 15.95 6,770.00 107,981.50 ton 9.50 6,770.00 64,315.00 ton 6.30 6,770.00 42,651.00 ton 21.76 6,770.00 147,315.20 ton 58.49 6,770.00 395,977.30 ton 20.21 6,770.00 136,821.70 Sub Total Reinforcing Steel: ton 206.78 6,770.00 1,399,900.60 Reinforcing Steel Re-bar,Deformed Bar Normal Bending,SD40,D10 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D19 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D22 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D25 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D19 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm 12450 Concrete Accessories Water Stop,B=200 m 248.00 37.00 9,176.00 12460 Expansion Joint, Gelacreyl Superflex AR m 115.00 42.00 4,830.00 Sub Total Concrete Accessories: m 363.00 38.58 14,006.00 Bill Of Quantities Process Plant Project Bill of Quantities Item Description Unit Sub Total Cast in Situ Concrete: LS 12470 12480 12490 12500 12510 12520 12530 12540 12550 12560 12570 12580 12590 12600 Rate Amount 1.00 3,197,909.99 3,197,909.99 ton 1.37 13,310.00 18,234.70 ton 2.73 13,310.00 36,336.30 ton 5.65 13,310.00 75,201.50 Sub Total Steel: ton 9.75 13,310.00 129,772.50 m2 22.11 450.00 9,949.50 m 201.00 15,750.00 3,165,750.00 Sub Total Misc Metal: LS 1.00 3,175,699.50 3,175,699.50 Sub Total Structural Steel: LS 1.00 3,305,472.00 3,305,472.00 m2 1,425.62 55.00 78,409.10 m2 1,304.69 55.00 71,757.95 m2 828.72 4.86 4,027.58 m2 155.30 53.00 8,230.90 m2 785.00 41.00 32,185.00 m2 3,959.20 55.00 217,756.00 m2 1,912.80 4.86 9,296.21 m2 1,044.60 53.00 55,363.80 Sub Total Waterproofing: m2 11,415.93 41.79 477,026.54 m3 1.43 6,820.00 9,752.60 Sub Total Mortar Grouting: LS 1.00 9,752.60 9,752.60 Sub Total Pit/Dike/Cooling Tower: m3 2,172.00 4,039.30 8,773,349.70 Structural Steel Steel Steel Item,Misc.Steel Fabrication,Steel with HDG Steel Item,Insert Plate,Steel with HDG Steel Item,Checked Plate with HDG Misc Metal Grating,I-32 with HDG Hand Rail,Steel,H=1.2m Hot-Dip-Galvanized Pipe Type Waterproofing Proofing,Epoxy Waterproofing Coal Tar Epoxy Coating, THK=1000 Microns Proofing,Epoxy Waterproofing, T=0.4 mm Coal Tar Epoxy Coating, THK=400 Microns (200 x 2coats) Proofing,PE Film THK=0.25mm PE Membrane Proofing,Polyurethane Min. THK=500 microns, Water Proof (250 x 2 coats) Proofing,Protection Board 3.5 mm bitumen impregnated fibreboard or 12 mm thickness bitumen impregnated soft board Proofing,Epoxy Waterproofing, T=0.4 mm Coal Tar Epoxy Coating, THK=400 Microns (200 x 2coats) Proofing,PE Film THK=0.25mm PE Membrane Proofing,Polyurethane Min. THK=500 microns, Water Proof (250 x 2 coats) Mortar Grouting Mortar Grouting,Non Shrinkage Cable Trench/Duct Bank Quantity Bill Of Quantities Process Plant Project Bill of Quantities Item Description Unit Quantity Rate Amount 12630 Structural Excavation & Backfill Excavation,Normal Soil,Back Hoe including surfacing and compaction 95 %, excavation depth=0~-2meters Back-filling and Compaction,Machine,T=15cm compaction ratio 95% of maximum dry density Disposal,Machine,0-10km ( Distance ) m3 6,590.70 11.00 72,497.70 12640 Sand filling and Compaction,Machine,T=15cm ( Compacted ) m3 10,638.84 110.00 1,170,272.40 12650 Excavation,Normal Soil,Back Hoe including surfacing and compaction 95 %, excavation depth=0~-2meters Back-filling and Compaction,Machine,T=15cm compaction ratio 95% of maximum dry density Disposal,Machine,0-10km ( Distance ) m3 2,544.00 150.00 381,600.00 m3 1,957.40 54.00 105,699.60 m3 588.10 11.00 6,469.10 m3 508.00 130.00 66,040.00 m3 382.00 54.00 20,628.00 12700 Excavation,Normal Soil,Back Hoe including surfacing and compaction 95 %, excavation depth=0~-2meters Back-filling and Compaction,Machine,T=15cm compaction ratio 95% of maximum dry density Disposal,Machine,0-10km ( Distance ) m3 145.00 11.00 1,595.00 12710 Crushed Stone Spreading with compaction,Machine m3 134.00 83.00 11,122.00 Sub Total Structural Excavation & Backfill: LS 1.00 3,427,520.72 3,427,520.72 m 8,607.40 0.00 0.00 4,701.00 237.00 48.00 48.00 225,648.00 11,376.00 12610 12620 12660 12670 12680 12690 12720 Conduit Warning Tape m3 21,313.57 50.00 1,065,678.50 m3 9,739.23 54.00 525,918.42 12730 12740 HI PVC Conduit, SCH. 40, Size : 6 Inches HI PVC CONDUIT FOR CONCRETE DUCT BANK. SCHEDULE 40 M M 12750 PVC CONDUIT SPACER SIZE : 8" UNIT : EA SET 475.00 34.00 16,150.00 12760 PVC CONDUIT SPACER SIZE : 6" UNIT : EA SET 5,234.00 34.00 177,956.00 Sub Total Conduit: LS 1.00 431,130.00 431,130.00 12770 Cast in Situ Concrete Formwork Forming Work,Ply Wood,3 Times m2 5,040.87 81.00 408,310.47 12780 Forming Work,Ply Wood,3 Times m2 477.45 81.00 38,673.45 12790 Forming Work,Ply Wood,3 Times m2 492.00 81.00 39,852.00 Sub Total Formwork: m2 6,010.32 81.00 486,835.92 Concrete Bill Of Quantities Process Plant Project Bill of Quantities Item 12800 12810 12820 12830 12840 12850 12860 12870 12880 12890 12900 12910 12920 Description Unit Concrete Pouring,Remicon, D=25mm,Fc=300kg/cm2,Slump 12cm Cement Type I with Minimum Cement Content 360kg/m3, Max. W/C Ratio 0.40, pouring height=-3~+3meters Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump 12cm Cement Type I with Silica Fume 6% of Cement,Minimum Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring height=-3~+3meters Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm Cement Type I,Minimum Cement Content 275kg/m3, Max W/C Ratio 0.45 Concrete Pouring,Remicon, D=25mm,Fc=170kg/cm2,Slump 12cm Red Color Powder Added 1kg/100kg cement, Cement Type I with Minimum Cement Content 354kg/m3, Max. W/C Ratio 0.40, pouring height=-3~+3meters Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm Cement Type I,Minimum Cement Content 275kg/m3, Max W/C Ratio 0.45 Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump 12cm Cement Type I with Silica Fume 6% of Cement,Minimum Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring height=-3~+3meters Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm Cement Type I,Minimum Cement Content 275kg/m3, Max W/C Ratio 0.45 Rate Amount m3 60.00 550.00 33,000.00 m3 1,174.44 590.00 692,919.60 m3 73.68 440.00 32,419.20 m3 395.22 440.00 173,896.80 m3 50.80 440.00 22,352.00 m3 149.00 590.00 87,910.00 m3 19.00 440.00 8,360.00 Sub Total Concrete: m3 1,922.14 546.71 1,050,857.60 ton 6.00 6,770.00 40,620.00 ton 117.45 6,770.00 795,136.50 ton 23.00 6,770.00 155,710.00 ton 0.48 6,770.00 3,249.60 ton 23.00 6,770.00 155,710.00 Sub Total Reinforcing Steel: ton 169.93 6,770.00 1,150,426.10 117.00 37.00 4,329.00 1.00 4,329.00 4,329.00 Reinforcing Steel Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm Concrete Accessories Water Stop,B=200 Quantity m Sub Total Concrete Accessories: LS Bill Of Quantities Process Plant Project Bill of Quantities Item Description Unit Sub Total Cast in Situ Concrete: LS 12930 12940 12950 12960 12970 12980 12990 13000 13010 13020 13030 13040 Quantity Rate Amount 1.00 2,692,448.62 2,692,448.62 m2 1,808.92 4.86 8,791.35 m2 4,696.13 55.00 258,287.15 m2 1,061.25 4.86 5,157.68 m2 1,401.20 54.00 75,664.80 m2 389.00 54.00 21,006.00 m2 170.00 55.00 9,350.00 m2 104.00 66.00 6,864.00 Sub Total Waterproofing: m2 9,630.50 39.99 385,120.98 ton 0.06 13,310.00 798.60 ton 0.01 13,310.00 133.10 Nos 13.00 1,810.00 23,530.00 Sub Total Misc Metal: LS 1.00 24,461.70 24,461.70 m2 7,575.74 47.00 356,059.78 m2 56.97 3,830.00 218,195.10 Sub Total Brick Masonry: m2 7,632.71 75.24 574,254.88 Sub Total Cable Trench/Duct Bank: m3 748.00 10,073.45 7,534,936.90 m3 306.00 18.00 5,508.00 m3 270.00 54.00 14,580.00 m3 36.00 11.00 396.00 m3 24.00 18.00 432.00 m3 20.00 53.00 1,060.00 Waterproofing Proofing,PE Film THK=0.25mm PE Membrane Proofing,Epoxy Waterproofing, T=0.4 mm Coal Tar Epoxy Coating, THK=400 Microns (200 x 2 coats) Proofing,PE Film THK=0.25mm PE Membrane Proofing,Epoxy Waterproofing, T=0.4 mm Coal Tar Epoxy Coating, THK=400 Microns (200 x 2 coats) Proofing,Epoxy Waterproofing, T=0.4 mm Coal Tar Epoxy Coating, THK=400 Microns (200 x 2 coats) Proofing,PE Film THK=0.25mm PE Membrane Proofing,Polyurethane Min. THK=500 microns, Water Proof (250 x 2 coats) Misc Metal Steel Item,Misc.Steel Fabrication,Steel with HDG Steel Item,Misc.Steel Fabrication,Steel with HDG Man Hole,Cover Cast Iron Cover Brick Masonry Laying Brick,Both Side Red Concrete Tile, 305x305x50 Laying Brick,Both Side Fence/Gate & Miscellaneous Works Line item no. 1075 is a Subcontract Work by 13050 13060 13070 13080 13090 Structural Excavation & Backfill Excavation,Normal Soil,Back Hoe including surfacing and compaction 95 %, excavation depth=0~-2meters Back-filling and Compaction,Machine,T=15cm compaction ratio 95% of maximum dry density Disposal,Machine,0-10km ( Distance ) Excavation,Normal Soil,Back Hoe including surfacing and compaction 95 %, excavation depth=0~-2meters Back-filling and Compaction,Machine,T=15cm compaction ratio 95% of maximum dry density Bill Of Quantities Process Plant Project Bill of Quantities Item Description Unit Quantity Rate Amount 13100 Disposal,Machine,0-10km ( Distance ) m3 4.00 11.00 44.00 13110 EXCAVATION (GRAVEL & SOIL) Including surfacing & compacyion 95% BACKFILLING & COMPACTION T=150 DISPOSAL (10KM) Unfactored soil, Disposal area(10km far) GRAVEL COMPACT. Aggregate base course,THK=150mm m3 30,535.78 18.00 549,644.04 m3 26,947.97 54.00 1,455,190.38 m3 3,527.79 11.00 38,805.69 m3 92.50 94.00 8,695.00 Sub Total Structural Excavation & Backfill: LS 1.00 2,074,355.11 2,074,355.11 13120 13130 13140 13150 Cast in Situ Concrete Formwork Forming Work,Ply Wood,3 Times m2 270.00 81.00 21,870.00 13160 Forming Work,Ply Wood,3 Times m2 20.00 86.00 1,720.00 13170 FORM (PLYWOOD) for U/G concrete m2 11,345.98 81.00 919,024.38 Sub Total Formwork: m2 11,635.98 81.01 942,614.38 m3 33.00 610.00 20,130.00 m3 3.90 440.00 1,716.00 m3 2.60 610.00 1,586.00 m3 0.30 440.00 132.00 m3 234.68 440.00 103,259.20 m3 2,878.91 620.00 1,784,924.20 m3 308.60 8,580.00 2,647,788.00 Sub Total Concrete: m3 3,461.99 1,317.03 4,559,535.40 7.20 6,770.00 48,744.00 13180 13190 13200 13210 13220 13230 13240 13250 Concrete Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump 12cm Cement Type I with Silica Fume 6% of Cement,Minimum Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring height=-3~+3meters Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm Cement Type I,Minimum Cement Content 275kg/m3, Max W/C Ratio 0.45 Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump 12cm Cement Type I with Silica Fume 6% of Cement,Minimum Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring height=-3~+3meters Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm Cement Type I,Minimum Cement Content 275kg/m3, Max W/C Ratio 0.45 CONCRETE 1 For U/G Plain Con'c.,ASTM 17MPa,ASTM C150 TYPE V minimum Cement Content 275kg/cm3 Max W/C Ratio 0.45 CONCRETE 3 For U/G RC,ASTM 35MPa,ASTM C150 TYPE I + Micro silica 6% Minimum Cement Content 364kg/cm3 Max W/C Ratio 0.4, Caicium Nitrite shall be added(min. 10 liters/m3 for 30% solution) CONCRETE ENCASEMENT Included FORM & MISC. WORK & Material Reinforcing Steel Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm ton Bill Of Quantities Process Plant Project Bill of Quantities Item 13260 13270 13280 13290 13300 13310 13320 13330 13340 13350 13360 13370 13380 13390 13400 13410 13420 13430 Description Unit Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy Coating ASTM A615 Grade60,Epoxy Coating ASTM A775 min 0.15mm RE-BAR 2 Dia.10~32,ASTM A615 Grade 60, Fusion bonded epoxy coating,thick.180~300micron Quantity Rate Amount ton 0.60 6,770.00 4,062.00 ton 326.56 6,770.00 2,210,811.20 Sub Total Reinforcing Steel: ton 334.36 6,770.00 2,263,617.20 Sub Total Cast in Situ Concrete: m3 3,462.00 2,243.14 7,765,766.98 Ton 13.00 13,310.00 173,030.00 EA 200.00 2.99 598.00 m2 57.02 53.00 3,022.06 Sub Total Misc Metal: LS 1.00 176,650.06 176,650.06 m2 216.00 54.00 11,664.00 m2 78.00 4.86 379.08 m2 16.80 54.00 907.20 m2 6.00 55.00 330.00 m2 16.80 53.00 890.40 m2 4,699.61 110.00 516,957.10 m2 m2 m2 537.35 630.02 12,070.75 63.00 66.00 52.00 33,853.05 41,581.32 627,679.00 Sub Total Waterproofing: m2 18,271.33 67.55 1,234,241.15 EA 2,492.00 98.00 244,216.00 EA 290.00 36.00 10,440.00 Sub Total Anchor Bolts: ea 2,782.00 91.54 254,656.00 400.00 480.00 192,000.00 1,599.00 460.00 735,540.00 1,999.00 464.00 927,540.00 Misc Metal Metal Work/FAB. & Installation of MISC. Steel for Embeded steel w/hot-dip-galvanized Nut welding for Fireproofing (for fixing WWF) ASTM A 563 w.w.f 50x50x2.5mm including material and installation work Waterproofing Proofing,Epoxy Waterproofing, T=0.4 mm Coal Tar Epoxy Coating, THK=400 Microns (200 x 2 coats) Proofing,PE Film THK=0.25mm PE Membrane Proofing,Epoxy Waterproofing, T=0.5 mm Coal Tar Epoxy Coating, THK=500 Microns Proofing,PE Film THK=0.25mm PE Membrane Proofing,Polyurethane Min. THK=500 microns, Water Proof (250 x 2 coats) LAYING PE FILM FLOOR.(0.25MMX1PLIES) Chemical resistant One Pack Moisture cured, 500micr(250mic X 2Plys) 400micro(200micro X 2Plys) Fence Anchor Bolts ANCHOR BOLT M25~M35, Hot Dip Galvanized ANCHOR BOLT hot dip galvarnize Fencing Fence,Bared Wire Fence m Post Space=2m,H=1.55m,Gavanised Installation and Disposal of Site Perimeter Fence (Temporary m Purpose) Sub Total Fencing: m Bill Of Quantities Process Plant Project Bill of Quantities Item 13440 13450 13460 13470 13480 13490 13500 13510 20000 20010 20020 20030 20040 20050 20060 20070 Description Unit Gates Gate,Gate with Rail W=8m,H=2.5m, Auto Sliding Gate for temporary fence, 6 m width Quantity Rate Amount EA 2.00 103,040.00 206,080.00 EA 5.00 6,050.00 30,250.00 Sub Total Gates: ea 7.00 33,761.43 236,330.00 EA 1,070.00 70.00 74,900.00 Sub Total Piles: ea 1.00 74,900.00 74,900.00 D/I D/I D/I 414.00 1,220.00 1,996.00 460.00 1,270.00 2,210.00 190,440.00 1,549,400.00 4,411,160.00 Sub Total Sockets: DI 3,630.00 1,694.49 6,151,000.00 m3 10.30 6,560.00 67,568.00 Sub Total Grout: LS 1.00 67,568.00 67,568.00 Sub Total Fence: LS 1.00 7,711,994.00 7,711,994.00 m2 7,515.72 370.00 2,780,816.40 Sub Total Fendolite: LS 1.00 2,780,816.40 2,780,816.40 Sub Total Fence/Gate & Miscellaneous Works: m3 3,458.00 6,287.98 21,743,823.70 Sub Total Civil Work: LS 1.00 71,803,366.09 71,803,366.09 m3 7,868.73 63.00 495,729.99 m3 3,429.75 71.00 243,512.25 m3 m3 6,073.74 1,403.14 71.00 11.00 431,235.54 15,434.54 m3 784.39 120.00 94,126.80 m3 1,148.85 61.00 70,079.85 m2 6,907.93 3.85 26,595.53 m2 927.08 12.00 11,124.96 Piles PILE HEAD TREATMENT Dia.=600mm, L=14m & 18m Sockets Non Internal Lined. Non External Lined. Socket (Fillet)Joint Non Internal Lined. Non External Lined. Socket (Fillet)Joint Non Internal Lined. Non External Lined. Socket (Fillet)Joint Grout GROUT Min.35MPa(7 days) : ASTM C1107 Fendolite FENDOLITE For 2 hrs fire resistance,including w.w.f 50x50x2.5mm and required(stud)bolt@300 & final urethane coating Building Work Sitework EXCAVATION (GRAVEL & SOIL) Including surfacing & compacyion 95% BACKFILLING & COMPACTION w/imported soil, 50mm sieve 100% passing, #200 sieve 0~20% passing, LL=Max.35, PL=Max.12 BACKFILLING & COMPACTION DISPOSAL (10KM) Unfactored soil, Disposal area(10km far) GRAVEL COMPACT. Aggregate base course,THK=150mm SAND POURING & COMPACTION Imported sand for sand bedding(w/Soil compaction underneath the bedding LAYING PE FILM FLOOR.(0.25MMX1PLIES) GRAVEL PAVING THK=100 Bill Of Quantities Process Plant Project Bill of Quantities Item 20080 20090 20100 20110 20120 20130 20140 20150 20160 20170 20180 20190 20200 Description Unit FENCE (P.V.C COATING) Havy duty expanded metal mesh - Hot dip galvanized(including Fence Door),removable, 8~12 gage 13mm Max.gap Rate Amount 923.95 730.00 674,483.50 Sub Total Sitework: LS 1.00 2,062,322.96 2,062,322.96 m2 12,326.21 110.00 1,355,883.10 m2 3,897.14 110.00 428,685.40 Sub Total Formwork: m2 16,223.35 110.00 1,784,568.50 m3 317.49 420.00 133,345.80 m3 1,703.25 690.00 1,175,242.50 m3 2,797.70 690.00 1,930,413.00 m3 1,703.25 31.00 52,800.75 m3 3,115.19 23.00 71,649.37 Sub Total Concrete: m3 9,636.88 349.02 3,363,451.42 ton 438.84 4,690.00 2,058,159.60 ton 153.24 6,470.00 991,462.80 ton 592.08 300.00 177,624.00 Sub Total Rebar: ton 1,184.16 2,725.35 3,227,246.40 Sub Total Reinforced Concrete: m3 9,637.00 869.07 8,375,266.32 m2 66.36 150.00 9,954.00 m2 647.52 180.00 116,553.60 Reinforced Concrete Formwork FORM (PLYWOOD) above ground FORM (PLYWOOD) for U/G concrete Concrete CONCRETE 1 For U/G Plain Con'c.,ASTM 17MPa,ASTM C150 TYPE I minimum Cement Content 275kg/cm3 Max W/C Ratio 0.45 CONCRETE 2 For A/G RC,ASTM 35MPa,ASTM C150 TYPE I + Micro silica Fume 6% Minimum Cement Content 364kg/cm3 Max W/C Ratio 0.4, Calcium Nitrite shall be added (min. 10 litres/m3 for 30% solution) CONCRETE 3 For U/G RC,ASTM 35MPa,ASTM C150 TYPE I + Micro silica 6% Minimum Cement Content 364kg/cm3 Max W/C Ratio 0.4, Caicium Nitrite shall be added(min. 10 liters/m3 for 30% solution) CON'C POURING ( PUMPCAR) CON'C POURING (REMICON) for U/G Concrete Rebar RE-BAR 1 Dia.10~32mm,ASTM A615/A615M Grade 60, Uncoated RE-BAR 2 Dia.10~32,ASTM A615 Grade 60, Fusion bonded epoxy coating,thick.180~300micron RE-BAR MANUFACTURING AND FITTING Masonry Work CONCRETE BLOCK WORK (ASTM C129,TYPE?),Including solid concrete fill,12mm vertical reinforcement & tooled finish(Min. 2hr. fire rated) including block mesh CONCRETE BLOCK WORK (ASTM C129,TYPE?),Including solid concrete fill,12mm vertical reinforcement & tooled finish(Min. 2hr. fire rated) including block mesh m Quantity Bill Of Quantities Process Plant Project Bill of Quantities Item 20210 20220 20230 20240 20250 20260 20270 20280 20290 Description Unit CONCRETE BLOCK WORK (ASTM C129,TYPE?),Including solid concrete fill,12mm vertical reinforcement & tooled finish(Min. 2hr. fire rated) including block mesh LINTEL FAB.