PSSRB Vivarium Monitoring Based Retro-Commissioning Jamie Hand Campus Energy Manager UCSF 7/8/2016 Adam Wheeler, P.E. Sherrill Engineering, Inc. Project Results Total costs: $510,030 PG&E Incentive: $394,000 Annual Utility Savings: $220,000 Payback period: 6 months Electricity (kWh) Steam (therms) Chilled Water (tons) CHW (peak tons) Baseline Post-MBCx Savings % Savings 2,760,453 1,402,251 1,358,202 49% 229,213 182,689 46,524 20% 385,765 148,654 237,111 61% 274 109 165 60% kWh/day 2 Implementation Period 7/8/2016 Building/Project Description Specialized Vivarium Building Constructed 2003-2005 80,000 ft2 and 6 floors, 250,000 mice 4 floors devoted to lab animal housing and support spaces Fully ventilated (Independent Supply and Exhaust) cage racks Continuous lab animal occupancy; 100% Outside Air ventilation Utilities and Mechanical Electricity fed from cogeneration plant Plant Steam for HHW generation, Humidifiers and Processes Plant Chilled Water, adequate pressure (no pumping in bldg) ~ 420 Pressure independent VAV Airflow Control Valves with Vortex shedding airflow measurement and HW reheat DDC controls throughout building Typical floor plan Baseline Development Metering Steam meter • Existing Vortex meter oversized (1000 lbs/hr min) • Replaced with Orifice plate meter (500 lbs/hr min) ‒ In retrospect, should used smaller pipe size to get lower min reading Chilled water meter • Turbine type meter had stopped functioning • Replaced with insertion mag-flow meter • Electric metering by campus SCADA system Cost Detail Metering purchase and install: $20k Cx Consultant: ~$100k In-house engineering: $11k In-house controls: $104k Energy Analyst: $24k Facilities Services: >$100k Motion sensor install: $28k Insulation: $10k PM: $33k - controls contractor - insulation contractor BMS data Analytics Package: $25k Retro-Commissioning Overview Analyze Building Operations • Where is Energy Being Used • What are the current Owner’s Requirements? Develop Energy Conservation Measures (ECM’s) • Analysis, Planning, Preparation • Estimate “costs” and savings, rank, choose some, defer others Develop Functional Improvement Needs • Integrate with ECM’s where feasible Complexity and Detail must be embraced to achieve best savings • Central Systems may be easier, but lots of savings in Zones Energy Conservation Measures (ECM’s) Consultant recommended about 30 ECMs • Vast majority were controls logic changes Examples: • Static pressure and temp reset (SA, EA, HHW) with deadband • Eliminated bypass flow; Opened HHW reheat balance valves • Motion Sensors & Schedules for Human occupied spaces ‒ Standby mode for unoccupied / unused spaces • Airflow and Temperature Set Point adjustments Not all measures implemented due to time & effort “budget.” Typical Small Animal Room Small Animal Room ECM’s Example ECM: Small Animal Rooms Current Use: Less racks than original design Result: More air than the needed Solution: BMS calculates flow SP based on # of racks in room • Relies on communication between users and operators Actual occupancy determined by detailed audit Airflow changes carefully validated at cage level to assure ventilation effectiveness Low ventilation issues found and corrected – Function Improvement Labor intensive but worth it! Example ECM: Animal Support Rooms Existing condition: Procedure Rooms ventilated 24/7, but little used Solution: Install motion sensors to determine occupancy Depending on use, sensitivity, etc. the room airflow could be either; • Turned off when unoccupied • Turned down whenever unoccupied • On during normal hours, reduced ACH off-hours when no occupancy sensed (most sensitive areas) Innovation: SA/EA Static Pressure Reset Rank all supply air (SA) valves by pressure requirement (how much they are opened), then divide into deciles (10 equal groups) Adjust static pressure to keep “second decile” average at a set point determined to satisfy all critical zones Most open air valves 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% Least open air valves Many faulty valves here “Second Decile” Innovation: SA/EA Static Pressure Reset Existing Control: fixed static pressure New strategy – Reset static pressure as follows: • Pull Air Flow Control Valve (AFCV) position for all zones • Create setpoint for average position of subset (via testing) • Initially: lots of ‘problem’ zones w/ dampers 100% open • Use DDC alarms to address outliers Controls and building engineers worked to greatly the reduce the number of ‘problem’ zones –Functionality Improvement Innovation: Stop “Creep” due to Hysteresis Innovation: Stop “Creep” Existing: Airflow Control Valve (AFCV) plus airflow measurement causes static pressure to “creep” up due to mechanical hysteresis • Airflow overshoot compresses spring in AFCV • Transient underflow opens valve, calling for more system static. New Strategy – Drop System Static pressure to relax springs • Every four hours static pressure set point is dropped 10% • System seeks optimum static pressure “from below” • Static Pressure Set Point “Creep” Controlled Elements Contributing to Project’s Success Differences between design and actual use (100% vs. 50% 24/7) Single user controls building, bought-in to project Detailed knowledge of building needs • Commissioning agent (CxA) performed detailed new bldg Cx • CxA had detailed knowledge of process needs & equipment Critical nature of building dissuaded prior optimization • Functionality & Schedule main concern for new building Sophisticated in-house resources: Controls, Engineering, Maint. Zone-by-Zone ECM’s had to overcome skepticism about value Team willing to invest resources and Persevere (2.5 years)! Recommendations for Future MBCx Pick a building with ‘modern’ controls down to zone level (DDC) Zone-by-zone analysis labor intensive but worth it. Review every zone to determine: • What are ventilation, pressurization, temp requirements? • How is space used? Can we use motion sensors for setbacks? Create and evaluate wish-list (BMS upgrades, flow measurement, TAB work) early in project Create written sequences that are detailed, even if controls changes are being done in-house Pull tasks in-house where possible (save $ for implementation) Consider / Plan Follow-on Project to leverage knowledge gained.
© Copyright 2025 Paperzz