& INSTALL PC Lintel, 250 x 300mm RE-BAR Dia.10~32mm,ASTM A615/A615M Grade 60, Uncoated GRANITE T=50(W=450) Rate Amount 1,800.00 220.00 396,000.00 m 11.50 170.00 1,955.00 ton 17.94 6,770.00 121,453.80 m2 96.88 1,350.00 130,788.00 Sub Total Masonry Work: m2 2,414.00 321.75 776,704.40 EA 276.00 260.00 71,760.00 EA 396.00 260.00 102,960.00 Sub Total Anchor Bolts: ea 672.00 260.00 174,720.00 ton 10.35 15,510.00 160,528.50 ton 42.80 10,900.00 466,520.00 ton 42.80 9,060.00 387,768.00 Sub Total Miscellaneous Metal: ton 95.95 10,576.51 1,014,816.50 Metal Work Anchor Bolts ANCHOR BOLT M25~M35, Hot Dip Galvanized ANCHOR BOLT hot dip galvarnize Miscellaneous Metal INSERT PLATE ASTM A36 MISC. STEEL hot dip galvanized material FAB. & INSTALL. OF MISC. STEEL m2 Quantity 20300 Metal Trim AL. MOULDING m 464.58 190.00 88,270.20 20310 SETTING NON-SLIP m 115.63 170.00 19,657.10 Sub Total Metal Trim: m 580.21 186.01 107,927.30 m3 8.26 5,210.00 43,034.60 Sub Total Grouting: LS 1.00 43,034.60 43,034.60 56.00 23,937.47 1,340,498.40 1,376.70 180.00 247,806.00 1,460.50 180.00 262,890.00 20320 Grouting GROUT Min.35MPa(7 days) : ASTM C1107 Sub Total Metal Work: t 20330 20340 Thermal & Mosture Protection Waterproofing Waterproofing SHEET WATERPROOFING m2 300*300*50thl. Cement Leight Weight Tiles or Gravel(50mm)+Alyaf 140Gm/m2 Seperation layer+insulation : Thk=50 Extruded polystyrene board+Thk.=0.2 P.E Film+Waterproof membrane : Torchseal membrane 4mm Thk.(2Layer)+Asphalt primer+Steel t SHEET-APPLIED MEMBRANE WATERPROOFING PU Waterproof Membrane m2 Bill Of Quantities Process Plant Project Bill of Quantities Item 20350 20360 20370 20380 20390 20400 20410 20420 20430 20440 20450 20460 Description WATERPROOF MORTAR For wall,T=30 WATERPROOF MORTAR Unit Quantity Rate Amount m2 257.92 81.00 20,891.52 m2 385.66 89.00 34,323.74 LIQUID WATERPROOFING m2 For floor & Wall WATERPROOF PROTECTION BOARD m2 Waterproof gypsum board(For wall), Waterproof plywood 9t + Waterproofed gypsumboard 9t 28.52 240.00 6,844.80 331.20 270.00 89,424.00 Sub Total Waterproofing: m2 3,840.50 172.42 662,180.06 m 700.00 51.00 35,700.00 m 255.30 60.00 15,318.00 m 40.25 130.00 5,232.50 Sub Total Joint Sealing: LS 1.00 56,250.50 56,250.50 Sub Total Waterproofing: m2 2,866.00 250.67 718,430.56 m2 1,926.25 23.00 44,303.75 Sub Total Insulation: LS 1.00 44,303.75 44,303.75 602.80 60.00 36,168.00 Sub Total Caulking & Sealing: LS 1.00 36,168.00 36,168.00 Sub Total Thermal & Mosture Protection: LS 1.00 798,902.31 798,902.31 9.00 3,980.00 35,820.00 27.00 5,420.00 146,340.00 7.00 5,960.00 41,720.00 Joint Sealing CAULKING Around Doors & Windows CONTROL JOINT WATER DRIP Water stop Insulation ROCK WOOL Wall (T=50) Caulking & Sealing EXPANSION JOINT/CAULKING m Doors & Windows Steel Doors STEEL DOOR EA (Size 0.8x2.1) Steel door on lightweight partition-Including Alkyd painting/Accessories/Grouting for the frames(If necessory), 10mmTHK.(ext.)/3mmTHK(int.) Cold rolled sheet door leaf(Both sides) & 100x65x2 Door frame STEEL DOOR EA (Size 1.0x2.2) Including Alkyd painting/Accessories/Grouting for the frames(if necessary). 45mm thick, grade2, heavy dyty, model2, seamless design 1.5mm thick colorolled steel sheet faces STEEL DOOR EA (Size 1.1x2.2) Including Alkyd painting/Accessories/Grouting for the frames(if necessary). 45mm thick, grade2, heavy dyty, model2, seamless design 1.5mm thick colorolled steel sheet faces Bill Of Quantities Process Plant Project Bill of Quantities Item Description Unit Quantity Rate Amount 20470 STEEL DOOR (Size 1.8x2.4)Including Alkyd painting/Accessories/Grouting for the frames(if necessary),45mm thick,grade?,Heavy duty,model2,seamless design 1.5mm thick cold rolled steel sheet faces EA 2.00 10,750.00 21,500.00 20480 STEEL DOOR EA (Size 2.2x2.6) Including Alkyd painting/Accessories/Grouting for the frames(if necessary). 45mm thick, grade2, heavy dyty, model2, seamless design 1.5mm thick colorolled steel sheet faces STEEL DOOR EA (Size 2.7x3.1) Including Alkyd painting/Accessories/Grouting for the frames(if necessary). 45mm thick, grade2, heavy dyty, model2, seamless design 1.5mm thick colorolled steel sheet faces 2.00 14,200.00 28,400.00 2.00 20,720.00 41,440.00 Sub Total Steel Doors: ea 49.00 6,433.06 315,220.00 EA 1.00 16,330.00 16,330.00 EA 1.00 21,360.00 21,360.00 EA 2.00 21,250.00 42,500.00 Sub Total Glass Doors: ea 4.00 20,047.50 80,190.00 EA 3.00 35,320.00 105,960.00 EA 1.00 129,320.00 129,320.00 Sub Total Special Doors: ea 4.00 58,820.00 235,280.00 EA 61.00 1,650.00 100,650.00 EA 61.00 1,040.00 63,440.00 EA 61.00 110.00 6,710.00 EA 18.00 16,970.00 305,460.00 7.00 1.00 880.00 1,650.00 6,160.00 1,650.00 1.00 484,070.00 484,070.00 EA 2.00 6,970.00 13,940.00 EA 13.00 46,930.00 610,090.00 20490 20500 20510 20520 20530 20540 20550 20560 20570 20580 20590 20600 Glass Doors TEMPERED GLASS DOOR 1.8*2.1 W/ACCESSORIES TEMPERED GLASS DOOR 2.0 X 2.4 W/ACCESORRIES TEMPERED GLASS DOOR 1.8 X 2.7 W/ACCESSORIES Special Doors BLAST RESISTANT DOOR (Size 1.0x2.2) Resisting against 2ton/m2(suction),including door accessories BLAST RESISTANT DOOR (Size 2.0x2.4) Resisting against 2ton/m2(suction),including door accessories Door Hardware LOCK SET 3 keys for each door, 3 keys for each building, 3 keys for each group, 3 keys for master DOOR CLOSER FOR GENERAL USE K-1630, for Heavy duty steel door" DOOR STOP FOR OPERATED FRICTION DOOR HOLDER PANIC DEVICE Stainless steel PIVOT HINGE DOOR KNOB SET EA Sub Total Door Hardware: LS 20610 20620 Windows AL. WINDOW/FRAME (Size 0.9x1.8) Including accessories Extruded aluminum complying with ASTM B221 alloy 6063-T5 AL. WINDOW/FRAME (Size 0.9x12) Including accessories Extruded aluminum complying with ASTM B221 alloy 6063-T5 Bill Of Quantities Process Plant Project Bill of Quantities Item 20630 20640 20650 20660 20670 20680 20690 20700 20710 20720 20730 20740 20750 20760 20770 20780 20790 20800 Description Unit AL. WINDOW/FRAME (Size 1.2x0.6) Including accessories Extruded aluminum complying with ASTM B221 alloy 6063-T5 AL. WINDOW/FRAME (Size 0.9x12) Including accessories Extruded aluminum complying with ASTM B221 alloy 6063-T5 AL. WINDOW/FRAME (Size 1.2x1.5) Including accessories Extruded aluminum complying with ASTM B221 alloy 6063-T5 AL. WINDOW/FRAME (Size 1.2x3.0) Including accessories Extruded aluminum complying with ASTM B221 alloy 6063-T5 AL. WINDOW/FRAME (Size 2.0x1.5) Including accessories Extruded aluminum complying with ASTM B221 alloy 6063-T5 AL. WINDOW/FRAME (Size 0.9x3.0) Including accessories Extruded aluminum complying with ASTM B221 alloy 6063-T5 AL. WINDOW/FRAME (Size 1.2x4.0) Including accessories Extruded aluminum complying with ASTM B221 alloy 6063-T5 AL. WINDOW/FRAME (Size 0.9x6.0) Including accessories Extruded aluminum complying with ASTM B221 alloy 6063-T5 Quantity Rate Amount EA 1.00 3,160.00 3,160.00 EA 3.00 46,930.00 140,790.00 EA 3.00 7,730.00 23,190.00 EA 3.00 15,450.00 46,350.00 EA 2.00 13,000.00 26,000.00 EA 2.00 11,710.00 23,420.00 EA 3.00 20,610.00 61,830.00 EA 4.00 23,360.00 93,440.00 Sub Total Windows: ea 36.00 28,950.28 1,042,210.00 m2 223.97 1,550.00 347,153.50 m2 16.39 4,270.00 69,985.30 m2 3.04 2,080.00 6,323.20 m2 13.70 3,090.00 42,333.00 m2 8.19 880.00 7,207.20 Sub Total Glazing: m2 265.29 1,782.96 473,002.20 EA 1.00 14,790.00 14,790.00 EA 4.00 33,110.00 132,440.00 EA 1.00 33,110.00 33,110.00 EA 5.00 50,550.00 252,750.00 Sub Total Shutters: ea 11.00 39,371.82 433,090.00 EA 36.00 6,180.00 222,480.00 Sub Total Louvres: LS 1.00 222,480.00 222,480.00 Sub Total Doors & Windows: ea 140.00 23,468.16 3,285,542.20 Glazing CLEAR GLASS Type I,Class 1, Quality Q4 PAIR GLASS Tempered Glass 6T + Air space 13T + Clear Glass 6T WIRED GLASS T=8 TEMPERED GLASS DAMP PROOFING MIRROR For toilet Shutters SHUTTER (ELECTRICAL) (Size 1.8x2.5) Steel, Galv. SHUTTER (ELECTRICAL) 3.0x3.5 (Steel Galvanized) SHUTTER (ELECTRICAL) 3.0x3.5 (Steel Galvanized) SHUTTER (ELECTRICAL) (Size 4.0x4.0) Steel, Galv. Louvres LOUVER(AL) (Size 1.2x1.2) Including accessories Bill Of Quantities Process Plant Project Bill of Quantities Item 20810 20820 20830 Description Unit Finishing Flooring CARPET TILE Modular carpet tile ACCESS FLOOR Rubber tile finish(H=600) - Galvanized steel frame filled with cement grout H=600mm,including accessories & anchor bolt including the 2% of the spare material supply BASE BOARD VINYL (H=100) 20850 20860 20870 20880 20890 20900 20910 20920 20930 20940 20950 20960 20970 20980 Rate Amount m2 43.70 90.00 3,933.00 m2 354.20 820.00 290,444.00 m 597.10 76.00 45,379.60 1.00 339,756.60 339,756.60 m2 2,196.50 96.00 210,864.00 m2 697.04 98.00 68,309.92 m2 3,686.50 88.00 324,412.00 m2 687.75 120.00 82,530.00 m2 360.87 100.00 36,087.00 m2 2,415.71 88.00 212,582.48 m2 24.15 75.00 1,811.25 m2 4,396.40 75.00 329,730.00 m2 279.45 77.00 21,517.65 m2 5,252.81 66.00 346,685.46 m2 769.43 81.00 62,323.83 m2 350.68 96.00 33,665.28 m 667.87 22.00 14,693.14 m m 163.30 22.99 19.00 25.00 3,102.70 574.75 Sub Total Painting: m2 21,117.29 82.82 1,748,889.46 Sub Total Flooring: LS 20840 Quantity Painting ACRYLIC PAINT On gypsum board - Fenomastic 04 flat emulsion w/Fenomastic 20 semi Gloss emulsion finish coat Acrylic emulsion Paint conforming to SASO SSA 470 for exterior emulsion ACRYLIC PAINT DOOR & WINDOW, Polyamide, Oil Paint 2 Plies ACRYLIC PAINT Fenomastic 04 flat emulsion w/Fenomastic 20 semi Gloss emulsion finish coat Acrylic emulsion Paint conforming to SASO SSA 470 for exterior emulsion ACRYLIC PAINT On exposed Con'c celing - Fenomastic 04 flat emulsion 2 coats Acrylic emulsion Paint conforming to SASO SSA 470 for exterior emulsion ACRYLIC PAINT Acrylic latex paint for exposed Conc.(WeatherProofing) ACRYLIC PAINT Block filler & Fenomastic 04 flat emulsion Acrylic emulsion paint cinforming to SASO SSA 470 for Exterior emulsion EPOXY COATING T=0.2mm Dust-proofing EPOXY COATING T=0.2mm Dust-proofing EPOXY COATING T=0.2mm For dust-proofing, under access floor Coaltar Epoxy,for U/G RC Surface,400micro (250mic.x 2plys) URETHANE COATING One Pack Moisture cured, 500micro 1 Ply VINYL TILE Resilient Vinyl Tile,300x300x3T,Homogenious type BASE BOARD SELLAMIN PAINT base board enamel paint(H=100) ARCRLIC PAINT (H=100) BASE BOARD EPOXY PAINT 20990 Tile CERAMIC TILE (INT.- WALL) m2 291.87 450.00 131,341.50 21000 CERAMIC TILE (FLOOR) m2 91.38 390.00 35,638.20 21010 ACIDPROOF TILE m2 26.45 650.00 17,192.50 Bill Of Quantities Process Plant Project Bill of Quantities Item Description Unit Sub Total Tile: m2 21020 21030 21040 Gypsum Board SETTING GYPSUM BOARD m2 16mm,for wall,including 22 gage steel stud frame(64) & runner & bead & sealant on the other side of the steel framed metal sheet wall cladding GYPSUM BOARD m2 GYPSUM PARTITION m2 Sub Total Gypsum Board: m2 Quantity Rate Amount 409.70 449.53 184,172.20 2,196.50 160.00 351,440.00 41.90 7.04 180.00 170.00 7,542.00 1,196.80 2,245.44 160.40 360,178.80 187.22 1,080.00 202,197.60 21060 Plastering METAL LATH m2 Heavy duty expanded metal mesh - Hot dip galvanized(excluding the steel frames),removable, 8~12 gage 13mm Max.gap CEMENT MORTAR m2 1,522.98 59.00 89,855.82 21070 CEMENT MORTAR m2 4,408.77 30.00 132,263.10 21080 CEMENT MORTAR m2 2,415.71 30.00 72,471.30 21090 LEVELLING MORTAR For roof STEEL TROWEL FINISH m2 963.60 57.00 54,925.20 m2 1,944.42 10.00 19,444.20 HARDENER Metallic,aggregate dry-shake floor hardener(including water soluble inorganic silicate based compound finish) MORTAR GROUTING AROUND WINDOW FRAME m2 752.25 55.00 41,373.75 m 38.64 47.00 1,816.08 9,312.00 65.97 614,347.05 m2 888.95 130.00 115,563.50 m2 407.10 27.00 10,991.70 m2 481.85 36.00 17,346.60 Sub Total Ceilings: LS 1.00 143,901.80 143,901.80 Sub Total Finishing: LS 1.00 3,391,245.91 3,391,245.91 m2 6.73 3,460.00 23,285.80 EA 1.00 35,370.00 35,370.00 21050 21100 21110 21120 Sub Total Plastering : m2 21130 21140 21150 Ceilings ACOUSTIC BOARD 15x600x600 - For ceiling,including paint including the 2% of the spare material supply CEILING SYSTEM 2 Lightweight ceiling frame - T bar CEILING SYSTEM 2 Lightweight ceiling frame - M bar 21170 Accessories TOILET PARTITION Including partition door and accessories FRP SEPTIC TANK 21180 FRP SEPTIC TANK EA 2.00 35,370.00 70,740.00 21190 FRP SEPTIC TANK 50 PERSON EA 1.00 52,280.00 52,280.00 Sub Total Accessories: LS 1.00 181,675.80 181,675.80 21160 Bill Of Quantities Process Plant Project Bill of Quantities Item 21200 Description Unit Furniture CURTAIN BOX Quantity Rate Amount m2 11.22 250.00 2,805.00 Sub Total Furniture: LS 1.00 2,805.00 2,805.00 Sub Total Building Work: LS 1.00 20,214,963.30 20,214,963.30 Ton 2,420.88 2,450.00 5,931,156.00 30010 CHK'D PLATE Ton Steel angle framed including painting works, HOT DIP GALV. 5.18 6,690.00 34,654.20 30020 Fabrication and Erection of Access Platform for Operation and Ton Maintenance Purpose 50.00 18,410.00 920,500.00 Sub Total Structural Steel: ton 2,476.06 2,781.16 6,886,310.20 m2 5,657.25 260.00 1,470,885.00 m2 540.00 110.00 59,400.00 Sub Total Grating & Deck Plate: m2 6,197.25 246.93 1,530,285.00 3,015.41 300.00 904,623.00 11.50 320.00 3,680.00 7.25 260.00 1,885.00 m 477.86 390.00 186,365.40 m 412.14 1,150.00 473,961.00 Sub Total Handrail, Ladders & Stairs: m 3,924.16 400.22 1,570,514.40 EA 850.00 21.00 17,850.00 EA 102.00 41.00 4,182.00 Sub Total Anchor Bolts: ea 952.00 23.14 22,032.00 m2 2,661.84 31.00 82,516.89 Sub Total Field Painting: LS 1.00 82,516.89 82,516.89 30000 30030 30040 30050 30060 30070 30080 30090 30100 30110 30120 Structural Steel Work Structural Steel Structural Steel STEEL ERECTION Grating & Deck Plate GRATING (SERRATED) F-32 (HOT DIP GALV. ) DECK PLATE Handrail, Ladders & Stairs HANDRAIL (SECL STANDARD) m Including Hot dip galvanizing(25kg/m)+POLYURETHANE COATING 50 MIC. H=1.1(Post&Top/Middle Rail Pipe) HANDRAIL (SECL STANDARD) m Removable Type, Including Hot dip galvanized H=1.1(Post & Top/Middle Rail Pipe) STEEL LADDER WITHOUT CAGE m STEEL LADDER WITH CAGE Hop Dip Galvanizing STEEL STAIR(SECL STD'D) w/ HANDRAIL (Hop Dip Galvanized) W=800~900 FL:GRTG.F-32 Anchor Bolts SET ANCHOR BOLT Expansion stud anchor SET ANCHOR BOLT Expansion Stud anchor Field Painting TOUCH UP PAINT Grouting Bill Of Quantities Process Plant Project Bill of Quantities Item 30130 Description Unit NON-SHRINK GROUT Quantity Rate Amount m3 11.54 5,210.00 60,123.40 Sub Total Grouting: LS 1.00 60,123.40 60,123.40 Sub Total Structural Steel: ton 2,847.00 3,565.78 10,151,781.89 30140 Roofing & Siding Work Roofing & Siding F.M SHEET (V-115) : FOR ROOFING m2 1,807.45 380.00 686,831.00 30150 F.M SHEET (V-115) : FOR SIDING m2 1,937.70 360.00 697,572.00 30160 S/W PANEL (GLASS WOOL) : FOR ROOFING Roof : C/S(0.6)+75+C/S(0.7) S/W PANEL (GLASS WOOL) : FOR SIDING Wall : C/S(0.6)+50+C/S(0.7) m2 37.98 27.00 1,025.46 m2 113.40 27.00 3,061.80 Sub Total Roofing & Siding: LS 1.00 1,388,490.26 1,388,490.26 m 469.52 170.00 79,818.40 m 364.30 280.00 102,004.00 m 360.41 450.00 162,184.50 Sub Total Flashing: m 1,194.23 288.06 344,006.90 m 408.98 100.00 40,898.00 m 246.73 370.00 91,290.10 Sub Total Gutter: m 655.71 201.60 132,188.10 30170 30180 30190 30200 30210 30220 Flashing FLASHING (COLOR SHEET) Factory painted galvanized steel FLASHING (COLOR SHEET) Factory painted galvanized steel FLASHING (COLOR SHEET) Factory painted galvanized steel Gutter STEEL DOWNSPOUT Galvanized alkyd painted GUTTER Gal.2.3t+Epoxy coating 2plys 30230 Drains ROOF DRAIN EA 19.00 830.00 15,770.00 30240 ROOF DRAIN EA 50.00 790.00 39,500.00 30250 FLOOR DRAIN Dia.250, Stainless steel SPLASH BLOCK EA 10.00 1,030.00 10,300.00 EA 50.00 2,090.00 104,500.00 LEADER HEAD t=0.7 Factory painted galvanized steel EA 50.00 2,440.00 122,000.00 Sub Total Drains: LS 1.00 292,070.00 292,070.00 Sub Total Roofing & Siding Work: m2 3,614.00 596.78 2,156,755.26 Sub Total Structural Steel Work: LS 1.00 12,308,537.15 12,308,537.15 30260 30270 Process Piping Work Underground Piping Installation Pipe Bill Of Quantities Process Plant Project Bill of Quantities Item 40000 40010 40020 40030 40040 40050 40060 40070 40080 41140 41150 40090 40100 40110 40120 40130 40140 40150 40160 40170 40180 40190 40200 40210 40220 40230 40240 40250 40260 40270 40280 Description Unit Flange to Flange connection, Installation of In-line components such as PIV etc. 3" ~ 6" (STD) FBE Coated Steel Pipes (3-Layer (FBE+PP) Coated) 8" ~ 10" (STD) FBE Coated Steel Pipes (3-Layer (FBE+PP) Coated) 12" ~ 24" (Over 7.93 ~ 9.53T) FBE Coated Steel Pipes (3Layer (FBE+PP) Coated) 26" ~ 48" (Over 7.93 ~ 9.53T) FBE Coated Steel Pipes (3Layer (FBE+PP) Coated) 26" ~ 48" (Over 9.53 ~ 12.70T) FBE Coated Steel Pipes (3Layer (FBE+PP) Coated) Quantity Rate Amount D/I 781.50 25.00 19,537.50 D/I 1,560.00 120.00 187,200.00 D/I 98.00 68.00 6,664.00 D/I 7,608.00 98.00 745,584.00 D/I 2,982.00 120.00 357,840.00 D/I 356.00 130.00 46,280.00 Sub Total Pipe: D/I 13,385.50 101.83 1,363,105.50 m2 76.00 2,200.00 167,200.00 Sub Total Wrapping: LS 1.00 167,200.00 167,200.00 774.00 78.00 470.00 310.00 363,780.00 24,180.00 Sub Total Testing: LS 1.00 387,960.00 387,960.00 Sub Total Underground Piping Installation: DI 13,386.00 143.30 1,918,265.50 m3 m3 12.00 6.00 580.00 6,670.00 6,960.00 40,020.00 Sub Total Piping Civil Work: LS 1.00 46,980.00 46,980.00 DI DI DI DI DI DI DI DI DI DI DI DI DI DI DI DI DI DI DI DI 2.00 31,937.30 3.00 25.00 21,647.40 23,029.25 4.00 5,652.00 7,562.00 26.00 1,124.00 5,851.50 4.00 22.00 23,029.25 4.00 5,652.00 7,562.00 26.00 1,124.00 73.00 68.00 75.00 75.00 110.00 110.00 110.00 90.00 66.00 96.00 95.00 120.00 120.00 120.00 110.00 130.00 64.00 70.00 100.00 100.00 146.00 2,171,736.40 225.00 1,875.00 2,381,214.00 2,533,217.50 440.00 508,680.00 499,092.00 2,496.00 106,780.00 702,180.00 480.00 2,640.00 2,533,217.50 520.00 361,728.00 529,340.00 2,600.00 112,400.00 Sub Total Carbon Steel Pipe: DI 134,286.70 92.72 12,451,007.40 Wrapping Wrapping/Coating For Welding Joint ALL Size (Included wrapping material) Testing NDT/PMI/Thick Test Shop NDT Radiographic Test NDT/PMI/Thick Test Shop NDT Liquid Penetration Test Above Ground Piping Piping Civil Work Local Foundation Installation Con'c only Local Foundation Installation Grouting only Piping Installation Carbon Steel Pipe Up to 2.1/2" Carbon Steel Up to 2.1/2" Carbon Steel Class 3000 & Below Up to 2.1/2" Carbon Steel Class 6000 & Over Up to 2.1/2" Carbon Steel Class 3000 ~ 9000 Up to 2.1/2" Carbon Steel STD 3" ~ 6" Carbon Steel STD 3" ~ 6" Carbon Steel SCH XS 8" ~ 10" Carbon Steel STD 12" ~ 24" Carbon Steel Over 7.93 ~ 9.53T 12" ~ 24" Carbon Steel Over 12.70T ~ 15.88T 12" ~ 24" Carbon Steel Over 7.93 ~ 9.53T Up to 2.1/2" Carbon Steel SCH XS Up to 2.1/2" Carbon Steel SCH XXS Up to 2.1/2" Carbon Steel SCH160 3" ~ 6" Carbon Steel STD 3" ~ 6" Carbon Steel SCH XS 8" ~ 10" Carbon Steel STD 12" ~ 24" Carbon Steel Over 7.93 ~ 9.53T 12" ~ 24" Carbon Steel Over 12.70T ~ 15.88T 26" ~ 48" Carbon Steel Over 7.93 ~ 9.53T SHT Point Bill Of Quantities Process Plant Project Bill of Quantities Item 40290 40300 40310 40320 40330 40340 40350 40360 40370 40380 40390 40400 40410 40420 40430 40440 40450 40460 40470 40480 40490 40500 40510 40520 40530 40540 40550 40560 40570 40580 40590 40600 40610 40620 40630 40640 40650 40660 40670 40680 40690 40700 Description Unit Stainless Steel Pipe Up to 2.1/2" Stainless Steel SCH10S Up to 2.1/2" Stainless Steel SCH40S Up to 2.1/2" Stainless Steel SCH80S Up to 2.1/2" Stainless Steel SCH40S Up to 2.1/2" Stainless Steel SCH80S Up to 2.1/2" Stainless Steel Class 3000 & Below 3" ~ 6" Stainless Steel SCH10S 3" ~ 6" Stainless Steel SCH40S 3" ~ 6" Stainless Steel SCH80S 3" ~ 6" Stainless Steel SCH80S 3" ~ 6" Stainless Steel SCH10S 3" ~ 6" Stainless Steel SCH40S 8" ~ 10" Stainless Steel Below than SCH 40 8" ~ 10" Stainless Steel SCH10S 8" ~ 10" Stainless Steel SCH80S 8" ~ 10" Stainless Steel Below than SCH 40 8" ~ 10" Stainless Steel SCH10S 8" ~ 10" Stainless Steel SCH80S 12" ~ 24" Stainless Steel Up to 7.93T 12" ~ 24" Stainless Steel Over 7.93 ~ 9.53T 12" ~ 24" Stainless Steel Over 9.53T ~ 12.70T 12" ~ 24" Stainless Steel Up to 7.93T 12" ~ 24" Stainless Steel Over 7.93 ~ 9.53T 12" ~ 24" Stainless Steel Over 9.53T ~ 12.70T 26" ~ 48" Stainless Steel Over 7.93 ~ 9.53T 26" ~ 48" Stainless Steel Over 7.93 ~ 9.53T Quantity Rate Amount DI DI DI DI DI DI DI DI DI DI DI DI DI DI DI DI DI DI DI DI DI DI DI DI DI DI 18,058.50 1,473.30 480.50 2,044.00 125.50 12,606.60 28,109.75 91.50 179.00 179.00 28,109.75 91.50 1,406.00 1,342.00 243.00 1,406.00 1,342.00 243.00 1,637.00 397.00 106.00 1,637.00 397.00 106.00 140.00 140.00 90.00 94.00 110.00 40.00 49.00 51.00 160.00 160.00 220.00 99.00 85.00 85.00 130.00 140.00 170.00 59.00 58.00 77.00 150.00 160.00 230.00 84.00 100.00 150.00 240.00 170.00 1,625,265.00 138,490.20 52,855.00 81,760.00 6,149.50 642,936.60 4,497,560.00 14,640.00 39,380.00 17,721.00 2,389,328.75 7,777.50 182,780.00 187,880.00 41,310.00 82,954.00 77,836.00 18,711.00 245,550.00 63,520.00 24,380.00 137,508.00 39,700.00 15,900.00 33,600.00 23,800.00 Sub Total Stainless Steel Pipe: DI 102,090.90 104.70 10,689,292.55 DI DI DI DI DI DI 3,314.60 4,458.70 2,726.50 2,736.50 697.00 2,458.50 9.85 15.00 11.00 11.00 11.00 11.00 32,648.81 66,880.50 29,991.50 30,101.50 7,667.00 27,043.50 Sub Total Screw Joint Pipe: DI 16,391.80 11.86 194,332.81 DI 210.00 8.46 1,776.60 Sub Total PVC Pipe: DI 210.00 8.46 1,776.60 1,178.00 48.00 56,544.00 EA DI 5.00 24.00 190.00 260.00 950.00 6,240.00 DI DI 30.00 2.00 15.00 56.00 450.00 112.00 DI DI 11.00 16.00 26.00 380.00 286.00 6,080.00 DI DI 1,411.00 598.00 25.00 25.00 35,275.00 14,950.00 Screw Joint Pipe Screw Joint Screw Joint Cast Iron Screw Joint Carbon Steel Screw Joint Carbon Steel Screw Joint Cooper Screw Joint Stainless Steel PVC Pipe Glass Fiber/PVC Appurtenances Appurtenaces Installation Multi Side Mounting Hose/Tube(W/ Connection) Apputenaces installation Multi Side Mounting Sight Glass Appurtenaces Installation Multi Side Mounting Safety(Eye) Shower Appurtenaces Installation Single Side Mounting pot Appurtenaces Installation Single Side Mounting Injection Nozzle Appurtenaces Installation Single Side Mounting Silencer Appurtenaces Installation Single Side Mounting Sampling System Appurtenaces Installation Single Side Mounting Strainer Appurtenaces Installation Single Side Mounting Steam Trap DI Bill Of Quantities Process Plant Project Bill of Quantities Item 40710 40720 40730 40740 40830 40840 40850 Description Unit 40890 40900 40910 40920 40930 40940 40950 40960 40970 40980 40990 41000 41010 41020 41030 Rate Amount Sub Total Appurtenances: DI 3,275.00 36.91 120,887.00 DI DI DI DI 19,007.40 220.80 252.00 7,333.00 25.00 23.00 25.00 38.00 475,185.00 5,078.40 6,300.00 278,654.00 Sub Total Bolt Up All Material: DI 26,813.20 28.54 765,217.40 Sub Total Piping Installation: DI 283,067.60 85.57 24,222,513.76 5.40 122.20 15,030.00 13,850.00 81,162.00 1,692,470.00 3.30 8,910.00 29,403.00 130.90 13,774.14 1,803,035.00 EA EA EA 31.00 12.00 18.00 140.00 140.00 1,640.00 4,340.00 1,680.00 29,520.00 Sub Total Fire Hydrant: ea 61.00 582.62 35,540.00 EA EA EA EA 12.00 200.00 200.00 200.00 55.00 37.00 37.00 37.00 660.00 7,400.00 7,400.00 7,400.00 Sub Total Sprinkers: ea 612.00 37.35 22,860.00 EA EA EA 4.00 2.00 2.00 170.00 140.00 94.00 680.00 280.00 188.00 Sub Total Deluge Valves: ea 8.00 143.50 1,148.00 EA EA EA EA 1.00 1.00 2.00 2.00 230.00 170.00 140.00 94.00 230.00 170.00 280.00 188.00 Sub Total Strainer Baskets: ea 6.00 144.67 868.00 EA EA EA EA 120.00 12.00 40.00 6.00 120.00 240.00 120.00 240.00 14,400.00 2,880.00 4,800.00 1,440.00 Sub Total Extinguishers: ea 178.00 132.13 23,520.00 Bolt Up All Material Bolting Up for Flange All Material Bolting Up for Flange All Material Bolting Up All Material Bolting Up for Valve All Material Pipe Supports Spring hanger/Support Installation ALL Size M/T Fabrication & Installation of Piping Support - Carbon Steel with M/T H.D.G (including U-bolts and clamps) Fabrication & Installation of Piping Support - Stainless Steel M/T (including U-bolts and clamps) Sub Total Pipe Supports: M/T 40860 40870 40880 Quantity Fire Accessories Fire Hydrant FIRE HYDRANT (4 WAY) FIRE HYDRANT WITH MONITOR (5 WAY) FIRE HOSE RACK Sprinkers NOZZLE FOR MONITOR WATER SPRAY NOZZLE SPRINKLER PILOT HEAD SPRINKLER HEAD(CLOSED TYPE) Deluge Valves DELUGE VALVE ASSEMBLY DELUGE VALVE ASSEMBLY DELUGE VALVE ASSEMBLY Strainer Baskets STRAINER(BASKET TYPE) STRAINER(BASKET TYPE) STRAINER(BASKET TYPE) STRAINER(BASKET TYPE) Extinguishers PORTABLE DRY CHEMCIAL EXTINGUISHER (7.7 kg) WHEELED DRY CHEMICAL EXTINGUISHER (56.7 kg) PORTABLE CO2 EXTINGUISHER (6.9 kg) WHEELED CO2 EXTINGUISHER (45.3 kg) Bill Of Quantities Process Plant Project Bill of Quantities Item Description Unit Sub Total Fire Accessories: LS 41040 41050 41060 41070 41080 41090 41100 41110 41120 41130 41160 41170 41180 41190 41200 41210 41220 41230 41240 41250 40750 40760 40770 40780 40790 40800 40810 40820 Quantity Rate Amount 1.00 83,936.00 83,936.00 EA EA 65.00 65.00 58.00 58.00 3,770.00 3,770.00 Sub Total Steam Manifolds: ea 130.00 58.00 7,540.00 5,942.00 3,512.00 30.00 36.00 178,260.00 126,432.00 Sub Total Steam Tracing: LS 1.00 304,692.00 304,692.00 Sub Total Steam Accessories: LS 1.00 312,232.00 312,232.00 EA EA EA EA EA EA 158.00 13.00 2.00 158.00 13.00 2.00 58.00 85.00 280.00 1,210.00 1,580.00 1,940.00 9,164.00 1,105.00 560.00 191,180.00 20,540.00 3,880.00 Sub Total PSV: LS 1.00 226,429.00 226,429.00 1,728.00 17,500.00 1,728.00 17,307.00 1,412.00 14,319.00 1,412.00 14,158.00 1,074.40 300.00 360.00 300.00 470.00 300.00 360.00 300.00 470.00 270.00 518,400.00 6,300,000.00 518,400.00 8,134,290.00 423,600.00 5,154,840.00 423,600.00 6,654,260.00 290,088.00 Sub Total Testing: LS 1.00 28,417,478.00 28,417,478.00 DI 5,103.10 130.00 663,403.00 Sub Total In Line Instruments: LS 1.00 663,403.00 663,403.00 5,060.00 35.00 12.00 2.00 3.00 7.00 50.00 18.00 300.00 140.00 458,370.00 1,710.00 1,130.00 34,400.00 91,080.00 10,500.00 1,680.00 916,740.00 5,130.00 7,910.00 1,720,000.00 300.00 160.00 48,000.00 Steam Accessories Steam Manifolds Installation of Steam Manifold, CM 8, 2"x1500 long Installation of Steam Manifold, SM 8, 2"x1500 long Steam Tracing Steam tracing, 1/2", Tube, A269 GR. TP316/316L Steam tracing, 1/2", Pre-insulated tube, A269 GR. TP316/316L PSV PSV PSV Installation Up to ND2.1/2" PSV PSV Installation ND5" ~ ND6" PSV PSV Installation ND5" ~ ND6" PSV PSV Popping Test Up to ND2.1/2" PSV PSV Popping Test ND3" ~ ND4" PSV PSV Popping Test ND5" ~ ND6" Testing NDT/PMI/Thick Test Field NDT Magnetic Test NDT/PMI/Thick Test Field NDT PMI Test NDT/PMI/Thick Test Field NDT Liquid Penetration Test NDT/PMI/Thick Test Field NDT Radiographic Test NDT/PMI/Thick Test Shop NDT Magnetic Test NDT/PMI/Thick Test Shop NDT PMI Test NDT/PMI/Thick Test Shop NDT Liquid Penetration Test NDT/PMI/Thick Test Shop NDT Radiographic Test Post Weld Heat Treatment (Included hardness test) In Line Instruments In-Line Instrument Miscellaneous Earth Bonding Lug Fabrication & Installation ALL Size Post Indicator Valve MONITOR Fabrication & Installation of Temporary Silencer Fabrication & Installation of Funnel Fabrication & Installation of Bird Screen Temp. piping for flushing, CW Passivation, Chemical cleaning (including pipes, fittings, valves, supports, etc.) Opening on grating for pipe and support Under 8" Refer to information "Standard Drawing for Bldg & Strl Grating Detail. M M Points Points Points SHT Points Points Points SHT DI EA EA EA EA EA EA M/T Points Bill Of Quantities Process Plant Project Bill of Quantities Item 50460 50470 50480 50490 50500 50510 50520 50530 50540 50550 50560 50570 50580 50590 50600 50610 50620 50630 50640 50650 50660 50670 50680 50690 50700 50710 50720 50730 50740 50750 50760 50770 Description Unit Quantity Rate Amount Sub Total Miscellaneous: LS 1.00 2,801,040.00 2,801,040.00 Sub Total Above Ground Piping: LS 1.00 58,577,046.76 58,577,046.76 Sub Total Process Piping Work: LS 1.00 60,495,312.26 60,495,312.26 Ton Ton Ton M3 M3 M3 Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton M3 M3 Ton 35.00 26.00 28.00 55.00 17.60 16.50 2.50 0.04 6.00 0.04 6.00 0.02 2.49 56.00 54.00 0.13 0.54 48.00 37.00 0.15 3,110.00 3,240.00 3,150.00 2,040.00 2,040.00 2,040.00 3,560.00 28,080.00 2,380.00 28,110.00 2,380.00 50,990.00 4,420.00 5,340.00 4,860.00 6,400.00 3,850.00 2,040.00 2,040.00 9,390.00 108,850.00 84,240.00 88,200.00 112,200.00 35,904.00 33,660.00 8,900.00 1,123.20 14,280.00 1,124.40 14,280.00 1,019.80 11,005.80 299,040.00 262,440.00 832.00 2,079.00 97,920.00 75,480.00 1,399.11 Sub Total Columns: Ton 391.01 3,207.03 1,253,977.31 Ton 1.00 7,860.00 7,860.00 Ton 1.00 9,390.00 9,390.00 Ton 4.50 4,640.00 20,880.00 Ton 6.50 3,950.00 25,675.00 Ton 25.40 4,240.00 107,696.00 Ton 5.00 4,020.00 20,100.00 Ton 3.00 4,080.00 12,240.00 Ton 8.00 3,610.00 28,880.00 Ton 6.00 3,950.00 23,700.00 Sub Total Vacuum System: Ton 60.40 4,245.38 256,421.00 67.00 82.00 11.80 12,040.00 11,870.00 1,740.00 806,680.00 973,340.00 20,532.00 Mechanical Erection Process Equipment Installation Heating Cooling Drying Equipment Columns DRYING COLUMN MEA COLUMN DEA SPLITTER COLUMN DRYING COLUMN MEA COLUMN DEA SPLITTER COLUMN DEA SPLITTER COLUMN DEA COLUMN DEA COLUMN TEA COLUMN TEA COLUMN MEA COLUMN MEA COLUMN DEA COLUMN TEA COLUMN DRYING COLUMN DRYING COLUMN DEA COLUMN TEA COLUMN DEA SPLITTER COLUMN Vacuum System DRYING COLUMN VACUUM SYSTEM (Refer to informative document attached) MEA COLUMN VACUUM SYSTEM (Refer to informative document attached) DEA SPLITTER VACUUM SYSTEM (Refer to informative document attached) DEA COLUMN VACUUM SYSTEM (Refer to informative document attached) TEA COLUMN VACUUM SYSTEM (Refer to informative document attached) REACTOR 120 VACUUM SYSTEM (Refer to informative document attached) POST TREATMENT VACUUM SYSTEM (Refer to informative document attached) REACTOR 220 VACUUM SYSTEM (Refer to informative document attached) REACTOR 320 VACUUM SYSTEM (Refer to informative document attached) Condenser DEA COLUMN CONDENSER TEA COLUMN CONDENSER AMMONIA STRIPPER MAIN CONDENSER Ton Ton Ton Bill Of Quantities Process Plant Project Bill of Quantities Item 50780 50790 50800 50810 50820 50830 50840 50850 50860 50870 50880 50000 50010 50020 50030 50040 50050 50060 50070 50080 50090 50100 50110 50120 50130 50140 50150 50160 50170 50180 50190 50200 50210 50220 50230 50240 50250 50260 50270 50280 50290 50300 50310 50320 50330 50340 50350 50360 50370 50380 50390 Description Unit AMMONIA STRIPPER AUXILIARY CONDENSER DRYING COLUMN CONDENSER MEA COLUMN CONDENSER DEA SPLITTER COLUMN CONDENSER ATMOSPHERIC STEAM CONDENSER REACTOR 120 CONDENSER POST TREATMENT CONDENSER REACTOR 220 CONDENSER REACTOR 320 CONDENSER ATM STEAM CONDENSER EFFLUENT CONDENSER Quantity Rate Amount Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton 15.00 20.80 23.00 28.00 4.50 1.50 1.40 1.40 1.10 1.20 1.30 2,350.00 3,710.00 3,520.00 2,380.00 2,340.00 3,850.00 3,450.00 3,450.00 3,940.00 3,940.00 3,450.00 35,250.00 77,168.00 80,960.00 66,640.00 10,530.00 5,775.00 4,830.00 4,830.00 4,334.00 4,728.00 4,485.00 Sub Total Condenser: Ton 260.00 8,077.24 2,100,082.00 Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton 0.20 0.20 0.20 0.20 4.00 0.20 0.60 0.60 2.10 0.20 0.60 0.60 2.00 0.20 1.90 0.50 18,750.00 18,750.00 18,750.00 18,750.00 2,340.00 8,950.00 3,370.00 3,370.00 3,220.00 11,260.00 4,200.00 4,200.00 1,130.00 7,670.00 3,220.00 5,650.00 3,750.00 3,750.00 3,750.00 3,750.00 9,360.00 1,790.00 2,022.00 2,022.00 6,762.00 2,252.00 2,520.00 2,520.00 2,260.00 1,534.00 6,118.00 2,825.00 Sub Total Heater: Ton 14.30 3,984.97 56,985.00 Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton 4.10 4.10 4.10 4.10 4.10 2.70 0.20 1.00 1.00 1.40 1.60 0.50 0.10 5.90 1.80 1.50 5.90 1.40 1.20 0.20 2.80 0.80 0.20 0.20 2,340.00 2,340.00 2,340.00 2,340.00 2,460.00 3,450.00 10,480.00 3,940.00 3,940.00 3,450.00 3,430.00 5,400.00 19,140.00 2,320.00 3,120.00 1,260.00 5,900.00 3,450.00 3,450.00 7,670.00 2,890.00 3,180.00 2,930.00 6,400.00 9,594.00 9,594.00 9,594.00 9,594.00 10,086.00 9,315.00 2,096.00 3,940.00 3,940.00 4,830.00 5,488.00 2,700.00 1,914.00 13,688.00 5,616.00 1,890.00 34,810.00 4,830.00 4,140.00 1,534.00 8,092.00 2,544.00 586.00 1,280.00 Sub Total Cooler: Ton 50.90 3,176.72 161,695.00 Heater Utility Station Steam Desuperheater MS DESUPERHEATER MS DESUPERHEATER LS DESUPERHEATER AMMONIA STRIPPER PRE-HEATER WASTE WATER HEATER NP PREHEATER FA PREHEATER WATER CIRCULATION HEATER I TEMPERED WATER HEATER I DEG PREHEATER SMO PREHEATER WATER CIRCULATION HEATER II TEMPERED WATER HEATER II WATER CIRCULATION HEATER III TEMPERED WATER HEATER III Cooler FIRST REACTOR INTERCOOLER SECOND REACTOR INTERCOOLER THIRD REACTOR INTERCOOLER FOUTH REACTOR INTERCOOLER FIFTH REACTOR INTERCOOLER AMMONIA SOLUTION COOLER RECYCLE WATER COOLER MEA PRODUCT COOLER AMINES RECYCLE COOLER DEA PRODUCT COOLER TEA PRODUCT COOLER HEAVY AMINES COOLER LEAN WATER COOLER WATER CIRCULATION COOLER I POST TREATMENT CIRCULATION COOLER PRODUCT COOLER I WATER CIRCULATION COOLER II POLYSORBATE COOLER PEGs COOLER PEG 600 I COOLER WATER CIRCULATION COOLER III PRODUCT COOLER III C-67920 COOLER EFFLUENT COOLER Bill Of Quantities Process Plant Project Bill of Quantities Item 50400 50410 50420 50430 50440 50450 Description Unit Reboiler AMMONIA STRIPPER REBOILER DRYING COLUMN REBOILER MEA COLUMN REBOILER DEA SPLITTER COLUMN REBOILER DEA COLUMN REBOILER TEA COLUMN REBOILER 50920 50930 50940 50950 50960 50970 50980 50990 51000 51010 51020 51030 51040 51050 51060 51070 Rate Amount Ton Ton Ton Ton Ton Ton 16.00 20.50 8.30 17.20 23.50 22.50 2,350.00 3,730.00 1,900.00 2,440.00 3,570.00 3,630.00 37,600.00 76,465.00 15,770.00 41,968.00 83,895.00 81,675.00 Sub Total Reboiler: Ton 108.00 3,123.82 337,373.00 1.00 4,166,533.31 4,166,533.31 Ton Ton Ton 6.10 6.00 2.50 2,320.00 5,900.00 2,890.00 14,152.00 35,400.00 7,225.00 Sub Total Exchanger: Ton 14.60 3,888.84 56,777.00 Ton Ton Ton Ton Ton Ton 0.30 0.50 0.30 0.50 0.30 0.50 6,280.00 3,670.00 5,590.00 4,200.00 5,590.00 4,200.00 1,884.00 1,835.00 1,677.00 2,100.00 1,677.00 2,100.00 Sub Total Filter: Ton 2.40 4,697.08 11,273.00 Ton Ton Ton Ton Ton 0.10 0.10 0.10 0.10 0.10 23,430.00 23,430.00 23,430.00 23,430.00 23,430.00 2,343.00 2,343.00 2,343.00 2,343.00 2,343.00 Sub Total Eductor: Ton 0.50 23,430.00 11,715.00 Ton 11.00 127,390.00 1,401,290.00 Ton Ton 0.10 0.10 23,430.00 23,430.00 2,343.00 2,343.00 Sub Total Compressor: Ton 11.20 125,533.57 1,405,976.00 Ton 9.40 1,820.00 17,108.00 Sub Total Receiver: Ton 9.40 1,820.00 17,108.00 Ton 15.00 9,610.00 144,150.00 1.00 144,150.00 144,150.00 Sub Total Heating Cooling Drying Equipment: LS 50890 50900 50910 Quantity Gas & Liquid Handling Equipment Gas Handling Equipment Exchanger REACTOR 120 EXCHANGER REATOR 220 EXCHANGER REACTOR 320 EXCHANGER Filter BASKET FILTER I CARTRIDGE FILTER I BASKET FILTER II CARTRIDGE FILTER II BASKET FILTER III CARTRIDGE FILTER III Eductor STEAM EDUCTOR STEAM EDUCTOR STEAM EDUCTOR STEAM EDUCTOR STEAM EDUCTOR Compressor HP Nitrogen Compressor Package (Refer to informative document attached) 5 Ton Geared Trolley with Chain Block 2 Ton Manual Geared Trolley Chain Hoist Receiver HP Nitrogen Compressor Discharge Receiver Evaporator EVAPORATOR (Refer to informative document attached) Sub Total Evaporator: LS Bill Of Quantities Process Plant Project Bill of Quantities Item 51080 51090 51100 51110 Description Unit Reactor ETHANOLAMINES REACTORS ETHOXYLATION I REACTOR ETHOXYLATION II REACTOR ETHOXYLATION III REACTOR Rate Amount Ton Ton Ton Ton 80.00 23.70 23.70 10.30 1,990.00 2,730.00 2,730.00 1,830.00 159,200.00 64,701.00 64,701.00 18,849.00 Sub Total Reactor: Ton 137.70 2,232.76 307,451.00 1.00 1,954,450.00 1,954,450.00 0.20 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 1.60 0.60 0.60 1.20 0.80 1.60 0.10 1.80 0.06 3.00 1.00 1.08 1.60 1.60 1.80 0.30 0.60 0.30 0.60 1.00 3.00 1.00 9.00 2.60 4.40 1.40 0.40 0.40 4.60 0.80 2.40 1.60 1.20 1.80 0.24 15,960.00 15,960.00 15,960.00 15,940.00 15,960.00 15,960.00 15,960.00 15,960.00 15,960.00 15,960.00 15,960.00 15,960.00 15,960.00 6,400.00 9,080.00 9,080.00 9,590.00 9,590.00 4,260.00 15,960.00 3,630.00 22,330.00 6,400.00 10,600.00 9,590.00 9,590.00 9,590.00 15,960.00 23,430.00 23,430.00 23,430.00 23,430.00 14,070.00 9,390.00 15,560.00 9,390.00 13,680.00 9,390.00 13,680.00 22,210.00 23,430.00 9,390.00 15,560.00 14,070.00 14,070.00 13,300.00 14,070.00 23,430.00 3,192.00 4,788.00 4,788.00 4,782.00 4,788.00 4,788.00 4,788.00 4,788.00 4,788.00 4,788.00 4,788.00 4,788.00 4,788.00 10,240.00 5,448.00 5,448.00 11,508.00 7,672.00 6,816.00 1,596.00 6,534.00 1,339.80 19,200.00 10,600.00 10,357.20 15,344.00 15,344.00 28,728.00 7,029.00 14,058.00 7,029.00 14,058.00 14,070.00 28,170.00 15,560.00 84,510.00 35,568.00 41,316.00 19,152.00 8,884.00 9,372.00 43,194.00 12,448.00 33,768.00 22,512.00 15,960.00 25,326.00 5,623.20 Sub Total Gas Handling Equipment: LS 51120 51130 51140 51150 51160 51170 51180 51190 51200 51210 51220 51230 51240 51250 51260 51270 51280 51290 51300 51310 51320 51330 51340 51350 51360 51370 51380 51390 51400 51410 51420 51430 51440 51450 51460 51470 51480 51490 51500 51510 51520 51530 51540 51550 51560 51570 51580 51590 Quantity Liquid Handling Equipment Pumps NP PROCESS FEED PUMP II AE3EO TRANSFER PUMP AE7EO TRANSFER PUMP AE9EO TRANSFER PUMP AE12EO TRANSFER PUMP NP3EO TRANSFER PUMP NP7EO TRANSFER PUMP NP9EO TRANSFER PUMP NP15EO/NP20EO TRANSFER PUMP NP25EO/NP30EO TRANSFER PUMP PEG 200 TRANSFER PUMP PEG 400/ PEG 600 TRANSFER PUMP PEG 1200/ PEG 1500 TRANSFER PUMP CONDENSATE RETURN PUMP CATALYST PUMP NEUTRALIZER PUMP SCRUBBER RECIRCULATION PUMP ORGANIC BLOW DOWN PUMP AQUEOUS EFFLUENT TRANSFER PUMP 20% NaOH Feed Pump TK-67930 RECIRCULATION PUMP ACID PUMP I DELUGE WATER PUMP Amines Storage Area PCS Sump Pump MEA Loading Pumps DEA Loading Pumps TEA 99 Loading Pump SANITARY PUMP (Including Startup Panel) ETHOXYLATE DRUMMING PUMP FA UNLOADING PUMP NP UNLOADING PUMP Eye Wash/Safety Shower Water Supply Pump Ammonia Transfer Pumps Deluge Water Pump - 1 Potentially Contaminated Surface Water Sump Pump - 1 EO FEED PUMPS AMMONIA SOLUTION CIRCULATION PUMPS AMMONIA SOLUTION FEED PUMPS AMINES RERUN PUMP RICH WATER HOT WELL PUMPS LEAN WATER HOT WELL PUMPS DRYING COLUMN BOTTOM PUMPS CYCLE WATER PUMPS MEA COLUMN BOTTOM PUMPS MEA PRODUCT PUMPS MEA TRANSFER PUMPS DEA SPLITTER BOTTOM PUMPS AMINES RECYCLE PUMPS Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Bill Of Quantities Process Plant Project Bill of Quantities Item 51600 51610 51620 51630 51640 51650 51660 51670 51680 51690 51700 51710 51720 51730 51740 51750 51760 51770 51780 51790 51800 51810 51820 51830 51840 51850 51860 51870 51880 51890 51900 51910 51920 51930 51940 51950 51960 51970 51980 51990 52000 52010 52020 52030 52040 52050 52060 52070 52080 52090 Description Unit DEA COLUMN BOTTOM PUMPS DEA PRODUCT PUMPS DEA TRANSFER PUMPS TEA COLUMN BOTTOM PUMPS TEA PRODUCT PUMPS TEA TRANSFER PUMPS TEA TOP COLUMN PURGE PUMP HEAVIES TRANSFER PUMP CONDENSATE RETURN PUMPS COLD COOLING WATER BOOSTER PUMPS WASTE WATER PUMPS DELUGE WATER PUMP BLOW DOWN DRUM PUMP REACTOR 120 RECIRCULATION PUMP WATER CIRCULATION PUMP I POST TREATMENT CIRCULATION PUMP EFFLUENT TRANSFER PUMP I HOLDING VESSEL I TRANSFER PUMP TEMPERED WATER RECIRCULATION PUMP I REACTOR 220 RECIRCULATION PUMP WATER CIRCULATION PUMP II EFFLUENT TRANSFER PUMP II POLYSORBATE TRANSFER PUMP PEGS TRANSFER PUMP PEG 600 I TRANSFER PUMP TEMPERED WATER RECIRCULATION PUMP II REACTOR 320 RECIRCULATION PUMP WATER CIRCULATION PUMP III HOLDING VESSEL III TRANSFER PUMP TA UNLOADING PUMP SMO UNLOADING PUMP CAO UNLOADING PUMP RAW MATERIAL BLOW DOWN PUMP FA PROCESS FEED PUMP I FA PROCESS FEED PUMP II FA PROCESS FEED PUMP III FA PROCESS FEED PUMP IV NP PROCESS FEED PUMP I Quantity Rate Amount Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton 2.80 1.20 1.40 3.20 1.20 1.40 0.07 0.90 2.20 9.90 1.00 0.20 0.70 2.30 1.50 2.90 0.20 0.70 0.20 2.40 0.50 0.20 0.30 0.40 0.20 0.20 1.90 1.40 0.30 0.20 0.30 0.20 0.70 0.20 0.20 0.20 0.20 0.30 13,680.00 13,300.00 12,850.00 9,390.00 13,320.00 12,850.00 19,140.00 9,590.00 9,590.00 6,400.00 10,600.00 15,960.00 8,760.00 6,400.00 9,330.00 6,400.00 15,960.00 8,760.00 15,960.00 6,400.00 10,600.00 15,960.00 15,960.00 10,600.00 19,140.00 19,140.00 6,400.00 9,330.00 15,960.00 15,960.00 15,960.00 15,960.00 8,760.00 15,960.00 15,960.00 15,960.00 15,960.00 15,960.00 38,304.00 15,960.00 17,990.00 30,048.00 15,984.00 17,990.00 1,339.80 8,631.00 21,098.00 63,360.00 10,600.00 3,192.00 6,132.00 14,720.00 13,995.00 18,560.00 3,192.00 6,132.00 3,192.00 15,360.00 5,300.00 3,192.00 4,788.00 4,240.00 3,828.00 3,828.00 12,160.00 13,062.00 4,788.00 3,192.00 4,788.00 3,192.00 6,132.00 3,192.00 3,192.00 3,192.00 3,192.00 4,788.00 Sub Total Pumps: Ton 104.15 10,468.07 1,090,250.00 Ton Ton 46.18 32.30 410.00 330.00 18,933.80 10,659.00 Sub Total Chemical Handling Equipment: Ton 78.48 377.07 29,592.80 Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton 0.10 0.10 0.10 0.10 0.10 0.10 1.00 0.10 0.20 0.20 28,110.00 28,110.00 28,110.00 28,110.00 28,110.00 28,110.00 9,390.00 23,430.00 27,530.00 18,750.00 2,811.00 2,811.00 2,811.00 2,811.00 2,811.00 2,811.00 9,390.00 2,343.00 5,506.00 3,750.00 Sub Total Mixer: Ton 2.10 18,026.19 37,855.00 Chemical Handling Equipment Catalyst Initial Loading (to TK-67911) Chemical Initial Filling (to TK-67912) Mixer STATIC MIXER STATIC MIXER STATIC MIXER STATIC MIXER STATIC MIXER STATIC MIXER REACTOR 120 STATIC MIXER POST TREATMENT VESSEL STATIC MIXER REACTOR 220 STATIC MIXER REACTOR 320 STATIC MIXER Bill Of Quantities Process Plant Project Bill of Quantities Item Description Unit Sub Total Liquid Handling Equipment: LS 52100 52110 52120 52130 52140 52150 52160 52170 52180 52190 52200 52210 52220 52230 52240 52250 52260 52270 52280 52290 52300 52310 52320 52330 52340 52350 52360 52370 52380 52390 52400 52410 52420 52430 52440 52450 52460 52470 52480 Quantity Rate Amount 1.00 1,157,697.80 1,157,697.80 Ton 40.00 6,150.00 246,000.00 Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton M3 M3 3.30 2.90 27.00 6.60 7.40 3.10 3.30 8.00 3.30 13.60 3.00 0.50 2,380.00 3,450.00 2,660.00 1,990.00 1,990.00 2,380.00 2,380.00 2,120.00 2,380.00 2,210.00 2,040.00 2,040.00 7,854.00 10,005.00 71,820.00 13,134.00 14,726.00 7,378.00 7,854.00 16,960.00 7,854.00 30,056.00 6,120.00 1,020.00 Sub Total Drum: Ton 122.00 3,612.96 440,781.00 Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton Ton 2.00 7.10 12.00 0.80 2.00 12.00 12.00 12.00 0.70 1.60 8.40 13.40 4.50 3,450.00 1,990.00 1,810.00 4,710.00 3,450.00 1,970.00 1,970.00 1,970.00 5,900.00 3,850.00 1,820.00 2,210.00 2,370.00 6,900.00 14,129.00 21,720.00 3,768.00 6,900.00 23,640.00 23,640.00 23,640.00 4,130.00 6,160.00 15,288.00 29,614.00 10,665.00 Sub Total Vessels: Ton 88.50 2,149.08 190,194.00 Ton Ton Ton 2.30 2.20 1.80 3,450.00 3,450.00 3,850.00 7,935.00 7,590.00 6,930.00 Sub Total Hotwell: Ton 6.30 3,564.29 22,455.00 M3 M3 3.00 1.50 7,830.00 7,830.00 23,490.00 11,745.00 Sub Total Disposal System: LS 1.00 35,235.00 35,235.00 5.50 14.60 14.60 14.60 4.80 5.70 5.70 3.40 2,020.00 2,320.00 2,140.00 2,140.00 2,370.00 2,020.00 2,020.00 920.00 11,110.00 33,872.00 31,244.00 31,244.00 11,376.00 11,514.00 11,514.00 3,128.00 Gas Liquid Storage Drum DRUM FILLING PACKAGE FACILITY (Refer to informative document attached) ORGANIC DRAIN DRUM EO SURGE DRUM AMMONIA SOLUTION SURGE DRUM LOW PRESSURE CONDENSATE FLASH DRUM ATMOSPHERIC CONDENSATE FLASH DRUM BLOWDOWN DRUM RAW MATERIAL BLOW DOWN DRUM DRUM FOR C-67920 ORGANIC BLOW DOWN DRUM AQUEOUS EFLUENT BLOW DOWN DRUM LOW PRESSURE CONDENSATE FLASH DRUM ATMOSPHERIC CONDENSATE FLASH DRUM Vessels WATER EXPANSION VESSEL I POST TREATMENT VESSEL HOLDING VESSEL I KNOCK DOWN VESSEL II WATER EXPANSION VESSEL II POLYSORBATE HOLDING VESSEL PEGS HOLDING VESSEL PEG 600 I HOLDING VESSEL KNOCK DOWN VESSEL III WATER EXPANSION VESSEL III HOLDING VESSEL III ATM FLASH VESSEL HIGH PRESSURE NITROGEN VESSEL Hotwell HOT WELL I HOT WELL II EJECTORS HOT WELL Disposal System Lube Oil Charge & Flushing & Disposal Seal Oil Charge & Flushing & Disposal Tanks RECYCLE WATER TANK MEA DAY TANKS DEA DAY TANKS TEA DAY TANKS HEAVIES DAY TANK CATALYST TANK NEUTRALIZER TANK Eye Wash/Safety Shower Water Storage Tank Ton Ton Ton Ton Ton Ton Ton Ton Bill Of Quantities Process Plant Project Bill of Quantities Item 52490 52500 52510 52520 52530 52540 52550 52560 52570 Description Unit AQUEOUS EFFLUENT NEUTRALIZATION TANK ACID TANK 3,430.00 5,640.00 7,546.00 1,974.00 Sub Total Tanks: Ton 71.45 2,162.66 154,522.00 Sub Total Gas Liquid Storage: LS 1.00 843,187.00 843,187.00 Sub Total Gas & Liquid Handling Equipment: LS 1.00 3,955,334.80 3,955,334.80 4.30 2.90 0.01 0.04 0.04 1.00 2.70 2,280.00 2,370.00 90,790.00 19,140.00 19,140.00 2,040.00 2,040.00 9,804.00 6,873.00 726.32 765.60 765.60 2,040.00 5,508.00 1.00 26,482.52 26,482.52 4.30 4.00 0.54 2,340.00 2,040.00 3,850.00 10,062.00 8,160.00 2,079.00 1.00 20,301.00 20,301.00 Ton Ton Ton 20.00 1.50 0.18 3,770.00 9,500.00 9,380.00 75,400.00 14,231.00 1,688.40 Sub Total Stripper: Ton 21.68 4,212.54 91,319.40 1.00 138,102.92 138,102.92 Ton Ton Ton Ton Ton 0.10 0.10 0.10 1.10 0.10 23,430.00 23,430.00 23,430.00 4,710.00 23,430.00 2,343.00 2,343.00 2,343.00 5,181.00 2,343.00 Sub Total Pot: Ton 1.50 9,702.00 14,553.00 Ton 1.00 9,390.00 9,390.00 1.00 9,390.00 9,390.00 Ton 25.00 1,910.00 47,750.00 Ton 3.40 300.00 1,020.00 Pollution Control Equipment Scrubber EO SCRUBBER EO CAUSTIC SCRUBBER EO SCRUBBER EO CAUSTIC SCRUBBER EO CAUSTIC SCRUBBER EO SCRUBBER EO CAUSTIC SCRUBBER Ton Ton Ton Ton Ton M3 M3 Absorber AMMONIA ABSORBER AMMONIA ABSORBER AMMONIA ABSORBER Ton M3 Ton Stripper AMMONIA STRIPPER AMMONIA STRIPPER AMMONIA STRIPPER Sub Total Pollution Control Equipment: LS 52700 52710 52720 52730 52740 52640 Other Equipment Pot CORROSION INHIBITOR POT CORROSION INHIBITOR POT CORROSION INHIBITOR POT KNOCK OUT POT SEAL POT FOR TK-66911 Ejector EJECTOR Sub Total Ejector: LS 52650 52660 Amount 2.20 0.35 Sub Total Absorber: LS 52610 52620 52630 Rate Ton Ton Sub Total Scrubber: LS 52580 52590 52600 Quantity Other WEIGHING BRIDGES (Refer to informative document attached) Eye Wash/Safety Shower Chiller Package (Refer to informative document attached) Bill Of Quantities Process Plant Project Bill of Quantities Item 52670 52680 52690 52750 52760 52770 52780 60000 60010 60020 60030 60040 60050 60060 60070 60080 60090 60100 60110 60120 60130 60140 Description Unit Ammonia Vapour Recovery Package (Refer to informative document attached) Safety valve poping test for rotating and package item at the site UV STERILIZER Rate Amount Ton 16.00 6,620.00 105,920.00 EA 51.00 940.00 47,940.00 Ton 0.20 9,390.00 1,878.00 Sub Total Other : LS 1.00 204,508.00 204,508.00 Sub Total Other Equipment: LS 1.00 228,451.00 228,451.00 120.00 6,270.00 752,400.00 Sub Total Miscellaneous Metal: LS 1.00 752,400.00 752,400.00 M3 M3 42.00 2.00 2,230.00 2,680.00 93,660.00 5,360.00 Sub Total Grouting: m3 44.00 2,250.45 99,020.00 Sub Total Process Equipment Installation: ton 1,800.00 5,188.80 9,339,842.03 LS 1.00 2,110,050.00 2,110,050.00 Sub Total HVAC & Plumbing: LS 1.00 2,110,050.00 2,110,050.00 Sub Total Mechanical Erection: LS 1.00 11,449,892.03 11,449,892.03 EA EA EA EA EA EA 320.00 120.00 180.00 91.00 10.00 37.00 150.00 170.00 730.00 710.00 700.00 1,410.00 48,000.00 20,400.00 131,400.00 64,610.00 7,000.00 52,170.00 Sub Total Lighting Fixtures: ea 758.00 426.89 323,580.00 4.00 8.00 10.00 2.00 5.00 1.00 1.00 3.00 7.00 240.00 240.00 200.00 680.00 680.00 680.00 570.00 570.00 680.00 960.00 1,920.00 2,000.00 1,360.00 3,400.00 680.00 570.00 1,710.00 4,760.00 41.00 423.41 17,360.00 438.00 49.00 21,462.00 Miscellaneous Metal PLATFORM & LADDER Ton Grouting Non-Shrink Grout Epoxy Grout HVAC & Plumbing HVAC & PLUMBING WORKS Electrical Systems Lighting System Lighting Fixtures LIGHTING FIXTURE EMER/STAND-BY LIGHTING FIXTURE LIGHTING FIXTURE2/36W LIGHTING FIXTURE4/36W LIGHTING FIXTURE13W EXIT LIGHT10W Lighting Panels PANEL BOARD( 30 )CKT PANEL BOARD( 24 )CKT PANEL BOARD( 24 )CKT LIGHTING PANELBOARD ( 30 )CKT RECEPTACLE PANEL ( 30 )CKT LIGHTING PANELBOARD ( 30 )CKT RECEPTACLE PANEL BOARD( 12 )CKT RECEPTACLE PANEL ( 12 )CKT LIGHTING PANELBOARD ( 30 )CKT SET SET SET SET SET SET SET SET SET Sub Total Lighting Panels: Set 60150 Quantity Lighting Junction Boxes JUNCTION BOX WITH COVER AND GASKETCAST IRON3/4" EA Bill Of Quantities Process Plant Project Bill of Quantities Item Description Unit Quantity Rate Amount 60160 JUNCTION BOX WITH COVER AND GASKETCAST IRON1" EA 101.00 52.00 5,252.00 60170 60180 60190 60200 60210 JUNCTION BOX WITH COVER AND GASKET3/4" JUNCTION BOX WITH COVER AND GASKET1" 4" SQUARE BOXZINC ELECTRO PLATE 3"X2" SQUARE BOXFOR OUTLET ZINC ELECTRO PLATE 3"X2" SQUARE BOX FOR SWITCHZINC ELECTRO PLATE1 GANG 4" SQUARE BOX FOR SWITCHZINC ELECTRO PLATE BUSHING & LOCK NUT FOR SQUARE BOX3/4" EA EA EA EA EA 438.00 101.00 669.00 72.00 16.00 49.00 52.00 49.00 38.00 38.00 21,462.00 5,252.00 32,781.00 2,736.00 608.00 EA EA 45.00 833.00 49.00 15.00 2,205.00 12,495.00 Sub Total Lighting Junction Boxes: ea 2,713.00 38.43 104,253.00 m m m m 836.00 26,493.00 2,946.00 164.00 13.00 16.00 13.00 13.00 10,868.00 423,888.00 38,298.00 2,132.00 Sub Total Lighting Cable: m 30,439.00 15.61 475,186.00 EA EA EA EA 1,633.00 126.00 1,302.00 81.00 5.07 5.07 5.07 5.07 8,279.31 638.82 6,601.14 410.67 Sub Total Cable Gland: ea 3,142.00 5.07 15,929.94 m 16,597.00 180.00 2,987,460.00 Sub Total Lighting Wire: m 16,597.00 180.00 2,987,460.00 1.00 3,478,575.94 3,478,575.94 2,724.00 34.00 92,616.00 m m 3,433.00 256.00 43.00 54.00 147,619.00 13,824.00 m 342.00 63.00 21,546.00 Sub Total Rigid Steel Conduit: m 6,755.00 40.80 275,605.00 60370 60380 PVC Conduit PVC CONDUITSCHEDULE 40 WITH RED CONCRETE3/4" m PVC CONDUITSCHEDULE 40 WITH RED CONCRETE1-1/4" m 1,928.00 12,836.00 0.00 22.00 0.00 282,392.00 60390 PVC CONDUITSCHEDULE 40 WITH RED CONCRETE2-1/2" m 299.00 42.00 12,558.00 Sub Total PVC Conduit: m 15,063.00 19.58 294,950.00 134.00 490.00 65,660.00 60220 60230 60240 60250 60260 60270 60280 60290 60300 60310 60320 Lighting Cabling Lighting Cable LIGHTING CABLE5/C * 6mm2 LIGHTING CABLE3/C * 6mm2 LIGHTING CABLE5/C * 10mm2 LIGHTING CABLE4/C * 6mm2 Cable Gland CABLE GLANDWEATHER PROOF TYPE3/4" CABLE GLANDWEATHER PROOF TYPE1" CABLE GLANDEXPLOSION PROOF TYPE3/4" CABLE GLANDEXPLOSION PROOF TYPE1" Lighting Wire LIGHTING WIRE4mm2 Sub Total Lighting Cabling: LS 60330 60340 60350 60360 60400 Lighting Conduit Rigid Steel Conduit RIGID STEEL CONDUIT HOT DIP GALVANIZED3/4" (22mm) m RIGID STEEL CONDUIT HOT DIP GALVANIZED1" (28mm) RIGID STEEL CONDUIT HOT DIP GALVANIZED1-1/4" (36mm) RIGID STEEL CONDUIT HOT DIP GALVANIZED1-1/2" Conduit Fittings FLEXIBLE CONDUITLIQUID TIGHT 3/4" EA Bill Of Quantities Process Plant Project Bill of Quantities Item Description Unit Sub Total Conduit Fittings: LS 60410 60420 60430 60440 60450 60460 60470 60480 60490 60500 60510 60520 60530 60540 60550 60560 60570 60580 60590 60600 60610 60620 60630 60640 60650 60660 60670 60680 60690 60700 60710 60720 60730 60740 Quantity Rate Amount 1.00 65,660.00 65,660.00 EA EA EA EA EA EA EA EA EA EA EA EA 206.00 1,354.00 186.00 922.00 1,905.00 2.00 2.00 197.00 1,905.00 2.00 2.00 197.00 26.00 29.00 35.00 38.00 84.00 94.00 100.00 110.00 8.76 8.76 8.76 8.76 5,356.00 39,266.00 6,510.00 35,036.00 160,020.00 188.00 200.00 21,670.00 16,687.80 17.52 17.52 1,725.72 Sub Total Conduit Clamps: ea 6,880.00 41.67 286,694.56 Sub Total Lighting Conduit: LS 1.00 922,909.56 922,909.56 m m m m 4,957.00 966.00 2,479.00 483.00 19.00 20.00 19.00 90.00 94,183.00 19,320.00 47,101.00 43,470.00 Sub Total Lighting Cable Tray: m 8,885.00 22.97 204,074.00 M 200.00 31.00 6,200.00 Sub Total Lighting Raceway: m 200.00 31.00 6,200.00 EA EA EA EA EA EA EA EA 1,735.00 412.00 158.00 2,479.00 483.00 1,735.00 412.00 158.00 68.00 71.00 73.00 6.70 6.70 17.00 17.00 17.00 117,980.00 29,252.00 11,534.00 16,609.30 3,236.10 29,495.00 7,004.00 2,686.00 Sub Total Cover Clamps: ea 7,572.00 28.76 217,796.40 Sub Total Lighting Cable Tray: LS 1.00 428,070.40 428,070.40 m 564.00 75.00 42,300.00 EA m3 SET SET SET SET SET SET 0.00 829.00 42.00 0.00 42.00 0.00 74.00 0.00 0.00 67.00 190.00 0.00 160.00 0.00 79.00 0.00 0.00 55,543.00 7,980.00 0.00 6,720.00 0.00 5,846.00 0.00 Conduit Clamps CONDUIT CLAMP UNISTRUT TYPE3/4" CONDUIT CLAMP UNISTRUT TYPE 1" CONDUIT CLAMP UNISTRUT TYPE 1-1/4" CONDUIT CLAMP UNISTRUT TYPE 1-1/2" CONDUIT CLAMPUNISTRUT TYPE3/4" CONDUIT CLAMPUNISTRUT TYPE1" CONDUIT CLAMPUNISTRUT TYPE1-1/4" CONDUIT CLAMPUNISTRUT TYPE1-1/2" CONDUIT CLAMP 3/4" CONDUIT CLAMP 1" CONDUIT CLAMP 1-1/4" CONDUIT CLAMP 1-1/2" Lighting Cable Tray Lighting Cable Tray PERFORATED CABLE TRAY50 X 50 PERFORATED CABLE TRAY100 X 50 PERFORATED CABLE TRAY50mm PERFORATED CABLE TRAY100mm Lighting Raceway RACE WAY100x50x2.6t Cover Clamps COVER CLAMP FOR PERFORATED CABLE TRAY50mm COVER CLAMP FOR PERFORATED CABLE TRAY100mm COVER CLAMP FOR PERFORATED CABLE TRAY150mm COVER CLAMP FOR PERFORATED CABLE TRAY50mm COVER CLAMP FOR PERFORATED CABLE TRAY100mm COVER CLAMP 50mm COVER CLAMP 100mm COVER CLAMP 150mm Lighting Support UNISTRUT CHANNELHOT DIP GALVANIZED STEEL 41 x 41 x 2.6t SUPPORT FOR JUNCTION BOX EXCAVATION & BACK FILL WORK SUPPORT FOR LIGHTING TRANSFORMER SUPPORT FOR LIGHTING TRANSFORMER SUPPORT FOR LIGHTING/RECEPTACLE PANEL SUPPORT FOR LIGHTING/RECEPTACLE PANEL SUPPORT FOR RECEPTACLE SUPPORT FOR RECEPTACLE Bill Of Quantities Process Plant Project Bill of Quantities Item 60750 60760 60770 60780 60790 60800 60810 60820 60830 60840 60850 60860 60870 Description Unit LIGHTING FIXTURE SUPPORT LIGHTING FIXTURE SUPPORT SUPPORT FOR JUNCTION BOX PERFORATED TRAY SUPPORT ANCHOR BOLT STAINLESS STEEL MISCELLANEOUS FOR LIGHTING SYSTEM SHANK BOLT AND NUT FOR PERFORATED CABLE TRAYSTAINLESS STEEL STAINLESS SHANK BOLT & NUT HANGER FITTING FOR RACE WAY110x85x2.6t THREAD STILL ROD FOR HANGER FITTING3/8" STRONG ANCHOR NON DRILLING, STAINLESS STEEL3/8" UNISTRUT CHANNEL FOR RACE WAY SUPPORT41 X 41 X 2.6t SHANK BOLT 60920 60930 60940 60950 60960 60970 60980 60990 61000 61010 61020 61030 Rate Amount SET SET EA SET EA LOT SET 570.00 0.00 633.00 2,962.00 240.00 1.00 13,777.00 110.00 0.00 87.00 230.00 37.00 122,210.00 17.00 62,700.00 0.00 55,071.00 681,260.00 8,880.00 122,210.00 234,209.00 EA M EA EA 17,769.00 40.00 200.00 200.00 1.52 33.00 38.00 59.00 27,008.88 1,320.00 7,600.00 11,800.00 EA 200.00 70.00 14,000.00 13,777.00 8.76 120,686.52 1.00 1,465,134.40 1,465,134.40 EA EA EA EA 62.00 20.00 34.00 40.00 57.00 55.00 31.00 31.00 3,534.00 1,100.00 1,054.00 1,240.00 Sub Total Lighting Receptacles: ea 156.00 44.41 6,928.00 EA EA EA EA 81.00 20.00 50.00 54.00 0.00 77.00 30.00 29.00 0.00 1,540.00 1,500.00 1,566.00 Sub Total Light Switches: ea 205.00 22.47 4,606.00 Sub Total Lighting Devices: LS 1.00 11,534.00 11,534.00 EA EA EA EA 37.00 1.00 222.00 153.00 6,180.00 5,950.00 2,240.00 1,790.00 228,660.00 5,950.00 497,280.00 273,870.00 Sub Total Light Poles: ea 413.00 2,435.25 1,005,760.00 Sub Total Lighting System: LS 1.00 7,757,177.30 7,757,177.30 EA EA EA EA 14.00 20.00 77.00 23.00 48.00 39.00 48.00 48.00 672.00 780.00 3,696.00 1,104.00 Sub Total Control Switches: ea 134.00 46.66 6,252.00 SET Sub Total Lighting Support: LS 60880 60890 60900 60910 Quantity Lighting Devices Lighting Receptacles CONVENIENCE RECEPTACLE CONVENIENCE RECEPTACLE CONVENIENCE RECEPTACLEOUTDOOR CONVENIENCE RECEPTACLEOUTDOOR Light Switches TUMBLER SWITCHGENERAL PURPOSE TUMBLER SWITCHGENERAL TUMBLER SWITCHINDUSTRIAL TUMBLER SWITCHOUTDOOR Light Poles LIGHTING POLE FOR STREET LIGHTING LIGHTING POLE FOR FLOOD LIGHTING LIGHTING POLE FOR STANCHION MTD FIXTURE LIGHTING POLE FOR STANCHION MTD FIXTURE Power Generation System Power Generatioin Equipment Switches Control Switches Control SwitchON - OFF W/SEL. SW Control SwitchON - OFF W/SEL. SW, AMMETER Control SwitchON - OFF W/SEL. SW CONTROL SWITCH STATION ON - OFF W/SEL. SW, AMMETER Bill Of Quantities Process Plant Project Bill of Quantities Item 61040 61050 61060 61070 61080 61090 61100 61110 61120 61130 61140 61150 Description Unit Safety Switches SAFETY SWITCH 3 PH, ( 480 )V, (60)HZ, SIZE : 16AF SAFETY SWITCH 3 PH, ( 480 )V, (60)HZ, SIZE : 32AF SAFETY SWITCH 3 PH, ( 480 )V, (60)HZ, SIZE : 100AF SAFETY SWITCH 3 PH, ( 480 )V, (60)HZ, SIZE : 500AF SAFETY SWITCH3 PH, ( 480 )V, (60)HZ, SIZE : 150AF 61220 61230 61240 61250 61270 61280 Amount 63.00 4.00 7.00 2.00 1.00 93.00 93.00 93.00 190.00 370.00 5,859.00 372.00 651.00 380.00 370.00 Sub Total Safety Switches: ea 77.00 99.12 7,632.00 Sub Total Switches: LS 1.00 13,884.00 13,884.00 EA 12.00 74.00 888.00 EA 5.00 180.00 900.00 Sub Total Welding Receptacle: ea 17.00 105.18 1,788.00 2.00 2.00 2.00 2.00 1.00 940.00 940.00 940.00 940.00 940.00 1,880.00 1,880.00 1,880.00 1,880.00 940.00 9.00 940.00 8,460.00 1.00 1.00 1.00 1.00 1.00 1.00 430.00 460.00 170.00 170.00 260.00 260.00 430.00 460.00 170.00 170.00 260.00 260.00 Sub Total Dry Type Transformer: Set 6.00 291.67 1,750.00 Sub Total Transformers: LS 1.00 10,210.00 10,210.00 2.00 2.00 2.00 1.00 680.00 590.00 590.00 1,270.00 1,360.00 1,180.00 1,180.00 1,270.00 7.00 712.86 4,990.00 PNL 18.00 1,370.00 24,660.00 PNL 18.00 1,370.00 24,660.00 PNL 11.00 1,480.00 16,280.00 Welding Receptacle WELDING RECEPTACLE3 PH, ( 480 )V, (60)HZ, 3P + 1E. WEATHER PROOF WELDING RECEPTACLE3 PH, ( 480 )V, (60)HZ, 3P + 1E. CLASS I,ZONE 2 IIC T4 Transformers Power Transformer Power Transformer 2000/2300kVA Power Transformer2000/2300kVA Power Transformer2000/2300kVA Power Transformer2000/2300kVA Power Transformer2000/2300kVA SET SET SET SET SET Dry Type Transformer Dry Type Transformer90KVA Dry Type Transformer100KVA Dry Type Transformer30KVA Dry Type Transformer: 30KVA Dry Type Transformer50KVA Dry Type Transformer50KVA SET SET SET SET SET SET Power Systems Power Capacitor Power Capacitor225 KVA Power Capacitor 180KVAR Power Capacitor300KVAR Power Capacitor( 600 )KVAR SET SET SET SET Sub Total Power Capacitor: Set 61260 Rate EA EA EA EA EA Sub Total Power Transformer: ea 61160 61170 61180 61190 61200 61210 Quantity Switchgear & MCC L.V. SwitchGear & MCC3 PH,( 0.48 )V,(60)HZ, ( 80 )kA/(1)SEC L.V. SwitchGear & MCC3 PH,( 0.48 )V,(60)HZ, ( 80 )kA/(1)SEC L.V. SwitchGear & MCC3 PH,( 0.48 )V,(60)HZ, ( 80 )kA/(1)SEC Bill Of Quantities Process Plant Project Bill of Quantities Item 61290 61300 Description Unit L.V. SwitchGear & MCC3 PH,( 0.48 )V,(60)HZ, ( 80 )kA/(1)SEC 61340 1,270.00 16,510.00 Sub Total Switchgear & MCC: PNL 60.00 1,368.50 82,110.00 SET 1.00 1,040.00 1,040.00 1.00 1,040.00 1,040.00 1.00 1.00 1.00 1,220.00 1,220.00 1,220.00 1,220.00 1,220.00 1,220.00 Sub Total UPS & Battery : Set 3.00 1,220.00 3,660.00 Sub Total Power Systems: LS 1.00 91,800.00 91,800.00 3.00 86.00 258.00 1.00 258.00 258.00 1.00 220.00 220.00 1.00 220.00 220.00 PNL 2.00 430.00 860.00 PNL 1.00 430.00 430.00 PNL 1.00 430.00 430.00 PNL 2.00 430.00 860.00 PNL 2.00 430.00 860.00 PNL 1.00 430.00 430.00 Sub Total L.V. Main Distribution Panel: PNL 9.00 430.00 3,870.00 1.00 1.00 1.00 10,230.00 2,870.00 3,750.00 10,230.00 2,870.00 3,750.00 3.00 5,616.67 16,850.00 1.00 300.00 300.00 1.00 300.00 300.00 Battery Charger & Battery Battery Charger & Battery UPS & Battery UPS & BATTERY( 1)PH, AC( 120)V, (60)HZ, (10)KVA UPS & BATTERY( 1)PH, AC( 120)V, (60)HZ, (80)KVA UPS & BATTERY( 1)PH, AC( 120)V, (60)HZ, (100)KVA Panels Interposing Relay Panel INTERPOSING RELAY AND MARSHALLING PANELSIZE : 800W X 800D X 2350H X 3PNLS SET SET SET SET Signal Concentrator Panel SIGNAL CONCENTRATOR PANELW1600 x D600 x H1800 x SET 1PNL Sub Total Signal Concentrator Panel: LS 61360 61370 61380 61390 61400 61410 61420 61430 61440 L.V. Main Distribution Panel L.V. Main Distribution Panel3 PH,( 4 )W, ( 208-120 )V,60HZ,( 20 )kA, ( 1)SEC L.V. Main Distribution Panel3 PH,( 4 )W, ( 480-277 )V,60HZ,( 80 )kA, ( 1)SEC L.V. Main Distribution Panel3 PH,( 3 )W, ( 480 )V,60HZ,( 80 )kA, ( 1)SEC L.V. Main Distribution Panel 3 PH,( 3 )W, ( 480 )V,60HZ,( 80 )kA, ( 1)SEC L.V. Main Distribution Panel3 PH,( 3 )W, ( 480 )V,60HZ,( 80 )kA, ( 1)SEC L.V. Main Distribution Panel3 PH,( 3 )W, ( 480 )V,60HZ,( 80 )kA, ( 1)SEC VSD Panel VSD Panel 3 PH, ( 0.48 )KV, 60HZ, VSD Panel 3 PH, ( 0.48 )KV, 60HZ, VSD Panel 3 PH, ( 0.48 )KV, 60HZ, SET SET SET Sub Total VSD Panel: Set 61450 Amount 13.00 Sub Total Interposing Relay Panel: LS 61350 Rate PNL Sub Total Battery Charger & Battery: LS 61310 61320 61330 Quantity Annunciator Panel ANNUNCIATOR PANEL BOARDSIZE : W800 x D800 x H2100 x 1PNL SET Sub Total Annunciator Panel: LS Bill Of Quantities Process Plant Project Bill of Quantities Item Description Unit Sub Total Panels: LS 61460 61470 61480 61490 61500 61510 61520 61530 61540 61550 61560 61570 61580 61590 61600 61610 61620 61630 61640 61650 61660 61670 61680 61690 61700 61710 61720 61730 61740 61750 61760 61770 61780 Rate Amount 1.00 21,498.00 21,498.00 11.00 5.00 1.00 1.00 3.00 4.00 69.00 69.00 69.00 69.00 69.00 69.00 759.00 345.00 69.00 69.00 207.00 276.00 Sub Total Power Junction Box: Set 25.00 69.00 1,725.00 Sub Total Power Generatioin Equipment: LS 1.00 140,905.00 140,905.00 EA EA EA EA EA EA EA EA 2.00 31.00 56.00 79.00 102.00 17.00 17.00 81.00 8.45 8.45 8.45 8.45 8.45 8.45 8.45 8.45 16.90 261.95 473.20 667.55 861.90 143.65 143.65 684.45 Sub Total Multi Cable Transit: ea 385.00 8.45 3,253.25 366.00 42.00 74.00 106.00 72.00 36.00 36.00 92.00 70.00 26.00 30.00 90.00 10.00 80.00 10.00 12.00 10.00 326.00 50.00 310.00 310.00 310.00 310.00 500.00 500.00 2,600.00 2,600.00 2,560.00 2,560.00 2,560.00 2,560.00 390.00 390.00 390.00 2,620.00 3,290.00 7.86 19.00 113,460.00 13,020.00 22,940.00 32,860.00 36,000.00 18,000.00 93,600.00 239,200.00 179,200.00 66,560.00 76,800.00 230,400.00 3,900.00 31,200.00 3,900.00 31,440.00 32,900.00 2,562.36 950.00 1,538.00 799.02 1,228,892.36 140.00 116.00 64.00 28.00 10.00 26.00 7.78 8.69 9.38 7.59 91.00 7.59 1,089.20 1,008.04 600.32 212.52 910.00 197.34 Power Junction Box POWER JUNCTION BOX610W X 610H X 203D POWER JUNCTION BOX 610W X 610H X 203D POWER JUNCTION BOX610W X 610H X 203D POWER JUNCTION BOX 610W X 610H X 203D POWER JUNCTION BOX 610W X 610H X 203D POWER JUNCTION BOX 610W X 610H X 203D Power Generation Cabling Multi Cable Transit MULTI CABLE TRANSIT RM 90 MULTI CABLE TRANSIT RM 60 MULTI CABLE TRANSIT RM 40 MULTI CABLE TRANSIT RM 30 MULTI CABLE TRANSIT RM 20 MULTI CABLE TRANSIT ROX SF SINGLE FRAME SF-6x1 MULTI CABLE TRANSIT ROX WEDGE 120 mm MULTI CABLE TRANSIT LV Power Termination Point POWER TERMINATION POINT LV POWER TERMINATION POINT 3/C 4mm2 LV POWER TERMINATION POINT 3/C 6mm2 LV POWER TERMINATION POINT 3/C 10mm2 LV POWER TERMINATION POINT 3/C 16mm2 LV POWER TERMINATION POINT 3/C 25mm2 LV POWER TERMINATION POINT 3/C 35mm2 LV POWER TERMINATION POINT 3/C 50mm2 LV POWER TERMINATION POINT 3/C 70mm2 LV POWER TERMINATION POINT 3/C 95mm2 LV POWER TERMINATION POINT 3/C 120mm2 LV POWER TERMINATION POINT 3/C 150mm2 LV POWER TERMINATION POINT 3/C 185mm2 LV POWER TERMINATION POINT 4/C 6mm2 LV POWER TERMINATION POINT 4/C 10mm2 LV POWER TERMINATION POINT 4/C 16mm2 LV POWER TERMINATION POINT 4/C 50+25mm2 LV POWER TERMINATION POINT 4/C 150+70mm2 LV POWER TERMINATION POINT 12/C 2.5mm2 LV POWER TERMINATION POINT 19/C 2.5mm2 SET SET SET SET SET SET SET SET SET SET SET SET SET SET SET SET SET SET SET SET SET SET SET SET SET Sub Total POWER TERMINATION POINT: Set 61790 61800 61810 61820 61830 61840 Quantity CONTROL TERMINATION POINT LV CONTROL TERMINATION POINT 3/C 2.5mm2 LV CONTROL TERMINATION POINT 5/C 2.5mm2 LV CONTROL TERMINATION POINT 7/C 2.5mm2 LV CONTROL TERMINATION POINT 2P 0.75mm2 LV CONTROL TERMINATION POINT 24/P 1.00mm2 LV CONTROL TERMINATION POINT 2T 1.0mm2 SET SET SET SET SET SET Bill Of Quantities Process Plant Project Bill of Quantities Item 61850 61860 61870 61880 61890 61900 61910 61920 61930 61940 61950 61960 61970 61980 61990 62000 62010 62020 62030 62040 62050 62060 62070 62080 62090 62100 62110 62120 62130 62140 62150 62160 62170 62180 62190 62200 62210 62220 62230 62240 62250 62260 62270 62280 62290 Description LV CONTROL TERMINATION POINT 1/C 35mm2 LV CONTROL TERMINATION POINT 1/C 70mm2 LV CONTROL TERMINATION POINT 1/C 95mm2 LV CONTROL TERMINATION POINT 1/C 120mm2 LV CONTROL TERMINATION POINT 2/C 4mm2 LV CONTROL TERMINATION POINT 2/C 6mm2 LV CONTROL TERMINATION POINT 2/C 10mm2 LV CONTROL TERMINATION POINT 2/C 16mm2 LV CONTROL TERMINATION POINT 2/C 25mm2 LV CONTROL TERMINATION POINT 8P 1.0mm2 LV CONTROL TERMINATION POINT 9/C 2.5mm2 LV CONTROL TERMINATION POINT 4/C 4mm2 Unit Rate Amount 4.00 16.00 4.00 18.00 138.00 40.00 42.00 20.00 8.00 28.00 6.00 4.00 21.00 27.00 35.00 61.00 4.02 5.71 7.52 11.00 190.00 30.00 11.00 8.29 84.00 432.00 140.00 1,098.00 554.76 228.40 315.84 220.00 1,520.00 840.00 66.00 33.16 Sub Total CONTROL TERMINATION POINT: Set 712.00 13.41 9,549.58 Sub Total LV Power Termination Point: Set 2,250.00 550.42 1,238,441.94 EA EA EA EA 25.00 91.00 36.00 5.00 310.00 370.00 2,560.00 4,270.00 7,750.00 33,670.00 92,160.00 21,350.00 Sub Total Motor Connections kit: ea 157.00 986.82 154,930.00 EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA 118.00 1,139.00 5,759.00 1,460.00 259.00 658.00 435.00 261.00 129.00 143.00 322.00 234.00 118.00 110.00 271.00 1.71 1.71 1.71 2.21 3.23 5.68 7.80 7.80 16.00 18.00 21.00 26.00 32.00 37.00 46.00 201.78 1,947.69 9,847.89 3,226.60 836.57 3,737.44 3,393.00 2,035.80 2,064.00 2,574.00 6,762.00 6,084.00 3,776.00 4,070.00 12,466.00 Sub Total Pressure Terminal: ea 11,416.00 5.52 63,022.77 750.00 1,884.00 408.00 46.00 292.00 2,698.00 5,255.00 559.00 849.00 2,932.00 7,746.00 11,494.00 9,464.00 2,776.00 2.87 4.53 3.35 1.47 1.28 0.77 0.86 0.92 1.03 0.86 0.86 0.86 1.03 1.21 2,152.50 8,534.52 1,366.80 67.62 373.76 2,077.46 4,519.30 514.28 874.47 2,521.52 6,661.56 9,884.84 9,747.92 3,358.96 Motor Connections kit MOTOR CONNECTION KITS 2.5 ~ 6mm² MOTOR CONNECTION KITS 4 ~ 25mm² MOTOR CONNECTION KITS 35 ~ 120mm² MOTOR CONNECTION KITS 150 ~ 300mm² Pressure Terminal PRESSURE TERMINAL PRESSURE TERMINAL PRESSURE TERMINAL PRESSURE TERMINAL PRESSURE TERMINAL PRESSURE TERMINAL PRESSURE TERMINAL PRESSURE TERMINAL PRESSURE TERMINAL PRESSURE TERMINAL PRESSURE TERMINAL PRESSURE TERMINAL PRESSURE TERMINAL PRESSURE TERMINAL PRESSURE TERMINAL 0.75mm² 1mm² 2.5mm² 4mm² 6mm² 10mm² 16mm² 25mm² 35mm² 50mm² 70mm² 95mm² 120mm² 150mm² 185mm² Cable Power Cable POWER CABLE, ELECTRIC (MV).1/C * 240mm2 POWER CABLE, ELECTRIC (MV).1/C * 630mm2 POWER CABLE, ELECTRIC (MV).3/C * 240mm2 POWER CABLE, ELECTRIC (LV).1/C * 95mm2 POWER CABLE, ELECTRIC (LV).1/C * 120mm2 POWER CABLE, ELECTRIC (LV).2/C * 4mm2 POWER CABLE, ELECTRIC (LV).2/C * 10mm2 POWER CABLE, ELECTRIC (LV).2/C * 16mm2 POWER CABLE, ELECTRIC (LV).2/C * 25mm2 POWER CABLE, ELECTRIC (LV).2/C * 6mm2 POWER CABLE, ELECTRIC (LV).3/C * 10mm2 POWER CABLE, ELECTRIC (LV).3/C * 16mm2 POWER CABLE, ELECTRIC (LV).3/C * 25mm2 POWER CABLE, ELECTRIC (LV).3/C * 50mm2 SET SET SET SET SET SET SET SET SET SET SET SET Quantity m m m m m m m m m m m m m m Bill Of Quantities Process Plant Project Bill of Quantities Item 62300 62310 62320 62330 62340 62350 62360 62370 62380 62390 62400 62410 62420 62430 62440 62450 62460 62470 62480 62490 62500 62510 62520 62530 62540 62550 62560 62570 62580 62590 62600 62610 62620 62630 62640 62650 62660 62670 62680 62690 62700 62710 62720 62730 62740 62750 62760 Description Unit POWER CABLE, ELECTRIC (LV).3/C * 70mm2 POWER CABLE, ELECTRIC (LV).3/C * 95mm2 POWER CABLE, ELECTRIC (LV).3/C * 120mm2 POWER CABLE, ELECTRIC (LV).3/C * 150mm2 POWER CABLE, ELECTRIC (LV).3/C * 185mm2 POWER CABLE, ELECTRIC (LV).1/C * 35mm2 POWER CABLE, ELECTRIC (LV).1/C * 70mm2 POWER CABLE, ELECTRIC (LV).3/C * 6mm2 POWER CABLE, ELECTRIC (LV).3/C * 35mm2 POWER CABLE, ELECTRIC (LV).4/C * 4mm2 POWER CABLE, ELECTRIC (LV).3.5/C * 150mm2 POWER CABLE, ELECTRIC (LV).4/C * 16mm2 POWER CABLE, ELECTRIC (LV).4/C * 6mm2 POWER CABLE, ELECTRIC (LV).4/C * 10mm2 POWER CABLE, ELECTRIC (LV).3.5/C * 50mm2 POWER CABLE, ELECTRIC (LV).3/C * 4mm2 POWER CABLE, ELECTRIC (LV).4/C * 10mm2 Quantity Rate Amount m m m m m m m m m m m m m m m m m 4,692.00 5,534.00 413.00 1,129.00 4,662.00 40.00 332.00 1,941.00 4,387.00 278.00 114.00 582.00 1,089.00 1,016.00 258.00 9,368.00 464.00 1.30 1.47 1.60 1.79 1.94 0.77 0.86 0.77 1.03 0.77 1.82 0.86 0.86 0.86 1.21 0.77 0.86 6,099.60 8,134.98 660.80 2,020.91 9,044.28 30.80 285.52 1,494.57 4,518.61 214.06 207.48 500.52 936.54 873.76 312.18 7,213.36 399.04 Sub Total Power Cable: m 83,452.00 1.15 95,602.52 m m m m m m m m m m m m 1,457.00 5,857.00 2,255.00 1,444.00 36,593.00 464.00 3,780.00 1,533.00 816.00 400.00 840.00 376.00 1.82 0.64 0.72 0.79 0.04 1.08 1.08 0.64 0.79 1.08 1.89 1.89 2,651.74 3,748.48 1,623.60 1,140.76 1,463.72 501.12 4,082.40 981.12 644.64 432.00 1,587.60 710.64 Sub Total Control Cable: m 55,815.00 0.35 19,567.82 EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA 35.00 124.00 144.00 21.00 26.00 16.00 5.00 1,061.00 436.00 148.00 62.00 116.00 131.00 26.00 5.00 2.54 2.54 2.54 2.54 3.42 3.42 2.54 2.54 2.54 2.54 2.54 3.42 3.42 3.80 3.80 88.90 314.96 365.76 53.34 88.92 54.72 12.70 2,694.94 1,107.44 375.92 157.48 396.72 448.02 98.80 19.00 Sub Total Cable Glands: ea 2,356.00 2.66 6,277.62 12.00 4.00 2.00 61.00 81.00 99.00 732.00 324.00 198.00 18.00 69.67 1,254.00 Control Cable CONTROL CABLE 2.5mm2 CONTROL CABLE 3/C * 2.5mm2 CONTROL CABLE 5/C * 2.5mm2 CONTROL CABLE 7/C * 2.5mm2 CONTROL CABLE 12/C * 2.5mm2 CONTROL CABLE 12/C * 2.5mm2 CONTROL CABLE 2P CONTROL CABLE 2T 1.00MM2 CONTROL CABLE 8P/1.00MM2 CONTROL CABLE 24P/1.00MM2 CONTROL CABLE, ELECTRIC 7/C * 2.5mm2 CONTROL CABLE, ELECTRIC 19/C * 2.5mm2 Cable Glands CABLE GLAND 1-1/2" (42mm) CABLE GLAND 3/4" (22mm) CABLE GLAND 1" (28mm) CABLE GLAND 1-1/4" (36mm) CABLE GLAND 2" (54mm) CABLE GLAND 2-1/2" (70mm) CABLE GLAND 1/2" CABLE GLAND 3/4" CABLE GLAND 1" CABLE GLAND 1-1/4" CABLE GLAND 1-1/2" CABLE GLAND 2" CABLE GLAND 2-1/2" CABLE GLAND 3" CABLE GLAND 4" Cable Termination Kits CABLE TERMINATION KIT.1/C * 240mm2 CABLE TERMINATION KIT.1/C * 630mm2 CABLE TERMINATION KIT.3/C * 240mm2 SET SET SET Sub Total Cable Termination Kits: Set Bill Of Quantities Process Plant Project Bill of Quantities Item 62770 62780 62790 62800 62810 62820 62830 62840 62850 62860 62870 62880 62890 62900 62910 62920 62930 62940 62950 62960 62970 62980 62990 Description Unit Variable Speed Drive Cable VARIABLE SPEED DRIVE CABLE3/C * 150mm2 VARIABLE SPEED DRIVE CABLE3/C * 185mm2 VARIABLE SPEED DRIVE CABLE3/C * 4mm2 VARIABLE SPEED DRIVE CABLE3/C * 10mm2 VARIABLE SPEED DRIVE CABLE3/C * 95mm2 VARIABLE SPEED DRIVE CABLE3/C * 70mm2 Quantity Rate Amount m m m m m m 20.00 1,244.00 2,081.00 525.00 666.00 722.00 1.78 1.99 0.77 0.77 1.47 1.30 35.60 2,475.56 1,602.37 404.25 979.02 938.60 Sub Total Variable Speed Drive Cable: m 5,258.00 1.22 6,435.40 Sub Total Cable: LS 1.00 129,137.36 129,137.36 Sub Total Power Generation Cabling: LS 1.00 1,588,785.32 1,588,785.32 m m m m m m m m m M M M m M M 1,015.00 231.00 126.00 552.00 95.00 81.00 2,420.00 32.00 89.00 4,826.00 5,127.00 1,192.00 214.00 228.00 21.00 4.22 7.95 10.00 16.00 21.00 3.66 7.82 30.00 55.00 55.00 17.00 17.00 35.00 17.00 17.00 4,283.30 1,836.45 1,260.00 8,832.00 1,995.00 296.46 18,924.40 960.00 4,895.00 265,430.00 87,159.00 20,264.00 7,490.00 3,876.00 357.00 Sub Total PVC Conduit: m 16,249.00 26.33 427,858.61 EA 1,394.00 31.00 43,214.00 EA 68.00 36.00 2,448.00 Sub Total PVC Plugs: ea 1,462.00 31.23 45,662.00 Sub Total PVC Conduit: LS 1.00 473,520.61 473,520.61 427.00 1,432.00 92.00 120.00 39,284.00 171,840.00 Power Generation Conduit PVC Conduit PVC Conduit HI PVC CONDUIT 1" (28mm) HI PVC CONDUIT 1-1/2" (42mm) HI PVC CONDUIT 2" (54mm) HI PVC CONDUIT 2-1/2" (70mm) HI PVC CONDUIT 3" (82mm) HI PVC CONDUIT 3/4" (22mm) HI PVC CONDUIT 1-1/4" (36mm) HI PVC CONDUIT 3-1/2" HI PVC CONDUIT 6" (150MM) PVC CONDUIT 6" PVC CONDUIT 6" PVC CONDUIT 6" PVC CONDUIT 200mm PVC CONDUIT 200mm PVC CONDUIT 200mm PVC Plugs PVC CONDUIT PLUG SIZE : 6" PVC CONDUIT PLUG SIZE : 8" Rigid Steel Conduit Rigid Steel Conduit Straight SPECIFICATION : RIGID STEEL CONDUIT HOT DIP GALVANIZED, METRIC THREADED BOTH ENDS WITH 1-COUPLING, SIZE: 3600mmL X 1" NPT SUPPLIED By Sub-Con. 63000 63010 RIGID STEEL CONDUIT3/4" (22mm) RIGID STEEL CONDUIT1" (28mm) m m Bill Of Quantities Process Plant Project Bill of Quantities Item 63020 63030 63040 63050 63060 63070 63080 Description RIGID STEEL CONDUIT1-1/4" (36mm) RIGID STEEL CONDUIT1-1/2" (42mm) RIGID STEEL CONDUIT2-1/2" (70mm) RIGID STEEL CONDUIT3" (82mm) RIGID STEEL CONDUIT3-1/2" (92mm) RIGID STEEL CONDUIT 2" RIGID STEEL CONDUIT 6" Unit Quantity Rate Amount m m m m m m m 1,223.00 95.00 570.00 86.00 5.00 13.00 21.00 190.00 200.00 370.00 510.00 630.00 260.00 1,000.00 232,370.00 19,000.00 210,900.00 43,860.00 3,150.00 3,380.00 21,000.00 Sub Total Rigid Steel Conduit Straight: m 3,872.00 192.35 744,784.00 EA EA EA EA EA EA EA EA EA 116.00 73.00 9.00 55.00 426.00 394.00 45.00 30.00 13.00 110.00 140.00 200.00 14.00 20.00 38.00 43.00 59.00 990.00 12,760.00 10,220.00 1,800.00 770.00 8,520.00 14,972.00 1,935.00 1,770.00 12,870.00 Sub Total Rigid Steel Elbow: ea 1,161.00 56.52 65,617.00 EA EA EA EA EA EA EA EA EA EA 186.00 623.00 532.00 41.00 6.00 248.00 37.00 2.00 9.00 18.00 14.00 21.00 35.00 47.00 34.00 34.00 34.00 34.00 34.00 34.00 2,604.00 13,083.00 18,620.00 1,927.00 204.00 8,432.00 1,258.00 68.00 306.00 612.00 Sub Total Rigid Steel Conduit Clamps: ea 1,702.00 27.68 47,114.00 Sub Total Rigid Steel Conduit: m 3,872.00 221.47 857,515.00 Sub Total Power Generation Conduit: LS 1.00 1,331,035.61 1,331,035.61 63280 63290 Power Generation Cable Tray Cable Tray Elbow CABLE TRAY VERT. ELBOW(90 DEGREE-IN) * 600mmW EA CABLE TRAY VERT. ELBOW(90 DEGREE-OUT) * 600mmW EA 2.00 2.00 33.00 33.00 66.00 66.00 63300 63310 63320 63330 CABLE TRAY TEE * 900mmW CABLE TRAY HORIZ. ELBOW(90 DEGREE) * 900mmW CABLE TRAY VERT. ELBOW(90 DEGREE-IN) * 450mmW CABLE TRAYVERT. ELBOW(90 DEGREE-OUT) * 300mmW EA EA EA EA 5.00 4.00 2.00 3.00 38.00 38.00 33.00 32.00 190.00 152.00 66.00 96.00 63340 CABLE TRAYVERT. ELBOW(90 DEGREE-OUT) * 450mmW EA 2.00 33.00 66.00 63350 63360 CABLE TRAYVERT. ELBOW(90 DEGREE-IN) * 300mmW EA COVER FOR CABLE TRAYVERT. ELBOW(90 DEGREE-IN) * ea 300mmW 2.00 2.00 32.00 32.00 64.00 64.00 63090 63100 63110 63120 63130 63140 63150 63160 63170 Rigid Steel Elbow RIGID STEEL ELBOW2-1/2" (70mm) RIGID STEEL ELBOW3" (82mm) RIGID STEEL ELBOW3-1/2" (92mm) RIGID STEEL ELBOW3/4" (22mm) RIGID STEEL ELBOW1" (28mm) RIGID STEEL ELBOW1-1/4" (36mm) RIGID STEEL ELBOW 1-1/2" (42mm) RIGID STEEL ELBOW 2" RIGID STEEL ELBOW 6" Rigid Steel Conduit Clamps I STOP HERE, TO BE CONTINUED ON SATURDAY.................. 63180 63190 63200 63210 63220 63230 63240 63250 63260 63270 CONDUIT CLAMP 3/4" CONDUIT CLAMP 1" CONDUIT CLAMP 1-1/4" CONDUIT CLAMP 1-1/2" CONDUIT CLAMP 2" CONDUIT CLAMP 2-1/2" CONDUIT CLAMP 3" CONDUIT CLAMP 3-1/2" CONDUIT CLAMP 4" CONDUIT CLAMP 1-1/4" Bill Of Quantities Process Plant Project Bill of Quantities Item 63370 63380 63390 63400 63410 63420 63430 63440 63450 63460 63470 63480 63490 63500 63510 63520 63530 63540 63550 63560 63570 63580 63590 63600 63610 63620 63630 63640 63650 Description COVER FOR CABLE TRAYHORIZ. ELBOW(90 DEGREE) * 300mmW COVER FOR CABLE TRAYVERT. ELBOW(90 DEGREE-IN) * 450mmW COVER FOR CABLE TRAYVERT. ELBOW(90 DEGREEOUT) * 300mmW COVER FOR CABLE TRAYVERT. ELBOW(90 DEGREEOUT) * 450mmW CABLE TRAY TEE * 600mmW CABLE TRAY HORIZ. ELBOW(90 DEGREE) * 300mmW CABLE TRAY HORIZ. ELBOW(90 DEGREE) * 450mmW CABLE TRAY HORIZ. ELBOW(90 DEGREE) * 600mmW COVER FOR CABLE TRAY HORIZ. ELBOW(90 DEGREE) * 450mmW Unit Rate Amount ea 6.00 32.00 192.00 ea 2.00 33.00 66.00 ea 3.00 32.00 96.00 ea 2.00 33.00 66.00 EA EA EA EA m 1.00 6.00 2.00 2.00 2.00 33.00 32.00 33.00 33.00 33.00 33.00 192.00 66.00 66.00 66.00 Sub Total Cable Tray Elbow: ea 50.00 33.46 1,673.00 EA EA EA EA EA 2.00 5.00 1.00 24.00 69.00 2.54 1.78 1.78 3.17 1.27 5.08 8.90 1.78 76.08 87.63 EA 10.00 1.27 12.70 EA EA EA EA EA EA EA 1,078.00 104.00 132.00 14.00 40.00 40.00 304.00 0.25 0.25 0.25 0.25 0.38 0.38 0.38 269.50 26.00 33.00 3.50 15.20 15.20 115.52 Sub Total Cable Tray Fittings: ea 1,823.00 0.37 670.09 m m m m m m m 96.00 240.00 72.00 108.00 12.00 72.00 108.00 33.00 38.00 41.00 33.00 33.00 33.00 33.00 3,168.00 9,120.00 2,952.00 3,564.00 396.00 2,376.00 3,564.00 Sub Total Cable Tray Straight: m 708.00 35.51 25,140.00 1.00 27,483.09 27,483.09 m3 m3 m3 m3 EA 20,273.00 12,159.00 7,652.26 930.00 52,912.00 1.90 69.00 44.00 1.90 3.16 38,518.70 838,971.00 336,699.40 1,767.00 167,201.92 Sub Total Power Generation Civil Works: LS 1.00 1,383,158.02 1,383,158.02 Cable Tray Fittings BLIND END PLATEEND BLIND PLATE * 600mmW BLIND END PLATEEND BLIND PLATE * 300mmW BLIND END PLATEEND BLIND PLATE * 450mmW BLIND END PLATEEND BLIND PLATE * 900mmW SEPERATOR FOR CABLE TRAY150 mmH * STRAIGHT(3000MML) SEPERATOR FOR CABLE TRAY150 mmH * VERT. ELBOW(600) CABLE TRAY HOLE DOWN CLAMPS CABLE TRAY COVER CLAMPS W: 300mm CABLE TRAY COVER CLAMPS W: 450mm CABLE TRAY COVER CLAMPS W: 600mm ADJUSTABLE RISER CONNECTOR VERTICAL TYPE ADJUSTABLE RISER CONNECTOR HORIZONTAL TYPE JOINT CONNECTOR THICKNESS : 2.6t(8 HOLES) Cable Tray Straight CABLE TRAY STRAIGHT * 600mmW CABLE TRAY STRAIGHT * 900mmW CABLE TRAYSTRAIGHT * 300mmW CABLE TRAYSTRAIGHT * 450mmW COVER FOR CABLE TRAYSTRAIGHT * 600mmW COVER FOR CABLE TRAYSTRAIGHT * 300mmW COVER FOR CABLE TRAYSTRAIGHT * 450mmW Sub Total Power Generation Cable Tray: LS 63660 63670 63680 63690 63700 Quantity Power Generation Civil Works EXCAVATION WORK BACK FILLING AND COMPACTION SAND FILLING AND COMPACTION EXCAVATION & BACK FILL WORK RED CONCRETE Power Generation Bus Bus Duct Bill Of Quantities Process Plant Project Bill of Quantities Item 63710 63720 63730 63740 63750 63760 63770 63780 63790 Description Unit BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA SET SET SET SET SET SET SET SET SET 63810 63820 63830 63840 63850 63860 63870 63880 63890 63900 63910 63920 63930 780.00 780.00 780.00 780.00 500.00 780.00 720.00 500.00 780.00 9.00 711.11 6,400.00 1,200.00 1.88 2,256.00 Sub Total Modular Bus: LS 1.00 2,256.00 2,256.00 Sub Total Power Generation Bus: LS 1.00 8,656.00 8,656.00 m m m m m 869.00 86.00 86.00 86.00 86.00 65.00 150.00 160.00 180.00 190.00 56,485.00 12,900.00 13,760.00 15,480.00 16,340.00 Sub Total Steel Angle: m 1,213.00 94.78 114,965.00 m SET EA 333.00 53.00 212.00 73.00 96.00 55.00 24,309.00 5,088.00 11,660.00 SET SET SET SET SET 211.00 25.00 17.00 30.00 9.00 520.00 520.00 97.00 1,100.00 1,100.00 109,720.00 13,000.00 1,649.00 33,000.00 9,900.00 1.00 208,326.00 208,326.00 2,176.00 6,488.00 30.00 55.00 143.00 40.00 1,166.00 949.00 111.00 474.00 157.00 3.00 91.00 58.00 24.00 17.00 69.00 71.00 75.00 73.00 24.00 26.00 29.00 36.00 44.00 50.00 16.00 91.00 52,224.00 110,296.00 2,070.00 3,905.00 10,725.00 2,920.00 27,984.00 24,674.00 3,219.00 17,064.00 6,908.00 150.00 1,456.00 5,278.00 Modular Bus RSS485(MODBUS)SHIELDED TWIST PAIR CABLE Power Generation Support Steel Angle STEEL ANGLE 50 x 50 x 6t STEEL ANGLE 200 x 2.6t STEEL ANGLE 300 x 2.6t STEEL ANGLE 500 x 2.6t STEEL ANGLE 800 x 2.6t Support CABLE TRAY SUPPORT 100 * 50 * 5T CABLE TRAY SUPPORT STEEL(0.75M/SET) BASE STEEL PLATE FOR CABLE TRAY SUPPORT 260 x 160 x 12t CONTROL STATION SUPPORT POWER JUNCTION BOX SUPPORT WELDING RECEPTACLE SUPPORT SUPPORT FOR BUS DUCT SUPPORT FOR BUS DUCT Clamps HOLD DOWN CLAMP SHANK BOLT AND NUT COVER CLAMPBAND TYPE COVER CLAMPBAND TYPE COVER CLAMPBAND TYPE COVER CLAMPBAND TYPE UNISTRUT CLAMP1" (28mm) UNISTRUT CLAMP1-1/4" (36mm) UNISTRUT CLAMP1-1/2" (42mm) UNISTRUT CLAMP2-1/2" (70mm) UNISTRUT CLAMP3" (82mm) UNISTRUT CLAMP3-1/2" (92mm) UNISTRUT CLAMP3/4" (22mm) CONDUIT CLAMP FOR OUTSIDE RAIL TRAY 1" (28mm) Amount 780.00 780.00 780.00 780.00 500.00 780.00 720.00 500.00 780.00 M Sub Total Support: LS 63940 63950 63960 63970 63980 63990 64000 64010 64020 64030 64040 64050 64060 64070 Rate 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Sub Total Bus Duct: Set 63800 Quantity EA SET EA EA EA EA EA EA EA EA EA EA EA EA Bill Of Quantities Process Plant Project Bill of Quantities Item Description Unit Quantity Rate Amount 64080 CONDUIT CLAMP FOR OUTSIDE RAIL TRAY EA 213.00 100.00 21,300.00 64090 1-1/4" (36mm) CONDUIT CLAMP FOR OUTSIDE RAIL TRAY EA 5.00 170.00 850.00 64100 2-1/2" (70mm) CONDUIT CLAMP FOR OUTSIDE RAIL TRAY EA 24.00 180.00 4,320.00 64110 3" (82mm) CONDUIT CLAMP FOR OUTSIDE RAIL TRAY EA 6.00 82.00 492.00 Sub Total Clamps: LS 1.00 295,835.00 295,835.00 EA EA EA 508.00 55.00 44.00 110.00 140.00 95.00 55,880.00 7,700.00 4,180.00 EA 44.00 120.00 5,280.00 Sub Total Connectors: ea 651.00 112.20 73,040.00 2,358.00 28.00 66,024.00 3/4" (22mm) 64120 64130 64140 64150 Connectors JOINT CONNECTOR150mmH EXPANSION CONNECTOR ADJUSTABLE CONNECTOR 150mmH * HORIZONTAL TYPE ADJUSTABLE CONNECTOR 150mmH * VERTICAL TYPE 64160 Other EXPANSION ANCHOR FOR TRAY SUPPORT STAINLESS STEEL (4EA /SET) EA 64170 WARNING TAPE 3" wide x 305m length x 2.5mm th'k Roll 483.00 430.00 207,690.00 64180 64190 CABLE ROUTE MARKER GROUNDING BONDING JUMPER WITH TERMINAL LUG35mm2 UNISTRUT CHANNELSTRAIGHT(3000mmL) MISCELLANEOUS FOR POWER SYSTEM STRONG ANCHOR BOLT M12xL75 NUT M12xL50 ANCHOR BOL M20xL500 WARNING SIGN SCREWS BOLT 1/4" CABLE ROUTE MARKER EXPANSION ANCHOR 1/2"- 30 SHANK BOLT STEEL 8 mm DIA /19mmL EXPANSION CONNECTOR THICKNESS : 2.6t(8 HOLES) EA EA 239.00 192.00 270.00 0.46 64,530.00 88.32 EA LOT EA 57.00 1.00 188.00 180.00 551,850.00 4.14 10,260.00 551,850.00 778.32 EA EA EA EA EA EA EA 52.00 11.00 6,880.00 1,659.00 938.00 3,883.00 33.00 4.99 9.22 2.66 250.00 220.00 5.24 85.00 259.48 101.42 18,300.80 414,750.00 206,360.00 20,346.92 2,805.00 Sub Total Other: LS 1.00 1,564,144.26 1,564,144.26 Sub Total Power Generation Support: LS 1.00 2,256,310.26 2,256,310.26 M/D M/D 540.00 270.00 160.00 190.00 86,400.00 51,300.00 Sub Total Power Generation Commissioning: M/D 810.00 170.00 137,700.00 1.00 6,874,033.30 6,874,033.30 64200 64210 64220 64230 64240 64250 64260 64270 64280 64290 64300 64310 Power Generation Commissioning Commissioning & Start-up Assist (LABOR) Commissioning & Start-up Assist (TECHNICIANS) Sub Total Power Generation System: LS Cathodic Protection System Cathodic Protection Anodes Bill Of Quantities Process Plant Project Bill of Quantities Item 64320 64330 64340 64350 64360 64370 64380 64390 64400 64410 64420 64430 64440 64450 64460 64470 64480 64490 64500 64510 64520 64530 64540 64550 64560 64570 Description Standard Anode IMPRESSED CURRENT ANODE MMO(MIXED METAL OXIDE) SACRIFICIAL ANODE TEMPORARY CATHODIC PROTECTION SACRIFICIAL ANODE TEMPORARY CATHODIC PROTECTION Unit Quantity Rate Amount EA 116.00 43,860.00 5,087,760.00 EA 116.00 4,690.00 544,040.00 EA 44.00 47,770.00 2,101,880.00 Sub Total Standard Anode: ea 276.00 28,020.58 7,733,680.00 M M 1,200.00 1,200.00 13.00 96.00 15,600.00 115,200.00 Sub Total Ribbon Anode: m 2,400.00 54.50 130,800.00 EA 104.00 4,350.00 452,400.00 Sub Total Reference Electrodes: LS 1.00 452,400.00 452,400.00 EA 10.00 200.00 2,000.00 EA 10.00 120.00 1,200.00 Sub Total Anode Power Feed Connectors: ea 20.00 160.00 3,200.00 Sub Total Cathodic Protection Anodes: ea 1.00 8,320,080.00 8,320,080.00 EA EA 518.00 518.00 25.00 430.00 12,950.00 222,740.00 Sub Total Cathodic Protection CADWelding: ea 1,036.00 227.50 235,690.00 M M 700.00 700.00 36.00 250.00 25,200.00 175,000.00 Sub Total Cathodic Protection Conductor Bar: m 1,400.00 143.00 200,200.00 M M M M M M M M M M M M M M 800.00 1,600.00 1,550.00 375.00 400.00 4,500.00 375.00 800.00 1,600.00 1,550.00 375.00 400.00 4,500.00 375.00 48.00 250.00 250.00 59.00 81.00 81.00 58.00 17.00 42.00 42.00 72.00 100.00 51.00 72.00 38,400.00 400,000.00 387,500.00 22,125.00 32,400.00 364,500.00 21,750.00 13,600.00 67,200.00 65,100.00 27,000.00 40,000.00 229,500.00 27,000.00 Sub Total Cathodic Protection Cabling: m 19,200.00 90.42 1,736,075.00 Ribbon Anode MMO RIBBON ANODE 6.4MM X 0.64T MMO RIBBON ANODE 6.4MM X 0.64T Reference Electrodes REFERFNCE ELECTRODE PERMANENT TYPE Anode Power Feed Connectors ANODE POWER FEEDER CONNECTOR 3MM Ti ROD X 25M/ROLL ANODE POWER FEEDER CONNECTOR 3MM Ti ROD X 25M/ROLL Cathodic Protection CADWelding CAD WELD WIRE TO STEEL SURFACE TYPE CAD WELD Cathodic Protection Conductor Bar CONDUCTOR BAR, 12.7MM X 0.89T CONDUCTOR BAR, 12.7MM X 0.89T Cathodic Protection Cabling TEST LEAD CABLE HMWPE CABLE 1C 10MM2 MONITORING CABLE HMWPE CABLE 1C 16MM2 ANOD LEAD CABLE HMWPE CABLE 16MM2 1C NEGATIVE CABLE HMWPE CABLE 1C 35MM2 NEGATIVE CABLE HMWPE CABLE 1C 50MM2 POSITIVE CABLE HMWPE-CV-IC-25MM2 POSITIVE CABLE HMWPE-CV-1C-35MM2 TEST LEAD CABLE 1C 10MM2 MONITORING CABLE 1C 16MM2 ANOD LEAD CABLE 16MM2 1C NEGATIVE CABLE 1C 35MM2 NEGATIVE CABLE 1C 50MM2 POSITIVE CABLE 25MM2 POSITIVE CABLE 35MM2 Bill Of Quantities Process Plant Project Bill of Quantities Item 64580 Description Unit Cathodic Protection Conduit Conduit RIGID STEEL CONDUITHOT DIP GALVANIZED, NPT THREADED BOTH ENDSWITH 1-COUPLING, 4" RIGID STEEL CONDUIT 4" Quantity Rate Amount m 2,500.00 63.00 157,500.00 m 2,500.00 230.00 575,000.00 Sub Total Conduit: m 5,000.00 146.50 732,500.00 m 69.00 57.00 3,933.00 EA 104.00 130.00 13,520.00 EA 104.00 31.00 3,224.00 EA 65.00 34.00 2,210.00 m EA EA EA 69.00 104.00 104.00 65.00 280.00 510.00 17.00 29.00 19,320.00 53,040.00 1,768.00 1,885.00 Sub Total Fittings: LS 1.00 98,900.00 98,900.00 1.00 831,400.00 831,400.00 22.00 22.00 25.00 81.00 5,050.00 4,660.00 3,740.00 1,340.00 111,100.00 102,520.00 93,500.00 108,540.00 150.00 2,771.07 415,660.00 SET 9.00 47,770.00 429,930.00 EA 1.00 47,770.00 47,770.00 EA 3.00 47,770.00 143,310.00 EA 1.00 47,770.00 47,770.00 Sub Total Cathodic Protection Equipment: Set 14.00 47,770.00 668,780.00 EA EA EA EA 244.00 202.00 244.00 202.00 770.00 770.00 840.00 540.00 187,880.00 155,540.00 204,960.00 109,080.00 Sub Total Cathodic Protection Markers: ea 892.00 737.06 657,460.00 64800 Cathodic Protection Miscellaneous MISCELLANEOUS FOR CATHODIC PROTECTION SYSTEM EA 1.00 144,570.00 144,570.00 64810 DESK FOR COMPUTER OPERATION 1.00 2,600.00 2,600.00 64590 64600 64610 64620 64630 64640 64650 64660 64670 Fittings CONDUIT ELBOW 90' HOT DIP GALVANIZED, NPT THREADED BOTH ENDS WITH 2-COULING 1" SEALING FITTINGFLAME EXPLOSION PROOF TYPE, UNIVERSAL CONDUIT CLAMP WITH 304SS BOLT & NUT UNISTRUT TYPE STAINLESS STEEL(304SS), 41 X 41 X 2.6t 3M LONG 2" DEA. SLOTTED PVC PIPE INSERTED IN GEOTEXTILE SOCK CONDUIT ELBOW 90' 1" SEALING FITTING CONDUIT CLAMP 4" (104mm) PVC PIPE 3M LONG 2" DEA. Sub Total Cathodic Protection Conduit: m 64680 64690 64700 64710 Cathodic Protection Junction Boxes ANODE JUNCTIION BOX EXPLOSION PROOF TYPE NEGATIVE JUNCTION BOX WEATHER PROOF BONDIN BOX WEATHER PROOF TYPE TEST BOX FOR CATHODIC PROTECTION EXPLOSION PROOF TYPE EA EA ea SET Sub Total Cathodic Protection Junction Boxes: ea 64720 64730 64740 64750 64760 64770 64780 64790 Cathodic Protection Equipment TRANSFORMER RECTIFIER FOR CATHODIC PROTECTION WEATHER PROOF TYPE TRANSFORMER RECTIFIER FOR CATHODIC PROTECTION WEATHER PROOF TYPE TRANSFOMER RECTIFIER FOR CATHODIC PROTECTION WEATHER PROOF TYPE TRANSFOMER RECTIFIER FOR CATHODIC PROTECTION WEATHER PROOF TYPE Cathodic Protection Markers ANODE MARKER CABLE MARKER ANODE MARKER CABLE MARKER EA Bill Of Quantities Process Plant Project Bill of Quantities Item 64820 64830 64840 64850 64860 64870 64880 64890 Description Unit PERSONAL COMPUTER AND MONITOR FOR CP SYSTEM EA MONITORING DIRECT BURIAL CABLE TRENCH FOR ANODE CATHODE M REFERENCE ELECTRODE CABLES 600mmW X 715mmD 64940 64950 64960 64970 64980 64990 65000 Rate Amount 1.00 57.00 57.00 7,000.00 48.00 336,000.00 CATHODIC PROTECTION EA DESK FOR COMPUTER OPERATION EA PERSONAL COMPUTER AND MONITOR FOR CP SYSTEM EA MONITORING 1.00 1.00 1.00 92,320.00 17,090.00 17,090.00 92,320.00 17,090.00 17,090.00 Sub Total Cathodic Protection Miscellaneous: ea 7,006.00 87.03 609,727.00 Sub Total Cathodic Protection System: LS 1.00 13,675,072.00 13,675,072.00 SET 2.00 2,870.00 5,740.00 SET SET 8.00 8.00 2,930.00 460.00 23,440.00 3,680.00 18.00 1,825.56 32,860.00 m m m m 2,227.00 2,169.00 210.00 80.00 15.00 12.00 12.00 12.00 33,405.00 26,028.00 2,520.00 960.00 Sub Total Cable: m 4,686.00 13.43 62,913.00 EA EA 12.00 36.00 6.34 6.34 76.08 228.24 Sub Total Cable Gland: ea 48.00 6.34 304.32 Sub Total CCTV Cabling: LS 1.00 63,217.32 63,217.32 m m 129.00 269.00 34.00 22.00 4,386.00 5,918.00 Sub Total Conduit: m 398.00 25.89 10,304.00 m EA EA 65.00 80.00 80.00 25.00 16.00 8.76 1,625.00 1,280.00 700.80 Sub Total Clamp: LS 1.00 3,605.80 3,605.80 Sub Total CCTV Conduit: LS 1.00 13,909.80 13,909.80 CCTV System CCTV Equipment CCTV SYSTEM EQUIPMENT19" 42U EQUIPMENT CABINETINDOOR COLOR CAMERA SONY'S MODEL FCB-EX SERIES WASHER TANK FOR COLOR CAMERA Sub Total CCTV Equipment: Set 64900 64910 64920 64930 Quantity CCTV Cabling Cable POWER CABLE, ELECTRIC 3/C * 4mm2 FIBER OPTIC CABLE4C SINGLE MODE FIBER OPTIC ABLE4C SINGLE MODE COMPOSITE CABLE FOR CCTV CAMERA Cable Gland CABLE GLANDEXPLOSION PROOF TYPE3/4" CABLE GLANDWEATHER PROOF3/4" CCTV Conduit Conduit RIGID STEEL CONDUIT 3/4" PVC CONDUITSCHEDULE 40 Clamp CONDUIT CLAMP 3/4" CONDUIT CLAMPUNISTRUT TYPE 3/4" CONDUIT CLAMP CCTV Cable Tray Tray Bill Of Quantities Process Plant Project Bill of Quantities Item 65010 65020 Description Unit PERFORATED CABLE TRAYSTRAIGHT PERFORATED CABLE TRAY SUPPORT m SET 65070 65080 65090 65140 65150 65160 4,407.00 9,890.00 1.00 14,297.00 14,297.00 EA EA EA EA 170.00 170.00 204.00 204.00 10.00 6.70 69.00 17.00 1,700.00 1,139.00 14,076.00 3,468.00 Sub Total Clamps: LS 1.00 20,383.00 20,383.00 Sub Total CCTV Cable Tray: LS 1.00 34,680.00 34,680.00 EA 8.00 100.00 800.00 Sub Total CCTV Junction Boxes: LS 1.00 800.00 800.00 1.00 1.00 1,180.00 1,400.00 1,180.00 1,400.00 1.00 2,580.00 2,580.00 EA EA m m 8.00 1,019.00 16.00 20.00 1,700.00 17.00 70.00 75.00 13,600.00 17,323.00 1,120.00 1,500.00 EA 8.00 78.00 624.00 1,219.00 1,219.00 17.00 8.76 20,723.00 10,678.44 1.00 65,568.44 65,568.44 1.00 86,900.00 86,900.00 Sub Total CCTV Miscellaneous: LS 1.00 86,900.00 86,900.00 Sub Total CCTV System: LS 1.00 300,515.56 300,515.56 m3 EA EA 456.00 12.00 11.00 67.00 420.00 420.00 30,552.00 5,040.00 4,620.00 Sub Total Fire Alarm Civil Work: LS 1.00 40,212.00 40,212.00 400.00 2,382.00 11.00 11.00 4,400.00 26,202.00 Clamps JOINT CONNECTOR COVER CLAMP FOR PERFORATED CT COVER CLAMP FOR PERFORATED CABLE TRAY50MM COVER CLAMP CCTV Junction Boxes JUNCTION BOX WITH COVER AND GASKET CCTV Computer Equipment 24 PORT LAN SWITCH, CISCO, WS-C3750E WORK STATION WITH KEYBOARD SET SET CCTV Support POLE FOR CCTV CAMERA SET STAINLESS SHANK BOLT & NUT STEEL ANGLE HOT DIP GALVANIZED STEEL UNISTRUT CHANNELHOT DIP GALVANIZED STEEL41 X 41 X 2.6t STEEL PLATE HOT DIP GALVANIZED STEEL 500 X 300 X 6t SHANK BOLT AND NUT SHANK BOLT SET SET Sub Total CCTV Support: LS 65170 65180 65190 65200 65210 65220 Amount 13.00 230.00 Sub Total CCTV Computer Equipment: LS 65100 65110 65120 65130 Rate 339.00 43.00 Sub Total Tray: LS 65030 65040 65050 65060 Quantity CCTV Miscellaneous MISCELLANEOUS FOR CCTV SYSTEM Fire Alarm System Fire Alarm Civil Work EXCAVATION & BACK FILL WORK FOUNDATION FOR MPS POLEW305 x D305 x H914 FOUNDATION FOR MPS POLEW305 x D305 x H510 Fire Alarm Cabling Cable LINEAR HEAT DETECTOR CABLE FIRE ALARM CABLE, ELECTRIC. 1P-1.5mm2 LOT m m Bill Of Quantities Process Plant Project Bill of Quantities Item 65230 65240 65250 65260 65270 65280 65290 65300 65310 65320 65330 65340 65350 65360 65370 65380 65390 65400 65410 65420 Description Unit FIRE ALARM CABLE, ELECTRIC. 6C-2.5mm2 FIRE ALARM CABLE, ELECTRIC. 2C-2.5mm2 FIRE ALARM CABLE, ELECTRIC. 3C-2.5mm2 FIRE ALARM CABLE, ELECTRIC. 4C-2.5mm2 FIRE ALARM CABLE, ELECTRIC. 12C-2.5mm2 FIRE ALARM CABLE, ELECTRIC. 19C-2.5mm2 FIRE ALARM CABLE, ELECTRIC. 30C-2.5mm2 CABLE FOR GAS DETECTOR1P-1.0mm2 FIRE ALARM CABLE, ELECTRIC. 10C-2.5mm2 65440 65450 Rate Amount m 95.00 11.00 1,045.00 m 7,743.00 11.00 85,173.00 m 285.00 11.00 3,135.00 m 520.00 11.00 5,720.00 m 1,330.00 11.00 14,630.00 m 4,233.00 11.00 46,563.00 m 505.00 11.00 5,555.00 m m 42.00 24.00 11.00 11.00 462.00 264.00 Sub Total Cable: m 17,559.00 11.00 193,149.00 EA 258.00 16.00 4,128.00 EA 2.00 20.00 40.00 EA 6.00 22.00 132.00 EA 1.00 26.00 26.00 EA 140.00 16.00 2,240.00 EA 4.00 20.00 80.00 EA 13.00 22.00 286.00 Sub Total Cable Gland: ea 424.00 16.35 6,932.00 Sub Total Fire Alarm Cabling: LS 1.00 200,081.00 200,081.00 m 5,368.00 42.00 225,456.00 m 565.00 56.00 31,640.00 m 317.00 27.00 8,559.00 m 35.00 76.00 2,660.00 1.00 268,315.00 268,315.00 m 1,642.00 24.00 39,408.00 m 45.00 26.00 1,170.00 m 568.00 28.00 15,904.00 Cable Gland CABLE GLAND 3/4" CABLE GLAND 1" CABLE GLAND 1-1/2" CABLE GLAND 2" CABLE GLAND 3/4" CABLE GLAND 1" CABLE GLAND 1-1/2" Fire Alarm Conduit Rigid Steel Conduit RIGID STEEL CONDUIT HOT DIP GALVANIZED, NPT THREADED BOTH ENDS1" RIGID STEEL CONDUIT 1-1/4" RIGID STEEL CONDUIT 1-1/2" RIGID STEEL CONDUIT 2" Sub Total Rigid Steel Conduit: LS 65430 Quantity PVC Conduit PVC CONDUIT (SCHEDULE 40) 1" PVC CONDUIT (SCHEDULE 40) 1-1/4" PVC CONDUIT (SCHEDULE 40) 1-1/2" Bill Of Quantities Process Plant Project Bill of Quantities Item 65460 65470 65480 65490 65500 65510 65520 65530 65540 65550 65560 65570 65580 65590 Description Unit PVC CONDUIT (SCHEDULE 40) 2" Quantity Rate Amount m 23.00 38.00 874.00 Sub Total PVC Conduit: m 2,278.00 25.18 57,356.00 m 38.00 110.00 4,180.00 Sub Total Flexible Metal Conduit: m 38.00 110.00 4,180.00 EA EA EA EA EA EA EA EA EA 1,398.00 90.00 149.00 2,000.00 3,957.00 754.00 2,000.00 3,957.00 754.00 29.00 35.00 38.00 25.00 29.00 35.00 97.00 130.00 160.00 40,542.00 3,150.00 5,662.00 50,000.00 114,753.00 26,390.00 194,000.00 514,410.00 120,640.00 Sub Total Conduit Clamp: ea 15,059.00 71.02 1,069,547.00 Sub Total Fire Alarm Conduit: LS 1.00 1,399,398.00 1,399,398.00 M M 60.00 30.00 20.00 59.00 1,200.00 1,770.00 Sub Total Tray: m 90.00 33.00 2,970.00 EA 30.00 6.70 201.00 Sub Total Clamps: ea 30.00 6.70 201.00 Sub Total Fire Alarm Cable Tray: LS 1.00 3,171.00 3,171.00 Flexible Metal Conduit FLEXIBLE METALLIC CONDUIT 3/4" Conduit Clamp CONDUIT CLAMP1" CONDUIT CLAMP1-1/4" CONDUIT CLAMP1-1/2" CONDUIT CLAMP 3/4" CONDUIT CLAMP 1" CONDUIT CLAMP 1 1/4" CONDUIT CLAMP 3/4" CONDUIT CLAMP 1" CONDUIT CLAMP 1-1/4" Fire Alarm Cable Tray Tray PERFORATED CABLE TRAY100 X 50 PERFORATED CABLE TRAY100MM Clamps COVER CLAMP100MM 65600 Fire Alarm Devices Fire Alarm Stations FIRE ALARM MANUAL STATION EA 30.00 150.00 4,500.00 65610 FIRE ALARM MANUAL STATION EA 18.00 140.00 2,520.00 65620 FIRE ALARM MANUAL STATION EA 14.00 120.00 1,680.00 65630 CO2 DISCHARGE MANUAL STATION EA 1.00 140.00 140.00 Sub Total Fire Alarm Stations: ea 63.00 140.32 8,840.00 65640 Warning Devices FIRE ALARM SIREN (MEDC DB3 RANGE) SET 38.00 190.00 7,220.00 65650 FIRE ALARM SIREN (MEDC DB3 RANGE) SET 44.00 190.00 8,360.00 Bill Of Quantities Process Plant Project Bill of Quantities Item Description Unit Quantity Rate Amount 65660 FIRE ALARM HORN/STROBE EA 12.00 340.00 4,080.00 65670 FIRE ALARM HORN/STROBE EA 6.00 340.00 2,040.00 65680 FLASH LIGHT FOR FIRE ALARM(BEACON) EA 8.00 250.00 2,000.00 65690 FLASH LIGHT FOR FIRE ALARM(BEACON) EA 8.00 250.00 2,000.00 65700 CO2 DISCHARGE WARNING LIGHT (LAMP) EA 1.00 250.00 250.00 65710 CO2 DISCHARGE WARNING SIREN EA 1.00 320.00 320.00 Sub Total Warning Devices: LS 1.00 26,270.00 26,270.00 65720 Fire Alarm Detectors FIRE DETECTOR EA 41.00 320.00 13,120.00 65730 DUCT SMOKE DETECTOR EA 12.00 320.00 3,840.00 65740 FIRE DETECTOR EA 1.00 110.00 110.00 65750 FIRE DETECTOR EA 62.00 110.00 6,820.00 65760 BEAM DETECTOR EA 5.00 110.00 550.00 Sub Total Fire Alarm Detectors: ea 121.00 201.98 24,440.00 EA 1.00 140.00 140.00 Sub Total Fire Alarm Switches: ea 1.00 140.00 140.00 Sub Total Fire Alarm Devices: LS 1.00 59,690.00 59,690.00 m 532.00 75.00 39,900.00 m 35.00 140.00 4,900.00 1,641.00 180.00 6.00 22.00 17.00 230.00 36,102.00 3,060.00 1,380.00 1.00 85,342.00 85,342.00 EA 1.00 450.00 450.00 EA 15.00 380.00 5,700.00 EA 16.00 380.00 6,080.00 EA 1.00 310.00 310.00 Sub Total Termination Boxes: ea 33.00 380.00 12,540.00 65770 65780 65790 65800 65810 65820 Fire Alarm Switches CO2 DISCHARGE ABORT SWITCH Fire Alarm Support UNISTRUT CHANNEL HOT DIP GALVANIZED STEEL41 X 41 X 2.6t STEEL CHANNEL HOT DIP GALVANIZED STEEL100 x 50 x 5t EXPANSION ANCHOR3/8" STAINLESS SHANK BOLT & NUT PERFORATED CABLE TRAY SUPPORT EA EA SET Sub Total Fire Alarm Support: LS 65830 65840 65850 65860 Fire Alarm Panels & Boxes Termination Boxes TERMINAL BOX FOR FIRE ALARM 40TB TERMINAL BOX FOR FIRE ALARM 20TB TERMINAL BOX FOR FIRE ALARM 20TB TERMINAL BOX FOR FIRE ALARM 5TB Bill Of Quantities Process Plant Project Bill of Quantities Item Description Unit Quantity Rate Amount 65870 Junction Boxes 4" SQUARE BOX EA 45.00 49.00 2,205.00 65880 4" SQUARE BOX EA 77.00 49.00 3,773.00 65890 65900 BUSHING & LOCK NUT FOR SQUARE BOX 1" BUSHING & LOCK NUT FOR SQUARE BOX 1-1/4" EA EA 220.00 24.00 15.00 16.00 3,300.00 384.00 Sub Total Junction Boxes: ea 366.00 26.40 9,662.00 3.00 2,740.00 8,220.00 3.00 2,740.00 8,220.00 4.00 2,740.00 10,960.00 Sub Total Fire Alarm Cabinets: LS 1.00 10,960.00 10,960.00 Sub Total Fire Alarm Panels & Boxes: LS 1.00 41,382.00 41,382.00 65910 Fire Alarm Panels ADDRESSABLE FIRE ALARM PANEL SET Sub Total Fire Alarm Panels: Set 65920 Fire Alarm Cabinets EDIO CABINET WITH 4 EDIO MODULES(400)W X (150)D X SET (405)H 65930 Fire Alarm Miscellaneous LINEAR HEAT DETECTOR WITH INTERFACE MODULE SET 1.00 2,740.00 2,740.00 65940 MISCELLANEOUS FOR FIRE ALRAM SYSTEM LOT 1.00 136,870.00 136,870.00 Sub Total Fire Alarm Miscellaneous: LS 1.00 139,610.00 139,610.00 Sub Total Fire Alarm System: LS 1.00 1,968,886.00 1,968,886.00 EA EA 11.00 11.00 120.00 73.00 1,320.00 803.00 Sub Total Grounding Reels: ea 22.00 96.50 2,123.00 161.00 180.00 28,980.00 161.00 180.00 28,980.00 m m m m 5,258.00 8,844.00 2,089.00 435.00 38.00 81.00 38.00 96.00 199,804.00 716,364.00 79,382.00 41,760.00 Sub Total Ground Wire: m 16,626.00 62.39 1,037,310.00 65950 65960 65970 Grounding System Grounding Reels GROUND REEL(EXPLOSION PROOF15m LONG STEEL PLATE FOR GROUND REEL203 x 203 x 13t Ground Conductors Ground Rods GROUNDING ROD WITH CONNECTOR38mmDIA * 1520mmL SET Sub Total Ground Rods: Set 65980 65990 66000 66010 Ground Wire GROUNDING WIRE, ELECTRIC35mm2 GROUNDING WIRE, ELECTRIC.70mm2 GROUNDING WIRE, ELECTRIC.35mm2 GROUNDING WIRE, ELECTRIC.120mm2 Bus Bar Bill Of Quantities Process Plant Project Bill of Quantities Item 66020 66030 66040 66050 66060 66070 66080 66090 66100 66110 66120 66130 66140 66150 66160 66170 Description Unit TINNED COPPER GROUNDING BUS BAR6mmT X 50mmW SET X 356mmL Quantity Rate Amount 67.00 520.00 34,840.00 Sub Total Bus Bar: LS 1.00 34,840.00 34,840.00 Sub Total Ground Conductors: LS 1.00 1,101,130.00 1,101,130.00 EA 59.00 630.00 37,170.00 EA 21.00 630.00 13,230.00 EA 1.00 630.00 630.00 EA 6.00 640.00 3,840.00 EA EA EA 2.00 2.00 1.00 630.00 630.00 630.00 1,260.00 1,260.00 630.00 Sub Total Thermal Moulds: ea 92.00 630.65 58,020.00 EA 1,395.00 42.00 58,590.00 EA 344.00 45.00 15,480.00 EA 7.00 53.00 371.00 EA 104.00 56.00 5,824.00 EA EA EA 24.00 19.00 4.00 56.00 61.00 56.00 1,344.00 1,159.00 224.00 Sub Total Thermal Welding Powder: ea 1,897.00 43.75 82,992.00 Sub Total Grounding Thermal Welds: LS 1.00 141,012.00 141,012.00 m 3,515.00 28.00 98,420.00 Sub Total Conduit: m 3,515.00 28.00 98,420.00 866.00 1,130.00 1,130.00 26.00 25.00 8.76 22,516.00 28,250.00 9,898.80 Sub Total Clamps: LS 1.00 60,664.80 60,664.80 Sub Total Grounding System Conduit: LS 1.00 159,084.80 159,084.80 Grounding Thermal Welds Thermal Moulds MOLD WITH FRAME FOR GROUND WIRE CONNECTIONMAIN: 70mm2 * TAP: 35mm2 MOLD WITH FRAME FOR GROUND WIRE CONNECTIONMAIN: 70mm2 * TAP: 70mm2 MOLD WITH FRAME FOR GROUND WIRE CONNECTIONMAIN: 120mm2 * TAP: 70mm2 MOLD WITH FRAME FOR GROUND WIRE CONNECTIONMAIN: 240mm2 * TAP: 240mm2 MOLD WITH FRAMEMAIN: 240mm2 * TAP: 70mm2 MOLD WITH FRAMEMAIN: 240mm2 * TAP: 240mm2 MOLD WITH FRAME MAIN: 70mm2 * TAP: 70mm2 Thermal Welding Powder THERMAL WELDING POWDER FOR GROUND WIRE CONNECTION # 45 THERMAL WELDING POWDERFOR GROUND WIRE CONNECTION# 115 THERMAL WELDING POWDER FOR GROUND WIRE CONNECTION# 150 THERMAL WELDING POWDER FOR GROUND WIRE CONNECTION# 150 THERMAL WELDING POWDER# 150 THERMAL WELDING POWDER# 500 THERMAL WELDING POWDER# 150 Grounding System Conduit Conduit PVC CONDUIT SCHEDULE 40 PVC 3/4" (22mm) 66180 66190 66200 Clamps CONDUIT CLAMP ONE HOLE CONDUIT CLAMP CONDUIT CLAMP 3/4" Grounding Support EA SET SET Bill Of Quantities Process Plant Project Bill of Quantities Item 66210 66220 66230 66240 Description Unit UNISTRUT CHANNEL UNISTRUT CHANNEL STEEL CHANNEL FOR GROUND REEL100 * 50 * 5T UNISTRUT CLAMP3/4" (22mm) 75.00 75.00 81.00 16.00 13,500.00 675.00 2,187.00 22,336.00 Sub Total Grounding Support: LS 1.00 38,698.00 38,698.00 2,385.00 67.00 159,795.00 11.00 7.00 88.00 270.00 968.00 1,890.00 1.00 162,653.00 162,653.00 58.00 850.00 49,300.00 1.00 49,300.00 49,300.00 2.00 840.00 1,680.00 Sub Total Bonding Boxes: LS 1.00 1,680.00 1,680.00 Sub Total Grounding Boxes: LS 1.00 50,980.00 50,980.00 EA EA 1,365.00 335.00 46.00 54.00 62,790.00 18,090.00 EA 18.00 46.00 828.00 Sub Total Servit Posts: ea 1,718.00 47.56 81,708.00 EA EA 58.00 12.00 120.00 93.00 6,960.00 1,116.00 Sub Total Fence Post Grounding Connector: ea 70.00 115.37 8,076.00 EA 12.00 730.00 8,760.00 Sub Total Copper Braid: ea 12.00 730.00 8,760.00 Sub Total Grounding Connectors: LS 1.00 98,544.00 98,544.00 SET 198.00 320.00 63,360.00 SET 2,089.00 54.00 112,806.00 EA SET 145.00 44.00 51.00 25.00 7,395.00 1,100.00 m3 66260 66270 BASE CONCRETE FOR GROUND REEL305 x 305 x 5t GROUNDING CABLE ROUTE MARKERSHEET EA SET Sub Total Grounding System Civil Work: LS Grounding Boxes Concrete Boxes GROUND WELLCONCRETE BOX TYPE267mm 438mm 305mm (EA) SET Sub Total Concrete Boxes: LS 66300 66310 66320 66330 66340 66350 66360 66370 66380 66390 Amount 180.00 9.00 27.00 1,396.00 Grounding System Civil Work EXCAVATION & BACK FILL WORK 66290 Rate EA EA m EA 66250 66280 Quantity Bonding Boxes GROUND BONDING BOX SET Grounding Connectors Servit Posts CONNECTION SERVIT POST CONNECTION SERVIT POST 25-70 mm²1/2"-13 x 3/4" STUD CONNECTION SERVIT POST FOR TRANSFORMER Fence Post Grounding Connector FENCE POST GROUNDING CONECTOR2" FENCE POST GROUNDING CONECTOR1-1/2" Copper Braid COPPER BRAID FOR FENCE GATE GROUND1"W x 12"L Grounding Accessories AIR TERMINALCOPPER WITH NICKEL 5/8"(DIA) 1'(LONG) (EA) SUPPORT FOR LIGHTNING CONDUCTOR CLIP TYPE 35 mm2 GROUND LUG (WITH/15mm HOLE)128 x 50 x 6t HEX HEAD BOLT, SPRING NUT AND LOCK WASHER1/4" x 20mm Bill Of Quantities Process Plant Project Bill of Quantities Item 66400 66410 66420 66430 66440 66450 66460 66470 66480 66490 66500 66510 66520 66530 66540 66550 66560 66570 66580 66590 66600 66610 66620 66630 66640 66650 66660 Description Unit MOUNTING BASE250 x 250 x 6T WARINING SIGN STEEL PLATE 76 x 76 x 6t MISCELLANEOUS FOR GROUNDING SYSTEM EXPANSION ANCHOR,1/2" - 30 STANDOFF INSULATOR FOR GROUNDING BUS BAR ALL THREAD ROD1/2"-13 x 4"L EXPANSION ANCKOR,1/2"-20 1/2" MACHINE BOLT1/2"-20 1/2" NUT, HEX1/2"-13 1/2" LOCKWASHER 1/2" LOCKWASHER PARALLEC CLAMP FOR LIGHTNING DOWN CONDUCTOR35 mm² SUPPORT FOR AIR TERMINAL(OUTSIDE) MACHINE BOLT1/2" x 20mm ANCHOR BOLT ANCHOR BOLT MACHINE BOLT 1/2" x 20mm ANCHOR BOLT 1/2" x 30mm ANCHOR BOLT 1/2" x 30mm 66710 66720 66730 66740 66750 Rate Amount EA EA LOT EA EA EA EA EA EA EA EA EA 198.00 11.00 1.00 44.00 84.00 84.00 134.00 134.00 335.00 413.00 80.00 48.00 230.00 57.00 41,760.00 24.00 63.00 18.00 17.00 9.72 9.72 8.96 8.96 51.00 45,540.00 627.00 41,760.00 1,056.00 5,292.00 1,512.00 2,278.00 1,302.48 3,256.20 3,700.48 716.80 2,448.00 SET SET EA EA SET EA EA 8.00 96.00 33.00 59.00 96.00 33.00 59.00 510.00 9.72 37.00 37.00 8.76 8.76 8.76 4,080.00 933.12 1,221.00 2,183.00 840.96 289.08 516.84 Sub Total Grounding Accessories: LS 1.00 304,213.96 304,213.96 Sub Total Grounding System: LS 1.00 2,058,438.76 2,058,438.76 1.00 1.00 2.00 2.00 4.00 20.00 69.00 4.00 2,180.00 2,180.00 2,180.00 2,180.00 190.00 92.00 300.00 300.00 2,180.00 2,180.00 4,360.00 4,360.00 760.00 1,840.00 20,700.00 1,200.00 1.00 37,580.00 37,580.00 m m m m 129.00 352.00 261.00 3,028.00 29.00 20.00 20.00 14.00 3,741.00 7,040.00 5,220.00 42,392.00 Sub Total Telephone System Cabling: m 3,770.00 15.49 58,393.00 m m 1,550.00 146.00 34.00 28.00 52,700.00 4,088.00 Sub Total Conduit: m 1,696.00 33.48 56,788.00 EA EA EA 74.00 776.00 74.00 8.76 16.00 17.00 648.24 12,416.00 1,258.00 Sub Total Clamps: ea 924.00 15.50 14,322.24 Communications System Telephone System Telephone System Equipment 19" EQPT CABINET 19" EQPT CABINET 19" EQPT CABINET 19" EQUT CABINET TELEPHONE HANDSET ASSEMBLY INDOOR TELEPHONE HANDSET STATION TERMINAL OUTLET4 PORT TYPE, RJ45 TELEPHONE OUTLETINDOOR 4 PORT SET SET SET SET EA EA EA EA Sub Total Telephone System Equipment: LS 66670 66680 66690 66700 Quantity Telephone System Cabling TELEPHONE CABLE, ELECTRIC50P-0.75mm2 TELEPHONE CABLE, ELECTRIC10P-0.75mm2 TELEPHONE CABLE, ELECTRIC4P-0.75mm2 UTPCAT NO.6, 4 PAIRS, UNARMORED Telephone System Conduit Conduit RIGID STEEL CONDUITHOT DIP GALVANIZED3/4" PVC CONDUIT SCHEDULE 40WITH3/4" Clamps UNISTRUT CLAMP 3/4" UNISTRUT CLAMP HOT DIP GALVANIZED3/4" UNISTRUT CLAMP Bill Of Quantities Process Plant Project Bill of Quantities Item Description Unit Sub Total Telephone System Conduit: LS 66760 66770 66790 66800 66810 66820 66830 66840 66850 66860 66870 66880 66890 66900 66910 Rate Amount 1.00 71,110.24 71,110.24 m3 589.00 67.00 39,463.00 Sub Total Telephone System Civil Work: LS 1.00 39,463.00 39,463.00 73.00 49.00 3,577.00 73.00 49.00 3,577.00 m 79.00 75.00 5,925.00 EA 405.00 37.00 14,985.00 Sub Total Telephone System Support: LS 1.00 20,910.00 20,910.00 1.00 65,920.00 65,920.00 Sub Total Telephone System Miscellaneous: LS 1.00 65,920.00 65,920.00 Sub Total Telephone System: LS 1.00 296,953.24 296,953.24 SET SET SET 4.00 4.00 4.00 2,870.00 2,870.00 1,990.00 11,480.00 11,480.00 7,960.00 SET SET 5.00 1.00 1,990.00 1,990.00 9,950.00 1,990.00 EA 1.00 350.00 350.00 Sub Total Computer Equipment: LS 1.00 43,210.00 43,210.00 m m 897.00 299.00 11.00 23.00 9,867.00 6,877.00 Sub Total Computer Cabling: m 1,196.00 14.00 16,744.00 Computer Panels FIBER OPTIC PATCH PANELW800 X D630 X H2000 EA FIBER OPTIC PATCH PANELINDOOR USEFOPP MODULE EA 1.00 12.00 2,870.00 1,990.00 2,870.00 23,880.00 Sub Total Computer Panels: LS 1.00 26,750.00 26,750.00 1.00 61,620.00 61,620.00 1.00 61,620.00 61,620.00 Telephone System Civil Work EXCAVATION & BACK FILL WORK Telephone System Junction Boxes 4" SQUARE BOXZINC ELECTRO PLATE SET Sub Total Telephone System Junction Boxes: Set 66780 Quantity Telephone System Support UNISTRUT CHANNELHOT DIP GALVANIZED STEEL41 X 41 X 2.6t EXPANSION ANCHOR3/8" Telephone System Miscellaneous MISCELLANEOUS FOR TELEPHONE SYSTEM Computer System Computer Equipment LAN/IP SYSTEM COMPONENTINDOOR LAN/IP SYSTEM COMPONENT48PORT ACCESS SWITCH LAN/IP SYSTEM COMPONENT24PORT UTP PATCH PANEL LAN/IP SYSTEM COMPONENTUPS MODULEADELMO LAN/IP SYSTEM COMPONENTANALOGUE PHONE GATEWAYCISCO PERSONAL COMPUTERFOR WEATHER MONITRING SYSTEM Computer Cabling FIBER OPTIC CABLESINGLE MODE4C FIBER OPTIC CABLESINGLE MODE, PVC INSULATED, STEEL WIRE ARMOURED48C Computer Miscellaneous MISCELLANEOUS FOR LAN SYSTEM LOT LOT Sub Total Computer Miscellaneous: LS Bill Of Quantities Process Plant Project Bill of Quantities Item Description Unit Sub Total Computer System: LS 66920 66930 66940 66950 66960 66970 66980 66990 67000 67010 67020 67060 67070 67080 67090 67100 67110 67120 67130 Amount 148,324.00 148,324.00 SET 1.00 8,980.00 8,980.00 SET 1.00 8,390.00 8,390.00 EA EA EA 1.00 2.00 17.00 3,040.00 2,150.00 380.00 3,040.00 4,300.00 6,460.00 EA 33.00 340.00 11,220.00 EA EA SET SET SET 47.00 1.00 10.00 2.00 2.00 340.00 200.00 170.00 2,650.00 1,700.00 15,980.00 200.00 1,700.00 5,300.00 3,400.00 1.00 68,970.00 68,970.00 m m m 6,655.00 228.00 285.00 16.00 40.00 47.00 106,480.00 9,120.00 13,395.00 Sub Total Cable: m 7,168.00 18.00 128,995.00 EA EA 45.00 45.00 6.34 6.34 285.30 285.30 Sub Total Cable Gland: ea 90.00 6.34 570.60 Sub Total Paging System Cabling: LS 1.00 129,565.60 129,565.60 m m EA 1,785.00 703.00 36.00 34.00 28.00 0.00 60,690.00 19,684.00 0.00 Sub Total Conduit: LS 1.00 80,374.00 80,374.00 m EA EA 893.00 1,207.00 1,207.00 16.00 17.00 8.76 14,288.00 20,519.00 10,573.32 Sub Total Clamps: LS 1.00 45,380.32 45,380.32 Sub Total Paging System Conduit: LS 1.00 125,754.32 125,754.32 Paging System Paging System Equipment CENTRAL PAGING EQUIPMENTTYCO MODEL NO.ACE 100INDOOR REMOTE PAGING EQUIPMENTTYCO MODEL NO.ACE 100RAINDOOR EE872 DIGITAL HAND SET MASTER STATION HAND SET STATION EXPLOSION PROOF CONE SPEAKER ASSEMBLY (FOR PAGING)INDOOR USE6W CONE SPEAKER ASSEMBLY (FOR PAGING)INDOOR USE6W HORN SPEAKER ASSEMBLY15W BEACON LAMP HAND HELD RADIOOUTDOOR USE MOBILE RADIOVEHICLES USETRANSMITTER BATTERY CHARGER FOR RADIO SYSTEMINDOOR Paging System Cabling Cable COMMUNICATION CABLE, ELECTRIC1P-2.5mm2 COMMUNICATION CABLE, ELECTRIC 2C - 2.5mm2 COMMUNICATION CABLE, ELECTRIC2P- 1.5mm2 Cable Gland CABLE GLAND, NICKEL PLATEWEATHER PROOF3/4" CABLE GLAND, NICKEL PLATEEXPLOSION PROOF3/4" Paging System Conduit Conduit RIGID STEEL CONDUIT HOT DIP GALVANIZED3/4" PVC CONDUITSCHEDULE 40 3/4" FLEXIBLE METALLIC CONDUIT INDOOR 3/4" Clamps UNISTRUT CLAMP HOT DIP GALVANIZED 3/4" UNISTRUT CLAMP HOT DIP GALVANIZED STEEL CLAMP 3/4" Paging System Support Rate 1.00 Sub Total Paging System Equipment: LS 67030 67040 67050 Quantity Bill Of Quantities Process Plant Project Bill of Quantities Item 67140 67150 67160 67170 67180 Description Unit UNISTRUT CHANNEL HOT DIP GALVANIZED STEEL41 X 41 X 2.6t HANDSET SUPPORT SPEAKER SUPPORTWITH 67200 67210 67220 67230 67240 67250 67260 67270 67280 67290 Amount 75.00 17,475.00 2.00 4.00 530.00 250.00 1,060.00 1,000.00 Sub Total Paging System Support: LS 1.00 19,535.00 19,535.00 Paging System Civil Work EXCAVATION & BACK FILL WORK FOR PAGING SYSTEM m3 130.00 67.00 8,710.00 Sub Total Paging System Civil Work: LS 1.00 8,710.00 8,710.00 82.00 49.00 4,018.00 1.00 4,018.00 4,018.00 1.00 73,980.00 73,980.00 Sub Total Paging System Miscellaneous: LS 1.00 73,980.00 73,980.00 Sub Total Paging System: LS 1.00 430,532.92 430,532.92 Sub Total Communications System: LS 1.00 875,810.16 875,810.16 9.00 970.00 8,730.00 EA EA EA 854.00 848.00 58.00 44.00 12.00 12.00 37,576.00 10,176.00 696.00 Sub Total Heat Tracing Equipment: LS 1.00 57,178.00 57,178.00 m m 19,120.00 167.00 12.00 12.00 229,440.00 2,004.00 m 37,820.00 35.00 1,323,700.00 Sub Total Cable: m 57,107.00 27.23 1,555,144.00 6.00 70.00 4,800.00 44.00 22.00 7.37 264.00 1,540.00 35,376.00 Sub Total Cable Accessories: LS 1.00 37,180.00 37,180.00 Sub Total Heat Tracing Cabling: LS 1.00 1,592,324.00 1,592,324.00 SET SET SET Sub Total Paging System Junction Boxes: LS 67190 Rate 233.00 Paging System Junction Boxes 4" SQUARE BOXZINC ELECTRO PLATE m Quantity Paging System Miscellaneous MISCELLANEOUS FOR PA SYSTEM LOT Heat Tracing System Heat Tracing Equipment TRANSFORMER ( ELECTRICAL HAET TRACING SYSTEM)DRY TYPE THERMOSTAT SENSOR CIRCUIT FABRICATION KIT POWER TERMINATION KITOUTDOOR Heat Tracing Cabling Cable SELF REGULATING HEATING CABLE MINERAL INSULATED CABLE THERMON CAT NO. MIQ SERIES POWER CABLE, ELECTRIC 3/C * 4mm2 Cable Accessories COLD & HOT LEAD FOR MI CABLE ALUMINUM TAPE THERMON CAUTION LABELTHERMON Heat Tracing Cable Tray Cable Tray SET EA ROLL EA Bill Of Quantities Process Plant Project Bill of Quantities Item 67300 67310 67320 67330 67340 67350 67360 67370 67380 67390 67400 67410 67420 Description Unit PERFORATED CABLE TRAYPUNCHED TYPE100mmW X 50mmH X 67480 67490 67500 Amount 12,810.00 32.00 409,920.00 Sub Total Cable Tray: m 12,810.00 32.00 409,920.00 EA EA 35.00 70.00 57.00 12.00 1,995.00 840.00 EA 13.00 18.00 234.00 EA 4.00 18.00 72.00 EA 4.00 18.00 72.00 EA 13.00 12.00 156.00 EA 4.00 12.00 48.00 EA EA EA 4.00 252.00 286.00 12.00 8.54 22.00 48.00 2,152.08 6,292.00 Sub Total Cable Tray Accessories: LS 1.00 11,909.08 11,909.08 Sub Total Heat Tracing Cable Tray: LS 1.00 421,829.08 421,829.08 M3 10.00 5,210.00 52,100.00 Sub Total Heat Tracing Civil Work: LS 1.00 52,100.00 52,100.00 9.00 750.00 6,750.00 1.00 6,750.00 6,750.00 35.00 600.00 144.00 520.00 230.00 37.00 18,200.00 138,000.00 5,328.00 1.00 161,528.00 161,528.00 EA EA 244.00 4.00 100.00 44.00 24,400.00 176.00 Sub Total Heat Tracing Junction Boxes: LS 1.00 24,576.00 24,576.00 95.00 1,300.00 1.00 11.00 12.00 42,110.00 1,045.00 15,600.00 42,110.00 1.00 58,755.00 58,755.00 Cable Tray Accessories CABLE TRAYSTRAIGHT600mmW TRAY COVER (FOR STRAIGHT) VENTILATED TYPE600mmW VERTICAL ELBOW (90°),(R = 600 mm),(OUTSIDE TYPE)600mmW VERTICAL ELBOW (90°),(R = 600 mm),(IN SIDE TYPE)600mmW HORIZONTAL ELBOW (90°),(R = 600 mm) TRAY COVER (FOR VERTICAL ELBOW OUTSIDE TYPE) 600mmW TRAY COVER (FOR VERTICAL ELBOW INSIDE TYPE)600mmW TRAY COVER (FOR HORIZONTAL ELBOW)600mmW CABLE TRAY COVER CLAMPS CABLE TRAY HOLE DOWN CLAMPS Heat Tracing Civil Work NON-SHRINK GROUT Heat Tracing Panels ELECTRICAL HEAT TRACING CONTROL PANEL( 36 )CKT SET Heat Tracing Support CABLE TRAY SUPPORT PERFORATED CABLE TRAY SUPPORT ANCHOR BOLT STAINLESS STEEL, M12, 600mmL SET SET EA Sub Total Heat Tracing Support: LS 67460 67470 Rate m Sub Total Heat Tracing Panels: LS 67430 67440 67450 Quantity Heat Tracing Junction Boxes JUNCTION BOX EXPLOSION PROOF BLIND END PLATES600mmW Heat Tracing Miscellaneous METALLIC TEE CONNECTION KITOUTDOOR POLYESTER FIBER TAPE THERMON MISCELLANEOUS FOR ELECTRICAL HAET TRACING SYSTEM EA ROLL LOT Sub Total Heat Tracing Miscellaneous: LS Bill Of Quantities Process Plant Project Bill of Quantities Item 70000 70010 70020 70030 70040 70050 70060 70070 70080 70090 70100 70110 70120 70130 70140 70150 70160 70170 70180 70190 70200 70210 70220 70230 70240 70250 70260 70270 70280 70290 70300 70310 70320 70330 70340 70350 70360 Description Unit Amount 1.00 2,375,040.08 2,375,040.08 Sub Total Electrical Systems: LS 1.00 35,884,973.16 35,884,973.16 EA EA EA EA EA EA EA EA EA 3.00 3.00 3.00 1.00 1.00 80.00 20.00 3.00 10.00 1,370.00 980.00 1,060.00 1,060.00 1,060.00 160.00 160.00 160.00 1,370.00 4,110.00 2,940.00 3,180.00 1,060.00 1,060.00 12,800.00 3,200.00 480.00 13,700.00 Sub Total Analyzer: ea 124.00 342.98 42,530.00 EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA 105.00 107.00 12.00 4.00 53.00 5.00 108.00 5.00 32.00 19.00 97.00 213.00 179.00 188.00 54.00 54.00 225.00 475.00 17.00 210.00 120.00 220.00 230.00 230.00 230.00 210.00 360.00 360.00 400.00 210.00 140.00 210.00 210.00 75.00 67.00 260.00 260.00 260.00 22,050.00 12,840.00 2,640.00 920.00 12,190.00 1,150.00 22,680.00 1,800.00 11,520.00 7,600.00 20,370.00 29,820.00 37,590.00 39,480.00 4,050.00 3,618.00 58,500.00 123,500.00 4,420.00 Sub Total Field Instruments: ea 1,952.00 213.49 416,738.00 87.00 50.00 2.00 1,040.00 490.00 490.00 90,480.00 24,500.00 980.00 Sub Total Computer System: LS 1.00 115,960.00 115,960.00 Sub Total Instrument Equipment: LS 1.00 575,228.00 575,228.00 52,500.00 7,500.00 7,500.00 15,000.00 34,000.00 2,800.00 1.62 1.62 1.62 22.00 24.00 11.00 85,050.00 12,150.00 12,150.00 330,000.00 816,000.00 30,800.00 Field Instruments ORIFICE PLATE & ASSEMBLY ORIFICE PLATE ONLY INTEGRAL ORIFICE PITOT TUBE, ANNUBAR FLOWMETER VARIABLE AREA METER PRESSURE & D/P TRANSMITTER CAPACITANCE TYPE LEVEL LEVEL GAUGE RADAR TYPE LEVEL PRESSURE & D/P TRANSMITTER PRESSURE GAUGE PRESSURE & D/P TRANSMITTER TEMPERATURE INSTRUMENT BIMETALLIC THERMOMETER TEST THERMOWELL CONTROL VALVE ON-OFF VALVE PRESSURE REGULATING Instrument Cable Cable SIGNAL CABLES SIGNAL CABLES SIGNAL CABLES MULTI CABLE MULTI CABLE FIBER OPTICAL Rate Sub Total Heat Tracing System: LS Instrumentation Work Instrument Equipment Analyzer ANALYZER ELECTROCHEMICAL ANALYZER CONDUCTIVITY ANALYZER OXYGEN ANALYZER DENSITY ANALYZER GAS DETECTOR FLAME DETECTOR INDICATOR MISCELLANEOUS FOR RECEIVER INST. Computer System COMPUTER SYSTEM LOCAL CONTROL BOX MMS, PDC Quantity set EA SET m m m m m m Bill Of Quantities Process Plant Project Bill of Quantities Item 70370 70380 70390 70400 70410 70420 70430 70440 70450 70460 70470 70480 70490 70500 70510 70520 70530 70540 70550 70560 70570 Description MULTI CABLE MULTI CABLE MULTI CABLE MULTI CABLE MULTI CABLE MULTI CORE MULTI CORE MULTI CORE MULTI CORE SINGLE CORE SINGLE CORE MULTI CORE MULTI CORE Unit m m m m m m m m m m m m m 70600 70610 70620 70630 70640 70650 70660 70670 70680 70690 Amount 21.00 5.66 21.00 9.61 10.00 2.59 7.30 11.00 17.00 3.33 3.36 4.65 4.65 147,000.00 186,780.00 147,000.00 19,220.00 40,000.00 97,125.00 36,500.00 55,000.00 136,000.00 14,985.00 5,040.00 125,550.00 6,975.00 Sub Total Cable: LS 262,300.00 8.78 2,303,325.00 EA EA EA EA EA EA 4,449.00 1,438.00 94.00 86.00 118.00 55.00 23.00 26.00 29.00 31.00 48.00 56.00 102,327.00 37,388.00 2,726.00 2,666.00 5,664.00 3,080.00 Sub Total Cable Gland: ea 6,240.00 24.66 153,851.00 Sub Total Instrument Cable: LS 1.00 2,457,176.00 2,457,176.00 610.00 580.00 29.00 85.00 17,690.00 49,300.00 1.00 66,990.00 66,990.00 m m 5.00 279.00 17.00 24.00 85.00 6,696.00 Sub Total Pipe Straight: m 284.00 23.88 6,781.00 EA EA EA EA 42.00 68.00 62.00 211.00 580.00 670.00 40.00 40.00 24,360.00 45,560.00 2,480.00 8,440.00 Sub Total Pipe Fittings: LS 1.00 80,840.00 80,840.00 Sub Total Pipe: LS 1.00 87,621.00 87,621.00 4,712.00 36.00 102.00 1,464.00 16,872.00 760.00 24.00 20.00 26.00 16.00 24.00 25.00 113,088.00 720.00 2,652.00 23,424.00 404,928.00 19,000.00 Cable Gland CABLE GLAND, 1/2" CABLE GLAND, 3/4" CABLE GLAND, 1-1/4" CABLE GLAND, 1-1/2" CABLE GLAND, 2" CABLE GLAND, 2-1/2" Instrument Conduit & Tubing Conduit PVC CONDUIT PVC CONDUIT Pipe Pipe Straight PIPE, 1/2" PIPE, 1" Pipe Fittings AIR MANIFOLD HEADER, 8 POLE AIR MANIFOLD HEADER, 12 POLE SEAL POT DRIP POT Tubing TUBE, 1/2" TUBE, 1/4" TUBE, 3/4" TUBE, 3/8" TUBE, 1/2" TUBE, PRE-INSULATED, 3/8" Rate 7,000.00 33,000.00 7,000.00 2,000.00 4,000.00 37,500.00 5,000.00 5,000.00 8,000.00 4,500.00 1,500.00 27,000.00 1,500.00 PCS m Sub Total Conduit: LS 70580 70590 Quantity m m m m m m Bill Of Quantities Process Plant Project Bill of Quantities Item 70700 Description TUBE, PRE-INSULATED, 3/8" Unit 70940 70950 70960 70970 70980 70990 71000 71010 71020 71030 71040 Amount 260.00 25.00 6,500.00 Sub Total Tubing: m 24,206.00 23.56 570,312.00 1.00 724,923.00 724,923.00 110.00 15.00 90.00 52.00 224.00 127.00 440.00 3,903.00 3,191.00 1,890.00 1,417.00 1,980.00 70.00 70.00 70.00 70.00 70.00 70.00 70.00 36.00 39.00 41.00 44.00 46.00 7,700.00 1,050.00 6,300.00 3,640.00 15,680.00 8,890.00 30,800.00 140,508.00 124,449.00 77,490.00 62,348.00 91,080.00 1.00 569,935.00 569,935.00 EA 3.00 4.00 1.00 4.00 11.00 12.00 102.00 804.00 240.00 261.00 151.00 350.00 380.00 450.00 500.00 550.00 590.00 67.00 67.00 67.00 67.00 67.00 1,050.00 1,520.00 450.00 2,000.00 6,050.00 7,080.00 6,834.00 53,868.00 16,080.00 17,487.00 10,117.00 Sub Total Cable Transit: LS 1.00 122,536.00 122,536.00 EA EA EA EA EA EA 13.00 68.00 5.00 32.00 36.00 102.00 170.00 230.00 300.00 370.00 430.00 500.00 2,210.00 15,640.00 1,500.00 11,840.00 15,480.00 51,000.00 Sub Total Junction Box: ea 256.00 381.52 97,670.00 EA EA EA EA EA 1.00 6.00 4.00 9.00 26.00 270.00 380.00 610.00 730.00 840.00 270.00 2,280.00 2,440.00 6,570.00 21,840.00 Sub Total Enclosures: ea 46.00 726.09 33,400.00 Sub Total Junction Box & Enclosures: LS 1.00 131,070.00 131,070.00 Cable Tray & Fitting CABLE TRAY, LADDER TYPE CABLE TRAY, LADDER TYPE CABLE TRAY, LADDER TYPE CABLE TRAY, LADDER TYPE CABLE TRAY, LADDER TYPE CABLE TRAY, LADDER TYPE CABLE TRAY, LADDER TYPE CABLE TRAY,PERFORATED TYPE CABLE TRAY,PERFORATED TYPE CABLE TRAY,PERFORATED TYPE CABLE TRAY,PERFORATED TYPE CABLE TRAY,PERFORATED TYPE PCS PCS PCS PCS PCS PCS PCS PCS PCS PCS PCS PCS Sub Total Cable Tray & Fitting: LS 70830 70840 70850 70860 70870 70880 70890 70900 70910 70920 70930 Rate m Sub Total Instrument Conduit & Tubing: LS 70710 70720 70730 70740 70750 70760 70770 70780 70790 70800 70810 70820 Quantity Cable Transit CABLE TRANSIT, SF-6 CABLE TRANSIT, SF-6x2 CABLE TRANSIT, SF-6x3 CABLE TRANSIT, SF-6x4 CABLE TRANSIT, SF-6+6x5 CABLE TRANSIT, SF-6+6x6 MCT BLOCK, 20Wx20HX60D MCT BLOCK, 30Wx30HX60D MCT BLOCK, 40Wx40HX60D MCT BLOCK, 60Wx60HX60D MCT BLOCK, 90Wx90HX60D Junction Box & Enclosures Junction Box JUNCTION BOX, 16P JUNCTION BOX, 28P JUNCTION BOX, 36P JUNCTION BOX, 40P JUNCTION BOX, 54P JUNCTION BOX, 80P Enclosures FIRE PROOFING ENCLOSURE, 16P FIRE PROOFING ENCLOSURE, 28P FIRE PROOFING ENCLOSURE, 40P FIRE PROOFING ENCLOSURE, 54P FIRE PROOFING ENCLOSURE, 80P EA LOT EA EA EA EA EA EA EA Bill Of Quantities Process Plant Project Bill of Quantities Item 71050 71060 71070 71080 71090 71100 71110 71120 71130 71140 71150 71160 71170 71180 Description Unit Support & Hardware STANCHION, 2" PIPE, HDG STANCHION, 2" PIPE, HDG ANGLE, STEEL FOR TRAY ANGLE, STEEL FOR PIPE, TUBE ANGLE, STEEL FOR JB CHANNEL, STEEL SUNSHADE SUPPORTING MISCELLANEOUS NON SHRINK GROUT EXCAVATION & BACKFILLING WORK SANDFILLING & COMPACTION WORK RED CONCRETE PROTECTIVE COVER WARNING TAPE SUPPORTING MISCELLANEOUS EA EA m m m m EA EA M3 M3 M3 EA SET LOT 80000 90000 Rate Amount 976.00 70.00 10,212.00 1,162.00 2,640.00 22,265.00 1,010.00 5,000.00 10.00 2,552.00 850.25 7,362.20 48.30 1.00 1,180.00 900.00 200.00 200.00 200.00 310.00 750.00 85.00 10,570.00 13.00 47.00 7.39 8.76 1,557,850.00 1,151,680.00 63,000.00 2,042,400.00 232,400.00 528,000.00 6,902,150.00 757,500.00 425,000.00 105,700.00 33,176.00 39,961.75 54,406.66 423.11 1,557,850.00 1.00 13,893,647.52 13,893,647.52 4,882.00 230.00 1,122,860.00 Sub Total Loop Test : LS 1.00 1,122,860.00 1,122,860.00 Sub Total Instrumentation Work: LS 1.00 19,597,375.52 19,597,375.52 LS 1.00 31,534,920.00 31,534,920.00 Sub Total Insulation Work: LS 1.00 31,534,920.00 31,534,920.00 m2 13,395.50 15.00 200,932.50 Sub Total Cleaning: m2 13,395.50 15.00 200,932.50 Sub Total Support & Hardware: LS 71190 Quantity Loop Test LOOP TEST Loop Insulation Work SUBCONTRACT INSULATIOM WORKS Painting Work Cleaning Solvent cleaning 90010 90020 90030 90040 90050 90060 90070 90080 90090 90100 Painting Sa 2 1/2 Painting SP, Surface tolerant, Epoxy Mastic, self priming, high solid Acrylic Polyurethane-Gloss Epoxy High Build Polyamide with Micaecous Iron Oxide Acylic Polyurethane-Gloss HT one pack Silicone coating Sa 3 Painting SP/HS Epoxy Phenolic Inorganic Zinc Silicate(IZS) primer SP, Surface tolerant, Epoxy Mastic, self priming, high solids m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 19,500.00 1,031.70 1,031.70 3,611.00 3,611.00 958.00 2,549.90 8,400.00 13,200.00 13,395.50 71.00 19.00 8.39 19.00 8.39 7.64 74.00 15.00 13.00 19.00 1,384,500.00 19,602.30 8,655.96 68,609.00 30,296.29 7,319.12 188,692.60 126,000.00 171,600.00 254,514.50 90110 90120 Acrylic Polyurethane-Gloss All Systems Paint m2 m2 13,395.50 3,325.00 8.39 18.00 112,388.25 59,850.00 Sub Total Painting: m2 84,009.30 28.95 2,432,028.02 36.00 6,810.00 245,160.00 1.00 245,160.00 245,160.00 90130 Galvanizing HDG after shop fabrication, Galvanizing Ton Sub Total Galvanizing: LS Line Marking Bill Of Quantities Process Plant Project Bill of Quantities Item 90140 Description Unit [Line marking, Identification & Lettering for piping, Equipment(including insulation items) Quantity Rate Amount Lot 1.00 227,770.00 227,770.00 Sub Total Line Marking: LS 1.00 227,770.00 227,770.00 Sub Total Painting Work: LS 1.00 3,105,890.52 3,105,890.52 Sub Total Process Plant Direct Costs: LS 1.00 266,395,230.02 266,395,230.02 Grand Total: LS 1.00 266,395,230.02 266,395,230.02
© Copyright 2026 Paperzz